P3 Fundamentals and Best Practices in Resource and Project Management

Size: px
Start display at page:

Download "P3 Fundamentals and Best Practices in Resource and Project Management"

Transcription

1 Achieving better value, timeliness and accountability through public-private partnerships P3 Fundamentals and Best Practices in Resource and Project Management Ottawa, Ontario November 26, 2015 Greg Smith Vice-President of Finance, Risk, and Administration and CFO

2 Definition P3s are a long-term performance-based approach for procuring public infrastructure where the private sector assumes a major share of the responsibility in terms of risk and financing for the delivery and the performance of the infrastructure, from design and structural planning, to long-term maintenance. 2

3 P3s Improving Resource and Project Management Thorough Analysis: qualitative assessment and quantitative assessment Benefits outweigh the costs Value-for-money on whole-of-life costs Competitive selection process drives value while achieving innovation Risk transfer through development of robust and detailed performance specifications Defined and measurable asset performance specifications for O&M Clear regime of asset renewal and repair based on condition and performance of assets 3

4 PPP Canada: Leading the Federal Government s P3 Agenda Acts as a Source of Expertise Developing and sharing knowledge to provide PPP leadership Advances Federal P3 Projects Advises federal clients on the identification, development, and execution of federal PPPs Supports Other Levels of Government Advises on, and invests in P3 projects being considered by provinces, territories, municipalities and First Nations 4

5 Traditional Procurement vs. P3 Procurement Assets Assets and services Input terms Components of delivery are separated Paid during or in full upon construction completion Output terms Components of delivery are bundled Partially paid over the life of asset - linked to operational performance. Risks are mainly retained Risks are mainly transferred 5

6 P3s: A different approach to infrastructure delivery P3s are about delivery: not funding, ownership or asset/service need P3s address three weaknesses in traditional delivery: risk: by linking payment to performance and employing discipline of private capital at risk whole life-cycle optimization: by integrating design, build, operate and maintain into single contract innovation: by specifying deliverable in terms of what service is expected not how to achieve it Benefits of P3s need to be assessed in relation to cost of private sector capital and procurement 6

7 P3 Characteristics Integration A P3 contract, or Project Agreement, typically includes all of the phases of an asset: from design & construction to operations and maintenance and how it will be financed In a P3 contract, the public sector retains the ownership of the asset A P3 contract is not a joint venture with the private sector, a coownership, a divesture of an asset or a lease contract 7

8 P3 Characteristics Performance The public sector includes performance specifications that define what is required rather than how it is done Encourages innovation in the private sector Includes powerful financial incentives and a strong monitoring regime to promote compliance through each phase of the project The public sector transfers risks that the private sector is best able to manage, such as: Risk of cost overruns, design deficiencies, early deterioration, construction delay, etc. 8

9 P3 Characteristics Financing Most P3s are financed by debt and equity, and rely on performance-based payments to be repaid. As a result: The financiers exercise a great deal of due diligence and oversight on the project The financing anchors the risk transfer to Project Co, and provides strong incentives for compliance with terms of the Project Agreement 9

10 P3 Benefits and Costs 10

11 Value-for-Money (VFM) Value for money compares the cost of traditional procurement vs. the cost of P3 procurement taking into consideration: Whole-of-life costs: total cost of ownership over the life of the asset Risk: total cost of risk retained by the public sector Discounting: present value of costs over the life of the asset 11

12 VFM Assessment VfM ensures projects are suitable for a P3 VfM will also support decision-making and rationale for the P3. Screening Tool Decision Support Tool Authorization to Proceed Disclosure and Transparency Only projects which clearly demonstrate positive VfM should be selected for procurement as a P3 Supports negotiations with bidders Evaluation of impact of capital markets conditions Serves as a check on quality of proposals from bidders Ensures that you have received good value proposals Can be used to demonstrate value to the public 12

13 Value for Money Construction Costs 2,500.0 Operations and Maintenance Costs 2, % VfM Risk Adjustment Transaction Cost Lifecycle Costs 1,500.0 Competitive Neutrality Financing Costs Financing Costs Competitive Neutrality Transaction Costs 1, Lifecycle Costs Operating and Maintenance Costs Construction Costs Risk Adjustment - PSC PPP 13

14 Risk Adjustment Most jurisdictions have developed standard risk matrices for public infrastructure projects ( common risks) Risk workshops are typically used to identify which risks apply to a given project Risk workshops or research on historic projects are used to estimate the likelihood that risks will occur and their impacts under different procurement options Transferred and Retained Risks are modeled through a Monte Carlo simulation Typically the total amount of estimated risk is lower under a P3, reflecting a better allocation of risk between public and private sector 14

15 Risk Transfer Comparison Project Risks Traditional P3 Public Sector Private Sector Public Sector Private Sector Approvals and Permits Land use approvals Environmental permits Development & Design Design Error Design Omissions Unforeseen site conditions Construction Cost Overruns Schedule Overruns Material inflation Labour disputes Operations & Maintenance Performance Changes in legislation Increased maintenance costs Finance Interest Rates after closure Sourcing of capital construction

16 Risk Transfer Comparison Design Build Finance & Maintain Model Traditional Model Risk Category Cost Base Probability Impact Probability Impact Portion of DBFM % 10th perct Typical 90th perct % 10th perct Typical 90th perct 4.00 Construction 4.01 Weather Design & Construction 5.00% 0.00% 0.25% 0.50% 5.00% 0.00% 0.25% 0.50% 4.02 Construction Delays Design & Construction 50.00% 0.00% 0.25% 1.00% 90.00% 1.00% 2.00% 5.00% 4.03 Failure to build to design. Design & Construction 1.00% 1.00% 2.50% 5.00% 1.00% 1.00% 2.50% 5.00% 4.04 Acceleration to maintain schedule - Construction Impact Design & Construction 50.00% 1.00% 2.00% 5.00% 75.00% 0.00% 0.25% 1.00% 4.05 Acceleration to maintain schedule - Labour Impact Design & Construction 2.00% 1.00% 10.00% 15.00% 2.00% 1.00% 3.00% 5.00% 4.06 Construction safety obligations Design & Construction 5.00% 0.00% 0.25% 2.00% 5.00% 0.00% 0.25% 2.00% 4.07 Force Majeure Design & Construction 1.00% 3.00% 5.00% 10.00% 1.00% 3.00% 5.00% 10.00% 4.08 Adequacy of Insurance Design & Construction 1.00% 5.00% 10.00% 15.00% 1.00% 5.00% 10.00% 15.00% 4.09 Acute Market Conditions Design & Construction 25.00% 1.00% 3.00% 4.00% 25.00% 1.00% 3.00% 4.00% 4.10 Deficiencies as Work Progresses Design & Construction 25.00% 0.00% 0.25% 5.00% 50.00% 0.00% 0.25% 5.00% 4.11 Latent Defects Design & Construction 5.00% 1.00% 3.00% 5.00% 5.00% 1.00% 3.00% 5.00% 4.12 Resource Availability; equipment Design & Construction 5.00% 0.25% 0.50% 0.75% 5.00% 0.25% 0.50% 0.75% 4.13 Resource Availability; materials, cement, steel, etc. Design & Construction 5.00% 0.25% 0.50% 0.75% 5.00% 0.25% 0.50% 0.75% 4.14 Resource Availability; Labour Design & Construction 10.00% 0.25% 0.50% 0.75% 10.00% 0.25% 0.50% 0.75% 16

17 PPP Canada Risk Analysis: Top 10 Transferred Risks Name % of Total Transferred Risk % of Total Transferred Risk (Cumulative) 1. Project schedule 30% 30% 2. Asset residual 18% 48% 3. Construction management efficiency/coordination 4. Due diligence in preparation of the tender/rfp specifications 10% 58% 7% 65% 5. Latent defects 6% 71% Top 3 Risks Represent 58% of Total Risk Transfer 6. Innovation 4% 75% 7. Quality management 3% 78% 8. Traffic management 3% 81% 9. Tendering competition 2% 83% 10. Scope changes initiated by the Sponsor 2% 85% 17

18 Interpreting VFM Results Sample Output Net Present value ($M) Public Sector Comparator (PSC) PPP (Shadow Bid) DBFM Difference Base Costs Base Costs Construction Costs 750 Construction Costs 750 Operating and Maintenance Costs 500 Operating and Maintenance Costs 500 Lifecycle Costs 154 Lifecycle Costs 154 Sub-Total 1,404 Sub-Total 1, % Financing Costs 0* Financing Costs 226 Sub-Total 1,404 Sub-Total 1,630 (226) -16.1% Competitive Neutrality 120 Competitive Neutrality 0 Transaction Costs 25 Transaction Costs 34 Sub-Total 1,549 Sub-Total 1,664 (115) -7.4% Risk Adjustment 440 Risk Adjustment 90 Total 1,989 Total 1, % * Discounting the payments made by the public sector in the PSC model explicitly accounts for the implied public sector financing cost. VfM Savings are typically expressed as a percentage of the traditional cost 18

19 VFM Methodologies Jurisdictions analyze the same project elements and essentially yield the same conclusion, although there are differences in methodologies: Different discount rates (risk-free vs. risk-adjusted) Quantify risks differently (research vs. workshops) Risk Adjustment approaches vary Different treatments of innovation and efficiencies 19

20 P3s Improving Resource and Project Management Thorough Analysis: qualitative assessment and quantitative assessment Benefits outweigh the costs Value-for-money on whole-of-life costs Competitive selection process drives value while achieving innovation Risk transfer through development of robust and detailed performance specifications Defined and measurable asset performance specifications for O&M Clear regime of asset renewal and repair based on condition and performance of assets 20

21 CONTACT US 100 Queen Street, Suite 630 Ottawa, Ontario K1P 1J9 Canada Telephone: Fax:

Infrastructure Impact and Challenges P3s in the Water/Wastewater Sector. Stefan Dery, PPP Canada June 8, 2016 Ottawa, ON

Infrastructure Impact and Challenges P3s in the Water/Wastewater Sector. Stefan Dery, PPP Canada June 8, 2016 Ottawa, ON Infrastructure Impact and Challenges P3s in the Water/Wastewater Sector Stefan Dery, PPP Canada June 8, 2016 Ottawa, ON Introduction PPP Canada Leading the Government s P3 Agenda Acts as a Source of Expertise

More information

The Benefits of P3s. Why do P3s work?

The Benefits of P3s. Why do P3s work? The Benefits of P3s Why do P3s work? P3s are a long-term performance-based approach for procuring public infrastructure where the private sector assumes a major share of the responsibility in terms of

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Government of Newfoundland and Labrador

Government of Newfoundland and Labrador Government of Newfoundland and Labrador Corner Brook Long Term Care Project Value for Money Report Table of contents 1. Limitations... 3 2. Executive Summary... 4 3. Background... 5 3.1 Project Description

More information

Public Private Partnerships (PPPs) Projects

Public Private Partnerships (PPPs) Projects Development Process of Public Private Partnerships (PPPs) Projects By Dr Paul H K Ho 1 Disclaimer Funded by Commerce, Industry and Technology Bureau, The Government of the Hong Kong Special Administrative

More information

Public Private Partnerships

Public Private Partnerships Public Private Partnerships A Presentation to the Association of Financial Professionals of Canada Edmonton Chapter March 20, 2013 Alternative Capital Financing Office Alberta Treasury Board and Finance

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

Government of Newfoundland and Labrador. Central Region Long Term Care Project Value for Money Assessment

Government of Newfoundland and Labrador. Central Region Long Term Care Project Value for Money Assessment Government of Newfoundland and Labrador Central Region Long Term Care Project Value for Money Assessment Government of Newfoundland and Labrador Central Region Long Term Care Project Limitations Ernst

More information

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Department of Supply and Services - Public-Private Partnership: Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Contents

More information

Contents Corporate Profile History and Qualifications of Altus Helyar Select Services to Building Owners and Developers...

Contents Corporate Profile History and Qualifications of Altus Helyar Select Services to Building Owners and Developers... Contents Letter of Transmittal Contents...1 1 Corporate Profile...2 1.1 History and Qualifications of Altus Helyar...3 1.2 Select Services to Building Owners and Developers...4 1.3 Risk Management Services...4

More information

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.05 Ministry of Infrastructure (formerly the Ministry of Economic Development, Employment and Infrastructure) Infrastructure Ontario Alternative Financing and Procurement Follow-Up on

More information

Value for Money and Project Report

Value for Money and Project Report Value for Money and Project Report Biosolids Project City of Greater Sudbury June 2013 Table of Contents Section 1: Executive Summary... 1 1.1 Overview... 1 Section 2: Project Overview... 3 2.1 Project

More information

GOVERNMENT OF NUNAVUT PUBLIC-PRIVATE PARTNERSHIP POLICY

GOVERNMENT OF NUNAVUT PUBLIC-PRIVATE PARTNERSHIP POLICY POLICY STATEMENT GOVERNMENT OF NUNAVUT PUBLIC-PRIVATE PARTNERSHIP POLICY The GN believes that a cooperative approach to building infrastructure through public-private partnerships (P3) can be an appropriate,

More information

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016

P3 CONTRACTS. Morteza Farajian, Ph.D. November 2016 P3 CONTRACTS Morteza Farajian, Ph.D. November 2016 What is a Public-Private Partnership (P3)? Overview of P3s Definition P3 Defined A P3 involves a partnership between the public and private sector to

More information

Government of Newfoundland and Labrador. New Adult Mental Health Facility Project Value for Money Assessment

Government of Newfoundland and Labrador. New Adult Mental Health Facility Project Value for Money Assessment Government of Newfoundland and Labrador New Adult Mental Health Facility Project Value for Money Assessment Government of Newfoundland and Labrador Central Region Long Term Care Project April 2018 Limitations

More information

VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT

VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT 1 2 3 4 Highway 407 East Phase 1 Project Artist s rendering Highlights of Highway 407 East Phase 1 Highway 407 East will help to relieve congestion

More information

Public-Private Partnerships (P3)

Public-Private Partnerships (P3) Public-Private Partnerships () Agenda What is a? How are s structured? De-mystified 1 Defined UK, Canada, USA A Public-Private Partnership (PPP) is a contractual agreement between a public agency (federal,

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

VALUE FOR MONEY ASSESSMENT TORONTO SOUTH DETENTION CENTRE M AK I N G P R O J E C T S H AP P EN: TORONTO SOUTH DETENTION CENTRE - P AG E 1 -

VALUE FOR MONEY ASSESSMENT TORONTO SOUTH DETENTION CENTRE M AK I N G P R O J E C T S H AP P EN: TORONTO SOUTH DETENTION CENTRE - P AG E 1 - VALUE FOR MONEY ASSESSMENT TORONTO SOUTH DETENTION CENTRE - P AG E 1 - - P AG E 2 - - P AG E 3 - - P AG E 4 - - P AG E 5 - ARTIST S RENDERING OF THE TORONTO SOUTH DETENTION CENTRE Image Courtesy of Integrated

More information

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships Budapest, Hungary March 7 8, 2007 The views expressed in this paper are those of the

More information

City Policy & Procedure

City Policy & Procedure City Policy & Procedure Subject: PUBLIC-PRIVATE PARTNERSHIP (P3) POLICY Policy Number: #1011 Effective: September 3rd, 2014 Purpose: The City of Brandon Public-Private Partnership (P3) Policy intends to

More information

Integrated Capital Planning Manual

Integrated Capital Planning Manual 0 Integrated Capital Planning Manual August 2017 0 Contents Introduction... 1 Annual Integrated Capital Planning Cycle... 3 Integrated Capital Plan Submission... 8 Business Case Guide and Template... 11

More information

Life-Cycle Project Delivery

Life-Cycle Project Delivery Life-Cycle Project Delivery A Note for Discussion IndII Round Table 11 th December 2012 Concerns with Conventional Project Delivery Government pays for inputs, not outputs Incentive for time/cost over-runs

More information

VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT

VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT VALUE FOR MONEY ASSESSMENT TRILLIUM HEALTH PARTNERS CREDIT VALLEY HOSPITAL SITE PRIORITY AREAS REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - Credit Valley Hospital Priority

More information

Table of Contents. Volume III Reports our 2011 Value-for-Money Work 3 Acknowledgements... 5

Table of Contents. Volume III Reports our 2011 Value-for-Money Work 3 Acknowledgements... 5 Table of Contents Chapter 1 Introductory Comments Volume III Reports our 2011 Value-for-Money Work 3 Acknowledgements... 5 Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor

More information

ONTARIO INFRASTRUCTURE AND LANDS CORPORATION. Value for Money Assessment. Sinai Health System Phase 3A Redevelopment Project at Mount Sinai Hospital

ONTARIO INFRASTRUCTURE AND LANDS CORPORATION. Value for Money Assessment. Sinai Health System Phase 3A Redevelopment Project at Mount Sinai Hospital ONTARIO INFRASTRUCTURE AND LANDS CORPORATION Value for Money Assessment Sinai Health System Phase 3A Redevelopment Project at Mount Sinai Hospital June 2017 Table of Contents I. EXECUTIVE SUMMARY 2 Ð 2

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

THE OTTAWA HOSPITAL REGIONAL CANCER PROGRAM REDEVELOPMENT PROJECT

THE OTTAWA HOSPITAL REGIONAL CANCER PROGRAM REDEVELOPMENT PROJECT VALUE FOR MONEY ASSESSMENT THE OTTAWA HOSPITAL REGIONAL CANCER PROGRAM REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - - PAGE 6 - - PAGE 7 - The Ottawa Hospital Artist s rendering

More information

CONFEDERATION LINE PROCUREMENT AS A PUBLIC PRIVATE PARTNERSHIP. Nancy Schepers Deputy City Manager, Planning and Infrastructure City of Ottawa

CONFEDERATION LINE PROCUREMENT AS A PUBLIC PRIVATE PARTNERSHIP. Nancy Schepers Deputy City Manager, Planning and Infrastructure City of Ottawa CONFEDERATION LINE PROCUREMENT AS A PUBLIC PRIVATE PARTNERSHIP Nancy Schepers Deputy City Manager, Planning and Infrastructure City of Ottawa OVERVIEW Project Overview Business Case & Benefits Procurement

More information

Delivering Public Private Partnerships in PNG

Delivering Public Private Partnerships in PNG Port Moresby Chamber of Commerce-INA Public Private Partnership Seminar Pt Moresby, 22 nd February, 2012 1.4 Delivering Public Private Partnerships in PNG Michael Regan Professor of Infrastructure Institute

More information

Procurement models for District Energy System Projects

Procurement models for District Energy System Projects Procurement models for District Energy System Projects IDEA Conference Presented by Tomasz Smetny-Sowa, Senior Director Energy Services Acquisition Program June 13, 2018 Real Property Services Branch Public

More information

VALUE FOR MONEY ASSESSMENT WATERLOO REGION CONSOLIDATED COURTHOUSE MAKING PROJECTS HAPPEN: WATERLOO REGION CONSOLIDATED COURTHOUSE - PAGE 1 -

VALUE FOR MONEY ASSESSMENT WATERLOO REGION CONSOLIDATED COURTHOUSE MAKING PROJECTS HAPPEN: WATERLOO REGION CONSOLIDATED COURTHOUSE - PAGE 1 - VALUE FOR MONEY ASSESSMENT WATERLOO REGION CONSOLIDATED COURTHOUSE - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - ARTIST S RENDERING OF THE WATERLOO REGION CONSOLIDATED COURTHOUSE Courtesy of ITS

More information

NIAGARA HEALTH SYSTEM S NEW HEALTH-CARE COMPLEX

NIAGARA HEALTH SYSTEM S NEW HEALTH-CARE COMPLEX VALUE FOR MONEY ASSESSMENT NIAGARA HEALTH SYSTEM S NEW HEALTH-CARE COMPLEX - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - NIAGARA HEALTH SYSTEM ARTIST S RENDERING Preliminary concept of the new Niagara Health

More information

Risk Assessment of the Niagara Tunnel Project

Risk Assessment of the Niagara Tunnel Project Canadian Society of Value Analysis October 24, 2006 Risk Assessment of the Presented by: David Eden, P. Eng., Ontario Power Generation Susan Sherman, P.Eng.,URS Canada Inc Overview Qualitative Risk Analysis

More information

Treasury Board Secretariat. Follow-Up on VFM Section 3.07, 2015 Annual Report RECOMMENDATION STATUS OVERVIEW

Treasury Board Secretariat. Follow-Up on VFM Section 3.07, 2015 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.07 Treasury Board Secretariat Infrastructure Planning Follow-Up on VFM Section 3.07, 2015 Annual Report Chapter 1 Follow-Up Section 1.07 RECOMMENDATION STATUS OVERVIEW # of Status of

More information

ONTARIO INFRASTRUCTURE AND LANDS CORPORATION. Value for Money Assessment. Eglinton Crosstown Light Rail Transit

ONTARIO INFRASTRUCTURE AND LANDS CORPORATION. Value for Money Assessment. Eglinton Crosstown Light Rail Transit ONTARIO INFRASTRUCTURE AND LANDS CORPORATION Value for Money Assessment Eglinton Crosstown Light Rail Transit February 2016 Table of Contents I. EXECUTIVE SUMMARY 2 ÐÐ 2 ÐÐAlternative Financing and Procurement

More information

Infrastructure Ontario Alternative Financing and Procurement

Infrastructure Ontario Alternative Financing and Procurement Infrastructure Ontario Alternative Financing and Procurement Presentation for the High Ground Panel on Public Finance: Who s Picking Up The Tab? Bonnie Lysyk, Auditor General of Ontario March 20, 2015

More information

VALUE FOR MONEY ASSESSMENT BLUEWATER HEALTH REDEVELOPMENT PROJECT

VALUE FOR MONEY ASSESSMENT BLUEWATER HEALTH REDEVELOPMENT PROJECT VALUE FOR MONEY ASSESSMENT BLUEWATER HEALTH REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Bluewater Health Artist s Rendering Farrow Partnership Architects Inc. Enhanced Services at

More information

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager Developing the Power Sector through Private Investment in Mongolia Edgar Saravia Program Manager October 2008 Setting the Context Government of Mongolia ( GoM ) wishes to introduce PSP in power generation

More information

AGENDA ITEM #9 SUMMARY

AGENDA ITEM #9 SUMMARY AGENDA ITEM #9 SUMMARY Briefing on business considerations and state law requirements for the use of a comprehensive development agreement to develop a transportation project. Strategic Plan Relevance:

More information

Particular Primary Principles of Public Private Partnerships. Doug Sanders, P.Eng., LL.B. November 2, 2011

Particular Primary Principles of Public Private Partnerships. Doug Sanders, P.Eng., LL.B. November 2, 2011 Particular Primary Principles of Public Private Partnerships Doug Sanders, P.Eng., LL.B. November 2, 2011 Introduction Highways, water and wastewater treatment facilities, buildings, all targets for PPP

More information

Value for Money Test in Korea

Value for Money Test in Korea Global Roundtable on Value for Money Value for Money Test in Korea Hyeon PARK Executive Director Public and Private Infrastructure Investment Management Center (PIMAC), KDI hpark@kdi.re.kr/ +82-19-445-2511

More information

Group Exercise to Screen a PPP Project for Financial Feasibility

Group Exercise to Screen a PPP Project for Financial Feasibility World Bank & Brazilian Ministry of Transport Workshop on the Toolkit for PPP in Roads and Highways Group Exercise to Screen a PPP Project for Financial Feasibility Cesar Queiroz, Ph.D. World Bank Brasilia,

More information

Public-Private Partnerships: Are Canadians Getting the Full Picture?

Public-Private Partnerships: Are Canadians Getting the Full Picture? Public-Private Partnerships: Are Canadians Getting the Full Picture? Publication No. 2015-50-E 26 June 2015 Lindsay McGlashan Economics, Resources and International Affairs Division Parliamentary Information

More information

Problems and Prospects of Public Private Partnership in Bangladesh

Problems and Prospects of Public Private Partnership in Bangladesh Problems and Prospects of Public Private Partnership in Bangladesh M. Fouzul Kabir Khan North South University Dhaka, 16 July 2012 What is PPP? PPP is a form of medium/long term contractual arrangement

More information

VALUE FOR MONEY ASSESSMENT CENTRE FOR ADDICTION AND MENTAL HEALTH CENTRE FOR ADDICTION AND MENTAL HEALTH REDEVELOPMENT PROJECT - PAGE 1 -

VALUE FOR MONEY ASSESSMENT CENTRE FOR ADDICTION AND MENTAL HEALTH CENTRE FOR ADDICTION AND MENTAL HEALTH REDEVELOPMENT PROJECT - PAGE 1 - VALUE FOR MONEY ASSESSMENT CENTRE FOR ADDICTION AND MENTAL HEALTH - PAGE 1 - - PAGE 1 - - PAGE 2 - Architectural rendering of CAMH Gateway Building Courtesy of Carillion Health Solutions Highlights of

More information

WAYPOINT CENTRE FOR MENTAL HEALTH CARE REDEVELOPMENT PROJECT (FORMERLY MENTAL HEALTH CENTRE PENETANGUISHENE)

WAYPOINT CENTRE FOR MENTAL HEALTH CARE REDEVELOPMENT PROJECT (FORMERLY MENTAL HEALTH CENTRE PENETANGUISHENE) VALUE FOR MONEY ASSESSMENT WAYPOINT CENTRE FOR MENTAL HEALTH CARE REDEVELOPMENT PROJECT (FORMERLY MENTAL HEALTH CENTRE PENETANGUISHENE) - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - - PAGE 5 - Waypoint Centre

More information

Workshop on PPP in Roads and Highways

Workshop on PPP in Roads and Highways Workshop on PPP in Roads and Highways Vickram Cuttaree, PPP-Coordinator, Europe & Central Asia Member of the Global Expert Team on PPP June 7, 2011 Agenda Rationale for PPP and International Experience

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

PPP Canada. PPP Canada Inc. Annual Report to Parliament on the Privacy Act. April 1, 2012 March 31, 2013

PPP Canada. PPP Canada Inc. Annual Report to Parliament on the Privacy Act. April 1, 2012 March 31, 2013 PPP Canada Inc. Annual Report to Parliament on the Privacy Act April 1, 2012 March 31, 2013 1. Introduction The Privacy Act, which took effect on July 1, 1983, extends to individuals the right of access

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

Public Private Partnerships 101

Public Private Partnerships 101 Public Private Partnerships 101 Tony Elkins, Commercial Director October 6, 2016 Cintra s LBJ Managed Lanes P3, Dallas, Texas The Ferrovial Group Development Over The Entire Infrastructure Lifecycle INFRASTRUCTURE

More information

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects GOLDEN EARS BRIDGE Alternative Transportation Financing ITE Quad Conference - May 2009 Fred Cummings Vice-President, Major Construction Projects Golden Ears Bridge Project Context/Project Overview Project

More information

Scarborough Subway Extension Project Delivery Options. City Manager Deputy City Manager & Chief Financial Officer

Scarborough Subway Extension Project Delivery Options. City Manager Deputy City Manager & Chief Financial Officer STAFF REPORT ACTION REQUIRED Scarborough Subway Extension Project Delivery Options Date: April 8, 2015 EX5.6 To: From: Wards: Reference Number: Executive Committee City Manager Deputy City Manager & Chief

More information

SUDBURY REGIONAL HOSPITAL REDEVELOPMENT PROJECT

SUDBURY REGIONAL HOSPITAL REDEVELOPMENT PROJECT VALUE FOR MONEY ASSESSMENT SUDBURY REGIONAL HOSPITAL REDEVELOPMENT PROJECT - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Sudbury Regional Hospital Artists Rendering Nicholls Yallowega Belanger Architects

More information

VALUE FOR MONEY ASSESSMENT WOMEN S COLLEGE HOSPITAL MAKING PROJECTS HAPPEN: WOMEN S COLLEGE HOSPITAL - PAGE 1 -

VALUE FOR MONEY ASSESSMENT WOMEN S COLLEGE HOSPITAL MAKING PROJECTS HAPPEN: WOMEN S COLLEGE HOSPITAL - PAGE 1 - VALUE FOR MONEY ASSESSMENT WOMEN S COLLEGE HOSPITAL - PAGE 1 - - PAGE 2 - Artist s Rendering of Women s College Hospital Courtesy of Women s College Partnership Highlights of the new Women s College Hospital

More information

Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS

Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS 1.1 Introduction Before the Sanctioning Authority can consider approving expenditure proposals, certain analysis needs to be carried out and presented

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing PPP Project Cycle Checklists and

More information

Value for Money Assessment Forensic Services and Coroner s Complex

Value for Money Assessment Forensic Services and Coroner s Complex Value for Money Assessment Forensic Services and Coroner s Complex - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - RENDERING OF THE FORENSIC SERVICES AND CORONER S COMPLEX Image Courtesy of Carillion Secure

More information

Evaluating Potential PBI Projects. April 22, 2016 Portland, Oregon

Evaluating Potential PBI Projects. April 22, 2016 Portland, Oregon Evaluating Potential PBI Projects April 22, 2016 Portland, Oregon What Is WCX? 501(c)(3) non-profit Formed by Oregon, Washington, California Advised by British Columbia A publicly-funded resource to public

More information

3.07. Infrastructure Stimulus Spending. Chapter 3 Section. Background. Ministry of Infrastructure

3.07. Infrastructure Stimulus Spending. Chapter 3 Section. Background. Ministry of Infrastructure Chapter 3 Section 3.07 Ministry of Infrastructure Infrastructure Stimulus Spending Background The global economic crisis in 2008 led governments around the world to adopt economic-stimulus measures. In

More information

Purpose. 2 Third Crossing Business Plan

Purpose. 2 Third Crossing Business Plan Business Plan April 18, 2017 Purpose This is the third of three information sheets on critical pieces of work related to the preliminary design and business plan development for the Third Crossing. This

More information

The Potential Role of Public-Private Partnerships in Delivering Metro Projects

The Potential Role of Public-Private Partnerships in Delivering Metro Projects The Potential Role of Public-Private Partnerships in Delivering Metro Projects PUBLIC-PRIVATE PARTNERSHIPS (P3) Public Sector Common Interest Private Sector What is a Public-Private Partnership? > Collaboration

More information

Audi0ng P3 Projects: Challenges, Opportuni0es and Lessons Learned

Audi0ng P3 Projects: Challenges, Opportuni0es and Lessons Learned Audi0ng P3 Projects: Challenges, Opportuni0es and Lessons Learned Rick Kennedy Chief Audit Execu.ve & Assistant Deputy Minister Ontario Internal Audit Division (OIAD), Treasury Board Secretariat John Reed

More information

INFRASTRUCTURE FINANCE AND PPP

INFRASTRUCTURE FINANCE AND PPP INFRASTRUCTURE FINANCE AND PPP INFRASTRUCTURE FINANCE AND PPP (Course Director: Meg Osius) Program Overview and Objectives In this three-day program participants will become familiar with the wide array

More information

Value for Money (VfM) Analysis Virginia s experiences and lessons learned

Value for Money (VfM) Analysis Virginia s experiences and lessons learned Value for Money (VfM) Analysis Virginia s experiences and lessons learned May 28, 2013 Morteza Farajian Program Manager Virginia s Enabling P3 Legislation Public-Private Transportation Act of 1995 Intent

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

Public Private Partnerships

Public Private Partnerships Public Private Partnerships Osgoode Certificate in Construction Law 19 November 2013 Timothy J. Murphy Chief Marketing Partner tim.murphy@mcmillan.ca Outline 1. Different P3 Models 2. Typical DBFM Transaction

More information

Assessing risk in infrastructure public private partnerships

Assessing risk in infrastructure public private partnerships Bond University epublications@bond Faculty of Society and Design Publications Faculty of Society and Design 9-25-2014 Assessing risk in infrastructure public private partnerships Michael Regan Bond University,

More information

Honolulu Rail Transit Project

Honolulu Rail Transit Project EXECUTIVE SUMMARY 3/20/2017 P3 Assessment for the Honolulu Rail Transit Project Executive Summary Honolulu Rail Transit Project Contents I. Background and Overview... 2 II. Key Findings... 3 1. Public

More information

The Bridges of Wellington County

The Bridges of Wellington County feature The Bridges of The Ontario Good Roads Association (OGRA) partnered with the Residential & Civil Construction Alliance of Ontario (RCCAO) and the Ministry of Transportation to undertake the Bridges

More information

Project Management Certificate Program

Project Management Certificate Program Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949

More information

Auditor General s Office

Auditor General s Office Auditor General s Office Review of Infrastructure Stimulus Funding Opportunities Exist to Improve Controls over Construction Projects Transmittal Report Audit Report Management s Response Jeffrey Griffiths,

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

Public Private Partnerships

Public Private Partnerships Revisiting the State and the Market The New Zealand Governance Centre The University of Auckland Friday 28 th October 2011 Public Private Partnerships Michael Regan Professor of Infrastructure Institute

More information

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD http://pmsymposium.umd.edu 1 APPLICATIONS Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE 2018 Project Management Symposium Friday, May 11, 2018 9:45am

More information

Updated Financial Analysis Final Draft

Updated Financial Analysis Final Draft Solar Market Pathways: San Francisco Solar and Storage for Resilience Project December 2017 Final Draft Important Notice This report was prepared by Arup North America Ltd. ( Arup ) in its capacity as

More information

Undertaking Successful PPPs in Kazakhstan

Undertaking Successful PPPs in Kazakhstan Undertaking Successful PPPs in Kazakhstan Stephen Watson Head of Service PPP Astana, Kazakhstan 24 October 2013 image courtesy of stock.xchng Contents PPP Principles PPPs in Kazakhstan Renewables in Kazakhstan

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework Economic growth and trade expansion in recent years have enhanced the relevance of port sector as a critical element in globalisation of the Indian economy.

More information

Infrastructure Ontario TRACK RECORD 2017 REPORT

Infrastructure Ontario TRACK RECORD 2017 REPORT Infrastructure Ontario TRACK RECORD 2017 REPORT CONTENTS EXECUTIVE SUMMARY A. BACKGROUND INFORMATION A1 Background of Infrastructure Ontario...4 A2 Background of Third-Party Consultant - Hanscomb...5 B.

More information

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP Construction Risk in P3 Projects Timothy J. Murphy Partner McMillan LLP Risk Transfer in a P3 Key aspects of a P3: Private sector financing Public sector clarity through output specifications Integrated

More information

Public Private Partnerships, The Rules Oranjestad February 18, Paul Swanenvleugel

Public Private Partnerships, The Rules Oranjestad February 18, Paul Swanenvleugel Public Private Partnerships, The Rules Oranjestad Paul Swanenvleugel Paul Swanenvleugel Director PricewaterhouseCoopers Advisory N.V. P.O.Box 9616 1006 GC Amsterdam The Netherlands Ph: +31 88 792 32 19

More information

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project http://dx.doi.org/10.3991/ijoe.v9i3.2804 Wei Peng 1,2, Honglei Liu 1, * 1 Tongji University, Shanghai

More information

Sameh I. Mobarek Senior Counsel Energy, LEGPS Member, Global Expert Team on Public-Private Partnerships. PPP Financing Overview

Sameh I. Mobarek Senior Counsel Energy, LEGPS Member, Global Expert Team on Public-Private Partnerships. PPP Financing Overview Sameh I. Mobarek Senior Counsel Energy, LEGPS Member, Global Expert Team on Public-Private Partnerships PPP Financing Overview What is a Public-Private Partnership? A PPP is a long-term (5 to 30 year)

More information

P3 Value for Money Assessment and Project Report. Alberta Schools Alternative Procurement (ASAP) Project Phase II

P3 Value for Money Assessment and Project Report. Alberta Schools Alternative Procurement (ASAP) Project Phase II P3 Value for Money Assessment and Project Report Alberta Schools Alternative Procurement (ASAP) Project Phase II September 2010 Table of Contents 1. Summary: Using a P3 for 10 new schools - did it work?...3

More information

An Overview of P3s in Maryland

An Overview of P3s in Maryland An Overview of P3s in Maryland Greater Baltimore Committee Transportation Summit May 19, 2015 1 Discussion Outline Public Private Partnerships (P3s) overview Maryland P3 Law Transportation P3 Process (Regulatory)

More information

Public Private Partnerships An overview from the legal perspective

Public Private Partnerships An overview from the legal perspective Public Private Partnerships An overview from the legal perspective Ren Niemann Partner Allens is an independent partnership operating in alliance with Linklaters LLP. 1 What is a public private partnership?

More information

10-Year Economic Impact Assessment of Public-Private Partnerships in Canada ( )

10-Year Economic Impact Assessment of Public-Private Partnerships in Canada ( ) 10-Year Economic Impact Assessment of Public-Private Partnerships in Canada (2003-2012) Prepared for The Canadian Council for Public-Private Partnerships Prepared by InterVISTAS Consulting Inc. Rev. 10

More information

Public Private Partnerships in the National Health Service: The Private Finance Initiative

Public Private Partnerships in the National Health Service: The Private Finance Initiative Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

CERTIFICATION AND INTERNAL CONTROL REGIME FOR CROWN CORPORATIONS

CERTIFICATION AND INTERNAL CONTROL REGIME FOR CROWN CORPORATIONS Internal Management Oversight: CERTIFICATION AND INTERNAL CONTROL REGIME FOR CROWN CORPORATIONS Crown Corporation Guidance This document is intended as advice or guidance and as a source of considerations

More information

Collective Allowances - Sound Credit Risk Assessment and Valuation Practices for Financial Instruments at Amortized Cost

Collective Allowances - Sound Credit Risk Assessment and Valuation Practices for Financial Instruments at Amortized Cost Guideline Subject: Collective Allowances - Sound Credit Risk Assessment and Valuation Practices for Category: Accounting No: C-5 Date: October 2001 Revised: July 2010 This guideline outlines the regulatory

More information

Model Concession Agreement for Highways: An Overview

Model Concession Agreement for Highways: An Overview Model Concession Agreement for Highways: An Overview - Gajendra Haldea The highways sector in India is witnessing significant interest from both domestic as well as foreign investors following the policy

More information

LONG TERM FINANCE AND RISK ALLOCATION ENHANCING ENERGY INFRASTRUCTURE AS AN ASSET-CLASS IN BRAZIL

LONG TERM FINANCE AND RISK ALLOCATION ENHANCING ENERGY INFRASTRUCTURE AS AN ASSET-CLASS IN BRAZIL LONG TERM FINANCE AND RISK ALLOCATION ENHANCING ENERGY INFRASTRUCTURE AS AN ASSET-CLASS IN BRAZIL LONG-TERM FINANCING AND RISK ALLOCATION THE SCOPE OF OUR ANALYSIS THIS POSITION PAPER WILL FOCUS ON ISSUES

More information

«Kekava Bypass» Case Study

«Kekava Bypass» Case Study «Kekava Bypass» Case Study 28 September, 2017 Contents Introduction 3 Project details 6 Legal aspects Procurement procedure 15 Legal aspects PPP Agreement 22 Finance aspects 26 Off balance sheet treatment

More information

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Ahsan Jamal Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Introduction For the last couple of years, we have seen enormous growth in the construction industry of Pakistan due to

More information

Doheny Desalination Project Value-for-Money Analysis. March

Doheny Desalination Project Value-for-Money Analysis. March Doheny Desalination Project Value-for-Money Analysis March 22 2017 Presentation Overview Team Introductions Goals of the VfM Analysis Financial Model Estimated Monthly Impacts to Typical Households In

More information

PPP PUBLIC PRIVATE PARTNERSHIP

PPP PUBLIC PRIVATE PARTNERSHIP PPP PUBLIC PRIVATE PARTNERSHIP Definition by MOF 1. An arrangement between Government and Private party 2. To provide public assets and/or related services for public benefit 3. Private party makes investments

More information