Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results

Size: px
Start display at page:

Download "Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results"

Transcription

1 Wairakei Ring Investment Proposal Project Reference: CTNI_TRAN-DEV-01 Attachment A GIT Results December 2008

2 Document Revision Control Document Number/Version 001/Rev A Description Wairakei Ring Investment Proposal Attachment A, GIT Results Date

3 TABLE OF CONTENTS 1 Introduction Purpose Glossary/terminology Document structure Compliance with the Grid Investment Test Moving from refined options to Short-list Conductor selection for the reconductoring options Outcomes from the Scenarios Basis of the scenarios Impact of regional constraints on the scenario outputs Impact on generation technology mix Operational Costs Conclusion on reasonableness of generation expansion plans Expected Net Market Benefit results Overall GIT results GIT results by market development scenario GIT Sensitivities Demand growth Uncertainty in the results Results using SDDP operational costs Timing of upgrades Longevity of short-list options Conclusion of the Grid Investment Test analysis Conclusions on timing...29 Appendix A Glossary

4 1 Introduction 1.1 Purpose The purpose of this document is to present and explain the results from Transpower s application of the grid investment test (GIT), undertaken as a part of the Wairakei Ring Investment Proposal (the Proposal). Note that unless otherwise specified all currency numbers presented in this report are pretax and discounted to $2008 at 7%. 1.2 Glossary/terminology A glossary of terms and acronyms used in this GIT Results paper is included in Appendix A. All references to rules in this document refer to those in Section III of Part F of the Electricity Governance Rules 2003 unless otherwise specified. 1.3 Document structure This document forms part of the Proposal. The documentation is structured according to the following diagram: Investment Proposal Attachment A GIT Results Attachment B Assumptions and Approach Attachment C Power System Analysis Attachment D Costing Report Attachment E Final Long-list and Criteria Attachment F Models and Data (in separate files) Attachment G Submissions This document is set out in four sections: The process moving from the combination options to the short-list; Outcomes from the scenarios; The results; and The sensitivities The approach and assumptions are set out in detail within Attachment B, and engineering analysis that lead to the options is described in Attachment C. 4

5 1.4 Compliance with the Grid Investment Test Under Rule 14.4, the Electricity Commission may approve proposed investments where Transpower has applied the GIT reasonably. As set out in Section 7.1 of the Proposal, investment in the Wairakei Ring is considered an economic investment. Therefore, to satisfy the GIT the Proposal must: maximise the expected net market benefit compared with a number of alternative projects, in a robust manner having regard to sensitivity analysis; and result in an expected net market benefit greater than zero, in a robust manner having regard to sensitivity analysis. Transpower considers that the results set out in this document demonstrate that Transpower has applied the GIT reasonably and that Option 4 (the new double circuit B line) satisfies the GIT criteria. 2 Moving from refined options to Short-list Attachment C, the power system analysis report, sets out the process by which the detailed short listed options were developed. This consisted of three stages: 1. The selection of eight upgrades (4 for each circuit); 2. Consideration of reasonable combinations of these upgrades; 3. Using the combinations, a staged short-list of options was developed. This section describes the process that lead from a list of reasonable combinations (step 2) to the staged short-list options. This was carried out utilising an initial cost benefit analysis of the upgrade combinations. The set of combination upgrades are repeated in Table 2-1 below. Table 2-1 Combination upgrades Combination A line Description B line Description 1 Reconductor Leave as is 160 MW 2 Reconductor Reconductor 660 MW Incremental improvement in injection capacity* 3 Leave as is Replace with a new double circuit line 4 Reconductor Replace with a new double circuit line 820 MW 1400 MW 5 Leave as is. Build a new single circuit line from ATI to WRK 6 Reconductor ATI-WKM, leave remainder as is. Build a new single circuit line from ATI to WRK (direct) 7 Replace with a new double circuit line 8 Leave ATI-WKM as is. Replace remainder with new double circuit line Replace with a new double circuit line Replace with a new double circuit line Replace with a new double circuit line Replace with a new double circuit line 970 MW 1650 MW 2080 MW 900 MW 9 Leave as is Reconductor - 5 MW 10 Replace with a new double circuit line Leave as is 910 MW 5

6 Combination A line Description B line Description Incremental improvement in injection capacity* 11 Leave as is Leave as is. Build a new single circuit line form WRK to WKM (via PPT) 540 MW 12 Leave as is Build a new single circuit line Leave as is 640 MW Each of these combinations was assessed against the 5 market development scenarios, the results of which are summarised in Table 2-2 below. The timing for all stage 1 investments was The timing was an initial estimation based on when constraints were first observed in the Base Case runs. Table 2-2: Results from analysing the combination upgrades Combination Benefit ($M) Transmission Capital Cost ($M) Net Market Benefit ($M) 1 (Recon A) 2 (Recon A/ Recon B) 3 (New DBL B) 4 (Recon A / New DBL B) 5 (Add SGL A (ATI) / New DBL B) 6 (Add SGL A (ATI)+ recon / New DBL B) 7 (New DBL A/ New DBL B) 8 (New DBL A (ATI) / New DBL B) 9 (Recon B) 10 (New DBL A) 11 (New SGL B) 12 (New SGL A) These results where used to derive an initial short-list. Specifically, the results showed that: Reconductoring the B line (combination 9) as a first stage had a negative impact on the benefits. This also confirmed the power system analysis which showed the capacity increase of the upgrade as being -5MW. Therefore it was not considered any further as a first stage investment. The options that had a combination of new circuits on both sides of the Wairakei Ring showed benefits that were equivalent to the unconstrained network over the 6

7 entire period. Therefore, this demonstrated that there would be significant benefit from staging new build options (due to the benefit of delaying capital expenditure) and that the larger capacity options were going to provide unnecessary over capacity. Therefore combinations 6 and 7 were not considered any further. Some options clearly provided less benefit for greater or similar costs as other options. Based on this, combinations 5 and 8 were not considered further. It was clear from this that the short-list of options needed to be staged. The analysis showed that the logical first stage of each short-list option was likely to be either: Reconductor the A line (combination 1); or Build a new double circuit B line (combination 3); or Build a new single circuit B line (combination 11). As the net benefit of combination 10 was low, it did not appear that a new build on the A line was going to be economic. However, there was a higher degree of uncertainty in these initial results. Accordingly, both the double and single circuit build options on the A line builds were also included as potential first stage investment options. The second stage investments were then considered. The analysis results showed that, in particular, the reconductoring of the A line would need to be closely followed by a second stage investment. The options for the second stage investment were: reconductoring the B line (combination 2), build a new double circuit B line (combination 4); or a new single circuit B line (this was added later for completeness). Second stage investments for the new build options were also considered and the timing tested. For example the double circuit B line was tested with a second stage reconductoring of the A line. However, it was found that for all new build options a second stage, while possibly necessary at some time in the future, was uneconomic over the study period given the current set of inputs. Therefore, second stage investments have not been included as modelled projects for the new build options. Table 2-3 below summarises the outcomes of the initial analysis. Table 2-3 Outcomes of initial analysis Combination Benefit* ($M) Transmission Capital Cost ($M) Net Market Benefit ($M) Initial Assessment 1 (Recon A) Stage 1 2 (Recon A/ Recon B) Indicative of a Stage 2 state 1 3 (New DBL B) Stage 1 4 (Recon A / New DBL B) Indicative of a Stage 2 state 1 That is, the combination represents that state of the Ring once a second stage investment has been made. 7

8 Combination Benefit* ($M) Transmission Capital Cost ($M) Net Market Benefit ($M) Initial Assessment 5 (Add SGL A (ATI) / New DBL B) 6 (Add SGL A (ATI)+ recon / New DBL B) 7 (New DBL A/ New DBL B) 8 (New DBL A (ATI) / New DBL B) 9 (Recon B) 10 (New DBL A) 11 (New SGL B) 12 (New SGL A) Filtered out Filtered out Filtered out Filtered out Filtered out Stage Stage Stage 1 * This was an initial analysis only and as such the results differ from those in the final model runs. As a result of this process the short-list was developed. Table 2-4 sets out the final short list used in the analysis. Table 2-4 Final Short-list options Short List Option Stage 1 Upgrade Stage 2 Upgrade Base Case Do nothing none Option 1 Reconductor A Line Reconductor B Line Option 2 Reconductor A Line New Single Circuit B Line Option 3 Reconductor A Line New Double Circuit B Line Option 4 New Double Circuit B Line none Option 5 New Single Circuit B Line none Option 6 New Double Circuit A Line none Option 7 New Single Circuit A Line None Notes: New double circuits include removal of the relevant existing line. New single circuit options are additional to the existing lines. The actual alignment of any new build option is subject to more detailed investigation, the assumed alignments are notional and are used for the purpose of costing only. 8

9 These options have been assessed against the scenarios used in the analysis. 2.1 Conductor selection for the reconductoring options The conductors used for the reconductoring options are: High temperature (ACSS) Pheasant for the A line. Pheasant is cheaper that the alternative duplex Goat. Pheasant also has a higher summer rating than duplex Goat. While the winter rating for Pheasant is lower than for duplex Goat, the analysis showed that the summer transmission ratings bind first and therefore as Pheasant was selected as the preferred conductor for the A line reconductoring. Duplex Zebra for the B line. Duplex Zebra was both cheaper and provided higher capacity than the alternative Falcon. Therefore it was selected as the preferred conductor for the analysis. Attachment D has a description of the transmission costing process. 3 Outcomes from the Scenarios The purpose of this section is to demonstrate that the scenarios are reasonable and to illustrate the impact of the transmission options studied. The full details of the inputs, models and scenario outputs are available in Attachment F. 3.1 Basis of the scenarios Transpower is required under the rules to use the market development scenarios specified in the Commission s SoO, unless the Commission determines that alternative scenarios are more appropriate. As set out in the GUP and Attachment B, Transpower has made a number of changes to the input data for these scenarios. A number of required changes have also been made to the GEM model so as to enable modelling of regional transmission augmentations. Transpower considers that these changes are reasonable to make in the context of the Wairakei Ring, and seeks a determination by the Commission that the alternative scenarios are more appropriate than the scenarios specified in the SoO. Three examples from the analysis have been used to illustrate the impact of the changes: 1. the impact of regional constraints on the scenario outputs; 2. the impact on the generation technology mix; and 3. the use of SDDP to verify the operational costs. This is an alternative method for testing the fuel costs from the GEM output. Each of these is discussed in the following sections. 3.2 Impact of regional constraints on the scenario outputs The most significant change from the SoO scenarios published by the Commission is the implementation of a constrained regional transmission network. The impact of the constrained network can be seen by considering the relative regional generation build between the base case (with constraints that reflect current transmission capacities and a fully unconstrained network) and a completely unconstrained network. This is shown in the following graph for MDS 1: 9

10 Figure 3-1: Relative Generation Build for MDS 1 Installed MW - Base verses Unconstrained for mds 1, by region Installed MW Base SI Uncon SI Base UNI Uncon UNI Base LNI Uncon LNI Base WRK Uncon WRK Year The main features from this are: The investment in the Wairakei area is significantly lower in the base case than in the unconstrained case (shown by the lower arrow). This is mirrored by an increase in the required thermal generation in the upper North Island for the base case, compared with the unconstrained case. Investment in the South Island and the lower North Island is only slightly impacted by the Wairakei Ring. The pattern of generation investment shown in the above graph is consistent with a constrained Wairakei Ring, and therefore Transpower considers that these results demonstrate the scenarios used in the analysis are reasonable. 3.3 Impact on generation technology mix A feature of the SoO scenarios is the change in generation mix between scenarios (ranging from more renewables in scenario 1 through to the more thermally based scenario 5). As the scenarios used for this GIT analysis are largely based on the SoO scenarios, this same theme should be evident in the scenarios developed for this GIT analysis. The only significant deviation results from the use of a constrained network and the updates Transpower has made in the early years of each scenario. The graphs below demonstrate that the general trends for generation technology mix developed within each SoO scenario have been carried through the Wairakei Ring analysis. 10

11 Figure 3-2: Base case installed MW by MDS The graphs clearly show the greater amounts of wind and smaller amounts of gas and coal in MDS 1 compared with MDS 5. This is further illustrated in the following graphs showing the GWhs generation by fuel type. 11

12 Figure 3-3: Base case GWh Generation by MDS Transpower considers that the trends illustrated by these graphs indicate that the use of the proposed alternative scenarios is reasonable for this analysis. 3.4 Operational Costs In order to verify the operational costs derived by the GEM model, which does not consider a full range of hydrology, Transpower conducted analysis using SDDP. To do this, the generation build sequence for each scenario was taken from GEM and simulated over 74 hydro sequences in SDDP. The following graph illustrates the absolute differences between the average operational costs from SDDP and the operational costs derived from GEM for the base case (the most constrained) for scenario 1. 12

13 Figure 3-4: Operating Cost Comparison GEM - SDDP Operating Cost Comparison - GEM Verses SDDP 2,000,000 1,800,000 1,600,000 1,400,000 Operating Cost ($k) 1,200,000 1,000, , , ,000 SDDP Operating Cost GEM Operating Cost 200, Year Note: the numbers shown in the graph have discounting and tax effects removed in order to illustrate the absolute differences. The graph illustrates that the operational costs from GEM, which are based on average hydrology only (input parameter), aligns relatively closely with the average operational costs output from SDDP for the 74 hydro sequences. While GEM overstates the operational costs this is not considered significant as: the same pattern of operational costs can be observed between the two models with the correlation between the two series being approximately 0.97; and testing has shown the differences between operational costs between transmission options is relatively consistent. Testing of the input data showed that the primary driver for the differences was the level of minimum utilisation assumed for existing generation plant by the Commission in the SoO scenarios. The results are relatively sensitive to these factors and some relaxation of these constraints yielded results that almost exactly aligned the results from SDDP and GEM. However, for the purposes of this analysis, Transpower has adopted the settings used by the Commission in the SoO scenarios. However, what the differences do illustrate is that there is significant uncertainty in both the assumptions and the results of the analysis. This uncertainty is driven, not only by the inherent uncertainty in the inputs, but also by the large difference in magnitudes between the option costs and the benefits being modelled. This is discussed further in Section 5 of this report along with the results using of the analysis from SDDP. 3.5 Conclusion on reasonableness of generation expansion plans Given that: the general trends shown by the scenario analysis are as expected; the impact of a constrained network on the build patterns is also expected; and the changes Transpower has made to the scenario input data are only minor, 13

14 Transpower concludes that GEM is producing reasonable generation expansion plans and that these generation expansion plans are suitable for assessing the economics of upgrading the Wairakei Ring. Full details of all the input assumptions and outputs are available in Attachment F. 4 Expected Net Market Benefit results This section sets out the results for the transmission options studied. It covers the: overall GIT results; sensitivities; and uncertainty in the results. The options have been analysed over a range of three demand growth assumptions, five market development scenarios and a range of other sensitivities. In terms of presentation in the remainder of this document, please note that: net market benefits highlighted in green indicate a result that satisfies the GIT; and net market benefits highlighted in orange indicate the highest net market benefit of the options, but that the result does not satisfy the GIT. The results reported in this document are the expected net market benefits only. Unless otherwise stated all results are those taken from the GEM modelling only. Results using SDDP to calculate operational costs are set out in section 5.1 below. 4.1 Overall GIT results The weight averaged expected net market benefit for each short list option is: Table 4-1: Overall results of application of the Grid Investment Test Item Generation fixed benefits (A) Generation variable benefits (B) Transmission costs (C) Terminal benefit (D) Expected Net Market Benefit (A+B-C+D) Base Case Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, discounted at 7%, in $m, and in $2008. These results show that Option 4, a new double circuit B line has the highest expected net market benefit of the short-list options, being some $16 million in 2008 present value terms 14

15 higher than the next highest alternative project, Option 5 (a new additional single circuit B line). The expected net market benefit of Option 4 is $493 million (forecast to arise over 20 years from commissioning of the new double circuit B line) and, being greater than zero, Transpower concludes that Option 4, therefore, meets the requirements of clauses and of the GIT. Transpower has considered the sensitivity of this result to changes in key variables and parameters to assess the robustness of this result (in accordance with clause of the GIT). 4.2 GIT results by market development scenario Table 4-2 shows the GIT results by market development scenario, weight averaged over the demand growth scenarios. Table 4-2: Results of application of the Grid Investment Test by generation scenario Net Market Benefit MDS1 MDS2 MDS3 MDS4 MDS5 Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, discounted at 7% and in $2008. The final GIT result is derived by applying equal weightings to the scenarios as defined in the 2008 SoO and detailed in Attachment B. The results show a decreasing value of an upgrade for the scenarios in which more thermal generation is built (although still positive), and the differences between options also decreases. This is shown in Table 4-3 below which illustrates the difference between each option and the option with the highest benefit in each scenario. Table 4-3 Relative difference in net benefits between options Net Market Benefit MDS1 MDS2 MDS3 MDS4 MDS5 Option Option Option Option

16 Net Market Benefit MDS1 MDS2 MDS3 MDS4 MDS5 Option Option Option Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% and in $2008. These results indicate that: scenario 1 drives the largest portion of the overall benefits; Option 4 has the highest expected net market benefit in the renewables scenario (mds1) and scenarios 3 and 4; Option 5 has the highest net benefit in scenario 2 and 5. However, of note, the difference between Option 4 and 5 is small in scenarios 2 and 5; Option 4 and Option 5, both new build options, come out ahead of the other options; and the larger capacity options, Options 3, 4 and 6, have a definite advantage under the renewables scenario. 4.3 GIT Sensitivities Transpower has carried out the following sensitivities to consider the robustness of the GIT result as part of its proposed GIT application: demand, high and low as in the 2008 SoO; discount rates, 4% and 10%; transmission capital costs, low - 80% and high - 120%; exchange rates, 10 year rolling average; carbon costs, low - 80%, high 120%; and property costs, 200%. The results from each are described in the following sections. 4.4 Demand growth To test this sensitivity, both high and low demand is used to calculate the benefits in GEM. Table 4-4 shows the GIT results by demand growth scenario, weight averaged over the market development scenarios: Table 4-4: Results of application of the Grid Investment Test by demand scenario Net Market Benefit Low Demand Medium Demand High Demand Option Option Option

17 Net Market Benefit Low Demand Medium Demand High Demand Option Option Option Option Notes: Costs and benefits are all pre-tax, discounted at 7% and in $2008. These results indicate that each short list option has a greater expected net market benefit as demand growth increases. This is reasonable, because as demand growth increases, the requirement for new generation north of the Wairakei ring would increase and the potential savings from increased capacity around the Wairakei ring would also increase. Option 4 is the most economic for all three demand growth options. Additionally, as demand grows, the larger capacity of Option 4 creates greater benefits relative to the next best alternative, Option 5, and the reconductoring option, Option Discount Rate 4%, 7% and 10% To test this sensitivity, the discount rates used to calculate the present values is 4%, 7% (the base GIT results) and 10%. Table 4-5: Results of application of the Grid Investment Test - 4% discount rate sensitivity Net Market Benefit 4% 7% (base results) 10% Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, in $m and in $2008. The significant conclusion to note is the double circuit B line (Option 4) comes out ahead for all the cases Capital Costs To test this sensitivity, the capital cost of the transmission equipment is varied between 80% and 120% of the expected cost used by Transpower in the GIT analysis. 17

18 Table 4-6: Results of application of the Grid Investment Test Transmission capital costs sensitivity Expected Net Market Benefit Low (80%) Base (100%) High (120%) Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% and in $2008. Significant conclusions to note are: Option 4 consistently comes out ahead of the other options. The separation in expected net market benefits between Option 4 and the option with the next highest benefit increases as the capital cost decreases Exchange rate variations To test this sensitivity, the exchange rates used to calculate the capital cost of the transmission equipment are varied from being an average calculated around +/- 20 business days of 1 September 2008 to an average calculated around the last ten years exchange rates. Table 4-7: Results of application of the Grid Investment Test - exchange rate sensitivity Expected Net Market Benefit Base (+/- 20 business days around 1 September) 10 yr average Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% and in $2008. Significant conclusions to note are: 18

19 The expected net market benefit is not particularly sensitive to the exchange rate basis used. The ranking of the short-list options does not change. Both results show Option 4 has the highest expected net market benefit Property Costs An additional sensitivity has been carried out on the property cost component of the options. This is done so as to verify the impact that property has on the ranking between the reconductoring option and the new build options. To test this sensitivity, the property cost for all the options has been doubled. Table 4-8: Results of application of the Grid Investment Test - Property cost sensitivity Expected Net Market Benefit Base 200% property cost Option Option Option Option Option Option Option Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% and in $2008. Significant conclusions to note are: While the total expected net market benefit is sensitive to property costs, the ranking of the options does not change. Both results show Option 4 has the highest expected net market benefit Carbon Costs A sensitivity has been run using a +/- 20% variation on carbon costs. The results are shown below in Table 4-9. Table 4-9 Carbon cost sensitivity Expected Net Market Benefit Low (80%) Base (100%) High (120%) Option Option Option Option Option

20 Expected Net Market Benefit Low (80%) Base (100%) High (120%) Option Option Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% and in $2008. The significant conclusions to note are: The higher carbon costs create a greater benefit for upgrading the transmission around the Wairakei Ring. This is reasonable as the cost of thermal generation becomes more expensive. Therefore the benefit gained from renewables will be greater i.e. they become relatively cheaper. Additionally, as a consequence of renewable generation being more likely to be located either within or south of the Wairakei Ring, the greater the benefit gained from an upgrade. All results show Option 4 has the highest expected net market benefit Summary table of sensitivity results Table 4-10 summarises the overall results and the sensitivities. Table 4-10: Sensitivity of expected net market benefit of the short-list options Expected Net Market Benefit Option 1 Option 2 Option 3 Option 4 Option 5 Option 6 Option 7 Base results Sensitivity: Discount rate, 4% Discount rate, 10% Capital 80% Capital 120% yr avg exchange rate High demand Low Demand Property Costs (200%) Low Carbon Cost (80%) High Carbon Cost (120%) Notes: Costs and benefits are all pre-tax, in $m, discounted at 7% (unless otherwise stated) and in $

21 This summary shows that the ranking of the short-list options is stable to a range of sensitivities. All sensitivities show Option 4, the new double circuit B line, having the highest positive expected net market benefit. Table 4-11 below shows the differences in expected net market benefit between each option and the option with the highest expected net market benefit. Table 4-11 Differences in net benefits Expected Net Market Benefit Option 1 Option 2 Option 3 Option 4 Option 5 Option 6 Option 7 Base results Sensitivity: Discount rate, 4% Discount rate, 10% Capital 80% Capital 120% yr avg exchange rate High demand Low Demand Property Costs (200%) Low Carbon Cost (80%) High Carbon Cost (120%) Average Difference (un weighted) The results show that the differences between Option 5, the new single circuit and Option 4, the new double circuit are close but consistently favour the new double circuit. The results for Option 4 are also shown diagrammatically below, in order to demonstrate what the expected net market benefit is most sensitive to. 21

22 Figure 4-1: Sensitivity ranges of expected net market benefit 5 Uncertainty in the results The results set out in this document have uncertainty associated with them. The uncertainty arises from three sources: 1. uncertainty inherent in the input assumptions. The modelling assumes certain generation costs which may or may not be accurate; 2. uncertainty in the problem formulation. The fact that the analysis is assessing the differences in generation investment and operation costs over 35 years (with an NPV of $20+ billion) can lead to a high degree of uncertainty in the results. To some extent this is mitigated by considering the results over five scenarios. However, aspects such as competitive response and unexpected and structural changes (such as a big gas discovery or large step change in demand) could contribute to the scenarios modelled not being representative of the actual future; 3. the large difference in magnitude of the benefits of each option and the relatively small difference between the cost of each transmission option. An indication of this can be seen in 4. Figure 4-1 above where the value changes due to the scenario swamps the value change due to a change in capital cost. Therefore small changes in the assumptions are highly likely to change the results of this analysis. However, as noted in the GUP and these attachments, Transpower has taken steps to mitigate these impacts as much as possible by: integrating commercial behaviour into the earlier years of the scenarios by fixing the build dates for a representative sample of generation investments that are already committed to by investors; 22

23 testing the transmission options over a range of sensitivities; and verifying the operational costs using SDDP (set out below). This provides verification using a different method of calculation and accounts for hydrological uncertainty. Therefore, Transpower considers that, given the level of information currently available, the application of the GIT to the transmission options is reasonable and that any changes to the assumptions and modelling parameters is likely to lead to changes in the option benefits that are common across all the options. As set out in the GUP, Transpower has also considered a number of un-quantified benefits of the options and concludes that in the long term Option 4, is the most appropriate first stage option for the Wairakei Ring. 5.1 Results using SDDP operational costs The following table sets out the overall GIT results using the operational costs derived using SDDP. SDDP tends to show higher constraint costs when the more detailed and accurate dispatch of the system is accounted for. The results are significantly higher as a result. Table 5-1 Overall GIT results using SDDP Item Generation fixed benefits (From GEM) (A) Generation variable benefits (B) Transmission costs (C) Terminal benefit (D) Expected Net Market Benefit (A+B-C+D) Option Option Option Option Option Option Option Notes: Benefits are all pre-tax, discounted at 7%, in $m, and in $2008. The results using SDDP show that: Option 4 still has the highest net benefit; operational benefits are significantly higher when hydrology is specifically accounted for and more detailed dispatch of the system. This is due to the network being generally more constrained; there is some change in the ranking of the options, with the larger capacity options benefiting; and the greater level of constraint means that a second stage investment is likely to be economically warranted at some in the future, although this has not been tested. 23

24 6 Timing of upgrades Sensitivity analysis on the timing of all the options was carried out using GEM. This showed that the optional economic timing for the options is either 2015 or The optimal economic timing depends on the benefit derived from delay in capital expenditure relative to the increase in constraint costs as a result of incurring that delay. The optimal economic timing for Option 4 is This equates to a commissioning date sometime during 2014, in order for the proposal to be in place for The timing analysis is illustrated, using Option 4 as an example, in Figure 6-1 below. Figure 6-1 GEM Optimal Economic Timing 8 7 GEM Optimal Economic Timing, Option 4 Optimal economic timing Incremental costs/benefits ($m) Total Net Benefit ($m) Incremental Capital Cost Savings Change in Generation Costs Expected Net Market Benefit 400 The graph shows that the net economic benefit (based on GEM runs) is maximised in 2015 i.e. the date in which the incremental savings from delaying transmission investment is equal to the cost increase in generation costs. However, there are several important factors that point to a preference for an earlier commissioning date: 1. The difference between the net benefit for 2015 and 2014 is relatively small. For example, for Option 4 it is $3.6 million. Therefore, given the uncertainty and the potential impact of providing insufficient transmission capacity, Transpower considers it is prudent to bring forward the date in which the transmission is required. 2. The risk associated with delayed commissioning is asymmetric. The market cost of constraints increases exponentially compared with the cost (in NPV terms) of bringing forward an investment by a year or so. There are a number of factors that may result in the delay to commissioning, including the RMA process and construction delays. 3. The cost of spill and hydro variability has not been factored into the timing analysis undertaken using GEM. SDDP analysis shows that in wet years, constraint costs tend to rise between 1 and 2 years earlier than shown in the average results produced by GEM. The impact of hydro variations on the marginal constraint cost is shown in Figure 6-2 below. 24

25 Figure 6-2: Marginal Constraint Cost, Base case, Scenario 1 Marginal Constraint Cost, Base Case, scenario 1 1,600 1,400 1,200 Optimal economic timing, ,000 k$/mw Average 5th Percentile 95th Percentile 400 Hydrology Impact Year The graph shows that the variation in constraint costs due to hydrology is between 1 and 2 years. In particular wetter hydro sequences will tend to introduce constraints through the Wairakei Ring from about 2013 onwards. As a result, SDDP tends to suggest an earlier optimal economic timing than GEM. Table 6-1 shows the difference in present value of the generation dispatch benefit as modelled by SDDP for Option 4 relative to The results show an $8m increase in benefits from improved generation dispatch from moving the timing of the transmission investment forward to 2014, which implies a 2013 commissioning date. It also illustrates the exponential risk of delayed commissioning with a loss of $34m moving from 2015 to Table 6-1 Generation Dispatch Benefit, as modelled by SDDP, Option 4, $m Year of Investment Scenario 1 Scenario 2 Scenario 3 Scenario 4 Scenario 5 Average Notes: Benefits are all pre-tax, discounted at 7%, in $m, and in $ In the base modelling, GEM allows many of the new generation stations to be built in stages. 2 In reality it is likely that many of these generators will be built in much larger steps within a much shorter length of time (that is, new generation plant tends to be more lumpy ). This is particularly true for some plant types e.g. geothermal. Therefore it is likely that constraints around the Wairakei ring would bind earlier than suggested by 2 Due to the complexity of the constraint equations being solved within GEM a relaxed mixed integer method is used to derive the generation expansion paths. As a result, GEM allows many of the new generators to be built in stages over a number of years to match demand growth. 25

26 Transpower s GEM analysis, and consequently, would lead to an earlier optimal timing. The impact of this has been tested using SDDP. The following graph illustrates the constraint values increase significantly between 2013 and Figure Constraint cost for block build Constraint Marginal Costs for Original Generation Build Plan and Blocked Build Plan MDS1 Option ATIOHKPPIWK1 Original ATIOHKPPIWK1 BlockBuild Marginal Cost (k$/mw) The constraint values in Figure 6-3 drop to zero following the construction of the new double circuit in Contact Energy has indicated that it is likely to be seeking resource consents for the Tauhara geothermal power station, near Wairakei, in the near future with a view to commissioning the plant in While this has not been treated as a fixed build in the scenarios, as it is not yet in the consenting process, given its potential impact on the Wairakei Ring, a sensitivity has been conducted on the impact it may have on the timing. At present Tauhara is progressively built by GEM from If Tauhara was to be built earlier in 2013 it would add to the constraints around the Wairakei Ring and bring the need date for investment forward. Figure 6-4 illustrates this impact. The analysis was carried out using the block build data described in 4 above. 26

27 Figure Impact of Tauhara on constraint values 900 Constraint Marginal Cost for ATI-OHK, PPI-WKM-1 Constraint 800 Tauhara built in stages from 2014 Tauhara built in Constraint Marginal Cost (k$/mw) This shows that Tauhara has as a cumulative impact on the constraint, increasing the constraint cost in 2013 and therefore bringing the need date for the investment further forward. This would suggest that 2012 is an appropriate commissioning date. However, there are potential practical difficulties with construction of a new line within that timeframe. 6. Earlier investment is also likely to lead to an increase in un-quantified benefits, such as competition and ancillary service benefits. 7. There was substantial support of an even earlier 2012 commissioning date from submitters. For these reasons, Transpower considers that: the optimal timing investments based on the GEM economic criteria only significantly underestimates the costs and risks associated with construction delays; and taking into account the GEM optimal economic timing (and its potential shortcomings), the SDDP results and timing analysis, un-quantified benefits, and construction timeframe, there is a strong case for bring forward the commissioning date on the basis that this will result in earlier realisation of market benefits and avoidance of asymmetric risks, with only a relatively small increase in the overall cost of the Proposal (in NPV terms). Therefore Transpower considers that a target commissioning date of early to mid 2013 is appropriate. 6.1 Longevity of short-list options While not part of the requirements for the GIT analysis as set out in the rules, Transpower considers that the frequency that which an area of the grid needs to be addressed is an important consideration that should be included in the assessment of the benefits of an option. This is because there is often significant impact on local communities that arise and the cumulative social and economic costs that cannot be quantified. Repeated visits to the same sections of the grid is also indicative of continuing fine operating margins which are likely to result in additional costs (such as a reduction in competition benefits and market costs incurred through the requirement for ongoing outage windows) that also cannot be quantified. 27

28 As such, Transpower has attempted to illustrate the differences in the longevity of the options in Figure 6-5 below. Figure 6-5 Longevity of Short-list options This clearly shows that the options with the highest capacity such as option 4, the double circuit B line and option 6 the double circuit A line requires the least disruption to both communities and the electricity market. Note that the timings for the red bars are indicative only as optimisation of the follow on stages was not explicitly carried out in the analysis. However, they have been approximated based on constraint cost information derived from the scenarios. 28

29 7 Conclusion of the Grid Investment Test analysis Transpower concludes that Option 4, a new double circuit 220 kv line along the alignment of the existing B line, satisfies the GIT because: it maximises the expected net market benefit when compared with the alternative projects; it has a positive net market benefit; and it is robust having regard to the results of a sensitivity analysis. It is noted that whilst the expected net market benefit of Option 4 is $493 million, this is averaged over five market development scenarios and uses a 7% discount rate. These results are robust to the wide range of sensitivity analysis carried out by Transpower. 7.1 Conclusions on timing After consideration of both the numerical results and the un-quantified benefits accruing from the Proposal, Transpower considers that the appropriate planned commissioning date for the preferred option, a new double circuit B line, is early to mid

30 Appendix A Glossary Term Alternative Project Base Case Description Projects that are reasonable to consider as alternatives to the proposed investment in applying the Grid Investment Test (GIT), in accordance with rule 19, Schedule F4, Part F Section III, Electricity Governance Rules (EGRs). The do nothing option, a counterfactual for other options to be considered against. CCGT Combined Cycle Gas Turbine Consultation Paper Document published by Transpower on 28 October economic investment Investments in the grid that can be justified on the basis of the Grid Investment Test under section III of part F, Electricity Governance Rules (EGRs), and are not reliability investments. EGRs Electricity Governance Rules. In the context of this document, it generally refers to Part F Transport, Section III Grid Upgrade and Investments, 28 June expected project costs GEM Expected project costs (or expected costs) represent the estimated (P50) cost plus a contingency for scope accuracy. Scope accuracy allows for unexpected variations in the design scope and a standard allowance, based on experience, for items not considered in the design. Generation Expansion Model, a model for generation expansion modelling originally developed by the Electricity Commission. GIT Grid Planning Assumptions HVDC Grid Investment Test. A test for reliability investments and economic investments in the grid developed in accordance with rule 6 of section III of Part F, Electricity Governance Rules (EGRs). The specific rules defining the Grid Investment test, as developed according to the process in rule 6 of section III, are set out in Schedule F4 of section III of Part F. Principles for these are contained in Rule 10 Electricity Governance Rules. The Rule provides that assumptions should cover a reasonable range pf credible forecasts and scenarios; should have a length of outlook commensurate with consideration of future investment in long-life transmission assets; and should be as accurate as possible. High Voltage Direct Current rights reserved 30

31 LNG modelled projects New Zealand Energy Strategy Liquified Natural Gas Transmission augmentation projects and non-transmission projects, other than the proposed investment and alternative projects, which are likely to occur in a market scenario, are reasonably expected to occur in that market development scenario within the time horizon for assessment of the market benefits and costs of the proposed investment and alternative projects, and the likelihood, nature and timing of which will be affected by whether the proposed investment or any alternative project proceeds. The New Zealand Energy Strategy to 2050 sets out the government's vision for a reliable and resilient system to deliver a sustainable, low emissions energy services. PLEXOS A proprietary power market model suitable for short, medium and longer term studies including generation expansion planning. It can furthermore model market behaviour to assess competition benefits. Rules The Electricity Governance Rules SDDP SRMC Stochastic Dual Dynamic Programming, a hydro-thermal dispatch model with representation of the transmission network used for short, medium and long term operation studies. Short Run Marginal Cost SOO Statement of Opportunities, published by the Electricity Commission Transpower Transpower New Zealand Limited, owner and operator of New Zealand s high-voltage electricity network (the national grid). rights reserved 31

Potential Upgrade of Queensland/New South Wales Interconnector (QNI) Assessment of Optimal Timing and Net Market Benefits

Potential Upgrade of Queensland/New South Wales Interconnector (QNI) Assessment of Optimal Timing and Net Market Benefits FINAL REPORT F 13 October 2008 Potential Upgrade of Queensland/New South Wales Interconnector (QNI) Assessment of Optimal Timing and Net Market Benefits Disclaimer While care was taken in preparation of

More information

Coordination and generation of of transmission investment

Coordination and generation of of transmission investment Coordination and generation of of transmission investment John John Gleadow Senior Senior Advisor Transmission Presented to to the the Transmission Advisory Group 19 19 April 2007 Purpose of this presentation

More information

STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018

STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018 STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018 INTRODUCTION SSE is working towards its vision of being a leading energy company in a low carbon world by focusing on core businesses of regulated

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

SOUTH AUSTRALIA VICTORIA (HEYWOOD) INTERCONNECTOR UPGRADE

SOUTH AUSTRALIA VICTORIA (HEYWOOD) INTERCONNECTOR UPGRADE 26 October 2012 Hugo Klingenberg Senior Manager Network Development Electranet Pty Ltd consultation@electranet.com.au Ashley Lloyd Senior Manager Victorian Planning Australian Energy Market Operator planning@aemo.com.au

More information

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1 Table of Contents Economic Uncertainty Analysis....0 Chapter Overview.... Probabilistic Analysis with Scenarios..... Methodology...... Determination of Highest Impact Factors...... Combinations of Highest

More information

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation Clearing Manager Financial Transmission Rights Prudential Security Assessment Methodology with September 2015 variation 18 September 2015 To apply from 9 October 2015 Author: Warwick Small Document owner:

More information

Resource Planning with Uncertainty for NorthWestern Energy

Resource Planning with Uncertainty for NorthWestern Energy Resource Planning with Uncertainty for NorthWestern Energy Selection of Optimal Resource Plan for 213 Resource Procurement Plan August 28, 213 Gary Dorris, Ph.D. Ascend Analytics, LLC gdorris@ascendanalytics.com

More information

HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology

HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology + HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology Decisions and reasons 14 August 2015 932889v7 Contents 1. Introduction 1 2. The Authority has decided to proceed

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

HVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs

HVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs HVDC Inter-Island Link Upgrade Project Investment Proposal Part V Project Costs Transpower New Zealand Limited 2005. All rights reserved 1 SUMMARY... 3 2 BACKGROUND... 4 3 APPROACH TO ESTIMATING COSTS...

More information

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL APPENDIX B: PORTFOLIO OPTIMIZATION MODEL PUBLIC UTILITY DISTRICT #1 OF SNOHOMISH COUNTY Prepared by Generation, Power, Rates, and Transmission Management Division Snohomish County PUD DRAFT 2017 Integrated

More information

Wanganui - Stratford Investment Proposal. Attachment B Costing report

Wanganui - Stratford Investment Proposal. Attachment B Costing report Wanganui - Stratford Investment Proposal Attachment B Costing report September 2009 Document Revision Control Document Number/Version Description Date 001/ A Wanganui-Stratford Investment Proposal Attachment

More information

SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014

SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014 SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014 1. INTRODUCTION This for Snowy Hydro Limited ( Snowy Hydro or the Company ) continues a focus on the continued development and augmentation of Snowy

More information

2016 INTEGRATED TRANSMISSION PLAN COMPLIANCE REPORT

2016 INTEGRATED TRANSMISSION PLAN COMPLIANCE REPORT 2016 INTEGRATED TRANSMISSION PLAN COMPLIANCE REPORT APPENDIX: ITP COMPLIANCE Introduction Our first integrated transmission plan (ITP), which we completed in 2013, was embedded within our regulatory proposal

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

SP Transmission successfully fast-tracked

SP Transmission successfully fast-tracked 2 RIIO-T1 Transmission Price Control January 2012 SP Transmission successfully fast-tracked SP Transmission is pleased to announce that it has reached agreement with the Government energy regulator Ofgem

More information

Attachment C: How capital expenditure is proposed and approved under the capex IM

Attachment C: How capital expenditure is proposed and approved under the capex IM ISBN no. 978-1-869455-84-2 Project no. 14.09/16274 Public version Attachment C: How capital expenditure is proposed and approved under the capex IM Transpower capex input methodology review - Proposed

More information

FINAL Framework and Approach for Powerlink

FINAL Framework and Approach for Powerlink FINAL Framework and Approach for Powerlink For the regulatory control period commencing 2017 June 2015 Powerlink 2017 22 Framework and approach 1 Powerlink 2017 22 Framework and approach 2 Powerlink 2017

More information

APPENDIX A - GLOSSARY

APPENDIX A - GLOSSARY APPENDIX A - GLOSSARY 1. Photovoltaic (PV) or Solar (interchangeable): These are devices that generate electricity directly from sunlight via an electronic process that occurs naturally in certain types

More information

PHASE I.A. STOCHASTIC STUDY TESTIMONY OF DR. SHUCHENG LIU ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

PHASE I.A. STOCHASTIC STUDY TESTIMONY OF DR. SHUCHENG LIU ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Rulemaking No.: 13-12-010 Exhibit No.: Witness: Dr. Shucheng Liu Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. Rulemaking 13-12-010

More information

Expenditure Forecast Methodology

Expenditure Forecast Methodology Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box

More information

December 9, City of Farmington Integrated Resource Planning (IRP)

December 9, City of Farmington Integrated Resource Planning (IRP) December 9, 2016 City of Farmington Integrated Resource Planning (IRP) Restricted Siemens AG 2013 All rights reserved. Answers for infrastructure and cities. Pace Global Disclaimer This Report was produced

More information

Electricity Industry Bill

Electricity Industry Bill Electricity Industry Bill Request for additional information by Finance and Expenditure Committee The additional information sought by the committee on 17 February 2010 is set out in the following tables.

More information

Results Presentation Six month period ended 31 December 2010

Results Presentation Six month period ended 31 December 2010 Results Presentation Six month period ended 31 December 2010 22 February 2011 Disclaimer This presentation may contain projections or forward looking statements regarding a variety of items. Such forward-looking

More information

Basel Committee on Banking Supervision

Basel Committee on Banking Supervision Basel Committee on Banking Supervision Basel III Monitoring Report December 2017 Results of the cumulative quantitative impact study Queries regarding this document should be addressed to the Secretariat

More information

Structural credit risk models and systemic capital

Structural credit risk models and systemic capital Structural credit risk models and systemic capital Somnath Chatterjee CCBS, Bank of England November 7, 2013 Structural credit risk model Structural credit risk models are based on the notion that both

More information

(Transpower) Reasons paper December 2010

(Transpower) Reasons paper December 2010 Individual price-quality path (Transpower) Reasons paper December 2010 Regulation Branch Commerce Commission Wellington NEW ZEALAND 22 December 2010 ISBN: 978-1-869450-95-3 Commerce Commission i Table

More information

Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs)

Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs) Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs) Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements

More information

Ventus 2 VCT plc. Strategy Note Executive Summary

Ventus 2 VCT plc. Strategy Note Executive Summary 1 Executive Summary This note summarises the outcome of a strategy review undertaken by the Board of Ventus 2 VCT plc (the Company ) over the past year during the period when the last of the Company s

More information

Transpower capex input methodology review

Transpower capex input methodology review ISBN no. 978-1-869456-35-1 Project no. 14.09/16274 Public version Transpower capex input methodology review Decisions and reasons Date of publication: 29 March 2018 2 Associated documents Publication date

More information

Manitoba Hydro 2015 General Rate Application

Manitoba Hydro 2015 General Rate Application Manitoba Hydro 2015 General Rate Application OVERVIEW & REASONS FOR THE APPLICATION Darren Rainkie Vice-President, Finance & Regulatory Manitoba Hydro Why Rate Increases are Needed 2 Manitoba Hydro is

More information

ASSET RISK MANAGEMENT Asset Health Framework

ASSET RISK MANAGEMENT Asset Health Framework ASSET RISK MANAGEMENT Asset Health Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to

More information

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101 BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION

More information

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101

BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 600 North Robert Street St. Paul, MN 55101 BEFORE THE MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS 00 North Robert Street St. Paul, MN 1 FOR THE MINNESOTA PUBLIC UTILITIES COMMISSION th Place East, Suite 0 St Paul MN 1-1 IN THE MATTER OF THE APPLICATION

More information

Otahuhu Sub-Station Conference. Graeme Everett 23 rd July 2007

Otahuhu Sub-Station Conference. Graeme Everett 23 rd July 2007 Otahuhu Sub-Station Conference Graeme Everett 23 rd July 2007 The World of Norske Skog Europe - 100% Skogn Follum Union Saubrugs Parenco Walsum Steti Golbey Bruck Chongwon Hebei Chonju Pan Asia - 100%

More information

PHASE I.A. DIRECT TESTIMONY OF DR. KARL MEEUSEN ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

PHASE I.A. DIRECT TESTIMONY OF DR. KARL MEEUSEN ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Rulemaking No.: --00 Exhibit No.: Witness: Dr. Karl Meeusen Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. Rulemaking --00 PHASE I.A.

More information

stated. This Ruling applies is the issue Manager. b) of Asteron A Life PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T

stated. This Ruling applies is the issue Manager. b) of Asteron A Life PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T Office O of the Chief Tax Counsel Te T Tari o te Rōia Tāke Matua Asteron A Life 555 Featherstonn Street PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T 044 890-1500 Facsimile F Numbers: Chief

More information

Project Assessment Conclusions Report

Project Assessment Conclusions Report Powerlink Queensland Project Assessment Conclusions Report 27 August 2018 Addressing the secondary systems condition Disclaimer While care was taken in preparation of the information in this document,

More information

Statement of Guidance for Licensees seeking approval to use an Internal Capital Model ( ICM ) to calculate the Prescribed Capital Requirement ( PCR )

Statement of Guidance for Licensees seeking approval to use an Internal Capital Model ( ICM ) to calculate the Prescribed Capital Requirement ( PCR ) MAY 2016 Statement of Guidance for Licensees seeking approval to use an Internal Capital Model ( ICM ) to calculate the Prescribed Capital Requirement ( PCR ) 1 Table of Contents 1 STATEMENT OF OBJECTIVES...

More information

Guidance consultation FSA REVIEWS OF CREDIT RISK MANAGEMENT BY CCPS. Financial Services Authority. July Dear Sirs

Guidance consultation FSA REVIEWS OF CREDIT RISK MANAGEMENT BY CCPS. Financial Services Authority. July Dear Sirs Financial Services Authority Guidance consultation FSA REVIEWS OF CREDIT RISK MANAGEMENT BY CCPS July 2011 Dear Sirs The financial crisis has led to a re-evaluation of supervisory approaches and standards,

More information

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Mason, Rangamuwa, Henning Page 1 of 15 MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Michael Mason 1, Siri Rangamuwa 1, Theunis F. P Henning 2 Corresponding Author: Michael

More information

BBC Pension Scheme. Actuarial valuation as at 1 April June willistowerswatson.com

BBC Pension Scheme. Actuarial valuation as at 1 April June willistowerswatson.com BBC Pension Scheme Actuarial valuation as at 1 April 2016 30 June 2017 willistowerswatson.com 1 Summary The main results of the Scheme s actuarial valuation are as follows: Technical provisions funding

More information

Comment on issues raised by Committee members on 21 April 2010

Comment on issues raised by Committee members on 21 April 2010 Electricity Industry Bill Comment on issues raised by Committee members on 21 April 2010 1. This note provides further comment on a number of issues raised by Committee members on Wednesday 21 April. 2.

More information

2.0 Reference: Application, Volume I, Chapter 2, Consolidated Revenue Requirements and Financial Schedules

2.0 Reference: Application, Volume I, Chapter 2, Consolidated Revenue Requirements and Financial Schedules 1 2.0 Reference: Application, Volume I, Chapter 2, Consolidated Revenue Requirements and Financial Schedules 2.2 2-3, Table 2-2: Please indicate for Columns C and D whether or not an average expected value

More information

Input methodologies review related party transactions

Input methodologies review related party transactions ISBN no. 978-1-869456-20-7 Project no. 14.20/16104 Public version Input methodologies review related party transactions Final decision and determinations guidance Date of publication: 21 December 2017

More information

Valuing Energy Security Quantifying the Benefits of Operational and Strategic Flexibility Tom Parkinson 4 October 2013

Valuing Energy Security Quantifying the Benefits of Operational and Strategic Flexibility Tom Parkinson 4 October 2013 Quantifying the Benefits of Operational and Strategic Flexibility Tom Parkinson 4 October 2013 We at The Lantau Group are experts in the economics of energy systems Seoul (TLG Korea) Asia Pacific Energy

More information

Viridian Group Investments Limited. Consolidated Financial Statements 31 March 2018

Viridian Group Investments Limited. Consolidated Financial Statements 31 March 2018 Viridian Group Investments Limited Consolidated Financial Statements 31 March 2018 CONTENTS Page Group Financial Highlights 3 Strategic and Director s Report - Operating Review 4 - Summary of Financial

More information

Conveying vs. Trucking Economics For Medium Sized Applications

Conveying vs. Trucking Economics For Medium Sized Applications Conveying vs. Trucking Economics For Medium Sized Applications Written by: R. Munson, BEUMER Kansas City LLC Introduction This paper shows how easy it is to perform fundamental economic evaluations of

More information

Flexible Ramping Product. Draft Final Technical Appendix

Flexible Ramping Product. Draft Final Technical Appendix Flexible Ramping Product Draft Final Technical Appendix January 25, 2016 Table of Contents 1. Introduction... 3 2. Generalized flexible ramping capacity model... 3 3. Flexible ramping product summary...

More information

Submitted by Western Power

Submitted by Western Power Final Determination on the New Facilities Investment Test for a 66/11 kv Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network Submitted by Western Power 19 February

More information

Branch Name Commerce Commission Wellington NEW ZEALAND 27 June 2011 ISBN:

Branch Name Commerce Commission Wellington NEW ZEALAND 27 June 2011 ISBN: Draft decision Minor Capital Expenditure and Operating Expenditure Allowances, and Quality Standards to apply to Transpower for the Remainder Period of Regulatory Control Period 1 Branch Name Commerce

More information

Quality of Wind BMU PNs pp11_47

Quality of Wind BMU PNs pp11_47 Quality of Wind BMU PNs pp11_47 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. by Erol Chartan

More information

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.

More information

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 17-M-0178 - Petition of Orange and Rockland Utilities, Inc. for

More information

7. OPERATING EXPENDITURE

7. OPERATING EXPENDITURE 7. OPERATING EXPENDITURE Box 7 1 Key messages operating expenditure JGN s opex program delivers critical activities to support the operation and maintenance of our assets, and the continued efficient administration

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

GN47: Stochastic Modelling of Economic Risks in Life Insurance

GN47: Stochastic Modelling of Economic Risks in Life Insurance GN47: Stochastic Modelling of Economic Risks in Life Insurance Classification Recommended Practice MEMBERS ARE REMINDED THAT THEY MUST ALWAYS COMPLY WITH THE PROFESSIONAL CONDUCT STANDARDS (PCS) AND THAT

More information

Lloyd s Minimum Standards MS13 Modelling, Design and Implementation

Lloyd s Minimum Standards MS13 Modelling, Design and Implementation Lloyd s Minimum Standards MS13 Modelling, Design and Implementation January 2019 2 Contents MS13 Modelling, Design and Implementation 3 Minimum Standards and Requirements 3 Guidance 3 Definitions 3 Section

More information

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005 2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005 Presentation Overview Economic Analysis Economic vs Financial Analysis Unit Costs vs Portfolio

More information

Long-Term Fiscal External Panel

Long-Term Fiscal External Panel Long-Term Fiscal External Panel Summary: Session One Fiscal Framework and Projections 30 August 2012 (9:30am-3:30pm), Victoria Business School, Level 12 Rutherford House The first session of the Long-Term

More information

Common Quality Development Plan Evaluation of Options

Common Quality Development Plan Evaluation of Options Common Quality Development Plan Evaluation of Options Table of Contents Introduction and Purpose... 4 Background... 4 Summary... 6 Overall Approach... 10 Frequency Development... 12 Overview of current

More information

AUFLS information paper

AUFLS information paper AUFLS information paper Contents 1 Introduction... 1 2 The under-frequency management challenge... 1 3 Overview of current arrangements... 3 3.1 The current AUFLS exemptions... 4 4 Initiatives to address

More information

NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010

NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010 NEW ZEALAND SOCIETY OF ACTUARIES PROFESSIONAL STANDARD NO. 91 ECONOMIC VALUATIONS MANDATORY STATUS EFFECTIVE DATE 1 JULY 2010 1. Introduction... 2 2. Effective Date... 3 3. Definitions... 3 4. Professional

More information

SIMULATION OF ELECTRICITY MARKETS

SIMULATION OF ELECTRICITY MARKETS SIMULATION OF ELECTRICITY MARKETS MONTE CARLO METHODS Lectures 15-18 in EG2050 System Planning Mikael Amelin 1 COURSE OBJECTIVES To pass the course, the students should show that they are able to - apply

More information

Transmission Loss Factor Methodology

Transmission Loss Factor Methodology Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3

More information

INVESTIGATIONS OF THE FINANCIAL CONDITION OF DEFINED BENEFIT SUPERANNUATION FUNDS

INVESTIGATIONS OF THE FINANCIAL CONDITION OF DEFINED BENEFIT SUPERANNUATION FUNDS PROFESSIONAL STANDARD 400 INVESTIGATIONS OF THE FINANCIAL CONDITION OF DEFINED BENEFIT SUPERANNUATION FUNDS INDEX 1 INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 4

More information

Milford Unit Trust PIE Funds. Statement of Investment Policy & Objectives

Milford Unit Trust PIE Funds. Statement of Investment Policy & Objectives Statement of Investment Policy & Objectives Statement of Investment Policy & Objectives Milford Funds Limited 29 June 2017 Table of Contents PART A: THE MILFORD UNIT TRUST PIE FUNDS 3 Introduction 3 Investment

More information

D.17 STATEMENT OF CORPORATE INTENT CONNECTING NEW ZEALAND SCI

D.17 STATEMENT OF CORPORATE INTENT CONNECTING NEW ZEALAND SCI D.17 STATEMENT OF CORPORATE INTENT CONNECTING NEW ZEALAND SCI 20 15 16 TABLE OF CONTENTS 1. ROLE AND OBJECTIVES... 3 1.1 Transpower s Role... 3 1.2 Transpower s Objectives... 3 2. TRANSPOWER S STRATEGY

More information

UK Power Networks. Overall Cost Benefit Analysis

UK Power Networks. Overall Cost Benefit Analysis UK Power Networks Overall Cost Benefit Analysis Contents 1 Executive Summary 3 1.1 Analysis Conclusions 3 1.2 Summary Table 4 2 Introduction 5 2.1 Scope 5 2.2 Input Parameters 6 2.3 Asset Replacement/Refurbishment

More information

Active Asset Allocation in the UK: The Potential to Add Value

Active Asset Allocation in the UK: The Potential to Add Value 331 Active Asset Allocation in the UK: The Potential to Add Value Susan tiling Abstract This paper undertakes a quantitative historical examination of the potential to add value through active asset allocation.

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information

CHAPTER 13: A PROFIT MAXIMIZING HARVEST SCHEDULING MODEL

CHAPTER 13: A PROFIT MAXIMIZING HARVEST SCHEDULING MODEL CHAPTER 1: A PROFIT MAXIMIZING HARVEST SCHEDULING MODEL The previous chapter introduced harvest scheduling with a model that minimized the cost of meeting certain harvest targets. These harvest targets

More information

Business Practice Manual For. Generator Management. Version 76

Business Practice Manual For. Generator Management. Version 76 Business Practice Manual For Generator Management Version 76 Revision Date: April 30, 3015June 1, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine

More information

ENTELLIGENT S SMART CLIMATE PORTFOLIO OPTIMIZER Smart Climate Data Solutions

ENTELLIGENT S SMART CLIMATE PORTFOLIO OPTIMIZER Smart Climate Data Solutions ENTELLIGENT S SMART CLIMATE PORTFOLIO OPTIMIZER Smart Climate Data Solutions Entelligent support@entelligent.com 303-443- 9447 Disclaimer This confidential document is only intended for the recipient to

More information

AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS

AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS ProgressEnergy SECOND REVISED SHEET No. 9.100 CANCELS FIRST REVISED SHEET No. 9.100 AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

STCP 16-1 Issue 005 Investment Planning

STCP 16-1 Issue 005 Investment Planning STCP 16-1 Issue 005 Investment Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Reviewing and Approving TYNDP A Regulatory Perspective Evangelos Penglis Partner, VIS Economic & Energy Consultants 08/12/2017

More information

2017 SEM PARAMETERS FOR THE DETERMINATION OF REQUIRED CREDIT COVER

2017 SEM PARAMETERS FOR THE DETERMINATION OF REQUIRED CREDIT COVER 2017 SEM PARAMETERS FOR THE DETERMINATION OF REQUIRED CREDIT COVER SEMO 2017 Page 1 of 17 Table of Contents 1. Background... 3 1.1 Introduction... 3 1.2 Objective... 4 2. Summary of Recommendations...

More information

Community and Renewable Energy Scheme Project Development Project Toolkit Project Finance Module

Community and Renewable Energy Scheme Project Development Project Toolkit Project Finance Module Community and Renewable Energy Scheme Project Development Project Toolkit Module Structure In the past, it was the case that the high costs involved with setting up loan finance for energy projects tended

More information

PEPANZ Submission: New Zealand Emissions Trading Scheme Review 2015/16

PEPANZ Submission: New Zealand Emissions Trading Scheme Review 2015/16 29 April 2016 NZ ETS Review Consultation Ministry for the Environment PO Box 10362 Wellington 6143 nzetsreview@mfe.govt.nz PEPANZ Submission: New Zealand Emissions Trading Scheme Review 2015/16 Introduction

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.6 INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES OCTOBER 2007 This document was prepared

More information

Managing Cash Flows in Volatile Markets Tools, Techniques and Global Experience

Managing Cash Flows in Volatile Markets Tools, Techniques and Global Experience www.pwc.com Managing Cash Flows in Volatile Markets Tools, Techniques and Global Experience 24-26 Agenda Backdrop Framework for Financial Risk Management The Cash Flow at Risk Model Q&A Slide 2 Backdrop

More information

Long-Term Trading Strategies

Long-Term Trading Strategies Long-Term Trading Strategies Alfred Hoffmann Bewag AG, Berlin 3th January 3, St. Veit, Austria 1 Structure Definition of the strategy Implementation of the strategy Case Study Conclusions Value chains

More information

Vanguard Global Capital Markets Model

Vanguard Global Capital Markets Model Vanguard Global Capital Markets Model Research brief March 1 Vanguard s Global Capital Markets Model TM (VCMM) is a proprietary financial simulation engine designed to help our clients make effective asset

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 1 2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 Agenda January 24 9:00am-9:30am pacific Capacity-Contribution Values for Energy-Limited Resources 9:30am-11:30am pacific Coal

More information

Supplement to the 2019/20 Electric Rate Application Index February 14, 2019 MANITOBA HYDRO 2019/20 ELECTRIC RATE APPLICATION. 1.0 Overview...

Supplement to the 2019/20 Electric Rate Application Index February 14, 2019 MANITOBA HYDRO 2019/20 ELECTRIC RATE APPLICATION. 1.0 Overview... 0 0 Supplement to the 0/0 Electric Rate Application Index February, 0 MANITOBA HYDRO 0/0 ELECTRIC RATE APPLICATION SUPPLEMENT TO THE APPLICATION INDEX.0 Overview....0 Reasons for the Rate Increase....0

More information

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH Count of Settlement Periods -1+ -1 - -9-9 - -8-8 - -7-7 - -6-6 - -5-5 - -4-4 - -3-3 - -2-2 - -1-1 - - 1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-1 1 + PUBLIC ISG26-SPAR REPORTING ON MAY 218 ISSUE 31 PUBLISHED

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2018 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 160

More information

Wellington Electricity CPP assessment of 2010/21 capex

Wellington Electricity CPP assessment of 2010/21 capex Commerce Commission P O Box 2351 Wellington 6140 For the Attention of: Kade Sheely 18th January 2018 Dear Kade Wellington Electricity CPP assessment of 2010/21 capex I am pleased to provide this briefing

More information

The cost allocation principles and methodologies in this Attachment Y cover only

The cost allocation principles and methodologies in this Attachment Y cover only 31.5 Cost Allocation and Cost Recovery 31.5.1 The Scope of Attachment Y Cost Allocation 31.5.1.1 Regulated Responses The cost allocation principles and methodologies in this Attachment Y cover only regulated

More information

CMP242 Charging arrangements for interlinked offshore transmission solutions connecting to a single onshore substation

CMP242 Charging arrangements for interlinked offshore transmission solutions connecting to a single onshore substation Stage 03: Workgroup Report Connection and Use of System Code (CUSC) CMP242 Charging arrangements for interlinked offshore transmission solutions connecting to a single onshore substation CMP242 aims to

More information

3: Balance Equations

3: Balance Equations 3.1 Balance Equations Accounts with Constant Interest Rates 15 3: Balance Equations Investments typically consist of giving up something today in the hope of greater benefits in the future, resulting in

More information

Explanatory Paper for Transmission Loss Adjustment Factor (TLAF) Calculation Methodology Publication Date: 27/09/2012 Version 1.0

Explanatory Paper for Transmission Loss Adjustment Factor (TLAF) Calculation Methodology Publication Date: 27/09/2012 Version 1.0 Explanatory Paper for Transmission Loss Adjustment Factor (TLAF) Calculation Methodology Publication Date: 27/09/2012 Version 1.0 Published on 27/09/2012 Page 1 of 20 CONTENTS 1. Introduction/Background...

More information

Advanced Operational Risk Modelling

Advanced Operational Risk Modelling Advanced Operational Risk Modelling Building a model to deliver value to the business and meet regulatory requirements Risk. Reinsurance. Human Resources. The implementation of a robust and stable operational

More information

DESCRIPTION OF THE CITI VOLATILITY BALANCED BETA (VIBE) EQUITY US GROSS TOTAL RETURN INDEX

DESCRIPTION OF THE CITI VOLATILITY BALANCED BETA (VIBE) EQUITY US GROSS TOTAL RETURN INDEX General DESCRIPTION OF THE CITI VOLATILITY BALANCED BETA (VIBE) EQUITY US GROSS TOTAL RETURN INDEX The Citi Volatility Balanced Beta (VIBE) Equity US Gross Total Return Index (the Index ) is an equity-linked

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information