Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48050) ON A LOAN IN THE AMOUNT OF US$100 MILLION TO THE

Size: px
Start display at page:

Download "Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48050) ON A LOAN IN THE AMOUNT OF US$100 MILLION TO THE"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48050) ON A LOAN IN THE AMOUNT OF US$100 MILLION TO THE KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY WITH THE GUARANTEE OF THE REPUBLIC OF KAZAKHSTAN FOR A NORTH-SOUTH ELECTRICITY TRANSMISSION PROJECT Sustainable Development Department Central Asia Country Unit Europe and Central Asia Region May 31, 2012

2 CURRENCY EQUIVALENTS (average rate for 2011) Currency Unit = Kazakh Tenge (KZT) 1.00 KZT = US$ 0.01 US$ 1.00 = KZT FISCAL YEAR January 1 December 31 ABBREVIATIONS AND ACRONYMS AC ARNM CIS CPS DBK EBRD EIRR EMP FIRR FM FMR FY GOK GWh HV IBRD ICB ICR IPO ISR KEGOC kv kwh KZT MW NPV N/S OHL PLC PDO PMD REK Alternating Current Agency for Regulation of Natural Monopolies Commonwealth of Independent States Country Partnership Strategy Development Bank of Kazakhstan European Bank for Reconstruction and Development Economic Internal Rate of Return Environmental Management Plan Financial Internal Rate of Return Financial Management Financial Monitoring Report Fiscal Year Government of Kazakhstan Gigawatt hour (1,000,000 KWh) High Voltage International Bank for Reconstruction and Development International Competitive Bidding Implementation Completion and Results Report Initial Public Offering Implementation Status and Results Report Kazakhstan Electricity Grid Operating Company Kilovolt (1,000 volts) Kilowatt Hour (1,000 watt hours) Kazakhstan Tenge Megawatt (1,000 kw) Net Present Value North-South Overhead Line Power Line Carrier Project Development Objective Project Management Department Regional Electricity Distribution Company

3 SA SAPR SOE SS TA TWh VAT Special Account Substation Automation and Protective Relaying Statement of Expenditure Substation Technical Assistance Terawatt hour (1 billion kwh) Value Added Tax Vice President: Philippe Le Houerou Country Director: Saroj Kumar Jha Sector Manager: Ranjit J. Lamech Project Team Leader: Mirlan Aldayarov ICR Primary Author: Jann Masterson

4 KAZAKHSTAN North-South Electricity Transmission Project CONTENTS A. Basic Information... i B. Key Dates... i C. Ratings Summary... i D. Sector and Theme Codes... ii E. Bank Staff... ii F. Results Framework Analysis... ii G. Ratings of Project Performance in ISRs... iv H. Restructuring (if any)... v I. Disbursement Profile... vi 1. Project Context, Development Objectives and Design Key Factors Affecting Implementation and Outcomes Assessment of Outcomes Assessment of Risk to Development Outcome Assessment of Bank and Borrower Performance Lessons Learned Comments on Issues Raised by Borrower/Implementing Agencies/Partners Annex 1. Project Costs and Financing Annex 2. Outputs by Component Annex 3. Economic and Financial Analysis Annex 4. Bank Lending and Implementation Support/Supervision Processes Annex 5. Beneficiary Survey Results Annex 6. Stakeholder Workshop Report and Results Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders Annex 9. List of Supporting Documents MAP IBRD 33971

5 A. Basic Information Country: Kazakhstan Project Name: North-South Electricity Transmission Project Project ID: P L/C/TF Number(s): IBRD ICR Date: 05/31/2012 ICR Type: Core ICR Lending Instrument: SIL Borrower: Original Total Commitment: Revised Amount: USD 98.08M Environmental Category: B Implementing Agencies: KEGOC Cofinanciers and Other External Partners: Development Bank of Kazakhstan B. Key Dates KAZAKHSTAN ELECTRICITY GRID OPERATING CO USD M Disbursed Amount: USD 98.08M Process Date Process Original Date Revised / Actual Date(s) Concept Review: 06/09/2005 Effectiveness: 12/22/2005 Appraisal: 07/25/2005 Restructuring(s): 06/20/ /22/ /29/2009 Approval: 10/27/2005 Mid-term Review: 10/30/ /30/2007 Closing: 12/31/ /30/2011 C. Ratings Summary C.1 Performance Rating by ICR Outcomes: Risk to Development Outcome: Bank Performance: Borrower Performance: Satisfactory Moderate Satisfactory Satisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Bank Ratings Borrower Ratings Quality at Entry: Satisfactory Government: Satisfactory Quality of Supervision: Satisfactory Implementing Agency/Agencies: Satisfactory i

6 Overall Bank Performance: Satisfactory Overall Borrower Performance: Satisfactory C.3 Quality at Entry and Implementation Performance Indicators Implementation QAG Assessments Indicators Performance (if any) Potential Problem Project No at any time (Yes/No): Problem Project at any time (Yes/No): DO rating before Closing/Inactive status: No Satisfactory Quality at Entry (QEA): Quality of Supervision (QSA): None None Rating D. Sector and Theme Codes Original Actual Sector Code (as % of total Bank financing) Power Theme Code (as % of total Bank financing) Infrastructure services for private sector development Other financial and private sector development Regional integration Regulation and competition policy E. Bank Staff Positions At ICR At Approval Vice President: Philippe H. Le Houerou Shigeo Katsu Country Director: Saroj Kumar Jha Dennis N. de Tray Sector Manager: Ranjit J. Lamech Sumter Lee Travers Project Team Leader: Mirlan Aldayarov Istvan Dobozi ICR Team Leader: ICR Primary Author: Mirlan Aldayarov Peggy Janice Masterson F. Results Framework Analysis Project Development Objectives (from Project Appraisal Document) The primary development objective of the overall North-South Electricity Transmission Project is to ensure that business enterprises and households in southern Kazakhstan have access to adequate, reliable and cost effective supply of electricity. The Project also ii

7 supports regional integration with respect to optimizing the use of energy resources through international electricity trade. Revised Project Development Objectives (as approved by original approving authority) (a) PDO Indicator(s) Indicator Indicator 1 : Value quantitative or Qualitative) Baseline Value Original Target Values (from approval documents) Formally Revised Target Values Actual Value Achieved at Completion or Target Years PDO: Increased volume of electricity transfer from generating plants in northern Kazakhstan to markets in southern Kazakhstan through N/S interconnector. 7.5 TWh electricity transfer from 3.9 TWh electricity 7.5 TWh northern transfer from northern electricity transfer Kazakhstan to Kazakhstan to southern through the second southern Kazakhstan through the North-South Kazakhstan through second North-South interconnector. the second Northinterconnector. South interconnector Date achieved 12/31/ /31/ /30/2011 Comments (incl. % Target 100% achieved, beginning in achievement) (b) Intermediate Outcome Indicator(s) Indicator Indicator 1 : Baseline Value Original Target Values (from approval documents) Formally Revised Target Values Maximum transmission capacity to southern Kazakhstan through N/S interconnector. Actual Value Achieved at Completion or Target Years Value (quantitative or Qualitative) 650 MW 1350 MW 1350 MW Date achieved 12/31/ /31/ /30/2011 Comments (incl. % Target 100% achieved, beginning in achievement) Indicator 2 : Reduction in the frequency of major outages on N/S interconnector. Value (quantitative or Qualitative) iii

8 Date achieved 12/31/ /31/ /30/2011 Comments (incl. % Target exceeded by 33%. achievement) Indicator 3 : Reduction in transmission losses on the N/S interconnector Value (quantitative or Qualitative) 8.8% 6.5% 7.6% Date achieved 12/31/ /31/ /30/2011 Comments Loss levels have been significantly reduced ard are expected to be reduced (incl. % further. achievement) Indicator 4 : Establishment of Balancing Market Value (quantitative or Qualitative) No Balancing Market Balancing Market established Balancing Market fully designed and operating in trial mode since January 1, Date achieved 12/31/ /31/ /30/2011 Comments (incl. % achievement) The current load following generation capacity is insufficient to launch the Balancing Market at this time. When additional generation comes into service later in 2012, it will be launched. 70% achievement. Indicator 5 : Introduction of zonal tariffs. Value (quantitative or Qualitative) Distortionary tariff structure that included a geographic distancebased component between sellers and buyers of electricity. Introduction of zonal tariffs by 2006 Zonal tariffs were adopted in 2006 and replaced in 2010 with a new, efficient tariff methodology based on a uniform national tariff. Date achieved 12/31/ /31/ /30/2011 Comments Target 100% achieved. The new uniform tariff is efficient, transparent and (incl. % covers justifiable costs and a regulated rate of return. achievement) G. Ratings of Project Performance in ISRs No. Date ISR Archived DO IP Actual Disbursements (USD millions) 1 06/09/2006 Satisfactory Satisfactory /01/2006 Satisfactory Satisfactory /28/2007 Satisfactory Satisfactory /08/2007 Satisfactory Satisfactory /24/2008 Satisfactory Satisfactory /05/2009 Satisfactory Satisfactory iv

9 7 06/22/2009 Satisfactory Satisfactory /21/2009 Satisfactory Highly Satisfactory /21/2010 Satisfactory Highly Satisfactory /04/2010 Satisfactory Highly Satisfactory /27/2011 Satisfactory Satisfactory H. Restructuring (if any) Restructuring Date(s) Board Approved PDO Change ISR Ratings at Restructuring DO IP Amount Disbursed at Restructuring in USD millions 06/20/2008 S S /22/2009 S S /29/2009 S S Reason for Restructuring & Key Changes Made KEGOC, given its substantial capital investment program, requested the Bank to amend the Loan Agreement to reduce its current ratio covenant from 1.4 to 1. To transfer the "Modernization of Substations Component" from the Electricity Transmission Rehabilitation Project to the N/S Electricity Transmission Project, using the savings from the N/S Project to cover a financing gap under the Electricity Transmission Rehabilitation Project. An additional component (US$16.4 million) was added to the N/S Project. Closing date extension was needed for the full completion of the "Modernization of Substations" component. The closing date was extended from December 31, 2009 to November 30, v

10 I. Disbursement Profile vi

11 1. Project Context, Development Objectives and Design 1.1 Context at Appraisal At appraisal in 2005, Kazakhstan s economic performance had been impressive, and its reform record was among the best in the former Soviet Union. Economic growth had been buoyant at about 11 percent on average since 2000, with income per capita expected to exceed US$2,000 in Growth had been driven mainly by increased oil production and higher oil prices. Electricity consumption grew rapidly at 6 percent per year. There were about 70 power generation plants with a total installed capacity of 18,485 MW, much of it coal-fired, privatized and technically outdated. The high voltage transmission system had three voltage levels: 1,150 kv, 500 kv and 220 kv. The state-owned Kazakhstan Electricity Grid Operating Company (KEGOC) operated all transmission assets at 1,150 kv and 500 kv levels. KEGOC was responsible for dispatch control and operated international connections, principally with Russia, Kyrgyz Republic and Uzbekistan. KEGOC s transmission system consisted of three regional power grids: (i) the Northern grid connected to the Russian power system; (ii) the Southern grid connected to the Central Asian power system and the Northern grid with a single circuit 500 kv transmission line; and (iii) the Western grid, comprising of two subsystems, which were isolated from the other systems. There were 21 Regional Distribution Companies (REKs), most of them privatized and technically outdated. In the area of power sector reforms, Kazakhstan ranked among the most advanced countries in the Former Soviet Union. The Government of Kazakhstan (GOK) began reforms in 1996, with a view to introducing massive private participation and establishing a competitive power market. The wholesale electricity market was fully liberalized and operated mainly on the basis of bilateral contracts between generators and REKs for direct sale of power. Project Rationale. Vigorous economic growth and increasing diversification of the economic base had led to a sharp upswing in electricity demand in Kazakhstan. While Kazakhstan, overall, had sufficient generation capacity to meet domestic power demand, four-fifths of power generation came from the northern part of the country, predominantly from coal-based power plants located in the Ekibastuz region and, to a lesser extent, from hydroelectric plants located primarily along the Irtysh River. Generation facilities in the south were limited to small hydro, combined heat and power plants, and a high cost gas/oil-fired power plant at Zhambyl which was operated to meet winter peak demand. The existing KEGOC-operated North-South (N/S) electricity transmission lines of 500 kv and 220 kv, via which low-cost electricity was transmitted from the northern power stations to the south, had a limited transmission capacity of 650 MW, which was grossly insufficient to meet demand in the booming southern part of the country, especially in the industrial belt between Almaty and Shymkent. The power deficit in the south was about 1

12 900 MW (half of regional consumption). The deficit was met largely by transmitting power from the north and, in part, by importing electricity. Historically, the southern regions of Kazakhstan imported power from the Central Asia Power System (CAPS), but with the break-up of the Soviet Union, the amount of imported power had reduced. The limited available imports could not fully meet regional electricity demand in the winter period of maximum electric loads, which necessitated restrictions on consumption (load shedding) with an adverse impact on regional economic development. At the same time, because of the limited N/S transmission capacity, surplus electricity from the northern power grid was exported to Russia. Furthermore, reliability of the existing 500 kv interconnector was low because of its single circuit design. Disconnection or outage of even one of the five 500 kv line sections could stop power transmission to southern Kazakhstan and the interconnected parallel operation of the Kazakh power system with CAPS and Russia. Irregular power flows caused frequent activation of emergency control systems on the interconnector, thus causing load rejection, disconnection and voltage control switching of 500 kv reactors. Due to the increasing overload of the interconnector, the number of major emergency breakdowns increased sharply. The resulting economic damage and dislocation was considerable. Fully appreciating the approaching needs, the GOK had initiated a number of studies. Indepth feasibility studies established that the least-cost method of meeting current and prospective electricity demand in the south was to expand and strengthen the capacity of the existing N/S transmission line. A detailed feasibility study of strengthening the N/S n line resulted in a three-phase approach: Phase I (YukGRES-Shu, 250 km), Phase II (Ekibastuz-Agadyr, 475 km), and Phase III (Agadyr-YukGRES, 390 km). KEGOC requested the Bank s financing for Phase II of the entire N/S Project. In addition to providing financing, the Bank s involvement would facilitate the continuation of the sector reform dialogue with respect to the completion of the transmission system reforms which had been initiated under the earlier Bank-financed Electricity Transmission Rehabilitation Project (Ln KZ). Moreover, the financial savings to KEGOC associated with Bank participation were substantial and would allow more moderate increases in transmission tariffs than would otherwise be required, while considerably easing the cash flow pressure on KEGOC over the near and medium terms. The Bank also had a strong interest in the development of regional electricity markets and, through its involvement in the Project, could ensure that the regional electricity integration aspects were properly addressed (e.g., by providing non-discriminatory Third Party Access to the N/S line for export and international transit related transmission services). Completion of the new N/S line would also help to ensure the sustainability and full realization of the benefits of previous Bank initiatives in the power sector (including support for transmission system rehabilitation, Grid Code, transmission tariff rationalization and development of the electricity spot market). Higher Level Objectives to which the Project would contribute. Kazakhstan s development focus was on achieving international standards for public services and enterprises and increasing the competitiveness of its tradable non-oil sectors. Reliable and cost effective electricity was fundamental to both social and economic development. Strengthening the transmission grid would ensure wide-spread access to low-cost generation, while development of the physical and institutional framework for electricity 2

13 trade would facilitate the longer-term development of competitive national and regional electricity markets. 1.2 Original Project Development Objectives (PDO) and Key Indicators The primary development objective of the overall N/S project, as captured in the PAD, was to ensure that business enterprises and households in southern Kazakhstan have access to adequate, reliable and cost effective supply of electricity. The project also supported regional integration with respect to optimizing the use of energy resources through international electricity trade. 1 For the purposes of the ICR, the PDO statement from the PAD was used as this is the one that was used throughout project implementation. The key indicators were: PDO Indicator Increased volume of electricity transfer from generating plants in northern Kazakhstan to markets in southern Kazakhstan through the N/S interconnector Intermediate Outcome Indicators Maximum transmission capacity to southern Kazakhstan through the N/S interconnector; Reduction in the frequency of major outages on the N/S interconnector; Reduction in transmission losses on the N/S interconnector; Establishment of a Balancing Market; Introduction of zonal tariffs. 1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and reasons/justification The Project Development Objectives and the Key Indicators were not revised. 1.4 Main Beneficiaries, The main beneficiaries of the Project were business enterprises and households in southern Kazakhstan, whose well-being was expected to be enhanced by (i) providing access to adequate, reliable and cost effective supply of electricity; and (ii) continued economic growth in the region through removing a binding energy supply constraint; and (iii) increasing the region s competitiveness with related economic benefits in terms of employment and income. Expanding the N/S transmission line would offer numerous benefits in terms of system reliability, increased export/transit capacity and the ability to make more effective use of low-cost generating plants in northern Kazakhstan. The new line would also improve the reliability of parallel operation of the power systems of Russia, Kazakhstan and Central Asia, thus improving the quality of power supply across 1 The development objectives, as stated in the Loan Agreement, were: (i) to ensure that business enterprises and households in southern Kazakhstan have access to reliable, cost effective and high quality supply of electricity; and (ii) to support regional integration with respect to optimizing the use of energy resources through international electricity trade. 3

14 the region. KEGOC would also benefit by improving its financial standing due to increased transmission volumes. 1.5 Original Components The Bank-supported project, which financed Phase II of the three-phase overall N/S Electricity Transmission Line Project, 2 involved the construction of 475 km of overhead lines (OHL) between Ekibastuz and Agadyr SSs and modernization of 500 kv outdoor switchgear at both SSs. The total estimated cost of the Phase II Project was US$160.8 million. The Project consisted of the following components: Component A. Construction of 500 kv Overhead Single Circuit Transmission Line (estimated cost: US$113.8 million, of which the Bank would finance US$99.5 million). Construction of a new 475 km 500 kv single circuit OHL from the air-insulated SS Ekibastuz (1,150/500 kv) to the air insulated SS Agadyr (500 kv), including a Fiber Optic Communications Line. Component B. Extension/Modernization of 1,150/500 kv Ekibastuz Air- Insulated SS (estimated cost: US$13.2 million financed by DBK and KEGOC). This component would involve expanding the existing 1,150/500 kv SS at Ekibastuz by three bays and installing shunt reactors to accommodate the new 500 kv link with Agadyr SS. The work would include installation of SF6 circuit breakers, disconnect switches, current transformers, voltage transformers, three single-phase shunt reactors as well as SS automation and protective relaying and a Power Line Carrier (PLC). Installation of shunt reactors was expected to improve the stability of the power grid and regulate voltage conditions of the transmission system. Component C. Extension/Modernization of 500 kv Agadyr Air-Insulated SS (estimated cost: US$32.8 million financed by DBK and KEGOC. This component would involve expanding the existing 500 kv SS at Agadyr by six bays to accommodate the new 500 kv link with the Ekibastuz and YukGRES SSs. Three new shunt reactors would be installed with two shunt control reactors connected to the busbar and the third shunt reactor connected to the Agadyr- YukGRES line. The work would include installation of SF6 circuit breakers, disconnect switches, current and voltage transformers shunt reactors, and SS automation and protective relaying as well as PLC. Installation of shunt reactors was intended to improve the stability of the power grid and regulate voltage conditions of the transmission system. Component D. Technical Assistance (US$0.9 million). This component includes consulting services for (i) procurement and project management for the construction of the 500 kv OHL between Ekibastuz and Agadyr (estimated cost US$0.5 million financed by the Bank) and (ii) further reforms of the transmission sector (estimated at US$0.4 million), including transmission pricing (zonal tariffs) and establishment of a real time balancing market. 2 The three-phase overall N/S project included the construction of 1,115 km of overhead 500 kv, single circuit alternate current (AC) line and upgrades of four high voltage air-insulated substations (1150/500 kv Ekibastuz, 500 kv Agadyr, 500 kv YukGRES and 500 kv Shu). The project was to be carried out in three phases: Phase I (YukGRES-Shu, 250 km); Phase II (Ekibastuz-Agadyr, 475 km) and Phase III (Agadyr- YukGRES, 390 km). 4

15 1.6 Revised Components In January 2009, the N/S Transmission Project was restructured to add a fifth component - Component E: Modernization of Transmission SSs - following a request from the Borrower. Under the restructuring, an unfinished portion of the earlier Electricity Transmission Rehabilitation Project (Loan No KZ) was transferred to the N/S Transmission Project for full completion. This allowed full and satisfactory completion of the Electricity Transmission Rehabilitation Project without compromising in any way the successful implementation of the N/S Project. The two Bank-financed transmission projects were closely connected, with the same intended outcome of improved reliability and quality of electricity supply to businesses and households, and successful completion of the Rehabilitation Project was a key to the satisfactory outcomes of both projects. The main modifications to the N/S Project consisted of: (i) the inclusion of an additional IBRD loan-financed component of US$16.4 million to modernize 27 high voltage SSs which were originally included in the Rehabilitation Project, which experienced a financing gap due to the large depreciation of the US$ against the Euro; and (ii) reduction of the IBRD loan-financed portion of the existing Component A Construction of Transmission Line Agadyr-Ekibastuz by the same amount. KEGOC would finance from its own funds the VAT, which had originally been intended to be financed from the IBRD Loan. 1.7 Other significant changes EBRD co-financing (originally planned at US$13.14 million equivalent). In 2007, the winning bid for the N/S Transmission Line came in at about US$5.7 million lower than the original cost estimate; therefore, EBRD co-financing for the second phase was no longer needed and was applied to a subsequent transmission project of the Borrower. In June 2008, following a request from KEGOC, the Bank amended the Loan Agreement to reduce the current ratio (ratio of current assets to current liabilities) covenant in the Loan Agreement from 1.4 to 1. Reallocation of savings. In January 2009, the Loan and Guarantee Agreements were amended to add the new component E. The cost savings of US$5.7 million from the transmission line contract were reallocated to the new component E, and KEGOC used its own funds to finance the VAT component (US$10.7 million) that had originally been intended to be financed from the Bank Loan. Closing Date extension. In July 2009, after it became apparent that the Component E Modernization of Transmission SSs, which had been transferred from the Electricity Transmission Rehabilitation Project, could not be completed by the original Closing Date of December 31, 2009, the Closing Date was extended to November 30, 2011 so that the remaining 27 SSs could be completed and commissioned. Final cancellation. On September 15, 2011, the remaining undisbursed loan balance of US$1,918, (about 2% of the total loan amount) resulting from savings achieved under the IBRD loan was cancelled. 2. Key Factors Affecting Implementation and Outcomes 2.1 Project Preparation, Design and Quality at Entry 5

16 Soundness of the Background Analysis. Lessons learned from prior work in the region and the sub-sector were taken into account during design and preparation of the Project. The Bank team coordinated among key government agencies on both the project processing schedule, project implementation plan and on the ultimate scope and design of the project; the Bank team included from the beginning of project identification and preparation the competent and efficient national project management staff of KEGOC; and the Bank team closely coordinated with co-financiers from an early stage to ensure non-duplication of efforts, efficient procurement and implementation of components as well as compatibility of lending terms and conditions. Prior experience in the implementation of transmission projects had revealed areas that required special attention, including the need for thorough technical analyses so that facilities were designed and routed to minimize environmental and social impact and the importance of commitment by provincial governments and public participation to ensure successful environmental management. These were addressed satisfactorily in preparation of the Project. Previous projects had also shown that the implementation of physical components of the project could be expedited by paying close attention to the following factors: prompt government clearance, effective design management to ensure a timely delivery of drawings, and this was the case in this Project, which was completed under budget and ahead of schedule (except for the new component added towards the end of Project implementation). Assessment of the Project Design. The objectives, components and implementation arrangements were realistic. The design involved standard technology for high-voltage transmission line and SS construction. KEGOC, the Borrower and implementing agency, was a competent grid operating company and had already gained experience in implementing the earlier Bank-financed Electricity Transmission Rehabilitation Project. Both its procurement and financial management capacity were assessed during preparation and found to be satisfactory. In the original financing plan there were two international co-financiers, the Bank and the EBRD, plus the Borrower and DBK. Each co-financier had clearly assigned roles in financing the three phases of the transmission system development. There was a clear recognition of the importance of the social and environmental safeguards in the detailed route selection and environmental impact assessment. Two project alternatives were considered but rejected: increased generation capacity in southern Kazakhstan, which was rejected after a least cost assessment during the prefeasibility study determined that the N/S transmission line was the best economic alternative by a considerable margin; and increased imports into southern Kazakhstan, an alternative which was rejected as hydropower plants in the Kyrgyz Republic and Tajikistan also supply water for irrigation, making surplus electricity from these countries available mainly on a seasonal basis. Adequacy of Government Commitment and Participatory Process. The N/S Transmission Project as a nationally top priority operation, enjoyed strong support from the GOK, as evidenced by the provision of State Guarantee for KEGOC which, at the time, was given only to few high-priority operations. KEGOC obtained the approval of the State Expertise and the support of the relevant ministries in regard to the feasibility study, environmental impact assessment and project financing plan early on during project preparation. The GOK demonstrated its commitment during project preparation by quickly facilitating the approval of the feasibility study for the N/S electricity 6

17 transmission line, authorizing KEGOC to arrange loan financing and supporting KEGOC s request to ARNM (sector regulator) to adjust the transmission tariffs to ensure that KEGOC would be able to finance the project and repay the debts. The company s Development Plan also envisioned further increases in the transmission tariff and in the dispatch tariff. A satisfactory public consultation on the Environmental Management Plan (EMP) for the Phase II Project was conducted with affected stakeholders and NGOs on June 28, 2005 in Astana, and was verified by the Bank s environmental specialist. Assessment of Risks. The overall risk rating was assessed as Moderate, which indeed proved to be the case. Only two of the seven risks were originally rated as Substantial: (i) inadequate transmission tariffs and project implementation delays due to lack of local financing: and (ii) weak project management and overloaded implementation capacity of the Borrower. Both risks were mitigated through the following measures: the provisions of the Guarantee Agreement ensured that tariffs would be maintained at levels sufficient to cover KEGOC s longer term cash flow requirements; The Project Management Department (PMD) of KEGOC was strengthened with an international consultant to assist in project management. The turnkey procurement arrangement prevented excessive project implementation delays. 2.2 Implementation The overall three-phase transmission line project was implemented in cooperation with other donors and partners, with EBRD providing financing for phases I and III of the overall N/S transmission line, DBK and the Bank providing financing for phase II, and KEGOC providing financing for all three phases. All three phases were completed by 2009 as scheduled. Project implementation proceeded mostly on schedule, and the original components (A- D) of the project were completed by the original closing date of December 31, Under Component E, transferred from the Electricity Transmission Rehabilitation Project, 19 high voltage transmission SSs were rehabilitated and commissioned and 8 high voltage SSs were commissioned by November 30, The project was never at risk and was continuously rated Satisfactory or Highly Satisfactory throughout project implementation. In July 2010, KEGOC informed the Bank about ARNM s decision to phase out the zonal tariffs introduced in As a result of the large-scale network expansion investments (including the second N/S transmission line), the major transmission line bottlenecks (congestion) had been eliminated and the transmission situation had vastly improved, allowing Kazakhstan to return to a nationally uniform tariff methodology based on a single tariff. (Earlier, the large zonal differences in national network access provided the justification for zonal tariffs, which reflected energy deficits/surpluses among the major power regions.) Importantly, the underlying principle of the new tariff methodology is fully consistent with the relevant provision of the Guarantee Agreement by ensuring that the transmission tariffs are (i) not dependent on geographical distances between generators and consumers of electricity; and (ii) maintained at levels sufficient to fully cover KEGOC s prudently incurred operating and capital expenditures. 7

18 The Project has been a success in achieving its primary objective. The annual volume of electricity transferred from generation plants in the north to consumers in the south has increased from 3.9 TWh to 7.5 TWh (92 percent increase). The reliability and quality of transmission has significantly improved as evidenced by the decrease in frequency and duration of forced outages (reduction from 19 major outages in 2005 to 6 in 2011). The four key reform covenants of the Guarantee Agreement have been substantially achieved (see Section 3.2). The following key factors contributed to the successful implementation of the Project: Solid project design, incorporating lessons learned from best practice regional and international experience of similar Bank-supported projects; Continuous GOK commitment and compliance with the reform covenants of the Guarantee Agreement; Efficient and committed counterpart, with KEGOC being an efficient, and commercially oriented Grid Operator that had acquired experience in implementing a Bank-financed project through the previous Electricity Transmission Rehabilitation Project; The use of a turn-key contract for the supply and installation of Ekibastuz-Agadyr transmission line reduced the administrative burden on KEGOC and prevented implementation delays. 2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization The outcome and intermediate indicators developed for the Project were adequately designed and provided a good indication of progress towards achieving the PDO. KEGOC s PMD regularly collected the appropriate data on the outcome and intermediate indicators and ensured information quality, using data from KEGOC s annual operating statistics and Dispatch Center reports. The PMD provided Financial Monitoring Reports (FMRs) within 45 days of the end of each quarter. KEGOC prepared comprehensive, accurate and transparent Annual Reports, which were used for management decision making, and enhanced KEGOC s reputation as a reliable and financially stable partner, enabling the company to raise substantial financial resources from international financial institutions. Because the M&E indicators are routinely collected by KEGOC, it is likely that they will continue to be collected in the future. 2.4 Safeguard and Fiduciary Compliance Safeguard Policy Issues. KEGOC complied fully with the Bank s safeguard policies and Kazakhstan s environmental protection regulations. The Project was classified as Category B, indicating limited impacts that could be readily managed through sound engineering design and construction. The only safeguard policy identified during preparation was Environmental Assessment. KEGOC prepared an EMP in accordance with Bank requirements. A satisfactory public consultation on the EMP for the Project was conducted with affected stakeholders and NGOs on June 28, 2005 in Astana. The EMP was followed by KEGOC throughout project implementation, and the Bank s team regularly supervised EMP implementation and confirmed that KEGOC was implementing it satisfactorily. 8

19 Fiduciary Compliance. Financial Management. KEGOC complied with the Bank s fiduciary policies and financial management (FM) requirements and complied with the financial covenants of the Loan Agreement. KEGOC consistently received an unqualified audit opinion on its financial statements including the project accounts for the year ending December 31, Procurement. Procurement under the Project was implemented in accordance with the Bank s Procurement and Consultant Guidelines dated May 2004 and in accordance with the provisions stipulated in the Loan Agreement. KEGOC ran a tight procurement process and a well-administered tender for the main turnkey contract, which came in at about US$5.7 million below the original cost estimate. 2.5 Post-completion Operation/Next Phase The second N/S Transmission Line and the SSs modernized are now completely operational and have been fully integrated into KEGOC s national grid system. A legal basis has been established for the tariff-setting methodology and the Regulator continues to set transmission tariffs that fully reflect KEGOC s operating costs and investment needs. In addition, the state holding company (Samruk-Kazyna, the sole shareholder of KEGOC) pledged additional equity injections to cover any cash-flow shortfalls that might arise as a result of the ongoing investment program. As a result, there appears to be adequate provision to ensure the financial sustainability of the company. KEGOC has formally requested the Bank s support for the proposed Third North-South Electricity Transmission Project, and preparations for a feasibility study are underway. The proposed project is included in the FY12-FY17 Country Partnership Strategy. Follow-up investments to strengthen the power network and improve the reliability of the electricity supply in southern Kazakhstan, such as the Bank-financed Moinak Electricity Transmission Project and the Alma Electricity Transmission Project are currently under implementation and provide the basis for continuing to monitor KEGOC s financial performance as well as sustain the agreed program of sector reforms. 3. Assessment of Outcomes 3.1 Relevance of Objectives, Design and Implementation The project objectives and design remain highly relevant in the context of Kazakhstan s development priorities. Kazakhstan has maintained an ongoing commitment to developing an infrastructure that meets international standards and is capable of supporting economic growth and social development. Establishment of an efficient and reliable power transmission network and the resultant improvements in the cost and reliability of power supply have been key in facilitating economic growth that has occurred during project implementation. Although the GOK has reduced its sovereignguaranteed borrowings in recent years, it continues to provide sovereign guarantees for KEGOC s program of transmission system expansion and upgrade, thereby 9

20 demonstrating the strategic importance that it assigns to these initiatives. This project was also part of the development strategy of Kazakhstan s national power grid for The strategy includes a list of seven projects aimed at reconstruction, reinforcement and modernization of the national power grid, which links not only regions within the country, but also aims at strengthening the energy interconnections with the neighboring Central Asian countries. The project remains consistent with the objectives of the IBRD and IFC CPS for FY12- FY17, which is designed to help the GOK implement its development priorities. The CPS was discussed by the Bank s Board of Executive Directors on May 1, A massive extension of the high voltage transmission system to integrate the currently poorly connected regions into the national network remains a top GOK priority. As stated in the FY05-11 CPS Completion Report, relieving the infrastructure constraints to growth was a key component of the GOK s competitiveness agenda, and the Bank has partially financed strategic investments in the transmission sector through four consecutive projects 3 that have made KEGOC one of the most technologically advanced grid companies among the CIS. The N/S Project was an investment project in a strategic, high-impact area of engagement of improving competitiveness and employment generation; it also responds to the country development goal to develop infrastructure connectivity to reduce economic distance by improving energy transmission to poor areas. The project also played a role in assisting the electricity grid operating company to enhance corporate governance and financial standards to international best practice and supporting regional electricity trade. 3.2 Achievement of Project Development Objectives All three phases of the overall North-South Transmission Line have been completed satisfactorily. With respect to the achievement of the PDO, the Project, and the whole line, has been a success. The annual volume of electricity transferred from generation plants in the north to consumers in the south has increased from 3.9 TWh to 7.5 TWh (92 percent increase). The reliability and quality of supply has significantly improved as evidenced by the decrease in frequency and duration of forced outages (reduction from nineteen major outages in 2005 to six in 2011). There are no longer quality of service issues (fluctuations of voltage and frequency) at the high voltage level. Transmission losses have been reduced from 8.5 percent in 2006 to 7.6 percent in Evolution of transmission losses Indicator * Transmission losses 8.5% 8.5% 9.2% 8.1% 7.8% 7.6% * - Year of commencement of operation of the line 3 Electricity Transmission Rehabilitation Project (FY99-09), North-South Electricity Transmission Project (FY06-11), Moinak Electricity Transmission Project (FY10-12) and Alma Electricity Transmission Project (FY11-15). 10

21 Customer losses due to outages on the N/S line have declined, and capacity has increased by about 700 MW. The Project provided substantial additional regional electricity transfer capacity to support electricity trade among Russia, Kazakhstan and other Central Asian countries. The Project allowed accessing the low-cost generation and was the leastcost method of meeting medium-term electricity demand in the south. The four key reform covenants of Section 3.01 of the Guarantee Agreement have been substantially achieved: maintain KEGOC s tariffs at levels sufficient to fully cover the company s cash flow requirements as well as a regulated rate of return on net fixed assets. An efficient tariff methodology has been established which is transparent and covers justifiable costs and a regulated rate of return. approve the implementation of a transmission tariff-setting methodology based on the concept of zonal tariffs. Zonal tariffs reflecting the existing power deficits/surpluses among the three regional power zones in Kazakhstan and the inter-zonal bottlenecks (congestion) in the transmission capacity were introduced in In 2010, ARNM decided to phase out the zonal tariffs introduced in 2006 because the major transmission line bottlenecks had been eliminated as a result of the large-scale network expansion investments, including the N/S line. As a result of these major network expansion investments, the transmission situation has vastly improved, allowing Kazakhstan to return to a nationally uniform tariff methodology based on a single tariff. cause KEGOC to ensure the implementation of non-discriminatory third party access to the N/S line, including access to export and international transit-related services, based on published tariffs, applicable to all customers and to be applied fairly and without discrimination between customers. Non-discriminatory third party access to the transmission grid is operational. The new tariff methodology is also consistent with the Guarantee Agreement by not including in the tariff structure a geographic distance-based component between sellers and buyers of electricity, which was highly distortionary. establish a real-time electricity balancing market to be operated by KEGOC based on transparent market rules. The Balancing Market has been fully designed and is operating in trial mode, producing invoices for electricity purchased on the Balancing Market and reconciliation statements of sold and purchased balancing electricity. The Balancing Market still operates in trial mode, primarily because the GOK considers the availability of flexible load following generation to be inadequate to launch the Balancing Market at this time. Once additional generation capacity is added in the near future, including the Moinak Hydropower Plant now close to full completion, the Balancing Market is expected to be launched live. 3.3 Efficiency Because the Bank-financed investment represented one segment of a three-phase overall transmission line project, the economic and financial analysis in the PAD examined the viability of these investments in the context of the viability of the N/S transmission line as a whole. This same approach has been adopted for the ex-post evaluation. At present, the outlook in terms of economic and financial efficiency is fully satisfactory. The second 11

22 N/S transmission line and SSs were completed on schedule, and while the economic costs were slightly higher than projected at the time of Board presentation, the financial costs were lower than projected owing to savings in taxes and efficiently administered procurement by KEGOC. This was achieved despite a 23 percent depreciation in the value of the KZT against the Euro and a 14 percent depreciation against the US$. Incremental transmission and dispatch on the new line has exceeded forecasts, and projections are that it will continue to do so as demand in the south continues to exceed local supply. In addition, transmission losses have dropped from over 8.8 percent to 7.6 percent and are likely to fall going forward. Tariffs have declined slightly in real terms since the start of the project. However, at current levels, they are sufficient to provide satisfactory financial returns. The expected financial and economic returns of the project are described in Annex 3. Based on current projections, the expected FIRR of the project is 7.2 percent, and the financial NPV (at KEGOC s WACC of 5.8 percent) is US$51 million. The expected EIRR of the project is 15.5%, and the economic NPV at a 10% discount rate is US$111 million. 3.4 Justification of Overall Outcome Rating Rating: Satisfactory The Project is considered to have been Satisfactory in terms of overall outcome. As discussed above, the PDO remains highly relevant to the priorities of both the GOK and the Bank/IFC CPS for FY12-FY17. The PDO outcome indicator target has been achieved, and most of the intermediate outcome indicator targets have also been achieved. The economic and financial benefits of the Project have been substantial, and the original Project was completed earlier than planned and with substantial cost savings. The only issue still to be addressed is that the Balancing Market has been operating since 2008 on a trial basis only. The Balancing Market has been fully designed and KEGOC is waiting for the GOK go-ahead to go live. It is expected that after sufficient new load following generation (including the Moinak HPP) comes on stream in 2012, GOK will give the green light to make the Balancing Market fully operational. 3.5 Overarching Themes, Other Outcomes and Impacts (a) Poverty Impacts, Gender Aspects, and Social Development The project has enhanced the well-being of the population in southern Kazakhstan by (i) providing increased, reliable and low-cost supply of electricity from the north; (ii) removing a binding energy supply constraint to continued economic growth in the region; and (iii) increasing the region s competitiveness with related benefits in terms of employment and income. Although not solely attributable to the project, there have been significant reductions in poverty and unemployment in southern Kazakhstan. Poverty dropped, on average, by 61 percent, and extreme poverty dropped by 76 percent in the four regions of southern Kazakhstan. The unemployment rate in southern Kazakhstan was reduced on average by 25 percent. (See tables on poverty and unemployment in Annex 3.) (b) Institutional Change/Strengthening 12

23 The Bank s engagement with KEGOC and the GOK in the energy sector over many years beginning with the Electricity Transmission Rehabilitation Project in 1999 has significantly contributed to the operational and institutional capacity of KEGOC and the energy sector as a whole. Kazakhstan has become a model for other CIS countries, having created an efficient, profitable and commercially oriented Grid Operator, a reasonably effective sector Regulator and a competitive power market within the framework of an overall sound institutional and legal framework. Generally speaking, the country and its institutions have established a solid foundation under the N/S Transmission Project for expansion and development to meet the electricity needs of a rapidly growing economy. Under the N/S Project, KEGOC s PMD gained additional experience with Bank procedures for financial management, procurement and disbursement and introduced a new computerized accounting system to automate FMR reporting. KEGOC staff received extensive advanced training from the vendors and suppliers in installation, operation and maintenance of the sophisticated systems and equipment provided under the project. (c) Other Unintended Outcomes and Impacts (positive or negative) After its successful physical completion, the N/S Electricity Transmission Project, through the restructuring in 2009 that transferred the unfinished automation of SS component from the Electricity Transmission Rehabilitation Project, helped to satisfactorily complete the project, after it closed on June 15, The two transmission projects were closely linked and served the same key objective of improving the reliability and quality of electricity supply to businesses and households. Because the SSs are connected to the integrated national grid, the N/S line could not operate efficiently and reliably without modernizing all the SSs. 3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops (Not applicable) 4. Assessment of Risk to Development Outcome Rating: Moderate The overall risk to development outcome is rated Moderate for the reasons given below: Technical risks: Negligible to Low. The technologies introduced under the project are well established, tested, and technically relatively simple. KEGOC s staff is fully trained. The companies suppliers of the equipment are present in the Kazakhstan market. Financial Risks: Moderate. The sector regulator has consistently granted tariff increases to cover KEGOC s full operating costs and the parent company, Samruk-Kazyna is committed to provide additional equity injections to cover any potential liquidity shortfalls associated with KEGOC s ambitious investment program. The company s overall financial position is solid, and there was no problem with KEGOC s own financing of the project. However, it cannot be totally excluded that KEGOC s future tariff request increases might not be approved. Environmental Risks: Negligible to Low. The EA rating of category B reflected appropriately the initial assessment that the environmental risks were of limited and manageable scope. KEGOC fully complied with the requirements. 13

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-79650) ON A LOAN KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-79650) ON A LOAN KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY Public Disclosure Authorized Document of The World Bank Report No: ICR00003396 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-79650) ON A LOAN IN THE AMOUNT OF US$78 MILLION

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL DOCUMENT ON A PROPOSED

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL DOCUMENT ON A PROPOSED

More information

ONA PROPOSED LOAN TO THE. October 1, 1999

ONA PROPOSED LOAN TO THE. October 1, 1999 Public Disclosure Authorized Document of The World Bank Report No: 19620-KZ Public Disclosure Authorized PROJECT APPRAISAL DOCUMENT ONA PROPOSED LOAN Public Disclosure Authorized IN THE AMOUNT OF US$140

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-72940) ON A LOAN IN THE AMOUNT OF US$48 MILLION TO AZERENERJI OJSC

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-72940) ON A LOAN IN THE AMOUNT OF US$48 MILLION TO AZERENERJI OJSC Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-72940)

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22644 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Mar ,450,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Mar ,450,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021097 Public Disclosure Authorized Public Disclosure Authorized Project ID P111598 Country Tanzania

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80090) ON A LOAN IN THE AMOUNT OF US$110 MILLION TO THE REPUBLIC OF UZBEKISTAN FOR THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80090) ON A LOAN IN THE AMOUNT OF US$110 MILLION TO THE REPUBLIC OF UZBEKISTAN FOR THE Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80090) ON A LOAN IN THE AMOUNT OF US$110 MILLION TO THE REPUBLIC

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48680) ON A LOAN IN THE AMOUNT OF US$200 MILLION UKRAINE FOR THE POWER TRANSMISSION PROJECT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48680) ON A LOAN IN THE AMOUNT OF US$200 MILLION UKRAINE FOR THE POWER TRANSMISSION PROJECT Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48680) Report No: ICR00003763 Public Disclosure Authorized ON A LOAN IN THE AMOUNT OF US$200 MILLION

More information

INVESTMENT OPPORTUNITIES in Central Asia Power Sector

INVESTMENT OPPORTUNITIES in Central Asia Power Sector INVESTMENT OPPORTUNITIES in Central Asia Power Sector Business Mission to Kazakhstan Almaty - Kazakhstan September 5, 2017 Pedro Robiou Senior Energy Specialist FOR DISCUSSION ONLY. The opinions expressed

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48580) ON A LOAN IN THE AMOUNT OF 92 MILLION EURO (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48580) ON A LOAN IN THE AMOUNT OF 92 MILLION EURO (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2671 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS: PROJECT 1 Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,040,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,040,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020616 Public Disclosure Authorized Public Disclosure Authorized Project ID P119939 Country Uzbekistan

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-40870) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-40870) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-40870) ON

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-46030) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE POWER GRID CORPORATION OF INDIA LIMITED

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-46030) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE POWER GRID CORPORATION OF INDIA LIMITED Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No:ICR000105 IMPLEMENTATION COMPLETION AND RESULTS

More information

CASA-1000 Project List of FAQs

CASA-1000 Project List of FAQs 1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-52541) ON A GRANT. IN THE AMOUNT OF US$ 7.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-52541) ON A GRANT. IN THE AMOUNT OF US$ 7. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001143 IMPLEMENTATION COMPLETION AND RESULTS

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002035 IMPLEMENTATION COMPLETION AND RESULTS

More information

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-94257) ON A CREDIT IN THE AMOUNT OF SDR 91.1 MILLION (US$ 150 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-94257) ON A CREDIT IN THE AMOUNT OF SDR 91.1 MILLION (US$ 150 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002312 IMPLEMENTATION COMPLETION AND RESULTS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:LAO 29284 ASIAN DEVELOPMENT BANK TECHNICAL ASSISTANCE TO ThE LAO PEOPLE'S DEMOCRATIC REPUBLIC FOR ThE CORPORATE AND FINANCIAL DEVELOPMENT OF ELECTRICIT DU LAO LI LI May 1996 - -I CURRENCY EQUIVALENTS

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR STRENGTHENING PROJECT LOAN OCTOBER 25, 2010 TO THE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR STRENGTHENING PROJECT LOAN OCTOBER 25, 2010 TO THE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES14735 Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43530,IDA-43540) ON A CREDIT IN THE AMOUNT OF SDR 9.1 MILLION (US$13.8 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43530,IDA-43540) ON A CREDIT IN THE AMOUNT OF SDR 9.1 MILLION (US$13.8 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00003952 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43530,IDA-43540)

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35380 IDA-35381)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001475 IMPLEMENTATION COMPLETION AND RESULTS

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021272 Public Disclosure Authorized Public Disclosure Authorized Operation ID P159774 Country Fiji Operation Name Fiji Post-Cyclone Winston

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910)

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON A CREDIT IN THE AMOUNT OF SDR16.4 MILLION (US$25 MILLION EQUIVALENT)

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON A CREDIT IN THE AMOUNT OF SDR16.4 MILLION (US$25 MILLION EQUIVALENT) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON

More information

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020731 Public Disclosure Authorized Public Disclosure Authorized Project ID P116080 Project Name EXPORT

More information

Loan Agreement. (Alma Electricity Transmission Project) between JOINT STOCK COMPANY KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY.

Loan Agreement. (Alma Electricity Transmission Project) between JOINT STOCK COMPANY KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY. Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 7965-KZ Public Disclosure Authorized Loan Agreement (Alma Electricity Transmission Project) Public Disclosure Authorized between JOINT STOCK COMPANY

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001476 IMPLEMENTATION COMPLETION AND RESULTS

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE EGYPT NATIONAL RAILWAYS RESTRUCTURING PROJECT

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE EGYPT NATIONAL RAILWAYS RESTRUCTURING PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-91120) ON A GRANT IN THE AMOUNT OF US$57 MILLION) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-91120) ON A GRANT IN THE AMOUNT OF US$57 MILLION) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002901 IMPLEMENTATION COMPLETION AND RESULTS

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Country Practice Area(Lead) Additional Financing Ukraine Energy & Extractives P110298,P115515

Country Practice Area(Lead) Additional Financing Ukraine Energy & Extractives P110298,P115515 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020606 Public Disclosure Authorized Public Disclosure Authorized Project ID P083702 Project Name HYDROPOWER

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003680 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF-92396 TF-96083)

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43510) ON A CREDIT IN THE AMOUNT OF SDR 6.0 MILLION (US$ 9.0 MILLION EQUIVALENT) MONTENEGRO FOR AN

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43510) ON A CREDIT IN THE AMOUNT OF SDR 6.0 MILLION (US$ 9.0 MILLION EQUIVALENT) MONTENEGRO FOR AN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR3012 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

NOTE ON CANCELLED OPERATION REPORT (IBRD-86190) ON A LOAN IN THE AMOUNT OF US$ USD MILLION TO THE FOR A

NOTE ON CANCELLED OPERATION REPORT (IBRD-86190) ON A LOAN IN THE AMOUNT OF US$ USD MILLION TO THE FOR A Public Disclosure Authorized Document of The World Bank Report No: NCO00004218 Public Disclosure Authorized NOTE ON CANCELLED OPERATION REPORT (IBRD-86190) ON A LOAN IN THE AMOUNT OF US$ USD 977.86 MILLION

More information

Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000

Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000 Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000 Conference on Normalizing India-Pakistan Trade Salman Zaheer, The World Bank New Delhi, January 22, 2014 Examples of Regional

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA MULT-54718) ON A CREDIT AND A GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA MULT-54718) ON A CREDIT AND A GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0435 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

The World Bank Third Secondary and Local Roads Project (P148048)

The World Bank Third Secondary and Local Roads Project (P148048) Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THIRD SECONDARY AND LOCAL ROADS PROJECT APPROVED ON JULY 3, 2014 TO GEORGIA REPORT NO.:

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project Report and Recommendation of the President to the Board of Directors Project Number: 44198 May 2012 Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project CURRENCY EQUIVALENTS (as

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Unit Europe and Central Asia Region Document of The World Bank RESTRUCTURING

More information

Tajikistan: Power Rehabilitation Project

Tajikistan: Power Rehabilitation Project Validation Report Reference Number: PCV: TAJ 2011-06 Project Number: 32513 Loan Number: 1817 April 2011 Tajikistan: Power Rehabilitation Project Independent Evaluation Department CURRENCY EQUIVALENTS (as

More information

Public Disclosure Copy. East-West Roads Project (Almaty-Korgos Section): Western Europe - Western China International Transit

Public Disclosure Copy. East-West Roads Project (Almaty-Korgos Section): Western Europe - Western China International Transit Public Disclosure Authorized East-West Roads Project (Almaty-Korgos Section): Western Europe - Western China International Transit Corridor EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Public Disclosure Authorized SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice IBRD/IDA Specific Investment

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT Public Disclosure Authorized The World Bank REPORT NO.: RES30161 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA LEONE INFRASTRUCTURE DEVELOPMENT FUND

IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA LEONE INFRASTRUCTURE DEVELOPMENT FUND Public Disclosure Authorized Document of The World Bank Report No: ICR00004215 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA

More information

The World Bank Indonesia Power Transmission Development Project (P117323)

The World Bank Indonesia Power Transmission Development Project (P117323) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 13 ARCHIVED on 28-Dec-2017 ISR30911 Implementing

More information

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project Report and Recommendation of the President to the Board of Directors Project Number: 43150 July 2010 Proposed Grant Republic of Tajikistan: Regional Power Transmission Project CURRENCY EQUIVALENTS (as

More information

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931)

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF LAND HUSBANDRY, WATER HARVESTING AND HILLSIDE IRRIGATION PROJECT APPROVED

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING ELECTRICITY SECTOR EFFICIENCY ENHANCEMENT PROJECT CR SE. April 25, 2005 TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING ELECTRICITY SECTOR EFFICIENCY ENHANCEMENT PROJECT CR SE. April 25, 2005 TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized The World Bank Power Recovery Project (P144029)

Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized The World Bank Power Recovery Project (P144029) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Albania Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 5 ARCHIVED on 31-Dec-2017 ISR30419 Implementing Agencies:

More information

The World Bank Indonesia Power Transmission Development Project (P117323)

The World Bank Indonesia Power Transmission Development Project (P117323) Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 7 ARCHIVED on 07-Jul-2015 ISR18557 Implementing Agencies:

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-58084) ON A GRANT IN THE AMOUNT OF US$ 5 MILLION TO THE LEBANESE REPUBLIC FOR THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-58084) ON A GRANT IN THE AMOUNT OF US$ 5 MILLION TO THE LEBANESE REPUBLIC FOR THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2675 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-57202) ON A LOAN IN THE AMOUNT OF 20.0 MILLION US$ EQUIVALENT)

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-57202) ON A LOAN IN THE AMOUNT OF 20.0 MILLION US$ EQUIVALENT) Public Disclosure Authorized Document of The World Bank Report No: ICR00002536 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48200 TF-57202) ON A LOAN IN THE AMOUNT OF

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011 Public Disclosure Authorized Document of The World Bank Report No: 65071-CM Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND

More information

Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan) Completion Report Project Number: 40043 Loan Numbers: 2303-TAJ (SF)/8320-TAJ and 2304-AFG (SF) Grant Number: 0230-AFG June 2014 Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002249 IMPLEMENTATION COMPLETION AND RESULTS

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF TF-94587) TRUST FUND GRANTS IN THE AMOUNT OF US$14.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF TF-94587) TRUST FUND GRANTS IN THE AMOUNT OF US$14. Public Disclosure Authorized Document of The World Bank Report No: ICR00002455 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92336 TF-94587) ON TRUST FUND GRANTS IN THE

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48270) ON A LOAN IN THE AMOUNT OF US$150 MILLION UKRAINE FOR THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48270) ON A LOAN IN THE AMOUNT OF US$150 MILLION UKRAINE FOR THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001407 IMPLEMENTATION COMPLETION AND RESULTS

More information

Olivier Le Ber Lead Transport Specialist World Bank

Olivier Le Ber Lead Transport Specialist World Bank World Bank Transport Projects in TRACECA Countries Olivier Le Ber Lead Transport Specialist World Bank 2 WB has 16 transport projects total US$ 4.8 billion in TRACECA countries (3 projects under preparation)

More information

EUROPEA U IO. Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 E ER 173 CODEC 704

EUROPEA U IO. Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 E ER 173 CODEC 704 EUROPEA U IO THE EUROPEA PARLIAMT THE COU CIL Brussels, 12 June 2009 (OR. en) 2007/0198 (COD) PE-CO S 3651/09 ER 173 CODEC 704 LEGISLATIVE ACTS A D OTHER I STRUMTS Subject: REGULATION OF THE EUROPEAN PARLIAMENT

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT ( IDA IDA ) ON A LOAN / CREDIT IN THE AMOUNT OF US$ MILLION (SDR 48.

IMPLEMENTATION COMPLETION AND RESULTS REPORT ( IDA IDA ) ON A LOAN / CREDIT IN THE AMOUNT OF US$ MILLION (SDR 48. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No:ICR-000039 IMPLEMENTATION COMPLETION AND RESULTS

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Report No:

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-44000, TF-99140)

More information

AFRICAN DEVELOPMENT BANK GROUP

AFRICAN DEVELOPMENT BANK GROUP AFRICAN DEVELOPMENT BANK GROUP Public Disclosure Authorized Public Disclosure Authorized SOUTH SUDAN JUBA POWER DISTRIBUTION SYSTEM REHABILITATION AND EXPANSION PROJECT RDGE/PEVP/PGCL DEPARTMENTS March

More information

FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-23406)

FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-23406) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45590) ON A LOAN IN THE AMOUNT OF US$516.

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45590) ON A LOAN IN THE AMOUNT OF US$516. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR0000807 IMPLEMENTATION

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 38196 November 2005 Proposed Loan Socialist Republic of Viet Nam: Northern Power Transmission Expansion Sector Project

More information

FRAMEWORK FINANCING AGREEMENT

FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT (Second Power Transmission Enhancement Investment Program) Parties This Framework Financing Agreement ( FFA ) dated 15 July 2016 is between

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0020321 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project ID P107840 Country Macedonia, former

More information

Bhutan: Sustainable Rural Electrification Project

Bhutan: Sustainable Rural Electrification Project Validation Report Reference Number: PCV: BHU 2008-23 Project Number: 29242 Loan Number: 1712 July 2008 Bhutan: Sustainable Rural Electrification Project Operations Evaluation Department ABBREVIATIONS ADB

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA SIDA SIDA-50554) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA SIDA SIDA-50554) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0000616 IMPLEMENTATION COMPLETION AND RESULTS

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0680, CIDA-54421) ON A INTERNATIONAL DEVELOPMENT ASSOCIATION GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0680, CIDA-54421) ON A INTERNATIONAL DEVELOPMENT ASSOCIATION GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0000656 IMPLEMENTATION COMPLETION AND RESULTS

More information

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021115 Public Disclosure Authorized Public Disclosure Authorized Project ID P118737 Project Name ENERGY

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

Actual Project Name : Transitional Support Credit Country: Bangladesh US$M): Project Costs (US$M Sector Board : EP Cofinancing (US$M

Actual Project Name : Transitional Support Credit Country: Bangladesh US$M): Project Costs (US$M Sector Board : EP Cofinancing (US$M IEG ICR Review Independent Evaluation Group Report Number : ICRR13360 1. Project Data: Date Posted : 03/30/2010 PROJ ID : P110167 Appraisal Actual Project Name : Transitional Support Project Costs (US$M

More information

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project Public Disclosure Authorized Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project (P124351) AFRICA Africa Energy and Mining Global Practice IBRD/IDA Specific Investment

More information

Actual Project Name : Mn - Sustainable Livelihoods Country: Mongolia US$M): Project Costs (US$M

Actual Project Name : Mn - Sustainable Livelihoods Country: Mongolia US$M): Project Costs (US$M IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 10/29/2008 Report Number : ICRR12989 PROJ ID : P067770 Appraisal Actual Project Name : Mn - Sustainable Project Costs (US$M US$M):

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Bangladesh: Bangladesh India Electrical Grid Interconnection Project

Bangladesh: Bangladesh India Electrical Grid Interconnection Project Completion Report Project Number: 44192-013 Loan Numbers: 2661 and 3031 September 2016 Bangladesh: Bangladesh India Electrical Grid Interconnection Project This document is being disclosed to the public

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Second Additional Financing to Road Rehabilitation & Maintenance Project Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Second Additional Financing to Road Rehabilitation & Maintenance Project Region Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Second Additional Financing to Road Rehabilitation & Maintenance Project Region AFRICA Sector Roads and highways (100%) Project ID P120723

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Oct ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Oct ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021153 Public Disclosure Authorized Public Disclosure Authorized Project ID P126180 Country Sierra Leone Project Name Sierra Leone Energy

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Morocco Energy and Mining Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 12 ARCHIVED on 17-Jun-2015 ISR19641 Implementing Agencies:

More information