EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS

Size: px
Start display at page:

Download "EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS"

Transcription

1 EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS Keith Potts, School of Construction, Engineering & Technology, University of Wolverhampton Dennis Toomey, Hong Kong Mass Transit Railway Corporation KEY WORDS Interim payments, pre-determined stage payments, milestones, "S" curve Summary The normal practice in the construction industry is for the contractor to be paid monthly advances during the execution of the works. The value of these payments being determined by agreement, often based on measurement, between the employer and contractor. However the Latham Report, published in the UK in July 1994, recommended that clients implement a new regime with payment against the achievement of milestones, activity schedules or payment schedules. Two different alternative payment systems have been developed and used - one in Hong Kong the other in the United Kingdom. Both of these systems utilise the concept of monthly payments based on pre-determined stage payments linked to the achievement of satisfactory progress monitored against milestones or the construction programme. Payment under the Hong Kong model, which was developed by the Hong Kong Mass Transit Railway Corporation and subsequently adopted for Airport related projects, is based on a cash flow pre-determined by the contractor and included in his bid. In contrast payment under the UK model [GC/Works/l(Edition 3)], which was devised by the Property Services Agency representing the UK Government, is based on a standard "S" curve established by the client and included in the contract. This paper critically examines and compares the effectiveness of these two systems. Introduction The Latham Report (1994) is a most ambitious attempt to reduce conflict and increase productivity in the UK construction industry. The Interim Latham Report, published in December 1993, identified that some clients were concerned that the traditional method of calculating monthly interim certificates based on measurements was not necessarily the best way to ensure satisfactory progress of construction contracts. The Interim Report further identified that there was an increased interest in negotiating agreed stages of work before the start of the contract, and payment being made when those stages are met. The aim of this paper is to briefly describe two different alternative payment systems - one used in Hong Kong the other in the UK - which have both been designed to link interim payments to satisfactory progress. The paper will firther examine the effectiveness of these payment systems based on the responses to a questionnaire sent to the main parties who have used them.

2 =Hone KO~Q Model General comments In 1978 the Mass Transit Railway Corporation (MTRC) introduced the concept of a monthly payment system based on the application of pre-determined percentages (Interim Payment Schedule percentages) to the total value of specified major elements of the works - linked to the achievement of "milestones". The system had been devised by the MTRC and Freeman Fox (now Acer Consultants). Milestones "One very important aspect of the MTRC approach was the identification of key dates for the required progress of each contract within the overall time frame of the project and their inclusion in the contract documents" (Sharpe, (1987)). "Critical dates" were generally applicable to a stage of completion and contract interface and were subject to liquidated damages whilst "milestone dates" were designated for the start or completion of activities. In general terms milestones were identified at about 3 month intervals during the period of completion for the works for each cost centre. However cost centre "A" contained only one milestone "submission of programme" Typically on a major civils project there would be 10 critical dates and over 60 milestones. Interim Payment Schedule (IPS) The bills of quantities were divided into "Cost Centres" reflecting major elements of work e.g. a station or tunnels between stations. There were between 4-8 cost centres per contract with cost centre "A" containing the general items, or preliminaries applicable to the whole contract. A separate Interim Payment Schedule (IPS) was provided for each cost centre. At tender stage each contractor was required to insert their required percentages for monthly payments against each cost centre. The IPS system thus enabled contractors to recover their initial mobilisation costs which on an international project of this magnitude were likely to be considerable. Provided that progress was satisfactory and the key dates met then payment would be made based on the full percentage value as bid. If one of the original milestone dates, or any subsequently revised date due to an extension of time award, was not met payment against the relevant cost centre was suspended. The IPS was then amended by a graphical method taking into account the date by which the non- achieved milestone would be achieved and the intervening percentages were re-evaluated accordingly; reference (Potts, (1988)) describes the procedure in detail. The system required that prior to payment to the contractor certain adjustments, i.e. additions and omissions were made to the value of each cost centre including: provisional sums, P.C. sums for nominated subcontractors, variation orders and the value of measured work. Benefits to the client By using this system the MTRC gained several benefits including: the ability to compare the true amount of tenders by using the discounted cash flow method by evaluating all tenders on a Net Present Value basis - in effect penalising contractors who have front-end load their tender, identification of the project cash-flow liability, senior management able to monitor progress simply by monitoring the cash flow, obtaining contracts which positively motivated contractors to meet key milestone dates and complete the works on time; thus providing a link between performance and payment and rewarding the efficient contractor., reduction in measurement staff needed to prepare monthly interim valuations.

3 greater likelihood of obtaining completion within time and cost, thus obtaining best value for money. David Sharpe, the former Chief Civil Engineer of the MTRC considered that "This payment system and its link with the Milestone Dates provided everyone (and particularly the construction management) with a clear and unequivocal measure for progress, and assisted management efforts towara3 the aim of completion on time." (Sharpe, (1 987)) New developments The IPS system was subsequently adopted and used by the Highways Department and one of Hong Kong's largest developers - the Hong Kong Jockey Club. The system is now used on the Airport Core Programme (ACP) and by the Provisional Airport Authority (PAA) as well as by MTRC on the Airport Railway. Generally there has been a certain amount of fme tuning on the payment system on MTRC, PAA and ACP contracts - mostly geared to ensuring a closer link between the IPS and the milestone schedule including: restraint on the total percentage amount to be included in Cost Centre A (preliminaries) restricted to 20-25%, 0% sometimes included by the Engineer in the IPS as part of the tender documentation to prevent excessive fiont loading, many more milestones in respect of Cost Centre A, payment restraints of minimum 2.5% between milestones and maximum 97.5% prior to completion of last milestone, greater power for Engineer to change the IPS and milestone schedule e.g. in the event of extensions of time or significant change to the cost centre value. The UK model General comments The Lump Sum with Quantities version of GC/Works/l (Edition 3) or to give it its full title "The General Conditions of Contract for Building and Civil Engineering" was first published in December 1989 and republished, after drafting changes, in GC/Works/l(Edition 3), which is intended for use on Government building or civil engineering works over 150,000, was developed by the Property Services Agency (PSA) of the Department of Environment. Stage Payment Chart Clause 48 "Advances on Account" introduces an entirely new concept providing for the payment of monthly interim payments based on a pre-determined "S" curve which was calculated by the PSA following analysis of over 500 projects. A "Stage Payment Chart" model form for projects above 5,500,000 is included in the back of the Conditions. The Stage Payment Chart (SPC), which is included in the tender documents links the monthly payment to satisfactory progress on a standard percentage basis. Retention is not considered on the charts and separate charts are available for nominated subcontractors. Contractors should therefore include in their tenders for any divergence between the likely payments and the anticipated resource cost. Provided that relevant instructions have been complied with and the work is to the satisfaction of the client's project manager then the contractor is paid monthly advances based on 95% of the proportion of the sum specified in the Stage Payment Chart for that month. Payments for variations and for prolongation and disruption are treated separately.

4 The client's project manager is firher given the power to amend the stage payment chart to reflect actual progress and any changes resulting from cost saving proposals under clause 52. The chart should be adjusted following the statement recorded by the project manager in the monthly progress meetings that the works are in delay or ahead of the programme. Programme Monitoring of the programme, which is normally submitted by the contractor within 2 1 days of contract award, should be in accordance with the guidelines laid down in "Planned Progress Monitoring" (DOE, (1986)). The guidelines recommend that the network is re-drawn into a bar chart form, preferably as a linked bar-chart, in such a way as to continue to show the inter- relationship and timing of the activities and the critical path. The linked bar chart should, after each monthly progress meeting, be monitored using the activity time unit method [counting the squares (CTS)]. This system greatly simplifies the monitoring process, however in practice some "weighting" of the activities may be desirable. The achieved percentage completion can be plotted onto the "S" curve derived from the "Stage Payment Chart" and the percentage proportion of the contract sum payable established. The interim payment thus reflects satisfactorily completed works on a progress basis and is not based on the rates included in the bill of quantities. Research methodolo~e A questionnaire was prepared with the objective of obtaining information on the effectiveness of the two alternative payment systems. A total of 80 questionnaires were sent in Hong Kong and 60 in the UK - to both contractor and client representatives. The questionnaire comprised 20 questions (see below) reflecting those issues identified in the Latham Report (1). The questionnaire required the respondents to consider each of the twenty statements and using the scale provided to circle the number that indicated the extent to which they agreed or disagreed with the statement. By using this numerical approach a direct comparison could then be made between the contractors' and clients' views of the two systems. Additional comments were sought from all respondents in order that particular items of concern could be identified. Analysis A total of 57 questionnaires (41%) were returned analysed as follows: Hong Kong: contractors - 8, client representatives - 2 1, United Kingdom: contractors - 24, client representatives - 4. The quality of feedback was excellent as the questionnaires were generally completed in detail by commercial directors, construction managers, senior partners and senior engineers. The following scale was used in the questionnaire: Strongly disagree Neutral Strongly agree All numbers in the chart that follows reflect the mean of the returned questionnaires in the respective categories - generally the higher the score the more favourable the response.

5 HK (IPS) Contr. Client Contr. Client 1. Promotes satisfactory progress 2. Allows for negotiation of agreed stage payments before start of contract 3. Enables contractors to specify magnitude and timing of mobilisation payments 4. Enables prompt recovery of cash flow reflecting value of work executed 5. Enables bidders to specify their preferred duration 6. Monitoring of progress is fairly assessed 7. Penalises contractors who are ahead of programme 8. Prompt changes easily made to payment schedule to accommodate extra works 9. Prompt changes easily made to payment schedule to accommodate extensions of time 10. Allows for payments of formal incentives and bonus 1 1. Allows for sharing of savings identified by contractor 12. Rules of interpretation are applied consistently 13. Operates better with fewer cost centres (4-8) 14. Operates better with frequent milestones per cost centre (every 3 months) 15. System suitable for any building1 civils project 16. Enhances team-working 17. Encourages use of computerised project planning systems 18. Reduces conflict 19. Increases productivity 20. On balance, has worked well in practice Mean score of items reflecting sound project management (all less 7, 13-15)

6 Summary of other relevant comments: (I) HONG KONG - "Interim Payment System" (a) H.K. contractors' comments: "The achievement of milestones can be subject to differing opinions and interpretation." "Must involve a fairer interpretation of revision clauses than now where all discretion is with the client - however we have successfully re-negotiated IPS to reflect programme." One respondent suggested introducing an automatic review of IPS andor the descriptions andor dates of milestones every 6 months. On the same theme, another respondent considered there should be a clear mechanism whereby the client is obliged to change the IPS in accordance with the approved programme - limited to 6 occasions, say three upon the client's initiative and three upon the contractor's request. "Items 2,3 and 4 depend upon whether the tender documents impose unrealistic limits on the monthly % per cost centre. Contractors must be allowed to structure their IPS to suit their true costs. A tender assessment making use of Net Present Value would control abuse". "Ultimately it depends on the logic applied in application, PQSIclient can use the milestone description and the IPS revision clauses as a big stick. However I think it is a good system when properly applied - if not fairly administered by the client the system is no improvement on other payment procedures". "Many professionals (engineers, contractors, civil servants and lawyers) believe that ACP contracts are in breach due to the non issuance of e o t's for V.O.'s and delays by the engineerlclient. They have not correctly modified milestones etc promptly and thus affected the contractors income by delays to payment from the IPS. A much more flexible administration is required". (b) H.K. client representatives' comments: " A prerequisite for the success, or otherwise, of a milestone type IPS arrangement is that the client should have a reasonably settled design and a thorough understanding of the construction programme necessary to complete the works within the time scale identified." "Has worked well on MTRC projects. Is not a sophisticated system and requires a fair and reasonable interpretation of the "intent" of the milestones. It is essential that the milestones are selected on the "critical path" and the Engineer's programme is robust." "Considerable care must be taken when determining milestone descriptions and dates to ensure that they provide adequate control for the ClientEngineer without applying too much pressure on the contractor or restricting the contractor's cash flow too much.'' "However its one inherent problem is that unless variations are agreed and valued on a regular basis and the IPS adjusted accordingly then either an underpayment, or more likely an overpayment, will occur." "The IPS approach has been readily accepted. The client can control cash flow by limiting the percentage payment up to a certain month in any cost centre. More cost centres and fewer milestones per cost centre can overcome the effects of changes to programme logic. "The contract needs to establish the contractors anticipated cash flow with his tender programme. It allows a fmancial comparison to be made between tenders. More importantly it provides a basis for revised IPS values for a change in programme logic". "The milestone payment system is equally applicable to (indeed is probably the best system for design and construct projects (including B.O.T.) where a major problem exists over the ascertainment of interim payments

7 and progress without a conventional detailed B of Q at bid stage. The system is fairly simple in base concept but requires a holistic approach to its incorporation into a contract. It is not just a set of changes to Conditions of Contract, so its incorporation into Standard Conditions of Contract will also require a number of guidance notes on alterations to associated documents". "Adoption of the IPS system should ideally be limited to linear (horizontavvertical operations." However one respondent commented that the system would not be appropriate on a road contract with say 20 access points where sections may be completed out of sequence. Three other client representatives identified the difficulties of using the system on complex building projects with many trades - indeed one observed that "its disadvantages may outweigh its benefits in contracts for more complicated works", another considered the system "naive and dangerous" (2) UNITED KINGDOM - "Stage Payment Chart" (a) UK Contractors' comments " In principle the idea and general arrangement of stage payment charts is essential to improve productivity etc. but the chart needs to be agreed between the client/contractor and should reflect the actual circumstances directly. Standard "PSA" type payment charts are not the answer." " User friendly, very flexible, can be modified to make allowances for e.g. e.o.t., V.O.'s, progress etc. Enables managers to retain a good feel financially without having to resort to too much detail." Areas of concern related to: stage payments to subcontractors, method for calculating progress achieved, incorporation of variations, real possibility that contractor may have to part-finance some projects, internal financial reconciliations, no provision regarding payment for off-site materials, implementation by individuals administering contracts prevents system working effectively - "red tape within the Ministry of Defence" (b) UK client's comment: "The system is based on the accuracy of the appointee's assessment of programme progress, however this should be agreed with the main contractor." Conclusions the HK IPS system generally contributed more to effective project management than did the UK SPC system. UK client representative (a small sample) considered the UK SPC a far better system than did UK contractors. the HK IPS system achieved a higher score from the contractors than did the UK SPC system from UK contractors on all issues except: - item 5 (enables bidders to specify their preferred duration - this was a marginal difference), - item 7 (penalises contractors who are ahead of programme), - item 18 (reduces conflict - this was surprising; however, the Hong Kong client representatives took a more positive view of the Hong Kong IPS system), the Hong Kong IPS system works better on 'linear' projects and has limitations on complex building work, the success, or otherwise, of alternative payment systems can be directly attributable to the "reasonableness" and "promptness" of the client and the client's contract administrator in operating the scheme, the New Engineering Contract, recommended by the Latharn Report as the preferred contract, should be amended to incorporate an option of payment using the Hong Kong IPS system.

8 References Latham, Sir M., Constructing the Team: Final report of the Government/Industry review of procurement and contractual arrangements in the UK Construction industry, HMSO, Sharpe, D.J., Urban Railways and the Civil Engineer, Conf: London , ICE, Session 3 - Construction, Paper 10, Completing on time- construction management, pp Potts, K.F., An aiternative payment system for major "fast track" construction projects, Construction management and Economics, 1988, 6, Department of Environment, (DOE), PSA, Professional Practice and Management Group, Directorate of Quantity Surveying Services, Planned Progress Monitoring, 1986.

Form of Agreement Between the Client And the Quantity Surveyor

Form of Agreement Between the Client And the Quantity Surveyor Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.

More information

Somewhere in Time - Securing and Protecting your Contractual Rights

Somewhere in Time - Securing and Protecting your Contractual Rights Howard KLEIN, United Kingdom Keywords: Ascertaining Delays, Delay Costs, Notice, Provisions, Extension of Time, Records, Construction Economics. SUMMARY Time is money and this is no less the case on construction

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

OWNER CONTROLLED INSURANCE PROGRAMME IN CONSTRUCTION CONTRACTS

OWNER CONTROLLED INSURANCE PROGRAMME IN CONSTRUCTION CONTRACTS Seminar 27 November 2015 OWNER CONTROLLED INSURANCE PROGRAMME IN CONSTRUCTION CONTRACTS Procurement Fact Sheet No. 001/14 Presented by Adrian King Senior Consultant Construction, Aon Hong Kong Limited

More information

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 INTRODUCTION TO THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017 BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable

More information

New Zealand Clearing Limited. Clearing and Settlement Procedures

New Zealand Clearing Limited. Clearing and Settlement Procedures New Zealand Clearing Limited Clearing and Settlement Procedures 6 May 2016 Contents Section A: Interpretation and Construction 7 Section 1: Introduction and General Provisions 8 Amendment Procedure 8 1.1

More information

Nigel White. Profile. Expertise:

Nigel White. Profile. Expertise: Nigel White Profile 40 years experience in the construction industry with specialist experience in dispute resolution, commercial management, and risk management. Tel: +971 50 427 2595 nigelwhite@whiteconsulting-me.com

More information

Clearing and Settlement Procedures. New Zealand Clearing Limited. Clearing and Settlement Procedures

Clearing and Settlement Procedures. New Zealand Clearing Limited. Clearing and Settlement Procedures Clearing and Settlement Procedures New Zealand Clearing Limited Clearing and Settlement Procedures 3 August 2010 Contents Section A: Interpretation and Construction 6 Section 1: Introduction and General

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

REQUEST FOR PROPOSAL FOR. Full Cost Allocation Plan and Citywide User Fee and Rate Study. Finance Department CITY OF HUNTINGTON BEACH

REQUEST FOR PROPOSAL FOR. Full Cost Allocation Plan and Citywide User Fee and Rate Study. Finance Department CITY OF HUNTINGTON BEACH REQUEST FOR PROPOSAL FOR Full Cost Allocation Plan and Citywide User Fee and Rate Study Finance Department CITY OF HUNTINGTON BEACH Released on October 17, 2007 Full Cost Allocation Plan and Citywide User

More information

Sheila Belayutham CHAPTER 6 CONTROL

Sheila Belayutham CHAPTER 6 CONTROL CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

UNIT 11: STANDARD COSTING

UNIT 11: STANDARD COSTING UNIT 11: STANDARD COSTING Introduction One of the prime functions of management accounting is to facilitate managerial control and the important aspect of managerial control is cost control. The efficiency

More information

Coverholder approval, restricted coverholders and Consumer Product Binding Authorities

Coverholder approval, restricted coverholders and Consumer Product Binding Authorities market bulletin Ref: Y4739 Title Purpose Type From Coverholder approval, restricted coverholders and Consumer Product Binding Authorities To inform the market of: proposed changes to the way in which coverholders

More information

QBCC PERIOD MINOR WORKS SUBCONTRACT

QBCC PERIOD MINOR WORKS SUBCONTRACT Build better. QBCC PERIOD MINOR WORKS SUBCONTRACT The General Conditions of the QBCC Period Minor Works Subcontract may not be suitable for all work and the QBCC does not make any representation as to

More information

Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004

Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004 Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004 Background 1. Target Cost Incentive Fee Arrangements are one of a range of contracting

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

encouragement to move on with optimisms. Opening Session : Employer (Respondent)

encouragement to move on with optimisms. Opening Session : Employer (Respondent) 359 can summarise it as the establishment of common facts, grounds, understandings, and so on, emitting the scent of constructiveness, progress and agreeability of the parties as encouragement to move

More information

Accountable Grant Arrangement

Accountable Grant Arrangement Name: XXX Address: XXX Office Address: Department for Transport, Great Minster House, Horseferry Road, London, SW1P 4DR Email: HTPGrants@ricardo.com DATE Dear XXX Accountable Grant Arrangement CAPITAL

More information

CHAPTER 1 25 INTRODUCTION

CHAPTER 1 25 INTRODUCTION CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time

More information

A guide to how we manage our with profits fund

A guide to how we manage our with profits fund Pensions Savings Investments Protection Insurance A guide to how we manage About this guide This guide tells you: how we manage how our with profits policies work, and what benefits policyholders can expect

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),

More information

CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk

More information

Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun

Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun A.G.D.Premalal 1, R.K.P.C.B. Mudalige 1 and S.N.Malkanthi 1 1 Department of Civil and Environmental

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

Cost and Schedule Controlling in Relation to Liquidity Management during Construction Projects

Cost and Schedule Controlling in Relation to Liquidity Management during Construction Projects Cost and Schedule Controlling in Relation to Liquidity Management during Construction Projects Martin Kopyto, University of Applied Sciences Giessen-Friedberg (martin.kopyto@bau.fh-giessen.de) Armin Möller,

More information

Admission Agreement To participate in the Local Government Pension Scheme [relating to services provided to [school/other employer]]

Admission Agreement To participate in the Local Government Pension Scheme [relating to services provided to [school/other employer]] Dated 2018 (1) WOLVERHAMPTON CITY COUNCIL (2) [SCHEME EMPLOYER] (3) [ADMISSION BODY] Admission Agreement To participate in the Local Government Pension Scheme [relating to services provided to [school/other

More information

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03

TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE 5.03 Ofwat Issued April 1997 Revised March 2000 1 TRANSFER PRICING IN THE WATER INDUSTRY REGULATORY ACCOUNTING GUIDELINE CONTENTS

More information

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:- Anti-Bribery & Corruption Policy of Intent STONBURY LIMITED TERMS AND CONDITIONS FOR SUBCONTRACTORS 1. INTERPRETATION (1) In these sub-contract conditions of agreement, the following words and phrases

More information

1. Risk of regularizing illegal connections

1. Risk of regularizing illegal connections 1. Risk of regularizing illegal connections Background: This is an example of a contract provision for mitigating the risk of converting illegal connections to legal connections in a 300,000 population

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

AIRPORT AUTHORITY HONG KONG

AIRPORT AUTHORITY HONG KONG AIRPORT AUTHORITY HONG KONG GENERAL CONDITIONS OF CONTRACT BUILDING AND CIVIL WORKS ISSUE NO. 10 August 2011 [this page not used] GENERAL CONDITIONS OF CONTRACT FOR BUILDING AND CIVIL WORKS TABLE OF CONTENTS

More information

`the contractor may at any time submit for the PM s agreement proposals for the amendment of the Programme.'

`the contractor may at any time submit for the PM s agreement proposals for the amendment of the Programme.' 6 PROGRAMME 6.1 Where a contractor submits a programme which is approved or accepted by the architect/engineer,is he obliged to follow it or can he amend it at his own discretion? 6.1.1 The programme is

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

LONG-TERM WARRANTY CONTRACTS RISK OR REWARD?

LONG-TERM WARRANTY CONTRACTS RISK OR REWARD? LONG-TERM WARRANTY CONTRACTS RISK OR REWARD? Anne Holt, P.Eng. Senior Engineer aholt@ara.com David K. Hein, P.Eng. Principal Engineer Vice-President, Transportation dhein@ara.com Applied Research Associates

More information

NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS

NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS IAN PARKINSON Senior Consultant, Manchester The NEC3 suite of contracts were first published in 2005, meaning that the industry has had 13 years getting to

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy Single Project Professional Indemnity Insurance Proposal Form Note: This is a proposal form for a claims made policy Please provide any necessary explanations or additional details by attaching separate

More information

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION NOTICE TO BIDDERS NO. 4 DATE: 10/25/2002 SUBJECT: DISADVANTAGED BUSINESS ENTERPRISES IN FEDERAL-AID HIGHWAY CONSTRUCTION This

More information

Pricing - Post Costing

Pricing - Post Costing Constraints None. Pricing - Post Costing Authoritative Guidance Summary 1. The 2003 General Review of the Government Profit Formula introduced new arrangements for post costing. Existing DEFCONs (648,

More information

Project Delays and Extensions of Time. Dr Tony Farrow

Project Delays and Extensions of Time. Dr Tony Farrow Project Delays and Extensions of Time Dr Tony Farrow Topics 1. Why Extensions of Time? 2. Methods of Analysis and examples 3. Schedule Float 4. Concurrent Delay 5. Exercise 6. Questions Construction Contracts

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR SCHEDULES 8 + 9 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR

More information

The Revenue can effectively audit any claim made within the last 5 accounting years this is the statute of limitation.

The Revenue can effectively audit any claim made within the last 5 accounting years this is the statute of limitation. Appendix 10: Irish Revenue Audits When auditing (can be either a desk or field audit) R&D tax credit claims, the Irish Revenue may appoint an external independent technical expert (usually a Professor

More information

1.1 The names and addresses of the parties to the reference are as follows:-

1.1 The names and addresses of the parties to the reference are as follows:- 1 DETAILS OF PARTIES Joint Reference to the Access Disputes Panel Of a Dispute Relating to Vehicle Change for Class 185 Diesel Multiple Units Reference ADP14 1.1 The names and addresses of the parties

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory

More information

RESULTS OF THE 2010 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MAY Prepared by: Dr HJ Marx

RESULTS OF THE 2010 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MAY Prepared by: Dr HJ Marx RESULTS OF THE 2010 SURVEY OF THE cidb CONSTRUCTION INDUSTRY INDICATORS MAY 2011 Prepared by: Dr HJ Marx of Quantity Surveying and Construction Management University of the Free State Marxhj@ufs.ac.za

More information

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001 NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller

More information

Retires in. Bonnie plans to retire in She s somewhat concerned about fluctuating investment values, so you could call her a balanced investor.

Retires in. Bonnie plans to retire in She s somewhat concerned about fluctuating investment values, so you could call her a balanced investor. Continuum risk-adjusted target date funds Investing in your retirement has never been easier with Continuum risk-adjusted target date funds. Think of risk-adjusted target date funds as a single-fund solution

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

CMGC Interim Pricing (OPCC) Milestone Process

CMGC Interim Pricing (OPCC) Milestone Process CMGC Interim Pricing (OPCC) Milestone Process Introduction and Purpose of this Document The purpose of this document is to outline MnDOT s process for validating CMGC pricing submitted by the CMGC Contractor

More information

GUIDANCE NOTE ASSET MANAGEMENT BY AUTHORIZED INSURERS

GUIDANCE NOTE ASSET MANAGEMENT BY AUTHORIZED INSURERS GN13 GUIDANCE NOTE ON ASSET MANAGEMENT BY AUTHORIZED INSURERS Office of the Commissioner of Insurance June 2004 GN13 Guidance Note on Asset Management By Authorized Insurers Table of Contents Page Preamble...

More information

RISK MITIGATION IN FAST TRACKING PROJECTS

RISK MITIGATION IN FAST TRACKING PROJECTS Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4

More information

Practical Issues arising from Valuation of Claims

Practical Issues arising from Valuation of Claims Practical Issues arising from Valuation of Claims Presented by KK Cheung and Joseph Chung, Partners of Deacons and Allen Lai, Senior Consultant of Charlton Martin Consultants Limited Presentation on 16

More information

Article 6 Modification and Termination of Contracts for Supplies and Services

Article 6 Modification and Termination of Contracts for Supplies and Services Article 6 Modification and Termination of Contracts for Supplies and Services 16601. Contract Clauses and their Administration 16601. Contract Clauses and their Administration. (a) Introduction. The following

More information

The future of life insurance, Solvency II and investment strategies

The future of life insurance, Solvency II and investment strategies KEYNOTE SPEECH Gabriel Bernardino Chairman of EIOPA The future of life insurance, Solvency II and investment strategies 11 th Handelsblatt Annual Conference Solvency II Munich, 15 July 2014 Page 2 of 9

More information

Introduction I The joint venture between Carillion (Qatar) LLC (a subsidiary of Carillion pie) and Qatar Building Company was selected and appointed to construct "Phase 1 B" of the Msheireb Downtown Doha

More information

Your Guide to the New Unfair Contract Terms Act

Your Guide to the New Unfair Contract Terms Act Your Guide to the New Unfair Contract Terms Act Prepared by Senior Partners of Holding Redlich, Scott Alden & Suzy Cairney Brought to you by: Standard contracts with small business soon to become voidable

More information

Construction Industry Council. Committee on Procurement

Construction Industry Council. Committee on Procurement Construction Industry Council Committee on Procurement The Meeting No. 003/09 of the Committee on Procurement was held on Thursday, 9 July 2009 at 2:30 pm at Room 1201, Murray Building, Garden Road, Central.

More information

RISKS AND RISK TREATMENTS IN PUBLIC PRIVATE PARTNERSHIP PROJECTS

RISKS AND RISK TREATMENTS IN PUBLIC PRIVATE PARTNERSHIP PROJECTS RISKS AND RISK TREATMENTS IN PUBLIC PRIVATE PARTNERSHIP PROJECTS Bing Li, A. Akintoye and C.Hardcastle School of Built and Natural Environment, Glasgow Caledonian University, Glasgow G4 0BA, UK Public

More information

Why an Independent UN Arbitration Tribunal for the Settlement of PPP Disputes is Necessary

Why an Independent UN Arbitration Tribunal for the Settlement of PPP Disputes is Necessary The article under is presented to the UNECE Secretariat and to the UNECE Team of Specialists on PPP S, by Dr. Wim A. Timmermans, Adv. (The Netherlands) and Mr. Assaf Behr, Adv. (Israel) Why an Independent

More information

Discussion Paper: Credit Hardship Obligations Outstanding Issues

Discussion Paper: Credit Hardship Obligations Outstanding Issues Mr Tim Gough Senior Manager Deposit Takers, Credit & Insurers Australian Securities and Investments Commission 120 Collins Street MELBOURNE VIC 3000 By email: Copy to: tim.gough@asic.gov.au rushika.curtis@asic.gov.au.

More information

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:

More information

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints None. Authoritative Guidance Summary 1. Cost Assurance and Analysis Service (CAAS) provide a range of services for the Defence Equipment

More information

Financing Terms. Guide to using Term Sheets Social Investment Toolkit Module 7. Version 1.0

Financing Terms. Guide to using Term Sheets Social Investment Toolkit Module 7. Version 1.0 Financing Terms Guide to using Term Sheets Social Investment Toolkit Module 7 Version 1.0 Content Overview 3 What is a Term Sheet? 4 How do you prepare a Term Sheet? 5 What is the format of a Term Sheet?

More information

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012 2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 3, Lesson 2 Contract Financing October 2017 CON170, Unit 3 Lesson 2 Contract Financing - Page 1 STUDENT PREPARATION Required Student Preparation

More information

TIME IS MONEY OR IS IT? (PART 2)

TIME IS MONEY OR IS IT? (PART 2) TIME IS MONEY OR IS IT? (PART 2) In Part 1 of this article we reviewed the legal and contractual principles which apply to the time for completion of construction works and the remedies available to both

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

BUILDING SOCIETIES PROVIDE SUPERIOR CUSTOMER SERVICE

BUILDING SOCIETIES PROVIDE SUPERIOR CUSTOMER SERVICE BUILDING SOCIETIES PROVIDE SUPERIOR CUSTOMER SERVICE Independent research commissioned by the BSA shows that building societies provide better service and satisfy their customers more than other financial

More information

Pest Control Services

Pest Control Services Pest Control Services Quotation #276 Issue Date: Friday, September 1, 2017 Jan Romer, Buyer Issued by: The Thames Valley District School Board Return Date: 4:00:00 pm, local time, Friday, September 15,

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

Frequently Asked Questions relating to MPF Products

Frequently Asked Questions relating to MPF Products Frequently Asked Questions Frequently Asked Questions relating to MPF Products This FAQ is prepared by the Investment Products Division of the Securities and Futures Commission (the Commission or SFC )

More information

Assessment of the suitability of the International Public Sector Accounting Standards (IPSASs) for the Member States

Assessment of the suitability of the International Public Sector Accounting Standards (IPSASs) for the Member States European Commission / EUROSTAT Public consultation Assessment of the suitability of the International Public Sector Accounting Standards (IPSASs) for the Member States CIPFA s response 11 May 2012 CIPFA,

More information

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge Against All Odds TE&A's Special Edition Issue by Clive Horridge Against All Odds by Clive Horridge Page 2 of 12 Not just a Phil Collins song-title depicting a common scenario of dispair, it is the case

More information

REQUEST FOR BID PROPOSALS

REQUEST FOR BID PROPOSALS REQUEST FOR BID PROPOSALS FOR EASTERN OREGON TRADE AND EVENT CENTER PROJECT BID ISSUANCE #8 LANDSCAPING AND IRRIGATION Hermiston, Oregon February 12, 2016 Eastern Oregon Trade and Event Center BID ISSUANCE

More information

Regulatory Impact Statement EXECUTIVE SUMMARY ADEQUACY STATEMENT STATUS QUO AND PROBLEM

Regulatory Impact Statement EXECUTIVE SUMMARY ADEQUACY STATEMENT STATUS QUO AND PROBLEM Regulatory Impact Statement EXECUTIVE SUMMARY Changes are proposed to Inland Revenue s administration of the student loan scheme to improve the overall integrity of the scheme, and reduce compliance costs

More information

NIRS 2: Contract extension

NIRS 2: Contract extension NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 LONDON: The Stationery Office 0.00 Ordered by the House of Commons to be printed on 12

More information

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 Appendix 4 to ESA ITT AO/1-8266/15/NL/MP Page 1/15 ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 [COVER LETTER] From:... (Tenderer to insert name of the company/institute

More information

Hong Kong Science & Technology Parks Corporation Request for Quotation on Direct Connectivity Service ( ) between HKSTP and PMC (Tai Po)

Hong Kong Science & Technology Parks Corporation Request for Quotation on Direct Connectivity Service ( ) between HKSTP and PMC (Tai Po) Hong Kong Science & Technology Parks Corporation Request for Quotation on Direct Connectivity Service (2017-19) between HKSTP and PMC (Tai Po) Hong Kong Science & Technology Parks Corporation (HKSTP) would

More information

A18 - Tendering Policy Authorised Reviewer: Head of Finance & Service Management

A18 - Tendering Policy Authorised Reviewer: Head of Finance & Service Management A18 - Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

Re: Public consultation: CSD s and Harmonisation of Securities Settlement

Re: Public consultation: CSD s and Harmonisation of Securities Settlement To: European Commission DG Markt G2 D(201) 8641 Rue de Spa Brussels BE 1049 by email to: markt-consultation-csd@ec.europa.eu March 1 st 2011 From: Omgeo Ltd 33 Aldgate High St London GB - EC3N 1DL For

More information

Discounting. Insurance IFRS Seminar Hong Kong, August 3, 2015 Eric Lu. Session 18

Discounting. Insurance IFRS Seminar Hong Kong, August 3, 2015 Eric Lu. Session 18 Discounting Insurance IFRS Seminar Hong Kong, August 3, 2015 Eric Lu Session 18 Background Liability = Assets Assets valued at market value (assumed) Fixed Income Asset market value = discounted cash flow

More information

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable

More information

A guide to how we manage our with profits fund

A guide to how we manage our with profits fund Contents Page 1 Useful terms 2 2 Principles and Practices of Financial Management 3 3 What is a with profits policy? 3 4 How do you decide how much to pay me? 4 5 How do you decide bonuses? 4 6 What is

More information

Conditions for the Carriage of Goods by Road

Conditions for the Carriage of Goods by Road Conditions for the Carriage of Goods by Road The Conditions set down the basis on which the Carrier will carry goods for the Customer (definitions of Carrier and Customer are given in Condition 1). The

More information