Doheny Desalination Project Value-for-Money Analysis. March

Size: px
Start display at page:

Download "Doheny Desalination Project Value-for-Money Analysis. March"

Transcription

1 Doheny Desalination Project Value-for-Money Analysis March

2 Presentation Overview Team Introductions Goals of the VfM Analysis Financial Model Estimated Monthly Impacts to Typical Households In District Service Area Risks/ Risk Adjusted Cash Flows Discussion 2

3 Team Introductions Mark Donovan, PE - GHD Desalination Program Manager 20 years of seawater desalination experience delivering projects across the globe under various project delivery methods Greg Finlayson - GHD Senior Principal Water & Strategy Technical Program Manager Victorian Desalination Project (120 mgd / AU$3B) Charles Snyder Professional Infrastructure Consulting Services (PICS) California Infrastructure Fund Bechtel Group PWC Securities 3

4 Key Questions facing SCWD to implement the Doheny Desalination Project 1. Which project delivery method is most appropriate? Design-build-operate (DBO), or Public-private-partnership (PPP) 2. Does the preferred delivery method change with different project sizes? 5 mgd base case from previous investigations 15 mgd larger regional project 4

5 What is a VfM? Value for Money is a tool used to assess the relative life-cycle costs and benefits of alternative project delivery methods Will a PPP delivery compare favorably with traditional public sector project financing undertaken by the District? Does greater risk transfer (value) offered by PPP outweigh its extra costs (money)? 1. Development of cash flow model 2. Risk identification / quantification 3. Risk-adjusted cash flow analysis 4. Recommendations 5

6 Assumptions and Limitations Key assumptions of our analysis have been covered in this presentation. However it is recommended that this presentation is viewed in the context of the full VfM report which contains further details. In parallel to this VfM analysis, CDMSmith is completing a District-level Reliability Study. Therefore, the focus of this VfM report is not the decision to execute the Doheny Desalination Project or not rather, it focuses on determining the best delivery approach for its implementation. 6

7 Project Delivery Methods 7

8 Delivery Method Option 1 - DBO Design-Build- Operate (DBO) Project is financed and owned by the District. Private sector contracts to design, build and operate the facilities For example: Charles E. Meyer Desalination Facility (Santa Barbara) 8

9 Delivery Method Option 2 - PPP Public- Private Partnership (PPP) Private Sector sponsor to build, own, finance and operate the facilities Water sold to the District under a long term water purchase agreement For example: Carlsbad Desalination Project 9

10 Cost Estimates and Assumptions 10

11 Capital and Operating Cost Estimates 5 mgd project Base Project, based on sizes from work-to-date. Includes site works that allow expansion to larger capacity in the future CAPEX (2018 dollars) = $105 million OPEX (in 2020 dollars) = $6 million per year (if operating at full capacity all year). Design-build Contractor s Overhead & Profits Allowance for Incomplete Cost Estimation Design-build Contingency 11

12 Capital and Operating Cost Estimates 15 mgd project Larger project. Latest slant well work suggests a larger project might be feasible. Additional CAPEX for potable water distribution system augmentation will be required, though not yet fully scoped or costed. $50 million allowed CAPEX (2018 dollars) = $240 million OPEX (in 2020 dollars) = $16 million per year (if operating at full capacity all year). Design-build Contractor s Overhead & Profits Allowance for Incomplete Cost Estimation Design-build Contingency 12

13 Key Assumptions in Project Analysis Base estimates of Project parameters: Parameter Base estimate Unit Comment First year of construction 2018 (i.e. FY 2017/18) First year of operation 2020 (i.e. FY 2019/20) Inflation 2.0% p.a. General inflation rate (CPI). Analysis in nominal dollars Capital price escalation Used to convert current CAPEX estimates (in 2016 dollars) 2.5% p.a. rate to future (in 2018 dollars) Electricity price in 2020 $ per Important parameter since desalination is energy kwhr intensive Electricity price escalation rate Variable cost escalation rate 2.6% p.a. Annual increase to power price 2.0% p.a. Fixed cost escalation rate 2.0% p.a. Discount rate 4.0% p.a. Based on SCWD advice Residual value of assets not included in analysis Includes cost of chemicals, disposal of waste streams (sludge and brine) and other costs. Assumed to rise with inflation. Includes cost of labour, maintenance, insurance and water quality laboratory tests. Assumed to rise with inflation. 13

14 Interest rate (% p.a.) Financing Unique to DBO Project is eligible for DWSRF loan, which offers fixed-rate loan at half the State GO bond rate. A PPP entity will not be eligible for this loan. Principal and interest for DWSRF loan is repaid over 20 years from start of operation Only interest is serviced during construction period Project may be eligible for a State Grant from California Dep. Water Resources, up to $5 million 2.6% 2.4% 2.2% 2.0% 1.8% 1.6% Recent SRF loan rates: 14

15 Base Estimates Adopted for DBO Financing Parameter Base estimate Unit Comment DWSRF loan proceeds 100% DWSRF loan interest rate 2.0% p.a. Loan repayment period 20 years I.e. proceeds from the DWSRF loan will be available to finance 100% of project costs Since 2012 interest rates offered have ranged from 1.6% to 2.1% p.a. and in 2017 to date, the rate is 1.7%. For drinking water projects not serving 'disadvantaged communities', repayment period of 20 years applies according to the terms of the DWSRF loan. The 20 years is commences 'within one year of completion of construction' State Grant $5 million Assumes maximum grant amount received. Applied as principal forgiveness sum i.e. a single lump-sum payment at beginning of operation period (after construction and proof-of-performance). 15

16 Contractual Structure Unique to PPP Under the PPP delivery method, a special purposes company will be established to take responsibility for financing, building, owning and operating the Project facilities A Water Purchase Agreement will be executed between PPP entity and SCWD for the off-take of water Requirement for District to take and pay for all water available from the Project Contract period of 30 years to provide credit support for the project financing Allocation of project risks between the PPP and District will be a critical component of the PPP contractual structure and value of this project delivery approach. 16

17 Base Estimates Adopted for PPP Parameters Parameter Debt / equity financing Base estimate 70% debt / 30% equity Unit Comment A reasonable range for debt to equity would be 60%-40% for conservative leveraged projects to 80%-20% for more highly leveraged projects. Equity stake may consist of a contribution from PPP Special Company as well as their subcontractors. Internal rate of return (IRR) sought for equity 9.5% p.a. IRR of 9.45% p.a. in Carlsbad Desalination Project WPA. The IRR demanded by equity participants varies depending on the strength of the project s contractual structure. IRRs can range from 5.5% to 15%, but are likely to be 8.5% to 12%. Debt interest rate 4.75% p.a. PPP can raise private activity bonds ( PABs ). Interest rate will depend on balance sheet of the owner, project structure / risks, and the District s credit. There is a risk that in the current economic and political climate, the rate is more likely to increase rather than decrease. 17

18 Cash Flow Analysis Base Estimates 18

19 Key Financial Outputs to Assess Project Net present cost (NPC) The sum of the discounted annual cashflows over the Project timeframe Lower NPCs are favorable to Project viability and capture whole-of-project factors NPC components include capital costs, operating costs, and value of risks. Cost of water profile Yearly breakdown of cost of desalinated water on $/AF basis over Project timeframe Cost profile illustrates the relative cost impact to current and future water customers Yearly water cost compared to MET imported water cost affects the value of the MWD rebate Monthly rate impact to customers Simplified calculations intended to estimate rate impacts to SCWD water customers Typical household consumes 10 hundred cubic feet (HCF) of water per month 19

20 Model Results - Overview 5 mgd 15 mgd DBO PPP DBO PPP Total Project Construction Cost $105 M $244 M NPC of Project $198 M $262 M $504 M $644 M Note: value of risk not included Project construction costs are assumed to be the same under both DBO and PPP approaches, as both will use similar fixed-price contract forms Project NPC is less under the DBO approach, mostly due to the significant advantage of DWSRF financing (to be discussed further) 20

21 Cash Flow Profiles DWSRF loan repaid (DBO only) 21

22 MET Rebate Options Rebate Option Nominal value of rebate Period of duration Rebate Option 1 Up to $475 per af First 15 years of operation Rebate Option 2 Up to $340 per af First 25 years of operation MET Local Resources Program (LRP) Rebate only provided to the extent that the cost of desalinated water is greater than that of MET imported water 22

23 MET Rebate Options Rebate Option 5 mgd DBO 5 mgd PPP NPC Cost of water in 2020 NPC Cost of water in 2020 No Rebate $226 M $2288 / AF $290 M $2764 / AF Rebate Option 1 ($475/af, 15 yr) Rebate Option 2 ($340/af, 25 yr) $198 M $1813 / AF $262 M $2289 / AF $202 M $1948 / AF $261 M $2424 / AF Similar results for 15 mgd Project Rebate Option 1 minimises NPC and maximises the benefit received in the earlier years of the project when there is a larger gap between cost of desalinated water and MET imported supply But Rebate Option 2 option has a smoother cost of water over time, and the difference in project NPC compared to Rebate Option 1 is not large. Rebate Option 1 is the preferred option (and is included in all base estimates) 23

24 DBO Financing Options no SRF? Table below shows that non-srf DBO financing results in DBO financial outcomes being similar to PPP E.g. municipal bonds with i = 5% p.a. over 30 years DBO DWSRF 5 mgd 15 mgd DBO Municipal bonds PPP DBO DWSRF DBO municipal bonds Effective interest rate 2% p.a % p.a. 6.2% p.a.* 2% p.a % p.a. 6.2% p.a.* Loan repayment period 20 years 30 years 20 years 30 years NPC of Project $198 M $232 M $262 M $504 M $584 M $644 M PPP Cost of water in 2020 $ 1503 / AF $ 1886 / AF $2289 / AF $ 1240 / AF $ 1526 / AF $1811 / AF The availability of the SRF loan for the DBO is the most significant factor creating the cost differential between the DBO and PPP 24

25 PPP Financing Options DBO repayment terms are fixed, however PPP allows for more flexibility in financing. At Carlsbad, back-loaded financing at 2.5% p.a. was incorporated in WPA to decrease cost of water in early years of project. Value of capital repayments escalate at a fixed rate each year and loan is paid off over same timeframe Back-loaded financing offers a way to reduce immediate increases in water bills with relatively small impact on total Project NPC Could be investigated further if PPP delivery is adopted. 25

26 PPP Financing Options 5 mgd: Project Size 5 mgd Escalation Constant 2% p.a. 4% p.a. Project NPC $262 M $267 M $273 M Similar results for 15 mgd Project 26

27 Approximate Monthly Bill Increase To Typical Residential Customer 5 MGD Desalination Project DB0 30 Year SRF Loan DBO 20 Year SRF Loan PPP $5/month $10/month $20/month 15 MGD Desalination Project DB0 30 Year SRF Loan DBO 20 Year SRF Loan PPP $0/month $5/month $10/month Order of Magnitude Estimate (Rounded to Nearest $5) Figures indicates amount more than purchasing MET water Based on 10 HCF usage per month Figures for first 5 Years of Project 27

28 Summary of Key Points for Base Estimates (Without Risk Adjustment) 1. DBO offers lower whole-of-life costs and lower cost of water than PPP, irrespective of Project size. The financing benefit from the DWSRF loan is the biggest factor. 2. Sensitivity analysis demonstrated CAPEX and electricity costs have biggest impact on Project viability, irrespective of delivery method 3. Back-loaded PPP financing may offer benefits for reducing immediate cost impacts to SCWD and its customers 28

29 Summary of Key Points for Base Estimates (Without Risk Adjustment) 5 mgd 15 mgd Total Project Capital Cost $105 M $244 M NPC of Project DBO $198 M $480 M NPC of Project PPP $262 M $586 M At 5 MGD, additional financing costs of the PPP result in higher NPC of ~ $65 million compared to the DBO. This means (for example) that the PPP would need to find a capital saving of $35 million (which becomes ~$65 million with financing costs) to compete with the DBO. This seems challenging given the total CAPEX of $105 million. Executing the 15 mgd Project requires involvement of multiple other regional agencies. This adds significant complexity to the Project. A PPP would reduce this complexity on behalf of the District, but requires additional NPC of ~$100 million compared to a DBO. 29

30 Risk Analysis Assumptions and Methodology 30

31 Types of risk This is a major capital project, long duration with exposure to external macroeconomic, political and regulatory conditions. There are risks throughout the Project timeframe that cannot be fully mitigated. Risks can be classified by their ability to be transferred: Retained risks: risks residing with the District Transferable risks: risks able to be transferred to the private sector and reduce the District s risk exposure. By also owning and financing the Project, PPPs reduce the overall risk exposure of the District compared to a DBO delivery. 31

32 Risk Allocation and Transfer Risks Party Likely to Accept in DBO Party Likely to Accept in PPP Comment Construction risks (Group A and B) Design and construction errors / avoidable delays / onshore geotechnical risks DB Contractor DB Contractor Slant well construction risks DB Contractor DB Contractor Exchange rate / industrial relations DB Contractor DB Contractor Offshore geotechnical risks SCWD SCWD or shared Many risks to be accepted by DB contractor and costed into the DB contractors bid as contingency. Same risk profile in DBO or PPP as contractual arrangements with DB contractor will be similar. As above, but slant wells are not common assets (thus perceived higher technical risk). Slant well contractors (small, specialist companies) may not be able to bear the full costs (e.g. enter liquidation in the worst case). District would likely provide geotech information as basis in DB contract specification. Difficult to provide certainty of offshore conditions and guarantee suitability for slant wells. Local regulations and/or community concerns SCWD PPP or shared High profile construction in public beach area. May lead to resistance and/or delays. PPP may agree to share risk of approvals. District not exposed Exposure to risk District shares/may be exposed District exposed 32

33 Risk Allocation and Transfer Risks Party Likely to Accept in DBO Party Likely to Accept in PPP Comment Operating risks (Group C and E) Aquifer flow and water quality SCWD SCWD or shared District will have to specify raw water quality and flow in contract specification, based on offshore investigations Electricity and consumables consumption SCWD PPP PPP can be held to electricity consumption benchmarks. Note that O-contractor may also be held to these, but not assumed for VfM analysis. Electricity price SCWD SCWD Energy price increases passed through to District Access to waste disposal options SCWD SCWD Brine outfall and sludge disposal Exposure to risk District not exposed District shares/may be exposed District exposed 33

34 Risk Allocation and Transfer Risks Party Likely to Accept in DBO Party Likely to Accept in PPP Comment Financing and Economic risks (Group F) Inflation and power cost escalation rates SCWD SCWD Interest rate risk SCWD (SRF loan) PPP Debt servicing SCWD PPP Financing risks with District in DBO but SRF is fixed rate loan. PPP takes on finance risk. In PPP case district retains obligations to meet payments to PPP if the PPP performs as required. Water supply risks (various) Water volume & quality produced meets contract SCWD PPP District to provide required treated water quality targets in contract specification. WPA with PPP sets financial penalties if not met. Risk of law change SCWD SCWD E.g. treated water quality regulations Exposure to risk District not exposed District shares/may be exposed District exposed 34

35 Risk Allocation and Transfer Summary Under both DBO and PPP approaches, the exposure to certain major CAPEX risks will be transferred to the DB contractor and certain operating risks will be transferred to the operating contractor. PPP approach will enable a range of risks to be transferred to the private sector (e.g. geotech, regulatory) The extent of this risk transfer will depends on contractual negotiations. All financing risks will be transferred under the PPP approach PPP finance costs will reflect a premium for this risk acceptance DBO approach will provide a level of risk transfer to the DB and operating contractors However, if DBO receives SRF loan, then financing risk is minimal since the interest rate is fixed. 35

36 Quantifying and modelling risks Contingent risk methodology Possible events that could result in additional costs above the base estimate outputs due to unpredictable circumstances Consequence distribution representing estimated range of costs that would be incurred to rectify the consequences of the risk if it eventuates Consequence distribution Likelihood of the risk eventuating (as a percentage probability) Value of risk = consequence x likelihood 36

37 Quantifying and modelling risks Inherent risk methodology Uncertainty in the scope of work and pricing assumptions Inherent risks affect parameters which are direct inputs into economic model These parameters modelled as probability distributions rather than fixed values. E.g. probability distribution of electricity consumption 37

38 Quantifying and modelling risks No bids have yet been sought or received from the private sector for either DBO or PPP delivery of the Project. In practice, the level of uncertainty and hence the risk profile of the Project will be reduced when bids are received from the market, and many risks are eliminated when a final project contracts are signed. Many inherent risks will be eliminated as contracts will include performance and costing benchmarks Further evaluation of the project economics under various contracting approaches to be completed between now and signing of contracts District also has option to re-scope, re-negotiate or abort Project prior to signing the contract Our analysis included consideration of the District s risk exposure before/after execution of a DBO or PPP contract. 38

39 Risk Analysis Results 39

40 A Note on P-values P-values (e.g. P90) represent statistical estimates of uncertainty. Essentially a way to obtain values from what are inherently probability distributions. P90 means 90% of possible costs are less than this value, and 10% are above The P90 value is often used by municipal bodies for valuation of contingent risk in infrastructure projects. P5 and P95 often used as expected range of possible costs However different parties may have a different risk appetite and hence value risks based on different P-values 40

41 Results of Risk Analysis 5 mgd Risk profile of CAPEX contingent risks (Risk Group B) for DBO and PPP 41

42 Results of Risk Analysis 5 mgd Value of risk transfer by PPP Risk profile of CAPEX contingent risks (Risk Group B) for DBO and PPP PPP enables risk transfer in the order of $5 million (P90 valuation) 42

43 Results of Risk Analysis 5 mgd Impact of inherent risks modelled by generating heat maps of Project costs by Monte-Carlo simulations (e.g. 50,000 iterations of possible outcomes) Graph below includes both contingent and inherent risks for DBO: 43

44 Results of Risk Analysis 5 mgd Impact of inherent risks modelled by generating heat maps of Project costs by Monte-Carlo simulations (e.g. 50,000 iterations of possible outcomes) Graph below includes both contingent and inherent risks for DBO: 44

45 Results of Risk Analysis 5 mgd Impact of inherent risks modelled by generating heat maps of Project costs by Monte-Carlo simulations (e.g. 50,000 iterations of possible outcomes) Graph below includes both contingent and inherent risks for PPP: 45

46 Summary of Key Points from Risk Analysis The range of costs (to the District) for the PPP is narrower than for the DBO case, as the PPP accepts more risks. However the PPP has higher financing costs and will likely include a risk premium for this. So, for the most probable outcomes, the NPC and Cost of Water is higher for a PPP than a DBO, but there is less exposure to changes in cost for a PPP if worst cases were to occur. This analysis suggests that it is possible, but unlikely, that a PPP would have a lower cost of water or a lower NPC than a DBO. 46

47 Summary of Risk Analysis Results A PPP reduces risk exposure significantly. However, that saving is not sufficient to counter the lower financing costs for DBO. If the SRF loan was not available, a PPP would appear very similar, and perhaps even more attractive than a DBO. 47

48 Summary 48

49 5 mgd Project: 49

50 Risk Adjusted NPC ~$60M 50

51 Questions? 51

52

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District 3585 Maple Street, Suite 250 Ventura, CA 93003 805-404-1467 Montecito Sanitary District Wastewater Rate Study Report March 2016 Montecito Sanitary District 1042 Monte Cristo Lane Santa Barbara CA 93108

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

SAN DIEGO COUNTY WATER AUTHORITY S CARLSBAD SEAWATER DESALINATION PUBLIC-PRIVATE PARTNERSHIP

SAN DIEGO COUNTY WATER AUTHORITY S CARLSBAD SEAWATER DESALINATION PUBLIC-PRIVATE PARTNERSHIP Third Annual Water Innovations Alliance Conf. Boston, MA September 27, 2011 SAN DIEGO COUNTY WATER AUTHORITY S CARLSBAD SEAWATER DESALINATION PUBLIC-PRIVATE PARTNERSHIP Eric S. Petersen Partner Hawkins

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

Ms. Laurel Ross, Acting Commission Secretary and Director

Ms. Laurel Ross, Acting Commission Secretary and Director Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

Kidsafe NSW Risk Management Plan. August 2014

Kidsafe NSW Risk Management Plan. August 2014 Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013 MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT September 2013 10540 TALBERT AVENUE, SUITE 200 EAST FOUNTAIN VALLEY, CALIFORNIA 92708 P. 714.593.5100 F. 714.593.5101 MARINA

More information

Introduction to the Toolkit Financial Models

Introduction to the Toolkit Financial Models World Bank & Brazilian Ministry of Transport Workshop on the Toolkit for PPP in Roads and Highways Introduction to the Toolkit Financial Models Cesar Queiroz World Bank Brasilia, Brazil, June 8-9, 2010

More information

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

P3 Fundamentals and Best Practices in Resource and Project Management

P3 Fundamentals and Best Practices in Resource and Project Management Achieving better value, timeliness and accountability through public-private partnerships P3 Fundamentals and Best Practices in Resource and Project Management Ottawa, Ontario November 26, 2015 Greg Smith

More information

PPP Finance and Legal Issues. Edward Farquharson 25 July 2006

PPP Finance and Legal Issues. Edward Farquharson 25 July 2006 PPP Finance and Legal Issues Edward Farquharson 25 July 2006 Modes of Finance Sovereign Finance Public Sector Full Recourse Private Sector Non Recourse Corporate Finance Project Finance Agenda Role of

More information

FRAMEWORK FOR SUPERVISORY INFORMATION

FRAMEWORK FOR SUPERVISORY INFORMATION FRAMEWORK FOR SUPERVISORY INFORMATION ABOUT THE DERIVATIVES ACTIVITIES OF BANKS AND SECURITIES FIRMS (Joint report issued in conjunction with the Technical Committee of IOSCO) (May 1995) I. Introduction

More information

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and

More information

PERFORMANCE IMPROVEMENT PLANNING MODEL PERFORMANCE ASSESSMENT SYSTEM PROJECT

PERFORMANCE IMPROVEMENT PLANNING MODEL PERFORMANCE ASSESSMENT SYSTEM PROJECT PERFORMANCE NING MODEL PERFORMANCE ASSESSMENT SYSTEM PROJECT Contents 2 1. Approach to Performance improvement planning model 2. Data Entry and Forecasts 3. Module I: Performance Assessment 4. Module II:

More information

VOLTA RIVER AUTHORITY

VOLTA RIVER AUTHORITY VOLTA RIVER AUTHORITY Capital Expenditure Guidelines November 2012 TABLE OF CONTENTS PAGE 1.0 Purpose and Scope of Guidelines...3 2.0 Projects Guidelines Apply To....4 3.0 Exemptions from Guidelines...4

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

IDENTIFYING AND QUANTIFYING RISKS AND UNCERTAINTIES IN DEVELOPING AN OFFSHORE OILFIELD UNDER VARYING OIL PRICE REGIMES

IDENTIFYING AND QUANTIFYING RISKS AND UNCERTAINTIES IN DEVELOPING AN OFFSHORE OILFIELD UNDER VARYING OIL PRICE REGIMES IDENTIFYING AND QUANTIFYING RISKS AND UNCERTAINTIES IN DEVELOPING AN OFFSHORE OILFIELD UNDER VARYING OIL PRICE REGIMES By Adeogun Oyebimpe, Wumi Iledare, Green Ovunda Emerald Energy Institute University

More information

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis Contract length analysis for Feed-in Tariff with Contracts for Difference Summary of onshore and offshore wind analysis August 2013 Contract length analysis for Feed-in Tariff with Contracts for Difference

More information

WATER AND SEWER UTILITIES RATE STUDY

WATER AND SEWER UTILITIES RATE STUDY WATER AND SEWER UTILITIES RATE STUDY RATE DESIGN WORKSHOP WITHCITYCOUNCIL / UTILITIES COMMISSION March 6, 2014 Agenda Overview of Rate Study Process Water / Sewer Developer Impact Fees Sewer Rates Water

More information

Financial Statements. For the year ended 30 June 2017

Financial Statements. For the year ended 30 June 2017 Financial Statements Statement of comprehensive income 18 Balance sheet 19 Statement of changes in equity 20 Statement of cash flows 21 22 n 24 n Long Term Assets 39 n Other information 41 Certificate

More information

Public Private Partnerships (PPPs) Projects

Public Private Partnerships (PPPs) Projects Development Process of Public Private Partnerships (PPPs) Projects By Dr Paul H K Ho 1 Disclaimer Funded by Commerce, Industry and Technology Bureau, The Government of the Hong Kong Special Administrative

More information

Independent auditor s report to the members of Barratt Developments PLC

Independent auditor s report to the members of Barratt Developments PLC 103 Annual Report and Accounts Financial Statements Independent auditor s report to the members of Opinion on the financial statements of In our opinion: > > the financial statements give a true and fair

More information

WATER AND SEWER RATE STUDY

WATER AND SEWER RATE STUDY FINAL WATER AND SEWER RATE STUDY B&V PROJECT NO. 179322.0100 PREPARED FOR City of Lynwood, CA JANUARY 11, 2017 Black & Veatch Holding Company 2011. All rights reserved. City of Lynwood, CA WATER AND SEWER

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management (Singapore)

Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management (Singapore) Answers Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management () June 2010 Answers 1 The answer should be presented as a briefing note. The standard financial appraisal is supplemented

More information

Planning Construction Procurement. A guide to risk and value management

Planning Construction Procurement. A guide to risk and value management Planning Construction Procurement A guide to risk and value management ISBN: 978-1-98-851708-7 (online) First published October 2015 Revised October 2016 New Zealand Government Procurement PO Box 1473

More information

UPDATED IAA EDUCATION SYLLABUS

UPDATED IAA EDUCATION SYLLABUS II. UPDATED IAA EDUCATION SYLLABUS A. Supporting Learning Areas 1. STATISTICS Aim: To enable students to apply core statistical techniques to actuarial applications in insurance, pensions and emerging

More information

STATISTICAL FLOOD STANDARDS

STATISTICAL FLOOD STANDARDS STATISTICAL FLOOD STANDARDS SF-1 Flood Modeled Results and Goodness-of-Fit A. The use of historical data in developing the flood model shall be supported by rigorous methods published in currently accepted

More information

Rethinking post-retirement asset allocation

Rethinking post-retirement asset allocation Rethinking post-retirement asset allocation While growth assets are widely accepted in asset allocation decisions during the accumulation phase, many investors overlook the benefit allocating to shares

More information

Home Affairs Bureau. Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak

Home Affairs Bureau. Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak Home Affairs Bureau Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak Final Report September 2013 Contents 1. Introduction...3

More information

Public Private Partnerships in the National Health Service: The Private Finance Initiative

Public Private Partnerships in the National Health Service: The Private Finance Initiative Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator

More information

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente Final COST OF SERVICE STUDY SEPTEMBER 2017 City of San Clemente Contents CONTENTS Executive Summary... 1 Study Goals and Drivers... 1 Water Rate Analysis & Adoption... 2 Recycled Water Rate Analysis &

More information

DATA GAPS AND NON-CONFORMITIES

DATA GAPS AND NON-CONFORMITIES 17-09-2013 - COMPLIANCE FORUM - TASK FORCE MONITORING - FINAL VERSION WORKING PAPER ON DATA GAPS AND NON-CONFORMITIES Content 1. INTRODUCTION... 3 2. REQUIREMENTS BY THE MRR... 3 3. TYPICAL SITUATIONS...

More information

The City of Sierra Madre

The City of Sierra Madre The City of Sierra Madre Comprehensive Water and Wastewater Cost of Service Study Report / December 24, 2018 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145 www.raftelis.com December

More information

Risk Management Framework. Group Risk Management Version 2

Risk Management Framework. Group Risk Management Version 2 Group Risk Management Version 2 RISK MANAGEMENT FRAMEWORK Purpose The purpose of this document is to summarise the framework which Service Stream adopts to manage risk throughout the Group. Overview The

More information

Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures

Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures European Banking Authority (EBA) www.managementsolutions.com Research and Development December Página 2017 1 List of

More information

San Diego County Water Authority Special Board of Directors Meeting September 20, 2012

San Diego County Water Authority Special Board of Directors Meeting September 20, 2012 Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources San Diego County Water Authority Special Board of Directors Meeting 1 September

More information

STATE BANK OF PAKISTAN BANKING POLICY & REGULATIONS DEPARTMENT

STATE BANK OF PAKISTAN BANKING POLICY & REGULATIONS DEPARTMENT STATE BANK OF PAKISTAN BANKING POLICY & REGULATIONS DEPARTMENT Table of Contents 1. Introduction... 1 2. Sources of interest rate risk... 2 2.2 Repricing risk... 2 2.3 Yield curve risk... 2 2.4 Basis risk...

More information

PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING

PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING (Chapter 3 Software Project Estimation) Alain Abran (Tutorial Contribution: Dr. Monica Villavicencio) 1 Copyright 2015 Alain Abran Topics covered 1.

More information

Santa Clarita Water Division

Santa Clarita Water Division Santa Clarita Water Division Retail Water Rate Cost of Service Study Report September 2017 445 S Figueroa St Suite 2270 Los Angeles, CA 90039 Phone 213.262.9300 www.raftelis.com September 11, 2017 Mr.

More information

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints None. Authoritative Guidance Summary 1. Cost Assurance and Analysis Service (CAAS) provide a range of services for the Defence Equipment

More information

PILLAR 3 Disclosures

PILLAR 3 Disclosures PILLAR 3 Disclosures Published October 2009 Contacts: Peter Downham William Playle Head of Finance Head of Risk Management 0207 776 4117 0207 776 4155 peter.downham@arabbanking.com william.playle@arabbanking.com

More information

CDP. Module: Introduction. Page: W0. Introduction. Water 2014 Information Request W0.1. Introduction

CDP. Module: Introduction. Page: W0. Introduction. Water 2014 Information Request W0.1. Introduction CDP Water 2014 Information Request Enerplus Corporation Module: Introduction Page: W0. Introduction W0.1 Introduction Please give a general description and introduction to your organization. Enerplus Corporation

More information

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects GOLDEN EARS BRIDGE Alternative Transportation Financing ITE Quad Conference - May 2009 Fred Cummings Vice-President, Major Construction Projects Golden Ears Bridge Project Context/Project Overview Project

More information

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol The following presentation was given at: SCAF Workshop Integrated Cost and Schedule Risk Analysis Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol Released for distribution by the Author www.scaf.org.uk/library

More information

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly

More information

TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT

TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT Table of Contents 1. Introduction 1 2. What is Energy Management Financing? 2 3. Barriers to Investing in Energy Management 3 1. Initial Costs 3 2.

More information

Establishing the right price for electricity in South Africa. Brian Kantor with assistance from Andrew Kenny and Graham Barr

Establishing the right price for electricity in South Africa. Brian Kantor with assistance from Andrew Kenny and Graham Barr Establishing the right price for electricity in South Africa Brian Kantor with assistance from Andrew Kenny and Graham Barr This exercise is designed to answer the essential question of relevance for consumers

More information

Lorie Tinfow, City Manager, City of Pacifica Lorenzo Hines Jr., Assistant City Manager, City of Pacifica

Lorie Tinfow, City Manager, City of Pacifica Lorenzo Hines Jr., Assistant City Manager, City of Pacifica DATE: March 7, 2017 TO: FROM: SUBJECT: Lorie Tinfow, City Manager, Lorenzo Hines Jr., Assistant City Manager, Douglas Dove, President Michael DeGroot, Financial Analyst Abigail Seaman, Financial Analyst

More information

Case-study location: Battaglia Terme\Galzignano Terme

Case-study location: Battaglia Terme\Galzignano Terme Economic modelling of low-temperature geothermal energy Case-study location: Battaglia Terme\Galzignano Terme Activity 4.3 in WP 4 Partner: PADUA Coordinated by: UM Index 1. INTRODUCTION... 3 2. ASSESSMENT

More information

Water and Sewer Utility Rate Studies

Water and Sewer Utility Rate Studies Final Report Water and Sewer Utility Rate Studies July 2012 Prepared by: HDR Engineering, Inc. July 27, 2012 Mr. Mark Brannigan Director of Utilities 591 Martin Street Lakeport, CA 95453 Subject: Comprehensive

More information

Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures

Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures EBA/GL/2017/16 23/04/2018 Guidelines on PD estimation, LGD estimation and the treatment of defaulted exposures 1 Compliance and reporting obligations Status of these guidelines 1. This document contains

More information

Offshore electricity transmission: a new model for delivering infrastructure

Offshore electricity transmission: a new model for delivering infrastructure REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 22 SESSION 2012-13 22 JUNE 2012 Gas and Electricity Markets Authority Department of Energy and Climate Change Offshore electricity transmission: a new model

More information

SOUTHERN CALIFORNIA GAS COMPANY Compression Services Application (A ) (2nd DATA REQUEST FROM DRA)

SOUTHERN CALIFORNIA GAS COMPANY Compression Services Application (A ) (2nd DATA REQUEST FROM DRA) Question 1: a. On page 15, lines 11-13 of his rebuttal testimony, Jeffrey Reed on behalf of SCG states that The proposed Compression Services Tariff employs a structure wherein the tariff customer guarantees

More information

RETHINKING POST-RETIREMENT ASSET ALLOCATION

RETHINKING POST-RETIREMENT ASSET ALLOCATION www.fsadvice.com.au 1 Sam Morris, CFA Sam is an investment specialist with Fidante Partners, who invest in and forms long-term alliances with talented investment professionals to create, grow and support

More information

BETASHARES S&P/ASX 200 RESOURCES SECTOR ETF ASX CODE: QRE BETASHARES S&P/ASX 200 FINANCIALS SECTOR ETF ASX CODE: QFN

BETASHARES S&P/ASX 200 RESOURCES SECTOR ETF ASX CODE: QRE BETASHARES S&P/ASX 200 FINANCIALS SECTOR ETF ASX CODE: QFN BETASHARES FUNDS PRODUCT DISCLOSURE STATEMENT BETASHARES S&P/ASX 200 RESOURCES SECTOR ETF ASX CODE: QRE BETASHARES S&P/ASX 200 FINANCIALS SECTOR ETF ASX CODE: QFN BetaShares Capital Ltd ABN 78 139 566

More information

Allocated Pension & Working Income Support Pension Maritime Super Division Product Disclosure Statement

Allocated Pension & Working Income Support Pension Maritime Super Division Product Disclosure Statement Allocated Pension & Working Income Support Pension Maritime Super Division Product Disclosure Statement 30 September 2017 PDS Maritime Super Division Allocated Pension and Working Income Support Pension

More information

32. Management of financial risks

32. Management of financial risks 298 F CONSOLIDATED FINANCIAL STATEMENTS NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS 32. Management of financial risks General information on financial risks As a result of its businesses and the global

More information

Outline Capital Investment Strategy

Outline Capital Investment Strategy Outline Capital Investment Strategy INDEX FOREWORD 1. INTRODUCTION 2. PURPOSE 3. SUMMARY 4. INFLUENCES ON CAPITAL INVESTMENT 5. CURRENT CAPITAL EXPENDITURE 6. COMMERCIAL PROPERTY INVESTMENT STRATEGY 7.

More information

CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com.

CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com. MANAGEMENT OF FINANCIAL RESOURCES AND PERFORMANCE SESSIONS 3& 4 INVESTMENT APPRAISAL METHODS June 10 to 24, 2013 CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com. WESTFORD 2008 Thomson SCHOOL South-Western

More information

Consolidated income statement For the year ended 31 December 2014

Consolidated income statement For the year ended 31 December 2014 Petrofac Annual report and accounts Consolidated income statement For the year ended 31 December Notes *Business performance Exceptional items and certain re-measurements Revenue 4a 6,241 6,241 6,329 Cost

More information

Parameter Sensitivities for Radionuclide Concentration Prediction in PRAME

Parameter Sensitivities for Radionuclide Concentration Prediction in PRAME Environment Report RL 07/05 Parameter Sensitivities for Radionuclide Concentration Prediction in PRAME The Centre for Environment, Fisheries and Aquaculture Science Lowestoft Laboratory Pakefield Road

More information

The Water Industry Commission for Scotland Scottish Water Scottish Water

The Water Industry Commission for Scotland Scottish Water Scottish Water The Water Industry Commission for Scotland Scottish Water Scottish Water Reporter s Report SR10 2 nd Draft Business Plan Appendix C Investment and Outputs Plan April 2009 SCOTTISH WATER REPORTER S REPORT

More information

LONDON BOROUGH OF HARINGEY PENSION FUND INVESTMENT STRATEGY STATEMENT. 1. Introduction

LONDON BOROUGH OF HARINGEY PENSION FUND INVESTMENT STRATEGY STATEMENT. 1. Introduction LONDON BOROUGH OF HARINGEY PENSION FUND INVESTMENT STRATEGY STATEMENT 1. Introduction Haringey Council is the Administering Authority for the Local Government Pension Scheme in the London Borough of Haringey

More information

Life-Cycle Project Delivery

Life-Cycle Project Delivery Life-Cycle Project Delivery A Note for Discussion IndII Round Table 11 th December 2012 Concerns with Conventional Project Delivery Government pays for inputs, not outputs Incentive for time/cost over-runs

More information

Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs)

Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs) Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs) Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements

More information

PPP PUBLIC PRIVATE PARTNERSHIP

PPP PUBLIC PRIVATE PARTNERSHIP PPP PUBLIC PRIVATE PARTNERSHIP Definition by MOF 1. An arrangement between Government and Private party 2. To provide public assets and/or related services for public benefit 3. Private party makes investments

More information

Pillar 3 Disclosure Statement

Pillar 3 Disclosure Statement ALJAZIRA CAPITAL COMPANY (A Closed Saudi Joint Stock Company) Pillar 3 Disclosure Statement As at 31 December 2015 1 TABLE OF CONTENTS 1. INTRODUCTION... 3 2. CAPITAL STRUCTURE... 3 3. CAPITAL ADEQUACY...

More information

Pillar 3 Disclosure (UK)

Pillar 3 Disclosure (UK) MORGAN STANLEY INTERNATIONAL LIMITED Pillar 3 Disclosure (UK) As at 31 December 2009 1. Basel II accord 2 2. Background to PIllar 3 disclosures 2 3. application of the PIllar 3 framework 2 4. morgan stanley

More information

State Revolving Fund (SRF) Drinking Water Program Application Instructions for Private Borrowers

State Revolving Fund (SRF) Drinking Water Program Application Instructions for Private Borrowers State Revolving Fund (SRF) Drinking Water Program Application Instructions for Private Borrowers These instructions have been designed to help you fill out the State Revolving Fund - Drinking Water Program

More information

Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt. March An introduction to infrastructure debt

Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt. March An introduction to infrastructure debt An introduction to infrastructure debt Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt March 2017 1 macquarie.com 2 Important Notice This document is issued by

More information

P1 Performance Operations

P1 Performance Operations Operational Level Paper P1 Performance Operations Examiner s Answers SECTION A Answer to Question One 1.1 The correct answer is D. 1.2 The maximum regret at a selling price of 40 is 20,000 The maximum

More information

M_o_R (2011) Foundation EN exam prep questions

M_o_R (2011) Foundation EN exam prep questions M_o_R (2011) Foundation EN exam prep questions 1. It is a responsibility of Senior Team: a) Ensures that appropriate governance and internal controls are in place b) Monitors and acts on escalated risks

More information

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper june 07 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Contents: Page Preface Executive Summary 1 2 1 Service Costing in the General Government

More information

Funding Recommendation: IFA Funds Totals

Funding Recommendation: IFA Funds Totals Date: March 31, 2016 To From: Robert Ault, Program Services Division Manager Infrastructure Finance Authority Mary Baker, Regional Coordinator Infrastructure Finance Authority Janna Graham, Public Finance

More information

PNC Bank, NA. Board Report. June 30, Pittsburgh, PA. A/L BENCHMARKS Standards for Asset/Liability Management

PNC Bank, NA. Board Report. June 30, Pittsburgh, PA. A/L BENCHMARKS Standards for Asset/Liability Management A/L BENCHMARKS Standards for Asset/Liability Management Board Report PNC Bank, NA June 30, 2006 Olson Research Associates, Inc. 10290 Old Columbia Road, Columbia, MD 21046 Phone: 888-657-6680 Web: http://www.olsonresearch.com

More information

Risk Management. Financial Risk. Asset and liability management

Risk Management. Financial Risk. Asset and liability management Risk Management CITIC Limited has established a risk management and internal control system covering all business segments to identify, assess and manage various risks in the Group s business activities.

More information

CONCEPT PAPER & DRAFT GUIDELINES FOR GRADING OF CONSTRUCTION ENTITIES

CONCEPT PAPER & DRAFT GUIDELINES FOR GRADING OF CONSTRUCTION ENTITIES CONCEPT PAPER & DRAFT GUIDELINES FOR GRADING OF CONSTRUCTION ENTITIES Preamble: Growth of economy depends to a very large extent on construction of various types in every sector. Construction is the second

More information

Version: th November 2010 RISK MANAGEMENT POLICY

Version: th November 2010 RISK MANAGEMENT POLICY Version: 1.2-25th November 2010 RISK MANAGEMENT POLICY Document History Document Location To be completed. Revision History Date of this revision: 17/09/2010 Date of next revision: N/A Revision Number

More information

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects Seminar on African Electrical Interconnection Module 6 - Financing Interconnection Projects Module 6 - Financing Interconnection Projects Contents 1) Major Financing Features 2) Basic Financing Approaches

More information

Public Private Partnerships

Public Private Partnerships Public Private Partnerships A Presentation to the Association of Financial Professionals of Canada Edmonton Chapter March 20, 2013 Alternative Capital Financing Office Alberta Treasury Board and Finance

More information

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS Identify, Quantify, and 237 217 200 237 217 200 Manage 237 217 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112

More information

Government of Newfoundland and Labrador

Government of Newfoundland and Labrador Government of Newfoundland and Labrador Corner Brook Long Term Care Project Value for Money Report Table of contents 1. Limitations... 3 2. Executive Summary... 4 3. Background... 5 3.1 Project Description

More information

INTEREST RATE RISK MAKING YOUR MODEL UNDERSTANDABLE AND RELEVANT

INTEREST RATE RISK MAKING YOUR MODEL UNDERSTANDABLE AND RELEVANT INTEREST RATE RISK MAKING YOUR MODEL UNDERSTANDABLE AND RELEVANT Scott J. Hopf, CPA Senior Manager BKD, LLP 375 North Shore Drive, Suite 501 Pittsburgh, PA 15212 shopf@bkd.com 412.364.9395 AGENDA The Basics

More information

6 th September not protectively marked 1

6 th September not protectively marked 1 Establishing Risk Management processes in UK Nuclear New Build - (inc Enterprise Risk Management & Probabilistic Cost & Schedule Risk Analysis processes) 6 th September 2016 not protectively marked 1 Introductions

More information

California WaterFix Benefit Cost Analysis

California WaterFix Benefit Cost Analysis California WaterFix Benefit Cost Analysis PRESENTED TO Metropolitan Water District PRESENTED BY David L. Sunding, Ph.D. Professor, UC Berkeley October 23, 2018 Copyright 2018 The Brattle Group, Inc. WaterFix

More information

Mr. D.K.Goswami Choice International Limited 12 November 2011

Mr. D.K.Goswami Choice International Limited 12 November 2011 Long-term financing of Projects Debt Mr. D.K.Goswami Choice International Limited 12 November 2011 1 Flow of Presentation Meaning of the word Project and its types Cost of Project Setting-up of a Project

More information

Consolidated Statement of Profit or Loss and Other Comprehensive Income For the Financial Year ended 30 June 2013

Consolidated Statement of Profit or Loss and Other Comprehensive Income For the Financial Year ended 30 June 2013 Consolidated Statement of Profit or Loss and Other Comprehensive Income For the Financial Year ended 30 2013 2013 2012 Notes $ $ Continuing Operations Revenue 5 92,276 Interest income 5 25,547 107,292

More information

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for Water & Sewer Cost of Service Rate Study for City of Norco, CA October 11, 2016 Table of Contents October 11, 2016 Chad Blais Director of Public Works City of Norco 2870 Clark Avenue Norco, CA 92860 Re:

More information

long term plan financial strategy Financial Strategy

long term plan financial strategy Financial Strategy 33 Financial Strategy long term plan 2012-22 financial strategy As a part of Council s planning for the future, we have considered the importance of good financial management and have prepared what we

More information

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management

More information

CONTRACT COSTING. INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts.

CONTRACT COSTING. INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts. CONTRACT COSTING INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts. This method is used in case of big jobs described as contracts.

More information

NWC Tariff Submission for the Period January 2019 to December Submission to the Office of Utilities Regulation (OUR)

NWC Tariff Submission for the Period January 2019 to December Submission to the Office of Utilities Regulation (OUR) NWC Tariff Submission for the Period January 2019 to December 2021 Submission to the Office of Utilities Regulation (OUR) October 2018 Table of Contents 1 Executive Summary 1 1.1 Build-Up of the Revenue

More information

Model Concession Agreement for Highways: An Overview

Model Concession Agreement for Highways: An Overview Model Concession Agreement for Highways: An Overview - Gajendra Haldea The highways sector in India is witnessing significant interest from both domestic as well as foreign investors following the policy

More information

Sensitivity = NPV / PV of key input

Sensitivity = NPV / PV of key input SECTION A 20 MARKS Question One 1.1 The answer is D 1.2 The answer is C Sensitivity measures the percentage change in a key input (for example initial outlay, direct material, direct labour, residual value)

More information

Product Disclosure Statement. Yarra Global Small Companies Fund. Contents. Dated 14 January 2017 ARSN

Product Disclosure Statement. Yarra Global Small Companies Fund. Contents. Dated 14 January 2017 ARSN Contents Product Disclosure Statement Dated 14 January 2017 Yarra Global Small Companies Fund ARSN 090 047 822 1. About Yarra Funds Management Limited 2 2. How the Yarra Global Small Companies Fund works

More information