Tajikistan: Power Rehabilitation Project

Size: px
Start display at page:

Download "Tajikistan: Power Rehabilitation Project"

Transcription

1 Validation Report Reference Number: PCV: TAJ Project Number: Loan Number: 1817 April 2011 Tajikistan: Power Rehabilitation Project Independent Evaluation Department

2 CURRENCY EQUIVALENTS (as of {Day Month Year}) Currency Unit somoni (TJS) TJS1.00 = $ $1.00 = TJS ABBREVIATIONS ADB Asian Development Bank EIRR economic internal rate of return FIRR financial internal rate of return GWh gigawatt-hour (1,000,000 kilowatt-hours) IAS international accounting standards NHPP Nurek Hydropower Plant PCR project completion report PIU project implementation unit PMU project management unit RRP report and recommendation of the President TA technical assistance WACC weighted average cost of capital WTP willingness to pay NOTES (i) (ii) The fiscal year (FY) of the government and Barki Tajik ends on 31 December. In this report, $ refers to US dollars. Key Words adb, asian development bank, barki tajik, hydropower, power, power rehabilitation, Tajikistan Director Team leader Team member R. B. Adhikari, Independent Evaluation Division 1, Independent Evaluation Department (IED) B. E. Palacios, Senior Evaluation Officer, IED I. Garganta, Senior Evaluation Assistant, IED In preparing any evaluation report, or by making any designation of or reference to a particular territory or geographic area in this document, the Independent Evaluation Department does not intend to make any judgments as to the legal or other status of any territory or area.

3 PROJECT COMPLETION REPORT VALIDATION A. Basic Project Data Project Completion Report (PCR) Validation Date Project Number Loan Number 1817 Project Name Power Rehabilitation Project Total Project Cost ($ million) Country: Tajikistan Loan/Grant ($ million) (SDR million) Sector Energy (electricity transmission Total Cofinancing (subsector) and distribution) ($ million) Asian Development Bank (ADB) Financing ($ million) Asian Development Fund Ordinary Capital Resources 0.00 Islamic Development Bank Government of Switzerland Approved April 2011 Actual Cofinanciers Islamic Development Bank Borrower ($ million) Government of Switzerland Beneficiaries ($ million) Others ($ million) Barki Tajik Approval Date 20 Dec 2000 Effectiveness Date 26 May Aug 2001 Signing Date: 26 Feb 2001 Closing Date 30 Jun Apr 2009 Project Officers Name A. Jude Location: ADB headquarters From 2000 To 2000 S. Vivekananda ADB headquarters X. Humbert ADB headquarters B. Byambasaikhan ADB headquarters L. Mtchedlishvilli ADB headquarters Validator: Quality Control Reviewer/Peer Reviewer B. E. Palacios P. Perera Source: Power Rehabilitation Project files. Director R. B. Adhikari, Independent Evaluation Division 1 B. Project Description (Summarized from the Report and Recommendation of the President) 1 (i) Rationale. Before the Soviet Union broke up, Tajikistan s power system was part of the electricity pool of Central Asia, helping to provide peak and reserve capacity that regulated voltage and frequency in the region. Tajikistan supplied the region with low-cost hydroelectric power, and it received oil and gas through net resource transfers. The disintegration of the Soviet Union in 1990 severely affected the power sector of Tajikistan. The weakly performing economy and damage caused by the civil war pushed the power supply system to the verge of collapse. The country stopped building new hydropower plants, and infrastructure maintenance languished from lack of funds. In addition, as gas and petroleum imports became more costly, residential consumers switched to hydropower sources, adding to demand. Power outages were common, especially in winter, when there was not enough water resources for power generation. If the power supply did not improve, the lives of the poor in particular would stay miserable. Social surveys during the 1 ADB Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Republic of Tajikistan for the Power Rehabilitation Project. Manila.

4 2 project feasibility study confirmed the fact that the poor had much less access to electricity supply than other sectors of the population. Given the urgent need to overcome the power supply constraints and to increase the efficiency of energy supply and use, the government assigned top priority in the medium term to retrofitting and rehabilitating power facilities rather than building new plants. Such measures were expected to particularly benefit the poor, who could not afford other fuels. The report and recommendation of the President (RRP) confirmed the importance given to the energy sector and the power subsector by the government and the Asian Development Bank (ADB), as expressed in ADB s interim operational strategy for Tajikistan. 2 (ii) (iii) Objectives or expected outcomes. The project was aimed at improving (a) the availability of electricity to poor consumers, so they could live better lives and poverty could be reduced; (b) the availability, reliability, and quality of electric supply in general; and (c) sector efficiency. These objectives were to be achieved in an environment-friendly manner through the rehabilitation of generation, transmission, and distribution facilities developed during the Soviet era. The targets set in the project framework were (a) an additional 7,571 gigawatt-hours (GWh) of electricity from the rehabilitated facilities; and (b) more reliable and better-quality electricity supply. Components and output. The project had five components: (a) rehabilitation of distribution lines and transformers in poor areas in the Khatlon region (part A); (b) rehabilitation of the Nurek Hydropower Plant (NHPP) and associated transmission facilities (part B); (c) improvement of power supply reliability in the Dushanbe region (part C); (d) bulk metering of power supply (part D); and (e) consulting services (part E). The output targets listed in the project framework were (a) 36 GWh more electricity supplied to the Khatlon region (for part A); (b) an additional 24,000 poor households with electricity connections, increasing total connections from 148,000 to 172,000 (also for part A); (c) 320 GWh more electricity generated from NHPP (for part B); (d) reduced load shedding in the Dushanbe region (for part C); (e) 3 months accounts receivable, down from 11 months in 1999, and international accounting standards (IAS) adopted (for part D); and (f) implementing guidelines developed for the Energy Law (for part E). To help Barki Tajik meet the targets set in the energy sector action plan, two advisory technical assistance (TA) grants were approved together with the loan. The first was for the design and implementation of a billing and collection system to reduce accounts receivable. 3 The second TA was to introduce IAS and prepare the corporate accounts of Barki Tajik for 2001 in line with both national regulations and IAS. 4 C. Evaluation of Design and Implementation (Project Completion Report Assessment and Validation) (i) Relevance of design and formulation. The project conformed to the government s development strategy, and to ADB s country assistance strategy for Tajikistan and its strategic objectives at the time of approval. The rehabilitation of infrastructure, especially roads and power, was a priority area in ADB s interim operational strategy for the country. The government s policies for the energy sector included (a) facilitating the development of laws and regulations for efficient sector operations, (b) increasing electricity tariffs toward full cost recovery, (c) encouraging private sector participation in the generation and supply of power with the passage of the Energy Law, and (d) promoting energy conservation. The planned outcomes confirmed the project s close relevance to ADB s and the government s development objectives and strategies for the country. The 2 ADB Economic Report and Interim Operational Strategy for Tajikistan. Manila (IN , November). 3 ADB Technical Assistance to the Republic of Tajikistan for Improving Barki Tajik s Billing and Collection System. Manila (TA 3600-TAJ, approved for $500,000). 4 ADB Technical Assistance to the Republic of Tajikistan for Introducing International Accounting Standards at Barki Tajik. Manila (TA 3601-TAJ, approved for $500,000).

5 3 rehabilitation of the power network in the Khatlon region and the provision of better and more reliable electricity supply through the NHPP were expected to improve the quality of life in the region. The passage of the Energy Law and the establishment of a Ministry of Energy were made conditions for the appraisal of the loan, the first to be made by ADB to Tajikistan for its energy sector. (ii) Project output. The original project design had four major components (not including consulting services). Parts A, B, and D were completed with their scopes reduced. The project achievements at completion compared with the achievements planned at appraisal are listed in Appendix 1 of the project completion report (PCR). 5 In part A, 61% of the 230 kilometers of medium-voltage lines in poor areas in the Khatlon region and 76% of the 415 kilometers of low-voltage lines were rehabilitated. The number of transformers that were replaced (100) was 6% below target (107). Although the Central Hydropower Plant was rehabilitated, the project did not achieve the target generation of 36 GWh per year, according to the PCR. Generation increased by only 9.4 GWh, 42% short of the 16.2 GWh target increase. The rehabilitation of the Sovhoz 2 substations was canceled; the implementation consultants saw no need for it. In part B, the rehabilitation of the control and protection systems for the 500/220 kilovolt Regar substation was canceled because of government budget constraints and because the work required turned out to be more costly than anticipated. A more reliable NHPP was expected to increase generation by 320 GWh. Generation increased by only 95 GWh as a result of the project, but the PCR gives no reason for the lower-than-expected increase in generation. The proposed improvement of power supply reliability in the Dushanbe region under part C was achieved as planned. At appraisal this component was foreseen to help reduce load shedding in the region. The RRP, however, gave no information about the frequency of load shedding or the power rationing in practice at the time of appraisal. The PCR also does not mention any improvement in load shedding, but it refers to the persistence of power rationing during the winter months of November to April. A change in scope, approved in February 2003, allowed the use of $1.5 million from the contingency balance for the restoration of power in Dushanbe, which had been without power since the winter freeze of December In part D, 95 high-voltage bulk-power energy meters were installed in lieu of the 500 proposed at appraisal. The reduced number was declared sufficient during implementation. At appraisal, it was envisioned that more efficient customer billing and collection would improve accounts receivable to 3 months worth from 11 months in 1999 and that IAS would be adopted. At the time of the project completion review mission, accounts receivable were still a problem. At the end of 2008, accounts receivable stood at 8.8 months (para. 38 of the PCR). This was better than the 11 months accounts receivable in 1999 but still fell short of the target. Furthermore, the financial accounts for that were submitted to ADB indicated that Barki Tarji had not yet adopted IAS (para. 39 of the PCR). The output expected at appraisal and achieved at completion is cataloged in the PCR, and the details are explained adequately in the report. 5 ADB Project Completion Report: Power Rehabilitation Project in Tajikistan. Manila.

6 4 (iii) Project cost, disbursements, borrower contribution, and conformance to schedule (as relevant to project performance). The project was implemented at a total cost of $75.41 million. The total base cost was $66.57 million, 37% higher than estimated at appraisal, despite the reduced scope of parts A, B and D. The appraisal and actual costs for each component are compared in the following table. Project Cost by Component, Appraisal and Actual Cost ($ million) Overrun (Underrun) Item Appraisal Actual Amount % Part A Part B (3.15) (18.50) Part C Part D (0.01) (0.13) Part E Total Base Cost Project monitoring unit Contingencies (7.43) (100.00) IDC (0.67) (9.81) Total Costs ( ) = negative, IDC = interest during construction. Source: Project completion report. The total cost for part C includes $1.87 million for emergency rehabilitation approved on February Without this amount the cost overrun for this component would be 72.69%. The actual cost incurred for the project monitoring unit was not programmed. The government decided unilaterally to establish this unit in July 2006 (section C[iv]). The PCR gives the following reasons for the cost overrun: (a) the rise in commodity and equipment prices in real terms between appraisal in 2000 and procurement in , (b) the higher costs of construction in Tajikistan due to the country s terrain, and (c) the decline in the value of the dollar against the euro. Project records suggest that the increase in costs was largely attributable to implementation delays, especially those that were due in part to the unfamiliarity of the project implementation unit (PIU) and the executing agency, Barki Tajik, with ADB procurement procedures and international competitive bidding. Cost estimation during project design should have been more rigorous and should have considered the country s difficult terrain. The project closed after two extensions and almost 3 years delay. ADB did not approve a third extension of the closing date to 30 September 2009 as the remaining works were not substantial and the project would not be any less effective if they were not implemented. As explained in the PCR, the 2-year delay at the start of implementation was partly due to the unfamiliarity of Barki Tajik with ADB s policies and procedures. This validation report takes the view that this shortcoming could have been addressed during project design. The lack of familiarity with the policies and practices of multilateral financing agencies of similar countries is among the lessons from earlier projects and seminars that were mentioned in the RRP (which did not, however, cite the source of the lessons). Capacity-building activities, such as seminars and workshops, even before the project would have acquainted Barki Tajik with those procedures in preparation for implementation. Work overload in the PIU also hampered the smooth implementation of the project.

7 5 (iv) Implementation arrangements, conditions and covenants, related technical assistance, and procurement and consultant performance. The PCR reports that implementation arrangements envisaged at appraisal were generally applied. A PIU was formed as agreed, but in July 2006 the government decided unilaterally to centralize project implementation responsibilities in the state project management unit (PMU). The PMU, separate from Barki Tajik, would handle all power projects in Tajikistan regardless of donor agency. The PCR fails to mention this major implementation issue. During implementation, ADB made known its disapproval of the arrangement to the government and pointed out that it was clearly in breach of the provision in the loan agreement that required the Borrower [to] cause Barki Tajik to maintain at all times a PIU within Barki Tajik. An ADB review mission in February 2007 found the PMU to be lacking in the required capacity for the efficient day-to-day operations of the project. In May 2007, nearly 1 year after the PMU was created, another ADB review mission informed the government that the PMU was ineffective because it lacked (a) ownership, (b) incentives for meeting disbursement and time schedule targets, (c) a streamlined bureaucracy, and (d) staff with international exposure. Moreover, its existence in place of the PIU in Barki Tajik violated a provision of the loan agreement with ADB. The PCR also states (para. 36) that the government and Barki Tajik had complied partly with the loan covenants at the time of the project completion review mission, but it does not give the number of covenants that were fully complied with. With Appendix 5 of the PCR as reference, this validation report notes that 11 of 24 covenants (46%) were complied with, 6 (25%) were partly complied with, 5 (21%) were not complied with, and 2 (8%) were not yet due. Of the 6 financial covenants, 2 were partly complied with and 4 were not complied with. Despite repeated reminders from ADB, Barki Tajik consistently failed to submit audited project accounts and audited financial statements on time. Quarterly progress reports were also submitted late. Partly for this reason, ADB in 2003 declared the project to be at risk. Another reason was Barki Tajik s high accounts receivable, which reached 13.3 months of gross billing in The PCR does not give an assessment of the implementation consultants performance. This validation report considers the performance only partly satisfactory. On several occasions ADB expressed its disappointment over the consultants failure to inform Barki Tajik of changes in scope and procurement procedures, which resulted in more implementation delays. At Barki Tajik s request, however, the services of the implementation consultants were retained despite the ADB review mission s dissatisfaction with their performance. The mission proposed the recruitment of an independent international consultant to assist the PIU in its day-to-day management of the project. Bidding documents were also of unacceptable quality, with many inconsistencies such as imprecisely defined scope of works. Two TA grants attached to the loan, for improving Barki Tajik s billing and collection system and for introducing IAS at Barki Tajik, are not assessed in the PCR, which only mentions the fact that the TA completion reports were prepared in (v) (vi) Performance of the borrower and the executing agency. The PCR rates the performance of the borrower and Barki Tajik satisfactory. Because of the borrower s less than satisfactory financial performance and low compliance rate with the loan covenants, and the unilateral change it made in the implementation arrangements, this validation report rates the performance of the borrower and Barki Tajik partly satisfactory. Performance of the Asian Development Bank. The PCR rates ADB s performance satisfactory and this validation report agrees with the assessment. The PCR states that ADB did not provide enough monitoring of the financial performance of Barki Tajik. Records, however, show that ADB persistently reminded the latter of the need to submit audited financial statements, and this enough

8 6 monitoring of the financial performance of Barki Tajik. Records, however, show that ADB persistently reminded the latter of the need to submit audited financial statements, and this validation report finds that ADB was not remiss in this aspect. D. Evaluation of Performance (Project Completion Report Assessment and Validation) (i) Relevance. The PCR rates the project highly relevant because it was in accordance with government priorities and ADB policies, and had the appropriate focus on repair and rehabilitation. Relevance assessment should also look at design and any change of scope during implementation. This validation report agrees with the PCR on the points raised and considers the project relevant to this day. However, the project had design weaknesses that resulted in changes in scope in three of the five components. In part A, the proposed rehabilitation of the Sovhoz 2 substations was dropped when it was determined during implementation that the power supply to the substations was adequate. This finding could have been made at the design stage Some rehabilitation works in part B were also dropped when they turned out to be more extensive and costly than originally anticipated a quality-at-entry issue. This validation report therefore rates the project relevant. (ii) (iii) Effectiveness in achieving outcome. The PCR rates the project effective. However, the PCR also states (para. 60) that electricity is used mainly for lighting and to power radios and television sets. The PCR does not give a consolidated accounting of how much more electricity was made available through the project, but the shortfall in targets under the different components indicates that the outcome target of 7,571 GWh additional electricity was not achieved. Furthermore, the PCR observes that, despite the project, cooking is still done with wood stoves and liquefied petroleum gas. At the time of the project completion review mission, Barki Tajik, unable to supply the total power demand in the winter, had resorted to rationing. This validation report believes that, for the same reasons given in the PCR, the project was less effective. Efficiency in achieving outcome and output. The project is rated partly efficient in the PCR because of the cost overruns and the implementation delays. This validation report concurs with this rating. The economic internal rate of return (EIRR), as recalculated in the PCR, is 13.2%. This validation report has several comments related to the computation of the EIRR. The PCR treats all power sold by the project as incremental, valued in terms of the PCR s estimate of willingness to pay (WTP). How WTP was estimated is unclear, and the significance of the last sentence in para. 13 of Appendix 7 is likewise ambiguous. Was the WTP estimated on the basis of the tariff? In practice, the price paid by the consumer for alternative sources of power (kerosene, candles, etc.) will indicate the WTP. The accuracy of the WTP estimate cannot be verified, given the insufficient documentation presented in the PCR. Para. 10 of Appendix 7 mentions a 10% interest rate slapped on the average economic cost of energy. The PCR should first of all document how the economic cost was estimated and the rationale for the 10% interest rate. It would have been more appropriate to break down the benefits into incremental and nonincremental benefits, and to value the incremental benefits at the users willingness to pay and the nonincremental at resource cost savings. The PCR chose to ignore commercial and agricultural consumption in estimating the EIRR because of the low tariffs. These sectors share of consumption is more than 20%, hardly justifying their exclusion from the economic benefit estimates. This validation report notes further that operation and maintenance costs and transmission charges were not converted to economic costs. Furthermore there were implementation delays and substantial cost overrun [C(iii)].

9 7 (iv) Preliminary assessment of sustainability. The PCR rates the sustainability of the project most likely (PCR uses the term highly sustainable ), given the quality of the facilities built. Even if project facilities are well built and can be useful for many years, they will require regular maintenance. To support the most likely rating the PCR should have discussed how the human, institutional, and financial circumstances of Barki Tajik could sustain the operation of the project facilities. Since Barki Tajik has submitted no corporate financial statements to ADB since 2003, its financial performance is difficult to assess. However, indicators presented in Appendix 6 of the PCR show that accounts receivable are still a problem at 8.8 months worth in 2008, significantly above the covenanted level of 3 months. Operating expenses continue to use up a very large portion of revenues generated. The PCR does not compare the recalculated financial internal rate of return (FIRR), 3.2%, with the weighted average cost of capital (WACC). At appraisal, no indicative set of interest rates could be used to estimate the WACC for the RRP. A power transmission project in Tajikistan that was approved in 2002 but subsequently canceled used the interest rate for ADB s London interbank offered rate based loans of 3.9% as a proxy for the WACC. The recalculated FIRR is below this proxy and does not support the most likely sustainability rating. This validation report rates the project s sustainability less likely because of the slow progress of corporate and financial reforms and the weak collection systems. The FIRR and available financial data also show that Barki Tajik may face some financial difficulty in funding a reasonable maintenance program for the facilities. (v) Impact (both intended and unintended). The project mostly involved the rehabilitation of existing facilities and was not expected to have any adverse environmental impact. The project was to contribute to poverty reduction by increasing energy supply to the poor. The 21,600 new connections, however, fell short of the intended impact. The project was also expected to improve the governance of state-owned energy enterprises, and the energy sector action plan provided for the corporatization of Barki Tajik. But at the time of the project completion review mission Barki Tarji had not yet been corporatized. The PCR adds that expectations regarding corporate reforms and improved financial performance and accounting practices in Barki Tajik have not yet been fulfilled. The PCR does not rate the impact of the project. This validation rates the impact moderate. E. Overall Assessment, Lessons, and Recommendations (Validation of Project Completion Report Assessment) (i) (ii) Overall assessment. The PCR rates the project successful. However, several issues identified in the PCR and this validation report indicate a lower rating: (a) weaknesses in design and formulation; (b) output below what was expected; (c) 34 months delay in implementation, actual costs higher than estimates, and a partly satisfactory rating for the implementation consultants and the borrower; and (d) failure to comply with important covenants including the corporatization of Barki Tajik. Finally, this validation report concurs with the PCR rating of less efficient on the basis of the implementation delays and cost overruns, and reiterates the necessity of recalculating the EIRR. This validation gives the project and overall rating of partly successful. Lessons. Three major lessons are identified in the PCR: (a) the need for more thorough due diligence, especially in estimating project costs; (b) the need to monitor the submission of required information by Barki Tajik; and (c) the need to ensure that Barki Tajik complies with the loan covenants.

10 8 This validation supports the first two lessons but feel that ADB was not remiss in reminding Barki Tajik of its obligations regarding the loan covenants. There is evidence that such reminders were issued every time a mission was fielded. The RRP brought out the lessons learned from ADB s experience in countries in transition. But listing the lessons in the RRP is not enough. Project implementation would have benefited if at least some of these lessons had been taken into account in project formulation and design. Many of the implementation problems arose because of Barki Tajik s unfamiliarity with ADB s procurement procedures, and the appraisal mission was well aware that such unfamiliarity has delayed the start of many projects in Central Asia. (iii) Recommendations. The PCR recommends (a) continued reminders to Barki Tajik of the need to monitor benefits, (b) continued monitoring of compliance with financial covenants, and (c) the inclusion in future covenants of a provision requiring Barki Tajik to charge a realistic interest rate on its overdue accounts. This validation report agrees with all of these recommendations. F. Monitoring and Evaluation Design, Implementation, and Utilization (Project Completion Report Assessment and Validation) At the start of project implementation, Barki Tajik was to submit a report to ADB on benchmark information; at project completion, it was to begin monitoring and evaluating the project benefits. Barki Tajik was also expected to submit a comprehensive report on the poverty reduction impact of the project within 3 months after project completion. The PCR is silent on these activities and it is not known whether they were carried out. The PCR also does not go into the poverty reduction impact of the project. G. Other (e.g., Safeguards, including Governance and Anticorruption Provisions; Fiduciary Aspects; Government Assessment of the Project, as Applicable) (Project Completion Report Assessment and Validation) Environment safeguards were in place. There were no resettlement issues and no adverse socioeconomic impact was expected. Local counterpart funds were provided in a timely manner. While the PCR identifies several possible governance issues (such as breach of loan agreement provision regarding implementation arrangements, delays in procurement, and poor quality of bidding documents), there is not enough information in the PCR or in the project files to indicate serious governance issues. Some of the delays in procurement may have been due, in part, to local authorities lack of experience.

11 9 Independent Evaluation Department H. Ratings Project Completion Report Review Reason for Disagreement and Comments Relevance Highly relevant Relevant Design weaknesses, resulting in change in scope (see section D[i] above) Effectiveness in achieving Effective Less effective Outcome only partly achieved (see outcome section D[ii] above) Efficiency in achieving Partly efficient Less efficient PCR uses the term partly but means less ; outcome and output no disagreement in ratings Preliminary assessment of Most likely Less likely No evidence of financial sustainability; also, sustainability FIRR less than WACC Satisfactory Borrower and executing agency Partly satisfactory Performance of ADB Satisfactory Satisfactory Impact Not rated Moderate Overall assessment Successful Partly Successful Quality of PCR Partly satisfactory Failure to comply with a number of covenants and unilateral changes in implementation arrangements (see section C[v] above) PCR needs to provide more evidence and analysis, such as numbers to support observations about power supply reliability, implementation issues, and covenants complied with, and calculate EIRR more thoroughly I. Comments on PCR Quality Several areas need improvement: (i) A summary evaluation of the attached TA grants should have been included in the PCR. (ii) Barki Tajik was supposed to submit benchmark information to ADB. It was also expected to carry out project benefit monitoring and evaluation upon project completion and to submit a comprehensive report (presumably to ADB). The PCR is silent on this monitoring activity. (ii) The EIRR methodology needs to be revisited. J. Recommendation for Independent Evaluation Department Follow-Up Project performance evaluation in 2011 is recommended to fill in or confirm information gaps, especially with regard to sustainability issues and the EIRR. Lessons and recommendations from the project performance evaluation report will be important in light of ADB s planned investment in energy in Tajikistan. For the period , ADB s country partnership strategy 6 for Tajikistan shows that 56% of ADB s public sector assistance projects and 30% of TA programs will be in the energy sector. The impact of the follow-on TA to strengthen the management of Barki Tajik (TA for Strengthening Corporate Management of Barki Tajik), 7 which was completed in March 2010, will be an important input in assessing the sustainability of the project. K. Data Sources for Validation PCR, RRP, and project files. 6 ADB Country Partnership Strategy: Tajikistan, Manila. 7 Attached to ADB Report and Recommendation of the President to the Board of Directors: Proposed Loans, Technical Assistance Grants, and Administration of Loans to the Islamic Republic of Afghanistan and the Republic of Tajikistan for the Regional Power Transmission Interconnection Project. Manila (TA 4908-TAJ).

12 REGIONAL DEPARTMENT S RESPONSE TO THE PROJECT COMPLETION REPORT VALIDATION REPORT On 12 April 2011, Director, Independent Evaluation Division 1 of the Independent Evaluation Department (IED) received the following comments from circulated the draft Project Completion Validation Report for interdepartmental comments. IED received the following comments from the Energy Division of the Central and West Asia Department. We do not share some views of IED, particularly, related on the relevance of the project. No further comments from our side.

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Validation Report Reference Number: PCV: PHI 2011-15 Project Number: 35379 Loan Number: 2012 July 2011 Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Independent

More information

Philippines: Philippine Energy Efficiency Project

Philippines: Philippine Energy Efficiency Project Validation Report Reference Number: PVR-436 Project Number: 42001-013 Loan/Grant Numbers: 2507 and 0142 December 2015 Philippines: Philippine Energy Efficiency Project Independent Evaluation Department

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan) Completion Report Project Number: 40043 Loan Numbers: 2303-TAJ (SF)/8320-TAJ and 2304-AFG (SF) Grant Number: 0230-AFG June 2014 Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

More information

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project Validation Report Reference Number: PVR-360 Project Number: 40198 Loan Number: 2374 December 2014* Viet Nam: Ho Chi Minh CityLong ThanhDauGiay Expressway Technical Assistance Project Independent Evaluation

More information

Bhutan: Sustainable Rural Electrification Project

Bhutan: Sustainable Rural Electrification Project Validation Report Reference Number: PCV: BHU 2008-23 Project Number: 29242 Loan Number: 1712 July 2008 Bhutan: Sustainable Rural Electrification Project Operations Evaluation Department ABBREVIATIONS ADB

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Georgia: Emergency Assistance for Post-Conflict Recovery

Georgia: Emergency Assistance for Post-Conflict Recovery Validation Report Reference Number: PCV: GEO 2011-49 Project Number: 32023 Loan Number: 2469-GEO(SF) December 2011 Georgia: Emergency Assistance for Post-Conflict Recovery Independent Evaluation Department

More information

Mongolia: Regional Road Development Project

Mongolia: Regional Road Development Project Validation Report Reference Number: PVR-481 Project Numbers: 35377-013 and 35377-023 Loan/Grant Numbers: 2087, 2621, and 0199 December 2016 Mongolia: Regional Road Development Project Independent Evaluation

More information

Pakistan: Road Sector Development Program

Pakistan: Road Sector Development Program Validation Report Reference Number: PCV: PAK 2010-69 Project Number: 32058 Loan Number: 1891 December 2010 Pakistan: Road Sector Development Program Independent Evaluation Department ABBREVIATIONS ADB

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

Philippines: Mindanao Basic Urban Services Sector Project

Philippines: Mindanao Basic Urban Services Sector Project Validation Report Reference Number: PCV: PHI 2011-25 Project Number: 30551 Loan Number: 1843 September 2011 Philippines: Mindanao Basic Urban Services Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

Tajikistan: Microfinance Systems Development Program

Tajikistan: Microfinance Systems Development Program Validation Report Reference Number: PCV: TAJ 2010-55 Project Number: 33040 Loan Number: 2000; 2001 November 2010 Tajikistan: Microfinance Systems Development Program Independent Evaluation Department ABBREVIATIONS

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

Cambodia: Small and Medium Enterprise Development Program

Cambodia: Small and Medium Enterprise Development Program Validation Report Reference Number: PCV: CAM 2010-73 Program Number: 36383 Loan Number: 2129(SF) December 2010 Cambodia: Small and Medium Enterprise Development Program Independent Evaluation Department

More information

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project f Validation Report Reference Number: PVR-370 Project Number: 29041 Loan Number: 1947 December 2014 Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project Independent Evaluation Department

More information

Pakistan: Decentralization Support Program

Pakistan: Decentralization Support Program Validation Report Reference Number: PCV: PAK 2011-53 Program Number: 34328 Loan Numbers: 1935/1936/1937/1938 December 2011 Pakistan: Decentralization Support Program Independent Evaluation Department ABBREVIATIONS

More information

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS: PROJECT 1 Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy

More information

India: Karnataka Urban Development and Coastal Environmental Management Project

India: Karnataka Urban Development and Coastal Environmental Management Project Validation Report Reference Number: PVR-334 Project Number: 30303 Loan Number: 1704 November 2014 India: Karnataka Urban Development and Coastal Environmental Management Project Independent Evaluation

More information

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Validation Report November 2017 Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Reference Number: PVR-535 Program Number: 40061-013 Loan Number: 2619 and 8245 Grant Number:

More information

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Validation Report Reference Number: PVR-471 Project Number: 47337-001 Loan Number: 3080 December 2016 Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Independent Evaluation

More information

India: Assam Governance and Public Resource Management Sector Development Program

India: Assam Governance and Public Resource Management Sector Development Program Validation Report Reference Number: PVR-335 Project Number: 36308 Loan Numbers: 2141, 2142, and 2442 November 2014 India: Assam Governance and Public Resource Management Sector Development Program Independent

More information

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON)

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) Board of Directors IN.365-10 21 December 2010 Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) The attached Report is circulated at the request of the Director General, Independent Evaluation

More information

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project Report and Recommendation of the President to the Board of Directors Project Number: 43150 July 2010 Proposed Grant Republic of Tajikistan: Regional Power Transmission Project CURRENCY EQUIVALENTS (as

More information

Indonesia: Capacity Building in Urban Infrastructure Management Project

Indonesia: Capacity Building in Urban Infrastructure Management Project Validation Report Reference Number: PCV: INO 2008-68 Project Number: 27289 Loan Number: 1572-INO May 2009 Indonesia: Capacity Building in Urban Infrastructure Management Project Independent Evaluation

More information

Viet Nam: Microfinance Development Program (Subprograms 1 and 2)

Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Validation Report Reference Number: PVR-478 Project Numbers: 42235-013 and 42235-023 Loan Numbers: 2877 and 3213 December 2016 Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Independent

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Islamic Republic of Pakistan: Update on Energy Sector Plan

Islamic Republic of Pakistan: Update on Energy Sector Plan Technical Assistance Report Project Number: 50081-001 Knowledge and Support Technical Assistance (KSTA) August 2017 Islamic Republic of Pakistan: Update on Energy Sector Plan This The views document expressed

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

Validation Report. Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation Project. Operations Evaluation Department

Validation Report. Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation Project. Operations Evaluation Department Validation Report Reference Number: PCV:KAZ/KGZ 2008-35 Project Number: 29568 and 32463 Loan Numbers: 1774 and 1775(SF) November 2008 Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation

More information

People's Republic of China: Ganzhou Longyan Railway Project

People's Republic of China: Ganzhou Longyan Railway Project Validation Report Reference Number: PCV: PRC 2009-22 Project Number: 33442 Loan Number: 1850 December 2009 People's Republic of China: Ganzhou Longyan Railway Project Independent Evaluation Department

More information

Bangladesh: Chittagong Hill Tracts Rural Development Project

Bangladesh: Chittagong Hill Tracts Rural Development Project Validation Report Reference Number: PVR-222 Project Number: 32467 Loan Number: 1771(SF) December 2012 Bangladesh: Chittagong Hill Tracts Rural Development Project Independent Evaluation Department ABBREVIATIONS

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department Validation Report Reference Number: PVR-451 Project Number: 38254-033 Loan Number: 2312 August 2016 India: North Karnataka Urban Sector Investment Program, Tranche 1 Independent Evaluation Department ABBREVIATIONS

More information

Afghanistan: Regional Airports Rehabilitation Project (Phase 1)

Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Validation Report Reference Number: PVR 225 Project Number: 37136 Loan Number: 2105 December 2012 Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Independent Evaluation Department ABBREVIATIONS

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO)

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) Board of Directors IN.247-11 14 October 2011 Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) The attached Report is circulated at the request of the Director

More information

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2)

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Validation Report July 2017 Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Reference Number: PVR-497 Project Number: 36169-023 Loan Number: 2641 Grant Number: 0208 ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK PPA: PRC 25013

ASIAN DEVELOPMENT BANK PPA: PRC 25013 ASIAN DEVELOPMENT BANK PPA: PRC 25013 PROJECT PERFORMANCE AUDIT REPORT ON THE DALIAN WATER SUPPLY PROJECT (Loan 1313-PRC) IN THE PEOPLE S REPUBLIC OF CHINA November 2003 At Appraisal (May 1994) CURRENCY

More information

FRAMEWORK FINANCING AGREEMENT

FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT (Second Power Transmission Enhancement Investment Program) Parties This Framework Financing Agreement ( FFA ) dated 15 July 2016 is between

More information

Validation Report. Tonga: Economic Support Program. Independent Evaluation Department

Validation Report. Tonga: Economic Support Program. Independent Evaluation Department Validation Report Reference Number: PVR-318 Program Number: 43152-01 Grant Number: 0185 September 2014 Tonga: Economic Support Program Independent Evaluation Department ABBREVIATIONS ADB Asian Development

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:LAO 29284 ASIAN DEVELOPMENT BANK TECHNICAL ASSISTANCE TO ThE LAO PEOPLE'S DEMOCRATIC REPUBLIC FOR ThE CORPORATE AND FINANCIAL DEVELOPMENT OF ELECTRICIT DU LAO LI LI May 1996 - -I CURRENCY EQUIVALENTS

More information

FINANCIAL ANALYSIS OF TRANCHE 1

FINANCIAL ANALYSIS OF TRANCHE 1 Town Electrification Investment Program (RRP PNG 41504) FINANCIAL ANALYSIS OF TRANCHE 1 A. Financial Analysis 1. Introduction 1. The financial analysis of the project covers the first three subprojects

More information

Kazakhstan: Countercyclical Support

Kazakhstan: Countercyclical Support Validation Report August 2018 Kazakhstan: Countercyclical Support Reference Number: PVR-567 Project Number: 49083-001 Loan Number: 3272 ABBREVIATIONS ADB CPS - - Asian Development Bank country partnership

More information

Completion Report. Project Number: Loan Number: 2128 October Viet Nam: Northern Power Transmission Sector Project

Completion Report. Project Number: Loan Number: 2128 October Viet Nam: Northern Power Transmission Sector Project Completion Report Project Number: 32273 Loan Number: 2128 October 2012 Viet Nam: Northern Power Transmission Sector Project CURRENCY EQUIVALENTS Currency Unit dong (D) At Appraisal At Project Completion

More information

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I.

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I. Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Project Performance

More information

ASIAN DEVELOPMENT BANK PPA: PAK 17003

ASIAN DEVELOPMENT BANK PPA: PAK 17003 ASIAN DEVELOPMENT BANK PPA: PAK 17003 PROJECT PERFORMANCE AUDIT REPORT ON THE KESC FIFTH POWER (SECTOR LOAN) PROJECT (Loan 925-PAK) IN PAKISTAN October 2001 CURRENCY EQUIVALENTS Currency Unit Pakistan

More information

Validation Report. Sri Lanka: Road Network Improvement Project. Independent Evaluation Department

Validation Report. Sri Lanka: Road Network Improvement Project. Independent Evaluation Department Validation Report Reference Number: PCV: SRI 2010 20 Project Number: 28331 Loan Number: 1649 August 2010 Sri Lanka: Road Network Improvement Project Independent Evaluation Department ABBREVIATIONS ADB

More information

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis

More information

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Validation Report December 2018 Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Reference Number: PVR-565 Project Numbers: 41121-023, 41121-033, 41121-043, and 41121-053 MFF

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project Report and Recommendation of the President to the Board of Directors Project Number: 44198 May 2012 Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project CURRENCY EQUIVALENTS (as

More information

Maldives: Tsunami Emergency Assistance Project

Maldives: Tsunami Emergency Assistance Project Validation Report Reference Number: PVR 218 Project Number: 39099 Loan Number: 2160 (SF) Grant Number: 0001 December 2012 Maldives: Tsunami Emergency Assistance Project Independent Evaluation Department

More information

Philippines: Small and Medium Enterprise Development Support Project

Philippines: Small and Medium Enterprise Development Support Project Validation Report Reference Number: PCV: PHI 2011 28 Project Number: 36419 Loan Number: 2186 October 2011 Philippines: Small and Medium Enterprise Development Support Project Independent Evaluation Department

More information

Multitranche Financing Facility Annual Report 2017

Multitranche Financing Facility Annual Report 2017 May 2018 Multitranche Financing Facility Annual Report 2017 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. ABBREVIATIONS ADB Asian Development

More information

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones Technical Assistance Report Project Number: 50004-001 Policy and Advisory Technical Assistance (PATA) October 2016 People s Republic of China: Study on Natural Resource Asset Appraisal and Management System

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22644 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR: PRC 26198 PROJECT COMPLETION REPORT ON THE HUNAN LINGJINTAN HYDROPOWER PROJECT (Loan 1318-PRC) IN THE PEOPLE S REPUBLIC OF CHINA November 2003 CURRENCY EQUIVALENTS Currency

More information

Pakistan: Agribusiness Development Project

Pakistan: Agribusiness Development Project Validation Report Reference Number: PVR-354 Project Number: 33364 Loan Number: 2171 November 2014 Pakistan: Agribusiness Development Project Independent Evaluation Department ABBREVIATIONS ADB ASF DALPMG

More information

Pakistan: Rural Finance Sector Development Program

Pakistan: Rural Finance Sector Development Program Validation Report Reference Number: PCV: PAK 2010-54 Project Number: 36075 Loan Number: 1987-PAK, 1988-PAK November 2010 Pakistan: Rural Finance Sector Development Program Independent Evaluation Department

More information

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis:

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis: Java Bali 500-Kilovolt Power Transmission Crossing Project (RRP INO 42362) FINANCIAL ANALYSIS 1. General Methodology. Financial analysis of the project has been undertaken in accordance with Asian Development

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

Indonesia: Participatory Irrigation Sector Project

Indonesia: Participatory Irrigation Sector Project Validation Report Reference Number: PVR-393 Project Number: 32359 Loan/Grant Numbers: 2064, 2065, and 4229 February 2015 Indonesia: Participatory Irrigation Sector Project Independent Evaluation Department

More information

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project Completion Report Project Number: 35087 Loan Number: 2119/2120 December 2011 Azerbaijan: Urban Water Supply and Sanitation Project CURRENCY EQUIVALENTS Currency Unit Azerbaijan manat (AZN) At Appraisal

More information

Bangladesh: Bangladesh India Electrical Grid Interconnection Project

Bangladesh: Bangladesh India Electrical Grid Interconnection Project Completion Report Project Number: 44192-013 Loan Numbers: 2661 and 3031 September 2016 Bangladesh: Bangladesh India Electrical Grid Interconnection Project This document is being disclosed to the public

More information

FINANCIAL MANAGEMENT ASSESSMENT

FINANCIAL MANAGEMENT ASSESSMENT Greater Malé Environmental Improvement and Waste Management Project (RRP MLD 51077) EXECUTIVE SUMMARY FINANCIAL MANAGEMENT ASSESSMENT 1. The financial management assessment (FMA) was conducted for the

More information

Afghanistan: Energy Supply Improvement Investment Program (Tranche 2)

Afghanistan: Energy Supply Improvement Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 47282-004 MFF Number: 0090 November 2016 Afghanistan: Energy Supply Improvement Investment Program (Tranche 2) This document is being disclosed to the

More information

Bangladesh: Road Network Improvement and Maintenance Project II

Bangladesh: Road Network Improvement and Maintenance Project II Validation Report Reference Number: PVR-435 Project Number: 34415 Loan Number: 2021 November 2015 Bangladesh: Road Network Improvement and Maintenance Project II Independent Evaluation Department ABBREVIATIONS

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department Validation Report Reference Number: PVR-307 Project Number: 36320 Loan Number: 2018 May 2014 India: Rural Roads Sector I Project Independent Evaluation Department ABBREVIATIONS ADB Asian Development Bank

More information

Maldives: Information Technology Development Project

Maldives: Information Technology Development Project Validation Report Reference Number: PVR-272 Project Number: 34276 Loan Number: 1882 December 2013 Maldives: Information Technology Development Project Independent Evaluation Department ABBREVIATIONS ADB

More information

Evaluation Study. Midterm Review Process. Operations Evaluation Department

Evaluation Study. Midterm Review Process. Operations Evaluation Department Evaluation Study Reference Number: SES:REG 2008-78 Special Evaluation Study Update December 2008 Midterm Review Process Operations Evaluation Department ABBREVIATIONS ADB Asian Development Bank BTOR back-to-office

More information

Completion Report. Project Number: Loan Number: 1912 April Tajikistan: Emergency Baipaza Landslide Stabilization Project

Completion Report. Project Number: Loan Number: 1912 April Tajikistan: Emergency Baipaza Landslide Stabilization Project Completion Report Project Number: 36233 Loan Number: 1912 April 2006 Tajikistan: Emergency Baipaza Landslide Stabilization Project CURRENCY EQUIVALENTS Currency Unit somoni (TJS) At Appraisal At Project

More information

Policy Paper. March Establishing the Project Design Facility

Policy Paper. March Establishing the Project Design Facility Policy Paper March 2011 Establishing the Project Design Facility ABBREVIATIONS ADB Asian Development Bank ADF Asian Development Fund COBP country operations business plan DMC developing member country

More information

India: Power Grid Transmission (Sector) Project

India: Power Grid Transmission (Sector) Project Completion Report Project Number: 38492-013 Loan Number: 2152 July 2017 India: Power Grid Transmission (Sector) Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

Pakistan: National Highway Development Sector Investment Program Tranche 2

Pakistan: National Highway Development Sector Investment Program Tranche 2 Validation Report December 2017 Pakistan: National Highway Development Sector Investment Program Tranche 2 Reference Number: PVR-521 MFF Number: 0002 Project Number: 37559-023, 37559-033, and 37559-043

More information

People s Republic of China: Guangdong Energy Efficiency and Environment Improvement Investment Program, Tranche 3 and Multitranche Financing Facility

People s Republic of China: Guangdong Energy Efficiency and Environment Improvement Investment Program, Tranche 3 and Multitranche Financing Facility Completion Report Project Number: 39653-043 Loan Number: 2773 MFF Number: 0020 August 2015 People s Republic of China: Guangdong Energy Efficiency and Environment Improvement Investment Program, Tranche

More information

Tajikistan: Financial Assessment of Barki Tojik

Tajikistan: Financial Assessment of Barki Tojik Public Disclosure Authorized Tajikistan: Financial Assessment of Barki Tojik Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized October 2013 Artur Kochnakyan Ani Balabanyan

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 38196 November 2005 Proposed Loan Socialist Republic of Viet Nam: Northern Power Transmission Expansion Sector Project

More information

Periodic Financing Request Report. India: Assam Power Sector Investment Program (Tranche 2)

Periodic Financing Request Report. India: Assam Power Sector Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 47101-003 MFF Number: 0083 November 2015 India: Assam Power Sector Investment Program (Tranche 2) This document is being disclosed to the public in accordance

More information

Philippines: Third Airports Development Project (Southern Philippines)

Philippines: Third Airports Development Project (Southern Philippines) Validation Report Reference Number: PCV: PHI 2008-29 Project Number: 28270 Loan Number: 1536 August 2008 Philippines: Third Airports Development Project (Southern Philippines) Operations Evaluation Department

More information

People s Republic of Bangladesh: Updating the Road Master Plan

People s Republic of Bangladesh: Updating the Road Master Plan South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) Technical Assistance Report Project Number: 40540-016 Transaction Technical Assistance (TRTA)

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

Team Leader: Srinivasan Palle Venkata, Evaluation Specialist ( Contact:

Team Leader: Srinivasan Palle Venkata, Evaluation Specialist (  Contact: Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Paper Project

More information

Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project

Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project Completion Report Project Number: 37265 Loan Number: 2327 October 2013 Maldives: Domestic Maritime Transport Project CURRENCY EQUIVALENTS Currency Unit Rufiyaa (Rf) At Appraisal At Project Completion (1

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project PD 00001-PAK June 6, 2016 PROJECT DOCUMENT Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project This document has a restricted distribution and may be used by recipients

More information

Indonesia: Earthquake and Tsunami Emergency Support Project

Indonesia: Earthquake and Tsunami Emergency Support Project Validation Report Reference Number: PVR 237 Project Number: 39127 Grant Number: 0002-SF December 2012 Indonesia: Earthquake and Tsunami Emergency Support Project Independent Evaluation Department ABBREVIATIONS

More information

Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project

Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project Validation Report Reference Number: PVR-430 Project Number: 35183-013 Loan Number: 2285 November 2015 Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project Independent

More information

India: Supporting the Second West Bengal Development Finance Program

India: Supporting the Second West Bengal Development Finance Program Second West Bengal Development Finance Program (RRP IND 49209) Technical Assistance Report Project Number: 49209-001 Transaction Technical Assistance (TRTA) August 2017 India: Supporting the Second West

More information

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT Access to Clean Energy Investment Program (RRP PAK 49056) PROGRAM EXPENDITURE AND FINANCING ASSESSMENT A. Expenditure Framework 1. Macroeconomic context. The budget preparation and approval process is

More information

Viet Nam: Health Care in the Central Highlands Project

Viet Nam: Health Care in the Central Highlands Project Validation Report Reference Number: PVR-344 Project Number: 37115 Loan Number: 2076 (SF) October 2014 Viet Nam: Health Care in the Central Highlands Project Independent Evaluation Department ABBREVIATIONS

More information

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Technical Assistance Report Project Number: 51308-002 Transaction Technical Assistance Facility (F-TRTA) December 2017 India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Distribution

More information