Attached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 12 months ending March 31, 2012.

Size: px
Start display at page:

Download "Attached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 12 months ending March 31, 2012."

Transcription

1 Janet Fraser Chief Regulatory Officer Phone: Fax: July 0, 01 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z N Dear Ms. Hamilton: RE: British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) F00/F006 Revenue Requirements Application BCUC Decision: October 9, 00; Directive 69 (page 01) (AMENDED pursuant to 006 Integrate Electricity Plan and 006 Long-Term Acquisition Plan BCUC Decision: May 11, 006; Directive 16 (page 1-16) Attached is BC Hydro s annual filing of the Report on Demand-Side Management Activities for the 1 months ending March 1, 01. For further information, please contact Geoff Higgins at or by at bchydroregulatorygroup@bchydro.com. Yours sincerely, (for) Janet Fraser Chief Regulatory Officer sh/rh Enclosure British Columbia Hydro and Power Authority, Dunsmuir Street, Vancouver BC V6B R

2 Report on Demand-Side Management Activities for Fiscal 01 July 16, 01

3 Table of Contents 1 Introduction... 1 Expenditures and Electricity Savings for Fiscal Expenditures to Date... 7 Plan Performance... 9 Mitigation Measures Operating Expenditures for Fiscal Allocation of Supporting Initiative Costs to Programs List of Tables Table 1 Expenditures and Incremental Electricity Savings for F01... Table Expenditures since F Table Cumulative Electricity Savings since April 1, Table Utility Cost of Electricity Savings: F008 to F Table Benefit Cost Ratios of Electricity Savings: F008 to F Table 6 Operating Expenditures for Fiscal Page i

4 Introduction This BC Hydro annual report to the British Columbia Utilities Commission (BCUC) on demand side management (DSM) activities responds to Directive 69 from the BCUC decision on BC Hydro s F00/F006 Revenue Requirements Application (F0/F06 RRA), Directive 16 from the BCUC decision on BC Hydro s 006 Integrated Electricity Plan and Long Term Acquisition Plan (006 IEP/LTAP) and Directives 6 and 8 from the BCUC decision on BC Hydro s 008 LTAP. The report provides information on DSM expenditures, electricity savings, plan performance and mitigation measures for the 01 fiscal year (F01), or the twelve months ending March 1, 01. Directive 69 directed BC Hydro to provide information to the Commission for on-going review of Power Smart performance through: Executive Summaries of milestone evaluation reports and full final evaluation reports for each program. Semi-annual reports on DSM activities which, amongst others, will include: detailed breakdown of OMA expenses related to support activities carried out within the Power Smart group and in other departments that support Power Smart organization; detailed description of the functions of portfolio level costs and how these costs are allocated to programs; summaries of the overall performance of Power Smart with reference to program objectives; and variances of fiscal year budgeted and actual deferred capital expenditures and explanation of variances. 6 Directive 16 directed BC Hydro to continue to file reports on DSM performance as described in Directive 69 included in Order No. G-96-0 and to file its Semi Annual Page 1

5 Demand Side Management Reports in the same format as the June 00 Report with the following enhancements: Provide annual and cumulative totals since program inception; (i) (ii) Express these values on a per unit basis; and Provide the benefit to cost ratios for the three DSM tests Directive 6 directed BC Hydro to switch from semi-annual to annual DSM performance reports while Directive 8 directed BC Hydro to include in these reports metrics for each initiative, achievements in relation to milestones, and description of past or planned mitigation measures where warranted. These mitigation measures should include shifting program resources and alternative supply options for each program. Ongoing DSM performance reporting should demonstrate how BC Hydro is continuously pursuing DSM and that specific programs are cost-effective. BC Hydro is filing evaluation reports as a separate package. This report addresses the balance of Directives 69 and 16, as well as Directives 6 and Expenditures and Electricity Savings for Fiscal 01 BC Hydro s DSM expenditures 1 in F01 totalled $17. million while incremental DSM electricity savings totalled 1,1 GWh/year. This was $1. million or 8 per cent below the DSM Plan in BC Hydro s Amended F01 to F01 Revenue Requirements Application (F1-F1 RRA). Electricity savings were 1 GWh/year or 1 per cent above the F1-F1 RRA. Table 1 presents planned and actual DSM expenditures and incremental electricity savings in F01. 1 Comprising all DSM-related deferred operating and specific capital expenditures. DSM operating expenditures are presented in Table 6 of this report. Page

6 Table 1 Expenditures and Incremental Electricity Savings for F01 Incremental Expenditures¹ Electricity Savings Plan² Actual Variance Plan² Actual Variance $ 000 $ 000 $ 000 % GWh/yr GWh/yr GWh/yr % Codes and Standards Residential % Commercial % Industrial % Total Codes and Standards % Rate Structures Residential, (1,8) (61%) % Commercial & Industrial Distribution,17,188 (99) (0%) % Industrial Transmission % (89) (9) 0 (%) Total Rate Structures,6,19 (,7) (1%) % DSM Programs Residential Sector Behaviour 6,08,197 (,81) (7%) 8 1% Lighting,, 11 7% % Refrigerator Buy-back,90,07 (9) (19%) (1) (7%) Low Income,181,6 (716) (1%) 7 6 (1) (1%) New Home,197,0 (17) (8%) (1) (1%) Appliances,07, % 0 10% Consumer Electronics,78,9 8 1% 9 10% Renovation Rebate,06,1 1,7 61% 6 6 (1) (11%) Load Displacement n/a Sector Enabling Activities 1, 1,69 () (17%) n/a n/a n/a n/a Residential Sector Total 0,981 8,607 (,7) (8%) % Commercial Sector Power Smart Partner 1,068,8,17 1% % Product Incentive 1,8,019 7,196 9% 8 69 % New Construction 6,8,901 (1,68) (6%) 1 8 () (1%) Load Displacement n/a Sector Enabling Activities 1,99 1,86 (6) (%) n/a n/a n/a n/a Commercial Sector Total,06 6,69 9,8 17% % Industrial Sector Power Smart Partner - Transmission 6,17 0, (,79) (%) % Power Smart Partner - Distribution 1,86 1,99 (7) (%) 0 8 () (8%) New Plant Design,91,78 (18) (%) % Load Displacement 1,817 8,100 (,717) (7%) (10) (6%) Sector Enabling Activities 1,1 1,010 (0) (%) n/a n/a n/a n/a Industrial Sector Total 9,88 7,718 (11,670) (0%) 17 6 % Cross Sectoral Sustainable Communities,6,69 8 1% n/a Lead by Example,78,010 (,68) (%) 1 % Cross Sectoral Total 8,1,70 (,1) (0%) 1 % Total Programs 1,907 1,718 (7,189) (%) % Supporting Initiatives Public Awareness and Education 7,86 7,10 (71) (9%) Community Engagement 6,6 6,097 (7) (8%) Technology Innovation 1,97 1,6 (601) (1%) Codes and Standards,1 1,7 (1,067) (%) Information Technology 1,60 1,099 (1) (%) Indirect and Portfolio Enabling 10,6 9,0 (1,) (1%) Supporting Initiatives Total 1,11 6,1 (,801) (1%) TOTAL DSM 189,77 17,0 (1,7) (8%) 988 1,1 16 1% 6 Table 1 Notes: 1 Including all DSM-related deferred operating and specific capital expenditures that are relevant for DSM cost-effectiveness. Plan figures are from BC Hydro s F1- F1 RRA. Page

7 Reported savings from codes and standards and residential and commercial & industrial distribution rate structures are based on planned estimates. Expenditures for Codes and Standards Support are reported under Supporting Initiatives. Plan savings are negative because they are a net number. The new savings in the year are more than offset by savings deductions due to historical projects reaching the end of their measure life. 6 The following are explanations for the above variances: Codes and Standards Residential Commercial Industrial Rate Structures Residential Commercial & Industrial Distribution Industrial Transmission Programs Residential Sector Behaviour Lighting Refrigerator Buy-Back Low Income Reported codes and standards electricity savings were on plan. Expenditures were below plan due to the residential rate design project starting later than expected. Electricity savings were on plan. Expenditures were below plan due to lower than planned implementation costs for the Medium General Service (MGS) rate structure and lower Large General Service (LGS) rate sustainment costs, both due to lower than planned customer care and communication costs. Electricity savings were on plan. Expenditures were approximately on plan. Planned electricity savings are negative due to new savings in F01 being more than offset by historical savings that have reached the end of their measure life. Electricity savings were above plan due to greater than expected customer self-generation and energy efficiency project activity. Expenditures were below plan due to a delay in the corporate Customer Portal project causing a delay of the In Home Feedback program. Electricity savings were above plan due to stronger than forecast program participation largely driven through BC Hydro promotions of online paperless billing which in turn encourages customers to sign up for the Behaviour program. Expenditures were approximately on plan. Electricity savings were above plan due to stronger than forecast program participation, particularly in sales of LED and CFL bulbs, in response to the program offer and active promotion on the part of retail partners. Expenditures and electricity savings were below plan due to lower than anticipated program participation. An investigation to determine the cause is underway however initial findings suggest that new refrigerator sales in BC have declined, perhaps in response to the recession, which in turn has decreased the volume of used refrigerators that could participate in the program. Expenditures and electricity savings were below plan due to lower than anticipated participation in the program s Energy Conservation Assistance Program component. Despite BC Hydro and partner efforts, this program component continues to have difficulty locating and enrolling customers. Page

8 New Home Appliances Consumer Electronics Renovation Rebate Load Displacement Sector Enabling Activities Commercial Sector Power Smart Partner Product Incentive New Construction Load Displacement Sector Enabling Activities Industrial Sector Power Smart Partner Transmission Power Smart Partner Distribution New Plant Design Load Displacement Expenditures and electricity savings were below plan due to lower than forecast participation. The new home market is still rebounding from the recession and HST and housing starts are shifting to multi-family dwellings. In turn, the number of detached housing starts, which offer the greatest electricity savings potential for this program, are lower than expected. Expenditures and electricity savings were approximately on plan. Expenditures and electricity savings were above plan due to greater than anticipated participation in the program s TV component as a result of successful partnerships with retail partners facilitating increased stocking of energy efficient TVs and training of retail store staff. The expenditure variance was less than the electricity savings variance due to fixed costs remaining the same despite higher program activity. Expenditures were above plan because they include costs from F011 program activity that could not be accrued due to insufficient information from program partners. Electricity savings were below plan due to lower than forecast participation resulting from the termination of federal grants for energy efficiency retrofits. No expenditures or electricity savings were planned. Expenditures were below plan due to delays in partner training initiatives and cost sharing with retailers and manufacturers. Expenditures and electricity savings were above plan due to higher than planned participation in response to a more streamlined program process, an effective program offer and strong trade ally support. Expenditures and electricity savings were above plan due to higher than planned participation in response to a more streamlined program process, an effective program offer and strong trade ally support. Expenditures and electricity savings were below plan due to a selection of large projects taking longer to complete than planned. No expenditures or electricity savings were planned. Expenditures were below plan due to the cancellation or delay of selected enabling activities in response to a re-prioritization of expenditures to commercial programs. Expenditures were below plan because electricity savings from the mix of projects were more cost effective than planned as well as a shift in Monitoring, Targeting and Reporting expenditures into F01 due to customer implementation delays. Electricity savings were above plan due to unanticipated customer self-funded projects identified through energy managers and studies. Expenditures and electricity savings were approximately on plan. Expenditures were approximately on plan despite higher than planned electricity savings due to lower than planned incentive costs for participating projects. Electricity savings were above plan due to increased program activity among oil and gas and chemical customers. Expenditures and electricity savings were below plan due to a delay in the completion of a customer load displacement project. Page

9 Sector Enabling Activities Cross Sectoral Sustainable Communities Lead By Example Total Programs Supporting Initiatives Public Awareness & Education Community Engagement Technology Innovation Codes and Standards Support Information Technology Indirect and Portfolio Enabling Activities Total DSM Expenditures were below plan due to study costs that were either under budget or delayed to the next fiscal year as well as a redirection of staff resources from industrial plant certification and market transformation strategy development to business case development for industrial programs. Expenditures were approximately on plan. No electricity savings were planned. Expenditures were below plan due to staffing reductions and the deferral of selected projects. Electricity savings were above plan due to the program focusing on projects with faster implementation. Expenditures were below plan largely because of lower than planned costs in the Industrial Power Smart Partner Transmission and Load Displacement programs. Electricity savings were above plan because of higher than planned savings in the Power Smart Partner Transmission, New Plant Design, Commercial Power Smart Partner and Product Incentive programs. Expenditures were below plan due to lower than planned advertising in light of an increased focus on smart meter communications. Expenditures were below plan due to a reduction in Outreach and sponsorship activities in light of an increased focus on smart meter communications. Expenditures were below plan due to several complex projects involving multiple funding partners proceeding more slowly than planned, as well as the receipt of a funding contribution from a project partner in late March that will offset project costs in F01. Expenditures were below plan due to lower than planned total funding requirements for energy efficiency standards development work by the Canadian Standards Association as well as higher than planned leveraging of co-funding from other funding organizations. Expenditures were below plan due to delays in an IT project which shifted project development costs into the subsequent fiscal year. Expenditures were below plan due to active cost reductions in several areas, combined with the delay in the information technology project noted above whose support and management costs are funded under this initiative. Expenditures were 8 per cent below plan because of lower than planned costs for programs, in particular the Industrial Power Smart Partner Transmission and Load Displacement programs. Electricity savings were 1 per cent above plan because of higher than expected savings from selected programs (Power Smart Partner Transmission, New Plant Design, Commercial Power Smart Partner, Product Incentive) and the Transmission Service Rate. Page 6

10 Expenditures to Date BC Hydro s DSM expenditures from F008 through F01 totalled $601.7 million. Table presents DSM expenditures from April 1, 007 to March 1, 01. Comprising all DSM deferred operating and specific capital expenditures that are relevant for DSM cost-effectiveness. To present information in a format consistent with the DSM expenditures presented in BC Hydro s 008 LTAP, which cover the years F008 forward, these figures do not include $1. million in incentive refunds received since F009 related to DSM program activity before F008. Page 7

11 Table Expenditures since F008 F008 1 ($ 000) F009 1 ($ 000) F010 1 ($ 000) F011 1 ($ 000) F01 ($ 000) Total ($ 000) Rate Structures Residential -, ,6 Commercial & Industrial Distribution -,7,8,66,188 11,91 Industrial Transmission Total Rate Structures -,000,9,87,19 18,01 DSM Programs Residential Sector Behaviour - 1,1,17,08,197 9,7 Lighting,007,,67,6, 1,7 Refrigerator Buy-back,01,90,77,,07,17 Low Income 11 1,9,97,610,6 1,1 New Home 1,1 1,19 1,6 1,,0 7,76 Appliances 1,0,6,8,6,167 16,8 Consumer Electronics - 98,68,618,9 9,96 Renovation Rebate 9 1,19,00 1,111,1 8,1 Load Displacement Sector Enabling Activities,9 1,897,08 1,6 1,69 9,01 Residential Sector Total 1,77 0, 6,11,817 8,607 11,10 Commercial Sector Power Smart Partner 10,7 17,76,77 6,06,8 11,078 Product Incentive,8 7,90 1,6 1,8,019 60,6 New Construction,16,71,6,88,901 0,8 Load Displacement Sector Enabling Activities 1,7,100 1,80 1, 1,86 7,7 Commercial Sector Total 17,10 1,68,819,66 6,69 01,66 Industrial Sector Power Smart Partner - Transmission 8, 6, 8,9 7,01 0, 0,7 Power Smart Partner - Distribution 1,1,96 10,068 9,8 1,99 0, New Plant Design 10 79,6,610,78 1,770 Load Displacement ,100 8,100 Sector Enabling Activities 1,19 1,8 1, 960 1,010,708 Industrial Sector Total 11,10 1,18,168 1,7 7, ,8 Cross Sectoral Sustainable Communities - - 1,76,096,69 6,0 Lead by Example ,77,010 6, Cross Sectoral Total - -,719,7,70 1,89 Total Programs 0,8 66,11 96,80 96,8 1,718, Supporting Initiatives Public Awareness and Education 11,9 8,69 8,67 9,190 7,10, Community Engagement - 7,79 7,079 7,081 6,097 8,00 Technology Innovation - 1,18 1,10 1,8 1,6,67 Codes and Standards 77 1,9 1,6 1,7 1,7 6,08 Information Technology 1,0 1,87 1, ,099 6,70 Indirect and Portfolio Enabling 11,1 9,90 8,7 8,78 9,0 7,7 Supporting Initiatives Total, 0,09 8,8 8,9 6,1 18,19 Total DSM 6,00 101,17 19,7 10,68 17,0 601,7 Table Notes: 1 These expenditures differ slightly from the actual expenditures presented in BC Hydro s Report on DSM Activities for F011 because of the exclusion of Voltage Optimization expenditures and Rate Structure operating expenditures in order to align with DSM expenditures presented in BC Hydro s F1-F1 RRA. Page 8

12 Plan Performance BC Hydro s DSM electricity savings since F008 totalled,0 GWh/year at March 1, 01, which equates to 10 per cent of the planned savings of,10 GWh/yr in the F1-F1 RRA. Table presents actual cumulative savings as a percentage of plan in F008 to F01. Page 9

13 Table Cumulative Electricity Savings since April 1, 007 Actual as a Percentage of Plan 1 F01 Codes and Standards Residential 100% Commercial 100% Industrial 100% Total Codes and Standards 100% Rate Structures Residential 100% Commercial & Industrial Distribution 100% Industrial Transmission 11% Total Rate Structures 10% DSM Programs Residential Sector Behaviour 11% Lighting 100% Refrigerator Buy-back 10% Low Income 97% New Home 9% Appliances 90% Consumer Electronics 19% Renovation Rebate 9% Load Displacement n/a Residential Sector Total 10% Commercial Sector Power Smart Partner 11% Product Incentive 100% New Construction 9% Load Displacement n/a Commercial Sector Total 10% Industrial Sector Power Smart Partner - Transmission 111% Power Smart Partner - Distribution 97% New Plant Design 1% Load Displacement 9% Industrial Sector Total 108% Cross Sectoral Sustainable Communities n/a Lead by Example 19% Cross Sectoral Total 19% Total Programs 10% Total DSM 10% Table Notes: 1 Reported savings for codes and standards and rates structures are based on planned estimates as well as evaluated results. Page 10

14 The DSM electricity savings presented in Table have been achieved at an average net levelized utility cost of $ per MWh. Table presents the net levelized utility cost of actual DSM electricity savings achieved from April 1, 007 through March 1, 01. Page 11

15 Table Utility Cost of Electricity Savings: F008 to F01 Net Levelized Utility Cost ($/MWh) 1 Codes and Standards Residential -16 Commercial -10 Industrial -9 Total Codes and Standards -1 Rate Structures Residential -10 Commercial & Industrial Distribution - Industrial Transmission -7 Total Rate Structures -7 Programs Residential Sector Behaviour 18 Lighting -1 Refrigerator Buy-back Low Income 97 New Home Appliances 9 Consumer Electronics 0 Renovation Rebate Load Displacement n/a Sector Enabling Activities n/a Residential Sector Total 1 Commercial Sector Power Smart Partner Product Incentive 18 New Construction 6 Load Displacement n/a Sector Enabling Activities n/a Commercial Sector Total 1 Industrial Sector Power Smart Partner - Transmission 1 Power Smart Partner - Distribution New Plant Design Load Displacement Sector Enabling Activities n/a Industrial Sector Total 1 Cross Sectoral Sustainable Communities n/a Lead by Example 1 Cross Sectoral Total 91 Total Programs 0 Rate Structures and Programs 8 Total DSM Table Notes: 1 Net levelized utility cost is calculated by subtracting capacity benefits from gross utility costs and then dividing the resulting net utility costs by electricity savings. A negative net levelized utility cost means that the subtracted capacity benefits exceed gross utility costs. Cross Sectoral Total is greater than Lead by Example because the total includes costs from the Sustainable Communities program but no corresponding electricity savings. Page 1

16 6 7 8 The DSM electricity savings presented in Table have been achieved at a substantially lower cost than new electricity supply, with a Total Resource Cost Test benefit-cost ratio of.. Table presents benefit cost ratios of actual DSM electricity savings achieved from April 1, 007 through March 1, 01. The Lead by Example program s benefit-cost ratios are less than one due to the program incurring costs in its early years while electricity savings take longer to come online. The program s benefit cost ratios will improve as more savings come online. Page 1

17 Table Benefit Cost Ratios of Electricity Savings: F008 to F01 Utility Test Benefit Cost Ratios Total Resource Cost Test 1 Non Participant Test Codes and Standards Residential n/a Commercial n/a Industrial n/a 9.7. Total Codes and Standards n/a Rate Structures Residential Commercial & Industrial Distribution Industrial Transmission Total Rate Structures Programs Residential Sector Behaviour Lighting Refrigerator Buy-back Low Income New Home.. 1. Appliances Consumer Electronics Renovation Rebate Load Displacement n/a n/a n/a Sector Enabling Activities n/a n/a n/a Residential Sector Total Commercial Sector Power Smart Partner Product Incentive New Construction Load Displacement n/a n/a n/a Sector Enabling Activities n/a n/a n/a Commercial Sector Total Industrial Sector Power Smart Partner - Transmission Power Smart Partner - Distribution New Plant Design Load Displacement Sector Enabling Activities n/a n/a n/a Industrial Sector Total Cross Sectoral Sustainable Communities n/a n/a n/a Lead by Example Cross Sectoral Total Total Programs Rate Structures and Programs Total DSM Table Notes: 1 In keeping with the DSM Regulation (Ministerial Order M 71), the avoided cost of natural gas is valued at 0 per cent of BC Hydro s long run marginal cost of acquiring electricity generated from clean or renewable resources in B.C. and non-energy benefits are valued at 1 per cent of electricity and natural gas benefits. Page 1

18 6 7 8 While the DSM regulation precludes the use of the Non Participant Test in determining cost-effectiveness of a demand-side measure, this benefit cost ratio is included in the table consistent with Directive from the BCUC decision on BC Hydro s 008 LTAP. The Total Resource Cost Test benefit-cost ratio for the Low Income program includes a 0 per cent adder to program benefits, rather than a 1 per cent value for non-energy benefits, in keeping with the DSM regulation. Cross Sectoral Total is less than Lead by Example because the total includes costs from the Sustainable Communities program but no corresponding electricity savings Mitigation Measures Table indicates that most DSM initiatives are above plan in terms of cumulative electricity savings in F01 while Table indicates that the portfolio has delivered electricity savings at a substantially lower cost than new electricity supply. Based on the experience gathered over the past few years through initiative tracking, the following are mitigation measures that have been undertaken or are planned for the future. Codes and Standards Residential Commercial Industrial Rate Structures Residential Commercial & Industrial Distribution Industrial Transmission Programs Residential Sector Behaviour Lighting Refrigerator Buy-Back Low Income New Home Cumulative electricity savings in F01 were on plan. Cumulative electricity savings in F01 were on plan. Cumulative electricity savings in F01 were on plan. Cumulative electricity savings in F01 were above plan. Cumulative electricity savings in F01 were above plan. Cumulative electricity savings in F01 were on plan. Incentive levels for LED lighting will be reduced in F01 as retail prices are expected to decline. Cumulative electricity savings were above plan but program participation is declining. BC Hydro is investigating this trend in F01 to identify causes of decreasing participation and formulating plans to address the trend. Cumulative electricity savings in F01 were slightly below plan. An expanded partnership with FortisBC Gas is expected to increase program participation. BC Hydro will determine if adjustments to program qualifying criteria are also required. Cumulative electricity savings in F01 were below plan. A new partnership with FortisBC Gas is expected to increase program participation. Page 1

19 Appliances Consumer Electronics Renovation Rebate Cumulative electricity savings in F01 were below plan. Program specifications for qualifying products are increasing again in F01 to remain ahead of improving appliance baseline energy consumption, therefore improving cost-effectiveness of the program. Ongoing discussions and negotiations with retail and manufacturing partners will continue to influence stocking and promotions of qualifying appliances. Cumulative electricity savings in F01 were above plan. Strong retail partnerships formed over the past years will allow BC Hydro to achieve targeted electricity savings in F01 while adjusting the qualifying criteria for TVs to manage free-ridership and lowering incentive levels to reduce costs. Cumulative electricity savings in F01 were below plan due to the termination of federal grants. BC Hydro will continue to work with the Ministry of Energy and Mines and FortisBC to drive program participation in F01 and determine the best program model going forward. Load Displacement No electricity savings were planned in F01. Commercial Sector Power Smart Partner Product Incentive New Construction Cumulative electricity savings in F01 were above plan. Electricity savings have increased relative to plan since F008 in response to program improvements and strong trade ally support. Cumulative electricity savings in F01 were on plan. Electricity savings have increased relative to plan since F008 in response to program improvements and strong trade ally support. Cumulative electricity savings in F01 were below plan due to project completions taking longer than planned. An expanded partnership with FortisBC Gas is expected to increase program participation. No further mitigation measures are warranted because planned cumulative electricity savings are expected to be achieved. Load Displacement No electricity savings were planned in F01. Industrial Sector Power Smart Partner Transmission Power Smart Partner Distribution New Plant Design Load Displacement Cross Sectoral Sustainable Communities Cumulative electricity savings in F01 were above plan. The program recovered from below plan results in F011 with a strong performance in the pulp and paper sector in F01. Cumulative electricity savings in F01 were slightly below plan. No mitigation measures are warranted. Cumulative electricity savings in F01 were above plan. Continued targeting of growth sectors with better market intelligence has increased the program s performance. Cumulative electricity savings in F01 were slightly below plan due to the delay of one project into F01. No mitigation measures are warranted as planned cumulative electricity savings are expected to be achieved. BC Hydro has adjusted the program due to the evolution of the district energy market and the characteristics of proposed district energy projects. BC Hydro will continue to support and influence the creation of community energy plans, but this effort will be structured as a supporting initiative within the existing Community Engagement initiative. Page 16

20 Lead by Example Cumulative electricity savings in F01 were above plan. The program has shifted focus towards projects offering more cost-effective electricity savings. 1 6 Operating Expenditures for Fiscal 01 BC Hydro s DSM operating expenditures in F01 totalled $8,000. Table 6 presents DSM operating expenditures in F01. Table 6 Operating Expenditures for Fiscal 01 ($000) Labour 707 Materials 18 ABS Services 19 Other Services 79 Facilities and Equipment Total Allocation of Supporting Initiative Costs to Programs This section describes how supporting initiative costs are allocated to programs for the purpose of cost test calculations. In keeping with Directive 61 from the BCUC decision on the F0/F06 RRA, when calculating levelized costs and benefit cost ratios for this report, supporting initiative costs are allocated to DSM programs and rate structures based on their share of DSM electricity savings in F018. For example, rate structures and programs are forecast to save roughly 6, GWh/year in F018, so a program that is forecast to save 6 GWh/year in F018 represents one per cent of the total. In turn, one per cent of supporting initiative costs would be allocated to that program in each year when calculating the program s levelized cost or benefit cost ratio. DSM operating expenditures are not included in earlier tables. A description of supporting initiatives is available in the F1-F1 RRA (Appendix II, Attachment ). Page 17

Re: FortisBC Inc. Application for Approval of Demand Side Management Expenditures for the Period of 2015 and 2016

Re: FortisBC Inc. Application for Approval of Demand Side Management Expenditures for the Period of 2015 and 2016 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL August 22, 2014 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604)

More information

For further information, please contact Fred James at or by at

For further information, please contact Fred James at or by  at Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com August 30, 2013 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

For further information, please contact Fred James at or by at

For further information, please contact Fred James at or by  at Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com February 28, 2014 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

For further information, please contact Fred James at or by at

For further information, please contact Fred James at or by  at Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com December 6, 2011 Ms. Alanna Gillis Acting Commission Secretary British Columbia Utilities

More information

BChgdro. lor\js. FOR GEt\JE B-1. September 30,2009

BChgdro. lor\js. FOR GEt\JE B-1. September 30,2009 BChgdro FOR GEt\JE lor\js B-1 Joanna Sofield Chief Regulatory Officer Phone: (0) -0 Fax: (0) -0 bchydroregulatorygroup@bchydro.com September 0,009 Ms. Erica M. Hamilton Commission Secretary British Columbia

More information

1. Background. March 7, 2014

1. Background. March 7, 2014 Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com March 7, 2014 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

November 8, Dear Mr. Wruck:

November 8, Dear Mr. Wruck: B-23 Fred James Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com November 8, 2017 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support

More information

For further information, please contact Fred James at or by at

For further information, please contact Fred James at or by  at Tom A. Loski Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com July 21, 2016 Ms. Laurel Ross Acting Commission Secretary British Columbia Utilities Commission

More information

FortisBC Inc. (FBC) Application for Approval of Demand Side Management (DSM) Expenditures for 2015 and 2016 FBC Final Submission

FortisBC Inc. (FBC) Application for Approval of Demand Side Management (DSM) Expenditures for 2015 and 2016 FBC Final Submission Dennis Swanson Director, Regulatory Affairs FortisBC Inc. Suite 100 1975 Springfield Road Kelowna, BC V1Y 7V7 Tel: (250) 717-0890 Fax: 1-866-335-6295 www.fortisbc.com Regulatory Affairs Correspondence

More information

BC HYDRO F2012 F2014 REVENUE REQUIREMENTS EXHIBIT A2 8

BC HYDRO F2012 F2014 REVENUE REQUIREMENTS EXHIBIT A2 8 ERICA M. HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL bchydroregulatorygroup@bchydro.com March 31, 2011 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

2015 Rate Design Application

2015 Rate Design Application 2015 Rate Design Application D-Wires Extension Policy Customer Workshops: July/August 2014 Discussion Guide Discussion Guide Distribution Extension Policy Review OVERVIEW Currently, BC Hydro is consulting

More information

BC Hydro takes this opportunity to raise the following two matters.

BC Hydro takes this opportunity to raise the following two matters. Tom A. Loski Chief Regulatory Officer Phone: 0--0 Fax: 0--0 bchydroregulatorygroup@bchydro.com September, 0 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 00

More information

For further information, please contact Guy Leroux at

For further information, please contact Guy Leroux at BChydro m R GENE IONS Joanna Sofield Chief Regulatory Officer Phone: (604 623-4046 Fax: (604 623-4407 bchyd roregulatorygroup@bchydro.com July 13 2009 Ms. Erica M. Hamilton Commission Secretary British

More information

FortisBC Inc. Annual Review of 2018 Rates Project No British Columbia Utilities Commission Information Request No. 1

FortisBC Inc. Annual Review of 2018 Rates Project No British Columbia Utilities Commission Information Request No. 1 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 September 6, 2017 Sent

More information

For further information please contact Fred James at

For further information please contact Fred James at BChydro Joanna Sofield Chief Regulatory Officer Phone: (604) 6-4046 Fax: (604) 6-4407 regulatory. group@bchydro.com July,008 Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission

More information

August 29, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

August 29, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. August 29, 2012 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 16705 Fraser Highway Surrey, B.C.

More information

BC HYDRO CONTRACTED GBL EXHIBIT A-6

BC HYDRO CONTRACTED GBL EXHIBIT A-6 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

For further information, please contact Sylvia von Minden at or by at

For further information, please contact Sylvia von Minden at or by  at B-1 Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com October 24, 2011 Ms. Alanna Gillis Acting Commission Secretary British Columbia Utilities

More information

Long-Term Rate Forecast

Long-Term Rate Forecast Long-Term Rate Forecast OVERVIEW This brief provides background information on the Long-Term Rate Forecast (LTRF) used in the 2011 Integrated Resource Plan (IRP). It is similar to the report filed as Attachment

More information

INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report November 24, 2017

INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report November 24, 2017 Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 INFORMATION RELEASE BCUC Receives Comments from BC Hydro on Site C Inquiry Final Report

More information

FORTISBC INC PERFORMANCE BASED RATEMAKING REVENUE REQUIREMENTS EXHIBIT A-27

FORTISBC INC PERFORMANCE BASED RATEMAKING REVENUE REQUIREMENTS EXHIBIT A-27 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL rhobbs@shaw.ca January 16, 2014 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. CANADA V6Z

More information

FortisBC Inc. Annual Review of 2018 Rates Project No Final Order with Reasons for Decision

FortisBC Inc. Annual Review of 2018 Rates Project No Final Order with Reasons for Decision Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 February 13, 2018 Sent

More information

INFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017

INFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017 INFORMATION RELEASE BCUC responds to BC Hydro s comments on the Site C Inquiry Final Report November 28, 2017 Vancouver The British Columbia Utilities Commission (BCUC) has responded to the letter from

More information

BC HYDRO F2017 F2019 REVENUE REQUIREMENTS EXHIBIT A-29

BC HYDRO F2017 F2019 REVENUE REQUIREMENTS EXHIBIT A-29 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX: (604)

More information

Power Smart Employment Impacts

Power Smart Employment Impacts Power Smart Employment Impacts DSM Programs, Rates and Codes and Standards, F2008 to F2037 March 2010 Prepared for: BC Hydro Power Smart 4555 Kingsway Avenue, Suite 900 Vancouver, BC V5H 4T8 Attention:

More information

FortisBC Inc. Application for an Exempt Residential Rate

FortisBC Inc. Application for an Exempt Residential Rate B-1 Corey Sinclair Manager, Regulatory Affairs FortisBC Inc. Suite 100-1975 Springfield Road Kelowna, BC V1Y 7V7 Ph: (250) 469-8038 Fax: 1-866-335-6295 electricity.regulatory.affairs@fortisbc.com www.fortisbc.com

More information

Revenue Requirement Application. 2004/05 and 2005/06. Volume 2. Appendix I. Power Smart 10-Year Plan

Revenue Requirement Application. 2004/05 and 2005/06. Volume 2. Appendix I. Power Smart 10-Year Plan Revenue Requirement Application 2004/05 and 2005/06 Volume 2 Appendix I. Power Smart 10-Year Plan 10-Year Plan: 2002/03 through 2011/12 December 2, 2003 Table of Contents 1 PLAN SUMMARY...1 2 PLAN COST-EFFECTIVENESS

More information

hydro /Yl- Fax: (604) Y,-- ww.bchydro. com Yours sinc

hydro /Yl- Fax: (604) Y,-- ww.bchydro. com Yours sinc -".... /Yl- -.-'- BC hydro Tony Morris Acting Chief Regulatory Offcer Phone: (604) 623-4046 Fax: (604) 623-4407 June 27, 2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities Commission

More information

BC Hydro Revenue Requirements Application Evidence #1

BC Hydro Revenue Requirements Application Evidence #1 BC Hydro Revenue Requirements Application Evidence #1 BCUC Project No.: 3698430 By: Ludo Bertsch, Horizon Technologies Inc. For: ESVI Energy Solutions for Vancouver Island Society Date: Oct 6, 2006 Background

More information

FEU COMMON RATES, AMALGAMATION RATE DESIGN RECONSIDERATION PHASE 2 EXHIBIT A-4

FEU COMMON RATES, AMALGAMATION RATE DESIGN RECONSIDERATION PHASE 2 EXHIBIT A-4 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL gas.regulatory.affairs@fortisbc.com July 24, 2013 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

VIA October 27, 2005

VIA  October 27, 2005 ROBERT J. PELLATT COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL

More information

FortisBC Energy Inc. (FEI) Project No Demand Side Management Expenditures Plan (the Application) Errata dated September 20, 2018

FortisBC Energy Inc. (FEI) Project No Demand Side Management Expenditures Plan (the Application) Errata dated September 20, 2018 B-1-1 Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

included in the survey is published in the Quarterly Reports and the Budget and Fiscal Plan.

included in the survey is published in the Quarterly Reports and the Budget and Fiscal Plan. Information Request No. 2.23.0(a) Dated: 5 April 2004 23.0 Reference: BC Hydro letter of March 29, 2004 indicating, among other things, that BC Hydro is prepared to call Mr. Robert Fairholm to testify

More information

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-3

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-3 Laurel Ross Acting Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 00 Howe Street Vancouver, BC Canada VZ N TEL: (0) 0-00 BC Toll Free: -00-- FAX: (0) 0- Log No. VIA

More information

PNG WEST 2013 REVENUE REQUIREMENTS EXHIBIT A-9

PNG WEST 2013 REVENUE REQUIREMENTS EXHIBIT A-9 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

STARGAS APPLICATION TO ALTER RATES. Re: Stargas Utilities Ltd. Application to Alter Rates and Refinance

STARGAS APPLICATION TO ALTER RATES. Re: Stargas Utilities Ltd. Application to Alter Rates and Refinance ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL FREE:

More information

Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 bcuc.com P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 ORDER NUMBER G-48-19 IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter

More information

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-3

FEVI DEFERRAL ACCOUNT PEC EXHIBIT A2-3 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL gas.regulatory.affairs@fortisbc.com April 4, 2013 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER,

More information

FortisBC Energy (Vancouver Island) Inc Revenue Requirements and Rates Application

FortisBC Energy (Vancouver Island) Inc Revenue Requirements and Rates Application February 20, 2014 File No.: 241455.00033/15275 Christopher R. Bystrom Direct 604 631 4715 Facsimile 604 632 4715 cbystrom@fasken.com BY ELECTRONIC FILING British Columbia Utilities Commission Sixth Floor,

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC. Commission de l énergie de l Ontario DECISION AND RATE ORDER GUELPH HYDRO ELECTRIC SYSTEMS INC. Application for rates and other charges to be effective January 1, 2018 By Delegation, Before: Theodore Antonopoulos

More information

BC Hydro FIrST QUArTEr report FISCAL 2015

BC Hydro FIrST QUArTEr report FISCAL 2015 BC Hydro FIRST QUARTER REPORT FISCAL 2015 BC Hydro & Power Authority Management S Discussion and Analysis This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority

More information

WHITBY HYDRO ELECTRIC CORPORATION

WHITBY HYDRO ELECTRIC CORPORATION Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER WHITBY HYDRO ELECTRIC CORPORATION Applications for an order approving just and reasonable rates and other charges for electricity

More information

January 23, Via Original via Mail. British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

January 23, Via  Original via Mail. British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 3700 2 nd Avenue Burnaby, BC V5C 6S4 January 23, 2014 Via Email Original via Mail 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Ms. Erica M. Hamilton, Commission Secretary Dear Ms. Hamilton:

More information

British Columbia Hydro and Power Authority

British Columbia Hydro and Power Authority 2016/17 SECOND QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

British Columbia Hydro and Power Authority

British Columbia Hydro and Power Authority 2017/18 THIRD QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

Diane Roy Vice President, Regulatory Affairs

Diane Roy Vice President, Regulatory Affairs B- Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro Ottawa Limited

More information

BC HYDRO INQUIRY OF EXPENDITURES SAP PLATFORM EXHIBIT A2-5. Commission staff submits the following document for the record in this proceeding:

BC HYDRO INQUIRY OF EXPENDITURES SAP PLATFORM EXHIBIT A2-5. Commission staff submits the following document for the record in this proceeding: Laurel Ross Acting Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX:

More information

Revenue Requirement Application 2004/05 and 2005/06. Volume 1. Chapter 2. Consolidated Revenue Requirements and Financial Schedules

Revenue Requirement Application 2004/05 and 2005/06. Volume 1. Chapter 2. Consolidated Revenue Requirements and Financial Schedules Revenue Requirement Application 00/0 and 00/0 Volume 1 Chapter. Consolidated Revenue Requirements and Financial Schedules Table of Contents LIST OF FIGURES... -IV LIST OF TABLES... -IV LIST OF SCHEDULES...-V

More information

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2013 and 2012

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2013 and 2012 An indirect subsidiary of Fortis Inc. Consolidated Financial Statements Prepared in accordance with United States Generally Accepted Accounting Principles MANAGEMENT S REPORT The accompanying annual consolidated

More information

BC Hydro writes in compliance with BCUC Order No. G to provide, as Exhibit B-3, its responses to BCUC Information Request No. 1.

BC Hydro writes in compliance with BCUC Order No. G to provide, as Exhibit B-3, its responses to BCUC Information Request No. 1. Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com October 25, 2013 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

July 7, 2015 File No.: /14797 BY . British Columbia Utilities Commission 6 th floor, 900 Howe Street Vancouver, BC V6Z 2N3

July 7, 2015 File No.: /14797 BY  . British Columbia Utilities Commission 6 th floor, 900 Howe Street Vancouver, BC V6Z 2N3 C7-3 July 7, 2015 File No.: 240148.00782/14797 Matthew Ghikas Direct +1 604 631 3191 Facsimile +1 604 632 3191 mghikas@fasken.com BY E-MAIL British Columbia Utilities Commission 6 th floor, 900 Howe Street

More information

CLASS EXEMPTION FOR BC HYDRO CUSTOMERS UNDER CERTAIN LEASE ARRANGEMENTS EXHIBIT A2-1

CLASS EXEMPTION FOR BC HYDRO CUSTOMERS UNDER CERTAIN LEASE ARRANGEMENTS EXHIBIT A2-1 Laurel Ross Acting Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX:

More information

Comprehensive Review of BC Hydro: Phase 1 Final Report

Comprehensive Review of BC Hydro: Phase 1 Final Report Comprehensive Review of BC Hydro: Phase 1 Final Report ii Table of Contents 1. Executive Summary 1 1.1 Enhancing Regulatory Oversight of BC Hydro 1 1.2 New Rates Forecast 3 1.3 Next Steps 5 2. Strategic

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. November 22, 2012 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 16705 Fraser Highway Surrey,

More information

building trust. driving confidence.

building trust. driving confidence. ~ building trust. driving confidence. January 29, British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Ms. Erica Hamilton, Commission Secretary and Director

More information

PARTIAL DECISION AND RATE ORDER

PARTIAL DECISION AND RATE ORDER Ontario Energy Board Commission de l énergie de l Ontario PARTIAL DECISION AND RATE ORDER KITCHENER-WILMOT HYDRO INC. Application for rates and other charges to be effective January 1, 2018 BEFORE: Lynne

More information

September 26, Via Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C.

September 26, Via  Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C. B-8 Diane Roy Director, Regulatory Affairs FortisBC Energy 16705 Fraser Highway Surrey, B.C. V4N 0E8 Tel: (604) 576-7349 Cell: (604) 908-2790 Fax: (604) 576-7074 Email: diane.roy@fortisbc.com www.fortisbc.com

More information

Terasen Gas (Vancouver Island) Inc. ( TGVI ) 2010 and 2011 Revenue Requirements and Rate Design Application (the Application )

Terasen Gas (Vancouver Island) Inc. ( TGVI ) 2010 and 2011 Revenue Requirements and Rate Design Application (the Application ) Tom A. Loski Chief Regulatory Officer 16705 Fraser Highway Surrey, B.C. V4N 0E8 Tel: (604) 592-7464 Cell: (604) 250-2722 Fax: (604) 576-7074 Email: tom.loski@terasengas.com www.terasengas.com Regulatory

More information

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014)

Parties are invited to make submissions on IR responses and the additional topics to be issued by the Panel. ACTION DATE (2014) ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

FORTISBC ENERGY CEC ROE 2016 EXHIBIT A-7

FORTISBC ENERGY CEC ROE 2016 EXHIBIT A-7 ERICA HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

Energy Conservation Resource Strategy

Energy Conservation Resource Strategy Energy Conservation Resource Strategy 2008-2012 April 15, 2008 In December 2004, EWEB adopted the most recent update to the Integrated Electric Resource Plan (IERP). Consistent with EWEB s three prior

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED Commission de l énergie de l Ontario DECISION AND RATE ORDER ORANGEVILLE HYDRO LIMITED Application for an order approving just and reasonable rates and other charges for electricity distribution to be

More information

FIVE YEAR PLAN FOR ENERGY EFFICIENCY

FIVE YEAR PLAN FOR ENERGY EFFICIENCY FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011

More information

2015 RATE DESIGN APPLICATION (RDA) TRANSMISSION SERVICE RATE (TSR) STRUCTURES WORKSHOP #1

2015 RATE DESIGN APPLICATION (RDA) TRANSMISSION SERVICE RATE (TSR) STRUCTURES WORKSHOP #1 2015 RATE DESIGN APPLICATION (RDA) TRANSMISSION SERVICE RATE (TSR) STRUCTURES WORKSHOP #1 22 October, 2014 INTRODUCTION AGENDA Approximate Time Item Presenter(s) 9 :00 9:10 Welcome Anne Wilson Background

More information

Long Run Marginal Cost (LRMC)

Long Run Marginal Cost (LRMC) Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Agenda & Objectives Preliminary Discussion PART I Provide a historic overview of FBC s LRMC Highlights from BC Hydro s stated

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); Ontario Energy Board Commission de l Énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); AND IN THE MATTER OF an Application by Peterborough Distribution

More information

Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan

Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan 2016-2018 Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan submitted to the Ontario Energy Board Date: November 10, 2016 DNV GL - Energy www.dnvgl.com/energy Table

More information

Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist

Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Long Run Marginal Cost (LRMC) Ryan Steele Power Supply Planning Specialist Overview Provide a historic overview of FBC s LRMC Highlight BC Hydro s stated LRMC Discuss FBC s proposed LRMC approach Relationship

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); Ontario Energy Board Commission de l Énergie de l Ontario RP-2005-0020 EB-2005-0371 IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); AND IN THE MATTER OF an Application

More information

GUELPH HYDRO ELECTRIC SYSTEMS INC.

GUELPH HYDRO ELECTRIC SYSTEMS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER GUELPH HYDRO ELECTRIC SYSTEMS INC. Application for an order approving just and reasonable rates and other charges for electricity

More information

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2017 and 2016

FortisBC Energy Inc. An indirect subsidiary of Fortis Inc. Consolidated Financial Statements For the years ended December 31, 2017 and 2016 An indirect subsidiary of Fortis Inc. Consolidated Financial Statements Prepared in accordance with accounting principles generally accepted in the United States of America MANAGEMENT S REPORT The accompanying

More information

September 10, Via Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C.

September 10, Via  Original via Mail. British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, B.C. C- Email: electricity.regulatory.affairs@fortisbc.comemail: electricity.regulatory.affairs@fortisbc.com Dennis Swanson Director, Regulatory Affairs FortisBC Inc. Suite 00 Springfield Road Kelowna, BC VY

More information

Exhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan

Exhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan Exhibit DAS-1 Tucson Electric Power Company Demand-Side Management Program Portfolio Plan 2008-2012 TABLE OF CONTENTS 1. Introduction...3 2. DSM Portfolio Performance Costs, Savings and Net Benefits...3

More information

DECISION AND RATE ORDER

DECISION AND RATE ORDER DECISION AND RATE ORDER WELLINGTON NORTH POWER INC. Application for rates and other charges to be effective May 1, 2019 By Delegation, Before: Pascale Duguay March 28, 2019 Ontario Energy Board 1 INTRODUCTION

More information

Cascade Pacific Power Corporation

Cascade Pacific Power Corporation February 7, 2008 C23-3 BC Hydro and Power Authority 17 th Floor, 333 Dunsmuir Street Vancouver, BC V6B 5R3 Attention: Ms. Joanna Sofield, Chief Regulatory Officer Dear MS. Sofield RE: Standing Offer Program

More information

75.0 Reference: Application, Volume I, Chapter 3, pp. 3-3 to 3-5; Chapter 6, p Budget Process and Variance Analysis

75.0 Reference: Application, Volume I, Chapter 3, pp. 3-3 to 3-5; Chapter 6, p Budget Process and Variance Analysis Revenue Requirements 1 75.0 Reference: Application, Volume I, Chapter 3, pp. 3-3 to 3-5; Chapter 6, p. 6-42 Budget Process and Variance Analysis Section 2 of Chapter 3 describes how the F2005 and F2006

More information

Economic Impact Assessment Study Ontario Rental Housing Sector

Economic Impact Assessment Study Ontario Rental Housing Sector Economic Impact Assessment Study Ontario Rental Housing Sector December 2013 Federation of Rental Housing Providers of Ontario KPMG Canada kpmg.ca Table of Contents 1. Executive Summary 1 2. Introduction

More information

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-6

FORTISBC ENERGY PROPOSAL FOR DEPRECIATION & NET SALVAGE RATE CHANGES EXHIBIT A2-6 Laurel Ross Acting Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX:

More information

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 AGENDA Background on BC Hydro s 2015 Rate Design Application

More information

Enersource Hydro Mississauga Inc. Application for Distribution Rates Effective January 1, 2017 Board File No.: EB

Enersource Hydro Mississauga Inc. Application for Distribution Rates Effective January 1, 2017 Board File No.: EB August 15, 2016 BY RESS & OVERNIGHT COURIER Ms. Kirsten Walli Board Secretary Ontario Energy Board P.O. Box 2319 2300 Yonge Street, Suite 2700 Toronto, Ontario M4P 1E4 Dear Ms. Walli: Re: Enersource Hydro

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC. Commission de l énergie de l Ontario DECISION AND RATE ORDER NIAGARA PENINSULA ENERGY INC. Application for an order approving just and reasonable rates and other charges for electricity distribution to

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support B-2 10 th Floor 1111 West Georgia Street Vancouver, BC, V6E 4M3 April 21, 2017 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Mr. Patrick Wruck, Commission

More information

Essex Powerlines Corporation 2730 Highway #3, Oldcastle, ON, N0R 1L0 Telephone: (519) Fax: (519)

Essex Powerlines Corporation 2730 Highway #3, Oldcastle, ON, N0R 1L0 Telephone: (519) Fax: (519) Kirstin Walli Board Secretary Ontario Energy Board 27 th Floor 2300 Yonge Street Toronto, ON M4P 1E4 September 27, 2013 RE: ESSEX POWERLINES CORPORATION 2014 IRM 3 Electricity Distribution Rates Application

More information

BCUC INQUIRY RESPECTING SITE C A-4

BCUC INQUIRY RESPECTING SITE C A-4 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 August 11, 2017 Sent

More information

2018/19 SECOND QUARTER REPORT

2018/19 SECOND QUARTER REPORT 2018/19 SECOND QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER VERIDIAN CONNECTIONS INC. Application for rates and other charges to be effective May 1, 2018 By Delegation, Before: Jane

More information

BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, RICHARD McCANDLESS

BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, RICHARD McCANDLESS BC HYDRO FISCAL 2017 TO FISCAL 2019 REVENUE REQUIREMENTS APPLICATION JUNE 8, 2017. RICHARD McCANDLESS THE BC UTILITIES COMMISSION SHOULD NOT APPROVE ANY DISCRETIONARY REQUESTS PENDING A NEW APPROACH TO

More information

Our File: Date: April 22, 2015

Our File: Date: April 22, 2015 B-2 BY E-MAIL British Columbia Utilities Commission 6th Floor - 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Erica Hamilton, Commission Secretary Dear Ms. Hamilton: Re: Reply Attention of: Matthew

More information

Reference: Exhibit B-5-1, page 1-4, Section , Electricity Demand Growth

Reference: Exhibit B-5-1, page 1-4, Section , Electricity Demand Growth C18-2 REQUESTOR NAME: Independent Power Producers of B.C. INFORMATION REQUEST ROUND NO: 1 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: July 5, 2006 PROJECT NO: 3698416 APPLICATION NAME: F2007/F2008

More information

BC Hydro 2008 Long Term Acquisition Plan. Request by Mr. Ludo Bertsch to represent other organizations

BC Hydro 2008 Long Term Acquisition Plan. Request by Mr. Ludo Bertsch to represent other organizations BC Hydro 2008 Long Term Acquisition Plan C23-5 Request by Mr. Ludo Bertsch to represent other organizations By: Ludo Bertsch, Horizon Technologies Inc. (250) 592-1488; ludob@horizontec.com Date: December

More information

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and

IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473. and BRITISH C OLUMBIA U TILITIES C OMMISSION O RDER NUMBER C-10-07 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com TELEPHONE: (604) 660-4700 BC TOLL FREE:

More information

CONSOLIDATED FINANCIAL STATEMENTS 2011

CONSOLIDATED FINANCIAL STATEMENTS 2011 FINANCIAL RESULTS CONSOLIDATED FINANCIAL STATEMENTS 2011 MANAGEMENT REPORT The consolidated financial statements of British Columbia Hydro and Power Authority (BC Hydro) are the responsibility of management

More information

VIA March 18, 2010 BCTC F2011 CAPITAL PLAN UPDATE EXHIBIT A 4

VIA  March 18, 2010 BCTC F2011 CAPITAL PLAN UPDATE EXHIBIT A 4 ERICA M. HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com VIA EMAIL Janet.fraser@bctc.com bctc.regulatory@bctc.com March 18, 2010 SIXTH FLOOR, 900 HOWE STREET,

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

British Columbia Hydro and Power Authority

British Columbia Hydro and Power Authority 2017/18 SECOND QUARTER REPORT MANAGEMENT S DISCUSSION AND ANALYSIS This Management s Discussion and Analysis (MD&A) reports on British Columbia Hydro and Power Authority s (BC Hydro or the Company) consolidated

More information

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2018

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2018 Oakville Hydro Electricity Distribution Inc. 2018 Distribution Rate Adjustment Application (EB-2017-0067) Effective January 1, 2018 IN THE MATTER OF the Ontario Energy Board Act, 1998, being Schedule B

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information