a tariff for the period 01 January 2012 to 31 March 2012 as follows; GTA Tariffs for period 01 January March TARIFF VOLUME

Size: px
Start display at page:

Download "a tariff for the period 01 January 2012 to 31 March 2012 as follows; GTA Tariffs for period 01 January March TARIFF VOLUME"

Transcription

1 ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding Transnet Pipelines gas transmission tariff assessment for the pipeline from Secunda to Durban south (Lilly pipeline) for the period 01 January 2012 to 31 March THE DECISION On 26 July 2012, the Energy Regulator approved the Piped-gas transmission tariff for Transnet Pipelines (Transnet) Lilly pipeline from Secunda to Durban South for the period 01 January 2012 to 31 March 2013 as follows: a tariff for the period 01 January 2012 to 31 March 2012 as follows; GTA Tariffs for period 01 January March TARIFF VOLUME (Proposed) R 0-12 m GJ/a m GJ/a 4.81 >18m GJ/a 4.24 tariff of R9.24/GJ for the period 01 April 2012 to 31 March 2013 for the Lilly Pipeline as summarised in the table below; and RoR Tariff for period 01 April 2012 to 31 March 2013 TRANSNET (Rm) (RAB = v-d +net working capital) Total RAB (AR = (RAB*WACC) + E +D +T±C) WACC 6.43% Return on assets Operating Costs Depreciation and Amortization Allowable Revenue before tax Tax Clawback 0.00 Total Allowable Revenue (AR) Forecasted Volume (m/gj) Tariff (R/GJ) 9.24 RfD Transnet Tariff Assessment 2012/13 Page 1 of 15

2 discounts on the above tariffs are permissible and these tariffs will be applicable until new tariffs are approved. REASONS FOR DECISION 1. APPLICABLE LAW 1.1 The Energy Regulator is mandated in terms of the National Energy Regulator Act, 2004 (Act No. 40 of 2004), to regulate the piped gas industry in terms of the Gas Act, 2001 (No. 48 of 2001), (Gas Act). 1.2 In addition, the Energy Regulator approved and published the Guidelines for Monitoring and Approving Piped-Gas Transmission and Storage tariffs in South Africa (Tariff Guidelines) on 01 May Section 4(h) of the Gas Act provides that the Energy Regulator must monitor and approve and, if necessary, regulate transmission and storage tariffs. In practice, this is interpreted as follows: In monitoring and approval, NERSA will not set tariffs but will review tariffs prepared by licensees or applicants for transmission and storage facilities; NERSA can request licensees or applicants to amend the levels of tariffs or tariff structure or both; and NERSA can approve or decide not to approve a tariff. 1.4 If NERSA decide not to approve the proposed tariff, then section 4h of the Gas Act requires the Energy Regulator to regulate the tariff. The process to be followed in regulating the tariff is outlined in the Tariff Guidelines. In regulating, NERSA will regulate by determining the tariffs, if necessary, to ensure that NERSA is fulfilling its regulatory duties, inter alia by ensuring tariffs are cost effective and applied in a non-discriminatory manner. 1.5 For monitoring purposes, the application for a tariff must be provided on an annual basis, although applicants are also allowed to apply for approval of tariffs for a period of several years. 1.6 The approved tariff becomes the applicable tariff and discounts are permissible. It must be noted that the discounts should be consistent with the objectives of the Gas Act as well as section 22 of the Gas Act. 1.7 The approved tariff will by virtue of section 22 of the Act also apply to third parties. 2. THE APPLICANT 2.1 Transnet Limited (registration number 1990/000900/06) is a public company registered and incorporated as such in terms of the company RfD Transnet Tariff Assessment 2012/13 Page 2 of 15

3 laws of the Republic of South Africa pursuant to the legal succession of the South African Transport Services Act, 1989 (Act No. 13 of 1989). 2.2 Transnet Limited ( Transnet ) operates the country s rail network (Transnet Freight Rail (formerly Spoornet)), its ports (Transnet National Ports Authority (formerly National Ports Authority)), the petroleum pipelines and the gas pipeline (Transnet Pipelines (formerly Petronet)), and other operations such as Transnet Port Terminals (formerly the South African Ports Operations) and Transnet Rail Engineering (formerly Transwerk). 2.3 The Transnet Pipelines Division of Transnet operates approximately kilometers of pipelines conveying gas, refined petroleum products and crude oil. Only 573 kilometers of this pipeline is used for conveying gas. Gas Pipeline 2.4 The current gas pipeline commonly referred to as the Lilly pipeline is a piped-gas transmission pipeline which came about as a result of a conversion of sections of a crude oil pipeline ( COP ) and the Durban Witwatersrand pipeline in On 11 November 2009, NERSA granted Transnet a Piped-gas transmission license to operate the Lilly pipeline which comprises: a 16 inch diameter, 153km pipeline from the inlet flange at Secunda via Standerton and Volksrust to Ingogo; An 18 inch diameter, 420 km pipeline from Ingogo via Scheepersnek and Empangeni to Durban; terminating near the Island View area at Bayhead; and Seven supply points at Newcastle, Empangeni, Mandini, Verulam, Phoenix, Avoca and Durban, along the pipeline route. 2.6 Transnet currently has one customer for transmission services, Sasol Gas, which is using the pipeline. A Gas Transportation Agreement (GTA) governs the relationship between Transnet and Sasol Gas. 3. TRANSNET TARIFF APPLICATION 3.1 On 25 November 2011, the National Energy Regulator received a tariff application from Transnet Pipelines ( the applicant or Transnet ) for the Piped-gas transmission tariff, for its pipeline from Secunda to Durban South, commonly referred to as the Lilly Pipeline, for the period 01 January 2012 to 31 March This is Transnet s third application since the Tariff Guidelines were approved and since Transnet s transmission operation licence was granted. 3.2 Transnet has in the past applied for approval for tariffs based on the Gas Transportation Agreement (GTA) with Sasol Gas Limited but changed to RfD Transnet Tariff Assessment 2012/13 Page 3 of 15

4 the Rate of Return (RoR) methodology for the tariff period 01 April 2012 to 31March Transnet also requested the Energy Regulator to change its tariff period from the calendar year (01 January December 2012), to its financial year (01 April March 2013) so as to align its tariff application to the Regulatory Financial Reporting period which is aligned to the applicant s financial year. 3.4 Transnet is applying for an allowable revenue of R157.2 million and tariffs which range from R6,83/GJ to R9.25/GJ for the period 01 April 2012 to 31 March 2013 using the RoR methodology. 3.5 Furthermore, Transnet is requesting that the Energy Regulator approve a tariff of R8.39 per gigajoule ( GJ ) for volumes up to 12million gigajoules ( MGJ ), R4.81/GJ for volumes greater than 12MGJ but less than 18MGJ and R4.24/GJ for volumes greater than 18MGJ, for the transitional period of 01 January 2012 to 31 March This is based on the GTA tariff formula. 3.6 In the previous tariff period, Transnet applied for and NERSA approved a volume based block tariff of R7.90/GJ for volumes from 0-12m gigajoules per annum (GJ/a), R4.53/GJ for volumes from 12.1m-18m GJ/a and R3.99/GJ for volumes above 18m GJ/a. 4. TESTING OF PROPOSAL 4.1 According to the Guidelines for Monitoring and Approving Transmission and Storage Tariffs for the Piped-Gas Industry in South Africa (Tariff Guidelines), applicants are required to submit a tariff application based on their respective preferred methodology that may be chosen from the approved menu of tariff methodologies. 4.2 Each tariff application is reviewed using the same methodology chosen and used by the tariff applicant and any other appropriate information or method for assessing the reasonableness of each application by the Energy Regulator. 4.3 Alternative tariff methodologies or variations on the methods listed on the menu may be used by the applicant, provided that such method is proven, tested and verifiable. 4.4 Therefore, to review Transnet s application for reasonableness, the Project Team used the Rate of Return ( RoR ) methodology since this was in line with the methodology followed by Transnet in its submission. 5. ELEMENTS OF ALLOWABLE REVENUE 5.1 As mentioned above, NERSA used the Rate of Return ( RoR ) methodology to assess the 2012/13 tariff application since this was in line RfD Transnet Tariff Assessment 2012/13 Page 4 of 15

5 with the way Transnet submitted its information. The formula of RoR used is as follows: AR = (RAB x WACC) + E + T + D ± C Where: RAB - Regulatory Asset Base WACC - Weighted Average Cost of Capital E- Expenses T - Taxes D - Depreciation C - Clawback 2012 Tariff Calculation Summary NERSA (Rm) TRANSNET (Rm) (RAB = v-d +net working capital) Total RAB (AR = (RAB*WACC) + E +D +T±C) WACC 6.41% 6.43% Return on assets Operating Costs Depreciation and Amortization Allowable Revenue before tax Tax Clawback Total Allowable Revenue (AR) Forecasted Volume (m/gj) Tariff (R/GJ) As indicated in the table above, Transnet applied for an annualised allowable revenue of R157.10m. This is 28% higher than the allowable revenue approved for the 2011 tariff period, of R122.78m and 6% lower than the 2012/13 NERSA assessment of an allowable revenue of R166.12m. 5.3 The paragraphs below provide an analysis of each component of the allowable revenue formula. Starting Asset Regulatory Base (SARB) 5.4 In terms of section of the Tariff Guidelines, the value of the RAB is the inflation-adjusted historical cost or trended original cost ( TOC ) of plant, property and equipment less the accumulated depreciation for the period under consideration plus net working capital. The formula for this is as follows: Regulatory Asset Base = Trended Original Cost of Property, Plant & Equipment (v) - Accumulated Depreciation (d) + Net Working Capital (w) RfD Transnet Tariff Assessment 2012/13 Page 5 of 15

6 5.5 NERSA used a Starting Asset Regulatory Base of R566m as approved by the Energy Regulator on the 25 th of March 2010, which was based on a 2009 study by PricewaterhouseCoopers (PWC) Report on the trended original cost valuation of Transnet Pipelines gas assets. 5.6 This PWC report provides an average useful life for each asset class whilst Transnet used specific useful lives of each asset in the class based on its asset register. 5.7 The following table gives a summary of NERSA s Trended Original Cost (TOC) calculation: TOC Determination (m) (m) (m) (m) (m) (m) (m) Opening TOC - Gas Pipeline Assets Fixed Assets Additions - Pro rated Non Pipeline Assets Total Assets Openining TOC CPI write up Subtotal Depreciation (d) and Amortization 5.8 Section of the Tariff Guidelines provides that accumulated depreciation (d) is the cumulative depreciation against plant property, vehicles and equipment in service should be calculated on a straight line basis over the economic life of the asset. 5.9 Since the asset base and the remaining economic life of assets were determined in the SRAB report, NERSA used the SRAB value to calculate the straight line depreciation amount. The inflation write up from the trending of the asset value was also amortized over the estimated remaining useful lives of these assets. Net working Capital (w) 5.10 According to the Tariff Guidelines, net working capital refers to the various regulatory asset-base funding requirements other than utility plant in service. This is determined using the following formula: Net working capital = inventory + receivables + operating cash + minimum cash balance trade payables NERSA used the working capital figure of R48.2m as provided by the applicant. Tax (T) 5.12 Section 4.4 of the Tariff Guidelines provides that the flow-through tax approach is the Energy Regulator s preferred tax methodology. Under RfD Transnet Tariff Assessment 2012/13 Page 6 of 15

7 this approach, only the current taxes payable are factored into the allowable revenue and recovered during the tariff period under review NERSA used the flow-through tax approach to determine the tax payable figure of R23.17m in the allowable revenue. Deferred tax was not taken into consideration since the flow-through tax method does not provide for future income taxes payable outside the tariff period. Expenses (E) 5.14 The Energy Regulator is required by section 4.3 of the Tariff Guidelines to assess the operating and maintenance expenses using principles such as whether the expenses were prudently incurred, its controllability and efficiency NERSA allowed all the costs of R58.9m provided by Transnet since the expenses were correctly classified, recorded and allocated between gas and petroleum activities as per the NERSA-approved Cost Allocation Manuals Transnet indicated that it escalated the actual operating expenses incurred in 2011 by the CPI to get the 2012 forecasts, except where other factors, such as electricity costs which increased by 16% and all indirect costs which were allocated using the approved cost drivers Transnet revised the electricity costs after NERSA s determination of the electricity price for 2012/ Included in the expenses is a decommissioning provision armotisation of R0.633m, provided in line with section 34 (1) (d) of the Gas Act and Regulation 11 (4) and (5) which require licensees to provide for financial security in respect of rehabilitation obligations. DECOMISSIONING PROVISION CALCULATION SUMMARY Transnet Pipelines - Provision for Land and rehabilitation reqired Present value of obligation (current values) Less: Cumulative Contributions for 2011/12 and prior tariff periods Less: Interest earned (net of tax of prior period collections) Balance of PV of obligations to collect in remaining tariff periods Contribution recovered in the 2012/13 tariff period Cumulative contribution including interest earned Balance of obligations to recover in future tariff periods Remaining period Lilly Pipeline 18,986, ,986, , ,520 18,353, Total 18,986, , ,520 18,353, Transnet used to recognise the decommissioning costs in accordance with International Financial Reporting Standards (IFRS) which required them to make a provision without having to collect the concomitant revenue as required by the regulations. RfD Transnet Tariff Assessment 2012/13 Page 7 of 15

8 5.20 In order to comply with section 34 (1) (d) of the Gas Act and Regulation 11 (4) and (5) which require licensees to provide for financial security in respect of rehabilitation obligations, Transnet is allowed and an amount was incorporated in the Allowable Revenues to be collected starting from the current tariff period which will be use in future towards land rehabilitation costs. Weighted Average Cost of Capital (WACC) 5.21 NERSA used the following formula in its determination of the WACC: WACC Where: E Dt E Dt Dt E ( real) * Ke( real) * Kd ( real) E = equity amount Dt = debt amount Ke (real) = real cost of equity derived from the Capital Asset Pricing Model (CAPM) Kd (real) = the post tax real cost of debt WACC calculation summary NERSA (Rm) TRANSNET (Rm) Cost of Equity (Ke=Rf+(MRP*beta) Real Market Risk Premium (MRP) 5.89% 6.38% Real Risk free rate (Rf) 3.88% 4.38% Beta Real Cost of Equity (Ke) 8.47% 8.49% Cost of Debt Nominal pre-tax Cost of Debt (kd) 10.36% 10.36% Nominal Post tax cost of debt (kd) 7.46% 7.46% Post tax Real cost of debt (kd) 1.62% 1.62% Debt ratio 30% 30% Equity ratio 70% 70% Real WACC 6.41% 6.43% 5.22 Based on the Tariff Guidelines, a minimum debt portion in the capital structure of 30% was used to calculate the WACC The mark-to-market risk free rate of a selected 5 to 10 year government of South Africa bonds were used for the expected risk free return (Rf) in the estimation of cost of equity. This yielded a real risk free rate of 3.88% The market return (Rm) was calculated using the JSE ALL Share Index, converted from a nominal to real value for the previous 25 years (April 1986 to March 2011). The average month-to-month CPI over the same period (April 1986 to March 2011) was used. This yielded a real market risk premium (MRP) of 5.89%. RfD Transnet Tariff Assessment 2012/13 Page 8 of 15

9 5.25 Transnet s MRP calculation was based on the petroleum pipelines tariff methodology determination The beta (β) was determined by proxy. As a proxy, the average of six gas pipeline companies chosen by the Energy Regulator that are listed on stock exchanges must be used as per the Tariff Guidelines. The following US companies were used by the Project Team as proxies: AGL Resources Inc. UGI Corporation South Jersey Industries WGL Holdings Inc. The Laclede Group Piedmont Natural Gas Company Inc NERSA updated and refined its list of proxy companies during the 2012 tariff period so as to capture the gas companies with operational risks closely related to a gas transmission company in South Africa, in this case Transnet. Therefore the companies which NERSA used were purely piped-gas pipelines companies as opposed to combined proxy petroleum pipeline companies used by Transnet in its tariff application NERSA used the Hamada approach to determine the beta, in line with the Tariff Guidelines. This resulted in a leveraged beta of 0.78 for Transnet s gas pipeline business and yielded a real cost of equity (Ke) of 8.47% On the other hand, Transnet used the Harris and Pringle approach to estimate the beta of 0.64, which combined with the different choices of proxy companies, resulted in a real cost of equity of 8.49% The table below gives a summary of NERSA s beta calculation: AGL Resources Inc. UGI Corporation South Jersey Industries WGL Holdings Inc. The Laclede Group Piedmont Natural gas Company Inc $m $m $m $m $m $m $m Total Capital 4, , , , , , Debt/Equity Ratio 53.39% 48.36% 49.74% 34.57% 39.03% 50.77% Effective Tax rate Proxy Beta (B1) Unlevered/Asset Beta (Ba) Weighted Average Beta(WB) Transnet Beta Estimation Tax Debt Equity 28% 30% 70% 0.78 Total 5.31 NERSA used a cost of debt (Kd) of 10.36%, as provided by the applicant, and a corporate tax rate of 28%. This resulted in a post tax cost of debt of 7.46%. RfD Transnet Tariff Assessment 2012/13 Page 9 of 15

10 5.32 The CPI used in calculating the real cost of debt is a forecasted CPI for the next 12 months (5.75%). The CPI information was sourced from the Bureau of Economic Research (BER). The resultant post tax real cost of debt was 1.62%, thus yielding a WACC of 6.41% It must be noted that the sources of information prescribed by NERSA were used as data source for calculating the WACC. Clawback 5.34 Clawback on last year s approved tariff was not determined as the tariff was approved based on the GTA between Transnet and Sasol Gas on which take or pay volumes were used. Therefore this is the first time Transnet seeks approval of the tariff whereby the allowable revenues are determined using the RoR methodology. 6. ANALYSIS OF PROPOSED TARIFFS 6.1 Transnet is requesting the Energy Regulator to change its tariff period from the calendar year (01 January December 2012), to its financial year (01 April March 2013) so as to realign the tariff application to the Regulatory Financial Reporting Period which is aligned to the applicant s financial year. 6.2 Given that both periods cover 12 months, Transnet submits that it does not consider any differences arising from the tariff period changes to be material. 6.3 However, this creates a gap where there is no approved tariff during the period 01 January 2012 to 31 March 2012 since the 2011 approved tariff expired on 31 December Transnet requested for approval of a two phased tariff structure where it will charge a volume based block tariff derived from the GTA formula during the transitional period and then apply the RoR determined tariff with effect from 01 April Analysis of the transitional GTA tariff for 1 January 2012 to 31 March Transnet submits that it will charge a tariff of R8.39 per gigajoule ( GJ ) for volumes up to 12m gigajoules ( MGJ ), R4.81/GJ for volumes greater than 12MGJ but less than 18MGJ and R4.24/GJ for volumes greater than 18MGJ, during the transitional period of 01 January 2012 to 31 March The above tariff structure yields an annualised allowable revenue of R130.39m. This is a 6% increase from the allowable revenue of R approved in RfD Transnet Tariff Assessment 2012/13 Page 10 of 15

11 6.7 The table below gives a comparison of the GTA tariffs for the transitional period against the 2011 GTA approved tariff. GTA Tariffs Proposed 2012 versus Approved 2011 VOLUME 2012 TARIFF Q1 1 (Proposed) R 2011 TARIFF (Approved) R % INCREASE 0-12 m GJ/a % m GJ/a % >18m GJ/a % 6.8 NERSA s previous tariff decisions have been to approve the GTA tariff whenever it was lower than the RoR determined tariff and within reasonable limits. 6.9 The NERSA 2012/13 RoR determined reference tariff is R9.77/GJ linked to a throughput of 17 million gigajoules per annum. Therefore, the approval of the above tariff will be consistent with the Energy Regulator s previous Transnet tariff decisions for the tariff periods ending 31 December 2010 and 31 December Analysis of the RoR determined tariff for April 2012 to March Transnet applied for approval of an allowable revenue of R157.10m based on a focasted throughput of 17 million gigajoules. This is 28% higher than the allowable revenue of R122.78m approved in the last tariff period In the previous tariff period, Transnet applied using the GTA formula. This yielded an allowable revenue of R122.78m. NERSA s assessment using the RoR methodology for the same period yielded an allowable revenue of R185.82m In the 2010 tariff period, the GTA determined allowable revenue was R117.36m while the NERSA RoR tariff assessment yielded an allowable revenue of R140m The table below summarises the above scenario. Comparison of RoR and GTA Allowable Revenues : TARIFF PERIOD NERSA RoR ASSESSMENT R'm TRANSNET GTA DETERMINATION R'm VARIANCE % % % 1 Tariff proposed for the transitional period of 01 January 2012 to 31 March 2012 RfD Transnet Tariff Assessment 2012/13 Page 11 of 15

12 6.14 The above table shows that the GTA formula has to date yielded significantly lower tariffs than the RoR methodology. Year-on-Year Tariff Assessment Comparison 6.15 The table below shows a year on year comparison of the NERSA RoR tariff assessment. Comparison of Year-on-Year NERSA RoR Assessment NERSA RoR TARIFF PERIOD ASSESSMENT Year R'm Year-on-Year Increase % % 6.16 It is important to note that the 2012 NERSA RoR assessment allowable revenue of R166.12m is 11% lower than the 2011 RoR assessment of R185.82m. This is partly attributable to the Regulatory Reporting Manual (RRM) implementation which led to a fair and enhanced allocation of costs between different business activities namely Piped-gas, petroleum pipelines and petroleum storage facilities In addition, the 2012 tariff application is based on an actual through-put of mGJ/annum as opposed to the 2011 tariff application which was based on a take-or-pay through-put of 18.2mGJ/annum Therefore, although the R157.10m allowable revenue Transnet is applying for is 28% higher than last year s GTA determined and approved allowable revenue of R122.78m, it is 18% lower than the 2011 NERSA RoR assessment of R185.82m and 6% lower than NERSA s 2012 RoR assessment of R166.12m. In light of these assessments, NERSA is able to approve this tariff. 7. CHANGE OF TARIFF PERIOD 7.1 Transnet requested the Energy Regulator to change its tariff period from the calendar year (01 January December 2012), to its financial year (01 April March 2013) so as to realign the tariff application to the Regulatory Financial Reporting period which is aligned to the applicant s financial year. 7.2 Transnet submitted that it did not consider any differences arising from the tariff period changes to be material, since both periods cover 12 months. RfD Transnet Tariff Assessment 2012/13 Page 12 of 15

13 8. THE DECISION MAKING PROCESS 8.1 The preliminary transmission tariff assessment for the Lilly pipeline was received on 27 January 2012 and was approved by NERSA on 22 March 2012, for the period 01 January 2012 to 31 March A consultation document and a notice on the preliminary tariff assessment were published on the NERSA website and in the media. The closing date for submitting comments to the Energy Regulator was 20 April A public hearing on the draft tariff assessment was held on 04 May The tariff was considered and approved by the Energy Regulator on 26 July The paragraphs below provide an analysis of the consultation comments. 9. PUBLIC HEARING 9.1 A public hearing was held on 04 May 2012 so as to solicit stakeholder comments. The following paragraphs discuss the main issues raised during the public hearing. Electricity expense 9.2 In its tariff application, Transnet had budgeted for a net increase of electricity expense of 25.1% in 2012/13, based on Eskom s focasted tariff increase of 25.9%. 9.3 However, due to the lower increase in the NERSA approved Eskom tariff for 2012 (16%), the Energy Regulator requested Transnet to restate its forecasted operating expenses using the latest electricity tariff increase. 9.4 The restatement has resulted in the decrease in Transnet s operating expenses from R59m to R58.9m. This restated expenses figure of R58.9m was used in the final tariff assessment to yield a reference tariff of R9.24/GJ. 9.5 The downward revision of the percentage year-to-year increases in electricity tariff only reduces total operating expenses by R0.1m. This indicates that non-recurring costs and decommissioning costs, which were previously not provided for in the last period, are a significant cost driver in the current period as opposed to the electricity cost. Gearing 9.6 The Energy Regulator requested Transnet to provide a split and allocation of the corporate gearing into different business units namely petroleum pipelines, petroleum storage facilities and piped-gas. RfD Transnet Tariff Assessment 2012/13 Page 13 of 15

14 9.7 The average corporate gearing is 40.8%. However, due to ring fencing, this translates to 44.3% for petroleum pipelines, 24.9% for piped-gas and 26.0% for petroleum storage facilities. 9.8 Since the gas gearing is 24.9%, a minimum gearing of 30% was used by both Transnet and NERSA in the tariff calculation as per the Tariff Guidelines. 10. STAKEHOLDER COMMENTS 10.1 Stakeholders were invited to provide written comments, on the draft tariff assessment to the Energy Regulator, which were considered before taking a final decision on the matter. Comments were received from 23 March 2012 to 20 April 2012 and are discussed below. Change in Tariff Methodology from GTA to RoR 10.2 Transnet applied for the GTA tariff in both 2010 and 2011 and that the commercially agreed tariff was approved by NERSA in both periods. Therefore it is not clear how conditions could have changed over a period of a year to justify a departure from the previous GTA tariff. Response 10.3 Section 3.1 of the Tariff Guidelines states that The Energy Regulator will request licensees to submit a tariff application based on their preferred methodology that may be chosen from the approved menu of tariff methodologies. The RoR is one of the approved tariff methodologies In the year under review, Transnet applied using the RoR and as per the Tariff Guidelines, NERSA used the same tariff methodology to assess the tariff application In addition, although NERSA approved the 2010 and 2011 GTA tariffs, the assessments were done using the RoR so as to test for their reasonableness. During both of those assessment, NERSA determined that the GTA does not allow Transnet to recover its fully efficiently incurred costs and make a profit commensurate with risk as required by the Regulations. In addition, the GTA seems not to have allowed Transnet to recover, over time, through tariffs the land rehabilitation costs in order to provide the financial security required by the Regulations. Operating expenses 10.6 It was asserted that a 21% increase in Transnet s operating expenses without extraordinary expense items is unexpected from a prudent operator. RfD Transnet Tariff Assessment 2012/13 Page 14 of 15

15 Response 10.7 Transnet has revised some of its costs in line with the latest Eskom approved electricity tariff decrease from 25.9% to 16%. Decommissioning costs which were not recognised in the previous period have contributed to the increase in expenses. Other non-recurring costs such as professional fees and legal fees emanating from the GTA renegotiation increased the 2012 forecasts. However with the application of the RoR, it will be possible to apply clawback should the estimated expenses turn out to be lower than the actual expenses for the tariff period under review In addition, all the other cost estimates were 2011 actual operating expenses escalated using the CPI to get the 2012 forecasts, except where other factors were at play such as electricity costs which increased by 16% and indirect costs which were allocated using the cost drivers from the Cost Allocation Manual approved by NERSA. Proxy companies used in beta calculation 10.9 There was an enquiry into the reasons why the set of proxy companies used by NERSA in its assessment was different from Transnet in its tariff application. Response NERSA updated and refined the list of proxy companies during the 2012 tariff period, in line with section of the Tariff Guidelines, so as to capture the piped-gas pipelines companies with operational risks closely related to a gas transmission company in South Africa, in this case Transnet. Therefore the companies which NERSA used were purely piped-gas pipelines companies as opposed to combined petroleum pipeline companies used by Transnet. 11. CONCLUSION 11.1 In light of the reasons highlighted above, the Energy Regulator decided to approve the gas transmission tariff for Transnet Pipelines Lilly pipeline from Secunda to Durban South for the period 01 January 2012 to 31 March as follows: a tariff of R8.39 per gigajoule ( GJ ) for volumes up to 12m gigajoules ( MGJ ), R4.81/GJ for volumes greater than 12MGJ but less than 18MGJ and R4.24/GJ for volumes greater than 18MGJ, for the period 01 January 2012 to 31 March 2012; a tariff of R9.24/GJ for the period 01 April 2012 to 31 March 2013; and discounts on the above tariffs are permissible and the tariffs will be applicable until new tariffs are approved. RfD Transnet Tariff Assessment 2012/13 Page 15 of 15

1. INTRODUCTION 2. APPLICABLE LAW

1. INTRODUCTION 2. APPLICABLE LAW Consultation document regarding the Republic of Mozambique Pipeline Investments Company (ROMPCO) pipeline s preliminary gas transmission tariff determination for 2011/12. 1. INTRODUCTION 1.1 The Energy

More information

TRANSNET SOC LTD: TARIFF APPLICATION FOR THE LICENCED PIPED GAS TRANSMISSION FACILITY FOR THE 2016/17 TARIFF YEAR

TRANSNET SOC LTD: TARIFF APPLICATION FOR THE LICENCED PIPED GAS TRANSMISSION FACILITY FOR THE 2016/17 TARIFF YEAR TRANSNET SOC LTD: TARIFF APPLICATION FOR THE LICENCED PIPED GAS TRANSMISSION FACILITY FOR THE 2016/17 TARIFF YEAR 1 Contents 1 Executive Summary... 6 2 Background... 8 3 Approach... 9 4 Regulatory Asset

More information

TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2012/13 (01 APRIL 2012 TO 31 MARCH 2013)

TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2012/13 (01 APRIL 2012 TO 31 MARCH 2013) TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2012/13 (01 APRIL 2012 TO 31 MARCH 2013) Table of Contents 1 Executive Summary... 5 2 Background... 8 3 Approach... 9 4 Regulatory Asset Base

More information

TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2011/12 (01 APRIL 2011 TO 31 MARCH 2012)

TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2011/12 (01 APRIL 2011 TO 31 MARCH 2012) TRANSNET PETROLEUM PIPELINES TARIFF APPLICATION FOR THE YEAR 2011/12 (01 APRIL 2011 TO 31 MARCH 2012) Table of Contents 1 Executive Summary... 5 2 Background... 8 3 Approach... 9 4 Regulatory Asset Base

More information

OPERATING MANUAL: NERSA s STORAGE TARIFF MODEL

OPERATING MANUAL: NERSA s STORAGE TARIFF MODEL OPERATING MANUAL: NERSA s STORAGE TARIFF MODEL According to Section 28 (1) of the Petroleum Pipelines Act, 2003 (Act No. 60 of 2003): The Authority must set as a condition of license the tariffs to be

More information

NERSA STORAGE AND LOADING FACILITIES MODEL. November 2008

NERSA STORAGE AND LOADING FACILITIES MODEL. November 2008 NERSA STORAGE AND LOADING FACILITIES MODEL November 2008 1 OVERVIEW Legal Mandate Tariff Approaches Allowable Revenue Assessment of Tariff Applications Questions and Discussions 2 LEGAL MANDATE Section

More information

Chevron Oil South Africa (Pty) Limited

Chevron Oil South Africa (Pty) Limited Chevron Oil South Africa (Pty) Limited NERSA s Storage Tariff Submission: Tariffs applicable for 2012/2013 For Waltloo and East London depots Initial submission 17 October 2011 Resubmission 10 August 2012

More information

DRAFT TARIFF DETERMINATION for TRANSNET LIMITED PETROLEUM PIPELINES SYSTEM for 2012/13

DRAFT TARIFF DETERMINATION for TRANSNET LIMITED PETROLEUM PIPELINES SYSTEM for 2012/13 DRAFT TARIFF DETERMINATION for TRANSNET LIMITED PETROLEUM PIPELINES SYSTEM for 2012/13 The Energy Regulator is publishing this document for public comment. This draft tariff determination uses numbers

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA (NERSA)

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA (NERSA) NATIONAL ENERGY REGULATOR OF SOUTH AFRICA (NERSA) In the matter regarding REVIEW OF THE GUIDELINES FOR MONITORING AND APPROVING TRANSMISSION AND STORAGE TARIFFS IN THE PIPED-GAS INDUSTRY IN SOUTH AFRICA

More information

TRANSNET SOC LIMITED PETROLEUM PIPELINES SYSTEM 2014/15 TARIFF DECISION

TRANSNET SOC LIMITED PETROLEUM PIPELINES SYSTEM 2014/15 TARIFF DECISION TRANSNET SOC LIMITED PETROLEUM PIPELINES SYSTEM 2014/15 TARIFF DECISION 13 March 2014 1 Table of Contents Page Table of Contents... 2 List of Tables... 3 List of Figures... 4 Abbreviations and Acronyms...

More information

APPROVAL OF TARIFF METHODOLOGIES FOR USE IN THE PETROLEUM PIPELINES INDUSTRY. THE DECISION

APPROVAL OF TARIFF METHODOLOGIES FOR USE IN THE PETROLEUM PIPELINES INDUSTRY. THE DECISION ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding APPROVAL OF TARIFF METHODOLOGIES FOR USE IN THE PETROLEUM PIPELINES INDUSTRY. THE DECISION On 31 March 2011 the Energy Regulator approved the following

More information

CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017

CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017 CONSULTATION PAPER THE DISCOUNT RATE METHODOLOGY FOR LICENSED ELECTRICITY DISTRIBUTORS PUBLISHED ON 19 SEPTEMBER 2017 Table of Contents Abbreviations and acronyms... 3 Definitions... 3 Executive summary...

More information

Transnet National Ports Authority Tariff Methodology: Position Paper Ports Regulator: Road Shows March delivering freight reliably

Transnet National Ports Authority Tariff Methodology: Position Paper Ports Regulator: Road Shows March delivering freight reliably Transnet National Ports Authority Tariff Methodology: Position Paper Ports Regulator: Road Shows March 2013 delivering freight reliably Vision for South African Ports A system of ports, seamlessly integrated

More information

Guidelines for Monitoring and Approving Piped-Gas Transmission and Storage Tariffs in South Africa

Guidelines for Monitoring and Approving Piped-Gas Transmission and Storage Tariffs in South Africa Guidelines for Monitoring and Approving Piped-Gas Transmission and Storage Tariffs in South Africa Final March 2017 These Tariff Guidelines replace the 2009 version CONTENTS GLOSSARY... III ABBREVIATIONS...

More information

EASIGAS PTY (LTD) NIGEL S STORAGE FACILITY TARIFF APPLICATION FOR THE YEARS Nigel Storage Facility

EASIGAS PTY (LTD) NIGEL S STORAGE FACILITY TARIFF APPLICATION FOR THE YEARS Nigel Storage Facility EASIGAS PTY (LTD) NIGEL S STORAGE FACILITY TARIFF APPLICATION FOR THE YEARS 2015 Nigel Storage Facility 2015 Page 1 Table of Contents 1. Introduction 5 2. Executive Summary 6/7 3. Approach 7/8 4. Regulatory

More information

NATIONAL ENERGY REGULATOR TARIFF METHODOLOGY FOR THE APPROVAL OF TARIFFS FOR PETROLEUM LOADING FACILITIES AND PETROLEUM STORAGE FACILITES

NATIONAL ENERGY REGULATOR TARIFF METHODOLOGY FOR THE APPROVAL OF TARIFFS FOR PETROLEUM LOADING FACILITIES AND PETROLEUM STORAGE FACILITES NATIONAL ENERGY REGULATOR TARIFF METHODOLOGY FOR THE APPROVAL OF TARIFFS FOR PETROLEUM LOADING FACILITIES AND PETROLEUM STORAGE FACILITES 2 nd Edition Approved: 31 March 211 Tariff Methodology for Petroleum

More information

Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the. Petroleum Pipelines Industry.

Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the. Petroleum Pipelines Industry. Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the Petroleum Pipelines Industry Approved 24 August 2017 Table of Contents Page Glossary of Terms and Abbreviations......4

More information

Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and. Robert Opini, Advisor, Regulatory Reporting. NERSA South Africa

Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and. Robert Opini, Advisor, Regulatory Reporting. NERSA South Africa Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and Robert Opini, Advisor, Regulatory Reporting NERSA South Africa Boosting Investor Confidence: The Role of Regulators The

More information

Regulatory Manual for the Tariff Year 2014/15

Regulatory Manual for the Tariff Year 2014/15 Regulatory Manual for the Tariff Year 2014/15 Page 1 of 17 Contents Page 1. Abbreviations 3 2. Introduction 4 3. The Regulator s Mandate 5 4. Special note on Compliance with the Directives, Regulations

More information

Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the. Petroleum Pipelines Industry.

Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the. Petroleum Pipelines Industry. Frequently Asked Questions (FAQ): Tariff Methodology for the Setting and Approval of Tariffs in the Petroleum Pipelines Industry Approved on 26 May 2016 Frequently Asked Questions (FAQ): Tariff Methodology

More information

Port Tariff Methodology. For Tariff Years 2018/ /21 MARCH 2017

Port Tariff Methodology. For Tariff Years 2018/ /21 MARCH 2017 Port Tariff Methodology For Tariff Years 2018/19 2020/21 MARCH 2017 Contents Page Methodology review context... 3 Introduction... 3 Background: The Regulator s Mandate... 4 The Multi-Year Methodology in

More information

MYPD Methodology Eskom Response to Consultation Paper

MYPD Methodology Eskom Response to Consultation Paper MYPD Methodology Eskom Response to Consultation Paper 2 June 2016 Introduction Eskom is pleased to provide comments Eskom has provided detailed responses to the consultation paper on the review of the

More information

Tariff Application. TOTAL South Africa (Proprietary) Limited

Tariff Application. TOTAL South Africa (Proprietary) Limited TOTAL South Africa (Proprietary) Limited Tariff Application Alrode, Bethlehem, East London, Island View Terminal, Nelspruit, Ohrigstad, Polokwane, Waltloo Sannieshof & Pietermaritzburg 213 Address: PO

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2018/19 FINANCIAL YEAR Consultation Paper Published on 28 February 2018 Table

More information

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2)

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2) Issues Paper Eskom Revenue Application Multi Year Price Determination 2010/11 to 2012/13 (MYPD 2) Published on 30 October 2009 1 TABLE OF CONTENTS Abbreviations... 3 Definitions... 4 1. Introduction...6

More information

NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY

NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY NERSA CONSULTATION PAPER: ESKOM MULTI-YEAR PRICE DETERMINATION METHODOLOGY Published on: 14 October 2011 TABLE OF CONTENTS Page Abbreviations and Acronyms... 3 1 The Consultation Process... 5 2 Introduction...

More information

THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS. Submission to the National Ports Regulator

THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS. Submission to the National Ports Regulator THE SOUTH AFRICAN ASSOCIATION OF FREIGHT FORWARDERS 12 Skeen Boulevard Bedfordview P O Box 2510 Bedfordview 2008 Republic of South Africa Tel: (011) 455 1726/1707 Fax: (011) 455 1709 Republic of South

More information

Draft Decision on Maximum Allowable Revenue Aurizon Network s 2014 Draft Access Undertaking. 30 September 2014

Draft Decision on Maximum Allowable Revenue Aurizon Network s 2014 Draft Access Undertaking. 30 September 2014 Draft Decision on Maximum Allowable Revenue Aurizon Network s 2014 Draft Access Undertaking 30 September 2014 Contents Background to Draft Decision Maximum Allowable Revenue Building Blocks for MAR Operating

More information

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT Reportable Case No: 728/2015 In the matter between: TRANSNET SOC LIMITED APPELLANT and TOTAL SOUTH AFRICA (PTY) LTD FIRST RESPONDENT SASOL OIL (PTY)

More information

DEFINITIONS 2 CHAPTER ONE: LICENSED ACTIVITIES... 3 CHAPTER TWO: GENERAL CONDITIONS... 4 CHAPTER THREE: SPECIFIC CONDITIONS... 10

DEFINITIONS 2 CHAPTER ONE: LICENSED ACTIVITIES... 3 CHAPTER TWO: GENERAL CONDITIONS... 4 CHAPTER THREE: SPECIFIC CONDITIONS... 10 Licence number: Gala.tr.F1/1421/2008 LICENCE CONDITIONS FOR TRADING IN GAS OVER THE GAS TRANSMISION FACILITIES SITUATED IN THE GAUTENG, FREE STATE AND MPUMALANGA PROVINCES BY SASOL GAS LIMITED TABLE OF

More information

A Methodology for the. Valuation of the Regulatory Asset Base

A Methodology for the. Valuation of the Regulatory Asset Base A Methodology for the Discussion Document & Valuation Methodology Rules Published for Public Comment The Ports Regulator of South Africa has published a Discussion Paper and Methodology Rules for the Valuation

More information

Independent Pricing and Regulatory Tribunal. Comparison of financial models - IPART and Australian Energy Regulator

Independent Pricing and Regulatory Tribunal. Comparison of financial models - IPART and Australian Energy Regulator Independent Pricing and Regulatory Tribunal Comparison of financial models - IPART and Australian Energy Regulator Research Research Paper November 2009 Comparison of financial models IPART and Australian

More information

The Revenue Requirement

The Revenue Requirement The Revenue Requirement Csaba Kovács Hungarian Energy Office NARUC Training on Tariff Development and Utility Regulation Baku, 07-11/05/2007 1 Content of the presentation Main principles of tariff regulation

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2017/18 FINANCIAL YEAR Consultation Paper 23 February 2017 TABLE OF CONTENTS

More information

GOLDFIELDS GAS PIPELINE. Proposed Revised Access Arrangement Information

GOLDFIELDS GAS PIPELINE. Proposed Revised Access Arrangement Information GOLDFIELDS GAS PIPELINE Proposed Revised Access Arrangement Information Review submission date: 1 January 2019 GOLDFIELDS GAS PIPELINE CONTACT DETAILS Principal Office: Level 5 Eastpoint Plaza 233 Adelaide

More information

Port of Melbourne tariff compliance statement

Port of Melbourne tariff compliance statement 2017-18 Port of Melbourne tariff compliance statement Interim commentary 9 November 2017 An appropriate citation for this paper is: Essential Services Commission 2017, 2017-18 Port of Melbourne tariff

More information

LESOTHO ELECTRICITY AUTHORITY. Regulatory Accounting Guidelines

LESOTHO ELECTRICITY AUTHORITY. Regulatory Accounting Guidelines LESOTHO ELECTRICITY AUTHORITY Regulatory Accounting Guidelines Table of Contents REGULATORY ACCOUNTING GUIDELINES 1. Abbreviations... 3 2. Definitions... 4 3. Introduction and Purpose... 6 4. Legal Basis

More information

Benchmarking Transnet Limited s Petroleum Pipelines

Benchmarking Transnet Limited s Petroleum Pipelines Benchmarking Transnet Limited s Petroleum Pipelines December 2011 Table of Contents Page CHAPTER 1... 1 1.1 Introduction... 1 1.2 Background... 2 1.3 Theoretical overview... 3 1.3.1 Literature Review...

More information

The consolidated financial statements were authorised for issue by the Board of Directors on 1 June 2015.

The consolidated financial statements were authorised for issue by the Board of Directors on 1 June 2015. ACCOUNTING POLICIES for the year ended 31 March 2015 Transnet SOC Ltd (the Company ) is a company domiciled in South Africa. The consolidated financial statements for the year ended 31 March 2015 comprise

More information

Determination: Allowable Revenue and Forecast Capital Expenditure for System Management 2013/14 to 2015/16

Determination: Allowable Revenue and Forecast Capital Expenditure for System Management 2013/14 to 2015/16 Determination: Allowable Revenue and Forecast Capital Expenditure for System Management 2013/14 to 2015/16 March 2013 31 March 2013 This document is available from the s website at www.erawa.com.au. For

More information

Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year

Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year 30 January 2013 Important Notice This document has been compiled in good faith by

More information

Financing and Cost of Capital estimation for Regulated Enterprises

Financing and Cost of Capital estimation for Regulated Enterprises 1 Financing and Cost of Capital estimation for Regulated Enterprises ERRA/NARUC Regulatory and tariff Workshop Baku, Azerbaijan July 2008 Hasso C. Bhatia, PhD Utility Sector Adviser USAID Trade and Investment

More information

The Authority s comments on the Tariff Methodology

The Authority s comments on the Tariff Methodology The Authority s comments on the Tariff Methodology 1. Context The National Ports Authority (the Authority) is one of five operating divisions of Transnet SOC Ltd. It is responsible for the safe, effective

More information

CROATIAN ENERGY REGULATORY AGENCY

CROATIAN ENERGY REGULATORY AGENCY UNOFFICIAL TRANSLATION CROATIAN ENERGY REGULATORY AGENCY Pursuant to Article 11, paragraph 1, item 9 of the Act on the Regulation of Energy Activities ( Official Gazette, number 120/12) and Article 88,

More information

DIRECT INFRASTRUCTURE VALUATIONS AND BOND RATE INCREASES:

DIRECT INFRASTRUCTURE VALUATIONS AND BOND RATE INCREASES: insightpaper DIRECT INFRASTRUCTURE VALUATIONS AND BOND RATE INCREASES: it s not what you expect April 2017 AMP CAPITAL INFRASTRUCTURE 1 Key points Future bond rate increases are likely to be moderate.

More information

.3t?/rJ4. 4 Od-ober Zo lb 7 DATE - " In the matter between: Heard: 12 May 2018 REPUBLIC OF SOUTH AFRICA

.3t?/rJ4. 4 Od-ober Zo lb 7 DATE -  In the matter between: Heard: 12 May 2018 REPUBLIC OF SOUTH AFRICA - " 1 REPUBLIC OF SOUTH AFRICA IN THE IDGH COURT OF SOUTH AFRICA GAUTENG DMSION, PRETORIA (I) (2) (3) REPORTABLE: Jtllt!tNO OF INTEREST TO OlHER JUOOES;;di(t NO REVISED: YESJM4..3t?/rJ4 7 DATE In the matter

More information

Compliance with Control Mechanisms. October 2014

Compliance with Control Mechanisms. October 2014 04.01.00 Compliance with Control Mechanisms October 2014 Contents 1 Introduction... 2 1.1 Overview... 2 1.2 Allocation of services to controls... 3 2 Compliance with Control Mechanism for Standard Control

More information

Economic Regulation Workshop

Economic Regulation Workshop Economic Regulation Workshop Role of IPART Setting prices for water utilities 8 October 2018 Contents 1. Why and how does IPART regulate prices? 2. Form of regulation 3. Building block approach 4. Expenditure

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

China Construction Bank Corporation, Johannesburg Branch

China Construction Bank Corporation, Johannesburg Branch China Construction Bank Corporation, Johannesburg Branch Pillar 3 Disclosure (for the year ended 31 December 2014) Builds a better future PUBLIC Content Page 1. Overview 3 2. Financial performance 3 3.

More information

Essential Energy Regulatory proposal Submission to the AER Issues Paper August 2018

Essential Energy Regulatory proposal Submission to the AER Issues Paper August 2018 This work by Energy Consumers Australia is licensed under a Creative Commons Attribution 4.0 International License. To view a copy of this license, visit http://creativecommons.org/licenses/by/4.0/. Where

More information

Review of Floor and Ceiling Cost Proposal of the Pilbara Infrastructure Pty Ltd

Review of Floor and Ceiling Cost Proposal of the Pilbara Infrastructure Pty Ltd In association with AECOM Economic Regulation Authority Review of Floor and Ceiling Cost Proposal of the Pilbara Infrastructure Pty Ltd Draft Report February 2011 Disclaimer This draft report has been

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Bloemfontein 15 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

Forecast Expenditure Summary Operating Costs

Forecast Expenditure Summary Operating Costs 06.01.01 Forecast Expenditure Summary Operating Costs Contents 1 Introduction... 4 1.1 Operating expenditure forecast summary... 4 1.2 Ergon Energy s approach... 6 1.3 Operating expenditure forecasting

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings 30 October 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained its revenue

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding NATIONAL ENERGY REGULATOR OF SOUTH AFRICA DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE FOR THE FINANCIAL YEAR 2013/14 AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS DECISION

More information

MYPD3 Application Gauteng January 2013

MYPD3 Application Gauteng January 2013 MYPD3 Application 2014-2018 Gauteng January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

TRANSNET NATIONAL PORTS AUTHORITY

TRANSNET NATIONAL PORTS AUTHORITY TRANSNET NATIONAL PORTS AUTHORITY TARIFF APPLICATION FOR FINANCIAL YEAR 2016/17 Tariff Application to the Ports Regulator in terms of the National Ports Act, 2005 (Act No.12 of 2005) Contents 1. Executive

More information

Submission to the Queensland Competition Authority (QCA) Gladstone Area Water Board 2015 Price Monitoring Investigation

Submission to the Queensland Competition Authority (QCA) Gladstone Area Water Board 2015 Price Monitoring Investigation Submission to the Queensland Competition Authority (QCA) Gladstone Area Water Board 2015 Price Monitoring Investigation Submission to the Queensland Competition Authority November 2014 Page 1 of 12 Contents

More information

Brookfield Infrastructure Partners L.P.

Brookfield Infrastructure Partners L.P. Brookfield Infrastructure Partners L.P. UNAUDITED INTERIM CONDENSED AND CONSOLIDATED FINANCIAL STATEMENTS AS OF AND FOR THE THREE MONTHS ENDED MARCH 31, 2012 (U.S. DOLLARS IN MILLIONS) INDEX Page Unaudited

More information

SOUTH AFRICAN NATIONAL TAXI COUNCIL (SANTACO) ACQUIRES A 25% STAKE IN SA TAXI FINANCE HOLDINGS PROPRIETARY LIMITED ( SA TAXI ) FOR R1.

SOUTH AFRICAN NATIONAL TAXI COUNCIL (SANTACO) ACQUIRES A 25% STAKE IN SA TAXI FINANCE HOLDINGS PROPRIETARY LIMITED ( SA TAXI ) FOR R1. Transaction Capital Limited (Incorporated in the Republic of South Africa) Registration number: 2002/031730/06 JSE share code: TCP ISIN: ZAE000167391 ( Transaction Capital ) SOUTH AFRICAN NATIONAL TAXI

More information

Determination Notice

Determination Notice Office of Utilities Regulation Jamaica Public Service Company Limited Extraordinary Rate Review 2017 Determination Notice DOCUMENT TITLE AND APPROVAL PAGE 1. DOCUMENT NUMBER: 2017/ELE/001/DET.001 2. DOCUMENT

More information

Chairman of the Ports Regulator of South Africa 11th Floor, The Marine Building 22 Dorothy Nyembe Street Durban 4001 South Africa

Chairman of the Ports Regulator of South Africa 11th Floor, The Marine Building 22 Dorothy Nyembe Street Durban 4001 South Africa Richards Bay Minerals The Farm RBM PO Box 401, Richards Bay, 3900 KwaZulu-Natal, South Africa T +27 (0) 35 901 3111 F +27 (0) 35 901 3442 Chairman of the Ports Regulator of South Africa 11th Floor, The

More information

14. Conclusion and recommendations

14. Conclusion and recommendations 14. Conclusion and recommendations 14.1. The recommendations resulting from the market inquiry seek to introduce or encourage changes in the domestic LPG sector that will promote efficiency, improve security

More information

TRANSMISSION TARIFF METHODOLOGY FOR THE WEST AFRICAN POWER POOL

TRANSMISSION TARIFF METHODOLOGY FOR THE WEST AFRICAN POWER POOL AUTHORIDADE REGIONAL REGULADORA DE ELETRICIDADE DA CEDEAO ECOWAS REGIONAL ELECTRICITY REGULATORY AUTHORITY AUTORITÉ DE RÉGULATION RÉGIONALE DU SECTEUR DE L ÉLECTRICITÉ DE LA CEDEAO TRANSMISSION TARIFF

More information

Q Supplemental Information Quarter ended September 30

Q Supplemental Information Quarter ended September 30 Q3 2015 Supplemental Information Quarter ended NYSE: BIP TSX: BIP.UN CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS 1 This Supplemental Information contains forward-looking information within

More information

Dear Shareholders, of Gruppo Editoriale L Espresso S.p.A. 1 Reason and object of the mandate

Dear Shareholders, of Gruppo Editoriale L Espresso S.p.A. 1 Reason and object of the mandate KPMG S.p.A. Accounting audit and organisation Via Ettore Petrolini, 2 00197 ROME RM Telephone +39 06 809611 e mail it fmauditaly@kpmg.it Certified e mail: kpmgspa@pec.kpmg.it Independent Auditors Report

More information

tes for Guidance Taxes Consolidation Act 1997 Finance Act 2017 Edition - Part 24

tes for Guidance Taxes Consolidation Act 1997 Finance Act 2017 Edition - Part 24 Part 24 Taxation of Profits of Certain Mines and Petroleum Taxation CHAPTER 1 Taxation of profits of certain mines 670 Mine development allowance 671 Marginal coal mine allowance 672 Interpretation (sections

More information

Determining the cost of capital for the UCLL and UBA price reviews

Determining the cost of capital for the UCLL and UBA price reviews ISBN no. 978-1-869453-57-2 Project no. 13.01/14544 Public version Determining the cost of capital for the UCLL and UBA price reviews Technical consultation paper Date: 7 March 2014 2 CONTENTS LIST OF DEFINED

More information

Weighted Average Cost of Capital (WACC) Consultation Paper ( )

Weighted Average Cost of Capital (WACC) Consultation Paper ( ) Weighted Average Cost of Capital (WACC) Consultation Paper Periodic review of input values for TSO/MO and DSO (2018-2022) DISCLAIMER This Consultation Paper has been prepared by ERO in order to inform

More information

Transmission Tariff Code

Transmission Tariff Code ENERGY AND WATER UTILITIES REGULATORY AUTHORITY (EWURA) THE TANZANIAN GRID CODE Transmission Tariff Code 7 of 8 Code Documents 28 th January 2014 Enquiries: EWURA, Tanzania Table of Contents 1 Introduction

More information

NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER Corporate information

NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER Corporate information 1 Corporate information Petrofac Limited (the Company ) is a limited liability company registered and domiciled in Jersey under the Companies (Jersey) Law 1991 and is the holding company for the international

More information

Economic regulation of capacity expansion at Heathrow: policy update and consultation

Economic regulation of capacity expansion at Heathrow: policy update and consultation Consumers and Markets Group Economic regulation of capacity expansion at Heathrow: policy update and consultation CAP 1610 Published by the Civil Aviation Authority, 2017 Civil Aviation Authority, Aviation

More information

METHODOLOGY DETERMINING PRICES FOR ACCESS AND TRANSMISSION OF NATURAL GAS THROUGH THE GAS TRANSMISSION NETWORKS OWNED BY BULGARTRANSGAZ EAD

METHODOLOGY DETERMINING PRICES FOR ACCESS AND TRANSMISSION OF NATURAL GAS THROUGH THE GAS TRANSMISSION NETWORKS OWNED BY BULGARTRANSGAZ EAD METHODOLOGY DETERMINING PRICES FOR ACCESS AND TRANSMISSION OF NATURAL GAS THROUGH THE GAS TRANSMISSION NETWORKS OWNED BY BULGARTRANSGAZ EAD Issued by State Energy and Water Regulatory Commission, promulgated

More information

Tariff Application Financial Year 13/14

Tariff Application Financial Year 13/14 Tariff Application Financial Year 13/14 Tariff application to the Ports Regulator in terms of the National Ports Act, 2005 (Act No. 12 of 2005) September 2012 1 Contents List of Tables and Diagrams...

More information

A A U D Pipelines 2018

A A U D Pipelines 2018 A U A D Pipelines 2018 2 Highlights Revenue of R4,1 billion, excluding clawback and levy A 1,43% increase in petroleum allowable revenue EBITDA margin of 71% Operationalisation of the Coastal Terminal

More information

Port Tariff Incentive Programme PTIP. 1

Port Tariff Incentive Programme PTIP.  1 Port Tariff Incentive Programme PTIP www.portsregulator.org 1 Introduction PRSA recognises that policy needs to be responsive to the current needs of the economy and a mechanism is required to support

More information

Cancellation of possessions conclusions on the proposal for a liquidated sums approach to compensation payment

Cancellation of possessions conclusions on the proposal for a liquidated sums approach to compensation payment Kings Place 90 York Way London, N1 9AG T: 020 3356 9325 24 September 2013 Cancellation of possessions conclusions on the proposal for a liquidated sums approach to compensation payment Dear colleague,

More information

FY2017/18, Year 5 of MYPD 3 Period

FY2017/18, Year 5 of MYPD 3 Period MYPD 3: Regulatory Clearing Account Submission to NERSA FY2017/18, Year 5 of MYPD 3 Period September 2018 Contents Contents Contents... 2 Preface... 8 1.1 The basis of submissions...8 1.2 The structure

More information

Guidance Notes for Preparing Enterprise Valuations of Irrigation Schemes

Guidance Notes for Preparing Enterprise Valuations of Irrigation Schemes Guidance Notes for Preparing Enterprise Valuations of Irrigation Schemes NOVEMBER 2016 Contents 1. Introduction 3 2. Irrigation scheme valuation issues 4 Unique features of irrigation cooperatives 4 Impacts

More information

Uniform System of Accounts for Electricity Tariff Setting.

Uniform System of Accounts for Electricity Tariff Setting. Uniform System of Accounts for Electricity Tariff Setting. submitted to by Dr. William Gboney (Electricity Consultant) March 11, 2015. 0 Definitions Audited Reports of Accounts: Means an account which

More information

Independent Pricing and Regulatory Tribunal. Comparison of financial models - IPART and Australian Energy Regulator

Independent Pricing and Regulatory Tribunal. Comparison of financial models - IPART and Australian Energy Regulator Independent Pricing and Regulatory Tribunal Comparison of financial models - IPART and Australian Energy Regulator Research Information Paper July 2012 Comparison of financial models IPART and Australian

More information

Ergon Energy s Building Block Components

Ergon Energy s Building Block Components 03.01.01 Ergon Energy s Building Block Components Contents 1 Introduction... 3 1.1 Overview... 3 1.2 Purpose of this document... 3 1.3 NER requirements... 4 1.4 Structure of this document... 5 2 Regulatory

More information

Consultation and decision paper CP17/44. PSR regulatory fees

Consultation and decision paper CP17/44. PSR regulatory fees Consultation and decision paper PSR regulatory fees Policy decision on the approach to the collection of PSR regulatory fees from 2018/19 and further consultation on the fees allocation method December

More information

OAO GAZPROM IFRS CONSOLIDATED FINANCIAL STATEMENTS 31 DECEMBER 2014

OAO GAZPROM IFRS CONSOLIDATED FINANCIAL STATEMENTS 31 DECEMBER 2014 IFRS CONSOLIDATED FINANCIAL STATEMENTS 31 DECEMBER 2014 1 NATURE OF OPERATIONS OAO Gazprom and its subsidiaries (the Group ) operate one of the largest gas pipeline systems in the world and are responsible

More information

1. INTRODUCTION AND PURPOSE 2. DEFINITIONS

1. INTRODUCTION AND PURPOSE 2. DEFINITIONS Solvency Assessment and Management: Steering Committee Position Paper 28 1 (v 6) Treatment of Expected Profits Included in Future Cash flows as a Capital Resource 1. INTRODUCTION AND PURPOSE An insurance

More information

Consultation Paper: Insurance Solvency Standards and NZ IFRS 16 Leases July 2018

Consultation Paper: Insurance Solvency Standards and NZ IFRS 16 Leases July 2018 Consultation Paper: Insurance Solvency Standards and NZ IFRS 16 Leases July 2018 Ref #7548363 2 3 The Reserve Bank welcomes your written feedback on this Consultation Paper by 5 pm, Friday 24 August 2018.

More information

PRESENTATION TO SABOA CONFERENCE

PRESENTATION TO SABOA CONFERENCE PRESENTATION TO SABOA CONFERENCE THE DEVELOPMENT OF PERFORMANCE BASED GROSS NEGOTIATED MODEL CONTRACT DOCUMENT FOR THE ROLL-OUT OF IPTNs 23 FEBRUARY 2012 1 CONTENTS PURPOSE OF THE PRESENTATION CURRENT

More information

ILLUSTRATIVE FINANCIAL STATEMENTS YEAR ENDED 31 DECEMBER 2018

ILLUSTRATIVE FINANCIAL STATEMENTS YEAR ENDED 31 DECEMBER 2018 ILLUSTRATIVE FINANCIAL STATEMENTS YEAR ENDED 31 DECEMBER 2018 NEW ZEALAND EQUIVALENTS TO INTERNATIONAL FINANCIAL REPORTING STANDARDS Tier 1 For-Profit Reporters 2 A Layout (New Zealand) Group Ltd Annual

More information

Debt Raising Transaction Costs Updated Report

Debt Raising Transaction Costs Updated Report M Debt Raising Transaction Costs Updated Report Debt raising transaction costs updated TransGrid January, 2015 Table of Contents 1. Executive Summary... 1 1.1 Total debt-raising transaction costs... 3

More information

Financial Reporting Frameworks and the Auditor s Report

Financial Reporting Frameworks and the Auditor s Report SAAPS 2 (Revised 2018) South African Auditing Practice Statement (SAAPS) 2 (Revised 2018) Financial Reporting Frameworks and the Auditor s Report Independent Regulatory Board for Auditors PO Box 8237,

More information

Market evidence on the cost of equity

Market evidence on the cost of equity Market evidence on the cost of equity Aurizon Network Pty Ltd 22 November 2016 NOTICE Ernst & Young ( EY or we ) was engaged on the instructions of Aurizon Network Pty Ltd ( Aurizon ) to undertake an assessment

More information

NOTES TO THE FINANCIAL STATEMENTS

NOTES TO THE FINANCIAL STATEMENTS NOTES TO THE FINANCIAL STATEMENTS 1. ACCOUNTING POLICIES 1.1 Nature of business Super Group Limited (Registration number 1943/016107/06), the holding Company (the Company) of the Group, is a Company listed

More information

ESKOM RCA Applications 2015/ / /18

ESKOM RCA Applications 2015/ / /18 ESKOM RCA Applications 2015/16 2016/17 2017/18 NERSA 16 April 2018 Nelson Mandela Bay Business Chamber Inputs and Recommendations Overview The Nelson Mandela Bay Business Chamber The Applications What

More information

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019 Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3 Public Hearings- Port Elizabeth Date: 16 January 2019 RCA (Yr 5, MYPD3) Timeline RCAs require 3 decisions: 1 Balance decision 2 Liquidation decision

More information

Safaricom is owned by the government of Kenya (35%), Vodafone Kenya (39.93%), public investors (25%) and Safaricom employees (0.07%).

Safaricom is owned by the government of Kenya (35%), Vodafone Kenya (39.93%), public investors (25%) and Safaricom employees (0.07%). Vodacom Group Limited (Incorporated in the Republic of South Africa) (Registration number 1993/005461/06) Share code: VOD ISIN: ZAE000132577 ADR code: VDMCY ISIN: US92858D2009 ("Vodacom Group" or the company

More information

General instructions and information

General instructions and information DENEB INVESTMENTS LIMITED Registration number: 2013/091290/06 (Incorporated in the Republic of South Africa) JSE share code: DNB ISIN: ZAE000197398 ( Deneb or the Group or the company ) Notice of annual

More information

The Actuarial Society of Hong Kong IFRS Insurance Contract Phase II Development

The Actuarial Society of Hong Kong IFRS Insurance Contract Phase II Development The Actuarial Society of Hong Kong IFRS Insurance Contract Phase II Development Jin Peng, PwC 6 November 2013 Agenda Introduction to 2013 Exposure Draft Key Industry Feedback Worldwide Feedback 2 Introduction

More information

GATWICK AIRPORT LIMITED

GATWICK AIRPORT LIMITED GATWICK AIRPORT LIMITED Investor briefing - CAA Q6 Final Decision 17 January 2014 CAA DECISION AND SUMMARY OF COMMITMENTS CAA published its Final Decision on Economic Regulation from April 2014 CAA concluded

More information