PAK: National Highway Development Sector Investment Program Tranche 2

Size: px
Start display at page:

Download "PAK: National Highway Development Sector Investment Program Tranche 2"

Transcription

1 Social Monitoring Report Final External Monitoring Report for the Implementation of Resettlement Plans June 2013 Loan 2540-PAK PAK: National Highway Development Sector Investment Program Tranche 2 Sukkur Jacobabad Road Project (N-65) Prepared by Shaukat Ali Shahid for National Highway Authority and the Asian Development Bank.

2 2 This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

3 NATIONAL HIGHWAY AUTHORITY Ministry of Communications Government of Pakistan SUKKUR JACOBABAD ROAD PROJECT (N-65) (ADB Loan 2540) FINAL EXTERNAL MONITORING FOR THE IMPLEMENTATION OF RESETTLEMENT PLANS By Shaukat Ali Shahid External Monitoring Consultant International Development Consultants (IDC) Suite # 3, 11-Civic Centre, C-Block, Faisal Town, Lahore. Ph: , Fax: , idcpk@hotmail.com June, 2013 i

4 NATIONAL HIGHWAY AUTHORITY Ministry of Communications Government of Pakistan SUKKUR JACOBABAD ROAD PROJECT (N-65) (ADB Loan 2540) FINAL EXTERNAL MONITORING FOR THE IMPLEMENTATION OF RESETTLEMENT PLANS By Shaukat Ali Shahid External Monitoring Consultant International Development Consultants (IDC) Suite # 3, 11-Civic Centre, C-Block, Faisal Town, Lahore. Ph: , Fax: ; idcpk@hotmail.com June, 2013 ii

5 TABLE OF CONTENTS LIST OF TABLES... iv LIST OF FIGURES... iv LIST OF ANNEXES... iv ABBREVIATIONS... v EXECUTIVE SUMMARY... vi 1. INTRODUCTION Background Objectives of the External Monitoring METHODOLOGY General Review of the Project Documents Consultative Meetings Data Collection and Analysis IMPLEMENTATION STATUS OF SECTION LARPs (I IV) Implementation Status of RP of Section Implementation Status of LARP of Section Implementation Status of RP of Section Implementation Status of RP of Section CONSULTATIVE MEETINGS Consultative Meetings Consultative Meetings with APs/ Locals PROJECT SUCCESS Institutional Arrangements ANNEXES iii

6 LIST OF TABLES Table 3.1: Status of Implementation of RP of Section Table 3.2: Status of Implementation of RP of Section Table 3.3: Status of Implementation of RP of Section Table 3.5: Status of Implementation of LARP of Section Table 4.1: List of APs/ Local People Consulted LIST OF FIGURES Figure 1.1: Location Map of Sukkur Jacobabad Road Project... 2 Figure 1.2: Layout Plan of Sukkur Jacobabad Road Project (N-65)... 2 LIST OF ANNEXES Annex A... xi Annex 1: List of Unpaid APs at Section Annex 2: List of Unpaid APs (Land Owners) at Section 2 (Shikarpur Bypass) Annex 3: List of Unpaid APs at Section Annex 4: List of Unpaid APs at Section iv

7 ABBREVIATIONS AD ADB AFs APs EALS EMA EMR GOP GRC IDC IMR LAA LAR LARF LARP LARU MFF NHA NHDSIP NTP PD PRM Rft. RoW RP Assistant Director Asian Development Bank Affected Families Affected Persons Environment, Afforestation, Land and Social External Monitoring Agency External Monitoring Report Government of Pakistan Grievance Redress Committee International Development Consultants Internal Monitoring Report Land Acquisition Act Land Acquisition and Resettlement Land Acquisition and Resettlement Framework Land Acquisition and Resettlement Plan Land Acquisition and Resettlement Unit Multi-tranche Financing Facility National Highway Authority National Highway Development Sector Investment Program Notice to Proceed Project Director Pakistan Resident Mission Running Feet Right of Way Resettlement Plan v

8 EXECUTIVE SUMMARY 1. This external monitoring report prepared based on field survey carried out from June, The report reflects the implementation status of sectional Resettlement Plans (I - IV) till the period upto 15 th June, 2013 and the actions agreed by NHA to complete the process of payments of all four sections. Summary of major findings of implementation status of Sectional LARPs as discussed in subsequent sections, reveals that over and above 97% of AFs are paid with no critical outstanding issues at the part of EA. Hence concluding that the LARP implementation is almost completed, it is the final External Monitoring Report for Sukkur-Jacobaabad (N-65) sub-project. Below is the implementation status of LARP in each section: Section 1 2. In LARP Section-1, out of total 300 AFs, 295 AFs (98.3%) are paid. The left over 5 AFs include 1 court case, 1 business renter and 3 AFs in employee category who left the project corridor with unknown whereabouts. The NHA is following up the court case for its early adjudication and confirmed that the court s decision will be implemented in letter and spirit. For the APs who left project corridor with unknown whereabouts, NHA has placed their entitled compensation in the project account and publically informed through newspapers (daily Kawish and daily Jang) the APs to come up and collect their compensation. NHA did all efforts (still continued) to disburse 100% compensation, but the leftover payments to 1.7% (5 AFs) AFs are beyond NHA s control. However NHA is committed to make payment to remaining APs as and when the court decide the issue or the APs with their whereabouts unknown approaches the NHA and submit their claims for payment. Conclusion 3. Based on progress achieved above 98.3%, it is concluded that the Resettlement Plan of Section 1 has been implemented and the RoW has already been cleared for construction work in the Second EMA report (March, 2012). Section 2 (Including Bypass): 4. The LARP Section 2 includes 15.7 Km carriage way section (RD to and to ) and 4.95 Km Bypass Section (RD to ) with total 85 AFs (7 in carriage way section and 78 in by-pass section). The compensation payment progress reflects that out of total 85 AFs, 84 AFs have been paid while 1 AF in land owner category (Bypass section) left unpaid because he has filed reference in the court for enhancement of compensation. NHA confirmed that the land cost is already deposited in the treasury and the court s decision will be binding to make payment of compensation accordingly. NHA maintained a close liaison between the land owner (AF) and the local revenue authorities to ensure timely disbursement of compensation as court decides. While as a last resort, the District Revenue Officer has already informed to all unpaid AFs publically (the daily Kawish and Jang newspapers) to come-up, submit their claims and collect their entitled compensation without delay. Conclusion 5. The overall progress reflected that only 1 AF is left unpaid due to court case which is beyond NHA s preview. Hence it is concluded that with 99% implementation progress, the LARP for Section 2 is effectively implemented and the whole length of Section 2 including existing carriage way and Bypass sections has already been cleared for commencement of construction works as per findings of 2 nd and 3 rd External Monitoring Reports respectively. vi

9 Section 3 6. In Section 3, out of the total length of 20.2 km, 13.4 km with zero LAR impacts area was cleared for construction following recommendations in Second EMA report (March, 2012). While, the remaining 6.5 km area having LAR impacts was withheld till the RP has been implemented successfully in different stretches of varying lengths and the RP implementation status is confirmed through the External Monitoring Agency (EMA). In the LARP Section 3 the resettlement impacts are mainly due to clearance of encroached RoW near settlements and total 241 AFs lost their assets and sources of livelihood. Update payment progress reflects that 228 AFs have been paid their full compensation. 7. Out of remaining unpaid 13 AFs; structures of 2 AFs are excluded from inventory list; 2 AFs have incomplete documents (CNIC/ Bank Account issues); 4 AFs (i.e. one owner of abandoned industrial structure constructed in encroached RoW, one owner of POL logo, and two employees categories) declines to receive their compensation; 2 AFs under process and 3 AFs left the project area without their whereabouts known. 8. The review of the record and consultation with the AFs reflects that NHA did its best efforts to convince the unpaid APs to come-up and collect their compensation. The notices are also issued to the AFs for receiving compensation amount and vacation of RoW. As a last resort, the APs are also informed through local and national print media (i.e. the daily Kawish and the daily Jang Newspapers) to show-up and collect their entitled compensation form the project office. Conclusion 9. The above progress reflects that except for an abandoned industrial structure of one AF (local politician/land lord) 1 on encroached RoW, all the issues are resolved satisfactorily and the LARP implementation is almost completed. Now the outstanding payments of 11 APs (structure owner AP included) are beyond NHA s control, however NHA is still making its efforts to make disbursement of compensation to remaining payable AFs whenever they are ready to get compensation. Thus, now the withheld 6.5 Km LAR section is available for construction as free from all encumbrances (Annex A). Section In Section 4, out of the total 73 AFs, 72 AFs have been paid, while remaining 1 AF is unpaid due to lack of CNIC/ Underage. In Section 4, of the total length (14.9 km), 13.5 km of zero LAR impacts section had already been cleared in Second EMA report (March, 2012). In remaining 1.4 km with LAR impact stretches, full implementation of LARP was confirmed and validated vide Third EMA Report (September, 2013), and the RoW was cleared as free of all encumbrances for construction. Overall Implantation Status 11. The implementation of LARP in all four sections is completed with only few (18) unpaid AFs left out of total 696 AFs 2 (699 as per LARP) in all four sections. Out of these 18 unpaid AFs, two AFs are in structure owner category one each in section 1 and 3, 1 landowner category, 1 in business renter category and 14 fall in employee category. The NHA did its best efforts to ensure disbursement of compensation to all unpaid AFs, however, the payments could not be made being out of NHA s preview. Table A below 1 Squatters occupying public safety zones can be provided with housing, land, or income-earning opportunities elsewhere. Since the rationale is to protect vulnerable groups, the project would not compensate landlords building structures illegally in public safety zones. (Resettlement Handbook, Guideline to Good Practices, 1998).} 2 3 AFs (2 structures owners and 1 rentee in Section 3) are excluded from inventory list and making a total 696 AFs instead of 699 AFs as per RP. vii

10 provides summary of overall payment status in each section and payment progress to outstanding unpaid AFs since 3 rd EMA report (September, 2012). Table A: Summary Status of Sectional RPs Implementation in Sukkur Jacobabad (N-65) Road Section Total AFs Reasons of Non-payment Actions Taken Clearance Status Section 1 ( ) (17.5 km) Payment Status as of 3rd EMA Report Updated Payment Status as of 30 June, 2013 Paid Unpaid Paid Unpaid One AF filed court case for land compensation - 4 AFs left project corridor with their whereabouts unknown. Consultative process continued. Notices issued for early collection of compensation. Funds put in project account and AFs with their whereabouts unknown informed publically through a national (the daily Jang) and local (the daily Kawish) newspapers to come-up and receive compensation. RP of Section 1 has been sufficiently implemented and the RoW has already been cleared for construction work since approval of 2 nd EMA report (March, 2012). Section 2 (excluding Bypass) ( km) Section 2 (Shikarpur Bypass) RD: (4.950 km) 7 7/ One unpaid AF contesting in the Court for enhancement of compensation. Sub-total Section 3 ( km) ( km) (11+2) - 2 excluded from inventory list by reduced construction limits. - 4 declines to receive compensation - 2, incomplete documents (CNIC/Bank Account), - 2 under process for payment, and - 3 have left project corridor with their whereabouts unknown. - RP of Section 2 has been implemented and the RoW has Close liaison with local revenue authorities and AF. Land compensation deposited in Treasury and the payment will be made as per court decision. NHA maintained a close liaison with AFs to convince the unpaid APs to come up and collect their compensation. The notices are also issued to the unpaid APs for receiving compensation amount and vacation of RoW. APs are also informed through local and national print media (local daily Kawish and the Jang News Papers dated and ) to collect compensation. already been cleared since 3rd EMA Report (September, 2012). RP is sufficiently implemented in Section 3 and 6.5 Km withheld LAR section is available for construction free of all encumbrances. The detail of LAR sections is given in Annex-A. viii

11 Section 4 ( ) Lack of CNIC/underage Maintained a close liaison with AF NHA to facilitate to this unpaid AF to complete their documents and NHA has planned to make payment to this AF through an Affidavit. RP is fully implemented and entire road length in this section cleared for construction work since third EMA report (September, 2012). 11. It is worth noting that on the whole, over 97% AFs have been paid their compensation and other resettlement entitlements as per approved sectional resettlement plans. Most of the affected business structures 3 have been re-constructed/ re-established outside RoW by the affected structure owners and have been rented out to the AFs from business renter category. Similarly, the affected residences of twelve affected households (squatters) 4 in Bypass Section 2, have be reconstructed at about a distance of 500 m from affected site on the other side of the existing Sukkur-Jacobabad road on the pieces of land purchased 5 by the AFs in their names. The replaced structures are constructed with better construction material and in general, it can be safely concluded that the APs seem better-off in their business and employment as well as re-establishment of their residential structures as compared to their pre-project conditions. In addition, the compensation for loss of community structures (mosques, schools) was paid to the Mosques committees for relocation of these structures out of the construction limit at their own. The respective mosque committees have either reconstructed the mosques at nearby places in consultation with the local community or the construction of replacement community structure is at an advance stage. 12. Although the achieved Implementation progress is above 97% with only such leftover AFs/ APs, who either had filed court cases or not shown up to collect their compensation due to their own reasons. However for remaining 17 AFs, it is suggested that the NHA project team should keep their efforts continued to facilitate these AFs to collect their compensation as and when they become available and submit their claims. Thus, keeping in view the disbursement of payment to the leftover APs, the following section-wise action plan is proposed: 3 Of the total business structures (204), only 3 left unpaid, i.e.1 Court case, 2 AFs (1 local politician and 1 businessman Karachi based) declined to receive their payment. 4 The affected residential structures were constructed on the land acquired for By Pass. The land was not in the name of the structure owners, they were verbally permitted by the land owner to construct their structures and work as farm labour on his land. With land acquisition for the bypass, the APs were left land less and were compensated for their structures only with additional assistance (equivalent to three months earning based on OPL) to facilitate them to relocate at their own in nearby area. 5 A copy of an affidavit of AFs who have purchased land is provided at Annex F as an evidence. ix

12 Proposed Action Plan 13. Keeping in view the disbursement of payment to the leftover APs, the following section-wise action plan is proposed: Proposed Action Plan Section Total AFs Unpaid AFs Proposed Actions Timeline Respons ibility Section NHA to pursue court s for early decision and compensate 1 AF in accordance with the court direction. In case of not located AF, NHA to keep close liaison with community to know the whereabouts of 4 AFs.. 31 October, 2013 Project Director (N-65) Section NHA should keep persuading the court for early decisions and compensate to 1 AF as per court decision. Section NHA to help in completion of documents and make payments to all payable AFs The AFs unwilling to receive Payment should be engaged to convince them receive payment. In case of not located AFs, NHA keep close liaison with community to know the whereabouts of 3 AFs. Section NHA to help in completion of documents and make payments to 1 AF. 31 October, October, September, 2013 Project Director (N-65) Project Director (N-65) Project Director (N-65) x

13 Sr. No. Annex A RP Implemented Subsections at Section 3 (RoW free of all encumbrances) Details of withheld sections measuring 6.5 KM at Section 3 (refer 2 nd EMA Report submitted in March 2012). RD-wise Detail of 6.5 KM LAR Area in Section 3 where LARP is Fully Implemented Length in km Total 6.5 km xi

14 1. INTRODUCTION 1.1 Background 1. This is the final external monitoring report prepared on the basis of field visit carried out from June, Based on this survey, the results of 3 rd External Monitoring report (September, 2012) was updated as of 15 th June, The report reflects the implementation of RPs of all four Sections (I IV) of Sukkur Jacobabad road (N-65). 2. The Sukkur-Jacobabad road is one of the subprojects 6 of this tranche 2 (ADB Loan 2540). The Resettlement Plan (RP) for Sukkur Jacobabad was approved by ADB in May However, its implementation was delayed due to various reasons including discrepancies in the inventory of losses and number of affected persons. Later-on it was agreed that i) 4 Sectional Resettlement Plans will be prepared, approved and implemented to facilitate commencement of civil works. ii) For each section, prior approval of ADB Safeguard Unit will be required to commence civil works upon full implementation of Resettlement Plan verified through External Monitoring Agency (EMA). 3. In this context, NHA divided the project corridor in four sections and accordingly updated the RP in following different sections: Section-1: RD to RD km (Zero to end of Lakki Town). Section-2: RD to km (End of Lakki Town to end of Shikarpur Bypass). Section-3: RD to km (End of Shikarpur Bypass to end of Humayun Town). Section-4: RD to km (End of Humayun town to start of Jacobabad). 4. The proposed project road falls under the administrative jurisdiction of three Districts of Sindh province, i.e. Sukkur, Shikarpur and Jacobabad. The location map and layout plan of the project is given in Figure 1.1 and 1.2 respectively. 5. After review the ADB approved sectional RPs by close of year 2011 and NHA started the implementation of Sectional RPs in the field as per implementation schedule for each sectional RP. To confirm and validate the implementation status of the Sectional RPs, the external monitoring has been conducted in compliance to ADB safeguard requirements. The section-wise implementation status of the approved RPs is discussed in subsequent sections. The Sukkur-Jacobabad road (N-65) is one of the subprojects of under Tranche 2. 6 This tranche includes, i) Sukkur Jacobabad road (Sindh), and ii) Qilla Saifullah Zhob road (Balochistan).. The scope of sub project includes rehabilitation & up-grading the capacity of existing road section to 4- lane dual carriageway. The proposed project road falls under the administrative jurisdiction of Sukkur, Jacobabad and Shikarpur Districts of Sindh Province. 1

15 Figure 1.1: Location Map of Sukkur Jacobabad Road Project Project Road Figure 1.2: Layout Plan of Sukkur Jacobabad Road Project (N-65) 1.2 Objectives of the External Monitoring 6. The monitoring is an integral part during the implementation of resettlement plan and facilitates to assess the implementation progress and decision making. Specifically, confirmation of full implementation of RPs through an independent external monitor before commencement of civil works is pre-requisite under ADB safeguards requirements. Keeping this in view the implementation progress of the approved sectional RPs is monitored to determine the updated progress on implementation status and validate the sections free of encumbrances to facilitate in decision making to allow the commencement of civil works. Furthermore, suggest remedial measures and corrective action plan regarding the payment to leftover APs to achieve full implementation of resettlement initiatives. 2

16 2. METHODOLOGY 2.1 General 7. The approach and methodology part of the study covered the activities done for information gathering, data collection and analysis as well as consultation with stakeholders including APs to determine implementation status of Land Acquisition and Resettlement Plan. The major activities carried out to accomplish the report are: i) data collection both primary and secondary; ii) interviews of APs; iii) consultations with APs and other local people; iv) consultative meeting with the project management, consultants and contractor; v) field survey including interviews, physical observations/ verifications and data inputting and analysis. 2.2 Review of the Project Documents 8. The project documents, including resettlement framework, resettlement plan of Section 1, 2, 3 and 4; internal monitoring reports, status of LAR implementation, Aide Memoires and other were reviewed and relevant data was compiled to establish the monitoring objectives and validated through conducting field surveys. 2.3 Consultative Meetings 9. The consultative meetings were carried out with APs and other local people/ local community/ representatives. In addition, the consultative meetings were also held with the Project Director, Consultant staff and Contractor staff. In these meetings, AP s concerns/ feedback about implementation of resettlement plan as well as actions taken by NHA regarding the payment of unpaid APs were discussed and accordingly presented in this report. 2.4 Data Collection and Analysis 10. Both primary and secondary data was collected about the efforts made by NHA to approach the unpaid APs for resolving their concerns and disburse compensation as well as notices issued to APs and published in the Newspapers for ensuring full implementation of LARP. The primary data includes interviews with APs, and group consultations, consultative meetings with the project management and physical observations/ verifications. The field survey was carried out from June, 2013 covered the status of payment of compensation as of 15 th June, However, some supplementary data/ supporting documents including copies of internal monitoring reports, meeting minutes and notices issued/published were collected from the office of NHA Sukkur after field survey to review and compile the report. A close liaison was maintained with NHA Project team till compilation of the draft report and thus implementation status as of 30 th June, 2013 was included in this final report. 3

17 3. IMPLEMENTATION STATUS OF SECTION LARPs (I IV) 3.1 Implementation Status of RP of Section The LARP Section-1 ( km) does not involve land acquisition, as an adequate RoW (110 ft. wide) was available with NHA. However, the RoW of existing road was encroached by the locals at various settlements located along the road. To implement project civil works clearance of encroached RoW warranted preparation of LARP with varying degree of impacts to identified APs. Below is detail of impacts with LARP implementation status Projects Impacts 12. The following are the project major impacts on this road section: Dismantling of 228 commercial structures; 300 AFs, i.e. 81 structure owners, 145 business renters and 74 employees 7 community structures including 5 small mosques and 2 schools (walls) Relocation of public structures (check posts) and utilities Status of Payment at Section Of the total 300 AFs, 295 AFs have been fully paid, while 5 AFs are unpaid so far due to one AF has filed a court case, followed by 4 those shifted elsewhere without their whereabouts known. 14. In this context, the actions taken are as below: The NHA has been following up with the court for early decision; however, NHA confirms that the AF will be compensated according to court decision. Regarding those shifted elsewhere, NHA has made all good faith efforts and frequent visits to the project sites to find out such AFs are conducted time and again, but so far could not find the remaining 4 AFs. NHA has put the entitled compensation of these AFs in a project account to ensure delivery of compensation to these APs as and when they appear and accordingly the APs have been informed publically through a public notice published in a national (the daily Jang) and local (the daily Kawish) newspapers on 31 August, Vide public notice published in the Newspapers, the AFs are advised to come and receive the compensation form office of the Project Director N-65, Sukkur. A copy of the advertisement is also presented. 4

18 15. The updated implementation progress in Section one reflect that 98.3% AFs have been paid their full compensation. NHA did its best efforts to disburse compensation to leftover 1.7% (5 Nos.) AFs including publishing in news papers, the names of unpaid AFs with their whereabouts unknown to locate them. The review of record reflects that the payment to left over AFs is beyond NHA s preview. Thus, it can be concluded that the RP of Section 1 is fully implemented and RoW is clear for construction activities based on findings of 2 nd External Monitoring Report (March 2012). 16. The status of implementation of RP for Section 1 is summarized in the Table 3.1, while details of Unpaid AFs are given in Annex 1. Table 3.1: Status of Implementation of RP of Section-1 Sr. No. Category of Impact 1 Loss of Structures Total APs Paid/ Unpaid Reasons of Non- Payment Actions Taken 81 80/ 1 1 Court case The NHA is following up the court case for its early adjudication and confirmed that the court s decision will be implemented in letter and spirit. Status of RoW Clearance RoW is clear. Conclu sions RP is fully implem ented. 2 Business Renters 3 Employment Loss / 1 1 Shifted in elsewhere 74 71/ 3 3 AFs shifted elsewhere.. For the APs who left project corridor with unknown whereabouts, NHA has placed their entitled compensation in the project account and publically informed (through the daily Kawish and the daily Jang newspapers) the APs to come up and collect their compensation. NHA has put the entitled compensation of these AFs in a project account to ensure delivery of compensation to these APs as and when they appear and accordingly the APs have been informed publically through a public notice published in a national (the daily Jang) and local (the daily Kawish) newspapers on 31 August, Total / Community The compensation for loss of structures (5 community structures (five small mosques and two schools) was mosques and paid to the Mosques 2 schools) Committees for relocation of these structures out of the construction limit at their own. On the reconstruction/ relocation of these structures (mosques & schools), NHA will verify and submit IMR to ADB by 31 Oct

19 5 Public structures/ Utilities (Utilities, Police Check Posts) In accordance with the agreement with NHA, relocation of structures and utilities being done by concerned Departments/ agencies, (including Police/ Rangers, WAPDA, PTCL). On the completion of relocation/ reconstruction, NHA will verify/ confirm and submit an Internal Monitoring report to ADB by 30 September, Implementation Status of LARP of Section The Section 2 ( ) involves land acquisition for the construction of Shikarpur Bypass, where private agricultural land to be acquired. Furthermore, RoW of carriageway has been encroached by the locals at various settlements located along the proposed road Project Impacts 18. In this section, there are total 85 AFs, out of which, 78 AFs are affected due to the construction of Shikarpur Bypass and 7 affected by carriageway. The following are the project major impacts relating to the improvement of existing carriageway and construction of Shikarpur bypass: i) Carriageway: comprises a total of 15.7 km from RD to and to commercial structures - 7 AFs (3 owners of commercial structures, 3 business renters and 1 employee) - 4 small mosques - 4 public structures (check posts) subject to be relocated from RoW ii) Shikarpur Bypass (RD to ) Acquisition of acres owned by 56 land owners Affected crops on acres (grown by 56 land owners and 10 sharecroppers); 423 trees (109 fruit and 314 wood/ timber trees) to be cut-down owned by 13 APs who are also the owners of land 43 affected structures owned by 12 AFs Total 78 AFs (i.e. 56 land owners, 10 sharecroppers and 12 owners of structures) Status of Payment i) Carriageway: comprises a total of 15.7 km from RD to and to (excluding bypass) Along the existing carriageway all 7 AFs have been paid.thus, the RP is sufficiently implemented in carriageway portion (15.7 km), which has already been cleared in 2 nd EMA report (March, 2012). 6

20 ii) Shikarpur Bypass (RD to ) There are total 78 AFs at Shikarpur bypass. Updated progress reflects that the payment has been made to 77 AFs, while remaining 1 AFs is still unpaid because he has filed a reference in the court against award for enhancement of compensation. 19. To ensure timely implementation of LARP the NHA maintained a close liaison between the AFs and local revenue authorities to resolve the petty issues of few AFs. Consequent upon NHA s efforts DDO (Revenue), Shikarpur has published an advertisement in national (the daily Jang) and local (the daily Kawish) newspapers on 31 August, 2012 and advising the AFs to come and receive their compensation. A copy of the advertisement is presented in this section. Resultantly all AFs, except one who has filed reference in the court are paid their full compensation. 20. In case of AF who filed reference in court, NHA has been pursuing with the Local Revenue Authorities and the court for early decision on the subject matter. The land cost has already been deposited in the District Treasury by NHA which is at the disposal of DDO (Revenue) that payment will be made as court decides. However, NHA is committed to abide by the court s decision and implement it as per its essence. 21. The updated implementation progress reflects that all outstanding issues are resolved and the Sectional LARP implementation is achieved upto 99%. The left over payment to one AF contesting in court is beyond NHA s preview. Thus, it is concluded that the LARP for Section 2 is implemented satisfactorily. Based on achieved implementation and findings of 3 rd EMA report (September, 2012) the Bypass section was cleared for construction works. 22. The status of implementation of RP of Section 2 is summarized in Table 3.2, while details of Unpaid AFs are given in Annex 2. 7

21 Table 3.2: Status of Implementation of RP of Section 2 Sr. No. Category of Impact i) Carriageway a) Owners of commercial structures, renters & employee ii) Shikarpur Bypass a) Land compensation, crops, trees, structures Total AFs Paid/ Unpaid Reasons for Non-Payment Actions Taken 7 7/ / 1 1 unpaid AP in land owner category (Bypass section), who has filed reference in the court for enhancement of compensation. NHA deposited land compensation in treasury and payment will be made as per court decision. NHA maintained a close liaison between the land owner AFs and the local revenue authorities to ensure the as court decides. DDO has also publically informed the AFs in national (the daily Jang) and local (the daily Kawish) newspaper to get their payment. RoW Clearance Status RoW is Clear for construction works. Conclusions LARP is sufficiently implemented b) Community structures 4 mosques (1 excluded from RoW and 3 remaining). c) Public utilities (waiting room owned by NHA, electric / telephone poles) Payment made to the all three Mosque committees and structures are dismantled and RoW is clear. On the re-construction of these structures by the community, NHA will verify and submit a report to ADB by 30 September, As per agreement with NHA, relocation of utilities being done by WAPDA and PTCL. On the relocation of utilities, NHA will verify/ confirm and submit an Internal Monitoring Report to ADB by 31 Oct

22 3.3 Implementation Status of RP of Section The Section 3 ( to km) does not involve land acquisition as an adequate RoW (i.e.110 ft wide) is available with NHA. However, RoW of existing road at this section has been encroached by the locals at various settlements located along the proposed road Projects Impacts 24. The following are the project major impacts on this road section: affected commercial structures - Total 238 AFs (88, 59 and 91 were owners of business structures, business renters and employees respectively) community structures (i.e. 17 small road side mosques, 7 boundary walls of mosques, 2 wash room and 2 hand pumps) public structures (including police check posts, boundary walls, rooms) Status of Payment at Section In the LARP Section 3 the resettlement impacts are mainly due to clearance of encroached RoW near settlements and total 241 AFs lost their assets and sources of livelihood. Update payment progress reflect that 228 AFs have been paid their full compensation. 26. Out of remaining unpaid 13 AFs; structures of 2 AFs are excluded from inventory list; 2 AFs have incomplete documents (CNIC/Bank Account issues); 2 AFs claims are under process; 4 AFs (One owner of abandoned industrial structure constructed in encroached RoW, one owner of POL logo and 2 employees categories} declines to receive their compensation; and 3 AFs left the project area without their whereabouts known. 27. The review of the record and consultation with the APs reflects that NHA did its best efforts to convince the unpaid APs to come-up and collect their compensation. The notices are also issued to the APs for receiving compensation amount and vacation of RoW. As a last resort the APs are also informed through local and national print media (local the Kawish and the Jang Newspapers) dated and 29 June 2013 to show-up and collect their entitled compensation form the project. A copy of the same is also attached. 9

23 28. The above progress reflects that except for an abandoned industrial structure of one AF (local politician/land lord) 7 on encroached RoW at RD and one owner of POL logo (encroached RoW), all the issues are resolved satisfactorily and the LARP implementation is almost completed. Now the outstanding payments of 10 APs (structure owner AP included) are beyond NHA s control, however NHA s efforts are continued to make disbursement of compensation to remaining payable AFs whenever they are ready to get compensation. Thus, now the withheld 6.5 Km LAR section is available for construction as free from all encumbrances (RD-wise 29 Jun details are in table below). A copy of letters is presented at Annex B, C, D and E. The details of Unpaid AFs are given in Annex 3. Sr. No. RD-wise Detail of 6.5 KM LAR Area where LARP is Fully Implemented Length in km Total 6.5 km 7 Squatters occupying public safety zones can be provided with housing, land, or income-earning opportunities elsewhere. Since the rationale is to protect vulnerable groups, the project would not compensate landlords building structures illegally in public safety zones (Resettlement Handbook, Guideline to Good Practices, 1998). 10

24 Table 3.3: Status of Implementation of RP of Section 3 ( km = 20.2 km) Sr. No. Category of Impact Total APs 1 Loss of Structures Paid/ Unpaid Reasons of Non- Payment 89 86/ 3 2 excluded from inventory by reducing construction limits. Actions Taken In consultation with the APs, construction limit reduced by redesigning median into new jersey type to avoid the impact on two industrial structures located at the edge of construction limit. Status of RoW Clearance RoW is clear for the whole Section 3. Conclusions LARP is implemented, RoW is free. 1, AF who is Karachi based local politician and is not interested to receive entitled compensation. NHA did consultations with AP s representative to make payments (See minutes of meeting vide NHA office letter No. GM Const.AP/ NHA/2013/ 1114A dated 22 Jan., 2013 at Annex B). 1 AF who is the owner of POL at encroached RoW is based at Karachi. NHA issued notices to this AP to come up and receive his compensation and vacate the RoW vide NHA office letters Nos. GM Const. AP/ NHA/2013/ 1124 dated 31 Jan., 2913 and GM Const. AP/ NHA/2013/ 1190 dated 14 June 2013 and at Annex C & D). 2 Business Renters As last resort, NHA has publically informed to this AP by publishing a notice in a national (the daily Jang) and local (the daily Kawish) newspapers on dated that contact NHA project staff in order to receive his compensation whenever AP desires / Employme nt Loss 91 82/ 10 2 AF under process 2 incomplete documents, including CNICs, and opening of bank accounts. 2 AFs are decline to receive payment 3 AFs shifted elsewhere. 11 NHA has publically informed to APs to receive their payments. NHA to facilitate APs in completion of requisite documents and receipt of compensation by 31 Oct., NHA maintained close liaison with APs. Delivered notices to AFs to submit their claims and collect their compensation accordingly, As a last resort NHA has published in a national (the

25 daily Jang) and local (the daily Kawish) newspaper dated 29 June 2013 to get their payment as and when appeared community mosques. Out of which, 5 mosques & 1 Imam Bargha) are excluded from RoW and 18 mosques left. 5 Public structures / Utilities - Police Check Posts) Total / Payment made to all 18 mosque committees. All structures dismantled and RoW is clear. NHA will submit an IMR on the re-construction by 31 Oct Re-relocation of utilities being made by the done by concerned Departments/ agencies. On the relocation of public utilities, NHA will confirm and submit an IMR to ADB by 31 Oct Implementation Status of RP of Section The Section 4 ( to km) does not involve land acquisition as an adequate RoW (i.e.110 ft wide) is available with NHA. However, RoW of existing road at this section has been encroached by the locals at various settlements located along the proposed road Projects Impacts 30. The Section 4 ( to km) does not involve land acquisition as an adequate RoW (i.e.110 ft wide) is available with NHA. However, RoW of existing road at this section has been encroached by the locals at various settlements located along the proposed road. The following are the project major impacts on this road section: - 66 affected commercial structures (shops, hotels, thatched-sheds, wooden cabin) affected families, including 28, 28 and 17 were owners of business structures, business renters and employees respectively. - 4 small road side mosques need to be relocated. - 3 public structures, i.e. police check posts 12

26 3.4.2 Status of Payments at Section Out of total 73 AFs, 72 AFs have been paid, while remaining 1 is unpaid due lack CNIC/underage and affidavit will be required in order to make payment to this AP.. In this context, the actions taken are as below: AF submitted his case to NHA after completing requisite documents. The payment of this case is under process with NHA and to be made by 30 September, The implementation progress reflects that the Sectional LARP is implemented satisfactorily. Hence it was concluded that in Section 4, the RoW of total length is available free of all encumbrances for carrying on construction activities. Consequent upon findings of previous External Monitoring Report (3 rd EMA report) this Section has already been cleared and construction works are ongoing smoothly. 33. The updated status of implementation of LARP of Section 4 is summarized in Table 3.5. The detail of Unpaid AF is given in Annex 4. Table 3.5: Status of Implementation of LARP of Section 4 ( = 14.9 km) Sr. No. Category of Impact Total APs Paid/ Unpaid 1 Loss of Structures 2 Business Renters 3 Employment Loss Reasons of Non- Payment Actions Taken 28 28/ / / 1 1 under process for payment NHA will make compensation to this AF (Underage) through an Affidavit by 30 September, Total 73 72/ community Payment made small to all five mosques. mosques and RoW is clear On the construction of these mosques, NHA will verify and submit IMR to ADB by 31 Oct Status of RoW Clearance RoW has already been cleared in 3 rd EMA report and the construction works are ongoing smoothly. Conclusion RP is fully implemented 13

27 5 Public structure / Utilities (Police check posts) These structures are being relocated and NHA will confirm and submit an IMR to ADB by 31 Oct

28 4. CONSULTATIVE MEETINGS 4.1 Consultative Meetings 34. The consultative meetings were held with the concerned officials associated with this project to get the todate status of progress, reasons for unpaid cases and other constraints associated with this project. The major points of feedback/ constraints regarding the disbursement of payment are as under: Out of total, 699 AFs, the number of un-paid AFs are only 18 in all 4 sections. Out of these 18 unpaid AFs, two AFs are in structure owner category one each in section 1 and 3, 1 landowner category, 1 in business renter category and 14 fall in employee categorythe reasons of unpaid cases are: 2 excluded from the inventory list, 2 having filed court cases, 4 not showing up to collect compensation (declined to receive compensation), 3 under process; 3 have incomplete documents and 7 shifted elsewhere with their whereabouts unknown In order to ensure the payment to leftover APs, NHA has taken the steps as: APs informed that funds are in the project account and payment will be made at Court decision in case of few APs, who have the court cases. NHA convened meetings of APCLC, to coordinate/consult AFs to resolve their issues at local level and facilitate them to process their compensation claims. NHA has publically informed to APs to receive their payments as it is available in the project account and notices have also been delivered to the APs. NHA did efforts through all means to locate the APs and finally, names of AP have been published in a National (the daily Jang) and local (the daily Kawish) newspaper to receive their payments. 36. The list of officials/ persons met is as below: 1. Mr. Tariq Mahmood, Project Director, Sukkur - Jacobabad Road (N-65) 2. Mr. Sohail Ahmad, AD (Engg.), Sukkur - Jacobabad Road (N-65) 3. Mr. Muhammad Arshad, AD (Land.), Sukkur - Jacobabad Road (N-65) 4. Mr. Pervaiz Akhtar, Resettlement Specialist (Consultant), Sukkur - Jacobabad Road (N-65) 5. Mr. Shaukat Zaman (Environmentalist Contractor staff) and Mr. Ghulam Mustafa (Contractor staff), Sukkur Jacobabad road 6. Other allied staff 4.2 Consultative Meetings with APs/ Locals 37. The consultation meetings were carried out with the APs and other local people during the visit survey. The following are the major feedback of the APs/ and local population: i). In general, the APs, local population, local representatives, even other stakeholders were found pleased with the construction of this valuable road project. 15

29 ii). Most of the APs who were temporarily displaced due to the clearance of the RoW have re-established their business; as well as residences especially in case of bypass Section II. iii). Most of the community mosques were re-constructed/ relocated at adjoining/ nearby places in consultation with the local community, while the construction works on remaining few were in progress at an advance stage. iv). The payment of compensation to almost all payable APs has been made. The left over payments are only those where APs are contesting in court, least interested to receive compensation, left the project corridor with their whereabouts unknown for which NHA s efforts are still continued. 38. In general the community showed its satisfaction with the LARP provisions and mechanism for payment of compensation different categories of AFs including Title holders, Structure owners, business renters and employees. However, during consultative meetings the community raised road side safety concerns during operation of two lane dual carriage way and proposed that the NHA should install adequate signboard reflecting reduced speed limits in and near the settlements to ensure safety of lives of the community at large and their belongings. Table 4.1: List of APs/ Local People Consulted Sr. No. Date Location/ Venue Sultan Kot Lodhra Jano Abad, Sukkur Names of Major Participants - Mr. Zaib Ali Patahn - Mr. Zahim Bux - Mr.Zahid Khan - Mr. Pilo khan Dayo - Mr. Subo s/o Hamzo - Mr. Maghan Zafari - Mr. Shamen Zafari - Mr. Lela RamM. Ghulam Siddiqui (Electrician) - Mr. Khadim Hussain s/o Punjal (Hotel operator) - Mr. Ghulam Akbar s/o Ghulam Qadir (Tailor shop) - Mr. Bachal s/o Dinal Shah (Labour) - Mr. Ghulam Abbas s/o Noor M. Bhutto (Land owner) - Mr. Wazar Khan s/o Jan M. (Land owner) - Mr. Munir Ahmad Bhutto (Land owner) - Mr. Habibullah (Local) - Mr. Talib Shah - Mr. Khadim Hussain - Mr. Ajjad Ali - Mr. Akhtar Ali - Agha Bux 16

30 5. PROJECT SUCCESS 39. It is worth noting that on the whole, about 97% APs have been paid their compensation and other resettlement entitlements as per approved sectional resettlement plans. Most of the affected business structures 8 have been reconstructed/ re-established outside ROW by the affected Structure owners and have been rented out to the AFs from business renter category. Similarly the affected residences of twelve affected households (squatters) 9 in By pass Section-2, have be reconstructed at about a distance of 500 m from affected site on the other side of the existing Sukkur-Jacobabad Road on the pieces of land purchased by the AFs in their names. The replaced structures are constructed with better construction material and in general, it can be safely concluded that the APs seem better-off in their business and employment as well as re-establishment of their residential structures as compared to their pre-project conditions. In addition, the community structures (mosques, schools) have also been reconstructed at nearby places in consultation with the local community, while the other are at advance stage of construction. Photograph-1: A view of some of the recently constructed business structures by the APs at Lodhra (RD ). Photograph-1: Recently constructed residential structures by the APs at Jafari village at Section 2 (RD ). Photograph-1: A view of road of Section 1, where Asphalt is being laid. Photograph-1: A boundary wall shifted little behind by the AP at Lodhra (RD ). 8 Of the total business structures (204), only 3 left unpaid, i.e.1 Court case, 2 AFs (1 local politician and 1 businessman Karachi based) declined to receive their payment. 9 The affected residential structures were constructed on the land acquired for By Pass. The land was not in the name of the structure owners, they were verbally permitted by the land owner to construct their structures and work as farm labour on his land. With land acquisition for the bypass, the APs were left land less and were compensated for their structures only with additional assistance (equivalent to three months earning based on OPL) to facilitate them to relocate at their own in nearby area. 17

31 4.4 Institutional Arrangements 40. Regarding institutional arrangements, the following are the major observations: A Project Management Unit (PMU) has already been established at NHA Complex Sukkur headed by a Project Director under the overall supervision of GM (construction), placed at Karachi. The associate staff includes Assistant Directors (Engg. & Land), Consultants, Contractors, EMA and other core staff. As per resettlement plans, the institutional arrangements for the implementation of RPs are in place including LAR Unit, GRC and ACLC and other committees (mosque committees). Accordingly, the meetings of LAR unit, GRC have also taken place periodically as well as on need basis. The ACLC has formed further community committees including mosques committees at field level to facilitate the process of disbursement of compensation, relocation/ reconstruction mosques as well as relocation of public utilities and other. To meet the implementation requirement of all four sections of the proposed road project, two Project Directors have already been deployed. One project Director is responsible for Section 1 and 2, while the second for Section 3 and 4. 18

32 ANNEXES 19

33 Annex B Annex C 20

34 Annex D Annex E 21

35 Annex F 22

PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project

PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project Internal Monitoring Report September 2016 PAK: National Motorway M-4 Gojra Shorkot Khanewal Section Project Prepared by National Highway Authority of Ministry of Communications for the Islamic Republic

More information

Land Acquisition and Resettlement

Land Acquisition and Resettlement Land Acquisition and Resettlement Internal Monitoring Report (E-35, Hassanabdal Havelian Expressway-Phase I, Package -I) May 2015, PAK: National Trade Corridor Highway Investment Program (NTCHIP) Tranche

More information

PAK: National Motorway M-4 Gojra Shorkot Project

PAK: National Motorway M-4 Gojra Shorkot Project External Monitoring Report Project Number: 48402-001 (Jul - Dec 2016) PAK: National Motorway M-4 Gojra Shorkot Project Prepared by Abdul Hameed, External Monitoring Agent (EMA), National Highway Authority,

More information

Safeguards Monitoring Report

Safeguards Monitoring Report Safeguards Monitoring Report Semiannual Report Covering July-Dec 2016 period February 2017 (ESDIP) Tranche-2 Chimtala- Arghandi 220 kv DC Transmission Line Subproject (DABS - 006/ICB) Prepared by Da Afghanistan

More information

Land Acquisition & Resettlement Plan Corrective Action Plan. PAK: Second Power Transmission Enhancement Investment Program, Tranche 1

Land Acquisition & Resettlement Plan Corrective Action Plan. PAK: Second Power Transmission Enhancement Investment Program, Tranche 1 Land Acquisition & Resettlement Plan Corrective Action Plan April 2018 PAK: Second Power Transmission Enhancement Investment Program, Tranche 1 Safeguard Due Diligence and Corrective Action Plan (CAP)

More information

PAK: Power Distribution Enhancement Investment Program, Tranche 2

PAK: Power Distribution Enhancement Investment Program, Tranche 2 Social Monitoring Report Bi-annual Social Monitoring Report July 2012 PAK: Power Distribution Enhancement Investment Program, Tranche 2 Prepared by Quetta Electric Supply Company (QESCO), Balochistan for

More information

Land Acquisition and Resettlement Plan Compliance Report. ARM: Sustainable Urban Development Investment Program Tranche 2

Land Acquisition and Resettlement Plan Compliance Report. ARM: Sustainable Urban Development Investment Program Tranche 2 Land Acquisition and Resettlement Plan Compliance Report May 2018 ARM: Sustainable Urban Development Investment Program Tranche 2 LARP Area (Babajanyan - Tichina Highway) Prepared by the AM Partners Consulting

More information

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2)

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Social Monitoring Report Bi-annual Social Monitoring Report July 2014 PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Prepared by Lahore Electric Supply Company, Punjab for the Asian

More information

Asian Development Bank Accountability Mechanism Compliance Review Panel

Asian Development Bank Accountability Mechanism Compliance Review Panel Asian Development Bank Accountability Mechanism Compliance Review Panel Terms of Reference for Monitoring under the Chashma Right Bank Irrigation Project (Stage III) Inspection Request I. Introduction

More information

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum)

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Resettlement Plan December 2014 GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Prepared by the Municipal

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Resettlement Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP June 2012 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Ghupa-Sanghu

More information

PAK: Sindh Provincial Road Improvement Project

PAK: Sindh Provincial Road Improvement Project Sindh Provincial Road Improvement Project (RRP PAK 46377) Resettlement Plan Land Acquisition and Resettlement Plan Draft Project Number: 46377 April 2015 PAK: Sindh Provincial Road Improvement Project

More information

AFG: Transport Network Development Investment Program, Tranche 1 (Bagramy Sapary Road Project)

AFG: Transport Network Development Investment Program, Tranche 1 (Bagramy Sapary Road Project) Transport Network Development Investment Program Resettlement Planning Document Land Acquisition & Resettlement Plan Document Status: Final December 2014 AFG: Transport Network Development Investment Program,

More information

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 4)

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 4) Social Monitoring Report Bi-annual Social Monitoring Report November 2015 PAK: MFF Power Distribution Enhancement Investment Program (Tranche 4) Prepared by Lahore Electric Supply Company, Punjab for the

More information

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli)

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli) ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN Subproject: SH-70 (Gaya to Rajauli) BIHAR STATE HIGHWAYS PROJECT ROAD CONSTRUCTION DEPARTMENT (RCD) GOVERNMENT OF BIHAR FEBRUARY 2008 TABLE OF CONTENTS ITEM Page

More information

VIE: Power Transmission Investment Program Tranche 3

VIE: Power Transmission Investment Program Tranche 3 Social Monitoring Report 2 nd Quarterly Report June 2017 VIE: Power Transmission Investment Program Tranche 3 Installation of a second transformer bank for 220 kv Duc Hoa substation Installation of a second

More information

Resettlement Planning Document. IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj)

Resettlement Planning Document. IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj) Resettlement Planning Document Resettlement Plan Document Stage: Updated Project Number: 41127 August 2008 IND: Bihar State Highways Project Subproject: SH-74 (Hajipur Areraj) Prepared by Road Construction

More information

Pakistan: National Highway Development Sector Investment Program Tranche 2

Pakistan: National Highway Development Sector Investment Program Tranche 2 Validation Report December 2017 Pakistan: National Highway Development Sector Investment Program Tranche 2 Reference Number: PVR-521 MFF Number: 0002 Project Number: 37559-023, 37559-033, and 37559-043

More information

Semi-Annual Social Safeguards Monitoring Report. SRI: Greater Colombo Wastewater Management Project

Semi-Annual Social Safeguards Monitoring Report. SRI: Greater Colombo Wastewater Management Project Semi-Annual Social Safeguards Monitoring Report Project No. 36173-013 Period Covering July to December 2013 April 2014 SRI: Greater Colombo Wastewater Management Project Prepared by the Ministry of Local

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project PD 00001-PAK June 6, 2016 PROJECT DOCUMENT Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project This document has a restricted distribution and may be used by recipients

More information

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project Environmental Safeguard Monitoring Report Semi Annual Report July 2016 ADB Project Number: 48141-001 ADB Loan Number: 3210 FIJ: Transport Infrastructure Investment Sector Project Prepared by Fiji Roads

More information

Multitranche Financing Facility Annual Report 2017

Multitranche Financing Facility Annual Report 2017 May 2018 Multitranche Financing Facility Annual Report 2017 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. ABBREVIATIONS ADB Asian Development

More information

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project Final Resettlement Monitoring Report Document stage: Final Project number: Loan 2517 May, 2017 VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote s Sector Project Sub-project:

More information

AFG: Transport Network Development Investment Program Proposed Tranche 2 (Paktika Economic Corridor: Sar Hawzar Orgun/ Rabat Shkin Roads Subproject)

AFG: Transport Network Development Investment Program Proposed Tranche 2 (Paktika Economic Corridor: Sar Hawzar Orgun/ Rabat Shkin Roads Subproject) Resettlement Plan November 2012 AFG: Transport Network Development Investment Program Proposed Tranche 2 (Paktika Economic Corridor: Sar Hawzar Orgun/ Rabat Shkin Roads Subproject) Prepared by Ministry

More information

Bi-annual Social Safeguards Monitoring Report

Bi-annual Social Safeguards Monitoring Report Bi-annual Social Safeguards Monitoring Report Project Number: 2727 PK, Tranche II {Jan Jun, 2011} Islamic Republic of Pakistan Power Distribution Enhancement Investment Project (PDEIP) Tranche II Multi

More information

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening SFG1532 Public Disclosure Authorized AZERBAIJAN REPUBLIC Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY AZERBAIJAN MOTORWAY IMPROVEMENT

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) the Borrower has applied to ADB for a loan

More information

PROJECT AGREEMENT. (Renewable Energy Development Sector Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF PUNJAB

PROJECT AGREEMENT. (Renewable Energy Development Sector Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF PUNJAB LOAN NUMBER 2286/2287(SF)-PAK PROJECT AGREEMENT (Renewable Energy Development Sector Investment Program Project 1) between ASIAN DEVELOPMENT BANK and PROVINCE OF PUNJAB DATED 5 October 2007 PAL:PAK 34339

More information

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Resettlement Plan Document Stage: Draft Project Number: 41598 September 2013 India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Prepared by the Haryana

More information

LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES

LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES LAND ACQUISITION AND RESETTLEMENT COMPENSATION POLICY FRAMEWORK AND IMPLEMENTING GUIDELINES Supplementary Appendix to the Report Recommendation of the President to the Board of Directors on the HEALTH

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-10112,TF-15895,TF Jun ,100,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-10112,TF-15895,TF Jun ,100,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020397 Public Disclosure Authorized Project ID P125584 Project Name PK: KP Emergency Roads Recovery

More information

Bi-annual Environmental Monitoring Report. Power Distribution Enhancement Investment Project (PDEIP) Tranche II Multi Tranche Financing Facility (MFF)

Bi-annual Environmental Monitoring Report. Power Distribution Enhancement Investment Project (PDEIP) Tranche II Multi Tranche Financing Facility (MFF) Bi-annual Environmental Monitoring Report Project Number: 2727 PK, Tranche II {Jan Jun, 2012} Islamic Republic of Pakistan Power Distribution Enhancement Investment Project (PDEIP) Tranche II Multi Tranche

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents EXECUTIVE

More information

Resettlement Action Plan (RAP)

Resettlement Action Plan (RAP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Resettlement Action Plan (RAP) FATA EMERGENCY RURAL ROADS PROJECT (PHASE-2) Bajaur Agency

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program)

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) 1. A project preparatory technical assistance (PPTA) for $700,000 in grant funds is

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program

Multitranche Financing Facility Republic of Uzbekistan: Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program Facility Administration Manual Project Number: 42107 MFF Number: 0042-UZB Loan Numbers: 2635-UZB (Project 1), 2746-UZB (Project 2), and 2868-UZB (Project 3) 21 August 2013 Multitranche Financing Facility

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June 2017 IND: Green Energy Corridor and Grid Strengthening Project (320 kv VSC-HVDC power transmission lines between Pugalur, Tamil Nadu and North Trichur, Kerala) Annexures

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Social Monitoring Report Final Report December 2016 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Prepared by the Southern

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Prepared by Central Vietnam Power Projects

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Additional Financing of National Motorway M-4 Gojra Shorkot Khanewal Section Project (RRP PAK 48402) ECONOMIC AND FINANCIAL ANALYSIS A. General 1. Roads are the main mode of transport in Pakistan, accounting

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report Semi Annual Report January June 2016 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Vietnam Power

More information

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= COMPENSATION,

More information

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-69 (Dumaria - Ranitalab)

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-69 (Dumaria - Ranitalab) ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN Subproject: SH-69 (Dumaria - Ranitalab) BIHAR STATE HIGHWAYS PROJECT ROAD CONSTRUCTION DEPARTMENT (RCD) GOVERNMENT OF BIHAR FEBRUARY 2008 TABLE OF CONTENTS ITEM

More information

Loan Agreement DMIUMTS OFFICIAL LOAN NUMBER 8131-CN PEOPLE'S REPUBLIC OF CHINA INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Loan Agreement DMIUMTS OFFICIAL LOAN NUMBER 8131-CN PEOPLE'S REPUBLIC OF CHINA INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT OFFICIAL DMIUMTS LOAN NUMBER 8131-CN Loan Agreement (Zhanghu Railway Project) between PEOPLE'S REPUBLIC OF CHINA and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Dated 8,2012 LOAN AGREEMENT AGREEMENT

More information

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH LOAN NUMBER 2499-PAK (SF) PROJECT AGREEMENT (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK and PROVINCE OF SINDH NORTH SINDH URBAN SERVICES CORPORATION LIMITED DATED

More information

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT Himachal Pradesh Clean Energy Transmission Investment Program (RRP IND 43464) TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT A. INTRODUCTION 1. The

More information

Public Private Partnerships in Pakistan

Public Private Partnerships in Pakistan Public Private Partnerships in Pakistan By Mujtaba Shahneel, CFA Director General PPP Unit, Finance Department Government of Sindh Pakistan Disclaimer: The views expressed in this document are those of

More information

Semi-annual Social Safeguards Monitoring Report

Semi-annual Social Safeguards Monitoring Report Semi-annual Social Safeguards Monitoring Report (January to June 2015) Armenia: Sustainable Urban Development Investment Program Tranche 1 and Tranche 2 Project Number: 42417 Loan Number: L2752 (T1) Prepared:

More information

Civil Aviation Development Investment Program Tranche 3

Civil Aviation Development Investment Program Tranche 3 Social Monitoring Report Semi-annual Report January 2017 Civil Aviation Development Investment Program Tranche 3 Prepared by National Airports Corporation for the Asian Development Bank. This Semi-annual

More information

Social Monitoring Report

Social Monitoring Report Social Monitoring Report Project Number: 44427-013 November 2016 Period: January 2016 June 2016 IND: Chhattisgarh State Road Sector Project Package: Group A Submitted by: Public Works Department, Government

More information

VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line Social Monitoring Report 5 th Independent Monitoring Report January April 2016 VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2)

Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2) Periodic Financing Request Report Project Number: 48078-004 MFF Number: 0092 September 2017 Pakistan: Second Power Transmission Enhancement Investment Program (Tranche 2) Distribution of this document

More information

PAK: National Trade Corridor Highway Investment Program (NTCHIP) Tranche 2 (Package I)

PAK: National Trade Corridor Highway Investment Program (NTCHIP) Tranche 2 (Package I) Land Acquisition and Resettlement Internal Monitoring Report (E-35, Hassanabdal Havelian Expressway) (November 2015 January 2016) PAK: National Trade Corridor Highway Investment Program (NTCHIP) Tranche

More information

Islamic Republic of Pakistan: Sindh Provincial Road Improvement Project

Islamic Republic of Pakistan: Sindh Provincial Road Improvement Project Sindh Provincial Road Improvement Project (RRP PAK 46377) Project Administration Manual Project Number: 46377 Loan Number: September 2015 Islamic Republic of Pakistan: Sindh Provincial Road Improvement

More information

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project Technical Assistance Report Project Number: 51107-001 Transaction Technical Assistance (TRTA) October 2017 Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project This

More information

CONCLUSION REPORT. M6 INTERSTATE ROAD - Armenia. Complaint SG/E/2017/05. Complaints Mechanism - Complaints Mechanism. m -

CONCLUSION REPORT. M6 INTERSTATE ROAD - Armenia. Complaint SG/E/2017/05. Complaints Mechanism - Complaints Mechanism. m - M6 INTERSTATE ROAD - Armenia Complaint SG/E/2017/05 Complaints Mechanism - Complaints Mechanis m - Complaints Mechanism - Complaints Mechanism Complaints Mechanism - Complaints Mechanism - Complaints Mechanism

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RESETTLEMENT POLICY FRAMEWORK HURRICANE TOMAS EMERGENCY RECOVERY PROJECT Saint Lucia

More information

India: Public Private Partnerships in Highways Sector

India: Public Private Partnerships in Highways Sector India: Public Private Partnerships in Highways Sector Prepared by World Bank as input for IDA paper, 2008 (provided by Tarun Sankar, PPIAF office, South Asia) India s transport program is one of the most

More information

THIRD QUARTERLY REPORT FOR THE PERIOD ENDED SEPTEMBER 30,

THIRD QUARTERLY REPORT FOR THE PERIOD ENDED SEPTEMBER 30, THIRD QUARTERLY REPORT FOR THE PERIOD ENDED SEPTEMBER 30, 2016 CONTENTS 02 Company Profile 04 Directors Report 05 Directors Report (Urdu) 06 Condensed Interim Balance Sheet 08 Condensed Interim Profit

More information

(c) Section 3.07 is deleted and the following is substituted therefor:

(c) Section 3.07 is deleted and the following is substituted therefor: 2 outstanding Loan on which a higher Fixed Spread is applicable. The amount of the Rebate shall be determined by multiplying (i) the difference between the Fixed Spread applicable to the outstanding Loan

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

Pakistan: Decentralization Support Program

Pakistan: Decentralization Support Program Validation Report Reference Number: PCV: PAK 2011-53 Program Number: 34328 Loan Numbers: 1935/1936/1937/1938 December 2011 Pakistan: Decentralization Support Program Independent Evaluation Department ABBREVIATIONS

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

APPLICATION FOR DEMOLITION PERMIT

APPLICATION FOR DEMOLITION PERMIT APPLICATION FOR DEMOLITION PERMIT TOWN OF CHARLOTTE 8 Lester Street, P.O. Box 482, Sinclairville, NY 14782 Phone: (716) 962-6047 Fax: (716) 962-2147 PLEASE COMPLETE ALL REQUIRED INFORMATION. (Incomplete

More information

TENDER NOTICE FOR HIRING OF ARMED SECURITY GUARDS

TENDER NOTICE FOR HIRING OF ARMED SECURITY GUARDS TENDER NOTICE FOR HIRING OF ARMED SECURITY GUARDS SME Bank Ltd. intends to hire the services of Security Guards from the Security Agencies approved by the Pakistan Bank s Association. The Security Guards

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

More information

Growth through. Diversification

Growth through. Diversification Growth through Diversification 2nd Quarterly Report For the Quarter & Half-Year ended December 31, Growth Through Diversification 1 CORPORATE INFORMATION BOARD OF DIRECTORS CHAIRMAN Mr. Sikandar Mustafa

More information

STATE BANK OF PAKISTAN

STATE BANK OF PAKISTAN STATE BANK OF PAKISTAN AGRICULTURAL CREDIT DEPARTMENT ACD MISSION Availability of Adequate and Timely Credit AND Improving Living Standard of Rural Community WITH Dissemination of Knowledge, Counselling

More information

Guidelines. e Passbook. STATE BANK OF PAKISTAN Agricultural Credit Department

Guidelines. e Passbook. STATE BANK OF PAKISTAN Agricultural Credit Department Guidelines on e Passbook STATE BANK OF PAKISTAN Agricultural Credit Department www.sbp.org.pk The Team Name Designation Contact Muhammad Ashraf Khan Kamran Akram Bakhshi Muhammad Akram Director Joint Director

More information

Condensed Interim Financial Informaion Nine Month Accounts (Un-audited) 31 March 2017 BOOK POST. Jubilee Spinning & Weaving Mills Ltd.

Condensed Interim Financial Informaion Nine Month Accounts (Un-audited) 31 March 2017 BOOK POST. Jubilee Spinning & Weaving Mills Ltd. BOOK POST If undelivered please return to: 45-A,Off Zafar Ali Road, Gulberg-V, Lahore-Pakistan. Condensed Interim Financial Informaion Nine Month Accounts (Un-audited) 31 March 2017 Company Information

More information

Section 3.06 is deleted and the following is substituted therefor:

Section 3.06 is deleted and the following is substituted therefor: 2 (c) Section 3.03 is deleted and the following is substituted therefor: Commitment Charge; Credit; Maturity Premium. (a) The Borrower shall pay a commitment charge on the unwithdrawn amount of the Loan

More information

INTEGRATEDSAFEGUARDSDATASHEET CONCEPT STAGE. I Estimated Board Date: October 28, 20 13

INTEGRATEDSAFEGUARDSDATASHEET CONCEPT STAGE. I Estimated Board Date: October 28, 20 13 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 09/26/2013 INTEGRATEDSAFEGUARDSDATASHEET

More information

LOAN AGREEMENT (Ordinary Operations) (National Motorway M-4 Gojra-Shorkot Section Project) between ISLAMIC REPUBLIC OF PAKISTAN.

LOAN AGREEMENT (Ordinary Operations) (National Motorway M-4 Gojra-Shorkot Section Project) between ISLAMIC REPUBLIC OF PAKISTAN. LOAN NUMBER 3300-PAK LOAN AGREEMENT (Ordinary Operations) (National Motorway M-4 Gojra-Shorkot Section Project) between ISLAMIC REPUBLIC OF PAKISTAN and ASIAN DEVELOPMENT BANK DATED 22 OCTOBER 2015 PAK

More information

LOAN AGREEMENT (Ordinary Operations) (North-South Road Corridor Investment Program Project 2) between REPUBLIC OF ARMENIA. and ASIAN DEVELOPMENT BANK

LOAN AGREEMENT (Ordinary Operations) (North-South Road Corridor Investment Program Project 2) between REPUBLIC OF ARMENIA. and ASIAN DEVELOPMENT BANK LOAN NUMBER 2729-ARM LOAN AGREEMENT (Ordinary Operations) (North-South Road Corridor Investment Program Project 2) between REPUBLIC OF ARMENIA and ASIAN DEVELOPMENT BANK DATED 30 MAY 2011 ARM 42145 LOAN

More information

PAK: Power Distribution Enhancement Investment Program, Tranche 2

PAK: Power Distribution Enhancement Investment Program, Tranche 2 Social Monitoring Report Bi-annual Social Monitoring Report July 2013 PAK: Power Distribution Enhancement Investment Program, Tranche 2 Prepared by Faisalabad Electric Supply Company, Punjab for the Asian

More information

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1

PERIODIC FINANCING REQUEST. RE: Higher Education in the Pacific Investment Program: Periodic Financing Request #1 PERIODIC FINANCING REQUEST Date: April 2012 To: Asian Development Bank 6 ADB Avenue Mandaluyong City, Metro Manila ATTENTION: Director General, Pacific Department Fax No. +632-632-6318 Sir: RE: Higher

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Quarterly Report (Un-Audited) For the Period ended March 31, 2017

Quarterly Report (Un-Audited) For the Period ended March 31, 2017 Quarterly Report (Un-Audited) For the Period ended March 31, 2017 1 Contents Page Company Information 2 Sales Offices 4 Directors Review 5 Condensed Interim Balance Sheet 6 Condensed Interim Profit and

More information

Bi-annual Environmental Monitoring Report

Bi-annual Environmental Monitoring Report Bi-annual Environmental Monitoring Report Project Number: 42145 January-June 2011 Armenia: North-South Road Corridor Investment Program, Tranches 1 and 2 (Financed by the ADB) Prepared by the Organization

More information

LOAN AGREEMENT (Special Operations) (Climate Resilient Rice Commercialization Sector Development Project) between KINGDOM OF CAMBODIA.

LOAN AGREEMENT (Special Operations) (Climate Resilient Rice Commercialization Sector Development Project) between KINGDOM OF CAMBODIA. LOAN NUMBER 3007-CAM (SF) LOAN AGREEMENT (Special Operations) (Climate Resilient Rice Commercialization Sector Development Project) between KINGDOM OF CAMBODIA and ASIAN DEVELOPMENT BANK DATED 26 AUGUST

More information

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project Technical Assistance Report Project Number: 51039-001 Transaction Technical Assistance (TRTA) September 2017 Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

More information

STEP 7. Before starting Step 7, you will have

STEP 7. Before starting Step 7, you will have STEP 7 Gap analysis Handing out mosquito nets in Bubulo village, Uganda Photo credit: Geoff Sayer/Oxfam Step 7 completes the gap-analysis strand. It should produce a final estimate of the total shortfall

More information

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2)

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Social Monitoring Report Bi-annual Social Monitoring Report January 2015 PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Prepared by Quetta Electric Supply Company, Balochistan for

More information

FRAMEWORK FINANCING AGREEMENT

FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT FRAMEWORK FINANCING AGREEMENT (Second Power Transmission Enhancement Investment Program) Parties This Framework Financing Agreement ( FFA ) dated 15 July 2016 is between

More information

SETTING UP FUEL STATIONS/PETROL PUMPS & ALLIED

SETTING UP FUEL STATIONS/PETROL PUMPS & ALLIED Name of Site B I D F O R M FOR SETTING UP FUEL STATIONS/PETROL PUMPS & ALLIED FACILITIES ON PAKISTAN RAILWAYS REAL ESTATE A. DETAILS OF APPLICANT 1. Name of OMC/Authorized Dealer/Franchisee/Individual(s)

More information

NOTICE OF THE TWENTY SECOND ANNUAL GENERAL MEETING

NOTICE OF THE TWENTY SECOND ANNUAL GENERAL MEETING NOTICE OF THE TWENTY SECOND ANNUAL GENERAL MEETING Notice is hereby given that the 22 nd Annual General Meeting of Faysal Bank Limited ( FBL ) will be held on March 29, 2017 at 9:00 a.m. at Marriott Hotel,

More information

NORTH-SOUTH ROAD CORRIDOR INVESTMENT PROGRAM TRANCHE 3 (Talin-Lanjik and Lanjik-Gyumri), SUBSECTION 1

NORTH-SOUTH ROAD CORRIDOR INVESTMENT PROGRAM TRANCHE 3 (Talin-Lanjik and Lanjik-Gyumri), SUBSECTION 1 ECOOMIC DEVELOPMET AD RESEARCH CETER ORTH-SOUTH ROAD CORRIDOR IVESTMET PROGRAM TRACHE 3 (Talin-Lanjik and Lanjik-Gyumri), SUBSECTIO 1 IMPLEMETATIO OF LAD ACQUISITIO AD RESETTLEMET PLA COMPLIACE REPORT

More information

Request for Proposal for Engineering Services. January 10, 2017 Sue Howard Closing Date: January 17,

Request for Proposal for Engineering Services. January 10, 2017 Sue Howard Closing Date: January 17, Request for Proposal for Sue Howard Closing Date: January 17, 2017 Email: sue.howard@wetaskiwin.ca Contents Purpose... 3 Background... 3 Terms of Reference... 4 1. General... 4 2. Key Dates... 5 Scope

More information

Company Information 2. Sales Offices 3. Directors Review 4. Condensed Interim Balance Sheet 6. Condensed Interim Profit and Loss Account 8

Company Information 2. Sales Offices 3. Directors Review 4. Condensed Interim Balance Sheet 6. Condensed Interim Profit and Loss Account 8 1 Contents Page Company Information 2 Sales Offices 3 Directors Review 4 Auditors Report to the Members on Review of Condensed Interim Financial Information 5 Condensed Interim Balance Sheet 6 Condensed

More information

Government of Pakistan Ministry of Religious Affairs and Inter-Faith Harmony ***** EXPRESSION OF INTEREST FROM THE BANKS FOR HAJJ 2019.

Government of Pakistan Ministry of Religious Affairs and Inter-Faith Harmony ***** EXPRESSION OF INTEREST FROM THE BANKS FOR HAJJ 2019. Government of Pakistan Ministry of Religious Affairs and Inter-Faith Harmony ***** Subject:- EXPRESSION OF INTEREST FROM THE BANKS FOR HAJJ 2019. The Ministry of Religious Affairs and Inter-Faith Harmony

More information

Table-1: Overall Cost of the Flood

Table-1: Overall Cost of the Flood EXECUTIVE SUMMARY Preliminary Damage and Needs Assessment Disaster Overview 1. Pakistan experienced extraordinary rainfall in mid-july 2010, which continued until September 2010. The result was unprecedented

More information

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER PK. Public Disclosure Authorized

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER PK. Public Disclosure Authorized Public Disclosure Authorized OFFICIAL DOCUMENTS CREDIT NUMBER 5982- PK Public Disclosure Authorized Financing Agreement Public Disclosure Authorized (Punjab Tourism for Economic Growth Project) between

More information

SUI NORTHERN GAS PIPELINES LIMITED Gas House, 21-Kashmir Road, P.O. Box No. 56, Lahore (Pakistan)

SUI NORTHERN GAS PIPELINES LIMITED Gas House, 21-Kashmir Road, P.O. Box No. 56, Lahore (Pakistan) SUI NORTHERN GAS PIPELINES LIMITED Gas House, 21-Kashmir Road, P.O. Box No. 56, Lahore (Pakistan) NOTICE OF EXTRAORDINARY GENERAL MEETING Notice is hereby given that an Extraordinary General Meeting of

More information

Draft Resettlement Plan

Draft Resettlement Plan Document stage: Draft for consultation Project Number: 51228-001 February 2018 IND: Railways Track Electrification Project Rohtak to Panipat Subproject Prepared by Central Organisation for Railway Electrification

More information

3rd Quarter. & Nine Months accounts PERVEZ AHMED SECURITIES LIMITED. for the Period ended March 31, 2011

3rd Quarter. & Nine Months accounts PERVEZ AHMED SECURITIES LIMITED. for the Period ended March 31, 2011 3rd Quarter & Nine Months accounts for the Period ended March 31, 2011 CONTENTS Company Information Directors' Report Condensed Interim Balance Sheet Condensed Interim Profit & Loss Account Condensed Interim

More information