NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

Size: px
Start display at page:

Download "NATIONAL ENERGY REGULATOR OF SOUTH AFRICA"

Transcription

1 NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS FOR THE FINANCIAL YEAR 2011/12 DECISION On 25 November 2010, the Energy Regulator decided as follows: 1. A guideline increase of 20.38% is approved for the 2011/12 municipal tariff review process. The 20.38% guideline increase is based on the following assumptions: municipal bulk purchase cost of 70%; bulk electricity purchase price increasing by 26.71% ; salaries and wages increasing by the assumed 2011/12 Consumer Price Index (CPI) 1 of 4.8% plus 2% as per the agreement between Local Government and its unions 2 ; and repairs and maintenance, capital charges and other costs increasing by the assumed inflation forecast of 4.8%. 2. The benchmarks for the 2011/12 financial year are approved as follows: Domestic Domestic Domestic Domestic Commercial Commercial Industrial Block 1 Block 2 Block 3 Block 4 Prepaid c/kwh 0 50kWh kWh kWh >600kWh 2000kWh 2000kWh 43800kWh RED RED RED RED RED RED National Treasury Forecasted Figure based on the Medium Term Budget Policy Statement (MTBPS) of 27 October This was confirmed with the South African Local Government Association (SALGA) Page 1 of 23

2 3. The Municipal Tariff Assessment timelines (aligned to the National Treasury Budgetary Process) are approved as presented in Annexure 1. 3 End. 3 It is important to note that in order for NERSA to adhere to these timelines, and/ for these timelines to be effectively implemented, the onus is on the licensees to ensure the timeous submission of their 2011/12 tariff applications. Page 2 of 23

3 REASONS FOR THE DECISION BACKGROUND AND INTRODUCTION 4. On an annual basis, NERSA calculates an appropriate tariff guideline increase, which is then communicated to municipal distributors as a guide in determining their annual electricity tariffs. 5. This guideline does not preclude a distributor from the legal obligation to apply to the Energy Regulator for tariff increases before implementation. 6. NERSA also reviews the tariff benchmarks and recommends new benchmarks that would be used in the evaluation of the municipal tariff evaluations. 7. In order to assist municipalities in meeting their budgeting process timelines and to ensure timeous submission of their tariff applications, NERSA embarked on a consultative process to ensure the finalisation of the 2011/12 municipal guideline increase at a much earlier time than previously done. 8. The fact that the determination on Eskom s second Multi-Year Price Determination (MYPD2) was already approved by the Energy Regulator in February 2010, makes it possible to have the determination of municipal tariff guideline and the application process approved much earlier than the previous years. The plan takes into account National Treasury s budgetary processes as well as NERSA s Information Resource Management (IRM) department in the collection and processing of Distribution Information Forms (D-forms) from licensees. 9. The Energy Regulator made decisions on the following matters: o o o the 2011/12 municipal tariff guideline in line with the decision on Eskom s application for the MYPD2; the 2011/12 municipal tariff benchmarks that are used in guiding average tariff levels; and the 2011/12 municipal tariff application process timelines. THE DECISION MAKING PROCESS 10. On 15 September 2010 the Energy Regulator approved the publication of the indicative municipal guideline consultation paper. This was published on NERSA s website on 16 September 2010 with an invitation to stakeholders for comments. The closing date for comments was 4 October Page 3 of 23

4 11. On 7 October 2010, the Energy Regulator held a public hearing, where stakeholders presented their views relating to the indicative guideline. 12. The issues raised in the written comments and at the public hearing have been considered in the determination. 13. On 25 November 2010, the Energy Regulator made its final decision on the municipal guideline and benchmarks and the municipal tariff application process timelines for the 2011/12 financial year. THE OBJECTORS AND OTHER INTERVENING PARTIES 14. On 19 and 20 September 2010, NERSA published a notice in national newspapers inviting stakeholders to comment on the NERSA consultation paper titled: Determination of the municipal tariff guideline and revision of municipal tariff benchmark for the 2011/12 financial year. 15. Prior to the finalization of the aforementioned document a meeting was held with National Treasury to discuss the basis and the components of the guideline increase. 16. On 21 September 2010 a workshop/meeting was held with the Association of Municipal Electricity Undertakings (AMEU) on this topic. 17. A total of 11 stakeholder comments were received. These were made up of comments from four municipalities namely: City of Cape Town, Langeberg, Buffalo City and Ethekwini. Other stakeholders who sent written comments were namely: The Association of Municipal Electricity Undertakings (AMEU), South African Local Government Association (SALGA), Southern Cape Karoo Electricity Forum, Institute for Municipal Finance Officers (IMFO), Sustainable Energy Africa (SEA), Power Measurement and Distribution (PM&D) and F M Smit trading as FSI Services. 18. A total of six verbal representations were made by various stakeholders during the public hearing held by NERSA, namely: AMEU, SALGA, IMFO, Ethekwini municipality, Steel and Engineering Industries Federation of South Africa (SEIFSA) and the Southern Cape Karoo Electricity Forum. ANALYSIS OF STAKEHOLDER COMMENTS 19. The following section deals with the comments received and issues raised by stakeholders together with NERSA s analysis of these issues. a) Approach used in determining the guideline Stakeholder Comments 20. It is inappropriate for NERSA to act as if the establishment of Regional Electricity Distributors (REDs) is already under implementation. Page 4 of 23

5 21. The analysis done towards determining benchmark weight, and the resultant averages should be categorised into metros, secondary and smaller municipalities. 22. The determination of the guideline was based on a random selection of D- forms and averaging is fundamentally flawed as each municipality has its own unique networks, customer bases, consumption and challenges. 23. There is no mention of tariffs to promote energy efficiency yet it is known that this is an inevitable shift for tariffs in future. 24. The proposed cost structure assumptions (i.e. bulk purchases, salaries, maintenance etc.) can be used as a starting point when determining the increase applicable for a municipality, however municipalities should be allowed to show the actual costs incurred based on the budgets and these should be used, if proven legitimate. NERSA Analysis 25. EDI Holdings was mandated by the Department of Minerals and Energy with the purpose of restructuring the Electricity Distribution Industry (EDI). In order to ensure that this is carried forward, EDI Holdings established the REDs. NERSA adopted this concept and has managed over the past few years to strive to rationalise tariffs in line with the RED structure. Without a specific policy direction, it is not advised to move away from this concept. 26. NERSA acknowledges that a one size fits all approach is not an ideal one, however given the uniqueness of each entity, categorising municipalities per size (i.e. metros, medium and small municipalities) would still not achieve a perfect fit for all 189 licensees. An ideal situation will only result when each municipality is assessed individually based on its unique cost structure and load profile. It must be noted though, that this approach would counter the uniformity that NERSA is striving to achieve within municipalities in a RED boundary. Further, in analysing applications, NERSA does consider each municipality s unique characteristics and challenges. 27. The graph below highlights the different cost structures of the various municipalities based on a sample including of metros, medium-sized and small municipalities. It highlights that the bulk purchase cost component varies from one municipality to the other regardless of the size of the municipality. The graph also illustrates that the NERSA-determined level of 70% for the bulk purchase costs, which is based on a method of averaging, is currently the optimal solution available, as it represents the mid- point for the majority of municipalities. The same principle is applicable to the rest of the cost components (repairs and maintenance, other costs etc.). Page 5 of 23

6 Page 6 of 23

7 28. Furthermore, a study on the categorisation of municipalities would require extensive research and consultation which would impact on the timelines for the finalisation of the guideline increase for 2011/12. Given this time constraint, NERSA could not undertake such a study in this financial year. NERSA will consider this in the 2012/13 financial year. 29. Apart from the above, another positive step taken by NERSA in trying to assess municipalities individually is the introduction of the rate of return methodology for large metros which is effective from July NERSA fully supports the implementation of tariff structures that promote energy efficiency e.g. time-of-use tariffs. Furthermore, while the primary objective of the IBT as introduced by NERSA in 2010/11 is protection of the poor, the secondary objective is promotion of energy conservation. 31. With regard to paragraph 24 above, it must be noted that although NERSA determines an average guideline increase applicable to municipalities, NERSA does consider municipalities with different cost structures (higher than guideline increase) on a case-by-case basis. However, the responsibility is on the municipality to demonstrate these differences in its cost structure, to NERSA. These municipalities are also required to give a presentation at a public hearing wherein they are required to further motivate their case. Reasons commonly accepted by NERSA for higher than guideline increases include the following: extensive repairs and maintenance programmes; capital expenditure programmes; need for additional funds due to the need to fill in critical vacancies (increased human resource costs); rationalisation and restructuring of tariffs: allowing municipalities with low tariff levels to increase by above the applicable guideline in order to bring them in line with the tariff benchmark levels of the respective REDs; municipalities facing serious financial challenges and municipalities placed under administration and any other special electricity related project that a municipality undertakes such as Demand Side Management (DSM) initiatives. Finally, when above the guideline increases are granted, there are certain conditions imposed on these municipalities. These include the need to ringfence the additional funds granted and reporting on a regular basis on progress made on these projects. NERSA further monitors these conditions to ensure compliance. Page 8 of 23

8 b) Views on other costs Stakeholder Comments 32. Municipalities are often highly dependent on revenues from electricity sales which are used to subsidise other services. It is unclear if the other costs category includes such revenues beyond electricity sector costs, and what ranges of costs would be acceptable in tariff design. 33. The contribution to the rates account or surcharge should be excluded from the cost structure and definitely not be included in the category other cost. By including it in the cost structure NERSA is effectively regulating provision that falls out of their regulatory competence. 34. With aging infrastructure, a municipal percentage of a total cost of 8% and an expected increase of 6% is not sufficient. The rapid increase in the rate and severity of deterioration is becoming a problem for municipalities that are not replacing network infrastructure when it is past its expected working life. 35. The notion that other costs are more than repairs and maintenance and should therefore be reduced is incorrect. These are real expenses over which electricity departments in many cases do not have control, over such as administrative charges by the municipality. The unilateral change of other costs from 10% to 8% cannot be supported unless proper research regarding the cost that represents the 10% has been conducted. NERSA Analysis 36. Below is NERSA s definition of other costs and it includes the following cost components: contribution to capital, contribution to funds i.e. o capital development fund, o tariff equalisation renewal fund, o bad debt reserve, o maintenance provision, and o other costs; charges allocated from other municipal departments, charges allocated to other municipal departments and general expenses. The definition above illustrates that Contribution to rates account and all municipal surcharges do not form part of the Other costs structure, as it is perceived. Page 9 of 23

9 37. Repairs and maintenance in the cost structure refers to normal planned maintenance and according to NERSA s guideline, 6% of the total costs is allowed for this cost category. Any other maintenance that is of extraordinary nature (e.g. dealing with backlog maintenance) is dealt with and considered separately and must be motivated for by the municipality. Furthermore, extensive capital expenditure projects are also considered separately and do not form part of the cost structure again these projects must be properly motivated for by the municipality. 38. According to the 2011/12 guideline, NERSA has indeed shifted the percentage weightings of the different cost elements. The other costs cost element has been decreased by two percentage points, to 8%. This was done to make allowance for higher costs, particularly for repairs and maintenance and capital charges, and is a measure to encourage municipalities to address their significant repairs and maintenance backlogs and aging infrastructure needs. This concept is also supported by the South African Local Government Association who stated that: The Electricity Distribution business has an obligation to financially contribute to Other costs, however, weighted against the need to invest more in infrastructure, and given the current state of infrastructure, the proposal to reduce the weight on Other costs is supported. c) Views on arrear debt Stakeholder Comments 39. The 0.5% provision is not adequate to address the problem at hand. Many municipalities have debtors days of more than 120 days, and outstanding non-current debt exceeding 50% of its annual revenue. A very large percentage of this money can or will not be recovered. The bad debt provision will thus have to be much more. 40. There are clear stipulations in GRAMAP and Municipal Finance Management Act (MFMA) of how bad debt should be addressed. It is therefore proposed that municipalities make the required provisions as allowed for in the legislation / regulations and submit this to NERSA. 41. The benchmark for bad debt should be in terms of electricity revenue and not the total revenue of the municipality. In this regard, 5-10% of electricity revenue would be appropriate. NERSA Analysis 42. The following are NERSA s definitions of bad debts and arrear debts: Bad debts are debts that will remain uncollectable and therefore written off at the end. Page 10 of 23

10 Bad debts forms part of the other operating costs, but the municipality must manage them in a manner that will not sacrifice the overall efficiency of the electricity trading account. Arrear debts are debts that have not been paid and remain due or owed. 43. Due to the aforementioned comments received by stakeholders, it is necessary for all licensees to provide NERSA with their current levels of arrear debt (as per the above definition) for 2010/11. This will enable NERSA to accurately determine the optimal levels of debt and thereby set the appropriate targets for 2011/12. d) Cross-subsidisation between customer categories Stakeholder Comments 44. The current NERSA proposals for IBTs for all domestic customers is rejected in its totality as: it does not comply with current policy, it is not practically implementable; and the negative impact is not sustainable. This is a subject that needs a separate debate which is ongoing between NERSA and AMEU. 45. The cross-subsidy to the low income consumers remains important and should be encouraged and preserved in addition to the Free Basic Electricity (FBE). 46. Cross subsidisation does not only subsidise indigent customers. All domestic customers benefit, thus resulting in massive loss of income to municipalities. 47. Real costs of electricity need to be defined for all customer groups, i.e. costs from generation, transmission, distribution, as well as internalising the environmental costs of electricity. 48. Cross subsidisation can only be modelled once the make-up of the customer base is known. The greater percentage of domestic customers in most municipalities does not buy enough electricity to get to the Block 3 tariffs. In reality, the cross subsidisation between customer groups is restricted by the customer mix within the municipality. To achieve a lower percentage increase for lower domestic blocks without further significant subsidisation from commercial customers, the current block design and/or tariff benchmarks need to be reconsidered. 49. The subject of cross subsidisation is one which should be determined by National Treasury. National Treasury has been neglecting its responsibility Page 11 of 23

11 in this respect. The current cross subsidisation in the EDI is taking place in a policy vacuum from a National Treasury point of view. NERSA Analysis 50. The principle of an IBT is supported by the South African Electricity Supply Industry: Electricity Pricing Policy GN 1398 of 19 December 2008 (EPP) which states that: : Low income tariff customer subsidization: Charging an appropriate tariff structure that allows for maximum subsidization at low consumption levels with gradually reducing cross-subsidies as the consumption levels increase. Furthermore, Section 16(e) of the Electricity Regulation Act, 2006 (Act No. 4 of 2006),states that the Regulator, may permit the cross-subsidy of tariffs to certain classes of customers. 51. The IBT structure has been designed to make allowance for the achievement of the objective of (1) protecting low-income tariff customers and (2) promoting energy efficiency. The Block 1 & 2 rates of the IBT are therefore set at subsidised rates, Block 3 is set to recover the average distributed costs and Block 4 to recover marginal cost plus residual revenues for domestic/residential customers. Therefore high consumption users who do not change their consumption pattern will not benefit /are not subsidised by the IBT structure. 52. The IBT s for municipalities that have a predominantly domestic customer base, a customer mix that is not ideal or low consumption domestic customers, will be considered on a case-by-case basis, i.e. NERSA will consider above the benchmark increases for these municipalities which will assist in reducing the cross-subsidies required from the rest of the customer base. Again, it must be noted that sufficient evidence of revenue impacts, customer numbers and consumption levels must be provided. e) Other issues impacting electricity price increase Stakeholder Comments 53. Eskom s High season and Low season tariffs play havoc with municipal cash flow. It is the start of the new financial year, and customers with credit bought in June, see the credit in July, however the municipality has to pay Eskom s High season tariffs. With no money in reserve as the financial year has just started, municipalities are having an ever increasing cash flow problem. 54. NERSA has approved a tariff increase of 26.71% for Eskom to municipalities, but no mention is made of tariff restructuring, or the Eskom proposed implementation of punitive IBTs for reactive energy. Page 12 of 23

12 NERSA Analysis 55. Time-of-use tariffs (TOU) have higher rates during peak periods and lower rates during off-peak periods. If a municipality is purchasing from Eskom on a TOU tariff, the municipality must consider its load profile/ consumption in its budgeting and forecasting process. 56. The 26.71% used as the bulk purchase percentage increase for municipalities in the calculation of the guideline, has been confirmed by Eskom s draft retail tariff submission to NERSA. It must be noted that there are no planned structural adjustments for the 2011/12 financial year. f) Appropriateness of financial analysis and benchmarks Stakeholder Comments 57. Percentage power cost and surplus benchmarks are supported; however the only problem with surpluses is that municipal financial statements are not ring-fenced and significant costs are hidden. Furthermore, NERSA has no control over this with a proper cross subsidy framework being compiled by National Treasury. 58. System losses benchmark is supported. The only problem is that the figures provided to NERSA are manipulated to yield acceptable losses. Large utilities with many large customers still experience very high losses. NERSA should obtain the data of any area that has losses of over 12% and detailed strategies of correcting this. These high losses should then be deducted from the allowed surplus. 59. The financial analysis does not consider the unique circumstance of each utility and their sustainability into the future. NERSA Analysis 60. During the analysis of the tariff applications, NERSA considers the financial health of the municipality in line with the financial benchmarks as set by NERSA. This includes the assessment of the surplus levels, system loss levels and average selling price versus the average purchase price. The information used for this analysis is obtained from the latest D-forms submitted by the municipality. 61. One of the requirements for submission of the D-forms to NERSA is that the forms need to be signed off by either the municipal Chief Financial Officer or the head of electricity technical service. NERSA therefore expects information supplied to be authentic and correct. 62. In instances where the analysis reveals very low surpluses, NERSA assists municipalities by considering higher tariff levels. In circumstances where the system losses of municipalities are also at extreme levels, NERSA requests the municipality to submit plans on how it intends to curb these Page 13 of 23

13 system losses. These plans are then monitored by NERSA to ensure that these inefficiencies are corrected. This aims to demonstrate that NERSA does not look at these financial indicators in isolation but considers the overall impact on tariff levels, revenues and efficiencies of the municipality. g) Appropriateness of benchmarking licensees against approved benchmarks Stakeholder Comments 63. The benchmark exercise is not appropriate as it only refers to the unit tariff and does not include aspects like basic charges, KVA charges, as well as time of usage. 64. All the benchmarks relating to IBTs are rejected. Tariffs must be applied as per EPP and other policies, then benchmarks can be used as a first indication of possible problems. These benchmarks should not be used to require changes but rather to use legitimate motivation provided by municipalities for the differences. 65. Criteria used to define Commercial (2000kWh) and Industrial (200kVA, LF30%) is not reflective of the customer base and therefore has little value in providing guideline for these customer categories. NERSA Analysis 66. All the commercial and industrial benchmarks are determined with all costs embedded into the benchmark level i.e. it is an average tariff level consisting of the basic charge, energy charge and demand charge. 67. The table below indicates the levels by which the 2010/11 IBT benchmark levels were adjusted together with the rationale for these increases resulting in the 2011/12 IBT benchmark levels. 68. The table aims to highlight that these benchmark levels have been set to meet the objective of protection of the poor. Municipalities that believe that these benchmarks are inappropriate or not applicable, they are required to submit an updated cost of supply study to support their need for such deviations. Page 14 of 23

14 Block Consumption Levels Block kwh Block kwh Block kwh Block 4 >600 kwh Basis of benchmark increase Limited to CPI ( as allowed for Eskom) CPI + % equal to or less than Eskom Real WACC% allowed Average (fully distributed) cost Domestic High benchmark plus guideline increase(long Run Marginal Cost + Residual Revenues) Rationale for the baseline point To ensure that the increases in this benchmarks category remain within inflation level and provides protection to the low income customers. Maintain the objective of low income customer tariff subsidization for those customers who spill over from first block by retaining same baseline for both block 1 and 2. To ensure that the increases of average consumption households are limited to the average guideline increases Higher end of the residential benchmarks and representative of the marginal cost for additional supply h) Appropriateness of benchmarking licensees tariff benchmark levels against each RED Stakeholder Comments 69. The difference in costs amongst the REDs is minimal and the justification of the table is highly questionable. NERSA Analysis 70. The minimal difference in the level of the benchmark levels is due to the effort by NERSA in order to harmonise the tariff levels within the RED areas. i) Timelines for tariff approval process Stakeholder Comments 71. The setting of timeframes is welcomed and municipalities look forward to the timeframes being met in order to ensure a legally compliant and robust process for 2011/12. Page 15 of 23

15 72. The local government elections taking place as early as May 2011, could impact on municipal budget preparation timeframes with some Councils aiming to approve their 2011/12 budgets earlier and before the elections. 73. The proposed timeline is not keeping in line with the requirements of MFMA, as MFMA stipulates that utility s final increase must be submitted by 15 March following all the necessary consultations including public hearings. Draft budget must be submitted to Council by 31 March. Expectations are for NERSA to have wound up its process and advised of the approved tariffs in time to input into the municipal budget process. 74. The idea that seeks to align the tariff approval process with MFMA requirements is supported. However, a need to differentiate between the two appeal processes is important, i.e. differentiate between a normal appeal process and a tribunal appeal process as per NERSA Act. 75. Communication of an approved tariff guideline by November is essential. Ideally, municipalities must submit initial applications and receive NERSA decision before end of May Resubmissions and public hearings to take place during April with final decision by May NERSA Analysis 76. The Municipal Tariff Assessment timelines (aligned to the National Treasury Budgetary Process) have been adjusted according to the comments received from stakeholder and is presented in Annexure Further engagement with key stakeholders (SALGA, AMEU and National Treasury) on these timelines is ongoing. 78. It is important to note that in order for NERSA to adhere to these timelines, and for these timelines to be effectively implemented, the onus is on the licensees to ensure the timeous submission of their 2011/12 tariff applications. APPLICABLE LAW 79. NERSA is the regulatory authority established as a juristic person in terms of section 3 of the National Energy Regulator Act, 2004 (Act No.40 of 2004). NERSA s mandate is to regulate the electricity, piped-gas and petroleum pipeline industries in terms of Electricity Regulation Act, 2006 ( Act No. 4 of 2006), Gas Act, 2001 (Act No. 48 of 2001 and Petroleum Pipelines Act, 2003 ( Act No. 60 of 2003). In terms of section 4(ii) of the Electricity Regulation Act, 2006 (Act no. 4 of 2006) the National Energy Regulator must regulate prices and tariffs. Page 16 of 23

16 DETERMINATION OF THE MUNICIPAL GUIDELINE Municipal Tariff Guideline 80. The guideline for the 2011/12 financial year has been calculated after taking into consideration Eskom s approved MYPD2. Eskom was granted an average increase of 25.8% increase for the 2011/12 financial year. This increase amounts to 26.71% for municipalities, which is due to the MFMA time lag. (i.e. municipalities implementation of 1 July). 81. When determining the percentage increase guideline for 2011/12, the following issues were also considered: the proposed Eskom price increase for 2011/12 applicable to municipal distributors; the analysis of other municipal costs besides purchase costs; tariff rationalization within a demarcated area and within a RED boundary and NERSA s regulatory objectives. 82. The revised weights as per the 2008/9 D-forms are as follows :- Current benchmarks (%) Revised benchmarks (%) Bulk Purchases Salaries Repairs & Maintenance 6 5 Capital charges 4 3 Other costs Table 1: Revised benchmark weights NERSA views on other costs: 83. Other costs are expenses that cannot be classified in terms of the municipal cost structure. The sampled municipalities allocate 10% of their revenue for other costs; this percentage is more than the costs of repairs and maintenance and capital combined. To rectify this situation it is proposed that the 10% be reduced by two percentage points. The reduced two percentage point should be added evenly to capital charges and repairs and maintenance. This would enable municipalities to invest more on their infrastructure. Page 17 of 23

17 Current benchmarks (%) Revised benchmarks (%) Bulk Purchases Salaries Repairs & Maintenance 6 6 Capital charges 4 4 Other costs 11 8 Table 2: Revised weights based on reduced other costs 84. The following assumptions were taken into consideration; bulk purchases have been increased by 26.71%; CPI equal to 4.8%; salary increases assumed at CPI plus 2% (as per agreement between organised local government and Unions); repairs and maintenance, Capital charges and Other Costs have been increased by CPI and the benchmark for bad debt is assumed at 0.5% of the total revenue of the municipality In determining the latest CPI forecast for the 2011/12 financial year, NERSA used the inflation figure as quoted in National Treasury s economic policy and outlook and the Medium Term Budget Policy statement (MTBPS) delivered by the Minister of Finance on 27 October This publication provides the latest official headline inflation forecasts; the forecasted inflation for 2011/12 is 4.8%. 86. NERSA s inflation figure, as calculated by Bureau of Economic Research (BER) is 5.5% for 2011/12. However, to avoid inconsistencies between municipalities, whose costs are generally calculated using National Treasury s guidelines, NERSA will assume National Treasury s forecasted figure of 4.8%. 87. When determining the percentage increase guideline for 2011/12, the following issues were considered and some assumptions made: The Eskom price for increase for 2011/12: Municipal distributors purchase their energy requirements from Eskom who generates 96% of the energy that is consumed in the country. It is therefore necessary that when considering the level at which municipalities will increase their tariffs, the Eskom price increase be taken into consideration. Based on the current study done in determining the guideline the electricity purchases by municipal distributors make up approximately 70% of their total costs to supply end-use customers; 4 This assumption is based on Eskom s approved arrear debt in the MYPD2 application. Page 18 of 23

18 The analysis of other municipal costs besides purchase costs: While purchase costs make up the bulk of municipal costs ( approximately 70% on average), municipalities are also subjected to other costs like operating and maintenance costs. Increases to these costs have a bearing on the municipalities ability to distribute electricity. Tariff rationalisation within a demarcated area and within a RED boundary: The process around tariff rationalisation within a future RED is an ongoing process. As an endeavour to tariff rationalisation, municipalities are divided into six RED s. NERSA adjusts the benchmarks to obtain a 5c/kWh margin between the upper and the lower limits of the required price. Currently municipalities which fall within the same RED are assessed on the benchmarks of that particular RED. If the required increase for a municipality is outside the guideline percentage, the increase is limited to the benchmarks in order for the tariffs to fall within the range for that RED, unless when the municipality has submitted a motivation stating reasons as to why it is applying for an increase that is above the guideline increase. Where such anomalies occur, the applications are treated on a case-by-case basis. This is based on the information provided by the particular applicant. 88. The formula for calculating the guideline: Where:- (%B x %BPI) + (%S x %SI)+ (%R x %RI)+(%C x %CCI)+(%OC x %OCI) (70 x 26.71) + (12 x 6.8%) + (6 x 4.8%) +(4 x 4.8%) +(8 x 4.8%) % B = % Bulk purchases BPI =% Bulk purchase increase S = % Salaries SI = %Salary increase R = % Repairs RI = %Repairs increase C = % Capital charges CCI =% Capital charges increase OC = % Other Charges OCI =% Other Charges increase Page 19 of 23

19 COST LINE ITEM PREVIOUS COSTS % MUNIC % OF TOTAL COST EXPECTED INCREASE % WEIGHTED AVERAGE EXPECTED INCREASE Purchases Salaries and wages Maintenance/Refurbishmen t/recapitalisation Capital charges in total Other costs % increase 20.38% Table 3: Calculation of the guideline for the 2011/12 financial year 89. It is considered to be appropriate to consider 70% of electricity cost as benchmark for energy purchases for a municipality. This was done according to a NERSA calculation based on a summary of municipality s data that was done in 2010; where a sample of municipalities electricity purchase costs was calculated as a percentage of total municipal costs and an average was reached per RED. The municipalities which were used in the sample study were selected based on the availability of the D-Form information submitted to NERSA by different municipalities. The percentage power costs for each of the six REDs ranged between 58% and 78%. This then resulted in an average of 70%. This benchmark ensures that municipalities are able to manage their costs more efficiently. There is a drive to push all municipalities to that level of efficiency. Municipal Tariff Benchmarks 90. The existing benchmarks are based on five assumed tariff/customer categories and average consumption levels for these categories. It should be noted that these are average consumption levels and that there may also be other tariff classes at various municipalities which will cater for other customer classes or consumption levels that are very different from the ones that are assumed. Where such anomalies exist, the applications will be treated on a case-by-case basis based on information provided by the applicant. 91. The criteria used in evaluating tariff increase applications from municipalities are as follows: o NERSA endeavours for efficiency by making sure that the tariff levels are within the benchmarks and are not excessive. o striving for rationalisation and harmonisation of tariffs in general, and particularly within a RED demarcation. o striving for an appropriate recovery of revenue from different customer categories. o while allowing cross subsidisation making sure that it is not excessive. Page 20 of 23

20 o promoting correct pricing signals through tariffs. 92. In analysing financial indicators more emphasis is put on the following issues: o system losses, if excessive and if there is an opportunity to improve on the surplus without increasing the tariffs o average price ratio where this is excessive and there is evidence of over recovery. This gives the regulator more reasons to limit the tariff levels. o surplus levels where it is excessive and there is evidence of over recover o where there is a special capital infrastructure upgrading. o where the connection fees were paid upfront by customers. o realignment of tariffs to allow for correct pricing signals 93. The Regulator will investigate the reasons, facts and evidence when considering a municipal motivation for a tariff increase above the guideline. 94. The existing benchmarks that are being revised are based on five assumed tariff/customer classes. Consumption levels for these customer classes are also assumed. It should be noted that these are average consumption levels and that there may also be other tariff classes at various municipalities which will cater for other customer classes or consumption levels that are very different from the ones that are assumed. Where such anomalies exist, the applications will be treated on a case-by-case basis. 95. For the purposes of benchmarking the following customer classes are assumed: domestic Tariffs 5 o Block 1 (1 50 kwh); o Block 2 (51 350kWh); o Block 3 ( kWh); and o Block 4 (> 600kWh); commercial (small business) single phase tariff this tariff is assumed to apply to small businesses and is generally a two part tariff consisting of both on energy and basic charge, with an assumed consumption level of 2000 kwh per month; commercial Prepaid this is generally a single energy rate tariff which may include some capital / fixed charges; and industrial / Large user tariff - This is a tariff for large customers (mainly industrial) low voltage assumed at a 30 % load factor (LF) and a maximum demand (MD) of 200 kva, which would give an average consumption level of kwh. 5 Domestic tariffs are based on the Inclining Block Tariffs (IBT) structure where the domestic low consumption level is assumed to be at 400kWh and the domestic high consumption at 800kWh. Page 21 of 23

21 96. The Regulator is aware of the fact that some municipalities use consumption levels that are different from what NERSA has assumed but for purposes of this report the mentioned consumption levels are used. This is so that the comparisons can be done on an apple to apple basis. Financial Benchmarks 97. When determining tariff increases for distributors, a financial analysis to test the efficiency and financial viability of the distributor is performed. This analysis is performed based on established financial indicator benchmarks to give an indication of the performance of the municipality i.e. to test whether the municipality is not overcharging its customers and whether the municipality will be able to continue as an ongoing concern given its current revenues from sales of electricity. 98. The following financial benchmarks are applicable: Average benchmarks Financial benchmarks (Tolerable range) Percentage Power cost 70% 58% - 78% Surplus percentage 15% 10% - 20% System losses 10% 5% - 12% Average Sales Price/Average Purchase Price ratio 1:1.5 1:2.1 1:1.5 1:2.1 Cross-subsidisation ratio (Commercial/ Domestic) 1:1.2 1:1.2 6 Cross-subsidisation ratio (Industrial/ Domestic) 1:1.25 1: Table 4: Applicable financial and technical benchmarks with the tolerable ranges 99. When revising the cost structure, the other ranges did not change except for the percentage power. This cost increased from the initial 67% to 70%. According to the analysis done, this figure is still within the range that was calculated in the previous tariff adjustment process. The lower and upper range of the power cost had to be increased by 3%, this was based on the difference between 67% and 70% When developing the domestic blocks, commercial and industrial benchmarks the following issues were taken into consideration: o Block The 2010/11 benchmarks were increased by the CPI inflation of 4.8%. 6 This is applicable to municipalities with an appropriate customer base/ mix i.e. municipalities that have sufficient domestic, commercial and industrial base. Municipalities that fall outside of these ratios will be treated on a case by case basis. 7 Ditto 8 The increases on block 1 up to block 4 tariffs are based on the Eskom s approved IBT structure. Page 22 of 23

22 Conclusion o Block 2 - The 2010/11 benchmarks were increased by CPI of 4.8% plus weighted average cost of capital of 8.16%. this results in a total increase of 12.96%. o Block 3 and 4 - The 2010/11 benchmarks were increased by the municipal tariff guideline increase of 20.38%. o The 2010/11 commercial and industrial benchmarks were increased by the municipal tariff guideline of 20.38% Based on the available reasons, facts and evidence NERSA s conclusion is set out below as follows: A guideline increase of 20.38% for the 2011/ municipal tariff review process. The 20.38% guideline increase was based on the following assumptions: o municipal bulk purchase cost of 70%; o bulk electricity purchase price increasing by 26.71% ; o salaries and wages increasing by the assumed 2011/12 Consumer Price Index (CPI) 9of 4.8% plus 2% as per the agreement between Local Government and its unions10; and o repairs and maintenance, capital charges and other costs increasing by the assumed inflation forecast of 4.8%. The municipal electricity tariff benchmarks for 2011/12 are as follows: c/kwh Domestic Block kWh Domestic Block kWh Domestic Block kWh Domestic Block 4 >600kWh Commercial Prepaid 2000kWh Commercial 2000kWh Industrial 43800kWh RED RED RED RED RED RED Table 5: The average benchmarks for 2011/12 End 9 National Treasury Forecasted Figure based on the Medium Term Budget Policy Statement (MTBPS) of 27 October This was confirmed with the South African Local Government Association (SALGA) Page 23 of 23

23 Annexure: 1 Timelines for annual municipal tariff review Dates Aug 10 Aug - Sept Details Mayor tables in council a schedule of key deadlines for various budget activities as outlined in section 21 of the MFMA Meeting with National Treasury and SALGA to discuss financial parameters and assumptions used in the determination of the guideline Meet with AMEU to discuss initial thoughts on the municipal guideline 6 Oct 10 Public Hearing 30 Oct 10 Due date for municipalities to submit their D-forms for the next tariff applications process Oct 10 National Treasury process - Municipal informal public meetings with key stakeholders, government spheres and entities 25 Nov 10 NERSA approval municipal guideline and benchmarks 26 Nov 10 Communicate indicative guideline increase to municipalities and put the draft decision on NERSA website, End Nov 10 Dec 10 Feb Jan 2011 Dec 10 May 11 Mar 11 National Treasury issues a budget circular to all municipalities. Municipalities compiles and submit draft tariffs application for consideration by NERSA *Deadline for municipalities to submit draft tariff applications to NERSA NERSA analyses applications and approval of tariffs within the guideline increase and communication of NERSA s decision to municipalities (incl. Revised application/appeal process) Mayor tables municipal and entity budgets and budget related policies (Draft) for consultation processes Apr- May 11 Public submissions on draft budget Council hearings to consider submissions Mayor resubmit amended budget for council approval and adoption 1 June Finalised budget is tabled in council again Applications above guideline Mar & April 11 Public Hearing for above guideline applications Mar May 11 Regulator meeting to approve above guidelines tariffs April - May 11 Consideration and approval of revised applications (appeal) 1 July 11 Implementation of approved budget including NERSA approved tariffs Sep11 Approved tariffs to be published on the website. Legend for the municipal tariff review process MFMA prescribed budgetary process for 2010/11 municipal financial year NERSA municipal applications and approval process Page 24 of 23

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding NATIONAL ENERGY REGULATOR OF SOUTH AFRICA DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE FOR THE FINANCIAL YEAR 2013/14 AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS DECISION

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2018/19 FINANCIAL YEAR Consultation Paper Published on 28 February 2018 Table

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2017/18 FINANCIAL YEAR Consultation Paper 23 February 2017 TABLE OF CONTENTS

More information

GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF

GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF 1. BACKGROUND AND APPROACH 1.1. During the National Energy Regulator of South Africa (NERSA) stakeholder consultation

More information

CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS

CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS Published on 21 September 2012 Page 1 of 41 TABLE OF CONTENTS 1. Introduction... 4 2. NERSA Mandate... 5 3. Background...

More information

(011) (fax) Department:

(011) (fax) Department: Telephone: (011) 999-5263 (work) Ekurhuleni Metropolitan Municipality (011) 917-1634 (fax) Department: e-mail: stephen.delport@ekurhuleni.gov.za Electricity and Energy PO Box 215 Boksburg 1460 62 nd AMEU(SA)

More information

SWARTLAND MUNICIPALITY

SWARTLAND MUNICIPALITY SWARTLAND MUNICIPALITY PRESENTATION AT NERSA PUBLIC HEARING 3 JUNE 2010 2010/11 ELECTRICITY TARIFF APPLICATION R DU TOIT Pr Eng 1 2 ACKNOWLEDGEMENTS Extracts and copies from public documents included in

More information

Residential tariff increases and restructuring for MYPD3 explained. Brochure

Residential tariff increases and restructuring for MYPD3 explained. Brochure Residential tariff increases and restructuring for MYPD3 explained Brochure November 2012 Residential brochure for MYPD3 changes Page 1 PART 1: ESKOM REVENUE REQUIREMENT Introduction Eskom applies for

More information

POST-CABINET MEDIA BRIEFING

POST-CABINET MEDIA BRIEFING POST-CABINET MEDIA BRIEFING By Phindile Nzimande CEO Holdings (Pty) Ltd 31 October 2006 Summary of Who We Are EDI HOLDINGS is a 100% state owned company We were established in 2003 to restructure the electricity

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA. Electricity Subcommittee Public Hearing 3 June 2010

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA. Electricity Subcommittee Public Hearing 3 June 2010 Presentation ti to the NATIONAL ENERGY REGULATOR OF SOUTH AFRICA Electricity Subcommittee Public Hearing 3 June 2010 1 Content of Presentation Motivation and background of Tariff Increases proposed General

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Bloemfontein 15 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2)

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2) Issues Paper Eskom Revenue Application Multi Year Price Determination 2010/11 to 2012/13 (MYPD 2) Published on 30 October 2009 1 TABLE OF CONTENTS Abbreviations... 3 Definitions... 4 1. Introduction...6

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings 30 October 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained its revenue

More information

MYPD3 Application January 2013

MYPD3 Application January 2013 MYPD3 Application 2014-2018 January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of any offer

More information

MYPD3 Application Gauteng January 2013

MYPD3 Application Gauteng January 2013 MYPD3 Application 2014-2018 Gauteng January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of

More information

Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom. by Chris Yelland CEng Managing editor EE Publishers

Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom. by Chris Yelland CEng Managing editor EE Publishers Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom by Chris Yelland CEng Managing editor EE Publishers Background to the ECS The ECS is a component of the Power Conservation Programme

More information

FUNDING & RESERVES POLICY

FUNDING & RESERVES POLICY FUNDING & RESERVES POLICY UNCHANGED 1 JULY 2016 STEVE TSHWETE LOCAL MUNICIPALITY MP 313 Approved May 2016 C36/05/2016 1. INTRODUCTION The funding and reserves policy is aimed to ensure that the municipality

More information

FFC Public Hearings on the LG Fiscal Framework. Comment by SALGA

FFC Public Hearings on the LG Fiscal Framework. Comment by SALGA FFC Public Hearings on the LG Fiscal Framework Comment by SALGA Leriba Lodge 4 June 2012 Overview Introduction General Comments Service Delivery Capital Investment Revenue Patterns Expenditure LGFF Proposed

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch

AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch Chief Engineer: Metering, Vending and Tariffs City of Ekurhuleni Stephen Delport 28 SEPTEMBER 2010 During the Depression years, when power lines first

More information

STRATEGIC PLAN AND BUDGET 2013 TO 2016 MUNICIPAL DEMARCATION BOARD

STRATEGIC PLAN AND BUDGET 2013 TO 2016 MUNICIPAL DEMARCATION BOARD STRATEGIC PLAN AND BUDGET 2013 TO 2016 MUNICIPAL DEMARCATION BOARD BRIEFING TO THE PORTFOLIO COMMITTEE ON COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS 19 MARCH 2013 DELEGATION Mr LJ Mahlangu Chairperson:

More information

BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016

BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016 BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016 Martin Kingston Chair: BUSA Standing Committee on Economic & Trade Policy

More information

Moretele Local Municipality. IDP/Budget Process Plan 2018/ ( IDP: Process Plan)

Moretele Local Municipality. IDP/Budget Process Plan 2018/ ( IDP: Process Plan) Moretele Local Municipality IDP/Budget Process Plan /2019 1 Revision Control Final - August 2017 Strategic Services IDP/PMS Unit Enquiries: 012 716 1321 / 1324 (tel) thabo.makwela@moretele.org.za nyakale.lale@moretele.org.za

More information

Large Commercial Rate Simplification

Large Commercial Rate Simplification Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate

More information

THE TRADE-OFFS BETWEEN PRO-POOR AND COST- REFLECTIVE TARIFFS IN SOUTH AFRICA: A REGULATORY PERSPECTIVE

THE TRADE-OFFS BETWEEN PRO-POOR AND COST- REFLECTIVE TARIFFS IN SOUTH AFRICA: A REGULATORY PERSPECTIVE THE TRADE-OFFS BETWEEN PRO-POOR AND COST- REFLECTIVE TARIFFS IN SOUTH AFRICA: A REGULATORY PERSPECTIVE Michael Maphosa Michael.maphosa@nersa.org.za +27 401 4699 National Energy Regulator of South Africa

More information

Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later?

Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later? Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later? Does South Africa need a cost reflective tariff? For years, low electricity costs have been a driver behind South Africa

More information

1.1 Executive Mayor s Report Council Resolutions Executive Summary Operating Expenditure Framework Capital Expenditure 22

1.1 Executive Mayor s Report Council Resolutions Executive Summary Operating Expenditure Framework Capital Expenditure 22 TABLE OF CONTENTS 2 PART 1 ANNUAL BUDGET Page 1.1 Executive Mayor s Report 5 1.2 Council Resolutions 7 1.3 Executive Summary 8 1.4 Operating Revenue Framework 10 1.5 Operating 18 1.6 Capital Expenditure

More information

EDI RESTRUCTURING AMEU 59th CONVENTION POLOKWANE SOUTH AFRICA 28 SEPTEMBER 2005

EDI RESTRUCTURING AMEU 59th CONVENTION POLOKWANE SOUTH AFRICA 28 SEPTEMBER 2005 EDI RESTRUCTURING AMEU 59th CONVENTION POLOKWANE SOUTH AFRICA 28 SEPTEMBER 2005 INTRODUCTION This document aims to give an update on the restructuring of the Electricity Distribution Industry (EDI) in

More information

TABLE OF CONTENTS SUBJECTS 1. INTRODUCTION 2. INSTITUTIONAL ARRANGEMENTS. Roles and responsibilities

TABLE OF CONTENTS SUBJECTS 1. INTRODUCTION 2. INSTITUTIONAL ARRANGEMENTS. Roles and responsibilities IDP REVIEW PROCESS PLAN DEPARTMENT OF THE OFFICE OF THE MUNICIPAL MANAGER JULY 2009-JUNE2010 TABLE OF CONTENTS SUBJECTS 1. INTRODUCTION 2. INSTITUTIONAL ARRANGEMENTS Roles and responsibilities 2.1 Council

More information

MANGAUNG METROPOLITAN MUNICIPALITY BUDGET POLICY

MANGAUNG METROPOLITAN MUNICIPALITY BUDGET POLICY MANGAUNG METROPOLITAN MUNICIPALITY BUDGET POLICY 2 INDEX 1. Statutory Framework... 3 2. Policy Objectives... 8 3. Votes, Categories of Expenditure and Line Items... 8 4. Capital Budget Mythology... 9 5.

More information

Portfolio Committee on Energy

Portfolio Committee on Energy Portfolio Committee on Energy Briefing Integrated National Electrification Programme (INEP) 26 August 2014 Context & Purpose Previous briefings to PC on INEP DoE in September 2013 Salga and DoE in February

More information

SETSOTO LOCALL MUNICIPALITY

SETSOTO LOCALL MUNICIPALITY ANNUAL BUDGET OF SETSOTO LOCALL MUNICIPALITY Page 1 TABLE OF CONTENTS 2013/14 TO 2015/16 MEDIUM TERM REVENUE AND EXPENDITURE FORECASTS PART 1: ANNUAL BUDGET 6 1.1 MAYOR S REPORT 6 (REFER TO THE ATTACHMENT)

More information

PRESENTATION TO THE PORTFOLIO COMMITTEE ON WATER AND ENVIRONMENTAL AFFAIRS

PRESENTATION TO THE PORTFOLIO COMMITTEE ON WATER AND ENVIRONMENTAL AFFAIRS PRESENTATION TO THE PORTFOLIO COMMITTEE ON WATER AND ENVIRONMENTAL AFFAIRS 24 MAY 2011 Presenters: Mthobeli Kolisa Executive Director: Municipal Infrastructure Services William Moraka Director: Water Services

More information

MYPD Methodology Eskom Response to Consultation Paper

MYPD Methodology Eskom Response to Consultation Paper MYPD Methodology Eskom Response to Consultation Paper 2 June 2016 Introduction Eskom is pleased to provide comments Eskom has provided detailed responses to the consultation paper on the review of the

More information

29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/ /2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK

29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/ /2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK 29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/2013 2014/2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK MBOMBELA LOCAL MUNICIPALITY 2012/13 TO 2014/15 DRAFT ANNUAL BUDGET AND

More information

Registration application fee to be paid by Small-Scale Embedded Generator Applicants

Registration application fee to be paid by Small-Scale Embedded Generator Applicants Consultation Paper: Registration application fee to be paid by Small-Scale Embedded Generator Applicants Published 16 December 2018 Version 1 December 2018 Issued by The National Energy Regulator of South

More information

CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017

CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017 CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017 Table of Contents Abbreviations and acronyms... 3 Definitions... 3 Executive summary...

More information

A study into approaches to minimise the impact of electricity price increases on the poor

A study into approaches to minimise the impact of electricity price increases on the poor TRADE AND INDUSTRY CHAMBER FUND FOR RESEARCH INTO INDUSTRIAL DEVELOPMENT, GROWTH AND EQUITY (FRIDGE) A study into approaches to minimise the impact of electricity price increases on the poor Final Report

More information

INFRASTRUCTURE DIALOGUE ELECTRICITY DISTRIBUTION INDUSTRY INFRASTRUCTURE PERSPECTIVE

INFRASTRUCTURE DIALOGUE ELECTRICITY DISTRIBUTION INDUSTRY INFRASTRUCTURE PERSPECTIVE INFRASTRUCTURE DIALOGUE ELECTRICITY DISTRIBUTION INDUSTRY INFRASTRUCTURE PERSPECTIVE PRESENTED BY DR WILLIE DE BEER 12 MAY 2011 Presentation Context Electricity Distribution Industry (EDI) Introduction

More information

PLAN AND MANAGE THE BUDGET POLICY & PROCEDURE MANUAL

PLAN AND MANAGE THE BUDGET POLICY & PROCEDURE MANUAL PLAN AND MANAGE THE BUDGET POLICY & PROCEDURE MANUAL THABA CHWEU LOCAL MUNICIPALITY Approved 25 June 2012 Resolution no: A50/2012 TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Vision and value statement...

More information

NATIONAL TREASURY MFMA IMPLEMENTATION PLAN - TEMPLATE (Medium Capacity Municipality Only)

NATIONAL TREASURY MFMA IMPLEMENTATION PLAN - TEMPLATE (Medium Capacity Municipality Only) NATIONAL TREASURY MFMA IMPLEMENTATION PLAN - TEMPLATE (Medium Capacity Municipality Only) Name of municipality: SIYANDA DISTRICT (eg: City of Johannesburg) Demarcation code:_dc8 (eg: GT001) Plan Action

More information

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017 SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017 www.salga.org.za Content Introduction Cllr Matshidiso Mfikoe SALGA Summary of Observations

More information

Economic Regulation Workshop

Economic Regulation Workshop Economic Regulation Workshop Role of IPART Setting prices for water utilities 8 October 2018 Contents 1. Why and how does IPART regulate prices? 2. Form of regulation 3. Building block approach 4. Expenditure

More information

Electricity theft and non-payment: Impact and action plan. by Chris Yelland CEng Managing editor EE Publishers

Electricity theft and non-payment: Impact and action plan. by Chris Yelland CEng Managing editor EE Publishers Electricity theft and non-payment: Impact and action plan by Chris Yelland CEng Managing editor EE Publishers Outline The scale of electricity theft and non-payment The impact on the national demand The

More information

PROGRESS WITH THE NATIONAL INFRASTRUCTURE MAINTENANCE STRATEGY

PROGRESS WITH THE NATIONAL INFRASTRUCTURE MAINTENANCE STRATEGY PROGRESS WITH THE NATIONAL INFRASTRUCTURE MAINTENANCE STRATEGY Kevin Wall CSIR, P.O. Box 395, Pretoria, 0001; Cell: 082-4593618, Email: kwall@csir.co.za ABSTRACT The National Infrastructure Maintenance

More information

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019 Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3 Public Hearings- Port Elizabeth Date: 16 January 2019 RCA (Yr 5, MYPD3) Timeline RCAs require 3 decisions: 1 Balance decision 2 Liquidation decision

More information

Why the Regional Electricity Distributors (REDs) concept is bad for Cape Town

Why the Regional Electricity Distributors (REDs) concept is bad for Cape Town Why the Regional Electricity Distributors (REDs) concept is bad for Cape Town The City of Cape Town has asked for public input as part of the Municipal Systems Amended Act (MSA) Section 78 process investigation

More information

PRESENTATION TO SABOA CONFERENCE

PRESENTATION TO SABOA CONFERENCE PRESENTATION TO SABOA CONFERENCE THE DEVELOPMENT OF PERFORMANCE BASED GROSS NEGOTIATED MODEL CONTRACT DOCUMENT FOR THE ROLL-OUT OF IPTNs 23 FEBRUARY 2012 1 CONTENTS PURPOSE OF THE PRESENTATION CURRENT

More information

Cover slide (same as IR cover)

Cover slide (same as IR cover) Integrated results for the year ended 31 March 2016 Cover slide (same as IR cover) 5 July 2016 This presentation is available at www.eskom.co.za/ir2016 Contents Overview of the year Financial review Operating

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

Public Hearing Presenter: D Matsheketsheke Designation: CFO (act) Date: 9 June 2011

Public Hearing Presenter: D Matsheketsheke Designation: CFO (act) Date: 9 June 2011 Public Hearing Presenter: D Matsheketsheke Designation: CFO (act) Date: 9 June 2011 MOE: City Power 1 Introduction: Strategic Priorities SERVICE 1. Social transformation (public lighting/ electrification)

More information

Submission to SALGA and National Treasury

Submission to SALGA and National Treasury MYPD 3 Re-opener for selective items (2015/16~2017/18) o OCGTs and o STPPP Including the Submission to SALGA and National Treasury In terms of the Municipal Finance Management Act (MFMA) 16 March 2015

More information

AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES

AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES Ir Leon Kritzinger 28 September 2010 What lies behind us and what lies before us are tiny matters compared to what lies within us. Walt Emerson Challenges

More information

Energy and Climate Change Programme P O Box 106 Office Tel: (+27) (0) Fax:

Energy and Climate Change Programme P O Box 106 Office Tel: (+27) (0) Fax: SAFCEI is a company not for profit Reg No 2006/014388/08 NPO 053498 PBO 930024255 Faith communities committed to cherishing living earth. www.safcei.org.za Energy and Climate Change Programme P O Box 106

More information

Eskom s Draft Application to NERSA for Price. Increase in 2008/9

Eskom s Draft Application to NERSA for Price. Increase in 2008/9 Eskom s Draft Application to NERSA for Price Increase in 2008/9 Submitted to NERSA on 17 March 2008 Table of Contents Executive Summary... 4 1 Background and Introduction... 12 2 Primary Energy... 20 3

More information

VANDERBILT AVENUE ASSET MANAGEMENT. The Market Impact of the Proposed U.S. Treasury Debt Buyback

VANDERBILT AVENUE ASSET MANAGEMENT. The Market Impact of the Proposed U.S. Treasury Debt Buyback The Market Impact of the Proposed U.S. Treasury Debt Buyback Much has been written lately about the government s announced plans to repurchase debt and reduce or eliminate the federal deficit by the second

More information

Draft Eskom 2018/19 Revenue Application

Draft Eskom 2018/19 Revenue Application Draft Eskom 2018/19 Revenue Application Nersa Public Hearings Durban 2 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

Water Regulation and Pricing RSA EXPERIENCE

Water Regulation and Pricing RSA EXPERIENCE Water Regulation and Pricing RSA EXPERIENCE Presenter: Avril Halstead Chief Director, National Treasury 26 June 2014 Outline Water Sector Value Chain Financial framework Framework for economic regulation

More information

ESKOM S DEMAND EXEMPTION POLICY. This document may be updated from time to time, please refer to for the latest version.

ESKOM S DEMAND EXEMPTION POLICY. This document may be updated from time to time, please refer to   for the latest version. ESKOM S DEMAND EXEMPTION POLICY This document may be updated from time to time, please refer to www.eskom.co.za/tariffs for the latest version. Eskom s Demand Exemption Policy Page 2 of 15 1. Introduction...

More information

Approach to Assessing Capital Expenditure for Price Reviews

Approach to Assessing Capital Expenditure for Price Reviews Approach to Assessing Capital Expenditure for Price Reviews January 2018 This document examines approaches to assessing capital expenditure (Capex) in general and what has been specifically employed by

More information

THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS. Submission to the National Ports Regulator

THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS. Submission to the National Ports Regulator THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS 12 Skeen Boulevard Bedfordview P O Box 2510 Bedfordview 2008 Republic of South Africa Tel: (011) 455 1726/1707 Fax: (011) 455 1709 Republic of South

More information

THE 2010/11 TARIFF ADJUSTMENT. Standard schedule of Tariffs

THE 2010/11 TARIFF ADJUSTMENT. Standard schedule of Tariffs THE TARIFF ADJUSTMENT Standard schedule of Tariffs Scenario Modelling Tool (SMT) Tariff options Only change is to the residential Standard ' options - Urban Rural Residential Megaflex Ruraflex Inclining

More information

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY No. 530 THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY 2 Ashween 1929 (s) Ranchi, Monday the 24 th September, 2007 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION -------------- REGULATIONS

More information

NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY

NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY Published on: 14 October 2011 TABLE OF CONTENTS Page Abbreviations and Acronyms... 3 1 The Consultation Process... 5 2 Introduction...

More information

NERSA Submissions ESKOM RCA

NERSA Submissions ESKOM RCA NERSA Submissions ESKOM RCA 4 February 2016 Presented by: Stefan Pieterse Armand Greyling Content 1. Who is AfriBusiness 2. RCA Methodology 3. Municipal Budget Process 4. Eskom Revenue Variance 5. OCGT

More information

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Price projection We project our prices for High Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

KEY DATES FOR THE MANGAUNG METROPOLITAN MUNCIPALITY IDP REVIEW/BUDGET 2017/18

KEY DATES FOR THE MANGAUNG METROPOLITAN MUNCIPALITY IDP REVIEW/BUDGET 2017/18 KEY DATES FOR THE MANGAUNG METROPOLITAN MUNCIPALITY IDP REVIEW/BUDGET 2017/18 Mangaung Metropolitan Municipality wishes to inform all its stakeholders and communities of the key opportunity to make inputs

More information

a tariff for the period 01 January 2012 to 31 March 2012 as follows; GTA Tariffs for period 01 January March TARIFF VOLUME

a tariff for the period 01 January 2012 to 31 March 2012 as follows; GTA Tariffs for period 01 January March TARIFF VOLUME ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding Transnet Pipelines gas transmission tariff assessment for the pipeline from Secunda to Durban south (Lilly pipeline) for the period 01 January 2012

More information

RELATIONSHIP BETWEEN THE BUDGET AND THE IDP 28 FEBRUARY 2017

RELATIONSHIP BETWEEN THE BUDGET AND THE IDP 28 FEBRUARY 2017 RELATIONSHIP BETWEEN THE BUDGET AND THE IDP 28 FEBRUARY 2017 1 Contents Introduction Legislative Requirements Inc. MSCOA Why MSCOA Local Government Accountability Cycle Budget Process and linkage to IDP

More information

uthungulu District Municipality

uthungulu District Municipality The Municipality Tariff Policy TABLE OF CONTENTS 1. Definitions 2. Preamble 3. General Introduction and Objective 4. Principles 5. Classification and pricing strategies of services 6. Calculation of Tariffs

More information

ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18

ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18 ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18 NERSA 15 January 2019 Nelson Mandela Bay Business Chamber Comments and Recommendations Overview The Nelson Mandela Bay Business Chamber What the applications

More information

STEVE TSHWETE LOCAL MUNICIPALITY MP

STEVE TSHWETE LOCAL MUNICIPALITY MP BUDGET POLICY AMENDED 1 JULY 2016 STEVE TSHWETE LOCAL MUNICIPALITY MP 313 Approved May 2016 C36/05/2016 TABLE OF CONTENTS 1. Definitions 2. Introduction 3. Objective 4. Budgeting principles 5. Budget preparation

More information

SANTA MONICA RENT CONTROL BOARD ADMINISTRATION MEMORANDUM

SANTA MONICA RENT CONTROL BOARD ADMINISTRATION MEMORANDUM SANTA MONICA RENT CONTROL BOARD ADMINISTRATION MEMORANDUM DATE: May 10, 2005 TO: FROM: Santa Monica Rent Control Board Mary Ann Yurkonis, Administrator FOR MEETING OF: May 12, 2005 RE: Annual General Adjustment

More information

Financial Reporting Matters

Financial Reporting Matters Financial Reporting Matters March 2009 Issue 26 AUDIT In this issue, we discuss some of the accounting issues to consider as entities prepare for their 31 March 2009 quarterly or year-end financial reporting.

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

Retail Exemptions Consultation Paper and Draft Exempt Selling Guideline. QCOSS Submission

Retail Exemptions Consultation Paper and Draft Exempt Selling Guideline. QCOSS Submission Retail Exemptions Consultation Paper and Draft Exempt Selling Guideline QCOSS Submission February 2011 Response to AER Consultation Paper: Retail Exemptions Queensland Council of Social Service (QCOSS)

More information

2016 Division of Revenue Amendment Bill Select and Standing Committees on Apportions

2016 Division of Revenue Amendment Bill Select and Standing Committees on Apportions 2016 Division of Revenue Amendment Bill Select and Standing Committees on Apportions National Treasury 10 November 2016 Overview The 2016 Division of Revenue Act (DoRA) was considered and approved by Legislatures

More information

Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010

Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010 Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010 The process of dealing with the EDI maintenance backlog: Can we catch up? Electricity Supply Chain GENERATION

More information

ESKOM One Year Application 2018/19

ESKOM One Year Application 2018/19 ESKOM One Year Application 2018/19 NERSA 1 November 2017 Nelson Mandela Bay Business Chamber Comments and Recommendations Overview The Nelson Mandela Bay Business Chamber What the application means for

More information

COMPANY OVERVIEW ABOUT PEC METERING. Background

COMPANY OVERVIEW ABOUT PEC METERING. Background COMPANY OVERVIEW ABOUT PEC METERING Background PEC Metering (Pty) Ltd is a private professional company established in 1994, specialising in utility management services and energy management with operations

More information

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Price projection We project our prices for Low Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

Theewaterskloof Municipality

Theewaterskloof Municipality Theewaterskloof Municipality Final Budget 2018/2019 to 2020/2021 29 May 2018 English is original version Copies of this document can be viewed: In the foyer of all municipal offices All public libraries

More information

Department of Energy South Africa

Department of Energy South Africa Department of Energy South Africa Policy to support the Energy Efficiency and Demand Side Management Program for the Electricity Sector through the Standard Offer Incentive Scheme Draft: March 2010 1 TABLE

More information

February 2016 Financial Report

February 2016 Financial Report 2016 February 2016 Financial Report Capital Metropolitan Transportation Authority 4/13/2016 Table of Contents SUMMARY REPORT Budgetary Performance - Revenue 2 - Sales Tax Revenue 5 - Operating Expenses

More information

April 30, 2016 Financial Report

April 30, 2016 Financial Report 2016 April 30, 2016 Financial Report Capital Metropolitan Transportation Authority 6/15/2016 Table of Contents SUMMARY REPORT Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

OVERSIGHT REPORT ON THE ANNUAL REPORT 2017/2018

OVERSIGHT REPORT ON THE ANNUAL REPORT 2017/2018 OVERSIGHT REPORT ON THE ANNUAL REPORT 2017/2018 WEST COAST DISTRICT MUNICIPALITY WESKUS DISTRIKSMUNISIPALITEIT Reference: (10/3/2/3/36) 10 January 2019 OVERSIGHT REPORT ON ANNUAL REPORT: 2017/2018 FINANCIAL

More information

COMPARATIVE ANALYSIS OF MONTHLY REPORTS ON THE OIL MARKET

COMPARATIVE ANALYSIS OF MONTHLY REPORTS ON THE OIL MARKET COMPARATIVE ANALYSIS OF MONTHLY REPORTS ON THE OIL MARKET AN INTERNATIONAL ENERGY FORUM PUBLICATION JUNE 2018 RIYADH, SAUDI ARABIA JUNE 2018 SUMMARY FINDINGS FROM A COMPARISON OF DATA AND FORECASTS ON

More information

SUBMISSION DOCUMENT EXECUTIVE SUMMARY

SUBMISSION DOCUMENT EXECUTIVE SUMMARY Unique Identifier 221-222 SUBMISSION DOCUMENT Document Type CCGTE Revision 1 Effective Date June 2011 Regulation & Governance SUBMISSION TO ICAS on 28 June 2011 EXECUTIVE SUMMARY 1. TITLE OF THE SUBMISSION

More information

COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS COSATU COMMENT ON ESKOM S MYPD3 FOR THE YEAR 2, 3, 4

COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS COSATU COMMENT ON ESKOM S MYPD3 FOR THE YEAR 2, 3, 4 COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS Head Office 110 Jorissen Street Braamfontein 2017 JOHANNESBURG P O Box 1019 JOHANNESBURG 2000 Tel: + 27 11 339 4911 Fax: + 27 11 339 5080 Internet: http://www.cosatu.org.

More information

1. INTRODUCTION 2. OVERVIEW OF POLICY PRIORITIES FOR 2016/17

1. INTRODUCTION 2. OVERVIEW OF POLICY PRIORITIES FOR 2016/17 REPORT OF THE PORTFOLIO COMMITTEE ON COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS ON THE ANNUAL PERFORMANCE PLAN AND BUDGET VOTE 4 OF THE DEPARTMENT OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS

More information

Government Gazette REPUBLIC OF SOUTH AFRICA

Government Gazette REPUBLIC OF SOUTH AFRICA Government Gazette REPUBLIC OF SOUTH AFRICA Vol. 526 Cape Town 3 April 2009 No. 32106 THE PRESIDENCY No. 408 3 April 2009 It is hereby notified that the President has assented to the following Act, which

More information

PMB Review: What s next? Evelyn Thsehla Clinical Researcher

PMB Review: What s next? Evelyn Thsehla Clinical Researcher PMB Review: What s next? Evelyn Thsehla Clinical Researcher Contents Background PMB Development Identified Gaps PMB review phases Proposed Intervention Work-plans Conclusion Background The Medical Schemes

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Wellington North Power

More information

MYPD 3 (Year 2013/14) Regulatory Clearing Account Submission to NERSA

MYPD 3 (Year 2013/14) Regulatory Clearing Account Submission to NERSA MYPD 3 (Year 2013/14) Regulatory Clearing Account Submission to NERSA November 2015 MYPD3 2013/14 RCA Submission to NERSA November 2015 Page 2 of 205 TABLE OF CONTENTS 1 PREFACE... 15 1.1 The basis of

More information

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Advisory Service for Energy and Climate Change John Lambert Senior Business Development Manager Direct Energy

More information

A Rational Price Path for South Africa

A Rational Price Path for South Africa A Rational Price Path for South Africa Finding the Balance Nersa s task in MYPD3 Serious Imbalance Not in Balance Balanced c. Contain taxes and levies A Balanced Solution Set Business, Eskom, NERSA and

More information

BERGRIVIER MUNICIPALITY REPORT BY THE STRATEGIC MANAGER

BERGRIVIER MUNICIPALITY REPORT BY THE STRATEGIC MANAGER BERGRIVIER MUNICIPALITY REPORT BY THE STRATEGIC MANAGER TO: MAYORAL COMMITTEE COUNCIL 2018/19 QUARTERLY BUDGET AND PERFORMANCE REPORT FOR QUARTER 1: 1 JULY 30 SEPTEMBER 2018 SUBMITTED IN TERMS OF SECTION

More information

Eskom Revenue Application. Multi-Year Price Determination (MYPD 4) FY2019/ /22

Eskom Revenue Application. Multi-Year Price Determination (MYPD 4) FY2019/ /22 Eskom Revenue Application Multi-Year Price Determination (MYPD 4) FY2019/20-2021/22 September 2018 Content Content Preface... 7 Executive Summary... 10 1.1 Key elements of allowed revenue for the 2019/20-2021/22

More information

PRESS STATEMENT SPEECH BY THE ERB BOARD ACTING CHAIRMAN PROF. FRANCIS YAMBA ON THE ZESCO APPLICATION TO VARY ELECTRICITY TARIFFS

PRESS STATEMENT SPEECH BY THE ERB BOARD ACTING CHAIRMAN PROF. FRANCIS YAMBA ON THE ZESCO APPLICATION TO VARY ELECTRICITY TARIFFS PRESS STATEMENT SPEECH BY THE ERB BOARD ACTING CHAIRMAN PROF. FRANCIS YAMBA ON THE ZESCO APPLICATION TO VARY ELECTRICITY TARIFFS - 2017 Members of the Board; Members of the Press; ZESCO Management; Energy

More information

DETERMINATION OF LESOTHO ELECTRICITY COMPANY (Pty) Ltd s APPLICATION FOR A TARIFF INCREASE FOR 2012/13

DETERMINATION OF LESOTHO ELECTRICITY COMPANY (Pty) Ltd s APPLICATION FOR A TARIFF INCREASE FOR 2012/13 LESOTHO ELECTRICITY AUTHORITY In the matter regarding a DETERMINATION OF LESOTHO ELECTRICITY COMPANY (Pty) Ltd s APPLICATION FOR A TARIFF INCREASE FOR 2012/13 1. DECISION After duly considering the application,

More information