The Case for Schedule Risk Analysis

Size: px
Start display at page:

Download "The Case for Schedule Risk Analysis"

Transcription

1 The Case for Schedule Risk Analysis Francisco Cruz, PE, VDC Section Meeting February 19, 2015

2 Presentation Outline The Case for Project Risk Analysis Risk Analysis Approach Tools to Treat Risks Final Remarks There are lies, there are damned lies, and then there are deterministic schedules Attributed to Dr. Vivek Puri, PMA s resident simulation guru 2

3 Francisco Cruz - Background Senior Associate at PMA Consultants Based in Tampa, Florida Registered Professional Engineer (P.E.) in FL and PR BS in Civil Engineering, M.Eng. in Construction Management Experience of over 10 years spans pharmaceutical, infrastructure, airports, municipal, and mixed-used projects. Performing Cost and Schedule Risk Analysis on projects since 2007 on over 50 projects in 3 continents, ranging in size from less than $5 million to over $1 billion AACEi member since

4 The New Normal in Project Management Terminology: Risk Management Soup to nuts strategy for identifying and controlling project or program risks. Control (Monitor & Communicate) Risk Management Planning Assess (Identify & Analyze) Treat (Plan & Implement) *TCM Framework (Section 7.6) 4

5 The Case for Project Risk Analysis What are the three most common causes of cost overruns? * What are the three most common causes of delays? * Material Price Escalation 60% Poorly Defined Scope 57% Poorly Defined Scope 55% Design Creep 57% Contractual Disputes 40% Lack of Approvals 36% Time Delay 36% Contractual Disputes 34% Design Creep 32% Weather 21% Achieving Productivities 19% Time Delay 17% Lack of Approvals 6% Achieving Productivities 15% Weather 4% Material Price Escalation 13% Industrial Relations 2% Commissioning Process 2% Others 26% Others 19% * KPMG 2008 Global Construction Survey According to the Bent Flyvbjerg s Study on Large Projects, 9 out of 10 projects have cost overrun; Overrun is found across the 20 nations and five continents. Overrun is constant for the 70-year period covered by the study; cost estimates have not improved over time. 5

6 The Case for Project Risk Analysis What is the current performance in the construction industry? Did you have underperforming projects? Main causes of underperforming projects * KPMG Global Construction Survey

7 Deterministic vs Probabilistic Schedules Deterministic Schedule Consider the following simple 2-activity schedule: Start Activity A (12 weeks) Finish Activity B (10 weeks) 7

8 Deterministic vs Probabilistic Schedules Deterministic Schedule % critical = 100% Start Activity A (12 weeks) Finish Activity B (10 weeks) % critical = 0% Project always to finish in 12 weeks 8

9 Deterministic vs Probabilistic Schedules Probabilistic Schedule OPT MOST PESS Start Activity A (12 weeks) Finish Activity B (10 weeks) OPT MOST PESS Activity B has much more variability to the pessimistic side due to inherent risks of its work 9

10 Deterministic vs Probabilistic Schedules Probabilistic Schedule Start % critical = 63% OPT MOST PESS Activity A (12 weeks) P10: 11.3 weeks P50: 13.1 weeks P90: 15 weeks Finish Activity B (10 weeks) OPT MOST PESS % critical = 37% 10

11 The New Normal in Project Management Risk Assessment process through probabilistic modeling is the next step in Project Management Brings together and aligns stakeholders Vets and improves project scope, schedule and estimate Promotes recognition and transparency in project challenges Risk treatment reduces potential impacts Evaluates feasibility of targets 11

12 How is the Schedule Contingency Typically Determined? Similar Project History Expert Judgment (a.k.a. Well-reasoned Heuristics) Rule-of-Thumb Guidelines Parametric Modeling Statistical Methods through Probabilistic Simulations 12

13 PMA s Risk Assessment Approach Qualitative Assessment Critical & Risk-sensitive sequences Project Risks & Uncertainty Identify Schedule Summary Sequences, Probabilistic Branching Model Durations of Risks & Critical Activities Range OPRA NetRisk Simulate Simulate Summarize Review Prioritize Range Identify Estimate Issues, Possible Risks & Response Plans Cost Model Cost Breakdown, Variables, & or Crystal Ball Develop Ranges for Variables: Scope, Price, Productivity, & Duration Quantitative Assessment * First Introduced at the 2004 AACEi Annual Meeting 13

14 Risk Register Sample Risk Register used to prioritize risks and subsequently input in the quantitative model. 14

15 Risk Thresholds Figure 1: Defined Conditions for Probability Scales of a Risk Very Low Low Medium High Very High Probability 0% 10% 11% to 30% 31% to 50% 51% to 70% >70% Figure 2: Defined Conditions for Impact Scales of a Risk on Major Project Objectives Project Objective Very Low Low Medium High Very High Cost Time Scope Insignificant Cost Increase 0-2 Week Time Increase Scope Decrease Barely Noticeable <2% of TPC 3-6 Week Time Increase Minor Areas of Scope Affected 2-7% Cost Increase 7-12 Week Time Increase Major Areas of Scope Affected 8-15% Cost Increase Week Time Increase Scope Reduction Unacceptable to PA >15% Cost Increase >18 Week Time increase Project Does not Satisfy Original Intent at Completion Project team defines thresholds to classify risks and reduce subjectivity Quality Quality Degradation Barely Noticeable Only Most Demanding Specs Not Met Degradation Requires PA Approval Quality Reduction Unacceptable to PA Major Re-work Required to Complete Project 15

16 Prioritization Probability & Impact Matrix (P/I) Probability Threats VH H M L VL VL L M H VH Impact Probability-Impact Score Legend High = > 9 Med = 5-9 Low = 1-4 Tolerance Thresholds Tolerance is used to define Risk appetite of the organization 16

17 Output Example: Cumulative Probability Distribution Pre-treatment Results What about posttreatment analysis? The project schedule deterministic date of 16-Sep-14 is in the 24 th percentile of the simulation results distribution (including weather effects). 17

18 Tornado Diagram Risks Contemporaneous Method /SRA Duration Sensitivity RD11 - FHWA Design Exception for substandard geometry not received by Q2, % REN4 - NY Environmental permits not received by Q4'12 41% RD9 - Cash Collection is required in toll Lanes 40% RC20 - Restricted Work Hours may delay construction 36% RD2 - Procurement Process w ill take longer than 8 months therefore D/B contract w ill not... 26% RC23 - Modified Toll Plaza collection not accepted for Toll Plaza delaying Traffic 15% RD3 - Program not fully defined by Q1, % RC14 - Relocation of Know n/unknow n Utilities may cause cost and schedule overruns 12% RD1 - Design Package for Design Build w ill not be completed in Q2, % RRW7 - ULURP process w ill affect property acquisition in NY 4% 18

19 Risk Impact Analysis Helps determine impact of each risk on project schedule Distribution Analyzer Removing RD1 - Finish Date Removing RC14 - Finish Date Removing RC23 - Finish Date Removing RD2 - Finish Date Removing RC20 - Finish Date Removing REN4 - Finish Date Removing RD9 - Finish Date Removing RD11 - Finish Date All Risks - Finish Date Variation:13 Variation:128 Variation:19 Variation:144 Variation:82 Variation:73 Variation:111 Variation: % 80% Variation:5 Variation:54 Variation:85 Variation:119 Variation:59 Variation:25 Variation:72 Variation:127 60% 40% Cum ulative Probability 20% 22/ 09/ / 12/ / 04/ / 07/ / 10/ / 02/ / 05/ / 08/ / 12/ / 03/ / 06/ / 09/ / 01/ % 19

20 Output Example: End Node Diagram of Criticality In lieu of an unhelpful table of activities, a graphical representation of the activities most likely to influence project completion is provided. 20

21 Which percentile would you use for your project? Most public agencies and private companies use the P80 through P90 Some practitioners use a combination of two percentiles to set the baseline, schedule margin and management reserve (e.g., P50 and P80) ID Public Agency / Private Company Confidence Level Aerospace 1 NASA 70% Consultant 2 Hulett and Associates (Project Risk Consultants) 80% Energy 3 NorthWestern (Montana, Nebraska, North Dakota) 95% 4 US Energy Information Administration (EIA) 90% Food, Health & Environmental 5 FDA & USDA 95 99% 6 Forest Ecology and Management (Australia) 90% 7 Environmental Protection Agency (EPA) 90 & 95% 8 Environmental and Occupational Health Private Industry 95 98% Government 9 US Corps of Engineers (CoE) 80% 10 US Government Accountability Office (GAO) 70 80% 11 USGS 90% Military 12 Air Force 80% Nuclear 13 US Nuclear Regulatory Commission (NRC) 90, 95, 98% Oil & Gas 14 British Petroleum (BP) 50% (Adjusted Mean)*, 90%* 15 GeoGlobal Resources 90% 16 Marathon 80% Pharmaceutical 17 Johnson & Johnson 75 90% 18 AstraZeneca 80% 19 Siemens HealthCare 80% Software % Transportation 21 DOT 95% 22 FRA 95% 23 FTA 70 & 90% 24 MTA 80% 25 Wisconsin DOT 80% 26 FHWA Mean, Standard Deviation, 90 95% 27 PANYNJ 90% 28 WSDOT 90% 21

22 Comparing Results What Do Pre and Post-Treatment Results have in Common? 22

23 Tools to Treat Risks Value Engineering Constructability Reviews Project Delivery Systems Virtual Design and Construction 23

24 Risk Transfer Through Project Delivery Systems 1. Design/Bid/Build (DBB) a. Multiple-Prime Contracting 2. Design/Build (DB) a. Bridging b. Public Private Partnership (P3 or PPP) 3. Construction Management at Risk (CMAR or CM/GC) 4. Integrated Project Delivery * CMAA s An Owner's Guide to Project Delivery Methods 24

25 Risk Allocation Through Contract Types * RP-67R-11 Contract Risk Allocation 25

26 * 2014 Mortenson VDC Construction Analysis Report 26

27 Risk Monitoring and Control 27

28 Final Remarks Any project or contract schedule that is not risked through its life cycle does not conform to scheduling best practices Any schedule that does not expressly reserve reasonable schedule margin does not conform to best practices either Most deterministic schedules have less than 20% chance of meeting baseline dates; majority have even less than 1% chance. Post-treatment analysis is hardly ever performed; both pre and post-treatment analysis should be performed in tandem The use of VE, VDC, Constructability and Risk Management greatly increases the probabilities of project success 28

29 29

30 THANK YOU Francisco Cruz, PE, VDC Senior Associate PMA Consultants 30

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD http://pmsymposium.umd.edu 1 APPLICATIONS Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE 2018 Project Management Symposium Friday, May 11, 2018 9:45am

More information

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 6 Risk Planning Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study Guide book.

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Every project is risky, meaning there is a chance things won t turn out exactly as planned. PMBOK 5 Ed. DEI- Every project is risky, meaning there is a chance things won t turn out exactly as planned. percent of runaway projects Did no risk management at all 38 percent did some, and 7 percent

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

California Department of Transportation(Caltrans)

California Department of Transportation(Caltrans) California Department of Transportation(Caltrans) Probabilistic Cost Estimating using Crystal Ball Software "You cannot exactly predict an uncertain future" Presented By: Jack Young California Department

More information

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Qatar PMI Meeting February 19, 2014 David T. Hulett, Ph.D. Hulett & Associates, LLC 1 The Traditional 3-point Estimate of Activity

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management Project Management Professional (PMP) Exam Prep Course 11 - Project Slide 1 Project Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS Identify, Quantify, and 237 217 200 237 217 200 Manage 237 217 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112

More information

CRAVE. Cost Risk Assessment + Value Engineering. CSVA 2011 Conference Toronto, Ontario Nov 14-16, Ken L. Smith, PE, CVS

CRAVE. Cost Risk Assessment + Value Engineering. CSVA 2011 Conference Toronto, Ontario Nov 14-16, Ken L. Smith, PE, CVS CRAVE Cost Risk Assessment + Value Engineering CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Ken L. Smith, PE, CVS 1 HDRINC all rights reserved Topic Overview marketing statement, what is in it

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

The City of Tarpon Springs

The City of Tarpon Springs Prepared By: Carr, Riggs & Ingram August 29, 2018 The City of Tarpon Springs Contract Compliance Assessment of The Reverse Osmosis Water Treatment Facility Table of Contents Transmittal Letter... 1 Executive

More information

Project Management Certificate Program

Project Management Certificate Program Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Unit 9: Risk Management (PMBOK Guide, Chapter 11) (PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should

More information

Project Risk Management

Project Risk Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information

NTEGRATEDCOSTANDSCHEDULE

NTEGRATEDCOSTANDSCHEDULE E 57R09 SA M PL I NTEGRATEDCOSTANDSCHEDULE RI SKANAL YSI SUSI NGMONTE CARLOSI MULATI ONOFACPM MODEL AACE International Recommended Practice No. 57R-09 INTEGRATED COST AND SCHEDULE RISK ANALYSIS USING MONTE

More information

Introduction to Risk for Project Controls

Introduction to Risk for Project Controls Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management INSE 6230 Total Quality Project Management Lecture 6 Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project

More information

CONTINGENCY. Filed: EB Exhibit D2 Tab 2 Schedule 7 Page 1 of 10

CONTINGENCY. Filed: EB Exhibit D2 Tab 2 Schedule 7 Page 1 of 10 Exhibit D Tab Schedule 7 Page 1 of 10 1 4 5 6 7 8 9 10 11 1 1 14 15 16 17 18 19 0 1 4 5 6 7 8 9 CONTINGENCY 1.0 OVERVIEW Risk management is a systematic approach for proactively identifying, analyzing,

More information

Risk Assessment of the Niagara Tunnel Project

Risk Assessment of the Niagara Tunnel Project Canadian Society of Value Analysis October 24, 2006 Risk Assessment of the Presented by: David Eden, P. Eng., Ontario Power Generation Susan Sherman, P.Eng.,URS Canada Inc Overview Qualitative Risk Analysis

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Richard J. Long, P.E. and Rod C. Carter, CCP, PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

Probabilistic Benefit Cost Ratio A Case Study

Probabilistic Benefit Cost Ratio A Case Study Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 David T. Hulett, Ph.D, Hulett & Associates, LLC # 27809 Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 Integrated Cost-Schedule Risk Analysis 1 February 25, 2012 1 Based on AACE International

More information

PRINCE2 Sample Papers

PRINCE2 Sample Papers PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Managing Project Risks Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Abstract Nearly all projects have risks, both known and unknown. Appropriately managing

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration. Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An

More information

Prince2 Foundation.exam.160q

Prince2 Foundation.exam.160q Prince2 Foundation.exam.160q Number: Prince2 Foundation Passing Score: 800 Time Limit: 120 min PRINCE2 Foundation PRINCE2 Foundation written Exam Sections 1. Volume A 2. Volume B Exam A QUESTION 1 Which

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 574 580 Creative Construction Conference 2015 (CCC2015) A method for estimating contingency based on project complexity

More information

Information Technology Project Management, Sixth Edition

Information Technology Project Management, Sixth Edition Management, Sixth Edition Prepared By: Izzeddin Matar. Note: See the text itself for full citations. Understand what risk is and the importance of good project risk management Discuss the elements involved

More information

I -15 Mira Mesa/ Scripps Ranch Direct Access Ramp and Transit Station Cost Risk Management Report

I -15 Mira Mesa/ Scripps Ranch Direct Access Ramp and Transit Station Cost Risk Management Report 2011 I -15 Mira Mesa/ Scripps Ranch Direct Access Ramp and Transit Station Project Manager: Andrew Rice Design Manager: Gerard Chadergian Corridor Project Director I-15 TRANSNET: Gustavo Dallarda Pedro

More information

RISK Modelling Realistic Outcomes using Integrated Cost and Schedule Risk Analysis

RISK Modelling Realistic Outcomes using Integrated Cost and Schedule Risk Analysis RISK-2510 Modelling Realistic Outcomes using Integrated Cost and Schedule Risk Analysis Abstract Colin H. Cropley After several decades of development of project quantitative risk analysis for time and

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

A SIMPLE METHOD OF RISK/HAZARD ASSESSMENT IN DREDGING

A SIMPLE METHOD OF RISK/HAZARD ASSESSMENT IN DREDGING A SIMPLE METHOD OF RISK/HAZARD ASSESSMENT IN DREDGING T. M. Verna 1 and L. A. Prieto-Portar 2 ABSTRACT The assessment of the hazards and assignment of risk of each activity of a project is an important

More information

Risk Assessment and Management for Large Infrastructure Projects. Outline

Risk Assessment and Management for Large Infrastructure Projects. Outline Risk Assessment and Management for Large Infrastructure Projects Travis McGrath, Ph.D., P.E. Bill Roberds, Sc.D. Alan Keizur Chuck Lockhart, P.E. 1 Outline Probabilistic, Risk-Based Integrated Cost and

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

An overview of budget contingency calculation methods in construction industry

An overview of budget contingency calculation methods in construction industry Creative Construction Conference 2014 An overview of budget contingency calculation methods in construction industry Payam Bakhshi a*, Ali Touran b a Assistant Professor, Wentworth Institute of Technology,

More information

M_o_R (2011) Foundation EN exam prep questions

M_o_R (2011) Foundation EN exam prep questions M_o_R (2011) Foundation EN exam prep questions 1. It is a responsibility of Senior Team: a) Ensures that appropriate governance and internal controls are in place b) Monitors and acts on escalated risks

More information

APPENDIX 1. Transport for the North. Risk Management Strategy

APPENDIX 1. Transport for the North. Risk Management Strategy APPENDIX 1 Transport for the North Risk Management Strategy Document Details Document Reference: Version: 1.4 Issue Date: 21 st March 2017 Review Date: 27 TH March 2017 Document Author: Haddy Njie TfN

More information

SAMPLE. CPM SCHEDULE RISK MODELING AND ANALYSIS: SPECIAL CONSIDERATIONS TCM Framework: 7.6 Risk Management

SAMPLE. CPM SCHEDULE RISK MODELING AND ANALYSIS: SPECIAL CONSIDERATIONS TCM Framework: 7.6 Risk Management E 64R11 SA M PL CPMSCHEDULERI SKMODELI NG ANDANAL YSI S:SPECI AL CONSI DERATI ONS AACE International Recommended Practice No. 64R-11 CPM SCHEDULE RISK MODELING AND ANALYSIS: SPECIAL CONSIDERATIONS TCM

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

CEVP Cost Estimate Validation Process

CEVP Cost Estimate Validation Process CEVP Cost Estimate Validation Process CSVA Conference 2004 Monica Bielenberg, P.E. Program Manager Why an Estimate is Not a Number Estimates are uncertain... Ultimate project cost and schedule cannot be

More information

Improving the Cost Estimating Capability at the Federal Aviation Administration (FAA)

Improving the Cost Estimating Capability at the Federal Aviation Administration (FAA) Improving the Cost Estimating Capability at the Federal Aviation Administration (FAA) Federal Aviation Administration Presented to: 2007 International Society of Parametric Analysts (ISPA) and Society

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales The PRINCE2 Practitioner Examination Sample Paper TR Answers and rationales For exam paper: EN_P2_PRAC_2017_SampleTR_QuestionBk_v1.0 Qu Correct Syll Rationale answer topic 1 A 1.1a a) Correct. PRINCE2

More information

L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik

L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik Projektledning och Projektmetodik 1 Project Risk Management Project risk management is the art and science of identifying, assigning, and responding to risk throughout the life of a project and in the

More information

Mitigating Delay Claims and Scheduling Best Practices

Mitigating Delay Claims and Scheduling Best Practices Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las

More information

Chapter-8 Risk Management

Chapter-8 Risk Management Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not

More information

6 th September not protectively marked 1

6 th September not protectively marked 1 Establishing Risk Management processes in UK Nuclear New Build - (inc Enterprise Risk Management & Probabilistic Cost & Schedule Risk Analysis processes) 6 th September 2016 not protectively marked 1 Introductions

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

Federal Transit Administration United States Department of Transportation Washington, DC 20590

Federal Transit Administration United States Department of Transportation Washington, DC 20590 Discrete Distributions Probability 0.3 0.25 0.2 0.15 0.1 0.05 0 1 2 3 4 5 Time (mos) (days) or Costs ($000) Project Cost, Mitigated and Opportunities Realized PROBABILITY Project Cost, Unmitigated PROJECT

More information

Public Private Partnerships 101

Public Private Partnerships 101 Public Private Partnerships 101 Tony Elkins, Commercial Director October 6, 2016 Cintra s LBJ Managed Lanes P3, Dallas, Texas The Ferrovial Group Development Over The Entire Infrastructure Lifecycle INFRASTRUCTURE

More information

The Risky Business of. Risk Management

The Risky Business of. Risk Management The Risky Business of Risk Management 1 About Me: Jan Holt, PMP Project Management Professional (PMP) since 2005 Project Management Institute (PMI) Michiana Chapter President PMP Prep Class Instructor

More information

MassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer

MassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer MassDOT Highway ACEC State Markets Conference April 5, 2018 Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer About MassDOT Highway 9,561 Lane Miles of Interstate, Numbered

More information

ECONOMIC CAPITAL MODELING CARe Seminar JUNE 2016

ECONOMIC CAPITAL MODELING CARe Seminar JUNE 2016 ECONOMIC CAPITAL MODELING CARe Seminar JUNE 2016 Boston Catherine Eska The Hanover Insurance Group Paul Silberbush Guy Carpenter & Co. Ronald Wilkins - PartnerRe Economic Capital Modeling Safe Harbor Notice

More information

Il Risk Management nei progetti chiavi in mano Saipem

Il Risk Management nei progetti chiavi in mano Saipem Il Risk Management nei progetti chiavi in mano Saipem Convegno AICQ-CI La qualità e la sicurezza nelle infrastrutture Roma, 6 dicembre 2018 G. Gentile gennaro.gentile@saipem.com AGENDA Today s Presentation

More information

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and

More information

Making Choices. Making Choices CHAPTER FALL ENCE 627 Decision Analysis for Engineering. Making Hard Decision. Third Edition

Making Choices. Making Choices CHAPTER FALL ENCE 627 Decision Analysis for Engineering. Making Hard Decision. Third Edition CHAPTER Duxbury Thomson Learning Making Hard Decision Making Choices Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 4b FALL 23 By Dr. Ibrahim. Assakkaf

More information

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects GOLDEN EARS BRIDGE Alternative Transportation Financing ITE Quad Conference - May 2009 Fred Cummings Vice-President, Major Construction Projects Golden Ears Bridge Project Context/Project Overview Project

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

Title of the Paper: Integrating Management and cost management to arrive at a realistic Estimate at Completion Theme: Project Management leadership -> To accelerate Economic Growth Keywords: Cost overrun,

More information

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1 Table of Contents Economic Uncertainty Analysis....0 Chapter Overview.... Probabilistic Analysis with Scenarios..... Methodology...... Determination of Highest Impact Factors...... Combinations of Highest

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Running Head: RISK MANAGEMENT PLAN 1

Running Head: RISK MANAGEMENT PLAN 1 Running Head: RISK MANAGEMENT PLAN 1 Project Risk Management Plan ERAU Students Embry-Riddle Aeronautical University PMGT 613 Assessing and Managing Project Risk RISK MANAGEMENT PLAN 2 Abstract This paper

More information

Scouting Ireland Risk Management Framework

Scouting Ireland Risk Management Framework No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015

More information

Costing and Budgeting. From cost to value: methods and techniques to set the right cost to software

Costing and Budgeting. From cost to value: methods and techniques to set the right cost to software Costing and Budgeting From cost to value: methods and techniques to set the right cost to software Goals of the Unit Questions you might face: How much does the development of the software cost? Is the

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

PROJECT MANAGEMENT IS RISK MANAGEMENT AND RISK MANAGEMENT IS PROJECT MANAGEMENT

PROJECT MANAGEMENT IS RISK MANAGEMENT AND RISK MANAGEMENT IS PROJECT MANAGEMENT PROJECT MANAGEMENT IS RISK MANAGEMENT AND RISK MANAGEMENT IS PROJECT MANAGEMENT CMAA Breakfast Session 18 December 2019 INTRODUCTION OF PRESENTERS Eric Lowther Jerry Klanac Years with PMA 22 29 PMA Home

More information

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE INTRODUCTION: Project Management for Engineering and

More information

Remediation and Liability Cost Estimating. Ken Lyon Advisian, WorleyParsons Group RemTech 2015, October 14, Banff, AB

Remediation and Liability Cost Estimating. Ken Lyon Advisian, WorleyParsons Group RemTech 2015, October 14, Banff, AB Remediation and Liability Cost Estimating Ken Lyon Advisian, WorleyParsons Group RemTech 2015, October 14, Banff, AB Subtitle: Unravelling a tangle of string Consultant: We found contamination. Site Owner/Operator:

More information

AACE Chinook Dinner Meeting Calgary, Alberta, Canada Projects, Risks and Contingency

AACE Chinook Dinner Meeting Calgary, Alberta, Canada Projects, Risks and Contingency AACE Chinook Dinner Meeting Calgary, Alberta, Canada Projects, Risks and Contingency Riskcore Calgary March 2017. Quotes He who is not courageous enough to take risks will accomplish nothing in life The

More information

A Second Runway for Gatwick Appendix. A21 Programme Risk Management

A Second Runway for Gatwick Appendix. A21 Programme Risk Management A Second Runway for Gatwick Appendix A21 Programme Risk Management London Gatwick Airport Expansion Airport Commission Programme Risk Management Report Turner & Townsend 7 Savoy Court London WC2R 0EX

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Exam Questions PMI-SP

Exam Questions PMI-SP Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,

More information

Risk Based Estimating and Management at

Risk Based Estimating and Management at Risk Based Estimating and Management at 2010 Capacity Building peer exchange August 11-13, 2010 Terry Berends, PE 1 Assistant State Design Engineer 2 Overview Risk Based Estimating @ WSDOT Risk Management

More information

GRAEME JOHNSEN Project Manager

GRAEME JOHNSEN Project Manager GRAEME JOHNSEN Project Manager Project Manager with MMK Consulting Inc. (2011-Present) Seven years management consulting experience specializing in business strategy, economics, and financial evaluations

More information