A Tale of Two Sisters: Bangladesh and Philippine PPP Programs 26 November 2014
|
|
- Sara Oliver
- 6 years ago
- Views:
Transcription
1 A Tale of Two Sisters: Bangladesh and Philippine PPP Programs 26 November 2014 Presented at the UNESCAP PPP Workshop on Public-Private Partnerships for Infrastructure Development in Myanmar
2 Background In early 2010, the governments of Bangladesh and Philippines both recognized a need to completely overhaul their approach to private participation in public infrastructure ADB, responding to this need, embarked on two Technical Assistance programs for national PPP framework development: Bangladesh December 2010 Philippines February 2011 ADB staff worked jointly to design the programs, drawing on Outline national policies generated by each government Each country s prior experience with PPPs both successes and failures Both countries had initially successful attempts at PPP in the late 1990s Neither repeated these successes for about 10 years at the time of the TA Drew on ADB s state-of-the-art knowledge of what elements were required for a workable, robust PPP program
3 Common principles, common design The following slides present the common elements of the Bangladesh and Philippine PPP programs The elements of these programs are now the standard by which successful national PPP programs are measured The World Economic Forum and the G-20 have both recognized the Philippine PPP program and its structures as the recommended approach for countries pursuing PPP G-20 Development Working Group Assessment of the Effectiveness of Project Preparation Facilities in Asia and Africa September World Economic Forum Accelerating Infrastructure Delivery: new evidence from international financial institutions September Why aren t we hearing the same things about the Bangladesh program?
4 Common elements of the PPP programs Central PPP Office A professionalized team led by a CEO with private sector experience Office sits above sector line ministries, serving all Empowered by the President/Prime Minister under both political and bureaucratic mandate to take control of the national development of PPP Enhanced Project Identification Objectively screen proposed projects from sector ministries/depts Use common criteria Assure they are viable as PPP Enhanced Project Preparation Use professional external advisors/consultants to prepare projects Preparation criteria in line with international project finance standards Development of robust project-level contracts that protect the interests of government, assure reasonable risk allocation, and are bankable Assure all preparatory work is done before letting out for tender
5 Common elements of the PPP programs Dedicated Project Development Funding Establish a fund that is used solely for PPP project preparation Allows coverage of the higher costs of professional advisors outside ordinary government operating budgets Fixed, objective criteria for consultant procurement and access to funds Transparent Tendering Process Standardized tendering process, outside ordinary govt procurement law Focused on achieving high quality output performance from projects (versus specifying inputs and quantities, like ordinary public sector procurement) Standardized prequalification documents to assure bidders have proper experience with building, financing and operating PPP projects Standardized request for proposal documents to assure bidders have all the information they need to lodge a firm proposal on an equal basis
6 Common elements of the PPP programs Consideration of PPP Project financial viability Seek to limit subsidies and rely on user fees wherever possible Seek to limit financial risk exposure of the government to PPP contracts, subject to the principle of fair risk allocation (party gets a risk who is best able to manage the risk) Subject to strict criteria, where a project is economically beneficial but commercially challenged, provide subsidies or viability gap financing from government, but limited to a maximum amount Public Financial Management Seek to quantify budget impacts and long-term liabilities that arise from PPP contracts Report on these metrics to Finance Ministry/Dept Track cumulative impacts of PPP program Monitor and manage exposures, currency Use as lever for driving future reforms at sector level
7 Bangladesh PPP structure CCEA provides: In-Principle Approval to proceed with project development Approves final project Line Ministry: Originates projects Prelim studies Technical resources Ultimate project ownership, regulatory oversight Planning Commission Sanctions Line Ministry development program Dept of Environment Compliance with environmental laws, approvals = PPP-specific functions = Other Govt functions Cabinet Committee on Economic Affairs Line Ministry Reviews and Approvals Law Ministry Contract vetting Project proposal Development coordination led by PPPO PPP Project PPPO PPP Office MOF PPP Unit PPPO determines which projects can access /need skills and financial support for project development Ministry of Finance Skills: Advisor Pool + Devel Money: PPP TA Fund PPPU reviews project proposals prepared by PPPO for financial vetting, quantifies and applies for financial supports Sanctions funding and supports VGF Budgeted Subsidies Guarantees 7
8 Philippine PPP Office Structure Independent Fund Manager Project Development and Monitoring Facility Hires and manages external advisors NEDA Office of the Exec Director PDMF Mgt Service Legal Service Policy Formulation & Evaluation Service Project Development Service Capacity Building & Knowledge Mgt Service Administrative Service Policy Formulation Project Development Mgt Information Svcs Finance Policy Evaluation & Monitoring Project Management Knowledge Mgt Human Resources Bulk of staff and services from this unit Capacity Building General Services
9 Actions taken Bangladesh Location Moved PPP functions from Board of Investment to under the Prime Minister s Office Staffing Established office with 6 govt administrative staff govt office Hired professionally experienced CEO Hired 6 staff professionallyoriented staff from govt cadre Fiscal oversight by MOF PPP unit Administers subsidies and support funds, against criteria Support funding from government PDF: $12m VGF: $325m Infra Fund: $200m Philippines Location Moved PPP Center from Dept of Trade & Industry to National Economic Development Authority Staffing Hired professionally experienced CEO Hired 20 professional staff initially Quickly began adding staff with growth in work load Fiscal oversight responsibility of PPP Center, initially Support funding from government Established PDMF: Initially, $13m Increased in increments to $90m Contingent Liabilities Fund: $200m
10 Outcomes to date ( ) Metric Bangladesh Philippines Office staffing: Initially (2Q2011) Now (4Q2014) (Professional/Total) 1/6 7/19 (Professional/Total) 16/20 75/100 Sectors being covered 7 8 Projects screened > 200 > 200 Projects identified Projects at concept stage 9 11 Projects procuring advisors 11 9 Projects under preparation 8 11 Projects tendered 4 15 Projects awarded 1* 8 * Project awarded before PPP framework and procedures completed; project currently stalled due to deficiencies in project preparation and contracts.
11 Challenges encountered both countries Project identification: First round is a battle with sector line ministries/departments Typically initially throw weak, non-viable or leftover projects at PPP unit Not used to having someone else vet their projects and have the full authority to do so Haven t had to think about performance outcomes previously, mostly focus on inputs and quantities Lack of understanding of commerciality, bankability, risk allocation Consultants/Advisors Procurement of transaction advisors requires material amounts of PPP staff time and effort and must be factored into development timeline Traditional national procurement standards may not be appropriate for advisors; focus is on quality and experience, less on cost Consultants/advisors need oversight, require PPP units to obtain key decisions from government ministries, both in sector and with umbrella level rules/policies
12 Challenges encountered both countries Project management in development PPP unit staff must have hands-on management of all aspects of the PPP project development process There must be sufficient staff of appropriate quality to manage projects Need to liaison with govt ministries on sector-based inputs, integration with other existing programs/infrastructure Need to support garnering of approvals, permissions from other govt bodies for the projects Tendering PPP units face tremendous pressure from government to get projects out the door, often before they are fully ready Evaluation of projects based on technical competency on a pass/fail basis worries technocrats Government ministries try to avoid key sector issues that impact project economics or ability to implement; this leads to challenges in developing fully-formed project contracts Staffing Never enough! Need procurement, legal, financial, and tech staff
13 Next steps in evolution Bangladesh Petitioning govt for more staff, outside of govt pay scale Greatly needed to accelerate consultant procurement, administer to projects under development/bidding, consult with govt ministries Exhausting PPPTAF monies; petitioning for top-up Nearing first success in 1Q15 Govt in need of proof of concept ahead of additional funding; will that be too late? Philippines Moved fiscal oversight unit out of PPP Center to Dept of Finance, creating adversarial review process Will manage quantify, track, and manage contingent liabilities arising from PPPs Near term prospects to get recycling of PDMF funds from awarded projects Govt is not topping up the PDMF as a result (not necessarily negative!)
14 Lessons learned Political will and leadership is of paramount importance Empowerment and independence of PPP unit is essential PPP unit leadership must be of highest professional quality Staffing quantity and quality of high importance; has material impact on speed, efficiency and quality of outcomes Clear, consistent, reliable rules, processes and institutional application is key to attracting investors and lenders Sustained commitment of government funds and resources required Adequate TA funding required upfront with external support from development partners ($1.725m in BAN vs $7.20m in PHI) Projects take longer to prepare and tender than initially anticipated: PDF monies need to be sized to account for this Once initial projects are through the process, it gets easier Outcomes from transparent competitive tendering have yielded High quality participants Value for money proposals
15 PPP, done correctly, can deliver too for Myanmar Public-Private Partnerships can be a key component of national development Creates additional sources of investment Can deliver higher efficiency and performance Complements public sector/sovereign investments Better manages national finances, and contingent liability exposures But getting it right is important There is a proven formula for success in PPP Grounded in the principles of international project finance Evidence shows that varying from this formula usually results in sub-optimal outcomes Structuring and tendering PPPs correctly requires Skills technical, legal, financial/commercial Project development capital to hire skills, conduct studies Informed management to drive outcomes, manage results National oversight of financial impacts for sustainability PPP holds potential for Government to achieve significant development investments at lowest cost and highest quality
16 ADB Contacts J. Grant Hauber PPP TA Project Manager and Principal Public-Private Partnership Specialist Public Management, Financial Sector and Trade Southeast Asia Department T: M: M: Thatha Hla Financial Sector Economist Public Management, Financial Sector and Trade Myanmar Resident Mission, Naypyitaw thla@adb.org T: M:
17 Bangladesh PPP structure Prime Minister PPP Advisory Committee Policy Consultation CEO In-Principle and Final Project Approvals Cabinet Committee on Economic Affairs Central point of PPP coordination for internal government, external investor, lender and civil society stakeholders. Screens, supports development of PPP projects, administers tendering, negotiates, and supports financing process on behalf of Government, specifically sector line ministries Core of PPP Program Creates and sanctions Annual Development Plan (ADP), which includes identification of specific development projects and associated capital budget allocation. Responsible for development of Five-year Plans Planning Commission Proposed development program PPP Office (PMO) PPP Project Proposals Line Line Ministries Line Ministries Line Ministries Ministries Fiscal Sanctioning of Individual PPP Projects Budget Allocation Sanctioned Projects and Expenditures in ADP PPP Unit (MOF) Finance (MOF) Fund Allocations Assesses fiscal viability and risk of PPP Projects Sanctions VGF, Subsidies Monitors Contingent Liabilities Sanctions and Administers Budgets for: Annual Development Plan (capital expenditure budget) Non-plan Budget (annual operating budgets) Special allocations for funds, such as PPPTAF, VGF, BIFF
Recent experience of establishing a PPP framework to mitigate fiscal risks in Bangladesh
(Strengthened Fiscal Management in Asia) Recent experience of establishing a PPP framework to mitigate fiscal risks in Bangladesh 4 June 2018 Mita Conference Hall, Tokyo PPP Authority Prime Minister s
More informationMINISTRY OF FINANCE AND ECONOMIC AFFAIRS
MINISTRY OF FINANCE AND ECONOMIC AFFAIRS Contents 1. PREAMBLE 4 2. THE POLICY OBJECTIVES 5 3. DEFINITION OF PPP 5 4. BENEFITS OF PPP 6 5. KEY GUIDING PRINCIPLES 7 6. SCOPE AND APPLICATION OF PPP PROJECTS
More informationThe World Bank Kenya Infrastructure Finance/PPP project (P121019)
Public Disclosure Authorized AFRICA Kenya Financial Systems Practice Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 4 ARCHIVED on 22-Dec-2014 ISR17114 Implementing Agencies: Public Private
More informationProblems and Prospects of Public Private Partnership in Bangladesh
Problems and Prospects of Public Private Partnership in Bangladesh M. Fouzul Kabir Khan North South University Dhaka, 16 July 2012 What is PPP? PPP is a form of medium/long term contractual arrangement
More informationBangladesh: Overview of the Public Private Partnership Program
Bangladesh: Overview of the Public Private Partnership Program Md Humayun Kabir Deputy Manager PPP Office (Prime Minister s Office) Date: 03 February 2014 Road to PPP: Bangladesh Scenario Public management
More informationWorld Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects. Workshop Program
World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects Workshop Program 3 June, 2015 Richard MacGeorge Successful preparation of bankable projects Getting Projects From Fairway
More informationHeadline Verdana Bold. Uganda PPP Act - Implications for Public Sector Accounting Kenneth LEGESI Deloitte (Uganda) Limited
Headline Verdana Bold Uganda PPP Act - Implications for Public Sector Accounting Kenneth LEGESI Deloitte (Uganda) Limited About us Kenneth Legesi Infrastructure and Capital Projects / PPP Advisory Deloitte
More informationEnvironmental Assessment Framework and Guidelines: Experience from the Philippines
Environmental Assessment Framework and Guidelines: Experience from the Philippines Presented by: Joe B. Tuyor Bishkek, Kyrgyz Republic March 26-28, 2008 Tbilisi, Georgia April 1-3, 2008 1 Outline of the
More informationProject Administration Manual
Project Administration Manual Project Number: 46538-002 November 2016 Proposed Loan and Administration of Grant and Technical Assistance Grant Islamic Republic of Pakistan: Supporting Public Private Partnership
More informationStrategy #1: Partnering with the Private Sector through PPP. EY Infrastructure Advisory. October 2017
Strategy #1: Partnering with the Private Sector through PPP EY Infrastructure Advisory October 2017 EY Infrastructure Advisory Page 2 EY s Infrastructure Advisory and Project Finance Advisory Capabilities
More informationAuditing Public Sector Projects and Programs. Speaker : Sanjay Vani The World Bank Washington DC
Auditing Public Sector Projects and Programs By Speaker : Sanjay Vani The World Bank Washington DC What is a Project and What is a Program? Auditing Public Sector Projects and Programs - Outline Stages
More informationLao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization
Completion Report Project Number: 46-01 Technical Assistance Number: 7857 April 016 Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization This document is being disclosed
More informationP3 Fundamentals and Best Practices in Resource and Project Management
Achieving better value, timeliness and accountability through public-private partnerships P3 Fundamentals and Best Practices in Resource and Project Management Ottawa, Ontario November 26, 2015 Greg Smith
More informationSumant Chak MAKING PPP ATTRACTIVE FOR PRIVATE FINANCE IN INFRASTRUCTURE THE INDIA STORY. Asian Institute of Transport Development
MAKING PPP ATTRACTIVE FOR PRIVATE FINANCE IN INFRASTRUCTURE THE INDIA STORY Sumant Chak Asian Institute of Transport Development Railway Staff College, Vadodara Course: BIMSTEC and MGC officers Course,
More informationBoosting Infrastructure Financing through Risk Mitigation Instruments
Boosting Infrastructure Financing through Risk Mitigation Instruments Financing Sources for Public-Private Partnerships Forum Kuala Lumpur, 25 November 2015 Dr Armand Hermawan CFO Indonesia Infrastructure
More informationLiberia Reconstruction Trust Fund Implementation Manual
Liberia Reconstruction Trust Fund Implementation Manual Updated November 2009 2011-02-28 LRTF Implementation Manual 1 I. Background... 3 II. Coverage... 3 III. General Principles... 4 IV. Project Development
More informationWorkshop on PPP in Roads and Highways
Workshop on PPP in Roads and Highways Vickram Cuttaree, PPP-Coordinator, Europe & Central Asia Member of the Global Expert Team on PPP June 7, 2011 Agenda Rationale for PPP and International Experience
More informationTechnical Assistance Report
Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia
More informationRepublic of the Maldives: Preparing Business Strategy for Port Development
Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed
More informationDraft PPP Policy Outline
Note 7 May 2012 Draft PPP Policy Outline This note is the seventh in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership (PPP) programs.
More informationRepublic of the Philippines: Government-Owned and -Controlled Corporations Reform
Technical Assistance Report Project Number: 39606 June 2006 Republic of the Philippines: Government-Owned and -Controlled Corporations Reform The views expressed herein are those of the consultant and
More informationThe Philippines. 1. Noteworthy practices for project preparation. Case Study PROJECT IDENTIFICATION FINANCING
Case Study The Philippines 1. Noteworthy practices for project preparation EXISTING ENABLING ENVIRONMENT Strong and effective institutional framework, with well-defined and clearly demarcated responsibilities
More informationOUTLINE TERMS OF REFERENCE FOR CONSULTANTS
Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical
More informationFACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS
INDONESIA INFRASTRUCTURE GUARANTEE FUND (IIGF) FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS United Nations Economic And Social Commission For Asia And
More informationCONFERENCE REPORT BACKGROUND
BACKGROUND Asia Pacific Infrastructure Partnership (APIP) Dialogue with the Government of Indonesia 22 October 2012 * 2:30 pm 5:30 pm Ballroom 3, The Ritz Carlton Jakarta Mega Kuningan, Jakarta, Indonesia
More informationDeveloping a PPP market: Getting the fundamentals right
Developing a PPP market: Getting the fundamentals right Essentials for private sector participation 17 March 2016 Why does private sector care about PPP projects? PPP projects offers stable cash flows
More informationProject Administration Instructions
Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to
More informationGOOD PRACTICE CASE STUDY MONGOLIA: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT
GOOD PRACTICE CASE STUDY MONGOLIA: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT M. Mozammal Hoque Vera Songwe December 2004 MONGOLIA: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT 1 CONTENTS
More informationThe Role of PT. Sarana Multi Infrastruktur in Infrastructure Development
The Role of PT. Sarana Multi Infrastruktur in Infrastructure Development 1 OUTLINE Background Profile Framework Financing Policy Challenges Target 2 BACKGROUND Rationale 1. Global economic condition 2.
More informationIslamic Republic of Pakistan: Enhancing Public- Private Partnerships in Punjab Project
Enhancing Public Private Partnerships in Punjab Project (RRP PAK 49128) Project Administration Manual Project Number: 49128-002 Loan, Grant, and TA Numbers: LXXXX; GXXXX; TAXXXX November 2017 Islamic Republic
More informationPROJECT PREPARATORY TECHNICAL ASSISTANCE
Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies
More informationKey issues considered in the dialogue: - what financing measures will best ensure bankable projects. Specifically, the dialogue focused on:
SUMMARY REPORT OF THE ASIA PACIFIC INFRASTRUCTURE PARTNERSHIP (APIP) DIALOGUE HELD WITH VIETNAM GOVERNMENT OFFICIALS AT THE MINISTRY OF FINANCE HANOI, VIETMAN 20 TH JULY 2012. Introduction: A highly constructive
More informationINTEGRATED SAFEGUARDS DATA SHEET
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET IDENTIFICATION / CONCEPT STAGE Date ISDS Prepared/Updated:
More informationDECREE ON THE ENVIRONMENT PROTECTION FUND
Lao People's Democratic Republic Peace independence Democracy Unity Prosperity Prime Minister s Office No. 146/PM Vientiane Capital, Date 06 June 2005 DECREE ON THE ENVIRONMENT PROTECTION FUND - Referring
More informationStrengthening the Coherence of the Financing for Development and Effective Development Cooperation Agendas
Strengthening the Coherence of the Financing for Development and Effective Development Cooperation Agendas Key Messages from Asia-Pacific Regional Consultation 27 th March 2015 At a meeting hosted by NEDA,
More informationGovernance Assessment (Summary) Nepal
Governance Assessment (Summary) Nepal Country Partnership Strategy: Nepal, 2013 2017 A. Current State of Governance GOVERNANCE ASSESSMENT 1. Nepal is passing through a historic political transition. The
More informationExamination Committee: Dr. Sundar Venkatesh (Chairman) Dr. Winai Wongsurawat (Co-chair) Dr. Yuosre Badir (Member)
Examination Committee: Dr. Sundar Venkatesh (Chairman) Dr. Winai Wongsurawat (Co-chair) Dr. Yuosre Badir (Member) Presented by Rathin Kumar Paul PMBF Programme, AIT 2011-2012 1 Introduction Provision for
More informationSECTOR ASSESSMENT (SUMMARY): CAPITAL MARKET DEVELOPMENT. 1. Sector Performance, Problems, and Opportunities
Second Capital Market Development Program (RRP BAN 43477) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CAPITAL MARKET DEVELOPMENT 1. Sector Performance, Problems, and Opportunities 1. Limited role of capital
More informationSECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities
Improving Public Expenditure Quality Program, SP1 (RRP VIE 50051-001) SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) 1 Sector Road Map 1. Sector Performance,
More informationATTACHED TECHNICAL ASSISTANCE
Third Capital Market Development Program (RRP BAN 45253) ATTACHED TECHNICAL ASSISTANCE A. Introduction 1. The attached technical assistance (TA) of $700,000 will support implementation of the proposed
More informationSECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT Sector Performance, Problems, and Opportunities
Sector Road Map Country Partnership Strategy: Fiji, 2014 2018 SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT 1 1. Sector Performance, Problems, and Opportunities 1. The government is responsible
More informationDetailed Recommendations 2: Develop Green Funds
Detailed Recommendations 2: Develop Green Funds 2 This is a background paper to the report: Establishing China s Green Financial System published by the Research Bureau of the People s Bank of China and
More informationPPP - ADB's role in structuring, financing and procurement. Asean Connectivity Forum 8 November, 2016
PPP - ADB's role in structuring, financing and procurement Asean Connectivity Forum 8 November, 2016 Contents I. Asian Development Bank products & procurement II. III. Challenges to PPP in Asia and the
More informationIPP TRANSACTION ADVISOR TERMS OF REFERENCE
IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction
More informationRepublic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance
Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved
More informationMEMORANDUM OF UNDERSTANDING
MEMORANDUM OF UNDERSTANDING March 2015 Memorandum of Understanding Between The Minister of Economic Development, Employment and Infrastructure And The Chair on behalf of the Ontario Infrastructure and
More informationINDONESIA ECONOMIC QUARTERLY CLOSING THE GAP. Frederico Gil Sander Lead Economist October 3, 2017
INDONESIA ECONOMIC QUARTERLY CLOSING THE GAP Frederico Gil Sander Lead Economist October 3, 2017 How is the economy doing? What to expect in 2018? Closing the gap Growth steady amid mostly favorable conditions
More informationOverview of the framework
Overview of the framework Need for a framework Economic growth and trade expansion in recent years have enhanced the relevance of port sector as a critical element in globalisation of the Indian economy.
More informationAnnex 1. Action Fiche for Solomon Islands
Annex 1 Action Fiche for Solomon Islands 1. IDENTIFICATION Title/Number FED/2012/023-802 Second Solomon Islands Technical Cooperation Facility (TCF II) Total cost EUR 1,157,000 Aid method / Method of implementation
More informationRecent Experiences in Assessing Public Infrastructure Management in Sri Lanka
Recent Experiences in Assessing Public Infrastructure Management in Sri Lanka Session II: Enhanced Framework For Public Investment Public Investment Processes And Benchmarking Tokyo Fiscal Forum 2018 June
More informationSUPPLEMENTARY DOCUMENT 3: THE PROPOSED NATIONAL COMMUNITY-DRIVEN DEVELOPMENT PROGRAM 1
KALAHI CIDSS National Community-Driven Development Project (RRP PHI 46420) SUPPLEMENTARY DOCUMENT 3: THE PROPOSED NATIONAL COMMUNITY-DRIVEN DEVELOPMENT PROGRAM 1 A. Program Objective and Outcomes 1. The
More informationReport and Recommendation of the President to the Board of Directors
Report and Recommendation of the President to the Board of Directors Project Number: 48458-001 October 2015 Proposed Programmatic Approach and Policy- Based Loan for Subprogram 1 Republic of the Philippines:
More informationMinistry of Foreign Affairs of Denmark. Concept Note Danida Business Finance Project Development Facility
Ministry of Foreign Affairs of Denmark Danida Concept Note Danida Business Finance Project Development Facility 5 May 2017 File No.: 2017-8006 1. CONTEXT... 3 2. PRESENTATION OF THE PROGRAMME... 5 3. MANAGEMENT
More informationPublic Financial Management
UNITAR Mustofi Fellowship Hiroshima, Japan 18 22 February 2012! Index! Overview and Objectives! Limitations and Problems! Public Financial Systems! Financial Management System Boundaries! Framework! Government
More informationAre you ready to go public?
Insights for 5executives Are you ready to go public? Make sure you have your internal controls house in order Of special interest to Chief audit executives Chief financial officers Jasmine, Chief Executive
More informationPartnership for Quality Infrastructure
Partnership for Quality Infrastructure Japan will fully mobilize public and private resources, in collaboration with other countries and international organizations, to address the immense demand for infrastructure
More informationThe Kuala Lumpur Statement on Financing Sources for Public-Private Partnerships in South-East Asia
Sub-Regional Expert Group Meeting (EGM) for South-East Asian Countries Financing Sources for Public-Private Partnerships (PPPs) The Kuala Lumpur Statement on Financing Sources for Public-Private Partnerships
More informationQueen Alia International Airport The Role of IFC in Facilitating Private Investment in a Large Airport Project
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Jordan s Queen Alia International Airport, located in Amman, was named best airport of
More informationQueen Alia International Airport The Role of IFC in Facilitating Private Investment in a Large Airport Project
www.ifc.org/thoughtleadership Note 35 April 2017 Queen Alia International Airport The Role of IFC in Facilitating Private Investment in a Large Airport Project In 2007 Jordan lacked the financial resources
More informationIndonesia. 1. Noteworthy practices for project preparation. Case Study
Case Study Indonesia 1. Noteworthy practices for project preparation EXISTING ENABLING ENVIRONMENT Domestic infrastructure financing institutions created by the Ministry of Finance are introducing good
More informationApplied Workshop on Preparing Infrastructure Projects 21 th - 25 th March Bangkok DAY 2
Applied Workshop on Preparing Infrastructure Projects 21 th - 25 th March Bangkok DAY 2 1 2 Recap of Day 1 Applying central concepts to structuring PPP projects S1: Project screening S2: Defining project
More information1 ST ISTANBUL PPP SUMMIT, 2015
1 ST ISTANBUL PPP SUMMIT, 2015 OVERVIEW OF THE PPP FRAMEWORK IN KENYA MS. HADIJA R. DIBA PPP UNIT, NATIONAL TREASURY - KENYA TUESDAY, 3 RD NOVEMBER 2015 BOĞAZİÇİ UNIVERSITY CAMPUS, ISTANBUL - TURKEY OUTLINE
More informationBudget Execution Rate in last three years- Baseline
Budget Execution Rate in last three years- Baseline 45 Average of Budget Execution % in last three Years 40 35 35.8 33 37 41 30 25 43 40 Ministry ofinterior Affairs 20 15 27 Ministry of Justice Ministry
More informationPROJECT PREPARATION TECHNICAL ASSISTANCE
12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility
More informationTHE MINING INVESTMENT AND GOVERNANCE REVIEW (MInGov)
THE MINING INVESTMENT AND GOVERNANCE REVIEW (MInGov) IGF Annual General Meeting October 26, 2016 Geneva, Switzerland Martin Lokanc The Mining Investment and Governance Review Funded by: Implemented by
More informationSUMMARY FINANCIAL MANAGEMENT ASSESSMENT
A. Introduction Emergency Assistance for Relief and Recovery from Typhoon Yolanda (RRP PHI 47337) UMMARY FINANCIAL MANAGEMENT AEMENT 1. This financial management assessment was prepared in accordance with
More informationRepublic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2
Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those
More informationClimate Change Finance Mainstreaming: A Snapshot
Climate Change Finance Mainstreaming: A Snapshot The Budget Cycle: Three basic Phases Oversight Preparation Implementation 2 Key Concepts Government/ CC Mitigation and Adaptation Policies Public Financial
More informationThe UNOPS Budget Estimates, Executive Board September 2013
The UNOPS Budget Estimates, 2014-2015 Executive Board September 2013 1 Key results of 2012 Benchmarks and standards Content UNOPS strategic plan 2014-2017 UNOPS budget estimates 2014-2015 Review of the
More informationPeople s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing
Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management
More informationGOVERNMENT OF ARUNACHAL PRADESH DEPARTMENT OF PLANNING
GOVERNMENT OF ARUNACHAL PRADESH DEPARTMENT OF PLANNING No. PD (PPP) 3/2010-11 Dated Itanagar, the 12th April, 2011 To. The Principal Secretaryl Commissioner/Secretary, GOVT. OF ARUNACHAL PRADESH. Sub:
More informationORISSA PUBLIC PRIVATE PARTNERSHIP POLICY-2007
ORISSA PUBLIC PRIVATE PARTNERSHIP POLICY-2007 PLANNING & CO-ORDINATION DEPARTMENT RESOLUTION No.12711 / PPP 38/2006 Dated 07 th August 2007 Sub: - ORISSA PUBLIC PRIVATE PARTNERSHIP (PPP) POLICY- 2007 1
More informationTHE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 )
THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) VIRGINIA DEPARTMENT OF TRANSPORTATION ( VDOT ) VIRGINIA DEPARTMENT OF RAIL AND PUBLIC TRANSPORTATION ( DRPT ) RESPONSE TO REQUEST FOR INFORMATION
More informationSUPPORTING INFRASTRUCTURE DEVELOPMENT IN ASEAN ECONOMIES: THE ACCESS TO RISK MITIGATION INSTRUMENTS. Knut Gummert, OECD Southeast Asia Division
SUPPORTING INFRASTRUCTURE DEVELOPMENT IN ASEAN ECONOMIES: THE ACCESS TO RISK MITIGATION INSTRUMENTS Knut Gummert, OECD Southeast Asia Division UNESCAP EGM meeting 25 November 2015 Outline i. OECD projects
More informationPublic-Private Partnerships in Infrastructure From Theory to Practice Astana, February 12-16, 2007
Monday, February 12, 2007 8:00 am Registration Opening Session Opening of the PPPI in Kazakhstan Workshop Welcome note from the host country representative: Mr. Aslan Musin, Minister of Economy and Budget
More informationPROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR
Filed: 0-0- EB-0-0 Page of 0 PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR.0 PURPOSE This evidence provides an overview of the nuclear operations project portfolio and other related project work. The project
More informationThe Role of Alternative Lenders
The Role of Alternative Lenders AND THE RELEVANCE TO SMALL BUSINESSES TODAY Business Lending. Simplified. Christophe Choquart VP Business Development & Strategic Partnerships Office : 678.264.8584 Fax
More informationGuidelines For Rajasthan Infrastructure Project Development Fund (RIPDF)
Guidelines For Rajasthan Infrastructure Project Development Fund (RIPDF) PPP Cell Planning Department Government of Rajasthan Contents 1. The RIPDF and its Role 2 i. Background of the RIPDF ---------------------------
More informationRole of Private Equity in Urban
Role of Private Equity in Urban Infrastructure July 18, 2013 Agenda Private Equity in India An overview Indian Infrastructure opportunity Key framework facilitating Infrastructure investment Uba Urban
More informationSECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT
A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide
More informationAudit of Regional Operations Manitoba Region
Audit of Regional Operations Manitoba Region WESTERN ECONOMIC DIVERSIFICATION CANADA Audit & Evaluation Branch December 2010 Table of Contents 1.0 Executive Summary 2 Findings 2 Statement of Assurance
More informationMobilizing Private Capital for Energy Efficiency through PPP Structures
Mobilizing Private Capital for Energy Efficiency through PPP Structures ADB s PPP Transaction Support for the State of Melaka s Large-scale LED Street Lighting Project, Malaysia 8 June 2017 Asia Clean
More informationGeneral management: update
PROGRAMME, BUDGET AND ADMINISTRATION EBPBAC16/2 COMMITTEE OF THE EXECUTIVE BOARD 3 May 2012 Sixteenth meeting Provisional agenda item 4.1 General management: update Report by the Secretariat 1. This document
More informationCITIZEN ENGAGEMENT IN BUDGETING AND PUBLIC ACCOUNTABILITY
CITIZEN ENGAGEMENT IN BUDGETING AND PUBLIC ACCOUNTABILITY Emilia T. Boncodin Professor University of the Philippines 6 th Session Committee of Experts in Public Administration April 10 14, 2007 United
More informationBusiness Transformation Project/Common Purpose 3.01 Procurement
MINISTRY OF COMMUNITY AND SOCIAL SERVICES Business Transformation Project/Common Purpose 3.01 Procurement Historically, the Ministry of Community and Social Services has provided social assistance to needy
More informationIndia. 1. Noteworthy practices for project preparation. Case Study
Case Study India 1. Noteworthy practices for project preparation EXISTING ENABLING ENVIRONMENT Programmatic approach to project development through specialised institutions established by the government
More informationAlternative ways of Financing Urban Development
External Support for Decentralization Reforms & Local Governance Systems in the Asia Pacific: Better Performance, Higher Impact? Cities Development Initiative for Asia Alternative ways of Financing Urban
More informationEstablishment of a Self- Sustaining Environmental Investment Service in the East Asian Seas Region
Project Proposal: Establishment of a Self- Sustaining Environmental Investment Service in the East Asian Seas Region by the GEF/UNDP/IMO Regional Programme on Partnerships in Environmental management for
More informationThe World Bank Ghana - PPP Project (P125595)
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Ghana Finance & Markets Global Practice IBRD/IDA Adaptable Program Loan FY 2012
More informationEIB Procurement Policy and Best Practice
EIB Procurement Policy and Best Practice José Luis Alfaro, Head of Procurement 1 Table of Contents EIB EIB Procurement Policy Best practice Procurement of services Tender documents Prequalification criteria
More informationFinancing Sustainable Infrastructure In Asia. Fei Yu Deputy Representative Asian Development Bank North American Representative Office
Financing Sustainable Infrastructure In Asia Fei Yu Deputy Representative Asian Development Bank North American Representative Office Agenda The Asia Scene The sustainable infrastructure gap The current
More informationASIA-PACIFIC FINANCIAL FORUM OVERVIEW
ASIA-PACIFIC FINANCIAL FORUM OVERVIEW EXECUTIVE SUMMARY The Asia-Pacific Financial Forum (APFF) Symposium was held on April 10-11, 2013 in Sydney, Australia. The Symposium was jointly sponsored by the
More informationPCDIP. Philippine City Disaster Insurance Pool
PCDIP Philippine City Disaster Insurance Pool Disaster Risk The Philippines is located in one of the world s most disaster-prone regions. Positioned on the Pacific Ring of Fire and within the Western North
More informationNINETY-SEVENTH MEETING WASHINGTON, D.C. APRIL
DEVELOPMENT COMMITTEE (Joint Ministerial Committee of the Boards of Governors of the Bank and the Fund on the Transfer of Real Resources to Developing Countries) NINETY-SEVENTH MEETING WASHINGTON, D.C.
More information162,951,560 GOOD PRACTICES 1.9% 0.8% 5.9% INTEGRATING THE SDGS INTO DEVELOPMENT PLANNING BANGLADESH POPULATION ECONOMY US$
GOOD PRACTICES INTEGRATING THE SDGS INTO DEVELOPMENT PLANNING BANGLADESH In this brief: Country context The whole of society approach Institutional arrangements for achieving the SDGs The Development Results
More informationIn Confidence. Office of the Minister for Regional Economic Development. Chair, Cabinet THE PROVINCIAL GROWTH FUND. Purpose
In Confidence Office of the Minister for Regional Economic Development Chair, Cabinet THE PROVINCIAL GROWTH FUND Purpose This paper sets the broad parameters for the Provincial Growth Fund. This will enable
More informationMEDICAL SCHEMES ACT OF SOUTH AFRICA AMENDMENT BILL, 2018
MEDICAL SCHEMES ACT OF SOUTH AFRICA AMENDMENT BILL, 2018 Purpose The Medical Schemes Amendment Bill 2017 ( the Bill ) seeks to improve The legislative oversight of the medical schemes industry, To align
More informationPTB KAPP PTB was set-up in 2008, under Article 12 of Law 7/2008 to serve as the main body responsible for PPP projects implementation
KAPP s Mission Transition from PTB to KAPP PTB KAPP PTB was set-up in 2008, under Article 12 of Law 7/2008 to serve as the main body responsible for PPP projects implementation Bureau under Ministry of
More informationPublic Private Partnership in Highway Sector in Punjab, India
Public Private Partnership in Highway Sector in Punjab, India Infrastructure Governance Roundtable March 24 th, 2006 Kulwinder Singh Rao Deputy Project Director Punjab Roads & Bridges Development Board
More informationMTEF Development in Abu Dhabi. Fiscal Policy Unit October 31, 2010
MTEF Development in Abu Dhabi Fiscal Policy Unit October 31, 2010 Index Abu Dhabi Overview Medium-Term Expenditure Framework Overview Components, Process, Document Setting Budget Ceilings Macroeconomic
More information