Hydropower Risk Mitigation. Joerg Hartmann PhD Independent Consultant Apr
|
|
- Posy Hutchinson
- 6 years ago
- Views:
Transcription
1 Hydropower Risk Mitigation Joerg Hartmann PhD Independent Consultant Apr
2 Acknowledgement The material in this presentation is the result of the collaboration with many individuals in the hydropower sector. In particular, a number of slides are borrowed and adapted from Judith Plummer, Risk Management and Impacts of Delay (at 2016 TNC Water Summit, NYC). The interpretation as well as all errors are the author s.
3 Introduction: What makes hydropower a risky business? (30 min) Conflicts, cost overruns and delays are a universal problem, not just in Nepal. The complexity of hydropower makes project selection and execution particularly challenging. Learning from other countries risk management failures and achievements may help Nepal deliver projects more successfully.
4 Risk and Uncertainty Risk wide colloquial sense: the general possibility of the occurrence of adverse events narrow technical sense: the product of the impact of a hazard and its probability ISO 3100:2018: effect of uncertainty on objectives Uncertainty a situation where the range of possible outcomes is known, but there is insufficient information to determine their probabilities
5 Universal problem for infrastructure average cost overrun of 170 largest German infrastructure projects since 1960: 73% average for nuclear power stations: 187% also often significant delays, benefit shortfalls, and quality issues
6 Is this really a problem for society? Everybody knows that you can t get projects approved at their real cost Everybody knows that infrastructure is needed If we would think too hard about this, we wouldn t have the Sydney Opera House (cost overrun 1,400%)
7 Is it a problem for the hydro sector? Ansar et al (2014) sample of 245 projects ( , 65 countries): average costs 96% and median costs 27% higher than estimated average schedule 44% and median schedule 27% longer than estimated not even counting costs of cancellations, and delayed revenues
8 8
9 Consequences of hydro risks From a business perspective: Risks lead to cancellations or cost and schedule overruns Risks reduce returns on investment (if costs cannot be passed on) Hydro risks are large enough to be existential threats to businesses From a public policy perspective: Hydro projects affect many involuntary risk-takers High business risks deter investment Non-served power is more expensive than any source of delivered power (estimates of USD 2 per kwh)
10 Standard explanations for hydro delays/cost overruns Geology Design errors and changes Project and contract management Does that capture recent experiences? Morgan Landy, IFC
11 Cancellations Combined capacity 18 GW Losses of more than USD 1 billion No tunnels
12 Delays and cost overruns Combined capacity 15 GW Overruns of more than USD 15 billion No tunnels
13 Technical Risks Economic and Financial Risks Political Risks Social Risks Environmental Risks Geotechnical-Seismic Construction and Installation Quality Performance of Contractors or Construction Schedule delays Cost Escalation (inflation, commodity prices, competition for resources and other local and international cost effects) Government response time risk (adequacy of Government and public sector agencies to respond in a timely manner in terms of issuance of licenses and approvals or other coordination with the project) Land and Water Use Conflicts (issues raised by local water users or downstream riparians on use of water or catchment) Public Health and Safety (issues of physical safety as well as spread of disease during all phases of the project) Fish Habitat Upstream and Downstream Flow Regime Hydrological (operational or construction related risk of lower and higher flows, floods or unusual seasonal variations Electro-mechanical Equipment Performance Financing Package Electricity Market (changes in the price of electricity for merchant plants or changes in the regulatory mechanism for setting price) Political Change Risk (to a project caused by local or national changes in government, policy, legislation, regulation, political instability or unrest) Resettlement and Social Unrest Cultural Heritage issues Biodiversity Greenhouse Gas Emission Operation and Maintenance Foreign Exchange Corruption risk (risk to the project implementation or developer reputation caused by corruption issues) Main international objections on social, environmental or cultural grounds Other environmental Sedimentation Other technical Other economic and financial Trans-Boundary Issues (upstream and downstream riparian rights and treaties, and border security issues) Other social Wetlands Protection Water-Air Quality
14 Non-Technical Risks - Similar Issues in Oil, Gas and Mining
15 The significant increase in hydropower capacity over the last 10 years is anticipated in many scenarios to continue with various environmental and social concerns representing perhaps the largest challenges to continued deployment if not carefully managed. Kumar, A., et al. (2011). Hydropower. In IPCC Special Report on Renewable Energy Sources and Climate Change Mitigation (emphasis added)
16 Two types of hydropower projects? Small Run-of-River Single Purpose Private finance Financial returns similar to economic (few externalities) 25% of global investment Main risk: Geology Main environmental issue: Connectivity Some risks of delays and cost overruns Large Storage Multi Purpose Public finance Financial returns different from economic (many positive and negative externalities) 75% of global investment Main risk: Resettlement Main environmental issue: Flow alteration Major risks of cancellation, delays and cost overruns
17
18 Case Studies (30 min) Even developed countries have multiple, systemic problems in delivering hydropower projects, as the example of Canada shows, with a number of large-scale projects at risk. Some risks are more technical, as examples of problems caused by geology in Bhutan show. Others are more multi-faceted. An example from Colombia shows how technical oversights can cause multiple environmental, social and public relations problems. Some risks may be misinterpreted and overstated in the public debate, but it can be very difficult to get the story right, leading to real consequences.
19 Muskrat Falls (824 MW), Canada (quotes from NALCOR CEO Marshall and Provincial Premier Ball)
20 Muskrat Falls (824 MW), Canada
21 Keeyask (695 MW), Canada Boston Consulting Group (BCG) report for Manitoba Hydro Board (2016): Keeyask was an imprudent project to undertake
22 Site C (1,100 MW), Canada
23 Bhutan Geotechnical Problems Punatsangchu I 1,200 MW: 6-year delay due to last-minute shift of dam site to increase capacity, without proper studies. New dam site has instability on right bank Punatsangchu II 1,020 MW: 2-year delay due to collapse of underground power house roof, 6 fatalities Mangdechhu 690 MW: landslide at dam pit, 5 fatalities
24
25
26 Fools and Liars... 26
27 Sogamoso (820 MW), Colombia
28 Sogamoso (820 MW), Colombia Problem 1: Plan to deliver environmental flow during filling of reservoir through bottom outlet which is 40 m above river bed Problem 2: Filling during dry instead of wet season Consequence: River bed falls dry for extended period Bad luck 1: Journalists find out and present story out of context Bad luck 2: Emergency solution partial opening of one diversion tunnel gate leads to log stuck in gate Consequence: - Significant public relations problems - Significant operational problems - Structural risk to diversion tunnel and dam Good luck: log finally dislodges itself and gate can be closed
29 Not a direct cause and effect, but the mixed reputation of the hydropower sector has real consequences...
30
31 The Risk Management Process: Identification, Avoidance and Mitigation (1 hour) A systematic approach to risk management starts with selecting lowrisk projects, followed by actively managing risks throughout the preparation, implementation and operation stage. Generic guidance such as ISO 31000, as well as hydropower-specific principles of the mitigation hierarchy will be discussed. Practical examples of tools to identify and prioritize risks will be provided, including risk assessments, risk registers and corrective action planning.
32 Stage Gate Approach
33 Gradually Reducing the Level of Uncertainty
34 Project Selection Challenge of narrowing uncertainty to a sufficient level to identify show stoppers and determine if the project has sufficient prospect of viability But: Are filtering activities being undertaken with sufficient objectivity? Is there a clear understanding of the breadth of issues that should be considered in the filtering process?
35 Once Project is Selected for Detailed Preparation...
36
37 Risk Appetite of Project Proponents and Stakeholders Owner is initially responsible for all of the project risks, as it is usually the owner s decision to execute the project or not Corporate structure Single project SPVs have little ability to absorb risk Utilities with multiple assets may be able to accept and manage risk as can spread risk Offtakers: Cost reflective tariffs help provide risk sharing Contractors: Fixed-price contracts help provide risk sharing Lenders and investors Equity investors typically carry more risk Lenders have varying appetite for risk generally risk averse
38 Technical Risks Economic and Financial Risks Political Risks Social Risks Environmental Risks Geotechnical-Seismic Construction and Installation Quality Performance of Contractors or Construction Schedule delays Cost Escalation (inflation, commodity prices, competition for resources and other local and international cost effects) Government response time risk (adequacy of Government and public sector agencies to respond in a timely manner in terms of issuance of licenses and approvals or other coordination with the project) Land and Water Use Conflicts (issues raised by local water users or downstream riparians on use of water or catchment) Public Health and Safety (issues of physical safety as well as spread of disease during all phases of the project) Fish Habitat Upstream and Downstream Flow Regime Hydrological (operational or construction related risk of lower and higher flows, floods or unusual seasonal variations Electro-mechanical Equipment Performance Financing Package Electricity Market (changes in the price of electricity for merchant plants or changes in the regulatory mechanism for setting price) Political Change Risk (to a project caused by local or national changes in government, policy, legislation, regulation, political instability or unrest) Resettlement and Social Unrest Cultural Heritage issues Biodiversity Greenhouse Gas Emission Operation and Maintenance Foreign Exchange Corruption risk (risk to the project implementation or developer reputation caused by corruption issues) Main international objections on social, environmental or cultural grounds Other environmental Sedimentation Other technical Other economic and financial Trans-Boundary Issues (upstream and downstream riparian rights and treaties, and border security issues) Other social Wetlands Protection Water-Air Quality
39 Areas of most concern: - Adversely affects upstream and downstream flow regime Extensive resettlement issues Cultural heritage issues High hydrological variation Contractual framework unclear/insufficient/ incomplete Government poor reputation for timely responses Adversely affects biodiversity Complex project Land and water use conflicts Lack of developer/operator/ EPC contractor experience International objections on social, environmental or cultural Areas subject to political change Poor off-taker credit worthiness, including undue risk of non- Area has reputation for corruption Project creates trans-boundary Issues Lack of strong regulatory environment Poor developer/operator/ EPC contractor reputation Power purchase agreement overly risky in nature Project includes multi-purpose aspects Adversely affects fish habitats History of project delays or false starts Likely adverse siltation issues High inflation No open access to electricity market No financing assistance available from Government Public health and safety concerns Adversely affects wetlands
40 Cost of Risks in a Typical Project Component With Risk Without Risk Construction cost (typical construction risks) EPC Premium (for design, interface, performance, fixed price risks) Equity returns (for development uncertainty, political & project risks) Debt interest (for repayment uncertainty) Debt service cover ratio (for repayment uncertainty) Contingency 30% 0% Cost premium 30% ±20% ROE required 0% <10% ROE required ±10% 4% (~US treasury bond rates) Min DSCR 1.3 Min DSCR 1.0
41 Cost of Risks in a Typical Project From simple financial modelling: Typical 100 MW scheme, 50% load factor, 30:70 equity:debt, 4 years construction: tariff = ± US 12 /kwh Removing risk: minus 30% construction risk contingency minus 30% EPC risk premium reduce ROE from ±20% to ±10% reduce debt interest from 10% to 4% Reduce DSCR from 1.3 to 1.0 tariff reduces to ± US 4 /kwh
42 Trade-off: Cost vs Certainty Typical trade-off between lowest cost and most certain outcome: More investigation should reduce risk of unexpected conditions Tunnel Boring Machines should reduce cost and time, but risk greater delay Dam type selection can reduce uncertainty, depending on site But Caution! In managing down risk may lose the objective of the project less risk is not always better, insurance has a cost
43 Assessing Risk - Approaches Decision Theory Sees risks as probability distributions Synthesizes individual risks into one risk factor Quantifies risks numerically Looks at probability distributions over all conceivable outcomes Sees risks as uncontrollable random events Managerial Sees risks as maximum exposures Breaks out risks into individual components Characterizes risks verbally and qualitatively Looks at relatively few critical outcomes Sees risks as avoidable and controllable
44 Increasing sophistication Assessing Risk Approaches to risk: Optimisation using Sensitivity indicates robustness Risk matrix relative levels of risk highlights most important Risk quantification quantity x probability ranks risks for action Risk combinations Monte Carlo simulations probability and consequence profiles
45 Sensitivity Analysis Trung Son (260 MW, Vietnam)
46
47 Cost impact of risk project A Delay impact of risk project A Level of risk impact on cost: - More than 25% Between 10% and 25% Between 5% and 10% Between 1% and 5% Less than 1% Not relevant Level of risk impact on time: - Indefinite More than 12 months Between 6 and 12 months Between 1 and 6 months Less than 1 month Not relevant
48 Cost impact of risk project B Delay impact of risk project B Level of risk impact on cost: - More than 25% Between 10% and 25% Between 5% and 10% Between 1% and 5% Less than 1% Not relevant Level of risk impact on time: - Indefinite More than 12 months Between 6 and 12 months Between 1 and 6 months Less than 1 month Not relevant
49 Cost impact of risk project C Delay impact of risk project C Level of risk impact on cost: - More than 25% Between 10% and 25% Between 5% and 10% Between 1% and 5% Less than 1% Not relevant Level of risk impact on time: - Indefinite More than 12 months Between 6 and 12 months Between 1 and 6 months Less than 1 month Not relevant
50 Monte Carlo Simulation Trung Son (260 MW, Vietnam)
51 Qualitative Risk Assessment (HSAP) Kabeli A (38 MW, Nepal)
52 Consequences of Poor Risk Assessment Time and money may be spent needlessly to prepare for risks that are actually negligible The need for contingency allowances may be overstated, tying up the owner s funds, preventing other vital projects from being funded (opportunity costs), and resulting in increased project costs, as excess contingencies are typically expended rather than returned Contingency allowances may be understated, leading to budget or schedule overruns and often performance and quality shortfalls as well, as quality and scope are reduced in an attempt to keep costs within the budget Actual significant risks may be missed and result in unwelcome surprises
53 Risk Management Plan
54 Managing Risk - Options Avoiding the risk by deciding not to start or continue with the activity that gives rise to the risk Postponing decisions to acquire more information (keep options open) Accepting or increasing the risk in order to pursue an opportunity Removing the risk source Changing the likelihood Changing the consequences Sharing the risk with another party or parties (including contracts and risk financing) Retaining the risk by informed decision
55 55 Allocating Risk Do NOT just allocate to those who can best bear risk Owner must Identify Assess Avoid/Mitigate Cost THEN - Allocate / Share Example: Hydrological risk during the operational phase allocated to the offtaker, project company, or shared
56 Tracking Risks with a Register
57 Tracking Progress with Earned Value Analysis Earned value represents the amount budgeted for performing the work which was accomplished by a given point in time.
58 Pre-Construction Delay A Risk in Itself For many stakeholders the effects of pre-construction delay are as serious, if not more serious, than the effects of construction delay (including affected families, government, environment, off-takers, consumers..).
59 Cost of Delays Rampur (412 MW, India) On time Delay Construction delay Economic rate of return of project 14.5% With one year delay 12.4% Financial rate of return 9.3% With one year delay 7.7% Pre-construction delay Economic rate of return of project 14.5% With one year delay 13.9% Financial rate of return 9.3% With one year delay 9.3% Data from World Bank Project Appraisal Report estimates and calculations
60 60
61 Application to Nepal: Discussion (1 hour) This will be an interactive session to discuss typical risks and risk management approaches in Nepal. Drawing on examples from participants, opportunities for improved risk management will be identified.
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs
More informationTrung Son Hydropower Project. Financial Analysis
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Trung Son Hydropower Project Financial Analysis Final Report February
More informationFINANCIAL ANALYSIS. A. Methodology and Major Assumptions
Second Green Power Development Project (RRP BHU 44444) FINANCIAL ANALYSIS 1. The project s financial analysis was carried out in accordance with the Financial Management and Analysis of Project Guidelines
More informationCost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE
Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and
More informationRegulatory Framework for Dam Safety
Regulatory Framework for Dam Safety Preliminary Results of the WB Global Dam Safety Legal & Institutional Framework Study Satoru Ueda, Lead Dam Specialist Sofia Grand Hotel, September 19, 2017 www.worldbank.org/water
More informationDelivering investor perspectives on what makes a project financially viable and attractive for them. Deconstructing facets of a financial proposal to
Delivering investor perspectives on what makes a project financially viable and attractive for them. Deconstructing facets of a financial proposal to ensure you are covering all bases appropriately. Delving
More informationEFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011
EFFECTIVE TECHNIQUES IN RISK MANAGEMENT Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011 Effective Techniques in Risk Management Risk Management Overview Exercise #1 Break Risk IT Exercise #2 Break Risk
More informationBERGRIVIER MUNICIPALITY. Risk Management Risk Appetite Framework
BERGRIVIER MUNICIPALITY Risk Management Risk Appetite Framework APRIL 2018 1 Document review and approval Revision history Version Author Date reviewed 1 2 3 4 5 This document has been reviewed by Version
More informationEnvironmental Assessment
OP 4.01 January 1999 These policies were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. Environmental Assessment (Archived August 2004) Note: OP and BP
More informationEnterprise Risk Management process at Dragon Oil
Enterprise Risk Management Risk Management Process Dragon Oil s business is potentially exposed to different risks. However, some business risks can be accepted by the Group provided that acceptance of
More informationSolvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies
Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies 1 INTRODUCTION AND PURPOSE The business of insurance is
More informationGuidance Note: Stress Testing Credit Unions with Assets Greater than $500 million. May Ce document est également disponible en français.
Guidance Note: Stress Testing Credit Unions with Assets Greater than $500 million May 2017 Ce document est également disponible en français. Applicability This Guidance Note is for use by all credit unions
More informationIntegrating Environmental, Social, and Governance Risks into Enterprise Risk Management. 7 May 2018
Integrating Environmental, Social, and Governance Risks into Enterprise Risk Management 7 May 2018 World Business Council for Sustainability Development MISSION: To accelerate the transition to a sustainable
More informationClimate Risk Management For A Resilient Asia-pacific Dr Cinzia Losenno Senior Climate Change Specialist Asian Development Bank
Climate Risk Management For A Resilient Asia-pacific Dr Cinzia Losenno Senior Climate Change Specialist Asian Development Bank APAN Training Workshop Climate Risk Management in Planning and Investment
More informationRegional Power Market Challenges and Opportunities from Nepalese perspective
Regional Power Market Challenges and Opportunities from Nepalese perspective Hitendra Dev Shakya Director, Power Trade Department, Nepal Electricity Authority Outline of the Presentation 1. Energy sector
More informationSECOND PROGRESS REPORT INDIA VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT (LOAN NO IN)
INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION SECOND PROGRESS REPORT ON THE IMPLEMENTATION OF MANAGEMENT S ACTION PLAN IN RESPONSE TO THE INSPECTION PANEL
More informationRisk Assessment of the Niagara Tunnel Project
Canadian Society of Value Analysis October 24, 2006 Risk Assessment of the Presented by: David Eden, P. Eng., Ontario Power Generation Susan Sherman, P.Eng.,URS Canada Inc Overview Qualitative Risk Analysis
More informationMainstreaming Disaster Risk Reduction in. Project Cycle Management
Mainstreaming Disaster Risk Reduction in Project Cycle Management Programmes, Activities, Projects (PAP) Programmes, Activities and Projects (PAP) provide good opportunities for mainstreaming DRR in development
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationAhsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS
Ahsan Jamal Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Introduction For the last couple of years, we have seen enormous growth in the construction industry of Pakistan due to
More informationHOW TO CONVINCE A LENDER
ILF BUSINESS CONSULT SERVICE LETTER N O. HOW TO CONVINCE A LENDER BANKABLE FEASIBILITY STUDIES ANDREAS LINKE, Ph.D. Introduction When an Investor seeks a non- or semi-recourse financing for his infrastructure
More informationRisk Management at Central Bank of Nepal
Risk Management at Central Bank of Nepal A. Introduction to Supervisory Risk Management Framework in Banks Nepal Rastra Bank(NRB) Act, 2058, section 35 (a) requires the NRB management is to design and
More informationEnterprise Risk Management Program
Enterprise Risk Management Program David W Sundvall, Risk Manager 3/2/2016 Page 0 of 12 Table of Contents Introduction... 2 Approach... 2 Risk Appetite... 3 Roles and Responsibilities... 3 Process... 4
More informationRISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS
N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...
More informationRISK MANAGEMENT POLICY October 2015
RISK MANAGEMENT POLICY October 2015 1. INTRODUCTION 1.1 The primary objective of risk management is to ensure that the risks facing the business are appropriately managed. 1.2 Paringa Resources Limited
More information10.0 NAM THEUN 2 ISSUES
10.0 NAM THEUN 2 ISSUES 10.1 Scope of Nam Theun 2 Issues The Nam Theun 2 PPA and concession agreement have been executed and these documents contractually commit GOL, EGAT and NTPC to the key parameters
More informationProject Appraisal and Selection
Project Appraisal and Selection Project Appraisal Objectives Dr. DNS Dhakal Duke University Leadership for Results Program for Mid-Level Officers in the Nepalese Civil Service Kathmandu, Nepal 2 September
More information1. Define risk. Which are the various types of risk?
1. Define risk. Which are the various types of risk? Risk, is an integral part of the economic scenario, and can be termed as a potential event that can have opportunities that benefit or a hazard to an
More informationRISK MANAGEMENT STRATEGY Version 3
RISK MANAGEMENT STRATEGY Version 3 Risk Management Strategy V3 - March 2018 1 Standard Operating Procedure St Helens CCG Risk Management Strategy Version 3.0 Implementation Date September 2014 Review Date
More informationDRAFT FOR CONSULTATION OCTOBER 7, 2014
DRAFT FOR CONSULTATION OCTOBER 7, 2014 Information Note 1: Environmental and Social Risk Classification The Board has requested the release of this document for consultation purposes to seek feedback on
More informationINTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 05-Sep-2013
More information4.1 Risk Assessment and Treatment Assessing Security Risks
Information Security Standard 4.1 Risk Assessment and Treatment Assessing Security Risks Version: 1.0 Status Revised: 03/01/2013 Contact: Chief Information Security Officer PURPOSE To identify, quantify,
More informationChapter-8 Risk Management
Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not
More informationPickering Whole-Site Risk
Pickering Whole-Site Risk Jack Vecchiarelli Manager, Pickering Relicensing Update to Commission Members December 14, 2017 CMD 17-M64.1 Outline Background Whole-site risk considerations Use of Probabilistic
More informationRisk Management Strategy
Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality
More informationProject Finance An Overview
Project Finance An Overview KAMAL TAK ICAI, Navi Mumbai Chapter December 16, 2012 1 Project Finance An Overview What is Project Financing? How is it different? How are Projects developed? Various Project
More informationREGULATORY GUIDELINE Liquidity Risk Management Principles TABLE OF CONTENTS. I. Introduction II. Purpose and Scope III. Principles...
REGULATORY GUIDELINE Liquidity Risk Management Principles SYSTEM COMMUNICATION NUMBER Guideline 2015-02 ISSUE DATE June 2015 TABLE OF CONTENTS I. Introduction... 1 II. Purpose and Scope... 1 III. Principles...
More informationRISK MANAGEMENT LECTURE 5. Ahmed Elyamany
RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.
More informationAudit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2017 Qtr 1
Audit Department Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2017 Qtr 1 To be leaders in building public trust in our civic government TABLE OF CONTENTS History...1
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationValue for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.
Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life
More informationINTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013)
INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE Nepal Rastra Bank Bank Supervision Department August 2012 (updated July 2013) Table of Contents Page No. 1. Introduction 1 2. Internal Capital Adequacy
More informationThe Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016
The Economics and Financing of Distributed Generation Investment Budapest, Hungary November 17, 2016 Topics to Cover How to Finance Distributed Generation Investments 1 Importance of financial aspects
More informationThe Government of the Republic of South Africa and the Government of the Kingdom of Lesotho (hereinafter called "the Parties");
TREATY ON THE LESOTHO HIGHLANDS WATER PROJECT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF SOUTH AFRICA AND THE GOVERNMENT OF THE KINGDOM OF LESOTHO SYLLABUS OF THE TREATY PREAMBLE ARTICLE 1: Definitions
More informationOverview of cogeneration project development
Overview of cogeneration project development 2004 Cogeneration Week in Thailand 23-25 March 2004 Miracle Grand Convention Hotel, Bangkok Romel M. Carlos Financial Advisor Project Development Process Commissioning
More informationTanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction
Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis
More informationRaising Equity for large biomass to power projects
Specialist investment. 16/09/2016 Raising Equity for large biomass to power projects Presentation to IrBEA 'Financing Bioenergy Projects' Workshop Dublin 14 th September 2016 Dedicated Renewable Focused
More informationSummary of Credit Suisse s Sector Policies and Guidelines
ccc Summary of Credit Suisse s Sector Policies and Guidelines CONTENT INTRODUCTION SUMMARY OF FORESTRY AND AGRIBUSINESS POLICY SUMMARY OF MINING POLICY SUMMARY OF OIL AND GAS POLICY SUMMARY OF CONTROVERSIAL
More informationAIG Global Property Construction Risk Engineering
AIG Global Property Construction Risk Engineering AIG is a leading provider of risk management and loss prevention services for Commercial Property, Energy and Construction risks worldwide. Through the
More informationMuskrat Falls Project
Review of project cost, schedule and related risks Interim report April 8, 2016 Julia Mullaley Clerk of the Executive Council & Secretary to Cabinet Government of Newfoundland and Labrador P.O. Box 8700
More informationMETHODOLOGY For Risk Assessment and Management of PPP Projects
METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental
More informationQ I N T E R I M R E P O R T. Brookfield Renewable Partners L.P.
Q2 2017 I N T E R I M R E P O R T Brookfield Renewable Partners L.P. OUR OPERATIONS We manage our facilities through operating platforms in North America, Colombia, Brazil, and Europe which are designed
More informationPrincipal risks and uncertainties
Principal risks and uncertainties Strategic report Principal risks are a risk or a combination of risks that, given the Group s current position, could seriously affect the performance, future prospects
More information1. Advance business transformation. 2. Provide attractive shareholder returns. 3. Increase investment in utility infrastructure
Table 1: PG&E Corporation Business Priorities 2006-2010 1. Advance business transformation 2. Provide attractive shareholder returns 3. Increase investment in utility infrastructure 4. Implement an effective
More informationRisk Management Policy and Framework
Risk Management Policy and Framework Risk Management Policy Statement ALS recognises that the effective management of risks is a fundamental component of good corporate governance and is vital for the
More informationUS Army Corps of Engineers Dam Safety
US Army Corps of Engineers General Program Overview & Impacts of Issues on Project Regulation Charles Pearre, PE Program Manager,, Emeritus June 2011 US Army Corps of Engineers BUILDING STRONG Defined
More informationINTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS
Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared
More information2014 Own Risk and Solvency Assessment (ORSA) Feedback Pilot Project Observations of the Group Solvency Issues (E) Working Group
2014 Own Risk and Solvency Assessment (ORSA) Feedback Pilot Project Observations of the Group Solvency Issues (E) Working Group During October 2014 through June 2015, a third ORSA Feedback Pilot Project
More informationUSAID-Funded Nepal Hydropower Development Project (NHDP)
USAID-Funded Nepal Hydropower Development Project (NHDP) Hydropower Financing: Traditional Project Finance, EPC and EPC-F Name of Facilitator: Sreeram Pethi Designation: Senior Financial Advisor Date:
More informationWhat is disaster risk? Progression of approaches. It s not that simple! Increasing disaster losses due to temperature rises and climate change?!
Increasing disaster losses due to temperature rises and climate change?! A Climate Risk Management Approach to Adaptation to Climate Change and Disaster Reduction Kamal Kishore Bureau for Crisis Prevention
More informationVocabulary of Flood Risk Management Terms
USACE INSTITUTE FOR WATER RESOURCES Vocabulary of Flood Risk Management Terms Appendix A Leonard Shabman, Paul Scodari, Douglas Woolley, and Carolyn Kousky May 2014 2014-R-02 This is an appendix to: L.
More information2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias
2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly
More informationAudit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 2
Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 2 Leaders in building public trust in civic government Audit Department TABLE OF CONTENTS History...5
More information51 st EEI Financial Conference
51 st EEI Financial Conference November 8, 2016 One of North America s largest electric utilities Disclaimers DISCLAIMERS In this presentation, all amounts are in Canadian dollars, unless otherwise indicated.
More informationMEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework
MEMORANDUM To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 Re: ERM Policy and Framework Executive Summary Attached are the draft Enterprise Risk Management
More informationEXCELLENCE INNOVATION SERVICE VALUE
Incorporation of Geotechnical Elements as an Asset Class within Transportation Asset Management and Development of Risk Based and Life Cycle Cost Performance Strategies by Mark Vessely, P.E. Shannon &
More informationDEFINING BEST PRACTICE IN FLOODPLAIN MANAGEMENT
DEFINING BEST PRACTICE IN FLOODPLAIN MANAGEMENT M Babister 1 M Retallick 1 1 WMAwater, Level 2,160 Clarence Street Sydney Abstract With the upcoming release of the national best practice manual, Managing
More informationENTERPRISE RISK MANAGEMENT (ERM) The Conceptual Framework
ENTERPRISE RISK MANAGEMENT (ERM) The Conceptual Framework ENTERPRISE RISK MANAGEMENT (ERM) ERM Definition The Conceptual Frameworks: CAS and COSO Risk Categories Implementing ERM Why ERM? ERM Maturity
More informationScouting Ireland Risk Management Framework
No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015
More informationEnterprise Risk Management Integrated Framework
ISACA S IT Audit, Information Security & Risk Insights Africa 2014, Alisa Hotel Enterprise Risk Management Integrated Framework Tony Bediako May 20, 2014 Today s organizations are concerned about: Risk
More informationProject Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich
Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements
More informationThe Proactive Quality Guide to. Embracing Risk
The Proactive Quality Guide to Embracing Risk Today s Business Uncertainties Are Driving Risk Beyond the Control of Every Business. Best Practice in Risk Management Can Mitigate these Threats The Proactive
More informationProject Management Certificate Program
Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949
More informationDr. Alexia Nalewaik FRICS CCP CCA November 2015
Dr. Alexia Nalewaik FRICS CCP CCA November 2015 Framing the project success problem Risk assessment and management Types of risk Auditing risk Questions and Answers Projects are often unique, complex,
More informationAACE Chinook Dinner Meeting Calgary, Alberta, Canada Projects, Risks and Contingency
AACE Chinook Dinner Meeting Calgary, Alberta, Canada Projects, Risks and Contingency Riskcore Calgary March 2017. Quotes He who is not courageous enough to take risks will accomplish nothing in life The
More informationMaster Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards
Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards A framework for the integration of risk management into the project and construction industry, following
More informationCOMMUNIQUE. Page 1 of 13
COMMUNIQUE 16-COM-001 Feb. 1, 2016 Release of Liquidity Risk Management Guiding Principles The Credit Union Prudential Supervisors Association (CUPSA) has released guiding principles for Liquidity Risk
More informationGOV : Enterprise Risk Management Policy
Name: Responsibility: Complements: Enterprise Risk Management Framework Coordinator, Enterprise Risk Management GOV-080-005: Enterprise Risk Management Policy Draft Date: November 2006; January 2012 Revised
More informationRISK MANAGEMENT FRAMEWORK
RISK MANAGEMENT FRAMEWORK 1. INTRODUCTION (Company) acknowledges that risk is inherent in its business. The Company s risk management framework is an important tool to guide the organisation towards achieving
More informationAn Overview of the Enterprise Risk Management Process
An Overview of the Enterprise Risk Management Process Laureen Regan, Ph.D. Fox School of Business and Management Temple University What is Enterprise Risk Management? Risk Management is "the culture, processes
More informationLEGAL ASPECTS OF PROJECT FINANCE. Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL
` LEGAL ASPECTS OF PROJECT FINANCE Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL About the speaker Anjan Neupane, Partner/Advocate, Neupane Law Associates LLB (Hons.) First Class, University
More informationApplying COSO s Enterprise Risk Management Integrated Framework. September 29, 2004
Applying COSO s Enterprise Risk Management Integrated Framework September 29, 2004 Today s organizations are concerned about: Risk Management Governance Control Assurance (and Consulting) ERM Defined:
More informationKidsafe NSW Risk Management Plan. August 2014
Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name
More informationAdaptation Assessment: Economic Analysis of Adaptation Measures
Adaptation Assessment: Economic Analysis of Adaptation Measures Presentation by Dr. Benoit Laplante Environmental Economist Workshop on Climate Risk Management in Planning and Investment Projects Manila,
More informationPresenting and Understanding Risk Management
The best source of information and training on Aboriginal finance and management The Aboriginal Finance and Management Capacity Development Series Presenting and Understanding Risk Management A Practical
More informationReport for the Commission of Inquiry Respecting the Muskrat Falls Project
Report for the Commission of Inquiry Respecting the Muskrat Falls Project Prof Bent Flyvbjerg* Dr Alexander Budzier *Lead author; all opinions expressed in this report are the opinions of the lead author
More informationEmpirical Issues in Crop Reinsurance Decisions. Prepared as a Selected Paper for the AAEA Annual Meetings
Empirical Issues in Crop Reinsurance Decisions Prepared as a Selected Paper for the AAEA Annual Meetings by Govindaray Nayak Agricorp Ltd. Guelph, Ontario Canada and Calum Turvey Department of Agricultural
More informationTD BANK INTERNATIONAL S.A.
TD BANK INTERNATIONAL S.A. Pillar 3 Disclosures Year Ended October 31, 2013 1 Contents 1. Overview... 3 1.1 Purpose...3 1.2 Frequency and Location...3 2. Governance and Risk Management Framework... 4 2.1
More information28 July May October 2016
Policy Name Risk Management Policy & Procedure Related Policies and Legislation AISWA Guidelines Risk Management Policy Category Planning & Management Relevant Audience Date of Issue / Last Revision All
More informationCREDIT RATING INFORMATION & SERVICES LIMITED
Rating Methodology INVESTMENT COMPANY CREDIT RATING INFORMATION & SERVICES LIMITED Nakshi Homes (4th & 5th Floor), 6/1A, Segunbagicha, Dhaka 1000, Bangladesh Tel: 717 3700 1, Fax: 956 5783 Email: crisl@bdonline.com
More informationRISK MANAGEMENT FRAMEWORK
RISK MANAGEMENT FRAMEWORK 1 RISK MANAGEMENT FRAMEWORK... 1 INTRODUCTION... 3 AN EFFECTIVE ENTERPRISE RISK MANAGEMENT SYSTEM... 4 Guiding Principles... 4 RISK GOVERNANCE... 5 Mandate and Commitment... 5
More informationAudit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 3
Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 3 To be leaders in building public trust in our civic government Audit Department TABLE OF CONTENTS History...5
More informationRisk Management Policy Adopted by:
Risk Management Policy Adopted by: Infigen Energy Limited Infigen Energy (Bermuda) Limited Infigen Energy RE Limited in its capacity as Responsible Entity of Infigen Energy Trust Adopted: 17 December 2009
More informationClimate risk management plan. Towards a resilient business
Type your organisation name here Climate risk management plan Towards a resilient business 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 Click the numbers to select your cover images 1 2 3 4 5 Document control sheet Document
More informationBRITISH COLUMBIA DAM SAFETY REGULATION 44/2000
PDF Version [Printer friendly ideal for printing entire document] BRITISH COLUMBIA DAM SAFETY REGULATION 44/2000 Published by Important: Quickscribe offers a convenient and economical updating service
More informationFERMA European Survey 2012 ERM Maturity Key Findings Dominique Pageaud Ernst & Young. In collaboration with
FERMA European Survey 2012 ERM Maturity Key Findings Dominique Pageaud Ernst & Young Content 1. 2. 3. How business environment impact ERM? Maturity of Risk Management practices at a glance How leading
More informationManaging Project Risk DHY
Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or
More informationGarfield County NHMP:
Garfield County NHMP: Introduction and Summary Hazard Identification and Risk Assessment DRAFT AUG2010 Risk assessments provide information about the geographic areas where the hazards may occur, the value
More informationIntegrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017
Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk
More informationWest Coast District Municipality. Risk Management Policy
West Coast District Municipality Risk Management Policy TABLE OF CONTENTS Page No. RISK MANAGEMENT POLICY 5 1. OVERVIEW 6 1.1. Policy Objective 6 1.2. Policy Statement 6 1.3. Risk Management Approach 6
More information