NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS

Size: px
Start display at page:

Download "NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS"

Transcription

1 NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS IAN PARKINSON Senior Consultant, Manchester The NEC3 suite of contracts were first published in 2005, meaning that the industry has had 13 years getting to grips with this family of contracts and specifically the provisions relating to the assessment of compensation events. However, I still come across cases/examples where the Parties, when assessing compensation events, fail to follow the contract. This short article is drafted to detail some of the key points to consider when assessing compensation events. DEFINED COST The assessment of compensation events is based upon the event s effect on the Defined Cost. The principle behind this is that a contractor should not unfairly gain or lose as a result of the compensation event. This is different from other standard forms of contract, which use the rates and prices included in the contract as a basis for assessment, where a contractor can potentially make significant gains or a significant loss as a result of a change. However, I continue to see examples of contractor s using their rates to price compensation events rather than the Defined Cost. This can mean the contractor is taking on more risk than they should and subsequently they under recover their full entitlement. Clause 63.1 states: The changes to the Prices are assessed as the effect of the compensation event upon: - the actual Defined Cost of the work already done; the forecast Defined Cost of the work not yet done and; the resulting Fee. 1

2 So, the contractor is entitled to assess the impact of the compensation event on their Defined Cost. The most frequently used contract options to calculate Defined Cost are either the Schedule of Cost Components (SCC) or the Shorter Schedule of Cost Components (SSCC). The cost components in the schedules include people; equipment; plant and materials; charges; manufacture and fabrication; design and insurance. If a cost item is not listed in the schedules, then it is deemed included in the Fee. Under the NEC3, the cut-off point between whether the contractor uses actual or forecast cost to assess the impact, is the date when the Project Manager instructed, or should have instructed, the Contractor to submit quotations. When making their assessment, contractors need to ensure that they account for not only the direct cost of doing the work, but the prolongation and disruption including any inefficient use of labour and plant as a result of the event. I often see assessments where the direct costs are included, but the contractor has not accounted for the disruption caused by the event, thus affecting their level of recovery and ultimately. If a compensation event occurs and, as a result of the event, there are labour and plant (Equipment under NEC3) resources not fully utilised, then this needs to be included in the assessment. A contractor would not be entitled to submit a separate claim for delay and disruption under an NEC3 form of contract. TIME Clause 62.2 of the NEC3 contract states Quotations for compensation events comprise proposed changes to the Prices and any delay to the Completion Date and Key Dates assessed by the Contractor. This means, that contractor must ensure they include any time impact within their quotations. Failure to do so may result in them not being entitled to an extension of time under the contract. Obtaining an extension of time is a precursor to recovering time-relating costs on the project. Failure to assess and include the time impact of the compensation event, will result in the contractor being unable to recover the time-related costs and could also make them liable for damages. On previous projects, I have seen contractors failing to 2

3 include the time impact of the event within the quotation, resulting in under recovery of costs and potential liability for damages. It should not be assumed that the impact of time on the project can be assessed globally. There is no scope for global claims under the NEC3 contract. The contract is clear, in that each event is assessed individually and in sequence. It is also worth remembering that delays to the Completion Date, are assessed as the length of time that, due to the compensation event, actual planned Completion is later than the planned Completion as shown on the Accepted Programme i, under clause Therefore, the Contractor is entitled to additional time and cost if the compensation event delays the planned Completion date, not the contractual Completion Date. RISK Clause 63.6 entitles the Contractor to include within their assessment, risk allowances for cost and time to cover matters which have a significant chance of occurring and are at the Contractor s risk under the contract. This is probably one of the main areas where contractors are under recovering their full entitlement on NEC3 contracts. As we all know, when pricing any construction work, assumptions have to be made for unknown elements that may or may not affect the works. Under the NEC3 form of contract it would be naïve to assume that by including your own assumptions within the quotation as to how you have assessed the event, you are protected if those assumptions turn out to be incorrect. The only contract provision entitling the contractor to additional time and/or cost is the compensation event provisions in clause Clause 60.1(17) entitles the contractor to a compensation event if the project manager (the contractor under the subcontract) notifies a correction to an assumption which he had stated i Last Accepted Programme if NEC4 applies 3

4 within his compensation event. Therefore, it is important to obtain the assumption from the project manager in accordance with clause 61.6, thus giving the contractor peace of mind that they will be entitled to an additional compensation event if those assumptions turn out to be incorrect. If an assumption is not forthcoming from the project manager then the contractor would be well advised to include risk allowances for any unknown/undefined factors, which may affect the works. I often find that this then prompts the project manager to provide the relevant assumption(s). In order to clearly explain pricing risk under the NEC3 contract I will give an example below based on the risk of weather events affecting the works. In this scenario clause 60.1(13) has been deleted from the contract, meaning the contractor carries the risk for all delays resulting from weather events. A compensation event occurs (a change to the Works Information) and a significant amount of rainfall is forecast in the month that the event is to occur. When making the assessment, should the contractor assume that all days will be affected, resulting in significant downtime or just a few days affected with little or no downtime? Taking this scenario back to the contract, the risk must have a significant chance of occurring, otherwise it is not a valid allowance in accordance with clause Therefore, the contractor must make a reasonable assessment of the likelihood of the rainfall causing downtime and make their allowance based on that assessment. The next threshold is that the risk must be with the contractor s under the contract. In this scenario the clause entitling the contractor to a compensation event due to a weather event, 60.1(13), has been deleted, meaning that any time and cost impact caused by weather events is at the contractor s risk under the contract. If this clause had not been omitted then the calculation would be completely different. Assessing risk in compensation events is akin to the way in which a contractor would assess the risk inherent in pricing a tender. If they get it right, they will maximise their return on investment, however if they get it wrong, they could stand to lose a significant amount of money on the project. If contractors adhere to the provisions of the contract relating to the assessment of compensation events, they will ensure that they maximise their returns on a project, thus maximising the bottom line. If you are having problems on an NEC3 or NEC4 contract regarding the assessment of compensation events, or any other matter, please do not hesitate to contact your nearest DGA office. 4

5 MORE INFORMATION If you would like to find out more details about any of the subjects covered in this Ebriefing please contact DGA Group through the contact details below or at DGA GROUP HEADQUARTERS 25 Eastcheap BIRMINGHAM Tel: +44 (0) London MANCHESTER Tel: +44 (0) United Kingdom NOTTINGHAM Tel: +44 (0) EC3M 1DE LEEDS Tel: +44 (0) BRISTOL Tel: +44 (0) Tel: +44 (0) MAIDSTONE Tel: +44 (0) UNITED ARAB EMIRATES SINGAPORE CANADA Office Anson Road 160 Quarry Park Boulevard SE Park Lane Tower #19-02 Suite 300 Al A amal Street Twenty Anson Calgary Business Bay Singapore Alberta United Arab Emirates Singapore Canada T2C 3G3 Tel: Tel: Tel: +1(403) Tel: HONG KONG AFRICA Suite 2802 Building 2 Lippo Centre Tower 2 Country Club Estate 89 Queensway 21 Woodmead Admiralty Sandton Hong Kong South Africa 2054 Tel:

6

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

NEC 3: How to claim as the main

NEC 3: How to claim as the main SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced

More information

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS C1.2 Contract Data Part one - Data provided by the Employer Clause Statement Data 1 General The conditions of contract are the core clauses and the clauses for main Option B: Priced Contract with Bill

More information

Newsletter Nr. 62 (EN) Demand Guarantees and Unfair Calling of Guarantees

Newsletter Nr. 62 (EN) Demand Guarantees and Unfair Calling of Guarantees Demand Guarantees and Unfair Calling of Guarantees November 2015 All rights reserved Lorenz & Partners 2015 Although Lorenz & Partners always pays great attention on updating information provided in newsletters

More information

Exposure Draft Accounting Guideline on Merger Accounting

Exposure Draft Accounting Guideline on Merger Accounting 30 March 2005 To: Members of the Hong Kong Institute of CPAs All other interested parties Exposure Draft Accounting Guideline on Merger Accounting Comments to be received by 31 May 2005 Issued by the Council,

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

Doing Business in the UAE September Alan Wood and Nigel Wilson Pinsent Masons LLP Dubai Branch

Doing Business in the UAE September Alan Wood and Nigel Wilson Pinsent Masons LLP Dubai Branch Doing Business in the UAE September 2009 Alan Wood and Nigel Wilson Pinsent Masons LLP Dubai Branch Introduction The Legal Framework of the UAE Legal Issues faced operating in the UAE Trading from Overseas

More information

McCarthy Tétrault Advance Building Capabilities for Growth. Group Terminations. Calgary, February 19, McCarthy Tétrault LLP / mccarthy.

McCarthy Tétrault Advance Building Capabilities for Growth. Group Terminations. Calgary, February 19, McCarthy Tétrault LLP / mccarthy. McCarthy Tétrault Advance Building Capabilities for Growth Group Terminations Calgary, February 19, 2015 Group Terminations in Alberta January 1 February 10 2014: 523 employees 2015: 4,544 employees Overall

More information

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable

More information

CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER 2017

CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER 2017 CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER 2017 CONTENTS CONSOLIDATED FINANCIAL STATEMENTS Page(s) Independent auditor s report 1-5 Consolidated statement of financial position 6

More information

Our members. At a glance 2016

Our members. At a glance 2016 Our At a glance 2016 Membership at a glance 2016 Gender split Age Location 67 % 33 % 30 Under 12,850 are 30 or under 43 % * inc Northern Ireland ** inc Republic of Ireland Male 19,963 9 % Rest of Europe**

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

Commercial (QS) Core Competencies (Feb 17)

Commercial (QS) Core Competencies (Feb 17) 01 Financial and commercial processes in civil engineering Optimum Activity Detail of A K E Management of budgets for civil engineering works. Cost forecasting, management and control processes including

More information

The Future of Retirement. Shifting sands

The Future of Retirement. Shifting sands The Future of Retirement Shifting sands Singapore The Future Future of Retirement of Retirement Report Shifting Shifting sands sands Foreword Key findings The changing retirement landscape Planning for

More information

The Future of Retirement. Shifting sands

The Future of Retirement. Shifting sands The Future of Retirement Shifting sands UK The Future Report Future of Retirement of Retirement Shifting Shifting sands sands Foreword Key findings The changing retirement landscape Planning for retirement

More information

THE COLD WAR: JCT AND ADVERSE WEATHER CONDITIONS

THE COLD WAR: JCT AND ADVERSE WEATHER CONDITIONS Date Posted: 02 December 2011 ramskill martin s previous article The Cold War: NEC and Adverse Weather Conditions explained the NEC s strict contractual rules for assessing when adverse weather is a Compensation

More information

Prompt Payment in Canada An Update Geza R. Banfai Thermal Insulation Association of Canada Banff, AB September 8, 2018

Prompt Payment in Canada An Update Geza R. Banfai Thermal Insulation Association of Canada Banff, AB September 8, 2018 Prompt Payment in Canada An Update Geza R. Banfai Thermal Insulation Association of Canada Banff, AB September 8, 2018 McMillan LLP Vancouver Calgary Toronto Ottawa Montréal Hong Kong mcmillan.ca Agenda

More information

Contractual Awareness Introduction

Contractual Awareness Introduction Contractual Awareness Introduction Geraldine Fleming Vice President and Executive Director February 2016 The Global Leader in Managing Construction Risk CORPORATE OVERVIEW Founded in 1973 in Manchester

More information

COMPARISON OF ARBITRATION RULES COMPARISON OF ARBITRATION RULES ICC UNCITRAL KLRCA. HKIAC HONG KONG INTERNATIONAL

COMPARISON OF ARBITRATION RULES COMPARISON OF ARBITRATION RULES ICC UNCITRAL KLRCA. HKIAC HONG KONG INTERNATIONAL COMPARISON OF RULES COMPARISON OF MALAYSIA - KUALA LUMPUR REGIONAL COMMERCE CENTRE FOR HONG KONG INTERNATIONAL CENTRE RULES About us Kennedys is an international law firm with over 150 partners and 800

More information

I18. Business Demography: Enterprise Births, Deaths and Survival Rates for 2016

I18. Business Demography: Enterprise Births, Deaths and Survival Rates for 2016 I18 Business Demography: Enterprise Births, Deaths and Survival Rates for 2016 Flavia D souza Public Intelligence (PRI) December 2017 Business Demography The latest Business Demography data for 2016 was

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Off-Site Manufacturing

Off-Site Manufacturing Off-Site Manufacturing The Legal Implications YORhub Conference 15 th November 2018 Dr Julie Morrissy A word of warning MODERNISE OR DIE 1 Modernise or die 2016 - The Farmer Review of the UK Construction

More information

International Commercial Arbitration - An Introduction. Steven Lim Managing Partner, Singapore, Nabarro LLP 12 October 2016

International Commercial Arbitration - An Introduction. Steven Lim Managing Partner, Singapore, Nabarro LLP 12 October 2016 International Commercial Arbitration - An Introduction Steven Lim Managing Partner, Singapore, Nabarro LLP 12 October 2016 Overview Rise in international arbitration Foundations of modern international

More information

Employment law update

Employment law update Employment law update May 2005 Transfer of undertakings The new TUPE regulations - how will they affect your business? This month we focus on the revised TUPE regulations published in draft by the DTI

More information

Exposure Draft (ED) of Proposed Statement of Auditing Standards (SAS) 730 The examination of prospective financial information

Exposure Draft (ED) of Proposed Statement of Auditing Standards (SAS) 730 The examination of prospective financial information Exposure Draft (ED) of Proposed Statement of Auditing Standards (SAS) 730 The examination of prospective financial information Comments to be received by 31 July 2002 Issued by the Auditing and Assurance

More information

The Future of Retirement. Shifting sands

The Future of Retirement. Shifting sands The Future of Retirement Shifting sands India The Future Future Report of Retirement of Retirement Shifting Shifting sands sands Foreword Key findings The changing retirement landscape Planning for retirement

More information

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success All in the Clause NEC to NEC4 Comparison of Core Clause 6 Compensation Events giving priority to your commercial success About us We provide: Quantity surveying and cost management Commercial management

More information

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT) Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the

More information

The Future of Retirement

The Future of Retirement The Future of Retirement Shifting sands Hong The Future Future of Kong Retirement of Retirement Report Shifting Shifting sands sands Foreword Key findings The changing retirement landscape Planning for

More information

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and

More information

PRODUCT HIGHLIGHTS SHEET

PRODUCT HIGHLIGHTS SHEET Prepared on: 30/04/18 This Product Highlights Sheet is an important document. It highlights the key terms and risks of this investment product and complements the Prospectus 1. It is important to read

More information

EDQ End Of Service Life Policy

EDQ End Of Service Life Policy EDQ End Of Service Life Policy Contents page 1. Introduction... 2 2. Explanation of terms... 2 3. End Of Service Life... 2 4. Availability of Technical Support... 3 Contact details... 4 1. Introduction

More information

BUSINESS CLASS FLYAWAY EXPERIENCE TO FASHION CITIES LUCKY DRAW PROMOTION 2018 TERMS AND CONDITIONS ( PROMOTION )

BUSINESS CLASS FLYAWAY EXPERIENCE TO FASHION CITIES LUCKY DRAW PROMOTION 2018 TERMS AND CONDITIONS ( PROMOTION ) BUSINESS CLASS FLYAWAY EXPERIENCE TO FASHION CITIES LUCKY DRAW PROMOTION TERMS AND CONDITIONS ( PROMOTION ) Definitions "Account" means a personal Singapore issued Maybank Credit and/or Debit Card account

More information

EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS

EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS Keith Potts, School of Construction, Engineering & Technology,

More information

Harmony CCP Connect for Equities

Harmony CCP Connect for Equities Harmony CCP Connect for Equities White Paper Contributions from: Contents Introduction Harmony CCP Connect for Equities The cost, operational and risk benefits include: 1. Improved efficiencies for settlement

More information

Shipbuilding Contracts the Value of Defence Club Cover

Shipbuilding Contracts the Value of Defence Club Cover Shipbuilding Contracts the Value of Defence Club Cover UKDC IS MANAGED BY THOMAS MILLER Why the UK Defence Club for newbuilding risks? Expertise: - Extensive experience in managing shipbuilding disputes

More information

DGA Group. International Construction Consultants

DGA Group. International Construction Consultants DGA Group International Construction Consultants Q4 2016 In this Issue: (Click on title to read article or scroll down) A message from the CEO Concurrent delay the Saga continues Grove Developments v Balfour

More information

Information regarding ISDA is set out in Annex 1 to this response.

Information regarding ISDA is set out in Annex 1 to this response. BY E-MAIL 20 April 2012 European Commission Directorate-General Internal Market and Services B-1049 Bruxelles/Brussel BELGIUM E-mail: markt-h4@ec.europea.eu Ladies and Gentlemen Discussion paper on the

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES PROLONGATION COST CLAIMS THE BASIC PRINCIPLES HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common

More information

Real Estate Bulletin

Real Estate Bulletin June 2014 Real Estate Bulletin Limiting Your Indemnity When the Words are Important Tsain-Ko Village Shopping Centre Limited Partnership v Watts ( Tsain-Ko ) 1 is the story of how the best laid plans of

More information

Importance of the amendment to the Public Procurement Law for the expenditure of EU funds

Importance of the amendment to the Public Procurement Law for the expenditure of EU funds August 2016 Practice Group(s): Government Contracts & Procurement Policy Piotr Kunicki, PhD, legal counsel in the Public Procurement Practice of K&L Gates Piotr Kunicki has been specializing in public

More information

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1 CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General

More information

Brexit considerations FOR BUSINESS CONTRACTS

Brexit considerations FOR BUSINESS CONTRACTS Brexit considerations FOR BUSINESS CONTRACTS d 1 Attorney advertising. Prior results do not guarantee a similar outcome. 2 With just over a year to Brexit, slated for 11.00pm on 29 March 2019, it is time

More information

THE HONG KONG INSTITUTE OF SURVEYORS

THE HONG KONG INSTITUTE OF SURVEYORS PART II ASSESSMENT 2013 DAY 2 Wednesday, 18 th September, 2013 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

Global Depositary Receipts and the new EU regime

Global Depositary Receipts and the new EU regime Global Depositary Receipts and the new EU regime Introduction This note sets out the implications of issuing Global Depositary Receipts ( GDRs ) on an EU regulated market (usually London in the case of

More information

Leaseholder Consultation Section 20 of the Landlord and Tenant Act 1985 (as amended)

Leaseholder Consultation Section 20 of the Landlord and Tenant Act 1985 (as amended) 1 Leaseholder Consultation Section 20 of the Landlord and Tenant Act 1985 (as amended) Insurance information sheet Tower Hamlets Community Housing manages in excess of 1,070 Leasehold and Shared Ownership

More information

WHAT IS A TRANSACTIONAL TAX PRACTICE?

WHAT IS A TRANSACTIONAL TAX PRACTICE? Transactional Tax Insights Betsy-Ann Howe Tax Partner - Sydney 19 August 2014 Copyright 2013 by K&L Gates. All rights reserved. WHAT IS A TRANSACTIONAL TAX PRACTICE? Corporate transactions Mergers & Acquisitions

More information

The 10 Most Important Issues General Counsel Should Know About Risk Transfer Involving Insurance

The 10 Most Important Issues General Counsel Should Know About Risk Transfer Involving Insurance The 10 Most Important Issues General Counsel Should Know About Risk Transfer Involving Insurance Wednesday April 27 th, 2016 Frank Palmay, P.Eng. Co-Chair, Financial Services Regulatory and Co-Chair, Cybersecurity

More information

MEASURING PERFORMANCE. Member and Broker Survey 2013 UKDC IS MANAGED BY THOMAS MILLER

MEASURING PERFORMANCE. Member and Broker Survey 2013 UKDC IS MANAGED BY THOMAS MILLER MEASURING PERFORMANCE Member and Broker Survey 2013 UKDC IS MANAGED BY THOMAS MILLER CONTENTS Background 1 Overall satisfaction 2 How is UKDC perceived 4 Likes and dislikes and comparison with other clubs

More information

Auditor General s Office

Auditor General s Office Auditor General s Office A MID-TERM REVIEW OF THE UNION STATION REVITALIZATION: MANAGING RISKS IN A HIGHLY COMPLEX MULTI-YEAR, MULTI-STAGE, MULTI- MILLION DOLLAR PROJECT Transmittal Report Audit Report

More information

INTERIM REPORT. FDM Group (Holdings) plc. For the six months ended 30 June Creating and inspiring exciting careers that shape our digital future

INTERIM REPORT. FDM Group (Holdings) plc. For the six months ended 30 June Creating and inspiring exciting careers that shape our digital future INTERIM REPORT For the six months ended 30 June 2016 Creating and inspiring exciting careers that shape our digital future Contents 1 About FDM 3 Highlights 6 Interim Management Review 14 Condensed Consolidated

More information

PROTECTING YOUR BUSINESS FROM EVERY POSSIBLE ANGLE

PROTECTING YOUR BUSINESS FROM EVERY POSSIBLE ANGLE PROTECTING YOUR BUSINESS FROM EVERY POSSIBLE ANGLE 01 QBE EUROPEAN OPERATIONS BUSINESS INSURANCE 02 Helping you achieve your ambitions At QBE European Operations, we aim to give you the confidence to achieve

More information

CHAPTER 1 25 INTRODUCTION

CHAPTER 1 25 INTRODUCTION CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time

More information

Prudential Unit Trusts

Prudential Unit Trusts Prudential Unit Trusts Contents Table of Contents Page 1. Prudential Unit Trusts - Pan European Fund... 1 2. Prudential Unit Trusts - Global Technology Fund... 6 3. Prudential Unit Trusts - Asian Balanced

More information

VAT update. News. Cases. August 2018

VAT update. News. Cases. August 2018 VAT update August 2018 In this month s update we report on (1) HMRC s revised guidance on the VAT cost share exemption; (2) HMRC s consultation and plans to address VAT avoidance via offshore looping;

More information

This form must be fully completed, signed and dated. Please delete accordingly and/ or state "N/A" if not applicable.

This form must be fully completed, signed and dated. Please delete accordingly and/ or state N/A if not applicable. For PATA Use Only PATA Travel Mart 2014 Diamond Island Convention and Exhibition Center, Phnom Penh, Cambodia 17-19 September 2014 SELLER ORGANISATION REGISTRATION APPLICATION ID# Date Batch# Appt# Booth

More information

CHINA TAIPING INSURANCE (UK) CO LTD LIABILITY POLICY SUMMARY

CHINA TAIPING INSURANCE (UK) CO LTD LIABILITY POLICY SUMMARY CHINA TAIPING INSURANCE (UK) CO LTD LIABILITY POLICY SUMMARY History You are in good hands. China Taiping Insurance (UK) Company Limited received its trading license in 1983 and commenced underwriting

More information

Exposure Draft ED/2009/4 Prepayments of a Minimum Funding Requirement, Proposed amendments to IFRIC 14

Exposure Draft ED/2009/4 Prepayments of a Minimum Funding Requirement, Proposed amendments to IFRIC 14 Deloitte Touche Tohmatsu 2 New Street Square London EC4A 3BZ United Kingdom Tel: +44 (0)20 7936 3000 Fax: +44 (0)20 7583 8517 www.deloitte.com Sir David Tweedie Chairman International Accounting Standards

More information

September 24, 2010 SUBMITTED BY

September 24, 2010 SUBMITTED BY Fasken Martineau DuMoulin LLP Barristers and Solicitors Patent and Trade-mark Agents www.fasken.com 66 Wellington Street West Suite 4200, Toronto Dominion Bank Tower Box 20, Toronto-Dominion Centre Toronto,

More information

PRODUCT HIGHLIGHTS SHEET

PRODUCT HIGHLIGHTS SHEET Prepared on: 23 December 2016 This Product Highlights Sheet is an important document. It highlights the key terms and risks of this investment product and complements the Prospectus 1. It is important

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

life protection I want substantial life protection at an affordable premium smart elite term smart term

life protection I want substantial life protection at an affordable premium smart elite term smart term life protection I want substantial life protection at an affordable premium smart elite term smart term Substantial protection, high flexibility and small premiums... You now get them all Financial obligations

More information

IS Prime Limited BEST EXECUTION REPORT FOR 2017 APRIL 2018

IS Prime Limited BEST EXECUTION REPORT FOR 2017 APRIL 2018 IS Prime Limited BEST EXECUTIO REPORT FOR 2017 APRIL 2018 Spot FX MiFID II RTS 28 Disclosures 1 Introduction IS Prime is a matched-principal broker in over-the-counter spot foreign exchange and precious

More information

New MAS Outsourcing Guidelines for Fund Managers and Other Financial Institutions

New MAS Outsourcing Guidelines for Fund Managers and Other Financial Institutions New MAS Outsourcing Guidelines for Fund Managers and Other Financial Institutions September 2016 SINGAPORE HONGKONG 20 YEARS IN PRACTICE EXECUTIVE SUMMARY Executive Summary Monetary Authority of Singapore

More information

BK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS

BK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALS Extensions of Time Valuation of Variations Bonds, Guarantees, Collateral Warranties

More information

Supplemental Information Memorandum

Supplemental Information Memorandum Supplemental Information Memorandum Deutsche Bank AG, Sydney Branch (a reference in this Supplemental Information Memorandum to Deutsche Bank AG, Sydney Branch is a reference to Deutsche Bank AG, a banking

More information

INTERACT POLICY

INTERACT POLICY INTERACT POLICY ---------------------------------------------------------------------------------------------------------------------------- TERMS AND CONDITIONS In consideration of You paying the Premiums

More information

Response to Exposure Draft Recognition of Deferred Tax Assets for Unrealised Losses

Response to Exposure Draft Recognition of Deferred Tax Assets for Unrealised Losses Kim Chiu Chua Singapore kim.chiu.chua@sg.pwc.com 18 December 2014 International Accounting Standards Board 30 Cannon Street London EC4M 6XH United Kingdom Submitted electronically through IFRS wedsite

More information

Why is the IFoA launching a new curriculum? Personal and Professional Development (PPD) Transferring from Core Technical to Core Principles

Why is the IFoA launching a new curriculum? Personal and Professional Development (PPD) Transferring from Core Technical to Core Principles Curriculum 2019 Curriculum Why is the IFoA launching a new curriculum? The 2019 Curriculum Qualification components Core Principles Core Practices Specialist Principles Specialist Advanced Professionalism

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

Miller Insurance Services (Singapore) Pte Ltd. Terms of Business Agreement ( TOBA )

Miller Insurance Services (Singapore) Pte Ltd. Terms of Business Agreement ( TOBA ) Miller Insurance Services (Singapore) Pte Ltd Terms of Business Agreement ( TOBA ) 1. Miller 1.1 Miller Insurance Services (Singapore) Pte Ltd (Miller Singapore) is a subsidiary of Miller Insurance Services

More information

b) by extending the relief to voluntary novations and making it clear that it can be applied retrospectively to past novations to CCPs.

b) by extending the relief to voluntary novations and making it clear that it can be applied retrospectively to past novations to CCPs. Ernst & Young Global Limited Becket House 1 Lambeth Palace Road London SE1 7EU Tel: +44 [0]20 7980 0000 Fax: +44 [0]20 7980 0275 www.ey.com International Accounting Standards Board 30 Cannon Street London

More information

10 THINGS TO KNOW ABOUT PROFESSIONAL INDEMNITY INSURANCE A GUIDE TO PROTECTING YOUR BUSINESS

10 THINGS TO KNOW ABOUT PROFESSIONAL INDEMNITY INSURANCE A GUIDE TO PROTECTING YOUR BUSINESS 10 THINGS TO KNOW ABOUT PROFESSIONAL INDEMNITY INSURANCE A GUIDE TO PROTECTING YOUR BUSINESS 01 10 THINGS TO KNOW ABOUT PROFESSIONAL INDEMNITY INSURANCE 10 things to know about Professional Indemnity insurance

More information

FUND PROTECT INNOVATION IN THE PROTECTION OF FUND DIRECTORS PERSONAL LIABILITY

FUND PROTECT INNOVATION IN THE PROTECTION OF FUND DIRECTORS PERSONAL LIABILITY FUND PROTECT INNOVATION IN THE PROTECTION OF FUND DIRECTORS PERSONAL LIABILITY FUND PROTECT INNOVATION IN THE PROTECTION OF FUND DIRECTORS PERSONAL LIABILITY Fund Protect Key Benefits Premium Market appraisal

More information

Certificate and Warrant Programme

Certificate and Warrant Programme PROSPECTUS The Royal Bank of Scotland plc (Incorporated in Scotland with limited liability under the Companies Acts 1948 to 1980, registered number SC090312) Certificate and Warrant Programme Under the

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

ABN AMRO (Channel Islands) Limited Order Execution Policy

ABN AMRO (Channel Islands) Limited Order Execution Policy ABN AMRO (Channel Islands) Limited Order Execution Policy 1. Introduction 1.1. What is the aim of this policy? In this policy document, the bank has set out the procedures and rules used to execute your

More information

Project Procedures. That Will Ensure Payment In Difficult Economic Times. By Neil Sinclair and Daniel Louw DMS International, Inc.

Project Procedures. That Will Ensure Payment In Difficult Economic Times. By Neil Sinclair and Daniel Louw DMS International, Inc. Project Procedures That Will Ensure Payment In Difficult Economic Times By Neil Sinclair and Daniel Louw DMS International, Inc. Introduction In today s market, subcontractors are pursuing work by cutting

More information

Personal and Executive Income Protection from Aviva

Personal and Executive Income Protection from Aviva Personal and Executive Income Protection from Aviva Key Features Retirement Investments Insurance Key features of Income Protection from Aviva Please read the Key Features document. It highlights the main

More information

How Do I Wire My Stock Plan Proceeds?

How Do I Wire My Stock Plan Proceeds? How Do I Wire My Stock Plan Proceeds? As the service provider for your company s stock plans, Morgan Stanley offers an automated way to transfer proceeds directly to your financial institution of choice.

More information

TIME IS MONEY OR IS IT? (PART 2)

TIME IS MONEY OR IS IT? (PART 2) TIME IS MONEY OR IS IT? (PART 2) In Part 1 of this article we reviewed the legal and contractual principles which apply to the time for completion of construction works and the remedies available to both

More information

LITIGATION FUNDING CLARITY I FOCUS I RESOLUTION

LITIGATION FUNDING CLARITY I FOCUS I RESOLUTION LITIGATION FUNDING Quantum Global Solutions (QGS) is a British founded and managed company, operating globally with our head office in the Middle East. We are a construction support consultancy partnering

More information

Negotiating the ISDA Master Agreement

Negotiating the ISDA Master Agreement Negotiating the ISDA Master Agreement Mastering an ISDA Master Agreement This course is presented in London on: 12 February 2019, 24 September 2019 If you have 5 or more participants, it may be cost effective

More information

ESTABLISHING A MANUFACTURING PLANT IN ASIA

ESTABLISHING A MANUFACTURING PLANT IN ASIA ESTABLISHING A MANUFACTURING PLANT IN ASIA Ian Lewis Partner Johnson Stokes & Master 20th May 2000 Today s discussion focuses on issues relevant to the establishment of a manufacturing plant in Asia. The

More information

IASB Exposure Draft on Classification and Measurement: Limited Amendments to IFRS 9

IASB Exposure Draft on Classification and Measurement: Limited Amendments to IFRS 9 28 March 2013 International Accounting Standards Board 30 Cannon Street London EC4M 6XH United Kingdom Dear Sir/Madam, IASB Exposure Draft on Classification and Measurement: Limited Amendments to IFRS

More information

HONG KONG SCIENCE AND TECHNOLOGY PARKS CORPORATION

HONG KONG SCIENCE AND TECHNOLOGY PARKS CORPORATION Description The Hong Kong Science and Technology Parks Corporation (HKSTP) is now inviting qualified and experienced Contractors to apply for pre-qualification for inclusion in the tenderer s list of Design

More information

Tax update. News items. Case reports. October 2018

Tax update. News items. Case reports. October 2018 Tax update October 2018 In this month s update we report on (1) HMRC s Spotlight 45 on umbrella company avoidance schemes; (2) an update to HMRC s Venture Capital Schemes Manual; and (3) call for evidence

More information

PRODUCT HIGHLIGHTS SHEET

PRODUCT HIGHLIGHTS SHEET This Product Highlights Sheet is an important document. Prepared on: 31 July 2018 It highlights the key terms and risks of this investment product and complements the Prospectus 1. It is important to read

More information

Dated 2015 THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF BARNET (EMPLOYER) -and- [ ] LIMITED (CONTRACTOR)

Dated 2015 THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF BARNET (EMPLOYER) -and- [ ] LIMITED (CONTRACTOR) Dated 2015 THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF BARNET (EMPLOYER) -and- [ ] LIMITED (CONTRACTOR) Pre-Construction Services Agreement in relation to [ ] Incorporating the conditions of the JCT

More information

Less is More: Private Equity Investments` Benefits

Less is More: Private Equity Investments` Benefits Real Estate as a Strategic Asset Class The Benefits of Illiquid Investments Real estate, a key asset class in a portfolio, can offer stable income returns, partial protection against inflation, and good

More information

Title Aggregated Procurement

Title Aggregated Procurement Policy and Resources Committee 02 September 2016 Title Aggregated Procurement Report of Chief Operating Officer Wards All Status Public Urgent No Key Yes Enclosures None Officer Contact Details Chris Smith

More information

Conflict of Interest Directors and prescribed officers

Conflict of Interest Directors and prescribed officers Conflict of Interest Directors and prescribed officers Position Paper 5 - June 2012 CONTENTS Introduction A broad overview Materiality in the context of conflicts When can conflicts be managed and when

More information

This Presentation is for information purposes in connection with Leed Resources PLC (the Company ). While the information contained herein has been

This Presentation is for information purposes in connection with Leed Resources PLC (the Company ). While the information contained herein has been This Presentation is for information purposes in connection with Leed Resources PLC (the Company ). While the information contained herein has been prepared in good faith, neither the Company nor any of

More information