Rules relating to intermittent generators - Assessment under section 172F(1) 1

Size: px
Start display at page:

Download "Rules relating to intermittent generators - Assessment under section 172F(1) 1"

Transcription

1 Rules relating to intermittent generators - Assessment under section 172F(1) 1 1 Sections 172E and 172F of the Electricity Act 1992 (Act) set out the requirements on the Electricity Commission (Commission) regarding consultation on, and assessment of, a rule before recommending that an amendment to the Electricity Governance Rules 2003 (Rules) be made to the Minister of Energy (Minister) 2. 2 As the proposal constitutes a rule amendment the process set out in the Act must be followed. 3 This appendix is a statement of proposal under section 172F(2) of the Act, for the purposes of consultation under section 172E(2)(b)(ii). As such, it is required to set out a detailed statement of the proposal, a statement of the reasons for it, provide an assessment of the proposal and reasonably practicable options identified by the Commission, and any other information that the Commission considers relevant. Overview of the proposal 4 The proposed changes collectively meet the objective to enable the power system to accommodate the increasing amounts of wind generation expected in the next few years. The rule changes are proposed as an interim solution while the Commission (through the WGIP) considers more long-term arrangements. 5 The proposal is a package of proposed rule changes, with each element of the package addressing a certain issue identified by the Commission through the course of the Tactical Wind Project. The three 3 elements are summarised in table 1 below: The assessment included here as Appendix 1 is that assessment which was prepared for the purposes of consultation on the proposed amendments, and published with the consultation material in August It is important to note that the rule changes now recommended differ in certain (comparatively minor) respects to the rule changes proposed in consultation, as a result of the Commission s consideration of the submissions made. A discussion of these changes is contained in the body of the paper to which this assessment is appended. Footnotes have been used in this appendix to provide updates to reflect the revisions made to the rule change recommendations. Section 172H(3) of the Act provides that if the Minister makes, or the Commission recommends, a rule for a purpose for which an electricity governance regulation may be made, the Minister and the Commission must comply with the same conditions and process that would apply under section 172D(3), section 172E, or section 172F if they were making recommendations on that electricity governance regulation, and those sections apply (with all necessary modifications) accordingly. Following consideration of submissions, the Commission has decided to defer the third of these to the WGIP process.

2 Table 1: Summary of proposed amendments Part Part A Defined Terms Part G Trading Arrangements Part C Common Quality Proposed Amendments A change to the definition of 'synchronous' so that intermittent generating stations are treated as synchronised for the purposes of the rules in section III of part C An amendment to rule in section II to ensure intermittent generators first obtain must-run auction rights for any electricity they wish to price at $0.00 An amendment to a new rule 8.3 (proposed under a separate rule change process) to be added to technical code C of schedule C3 of part C requiring intermittent generators making offers under rule 3.1 of section II of part G to provide indications and measurements specified in rule 4.1 in technical code C at intervals equal to or less than four seconds 4 6 The amendments relate to parts A, C and G of the Rules. Details of the proposed rule amendments are set out in Appendix 2 to this paper 5. 7 This Statement of Proposal is structured around the three elements of the proposal that collectively deliver the interim solution proposed by the Commission pending the WGIP process. For ease of reference, the elements are labelled as follows: Element A: 'Synchronism' Element B: 'MRDA' ensuring AOPOs are applicable to asynchronous wind turbines; ensuring intermittent generators have must-run (dispatch) auctions rights (MRDA) to price generation at $0.00; and Element C: 'Refresh Rate' ensuring intermittent generators are required to provide measurements at a specific refresh rate. 6 The proposal (Synchronism) 8 The proposal is to amend the definition of synchronism in part A of the Rules to ensure that the AOPOs in section III of part C are applicable to asynchronous wind turbines. 9 After considering alternative approaches, the system operator s advice, feedback from the CQAG and WMAG, and advice from its own legal staff, the Commission proposes (as an interim measure pending Following consideration of submissions, the Commission has decided not to pursue this rule change at this time, and has instead referred the issue to the WGIP. The appendix referred to here related to the consultation proposal. It has since been superseded and is no longer relevant. Instead the recommended set of rule changes is presented in Appendix 4. Following consideration of submissions, the Commission has decided not to pursue this rule change at this time, and has instead referred the issues to the WGIP.

3 completion of the WGIP process) to alter the definition of synchronised in part A of the Rules, as follows: synchronised means the condition whereby a synchronous machine is connected to a network and the electrical angular velocity of the machine corresponds with the network frequency and synchronise, de-synchronise, synchronising, synchronism and synchronisation have corresponding meanings;. Intermittent generating stations will be treated as being synchronised for the purposes of rules in section III of part C Statement of the reasons for the proposal (Synchronism) 10 The reasons for the proposed rule amendments are outlined in section 6 in the main body of this consultation paper In summary, the reason for the change is to clarify the applicability of the provisions using the term 'synchronous' (or similar) to asynchronous wind turbines. In particular, the objective is to make a change relatively urgently to make it clear to current asset owners and future investors that asynchronous generators are required to contribute to voltage and frequency management. Identification and assessment of reasonably practicable options (Synchronism) 12 Section 172F(1) of the Act requires the Commission to seek to identify all reasonably practicable options for achieving the objective of the rule. Section 172F(1) of the Act requires the Commission to assess: a. the costs and benefits of each reasonably practicable option, including the proposal; b. the extent to which the objective would be promoted or achieved by each option; and c. any other matters that the Commission considers relevant. 13 The Commission considers that the lack of clarity with the current rules in this area is such that preserving the status quo is not a reasonably practicable option. 14 The Commission considers that the only reasonably practicable option is to change each rule referring to synchronism in some manner (rather than the definition of the term 'synchronous' itself) so that it appropriately includes/excludes asynchronous generators. 15 The Commission does not favour this alternative. It considers that this option raises a number of other issues of clarity, broader than just those 7 This cross-reference relates to the consultation paper published in August The material referred to from that document (particularly paragraphs 6.3 to 6.13) setting out the description and rationale for these recommended rule changes has been included in the body of this paper to the Minister beginning at paragraph Error! Reference source not found..

4 needing urgent attention. It therefore considers that the rules in part C would require careful redrafting and extensive and thorough consultation given the consequences for asset owners and on system operation. Consequently, the Commission considers it more appropriate that this exercise be carried out by the WGIP as part of its comprehensive review of the AOPOs. Benefits and costs (synchronism) 16 The Commission has considered and decided that it is not possible to calculate the costs and benefits of the proposal and the alternative with any reasonable degree of accuracy. Therefore, the benefits and costs of its proposal and the alternative have been evaluated in qualitative terms. 17 The Commission considers that the benefits of the proposed change include: certainty for wind generation asset owners and investors regarding their obligations under these rules; clarity for the system operator in terms of the level of compliance with these rules it can expect from intermittent generators; and reduced compliance and monitoring activity and associated costs. 18 The only cost identified by the Commission is the cost associated with making this rule change. 19 The benefit of the alternative is greater than the proposal as it would provide more clarity in a number of other areas but at an increased cost in time and resources. Importantly, the Commission considers that the time required to undertake a more comprehensive review would adversely affect the Commission s ability to progress the urgent changes it considers are required. Therefore, the Commission considers the proposal to be relatively less costly and time consuming and, as a result, is superior to the alternative. Extent to which the proposal and the alternatives meet the objective (synchronism) 20 The objective of the change is to make a relatively urgent change to make it clear to current asset owners and future investors that generation alternatives are required to make a contribution to frequency and voltage management whether or not the machines are synchronous. The Commission considers this proposal meets the objective more swiftly than the alternative. Therefore, the Commission favours the proposal over the alternative. The proposal (MRDA) 21 The proposal is to ensure the rules are clear that intermittent generators must first obtain must-run auction rights for any electricity they wish to price at $0.00.

5 22 After considering alternative approaches, the system operator s advice, feedback from the CQAG and WMAG, and advice from its own legal staff, the Commission proposes (as an interim measure pending completion of the WGIP process) to alter rule in section II of part G of the Rules, as follows (text inserted is under lined): Specify Price Specify a price of either $0.00 (subject to rules 2.13 and 2.14 of section IV of part G) or $0.01 for the price band. Statement of the reasons for the proposal (MRDA) 23 The reasons for the proposed rule amendment are outlined in section 6 in the main body of this consultation paper In summary, the reason for the change is to clarify the existing rules to ensure intermittent generators must obtain must-run auction rights for quantities of electricity they wish to price at $0.00. Identification and assessment of reasonably practicable options (MRDA) 25 The Commission considers that the lack of clarity with the current rules in this area is such that preserving the status quo is not a reasonably practicable option. 26 Given the minor nature of the change proposed, the Commission considers that there is no other reasonably practicable option. Benefits and costs (MRDA) 27 The Commission has considered and decided that it is not possible to calculate the costs and benefits of the proposal with any reasonable degree of accuracy. Therefore, the benefits and costs of the proposal have been evaluated in qualitative terms. 28 The benefits of the proposal are that it provides certainty for wind generation asset owners and investors regarding their obligations under the Rules and clarity for the system operator in terms of the level of compliance with the Rules it can expect from intermittent generators. 29 The only cost identified by the Commission is the cost in making the rule change. Extent to which the proposal meets the objective (MRDA) 30 The objective of the change is to clarify the existing rules to ensure intermittent generation must obtain must-run auction rights for quantities 8 This cross-reference relates to the consultation paper published in August The material referred to from that document (particularly paragraphs 6.14 to 6.24) setting out the description and rationale for these recommended rule changes has been included in the body of this paper to the Minister beginning at paragraph 32.

6 of electricity they wish to price at $0.00. The Commission considers the proposal meets this objective by including a reference to rules 2.13 and 2.14 of section IV of part G. The proposal (refresh rate) 31 Following consideration of submissions, the Commission has decided not to pursue this rule change at this time. It has instead referred the issue to the WGIP for further consideration. 32 The proposed rule amendment below applies to a new rule, 8.3, which forms part of a complete replacement for technical code C, which, if accepted, is expected to come into effect in October Maximum interval between indications and measurements Station net MW, generating unit gross MW, station net Mvar and generating unit gross Mvar measurements provided in accordance with rule 8.1 from intermittent generators must be updated at the grid owner s SCADA remote terminal or the system operator s interface unit at least once every 4 seconds when provided by the primary means of data transmission communications. All other Each indications and measurements provided in accordance with rule 8.1 must be updated at the grid owner s SCADA remote terminal or the system operator s interface unit at least once every 8 seconds when provided by the primary means of data transmission communications. Statement of the reasons for the proposal (refresh rate) 33 The reasons for the proposed rule amendments are outlined in section 6 in the main body of this consultation paper In summary, the reason for the change is that, due to the continual and rapid variation in their output, intermittent generators appear to have greater potential to create temporal error in their measurements. The objective of this change is to reduce the potential temporal error associated with the measurements provided by intermittent generators. Identification and assessment of reasonably practicable options (refresh rate) 35 The Commission considers that the only reasonably practicable option is the status quo ie intermittent generating stations provide measurements at the same refresh rate as other generating stations. 9 This cross-reference relates to the consultation paper published in August 2006.

7 Benefits and costs (refresh rate) 36 The Commission has considered and decided that it is not possible to calculate the costs and benefits of the proposal and the alternative with any reasonable degree of accuracy. Therefore, the benefits and costs of its proposal and the alternative have been evaluated in qualitative terms. 37 The Commission considers that the benefits of the proposal over the alternative are: a reduction on the level of dispatch error, and a corresponding reduction in the level of frequency keeper deviation from its set point; and an improvement in the operation of the system operator s state estimator tool which is used to conduct contingency analysis and other security checks on the system. 38 The Commission s initial view 10 is that the cost of both the proposal and the alternative is the same. 39 Therefore, the Commission considers the proposal to be superior to the alternative. Extent to which the proposal and the alternatives meet the objective (refresh rate) 40 The objective of this change is to reduce the potential temporal error associated with the measurements provided by intermittent generators. The Commission s initial view is that the proposal meets the objective to a greater degree than the alternative and therefore the proposal is superior 20. Summary of the assessment The assessment of the benefits and costs of the proposal and reasonably practicable options all support the proposal. 42 The Commission considers that the proposal meets the objectives of each rule amendment to the greatest extent. 43 Accordingly, overall, the assessment of the benefits and costs of, and the extent to which the objective would be promoted and achieved by, each option supports the proposal. Other means to achieve the objective 44 The Commission must ensure that the objective of the rule is unlikely to be satisfactorily achieved by any reasonably practicable means other than the making of the rule (for example, by education, information, or voluntary compliance). The Commission considers that the objective of 10 Following consideration of submissions, the Commission has decided not to pursue this rule change at this time, and has instead referred the issue to the WGIP.

8 the rule is unlikely to be satisfactorily achieved by any reasonably practicable means other than the making of or amending the rule because the changes to the rules provide the greatest degree of certainty to participants as to their obligations. For instance, investors are unsure of their obligations to contribute to frequency and voltage management because the rules are unclear. The Commission considers changing the rules to be the best option to remove the ambiguity inherent in the existing rules. A voluntary arrangement would not give the system operator the certainty it requires regarding the capability of assets, which materially affects the system operator's ability to meet the Principal Performance Objectives (PPOs).

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION SCHEDULE F BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION cl. 7.3.1, 9.1.1 F1 Qualitative information required in a base capex proposal For the purpose of clause 7.3.1 (1) a base capex proposal must, in

More information

In preparing a causer pays procedure AEMO must take into account:

In preparing a causer pays procedure AEMO must take into account: Pacific Hydro makes this submission in response to the Causer Pays Procedure Factors for Asynchronous Operation: Issues Paper (October 2016) (Issues Paper).This submission has been jointly developed by

More information

STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing

STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STCP19-5 Issue 002 Offshore Transmission System Compliance Process & Testing STC Procedure Document Authorisation Company National Grid Electricity Transmission plc Name of Party Representative Signature

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Generating Unit Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Generating Unit Operating Requirements Applicability 1 Section 502.6 applies to: (a) the operator of a generating unit that is: (i) synchronized to the interconnected electrical system; and (ii) directly connected to the transmission system

More information

Alberta Electricity Markets

Alberta Electricity Markets Alberta Electricity Markets Tyler Drever Nov 9, 2009 Alberta Electricity Market - History Prior to 2000: Alberta market centrally controlled by the provincial government and a handful of vertically-integrated

More information

AUFLS information paper

AUFLS information paper AUFLS information paper Contents 1 Introduction... 1 2 The under-frequency management challenge... 1 3 Overview of current arrangements... 3 3.1 The current AUFLS exemptions... 4 4 Initiatives to address

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

Common Quality Development Plan Evaluation of Options

Common Quality Development Plan Evaluation of Options Common Quality Development Plan Evaluation of Options Table of Contents Introduction and Purpose... 4 Background... 4 Summary... 6 Overall Approach... 10 Frequency Development... 12 Overview of current

More information

Determination of the Ancillary Service Margin Peak and Margin Off-Peak parameters for the 2016/17 financial year

Determination of the Ancillary Service Margin Peak and Margin Off-Peak parameters for the 2016/17 financial year Determination of the Ancillary Service Margin Peak and Margin Off-Peak parameters for the 2016/17 financial year 31 March 2016 2016/17 financial year < Month 200x> Economic Regulation Authority 2016 This

More information

Market Rule Amendment Proposal

Market Rule Amendment Proposal Market Rule Amendment Proposal PART 1 MARKET RULE INFORMATION Identification No.: Subject: Generation Cost Guarantees Title: Real-Time Generation Cost Guarantee Revisions to Eligibility and Cost Submissions

More information

DS3 System Services Protocol Regulated Arrangements

DS3 System Services Protocol Regulated Arrangements DS3 System Services Protocol Regulated Arrangements DS3 System Services Implementation Project 12 December 2017 Version 1.0 Contents 1 Introduction... 4 1.1 Service Provider Intermediary for a Providing

More information

Market Rule Amendment Proposal

Market Rule Amendment Proposal Market Rule Amendment Proposal PART 1 MARKET RULE INFORMATION Identification No.: MR-00425 Subject: Real-Time Generation Cost Guarantee Title: Real-Time Generation Cost Guarantee Cost Recovery Framework

More information

Assessment of real-time pricing options

Assessment of real-time pricing options Assessment of real-time pricing options Information paper Submissions close: 24 May 2016 12 April 2016 Executive summary The Authority is seeking submissions to decide whether to explore real-time pricing

More information

SECTION B ADMINISTRATIVE RULES INDEX

SECTION B ADMINISTRATIVE RULES INDEX M. P. S. C. No. 2 Electric 2 nd Revised Sheet No. B-1.0 NORTHERN STATES POWER COMPANY, Cancels 1 st Revised Sheet No. B-1.0 SECTION B ADMINISTRATIVE RULES INDEX B1. TECHNICAL STANDARDS FOR ELECTRIC SERVICE

More information

Staff Paper Date October 2009

Staff Paper Date October 2009 IASB Meeting Agenda reference Appendix to Paper 7 Staff Paper Date October 2009 Project Liabilities amendments to IAS 37 Topic In June 2005, the Board published for comment an Exposure Draft of Proposed

More information

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation Clearing Manager Financial Transmission Rights Prudential Security Assessment Methodology with September 2015 variation 18 September 2015 To apply from 9 October 2015 Author: Warwick Small Document owner:

More information

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Transmission Planning Standards Industry Webinar: Footnote b January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair Topics Brief history Overview of as posted draft standard Changes since last posting

More information

Five-Minute Settlements Education

Five-Minute Settlements Education Five-Minute Settlements Education Disclaimer PJM has made all efforts possible to accurately document all information in this presentation. The information seen here does not supersede the PJM Operating

More information

DECISION ON MODIFICATIONS TO THE ELECTRICITY INTERCONNECTOR OPERATOR LICENCE

DECISION ON MODIFICATIONS TO THE ELECTRICITY INTERCONNECTOR OPERATOR LICENCE An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities DECISION ON MODIFICATIONS TO THE ELECTRICITY INTERCONNECTOR OPERATOR LICENCE Decision Paper Reference: CRU/18/049 Date Published: 23/03/2018

More information

Tier 1 Compensation Education

Tier 1 Compensation Education Tier 1 Compensation Education January 5, 2015 Problem Statement Tier 1 synch reserves are credited at the synch reserve market clearing price when the non-synch reserve market clearing price is above $0.

More information

DS3 System Services Protocol Interim Arrangements

DS3 System Services Protocol Interim Arrangements DS3 System Services Protocol Interim Arrangements DS3 System Services Implementation Project August 2017 Version 2.1 Contents 1 Introduction... 3 2 Governance... 5 3 Compliance Requirements... 6 4 Performance

More information

Comments of CalPeak Power, LLC and Malaga Power, LLC on CAISO s Bidding Rules Enhancements Straw Proposal,

Comments of CalPeak Power, LLC and Malaga Power, LLC on CAISO s Bidding Rules Enhancements Straw Proposal, Comments of CalPeak Power, LLC and Malaga Power, LLC on CAISO s Bidding Rules Enhancements Straw Proposal, dated April 22, 2015 Comments Only on Questions Relating to FERC Order 809 Submitted May 6, 2015

More information

SURPLUS ENERGY PURCHASE AGREEMENT PARALLEL CUSTOMER GENERATION CGS 8 WISCONSIN AGGREGATE RENEWABLE CAPACITY OF 20 KILOWATTS OR LESS

SURPLUS ENERGY PURCHASE AGREEMENT PARALLEL CUSTOMER GENERATION CGS 8 WISCONSIN AGGREGATE RENEWABLE CAPACITY OF 20 KILOWATTS OR LESS SURPLUS ENERGY PURCHASE AGREEMENT PARALLEL CUSTOMER GENERATION CGS 8 WISCONSIN AGGREGATE RENEWABLE CAPACITY OF 20 KILOWATTS OR LESS This Agreement made this day of, by and between Wisconsin Electric Power

More information

CUSC Modification Proposal Form CMP259

CUSC Modification Proposal Form CMP259 CUSC Modification Proposal Form CMP259 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Clarification of decrease in TEC as a Modification Submission Date 20 January 2016

More information

Proposed Reserve Market Enhancements

Proposed Reserve Market Enhancements Proposed Reserve Market Enhancements Energy Price Formation Senior Task Force December 14, 2018 Comprehensive Reserve Pricing Reform The PJM Board has determined that a comprehensive package inclusive

More information

FILED 11/02/ :33 AM ARCHIVES DIVISION SECRETARY OF STATE & LEGISLATIVE COUNSEL

FILED 11/02/ :33 AM ARCHIVES DIVISION SECRETARY OF STATE & LEGISLATIVE COUNSEL OFFICE OF THE SECRETARY OF STATE DENNIS RICHARDSON SECRETARY OF STATE LESLIE CUMMINGS DEPUTY SECRETARY OF STATE PERMANENT ADMINISTRATIVE ORDER PUC 8-2018 CHAPTER 860 PUBLIC UTILITY COMMISSION ARCHIVES

More information

COMPARISION OF OFFSHORE REQUIREMENTS

COMPARISION OF OFFSHORE REQUIREMENTS Key to Table COMPARISION OF OFFSHORE REQUIREMENTS (Comparison based on GB Grid Code Issue 4 Revision 13 only and ENSTO - E RFG Internal Version dated 26 June 2012) (Note Does not include other Industry

More information

All Energy 2015 CfD: The New Normal?

All Energy 2015 CfD: The New Normal? All Energy 2015 CfD: The New Normal? Sarah-Jane McArthur, Associate 6 May 2015 Key Themes CfD 101 Reflections on allocation process Reflections on the auction outcome What next for the winners What next

More information

HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology

HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology + HVDC component of Transpower s proposed variation to the Transmission Pricing Methodology Decisions and reasons 14 August 2015 932889v7 Contents 1. Introduction 1 2. The Authority has decided to proceed

More information

Councilofthe EuropeanUnion Brussels,30January2015 (OR.en)

Councilofthe EuropeanUnion Brussels,30January2015 (OR.en) ConseilUE Councilofthe EuropeanUnion Brussels,30January2015 (OR.en) InterinstitutionalFile: 2014/0011(COD) PUBLIC 5637/15 LIMITE CLIMA6 ENV27 MI42 IND11 ENER17 ECOFIN48 TRANS35 COMPET17 CODEC108 NOTE From:

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (1) Section 1.10 Could the Evaluation Team elaborate on what types of changes constitute a new project, including listing additional examples? For example, we have assumed that

More information

Standard Development Timeline

Standard Development Timeline PRC 012 2 Remedial Action Schemes Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

4.2 Definitions In this Clause 4 and Schedule E the following terms shall have the meanings ascribed to them below:-

4.2 Definitions In this Clause 4 and Schedule E the following terms shall have the meanings ascribed to them below:- 4. BLACK START CAPABILITY [Note: this clause will need substantial amendment to reflect the circumstances of any individual case, for example the type of Black Start Plant, use of distillate fuel, whether

More information

Decision on Electricity Network Connection Policy

Decision on Electricity Network Connection Policy Decision on Electricity Network Connection Policy DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/09/138 25 August 2009 John Orme (distribution@cer.ie) The Commission for Energy

More information

Comment on issues raised by Committee members on 21 April 2010

Comment on issues raised by Committee members on 21 April 2010 Electricity Industry Bill Comment on issues raised by Committee members on 21 April 2010 1. This note provides further comment on a number of issues raised by Committee members on Wednesday 21 April. 2.

More information

EXCERPTS from the SAMS-SPCS SPS Technical Reference

EXCERPTS from the SAMS-SPCS SPS Technical Reference Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity

More information

NPCC Regional Reliability Reference Directory # 5 Reserve

NPCC Regional Reliability Reference Directory # 5 Reserve NPCC Regional Reliability Reference Directory # 5 Task Force on Coordination of Operations Revision Review Record: December 2 nd, 2010 October 11 th, 2012 Adopted by the Members of the Northeast Power

More information

DRAFT STCP 18-1 Issue 004 Connection and Modification Application

DRAFT STCP 18-1 Issue 004 Connection and Modification Application STCP 18-1 Connection and Modification Application Draft Issue 004 - June 2014 DRAFT STCP 18-1 Issue 004 Connection and Modification Application STC Procedure Document Authorisation Party Name of Party

More information

Community Solar Rate Rider: Schedule No February 13, 2018

Community Solar Rate Rider: Schedule No February 13, 2018 Community Solar Rate Rider: Schedule No. 500 February 13, 2018 1 Community Solar Agenda Design Principles Program Highlights Pricing Methodology Example Customer Impact Conclusion Next Steps 2 Design Principles

More information

ISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules

ISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules Original Sheet No. 637 ISO TARIFF APPENDIX L Rate Schedules Original Sheet No. 638 Schedule 1 Grid Management Charge The Grid Management Charge (ISO Tariff Section 8.0) is a formula rate designed to recover

More information

Loss of Transmission Access Compensation Guidance Note for Customers

Loss of Transmission Access Compensation Guidance Note for Customers Loss of Transmission Access Compensation Guidance Note for Customers This document has been produced to complement the Loss of Transmission Access Compensation Claim Form. Both the claim form and this

More information

Application instruction for the maintenance of frequency controlled reserves

Application instruction for the maintenance of frequency controlled reserves Appendix 2 to the Yearly Agreement and Hourly Market Agreement for Frequency Controlled Normal Operation Reserve and Frequency Controlled Disturbance Reserve Valid as of 1 January 2017 Unofficial translation

More information

Consultation Paper. Draft Regulatory Technical Standards

Consultation Paper. Draft Regulatory Technical Standards JC 2018 15 04 May 2018 Consultation Paper Draft Regulatory Technical Standards Amending Delegated Regulation (EU) 2016/2251 on risk-mitigation techniques for OTC-derivative contracts not cleared by a CCP

More information

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Department of Market Monitoring White Paper Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Revised: November 21, 2011 Table of Contents 1 Executive

More information

P294 Addition of Offshore Transmission System and OTSUA to the definition of the Total System

P294 Addition of Offshore Transmission System and OTSUA to the definition of the Total System Stage 03: Assessment Report What stage is this document in the process? Addition of Offshore Transmission System and OTSUA to the definition of the Total System Amend the BSC definition of Total System

More information

Generation Licence Compliance

Generation Licence Compliance An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Generation Licence Compliance Guidance Notes for Licence Holders Version 1 August 2012 0 www.cru.ie Table of Contents Table of Contents...

More information

Following Industry Consultation

Following Industry Consultation Report to Authority Proposed Revisions to the Balancing Principles Statement, Balancing Services Adjustment Data Methodology Statement, Procurement Guidelines, System Management Action Flagging Methodology

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

Business Combinations (Topic 805)

Business Combinations (Topic 805) Proposed Accounting Standards Update Issued: February 14, 2019 Comments Due: April 30, 2019 Business Combinations (Topic 805) Revenue from Contracts with Customers Recognizing an Assumed Liability a consensus

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

Managing Locational Price Risk: Options

Managing Locational Price Risk: Options Managing Locational Price Risk: Options Session 2, 29 October 2009 Tim Street Grant Read (EGR Consulting) Alistair Dixon (KEA3) Agenda Background Problem definition Options Evaluation Initial preferred

More information

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT Issue #2 1 April 2013 National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA Website:

More information

COMMISSION DELEGATED REGULATION (EU) /... of amending Delegated Regulation (EU) No 231/2013 as regards safe-keeping duties of depositaries

COMMISSION DELEGATED REGULATION (EU) /... of amending Delegated Regulation (EU) No 231/2013 as regards safe-keeping duties of depositaries EUROPEAN COMMISSION Brussels, 12.7.2018 C(2018) 4377 final COMMISSION DELEGATED REGULATION (EU) /... of 12.7.2018 amending Delegated Regulation (EU) No 231/2013 as regards safe-keeping duties of depositaries

More information

Independent Electricity System Operator Licence EI

Independent Electricity System Operator Licence EI Licence Valid Until September 25, 2033 Original signed by Peter Fraser Vice President, Industry Operations & Performance Ontario Energy Board Date of Issuance: September 26, 2013 Date of Amendment: July

More information

Financial Reporting Matters

Financial Reporting Matters Financial Reporting Matters March 2009 Issue 26 AUDIT In this issue, we discuss some of the accounting issues to consider as entities prepare for their 31 March 2009 quarterly or year-end financial reporting.

More information

Final Draft Regulatory Technical Standards

Final Draft Regulatory Technical Standards JC 2018 77 12 December 2018 Final Draft Regulatory Technical Standards Amending Delegated Regulation (EU) 2016/2251 on risk-mitigation techniques for OTC derivative contracts not cleared by a central counterparty

More information

POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES

POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: November 2016 INCIDENT CLASSIFICATIONS Classification

More information

Engagement between external auditors and supervisors and commencing the PRA s disciplinary powers over external auditors and actuaries

Engagement between external auditors and supervisors and commencing the PRA s disciplinary powers over external auditors and actuaries Policy Statement PS1/16 Engagement between external auditors and supervisors and commencing the PRA s disciplinary powers over external auditors and actuaries January 2016 Prudential Regulation Authority

More information

Transpower capex input methodology review

Transpower capex input methodology review ISBN no. 978-1-869456-35-1 Project no. 14.09/16274 Public version Transpower capex input methodology review Decisions and reasons Date of publication: 29 March 2018 2 Associated documents Publication date

More information

CESR Level 3 Guidelines on MiFID Transaction Reporting. Feedback Statement THE COMMITTEE OF EUROPEAN SECURITIES REGULATORS.

CESR Level 3 Guidelines on MiFID Transaction Reporting. Feedback Statement THE COMMITTEE OF EUROPEAN SECURITIES REGULATORS. THE COMMITTEE OF EUROPEAN SECURITIES REGULATORS Ref.: CESR/07-319 CESR Level 3 Guidelines on MiFID Transaction Reporting Feedback Statement May 2007 11-13 avenue de Friedland - 75008 PARIS - FRANCE - Tel.:

More information

Qualifying Facility Avoided Cost Procedures

Qualifying Facility Avoided Cost Procedures I.P.U.C. No. 1 Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF IDAHO Qualifying Facility Avoided Cost Procedures PREFACE: 1. The process outlined in this Schedule

More information

6 Rebalancing Auctions

6 Rebalancing Auctions 6 Rebalancing Auctions This section addresses the rebalancing auctions that will enable the AESO to purchase additional capacity and provide opportunities for capacity assets to either increase or reduce

More information

Liquidity Policy. Prudential Supervision Department Document BS13. Issued: January Ref #

Liquidity Policy. Prudential Supervision Department Document BS13. Issued: January Ref # Liquidity Policy Prudential Supervision Department Document Issued: 2 A. INTRODUCTION Liquidity policy and the Reserve Bank s objectives 1. This Liquidity Policy sets out the Reserve Bank of New Zealand

More information

Available To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon.

Available To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon. FACILITIES OF GREATER THAN 10,000 KW Page 1 Available To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon. Applicable For power purchased from Qualifying

More information

Wholesale market information

Wholesale market information Wholesale market information Review of disclosure regime Consultation paper Submissions close: 3 October 2017 8 August 2017 Executive summary The Electricity Authority (Authority) is reviewing the disclosure

More information

5000 PUBLIC PERSONAL INJURY COMPENSATION PLANS

5000 PUBLIC PERSONAL INJURY COMPENSATION PLANS 5000 PUBLIC PERSONAL INJURY COMPENSATION PLANS Page 5001 TABLE OF CONTENTS 5000 PUBLIC PERSONAL INJURY COMPENSATION PLANS 5001 5100 Scope... 5003 5200 Extension of scope... 5004 5300 General... 5005 5310

More information

All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2

All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2 All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission

More information

Suspending the Implementation of the Zonal Allocation of Transmission Losses

Suspending the Implementation of the Zonal Allocation of Transmission Losses Draft MODIFICATION REPORT for Modification Proposal P156 Suspending the Implementation of the Zonal Allocation of Transmission Losses Prepared by: Modification Group Date of issue: 22.01.04 Document reference:

More information

PRC Remedial Action Schemes

PRC Remedial Action Schemes PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable

More information

Unofficial Comment Form Emergency Operations EOP-004-4

Unofficial Comment Form Emergency Operations EOP-004-4 2015-08 Emergency Operations EOP-004-4 Do not use this form for submitting comments. Use the electronic form to submit comments on Project 2015-08 Emergency Operations; EOP-004-4 Event Reporting. The electronic

More information

Multiple Frequency Keepers Project Plan

Multiple Frequency Keepers Project Plan Multiple Frequency Keepers Project Plan Prepared by Mike Collis Project number: CQ01 Date: September 2009 Version: 1.0 601068-1_Multiple Frequency Keepers - Project Plan A 2 November 2010 3.07 p.m. Document

More information

General Conditions of Contract for Civil Works

General Conditions of Contract for Civil Works General Conditions of Contract for Civil Works Dear Sir/Madam, MODEL CONTRACT FOR WORKS Date Ref.: / / [INSERT PROJECT NUMBER AND TITLE] The United Nations Development Programme (hereinafter referred to

More information

CONTACT(S) Roberta Ravelli +44 (0) Hagit Keren +44 (0)

CONTACT(S) Roberta Ravelli +44 (0) Hagit Keren +44 (0) STAFF PAPER IASB meeting October 2018 Project Paper topic Insurance Contracts Concerns and implementation challenges CONTACT(S) Roberta Ravelli rravelli@ifrs.org +44 (0)20 7246 6935 Hagit Keren hkeren@ifrs.org

More information

(Blackline) VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL

(Blackline) VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL VOLUME NO. III Page No. 878 SCHEDULING PROTOCOL VOLUME NO. III Page No. 879 SCHEDULING PROTOCOL Table of Contents SP 1 SP 1.1 OBJECTIVES, DEFINITIONS AND SCOPE Objectives SP 1.2 Definitions SP 1.2.1 Master

More information

LCIV Proposed Strategy for Consultation. January 2018

LCIV Proposed Strategy for Consultation. January 2018 LCIV Proposed Strategy for Consultation January 2018 Contents Introduction Page 3 Background Page 4 Executive Summary Page 5 Consultation Process Page 6 Governance Page 9 Client Page 12 Investment Page

More information

) ) ) ) ) ) ) ) ) ) ) ) PCAOB Release No March 9, 2004

) ) ) ) ) ) ) ) ) ) ) ) PCAOB Release No March 9, 2004 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8430 www.pcaobus.org PROPOSED AUDITING STANDARD CONFORMING AMENDMENTS TO PCAOB INTERIM STANDARDS RESULTING FROM THE

More information

Support regimes for offshore wind in Europe Florian Bauernfeind

Support regimes for offshore wind in Europe Florian Bauernfeind Winter Academy 2018 Trading, Sales and Financing in the European Energy Market and Industry Support regimes for offshore wind in Europe Florian Bauernfeind Vattenfall Agenda 1. Wind Power in Vattenfall

More information

5000 Public Personal Injury Compensation Plans

5000 Public Personal Injury Compensation Plans 5000 Public Personal Injury Compensation Plans Page 5001 Table of Contents 5000 Public Personal Injury Compensation Plans.5001 5100 Scope... 5003 5200 Valuation for Financial Reporting Purposes... 5004

More information

DISTRIBUTED GENERATION SERVICE RIDER. DESCRIPTION CODE Distributed Generation Service Rider C

DISTRIBUTED GENERATION SERVICE RIDER. DESCRIPTION CODE Distributed Generation Service Rider C Page 1 of 6 DISTRIBUTED GENERATION SERVICE RIDER DESCRIPTION RATE CODE 32-931 C RULES AND REGULATIONS: Terms and conditions of this electric rate schedule and the General Rules and Regulations govern use

More information

Policy Statement PS11/18 Resolution planning: MREL reporting. June 2018

Policy Statement PS11/18 Resolution planning: MREL reporting. June 2018 Policy Statement PS11/18 Resolution planning: MREL reporting June 2018 Policy Statement PS11/18 Resolution planning: MREL reporting June 2018 Bank of England 2018 Prudential Regulation Authority 20 Moorgate

More information

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex Southern Companies Attachment J (LGIP), Page 1 ATTACHMENT J STANDARD LARGE GENERATOR INTERCONNECTION PROCEDURES (LGIP) including STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) Southern Companies

More information

2014 Price Review Business Plan Supporting Appendices Change Protocol. Published 2 December 2013

2014 Price Review Business Plan Supporting Appendices Change Protocol. Published 2 December 2013 2014 Price Review Business Plan Supporting Appendices Published 2 December 2013 2 Contents Page Section 1. Introduction... 3 Section 2. Mechanism for implementing the change protocol... 3 Section 3. The

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances?

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances? Questions for respondents Question 1 What information about the entity s rate-regulated activities and the rate-regulatory environment do you think preparers of financial statements need to include in

More information

OUTPUT CLASS 1 POLICY ADVICE OUTPUT DELIVERY TARGETS

OUTPUT CLASS 1 POLICY ADVICE OUTPUT DELIVERY TARGETS OUTPUT CLASS 1 POLICY ADVICE OUTPUT DELIVERY TARGETS Performance Delivery and Measurement Document 2011/12 Page 1 of 16 Output 1.1 Policy Advice in Relation to Tax and Social Policy Performance Measures

More information

UNC 0680: UNC Changes as a Consequence of no deal United Kingdom Exit from the European Union. UNC Modification

UNC 0680: UNC Changes as a Consequence of no deal United Kingdom Exit from the European Union. UNC Modification UNC Modification At what stage is this document in the process? UNC 0680: UNC Changes as a Consequence of no deal United Kingdom Exit from the European Union Purpose of Modification: A number of minor

More information

SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED

SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED Attachment E to Notice of Revised Proposed Amendments to the System Code and the Distribution System Code August 23, 2018 EB-2016-0003 SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED Below is a high level

More information

Unlocking grid flexibility:

Unlocking grid flexibility: Jan Vorrink TenneT at a glance 2017 Europe's first cross-border grid operator 4,068 Employees EBIT 897 (EUR million) Assets 20.4 (EUR billion) Investments (2018-2028) 28 (EUR billion) Connected offshore

More information

Supplemental Balancing Reserve

Supplemental Balancing Reserve Supplemental Balancing Reserve From Forecasting to Despatch Pete Chandler Control Implementation Manager SBR Units Contracted Long notice start up required Eggborough 52 Hours Fiddlers Ferry 26 Hours South

More information

Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs

Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs The Hawaiian Electric Companies 1 process for developing their draft request for proposals ( RFP ) for Firm Capacity

More information

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. First Revision of Sheet No. 38.1 P.S.C.U. No. 50 Canceling Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF UTAH Qualifying Facility Procedures PREFACE: 1. The process

More information

Costs considered in assessing whether a contract is onerous (IAS 37) Items on the current agenda

Costs considered in assessing whether a contract is onerous (IAS 37) Items on the current agenda STAFF PAPER IFRS Interpretations Committee Meeting November 2017 Project Paper topic Costs considered in assessing whether a contract is onerous (IAS 37) Items on the current agenda CONTACT(S) Craig Smith

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 33 Hour-Ahead Scheduling Process (HASP)... 2 33.1 Submission Of Bids For The HASP And RTM... 2 33.2 The HASP Optimization... 3 33.3 Treatment Of Self-Schedules In HASP... 3 33.4 MPM For

More information

Supply Participation. 2.1 Prequalification applications. Rationale

Supply Participation. 2.1 Prequalification applications. Rationale Supply Participation Rationale 2.1 Prequalification applications Prequalification of existing versus new capacity assets 2.1.1 In order to participate in the Alberta capacity market, a new capacity asset

More information

Product disclosure: Retail investment changes to reflect RDR Adviser Charging and to improve pension scheme disclosure

Product disclosure: Retail investment changes to reflect RDR Adviser Charging and to improve pension scheme disclosure Product disclosure: Retail investment changes to reflect RDR Adviser Charging and to improve pension scheme disclosure The ABI s response to CP11/3 1. The Association of British Insurers (ABI) is the voice

More information

Consultation Paper Review of the technical standards on reporting under Article 9 of EMIR

Consultation Paper Review of the technical standards on reporting under Article 9 of EMIR Consultation Paper Review of the technical standards on reporting under Article 9 of EMIR 10 November 2014 ESMA/2014/1352 Date: 10 November 2014 ESMA/2014/1352 Annex 1 Responding to this paper ESMA invites

More information

REASONS FOR DECISION. January 16, 2014 BEFORE:

REASONS FOR DECISION. January 16, 2014 BEFORE: Page 1 of 20 IN THE MATTER OF BRITISH COLUMBIA HYDRO AND POWER AUTHORITY MANDATORY RELIABILITY STANDARDS ASSESSMENT REPORT NO. 6 AND THE DETERMINATION OF RELIABILITY STANDARDS FOR ADOPTION IN BRITISH COLUMBIA

More information

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018

DE MINIMIS ACCEPTANCE THRESHOLD (DMAT) AND CONTINUOUS ACCEPTANCE DURATION LIMIT (CADL) REVIEW 2018 PAPER NAME De Minimis acceptance Threshold (DMAT) and Continuous Acceptance Duration Limit (CADL) Review Target Audience Purpose of paper Deadline for responses Contact name and details BSC Parties For

More information

PUBLIC BENEFIT ENTITY STANDARDS. IMPACT ASSESSMENT FOR PUBLIC SECTOR PBEs

PUBLIC BENEFIT ENTITY STANDARDS. IMPACT ASSESSMENT FOR PUBLIC SECTOR PBEs PUBLIC BENEFIT ENTITY STANDARDS IMPACT ASSESSMENT FOR PUBLIC SECTOR PBEs Prepared June 2012 Issued November 2013 This document contains assessments of the impact for public sector PBEs of transitioning

More information