Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project

Size: px
Start display at page:

Download "Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project"

Transcription

1 Completion Report Project Number: Loan Number: 2327 October 2013 Maldives: Domestic Maritime Transport Project

2 CURRENCY EQUIVALENTS Currency Unit Rufiyaa (Rf) At Appraisal At Project Completion (1 March 2007) (31 December 2010) Rf1.00 = $0.078 $0.078 $1.00 = Rf Rf ABBREVIATIONS ADB Asian Development Bank EIRR economic internal rate of return EMP environment management plan FIRR financial internal rate of return IDCB institutional development and capacity building IIC infrastructure investment component MCPI Ministry of Construction and Public Infrastructure MNH Malé North Harbor MPL Maldives Ports Limited MTC Ministry of Transport and Communication NDP national development plan PIU project implementation unit SDR special drawing rights NOTE In this report, $ refers to U.S. dollars.

3 Vice President X. Zhao, Operations 1 Director General J. Miranda, South Asia Department (SARD) Director S. Widowati, Transport and Communications Division, SARD Team leader Team member P. Chiang, Transport and Communications Division, SARD T. Prado, Transport and Communications Division, SARD In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

4 CONTENTS BASIC DATA Page i I. PROJECT DESCRIPTION 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION 1 A. Relevance of Design and Formulation 1 B. Project Outputs 2 C. Project Costs 3 D. Disbursements 4 E. Project Schedule 4 F. Implementation Arrangements 5 G. Conditions and Covenants 6 H. Consultant Recruitment and Procurement 6 I. Performance of Consultants and Contractors 7 J. Performance of the Borrower and the Executing Agency 8 K. Performance of the Asian Development Bank 9 III. EVALUATION OF PERFORMANCE 9 A. Relevance 9 B. Effectiveness in Achieving Outcome 10 C. Efficiency in Achieving Outcome and Outputs 10 D. Preliminary Assessment of Sustainability 11 E. Impact 12 IV. OVERALL ASSESSMENT AND RECOMMENDATIONS 13 A. Overall Assessment 13 B. Lessons 13 C. Recommendations 14 APPENDIXES 1. Design and Monitoring Framework Details of Project Outputs Project Cost and Financing Plan Disbursement of ADB Loan Proceeds Actual Project Implementation Schedules Chronology of Major Events Organizational Structure for Project Implementation Status of Compliance with Major Loan Covenants Summary of Contract Packages Initial Operation of the Project Reevaluation of Economic Analysis Reevaluation of Financial Analysis 42

5 i BASIC DATA A. Loan Identification 1. Country 2. Loan Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Project Completion Report Number The Republic of the Maldives Loan 2327-MLD Domestic Maritime Transport Project The Republic of the Maldives Ministry of Finance and Treasury SDR 3,544,000 ($ 5,330,000 equivalent) MLD 1416 B. Loan Data 1. Appraisal Date Started Date Completed 2. Loan Negotiations Date Started Date Completed 3. Date of Board Approval 4. Date of Loan Agreement 5. Date of Loan Effectiveness In Loan Agreement Actual Number of Extensions 6. Closing Date In Loan Agreement Actual Number of Extensions 7. Terms of Loan Interest Rate Maturity (number of years) Grace Period (number of years) 28 January February March March April August November October 2007 None 31 December December % per annum during grace period 1.5% per annum after grace period 32 years 8 years 8. Disbursements a. Dates Initial Disbursement 20 May 2008 Effective Date 23 October 2007 Final Disbursement 16 March 2012 Original Closing Date 31 December 2009 Time Interval 46 months Time Interval 26 months

6 ii b. Amount (SDR) Last Revised Allocation Amount Increased/ (Canceled) Category Original Allocation Amount Disbursed Undisbursed Balance a 1. Civil Works 2,435,000 2,435, ,411,803 23, Consulting Services 906, , ,954 77, Interest Charge 33,000 33, ,831 12, Unallocated 170, , ,000 Total SDR 3,544,000 3,544, ,261, ,412 Total $ equivalent 5,330,000 5,059,290 Source: ADB loan financial information system. a The undisbursed balance was automatically cancelled at the loan account closing. C. Project Data 1. Project Cost ($ million) Cost Appraisal Estimate Actual Foreign Exchange Cost Local Currency Cost Total Source: ADB loan financial information system. 2. Financing Plan ($ million) Cost Appraisal Estimate Actual Implementation Costs Borrower Financed ADB Financed Total Financial Charge a Borrower Financed ADB Financed Total ADB = Asian Development Bank. a Including interest during construction. Source: ADB loan financial information system. 3. Cost Breakdown by Project Component ($ million) Component Appraisal Estimate Actual 1. Base Costs A. Component 1: Infrastructure Improvement a. Dredging, reclamation, and quay walls b. Fenders, mooring bars, and bollards c. Paving works d. Land works (shed, fence, gate, guard post, crane, and lights)

7 iii e. Detailed design, bid preparation, site supervision, and project management B. Component 2: Institutional Development and Capacity Building a. Institutional development and capacity building b. Environmental impact assessment Taxes and Duties Contingencies a. Physical b. Price Financing Charges: Interest Capitalized during Construction Total ( ) Source: ADB loan financial information system. 4. Project Schedule Item Appraisal Estimate Actual Consultant for IIC component Recruitment Q Q Q Q Implementation Q Q Q Q IIC component Procurement Q Q Q Q Implementation Q Q Q Q IDCB component Recruitment Q Q Q Q Implementation Q Q Q Q IIC = infrastructure investment component, IDCB = institutional development and capacity building. Source: ADB loan financial information system. 5. Project Performance Report Ratings Ratings Implementation Period Development Objectives Implementation Progress From 30 Apr 2007 to 31 Dec 2007 Satisfactory Satisfactory From 1 Jan 2008 to 30 Jun 2008 Satisfactory Satisfactory From 1 Jul 2008 to 31 Dec 2008 Satisfactory Satisfactory From 1 Jan 2009 to 31 Jun 2009 Satisfactory Satisfactory From 1 Jul 2009 to 31 Dec 2009 Satisfactory Satisfactory From 1 Jan 2010 to 30 Jun 2012 Satisfactory Satisfactory From 1 Jul 2010 to 31 Jul 2010 Satisfactory Unsatisfactory From 1 Aug 2010 to 31 Dec 2010 Satisfactory Satisfactory

8 iv D. Data on Asian Development Bank Missions Name of Mission Date No. of Persons No. of Person- Days Specialization of Members Fact-finding Nov p, e, t (2), s, f, l Loan appraisal 28 Jan 2 Feb p, f, l, e, t, a Special loan administration Jul t, i Inception Jan t (2) i Special loan administration 5 7 Aug t (2) Review 6 9 Jul t (2), a Special loan administration Dec t Review 28 Feb 2 Mar t Review Sep t (2) Special loan administration Apr t, a Completion review Oct t, a, c a = analyst, c = consultant, e = environment specialist, f = financial specialist, i = implementation officer, l = counsel, p = private sector development specialist, s = social specialist, t = transport specialist.

9 I. PROJECT DESCRIPTION 1. The Asian Development Bank (ADB) approved a loan of SDR3,544,000 ($5.33 million equivalent) from its Special Funds resources to the Republic of the Maldives on 24 April 2007 for the Domestic Maritime Transport Project. The project s objective was to deliver sustained, equitable, and regionally balanced economic growth within the Maldives through facilitating access to markets and social services. 2. At appraisal, the project comprised (i) an infrastructure investment component (IIC), and (ii) an institutional development and capacity building (IDCB) component. 1 The IIC was to expand the existing Malé North Harbor (MNH) through (i) construction of a new quay 290 meters (m) long, projecting northward at right angles to Marine Drive alongside the boundary to Malé Commercial Harbor; (ii) ancillary civil works; (iii) provision of cargo handling equipment; (iv) construction of a temporary transit area for goods and passengers; and (v) consulting services for detailed design, preparation of tender documents, bid evaluation, construction supervision, and project management assistance. The IDCB component aimed to increase sustainability of the investment and enhance ongoing sector initiatives by providing support for (i) current efforts to align the organizational structure of the Ministry of Transport and Communication (MTC) to its sector mandate, in particular focusing on policy, planning, and regulatory functions of international and domestic maritime transport infrastructure and transport services; (ii) capacity building within MTC in the areas of (a) strategic planning and policy analysis, (b) establishment of harbor usage charges, (c) maritime safety regulations and vessel inspection and registration procedures, and (d) project performance and impact monitoring; and (iii) capacity building within the Ministry of Construction and Public Infrastructure (MCPI) to enable it to manage, operate, and maintain maritime transport infrastructure in Malé in a sustainable manner through (a) harbor management, and (b) financial management training. 3. The investment cost of the project was estimated at $6.65 million, including taxes and duties of $0.43 million. The project cost would be financed by an ADB loan of $5.33 million and government counterpart funds of $1.32 million. The executing agency was to be the Ministry of Finance and Treasury. The implementing agency was to be MTC. Project implementation units (PIUs) were to be established in MTC and MCPI, respectively, to implement the IDCB component and IIC. The project will directly benefit vessel owners, passengers (domestic and international), and cargo owners and shippers from outer atolls. The economic internal rate of return was originally estimated at 22.5%. The project was scheduled for completion before 31 December II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation 4. Malé North Harbor is the lifeline access point to the social and economic development opportunities available in the capital for 70% of the population living in outer atolls, where the incidence of poverty is highest. At appraisal, congestion in MNH was chronic, constituting a bottleneck for the poorest population to enter the capital as a result of inadequate harbor capacity and weak harbor management. Improvement of the existing harbor facilities was ranked the highest priority within the government s Seventh National Development Plan ADB Report and Recommendation of the President to the Board of Directors on a Proposed Loan to the Republic of the Maldives for the Domestic Maritime Transport Project. Manila.

10 (7th NDP). 2 Constructing an additional quay and associated facilities would alleviate congestion at the harbor and on the feeder road. Together with the IDCB component, the infrastructure investment would enhance sustainability and increase MNH s operational efficiency. 5. ADB shared the government s view on MNH s importance within the country s socioeconomic context. 3 Therefore, assistance to improve the country s main inter-atoll transport hub became a priority investment project. This was also included in ADB s country strategy and program update. ADB supported the government s long-term sector objectives of (i) separating maritime transport sector policy, planning, and regulatory functions from operational activities; (ii) realigning MTC to materialize the changes; and (iii) introducing efficiency and sustainability into public sector provision of domestic maritime transport infrastructure, as outlined in the 7th NDP. The project was designed to address both investment and institutional aspects in the transport sector. Availability of skilled and experienced staff for project implementation and monitoring was identified as a major constraint which was to be mitigated through the deployment of consulting services for the IIC and capacity building in the IDCB component. 6. At both appraisal and completion, the project was deemed relevant 4 to the government s objectives and policies, as well as to ADB s country strategy. Upon completion, a new quay of 268 m was constructed to enhance the existing MNH. The required ancillary facilities and cargo handling equipment were also installed at the new quay. The project was supported with substantial consulting services, including those for the IIC and IDCB. Despite its slightly longer implementation period, the project successfully achieved its objectives at appraisal. The outputs and outcomes of the project meet the government s development objectives and ADB s country strategy. The design and monitoring framework of the project with results is in Appendix 1. B. Project Outputs 1. Infrastructure Investment Component 7. During implementation, it was found that the original budget was insufficient to implement the full length of the proposed quay wall. As such, there was a minor revision to build a quay wall 268 m long, rather than 290 m long. The IIC entailed (i) dredging of the harbor basin to a mean sea level of 4.0 m deep and reclamation of 26,500 cubic meters; (ii) construction of additional drive-on access and cargo handling area of 6,500 square meters paved with interlocking concrete blocks; (iii) provision of such ancillary harbor facilities as mooring bollards, fenders, gates, fencing, guard posts, and lighting system; (iv) a covered shelter of 480 square meters to protect passengers and cargos, as well as for a management office and guard room; and (v) utility works such as electricity, water supply, drainage, and sewer lines. Project outputs are detailed in Appendix 2. The IIC was completed by 31 December 2010, the extended loan closing date. No serious quality problem was reported during the defects liability period. 5 The project completion review mission found that the new infrastructure was constructed in good quality and is currently in operation. 2 The 7th NDP, endorsed by the ministers in the Cabinet, covers the period ADB Country Strategy and Program Updates ( ): Maldives. Manila 4 The rating is determined based on ADB Guidelines for Preparing Performance Evaluation Reports for Public Sector Operations. Manila. 5 One year after physical completion of the civil work.

11 3 2. Institutional Development and Capacity Building Component 8. The IDCB was focused on (i) institutional alignment of MTC s maritime transport activities with its sector mandate; (ii) capacity building in MTC to effectively plan and regulate the maritime transport sector; and (iii) capacity building in MCPI, especially for harbor management and financial management training. 9. The key recommendation of the IDCB was to set up a Maldives Ports and Maritime Authority to separate planning, policy, and regulatory functions from operational functions. The authority is currently being implemented. As part of improving capacity to better regulate the maritime sector, a new harbor usage charge was also developed and introduced successfully. 10. It had been envisioned during appraisal that MCPI would take over and operate the new harbor facilities. Due to internal restructuring, however, the government decided to hand over management and operation of the new facilities to Maldives Ports Limited (MPL) rather than MCPI. Since MPL already owned and operated the commercial port activities at the commercial harbor adjacent to MNH, the training and financial management component under the IDCB was no longer relevant. Consequently, this was removed from the original scope of the IDCB. C. Project Costs 11. At appraisal, the total project cost, including IIC and IDCB, was estimated at $6.65 million. This included the base cost, tax, contingency, and financial charge. Upon completion, the actual project cost totaled $6.14 million, or about 7.7% less than estimated. 12. The actual cost for the IIC was about 23% higher than originally estimated. This was mainly due to increase in scope and price inflation, since the costs were estimated in 2002 but procurement was during Nevertheless, the additional costs could be fully covered by contingencies. 7 At the same time, the actual cost for the IDCB component was diminished from $0.69 million to $0.65 million due to the reduction in scope. Hence, the actual cost at completion turned out to be only slightly (7.7%) lower than originally estimated. Appendix 3 compares the details of the project costs at appraisal and at completion. 13. The project was financed by the ADB loan of $5.33 million (80.2% of total project cost) and the government s counterpart funds of $1.32 million (19.8% or total). The ADB loan came from ADB s Special Funds resources with a 32-year term (including a grace period of 8 years) and annual interest rate of 1.0% during the grace period and 1.5% thereafter. The interest charges were capitalized. Under the loan, ADB was to finance 80% of civil works and 100% of consultancy services for both the IIC and IDCB. The government was to provide counterpart funding for the remaining 20% of civil works costs. During implementation, however, the cost of the civil works component increased, while the cost of consulting services decreased. To maximize use of the loan, ADB s financing portion for civil works was raised. Overall, ADB s financing portion rose from 80% to 82.3% and the government s counterpart financing share declined from 20% to 17.7%. Detailed comparison of the financing plan at appraisal and actual is in Appendix 3. 6 During implementation, it was found that additional scope was required for demolition of existing structures and constructing additional facilities (including a management office with guard room). 7 In Maldives, the average consumer price index was 4.15% per annum during

12 4 D. Disbursements 14. The ADB loan was approved on 24 April 2007, signed on 29 August 2007, and became effective on 23 October Initial disbursement of the ADB loan was slow, mainly due to start-up delays in procuring civil works. Moreover, a lengthy withdrawal application process was used initially and involved several agencies. This was resolved during a review mission, whereby the process was streamlined and shortened to involve only key agencies. To enable completion of the project, the government requested, and ADB approved in December 2009, an extension of the loan closing date by 12 months from original 31 December 2009 to 31 December The ADB loan closed on 31 December 2010, by which time the IIC was completed. The loan account was kept open to facilitate loan disbursement beyond the loan closing. In 2011, the total loan disbursement was $1.97 million (38.6% of the total loan amount). After resolving some disputes between the government and the IDCB consultants regarding the reduction of scope in the IDCB, the final disbursement of $79, was made on 16 March 2012, at which time the ADB loan account was closed. Overall, SDR3,261, ($5,059, equivalent) was disbursed. The undisbursed amount of SDR282, was automatically cancelled. Appendix 4 shows the projected and actual disbursements of the loan proceeds. E. Project Schedule 1. Infrastructure Investment Component (IIC) 16. Although advanced actions were taken to engage consulting services for the IIC in December 2006, the recruitment took longer than expected. The IIC consultants contract was awarded in November 2007, which was about 5 months behind the original schedule. The consultants made rapid progress to undertake detailed design and produced the bidding documents ready for tender of the IIC works by March During the first bidding exercise, the bids opened in August 2008 were substantially higher than the original budget. To fit the budget, the government made a minor revision by reducing the length of the quay wall. The retender was issued in May The contract for IIC works was awarded in October 2009, and mobilized in November The construction works were completed by December The construction took 2 months longer than estimated at appraisal, which resulted in a 12-month delay in project completion. To enable project completion, ADB extended the loan from 31 December 2009 to 31 December The consulting service for the IIC was completed at the same time, with extensions approved by ADB. 2. Institutional Development and Capacity Building Component 18. Similarly to the case for the IIC, advanced actions were taken to engage the IDCB consultants in December The first round of selection was not successful, however, since none of the submitted bids met the minimum qualifications stated in the terms of reference. Moreover, the bidders also lacked familiarity with local conditions. The second round of selection that was re-advertised in October 2007 was successful, and the IDCB consultants contract was awarded on 7 August 2008 and mobilized on 17 September Since the IDCB was initially designed to develop capacity within MCPI to undertake operational responsibilities for the new harbor infrastructure, the operational training component

13 5 was postponed by the delays in constructing the new harbor. Moreover, the government underwent major restructuring during project implementation and there were delays due to the time taken by the government to decide on the appropriate agency to operate and manage the new harbor. The government eventually decided to hand over this responsibility to MPL. Since MPL was already managing existing ports, the financial management and training components in the IDCB were no longer required and accordingly were removed from the IDCB scope. 20. Although the consultant made requests to extend the contract expiry date beyond the original expiry date of 30 November 2010 to complete the outstanding tasks, the government did not approve these, as it was felt that the remaining tasks were no longer required and should be removed from the original scope. This resulted in some disputes between the government and the IDCB consultants regarding the final payment. Eventually, this was resolved successfully by mutual agreement for partial payment to the consultant, and the contract was concluded on 31 December The actual project implementation schedule is in Appendix 5 and a chronology of major events is in Appendix Overall, it is assessed that the IIC constituted the project s critical path. The main contributor to delay in project completion was the delay in procuring the civil works. F. Implementation Arrangements 22. At appraisal, the Ministry of Finance and Treasury was identified as the executing agency and MTC as the implementing agency. During implementation, a project implementation unit (PIU) was established within MTC for the IDCB component and another PIU was established within MCPI for the IIC. Due to restructuring of the government after the presidential election in November 2008, key persons responsible for implementing and administering the transport project were reappointed. MTC and MCPI were merged with other ministries and formed a new ministry the Ministry of Housing, Transport and Environment. Consequently, the two PIUs merged. 23. A project steering committee was established during project preparation. This was chaired by MTC and included representatives at director level from the Ministry of Finance and Treasury; MCPI; Ministry of Environment, Energy, and Water; Ministry of Planning and National Development; Ministry of Housing and Urban Development; and Malé Municipality. The project steering committee held regular meetings and provided overall policy and operational advice and guidance to project implementation. 24. The PIU was further supported by the IIC consultants, who were organized into two sub-teams the design and supervision group and the project management assistance group. The project management group assisted the PIU in many aspects, including to prepare work schedules, monitor progress, check tender documents and drawings, review construction costs and payments, assist with procurement and contract management, coordinate meetings, prepare monthly reports, and carry out environmental monitoring. The design and supervision group focused on the engineering design and construction quality control. Given the successful completion of the civil works, this arrangement proved to be effective. 25. The IDCB consultants also supported the PIU to facilitate efficient loan administration and implementation. The organizational structure for project implementation is in Appendix 7.

14 6 G. Conditions and Covenants 26. The project implementation mostly complied with most of the loan conditions and covenants, including institutional arrangement, counterpart fund provision, financial and contract management, environmental and social safeguard, report preparation and submission, and initial operation arrangement. As part of enhancing governance, the IIC consultants successfully provided support to the PIU on procurement and project management. A separate financial account was established for the project, an external editor was recruited to audit the financial statements, and audited project accounts were submitted up to There were delays encountered in the submission of financial statements, mainly due to shortage of experienced staff. Nevertheless, the establishment of the financial audit system itself presents a significant improvement toward enhancing governance. In terms of monitoring, the project performance monitoring system for socioeconomic impact was not implemented as planned. This has caused some difficulties in monitoring the performance of the project. Nevertheless, some of this impact is mitigated as MPL collects some of the required data as part of its operations. The status of compliance with key loan covenants of the project is summarized in Appendix 8. H. Consultant Recruitment and Procurement 27. At appraisal, two consulting services packages and one civil works package were designed. During implementation, both consultancy services packages were recruited in compliance with ADB s Guidelines on the Use of Consultants (2006, as amended from time to time). These packages are summarized in Appendix 9. At appraisal, the government requested ADB s assistance for undertaking advance actions necessary to facilitate the consultant recruitment, which was approved by ADB. The consulting services were advertised on ADB s Business Opportunities website on 19 December 2006, and the expressions of interest were requested by 15 February 2007 for the IIC consultants and by 15 March 2007 for the IDCB consultant. For the IIC consultants, quality- and cost-based selection on biodata proposals was used. Following ADB s approval of the short list and evaluation criteria, the request for proposals was issued on 23 March 2007 with a submission date of 14 April The evaluation result of the technical proposals was approved by ADB on a no-objection basis on 14 May 2007, and the subsequent opening and evaluation of financial proposals led to the conclusion that Japan Port Consultants was the only eligible firm. 8 On 14 June 2007, ADB advised the government to proceed with inviting the firm for contract negotiations and reminded the government that the consultant should not be mobilized prior to the loan effectiveness. On this basis, the government proceeded with inviting Japan Port Consultants for contract negotiation and requested ADB s participation as an observer. The contract between the government and the IIC consultants was signed on 15 November Quality- and cost-based selection was also used for recruiting the IDCB consultants, and simplified technical proposals were required. ADB approved the short list and evaluation criteria for the IDCB consultants on 19 April The request for proposals was issued on 26 April 2007, but the technical evaluation concluded on 18 July 2007 that none of the firms were qualified. Following discussions with the government, the IDCB component was re-advertised. This time, a consortium of firms was selected. 9 Contract negotiations on the consulting services were held in Malé on 5 August 2008, and the contract was signed on 7 August Japan Port Consultants, Tokyo, Japan. 9 SMEC International Pty Ltd (Australia), in association with GreenTech Consultants Pvt. Ltd (Sri Lanka) and Commerce, Development and Environment Pvt. Ltd (Maldives).

15 7 29. The civil works for the IIC, comprising just one contract of $3.89 million, was procured using international competitive bidding and the single-stage, one-envelope procurement method. Following the bid opening on 7 August 2008, however, it was found that the bidding price was substantially higher than budgeted. The government reduced and revised the scope of the project, and reissued the retender documents on May The bids of the retenders were opened and evaluated on 9 July This time a domestic firm was successfully selected, and the civil works contract was signed on 27 October Overall, the procurement for civil works was compliant with ADB s Procurement Guidelines (2007, as amended from time to time). I. Performance of Consultants and Contractors 1. IIC Consultants 30. The performance of the IIC consultants was highly satisfactory. As anticipated at appraisal and as specified in the terms of reference, the IIC consultants successfully completed (i) detailed design, (ii) preparation of tender documents, (iii) bid evaluation support, (iv) construction supervision, (v) project management assistance to the government, and (vi) environment monitoring. Due to delay in the civil works procurement and implementation, however, the contract for the IIC consultants was extended several times upon requests from the government. The IIC consultants completed their services on 31 December 2010 with total inputs of person-months that included person-months for international consultants and person-months for domestic consultants. Upon completion, two reports were submitted by the consultant, including the main completion report and an environmental monitoring report. 10 The main report was comprehensive, covering the necessary aspects of the project implementation, including major activities, implementation schedule, institutional framework, and project cost. The environmental reports included the results of the environmental monitoring survey and assessed the environmental impacts. These reports were comprehensive and sufficiently addressed all environmental issues. 2. IDCB Consultants 31. The performance of the IDCB consultants was partly satisfactory. The IDCB component consisted of three subcomponents: (i) institutional alignment of MTC s maritime transport activities with its sector mandate, particularly focusing on policy, planning, and regulatory functions of international and domestic maritime transport infrastructure and domestic maritime transport services; (ii) capacity building in MTC in the areas of (a) strategic planning and policy analysis, (b) establishment of harbor usage charges, (c) maritime safety regulations and vessel inspections and registration procedures, and (d) project performance and impact monitoring; and (iii) capacity building in MCPI, especially on harbor management and financial management training. The contract was time-based, with a total ceiling of $764,992 and subceilings for each of 18 milestones. Most of the components were implemented successfully except for capacity building of MCPI due to restructuring of responsibilities within the government. The project performance and impact monitoring system was also not implemented. 32. Capacity building of MCPI. Although, the contract was implemented smoothly at first, there were challenges toward the end. Since the construction was delayed, some of the milestones could not be completed by the consultant before the contract expiry date of JPC Completion Report Domestic Maritime Transport Project (Consulting Services for Infrastructure Investment Component); JPC Environmental Monitoring Report (July to December 2010) Domestic Maritime Transport Project (ADB Loan Agreement No MLD).

16 8 November Moreover, the government decided that MPL would operate the new facilities, rather than MCPI as originally envisaged during appraisal. Since MPL was already an experienced operator of existing commercial ports, the government decided not to extend the contract and to cancel the contract milestones relating to harbor management and financial training of the port operator. Thereafter, the consultant submitted a set of invoices on 31 March 2011, requesting payment for preparatory works that had already been undertaken for the cancelled milestones. The implementing agency, upon review of the invoices, requested the consultant to submit proof of the physical work carried out. There were some disputes on the final payment. As requested, the consultant submitted a revised draft final report in December After reviewing the draft reports prepared by the consultant, the government issued a letter to inform the consultant that the contract was concluded on 31 December 2010 and the disputed issue was settled with partial payment. The project completion review mission confirmed that there were no outstanding payment issues. 33. Project performance and impact monitoring. Although a project performance monitoring system was proposed at appraisal, the necessary surveys and monitoring activities were not implemented during the project. 3. IIC Contractor 34. Overall, the performance of the IIC contractor was satisfactory. A domestic construction company was engaged to undertake the civil works. There was some initial delay in physical progress. This was caused by difficulties in transporting construction materials to the project site, which continued to operate as a harbor during construction. This necessitated contract extension for both the IIC consultants and the contractors. An ADB mission in September 2010 also found that the construction progress was far behind of schedule due to the lengthy withdrawal application process that was used. To expedite matters, the ADB mission and the government took necessary actions to streamline and shorten the withdrawal application process. Thereafter, the disbursements accelerated considerably and the infrastructure component was substantially completed by 31 December The completion certificate was also issued on 31 December 2010, and the final inspection of the project site was conducted by the client and the IIC consultants team on 6 February J. Performance of the Borrower and the Executing Agency 35. The performance of the borrower and the executing agency was satisfactory. The borrower is the Republic of the Maldives and the executing agency is the Ministry of Finance and Treasury. MTC was designated as the implementation agency. During implementation, a project steering committee was established to provide substantial guidance and coordination support to the project. The government provided counterpart funds and all necessary support in a timely manner. The PIU was responsible for day-to-day project management and facilitated the project s successful completion. The PIU was well staffed and responsible. Staff members worked in a collaborative manner with ADB, consultants, and contractors to resolve implementation challenges. With assistance from the IIC consultants, the PIU was able to prepare all the project progress reports. An external auditor was recruited to audit the project s financial statements. 12 The audited report for 2008 was submitted to ADB a year late, however, and this resulted in the Project Performance Report Rating being at risk. 11 SMEC Draft Final Report Domestic Maritime Transport Project Institutional Development and Capacity Building (ADB Loan 2327-MLD). 12 The financial accounts were audited by AH&ASSOCIATES, Maldives.

17 9 K. Performance of the Asian Development Bank 36. Overall, the performance of ADB was satisfactory. The project was administered and supervised from ADB headquarters. ADB provided substantial guidance and support to the government and the PIU in all aspects of project implementation, such as approving advance actions, preparing documents and evaluation reports related to procurement, engaging consultants and contractor, and commenting on technical issues. ADB maintained close engagement with the implementing agency during project implementation. Eight project review missions were conducted, during which ADB participated in joint coordination and review meetings together with the Ministry of Finance and Treasury, the implementing agency, and the contractor and consultants. ADB was closely involved in monitoring progress. It identified project issues especially time-critical issues and worked with the government to resolve these. The loan closing date was extended once to accommodate the revised project schedule. The role of the ADB missions in advising on contract administration and technical issues was also recognized by the government. III. EVALUATION OF PERFORMANCE A. Relevance 37. At appraisal and completion, the project was rated relevant and consistent with the government s development strategy and ADB s country partnership strategy. Given its geographic and physical characteristics, maritime transport is the country s lifeline. The MNH project was and remains crucial to enhancing distribution of essential supplies and accessibility from the capital city of Malé to the other atolls for the majority of the population. The outputs and outcomes have proven that the project is important, timely, and effective in enhancing domestic maritime transport sector development in the Maldives and promoting economic development. 38. The project is a continuation of ADB s efforts to support the government s development plans. The 7th NDP outlines a development path based on economic growth, social equity, poverty reduction, environmental protection, and good governance. It provides a policy framework for realizing the long-term goals of the President s Vision The plan, which continues the strategies and lessons from implementing the Sixth National Development Plan, focuses on creating equitable opportunities and more fairly distributing income and wealth. 39. Recognizing the paramount importance of the maritime transport sector in ensuring population-wide access to social and economic development opportunities, the 7th NDP includes 12 policies with supporting sub-strategies in the form of a combined land and sea transport roadmap. Considering the lifeline characteristics of MNH in enhancing access for the majority of the population living in the outer atolls, where the incidence of poverty is higher, the project has been considered a high priority investment within that roadmap. 40. In terms of institutional capacity, and in line with the 7th NDP objectives of improving the overall management and efficiency of the transport sector, the project also identified the need to separate maritime regulatory functions from operational functions. The recommendation to establish a Maldives Ports and Maritime Authority is currently being implemented. The project was also particularly successful in developing and successfully implementing harbor usage charges at MNH. This promotes better financial and operational sustainability over the long-term, and it fits with the 7th NDP objective to enhance harbor management capacity at Malé.

18 10 B. Effectiveness in Achieving Outcome 41. The project is rated highly effective in achieving its outcome. At appraisal, MNH, served as the gateway to the capital for the outer atoll population and for inter-atoll passenger and cargo vessels. It had a quay wall of just 200 m. The harbor area had no infrastructure to support loading and unloading, and its operational efficiency was hindered by lack of harbor management. The insufficient capacity resulted in long vessel waiting times, severe congestion, and, consequently, economic losses for vessel owners. The combination of the aforementioned factors essentially increased transport costs for passenger movement and cargo distribution to and from Malé, thereby limiting access to social and economic development opportunities. 42. The project successfully delivered a new quay 268 m long that has drive-on access, a cargo handling area, ancillary facilities, and utilities. Upon completion, MNH s operation was handed over to MPL, which has been operating the adjacent Malé Commercial Port for many years. Hence, MPL already possessed the capacity needed to operate the new facilities in terms of management, staffing, funding, and maintenance. Since taking over the new facilities, MPL has implemented various traffic management measures which have been effective in ensuring smooth operations on both the road side and harbor side. 43. Before the physical improvements at MNH, the average turnaround time for vessels was 3.99 days. According to MPL, after the new facilities were opened, the turnaround times for the vessels was reduced to 2.41 days in 2011 and 2.59 days in This was estimated based on the 2,521 vessel arrivals at MNH during 2011 (May to December) and 3,502 vessel arrivals during 2012 (January to October). The drive-on access and cargo handling area have substantially improved the efficiency in loading and unloading cargo. This drive-on access area has been well utilized, being used on average by about 473 vehicles daily. The operation of the new quay and improvement of the harbor facilities have well facilitated the rapidly growing traffic. Reduced waiting and handling times have brought significant economic benefits to the Maldives. Meanwhile, the project is also generating increased revenue through new harbor usage charges that were developed under the IDCB component. This, too, has supported more efficient harbor operations while at the same time contributing to recovery of the investment costs. Appendix 10 provides a summary of the project s initial operation. 44. The key recommendations under the IDCB component have been implemented. For example, the proposed creation of the Maldives Ports and Maritime Authority (in order to separate regulatory and operational functions) is currently being implemented; a harbor usage charging system has been introduced at the new facilities (see Appendix 10); and the review of maritime safety regulations has been completed. Although the project performance monitoring system was not implemented, this did not impact on project outcome since MPL already had an existing system that collects information similar to that required by the performance monitoring system for the new facilities. C. Efficiency in Achieving Outcome and Outputs 45. Overall, despite the year-long delay in project completion, the project is still rated efficient in consideration of its robust economic benefits and generation of additional revenues from the introduction of harbor usage charges. 46. The economic reevaluation compared the economic costs and benefits for the withproject and without-project cases. Economic benefits considered in the reevaluation include (i) passenger time cost savings, (ii) vessel turnaround time cost savings, and (iii) vehicle

19 11 congestion cost savings. The economic internal rate of return (EIRR) was recalculated on the basis of 23 years ( ), including 3 years of construction and 20 years of operation. The EIRR was recalculated at 29.1%. Since the recalculated EIRR is above the ADB-recommended hurdle rate of 12%, the project is considered economically viable. Compared with 22.5% at appraisal, the higher EIRR is mainly attributed to higher traffic than estimated at appraisal (about double). The EIRR was subjected to sensitivity analysis to test different scenarios. The project was found to be economically viable for all scenarios. In the worst case, combining both a 30% operation and maintenance cost increase and 30% benefit reduction, the EIRR was 22.1%- which is still higher than the 12% hurdle rate. A summary of the economic reevaluation is in Appendix The financial internal rate of return (FIRR) was recalculated using a methodology similar to that at appraisal but based on actual costs and revenues. The actual costs have been higher than at appraisal primarily because the actual infrastructure cost was 23% more than originally estimated. On the revenues side, the actual harbor usage charges implemented are about 80% 90% lower than originally envisaged. As a result the actual FIRR is estimated as 2.18%. An FIRR equivalent to the weighted average cost of capital of 1.36% could be obtained by about a one-third increase in revenues. This could be realistically achieved by boosting the port s operating efficiency and gradually raising the harbor usage charges. The latter might be more challenging in the short term due to political pressures to keep the usage charges low. D. Preliminary Assessment of Sustainability 48. Overall, the sustainability of the project is rated likely. 49. Harbor s operational efficiency. Since its opening, the new facilities have been well utilized, especially during peak periods. MNH is now able to accommodate 35 vessels at a time, and there are 203 vessels currently registered to use MNH. MPL expects the vessel arrivals to grow by at least 5% annually. Therefore, an efficient harbor management system needs to be maintained to maximize operational efficiency. 50. Domestic maritime sector development. The provision of additional capacity for berthing and loading and unloading has alleviated the congestion on both the harbor and on the land side. Nevertheless, since MNH is the gateway to the capital for the outer atoll population and is also currently used for inter-atoll passenger-cum-cargo vessels, demand is expected to increase rapidly in the longer term. There is potential scope for improving the efficiency of domestic passenger and cargo distribution at MNH, possibly by segregating cargo and passenger movements in the longer term. 51. Institutional strengthening and capacity building. The key components of the IDCB are being implemented. The separation of regulatory and operational functions through introducing the Maldives Ports and Maritime Authority is being implemented. Harbor usage charges have been successfully introduced, and this has improved both financial sustainability and efficiency of the operations. The change in implementation arrangement to hand over the new facilities to MPL rather than MCPI is more beneficial than the original arrangement, since MPL already has the capacity to manage and operate the new infrastructure. 52. Harbor infrastructure maintenance. The physical improvements were delivered in high quality. The financial reevaluation also demonstrates that the revenues from harbor operations would be sufficient to cover routine maintenance of the new facilities, as well as longer-term periodic maintenance (for wear-and-tear).

20 Financial cost recovery. Although MNH operated at a loss in 2011, its financial status turned modestly profitable in 2012 due to build-up of vessel demand. This should improve, as traffic is anticipated to increase. To capture this growth, MNH should continuously enhance port operational efficiency to manage additional demand. MPL recognizes that the actual tariffs are much lower than envisaged during appraisal. Although there are no firm plans to increase tariffs immediately, the financial position of port operations could be improved by increasing revenues from efficiency improvements as well as gradual increase in usage charges. To further boost revenues, MPL is planning to rent part of the spare capacity in the passenger facilities for retail shops. E. Impact 1. Environmental Safeguards 54. At appraisal, the project was classified as category B according to ADB s Environmental Assessment Guidelines (2003). In compliance with the Environmental Protection and Preservation Act, 1993, an initial environmental examination report was prepared during project preparation. Provisions were made in the project cost to cover environmental mitigation and monitoring. The initial environmental examination also provided a framework for developing the environmental management plan. The framework included a rolling action plan with periodic monitoring and appropriate budget allocations. The IIC contractors prepared and submitted the environmental management plan in accordance with the initial environmental examination. 55. All impacts identified in the initial environmental examination were addressed during implementation. The IIC contractor executed the environmental measures in the environmental management plan. The key measures included (i) installing a temporary steel sheet pile wall to prevent water-quality impacts; (ii) installing a silt curtain to protect the water quality of the basin; (iii) selecting proper equipment to minimize noise impact on the surrounding area; and (iv) adjusting the timing for transporting construction materials to mitigate additional congestion around the adjacent commercial market. The contractor also conducted regular environmental monitoring in relation to water quality, waste treatment, oil spillage, noise levels, and air pollution at the project site. The IIC consultants supervised the implementation of such surveys and monitoring. The IIC consultants final report confirmed that the project caused no significant environmental impacts, and the environmental conditions were generally maintained within original conditions Land Acquisition and Social Safeguards 56. During project preparation, it was identified that all land required for the project was owned by the government, no additional land would need to be acquired from private landowners, and no resettlement would be involved. During implementation, the executing agency confirmed that no significant changes occurred from the project design. 3. Socioeconomic Impact 57. At appraisal, the social impact analysis (including a poverty analysis) indicated that the project influence area would be nationwide and approximately 70% of the population (about 209,189 people) residing in outer atolls would benefit from enhanced domestic connectivity with 13 JPC Environmental Monitoring Report (July to December 2010), Domestic Maritime Transport Project (ADB Loan 2327-MLD.

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

Independent State of Samoa: Port Development Project

Independent State of Samoa: Port Development Project Project Design Advance Project Number: 47358-003 April 2018 Independent State of Samoa: Port Development Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project Validation Report Reference Number: PVR-360 Project Number: 40198 Loan Number: 2374 December 2014* Viet Nam: Ho Chi Minh CityLong ThanhDauGiay Expressway Technical Assistance Project Independent Evaluation

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Bangladesh: Chittagong Port Trade Facilitation Project

Bangladesh: Chittagong Port Trade Facilitation Project Completion Report Project Number: 36105 Loan Number: 2147 June 2014 Bangladesh: Chittagong Port Trade Facilitation Project This document is being disclosed to the public in accordance with ADB s Public

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Validation Report Reference Number: PCV: PHI 2011-15 Project Number: 35379 Loan Number: 2012 July 2011 Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Independent

More information

Philippines: Mindanao Basic Urban Services Sector Project

Philippines: Mindanao Basic Urban Services Sector Project Validation Report Reference Number: PCV: PHI 2011-25 Project Number: 30551 Loan Number: 1843 September 2011 Philippines: Mindanao Basic Urban Services Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Maldives: Information Technology Development Project

Maldives: Information Technology Development Project Validation Report Reference Number: PVR-272 Project Number: 34276 Loan Number: 1882 December 2013 Maldives: Information Technology Development Project Independent Evaluation Department ABBREVIATIONS ADB

More information

Tuvalu: Outer Island Maritime Infrastructure Project

Tuvalu: Outer Island Maritime Infrastructure Project Project Design Advance Project Number: 48484-003 November 2015 Tuvalu: Outer Island Maritime Infrastructure Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

Maldives: Enhancing Tax Administration Capacity

Maldives: Enhancing Tax Administration Capacity Completion Report Project Number: 47150-001 Technical Assistance Number: 8525 August 2018 Maldives: Enhancing Tax Administration Capacity This document is being disclosed to the public in accordance with

More information

Philippines: Philippine Energy Efficiency Project

Philippines: Philippine Energy Efficiency Project Validation Report Reference Number: PVR-436 Project Number: 42001-013 Loan/Grant Numbers: 2507 and 0142 December 2015 Philippines: Philippine Energy Efficiency Project Independent Evaluation Department

More information

Mongolia: Regional Road Development Project

Mongolia: Regional Road Development Project Validation Report Reference Number: PVR-481 Project Numbers: 35377-013 and 35377-023 Loan/Grant Numbers: 2087, 2621, and 0199 December 2016 Mongolia: Regional Road Development Project Independent Evaluation

More information

People s Republic of Bangladesh: Updating the Road Master Plan

People s Republic of Bangladesh: Updating the Road Master Plan South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) Technical Assistance Report Project Number: 40540-016 Transaction Technical Assistance (TRTA)

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project Completion Report Project Number: 27250 Loan Number: 1472 August 2006 Philippines: Small Towns Water Supply Sector Project CURRENCY EQUIVALENTS Currency Unit Philippine peso (P) At Appraisal At Project

More information

Georgia: Emergency Assistance for Post-Conflict Recovery

Georgia: Emergency Assistance for Post-Conflict Recovery Validation Report Reference Number: PCV: GEO 2011-49 Project Number: 32023 Loan Number: 2469-GEO(SF) December 2011 Georgia: Emergency Assistance for Post-Conflict Recovery Independent Evaluation Department

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

India: Karnataka Urban Development and Coastal Environmental Management Project

India: Karnataka Urban Development and Coastal Environmental Management Project Validation Report Reference Number: PVR-334 Project Number: 30303 Loan Number: 1704 November 2014 India: Karnataka Urban Development and Coastal Environmental Management Project Independent Evaluation

More information

Institutional Strengthening for Aviation Regulation

Institutional Strengthening for Aviation Regulation Technical Assistance Report Project Number: 43429 Regional capacity development technical assistance (R-CDTA) December 2010 Institutional Strengthening for Aviation Regulation The views expressed herein

More information

Pakistan: Decentralization Support Program

Pakistan: Decentralization Support Program Validation Report Reference Number: PCV: PAK 2011-53 Program Number: 34328 Loan Numbers: 1935/1936/1937/1938 December 2011 Pakistan: Decentralization Support Program Independent Evaluation Department ABBREVIATIONS

More information

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department Validation Report Reference Number: PVR-307 Project Number: 36320 Loan Number: 2018 May 2014 India: Rural Roads Sector I Project Independent Evaluation Department ABBREVIATIONS ADB Asian Development Bank

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) by a loan agreement of even date herewith

More information

Afghanistan: Regional Airports Rehabilitation Project (Phase 1)

Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Validation Report Reference Number: PVR 225 Project Number: 37136 Loan Number: 2105 December 2012 Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Independent Evaluation Department ABBREVIATIONS

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

Validation Report. Sri Lanka: Colombo Port Efficiency and Expansion Project. Independent Evaluation Department

Validation Report. Sri Lanka: Colombo Port Efficiency and Expansion Project. Independent Evaluation Department Validation Report Reference Number: PVR-474 Project Number: 33019-013 Loan Number: 1841 December 2016 Sri Lanka: Colombo Port Efficiency and Expansion Project Independent Evaluation Department ABBREVIATIONS

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan Republic of the Maldives: Domestic Maritime Transport Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan Republic of the Maldives: Domestic Maritime Transport Project Report and Recommendation of the President to the Board of Directors Project Number: 37265 March 2007 Proposed Loan Republic of the Maldives: Domestic Maritime Transport Project CURRENCY EQUIVALENTS (as

More information

People's Republic of China: Ganzhou Longyan Railway Project

People's Republic of China: Ganzhou Longyan Railway Project Validation Report Reference Number: PCV: PRC 2009-22 Project Number: 33442 Loan Number: 1850 December 2009 People's Republic of China: Ganzhou Longyan Railway Project Independent Evaluation Department

More information

Bangladesh: Road Network Improvement and Maintenance Project II

Bangladesh: Road Network Improvement and Maintenance Project II Validation Report Reference Number: PVR-435 Project Number: 34415 Loan Number: 2021 November 2015 Bangladesh: Road Network Improvement and Maintenance Project II Independent Evaluation Department ABBREVIATIONS

More information

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH LOAN NUMBER 2499-PAK (SF) PROJECT AGREEMENT (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK and PROVINCE OF SINDH NORTH SINDH URBAN SERVICES CORPORATION LIMITED DATED

More information

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project Technical Assistance Report Project Number: 51107-001 Transaction Technical Assistance (TRTA) October 2017 Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project This

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:ETM 34402 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO EAST TIMOR FOR TRANSPORT SECTOR IMPROVEMENT October 2001 ABBREVIATIONS ADB Asian Development Bank ETTA

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department Validation Report Reference Number: PVR-451 Project Number: 38254-033 Loan Number: 2312 August 2016 India: North Karnataka Urban Sector Investment Program, Tranche 1 Independent Evaluation Department ABBREVIATIONS

More information

Project Completion Report

Project Completion Report Project Completion Report Project Number: 38074-013 Loan Number: 2208-UZB December 2011 Uzbekistan: Kashkadarya and Navoi Rural Water Supply and Sanitation Sector Project CURRENCY EQUIVALENTS Currency

More information

FINANCIAL MANAGEMENT ASSESSMENT

FINANCIAL MANAGEMENT ASSESSMENT Greater Malé Environmental Improvement and Waste Management Project (RRP MLD 51077) EXECUTIVE SUMMARY FINANCIAL MANAGEMENT ASSESSMENT 1. The financial management assessment (FMA) was conducted for the

More information

ASIAN DEVELOPMENT BANK TAR: MLD 30026

ASIAN DEVELOPMENT BANK TAR: MLD 30026 ASIAN DEVELOPMENT BANK TAR: MLD 30026 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO THE REPUBLIC OF MALDIVES FOR PRIVATE SECTOR PARTICIPATION IN THE MALDIVES' PORTS November 1998 CURRENCY

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Unit Europe and Central Asia Region Document of The World Bank RESTRUCTURING

More information

Bangladesh: Road Maintenance and Improvement Project

Bangladesh: Road Maintenance and Improvement Project Performance Evaluation Report Bangladesh: Road Maintenance and Improvement Project Independent Evaluation Performance Evaluation Report December 2014 Bangladesh: Road Maintenance and Improvement Project

More information

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project Completion Report Project Number: 35087 Loan Number: 2119/2120 December 2011 Azerbaijan: Urban Water Supply and Sanitation Project CURRENCY EQUIVALENTS Currency Unit Azerbaijan manat (AZN) At Appraisal

More information

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1 PERIODIC FINANCING REQUEST Date: April 2012 To: Asian Development Bank 6 ADB Avenue Mandaluyong City, Metro Manila ATTENTION: Director General, Pacific Department Fax No. +632-632-6318 Sir: RE: Higher

More information

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project f Validation Report Reference Number: PVR-370 Project Number: 29041 Loan Number: 1947 December 2014 Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project Independent Evaluation Department

More information

Solomon Islands: Transport Sector Development Project

Solomon Islands: Transport Sector Development Project Validation Report September 2018 Solomon Islands: Transport Sector Development Project Reference Number: PVR-582 Project Number: 41171-022 Grant Number: 0243 ABBREVIATIONS ADB Asian Development Bank ADF

More information

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization Completion Report Project Number: 46-01 Technical Assistance Number: 7857 April 016 Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization This document is being disclosed

More information

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities Improving Public Expenditure Quality Program, SP1 (RRP VIE 50051-001) SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) 1 Sector Road Map 1. Sector Performance,

More information

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT Public Disclosure Authorized The World Bank REPORT NO.: RES30161 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 51360-002 Transaction Technical Assistance Facility (F-TRTA) April 2018 Turkmenistan: Preparing the Central Asia Regional Economic Cooperation Corridors 2, 3

More information

Indonesia: Capacity Building in Urban Infrastructure Management Project

Indonesia: Capacity Building in Urban Infrastructure Management Project Validation Report Reference Number: PCV: INO 2008-68 Project Number: 27289 Loan Number: 1572-INO May 2009 Indonesia: Capacity Building in Urban Infrastructure Management Project Independent Evaluation

More information

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and CONFORMED COPY LOAN NUMBER 4674 HR Loan Agreement (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Dated September

More information

Establishment of the Leading Asia s Private Sector Infrastructure Fund

Establishment of the Leading Asia s Private Sector Infrastructure Fund March 2016 Establishment of the Leading Asia s Private Sector Infrastructure Fund This document is being disclosed to the public prior to Board consideration in accordance with ADB s Public Communications

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 50138-001 September 2017 Proposed Loan Walkers Colombo Shipyard (Private) Limited Shipyard Rehabilitation and Infrastructure

More information

GAMAS means Mongolia Customs Automated Data Processing

GAMAS means Mongolia Customs Automated Data Processing 2 System; (c) GAMAS means Mongolia Customs Automated Data Processing (d) Grant Account means the account opened by ADB on its books in the name of Mongolia for the purposes of the Project and to which

More information

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON)

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) Board of Directors IN.365-10 21 December 2010 Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) The attached Report is circulated at the request of the Director General, Independent Evaluation

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

People s Republic of Bangladesh: Rural Infrastructure Maintenance Program

People s Republic of Bangladesh: Rural Infrastructure Maintenance Program Project Design Advance Project Administration Manual Project Number: 47243-003 June 2016 People s Republic of Bangladesh: Rural Infrastructure Maintenance Program CONTENTS I. PROPOSED PROJECT DESCRIPTION

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Philippines: Small and Medium Enterprise Development Support Project

Philippines: Small and Medium Enterprise Development Support Project Validation Report Reference Number: PCV: PHI 2011 28 Project Number: 36419 Loan Number: 2186 October 2011 Philippines: Small and Medium Enterprise Development Support Project Independent Evaluation Department

More information

ASIAN DEVELOPMENT BANK PCR: PHI 19178

ASIAN DEVELOPMENT BANK PCR: PHI 19178 ASIAN DEVELOPMENT BANK PCR: PHI 19178 PROJECT COMPLETION REPORT ON THE SECOND MANILA PORT PROJECT (Loan No. 875-PHI) IN THE PHILIPPINES September 1997 CURRENCY EQUIVALENTS Currency Unit - Philippine Peso

More information

The World Bank LK GPOBA - Access to Sanitation Project (P111161)

The World Bank LK GPOBA - Access to Sanitation Project (P111161) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF LK GPOBA - ACCESS TO SANITATION PROJECT APPROVED ON JUNE 8, 2011 TO DEMOCRATIC

More information

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program Facility Administration Manual Project Number: 42107 MFF Number: 0042-UZB Loan Numbers: 2635-UZB (Project 1), 2746-UZB (Project 2), and 2868-UZB (Project 3) 21 August 2013 Multitranche Financing Facility

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

Completion Report. Project Number: Loan Number: 1548 September Mongolia: Ulaanbaatar Heat Efficiency Project

Completion Report. Project Number: Loan Number: 1548 September Mongolia: Ulaanbaatar Heat Efficiency Project Completion Report Project Number: 29629 Loan Number: 1548 September 2008 Mongolia: Ulaanbaatar Heat Efficiency Project CURRENCY EQUIVALENTS Currency Unit togrog (MNT) At Appraisal At Project Completion

More information

Completion Report. Project Number: Loan Numbers: 2279/2280 September Bhutan: Financial Sector Development Program

Completion Report. Project Number: Loan Numbers: 2279/2280 September Bhutan: Financial Sector Development Program Completion Report Project Number: 37164 Loan Numbers: 2279/2280 September 2013 Bhutan: Financial Sector Development Program AASB AASBB AASC CURRENCY EQUIVALENTS Currency Unit ngultrum (Nu) At Appraisal

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

The World Bank Third Secondary and Local Roads Project (P148048)

The World Bank Third Secondary and Local Roads Project (P148048) Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THIRD SECONDARY AND LOCAL ROADS PROJECT APPROVED ON JULY 3, 2014 TO GEORGIA REPORT NO.:

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

Multitranche Financing Facility Annual Report 2017

Multitranche Financing Facility Annual Report 2017 May 2018 Multitranche Financing Facility Annual Report 2017 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. ABBREVIATIONS ADB Asian Development

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR: THA 27262 PROJECT COMPLETION REPORT ON THE CHONBURI WATER SUPPLY PROJECT (Loan 1326-THA) IN THAILAND March 2002 CURRENCY EQUIVALENTS Currency Unit Baht (B) At Appraisal (August

More information

Maldives: Developing the Revenue Administration Management Information System

Maldives: Developing the Revenue Administration Management Information System Completion Report Project Number: 44414-012 Technical Assistance Number: 7946 July 2015 Maldives: Developing the Revenue Administration Management Information System This document is being disclosed to

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

Mongolia: Development of State Audit Capacity

Mongolia: Development of State Audit Capacity Technical Assistance Report Project Number: 47198-001 Capacity Development Technical Assistance (CDTA) November 2013 Mongolia: Development of State Audit Capacity The views expressed herein are those of

More information

Establishment of the High-Level Technology Fund

Establishment of the High-Level Technology Fund April 2017 Establishment of the High-Level Technology Fund Distribution of this document is restricted until it has been approved by Management. Following such approval, ADB will disclose the document

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING NIGERIA PUBLIC SECTOR GOVERNANCE REFORM AND DEVELOPMENT PROJECT APPROVED ON JUNE 29, 2010

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING NIGERIA PUBLIC SECTOR GOVERNANCE REFORM AND DEVELOPMENT PROJECT APPROVED ON JUNE 29, 2010 Public Disclosure Authorized The World Bank RESTRUCTURING PAPER REPORT NO.: RES24803 Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF NIGERIA PUBLIC SECTOR GOVERNANCE REFORM AND DEVELOPMENT

More information

India: Bihar State Highways Project

India: Bihar State Highways Project Completion Report Project Number: 41127-013 Loan Number: 2443 Technical Assistance Number: 7130 August 2018 India: Bihar State Highways Project This document is being disclosed to the public in accordance

More information

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4199 UG Public Disclosure Authorized Financing Agreement (Uganda Public Service Performance Enhancement Project) between Public Disclosure Authorized

More information

Completion Report. Project Number: Loan Number: 2433 September Azerbaijan: Road Network Development Program (Project 2)

Completion Report. Project Number: Loan Number: 2433 September Azerbaijan: Road Network Development Program (Project 2) Completion Report Project Number: 39176 Loan Number: 2433 September 2013 Azerbaijan: Road Network Development Program (Project 2) CURRENCY EQUIVALENTS Currency Unit Azerbaijan manat (AZN) At Appraisal

More information

STATE-OWNED ENTERPRISE ANALYSIS (Republic of the Marshall Islands: Public Sector Program)

STATE-OWNED ENTERPRISE ANALYSIS (Republic of the Marshall Islands: Public Sector Program) Public Sector Program (RRP RMI 43321-01) A. Introduction STATE-OWNED ENTERPRISE ANALYSIS (Republic of the : Public Sector Program) 1. The Republic of the (RMI) operates an extensive state-owned enterprises

More information

CONTENTS. Page EXECUTIVE SUMMARY I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19

CONTENTS. Page EXECUTIVE SUMMARY I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19 CONTENTS Page EXECUTIVE SUMMARY i I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19 CURRENCY EQUIVALENTS (as of 28 February 2016) Currency unit = Papua New Guinea Kina (PGK) 1

More information

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project Environmental Safeguard Monitoring Report Semi Annual Report July 2016 ADB Project Number: 48141-001 ADB Loan Number: 3210 FIJ: Transport Infrastructure Investment Sector Project Prepared by Fiji Roads

More information

Pakistan: Agribusiness Development Project

Pakistan: Agribusiness Development Project Validation Report Reference Number: PVR-354 Project Number: 33364 Loan Number: 2171 November 2014 Pakistan: Agribusiness Development Project Independent Evaluation Department ABBREVIATIONS ADB ASF DALPMG

More information

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I.

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I. Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Project Performance

More information

Viet Nam: Microfinance Development Program (Subprograms 1 and 2)

Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Validation Report Reference Number: PVR-478 Project Numbers: 42235-013 and 42235-023 Loan Numbers: 2877 and 3213 December 2016 Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Independent

More information

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Department of Fisheries Ministry of Natural Resources Teone, Funafuti TUVALU Email: proptuv@gmail.com / proptuv@tuvalufisheries.tv

More information

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN Terms of Reference for Consultants 1. BACKGROUND INFORMATION Government of Vanuatu has requested TA support in the formulation and preparation of a national infrastructure

More information

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO)

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) Board of Directors IN.247-11 14 October 2011 Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) The attached Report is circulated at the request of the Director

More information

Cambodia: Small and Medium Enterprise Development Program

Cambodia: Small and Medium Enterprise Development Program Validation Report Reference Number: PCV: CAM 2010-73 Program Number: 36383 Loan Number: 2129(SF) December 2010 Cambodia: Small and Medium Enterprise Development Program Independent Evaluation Department

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information