1 Caltrans Legal Division Contract Law Workshop San Diego, California March 21, 2007 PUBLIC-PRIVATE PARTNERSHIPS Fredric W. Kessler, Esq. Nossaman Guthner Knox & Elliott LLP The information contained herein does not constitute a legal opinion and should not be relied upon by the reader as legal advice or be regarded as a substitute for legal advice. Copyright, 2007 Nossaman Guthner Knox & Elliott, LLP. All Rights Reserved. 1 1

2 Overview Project Delivery Methods From DBB to PDA The Power of Concession Financing Types of Concessions Pre-Development Agreements Key Concession Contract Terms Protecting public sector while attracting private capital California Legislative Status 2 2

3 Project Delivery Methods: Public and Private Roles Method Design/ Construction O&M Financing Revenues Legal Authority GA Risk GA Control A. DBB GA/PS GA GA GA Y B. DB PS GA GA GA N C. DBOM PS PS GA GA N D. Availability Concession PS PS PS GA N E. Toll Concession PS PS PS PS N F. Prevelopment Agreement PS PS PS PS N GA Government Agency PS Private Sector 3 3

4 Project Delivery Methods: Design-Bid-Build as Base Case All projects are delivered through public-private partnerships just a question of degree! Most projects are delivered using the Design-Bid-Build model Public owner: Designs project to 100% PS&E Achieves environmental clearance Breaks project up into biddable scopes Pays all invoices out of allocated STIP funds, other tax revenues and/or bond proceeds Operates and maintains project itself or through separately procured contractors Provides design oversight and construction management Keeps integration, traditional construction contract risk, long term performance and revenue risks 4 4

5 Project Delivery Methods: Design-Bid-Build as Base Case Private Parties: Design project and perform construction under conventional contracts Have conventional rights to claims and change orders Alternatives frequently require special state legislation and, where federalized, sometimes exemptions from federal rules and statutes (e.g. SEP 14, SEP15) 5 5

6 Project Delivery Methods: Why Change? To justify deviating from the Base Case, P3 delivery method should offer advantages: Significantly accelerate project delivery Fix costs/completion date early in design phase; unlike Base Case Capture private sector innovation early in project development, especially in design, environmental and permitting processes Efficiently shift to private sector major risks and reduce claims which under Base Case would be government responsibility Encourage lifecycle cost efficiencies and quality facility performance over time Raise more capital to close funding gaps, deliver more mobility sooner 6 6

7 The Power of Concession Financing Equity Market appetite Factor Traffic and revenue projections Senior debt coverage ratios Subordinate debt coverage ratios Federal tax subsidies Tax exempt interest Depreciation / amortization Subordinate TIFIA debt Blended rate of interest on debt Maximum toll rates Yes Yes, if use PABs Yes Yes Concession Financing More aggressive Moderate to Conservative ( ) Moderate to liberal (1.1) Comparable (with PABs + TIFIA) Locked in by contract Strong market demand for debt and equity Tax Exempt Revenue Financing Conservative Conservative (1.25 +) Moderate to liberal (1.1) No Yes No Possible, but not likely Comparable Subject to political risk Deep, liquid bond market 7 7

8 The Power of Concession Financing Private Equity vs. Tax-Exempt Tax-exempt financing has more conservative debt coverage ratios (limits amount of debt Investor classes are different Private equity investors have sector expertise Private equity investors willing to take longer horizon view vs. typical year tax-exempt bond investors Surplus revenues not valued in tax-exempt structure, but highly valued by private equity Accelerated depreciation creates significant value for private equity that public sector cannot realize 8 8

9 The Power of Concession Financing What equity values (that tax-exempt financing doesn t) $ Surplus adds value Debt Service Operating Costs Y 40 Municipal bond investors rely on historical revenues to determine leverage levels, constraining total value for the owner Equity investors look for future returns based on growth Debt + Equity = Greater Proceeds for Owner of Asset 9 9

10 Types of Concessions Toll Concessions Availability Payment Concessions Asset Monetization Development Concession Mixed Concession Revenue Positive Revenue Negative 10

11 Types of Concessions Attributes of an Asset Monetization Long term lease and operation of existing facility ( Brownfield ) Operations, traffic and maintenance history Stable cash flows from tolls Stable expenses Lower risk profile for concessionaire in terms of traffic and revenue Buying a going concern Examples: Chicago Skyway, Indiana Toll Road 11

12 Types of Concessions Attributes of a Development Concession Project Characteristics Design, Construction, Operation of new facility ( Greenfield ) Long term lease No operations, traffic or maintenance history Unproven cash flows and expenses Reliance on cost estimates and traffic & revenue projections Higher risk profile for concessionaire Construction risk (delay and cost overruns) Traffic and revenue/start-up risk Higher risk profile requires higher return to investor Once past start-up, risks become similar to asset monetization 12

13 Types of Concessions Attributes of a Development Concession Nature of Competition Public partner defines project Clears it environmentally Achieves public consensus on project and PPP Validates financial feasibility Sets toll rate schedule Develops complete business and contract terms, technical specifications 13

14 Types of Concessions Attributes of a Development Concession Nature of Competition Qualifications submittal and short listing Industry workshops One-on-one proposal meetings Competing hard money bids Proposer assembles design, construction, O&M pricing and forces Proposer delivers firm equity/debt commitments Selection primarily a price competition Examples: Port of Miami Tunnel, Knik Arm Crossing 14

15 Types of Concessions Attributes of a Mixed Concession Combination of existing facility plus new construction Reconstruction Capacity Expansions e.g., managed lanes Project extensions Long term lease Examples VDOT Pocahontas Parkway TxDOT SH segments, 24 miles One segment operational and almost complete; one almost complete; two have frontage roads only; one in NEPA process $2.1B up-front payment; $700M NPV of annual lease payments $550M construction Revenue sharing, including refinancing gain Bank debt plus TIFIA; PABs as Plan B 15

16 Types of Concessions Revenue Positive Concessions Project revenues exceed: Capital costs Debt costs (interest, principal, reserves) O&M costs Handback/end of term costs Return to private partner Can result in upfront payment from private partner to public owner, revenue sharing, or both Examples: TxDOT SH 130, Segments 5&6 16

17 Types of Concessions Revenue Negative Concessions Project revenues insufficient to cover: Capital costs Debt costs (interest, principal, reserves) O&M costs Handback/end of term costs Return to private partner Competition based primarily on least amount of public funds needed 17

18 Types of Concessions Contract provides for how gap filled How, when, on what conditions is Owner or other $ funded - Progress, milestone, periodic, etc. It may provide for recapture of $ back to Owner if Project performs above a certain measure Can affect contract provisions on Owner oversight, performance security Examples: TxDOT IH 635, North Tarrant Express 18

19 Types of Concessions Attributes of an Availability Payment Concession Same as Toll Concession, except Public Owner Retains project revenues, if any, and related risks Pays private party based upon project availability and performance over extended period Private Party Assumes concession type risks, sometimes even usage risk, but not collection of tolls, cost of collection or total revenue collected Competition primarily based on lowest availability payments needed to deliver and operate project 19

20 Examples Types of Concessions Florida DOT Port of Miami Tunnel British Columbia MOT Sea to Sky Highway 20

21 Pre-Development Agreements Attributes of PDA Project characteristics PPP formed at beginning or during environmental process Complex, large development project Project configuration fluid Finance plan rudimentary or non-existent Preliminary T&R analysis done and suggests financial feasibility Public partner may lack funds, resources to progress project 21

22 Pre-Development Agreements Attributes of PDA Nature of Competition: Selection is qualifications based Project understanding Conceptual development and finance plans Track record Pricing of pre-development work Successful work earns exclusive right to negotiate concession agreement 22

23 Pre-Development Agreements PDA Examples Wide domestic use, little international use California - SR 125, SR 91 Virginia Pocahontas, I-81 Truck Lanes, I-95/395 HOT Lanes, Dulles Rail Corridor Texas TTC-35, SH 130 Segments 5& 6, TTC-69 Oregon Sunrise, Newberg Dundee, I 205 South Corridor Washington Tacoma Narrows 23

24 Pre-Development Agreements Comparison of PDAs and Toll Concessions Private partner participation in predevelopment work Project definition Environmental review Preliminary T&R work Investment grade T&R study Value engineering Stakeholder relations PDA Strategic partner Strong Technical and economic analysis Yes Yes Yes, all stages Possibly Toll Concession Minimal Role Weak None No Yes Only via Alternative Technical Concepts at proposal stage, and postaward design More limited 24

25 Pre-Development Agreements (cont d) (cont d) Technical specification development Financial planning analysis Nature of Competition Predevelopment contract Concession contract Transparency Predevelopment PPP Direct participation Yes Qualifications Sole source negotiation (price reasonableness analysis) Less Hard $ PPP Only via industry draft review and comment No N/A Price competition More 25

26 Key Concession Contract Terms: Quality Design, Construction, Operation and Maintenance P3 Approach Private partner designs, constructs, operates, maintains Private investors and lenders will not accept traditional public sector control How can public partner assure quality? 26

27 Key Concession Contract Terms: Quality Design, Construction, Operation and Maintenance Tools Performance-based measures and standards specify outcomes, and inspections to measure outcome achievement Private partner project management plan procedures, processes, quality management systems for all aspects of work. Subject to public partner approval Private partner responsibility for acceptance testing and inspection 27

28 Key Concession Contract Terms: Quality Design, Construction, Operation and Maintenance Tools Use of Independent Engineer Field inspections, monitoring and auditing Document review and audits for compliance with management plan and performance standards Verification testing (at lesser frequency than private partner s testing) Reporting to both parties Measures to assure independence 28

29 Key Concession Contract Terms: Quality Design, Construction, Operation and Maintenance Regular performance measurement inspections and reports by private partner to determine and maintain asset condition Public partner audit and monitoring of IE and private partner, and spot testing and inspection Renewal and replacement scheduling and reserves Handback requirements 29

30 Key Concession Contract Terms: Quality Design, Construction, Operation and Maintenance Changes in Standards What is private sector obligation to conform to future changes in standards? PPP solutions vary Conform at public partner s election and expense (cost and revenue impacts) Conform at private partner s expense Sharing of cost risk 30

31 Key Concession Contract Terms: Reasonable Tolling Structure and Profits Public sector needs: Maximize its income? Minimize toll rates? Prevent excessive profit? Manage traffic demand and congestion? Depoliticize setting toll rates? Toll exemptions for critical public purposes? Tools: Indexed toll rate schedule caps future toll rates, depoliticizes Set initial rates Use stated rates of increase and/or inflation indices for capping future toll rate adjustments CPI, GDP, GSP, ECI 31

32 Key Concession Contract Terms: Reasonable Tolling Structure and Profits Toll Pricing congestion management Dynamic toll rates varying by time of day, level of congestion SR91, San Diego, SH 121, IH 635 (managed lanes) Banded revenue sharing generates public partner revenues, prevents excessive profit Public partner takes escalating share of toll revenue as rate of return increases Examples: Pocahontas: 40% of real net cash flow after IRR on total investment = 6.5%; 80% after IRR=8.0% Segments 5 & 6: 4.65% of gross revenue until IRR on equity = 11%; 9.3% of next band of gross until IRR = 15%, 50% of all further gross 32

33 Key Concession Contract Terms: Reasonable Tolling Structure and Profits Shadow tolls and availability payments reduce or eliminate tolls, prevent excessive profits, depoliticize Toll exemptions / suspensions Police, fire, emergency vehicles Transit vehicles School buses Contractor vehicles Suspend tolls for mass evacuations, emergency traffic diversions 33

34 Key Concession Contract Terms: Balanced Approach to Competing Facilities Public Sector Need - right to build other projects over time to address traffic safety and system capacity issues Private Sector Need - protection of the originally expected revenue stream 34

35 Key Concession Contract Terms: Balanced Approach to Competing Facilities The Mistakes of SR91 Contract prohibited operation of competing facilities Exceptions too narrow Result: Private partner had, and exercised, legal right to enjoin expansion of free lanes on SR91 The Lessons Learned The sole remedy is $ to cover net revenue impact No right to enjoin. Public sector free to build whatever it wants 35

36 Key Concession Contract Terms: Balanced Approach to Competing Facilities Exceptions for: All projects identified in transportation plans All projects outside a competing facilities zone Improvements for safety, maintenance or operational purposes Certain capacity improvements ITS systems, metering devices, intersection grade separations, restriping that adds lanes HOV/HOT lane additions on other roadways Transit and other non-highway projects All projects outside public partner s control 36

37 Key Concession Contract Terms: Effective Remedies Scale remedies to the type and severity of breach Liquidated damages for delayed completion, noncompliance with routine covenants Owner step-in rights, including receivership Work suspension during construction Anticipatory breach and assurances of future performance for persistent default Termination for major uncured default Lender rights to notice and cure Termination compensation to private partner 37

38 California Legislative Status History AB 680 adopted in late 1980 s; repealed in 2004: SR-91 and SR-125 Local Government Authority: Gov. Code et seq. (City/County Development Agreements) Local Government Privatization Act of 1985 Gov. Code 5956 et seq. (AB 2660) Individual agencies with broad enabling legislation 38

39 California Legislative Status AB 1467 Chaptered May project pilot program 2 in No. Cal and 2 in So. Cal and at least 2 must be sponsored by local transportation agencies Key Provisions/Concepts Designed for goods movement projects Can only toll commercial or non-commercial vehicles with 3 or more axles Legislature can reject contract within 60 days after submission P3 Agreement must establish specific toll rates Investor can earn reasonable return Reversion to government agency No more SR 91 non-competes 39

40 California Legislative Status Issues with AB 1467 Post-award legislature involvement How much flexibility in terms of setting toll rates? Indexing? Congestion Pricing? What is a reasonable rate of return? Conveyance at expiration at no charge Government reimbursed for provision of services Non-compete clauses Is DB permissible? Prescriptive specs 40

41 California Legislative Status Where do we go from here. Amend AB 1467 to address issues Expand AB 1467 for other projects Seek new/other P3 legislation Regional agencies are key!! Specific project-focused legislation Runner Bill 41

42 CONTACT Fredric W. Kessler Partner Nossaman Guthner Knox & Elliott LLP 445 S. Figueroa Street, 31st Floor Los Angeles, CA (213)

47th Annual Workshop on Transportation Law

47th Annual Workshop on Transportation Law 47th Annual Workshop on Transportation Law Public Private Partnership Update: Legal Challenges and Obstacles - Protecting the Public Owner Implementation of the Texas Concessions Initiatives July 9, 2008

More information

Overview of Highway Public-Private Partnerships (P3s)

Overview of Highway Public-Private Partnerships (P3s) Overview of Highway Public-Private Partnerships (P3s) FHWA Office of Innovative Program Delivery Presentation to GBC Transportation & Mobility Committee March 11, 2015 Presentation Outline 2 Part 1 Part

More information

TRANSPORTATION RESEARCH BOARD. CONCESSIONS: A NEW FRONTIER? July 18, 2005 Portland, Oregon GEOFFREY S. YAREMA NOSSAMAN GUTHNER KNOX & ELLIOTT LLP

TRANSPORTATION RESEARCH BOARD. CONCESSIONS: A NEW FRONTIER? July 18, 2005 Portland, Oregon GEOFFREY S. YAREMA NOSSAMAN GUTHNER KNOX & ELLIOTT LLP TRANSPORTATION RESEARCH BOARD 44th ANNUAL WORKSHOP ON TRANSPORTATION LAW CONCESSIONS: A NEW FRONTIER? July 18, 2005 Portland, Oregon GEOFFREY S. YAREMA NOSSAMAN GUTHNER KNOX & ELLIOTT LLP The information

More information

The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships

The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships The Federal Perspective: Project Finance, TIFIA and Public Private Partnerships Mark Sullivan, Federal Highway Administration Innovative Transportation Finance Workshop Shoreview, Minnesota October 20,

More information

Florida Transportation Commission PUBLIC-PRIVATE PARTNERSHIPS (P3)

Florida Transportation Commission PUBLIC-PRIVATE PARTNERSHIPS (P3) Florida Transportation Commission PUBLIC-PRIVATE PARTNERSHIPS (P3) AGENDA Current Status in Florida Federal Reauthorization/ SEP-15 P-3 Options Overview Key aspects of P-3 Georgia Status P-3 Initiatives

More information

National Conference of State Legislatures

National Conference of State Legislatures National Conference of State Legislatures Spring Forum April 22 23, 2009 Pamela Bailey-Campbell Parsons Brinckerhoff What is a PPP? An Agreement Between the Public and Private Sector Parties that Transfers

More information

Public Private Partnerships 101

Public Private Partnerships 101 Public Private Partnerships 101 Tony Elkins, Commercial Director October 6, 2016 Cintra s LBJ Managed Lanes P3, Dallas, Texas The Ferrovial Group Development Over The Entire Infrastructure Lifecycle INFRASTRUCTURE

More information

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016 P3 CONTRACTS Morteza Farajian, Ph.D. November 2016 What is a Public-Private Partnership (P3)? Overview of P3s Definition P3 Defined A P3 involves a partnership between the public and private sector to

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

Transportation Infrastructure Finance and Innovation Act (TIFIA)

Transportation Infrastructure Finance and Innovation Act (TIFIA) Slide 1 Transportation Infrastructure Finance and Innovation Act (TIFIA) Reno Rail Corridor Port of Miami Tunnel SH 130 Jorianne Jernberg, Financial Analyst Office of Innovative Program Delivery Federal

More information

October 7, Introduction to the TIFIA Credit Program

October 7, Introduction to the TIFIA Credit Program October 7, 2015 Introduction to the TIFIA Credit Program Types of Credit Assistance 2 Secured (Direct) Loan Maximum term of 35 years from substantial completion Repayments must start 5 years after substantial

More information

Managed Lanes: Transaction Strategies from the PPP Forefront

Managed Lanes: Transaction Strategies from the PPP Forefront Managed Lanes: Transaction Strategies from the PPP Forefront December 2015 kpmg.com Managed Lanes: Transaction Strategies from the PPP Forefront 1 Introduction Managed lane projects have become an important

More information

PUBLIC-PRIVATE PARTNERSHIPS What? Why? Who? How? Where? and Here. I-77 HOT Lanes P3 Project. Lake Norman Transportation Summit March 13, 2013

PUBLIC-PRIVATE PARTNERSHIPS What? Why? Who? How? Where? and Here. I-77 HOT Lanes P3 Project. Lake Norman Transportation Summit March 13, 2013 PUBLIC-PRIVATE PARTNERSHIPS What? Why? Who? How? Where? and Here I-77 HOT Lanes P3 Project Lake Norman Transportation Summit March 13, 2013 Concession Getting past the jargon Turnkey BAFO RFQ BABs AFP

More information

Transportation Infrastructure Finance and Innovation Act (TIFIA) Program Overview

Transportation Infrastructure Finance and Innovation Act (TIFIA) Program Overview Transportation Infrastructure Finance and Innovation Act (TIFIA) Program Overview (general summary and overview only for full details, see 23 United States Code Section 601) TIFIA IS A CREDIT PROGRAM (not

More information

Description of the Submission / Conditions Precedent

Description of the Submission / Conditions Precedent Submittal Relating to the Development of the TxDOT North Tarrant Express Project, Segments 3A and 3B through a Facility Implementation Plan and Facility Agreement Description of the Submission / Conditions

More information

I-66 RFI Response Vinci Concessions USA 25 November 2013

I-66 RFI Response Vinci Concessions USA 25 November 2013 General: 1. Please describe your firm, its experience in relation to public-private partnership projects, and its potential interest in relation to the Project (e.g., design/engineering firm, construction

More information

THE USE OF FEDERAL INNOVATIVE FINANCE TECHNIQUES IN PUBLIC-PRIVATE PARTNERSHIPS THE CASE OF THE CAPITAL BELTWAY BY MARTIN J. LUBY

THE USE OF FEDERAL INNOVATIVE FINANCE TECHNIQUES IN PUBLIC-PRIVATE PARTNERSHIPS THE CASE OF THE CAPITAL BELTWAY BY MARTIN J. LUBY THE USE OF FEDERAL INNOVATIVE FINANCE TECHNIQUES IN PUBLIC-PRIVATE PARTNERSHIPS THE CASE OF THE CAPITAL BELTWAY BY MARTIN J. LUBY Compared with the rest of the world, the United States has been relatively

More information

AVAILABILITY PAYMENTS What Can We Learn from Surface Transportation Projects? Pamela Bailey Campbell President, LeighFisher

AVAILABILITY PAYMENTS What Can We Learn from Surface Transportation Projects? Pamela Bailey Campbell President, LeighFisher AVAILABILITY PAYMENTS What Can We Learn from Surface Transportation Projects? Pamela Bailey Campbell President, LeighFisher What IS a Availability Payment P3? Direct payments From public sector to private

More information

Introduction to Alternative Procurement Delivery

Introduction to Alternative Procurement Delivery Introduction to Alternative Procurement Delivery for Florida Transportation Commission January 24, 2013 TABLE OF CONTENTS Alternative Project Delivery (APD) US Market Overview APD Funding and Financing

More information

AGENDA ITEM #9 SUMMARY

AGENDA ITEM #9 SUMMARY AGENDA ITEM #9 SUMMARY Briefing on business considerations and state law requirements for the use of a comprehensive development agreement to develop a transportation project. Strategic Plan Relevance:

More information

Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co. April 22, 2008

Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co. April 22, 2008 MUNIROOT\V_NY\MuniVol0\Shared\Zach\PPP\Greg Carey's Speech for Texas Transportation Forum v4.10.08.doc effroz 11 Apr 2008 16:46 1/13 Solutions: Accelerating Infrastructure Projects Goldman, Sachs & Co.

More information

F = MA : CSG SLC WEBINAR DECEMBER 16, J. Douglas Koelemay, Director

F = MA : CSG SLC WEBINAR DECEMBER 16, J. Douglas Koelemay, Director F = MA : CSG SLC WEBINAR DECEMBER 16, 2014 J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation adopted 1995; PPEA followed PPTA implementation guidelines

More information

ACCESSING PRIVATE CAPITAL FOR TRANSPORTATION INFRASTRUCTURE PROJECTS

ACCESSING PRIVATE CAPITAL FOR TRANSPORTATION INFRASTRUCTURE PROJECTS ACCESSING PRIVATE CAPITAL FOR TRANSPORTATION INFRASTRUCTURE PROJECTS Transportation Infrastructure Finance Workshop Chicago, Illinois OVERVIEW AND KEY PLANNING FACTORS April 29, 2008 David Seltzer, Principal

More information

The Bond Buyers 8 th Annual Transportation Finance/P3 Conference

The Bond Buyers 8 th Annual Transportation Finance/P3 Conference The Bond Buyers 8 th Annual Transportation Finance/P3 Conference Highly-Leveraged Public Deals October 18, 2007 Brian Mayhew Chief Financial Officer MTC/Bay Area Toll Authority Is PPP The Answer Or Can

More information

Public-Private Partnerships for Transit

Public-Private Partnerships for Transit Public-Private Partnerships for Transit What is a P3? An agreement between public and private sector partners which allows more private sector participation than is traditional: Private sector may design,

More information

I-77 Managed Lanes Project Project Update. Ned Curran & Louis Mitchell September 2014

I-77 Managed Lanes Project Project Update. Ned Curran & Louis Mitchell September 2014 I-77 Managed Lanes Project Project Update Ned Curran & Louis Mitchell September 2014 Congestion and General Purpose lanes 2 Local Response CDOT NCDOT SCDOT MUMPO FHWA CATS Phase I: 2007 Phase II: 2008

More information

P3: OPPORTUNITIES FOR AMERICA S INFRASTRUCTURE. Greg Hummel

P3: OPPORTUNITIES FOR AMERICA S INFRASTRUCTURE. Greg Hummel P3: OPPORTUNITIES FOR AMERICA S INFRASTRUCTURE Greg Hummel Public Private Partnerships ( P3 ) Broadly refers to a variety of transactions in which a public or quasi-public entity shifts some degree of

More information

Irvine Corona Expressway Project Financing Review

Irvine Corona Expressway Project Financing Review Irvine Corona Expressway Project Financing Review Sperry June 4, 2010 1 The Proposed Irvine Corona Expressway (ICE) Project Project screening is key aspect of pre-development discussions Environmental

More information

Public-Private Partnerships and Innovative Finance

Public-Private Partnerships and Innovative Finance Public-Private Partnerships and Innovative Finance Agenda Brief Overview of P3 Lowell Clary, President Clary Consulting, LLC P3 and Innovative Finance 101 Lowell Clary Question/Answer Period Clary Background

More information

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment 1 EXECUTIVE SUMMARY The Transportation Agency for Monterey County (TAMC) Board commissioned a Level 2 Traffic and Revenue study on the feasibility of collecting tolls to fund the proposed new SR156 connector

More information

Highway Public-Private Partnerships

Highway Public-Private Partnerships Highway Public-Private Partnerships Securing Public Benefits and Protecting the Public Interest Presentation before the Enterprise Risk Management Symposium April 19, 2012 Steve Cohen Assistant Director

More information

Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads

Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads TRANSACTION ADVISORY SERVICES PPP ADVISORY Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads Alistair SAWERS, Head of Transport, PPP Advisory, Ernst & Young 1 Introduction Brownfield

More information

Public Hearing Tarrant County. April 14, 2009

Public Hearing Tarrant County. April 14, 2009 Public Hearing Tarrant County April 14, 2009 Public Hearing Agenda Welcome and Project Overview Ms. Maribel P. Chavez, P.E. District Engineer Texas Department of Transportation Fort Worth District 2 Public

More information

Preliminary Findings and Recommendations

Preliminary Findings and Recommendations Review of the Comprehensive Agreement between the North Carolina Department of Transportation and I-77 Mobility Partners LLC Preliminary Findings and Recommendations July 2017 Overview NCDOT has initiated

More information

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 )

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) VIRGINIA DEPARTMENT OF TRANSPORTATION ( VDOT ) VIRGINIA DEPARTMENT OF RAIL AND PUBLIC TRANSPORTATION ( DRPT ) RESPONSE TO REQUEST FOR INFORMATION

More information

April 25, Martin Klepper Executive Director

April 25, Martin Klepper Executive Director April 25, 2017 Martin Klepper Executive Director A New Formula for Infrastructure Investment The BUILD AMERICA BUREAU 2 Bureau Credit Programs Transportation Infrastructure Finance and Innovation Act (TIFIA)

More information

Finance Tools for Project Advancement

Finance Tools for Project Advancement Florida Department of TRANSPORTATION Finance Tools for Project Advancement Leon Corbett Project Finance Manager NCSL Southern States Fiscal Leaders September 23, 2016 Discussion Topics Public-Private Partnerships

More information

NEWBERG-DUNDEE TRANSPORTATION IMPROVEMENT PROJECT. Milestone 1 Final Report Feasibility Assessment

NEWBERG-DUNDEE TRANSPORTATION IMPROVEMENT PROJECT. Milestone 1 Final Report Feasibility Assessment NEWBERG-DUNDEE TRANSPORTATION IMPROVEMENT PROJECT Milestone 1 Final Report Feasibility Assessment C/O Macquarie North America Ltd. Suite 2664, 1055 Dunsmuir Street Vancouver, BC, V7X 1K8 Phone: (604) 605-3944

More information

Public Private Partnerships. Virginia GFOA s 2015 Fall Conference. prepared for. by JoAnne Carter, Managing Director.

Public Private Partnerships. Virginia GFOA s 2015 Fall Conference. prepared for. by JoAnne Carter, Managing Director. Public Private Partnerships prepared for Virginia GFOA s 2015 Fall Conference by JoAnne Carter, Managing Director October 21, 2015 4350 North Fairfax Drive, Suite 580 Arlington, Virginia 22203 2015 Public

More information

PPP s Misconceptions NICOLAS RUBIO US PRESIDENT, CINTRA

PPP s Misconceptions NICOLAS RUBIO US PRESIDENT, CINTRA PPP s Misconceptions NICOLAS RUBIO US PRESIDENT, CINTRA 1. PPPs involve the "sale" of roads to private interests 10 Myths and Facts on The Reason Transportation Foundation, May 31, 2011 - By Leonard PPPs

More information

Public Private Partnerships What is That??? Raymond Partridge, Program Manager July 17, 2013

Public Private Partnerships What is That??? Raymond Partridge, Program Manager July 17, 2013 Public Private Partnerships What is That??? Raymond Partridge, Program Manager July 17, 2013 Agenda What is a Public-Private Partnership? P3 Lessons Learned Locality Concerns Pop Quiz: Is this a P3 Project????

More information

Renegotiations & Bankruptcies in U.S. surface transportation P3s

Renegotiations & Bankruptcies in U.S. surface transportation P3s Renegotiations & Bankruptcies in U.S. surface transportation P3s Lisardo Bolaños Center for Transportation Public-Private Partnership Policy George Mason University http://p3policy.gmu.edu/ IRF Public

More information

Public Private Partnerships: Managing Risks, Unlocking Rewards

Public Private Partnerships: Managing Risks, Unlocking Rewards ABA Public Contract Law Section Public Private Partnerships: Managing Risks, Unlocking Rewards 3 rd Annual State & Local Procurement Symposium May 2, 2008, Austin, TX ABA Public Contract Law Section State

More information

Availability Payment or Revenue-Risk P3 Concessions? Pros and Cons for Highway Infrastructure

Availability Payment or Revenue-Risk P3 Concessions? Pros and Cons for Highway Infrastructure Reason Foundation Policy Study No. 458 November 2017 Availability Payment or Revenue-Risk P3 Concessions? Pros and Cons for Highway Infrastructure by Robert W. Poole, Jr. Reason Foundation Reason Foundation

More information

Texas' LBJ Freeway Managed Lanes P3

Texas' LBJ Freeway Managed Lanes P3 Texas' LBJ Freeway Managed Lanes P3 28/07/2010 The I-635/LBJ Managed Lanes project in Texas marks a major milestone in the development of private sector investment in infrastructure, standing as the largest

More information

PUBLIC PRIVATE PARTNERSHIPS Rationale and Motivation. November 2015 Nicolas Rubio US President, Cintra

PUBLIC PRIVATE PARTNERSHIPS Rationale and Motivation. November 2015 Nicolas Rubio US President, Cintra PUBLIC PRIVATE PARTNERSHIPS Rationale and Motivation November 2015 Nicolas Rubio US President, Cintra nrubio@cintra.us Agenda 1. The transportation infrastructure problem 2. Understanding the Private Sector

More information

Financial Submission

Financial Submission Financial Submission Prepared by NTE Mobility Partners Segments 2-4, LLC May 19, 2010 i Table of Contents 1 Feasibility of Financing Plan... 1 2 Introduction... 2 2.1 The Proposer... 2 2.2 Details of Equity

More information

Private Financing for Port Infrastructure

Private Financing for Port Infrastructure Private Financing for Port Infrastructure Presented at AAPA Port Real Estate Issues Workshop Seattle, WA September 18, 2018 Andrée M. Blais, Partner Infrastructure Practice Group Shant S. Boyajian, Associate

More information

Transportation Infrastructure Finance and Innovation Act (TIFIA)

Transportation Infrastructure Finance and Innovation Act (TIFIA) TIFIA Credit Program Overview Transportation Infrastructure Finance and Innovation Act (TIFIA) Updated September 27, 2006 Background on TIFIA Strategic goal to leverage limited Federal resources and stimulate

More information

Public-Private Partnerships Association of Government Accountants

Public-Private Partnerships Association of Government Accountants Public-Private Partnerships Association of Government Accountants Fall Education Seminar Bob Childree November 2010 America's Infrastructure Report Card America s Infrastructure Report Card (American Society

More information

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE I-95/395 HOV/HOT LANES PROJECT DATED AS OF JUNE 8, 2017 BY AND BETWEEN

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE I-95/395 HOV/HOT LANES PROJECT DATED AS OF JUNE 8, 2017 BY AND BETWEEN Execution Version AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE I-95/395 HOV/HOT LANES PROJECT DATED AS OF JUNE 8, 2017 BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of

More information

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG

AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG EXECUTION COPY AMENDED AND RESTATED COMPREHENSIVE AGREEMENT RELATING TO THE ROUTE 495 HOT LANES IN VIRGINIA PROJECT DATED AS OF DECEMBER 19, 2007 BY AND AMONG VIRGINIA DEPARTMENT OF TRANSPORTATION, an

More information

Public Private Partnerships and Infrastructure Finance: Policy and Recent Evidence

Public Private Partnerships and Infrastructure Finance: Policy and Recent Evidence Public Private Partnerships and Infrastructure Finance: Policy and Recent Evidence Presentation to: TRIWAY International Group October 8, 2016 Jonathan L. Gifford, Ph.D. George Mason University, Schar

More information

70 th Annual Meeting CSG WEST August 18 th, 2017

70 th Annual Meeting CSG WEST August 18 th, 2017 70 th Annual Meeting CSG WEST August 18 th, 2017 Rick Sulzer, P.E. Chief Operating Officer Over 25 years in Transportation Infrastructure Design, Manufacturing, Distribution, Construction and Maintenance

More information

North Carolina Department of Transportation Report to Joint Legislative Transportation Oversight Committee

North Carolina Department of Transportation Report to Joint Legislative Transportation Oversight Committee North Carolina Department of Transportation Report to Joint Legislative Transportation Oversight Committee Public Private Partnerships Policy and Document Standardization October 1, 2013 Executive Summary

More information

Nossaman Infra Insight

Nossaman Infra Insight Nossaman Infra Insight MAP-21: Surface Transportation Reauthorization Ushers in Significant Changes to TIFIA By: Fredric W. Kessler, Peter W. Denton, Nossaman LLP 07/06/12 On June 29, 2012 Congress passed

More information

P3 Financing. Barney Allison. Peter Luchetti. Alfonso Mendez. Partner, Nossaman LLP. Managing Partner, Table Rock Capital

P3 Financing. Barney Allison. Peter Luchetti. Alfonso Mendez. Partner, Nossaman LLP. Managing Partner, Table Rock Capital P3 Financing Barney Allison Partner, Nossaman LLP Peter Luchetti Managing Partner, Table Rock Capital Alfonso Mendez Senior Financial Advisor, Arup Typical P3 Financing Structure Project Company SPV P3

More information

AAPA Finance Seminar Seaport Project Financing

AAPA Finance Seminar Seaport Project Financing AAPA Finance Seminar Seaport Project Financing April 9, 2014 Presented by: David C. Miller, Managing Director Public Financial Management, Inc. 300 South Orange Avenue, Suite 1170 Orlando, Florida 32801

More information

Emerging Trends in Port Infrastructure: Using P3s to Maximize Value

Emerging Trends in Port Infrastructure: Using P3s to Maximize Value Emerging Trends in Port Infrastructure: Using P3s to Maximize Value Presented at AAPA Planning for Shifting Trade Program Tampa, FL 9:00 10:30 am, January 31, 2019 Brian G. Papernik, Partner Infrastructure

More information

I-77 Express Lanes Project Project Update. Rodger Rochelle October 2014

I-77 Express Lanes Project Project Update. Rodger Rochelle October 2014 I-77 Express Lanes Project Project Update Rodger Rochelle October 2014 Project Description In 2009, NCDOT conducted a Fast Lanes Study that analyzed 12 corridors in a 10 county region. The Charlotte City

More information

SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania

SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania January 2013 Table of Contents... 1 Introduction... 2 Project

More information

TxDOT SH 288 TOLL LANES PROJECT IN HARRIS COUNTY TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET

TxDOT SH 288 TOLL LANES PROJECT IN HARRIS COUNTY TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET TxDOT SH 288 TOLL LANES PROJECT IN HARRIS COUNTY TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET This document provides a summary of key terms and conditions for the toll concession Public

More information

Model Concession Agreement for Highways: An Overview

Model Concession Agreement for Highways: An Overview Model Concession Agreement for Highways: An Overview - Gajendra Haldea The highways sector in India is witnessing significant interest from both domestic as well as foreign investors following the policy

More information

GRAND PARKWAY TRANSPORTATION CORPORATION MONTHLY TRAFFIC AND OPERATING REPORT* For the Period Ending: September 30, 2017

GRAND PARKWAY TRANSPORTATION CORPORATION MONTHLY TRAFFIC AND OPERATING REPORT* For the Period Ending: September 30, 2017 TABLE OF CONTENTS SYSTEM REVENUE AND EXPENSES SYSTEM TRANSACTIONS PROCEEDS FROM SALE OF SYSTEM ASSETS FOOTNOTES TO PAGE 3 4 TOLL RATE SCHEDULE 6 OUTSTANDING OBLIGATIONS 7 TRUST ACCOUNT BALANCES & ACTIVITY

More information

U.S. Privatization Trends and the Ports Sector

U.S. Privatization Trends and the Ports Sector AAPA Port Property Management and Pricing Seminar - October 24, 2006 U.S. Privatization Trends and the Ports Sector Joshua Schaff Infrastructure Finance AGENDA 1. Moody s Port Sector Ratings 2. Privatization

More information

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN

COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN EXECUTION VERSION COMPREHENSIVE AGREEMENT RELATING TO THE TRANSFORM 66 P3 PROJECT DATED AS OF DECEMBER 8, 2016, BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of the Commonwealth of Virginia

More information

Fiscal Year th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017

Fiscal Year th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017 Fiscal Year 2017 4 th Quarter Report Quarterly Report of Actual Traffic and Revenue For period ending August 31, 2017 Footer Text Date Table of Contents Section Page Number Notes and Observations 3-4 Significant

More information

Value for Money (VfM) Analysis Virginia s experiences and lessons learned

Value for Money (VfM) Analysis Virginia s experiences and lessons learned Value for Money (VfM) Analysis Virginia s experiences and lessons learned May 28, 2013 Morteza Farajian Program Manager Virginia s Enabling P3 Legislation Public-Private Transportation Act of 1995 Intent

More information

DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED)

DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED) DRAFT REQUEST FOR QUALIFICATIONS RELATING TO THE TRANSFORM 66 P3 PROJECT UNDER THE VIRGINIA PUBLIC-PRIVATE TRANSPORTATION ACT OF 1995 (AS AMENDED) VIRGINIA DEPARTMENT OF TRANSPORTATION POSTED AUGUST 31,

More information

GRAND PARKWAY TRANSPORTATION CORPORATION MONTHLY TRAFFIC AND OPERATING REPORT* For the Period Ending: August 31, 2017

GRAND PARKWAY TRANSPORTATION CORPORATION MONTHLY TRAFFIC AND OPERATING REPORT* For the Period Ending: August 31, 2017 TABLE OF CONTENTS SYSTEM REVENUE AND EXPENSES SYSTEM TRANSACTIONS PROCEEDS FROM SALE OF SYSTEM ASSETS FOOTNOTES TO PAGE 3 4 TOLL RATE SCHEDULE 6 OUTSTANDING OBLIGATIONS 7 TRUST ACCOUNT BALANCES & ACTIVITY

More information

Florida Department of Transportation

Florida Department of Transportation JEB BUSH GOVERNOR Florida Department of Transportation 605 Suwannee Street, MS 07 Tallahassee, FL 32399 JOSE ABREU SECRETARY September 30, 2003 Dear MIC Partner: Attached is the third Annual Update of

More information

SH 183 MANAGED LANES PROJECT TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET

SH 183 MANAGED LANES PROJECT TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET SH 183 MANAGED LANES PROJECT TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET This document provides a summary of key terms and conditions for the toll concession Public Private Partnership

More information

Comprehensive Development Agreement State Highway 288 Toll Lanes in Harris County. Between Texas Department of Transportation and [ ]

Comprehensive Development Agreement State Highway 288 Toll Lanes in Harris County. Between Texas Department of Transportation and [ ] Comprehensive Development Agreement State Highway 288 Toll Lanes in Harris County Between Texas Department of Transportation and [ ] Dated [ ] PART A ARTICLE 1 TABLE OF CONTENTS THE TRANSACTION; FINANCING

More information

CAPITAL MAINTENANCE AGREEMENT I-2/I-69C INTERCHANGE PROJECT. between TEXAS DEPARTMENT OF TRANSPORTATION. and [DB CONTRACTOR] Dated as of:, 2019

CAPITAL MAINTENANCE AGREEMENT I-2/I-69C INTERCHANGE PROJECT. between TEXAS DEPARTMENT OF TRANSPORTATION. and [DB CONTRACTOR] Dated as of:, 2019 CAPITAL MAINTENANCE AGREEMENT I-2/I-69C INTERCHANGE PROJECT between TEXAS DEPARTMENT OF TRANSPORTATION and [DB CONTRACTOR] Dated as of:, 2019 HIDALGO COUNTY Texas Department of Transportation I-2/I-69C

More information

Charting a New Course? Infrastructure Investment Ahead. Bryan Grote

Charting a New Course? Infrastructure Investment Ahead. Bryan Grote Charting a New Course? Infrastructure Investment Ahead Bryan Grote January 11, 2017 What is the Infrastructure Plan? Potential Federal Incentives Investment Tax Credits? Wilbur Ross (Commerce), Peter Navarro

More information

OREGON DEPARTMENT OF TRANSPORTATION. Bear, Stearns & Co. Inc. Sperry Capital Inc. Oregon Innovative Partnership Program

OREGON DEPARTMENT OF TRANSPORTATION. Bear, Stearns & Co. Inc. Sperry Capital Inc. Oregon Innovative Partnership Program OREGON DEPARTMENT OF TRANSPORTATION Oregon Innovative Partnership Program : Analysis of the Proposed Concession Arrangement for the Newberg-Dundee Bypass Project June 15, 2007 Bear, Stearns & Co. Inc.

More information

Form DOT F (8-72) 7. Author(s) Thomas L. Glenn. 10. Work Unit No. (TRAIS) 16. Abstract

Form DOT F (8-72) 7. Author(s) Thomas L. Glenn. 10. Work Unit No. (TRAIS) 16. Abstract I. Report No. 2. Government Accession No. FHWA/TX-99/1756-3 4. Title and Subtitle SUGGESTED GUIDELINES FOR THE PREP ARA 1;ION OF FEASIBILITY STUDIES FOR PRlV ATE TOLL ROAD PROJECTS IN TEXAS 7. Author(s)

More information

St. Croix River Crossing Project: Innovative Financing Study. January 2011

St. Croix River Crossing Project: Innovative Financing Study. January 2011 St. Croix River Crossing Project: Innovative Financing Study January 2011 Cost of Completing this Study The consultant contract cost to complete this feasibility analysis and report was approximately $146,000.

More information

Transportation Revenue Options and State Funding Initiatives

Transportation Revenue Options and State Funding Initiatives M I D A M E R I C A A S S O C I A T I O N O F S T A T E T R A N S P O R T A T I O N O F F I C I A L S 2 0 1 3 A N N U A L M E E T I N G M I L W A U K E E, W I W E D N E S D A Y 1 7 J U L Y 2 0 1 3 WHAT

More information

UNITED STATES DEPARTMENT OF TRANSPORTATION INDICATIVE TERM SHEET FOR TIFIA LOAN AGREEMENT

UNITED STATES DEPARTMENT OF TRANSPORTATION INDICATIVE TERM SHEET FOR TIFIA LOAN AGREEMENT Draft 9/9/16 UNITED STATES DEPARTMENT OF TRANSPORTATION INDICATIVE TERM SHEET FOR TIFIA LOAN AGREEMENT TRANSFORM 66 P3 PROJECT (TIFIA APPLICATION FOR CREDIT ASSISTANCE NO. ) 1 The terms set forth herein

More information

Caution on New Jersey Turnpike and Parkway Deal

Caution on New Jersey Turnpike and Parkway Deal New Jersey Public Interest Research Group Caution on New Jersey Turnpike and Parkway Deal Six Public Interest Principles for Considering Toll Road Monetization A deal to monetize the New Jersey Turnpike

More information

Public Private Partnerships (PPPs) in North America The Advent of a Market

Public Private Partnerships (PPPs) in North America The Advent of a Market Public Private Partnerships (PPPs) in North America The Advent of a Market RBS North American Infrastructure Advisory and Finance optional client logo 24 June 2008 Sell-Side Driver: The PPP market, while

More information

Public-Private. League of Women Voters. Nick Farber, Operations Manager, High Performance Transportation Enterprise. April 3, 2018

Public-Private. League of Women Voters. Nick Farber, Operations Manager, High Performance Transportation Enterprise. April 3, 2018 -Private Partnerships 101 League of Women Voters Nick Farber, Operations Manager, High Performance Transportation Enterprise April 3, 2018 What is Driving the Need? Continued Growth 1991 2015 2040 3.3

More information

SH 249 EXTENSION PROJECT DRAFT COMPREHENSIVE MAINTENANCE AGREEMENT TERM SHEET DESCRIPTION OF SERVICES

SH 249 EXTENSION PROJECT DRAFT COMPREHENSIVE MAINTENANCE AGREEMENT TERM SHEET DESCRIPTION OF SERVICES SH 249 EXTENSION PROJECT DRAFT COMPREHENSIVE MAINTENANCE AGREEMENT TERM SHEET This document provides background information and summarizes the major terms of the Comprehensive Maintenance Agreement ( COMA

More information

ACTION ELEMENT CONCLUSIONS

ACTION ELEMENT CONCLUSIONS ACTION ELEMENT CONCLUSIONS The Action Element identifies all transportation projects within the horizon of the RTP/SCS and are financially constrained. This Action Element implements the Policy Element

More information

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD October 1, 2015 MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD This Term Sheet ( Term Sheet ) provides a summary of major business terms to be

More information

June 2, 2017 I Ratings

June 2, 2017 I Ratings Rating Methodology for ratings of road projects based on Hybrid Annuity Model (HAM) June 2, 2017 I Ratings Introduction: The Government of India has approved the hybrid annuity model (HAM) to increase

More information

EXECUTION VERSION JULY 31, 2012 COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF JULY 31, 2012 BY AND BETWEEN

EXECUTION VERSION JULY 31, 2012 COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF JULY 31, 2012 BY AND BETWEEN COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of the Commonwealth of Virginia AND 95 EXPRESS LANES LLC,

More information

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates.

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates. , Segments 2-4 Chapter 6: Preliminary Cost Estimates Table of Contents 6.1 Details of Facilities... 17 6.2 Pre-Development and Facility Feasibility... 1 6.2.1 Planning... 1 6.2.2 Environmental Mitigation...

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework The highways sector in India is witnessing a significant interest from both domestic as well as foreign investors following the policy initiatives taken by

More information

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee on Bridges & Structures April 19, 2010 1 Topics VDOT

More information

TO THE MEMBERS OF THE COMMITTEES ON GROUNDS AND BUILDINGS AND FINANCE: DISCUSSION ITEM EXECUTIVE SUMMARY

TO THE MEMBERS OF THE COMMITTEES ON GROUNDS AND BUILDINGS AND FINANCE: DISCUSSION ITEM EXECUTIVE SUMMARY Office of the President J1 TO THE MEMBERS OF THE COMMITTEES ON AND FINANCE: DISCUSSION ITEM For the Meeting of UPDATE ON THE 2020 PROJECT, MERCED CAMPUS EXECUTIVE SUMMARY This item provides an overview

More information

The challenge of paying for smart cities projects

The challenge of paying for smart cities projects The challenge of paying for smart cities projects 2 About John Skowron John has more than 25 years of experience in industry and management consulting. Within Deloitte Consulting LLP, he serves as the

More information

CASH MANAGEMENT & CONTRACT AWARDS

CASH MANAGEMENT & CONTRACT AWARDS CASH MANAGEMENT & CONTRACT AWARDS Brian Ragland, Chief Financial Officer Bill Hale, Chief Engineer Randy Hopmann, Director of District Operations Footer Text Date I. Cash Management Practices 2 FY 2018-2019

More information

77th OREGON LEGISLATIVE ASSEMBLY Regular Session. Enrolled. House Bill 2800 CHAPTER... AN ACT

77th OREGON LEGISLATIVE ASSEMBLY Regular Session. Enrolled. House Bill 2800 CHAPTER... AN ACT 77th OREGON LEGISLATIVE ASSEMBLY--2013 Regular Session Enrolled House Bill 2800 Sponsored by Representatives READ, BENTZ, Senators BEYER, STARR CHAPTER... AN ACT Relating to the Interstate 5 bridge replacement

More information

Public Private Partnerships

Public Private Partnerships Public Private Partnerships Dennis J. Enright Principal 201-656-0115 The PPP Decision 2 P3 Issues It s Greek to Me!! 3 Monetization Value for Money Project Finance Mezzanine Debt Weighted Average Cost

More information

ECONOMIC FEASIBILITY DEVELOPMENT PROCESS

ECONOMIC FEASIBILITY DEVELOPMENT PROCESS Approved: Effective: January 29, 2013 Office: Work Program & Budget Topic No.: 350-090-001-j Department of Transportation ECONOMIC FEASIBILITY DEVELOPMENT PROCESS PURPOSE: To implement the requirements

More information

Public-Private Partnerships. Lowell R. Clary

Public-Private Partnerships. Lowell R. Clary Public-Private Partnerships P3 Lowell R. Clary lclary@p3devco.com Types of P3s Design Build (DB) Asset Management Contract Design Build Operate Maintain (DBOM) Design Build Finance Operate (DBFO) Build

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018

I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018 I-80 Corridor Unsolicited Proposal Transportation Board Meeting December 3, 2018 UNSOLICITED PROPOSAL NDOT is actively addressing issues on I-80 Reno-Sparks Traffic Study (Completed Spring 2018) o Identified

More information