1 Alberta Electricity Markets Tyler Drever Nov 9, 2009

2 Alberta Electricity Market - History Prior to 2000: Alberta market centrally controlled by the provincial government and a handful of vertically-integrated companies TransAlta, ATCO Power and EPCOR August 2000: PPA Auctions Preparing for Deregulation Companies were required to sell the right to commercially market large generators built during regulation (Coal / Hydro) Done to prevent market power and encourage private development Auctions called Power Purchase Agreements (PPAs) Contracts lasted for a maximum of 20 years Jan 2001: Deregulated market begins All generators compete in order of least cost to provide power to the Alberta grid

3 Electricity is a unique commodity Power cannot be effectively stored Natural Gas, Oil, Precious metals, etc can all be physically purchased and resold or consumed at a later date. Power is created and consumed instantaneously Supply = Demand. Always! The entire grid is electromagnetically synchronized. From Alberta to California, the same line frequency is required. Problems will impact large areas if not corrected quickly North East blackouts of 2003

4 Alberta Power Markets - Overview Generators offer any electricity they can generate to the grid at a specified price Price can vary from $0 to $1000/MW Ordered by least cost (Merit Order) Alberta System Operator dispatches enough supply to equal system demand at that time. Dispatched in order of least cost Any generator that is dispatched is paid equal to the marginal unit. Any generator not dispatched is not paid. Example: The last generator s offer is $45.00/MW. All energy flowing to the grid at that moment is paid $45.00/MW, regardless of if it was offered for $0 or $44.99.

5 Price Available MW $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ - 1 $1,000 Price ($) $900 $800 $700 $600 $500 $400 $300 $200 $100 Merit Order - Snapshot Offered Energy Energy Merit Order - Sept 1-14:00 System Demand $ System Load (MW) Intersection of Offered Energy (Supply) and System Demand = Price of Power in Alberta

6 Alberta System Load - Daily

7 What does that look like?

8 Our Market Can Be Volatile

9 Market Participants What I Did Real Time Desk 24 Hour Desk Commercial monitoring Market Analysis How are other companies offered? Why? Are our assets offered in an optimal market position? Remote operational plant control of smaller assets

10 Market Participants What I Did Real Time Desk Required to be the daily market expert on what is happening on the grid Coal Derates Wind Forecast System Load Forecast ATCO Offer Strategy Where are we within the merit order? Have other competitors altered their offers? Why? Should we respond? Remote Dispatch - Operations Can start/stop peaker turbines, respond to system requests for emergency energy, interface with our cogeneration stations

11 Market Participants What I Do Ancillary Services Derivatives of electricity Contracts to provide fast ramping emergency energy to the grid Contracts are sold on a open trading system Watt-Exchange (watt-ex) Usually mutually exclusive to energy You can t flow energy and withhold it to flow in emergency

12 Market Participants What I Do Ancillary Services Since AS and Energy are mutually exclusive the market requires contracts that pay for 24/7 service Even if we only provide the emergency power for a fraction of that time, we re still paid to hold the energy in reserve on demand Otherwise we d face a high opportunity cost of not flowing the energy to the grid for pool price Ancillary Service contracts are sold at an index to power price Example: A contract worth -20 pays $40/MW if Pool Price is $60. Contracts cannot be worth negative amounts Detailed Pool Price forecasts are required to transact effectively What will Pool Price be tomorrow? How volatile is the market likely to be? Lots of sporadic wind generation? Hot summer day could mean a spike in air conditioning load, do we have enough base load power to service it?

13 Market Participants Continued Energy Marketing Responsible for overall energy offer strategy Co-optimal strategy of Ancillary Services and Electricity Asset Optimization Maintains price forecasts, monitors natural gas developments

14 Market Participants North America Physical Power Market

15 Market Participants: Financial Power Markets

16 Questions? Sites of Interest: Alberta Electric System Operator Market Surveillance Administrator (Market watchdog ) Click Reports for lots of public reports and data My Contact Information: Tyler.Drever@atcopower.com Ancillary Services Marketer Asset Optimization

Q2/17 Quarterly Report

Q2/17 Quarterly Report Q2/17 Quarterly Report April June 2017 August 11, 2017 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets

More information

Operating Reserves Procurement Understanding Market Outcomes

Operating Reserves Procurement Understanding Market Outcomes Operating Reserves Procurement Understanding Market Outcomes TABLE OF CONTENTS PAGE 1 INTRODUCTION... 1 2 OPERATING RESERVES... 1 2.1 Operating Reserves Regulating, Spinning, and Supplemental... 3 2.2

More information

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited)

Condensed Interim Financial Statements and Review. Balancing Pool. For the three months ended March 31, 2018 (Unaudited) Condensed Interim Financial Statements and Review Balancing Pool For the three months ended March 31, 2018 (Unaudited) NOTICE OF NO AUDITOR S REVIEW OF INTERIM FINANCIAL STATEMENTS The accompanying unaudited

More information

3 Calculation of Unforced Capacity (UCAP)

3 Calculation of Unforced Capacity (UCAP) 3 Calculation of Unforced Capacity (UCAP) This section addresses the methodologies for calculating unforced capacity (UCAP) of capacity assets. 3.1 Calculation of UCAP 3.1.1 Before every base auction and

More information

Alberta Electric System Operator 2017 ISO Tariff Update

Alberta Electric System Operator 2017 ISO Tariff Update Alberta Electric System Operator 2017 ISO Tariff Update Date: October 20, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Classification: Public Table of Contents

More information

Second Quarter & Year-to-Date 2007 Results

Second Quarter & Year-to-Date 2007 Results Second Quarter & Year-to-Date 2007 Results Strong business model. Diversified generating assets. Technical and commercial expertise. Environmental leadership. Financial discipline. Forward looking statements

More information

Managing Risk of a Power Generation Portfolio

Managing Risk of a Power Generation Portfolio Managing Risk of a Power Generation Portfolio 1 Portfolio Management Project Background Market Characteristics Financial Risks System requirements System design Benefits 2 Overview Background! TransAlta

More information

THIRD QUARTER REPORT FOR 2007

THIRD QUARTER REPORT FOR 2007 TRANSALTA CORPORATION THIRD QUARTER REPORT FOR 2007 MANAGEMENT S DISCUSSION AND ANALYSIS This management s discussion and analysis ( MD&A ) contains forward-looking statements. These statements are based

More information

Electricity trading and risk management in liberalised market

Electricity trading and risk management in liberalised market www.pwc.com/jp Electricity trading and risk management in liberalised market PricewaterhouseCoopers Agenda Page 1 Current electricity trading in Japan 1 2 Evolution of trading in a deregulated market 5

More information

Spinning Reserve Market Event Report

Spinning Reserve Market Event Report Spinning Reserve Market Event Report 23 January, 2004 TABLE OF CONTENTS PAGE 1. MARKET EVENT... 1 2. BACKGROUND... 2 3. HYDRO GENERATION, THE HYDRO PPA AND THE AS MARKET... 4 4. CHRONOLOGY AND ANALYSIS...

More information

TransAlta Corporation Management s Discussion and Analysis December 31, 2017

TransAlta Corporation Management s Discussion and Analysis December 31, 2017 TransAlta Corporation Management s Discussion and Analysis December 31, 2017 TRANSALTA CORPORATION Management s Discussion and Analysis Table of Contents Forward-Looking Statements M2 Additional IFRS Measure

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 8: Supply Obligations and Performance Assessments Prepared by: Alberta Electric System Operator Date: January

More information

Rules relating to intermittent generators - Assessment under section 172F(1) 1

Rules relating to intermittent generators - Assessment under section 172F(1) 1 Rules relating to intermittent generators - Assessment under section 172F(1) 1 1 Sections 172E and 172F of the Electricity Act 1992 (Act) set out the requirements on the Electricity Commission (Commission)

More information

20 years operation of the Nordic electricity market

20 years operation of the Nordic electricity market ENERGY 20 years operation of the Nordic electricity market ADB Regional Energy Trade Workshop September 8-9, 2014 Manila Dr. Per Christer Lund 1 SAFER, SMARTER, GREENER Electricity market world wide 2

More information

48 th Annual EEI Financial Conference November Brett Gellner, Chief Financial Officer

48 th Annual EEI Financial Conference November Brett Gellner, Chief Financial Officer 48 th Annual EEI Financial Conference November 2013 Brett Gellner, Chief Financial Officer 1 Forward Looking Statements This presentation may contain forward-looking statements pertaining to the following:

More information

November th Annual EEI Financial Conference. Brett Gellner Chief Financial Officer

November th Annual EEI Financial Conference. Brett Gellner Chief Financial Officer November 2012 47 th Annual EEI Financial Conference Brett Gellner Chief Financial Officer 1 Forward looking statements This presentation contains forward looking statements, including statements regarding

More information

TD Securities 2011 Calgary Unconventional Energy Conference July 7, Dawn Farrell Chief Operating Officer

TD Securities 2011 Calgary Unconventional Energy Conference July 7, Dawn Farrell Chief Operating Officer TD Securities 2011 Calgary Unconventional Energy Conference July 7, 2011 Dawn Farrell Chief Operating Officer 1 Forward looking statements This presentation may contain forward looking statements, including

More information

CIBC 2014 Institutional Investor Conference Dawn Farrell Chief Executive Officer

CIBC 2014 Institutional Investor Conference Dawn Farrell Chief Executive Officer CIBC 2014 Institutional Investor Conference Dawn Farrell Chief Executive Officer 1 Forward Looking Statements This presentation may contain forward-looking statements pertaining to the following: the timing

More information

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.

More information

Forward looking statements

Forward looking statements Forward looking statements This presentation may contain forward looking statements, including statements regarding the business and anticipated financial performance of TransAlta Corporation. All forward

More information

Alberta Electric System Operator Amended 2018 ISO Tariff Application

Alberta Electric System Operator Amended 2018 ISO Tariff Application Alberta Electric System Operator Amended 2018 ISO Tariff Application Date: August 17, 2018 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 7 1.3 Relief requested...

More information

Building on strengths

Building on strengths Building on strengths CIBC World Markets 10 th Annual Whistler Institutional Investor Conference Steve Snyder, President & CEO February 23, 2007 Forward looking statements This presentation may contain

More information

Alberta Electric System Operator 2018 ISO Tariff Application

Alberta Electric System Operator 2018 ISO Tariff Application Alberta Electric System Operator 2018 ISO Tariff Application Date: September 14, 2017 Table of Contents 1 Application... 6 1.1 Background... 6 1.2 Organization of application... 6 1.3 Relief requested...

More information

TRANSALTA CORPORATION

TRANSALTA CORPORATION Management's Discussion and Analysis TRANSALTA CORPORATION Second Quarter Report for 2018 This Management s Discussion and Analysis ( MD&A ) contains forward-looking statements. These statements are based

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions for the Imposition of Mitigation Measures... 2 39.2.1

More information

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Advisory Service for Energy and Climate Change John Lambert Senior Business Development Manager Direct Energy

More information

Anders Plejdrup Houmøller 10 May Wholesale market models and the role of exchanges and traders. Prepared by Anders Plejdrup Houmøller

Anders Plejdrup Houmøller 10 May Wholesale market models and the role of exchanges and traders. Prepared by Anders Plejdrup Houmøller Wholesale market models and the role of exchanges and traders Prepared by Anders Plejdrup Houmøller www. erranet.org Agenda The trading system. The spot market. Transparency. Surveillance of the market.

More information

WESTERN MARKET SNAPSHOT

WESTERN MARKET SNAPSHOT The Market Monitor is published on the Market Surveillance Administrator's web site (www.albertamsa.ca) every Tuesday reporting on key market indicators and weekly trends in Alberta's evolving electricity

More information

Termination of the Battle River 5 Power Purchase Arrangement with the Generation Owner

Termination of the Battle River 5 Power Purchase Arrangement with the Generation Owner Termination of the Battle River 5 Power Purchase Arrangement with the Generation Owner Table of Contents January 12, 2018 Disclaimer... 1 Executive Summary... 2 Overview of the Balancing Pool and the Power

More information

ANNUAL INFORMATION FORM

ANNUAL INFORMATION FORM ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2002 ONTARIO POWER GENERATION INC. March 31, 2003 TABLE OF CONTENTS Page ITEM 1 - CORPORATE STRUCTURE... 1 ITEM 2 - BACKGROUND... 2 Overview... 2

More information

BMO 2015 Fixed Income Conference. Todd Stack VP & Treasurer

BMO 2015 Fixed Income Conference. Todd Stack VP & Treasurer BMO 2015 Fixed Income Conference Todd Stack VP & Treasurer 1 Forward Looking Statements This presentation may contain forward looking statements, including statements regarding the business and anticipated

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

Chapter 7 DESIGN FLAWS AND A WORSENING CRISIS. Sequential Markets and Strategic Bidding

Chapter 7 DESIGN FLAWS AND A WORSENING CRISIS. Sequential Markets and Strategic Bidding Chapter 7 DESIGN FLAWS AND A WORSENING CRISIS During the first two successful years of restructuring in California, prices declined. This initial success meant that the restructured market s design flaws

More information

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION November 30, 2016 www.poweradvisoryllc.com To: Power Advisory Clients and Colleagues From: Kris Aksomitis, Jason Chee-Aloy, Brenda Marshall,

More information

Third Quarter & Year-to-Date 2007 Results

Third Quarter & Year-to-Date 2007 Results Third Quarter & Year-to-Date 2007 Results Strong business model. Diversified generating assets. Technical and commercial expertise. Environmental leadership. Financial discipline. Forward looking statements

More information

Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets

Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets Frank A. Wolak Department of Economics Stanford University Stanford, CA 94305-6072 wolak@zia.stanford.edu http://www.stanford.edu/~wolak

More information

TRANSALTA CORPORATION

TRANSALTA CORPORATION Management's Discussion and Analysis TRANSALTA CORPORATION First Quarter Report for 2018 This Management s Discussion and Analysis ( MD&A ) contains forward-looking statements. These statements are based

More information

Seasonal Factors and Outlier Effects in Returns on Electricity Spot Prices in Australia s National Electricity Market.

Seasonal Factors and Outlier Effects in Returns on Electricity Spot Prices in Australia s National Electricity Market. Seasonal Factors and Outlier Effects in Returns on Electricity Spot Prices in Australia s National Electricity Market. Stuart Thomas School of Economics, Finance and Marketing, RMIT University, Melbourne,

More information

C2-102 COMMON NORDIC BALANCE MANAGEMENT. K.LINDSTRÖM FINGRID (Finland)

C2-102 COMMON NORDIC BALANCE MANAGEMENT. K.LINDSTRÖM FINGRID (Finland) 21, rue d'artois, F-75008 Paris http://www.cigre.org C2-102 Session 2004 CIGRÉ COMMON NORDIC BALANCE MANAGEMENT O.GJERDE* STATNETT (Norway) F.WIBROE ELTRA (Denmark) J-E. FISCHER ELKRAFT (Denmark) K.LINDSTRÖM

More information

The Role of Flexibility and Virtual Power Plants in Modern Power Markets

The Role of Flexibility and Virtual Power Plants in Modern Power Markets The Role of Flexibility and Virtual Power Plants in Modern Power Markets Nicolas Sommer Joint Meeting Hertie Energy and Environment Network (HEEN) and Strommarkttreffen 01. July 2016 Outline NEXT Kraftwerke,

More information

Supply Chain. An Insurer Perspective. Willis Energy Summit 21 January 2016 Jamie Summons, Head of Weather Solutions, Asia Pacific

Supply Chain. An Insurer Perspective. Willis Energy Summit 21 January 2016 Jamie Summons, Head of Weather Solutions, Asia Pacific Supply Chain An Insurer Perspective Willis Energy Summit 21 January 2016 Jamie Summons, Head of Weather Solutions, Asia Pacific The Supply Chain: Current approach to risk transfer Contingent Business Interruption:

More information

Decision D Balancing Pool

Decision D Balancing Pool Decision 22184-D10-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the, TransAlta Generation Partnership, and Capital Power Generation Services Inc.

More information

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum does not require Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: November 7, 2018 Re: Department of Market Monitoring

More information

The University of Calgary

The University of Calgary Decision 23147-D01-2018 Application for an Order Permitting the Sharing of Records Not Available to the Public Between the University of Calgary and URICA Energy Real Time Ltd. January 30, 2018 Alberta

More information

Long-Term Reliability Assessment

Long-Term Reliability Assessment Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information

peaksaver in the DR Auction Challenges to Implementing Residential DR in the Energy Market

peaksaver in the DR Auction Challenges to Implementing Residential DR in the Energy Market peaksaver in the DR Auction Challenges to Implementing Residential DR in the Energy Market About Rodan Ontario s largest Meter Service Provider and Demand Response Aggregator Recently acquired Energent

More information

Workshop on Regional Electricity Trade and Market Development

Workshop on Regional Electricity Trade and Market Development Workshop on Regional Electricity Trade and Market Development Cross-border Electricity Trade and Tariffs April 23, 2014 Cross-border Electricity Trade (CBT) Flows within which part of the transmission

More information

2014 Investor Day Positioned for Growth

2014 Investor Day Positioned for Growth 2014 Investor Day Positioned for Growth November 2014 1 Forward Looking Statements This presentation contains certain forward looking statements and forward looking information within the meaning of applicable

More information

TRANSALTA CORPORATION NEWS RELEASE

TRANSALTA CORPORATION NEWS RELEASE TRANSALTA CORPORATION NEWS RELEASE TransAlta achieves record cash flow and double digit comparable earnings per share growth for the year 2008 comparable earnings per share 1 increased 11 per cent to $1.46

More information

CIBC 2013 Institutional Investor Conference Dawn Farrell Chief Executive Officer POWER INFRASTRUCTURE

CIBC 2013 Institutional Investor Conference Dawn Farrell Chief Executive Officer POWER INFRASTRUCTURE CIBC 2013 Institutional Investor Conference Dawn Farrell Chief Executive Officer POWER INFRASTRUCTURE Forward looking statements This presentation contains forward looking statements, including statements

More information

Spanish Regulation & Latam

Spanish Regulation & Latam London. 24th February, 2010 Spanish Regulation & Latam José Luis San Pedro 1 Regulation: Sector evolution during the last year Royal Decree Law 6/2009 deepens the liberalisation of the sector Removal of

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

Chapter 5: Trading. Industry Guide to the I-SEM

Chapter 5: Trading. Industry Guide to the I-SEM Chapter 5: Trading Industry Guide to the I-SEM 1 5.1 Submission timelines Each market operates over different timelines, as described in Chapter 4. By way of an example, the combined submission timelines

More information

Positioned for Growth. Business Review & Outlook

Positioned for Growth. Business Review & Outlook Positioned for Growth Business Review & Outlook 1 Forward Looking Statements This presentation may contain forward looking statements, including statements regarding the business and anticipated financial

More information

ICForecast: Strategic Power Outlook. Q Sample

ICForecast: Strategic Power Outlook. Q Sample ICForecast: Strategic Power Outlook Q1 2015 - Sample 2015 ICF International, Inc. Any views or opinions expressed in this paper are solely those of the author(s) and do not necessarily represent those

More information

TransAlta Corporation

TransAlta Corporation TransAlta Corporation First Quarter 2018 Results Tuesday May 8, 2018 1 Forward Looking Statements This presentation includes forward-looking statements or information (collectively referred to herein as

More information

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018 PAPER NAME De Minimis acceptance Threshold (DMAT) and Continuous Acceptance Duration Limit (CADL) Review Target Audience Purpose of paper Deadline for responses Contact name and details BSC Parties For

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 22669-D03-2017 Application for an Order Permitting the Sharing of Records Not Available to the Public Between Canadian Natural Resources Limited and ATCO Power Canada Ltd. July 21, 2017 Alberta

More information

Forward looking statements

Forward looking statements Forward looking statements This presentation may contain forward-looking statements, including statements regarding the business and anticipated financial performance of TransAlta Corporation. All forwardlooking

More information

TransAlta Corporation Investor Presentation November 2018

TransAlta Corporation Investor Presentation November 2018 TransAlta Corporation Investor Presentation November 2018 1 Forward Looking Statements This presentation includes forward-looking statements or information (collectively referred to herein as forward-looking

More information

SALES AND HIGHLIGHTS 2017 FIRST QUARTER

SALES AND HIGHLIGHTS 2017 FIRST QUARTER SALES AND HIGHLIGHTS 2017 FIRST QUARTER DISCLAIMER This presentation does not constitute an offer to sell securities in the United States or any other jurisdiction. No reliance should be placed on the

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ

INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT INDEX Executive

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation may be considered forward-looking

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

Power Procurement Strategy

Power Procurement Strategy Power Procurement Strategy 01.03.16 IIT-Kanpur For Public Use POWER SECTOR OVERVIEW Source: Executive Summary of October 2015, CEA *including renewable generation Installed Capacity (All) Category Installed

More information

Development of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement

Development of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement Development of the Renewable Dispatchable Generation Model Overview of SEPA & ScottMadden Engagement Speakers John Sterling Senior Director, Advisory Services Smart Electric Power Alliance John Pang Partner

More information

Quarterly Report: April - June 2012 (Q2/12)

Quarterly Report: April - June 2012 (Q2/12) Quarterly Report: April - June 2012 (Q2/12) August 20, 2012 Market Surveillance Administrator 403.705.3181 #500, 400 5th Avenue S.W., Calgary AB T2P 0L6 www.albertamsa.ca The Market Surveillance Administrator

More information

INVESTOR PRESENTATION JUNE 2018

INVESTOR PRESENTATION JUNE 2018 INVESTOR PRESENTATION JUNE 2018 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and Canadian Utilities Limited and information provided in this presentation JUNE be considered forward-looking

More information

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 6 Title Page SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Issued on: December 23, 2002 Effective: January

More information

The Ministry of Energy consists of the Department of Energy, the Alberta Petroleum Marketing Commission, and the Alberta Energy and Utilities Board.

The Ministry of Energy consists of the Department of Energy, the Alberta Petroleum Marketing Commission, and the Alberta Energy and Utilities Board. Energy BUSINESS PLAN 2007-10 ACCOUNTABILITY STATEMENT The business plan for the three years commencing April 1, 2007 was prepared under my direction in accordance with the Government Accountability Act

More information

Real Options: Creating and Capturing the Option Value in Regulated Assets

Real Options: Creating and Capturing the Option Value in Regulated Assets STRATEGIC CONSULTING Energy Real Options: Creating and Capturing the Option Value in Regulated Assets White Paper The fundamental insight is recognizing that faced with uncertainty, flexibility has value.

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23065-D01-2017 Alberta Electric System Operator 2018 Independent System Operator Tariff Update November 28, 2017 Alberta Utilities Commission Decision 23065-D01-2017 Alberta Electric System Operator

More information

Economic Dispatch. Quantitative Energy Economics. Anthony Papavasiliou 1 / 21

Economic Dispatch. Quantitative Energy Economics. Anthony Papavasiliou 1 / 21 1 / 21 Economic Dispatch Quantitative Energy Economics Anthony Papavasiliou Economic Dispatch 2 / 21 1 Optimization Model of Economic Dispatch 2 Equilibrium Model of Economic Dispatch Outline 3 / 21 1

More information

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination

ISO Rules Part 300 System Reliability and Operations Division 306 Outages and Disturbances Section Generation Outage Reporting and Coordination Applicability 1 Section 306.5 applies to: (a) a pool participant with a generating source asset with a maximum capability of five (5) MW or higher; (b) a legal owner of a source asset described in subsection

More information

TransAlta Corporation. Investor Presentation April 2017

TransAlta Corporation. Investor Presentation April 2017 TransAlta Corporation Investor Presentation April 2017 1 Forward Looking Statements This presentation may include forward-looking statements or information (collectively referred to herein as forward-looking

More information

California ISO October 1, 2002 Market Design Elements

California ISO October 1, 2002 Market Design Elements California October 1, 2002 Market Design Elements California Board of Governors Meeting April 25, 2002 Presented by Keith Casey Manager of Market Analysis and Mitigation Department of Market Analysis 1

More information

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144 ICAP Demand Curve Zachary T. Smith Supervisor, ICAP Market Operations, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 12144 1 Objectives Upon the completion of this module, trainees should

More information

Capacity Expansion in Competitive Electricity Markets

Capacity Expansion in Competitive Electricity Markets Capacity Expansion in Competitive Electricity Markets Efthymios Karangelos University of Liege November 2013 In the past... Vertical Integration A single utility owned & operated all power system infrastructure.

More information

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P.

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P. Q2 2017 I N T E R I M R E P O R T Brookfield Renewable Partners L.P. OUR OPERATIONS We manage our facilities through operating platforms in North America, Colombia, Brazil, and Europe which are designed

More information

Results Presentation Six month period ended 31 December 2010

Results Presentation Six month period ended 31 December 2010 Results Presentation Six month period ended 31 December 2010 22 February 2011 Disclaimer This presentation may contain projections or forward looking statements regarding a variety of items. Such forward-looking

More information

NEAS ENERGY - Route to Market

NEAS ENERGY - Route to Market NEAS ENERGY - Route to Market Overview Wholesale Power Market developments Revenue Profiles Secured and Unsecured FIT CFD v ROC PPA Key terms and conditions PPA Backstop PPA Cash flows for CfD and ROC

More information

Merrill Lynch Power & Gas Leaders Conference September 26, 2007

Merrill Lynch Power & Gas Leaders Conference September 26, 2007 Merrill Lynch Power & Gas Leaders Conference September 26, 2007 John Bryson, Chairman, Chief Executive Officer and President Forward-Looking Statements Statements contained in this presentation about future

More information

Compliance Review 2017

Compliance Review 2017 February 27, 2018 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table of Contents

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

Uplift Charges, FTR Underfunding and Overallocation

Uplift Charges, FTR Underfunding and Overallocation Uplift Charges, FTR Underfunding and Overallocation Solutions in PJM Getting to Yes on Uplift Allocation Fixing FTR Funding Abram W. Klein 9 October 2014 Platts Nodal Trader Conference New York City Discussion

More information

Market power issues in the NEM

Market power issues in the NEM CEEM Specialised Training Program EI Restructuring in Australia Market power issues in the NEM Xinmin Hu Centre for Energy and Environmental Markets Australian Graduate School of Management The University

More information

MMC Energy Inc. MMCN.OTC:BB NASDAQ

MMC Energy Inc. MMCN.OTC:BB NASDAQ MMC Energy Inc. MMCN.OTC:BB NASDAQ Disclaimer This presentation material contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E

More information

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 1 2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 Agenda January 24 9:00am-9:30am pacific Capacity-Contribution Values for Energy-Limited Resources 9:30am-11:30am pacific Coal

More information

This memo provides highlights of market performance in October and November.

This memo provides highlights of market performance in October and November. California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: December 5, 2018 Re: Department of Market Monitoring

More information

ISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules

ISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules Original Sheet No. 637 ISO TARIFF APPENDIX L Rate Schedules Original Sheet No. 638 Schedule 1 Grid Management Charge The Grid Management Charge (ISO Tariff Section 8.0) is a formula rate designed to recover

More information

GDF SUEZ Energy France Business line. Henri Ducré

GDF SUEZ Energy France Business line. Henri Ducré GDF SUEZ Energy France Business line Henri Ducré Key business figures * Leading positions in gas and electricity in France 1 st gas supplier 2 nd producer and supplier of electricity 1 st player in the

More information

Transmission Formula Rate 2017 Annual Update. June 23, 2017

Transmission Formula Rate 2017 Annual Update. June 23, 2017 Transmission Formula Rate 2017 Annual Update June 23, 2017 1 Topics Introductions Annual Update Overview 2017 Projection and 2016 True-Up Schedule 1 Additional Information Questions and Discussion 2 OASIS

More information

Resource Adequacy in Energy-Only ERCOT

Resource Adequacy in Energy-Only ERCOT Resource Adequacy in Energy-Only ERCOT Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) 619-3532 shams@crescentpower.net June 27, 2007 Background on ERCOT Electric Reliability Council of Texas (ERCOT) is:

More information

Largest nuclear site in North America Facilities spread over 2,300 acres connected by 56 kms (35 miles) of roadway

Largest nuclear site in North America Facilities spread over 2,300 acres connected by 56 kms (35 miles) of roadway Bruce Power Update Bruce Power Today Largest operating nuclear facility in the World Site capable of producing 6,300 MW or between 25-30% of Ontario s electricity needs. Largest private investor in Ontario

More information

Unlocking grid flexibility:

Unlocking grid flexibility: Jan Vorrink TenneT at a glance 2017 Europe's first cross-border grid operator 4,068 Employees EBIT 897 (EUR million) Assets 20.4 (EUR billion) Investments (2018-2028) 28 (EUR billion) Connected offshore

More information

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet ISO 2016-2017 Transmission Planning Process Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet January 4, 2018 Contents 1. Introduction... 1 2. Background... 1 3. Objectives

More information

DS3 System Services Protocol Regulated Arrangements

DS3 System Services Protocol Regulated Arrangements DS3 System Services Protocol Regulated Arrangements DS3 System Services Implementation Project 12 December 2017 Version 1.0 Contents 1 Introduction... 4 1.1 Service Provider Intermediary for a Providing

More information