Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)

Size: px
Start display at page:

Download "Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan)"

Transcription

1 Completion Report Project Number: Loan Numbers: 2303-TAJ (SF)/8320-TAJ and 2304-AFG (SF) Grant Number: 0230-AFG June 2014 Regional Power Transmission Interconnection Project (Afghanistan and Tajikistan) This document is being disclosed to the public in accordance with ADB's Public Communications Policy 2011.

2 CURRENCY EQUIVALENTS Currency unit (Afghanistan) afghani (AF) At Appraisal At Project Completion (6 November 2006) (16 May 2014) AF1.00 = $0.02 $0.017 $1.00 = AF49.44 AF57.35 Currency unit (Tajikistan) somoni (TJS) At Appraisal At Project Completion (6 November 2006) (16 May 2014) TJS1.00 = $0.30 $0.21 $1.00 = TJS3.35 TJS4.84 ABBREVIATIONS ADB Asian Development Bank DABM Da Afghanistan Breshna Moassessa (Afghanistan Power Authority) DABS Da Afghanistan Breshna Sherkat (Afghanistan Power Utility) EIRR economic internal rate of return FIRR financial internal rate of return FY fiscal year IDB Islamic Development Bank O&M operation and maintenance OFID Organization of the Petroleum Exporting Countries Fund for International Development PIU project implementation unit P power purchase agreement PPMS project performance management system QCBS quality- and cost-based selection SCADA supervisory control and data acquisition TA technical assistance TCR technical assistance completion report WEIGHTS AND MEASURES GWh gigawatt-hour km kilometer kv kilovolt kwh kilowatt-hour MW megawatt NOTES (i) The fiscal year (FY) of the Government of Afghanistan and its agencies ends on 20 March. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2006 ends on 20 March However, in 2012, the ending date of government s fiscal year was changed from 20 March to 21 December to align with international practice. (ii) The fiscal year of the Government of Tajikistan and its agencies ends on 31 December. (iii) In this report, "$" refers to US dollars.

3 Vice-President W. Zhang, Operations 1 Director General K. Gerhaeusser, Central and West Asia Department (CWRD) Director R. Stroem, Energy Division, CWRD Team leader Team member J. Hwang, Senior Portfolio Management Specialist, CWRD L. Dimayuga, Senior Project Officer, CWRD R. Benavidez, Senior Operations Assistant, CWRD In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

4 BASIC DATA CONTENTS Page I. PROJECT DESCRIPTION 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION 1 A. Relevance of Design and Formulation 1 B. Project Outputs 2 C. Project Costs 4 D. Disbursements 5 E. Project Schedule 5 F. Implementation Arrangements 6 G. Conditions and Covenants 7 H. Related Technical Assistance 7 I. Consultant Recruitment and Procurement 8 J. Performance of Consultants, Contractors, and Suppliers 10 K. Performance of the Borrower and the Executing Agency 10 L. Performance of the Asian Development Bank 10 III. EVALUATION OF PERFORMANCE 11 A. Relevance 11 B. Effectiveness in Achieving Outcome 11 C. Efficiency in Achieving Outcome and Outputs 12 D. Preliminary Assessment of Sustainability 12 E. Impact 13 IV. OVERALL ASSESSMENT AND RECOMMENDATIONS 14 A. Overall Assessment 14 B. Lessons 14 C. Recommendations 15 i APPENDIXES 1. Design and Monitoring Framework Project Costs ADB Annual Disbursements Implementation Schedule Status of Compliance with Loan Covenants Contracts and Disbursements Financed by ADB Financial Assessment of Executing Agencies and Project Economic Analysis Quantitative Assessment of Overall Project Performance Contribution to the ADB Results Framework 67

5 BASIC DATA AFGHANISTAN A. Loan Identification 1. Country 2. Loan Number / Grant Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan / Grant 7. Project Completion Report Number Afghanistan 2304-AFG(SF) / 0230-AFG Regional Power Transmission Interconnection Project Afghanistan Ministry of Energy and Water SDR23,563,000 / $12,000,000 REG 1451 B. Loan Data 1. Fact Finding Date Started Date Completed 2. Loan Negotiations Date Started Date Completed 3. Date of Board Approval 4. Date of Agreement 5. Date of Effectiveness In Agreement Actual Number of Extensions 6. Closing Date In Agreement Actual b Number of Extensions 7. Terms of Loan Interest Rate Maturity (number of years) Grace Period (number of years) 8. Terms of Relending Interest Rate Maturity (number of years) Grace Period (number of years) ADB Loan/Grant 28 August September November November December May August August September June % per annum (1.0% per annum during grace period) ADB Grant Not applicable a 18 October October November January February September December June % per annum (1.0% per annum during grace period) a Project concept paper for supplementary financing approved on 29 September b Actual loan financial closing date was 5 March 2014 and actual grant financial closing date was 29 October 2013.

6 ii Loan: 9. Disbursements a. Dates Initial Disbursement 23 February 2009 Final Disbursement 25 February 2014 Time Interval 60 months Grant : Effective Date 22 August 2007 Initial Disbursement 19 December 2011 Original Closing Date 30 September 2009 Final Disbursement 17 October 2013 Time Interval 25 months Time Interval 22 months Effective Date 12 September 2010 Original Closing Date 31 December 2011 Time Interval 15 months Category b. Loan Amount (SDR 000) Original Allocation Last Revised Allocation Amount Disbursed Amount Cancelled 1 Transmission line 17,302 21,777 21, Demining Incremental administration, training, and PIU support 4 Consulting services Interest during construction 6 Unallocated 471 3, Total SDR 23,563 23,563 22, Total $ equivalent 35,000 36,208 35,154 1,074 PIU = project implementation unit, SDR = special drawing right. Note: 1 SDR = $ Category c. Grant Amount ($ 000) Original Allocation 471 Amount Disbursed 471 Amount Cancelled 1 Transmission line 8,300 4,011 4,289 2 Implementation consultant Unallocated 3, ,000 Total 12,000 4,568 7, Local Costs (Financed, ADB Loan) Not applicable Local Costs (Financed, ADB Grant) Not applicable 0

7 iii C. Project Data Cost 1. Project Cost ($ million) Appraisal Estimate Supplementary Financing Estimate Total Estimate Actual Foreign Exchange Cost Total Financing Plan ($ million) Cost Implementation Costs Appraisal Estimate Supplementary Financing Total Estimate Actual Borrower Financed ADB Loan Financed ADB Grant Financed Afghanistan Reconstruction Trust Fund Islamic Development Bank Total IDC Costs Borrower Financed ADB Financed Other external financing Total ADB = Asian Development Bank, IDC = interest during construction. 3. Cost Breakdown by Project Component ($ million) Component Appraisal Estimate Supplementary Financing Total Estimate Actual Transmission line Kunduz substation a Baghlan substation Implementation consultant Incremental administration, training and PIU support Demining Taxes and duties Security during construction b Contingencies n/a Land acquisition and resettlement cost Interest during construction Total n/a = not applicable, PIU = project implementation unit. a Substations not yet complete. Contract cost of $17.54 million that covers Kunduz and Baghlan substations. b The government contributed to security during construction by means of local police force. As such, its amount is not recorded

8 iv 4. Project Schedule Item Appraisal Estimate Actual Establishment of project management office 1 November 2005 Date of contract with consultants Loan: Project management consultants Loan and grant: Demining consultants April January April 2011 Civil works contracts Loan and grant: Transmission line October November 2008 Completion of Work March 2009 October 2011 Item Appraisal Estimate Actual Other Milestones Minor implementation arrangements change (separate bidding document for Afghanistan and Tajikistan) Major implementation arrangements change (selection method QCBS 80:20 to 90:10) Request for imprest account establishment Major implementation change (change in IA) Extension of winding up and interest charges as eligible project expenditures 7 October October April December February 2014 Reallocation of Loan Funds First Second Equipment and Supplies First Procurement Completion of Equipment Installation Start of Operations Completion of Tests and Commissioning Beginning of Start-Up 4 November November 2011 November 2007 March 2009 December 2008 October 2008 October October October Project Performance Report Ratings Implementation Period 1 January December January December 2010 Ratings Development Objectives Implementation Progress Satisfactory Satisfactory Satisfactory Partly satisfactory Overall Project Rating a 1 January December 2013 On track a In 2011, e-operations replaced the project performance rating. The indicators used in performance rating are technical, procurement, disbursement, financial management, and safeguards. A single rating applies to the project (Tajikistan loans and Afghanistan loan and grant).

9 v D. Data on Asian Development Bank Missions Name of Mission Date No. of Persons No. of Person- Days Specialization of Members a Inception Mar a, b, c Review 1 10 May a, c, e Review Nov a, c, g Review 3 26 Jan 2 Feb a, b, c, e, g Review 4 Review 5 Review 6 Contact/Consultation Contact /Review Consultation Mar Jun 3 Jul Aug 2 Sep Feb Oct Aug g, c, h a, c, e, h, i, j a, h, j, k f, d, h a, c, h, j a, c, j Project completion review Nov a, h, j Consultation mission 3 11 Dec a, c, h, j a a = energy specialist/investment officer/mission leader, b = project analyst, c = project officer Afghanistan Resident Mission (AFRM), d = portfolio management specialist, e = energy specialist, f = sector director, g = principal energy specialist, h = energy specialist AFRM, i = social development specialist (resettlement), j = assistant project analyst AFRM, k = investment specialist.

10 vi BASIC DATA TAJIKISTAN A. Loan Identification 1. Country 2. Loan Numbers 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Project Completion Report Number Republic of Tajikistan 2303-TAJ(SF) / 8230-TAJ a Regional Power Transmission Interconnection Project Republic of Tajikistan Barki Tojik SDR14,475,000 / $8,500,000 REG 1451 B. Loan Data 1. Fact-finding Date Started Date Completed 2. Appraisal Date Started Date Completed 3. Loan Negotiations Date Started Date Completed 4. Date of Board Approval 5. Date of Loan Agreement 6. Date of Loan Effectiveness In Loan Agreement Actual Number of Extensions 7. Closing Date In Loan Agreement Actual Number of Extensions ADB Loan 28 August September 2006 Waived Waived 17 November November December February May August December May OFID Loan 10 January September 2007 and 6 November January December June Terms of Loan (ADB) Interest Rate Maturity (number of years) Grace Period (number of years) 1.5% per annum (1.0%) per annum during grace period 32 8 Terms of Loan (OFID) Interest Rate Maturity (number of years) Grace Period (number of years) 1% per annum 20 5 a Cofinancing provided by the Organization of the Petroleum Exporting Countries Fund for International Development (OFID). ADB and OFID signed a letter of administration on 6 November 2007.

11 vii 9. Terms of Relending Interest Rate Maturity (number of years) Grace Period (number of years) LIBOR-based Disbursements ADB Loan: a. Dates Initial Disbursement 18 January 2008 Final Disbursement 16 May 2011 Time Interval 40 months OFID Loan: Effective Date 22 August 2007 Initial Disbursement 8 May 2011 Original Closing Date 31 December 2010 Final Disbursement 31 May 2011 Time Interval 40 months Time Interval 11 months Effective Date 15 January 2008 Original Closing Date 31 December 2010 Time Interval 35 months Category b. Amount (SDR 000) Original Allocation Last Revised Allocation Amount Canceled Amount Disbursed 1 Transmission line 7,204 8, ,537 2 Baipaza hydropower pant 1,279 1, ,324 3 Bulk metering 1,145 1, ,078 4 Optimization of Vakhsh a Resettlement and environmental activities 6 Consulting services 1,346 1, ,261 7 Interest during construction Unallocated 2, Total SDR 14,475 12,313 2,161 2,313 Total $ equivalent 21,500 18,900 3,458 18,900 SDR = special drawing right. a A feasibility study for Vakhsh Optimization was completed by the project implementation consultant, after ADB s approval of the contract variation. Note: 1 SDR = $ Local Costs (Financed) Not applicable C. Project Data 1. Project Cost ($ million) Cost a Appraisal Estimate Actual Foreign Exchange Cost Total a No differentiation was made at appraisal or in actual costs between foreign and local costs.

12 viii 2. Financing Plan ($ million) Cost Appraisal Estimate Actual Implementation Costs Borrower Financed (Barki Tojik) ADB Financed Islamic Development Bank OFID Total IDC Costs Borrower Financed ADB Financed Other external financing Total ADB = Asian Development Bank, IDC = interest during construction, OFID = Organization of the Petroleum Exporting Countries Fund for International Development. 3. Cost Breakdown by Project Component ($ million) Component Appraisal Estimate Actual A. Investment Costs 1a. Engineering, Supply and Construction of the Transmission line and 220 kv Line Bay at Sangtuda b. Supply of conductors Baipaza HPP Excitation System Bulk metering Golovnaya HPP Transformer T3 a Golovnaya HPP Unit b 6. Dredging Canals: Centralnaya and Prepadnaya HPPs 7. Implementation Consultant Optimization of Vakhsh River cascade c Land acquisition and compensation Environmental monitoring Subtotal (A) B. Contingencies d 1. Physical Contingencies 2. Financial Contingencies Subtotal (B) C. Interest During Construction Total kv = kilovolt, HPP = hydropower plant. Note: Totals may not add up due to rounding. a Canceled. b Financed Golovnaya Unit 4, in lieu of Unit 3. c Canceled. d Not identified separately in actual cost estimate.

13 ix 4. Project Schedule Item Appraisal Estimate Actual Establishment of project implementation unit July 2006 Date of contract with consultants Mid December 2007 Civil works contracts (i) Lot 1, 220 kv Transmission Line Date of Award Completion of Work April 2007 January December November 2010 (ii) Lot 5, Rehabilitation of Excitation and Temperature System for Generator Units at Baipaza hydropower plant Date of Award Completion of Work March 2008 April December July 2010 (iii) Lot 6, Supply and Installation of Meters and Associated Plant Date of Award Completion of Work August 2008 August March December 2010 Equipment and supplies First procurement June July 2007 Last procurement November August 2010 Completion of equipment installation January October 2010 Start of Operations Completion of Tests and Commissioning Beginning of Start-Up Other Milestones Minor change in implementation arrangements and loan reallocation Minor change in scope and implementation arrangements Minor change in implementation arrangements Reallocation of Loan Proceeds First Second Third Fourth kv = kilovolt. 8 October October June August October June February March 2010 December 2010

14 x 5. Project Performance Report Ratings Implementation Period 1 January December January January February December 2010 Development Objectives Satisfactory Satisfactory Satisfactory Ratings Implementation Progress Satisfactory Partly Satisfactory Satisfactory Overall Project Rating a 1 January December 2013 On track a In 2011, e-operations replaced the project performance rating. The indicators used in performance rating are technical, procurement, disbursement, financial management, and safeguards. A single rating applies to the project (Tajikistan loans and Afghanistan loan and grant). D. Data on Asian Development Bank Missions Name of Mission Date No. of Persons No. of Person- Days Specialization of Members Inception 29 March 4 April a, b Review 1 19 May a Review October c, d Contact April a, f Review March c, e, f Review June c, f Review 5 Review 6 Review February May November g, b, e c, h, g, i g Project completion review 5 9 November j, k, f a = energy specialist, b = project analyst, c = principal energy specialist, d = infrastructure specialist, e = project implementation officer Tajikistan Resident Mission, f = staff consultant, g = investment specialist, h = director energy division, i = energy specialist, j = project administration unit head/senior energy specialist, k = senior project officer.

15 I. PROJECT DESCRIPTION 1. At the time of project preparation in 2006, Afghanistan s electricity infrastructure had been severely affected by years of conflict, with generation capacity declining to 250 megawatts (MW) in 2005 from 456 MW in the 1990s. Electricity generation was limited and unable to meet demand, leading to widespread load shedding, and the transmission grid was almost nonexistent. This led to the use of small-scale diesel power generators in Kabul and elsewhere, resulting in pollution and high electricity costs. Electricity demand was also forecast to grow at 5.5% per annum to about 1,100 MW by At the same time, Tajikistan had a surplus of power generation capacity in the summer months. Installed electricity generation capacity was 4,405 MW, of which 4,060 MW (92%) was hydropower. Annual hydropower output was about 16,000 gigawatt-hours (GWh) and, on average, there was a summer surplus of 1,500 GWh that was available for export. This surplus increased by 2,700 GWh when the Sangtuda-I hydropower plant was commissioned in April Part of this surplus was exported. Because of a lack of sufficient access to power markets, Tajikistan s hydropower plants were forced to spill water. 3. To address these issues, the Regional Power Transmission Interconnection Project was designed to (i) increase the power export and income-generating capacity of Tajikistan; (ii) restore power supply and lower the cost of electricity in Afghanistan; (iii) improve capacity in the operation of the Afghanistan Power Authority (DABM); and (iv) strengthen the commercial operation of Barki Tojik, the company responsible for electricity generation, transmission, and distribution. 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation 4. At appraisal, the project was relevant to each country s development objectives, and to the country strategies and regional cooperation program of the Asian Development Bank (ADB). In 2004, the Government of Afghanistan formulated an electricity sector policy and road map in which the establishment of a regulatory framework and the restructuring and commercialization of the power sector were key features. The aim of the policy was to supply all of Afghanistan with reliable power by To achieve this goal, there were plans to invest in system rehabilitation; increase the power supply, including through imports; and expand generation, transmission, and distribution capacity. The project was designed to support these activities through the development of energy infrastructure to increase imports of electricity from Tajikistan. 5. In 2005, the Government of Tajikistan adopted a two-pronged strategy aimed at (i) rehabilitating the domestic electricity market through policy measures and investment to improve sector operating conditions and enhance financial viability; and (ii) increasing electricity exports, first by using existing potential surpluses, and then by expanding generation capacity. The project was designed to support the expansion of generation and transmission, including exports to Afghanistan. 6. The goal of ADB s Initial Country Strategy and Program for Afghanistan was national reconstruction, with a focus on agriculture and water resources, education, infrastructure, 1 ADB Report and Recommendation of the President to the Board of Directors: Proposed Loans, Technical Assistance Grants, and Administration of Loan by the OPEC Fund for International Development to the Islamic Republic of Afghanistan and Republic of Tajikistan for the Regional Power Transmission Interconnection Project. Manila.

16 2 and the environment. 2 At the government s request in 2003, ADB assistance in the energy sector was directed at generating and distributing electricity, upgrading hydropower, and rehabilitating natural gas and petroleum infrastructure. 7. In Tajikistan, ADB s Country Strategy and Program reflected ADB s overarching objective of poverty reduction. 3 It focused on economic growth with an emphasis on rural development and regional cooperation. Increasing productivity and profitability in rural areas was to be supported through rehabilitation of rural infrastructure to improve agricultural output, market access, and electricity supply. 8. The individual country strategies and programs were to be linked with and complemented by ADB s regional cooperation program. This focused on identifying infrastructure needs and providing the investment environment for promoting cross-border trade, including trade in energy. In the energy sector, ADB s focus was on (i) maximizing the use of national resources and assets, (ii) benefiting neighboring countries by rationalizing and encouraging regional energy trade based on market principles, and (iii) rehabilitating existing infrastructure. 9. The design of the project was sound and addressed the main issues of surplus hydroelectricity in Tajikistan and the lack of transmission capacity in Afghanistan to import electricity from Tajikistan. The design was enhanced with a power purchase agreement (P), arrangements for the institutional strengthening of Barki Tojik and DABM, and measures to encourage the private sector to participate in the energy sector in Afghanistan. The project was formulated in close cooperation with stakeholders. The Government of Tajikistan had pursued opportunities to sell its excess power in spring and summer, while the Government of Afghanistan had identified power imports as the most effective way of meeting its short-term power shortfall. The project was endorsed by the energy and finance ministers and key power sector enterprises of both countries. 10. At completion, the project remains relevant to each country s development objectives, which for Afghanistan includes the development of energy links with neighboring countries and for Tajikistan includes increasing electricity exports. 4 B. Project Outputs 1. Afghanistan Component 11. Part A: Transmission lines. The 220 kilovolt (kv) transmission line was constructed as planned from the border with Tajikistan to Pul-e-Khumri substation in Afghanistan, and was commissioned in October The length of the completed transmission line was increased to 163 kilometers (km) from 157 km to avoid a populated area along the route. To address potential security concerns resulting from possible residual landmines in the line route, a demining contractor was procured under the Afghanistan loan. The contractor cleared a 4.5 km section before construction, as required by the United Nations Mine Action Centre for Afghanistan. 12. Part B: Substations. Work on the substations was delayed. Construction of two switchyards, financed by the Islamic Development Bank (IDB), was carried out by an Iranian contractor, but progress was affected by sanctions imposed on Iran, the contractor, and its 2 ADB Initial Country Strategy and Program: Afghanistan, Manila. 3 ADB Country Strategy and Program: Tajikistan, Manila. 4 ADB Country Partnership Strategy: Afghanistan, Manila; ADB Country Strategy and Program: Tajikistan, Manila.

17 3 banks by the international community, restricting payments to the contractor. As of May 2014, construction was 95% complete, with major equipment already installed. Completion is expected by September Tajikistan Component 13. Part A: Transmission lines. The actual length of the completed transmission line from Sangtuda to the Pyanj River crossing was km, compared to the km expected at appraisal. The transmission line was completed on 30 November 2010, and commissioned and energized for electricity export to Afghanistan on 27 October Part B: Substations. Work at the Sangtuda substation was completed as planned. Two new line bays, numbers 12 and 13, were constructed at the substation. The transmission line was connected to two existing bays, numbers 7 and 8, after installation of new transformers to ensure proper clearance from the existing lines. 15. Part C: Generation. The dredging of the canals at Centralnaya and Prepadnaya hydropower plants was completed in December The dredging at Prepadnaya hydropower plant resulted in a lowering of the water level by about 1 meter. The dredging at Centralnaya hydropower plant was completed as originally planned, but resulted in only marginal improvement as sedimentation was more extensive than expected. A follow-up study recommended the dredging of an additional 12 km along the canal. This dredging was completed in September The upgrading of unit 3 at Golovnaya hydropower plant was not undertaken because unit 4 had failed in the meantime and higher priority was placed on unit 4. Therefore, the loan financed the rehabilitation of unit 4 instead. The operational acceptance certificate was issued on 31 December Rehabilitation of the excitation system at Baipaza hydropower plant was completed in July 2010 with scope expanded to procure 144 additional temperature sensors and associated equipment. 17. The replacement of transformer T3 at the Golovnaya hydropower plant was originally to be financed by Barki Tojik. The first tender, using the limited international bidding procedure, failed to attract interest. The second tender, using international competitive bidding, was successful, but Barki Tojik was unable to fund the required work. This component was therefore not implemented. 5 The optimization of the Vakhsh River cascade was also not implemented as no bid was received during tendering, and its implementation during the project was not feasible given that there was no data acquisition system in place. Instead, the scope of the project implementation consultant was increased to include a feasibility study for (i) the optimization work, and (ii) a supervisory control and data acquisition (SCADA) system. The feasibility study was completed in November The Vakhsh optimization and SCADA are now included under the ADB-financed Regional Power Transmission Project Part D: Metering. The metering component comprised: (i) the replacement of mechanical meters with digital meters, (ii) the replacement of current and voltage transformers, and (iii) improved energy data collection. This component was successfully completed in December 2010 by installing 320 bulk meters, 18 current transformers, and 19 voltage transformers in the western and central grids. During implementation, Barki Tojik 5 Replacement of transformer T3 is included in the scope of the Golovnaya 240 Megawatt Hydropower Plant Rehabilitation Project (Grant 0236-TAJ). 6 ADB Report and Recommendation of the President to the Board of Directors: Proposed Grant to the Republic of Tajikistan for the Regional Power Transmission Project. Manila.

18 4 proposed and ADB approved (i) an increase in the number of staff trained in operation and maintenance (O&M) of the new meters from 40 to 90, and (ii) additional construction works at Kurgan-Tyube and Chapaevo substations to install the current and voltage transformers. 19. Actual project achievements with respect to impact, outcome, and outputs, as specified in the project design and monitoring framework, are in Appendix 1. C. Project Costs 20. The cost of the project was estimated at $109.5 million at appraisal, comprising $55.5 million for the Afghanistan component and $54.0 million for the Tajikistan component. A funding gap arose in the Afghanistan portion of the transmission line because (i) start-up of construction was delayed and security in the Afghanistan project area worsened, further delaying implementation and increasing costs; 7 and (ii) additional towers and line lengths were required to reroute the transmission line to avoid a populated area. ADB approved a supplementary grant of $12.0 million, with the government financing an additional $0.4 million for taxes and duties. 8 The cost increases, including an expected price escalation, amounted to $8.3 million. The balance included an increase in the cost of implementation consulting services ($0.7 million) and an increase in price contingencies ($3.0 million). 9 This increased the estimated cost of the Afghanistan component to $67.9 million and raised the cost for the project as a whole to $121.9 million. Actual project costs amounted to $102.8 million. 10 Details of estimated and actual project costs by component are in Appendix Under the Afghanistan component, ADB actually financed $35.1 million under the Afghanistan loan against $35.0 million estimated at appraisal due to a fall in the SDR dollar exchange rate. Only $4.6 million was disbursed under the Afghanistan grant against $12.0 million approved, equivalent to 38% of the approved amount. At appraisal, the Afghanistan Reconstruction Trust Fund was to finance $16.5 million. Subsequently, this financing was replaced by financing from the IDB, amounting to 12.7 million ($17.5 million equivalent). The government financed $0.7 million against $4.4 million estimated at appraisal At appraisal, ADB was to partly finance the transmission line in Tajikistan, together with the line bay at the Sangtuda hydropower plant, and fully finance the Baipaza excitation and temperature system, bulk metering, the implementation consultant, optimization of the Vakhsh River cascade, land acquisition and compensation, and environmental monitoring. IDB was earmarked for partial financing of the Golovnaya hydropower plant unit 3. The Organization of the Petroleum Exporting Countries Fund for International Development (OFID) was to finance the balance of the cost of the transmission, amounting to $8.5 million. Barki Tojik was to finance conductors related to the transmission line, Golovnaya hydropower plant transformer T3, part of the cost of Golovnaya hydropower plant unit 3, and the dredging of canals at the Centralnaya and Prepadnaya hydropower plants. Under the Tajikistan loan, ADB actually financed $18.9 million against $21.5 million estimated at appraisal. 12 IDB financing was increased from $10 million proposed at appraisal to $ Construction began only in ADB Report and Recommendation of the President to the Board of Directors: Proposed Supplementary Grant to the Islamic Republic of Afghanistan for the Regional Power Transmission Interconnection Project. Manila. 9 Detailed cost escalation estimates are provided in Appendix 2 of the grant report and recommendation of the President, (footnote 6). 10 This Includes financing charges of $0.87 million, $0.15 million under the Afghanistan loan, and $0.72 million under the Tajikistan loan. 11 This includes $0.3 million for taxes and duties, and $407, for compensation for land acquisition and resettlement. 12 Due to a fall in the SDR dollar exchange rate, the SDR value of ADB s disbursement was SDR12,313,617. An amount of SDR2,161,383 ($3,458,905) was cancelled on 16 May 2011.

19 5 million because the awarded contract price exceeded the cost estimate. OFID financed $7.91 million of the proposed $8.50 million and Barki Tojik financed $4.12 million of the proposed $14.00 million. D. Disbursements 23. A breakdown of annual disbursements under loans and grant is in Appendix 3. Total disbursements under the Afghanistan loan were $35,153, compared with $35,000,000 specified in the loan agreement, and $1,074,337 was canceled at closing. Under the Afghanistan grant, the total amount disbursed was $4,567,937 compared with $12,000,000 specified in the grant agreement. Under the Tajikistan loan, total disbursements amounted to $18,900,033, compared with $21,500,000 in the loan agreement. An amount of $3,458,905 from this loan was canceled. 24. For the Afghanistan loan, an imprest account was opened in Da Afghanistan Bank with a limit of $60,000. The average annual turnover ratio of the imprest fund was 1.12, indicating a low annual turnover or utilization. This indicates that the imprest fund was not used efficiently as procedures require that at least twice the amount of the funds advanced to the executing agency should be liquidated every year. The imprest account was closed on 5 March E. Project Schedule 25. Implementation was significantly delayed by the failure to agree the terms of the intergovernmental P, in particular with respect to price. 14 The P was finally signed on 29 August 2008, 12 months after loan effectiveness. An implementation schedule showing the estimated and actual timing of activities under the project is in Appendix At appraisal, the Afghanistan component of the project was to be implemented from December 2006 to March The loan was scheduled to close on 30 September Loan closing was first extended on 1 April 2009 to 31 December 2010 due to the delay in P signing, which was a condition for contract award of civil works. It was subsequently extended to 31 December 2011 and then to 31 December 2012 because of unresolved resettlement issues. The Afghanistan grant was approved on 18 November 2010, and was also scheduled to close on 31 December During 2011, with construction nearing completion, the Ministry of Energy and Water identified an additional 40 families that would be affected by the transmission line near Pul-e-Khumri. 16 The contract of the implementation consultant was extended to prepare land acquisition and resettlement plans. Consequently, the loan and grant closing dates were extended until 30 September 2012 to accommodate the additional work and resolve remaining resettlement issues. The additional land acquisition and resettlement plans were approved by ADB on 18 October Further extensions of the loan and grant closing dates to 31 December 2012 and finally to 30 June 2013 were approved to ensure that all land acquisition and resettlement plan activities would be completed. The Ministry of Energy and Water implemented the compensations as approved in the land acquisition and resettlement plans, and ADB accepted the compliance reports on 1 April The actual physical closing date of the loan and grant accounts was 30 June 2013, while the actual loan financial closing was on 5 March 2014 and grant financial closing was on 29 October Due to a fall in the SDR dollar exchange rate, the SDR value of ADB s disbursement was SDR22,868,715. An amount of SDR694,285 ($1,074,337) was cancelled on 5 March As indicated in the report and recommendation of the President for the Afghanistan grant (para. 5), it was agreed that a P would be signed before any contract award. 15 At the end of 2009, cumulative disbursements amounted to only 7.8%. 16 In total, 138 affected families had been identified along the route of the line.

20 6 27. The Tajikistan component was to be implemented from December 2006 to June The loan agreement was signed on 22 February 2007, and became effective on 22 August 2007, with a delay of 3 months. 17 The loan was scheduled to close on 31 December Loan closing was extended once to 15 March 2011, with financial closing on 16 May The contracts for the transmission line and the Baipaza excitation system 18 were awarded in January The contract for bulk metering was awarded in April Apart from initial delays in start-up and contract bidding and award, a number of delays beyond the control of the contractors, executing agency, and project management unit prevented earlier completion. Work on the transmission line was delayed because the delivery of materials was held up in Uzbekistan and then rerouted through the Kyrgyz Republic. This delayed completion to November 2010, 22 months after the appraisal deadline of January While work on the Baipaza excitation system was completed 1 month ahead of the contractual deadline of August 2010, completion was delayed by a problem with the stator core winding in generator unit 2 that affected the testing and commissioning of the excitation system at full power. 20 The bulk metering works were on schedule for completion in October 2010, but additional site works at two substations delayed completion until December 2010, 17 months after the appraisal deadline on July The original scope of the dredging of canals at the Centralnaya and Prepadnaya hydropower plants was completed in December The additional dredging at the Prepadnaya hydropower plant was completed by December The upgrading and testing of generation unit 4 at the Golovnaya hydropower plant was completed on 26 December F. Implementation Arrangements 29. In Afghanistan, the Ministry of Energy and Water was designated as the executing agency and the Afghanistan Power Authority (DABM) as the implementing agency. The project implementation unit (PIU) was established in the ministry in November 2005 to manage ADB-financed projects and coordinate with Tajikistan counterparts. In September 2009, DABM was restructured as a new power utility, Da Afghanistan Breshna Sherkat (DABS). DABS took over the role of implementing agency for the project, and was bound by the terms and conditions of the project agreement, subsidiary loan agreement, and P. The implementation arrangements were satisfactory. 30. In Tajikistan, Barki Tojik was designated as the executing agency. It was to appoint a project director to take responsibility for day-to-day project operations and coordination with counterparts in Afghanistan. A new, independent PIU was to be set up specifically for the project. However, a PIU had already been set up in Barki Tojik in March 2001 with responsibility for coordination, procurement, disbursement, and reporting on projects implemented by Barki Tojik. In June 2006, this PIU was administratively and physically separated from Barki Tojik, and a project management unit was established under the Office of the President. 21 The project management unit was managed by a director and several deputy directors, and comprised 120 staff. It had significant experience in the implementation of projects financed by international financial institutions, including ADB. The implementation arrangements were satisfactory. 17 Loan effectiveness was delayed by 3 months to submit (i) revised subsidiary loan agreement and (ii) legal opinion. 18 The same contractor was awarded the contract for Golovnaya hydropower plant unit The contract for dredging of canals at the Centralnaya and Prepadnaya hydropower plants was awarded on 1 January In mid-june 2010, Barki Tojik agreed to test the system at reduced power and not to hold the contractor responsible for excitation system failure resulting from the problem in unit The project management unit was named the State Establishment Project Management Unit for Electro- Energy Sector.

21 7 31. Executing agencies, with the assistance of the implementation consultants, were required to establish comprehensive project performance management systems (PPMSs) to monitor and evaluate project performance, as well as delivery of planned facilities and project benefits under the Afghanistan and Tajikistan components. These requirements were complied with, but the focus was primarily on project implementation. The PPMSs did not adequately collect data on project benefits and beneficiaries on which to assess the impact and benefit of the project. The design and implementation of the PPMSs were less than satisfactory. G. Conditions and Covenants 32. Loan and grant covenants were generally complied with and are summarized in Appendix 5. Partial or noncompliance with covenants was mainly related to financial issues as follows: Afghanistan loan and grant (i) DABS operating ratio was below the required level of 90% for fiscal year (FY) 2012 only, but improved in each year since its establishment in (ii) DABS complied with the accounts receivable covenant in FY2010 and However, it was not in compliance in 2012 when accounts receivable rose to 4.3 months, in excess of the 3 months requirement. (iii) (iv) The Ministry of Energy and Water has not submitted the audited project financial statements for FY2012 and FY2013. DABS submission of entity audited financial statement for FY2013 is awaited. The DABS website does not provide project data or financial statements. Tajikistan loan (i) Barki Tojik met the covenanted 6 months accounts receivable in FY2008 and FY2009, but did not comply in FY when accounts receivable were required to be no more than 3 months billing. In FY2012, accounts receivable were almost 3 times the covenanted level at 8.8 months. (ii) Barki Tojik s operating ratio was above the required level of 90% every year since FY2008, except for FY2010 when the covenant was complied with. (iii) From FY2010, Barki Tojik s debt service coverage ratio was below the required level of 1.3. (iv) Tariffs were not adequately adjusted throughout the project implementation period to enable Barki Tojik to comply with financial covenants. (v) The notes to Barki Tojik s financial statements for FY2008 indicated that a part of Barki Tojik s transactions were carried out by mutual set-offs, barter, and other noncash settlements. This contravened the covenant that all barter trade would cease by the end of FY2007. No reports of barter trade were made in the annual reports of 2009 to (vi) Barki Tojik s website does not provide project data or financial statements. H. Related Technical Assistance 33. Technical assistance for Strengthening Corporate Management of Barki Tojik. The technical assistance (TA) was designed to build the capacity of Barki Tojik, focusing on internal management, customer responsiveness, and reliability. The approach proposed by the TA was to engage consultants in a performance-based management contract with an expected impact of improving commercial operations and an outcome of improved institutional capacity of Barki Tojik. Expected outputs were (i) a work plan for restructuring Barki Tojik with detailed steps for the first 3 5 years, (ii) prequalification documents and bidding documents for the management contract, and (iii) an evaluation of the bids.

22 8 34. After several months of debate, the government decided that a management contract was not an appropriate option at the time for Barki Tojik. ADB agreed to revise the TA to emphasize short-term improvements in Barki Tojik operations including implementing governance structures, improving efficiency in key areas (e.g., corporate planning and accounting), and raising operational efficiency to international standards. The change in focus was considered consistent with the original impact and outcomes. The output was revised to an updated sector restructuring plan and a corporate restructuring methodology for Barki Tojik. 35. Overall, the TA completion report (TCR) rated the TA partly successful because it did not achieve the output related to the management contract for Barki Tojik. 22 However, it did initiate the restructuring of Barki Tojik, to which the government and Barki Tojik were committed and which will continue to receive support from ADB. The restructuring of Barki Tojik was adopted under ADB s follow-on Regional Power Transmission Project, to improve the operational and financial performance of the power sector to strengthen Barki Tojik s capacity to service debt while providing high-quality electricity services. 36. Technical assistance for Improving the Capacity of Da Afghanistan Breshna Moassessa. The TA was designed to improve the institutional, technical, and financial capacity of DABM. The expected impact was to improve the capacity of the Ministry of Energy and Water to reduce risks that could undermine the sustainability of the assets financed by the loan. The expected outcomes were (i) strengthened institutional and management capacity, and (ii) improved capacity of technical employees, especially in transmission and distribution. The expected outputs were (i) enhanced staff capability in management and operations, financial management and accounting, human resources management, and customer care management; and (ii) improved technical efficiency of O&M. 37. The TCR stated that the institutional and management capacity building was not achieved and no consultant inputs were provided for this aspect of the TA. 23 It highlighted a lack of commitment on the part of DABM to strengthening its capacity, other than in relation to its technical employees. DABM was at the time in the process of restructuring into DABS and argued that it could not identify potential institutional and management trainees before the establishment of DABS. 38. The TCR concluded that the TA was highly relevant to the needs of the power sector, in particular the need to address the risks to sustainability of the assets financed under the Afghanistan loan. However, the TA was rated less effective because it did not achieve the institutional capacity building output, and less efficient given that no consultant inputs were provided for institutional capacity building. As a result, the TA was rated less likely sustainable and the overall TA rating was partly successful. I. Consultant Recruitment and Procurement 39. Under the Afghanistan loan, the contract for the main project management and implementation consultant was awarded in accordance with ADB Guidelines on the Use of Consultants, at $1.41 million using the quality- and cost-based selection (QCBS) procedure. The same consultant was engaged for both the Afghanistan and Tajikistan loans. The amount disbursed was $1.37 million, equivalent to 94.3% of the contract amount. Following the signing of the Afghanistan grant, a contract variation was approved on 21 November 22 ADB Technical Assistance Completion Report: Strengthening Corporate Management of Barki Tajik intajikistan. Manila (TA 4908-TAJ). 23 ADB Technical Assistance Completion Report: Improving the Capacity of Da Afghanistan Breshna Moassessa in Afghanistan. Manila (TA 4909-AFG).

23 extending the implementation consultant s contract to 31 December An additional amount of $0.634 million was added to the contract from the grant. Of this, $0.56 million (88%) was disbursed. 40. ADB supported the change in the consultant selection method from QCBS 80:20 to QCBS 90:10. The continuing conflict in Afghanistan creates unusual conditions in which consultants must use unconventional approaches to reach project sites, conduct test, supervise works, attract and retain qualified staff, and engage experts with special skills. The difficulty in mobilizing national and international specialists on a timely basis, maintaining close supervision of construction works, and advising the executing agency on urgent issues contributes to cost overruns and implementation delays. 41. Under the Tajikistan component, a single contract for $2.66 million was awarded in accordance with ADB Guidelines on the Use of Consultants using the QCBS procedure. 24 Two contract variations were then approved one to expand the scope of the consulting services to include a feasibility study for Vakhsh River optimization and SCADA, and the other to extend the completion date to the loan closing date of 31 December Actual disbursement was $1.98 million. 42. The procurement of works and goods and services was carried out in accordance with ADB s Procurement Guidelines. The original arrangement was to issue a single bidding document for the complete line, with bidders free to bid for the Afghanistan portion and/or the Tajikistan portion to improve competition. Bidding documents would be issued from Tajikistan. However, ADB supported the Government of Afghanistan s request to prepare separate bidding documents for the Afghanistan and Tajikistan components. A single bidding for two components of work with two employers is administratively complicated particularly for pre-award activities. Also, with ADB s approval, the demining contract was awarded through direct contracting due to the need to urgently proceed with demining works, the small contract amount ($.161,000), and the highly specialized nature of the service. 43. A summary of contracts awarded by ADB under each loan and the grant is in Appendix 6. Under the Afghanistan component, a contract for the transmission line construction was awarded under international competitive bidding for $32.9 million under the Afghanistan loan. 25 A contract variation with a value of $4.73 million was provided to the transmission line contractor under the Afghanistan grant. 44. Under the Tajikistan component, four contracts were awarded with a total value of $24.65 million. The contracts for the work at Sangtuda substation and construction of the transmission line for $20.93 million and the excitation system at Baipaza hydropower plant for $2 million were awarded to international contractors. The contract for the supply and installation of metering equipment for $1.7 million was awarded to a national company. The fourth contract, with a value of $0.02 million, was for resettlement and environmental activities. Actual disbursements were $13.02 million (62.2% of the contract value) for the Sangtuda substation and transmission line, $2.08 million for the excitation system at Baipaza hydropower plant (104% of the contract value), $1.65 million (97% of the contract value) for metering, and $0.02 (100% of the contract value) for resettlement activities. 24 The contract was awarded on 19 December This contract was awarded to the same contractor who was awarded the transmission line contract under the Tajikistan loan.

Tajikistan: Power Rehabilitation Project

Tajikistan: Power Rehabilitation Project Validation Report Reference Number: PCV: TAJ 2011-06 Project Number: 32513 Loan Number: 1817 April 2011 Tajikistan: Power Rehabilitation Project Independent Evaluation Department CURRENCY EQUIVALENTS (as

More information

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project

Report and Recommendation of the President to the Board of Directors. Proposed Grant Republic of Tajikistan: Regional Power Transmission Project Report and Recommendation of the President to the Board of Directors Project Number: 43150 July 2010 Proposed Grant Republic of Tajikistan: Regional Power Transmission Project CURRENCY EQUIVALENTS (as

More information

Afghanistan: Energy Supply Improvement Investment Program (Tranche 2)

Afghanistan: Energy Supply Improvement Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 47282-004 MFF Number: 0090 November 2016 Afghanistan: Energy Supply Improvement Investment Program (Tranche 2) This document is being disclosed to the

More information

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects

India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Technical Assistance Report Project Number: 51308-002 Transaction Technical Assistance Facility (F-TRTA) December 2017 India: Enhancing Capacity of State Utilities in Preparing Energy Sector Projects Distribution

More information

Bangladesh: Bangladesh India Electrical Grid Interconnection Project

Bangladesh: Bangladesh India Electrical Grid Interconnection Project Completion Report Project Number: 44192-013 Loan Numbers: 2661 and 3031 September 2016 Bangladesh: Bangladesh India Electrical Grid Interconnection Project This document is being disclosed to the public

More information

CASA-1000 Project List of FAQs

CASA-1000 Project List of FAQs 1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING CENTRAL ASIA SOUTH ASIA ELECTRICITY TRANSMISSION AND TRADE PROJECT (CASA-1000)

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING CENTRAL ASIA SOUTH ASIA ELECTRICITY TRANSMISSION AND TRADE PROJECT (CASA-1000) Public Disclosure Authorized The World Bank REPORT NO.: RES29565 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF CENTRAL ASIA SOUTH ASIA ELECTRICITY TRANSMISSION

More information

Philippines: Philippine Energy Efficiency Project

Philippines: Philippine Energy Efficiency Project Validation Report Reference Number: PVR-436 Project Number: 42001-013 Loan/Grant Numbers: 2507 and 0142 December 2015 Philippines: Philippine Energy Efficiency Project Independent Evaluation Department

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project

Report and Recommendation of the President to the Board of Directors. Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project Report and Recommendation of the President to the Board of Directors Project Number: 44198 May 2012 Proposed Loan and Grant Kyrgyz Republic: Power Sector Rehabilitation Project CURRENCY EQUIVALENTS (as

More information

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis

More information

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Validation Report Reference Number: PCV: PHI 2011-15 Project Number: 35379 Loan Number: 2012 July 2011 Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Independent

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

Project Completion Report

Project Completion Report Project Completion Report Project Number: 38074-013 Loan Number: 2208-UZB December 2011 Uzbekistan: Kashkadarya and Navoi Rural Water Supply and Sanitation Sector Project CURRENCY EQUIVALENTS Currency

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF TRANSMISSION GRID STRENGTHENING PROJECT LOAN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22644 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR: PRC 26198 PROJECT COMPLETION REPORT ON THE HUNAN LINGJINTAN HYDROPOWER PROJECT (Loan 1318-PRC) IN THE PEOPLE S REPUBLIC OF CHINA November 2003 CURRENCY EQUIVALENTS Currency

More information

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical

More information

Completion Report. Project Number: Loan Number: 2128 October Viet Nam: Northern Power Transmission Sector Project

Completion Report. Project Number: Loan Number: 2128 October Viet Nam: Northern Power Transmission Sector Project Completion Report Project Number: 32273 Loan Number: 2128 October 2012 Viet Nam: Northern Power Transmission Sector Project CURRENCY EQUIVALENTS Currency Unit dong (D) At Appraisal At Project Completion

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

Completion Report. Project Number: Loan Number: 1912 April Tajikistan: Emergency Baipaza Landslide Stabilization Project

Completion Report. Project Number: Loan Number: 1912 April Tajikistan: Emergency Baipaza Landslide Stabilization Project Completion Report Project Number: 36233 Loan Number: 1912 April 2006 Tajikistan: Emergency Baipaza Landslide Stabilization Project CURRENCY EQUIVALENTS Currency Unit somoni (TJS) At Appraisal At Project

More information

Periodic Financing Request Report. Afghanistan: Energy Supply Improvement Investment Program (Tranche 3)

Periodic Financing Request Report. Afghanistan: Energy Supply Improvement Investment Program (Tranche 3) Periodic Financing Request Report Project Number: 47282 005 MFF Number: 0090 September 2017 Afghanistan: Energy Supply Improvement Investment Program (Tranche 3) Distribution of this document is restricted

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project Validation Report Reference Number: PVR-360 Project Number: 40198 Loan Number: 2374 December 2014* Viet Nam: Ho Chi Minh CityLong ThanhDauGiay Expressway Technical Assistance Project Independent Evaluation

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:LAO 29284 ASIAN DEVELOPMENT BANK TECHNICAL ASSISTANCE TO ThE LAO PEOPLE'S DEMOCRATIC REPUBLIC FOR ThE CORPORATE AND FINANCIAL DEVELOPMENT OF ELECTRICIT DU LAO LI LI May 1996 - -I CURRENCY EQUIVALENTS

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT Public Disclosure Authorized The World Bank REPORT NO.: RES30161 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE

More information

Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000

Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000 Realizing a Central Asia-South Asia Regional Electricity Market: CASA-1000 Conference on Normalizing India-Pakistan Trade Salman Zaheer, The World Bank New Delhi, January 22, 2014 Examples of Regional

More information

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS: PROJECT 1 Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy

More information

India: Power Grid Transmission (Sector) Project

India: Power Grid Transmission (Sector) Project Completion Report Project Number: 38492-013 Loan Number: 2152 July 2017 India: Power Grid Transmission (Sector) Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

FRAMEWORK FINANCING AGREEMENT

FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT (Second Power Transmission Enhancement Investment Program) Parties This Framework Financing Agreement ( FFA ) dated 15 July 2016 is between

More information

India: Karnataka Urban Development and Coastal Environmental Management Project

India: Karnataka Urban Development and Coastal Environmental Management Project Validation Report Reference Number: PVR-334 Project Number: 30303 Loan Number: 1704 November 2014 India: Karnataka Urban Development and Coastal Environmental Management Project Independent Evaluation

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those

More information

RESTRUCTURING PAPER ON A. PROPOSED PROJECT RESTRUCTURING OF EMERGENCY POWER REHABILITATION PROJECT (CR 3933 & TF 54718) (June 22, 2004)

RESTRUCTURING PAPER ON A. PROPOSED PROJECT RESTRUCTURING OF EMERGENCY POWER REHABILITATION PROJECT (CR 3933 & TF 54718) (June 22, 2004) Document of The World Bank Report No: RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF EMERGENCY POWER REHABILITATION PROJECT (CR 3933 & TF 54718) (June 22, 2004) TO THE ISLAMIC REPUBLIC OF AFGHANISTAN

More information

ASIAN DEVELOPMENT BANK PPA: PAK 17003

ASIAN DEVELOPMENT BANK PPA: PAK 17003 ASIAN DEVELOPMENT BANK PPA: PAK 17003 PROJECT PERFORMANCE AUDIT REPORT ON THE KESC FIFTH POWER (SECTOR LOAN) PROJECT (Loan 925-PAK) IN PAKISTAN October 2001 CURRENCY EQUIVALENTS Currency Unit Pakistan

More information

Project Concept Note

Project Concept Note Project Concept Note I. Project Details Project Name Sector Project type Countries, in which the Project is to be implemented Nurek HPP Rehabilitation (Phase 1). Component: Rehabilitation of three generating

More information

Completion Report. Project Number: Loan Number: 1548 September Mongolia: Ulaanbaatar Heat Efficiency Project

Completion Report. Project Number: Loan Number: 1548 September Mongolia: Ulaanbaatar Heat Efficiency Project Completion Report Project Number: 29629 Loan Number: 1548 September 2008 Mongolia: Ulaanbaatar Heat Efficiency Project CURRENCY EQUIVALENTS Currency Unit togrog (MNT) At Appraisal At Project Completion

More information

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

Uzbekistan: Second Small and Microfinance Development Project

Uzbekistan: Second Small and Microfinance Development Project Completion Report Project Number: 42007-013 Loan Number: 2634 September 2015 Uzbekistan: Second Small and Microfinance Development Project This document is being disclosed to the public in accordance with

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

Periodic Financing Request Report. India: Assam Power Sector Investment Program (Tranche 2)

Periodic Financing Request Report. India: Assam Power Sector Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 47101-003 MFF Number: 0083 November 2015 India: Assam Power Sector Investment Program (Tranche 2) This document is being disclosed to the public in accordance

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization Completion Report Project Number: 46-01 Technical Assistance Number: 7857 April 016 Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization This document is being disclosed

More information

Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2)

Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 48078-004 MFF Number: 0092 September 2017 Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2) Distribution of this document

More information

Philippines: Mindanao Basic Urban Services Sector Project

Philippines: Mindanao Basic Urban Services Sector Project Validation Report Reference Number: PCV: PHI 2011-25 Project Number: 30551 Loan Number: 1843 September 2011 Philippines: Mindanao Basic Urban Services Sector Project Independent Evaluation Department ABBREVIATIONS

More information

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones Technical Assistance Report Project Number: 50004-001 Policy and Advisory Technical Assistance (PATA) October 2016 People s Republic of China: Study on Natural Resource Asset Appraisal and Management System

More information

India: Preparing for the Ara Canal Water Productivity Improvement Project

India: Preparing for the Ara Canal Water Productivity Improvement Project Technical Assistance Report Project Number: 52153-002 Transaction Technical Assistance (TRTA) June 2018 India: Preparing for the Ara Canal Water Productivity Improvement Project This document is being

More information

Validation Report. Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation Project. Operations Evaluation Department

Validation Report. Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation Project. Operations Evaluation Department Validation Report Reference Number: PCV:KAZ/KGZ 2008-35 Project Number: 29568 and 32463 Loan Numbers: 1774 and 1775(SF) November 2008 Kazakhstan and Kyrgyz Republic: Almaty Bishkek Regional Road Rehabilitation

More information

Completion Report. Project Number: Loan Number: 2091-AFG(SF) December Afghanistan: Afghanistan Investment Guarantee Facility Project

Completion Report. Project Number: Loan Number: 2091-AFG(SF) December Afghanistan: Afghanistan Investment Guarantee Facility Project Completion Report Project Number: 38912 Loan Number: 2091-AFG(SF) December 2011 Afghanistan: Afghanistan Investment Guarantee Facility Project CURRENCY EQUIVALENTS Currency Unit afghani (AF) At Appraisal

More information

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project Completion Report Project Number: 27250 Loan Number: 1472 August 2006 Philippines: Small Towns Water Supply Sector Project CURRENCY EQUIVALENTS Currency Unit Philippine peso (P) At Appraisal At Project

More information

Viet Nam: Microfinance Development Program (Subprograms 1 and 2)

Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Validation Report Reference Number: PVR-478 Project Numbers: 42235-013 and 42235-023 Loan Numbers: 2877 and 3213 December 2016 Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Independent

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

Afghanistan: Multitranche Financing Facility for Energy Sector Development Investment Program

Afghanistan: Multitranche Financing Facility for Energy Sector Development Investment Program Multitranche Financing Facility Administration Memorandum MFF Number: 0026 Project Numbers: Grant 0134, JFPR 9128 (Tranche 1), Grant 0184 (Tranche 2) June 2010 Afghanistan: Multitranche Financing Facility

More information

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Validation Report Reference Number: PVR-471 Project Number: 47337-001 Loan Number: 3080 December 2016 Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Independent Evaluation

More information

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program Facility Administration Manual Project Number: 42107 MFF Number: 0042-UZB Loan Numbers: 2635-UZB (Project 1), 2746-UZB (Project 2), and 2868-UZB (Project 3) 21 August 2013 Multitranche Financing Facility

More information

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) A. Approach FINANCIAL ANALYSIS 1. Financial analysis of the project was carried out in accordance with the Financial

More information

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO)

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) Board of Directors IN.247-11 14 October 2011 Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) The attached Report is circulated at the request of the Director

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Country Sector(s) Theme(s) Lending Instrument Project ID Borrower(s)

More information

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Validation Report November 2017 Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Reference Number: PVR-535 Program Number: 40061-013 Loan Number: 2619 and 8245 Grant Number:

More information

Mongolia: Regional Road Development Project

Mongolia: Regional Road Development Project Validation Report Reference Number: PVR-481 Project Numbers: 35377-013 and 35377-023 Loan/Grant Numbers: 2087, 2621, and 0199 December 2016 Mongolia: Regional Road Development Project Independent Evaluation

More information

Bhutan: Sustainable Rural Electrification Project

Bhutan: Sustainable Rural Electrification Project Validation Report Reference Number: PCV: BHU 2008-23 Project Number: 29242 Loan Number: 1712 July 2008 Bhutan: Sustainable Rural Electrification Project Operations Evaluation Department ABBREVIATIONS ADB

More information

Islamic Republic of Pakistan: Update on Energy Sector Plan

Islamic Republic of Pakistan: Update on Energy Sector Plan Technical Assistance Report Project Number: 50081-001 Knowledge and Support Technical Assistance (KSTA) August 2017 Islamic Republic of Pakistan: Update on Energy Sector Plan This The views document expressed

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 51360-002 Transaction Technical Assistance Facility (F-TRTA) April 2018 Turkmenistan: Preparing the Central Asia Regional Economic Cooperation Corridors 2, 3

More information

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project

Completion Report. Project Number: Loan Number: 2119/2120 December Azerbaijan: Urban Water Supply and Sanitation Project Completion Report Project Number: 35087 Loan Number: 2119/2120 December 2011 Azerbaijan: Urban Water Supply and Sanitation Project CURRENCY EQUIVALENTS Currency Unit Azerbaijan manat (AZN) At Appraisal

More information

Viet Nam: Mong Duong 1 Thermal Power Project

Viet Nam: Mong Duong 1 Thermal Power Project Completion Report Project Number: 39595-013 Loan Numbers: 2353 and 2610 July 2018 Viet Nam: Mong Duong 1 Thermal Power Project This document is being disclosed to the public in accordance with ADB s Public

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

Afghanistan: Regional Airports Rehabilitation Project (Phase 1)

Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Validation Report Reference Number: PVR 225 Project Number: 37136 Loan Number: 2105 December 2012 Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Independent Evaluation Department ABBREVIATIONS

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Unit Europe and Central Asia Region Document of The World Bank RESTRUCTURING

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2)

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Validation Report July 2017 Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Reference Number: PVR-497 Project Number: 36169-023 Loan Number: 2641 Grant Number: 0208 ABBREVIATIONS

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-52541) ON A GRANT. IN THE AMOUNT OF US$ 7.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-52541) ON A GRANT. IN THE AMOUNT OF US$ 7. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001143 IMPLEMENTATION COMPLETION AND RESULTS

More information

People s Republic of Bangladesh: Updating the Road Master Plan

People s Republic of Bangladesh: Updating the Road Master Plan South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) Technical Assistance Report Project Number: 40540-016 Transaction Technical Assistance (TRTA)

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1 PERIODIC FINANCING REQUEST Date: April 2012 To: Asian Development Bank 6 ADB Avenue Mandaluyong City, Metro Manila ATTENTION: Director General, Pacific Department Fax No. +632-632-6318 Sir: RE: Higher

More information

Evaluation Study. Midterm Review Process. Operations Evaluation Department

Evaluation Study. Midterm Review Process. Operations Evaluation Department Evaluation Study Reference Number: SES:REG 2008-78 Special Evaluation Study Update December 2008 Midterm Review Process Operations Evaluation Department ABBREVIATIONS ADB Asian Development Bank BTOR back-to-office

More information

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project Technical Assistance Report Project Number: 51039-001 Transaction Technical Assistance (TRTA) September 2017 Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

More information

Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project

Completion Report. Project Number: Loan Number: 2327 October Maldives: Domestic Maritime Transport Project Completion Report Project Number: 37265 Loan Number: 2327 October 2013 Maldives: Domestic Maritime Transport Project CURRENCY EQUIVALENTS Currency Unit Rufiyaa (Rf) At Appraisal At Project Completion (1

More information

ASIAN DEVELOPMENT BANK TAR:UZB 36498

ASIAN DEVELOPMENT BANK TAR:UZB 36498 ASIAN DEVELOPMENT BANK TAR:UZB 36498 TECHNICAL ASSISTANCE TO THE REPUBLIC OF UZBEKISTAN FOR DEVELOPMENT OF THE CAPITAL MARKET July 2003 CURRENCY EQUIVALENTS (as of 30 June 2003) Currency Unit sum SUM1.00

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR:NEP 26362 PROJECT COMPLETION REPORT ON THE KALI GANDAKI "A" HYDROELECTRIC PROJECT (Loan 1452-NEP[SF]) IN NEPAL April 2004 CURRENCY EQUIVALENTS (as of 15 March 2004) Currency

More information

Multitranche Financing Facility Annual Report 2017

Multitranche Financing Facility Annual Report 2017 May 2018 Multitranche Financing Facility Annual Report 2017 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. ABBREVIATIONS ADB Asian Development

More information

Pakistan: Decentralization Support Program

Pakistan: Decentralization Support Program Validation Report Reference Number: PCV: PAK 2011-53 Program Number: 34328 Loan Numbers: 1935/1936/1937/1938 December 2011 Pakistan: Decentralization Support Program Independent Evaluation Department ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

Myanmar: Power Distribution Improvement Project

Myanmar: Power Distribution Improvement Project Power Distribution Improvement Project (RRP MYA 46390) Project Administration Manual Project Number: 46390 November 2013 Myanmar: Power Distribution Improvement Project Contents ABBREVIATIONS I. PROJECT

More information

Kyrgyz Republic: Central Asia Regional Economic Cooperation Corridor 3 (Bishkek Osh Road) Improvement Project, Phase 4

Kyrgyz Republic: Central Asia Regional Economic Cooperation Corridor 3 (Bishkek Osh Road) Improvement Project, Phase 4 Central Asia Regional Economic Cooperation Corridor 3 (Bishkek Osh Road) Improvement Project, Phase 4 (RRP KGZ 45169) Project Administration Manual Project Number: 45169 Loan and Grant Numbers: L3056;

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR STRENGTHENING PROJECT LOAN OCTOBER 25, 2010 TO THE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR STRENGTHENING PROJECT LOAN OCTOBER 25, 2010 TO THE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES14735 Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE ENERGY SECTOR

More information

Policy Paper. March Establishing the Project Design Facility

Policy Paper. March Establishing the Project Design Facility Policy Paper March 2011 Establishing the Project Design Facility ABBREVIATIONS ADB Asian Development Bank ADF Asian Development Fund COBP country operations business plan DMC developing member country

More information

Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade and Distribution Project

Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade and Distribution Project Appendix 3 11 Technical Assistance Report Project Number: 51329-002 Transaction Technical Assistance (TRTA) November 2017 Lao People s Democratic Republic: Preparing the Northern Cross-Border Power Trade

More information

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Validation Report December 2018 Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Reference Number: PVR-565 Project Numbers: 41121-023, 41121-033, 41121-043, and 41121-053 MFF

More information

Mongolia: Development of State Audit Capacity

Mongolia: Development of State Audit Capacity Technical Assistance Report Project Number: 47198-001 Capacity Development Technical Assistance (CDTA) November 2013 Mongolia: Development of State Audit Capacity The views expressed herein are those of

More information

Cambodia: Road Asset Management Project

Cambodia: Road Asset Management Project Completion Report Project Number: 41123-013 Loan Number: 2406-CAM June 2015 Cambodia: Road Asset Management Project This document is being disclosed to the public in accordance with ADB's Public Communications

More information

Country Operations Business Plan. Afghanistan November 2015

Country Operations Business Plan. Afghanistan November 2015 Country Operations Business Plan November 2015 Afghanistan 2016 2018 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. CURRENCY EQUIVALENTS (as

More information