Application for Approval of a Deferral Account

Size: px
Start display at page:

Download "Application for Approval of a Deferral Account"

Transcription

1 B-9 Application for Approval of a Deferral Account in connection to the Development Agreement between FEVI and PEC Streamlined Review Process April 23,

2 Agenda Approval Sought Overview of Existing FEVI System Woodfibre LNG Project Pipeline Reinforcement Project Development Agreement Other Key Activities Scope of Development Work Treatment of Development Costs Treatment of Commitment Fees Deferral Account Balance Examples of Disposition of Deferral Account Balance AFUDC Treatment of Deferral Balance - 2 -

3 Approval Sought FEVI seeks BCUC approval of: Deferral Account to capture Development Costs and; Commitment Fees Treatment of the Deferral Account, which is: Consistent with regulatory practice Consistent with previously approved treatment in FEVI The work undertaken in the development stage of this project will answer the many questions raised about the Pipeline Reinforcement Project itself - 3 -

4 Overview of Existing FEVI System FEVI Peak Day Load Customer TJ/d MMscfd Core VIGJV BC Hydro FEW / Squamish Total

5 Woodfibre LNG Site Proposed Site - 5 -

6 Woodfibre LNG Project Pacific Energy Corporation ( PEC ) is a Canadian-incorporated company and part of Pacific Oil & Gas Group ( PO&G ), an independent energy resource development company established in Indonesia in 2003 PEC is in the early stages of planning, analysis and community engagement regarding a small-scale LNG processing and export facility ( Woodfibre LNG Project ) Site conditionally acquired by PEC; former pulp-mill near Squamish, BC PEC working on feasibility study for LNG Facility PEC s Final Investment Decision expected Dec 2015 Firm Contract Demand Requirements: MMscfd - 6 -

7 FEVI 2017/2018 Design Load Duration Curve FEVI 2017/18 Design Load Duration Curve Core Load ICP + VIGJV Existing Capacity TJs per Day Mt. Hayes LNG Existing Pipeline and Compression Coldest to Warmest Day (Design Scenario) - 7 -

8 Woodfibre Demand: 161 TJ/d (150 MMscfd) FEVI 2017/18 Design Load Duration Curve Core Load ICP + VIGJV Woodfibre New Capacity 350 TJs per Day Mt. Hayes LNG Proposed Pipeline and Compression Coldest to Warmest Day (Design Scenario) - 8 -

9 Pipeline Reinforcement Project Proposed Site FEVI Transmission System Highlighted Area shows Potential System Reinforcements - 9 -

10 Development Agreement: FEVI and PEC To commence Development Work for the Pipeline Reinforcement Project Development Work to be completed in three Phases; Target completion Dec 2015 PEC to provide performance security on the Development costs that FEVI would incur to complete the Development Work PEC to pay FEVI Commitment Fees of $3.24 million over the three Phases of Development Work

11 Other Key Activities Negotiate Transportation Service Agreement between FEVI and PEC Firm Contract Daily Demand Toll Consistent with BCUC ongoing ratemaking regulation Consistent with FEVI General Terms & Conditions Subject to BCUC approval Wheeling Agreement between FEVI and FEI FEVI to extend the initial term of the Wheeling Agreement FEVI to determine its long term capacity requirements on FEI s CTS and to increase the capacity, if required Subject to BCUC approval

12 FEVI Scope of Development Work PHASE 1 ($1.2 M) Feasibility Study Environmental Assessment Pre-Application Class 4 Cost Estimate for Pipeline Reinforcement; Indicative toll for PEC Stakeholder and First Nations Consultation PHASE 2 ($2.8 M) Front End Engineering and Design Environmental and Engineering Field Studies Class 3 Cost Estimate for Pipeline Reinforcement; Indicative Toll for PEC Stakeholder and First Nations Consultation PHASE 3 ($1.7 M) Regulatory Approvals Submit Environmental Assessment to BCEAO/CEAA and Obtain Approvals Submit CPCN to BCUC and Obtain Approvals Stakeholder and First Nations Consultation For details, please refer to Appendix B of the Application

13 Treatment of Development Costs FEVI to incur Development Costs LNG Project proceeds LNG Project does not proceed Development Costs become part of Project Costs PEC to reimburse FortisBC for Development Costs incurred

14 Commitment Fees Payment Schedule $240 within 10 business days after Approval of Deferral Account Application $1,500 within 10 business days after completion of Phase 1 (i.e. Dec 31, 2013) $1,500 within 10 business days after completion of Phase 2 (i.e. Dec 31, 2014) Commitment Fees are in $000 s

15 Treatment of Commitment Fees PEC to pay Commitment Fees to FEVI LNG Project proceeds LNG Project does not proceed Commitment Fees credited against PEC s future demand charges PEC elects not to proceed FEVI fails to obtain necessary approvals Commitment Fees credited to customers Commitment Fees refunded to PEC

16 Deferral Account Balance (in $000 s) PHASE 1 PHASE 2 PHASE 3 Total Estimated Development Costs $1,200 $2,800 $1,700 $5,700 Commitment Fees $(240) $(1,500) $(1,500) $(3,240) Estimated Balance before AFUDC $960 $300 $200 $2,460 AFUDC $19 $63 $118 $199 Estimated Total Balance $979 $1,363 $318 $2,659 Final disposition of Deferral Account under three possible scenarios Scenario 1: Woodfibre LNG Project & Pipeline Reinforcement Project proceeds Scenario 2: PEC Elects Not to Proceed with Woodfibre LNG Project Scenario 3: FEVI fails to Obtain necessary approvals

17 Examples of Disposition of Deferral Account Example 1: LNG Project and Pipeline Reinforcement Project Proceeds Estimated Deferral Account Balance - $2,659 Estimated Development Costs of $5,700 and AFUDC $199 become part of Project Costs Commitment Fees of $3,240 credited to PEC s future demand charges Customers Benefit Expected reduction in the unit costs of transportation on FEVI system All numbers are in $000 s

18 Examples of Disposition of Deferral Account Example 2: PEC elects not to proceed with LNG Project at end of Phase 2 Estimated Deferral Account Balance - $2,342 Development Costs of $4,000 incurred by FEVI will be reimbursed by PEC PEC forfeits $1,740 of Commitment Fees Customers Benefit - $1,658 (Commitment Fees net of AFUDC amount) All numbers are in $000 s

19 Examples of Disposition of Deferral Account Example 3: FEVI fails to Obtain necessary approvals at end of Phase 3 Estimated Deferral Account Balance - $2,659 Estimated Development Costs of $5,700 incurred by FEVI will be reimbursed by PEC Commitment Fees of $3,240 refunded to PEC Balance amount of $199 to be recovered through Customers in future rates All numbers are in $000 s

20 AFUDC Treatment of Deferral Balance Distinction between feasibility and development costs only required for regular capital; both types are treated the same for large capital projects Consistent with past FEI/FEVI practice and accepted regulatory accounting treatment & USoA that all these costs in support of capital are treated the same In addition, rate base return (AFUDC) appropriate for costs incurred in support of a fixed asset (capital)

21 Thank You

Diane Roy Director, Regulatory Services

Diane Roy Director, Regulatory Services Diane Roy Director, Regulatory Services Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-3

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-3 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL gas.regulatory.affairs@fortisbc.com April 4, 2013 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-1

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-1 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL gas.regulatory.affairs@fortisbc.com April 4, 2013 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

TERASEN GAS (VANCOUVER ISLAND) INC REVENUE REQUIREMENT. Workshop Presentation. August 31, 2005

TERASEN GAS (VANCOUVER ISLAND) INC REVENUE REQUIREMENT. Workshop Presentation. August 31, 2005 TERASEN GAS (VANCOUVER ISLAND) INC. 2006 2007 REVENUE REQUIREMENT Workshop Presentation August 31, 2005 Review of Agenda Scott Thomson Vice President Finance and Regulatory Affairs Workshop Agenda 1. Welcome

More information

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. November 22, 2012 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 16705 Fraser Highway Surrey,

More information

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-3

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-3 Laurel Ross Acting Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 00 Howe Street Vancouver, BC Canada VZ N TEL: (0) 0-00 BC Toll Free: -00-- FAX: (0) 0- Log No. VIA

More information

Doug Slater Director, Regulatory Affairs

Doug Slater Director, Regulatory Affairs B- Doug Slater Director, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

FortisBC Energy (Vancouver Island) Inc Revenue Requirements and Rates Application

FortisBC Energy (Vancouver Island) Inc Revenue Requirements and Rates Application February 20, 2014 File No.: 241455.00033/15275 Christopher R. Bystrom Direct 604 631 4715 Facsimile 604 632 4715 cbystrom@fasken.com BY ELECTRONIC FILING British Columbia Utilities Commission Sixth Floor,

More information

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2017 and 2016

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2017 and 2016 An indirect subsidiary of Fortis Inc. Consolidated Financial Statements Prepared in accordance with accounting principles generally accepted in the United States of America MANAGEMENT S REPORT The accompanying

More information

August 29, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

August 29, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. August 29, 2012 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 16705 Fraser Highway Surrey, B.C.

More information

FortisBC Inc. Annual Review of 2018 Rates Project No British Columbia Utilities Commission Information Request No. 1

FortisBC Inc. Annual Review of 2018 Rates Project No British Columbia Utilities Commission Information Request No. 1 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 September 6, 2017 Sent

More information

included in the survey is published in the Quarterly Reports and the Budget and Fiscal Plan.

included in the survey is published in the Quarterly Reports and the Budget and Fiscal Plan. Information Request No. 2.23.0(a) Dated: 5 April 2004 23.0 Reference: BC Hydro letter of March 29, 2004 indicating, among other things, that BC Hydro is prepared to call Mr. Robert Fairholm to testify

More information

BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS

BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS QUESTION 1 Reference: Application, Volume 1, Chapter 1, page 1-7, Tables 1-1 and 1-2 a) Please clarify

More information

FEU COMMON RATES, AMALGAMATION RATE DESIGN RECONSIDERATION PHASE 2 EXHIBIT A-4

FEU COMMON RATES, AMALGAMATION RATE DESIGN RECONSIDERATION PHASE 2 EXHIBIT A-4 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL gas.regulatory.affairs@fortisbc.com July 24, 2013 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 ORDER NUMBER G-48-19 IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter

More information

Preliminary 2011 Revenue Requirements. Appendix B. Accounting Changes

Preliminary 2011 Revenue Requirements. Appendix B. Accounting Changes Accounting Changes Accounting Changes This section discusses the developments and implementation of accounting guidance under Canadian Generally Accepted Accounting Principles ( GAAP ) and International

More information

Diane Roy Director, Regulatory Services

Diane Roy Director, Regulatory Services Diane Roy Director, Regulatory Services Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

2017 EEI Financial Conference

2017 EEI Financial Conference 2017 EEI Financial Conference November 2017 2017 INVESTOR DAY 1 Forward-looking information Forward-Looking Information Fortis Inc. ( Fortis or the Corporation ) includes forward-looking information in

More information

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2013 and 2012

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2013 and 2012 An indirect subsidiary of Fortis Inc. Consolidated Financial Statements Prepared in accordance with United States Generally Accepted Accounting Principles MANAGEMENT S REPORT The accompanying annual consolidated

More information

FortisBC Inc. Annual Review of 2018 Rates Project No Final Order with Reasons for Decision

FortisBC Inc. Annual Review of 2018 Rates Project No Final Order with Reasons for Decision Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 February 13, 2018 Sent

More information

Attached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 12 months ending March 31, 2012.

Attached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 12 months ending March 31, 2012. Janet Fraser Chief Regulatory Officer Phone: 60-6-06 Fax: 60-6-07 bchydroregulatorygroup@bchydro.com July 0, 01 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor

More information

On June 10 and July 5, 2013, FEI and FBC, respectively, filed the Applications as referenced above.

On June 10 and July 5, 2013, FEI and FBC, respectively, filed the Applications as referenced above. Diane Roy Director, Regulatory Affairs FortisBC Energy 16705 Fraser Highway Surrey, B.C. V4N 0E8 Tel: (604) 576-7349 Fax: (604) 576-7074 www.fortisbc.com Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com

More information

2015 Rate Design Application

2015 Rate Design Application 2015 Rate Design Application D-Wires Extension Policy Customer Workshops: July/August 2014 Discussion Guide Discussion Guide Distribution Extension Policy Review OVERVIEW Currently, BC Hydro is consulting

More information

FORTISBC INC PERFORMANCE BASED RATEMAKING REVENUE REQUIREMENTS EXHIBIT A-27

FORTISBC INC PERFORMANCE BASED RATEMAKING REVENUE REQUIREMENTS EXHIBIT A-27 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL rhobbs@shaw.ca January 16, 2014 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. CANADA V6Z

More information

REGULATORY ACCOUNTS. The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Accounts.

REGULATORY ACCOUNTS. The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Accounts. Exhibit F Schedule Page of REGULATORY ACCOUNTS. INTRODUCTION The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Accounts. 0 All of the Regulatory Accounts reported

More information

SUMMARY OF APPLICATION

SUMMARY OF APPLICATION Filed: September, 00 EB-00-00 Schedule Page of SUMMARY OF APPLICATION Hydro One Networks ( Hydro One or Hydro One Transmission ) is applying for an Order approving the revenue requirement, cost allocation

More information

For further information, please contact Guy Leroux at

For further information, please contact Guy Leroux at BChydro m R GENE IONS Joanna Sofield Chief Regulatory Officer Phone: (604 623-4046 Fax: (604 623-4407 bchyd roregulatorygroup@bchydro.com July 13 2009 Ms. Erica M. Hamilton Commission Secretary British

More information

ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2013

ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2013 ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2013 March 14, 2014 ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2013 TABLE OF CONTENTS 1.0 CORPORATE STRUCTURE... 6 1.1 Name and Incorporation...

More information

17 GWh Domestic 51,213 57, LT Debt incl. current 16,876 18, Equity 4,170 4, Net Reg. & Def. Balance 5,433 5,908 5,685 5,894 6,006

17 GWh Domestic 51,213 57, LT Debt incl. current 16,876 18, Equity 4,170 4, Net Reg. & Def. Balance 5,433 5,908 5,685 5,894 6,006 C5-2 BC HYDRO REVENUE REQUIREMENTS APPLICATION F2017 to F2019 INFORMATION REQUEST No. 1 RICHARD McCANDLESS October 17, 2016. 1.0 FINANCIAL SUMMARY 1.1 The table below as developed from the 2015/16 Annual

More information

July 7, 2015 File No.: /14797 BY . British Columbia Utilities Commission 6 th floor, 900 Howe Street Vancouver, BC V6Z 2N3

July 7, 2015 File No.: /14797 BY  . British Columbia Utilities Commission 6 th floor, 900 Howe Street Vancouver, BC V6Z 2N3 C7-3 July 7, 2015 File No.: 240148.00782/14797 Matthew Ghikas Direct +1 604 631 3191 Facsimile +1 604 632 3191 mghikas@fasken.com BY E-MAIL British Columbia Utilities Commission 6 th floor, 900 Howe Street

More information

CENTRA GAS BRITISH COLUMBIA INC RATE DESIGN APPLICATION

CENTRA GAS BRITISH COLUMBIA INC RATE DESIGN APPLICATION IN THE MATTER OF the Utilities Commission Act R.S.B.C. 1996, Chapter 473 and IN THE MATTER OF CENTRA GAS BRITISH COLUMBIA INC. 2002 RATE DESIGN APPLICATION DECISION JUNE 5, 2003 Before: Peter Ostergaard,

More information

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES Filed: September 0, 00 EB-00-0 Tab Page of PAYMENTS IN LIEU OF CORPORATE INCOME TAXES.0 INTRODUCTION Under the Electricity Act,, Hydro One Networks Inc. ( Networks ) is required to make payments in lieu

More information

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 AGENDA Background on BC Hydro s 2015 Rate Design Application

More information

J.P.Morgan Energy Equity Conference June 27, 2017 FORTIS INC. WIRED FOR GROWTH

J.P.Morgan Energy Equity Conference June 27, 2017 FORTIS INC. WIRED FOR GROWTH J.P.Morgan Energy Equity Conference June 27, 2017 Forward-Looking Information Fortis Inc. ( Fortis or, the Corporation ) includes forward-looking information in this presentation within the meaning of

More information

SUMMARY OF BOARD DIRECTIVES AND UNDERTAKINGS FROM PREVIOUS PROCEEDINGS

SUMMARY OF BOARD DIRECTIVES AND UNDERTAKINGS FROM PREVIOUS PROCEEDINGS Filed: September, 006 EB-00-00 Page of 7 SUMMARY OF BOARD DIRECTIVES AND UNDERTAKINGS FROM PREVIOUS PROCEEDINGS 6 7 8 9 0 This exhibit identifies chronologically, in Tables through below, Board directives

More information

January 23, Via Original via Mail. British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

January 23, Via  Original via Mail. British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 3700 2 nd Avenue Burnaby, BC V5C 6S4 January 23, 2014 Via Email Original via Mail 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Ms. Erica M. Hamilton, Commission Secretary Dear Ms. Hamilton:

More information

REVENUE REQUIREMENT CGA Regulatory Course. Michelle Carman FortisBC Energy Inc.

REVENUE REQUIREMENT CGA Regulatory Course. Michelle Carman FortisBC Energy Inc. REVENUE REQUIREMENT 2016 CGA Regulatory Course Michelle Carman FortisBC Energy Inc. 1 Introduction Presentation Objectives Part 1: Explain and demonstrate the calculation of revenue requirement for the

More information

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES Filed: May, 0 EB-0-00 Tab Page of PAYMENTS IN LIEU OF CORPORATE INCOME TAXES.0 INTRODUCTION Under the Electricity Act,, Hydro One Networks Inc. ( Networks ) is required to make payments in lieu of corporate

More information

November 8, Dear Mr. Wruck:

November 8, Dear Mr. Wruck: B-23 Fred James Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com November 8, 2017 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support

More information

November 16, British Columbia Utilities Commission 6th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

November 16, British Columbia Utilities Commission 6th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. FORTISBC ENERGY BFI COMPLIANCE FILING EXHIBIT B-1 November 16, 2012 16705 Fraser Highway Surrey, B.C. V4N 0E8 Tel: (604) 576-7349 Cell:

More information

Reference: Exhibit B-5-1, page 1-4, Section , Electricity Demand Growth

Reference: Exhibit B-5-1, page 1-4, Section , Electricity Demand Growth C18-2 REQUESTOR NAME: Independent Power Producers of B.C. INFORMATION REQUEST ROUND NO: 1 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: July 5, 2006 PROJECT NO: 3698416 APPLICATION NAME: F2007/F2008

More information

Re: FortisBC Inc. Application for Approval of Demand Side Management Expenditures for the Period of 2015 and 2016

Re: FortisBC Inc. Application for Approval of Demand Side Management Expenditures for the Period of 2015 and 2016 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL August 22, 2014 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604)

More information

Long-Term Rate Forecast

Long-Term Rate Forecast Long-Term Rate Forecast OVERVIEW This brief provides background information on the Long-Term Rate Forecast (LTRF) used in the 2011 Integrated Resource Plan (IRP). It is similar to the report filed as Attachment

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014)

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014) ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

Investor Relations Presentation January INVESTOR DAY

Investor Relations Presentation January INVESTOR DAY Investor Relations Presentation January 2018 Forward-Looking Information Forward-Looking Information Fortis Inc. ( Fortis or the Corporation ) includes forward-looking information in this presentation

More information

BC Hydro FIrST QUArTEr report FISCAL 2015

BC Hydro FIrST QUArTEr report FISCAL 2015 BC Hydro FIRST QUARTER REPORT FISCAL 2015 BC Hydro & Power Authority Management S Discussion and Analysis This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority

More information

Third Quarter Report. For the nine months ended December 31, 2003 A04-24

Third Quarter Report. For the nine months ended December 31, 2003 A04-24 Third Quarter Report For the nine months ended December 31, 2003 A04-24 INDEX 1. Overview......................... 3 2. Financial......................... 6 3. Performance Measures............. 26 4. Lines

More information

1.0 Topic: Qualifications to provide expert evidence Reference: Exhibit C3-7, AMCS-RDOS Evidence, pages 1 and 51 of pdf

1.0 Topic: Qualifications to provide expert evidence Reference: Exhibit C3-7, AMCS-RDOS Evidence, pages 1 and 51 of pdf C2-7 REQUESTOR NAME: BC Sustainable Energy Association and Sierra Club BC INFORMATION REQUEST ROUND NO: 1 TO: ANARCHIST MOUNTAIN COMMUNITY SOCIETY AND REGIONAL DISTRICT OF OKANAGAN-SIMILKMEEN (AMCS RDOS)

More information

BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, RICHARD McCANDLESS

BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, RICHARD McCANDLESS BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, 2017. RICHARD McCANDLESS THE BC UTILITIES COMMISSION SHOULD NOT APPROVE ANY DISCRETIONARY REQUESTS PENDING A NEW APPROACH TO

More information

2017 Q1 Earnings Call. May 2, 2017

2017 Q1 Earnings Call. May 2, 2017 2017 Q1 Earnings Call May 2, 2017 Forward-Looking Information Fortis Inc. ( Fortis or, the Corporation ) includes forward-looking information in this presentation within the meaning of applicable securities

More information

Cascade Pacific Power Corporation

Cascade Pacific Power Corporation February 7, 2008 C23-3 BC Hydro and Power Authority 17 th Floor, 333 Dunsmuir Street Vancouver, BC V6B 5R3 Attention: Ms. Joanna Sofield, Chief Regulatory Officer Dear MS. Sofield RE: Standing Offer Program

More information

ITEM NO. 7. PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: May 20, 2008

ITEM NO. 7. PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: May 20, 2008 PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: May 20, 2008 ITEM NO. 7 REGULAR X CONSENT EFFECTIVE DATE N/A DATE: May 1, 2008 TO: FROM: Public Utility Commission Lynn Kittilson THROUGH:

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support B-2 10 th Floor 1111 West Georgia Street Vancouver, BC, V6E 4M3 April 21, 2017 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Mr. Patrick Wruck, Commission

More information

EXECUTIVE SUMMARY OF APPLICATION

EXECUTIVE SUMMARY OF APPLICATION Updated: 0-0-0 EB-0-00 Page of EXECUTIVE SUMMARY OF APPLICATION. SCOPE OF APPLICATION Hydro One Networks Inc. ( Hydro One ) is applying for an Order approving the revenue requirement, cost allocation and

More information

Financials April 1, 2009 March 31, Management s Discussion and Analysis 23. Management Report 40

Financials April 1, 2009 March 31, Management s Discussion and Analysis 23. Management Report 40 Financials 2010 April 1, 2009 March 31, 2010 Management s Discussion and Analysis 23 Management Report 40 Report of the Auditor General of British Columbia 41 Audited Financial Statements 42 Financial

More information

Canada s Oil & Natural Gas. Market Access The Key to Future Growth. Enabling Responsible Development. Calgary Real Estate Forum October 29, 2013

Canada s Oil & Natural Gas. Market Access The Key to Future Growth. Enabling Responsible Development. Calgary Real Estate Forum October 29, 2013 Canada s Oil & Natural Gas Market Access The Key to Future Growth Calgary Real Estate Forum October 29, 2013 Enabling Responsible Development 2 Canadian Oil Sands Source: Cenovus Global Crude Oil Reserves

More information

Canada s Oil & Natural Gas. Market Access The Key to Future Growth. Calgary Real Estate Forum October 29, 2013

Canada s Oil & Natural Gas. Market Access The Key to Future Growth. Calgary Real Estate Forum October 29, 2013 Canada s Oil & Natural Gas Market Access The Key to Future Growth Calgary Real Estate Forum October 29, 2013 Enabling Responsible Development Energy Markets Environment Benefits 2 Canadian Oil Sands Source:

More information

DECISION and Order E and Letter L-15-16

DECISION and Order E and Letter L-15-16 IN THE MATTER OF FortisBC Energy Inc. 2015 Price Risk Management DECISION and Order E-10-16 and Letter L-15-16 June 17, 2016 Before: D. A. Cote, Commissioner/Panel Chair B. A. Magnan, Commissioner R. D.

More information

FORM F4 BUSINESS ACQUISITION REPORT

FORM F4 BUSINESS ACQUISITION REPORT FORM 51-102F4 BUSINESS ACQUISITION REPORT ITEM 1 IDENTITY OF COMPANY 1.1 Name and Address of Company Fortis Inc. ("Fortis" or the "Corporation") Suite 1201, 139 Water Street St. John's, Newfoundland and

More information

INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report November 24, 2017

INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report November 24, 2017 Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report

More information

BC Gas Utility Ltd. Annual Report 2002

BC Gas Utility Ltd. Annual Report 2002 Annual Report 2002 Corporate Profile is the largest distributor of natural gas serving British Columbia, with 774,000 residential, commercial and industrial customers in more than 100 communities., with

More information

Exhibit B-3, pp. 1-2, Exhibit 1; Exhibit B-1, p. 3 Capital costs

Exhibit B-3, pp. 1-2, Exhibit 1; Exhibit B-1, p. 3 Capital costs Page 1 B-7 BRITISH COLUMBIA UTILITIES COMMISSION INFORMATION REQUEST ON BYPASS COSTS TO PACIFIC NORTHERN GAS (N.E.) LTD. [PNG (N.E.)] Dawson Creek Division Application for Approval of AltaGas Ltd. Industrial

More information

Long Run Marginal Cost (LRMC)

Long Run Marginal Cost (LRMC) Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Agenda & Objectives Preliminary Discussion PART I Provide a historic overview of FBC s LRMC Highlights from BC Hydro s stated

More information

REGULATORY ASSETS. The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Assets.

REGULATORY ASSETS. The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Assets. Filed: May, 0 EB-0-000 Page of REGULATORY ASSETS.0 INTRODUCTION The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Assets. All of the Regulatory Assets reported

More information

September 10, Via Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C.

September 10, Via  Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C. C- Email: electricity.regulatory.affairs@fortisbc.comemail: electricity.regulatory.affairs@fortisbc.com Dennis Swanson Director, Regulatory Affairs FortisBC Inc. Suite 00 Springfield Road Kelowna, BC VY

More information

All Source Request for Proposal Bid Conference. October 22, 2008

All Source Request for Proposal Bid Conference. October 22, 2008 All Source Request for Proposal Bid Conference October 22, 2008 Agenda Overview of All Source Request for Proposal Schedule and timeline Resource Alternatives Delivery Points Bid Fee (s) Fixed and Index

More information

ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2010

ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2010 ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2010 March 7, 2011 ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2010 TABLE OF CONTENTS 1.0 CORPORATE STRUCTURE 1.1 Name and Incorporation...

More information

FortisBC Inc. s Preliminary 2011 Revenue Requirements Application for Approval Pursuant to Sections 60 and 61 of the Utilities Commission Act

FortisBC Inc. s Preliminary 2011 Revenue Requirements Application for Approval Pursuant to Sections 60 and 61 of the Utilities Commission Act Dennis Swanson Director, Regulatory Affairs FortisBC Inc. Suite 00 - Springfield Road Kelowna, BC VY V Ph: (0) -00 Fax: --- regulatory@fortisbc.com www.fortisbc.com October, 00 B- Via Email Original via

More information

B.C. Utilities Commission File No.: 4.2 (2015) 6 th Floor Howe Street Vancouver, B.C. V6Z 2N3

B.C. Utilities Commission File No.: 4.2 (2015) 6 th Floor Howe Street Vancouver, B.C. V6Z 2N3 B-3 Janet P. Kennedy Vice President, Regulatory Affairs & Gas Supply Pacific Northern Gas Ltd. 950, 1185 West Georgia Street Vancouver, BC V6E 4E6 Tel: (604) 691-5680 Fax: (604) 697-6210 Email: jkennedy@png.ca

More information

IN THE MATTER OF FORTISBC ENERGY INC.

IN THE MATTER OF FORTISBC ENERGY INC. IN THE MATTER OF FORTISBC ENERGY INC. APPLICATION FOR APPROVAL OF A CAPITAL EXPENDITURE SCHEDULE, RATE DESIGN AND RATES FOR AN OPERATING AND MAINTENANCE AGREEMENT TO PROVIDE THERMAL ENERGY SERVICES BETWEEN

More information

FortisBC Energy Inc. (FEI) Project No Demand Side Management Expenditures Plan (the Application) Errata dated September 20, 2018

FortisBC Energy Inc. (FEI) Project No Demand Side Management Expenditures Plan (the Application) Errata dated September 20, 2018 B-1-1 Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and BRITISH C OLUMBIA U TILITIES C OMMISSION O RDER NUMBER C-10-07 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

IN THE MATTER OF AND DECISION. July 29, Before:

IN THE MATTER OF AND DECISION. July 29, Before: IN THE MATTER OF PACIFIC NORTHERN GAS LTD. AND AN APPLICATION TO RECAPITALIZE UNDER AN INCOME TRUST OWNERSHIP STRUCTURE DECISION July 29, 2004 Before: L.A. Boychuk, Panel Chair and Commissioner N.F. Nicholls,

More information

Investor Relations Presentation Q Investing in Our Networks

Investor Relations Presentation Q Investing in Our Networks Investor Relations Presentation Q2 2018 Investing in Our Networks Forward-Looking Information Fortis includes "forward-looking information" in this presentation within the meaning of applicable Canadian

More information

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES

PAYMENTS IN LIEU OF CORPORATE INCOME TAXES Filed: September, 00 EB-00-00 Tab Page of PAYMENTS IN LIEU OF CORPORATE INCOME TAXES Under the Electricity Act,, Hydro One Networks Inc. ( Networks ) is required to make payments in lieu of corporate income

More information

IN THE MATTER OF REPORT. December 27, Before:

IN THE MATTER OF REPORT. December 27, Before: IN THE MATTER OF FORTISBC ENERGY INC. INQUIRY INTO THE OFFERING OF PRODUCTS AND SERVICES IN ALTERNATIVE ENERGY SOLUTIONS AND OTHER NEW INITIATIVES REPORT December 27, 2012 Before: N.E. MacMurchy, Commissioner/Panel

More information

Terasen Gas Inc. ( Terasen Gas ) Extension of the Multi-Year Performance Based Rate Plan 2007 Annual Review

Terasen Gas Inc. ( Terasen Gas ) Extension of the Multi-Year Performance Based Rate Plan 2007 Annual Review Scott A. Thomson Vice President, Regulatory Affairs and Chief Financial Officer 16705 Fraser Highway Surrey, B.C. V4N 0E8 Tel: (604) 592-7784 Fax: (604) 576-7074 Email: scott.thomson@terasengas.com www.terasengas.com

More information

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Regulatory Framework & Incentives for Infrastructure Development Sergio Ascari VIS Consultants Gas Advisor, Florence School

More information

Competitive Power Market for Oregon Nonresidential Customers

Competitive Power Market for Oregon Nonresidential Customers Competitive Power Market for Oregon Nonresidential Customers Background The Oregon Legislature passed electric industry restructuring in 1999 (Senate Bill 1149). The law allows all nonresidential customers

More information

British Columbia Hydro and Power Authority

British Columbia Hydro and Power Authority 2017/18 SECOND QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

~ LAWSON /a LUNDEL~ I

~ LAWSON /a LUNDEL~ I ~ LAWSON /a LUNDEL~ I Suite 1600 Cathedral Pl ace 925 West Georgia Street Vancouver, BC Canada V6C 3L2 T: 604.685.3456 C1-6 ELECTRONICALLY FILED Keith Bergner D: 604.631.9119 I 403.218.7538 F: 604.694.2910

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

Terasen Gas Inc. A subsidiary of Fortis Inc. Annual Information Form. For the Year Ended December 31, 2008 dated February 18, 2009

Terasen Gas Inc. A subsidiary of Fortis Inc. Annual Information Form. For the Year Ended December 31, 2008 dated February 18, 2009 A subsidiary of Fortis Inc. Annual Information Form For the Year Ended December 31, 2008 dated February 18, 2009. 1 TABLE OF CONTENTS CORPORATE STRUCTURE... 3 DESCRIPTION OF THE BUSINESS... 4 DISTRIBUTION

More information

FEI 2017 PRICE RISK MANAGEMENT PLAN EXHIBIT A-6

FEI 2017 PRICE RISK MANAGEMENT PLAN EXHIBIT A-6 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 March 8, 2018 Sent via

More information

Ms. Laurel Ross, Acting Commission Secretary and Director

Ms. Laurel Ross, Acting Commission Secretary and Director Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

Alberta Coalition Presentation. BCUC Workshop - August 23, BCTC Network Economy and Open Access Transmission Tariff

Alberta Coalition Presentation. BCUC Workshop - August 23, BCTC Network Economy and Open Access Transmission Tariff C8-7 Alberta Coalition Presentation BCUC Workshop - August 23, 2006 BCTC Network Economy and Open Access Transmission Tariff August 23, 2006 Alberta Coalition 1 Overview of AC Evidence August 23, 2006

More information

Caribbean Regulated Electric Utilities contributed $6 million of earnings, comparable to the second quarter of 2011.

Caribbean Regulated Electric Utilities contributed $6 million of earnings, comparable to the second quarter of 2011. Second Quarter 2012 Dear Shareholder: Fortis achieved second quarter net earnings attributable to common equity shareholders of $62 million, or $0.33 per common share, compared to $57 million, or $0.32

More information

BC Hydro s Clean Power Call

BC Hydro s Clean Power Call BC Hydro s Clean Power Call November 27, 2007 Housekeeping Details Morning break at 9:45 for 15 minutes Lunch is at 12:30 for 30 minutes Break out groups at 1:30 for 1 hour Meeting ends at 4:00 Washrooms

More information

ALTAGAS REPORTS SECOND QUARTER EARNINGS

ALTAGAS REPORTS SECOND QUARTER EARNINGS ALTAGAS REPORTS SECOND QUARTER EARNINGS Calgary, Alberta (August 5, 2009) AltaGas Income Trust (AltaGas or the Trust) (TSX: ALA.UN) today announced net income of $36.9 million ($0.47 per unit - basic)

More information

British Columbia Hydro and Power Authority

British Columbia Hydro and Power Authority 2017/18 THIRD QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and BRITISH C OLUMBIA U TILITIES C OMMISSION O RDER NUMBER G-52-06 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

Balsam Lake Coalition Interrogatory # 8

Balsam Lake Coalition Interrogatory # 8 Tab Schedule BLC- Page of 0 0 0 Balsam Lake Coalition Interrogatory # Issue : Are the proposed amounts, disposition and continuance of Hydro One s existing deferral and variance accounts appropriate? Ontario

More information

FERC Accounting and Reporting Issues

FERC Accounting and Reporting Issues Background At the Spring Accounting Conference, we have scheduled a panel discussion on FERC Accounting and Reporting Issues. This agenda item is part of a larger effort to respond to an invitation from

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Direct Testimony of Michael G. Wilding

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Direct Testimony of Michael G. Wilding Rocky Mountain Power Docket No. 18-035-01 Witness: Michael G. Wilding BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Michael G. Wilding March 2018 1

More information

Comprehensive Review of BC Hydro: Phase 1 Final Report

Comprehensive Review of BC Hydro: Phase 1 Final Report Comprehensive Review of BC Hydro: Phase 1 Final Report ii Table of Contents 1. Executive Summary 1 1.1 Enhancing Regulatory Oversight of BC Hydro 1 1.2 New Rates Forecast 3 1.3 Next Steps 5 2. Strategic

More information

Canadian Manufacturers & Exporters (CME) INTERROGATORY #1 List 1

Canadian Manufacturers & Exporters (CME) INTERROGATORY #1 List 1 Filed: December, 00 Schedule Page of 0 0 0 0 Canadian Manufacturers & Exporters (CME) INTERROGATORY # List General Issues. Ref: Exhibit A, Tab, Schedule, paragraph Exhibit A, Tab, Schedule, page Exhibit

More information

BC Natural Resources Forum Rock Into the Future. Mark Edwards VP Community and Government Relations

BC Natural Resources Forum Rock Into the Future. Mark Edwards VP Community and Government Relations BC Natural Resources Forum Rock Into the Future Mark Edwards VP Community and Government Relations Forward-Looking Information These slides contain certain forward-looking statements within the meaning

More information

THE SOUTHERN CONNECTICUT GAS COMPANY AUDITED CONSOLIDATED FINANCIAL STATEMENTS AS OF AND FOR THE YEARS ENDED DECEMBER 31, 2017 AND 2016

THE SOUTHERN CONNECTICUT GAS COMPANY AUDITED CONSOLIDATED FINANCIAL STATEMENTS AS OF AND FOR THE YEARS ENDED DECEMBER 31, 2017 AND 2016 AUDITED CONSOLIDATED FINANCIAL STATEMENTS AS OF AND FOR THE YEARS ENDED DECEMBER 31, 2017 AND 2016 TABLE OF CONTENTS Page Number Independent Auditor s Report 2 Consolidated Financial Statements: Consolidated

More information