Coordination and generation of of transmission investment
|
|
- Adam O’Brien’
- 5 years ago
- Views:
Transcription
1 Coordination and generation of of transmission investment John John Gleadow Senior Senior Advisor Transmission Presented to to the the Transmission Advisory Group April 2007
2 Purpose of this presentation Present the discussion paper - Coordination of transmission and renewable generation investment - circulated to the TAG Promote discussion on: the issue of coordination generation and transmission investment and the proposed approach for addressing this coordination problem 2
3 Background One of the main issues for the electricity industry is the coordination of transmission and generation investment in the deregulated generation sector Several stakeholders has raised concerns that this coordination problem with the Commission The Commission is currently considering the coordination of renewable generation and interconnection investments 3
4 The coordination problem Investors in new generation will be more willing and able to invest if new transmission assets are committed that are required to support (or increase utilisation of) new generation If a transmission investment is not needed in the absence of new generation, investors in transmission assets will rationally want investors to commit to building new generation This problem is further exacerbated by the usually substantially longer lead time of a large transmission investment relative to a generation investment 4
5 Conceptual approaches Various conceptual approaches internationally: Argentina: Transmission only built when one user (or a group of users) agree to underwrite a specific investment. Past experience in New Zealand has demonstrated that it is not a practical approach Alberta (Canada): Market generation investment outcomes are uncertain and, therefore, a constraint-free grid is provided to allow for connection of future generation in any location 5
6 The constraint-free approach Some parties have in the past advocated the constraint-free approach However, off-take customers face the cost of new interconnection assets and would only want a new asset if: it is necessary for reliability purposes or provides a clear economic benefit Endorsing the constraint-free approach would likely result in over investment in the grid and is inconsistent with the current regulatory framework and objectives of the Commission 6
7 Rule framework Two type of investments Economic investments - benefits outweigh the cost Reliability investments - needed to meet reliability standards Interconnection investments needed to support remote generation investment are treated as economic investment if they are not needed to security standards (this will almost always be the case) 7
8 SOO and the MDS The Statement of Opportunities (SOO): is produced every two years enables the identification of potential opportunities for efficient management of the grid provide participants with a list of committed and highly likely generation projects sets out the market development scenarios (MDS) The MDS represents the possible future states of the electricity market and: are used to evaluate the merits of a transmission investment option with the GIT and assign specific economic parameters for possible future projects 8
9 Investment cycle 9
10 Current approval process The Commission recognised that, some time after publication of the SOO, more accurate information regarding the demand levels or prospective generation would arise Accordingly, the GIT allows Transpower, the proponent of a transmission alternative or the Commission to use a more appropriate revised set of MDS to evaluate a proposal This approach has already been used for several reliability investment projects where assumptions have been made regarding the location and costs of possible future transmission and generation investments 10
11 Staged approval (1) However, Transpower has indicated that a key issue is being able to initiate the RMA process, as it dominates the overall lead time for building transmission lines A pragmatic solution is the staged approval of long lead time investments within the existing Rules framework As the current Rules framework allows Transpower to submit an economic investment for approval, before a commitment by investors to build generation, approval of transmission investment could be sought in stages 11
12 Staged approval (2) The Commission is able to approve expenditure for initial stages (such as preliminary design, RMA and land costs) Approval of remaining stages of expenditure (such as capital costs) would be at a later date This would allow Transpower (and the Commission) to the receive further information on the commitment of investors and other relevant parameters before approving the majority of the expenditure is incurred This process avoid the provision of unnecessary transmission interconnection assets 12
13 Staged approval (3) Step I EC Support for (RMA) consultation Step II Initial and preparatory stage(s) approved Step III Approval of remaining stages Project Cost $ Transpower recovers expenditure from internal budget Costs incurred passed on to industry through pricing methodology, regardless of whether unconditional approval is given 10% Time Now Oct 2007 Late 2008 Late Typical Grid Upgrade Approval Timing 13
14 Staged approval (4) In approving a staged investment, the Commission may, for example, consider: The extent that a coordination problem is addressed (primary effect on proposed generation and secondary effect on future generation) The extent to which net benefits are diminished by delaying transmission and generation investment The effect of staged approval on the comparison the proposal to alternatives at later stages 14
15 Other types of transmission investment There are other types of investment that need to be discussed Substation investment: often located at one physical site and offer modification of existing sites Greenfield substations would involve similar timescale to new generation investment Connection assets: new generators require the use of dedicated connection assets (e.g. spur transmission lines) process and cost need to be agreed with the developer some recent wind generation projects have identified these assets in their RMA process 15
16 Examples Central Hawkes Bay (1) Transpower and Commission staff have recently discussed the effect of a number of wind generators potentially connecting in the Central Hawkes Bay It was suggested that a revised regional scenario be developed to include new information to assist in demonstrating the economic need for investment provide effective coordination in investment activities by supplying valuable information and signals to potential investors 16
17 Examples Central Hawkes Bay (2) The Commission would need to take into account the difference in timing between work to build the transmission investment and that for generation investment Therefore, a staged approval process would also be appropriate to coordinate investment so that any investment was likely to be utilised after commissioning In addition to the short term focus, the Commission could consider the likelihood of investment in the medium term that may also occur 17
18 Examples Lower South Island (1) Concern about constraint on the grid in the Central Otago region 733 MW of new wind generation in Central Otago proposed Currently 752 MW of hydro generation in the same region Existing constraints sometimes lead to hydro generation at Roxburgh/Clyde being unable to generate to capacity New wind generation, without sufficient investment in transmission, could lead to the further constraint of Roxburgh/Clyde generation 18
19 Examples Lower South Island (2) USI Demand HVDC Benmore /Twizel Existing Generation (Clyde, Roxburgh, Manapouri) G Transmission Constraint Roxburgh /Clyde Possible New Wind Generation (Project Hayes, Lake Mahinerangi) LSI Demand (including Tiwai) 19
20 Examples Lower South Island (3) In this example the coordination problem means that wind energy could displace hydro, and economic loss may arise as a result of energy spill Generation investors may become concerned with the level of transmission constraints in the region - they need to have confidence that necessary transmission investment would be forthcoming to invest 20
21 Examples Lower South Island (4) The Commission has undertaken analysis that provides information that reflects the likely result of different levels of investment which provides a signal which may, in part, relieve coordination problems reflects (at a very high level) the type of analysis that Transpower would undertake to support a staged economic investment that arises from potential new generation The results of the analysis are set out on the following slide. Details of the analysis are set out in Appendix 3 of the accompanying discussion paper 21
22 Examples Lower South Island (5) 22
23 Examples Lower South Island (6) 23
24 Conclusion Transpower has the opportunity to seek approval for economic investments through the normal GIT process (i.e. using the SOO MDS) or a combination of the following approaches Modifying the MDS (which the Commission must ultimately agree are appropriate) A staged approval process A further process of engagement is to be initiated with Transpower to discuss the opportunities for a staged approval process This could be through the GUP/GIT guidelines 24
Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results
Wairakei Ring Investment Proposal Project Reference: CTNI_TRAN-DEV-01 Attachment A GIT Results December 2008 Document Revision Control Document Number/Version 001/Rev A Description Wairakei Ring Investment
More informationHVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs
HVDC Inter-Island Link Upgrade Project Investment Proposal Part V Project Costs Transpower New Zealand Limited 2005. All rights reserved 1 SUMMARY... 3 2 BACKGROUND... 4 3 APPROACH TO ESTIMATING COSTS...
More informationElectricity Industry Bill
Electricity Industry Bill Request for additional information by Finance and Expenditure Committee The additional information sought by the committee on 17 February 2010 is set out in the following tables.
More informationSystem Operator Reports October Contents System Operator Monthly Operational Performance Report System Performance Report
System Operator Reports October 2015 Contents Section 1 Section 2 System Operator Monthly Operational Performance Report System Performance Report System Operator Operational and System Performance Report
More informationAUFLS information paper
AUFLS information paper Contents 1 Introduction... 1 2 The under-frequency management challenge... 1 3 Overview of current arrangements... 3 3.1 The current AUFLS exemptions... 4 4 Initiatives to address
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationWanganui - Stratford Investment Proposal. Attachment B Costing report
Wanganui - Stratford Investment Proposal Attachment B Costing report September 2009 Document Revision Control Document Number/Version Description Date 001/ A Wanganui-Stratford Investment Proposal Attachment
More information2016 INTEGRATED TRANSMISSION PLAN COMPLIANCE REPORT
2016 INTEGRATED TRANSMISSION PLAN COMPLIANCE REPORT APPENDIX: ITP COMPLIANCE Introduction Our first integrated transmission plan (ITP), which we completed in 2013, was embedded within our regulatory proposal
More informationENERGY STRATEGY FOR YUKON. Micro-Generation Policy
ENERGY STRATEGY FOR YUKON Micro-Generation Policy October 23, 2013 IMPLEMENTING THE ENERGY STRATEGY FOR YUKON Yukon Government Micro-Generation Policy Page 1 of 4 BACKGROUND The Yukon government released
More informationHVDC component of Transpower s proposed variation to the Transmission Pricing Methodology
+ HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology Decisions and reasons 14 August 2015 932889v7 Contents 1. Introduction 1 2. The Authority has decided to proceed
More informationContents Introduction Chapter 1 - Security Policy... 6
Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...
More informationStatement of Intent
Statement of Intent 2018 2021 Contents 1. Introduction... 3 2. Corporate Overview... 4 2.1 The Power Company Limited... 4 2.2 Company Structure... 5 2.3 Investment Diversification... 5 3. Industry Landscape...
More informationAN ORDER OF THE BOARD NO. P.U. 47(2014)
NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 47(2014) 1 IN THE MATTER OF the Electrical Power 2 Control Act, 1994, SNL 1994, Chapter E-5.1 (the 3
More informationMeridian Energy NZX retail investor presentation
Meridian Energy NZX retail investor presentation 1 October 2018 Attached is a presentation Meridian Energy Limited is making at NZX retail investor evenings in early October 2018. ENDS Neal Barclay Chief
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationMultiple Frequency Keepers Project Plan
Multiple Frequency Keepers Project Plan Prepared by Mike Collis Project number: CQ01 Date: September 2009 Version: 1.0 601068-1_Multiple Frequency Keepers - Project Plan A 2 November 2010 3.07 p.m. Document
More informationReal Options and Transmission Investment: the New Zealand Grid Investment Test
Real Options and Transmission Investment: the New Zealand Grid Investment Test Glenn Boyle New Zealand Institute for the Study of Competition and Regulation, Victoria University of Wellington, Wellington,
More informationHORIZON ENERGY DISTRIBUTION LIMITED
HORIZON ENERGY DISTRIBUTION LIMITED THRESHOLD COMPLIANCE STATEMENT FOR THE ASSESSMENT DATE, 31 MARCH 2010 Pursuant to the Commerce Act (Electricity Distribution Thresholds) Notice 2004 and Amendment Notice
More informationMERIDIAN ENERGY SUBMISSION ON TRANSMISSION PRICING METHODOLOGY: ISSUES AND PROPOSAL CONSULTATION PAPER
MERIDIAN ENERGY SUBMISSION ON TRANSMISSION PRICING METHODOLOGY: ISSUES AND PROPOSAL CONSULTATION PAPER 1 March 2013 TABLE OF CONTENTS EXECUTIVE SUMMARY 4 The Authority s proposal is based on sound principles
More informationElectricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))
GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation
More informationNorthern Tier Transmission Group Cost Allocation Principles Work Group. Straw Proposal. May 29, 2007
Northern Tier Transmission Group Cost Allocation Principles Work Group Straw Proposal May 29, 2007 NTTG Cost Allocation Principles and Process page 1 INTRODUCTION This paper makes a strawman proposal responsive
More informationRoadshow Presentation
Roadshow Presentation April 2010 Tonbridge Power Inc. The Waterpark Place 20 Bay Street, 11 th Floor Toronto, ON t: 416.850.2150 f: 416.850.1985 1 www.tonbridgepower.com Disclaimer This presentation and
More informationOrganization of MISO States Response to the Midwest ISO October Hot Topic on Pricing
Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of
More informationProject Assessment Conclusions Report
Powerlink Queensland Project Assessment Conclusions Report 27 August 2018 Addressing the secondary systems condition Disclaimer While care was taken in preparation of the information in this document,
More informationNORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY
NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent
More informationCMP303 - Improving local circuit charge cost-reflectivity
CMP303 - Improving local circuit charge cost-reflectivity This modification seeks to make part of the TNUoS charge more cost-reflective through removal of additional costs from local circuit expansion
More informationSPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects
SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder
More informationSmart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems
Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems -1- TABLE OF CONTENTS Section I. Application Process..
More informationMISO Planning Process. May 31, 2013
MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.
More informationAdditional examples of government support on projects has been provided on the record in response to MH/MIPUG I-3.
0 0 REFERENCE: Undertaking #, Transcript page 0, QUESTION: a) MIPUG panel to provide brief summary of various examples of government support or intervention in projects to deal with rate pressures; also
More informationUser Commitment for Generator Focused Anticipatory Investment (GFAI)
All Industry Parties Patrick Hynes Electricity Charging & Capacity Development Manager patrick.hynes@nationalgrid.com Direct tel.: 01926 656319 22 nd May 2015 Dear Colleagues, User Commitment for Generator
More informationOctober Leading Energy
October 2012 Leading 2 Introduction Welcome to your update on the key issues and challenges for New Zealand s electricity generation and retail companies in FY12. We take a look at how the sector dealt
More informationPowering today, protecting tomorrow. MERIDIAN ENERGY LIMITED I investor roadshow presentation
Powering today, protecting tomorrow Disclaimer The information in this presentation was prepared by Meridian Energy with due care and attention. However, the information is supplied in summary form and
More informationExhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs
Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs The Hawaiian Electric Companies 1 process for developing their draft request for proposals ( RFP ) for Firm Capacity
More informationEIPC Roll-Up Report & Scenarios
EIPC Roll-Up Report & Scenarios Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG/ESPWG Meeting January 6, 2014 2013 New York Independent System Operator, Inc.
More informationCASA-1000 Project List of FAQs
1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan
More informationIntegrated Single Electricity Market (I-SEM) Capacity Remuneration Mechanism Parameters Consultation Paper SEM
Integrated Single Electricity Market (I-SEM) Capacity Remuneration Mechanism Parameters Consultation Paper SEM-18-028 A Submission by EirGrid and SONI 26 th June 2018 Contents 1 Introduction...2 1.1 EirGrid
More informationEstimating Capacity Benefits of the AC Transmission Public Policy Projects
Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second
More informationstated. This Ruling applies is the issue Manager. b) of Asteron A Life PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T
Office O of the Chief Tax Counsel Te T Tari o te Rōia Tāke Matua Asteron A Life 555 Featherstonn Street PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T 044 890-1500 Facsimile F Numbers: Chief
More informationEMA Submission. to the. Electricity Authority. on the. Transmission Pricing Methodology Issues and Proposal (Second Issues Paper)
EMA Submission to the Electricity Authority on the Transmission Pricing Methodology Issues and Proposal (Second Issues Paper) Submitted July 26 2016 About the EMA The EMA has a membership of more than
More informationOtahuhu Sub-Station Conference. Graeme Everett 23 rd July 2007
Otahuhu Sub-Station Conference Graeme Everett 23 rd July 2007 The World of Norske Skog Europe - 100% Skogn Follum Union Saubrugs Parenco Walsum Steti Golbey Bruck Chongwon Hebei Chonju Pan Asia - 100%
More informationTRANSMISSION OWNER ZONAL PLACEMENT PROCESS
TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection
More informationDistributed Generation Connection Standard ST B Planning Engineer. Network Planning Manager. General Manager Network
Effective Date 1 May 2018 Issue Number 1.1 Page Number Page 1 of 26 Document Title Distributed Generation Connection Standard Document Number ST B1.1-001 Document Author Planning Engineer Document Reviewer
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Kirby North Central Processing Facility Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities
More informationSmart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial
Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial Distribution Systems Revised January 1, 2017 TABLE OF CONTENTS
More informationKing Country Energy Limited. Independent Adviser s Report. In Respect of the Full Takeover Offer by the King Country Energy Joint Venture
King Country Energy Limited Independent Adviser s Report In Respect of the Full Takeover Offer by the King Country Energy Joint Venture December 2017 Statement of Independence Simmons Corporate Finance
More informationLOSS AND CONSTRAINT EXCESS PAYMENT
LOSS AND CONSTRAINT EXCESS PAYMENT METHOD FOR DETERMINING CUSTOMER SHARE Transpower New Zealand Limited September 2017 i Table of Contents Introduction... ii 1 What are transmission rentals?... 1 1.1
More informationCMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment
Stage 04: Code Administrator Consultation Connection and Use of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment 01 02 03 04 05 What
More informationLivingstone Landowners Guild
Decision 20846-D01-2016 Livingstone Landowners Guild Application for Review of Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement as amended
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,
More informationTransmission Loss Factor Methodology
Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3
More informationAmendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:
More informationCUSC Section 15 (CMP192) User Commitment Methodology
CUSC Section 15 (CMP192) User Commitment Methodology Guidance and Implementation Document 1 May 2012 Version 1 1 1. Summary... 3 2. Purpose of the document...3 3. Background... 4 4. Attributable and Wider
More informationDecision on Electricity Network Connection Policy
Decision on Electricity Network Connection Policy DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/09/138 25 August 2009 John Orme (distribution@cer.ie) The Commission for Energy
More informationBalancing Market Principles Statement Terms of Reference Scoping Document. Energy Trading Arrangements Rules Working Group 5
Balancing Market Principles Statement Terms of Reference Scoping Document Energy Trading Arrangements Rules Working Group 5 RA Project Team Discussion Document 11 February 2016 INTRODUCTION This document
More informationSummary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts
Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts 1. Commission Directives to Submit a Market Redesign Plan The direct origin of the requirement that the CAISO
More informationNOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54-55 AND REGULATION 1228\03 IN THE ELECTRICITY AND GAS INTERNAL MARKET
NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54-55 AND REGULATION 1228\03 IN THE ELECTRICITY AND GAS INTERNAL MARKET THIS DOCUMENT IS NOT BINDING ON THE COMMISSION EXEMPTIONS FROM CERTAIN PROVISIONS
More informationLong-Term Reliability Assessment
Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and
More informationKing Country Energy Limited. Independent Adviser s Report. In Respect of the Full Takeover Offer by King Country Energy Holdings Limited
King Country Energy Limited Independent Adviser s Report In Respect of the Full Takeover Offer by King Country Energy Holdings Limited November 2015 Statement of Independence Simmons Corporate Finance
More informationCOMMERCE COMMISSION Regulation of Electricity Distribution Businesses Review of the Information Disclosure Regime
COMMERCE COMMISSION Regulation of Electricity Distribution Businesses Review of the Information Disclosure Regime Process Paper: Implementation of the New Disclosure Requirements 30 April 2008. Network
More informationMuskrat Falls Project
Review of project cost, schedule and related risks Interim report April 8, 2016 Julia Mullaley Clerk of the Executive Council & Secretary to Cabinet Government of Newfoundland and Labrador P.O. Box 8700
More informationExpenditure Forecast Methodology
Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box
More informationProject Coordination and Path Rating
Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document
More informationBC Hydro Open Access Transmission Tariff Effective: 09 December 2010 OATT Attachment M-1 Appendix 5 Page 1
APPENDIX 5 to SGIP BC Hydro OATT Attachment M-1 Appendix 5 Page 1 Standard Generator Interconnection Agreement (SGIA) Project Name Table of Contents BC Hydro OATT Attachment M-1 Appendix 5 Page 2 Article
More informationSNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014
SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014 1. INTRODUCTION This for Snowy Hydro Limited ( Snowy Hydro or the Company ) continues a focus on the continued development and augmentation of Snowy
More informationMEMORANDUM OF UNDERSTANDING
MEMORANDUM OF UNDERSTANDING This Memorandum of Understanding ( MOU ) is made effective as of January 30, 2019 among Central Maine Power Company, a Maine corporation with offices located at 83 Edison Drive,
More information(Transpower) Reasons paper December 2010
Individual price-quality path (Transpower) Reasons paper December 2010 Regulation Branch Commerce Commission Wellington NEW ZEALAND 22 December 2010 ISBN: 978-1-869450-95-3 Commerce Commission i Table
More informationAcciona Wind Energy Canada, Inc.
Decision 2013-439 Acciona Wind Energy Canada, Inc. New Dayton Wind Power Project Facility & Substation Costs Award December 11, 2013 The Alberta Utilities Commission Decision 2013-439: Acciona Wind Energy
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket No. ER99-3339-000 Operator Corporation ) ) REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT
More informationOrder No Transmission Planning and Cost Allocation
Order No. 1000 Transmission Planning and Cost Allocation Thursday, August 18, 2011, 1:00 pm Eastern Panelists: John D. McGrane, Floyd L. Norton, IV, Stephen M. Spina www.morganlewis.com Overview Order
More informationISO Transmission Planning Process. Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet
ISO 2016-2017 Transmission Planning Process Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet January 4, 2018 Contents 1. Introduction... 1 2. Background... 1 3. Objectives
More informationCoos County Transmission Action Plan & Cost Allocation Methodologies
Coos County Transmission Action Plan & Cost Allocation Methodologies Presentation to the NCTC KEMA, Inc. June 17, 2010 Experience you can trust. Agenda Introduction to KEMA Project Objectives Status of
More informationDevelopment of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement
Development of the Renewable Dispatchable Generation Model Overview of SEPA & ScottMadden Engagement Speakers John Sterling Senior Director, Advisory Services Smart Electric Power Alliance John Pang Partner
More information2017 Winter review. Final report. 22 March Market Performance
2017 Winter review Final report 22 March 2018 Market Performance Executive summary The winter of 2017 was characterised by an extended period of low hydro inflows in the South Island. The Electricity Authority
More informationREPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED
THE REPUBLIC OF UGANDA REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED KARUMA INTERCONNECTION PROJECT FEASIBILITY STUDY FOR PERIOD 5 TH
More informationTransmission Charging Methodologies Forum
Transmission Charging Methodologies Forum Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Tuesday
More informationRisk Management Framework. Metallica Minerals Ltd
Risk Management Framework Metallica Minerals Ltd Risk Management Framework 23 March 2012 Table of Contents Contents 1. Introduction... 3 2. Risk Management Approach... 3 3. Roles and Responsibilities...
More informationNPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY
NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY NEW BRUNSWICK POWER CORP. NOVA SCOTIA POWER INC. MARITIME ELECTRIC COMPANY, LIMITED NORTHERN MAINE ISA, INC. Approved by RCC December 5, 2017
More informationPreliminary Economic and Fiscal Impacts of the Proposed Northern Pass Transmission Project Prepared for Northern Pass Transmission LLC
Preliminary Economic and Fiscal Impacts of the Prepared for Northern Pass Transmission LLC Prepared by Dr. Lisa Shapiro Chief Economist and Heidi Kroll Policy Analyst Gallagher, Callahan & Gartrell, P.C.
More informationSubmission to the Commerce Commission on the CPP Process Review
Submission to the Commerce Commission on the CPP Process Review An independent report prepared for the Electricity Retailers Association of New Zealand 30 th July 2018 tdb.co.nz TDB Advisory Limited L5,
More informationCMP223 Arrangements for
Stage 02: 03: Workgroup Consultation Report Connection and and Use Use of of System Code (CUSC) CMP223 Arrangements for Relevant Distributed Generators Under the Enduring Generation User Commitment What
More informationCity of Montclair, California Debt Management Policy
City of Montclair, California Debt Management Policy POLICY This Debt Management Policy sets forth certain debt management objectives for the City of Montclair (City), and establishes overall parameters
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for the Riverview Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission
More informationPeople s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing
Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management
More informationCHARGING METHODOLOGY STATEMENT FOR THE ELECLINK INTERCONNECTOR
CHARGING METHODOLOGY STATEMENT FOR THE ELECLINK INTERCONNECTOR ISSUE 1.0 1 Contents 1. Introduction... 3 2. Interconnector charging methodology... 3 2.1 Introduction... 3 2.2 Objectives of the Charging
More informationCalifornia ISO. Flexible Ramping Product Uncertainty Calculation and Implementation Issues. April 18, 2018
California Independent System Operator Corporation California ISO Flexible Ramping Product Uncertainty Calculation and Implementation Issues April 18, 2018 Prepared by: Kyle Westendorf, Department of Market
More informationAlberta Utilities Commission
Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Request for Modifications to SCE s Renewable Auction Mechanism ( RAM ) Program Pursuant to Decision 10-12-048 Rulemaking 11-05-005 (Filed
More informationGeorge Moran, British Gas 28th August 2015
CMP 251: Removing the error margin in the cap on total TNUoS recovered by generation and introducing a new charging element to TNUoS to ensure compliance with European Commission Regulation 838/2010 George
More informationAlberta Electricity Markets
Alberta Electricity Markets Tyler Drever Nov 9, 2009 Alberta Electricity Market - History Prior to 2000: Alberta market centrally controlled by the provincial government and a handful of vertically-integrated
More informationIndependent Adviser s Report. In Respect of the Continuation of the Buyback Programme
Trustpower Limited Independent Adviser s Report In Respect of the Continuation of the Buyback Programme May 2014 Statement of Independence Simmons Corporate Finance Limited confirms that it: has no conflict
More informationEntry Capacity Substitution Methodology Statement
Issue Revision 7.0 Approved Entry Substitution Methodology Statement Effective from 1 st November 2015 Page 1 of 30 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT Document Revision History Version/
More informationNEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 9(2018)
NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public
More informationThe IASB s technical agenda
IFRS Foundation The IASB s technical agenda Martin Edelmann September 2016 The views expressed in this presentation are those of the presenter, not necessarily those of the International Accounting Standards
More informationSummary and analysis of Wellington Airport s third price setting event
ISBN no. 978-1-869454-49-4 Project no. 18.08/15078 Public version Summary and analysis of Wellington Airport s third price setting event Date: 30 June 2015 2 [BLANK PAGE] 3 Contents 1. INTRODUCTION...5
More informationThe Entry Capacity Substitution Methodology Statement
Issue 6.06.2 Revision ApprovedCons ultation Draft The Entry Substitution Methodology Statement Effective from 27 th February1 st November 2015 Page 1 of 32 The Entry Substitution Methodology Statement
More informationAchievable Potential Study FAQs for LDCs
Achievable Potential Study FAQs for LDCs November 25, 2016 1. What is the Achievable Potential Study? The IESO is required, through direction from the Minister of Energy, to conduct an Achievable Potential
More informationThe Entry Capacity Substitution Methodology Statement
Issue 5.26.1 Revision Informal Consultation Draft The Entry Substitution Methodology Statement Effective from 2 nd February1 st September 2015 Page 1 of 31 ENTRY CAPACITY SUBSTITUTION METHODOLOGY STATEMENT
More information