10.0 NAM THEUN 2 ISSUES

Size: px
Start display at page:

Download "10.0 NAM THEUN 2 ISSUES"

Transcription

1 10.0 NAM THEUN 2 ISSUES 10.1 Scope of Nam Theun 2 Issues The Nam Theun 2 PPA and concession agreement have been executed and these documents contractually commit GOL, EGAT and NTPC to the key parameters of the present project layout and design. The Nam Theun 2 issues explored under the PSDP are based on the NTPC concept design, with some comparisons being made to the earlier 681 MW project configuration. The TOR defines specific tasks in relation to the Nam Theun 2 Hydroelectric Project; they are to: (i) (ii) Evaluate alternative reservoir Full Supply Levels (FSLs) Compare Nam Theun 2 with alternative power projects and determine: whether the power EdL receives from Nam Theun 2 as domestic offtake will be at lower cost than the power from alternative projects; and whether the revenues paid by NTPC to GOL and EdL as taxes, royalties and dividends will be greater than corresponding revenues from alternative projects. (iii) Determine how long it will take for the domestic off-take allocation from Nam Theun 2 of 300 GWh per annum to be fully absorbed by the Lao power system Comparison of Full Supply Levels Effect of FSL on Economic Performance The economic performance of the Nam Theun 2 project was simulated across a range of FSLs and the trade-off between economic and environmental attributes was examined. The NTPC concept design configuration (FSL = 538 masl) is the reference case and the effect of reducing the size of the reservoir was simulated using EVALS. The relationship between economic performance and FSL is reported in Table 10.1 in terms of annual energy production and generation cost as a percentage of the NTPC reference case. Final Report Vol A: Main Report 224

2 Table 10.1: Nam Theun 2 Comparison of FSLs FSL (m asl) Reservoir Area (km 2 ) Volume (mcm) Installed Capacity (MW) Energy Generation (GWh pa) Relative Project Cost (%) Relative Generation Cost (%) 1/ ,898 (100%) ,218 (88%) ,674 (79%) ,544 (77%) ,357 (74%) NOTES: 1/ Based on weighted average generation cost. 2/ Energy outputs are adjusted for reduced generation at Theun Hinboun (210 MW) It can be seen that the cost of generation increases sharply as FSL is lowered. The generation cost at RL 532 masl is 36% higher than the reference case and FSLs below this level were not considered further in the analysis of trade-offs between economic and environmental attributes. Three project alternatives were shortlisted for further study from some 80 variants examined initially under the Nam Theun 2 Study of Alternatives (Lahmeyer/Worley, 1998). The shortlisted project layouts are: 1. Reference case as proposed by NTPC (FSL = 538 masl) 2. Run-of-river case (FSL = 532 masl) 3. Ban Signo case with the dam moved upstream (FSL = 538 masl) The PSDP analysis of these three cases draws on the work conducted initially under the Nam Theun 2 Study of Alternatives, and updates it to incorporate additional information now available and reflect changes to the installed capacity of the project Run-of-River Case The run-of-river layout involves a significantly smaller reservoir (FSL of 532 masl). This would have a number of social and environmental benefits: The area inundated at a FSL of 532 masl would be substantially reduced, with the reservoir covering only 40 km 2 or less than 10% of the NTPC case); The length of river inundated would be about 25% of the NTPC case; The regulation effect on the Nam Theun would be less and more water would spill downstream, slightly reducing biodiversity impacts in that reach; Flood levels in the Nam Theun would be higher than the natural condition due to the diversion weir and communities living adjacent to the river would still be affected. About 1000 people would need to be resettled, compared with 6,000 for the NTPC case; Final Report Vol A: Main Report 225

3 Fisheries yields from the smaller reservoir would be less than those expected from the NTPC reservoir but downstream fisheries might benefit slightly from the increased spill in the downstream reach; Project impacts on terrestrial biodiversity would be reduced due to the smaller area of inundation; Two thirds of the Nakai wetlands would be preserved; With less water diverted through the turbines, effects in the Xe Bang Fai would be reduced slightly. Although the social and environmental advantages of the smaller reservoir are significant, they are associated with a 36% increase in the cost of generation. Such a change would fundamentally affect the viability of the project under current market conditions. It is difficult to see how the project with a reservoir FSL of RL 532 masl could simultaneously meet the EGAT avoided cost tariff ceiling and investors minimum rate of return criteria Ban Signo Case The Ban Signo variant has the same FSL as the NTPC reference case but moving the dam to a site about 10 km upstream reduces impacts. Two variants of the Ban Signo case were investigated one with the same installed capacity as the NTPC proposal and one with the same ICF (equivalent to an installed capacity of 945 MW). The principal social benefit of moving the dam upstream to Ban Signo is a reduction of 413 (or 9%) in the number of people resettled. 63 From an environmental perspective, the reservoir area would reduce by 137 km 2 (30%). Of this area, about 100 km 2 is degraded by logging but 20 km 2 of pristine forest would be saved, i.e. about 2% of this forest type in the NBCA and about 10% of that found at low elevations. With a smaller reservoir, the Ban Signo dam would also be associated with a marginal increase in downstream flows and the aquatic ecology might benefit from this. The corollary is that fisheries in the smaller reservoir would be reduced marginally. There are no wetlands in the reach between the NTPC dam site and Ban Signo and therefore the move will not alleviate wetlands impacts. A comparison of the economic benefits of the NTPC and Ban Signo cases is presented in Table It indicates that the trade-off for the social and environmental gains would be a 20% higher cost of generation, an increase that could undermine the viability of the project under current market conditions. Further concessions in taxes and royalties could be made to help early cash flow and debt service but this would cut into GOL s revenue stream and bring into question the whole basis for pursuing the project. 63 Provided WCD standards are adhered to, people resettled should be better off than before and it could be argued that the reduction in resettlement is also a reduction in non-monetary project benefits. Final Report Vol A: Main Report 226

4 Table 10.2: Nam Theun 2 - Comparison of NTPC and Ban Signo Cases Alternative Installed Capacity (MW) Annual Energy (GWh) Basic Cost (mus$) Generation Costs Average ( /kwh) Weighted ( /kwh) NTPC dam site Ban Signo dam site same ICF (-12%) (-15%) (0%) (+17%) (+17%) Ban Signo dam site same capacity (MW) (0%) (-12%) (+8%) (+22%) (+21%) Again, the Ban Signo case is associated with social and environmental gains but they are not as extensive as would appear on first inspection. The downside is an increase in the cost of generation of about 20% and such an increase would be difficult to reconcile with EGAT s avoided cost tariff ceiling and investors minimum rate of return criteria Comparison of Benefits from Nam Theun Scope of Benefits Review The PSDP TOR seeks confirmation that: (i) the power EdL receives from Nam Theun 2 as domestic off-take will cost less than the power from alternative projects; and (ii) the revenues paid by NTPC to GOL and EdL as taxes, royalties and dividends will be greater than corresponding revenues from alternative projects. These issues were investigated using project simulations as necessary and the conclusions are reported in the following sections Least Cost Domestic Supply In relation to the matter of the price of domestic off-take from Nam Theun 2, the price paid by EdL for power from an export IPP project such as Nam Theun 2 is tied to the opportunity cost of that power to the project company, i.e. the revenue foregone by the project company for each unit of output sold to EdL rather than the foreign offtaker. In general terms, the revenue foregone will be equal to the export tariff as adjusted to take account of transmission loss differentials and wheeling costs. The export tariff is determined, in turn, by negotiation based on avoided cost within the foreign off-taker s system at the time the tariff was negotiated (refer Section 5.8). This general proposition assumes that the quality of the traded energy is the same for the domestic and foreign purchasers and, more particularly, that the terms governing the contractual commitment to supply are the same, i.e. firm / non-firm, liquidated damages, etc. In the specific case of Nam Theun 2, the level of supply commitment is different in detail and this is reflected in differences in the value and structure of the EGAT and EdL tariffs. Final Report Vol A: Main Report 227

5 The domestic off-take tariffs from other candidate export projects are not yet fixed and therefore firm comparisons with Nam Theun 2 cannot be made. However, one can speculate that the same tariff setting imperatives will apply and that, regardless of the project, the wholesale tariff paid by EdL will reflect the avoided cost in the foreign purchaser s system, be it EGAT or EVN. Thus, comparisons between the domestic off-take tariffs of Nam Theun 2 and other projects are not particularly relevant. The characteristics of a project determine whether it will proceed, not the value of the tariff it receives. The value of tariff depends more on the characteristics of the buyer s system and the skills of the negotiating teams. To determine whether Nam Theun 2 will provide least-cost domestic power, it then remains to be seen whether domestic off-take is cheaper than power generated by projects built exclusively for supply to EdL. This will depend on the characteristics of the competing domestic project and its financing terms. Table 10.3 presents a comparison between the Nam Theun 2 tariff and the calculated costs of production from shortlisted domestic projects. The Nam Theun 2 and Theun Hinboun off-take tariffs are based on the rates specified in their respective PPAs. For the other projects, the lowest tariff that would achieve a return on equity of 17% (nominal) is used (refer Table 9.3). The tariffs in Table 9.3 and the Nam Theun 2 and Theun Hinboun PPA rates are not comparable as the Table 9.3 rates quote only the primary energy tariff and do not account for the portion of output paid at the lower secondary energy rate (modelled at 56% of the primary energy tariff). To give greater meaning to the Table 10.3 comparison, the non-ppa tariffs are presented as weighted combined tariffs, calculated according to the proportion of primary and secondary energy produced by a project in an average year. The comparison of tariffs confirm the intuitive position that Nam Theun 2 domestic offtake is competitive when compared with Lao-based generation, whether it is sourced as domestic allocations from primarily export projects or as output from domestic projects developed under commercial terms. However, domestic projects developed with concessional finance might well produce cheaper output if projects are carefully selected, and proper procurement standards apply GOL Revenues from Nam Theun 2 Export Sales The TOR asks whether the GOL receipts over the lifetime of the project will be greater than those generated by other projects. GOL receipts from IPP projects come in the form of taxes, royalties and dividends. Dividends deriving from GOL s equity in the project are paid to the agency nominated by GOL to hold the shares EdL in the case of Theun Hinboun and Houay Ho. The strength of the GOL revenue stream depends on a number of factors including average annual generation, tariff, GOL equity share and concession terms (taxes and royalties). The earnings potential of Nam Theun 2 has been demonstrated by a number of consultants including Louis Berger, Credit Agricole Indosuez and Lahmeyer/Worley. The Lahmeyer/Worley studies 64 used financial modeling of Nam Theun 2 and competing candidates based on actual and assumed tariffs and concession terms to quantify and compare the respective GOL revenue streams. 64 Nam Theun 2 Study of Alternatives (Lahmeyer/Worley, 1998) and Hydropower Development Strategy Study (Worley/Lahmeyer, 2000) Final Report Vol A: Main Report 228

6 Table 10.3: Nam Theun 2 EdL Tariff - Comparison with Domestic Generation Project MW Financial Weighted Tariff 1/ ( /kwh) Comments Nam Theun Tariff in EdL PPA, levelized in 2003 dollars Theun Hinboun Exp Current EdL off-take tariff from THB Thakho Mainstream Mekong, counter-seasonal 2/ Nam Sane Large resettlement problem Nam Ngiep Includes generation from reg. dam H. Lamphan Gnai Nam Sim Large proportion of secondary energy Nam Pot Xe Katam Run-of-river mainly secondary energy Nam Ngum Nam Long Nam Bak 2B Modeled as a storage project 1/ Unless otherwise specified in the Comments column, the quoted tariff is the weighted combined tariff for primary and secondary energy tariff calculated in financial terms to equate to the levelized tariff specified in the Nam Theun 2 EdL PPA. The primary and secondary tariffs were those required to achieve a 17% nominal return on equity and minimum debt service coverage of around / Thakho is run-of-river and produces predominantly secondary energy but it is counter-seasonal, producing most of its energy in the dry season and its output is therefore valued at primary energy rates. Also, although attractive in a financial sense, the potential economic impacts are difficult to assess and it is penalized heavily in an economic / SESAMEE evaluation. In the time since these studies were done, many of the frontline candidates have been overtaken by events. Some have not progressed since the onset of the Asian Economic Crisis seven years ago. Nam Theun 2, Nam Mo and Xe Kaman 3, though, have formal standing in the power development plans of EGAT or EVN and it is understood that the prospects for Theun Hinboun Expansion are bright. The status of the developer groups, tariff agreements and concession terms of other projects are in doubt and the revenue comparisons are therefore based on a standardized set of assumptions rather than on lapsed or neglected agreements (refer Annex 4.3). The comparison of benefits of Nam Theun 2 with other candidates has been approached from both economic and financial perspectives: (i) Economic Comparison Using EVALS and SESAMEE, an economic study of all shortlisted projects, including Nam Theun 2, was carried out. The economic benefits of projects, as represented by the average and weighted cost of generation, are compared in Tables 6.12 and 6.13 and these establish Nam Theun 2 as the most beneficial candidate by a comfortable margin. Final Report Vol A: Main Report 229

7 (ii) Financial Comparison The financial performances of shortlisted export alternatives were simulated and cash flow projections prepared as described in Section 9. Standard assumptions were used for all projects other than Nam Theun 2, for which the contractually binding tariff and concession conditions were used. A comparison of tax, royalty and dividend streams of the various projects produces a similar finding to the economic evaluation, with the benefits from Nam Theun 2 exceeding those of other candidates (refer Table 10.4). It is evident from the financial analyses that superior characteristics of the Nam Theun 2 site allow more favorable tax and royalty conditions to be negotiated without impairing the project s ability to clear return-on-equity and debt service hurdles. Thus, the benefits from Nam Theun 2 should be greater not only because of the project s larger energy production, but also because GOL is likely to receive more on a per GWh basis. Table 10.4: GOL Net Receipts (nominal) Common Construction Start (2003) Project 2/ Xe Kaman 3 Nam Theun 2 Nam Mo Base Cost 1/ Royalties 10% Taxes 10% Dividends 10% Total GOL Receipts 3/ 10% GOL Receipts (% Base Cost) % % % Xe Kaman % Xe Kong % Nam Ngum 3B % Nam Ngum 2B % 1/ Base cost including SESAMEE environmental and social impacts (positive and negative) 2/ All projects other than Nam Theun 2 modeled according to common set of assumptions as described in Section 9.2. All projects, including Nam Theun 2, modeled on a common COD. 3/ GOL receipts have been estimated using project costs and energy production figures calculated using EVALS. In the case of Nam Theun 2, the official GOL estimate of Nam Theun 2 receipts is based on a more conservative estimate of primary energy production (i.e. 4,406 GWh, versus 4,883 GWh as calculated using EVALS) Absorption of Domestic Off-take Nam Theun 2 is located strategically in the C2.1 supply area and will contribute 300 GWh p.a. to the grid which, by the time of commissioning, will be interconnected to the C1 and C2.2 grids. Demand growth within the central area of Lao PDR is very rapid and will remain so for a few years. Increasing economic activity is boosting demand generally but this is being further boosted by significant new point loads related to the Sepone mine, Nam Theun 2 construction, a cement factory, expanding irrigation and other industrial loads. This growth is currently being met by imports. The optimal power system expansion scenario identified by the SEXSI simulations would restore a balance by interconnecting the C1, C2.1 and C2.2 grids (2005) and by taking output from Theun Hinboun Expansion (from 2008) and Nam Theun 2 (from Final Report Vol A: Main Report 230

8 2010). The SEXSI power system simulations demonstrate that the commissioning of Theun Hinboun Expansion (105 MW) in 2008 would reduce imports to less than 10%. Demand growth from 2008 would see imports rise again but in 2010 the Nam Theun 2 domestic off-take would restore the situation by absorbing the demand growth for the two years between the CODs of the two projects. It therefore follows that the domestic allocation of Nam Theun 2 will be absorbed, if not immediately, then within a short time. Antecedent supply and demand conditions are fundamental to this outcome, with the timing of prior capacity increments and transmission interconnections largely determining the result. If capacity is added to the system before it goes into deficit, surplus power can be sold to Thailand while domestic demand catches up with the augmented system capacity. Such trade would, however, attract only a non-firm energy tariff. The more attractive option from economic and financial perspectives involves a strategy in which a deficit, balanced by imports from Thailand, is allowed to develop in advance of new capacity. In this way, new plant will be employed more fully upon entering commercial service, allowing the economic benefits of investments to be maximized from the outset. Final Report Vol A: Main Report 231

9.0 FINANCIAL EVALUATION OF POWER PROJECTS

9.0 FINANCIAL EVALUATION OF POWER PROJECTS 9.0 FINANCIAL EVALUATION OF POWER PROJECTS 9.1 Objectives of Financial Evaluations The financing of power projects in Asia and elsewhere has been undergoing a transition over the last decade as the participation

More information

Project Finance and Guarantees June Project Finance and Guarantees Group

Project Finance and Guarantees June Project Finance and Guarantees Group Project Finance and Guarantees June Project Finance and Guarantees Group 2005 IDA Guarantee Paves Renewed Interest in Private Hydropower the Nam Theun 2 Project Largest Cross Border Project Financing in

More information

EDL-GENERATION PUBLIC COMPANY

EDL-GENERATION PUBLIC COMPANY EDL-GENERATION PUBLIC COMPANY No. 72/2018 7 June 2018 CORPORATES Company Rating: Issue Ratings: Senior unsecured Outlook: Negative Company Rating History: Date Rating Outlook/Alert 12/06/17 Negative 15/10/14

More information

Lao PDR Development Report 2010 Natural Resource Management for Sustainable Development

Lao PDR Development Report 2010 Natural Resource Management for Sustainable Development Lao PDR Development Report 2010 Natural Resource Management for Sustainable Development TECHNICAL NOTE Fiscal Regime in the Hydro Power Sector This note was prepared by Richard MacGeorge, James B. Stewart,

More information

11 Economic Evaluation

11 Economic Evaluation 11 Economic Evaluation Contents 11.1 Project Decription... 1 11.2 Scope and Methodology of Study... 1 11.3 Basic Assumptions... 2 11.3.1 Construction Period & Commercial Operation Period... 2 11.3.2 Energy

More information

Project Name Nam Theun 2 (NT2) Hydropower Project and the Nam Theun 2 Social and Environment Project (NTSEP) Region

Project Name Nam Theun 2 (NT2) Hydropower Project and the Nam Theun 2 Social and Environment Project (NTSEP) Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) UPDATE: Joint PID for NT2 and NTSEP Report No.: 30967

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:LAO 29284 ASIAN DEVELOPMENT BANK TECHNICAL ASSISTANCE TO ThE LAO PEOPLE'S DEMOCRATIC REPUBLIC FOR ThE CORPORATE AND FINANCIAL DEVELOPMENT OF ELECTRICIT DU LAO LI LI May 1996 - -I CURRENCY EQUIVALENTS

More information

The World Bank Nam Theun 2 Social and Environment Project (P049290)

The World Bank Nam Theun 2 Social and Environment Project (P049290) Public Disclosure Authorized EAST ASIA AND PACIFIC Lao People's Democratic Republic Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2005 Seq No: 10 ARCHIVED on

More information

Nam Theun 2. Board Update: Project Progress during 2012 ADB. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Nam Theun 2. Board Update: Project Progress during 2012 ADB. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Nam Theun 2 Board Update: Project Progress during 2012 ADB Nam Theun 2: Making a Difference

More information

LAO PDR NAM THEUN 2 HYDROELECTRIC PROJECT by Gráinne Ryder

LAO PDR NAM THEUN 2 HYDROELECTRIC PROJECT by Gráinne Ryder LAO PDR NAM THEUN 2 HYDROELECTRIC PROJECT by Gráinne Ryder Probe International Briefing May 28, 1996 PROJECT BACKGROUND In October 1995, the Nam Theun 2 Project developers prepared their own public information

More information

FINANCIAL PERFORMANCE AND PROJECTIONS OF LAO HOLDING STATE ENTERPRISE

FINANCIAL PERFORMANCE AND PROJECTIONS OF LAO HOLDING STATE ENTERPRISE Greater Mekong Subregion Nam Ngum 3 Hydropower Project (RRP LAO 41385) Supplementary Appendix 3 FINANCIAL PERFORMANCE AND PROJECTIONS OF LAO HOLDING STATE ENTERPRISE A. Introduction 1. An assessment of

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (1) Section 1.10 Could the Evaluation Team elaborate on what types of changes constitute a new project, including listing additional examples? For example, we have assumed that

More information

MODEL CA DOMESTIC & EXPORT SALES [ ] HYDROELECTRIC POWER PROJECT CONCESSION AGREEMENT BETWEEN THE GOVERNMENT OF THE LAO PEOPLE S DEMOCRATIC REPUBLIC

MODEL CA DOMESTIC & EXPORT SALES [ ] HYDROELECTRIC POWER PROJECT CONCESSION AGREEMENT BETWEEN THE GOVERNMENT OF THE LAO PEOPLE S DEMOCRATIC REPUBLIC MODEL CA DOMESTIC & EXPORT SALES [ ] HYDROELECTRIC POWER PROJECT CONCESSION AGREEMENT BETWEEN THE GOVERNMENT OF THE LAO PEOPLE S DEMOCRATIC REPUBLIC AND [ ] POWER COMPANY LIMITED [ ] 20[ ] CONCESSION AGREEMENT

More information

Response from the World Bank and ADB (dated 16 December 2016) to Mekong Watch s inquiries

Response from the World Bank and ADB (dated 16 December 2016) to Mekong Watch s inquiries Response from the World Bank and ADB (dated 16 December 2016) to Mekong Watch s inquiries (dated 5 & 23 August 2016) === RE: Request for your attention on the riverbank erosion in Lao PDR s Nam Theun 2

More information

Water Security and Dams Rehab. Workshop

Water Security and Dams Rehab. Workshop Water Security and Dams Rehab. Workshop Dam Rehabilitation: Financial Instruments, O&M and Sustainability 19 September 2017 PRESENTATION OUTLINE The financial instruments, PPP and new instruments and approaches

More information

COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014

COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014 COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014 Problem Set 2 Timing, Scale and Cost of capital Due May 21 @ 16:00 hrs 1 Timing, Scale and Cost of capital 1. Timing A small firm is considering

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK UPDATE ON THE IMPLEMENTATION STATUS OF THE LAO PEOPLE S DEMOCRATIC REPUBLIC NAM THEUN 2 HYDROELECTRIC PROJECT July 2005 ABBREVIATIONS ADB Asian Development Bank AFD Agence Française

More information

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) A. Approach FINANCIAL ANALYSIS 1. Financial analysis of the project was carried out in accordance with the Financial

More information

CASA-1000 Project List of FAQs

CASA-1000 Project List of FAQs 1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan

More information

Trung Son Hydropower Project. Financial Analysis

Trung Son Hydropower Project. Financial Analysis Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Trung Son Hydropower Project Financial Analysis Final Report February

More information

Subscription Document for New Ordinary Shares (Right Offering)

Subscription Document for New Ordinary Shares (Right Offering) Subscription Document for New Ordinary Shares (Right Offering) Of EDL-Generation Public Company Prepared by BECL-KT Securities Public Company Limited 7 th Floor, Lao Securities Exchange Building, Kampaengmeuang

More information

Trouble on the Theun-Hinboun: A Field Report on the Socio-Economic and Environmental

Trouble on the Theun-Hinboun: A Field Report on the Socio-Economic and Environmental 1 of 19 27/12/2011 2:25 PM Back to Mekong Campaign Probe International Home Trouble on the Theun-Hinboun: A Field Report on the Socio-Economic and Environmental Effects of the Nam Theun-Hinboun Hydropower

More information

EDL-Generation Public Company Presentation Thailand Focus 2017

EDL-Generation Public Company Presentation Thailand Focus 2017 EDL-Generation Public Company Presentation Thailand Focus 2017 Table of Contents Lao PDR Overview o Country Overview o Industry Overview o Lao Power Industry EDL-Generation Public Company o EDL-Gen Overview

More information

o RATCH Overview o RATCH Highlights

o RATCH Overview o RATCH Highlights 4th CLSA Corporate Access Forum: 12-14 May 2010 Table of Contents o RATCH Overview o RATCH Highlights Appendix RATCH Overview Company History In February 1999 the Thai Cabinet approved private participation

More information

By Thavichanh Thiengthepvongsa Deputy Director General Investment Promotion Department Ministry of Planning and Investment

By Thavichanh Thiengthepvongsa Deputy Director General Investment Promotion Department Ministry of Planning and Investment By Thavichanh Thiengthepvongsa Deputy Director General Investment Promotion Department Ministry of Planning and Investment Outlines Lao Government Policy PPP Development Status Challenges Answers to Questions

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

Regional Power Market Challenges and Opportunities from Nepalese perspective

Regional Power Market Challenges and Opportunities from Nepalese perspective Regional Power Market Challenges and Opportunities from Nepalese perspective Hitendra Dev Shakya Director, Power Trade Department, Nepal Electricity Authority Outline of the Presentation 1. Energy sector

More information

SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014

SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014 SNOWY HYDRO LIMITED STATEMENT OF CORPORATE INTENT 2014 1. INTRODUCTION This for Snowy Hydro Limited ( Snowy Hydro or the Company ) continues a focus on the continued development and augmentation of Snowy

More information

Public-Private Infrastructure Advisory Facility (PPIAF) Presentation to Financing Renewable Energy Projects Training Program October 11, 2012

Public-Private Infrastructure Advisory Facility (PPIAF) Presentation to Financing Renewable Energy Projects Training Program October 11, 2012 Public-Private Infrastructure Advisory Facility (PPIAF) Presentation to Financing Renewable Energy Projects Training Program October 11, 2012 1 Agenda 1. Structuring PPPs 2. What is PPIAF? 2 Agenda 1.

More information

Introduction to Cost Benefit Analysis (CBA)

Introduction to Cost Benefit Analysis (CBA) Water Resources Management Good Practices and Knowledge Transfer - project component Introduction to Cost Benefit Analysis (CBA) András Kis Basics Why do a CBA? To see if a decision (frequently an investment

More information

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis Contract length analysis for Feed-in Tariff with Contracts for Difference Summary of onshore and offshore wind analysis August 2013 Contract length analysis for Feed-in Tariff with Contracts for Difference

More information

A. Problems with Interim Compensation, Downstream Channel

A. Problems with Interim Compensation, Downstream Channel July 20, 2006 Mr. Jean Foerster Social and Environmental Director Nam Theun 2 Power Company PO Box 5862 Vientiane, LAO PDR By email: jean.foerster@namtheun2.com Dear Mr. Foerster As you are aware, IRN

More information

Lao PDR World Bank Management Mission on the Nam Theun 2 Project AIDE MEMOIRE May 17-18, 2004

Lao PDR World Bank Management Mission on the Nam Theun 2 Project AIDE MEMOIRE May 17-18, 2004 Lao PDR World Bank Management Mission on the Nam Theun 2 Project AIDE MEMOIRE May 17-18, 2004 Introduction A World Bank management mission on the proposed Nam Theun 2 project visited Vientiane during May

More information

Role of Private Sector in the growth of Power Infrastructure in South Asia. Mukunda Paudyal, Joint Secretary, Investment Board, Government of Nepal

Role of Private Sector in the growth of Power Infrastructure in South Asia. Mukunda Paudyal, Joint Secretary, Investment Board, Government of Nepal Role of Private Sector in the growth of Power Infrastructure in South Asia Mukunda Paudyal, Joint Secretary, Investment Board, Government of Nepal Outline of Presentation 1. The case for Private Investment

More information

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL APPENDIX B: PORTFOLIO OPTIMIZATION MODEL PUBLIC UTILITY DISTRICT #1 OF SNOHOMISH COUNTY Prepared by Generation, Power, Rates, and Transmission Management Division Snohomish County PUD DRAFT 2017 Integrated

More information

The World Bank Guarantees

The World Bank Guarantees The World Bank Guarantees Leveraging Private Finance for Emerging Markets Financial Solutions Unit Finance, Economics and Urban Development Department 1 Sustainable Development Network Vice-Presidency

More information

Montecristo Hydroelectric Project

Montecristo Hydroelectric Project Montecristo Hydroelectric Project Answers to Clarifications Required Reference No. UNFCCC 1077 Date: August 22, 2007 2 Montecristo Hydroelectric Project Answers to Clarifications Required Reference No.

More information

Lao PDR World Bank Mission on the Nam Theun 2 Project and Related Matters AIDE MEMOIRE October 28 and 29, 2002

Lao PDR World Bank Mission on the Nam Theun 2 Project and Related Matters AIDE MEMOIRE October 28 and 29, 2002 Lao PDR World Bank Mission on the Nam Theun 2 Project and Related Matters AIDE MEMOIRE October 28 and 29, 2002 Introduction A World Bank mission on the proposed Nam Theun 2 project and related issues led

More information

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS: PROJECT 1 Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy

More information

Excellence. Creativity. Trust Since Membership in Professional Societies: Key Qualifications: Education:

Excellence. Creativity. Trust Since Membership in Professional Societies: Key Qualifications: Education: Name: Position: Location: Experience: Nationality: David D. Doran Founding Partner Bangkok, Thailand Over 20 years Thai; American Curriculum Vitae Membership in Professional Societies: California State

More information

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT Energy Department Government of Bihar 2012 ( 1 ) Table of Content 1. Objective 2. Title and Enforcement 3. Scope and Coverage 4. Nodal Agency 5. Classification

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

Mekong River Commission

Mekong River Commission Mekong River Commission Office of the Secretariat in Phnom Penh (OSP) 576 National Road, # 2, Chak Angre Krom, P.O. Box 623, Phnom Penh, Cambodia Tel. (855-23) 425 353. Fax (855-23) 425 363 Office of the

More information

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P.

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P. Q2 2017 I N T E R I M R E P O R T Brookfield Renewable Partners L.P. OUR OPERATIONS We manage our facilities through operating platforms in North America, Colombia, Brazil, and Europe which are designed

More information

Economic and financial feasibility of PV projects

Economic and financial feasibility of PV projects Economic and financial feasibility of PV projects Monika BIERI Research Associate Solar Energy Research Institute of Singapore (SERIS) National University of Singapore (NUS) SERIS INDUSTRY DAY on PV Quality

More information

BRITISH COLUMBIA DAM SAFETY REGULATION 44/2000

BRITISH COLUMBIA DAM SAFETY REGULATION 44/2000 PDF Version [Printer friendly ideal for printing entire document] BRITISH COLUMBIA DAM SAFETY REGULATION 44/2000 Published by Important: Quickscribe offers a convenient and economical updating service

More information

Development Strategy and Socio-economic Development Framework of Laos

Development Strategy and Socio-economic Development Framework of Laos Development Strategy and Socio-economic Development Framework of Laos Syviengxay Oraboune G-cube/phd14409 Policy Design and Implementation for Developing Country Seminar/Spring 2015 (GRIPS) Outline of

More information

Concession Agreement of IPP

Concession Agreement of IPP Asia 2016 NCC, Vientiane Capital. Lao PDR 1-3 March 2016 Concession Agreement of IPP from the Lao Government s Perspective Xaypaseuth Phomsoupha Director General Department of Energy Business Ministry

More information

BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS

BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS QUESTION 1 Reference: Application, Volume 1, Chapter 1, page 1-7, Tables 1-1 and 1-2 a) Please clarify

More information

Understanding Risk and Preparing the RFP

Understanding Risk and Preparing the RFP Understanding Risk and Preparing the RFP Table of Contents Excerpts from Risk Allocation Primer... A Sample term sheet... B Description of disasters... C Excerpts from Risk Allocation Primer Please note

More information

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis

More information

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner The policy and regulatory aspects of a bankable solar power project Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner Contents 1. The restriction of subsidies and policy priorities. 2.

More information

ANALYST MEETING 1Q11. May 12, 2011

ANALYST MEETING 1Q11. May 12, 2011 ANALYST MEETING 1Q11 May 12, 2011 Agenda Highlights Operation Performance Project Highlights Financial Performance Acquisition Of TSI 2 Highlights 3 Highlights 1Q11 Power Consumption Peak generation was

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (2) Section 1.7.4.1 Can the Evaluation Team provide guidance on the scope and amount of information that could be requested from ISO-NE, and the expected magnitude of any associated

More information

Development of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement

Development of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement Development of the Renewable Dispatchable Generation Model Overview of SEPA & ScottMadden Engagement Speakers John Sterling Senior Director, Advisory Services Smart Electric Power Alliance John Pang Partner

More information

Compendium of State Government Policies on Renewable Energy Sector in India ARUNACHAL PRADESH

Compendium of State Government Policies on Renewable Energy Sector in India ARUNACHAL PRADESH 85 ARUNACHAL PRADESH Small Hydro Power Policy- 2007 Dated 24 th January, 2008 & Amendment Dated 13 th Oct. 2008 1. Order PWRS/HPD/W-1305/2005 dated 24 th January, 2008. And Amendment order No: PWRS/W-1305/2005/

More information

Mekong Integrated Water Resources Management Project (M-IWRMP) Transboundary Cooperation for River Basin Management between Lao PDR and Thailand

Mekong Integrated Water Resources Management Project (M-IWRMP) Transboundary Cooperation for River Basin Management between Lao PDR and Thailand Mekong River Commission Mekong Integrated Water Resources Management Project (M-IWRMP) Project Document Transboundary Cooperation for River Basin Management between Lao PDR and Thailand in Xe Bang Hieng

More information

EUGENE WATER & ELECTRIC BOARD INDEPENDENT AUDITOR S REPORTS AND FINANCIAL STATEMENTS DECEMBER 31, 2006 AND 2005

EUGENE WATER & ELECTRIC BOARD INDEPENDENT AUDITOR S REPORTS AND FINANCIAL STATEMENTS DECEMBER 31, 2006 AND 2005 INDEPENDENT AUDITOR S REPORTS AND FINANCIAL STATEMENTS DECEMBER 31, 2006 AND 2005 CONTENTS BOARD OF COMMISSIONERS AND OFFICERS 1 PAGE INDEPENDENT AUDITOR S REPORT 2 MANAGEMENT S DISCUSSION AND ANALYSIS

More information

ECONOMIC CONSULTING ASSOCIATES LIMITED 41 Lonsdale Road London NW6 6RA UK tel +44 (0) / fax +44 (0)

ECONOMIC CONSULTING ASSOCIATES LIMITED 41 Lonsdale Road London NW6 6RA UK tel +44 (0) / fax +44 (0) Ghana Power Sector Review of Reform Programme Ray Tomkins (ECA) ECONOMIC CONSULTING ASSOCIATES LIMITED 41 Lonsdale Road London NW6 6RA UK tel +44 (0)20 7604 4545 / fax +44 (0)20 7604 4547 www.eca-uk.com

More information

Tajikistan: Financial Assessment of Barki Tojik

Tajikistan: Financial Assessment of Barki Tojik Public Disclosure Authorized Tajikistan: Financial Assessment of Barki Tojik Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized October 2013 Artur Kochnakyan Ani Balabanyan

More information

Brookfield Renewable Energy Partners L.P. Q INTERIM REPORT

Brookfield Renewable Energy Partners L.P. Q INTERIM REPORT Brookfield Renewable Energy Partners L.P. Q3 2015 INTERIM REPORT TABLE OF CONTENTS Letter to Shareholders 1 Generation and Financial Review for the Three Months Ended September 30, 2015 10 Generation and

More information

Regional Transmission Organization Frequently Asked Questions

Regional Transmission Organization Frequently Asked Questions 1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy

More information

Energy Projects in the Mekong Region

Energy Projects in the Mekong Region CLICK TO EDIT MASTER TITLE STYLE Energy Projects in the Mekong Region IBA Annual Meeting Tokyo IBA Power Law Committee Panel 22th October 2014 B A N G L A D E S H C A M B O D I A I N D O N E S I A L A

More information

Development Fee Program: Comparative risk analysis

Development Fee Program: Comparative risk analysis Development Fee Program: Comparative risk analysis January 2008 Sacramento Area Flood Control Agency David Ford Consulting Engineers, Inc. 2015 J Street, Suite 200 Sacramento, CA 95811 Ph. 916.447.8779

More information

UPDATE ON THE LAO PDR: NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT

UPDATE ON THE LAO PDR: NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT UPDATE ON THE LAO PDR: NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT October 20, 2006 ABBREVIATIONS AND ACRONYMS ADB AfD ASOSAI BOL CA CPI DG DSRP EMU GDP GLIP GOL GOLE HCC IAG IDA IFIs IMA IMF INTOSAI JBIC

More information

Chapter Five. Scale, Timing, Length, and Interdependencies in Project Selection

Chapter Five. Scale, Timing, Length, and Interdependencies in Project Selection Chapter Five Scale, Timing, Length, and nterdependencies in Project Selection 5.1 ntroduction n the previous chapter, it was concluded that a project s net present value (NPV) is the most important criterion

More information

Electricity Industry Bill

Electricity Industry Bill Electricity Industry Bill Request for additional information by Finance and Expenditure Committee The additional information sought by the committee on 17 February 2010 is set out in the following tables.

More information

The Government of the Republic of South Africa and the Government of the Kingdom of Lesotho (hereinafter called "the Parties");

The Government of the Republic of South Africa and the Government of the Kingdom of Lesotho (hereinafter called the Parties); TREATY ON THE LESOTHO HIGHLANDS WATER PROJECT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF SOUTH AFRICA AND THE GOVERNMENT OF THE KINGDOM OF LESOTHO SYLLABUS OF THE TREATY PREAMBLE ARTICLE 1: Definitions

More information

FINANCIAL ANALYSIS. A. Methodology and Major Assumptions

FINANCIAL ANALYSIS. A. Methodology and Major Assumptions Second Green Power Development Project (RRP BHU 44444) FINANCIAL ANALYSIS 1. The project s financial analysis was carried out in accordance with the Financial Management and Analysis of Project Guidelines

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION. LeRoy Koppendrayer

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION. LeRoy Koppendrayer STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION LeRoy Koppendrayer Ellen Gavin Marshall Johnson Phyllis Reha Gregory Scott Chair Commissioner Commissioner Commissioner Commissioner

More information

SECOND PROGRESS REPORT INDIA VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT (LOAN NO IN)

SECOND PROGRESS REPORT INDIA VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT (LOAN NO IN) INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION SECOND PROGRESS REPORT ON THE IMPLEMENTATION OF MANAGEMENT S ACTION PLAN IN RESPONSE TO THE INSPECTION PANEL

More information

Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin

Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin Summary note Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin Final draft In an effort to communicate openly with broader stakeholders of the Mekong River Commission

More information

Hydropower Risk Mitigation. Joerg Hartmann PhD Independent Consultant Apr

Hydropower Risk Mitigation. Joerg Hartmann PhD Independent Consultant Apr Hydropower Risk Mitigation Joerg Hartmann PhD Independent Consultant joerg.hartmann.water@gmail.com Apr 27 2018 Acknowledgement The material in this presentation is the result of the collaboration with

More information

FINANCIAL ANALYSIS. A. Background

FINANCIAL ANALYSIS. A. Background SASEC Second Bangladesh India Electrical Grid Interconnection Project (RRP BAN 44192) A. Background FINANCIAL ANALYSIS 1. The South Asia Subregional Economic Cooperation (SASEC) Second Bangladesh India

More information

INTERNATIONAL DEVELOPMENT ASSOCIATION INTERNATIONAL MONETARY FUND LAO PEOPLE S DEMOCRATIC REPUBLIC

INTERNATIONAL DEVELOPMENT ASSOCIATION INTERNATIONAL MONETARY FUND LAO PEOPLE S DEMOCRATIC REPUBLIC INTERNATIONAL DEVELOPMENT ASSOCIATION INTERNATIONAL MONETARY FUND LAO PEOPLE S DEMOCRATIC REPUBLIC Joint Bank/Fund Debt Sustainability Analysis 28 1 Prepared by the staffs of the International Development

More information

Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade and Distribution Project

Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade and Distribution Project Appendix 3 11 Technical Assistance Report Project Number: 51329-002 Transaction Technical Assistance (TRTA) November 2017 Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade

More information

July 31, The Many Values of. Renewable Energy. Prepared For

July 31, The Many Values of. Renewable Energy. Prepared For The Many Values of Renewable Energy Prepared For About Duff & Phelps Duff & Phelps is the global advisor that protects, restores and maximizes value for clients in the areas of valuation, corporate finance,

More information

REVENUE AND EXPENDITURE MANAGEMENT

REVENUE AND EXPENDITURE MANAGEMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TECHNICAL BRIEF REVENUE AND EXPENDITURE MANAGEMENT Nam Theun 2 Hydroelectric Project

More information

USAID-Funded Nepal Hydropower Development Project (NHDP)

USAID-Funded Nepal Hydropower Development Project (NHDP) USAID-Funded Nepal Hydropower Development Project (NHDP) Electricity Regulatory Commission and the Emerging Legal, Policy, and Regulatory Framework for Hydropower in Nepal Arun Anandan Regulatory Advisor

More information

Risk Factors. We are exposed to fluctuations in fuel prices

Risk Factors. We are exposed to fluctuations in fuel prices Risk Factors We are exposed to fluctuations in fuel prices Fuel is our most significant operating cost, accounting for 81.7 percent of our total expenses in 2014. Whether and to what extent we can pass

More information

Ratchaburi Electricity Generating Holding PLC

Ratchaburi Electricity Generating Holding PLC Ratchaburi Electricity Generating Holding PLC Announcement no. 873 9 May 2012 Company Rating: Outlook: AA Stable New Issue Rating: Rating History: Date Company Issue (Secured/ Unsecured) 09/02/11 AA/Sta

More information

Lao PDR World Bank Mission AIDE MEMOIRE April 1, 2002

Lao PDR World Bank Mission AIDE MEMOIRE April 1, 2002 Lao PDR World Bank Mission AIDE MEMOIRE April 1, 2002 Introduction A World Bank mission on the proposed Nam Theun 2 project and related issues led by Mr. Ian Porter, Country Director, and comprising of

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 36. Congestion Revenue Rights... 3 36.1 Overview Of CRRs And Procurement Of CRRs... 3 36.2 Types Of CRR Instruments... 3 36.2.1 CRR Obligations... 3 36.2.2 CRR Options... 3 36.2.3 Point-To-Point

More information

Financing Utility Scale Solar

Financing Utility Scale Solar Financing Utility Scale Solar Matt Handel Vice President Solar, Distributed Generation & Storage August 25, 2016 Headquartered in Juno Beach, FL, NextEra Energy, Inc. has operations in 27 states, Canada,

More information

Utilizing MIGA Products to Support Renewable Energy Projects

Utilizing MIGA Products to Support Renewable Energy Projects Utilizing MIGA Products to Support Renewable Energy Projects April 25, 2014 MULTILATERAL INVESTMENT GUARANTEE AGENCY WORLD BANK GROUP The World Bank Group 1944 IBRD International Bank for Reconstruction

More information

UPDATE ON THE LAO PDR NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT

UPDATE ON THE LAO PDR NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT UPDATE ON THE LAO PDR NAM THEUN 2 (NT2) HYDROELECTRIC PROJECT The World Bank in Lao P.D.R. October 2006 UPDATE ON NAM THEUN 2 PROJECT ABBREVIATIONS AND ACRONYMS ADB Asian Development Bank AfD Agence Franaise

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

Cross Border Electricity Trade

Cross Border Electricity Trade Cross Border Electricity Trade Afghanistan Pakistan Nepal Bhutan India First meeting of core team on South Asian Regional Power Exchange (SARPEX) Bangladesh 7 th - 9 th February, 2017 New Delhi, India

More information

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to Power Purchase Agreement (PPA) Guidelines Zambia Lusaka August 7 to 11 2017 I. Objective of the PPA Guideline II. Length of the Agreement III. Commissioning Process IV. Sale and Purchase V. PPA Pricing

More information

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019 Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3 Public Hearings- Port Elizabeth Date: 16 January 2019 RCA (Yr 5, MYPD3) Timeline RCAs require 3 decisions: 1 Balance decision 2 Liquidation decision

More information

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

Report of Independent Auditors

Report of Independent Auditors Report of Independent Auditors To the Board of Commissioners Public Utility District No. 1 of Clark County Vancouver, Washington Report on the Financial Statements We have audited the accompanying individual

More information

Appendix 5D Water Transfer Analysis Methodology and Results

Appendix 5D Water Transfer Analysis Methodology and Results Appendix D Water Transfer Analysis Methodology and Results 0 Appendix D Water Transfer Analysis Methodology and Results D. Introduction This appendix provides a detailed description of the transfers analysis

More information

The Long-Term Financial Integrity of the African Development Fund

The Long-Term Financial Integrity of the African Development Fund The Long-Term Financial Integrity of the African Development Fund Discussion Paper ADF-12 Replenishment February 2010 Cape Town, South Africa AFRICAN DEVELOPMENT FUND Executive Summary Preparations for

More information

No An act relating to the Vermont energy act of (S.214) It is hereby enacted by the General Assembly of the State of Vermont:

No An act relating to the Vermont energy act of (S.214) It is hereby enacted by the General Assembly of the State of Vermont: No. 170. An act relating to the Vermont energy act of 2012. (S.214) It is hereby enacted by the General Assembly of the State of Vermont: * * * Renewable Energy Goals, Definitions * * * Sec. 1. 30 V.S.A.

More information

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank GET FIT Programme Energy Sector Working Group Maputo, 25 May 2016 Julia Crause Infrastructure, Southern Africa KfW Development Bank Agenda 1 GET FIT Uganda Results and Approach 2 Potential GET FiT Programme

More information

1997 PACIFIC NORTHWEST COORDINATION AGREEMENT

1997 PACIFIC NORTHWEST COORDINATION AGREEMENT 1997 PACIFIC NORTHWEST COORDINATION AGREEMENT Agreement for Coordination of Operations among Power Systems of the Pacific Northwest June 18, 1997 Conformed Copy i Table of Contents Table of Contents i

More information

Additional examples of government support on projects has been provided on the record in response to MH/MIPUG I-3.

Additional examples of government support on projects has been provided on the record in response to MH/MIPUG I-3. 0 0 REFERENCE: Undertaking #, Transcript page 0, QUESTION: a) MIPUG panel to provide brief summary of various examples of government support or intervention in projects to deal with rate pressures; also

More information

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project Final Resettlement Monitoring Report Document stage: Final Project number: Loan 2517 May, 2017 VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote s Sector Project Sub-project:

More information

Ratchaburi Electricity Generating Holding Public Company Limited

Ratchaburi Electricity Generating Holding Public Company Limited Contacts E-mail Addresses Rungrat Suntornpagasit rungrat@trisrating.com Sermwit Sriyotha sermwit@trisrating.com Nopalak Rakthum nopalak@tris.co.th Wiyada Pratoomsuwan, CFA wiyada@tris.co.th N e w s f o

More information