Motorway Communications Services PFI Study

Size: px
Start display at page:

Download "Motorway Communications Services PFI Study"

Transcription

1 Motorway Communications Services PFI Study Final Report Volume 3 - Financial Analysis Author Various Checker Name Redacted under Sec 40 of the FOIA Exemptions Personal Information Approver Name Redacted under Sec 40 of the FOIA Exemptions Personal Information This report has been prepared for in accordance with the terms and conditions of appointment for the Motorway Communications Services PFI Study dated 30/03/99. KHHS can not accept any responsibility for any use of or reliance on the contents of this report by any third party.

2 2/40

3 TABLE OF CONTENTS 1.0 FINANCIAL MODEL Introduction Wider socio-economic benefits Description of the financial model QA of the financial model FINANCIAL ANALYSIS AND RANKING HA risk adjusted NPV retained costs Commentary on results STRATEGY CAPITAL AND OPERATING COSTS Capital costs analysis by strategy Operating costs analysis by strategy THIRD PARTY REVENUES Third party revenue analysis by strategy MCS CO CHARGES MCS Co charges analysis by strategy Commentary on analysis HA MANAGEMENT AND ADMINISTRATION COSTS HA management and administration costs analysis by Commentary on analysis STRATEGY RISK ASSESSMENT Basis of risk assessment Risk modelling method Analysis of key risks for Motorway Communication Services Other risks considered by the Study Assessment of HA s retained risks under each strategy SENSITIVITIES Introduction Revenue sensitivities Break-even levels of third party revenues Discount rate sensitivity /40

4 THIS PAGE INTENTIONALY LEFT BLANK 4/40

5 GLOSSARY OF FINANCIAL ANALYSIS TERMS Capital allowances Corporation tax Debt Tax relief based upon the capital value of an asset, calculated each year as 25% of the tax written down value of that asset. The UK s corporate taxation system. A rate of 30% of taxable profits has been assumed. Borrowings from third party financing institutions, frequently banks, which have a priority over other investors in terms of their claim on the free cashflows of the SPV. Debt equity ratio The ratio of debt and equity in total funding. This is typically 90% in funding PFI projects, i.e. a project costing 100 in total is funded by 90 debt and 10 equity. Debt service cover ratio Equity Discounting PFI projects are generally funded on a project financing basis, where the lenders take security from a stream of cashflows. (eg payments from the HA to the PFI contractor) rather than from the more usual security of physical assets. Lenders monitor the cashflows available to repay their debt by means of banking cover ratios, the breach of which results in prescribed actions to protect the bank s security. The debt service cover ratio is one particular security, which is defined as cash before financing/capital repayment outstanding for the period. Funds invested in a project company by its owners through the subscription of share capital. The application of an interest rate to future cash flows to allow for the time value of money, e.g. if the interest rate is 10% per anum, a person should be indifferent between receiving 100 now or 110 in a year s time. Put differently, at an annual interest rate of 10%, 110 in a year s time has the same value as 100 now. This enables timing differences between cashflows to be reflected in project appraisal. Discount rate Latin hypercube sampling analysis The rate used to calculate present values. The Treasury discount rate of 6% is used in this study. This is a method of sampling which uses stratification to mitigate the effects of skewed distributions and enables results to be generated with smaller samples sizes than comparable methods such as Monte Carlo analysis. The method uses estimates of potential variations in selected items, to calculate probable risk values. These are used in the calculation of risk adjusted cashflows. 5/40

6 IRR NPV Present value PSC Rolled up interest Special purpose vehicle ( SPV ) Internal rate of return. The discount rate at which a project has a net present value of zero. Net present value. The present value of revenues less costs. The discounted value of future cash flows. At an annual interest rate of 10%, the present value of 110 received in a year s time is 100. Public sector comparator. A conventionally procured alternative to the PFI contract. The term given to interest on a loan (usually incurred during a construction period) which is not paid, but rather rolled into the principal loan amount for future repayment. A company set up by partners in a project, specifically for the purposes of that project. In a PFI context, SPVs are often used by bidding partners for the purposes of contracting to provide PFI services. The SPV has contractual relationships with its owners, financiers, equipment and service providers as well as the customer. From a financing perspective, the primary purpose of the SPV is often to limit the recourse of lenders to the project sponsors. There may also be taxation based or management/control motivation to use such a structure. In the context of this Study, it has been assumed that MCS Co would take the form of an SPV. Taxable profits Unitary charge Profit adjusted in accordance with UK tax legislation. The annual amount payable by the HA in respect of services provided by the SPV. 6/40

7 1.0 FINANCIAL MODEL 1.1 Introduction The financial models in this report estimate the cost to the ( HA ) of each of the Strategies developed in Volume 2 of this Final Report so that they can be ranked where appropriate and assessed for potential value for money against their relevant Public Sector Comparator ( PSC ). The materiality and sophistication of the models, and the inputs and assumptions, reflect the feasibility status of the Study. Much of the information being modelled at this stage has been supplied without commitment on the part of interviewees and is substantially untested. Nevertheless, the financial model has been planned and developed to provide as accurately as possible at this stage in the project a high level indication of the potential benefits of one over another The financial models and supporting schedules are attached as Appendices Wider socio-economic benefits This financial analysis is concerned solely with the financial costs and benefits of each of the Strategies to the HA, i.e. those costs and benefits which ultimately result in cashflows to or from the HA. It does not attempt to place a value on the wider socio-economic benefits of each of the Strategies, that is those costs and benefits to the HA s customers resulting from increased safety, journey time savings, journey time certainty, vehicle operating costs and the like Thus, in this analysis, Strategies which are more limited in scope and thereby incur less cost, may compare favourably in terms of their NPV cost to the HA against more ambitious Strategies which on the face of it cost more, but which aim to provide a larger range of socio-economic benefits to the road user in furtherance of the HA s policy objectives An assessment of the socio-economic benefits was not required by the Specification and is inappropriate in anything other than qualitative terms at this feasibility stage of the Study. However, an assessment of these benefits, is likely to be appropriate when developing the chosen Strategies in more detail in Part B. An initial assessment of the Strategies against New Approach to Appraisal ( NATA ) criteria has, however, been undertaken and is presented in Volume 2 section Description of the financial model The Strategies Seven main iterations of the financial model have been prepared for the different Strategies and their PSC variants identified in the Final Report. These are as follows: a) 2, the Do Minimum; 7/40

8 b) 3 PSC, the PSC variant of the Private Finance Initiative ( PFI ) for a national network strategy; c) 3 PFI, the PFI for a national network; d) 4 PSC UMTS, the PSC variant of the PFI for an enhanced national network strategy based on a UMTS roadside to vehicle communications link; e) 4 PFI UMTS, the PFI for an enhanced national network strategy based on a UMTS roadside to vehicle communications link; f) 4 PSC DSRC, the PSC variant of the PFI for an enhanced national network strategy based on a DSRC roadside to vehicle communications link; and g) 4 PFI DSRC, the PFI for an enhanced national network strategy based on a DSRC roadside to vehicle communications link. Model outline The model is illustrated in Figure 1.1. Data Assumptions Calculations Outputs Triple package/ CSR Risk assumptions HA project management cash and admin assumptions Risk calculations Capex and opex calculations HA retained costs model UMTS Data DSCR Data 3rd P revenue assumptions Project management and admin assumptions 3rd P revenue calculations Project management and admin calculations MCS Co model HA Incremental costs model Mast Data Risk assumptions Risk calculations Financing and tax assumptions MCS Co financing/tax calculations Figure 1.1: Model outline Data on the triple package was generated using National Communications Programme ( NCP ) information provided by the HA. KHHS sought to identify cabling tasks within the triple package, which would be suitable for inclusion in a PFI project. 8/40

9 1.3.4 Information based upon industry knowledge and limited market research was used in respect of: GSM/UMTS systems; mobile phone masts; DSRC systems; and data management In the modelling process, data was separated between Project items and Non project items to illustrate the portion of the HA s communications services which are likely to be effected by a PFI from Year 4 onwards. Since the Strategies with a PFI Option, Strategies 3 and 4, concern the motorway communications network, Project costs broadly relate to these activities. Non project costs broadly relate to the HA s other communications activities included within the Study, namely provision and maintenance of the roadside equipment and provision of the business communications network Project costs and revenues relating to the activities which may be effected by a PFI are modelled separately from the HA s retained Non project costs and revenues in both the PFI and PSC scenarios, so that the costs, revenues and risks relating to these options are directly comparable, without distortion by the high levels of Non project expenditure retained by the HA The project data relating to the private sector PFI services provider, Motorway Communication Services Company ( MCS Co ) is used in the MCS Co model, together with financing and taxation assumptions to calculate a unitary charge to the HA which is set to enable MCS Co to attain a reasonable target rate of return. The unitary charge is reflected in the HA Project costs model in the PFI scenarios A fifteen year period of assessment was chosen to reflect a procurement period of approximately three to four years, commencing in April 1999, and an initial contract term of approximately ten years. 1.4 QA of the financial model The model has been subject to: a) review by KPMG s business modelling unit; b) walk-through checks; and c) review of output by the project Assistant Director and Partner. 9/40

10 THIS PAGE INTENTIONALY LEFT BLANK 10/40

11 2.0 FINANCIAL ANALYSIS AND RANKING 2.1 HA risk adjusted NPV retained costs The NPV cost of each to the HA and its risk adjusted cost to the HA is set out in Figure 2.1 below. Retained HA NPV costs Non project costs 2 3 PSC 3 PFI 4 PSC UMTS 4 PFI UMTS 4 PSC DSRC 4 PFI DSRC m m m m m m m HA capital costs (369.0) (346.4) (346.4) (346.4) (346.4) (346.4) (346.4) HA operating costs (105.5) (100.1) (100.1) (100.1) (100.1) (100.1) (100.1) HA mgt and admin (24.2) (24.3) (24.3) (24.3) (24.3) (24.3) (24.3) HA revenues Non project costs (498.7) (467.5) (467.5) (467.5) (467.5) (467.5) (467.5) Project costs HA capital costs - (42.8) - (42.8) - (42.8) - HA operating costs - (30.2) - (30.2) - (30.2) - MCS Co charges - - (32.7) - (27.3) HA mgt and admin - (2.1) (3.7) (2.1) (3.7) (2.1) (3.7) Consultants fees - - (2.8) - (2.8) - (2.8) HA revenues Project costs - (36.7) (39.2) (36.7) (33.8) (36.7) Total HA costs before risk Mean non project risk adjusted costs Mean project risk adjusted costs (498.7) (504.2) (506.7)) (504.2) (501.3) (504.2) (275.6) (520.6) (490.9) (490.9) (490.9) (490.9) (490.9) (490.9) - (56.4) (39.4) (56.4) (34.0) (56.4) th percentile - (40.4) (39.0) (40.4) (33.6) (39.5) th percentile - (75.4) (39.9) (75.9) (34.5 (76.0) Mean total HA risk adjusted costs (520.6) (547.3) (530.3) (547.3) (524.9) (547.3) (299.1) 95 th percentile (496.5) (504.7) (503.3) (504.7) (498.8) (503.8) (221.9) 5 th percentile (550.1) (591.0) (555.5) (591.5) (544.2) (591.6) (324.3) Figure 2.1: NPV of HA risk adjusted retained costs by The costs are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6%. 11/40

12 2.1.3 The risk adjustments made to the risk adjusted costs have been made in accordance with the risk assessments set out in section 7 using Latin hypercube sampling analysis. This provides a distribution of results for which we have provided the mean figure and the 90% confidence range bounded by the 95 th and 5 th percentile illustrated in figure 2.2 below: Probability 5 th Percentile Mean 95 th Percentile Risk adjusted NPV Cost Figure 2.2: Risk adjusted NPV cost Analysis of results As noted in section 1, Non project costs broadly relate to all the HA s activities up to the end of Year 3, which is considered to be the earliest date for the introduction of an MCS contract, and, from Year 4 onwards, to the provision and maintenance of the roadside equipment and provision of the business communications network Project costs and revenues relate to the activities which may be effected by an MCS contract from Year 4 onwards and, therefore, cover broadly the operation of the motorway communications network , the Do Minimum, relates to all of the activities included in the Study, and so includes both the Non project and Project costs. In comparing 2 with the other Strategies it is necessary to review the total HA risk adjusted costs, highlighted by the lower box in Figure Strategies 3 and 4 relate solely to Project activities, i.e. the operation of the motorway communications network and associated opportunities from Year 4 onwards. Therefore, when comparing Strategies 3 and 4 with each other and with their PSCs, it is necessary to review the mean Project risk adjusted costs to the HA, highlighted by the upper box in Figure Commentary on results Project and non project costs The striking observation for all of the strategies is that the non-project costs are so much greater than the project costs. The inference is that the majority of the cost in the HA s communications services resides in the provision and maintenance of its roadside devices. 12/40

13 2.2.2 However, KHHS believe that the wider opportunities for the HA, both in financial terms and in terms of achieving its broader policy objectives, rest in the development of its motorway communications network. That is why the two Strategies developed in most detail, Strategies 3 and 4, concern this part of the MCS and only 5 considers the procurement of the roadside equipment Furthermore, we believe that if the financial analysis were extended to include an assessment of the broader socio-economic benefits, we would expect to see a greater portion of the value being generated in the motorway communications network. This is because we would expect to see the emphasis move away from current dependency on roadside communications devices to the delivery of more detailed and tailored traffic information generally, to drivers via in-car and other journey planning and management services, and to the TCC, PCOs and other traffic management bodies. Public sector options has a lower NPV risk adjusted cost to the HA at million than each of the PSCs for the PFI Strategies 3 and 4 which each cost million. This is to be expected since 2 is a smaller scope option and no account is taken in this analysis of the broader socio-economic benefits which the HA would expect to achieve through Strategies 3 and 4. PFI options When reviewing the PFI options in Strategies 3 and 4, it is apparent that 3 appears to be marginally more expensive than its PSC alternative, and 4 UMTS appears to be marginally less expensive than its PSC alternative, before account is taken of risk (see Project costs line in Figure 2.1), but that each appears to demonstrate substantial value for money (i.e. is a lower cost to its PSC) when the HA s retained risk is also considered. Furthermore, 4 also provides better value for money than 2, the Do Minimum, even before taking account of broader socio-economic benefits Whilst PFI Strategies 3 and 4 UMTS appear marginal in comparison with 2, in terms of the total cost to the HA, they actually represent far greater value for money, since the HA will acquire far greater capability for a similar outlay. The overall cost of PFI is lower in each case when compared with the PSC The figure for the 4 DSRC option assumes that MCS Co would be the sole national operator (at least until such time as another operator started-up in competition) of the beacon-based roadside to in-vehicle communications services, because there is no existing DSRC network. Thus MCS Co would capture all subscription revenues from motorists using the service. With the UMTS option motorists are not assumed to subscribe to MCS Co, but to their usual mobile operator. In this scenario, MCS Co would only make a small margin on telematics communications traffic carried over the operators networks. 13/40

14 2.2.8 It is apparent from the results that the 4 DSRC PFI appears prima facie to be the best option for the HA. Indeed, such are the assumed potential revenues under the DSRC option (even when reduced to 40% of expected total revenues for the purposes of calculating the cost to the HA), MCS Co would appear to be paying the HA to provide the services rather than vice-versa. This results in an NPV risk adjusted cost to the HA of million against million for the DSRC PSC, and million and million for each of the other PFI options However, it must be pointed out that the revenue numbers, particularly, are very speculative, and would need thorough testing in the market. The HA would not seek, in requesting tenders for a 4 bid, to specify either a UMTS or DSRC solution, and it would be for the bidders, based on their knowledge of the market conditions and the technologies at the time to decide on the solutions and to carry the risk of achieving forecast revenues. The results of the financial analysis are useful though in giving an idea of the range of potential savings the HA may seek to achieve through PFI over a conventional procurement. 14/40

15 3.0 STRATEGY CAPITAL AND OPERATING COSTS 3.1 Capital costs analysis by strategy The NPV capital costs incurred by the HA in each, and those incurred by MCS Co in the PFI Strategies, are set out in Figure 3.1 below. Retained HA NPV capital costs Non project costs 2 3 PSC 3 PFI 4 PSC UMTS 4 PFI UMTS 4 PSC DSRC 4 PFI DSRC m m m m m m m Infrastructure (367.4) (338.5) (338.5) (338.5) (338.5) (338.5) (338.5) Transmission (1.6) (1.6) (1.6) (1.6) (1.6) (1.6) (1.6) Mast costs - (6.3) (6.3) (6.3) (6.3) (6.3) (6.3) Non project costs (369.0) (346.4) (346.4) (346.4) (346.4) (346.4) (346.4) Project costs Infrastructure - (28.9) - (28.9) - (28.9) - Transmission - (2.0) - (2.0) - (2.0) - Mast costs - (11.9) - (11.9) - (11.9) - Project costs - (42.8) - (42.8) - (42.8) - Total capital costs (369.0) (389.2) (346.4) (389.2) (346.4) (389.2) (346.4) MCS Co Project costs Infrastructure - - (23.6) - (23.6) - (23.6) Transmission - - (3.2) - (3.2) - (3.2) Mast costs - - (12.0) - (12.0) - (12.0) GSM/UMTS (5.0) - - DSRC Beacon costs (8.5) MCS Co project capital costs - - (38.8) - (43.8) - (47.3) Figure 3.1: NPV of capital costs by The costs are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6%. 15/40

16 3.1.3 In the above analysis, Non project capital costs broadly relate to all the HA s activities up to the end of Year 3, and, from Year 4 onwards, to the provision and maintenance of the roadside equipment and provision of the business communications network. Non project expenditure is in effect expenditure which is made regardless of whether a PFI or PSC option is taken. Project capital expenditure in the PSC Strategies relates to the national motorway communications network activities from Year 4 onwards Non project expenditure includes masts cost which the HA is assumed to incur prior to the commencement of operation of MCS Co. Project expenditure represents continued expenditure on masts, infrastructure and transmission systems in the absence of MCS co The expenditure apportioned to MCS Co from the HA s continuing projects relates to cabling work. Expenditure retained by the HA is assumed to relate to roadside devices and business communications Infrastructure costs are based upon a review of HA plans. Other costs are KHHS best estimates based upon industry knowledge. The PFI scenarios assume that a 20% cost saving is possible on the HA s infrastructure costs through more effective procurement practices It is assumed in the 4 PSC scenarios that the HA would not undertake the development of the roadside to vehicle links due to the risks involved and the capabilities required. Consequently, the HA incurs no expenditure on GSM/UMTS or DSRC equipment in the 4 PSCs. 16/40

17 3.2 Operating costs analysis by strategy The NPV operating costs incurred by the HA in each, and those incurred by MCS Co in the PFI Strategies, are set out in Figure 3.2 below. Retained HA NPV operating costs Non project costs 2 3 PSC 3 PFI 4 PSC UMTS 4 PFI UMTS 4 PSC DSRC 4 PFI DSRC m m m m m m m Infrastructure (84.8) (86.3) (86.3) (86.3) (86.3) (86.3) (86.3) Transmission (20.7) (12.2) (12.2) (12.2) (12.2) (12.2) (12.2) Mast costs - (1.6) (1.6) (1.6) (1.6) (1.6) (1.6) Non project costs (105.5) (100.1) (100.1) (100.1) (100.1) (100.1) (100.1) Project costs Infrastructure - (1.3) - (1.3) - (1.3) - Transmission - (9.7) - (9.7) - (9.7) - Mast costs - (19.2) - (19.2) - (19.2) - Project costs - (30.2) - (30.2) - (30.2) - Total operating costs (105.5) (130.3) (100.1) (130.3) (100.1) (130.3) (100.1) MCS Co Project costs Operating expenditure - - (1.3) - (1.3) - (1.3) Transmission maintenance expenditure - - (5.6) - (5.6) - (5.6) Mast maintenance - - (20.5) - (20.5) - (20.5) Data Management Systems Microcell/beacon maintenance - - (1.0) - (1.0) - (1.0) (7.5) - (17.7) MCS Co project operating costs - - (28.4) - (35.9) - (46.1) Figure 3.2: NPV of operating costs by The costs are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6%. 17/40

18 3.2.3 Operating expenditure for non project activities in all scenarios includes maintenance costs and maintenance contract arrangements consistent with those already in place. This includes RMC and RMCMC costs in respect of maintenance of the roadside equipment. Project costs include NTMC arrangements in respect of the cable and transmission infrastructure in the PSC scenarios and MCS Co s own maintenance in the PFI scenarios Transmission expenditure in MCS Co is estimated to cover an upgraded transmission network In the PFI scenarios, the cost streams and associated revenues relating to mobile phone masts pass to the MCS Co on commencement of its operations. In PSC scenarios these cost streams and associated revenues continue in the HA and are shown as project costs In the MCS Co scenarios, operating costs are incurred on DSRC and UMTS activities. As mentioned above, it is assumed that the HA would not develop this additional functionality Infrastructure costs are based on a review of HA plans. Other costs are based upon KHHS best estimates derived from industry knowledge. 18/40

19 4.0 THIRD PARTY REVENUES 4.1 Third party revenue analysis by strategy The NPV revenues received by the HA in each, and those received by MCS Co in the PFI Strategies, are set out in Figure 4.1 below. HA NPV revenues Non project revenues 2 3 PSC 3 PFI 4 PSC UMTS 4 PFI UMTS 4 PSC DSRC 4 PFI DSRC m m m m m m m Mast revenues Non project rev s Project revenues Mast revenues Project revenues Total HA revenues MCS Co revenues Mast revenues Data management Sale of traffic data Sale of comms/airtime Microcell rentals/dsrc Beacon rentals MCS Co revenues Figure 4.1: NPV of third party revenues by The revenues are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6% In 2, the Do Minimum, no revenues accrue to the HA as it is assumed that the HA would not undertake any revenue generating opportunities. 19/40

20 4.1.4 In Strategies 3 and 4, it is assumed that the HA will initiate an interim strategy in respect of the masts opportunity. This is reflected in the 3.3 million Non Project mast revenues. In the PFI scenarios, these activities are transferred during year 4, to MCS Co and are reflected in mast revenues. In the PSC scenarios, the HA continues these activities itself and the revenues generated from year 4 on are reflected in Project revenues The PFI revenues in Strategies 3 and 4 also reflect additional revenue generating activities which would be undertaken by MCS Co, including data management in 3 and the UMTS/DSRC activities in The revenues shown in the PFI scenarios represent 40% of the gross potential revenues which may be expected to accrue. This is a conservative estimate of the proportion of expected revenues which the private sector may offer to offset against charges to the HA. In reality this figure would be derived in the competitive tendering process and negotiated with the preferred bidder. Revenues are based upon KHHS best estimates and are stated net of direct costs Revenues accruing to HA directly in the interim arrangements and PSC scenarios have been reduced to 30% of potential income on the assumption that the private sector will possess more finely honed commercial and selling skills To demonstrate the effect of these revenue assumptions on the total costs to the HA in each scenario, sensitivities assuming 0% and 100% achievement of gross potential revenue are provided in section 8. In addition, we have run a sensitivity for each strategy illustrating the level of revenue at which the matches the PSC in NPV value and at which the NPV cost to the HA is zero. 20/40

21 5.0 MCS CO CHARGES 5.1 MCS Co charges analysis by strategy The NPV of MCS Co (charges)/royalty to the HA for each of the PFI Strategies is set out in Figure 5.1 below. NPV MCS Co (charges)/royalty 3 PFI 4 UMTS PFI 4 DSRC PFI m m m (32.7) (27.3) Equivalent annual (charge)/royalty (5.9) (4.9) 36.0 NPV MCS Co charges (no third party revenue) (106.1) (116.2) (135.4) Equivalent annual charge (18.4) (21.1) (24.6) Figure 5.1: NPV of MCS Co charges by The charges are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6%, together with the equivalent annual (charge)/royalty MCS Co s (charges)/royalties are calculated so as to recover the MCS Co capital and operating expenditure in Figures 3.1 and 3.2, allowing for MCS Co revenues in Figure 4.1, plus sufficient profit to attain a post tax project IRR of 15% for Strategies 3 and 4 UMTS. A return of 25% is assumed under 4 DSRC to reflect the risk arising to the MCS Co from heavy dependence on DSRC revenues The charges have been modelled based on the following assumptions: a) MCS Co will be funded by 90% debt and 10% equity; b) interest is charged on balances outstanding at 7.5%; c) interest is rolled up for the first two years of MCS Co s operation; d) a debt service cover ratio of 1.3 is required; e) loan repayments commence in MCS Co s third year of operation and the capital balance is repaid in equal annual instalments at each period end commencing in MCS Co s third year of operation; f) corporation tax is assumed to be charged at 30%; and 21/40

22 g) capital allowances are available on capital expenditure at 25%. 5.2 Commentary on analysis The benefit of third party revenues on the level of charge to the HA is clearly demonstrated in the Figure above as the charge is expected to be lower for the higher functionality 4 than for 3. Indeed in 4 DSRC, the MCS Co would pay the HA for the right to provide the services due to the third party revenue opportunities this would provide. 4 DSRC is heavily dependent upon growth in new technologies and markets, whereas the UMTS option could build on existing networks. Detailed research will be necessary to establish more firmly the market opportunities for the MCS Co. This will be a key issue for a private sector investor assessing the viability of a potential PFI project and for the HA in assessing likely levels of charge. 22/40

23 6.0 HA MANAGEMENT AND ADMINISTRATION COSTS 6.1 HA management and administration costs analysis by The NPV cost to the HA for management and administration costs in each is set out in Figure 6.1 below. HA NPV retained costs Non project costs HA management and admin costs 2 3 PSC 3 PFI 4 PSC UMTS 4 PFI UMTS 4 PSC DSRC 4 PFI DSRC m m m m m m m (24.2) (24.3) (24.3) (24.3) (24.3) (24.3) (24.3) Project costs HA management and admin costs - (2.1) (3.7) (2.1) (3.7) (2.1) (3.7) Total management and admin costs (24.2) (26.4) (28.0) (26.4) (28.0) (26.4) (28.0) Figure 6.1: NPV of HA management and administration costs by The costs are shown over the 15 year evaluation period commencing 1 April 1999 and ending 31 March 2014, discounted at the Treasury s appraisal rate of 6% In order to quantify costs resulting directly from the HA s anticipated capital expenditure programme a staff model has been developed. This staff model reflects proposed expenditure under the NCP and relates this to numbers of HA staff against different grades and pay bands. Averaged HA pay bands for London and outer London based staff have been used along with a fixed rate for overhead costs, again based on an HA standard figure. The ratio of capital expenditure managed per employee has been used as a means to gauge the output of the staff model. Output figures have been compared with typical HA figures for various types of project work. This exercise would suggest that the staff model is reasonably accurate. An analysis of staff numbers has been provided in Figures 6.2 to 6.4 below Where it is proposed that the cabling works in schemes are transferred to MCS Co under Strategies 3 and 4, then a similar model has been used to determine MCS Co s staff costs. Efficiency savings within the private sector are catered for by an anticipated increase in the ratio of capital expenditure managed per staff employed. Capital costs transferred out of the HA domain require an adjustment to the basic HA staff cost model, firstly to reflect the reduced amount of capital expenditure and secondly to allow for the HA to manage effectively its interests in respect of MCS Co s operations. This actually results in a small increase in HA staff costs. 23/40

24 Project staff numbers The Project staff costs in the PFI Strategies reflect the costs of some 19 staff of varying grades to manage the contract and two staff to oversee the technical aspects of the procurement. It is assumed that financial assistance is obtained from FS and from external advisers. These may be analysed as follows; Grade Years 1 3 Years Figure 6.2: HA Project staff to manage PFI contracts Project staff numbers in each PSC are as follows: Years Grade Figure 6.3: HA Project staff numbers PSC 24/40

25 Non project staff numbers The non project staff in Strategies 2, 3 and 4 are as follows: Years Grade Figure 6.4: HA staff - 2, 3 and Commentary on analysis The PFI scenarios are consistently more expensive than the PSC conventional procurement, reflecting the need set out above for relatively senior staff to manage the contract. 25/40

26 THIS PAGE INTENTIONALY LEFT BLANK 26/40

27 7.0 STRATEGY RISK ASSESSMENT 7.1 Basis of risk assessment The aim of the risk assessment process is to arrive at a valuation of the risks retained by the HA under each, distinguishing between the PFI options and the PSC options, to enable a like with like comparison of the value for money provided by one strategy over another and by a PFI strategy against its PSC In assessing cost of retained risk by the HA, KHHS have focused only on those risks which are likely to have a material impact on the likely benefit of each, and are likely to differ materially between Strategies and between the PFI and PSC options of each The identification of the risks to be assessed is based both on KHHS s experience in this and related projects and on the basis of a risk workshop held with HA management and staff For the purposes of this risk assessment, we have focused on the risks associated with the upgrade and enhancement of the motorway communication services, since it is the Strategies 2, 3 and 4 affecting the MCS for which the risk adjusted financial analysis is being prepared. 7.2 Risk modelling method The risks are modelled using triangular distribution with three points - a minimum, most likely and maximum. As shown in Figure 7.1 below, the direction of the skew of the triangular distribution is set by the size of the most likely value relative to the minimum and the maximum. The probability of the occurrence of the minimum and maximum values are zero. Probability Minimum Most Likely Maximum Value of risk Figure 7.1: Triangular distribution The most likely values for each of the risks modelled are the annual input data for the cost or revenue input provided in respect of each. The minimum and maximum values are estimated as variances in percentage terms from the most likely value. 27/40

28 7.2.3 The effects of the risks on the total cost of each are combined using Latin hypercube sampling analysis. This provides a distribution of results from which we can obtain the mean risk adjusted cost and the 90% confidence range bounded by the 95 th and 5 th percentile Latin hypercube is a relatively new stratified sampling technique used in simulation modelling. Stratified sampling techniques, as opposed to Monte Carlo techniques, tend to force convergence of a sampled distribution in fewer samples. 7.3 Analysis of key risks for Motorway Communication Services In PFI projects, the basket of risks that are generally considered in the risk assessment are: a) design and construction risk: including fitness for purpose, failure to deliver against requirements, time and cost overrun; b) commissioning and operating risks: including the availability of the services; c) demand risks: risk of variability of usage; d) residual value risk: the risk concerning asset value at the termination of the contract; e) technology and obsolescence risk: risk that the assets will cease to be the most technically effective means of delivering the services; and f) regulatory and legislation risk: risk of changes in law and regulations affecting the services Against these typical risk headings KHHS have identified the key risks particular to the MCS. These are described below in general terms and assessed against the particular strategies below. Time and cost overrun during construction A key design and construction risk in most PFI projects is time and cost overrun. Experience in the public sector suggests that historically it has a poor record of managing cost overruns in large projects and the aim in PFI is to transfer much, if not all, of this risk to the private sector. In the case of this project, the particular issues concerning land ownership, the right access to the roadside verges and the scheduling thereof and ground conditions experienced in civil works all contribute to this risk The risks of Capital costs risk - overrun has been modelled in this feasibility study by reference to percentage increases and decreases on the annual input amounts to give maximum, most likely, and minimum inputs. The percentage increases and decreases are based on assessments described in section 7.5 which vary between Strategies and between the PSC and PFI inputs for the same. 28/40

29 Transition/migration - physical and contractual Among the commissioning and operating risks, transition risk is seen as a key risk to the HA in terms of underestimating the HA resources required to manage the transition from its existing contractual arrangements to new PSC or PFI arrangements proposed in the Strategies. Shortfalls in resources or skills will either need to be met through additional recruitment or result in project delays HA management and administration cost risk has been modelled in this feasibility study by reference to percentage increases and decreases on the annual input amounts to give maximum, most likely, and minimum inputs. The percentage increases and decreases are based on assessments described in section 7.5 which vary between Strategies and between the PSC and PFI inputs for the same There is also a technical risk relating to the transition and migration from the HA s existing largely bespoke, non-standard and multiple standard equipment to a new, modern, commercial equivalent. The HA is concerned that it or a PFI supplier may underestimate the work required in moving its systems and devices across to a new platform and the reconfiguration this is likely to entail This technical transition risk has been included for the purposes of the feasibility study in the assessment of Capital costs risk - transition which is again modelled by reference to percentage increases and decreases on the annual input amounts to give maximum, most likely, and minimum inputs. The percentage increases and decreases are based on assessments described in section 7.5 which vary between Strategies and between the PSC and PFI inputs for the same. Latent defect risk Another commissioning and operating risk which has been highlighted by potential private sector suppliers to the HA concerns latent defects in the HA s roadside equipment. Concerns focus particularly on some of the HA s fibre optic cable which is direct buried and more than five years old. It is feared that this may have deteriorated and not be of sufficient quality to be able to convey modern high data rates This is noted as a risk in this report but is not included in the risk assessment as we understand that the HA has issued instructions for tests to be carried out on the fibre concerned to establish the extent of this risk. The results of these tests are expected well before any contract involving third party exploitation of the cable is to be negotiated. However, in Part B of the project, we will have to examine in more detail a range of risks concerning the condition of the existing equipment, if it is to be transferred to the private sector, and the risks posed by the limited number of suppliers with the skills and knowledge to service it. 29/40

30 Reconfiguration risks The HA has identified a risk concerning the work currently required when new items of roadside equipment or new schemes are added to the existing communications network. These additions are often time critical to ensure the continuing safety of the highways. Given the hierarchical structure of much of the existing network, the addition of new equipment to it requires substantial, specialised reconfiguration. To complicate matters, the TSS team at the HA is often not given notice of the new requirements until very late in a project, requiring an immediate and considerable mobilisation of effort. This was demonstrated most recently by the bus lane project between Heathrow and Heston on the M The risk has several parts to it. First, there is the risk of perpetuating a hierarchical system design which renders additions to the network difficult and costly. Second, there is the risk that a new system or contract structure would not be flexible enough to allow a rapid response to safety requirements. Third, there is the risk that HA work practices and highways conditions generally will continue to generate unplanned and immediate requirements not covered by contractual obligations The first risk of unforeseen reconfiguration costs has been included for the purposes of the feasibility study in the assessment of Operating cost risk - reconfiguration which is modelled by reference to percentage increases and decreases on the annual input amounts to give maximum, most likely, and minimum inputs. The percentage increases and decreases are based on assessments described in section 7.5 which vary between Strategies and between the PSC and PFI inputs for the same The second risk in respect of the threat to improvements in road safety has not been assessed since a consideration of the benefits from improvements in road safety resulting from the project is not within the scope of the Specification The third risk relating to additional operating costs from unforeseen additional works has been included for the purposes of the feasibility study in the assessment of Operating cost risk - overrun. This also has been modelled by reference to percentage increases and decreases on the annual input amounts to give maximum, most likely, and minimum inputs. The percentage increases and decreases are based on assessments described in section 7.5 which vary between Strategies and between the PSC and PFI inputs for the same. Demand risk Demand risk relates to the HA s use of its communications network, and whether its actual usage justifies the investment in infrastructure. This risk will require careful consideration in Part B of the project as the scope of the requirement and potential demand for communications services is developed in detail. 30/40

31 Perhaps more significant for this project is the risk attaching to the demand from third parties for commercial services. As noted in section 8.2 of the Volume 2, MCS Co s assessment of this risk will determine the amount by which it is prepared to subsidise its charges to the HA. This has been treated as a sensitivity rather than a risk adjustment in the financial model as described in section 8. Additionally, revenues accruing to the HA have been subject to a risk assessment using a maximum value of +5% and a minimum of -100%. 7.4 Other risks considered by the Study During the course of the Study, other risks specific to the motorway communications network have been identified by KHHS. These risks are described here but have not been included in the financial assessment for the reasons noted. Capacity/availability With ever increasing demands for capacity, the HA is faced with the risk that whatever the arrangements it makes now for its motorway communications network, be they public sector procured or PFI, its capacity requirements in the future are misjudged and it finds itself constrained by its existing provision and is forced to make additional arrangements at additional expense. This risk is not considered material by the Study as modern technologies are providing ever increasing capacities over existing infrastructure. The HA s capacity requirements for the foreseeable future are thought unlikely to exceed the capacities which its existing infrastructure, and any new infrastructure, should be capable of providing with the necessary upgrades and modifications to its transmission The HA also faces a specific risk regarding the availability of its services given the current prevalence of civil contractors on the highways damaging the HA s buried equipment during the course of civil works. Whilst this practice causes considerable irritation and disruption to the HA, it is unlikely to result in a material financial risk. However, it does highlight the consideration which will need to be given to all of the interfaces an MCS Co will have with the HA and its existing contractors during Part B of the Project. Technology risk/residual value Given the speed of developments in telecommunications and the time taken in the public sector to formulate and receive authorisation for projects, be they public sector funded or private sector funded, there is a risk to the HA that it adopts or is provided with a communications network which over the course of the project ceases to be the most technically effective means of delivering the service. The result would be that the HA is locked into a higher operational cost than is necessary or has to reinvest in order to secure a more cost effective service or one that meets new requirements enabled by new technology. 31/40

32 7.4.5 This risk is common across all telecommunications solutions for communications traffic, but it is greater for more specific applications such as roadside to vehicle links. It is not possible to quantify this risk, but it will require a qualitative consideration when determining between bidders solutions in 4 and between Strategies 3 and Assessment of HA s retained risks under each strategy Following on from the narrative in section 7.3 above, KHHS have identified the following risks for inclusion in the financial assessment of risks retained by the HA under each : a) Capital costs risk - overrun; b) Capital costs risk - transition; c) HA management and administration cost risk; d) Operating costs risk - overrun; e) Operating costs risk - reconfiguration; f) Revenue risk. Capital costs risk - overrun Capital cost risk - overrun is simply the risk of cost overruns in the capital costs of the project. Possible causes of such overruns, in addition to the usual incomplete budgeting risks, have been identified as difficulties in access to the roadside verges and ground conditions. The risk is stated in terms of minimum and maximum percentage variations from the annual capital cost input data The assessments for each strategy are set out in Figure 7.2 below: Project 2 3 PSC 3 PFI 4 PSC 4 PFI % % % % % Minimum n/a -5% n/a -5% n/a Most Likely n/a 0% n/a 0% n/a Maximum n/a +50% n/a +50% n/a Non project Minimum -5% -5% -5% -5% -5% Most Likely 0% 0% 0% 0% 0% Maximum +15% +15% +15% +15% +15% Figure 7.2: Capital cost risk - overrun assessment 32/40

33 7.5.4 The risk workshop assessed capital cost risks separately for Project and Non Project costs In the PFI Strategies 3 and 4, it considered that risk of capital cost overruns for Project costs would be transferred entirely to the private sector and there would therefore be minimal retained risk to the HA However where the costs are retained by the public sector, which includes all Non project capital costs and Project costs in the PSCs, the risk is retained by the HA. Project costs were viewed as carrying a substantially higher risk than Non project costs, with the potential for up to a 50% overrun. Historically, the HA has never completed a capital project for a lower cost than the original estimate. The risk for Non project costs of overruns was less at 15%, and both on the upside could benefit from up to a 5% underspend. Capital costs risk - transition Capital cost risk - transition is the risk relating to the transition and migration from the HA s existing largely bespoke, non-standard and multiple standard equipment to a new, modern, commercial equivalent. The risk is stated in terms of minimum and maximum percentage variations from the annual capital cost input data The basis of the risk assessment is that the risk of transition cost overruns in the 3 and 4 PFI options is transferred entirely to the private sector and there is therefore no retained risk to the HA. For the public sector options, 2, 3 PSC and 4 PSC the risk is retained by the HA and it may suffer a maximum 2.5% overspend on Project capital costs as a result The workshop agreed that this risk is reflected within the 50% assessment in Figure 7.2 above. HA management and administration cost risk HA management and administration cost risk is simply the risk of cost overruns in these costs. Possible causes of such overruns, in addition to the usual incomplete budgeting risks, have been identified as difficulties in managing the transition from existing contractual arrangements to new arrangements. The risk is stated in terms of minimum and maximum percentage variations from the annual HA management and administration cost input data The assessments for each strategy are set out in Figure 7.3 below: 2 3 PSC 33/40 3 PFI 4 PSC 4 PFI % % % % % Minimum -5% -5% -10% -5% -10% Most Likely 0% 0% 0% 0% 0% Maximum +15% +15% +25% +15% +25% Figure 7.3: HA management and administration cost risk assessment

Public Private Partnerships in the National Health Service: The Private Finance Initiative

Public Private Partnerships in the National Health Service: The Private Finance Initiative Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Home Affairs Bureau. Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak

Home Affairs Bureau. Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak Home Affairs Bureau Detailed Financial Profile of the Procurement and Financing Options related to the Multipurpose Sports Complex (MPSC) at Kai Tak Final Report September 2013 Contents 1. Introduction...3

More information

Learning Le cy Document

Learning Le cy Document PROGRAMME CONTROL Quantitative Risk Assessment Procedure Document Number: CR-XRL-Z9-GPD-CR001-50004 Document History: Revision Prepared Date: Author: Reviewed by: Approved by: Reason for Issue 1.0 15-06-2015

More information

Sri Lanka Accounting Standard-SLFRS 7. Financial Instruments: Disclosures

Sri Lanka Accounting Standard-SLFRS 7. Financial Instruments: Disclosures Sri Lanka Accounting Standard-SLFRS 7 Financial Instruments: Disclosures CONTENTS SRI LANKA ACCOUNTING STANDARD-SLFRS 7 FINANCIAL INSTRUMENTS: DISCLOSURES paragraphs OBJECTIVE 1 2 SCOPE 3 5 CLASSES OF

More information

Model Concession Agreement for Highways: An Overview

Model Concession Agreement for Highways: An Overview Model Concession Agreement for Highways: An Overview - Gajendra Haldea The highways sector in India is witnessing significant interest from both domestic as well as foreign investors following the policy

More information

Redevelopment of MOD Main Building

Redevelopment of MOD Main Building Ministry of Defence Redevelopment of MOD Main Building REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 748 Session 2001-2002: 18 April 2002 LONDON: The Stationery Office 0.00 Ordered by the House of Commons

More information

VOLTA RIVER AUTHORITY

VOLTA RIVER AUTHORITY VOLTA RIVER AUTHORITY Capital Expenditure Guidelines November 2012 TABLE OF CONTENTS PAGE 1.0 Purpose and Scope of Guidelines...3 2.0 Projects Guidelines Apply To....4 3.0 Exemptions from Guidelines...4

More information

Public Private Partnerships (PPPs) Projects

Public Private Partnerships (PPPs) Projects Development Process of Public Private Partnerships (PPPs) Projects By Dr Paul H K Ho 1 Disclaimer Funded by Commerce, Industry and Technology Bureau, The Government of the Hong Kong Special Administrative

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework The highways sector in India is witnessing a significant interest from both domestic as well as foreign investors following the policy initiatives taken by

More information

The Capital Expenditure Decision

The Capital Expenditure Decision 1 2 October 1989 The Capital Expenditure Decision CONTENTS 2 Paragraphs INTRODUCTION... 1-4 SECTION 1 QUANTITATIVE ESTIMATES... 5-44 Fixed Investment Estimates... 8-11 Working Capital Estimates... 12 The

More information

Sensitivity = NPV / PV of key input

Sensitivity = NPV / PV of key input SECTION A 20 MARKS Question One 1.1 The answer is D 1.2 The answer is C Sensitivity measures the percentage change in a key input (for example initial outlay, direct material, direct labour, residual value)

More information

Distractor B: Candidate gets it wrong way round. Distractors C & D: Candidate only compares admin fee to cost without factor.

Distractor B: Candidate gets it wrong way round. Distractors C & D: Candidate only compares admin fee to cost without factor. Answers ACCA Certified Accounting Technician Examination, Paper T10 Managing Finances June 2010 Answers Section A 1 D 2 A 365/ 23 100 1 173 % 100 1 = 365/ 23 1 1+ 1 173 99 = % Candidates should answer

More information

Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt. March An introduction to infrastructure debt

Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt. March An introduction to infrastructure debt An introduction to infrastructure debt Macquarie Infrastructure Debt Investment Solutions An introduction to infrastructure debt March 2017 1 macquarie.com 2 Important Notice This document is issued by

More information

The challenge of paying for smart cities projects

The challenge of paying for smart cities projects The challenge of paying for smart cities projects 2 About John Skowron John has more than 25 years of experience in industry and management consulting. Within Deloitte Consulting LLP, he serves as the

More information

P3 Fundamentals and Best Practices in Resource and Project Management

P3 Fundamentals and Best Practices in Resource and Project Management Achieving better value, timeliness and accountability through public-private partnerships P3 Fundamentals and Best Practices in Resource and Project Management Ottawa, Ontario November 26, 2015 Greg Smith

More information

Allocation of risk between parties - fixed price mechanisms Price setting mechanisms

Allocation of risk between parties - fixed price mechanisms Price setting mechanisms 10.0 Price setting mechanisms Price setting mechanisms fall into two main categories: fixed and variable. A fixed price mechanism is a straightforward concept which typically results in a relatively stable

More information

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints None. Authoritative Guidance Summary 1. Cost Assurance and Analysis Service (CAAS) provide a range of services for the Defence Equipment

More information

P1 Performance Operations September 2014 examination

P1 Performance Operations September 2014 examination Operational Level Paper P1 Performance Operations September 2014 examination Examiner s Answers Note: Some of the answers that follow are fuller and more comprehensive than would be expected from a well-prepared

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Waste Management Advisory Group Leader and Cabinet Housing and Environmental Services Director

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Waste Management Advisory Group Leader and Cabinet Housing and Environmental Services Director SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: AUTHOR: Waste Management Advisory Group Leader and Cabinet Housing and Environmental Services Director 13 July 2005 14 July 2005 PROCUREMENT OPTIONS FOR

More information

Office of Utility Regulation

Office of Utility Regulation Office of Utility Regulation Investigation into Wholesale Broadband Pricing Draft Decision Document No: OUR 06/05 February 2006 Office of Utility Regulation Suites B1 & B2, Hirzel Court, St Peter Port,

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Doheny Desalination Project Value-for-Money Analysis. March

Doheny Desalination Project Value-for-Money Analysis. March Doheny Desalination Project Value-for-Money Analysis March 22 2017 Presentation Overview Team Introductions Goals of the VfM Analysis Financial Model Estimated Monthly Impacts to Typical Households In

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

Nigeria Infrastructure Building Conference 2014

Nigeria Infrastructure Building Conference 2014 Nigeria Infrastructure Building Conference 2014 May 2011 Project Finance as a viable option for financing Infrastructure Projects P R E P A R E D B Y: Helen Brume Divisional Head, Power, Infrastructure

More information

F3 Financial Strategy

F3 Financial Strategy Strategic Level Paper F3 Financial Strategy Senior Examiner s Answers SECTION A Answer to Question One (a)(i) Valuation of Company NN (excluding potential synergistic benefits and integration costs) NN:

More information

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION SCHEDULE F BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION cl. 7.3.1, 9.1.1 F1 Qualitative information required in a base capex proposal For the purpose of clause 7.3.1 (1) a base capex proposal must, in

More information

INTERNATIONAL STANDARD ON AUDITING (UK) 570 (REVISED) GOING CONCERN

INTERNATIONAL STANDARD ON AUDITING (UK) 570 (REVISED) GOING CONCERN INTERNATIONAL STANDARD ON AUDITING (UK) 570 (REVISED) GOING CONCERN (Effective for audits of financial statements for periods commencing on or after 15 December 2019) Introduction CONTENTS Paragraph Scope

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

IRAS e-tax Guide. Transfer Pricing Guidelines (Fourth edition)

IRAS e-tax Guide. Transfer Pricing Guidelines (Fourth edition) IRAS e-tax Guide Transfer Pricing Guidelines (Fourth edition) Published by Inland Revenue Authority of Singapore Published on 12 Jan 2017 First edition on 23 Feb 2006 Disclaimers: IRAS shall not be responsible

More information

Accounting Standard (AS) 32 Financial Instruments: Disclosures. Issued by The Institute of Chartered Accountants of India New Delhi

Accounting Standard (AS) 32 Financial Instruments: Disclosures. Issued by The Institute of Chartered Accountants of India New Delhi Accounting Standard (AS) 32 Financial Instruments: Disclosures Issued by The Institute of Chartered Accountants of India New Delhi 2 Accounting Standard (AS) 32 Financial Instruments: Disclosures Contents

More information

Chapter-8 Risk Management

Chapter-8 Risk Management Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

(a) (i) Year 0 Year 1 Year 2 Year 3 $ $ $ $ Lease Lease payment (55,000) (55,000) (55,000) Borrow and buy Initial cost (160,000) Residual value 40,000

(a) (i) Year 0 Year 1 Year 2 Year 3 $ $ $ $ Lease Lease payment (55,000) (55,000) (55,000) Borrow and buy Initial cost (160,000) Residual value 40,000 Answers Applied Skills, FM Financial Management (FM) September/December 2018 Sample Answers Section C 31 Melanie Co (a) (i) Year 0 Year 1 Year 2 Year 3 $ $ $ $ Lease Lease payment (55,000) (55,000) (55,000)

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

KING FAHAD UNIVERSITY OF PETROLEUM & MINERALS COLLEGE OF ENVIROMENTAL DESGIN CONSTRUCTION ENGINEERING & MANAGEMENT DEPARTMENT

KING FAHAD UNIVERSITY OF PETROLEUM & MINERALS COLLEGE OF ENVIROMENTAL DESGIN CONSTRUCTION ENGINEERING & MANAGEMENT DEPARTMENT KING FAHAD UNIVERSITY OF PETROLEUM & MINERALS COLLEGE OF ENVIROMENTAL DESGIN CONSTRUCTION ENGINEERING & MANAGEMENT DEPARTMENT Report on: Associated Problems with Life Cycle Costing As partial fulfillment

More information

Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management (Singapore)

Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management (Singapore) Answers Professional Level Options Module, Paper P4 (SGP) Advanced Financial Management () June 2010 Answers 1 The answer should be presented as a briefing note. The standard financial appraisal is supplemented

More information

WHAT S NEXT FOR UK PROJECTS?

WHAT S NEXT FOR UK PROJECTS? WHAT S NEXT FOR UK PROJECTS? THE END OF PFI AND THE CHALLENGE AHEAD WHAT S HAPPENED? In his budget speech of 29 October, Philip Hammond announced the end of PFI and PF2, stating that as Chancellor he had

More information

OPERATIONAL CASE STUDY NOVEMBER 2016 EXAM ANSWERS. Variant 2. The November 2016 exam can be viewed at

OPERATIONAL CASE STUDY NOVEMBER 2016 EXAM ANSWERS. Variant 2. The November 2016 exam can be viewed at OPERATIONAL CASE STUDY NOVEMBER 2016 EXAM ANSWERS Variant 2 The November 2016 exam can be viewed at https://connect.cimaglobal.com/resources/november-2016- operational-case-study-variant-2 SECTION 1 EFFECTIVE

More information

C A Y M A N I S L A N D S MONETARY AUTHORITY

C A Y M A N I S L A N D S MONETARY AUTHORITY Statement of Guidance Credit Risk Classification, Provisioning and Management Policy and Development Division Page 1 of 22 Table of Contents 1 Statement of Objectives... 3 2 Scope... 3 3 Terminology...

More information

B.4. Intra-Group Services

B.4. Intra-Group Services B.4. Intra-Group Services Introduction B.4.1. This chapter considers the transfer prices for intra-group services within an MNE group. Firstly, it considers the tests for determining whether chargeable

More information

Approach to Assessing Capital Expenditure for Price Reviews

Approach to Assessing Capital Expenditure for Price Reviews Approach to Assessing Capital Expenditure for Price Reviews January 2018 This document examines approaches to assessing capital expenditure (Capex) in general and what has been specifically employed by

More information

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from PPP Forum

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from PPP Forum About Finance Committee Inquiry into methods of funding capital investment projects Submission from Established in 2001, the is an industry body representing over 110 private sector companies involved

More information

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper june 07 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Contents: Page Preface Executive Summary 1 2 1 Service Costing in the General Government

More information

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001 NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller

More information

Chapter 14 Solutions Solution 14.1

Chapter 14 Solutions Solution 14.1 Chapter 14 Solutions Solution 14.1 a) Compare and contrast the various methods of investment appraisal. To what extent would it be true to say there is a place for each of them As capital investment decisions

More information

TIME:CTC. Corporate Trading Companies. Information Memorandum

TIME:CTC. Corporate Trading Companies. Information Memorandum Corporate Trading Companies Information Memorandum Corporate Trading Companies This document is for Authorised Financial Advisers only and for existing Shareholders for information only. Issued in the

More information

Q. Can you explain the main principles of PFI, what it will mean for the Island and how it is financed?

Q. Can you explain the main principles of PFI, what it will mean for the Island and how it is financed? The Highways Private Finance Initiative (PFI) has been the subject of much interest recently. This is not surprising given the massive scope of the scheme and the impact it will have on the Island s transport

More information

The Examiner's Answers Specimen Paper F3 - Financial Strategy

The Examiner's Answers Specimen Paper F3 - Financial Strategy The Examiner's Answers Specimen Paper F3 - Financial Strategy SECTION A Answer to Question One Requirement (a) Appendix A 1. Assume constant exchange rate Project years 1 3 4 5 5 to 24 6 to 25 Calendar

More information

RESERVE BANK OF MALAWI

RESERVE BANK OF MALAWI RESERVE BANK OF MALAWI GUIDELINES ON INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS (ICAAP) Bank Supervision Department March 2013 Table of Contents 1.0 INTRODUCTION... 2 2.0 MANDATE... 2 3.0 RATIONALE...

More information

MODULE 4 PLANNING AND CONTROL

MODULE 4 PLANNING AND CONTROL MODULE 4 PLANNING AND CONTROL OUTLINES The purpose of budgetary control system Alternative approaches to budgeting, including incremental budgeting, Zero-based budgeting, Activity-based budgeting, rolling

More information

Routes to Market: Smart Motorways Alliance Commercial Model Summary

Routes to Market: Smart Motorways Alliance Commercial Model Summary Routes to Market: Smart Motorways Alliance Commercial Model Summary August 2018 Overview: The proposals outlined within are draft proposals and subject to sign-off from our governance process. Non-participation

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

Global Investment Opportunities and Product Disclosure

Global Investment Opportunities and Product Disclosure Global Investment Opportunities and Product Disclosure Our clients look to us, the Citi Private Bank, to help them diversify their investment portfolios across different currencies, asset classes and markets

More information

FRAMEWORK FOR SUPERVISORY INFORMATION

FRAMEWORK FOR SUPERVISORY INFORMATION FRAMEWORK FOR SUPERVISORY INFORMATION ABOUT THE DERIVATIVES ACTIVITIES OF BANKS AND SECURITIES FIRMS (Joint report issued in conjunction with the Technical Committee of IOSCO) (May 1995) I. Introduction

More information

Privatisation and Infrastructure Australian Federal Tax Framework (January 2017 Draft)

Privatisation and Infrastructure Australian Federal Tax Framework (January 2017 Draft) Privatisation and Infrastructure Australian Federal Tax Framework (January 2017 Draft) QUALIFICATION THIS DOCUMENT IS A DRAFT. IT IS INTENDED TO GENERATE FEEDBACK FROM STAKEHOLDERS ON THE ISSUES IT RAISES

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 Ofwat Issued April 1997 Revised March 2000 1 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE CONTENTS

More information

Financial Instruments: Disclosures

Financial Instruments: Disclosures IFRS 7 International Financial Reporting Standard 7 Financial Instruments: Disclosures This version includes amendments resulting from IFRSs issued up to 31 December 2008. IAS 30 Disclosures in the Financial

More information

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,

More information

Undertaking Successful PPPs in Kazakhstan

Undertaking Successful PPPs in Kazakhstan Undertaking Successful PPPs in Kazakhstan Stephen Watson Head of Service PPP Astana, Kazakhstan 24 October 2013 image courtesy of stock.xchng Contents PPP Principles PPPs in Kazakhstan Renewables in Kazakhstan

More information

E.WA.R.U. Efficient WAter Resource Use ANNEX N.8 PROJECT FINANCING DRAFT REPORT

E.WA.R.U. Efficient WAter Resource Use ANNEX N.8 PROJECT FINANCING DRAFT REPORT E.WA.R.U. Efficient WAter Resource Use ANNEX N.8 PROJECT FINANCING DRAFT REPORT JANUARY 2007 Project Finance draft report 1. Generalities Project Financing is a particular financial technique with the

More information

P1 Performance Operations March 2014 examination

P1 Performance Operations March 2014 examination Operational Level Paper P1 Performance Operations March 2014 examination Examiner s Answers Note: Some of the answers that follow are fuller and more comprehensive than would be expected from a well-prepared

More information

Project Finance An Overview

Project Finance An Overview Project Finance An Overview KAMAL TAK ICAI, Navi Mumbai Chapter December 16, 2012 1 Project Finance An Overview What is Project Financing? How is it different? How are Projects developed? Various Project

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

Probabilistic Benefit Cost Ratio A Case Study

Probabilistic Benefit Cost Ratio A Case Study Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case

More information

Ingenious Capital Management Limited: Pillar III Disclosure

Ingenious Capital Management Limited: Pillar III Disclosure CONTENTS 1. Introduction 2. Risk Management 3. Capital Resources 4. Internal Capital Adequacy Assessment Process (ICAAP) 5. Remuneration Policy Disclosure 1. INTRODUCTION 1.1 Scope of Application Ingenious

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

PPP Finance and Legal Issues. Edward Farquharson 25 July 2006

PPP Finance and Legal Issues. Edward Farquharson 25 July 2006 PPP Finance and Legal Issues Edward Farquharson 25 July 2006 Modes of Finance Sovereign Finance Public Sector Full Recourse Private Sector Non Recourse Corporate Finance Project Finance Agenda Role of

More information

RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS

RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS CARE s rating methodology for debt issues of road projects (RPs) is designed to facilitate appropriate credit risk assessment, keeping in view the

More information

When Worlds Collide: Indefeasible Rights of Use, Tax and Commercial Reality

When Worlds Collide: Indefeasible Rights of Use, Tax and Commercial Reality When Worlds Collide: Indefeasible Rights of Use, Tax and Commercial Reality J a m e s H a llid a y a n d L in k T ran James Halliday (Partner, Baker & McKenzie) and Link Tran (Associate, Baker & McKenzie)

More information

Revenue from Contracts with Customers A guide to IFRS 15

Revenue from Contracts with Customers A guide to IFRS 15 Revenue from Contracts with Customers A guide to IFRS 15 March 2018 This guide contains general information only, and none of Deloitte Touche Tohmatsu Limited, its member firms, or their related entities

More information

Risk Management Guidelines

Risk Management Guidelines Risk Management Guidelines Guideline as defined for this manual is a detailed minimum requirement to implement Risk Management 10/19/2011 Risk Management Guidelines for the Capital Program PD-QA-05-019,

More information

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK ANNEXURE A ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK CONTENTS 1. Enterprise Risk Management Policy Commitment 3 2. Introduction 4 3. Reporting requirements 5 3.1 Internal reporting processes for risk

More information

Programmatic Risk Management in Space Projects

Programmatic Risk Management in Space Projects r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands

More information

Cambourne to Cambridge Better Bus Journeys Scheme: Strategic Outline Business Case Commercial Case City Deal Partners.

Cambourne to Cambridge Better Bus Journeys Scheme: Strategic Outline Business Case Commercial Case City Deal Partners. Cambourne to Cambridge Better Bus Journeys Scheme: Strategic Outline Business Case City Deal Partners 23 September 2016 Notice This document and its contents have been prepared and are intended solely

More information

RISK FACTORS RISKS RELATING TO PARTICIPATION IN THE TOKEN SALE

RISK FACTORS RISKS RELATING TO PARTICIPATION IN THE TOKEN SALE RISK FACTORS You should carefully consider and evaluate each of the following risk factors and all other information contained in the Terms of Token Sale (the Terms ) before deciding to participate in

More information

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES)

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES) Prop Co (NO APPENDICES) 1 CONTENTS 1 Context 4 2 Overview of PropCo 5 2.1 Form of PropCo 5 2.2 Scope of PropCo 5 2.3 Included services 6 2.4 Excluded services 6 2.5 Services to be included subject to confirming

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

Notes to the Financial Statements

Notes to the Financial Statements For the financial year ended 31 March These notes form an integral part of and should be read in conjunction with the accompanying financial statements. 1. GENERAL Singtel is domiciled and incorporated

More information

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10.

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10. Meeting Finance Committee Date and Time 15 th May 2018 Location SPA Boardroom, Pacific Quay Title of Paper Forensic Services Budget Management and Month End Guidelines Item Number 10.2 Presented By Amy

More information

POLICY BRIEFING The Private Finance Initiative: Treasury Select Committee report

POLICY BRIEFING The Private Finance Initiative: Treasury Select Committee report The Private Finance Initiative: Treasury Select Committee report Date: 23 August 2011 Author: Janet Sillett Overview In a statement accompanying the publication of the Treasury Select Committee's report

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. cover_test.indd 1-2 4/24/09 11:55:22

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. cover_test.indd 1-2 4/24/09 11:55:22 cover_test.indd 1-2 4/24/09 11:55:22 losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 1 4/24/09 11:58:20 What is an actuary?... 1 Basic actuarial

More information

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project http://dx.doi.org/10.3991/ijoe.v9i3.2804 Wei Peng 1,2, Honglei Liu 1, * 1 Tongji University, Shanghai

More information

SCHEDULE 9 COMPENSATION ON TERMINATION TABLE OF CONTENTS 1. TERMINATION FOR AUTHORITY EVENT OF DEFAULT OR AT AUTHORITY S OPTION...

SCHEDULE 9 COMPENSATION ON TERMINATION TABLE OF CONTENTS 1. TERMINATION FOR AUTHORITY EVENT OF DEFAULT OR AT AUTHORITY S OPTION... SCHEDULE 9 COMPENSATION ON TERMINATION TABLE OF CONTENTS 1. TERMINATION FOR AUTHORITY EVENT OF DEFAULT OR AT AUTHORITY S OPTION... 1 1.1 Calculation... 1 1.2 Notice to the Authority... 2 2. TERMINATION

More information

Impact of changes to the Paper P3, Business Analysis and Paper P5, Advanced Performance Management syllabuses from June 2011

Impact of changes to the Paper P3, Business Analysis and Paper P5, Advanced Performance Management syllabuses from June 2011 RELEVANT TO ACCA QUALIFICATION PAPERS P3 AND P5 Impact of changes to the Paper P3, Business Analysis and Paper P5, Advanced Performance Management syllabuses from June 2011 This article explains the rationale

More information

Project Finance Modelling

Project Finance Modelling Project Finance Modelling A 3 Day Programme This course is presented in London on: 28 February 2 March 2018, 10-12 September 2018 The Banking and Corporate Finance Training Specialist Course Objectives

More information

Management Accounting

Management Accounting Management Accounting Level 3 Model Answers Series 3 2008 (Code 3023) 1 ASE 3023 2 06 1 3023/2/06 >f0t@w9w2`?[i]bkbw5k# Management Accounting Level 3 Series 3 2008 How to use this booklet Model Answers

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: PRINCE2 Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 1.0 Exam M QUESTION 1 Identify the missing word(s) from the following sentence. A project is a temporary organization that is

More information

Module 7 Statement of Cash Flows

Module 7 Statement of Cash Flows IFRS for SMEs Standard (2015) + Q&As IFRS Foundation Supporting Material for the IFRS for SMEs Standard Module 7 Statement of Cash Flows IFRS Foundation Supporting Material for the IFRS for SMEs Standard

More information

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management AACE International Recommended Practice No. 44R-08 RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management Acknowledgments: John K. Hollmann, PE CCE CEP (Author)

More information

Infrastructure Ontario Alternative Financing and Procurement

Infrastructure Ontario Alternative Financing and Procurement Infrastructure Ontario Alternative Financing and Procurement Presentation for the High Ground Panel on Public Finance: Who s Picking Up The Tab? Bonnie Lysyk, Auditor General of Ontario March 20, 2015

More information

Community and Renewable Energy Scheme Project Development Project Toolkit Project Finance Module

Community and Renewable Energy Scheme Project Development Project Toolkit Project Finance Module Community and Renewable Energy Scheme Project Development Project Toolkit Module Structure In the past, it was the case that the high costs involved with setting up loan finance for energy projects tended

More information

Kyrgyz Republic: Borrowing by Individuals

Kyrgyz Republic: Borrowing by Individuals Kyrgyz Republic: Borrowing by Individuals A Review of the Attitudes and Capacity for Indebtedness Summary Issues and Observations In partnership with: 1 INTRODUCTION A survey was undertaken in September

More information

Economic Analysis Concepts

Economic Analysis Concepts Economic Analysis Concepts Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds

More information

Life-Cycle Project Delivery

Life-Cycle Project Delivery Life-Cycle Project Delivery A Note for Discussion IndII Round Table 11 th December 2012 Concerns with Conventional Project Delivery Government pays for inputs, not outputs Incentive for time/cost over-runs

More information

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.

More information

Date: July 18, 2010 Max Marks: 60 Max Time: 3 Hours. Discuss a Project Development Cycle in detail.

Date: July 18, 2010 Max Marks: 60 Max Time: 3 Hours. Discuss a Project Development Cycle in detail. University of Karachi FINAL EXAMINATION, JUEN 2010; AFFILIATED COLLEGES PROJECT APPRAISAL: BA (M) - 683 Date: July 18, 2010 Max Marks: 60 Max Time: 3 Hours Question 1 What do you understand by a project

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information