Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Size: px
Start display at page:

Download "Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong"

Transcription

1 Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager Mobile: January 2017

2 Note: This set of notes has been prepared according to the speaker s interpretation of the NEC and related documents and is intended for knowledge sharing purpose only. While every care has been taken in the assembly of this material, no responsibility for loss occasioned to any person acting or refraining from action occasioned by or as a result of any material included herein can be accepted by the speaker.

3

4

5 DEVB's website (for access by the construction industry stakeholders)

6 DevB Webpage:

7 Contents in the 120-pages PN Background Information (Chapters 1 3) Pre-Tender Stage (Chapter 4) Tender Stage (Chapter 5) Construction Stage (Chapter 6) Knowledge Sharing (Chapter 7) This 120-pages PN Part A (a living document) is for ECC only. There will be Part B and Part C for TSC and PSC.

8 Key Topics in Part A for ECC 1. Option selection A Partnering A Pain/Gain for target cost contracts A Pre-tender estimate, contingency and provisional sums A Tender documents set of standard documents such as amendments to the NEC clauses, ACC, etc. 6. Effective project management A6.1 to A Healthy financial management under target cost contracts A Cost control and corruption prevention for subcontracting A pages 9. Payment checking for target cost contracts A Equitable risk allocation and management of compensation events A CSD and alternative proposals A Performance benchmarking A Knowledge sharing 7

9 Coverage in this Seminar NEC provisions, highlights of the PN and common issues in the following aspects: Time (Programme) Subcontracting Payment Compensation event Specific issues encountered / anticipated by the participants

10 NEC provisions, PN Highlights and Common Issues TIME (PROGRAMME)

11 Time NEC Provisoins Cl. 31.1: Contractor submits a first programme; failing in submitting the first programme, 25% payment reduction (cl. 50.3) Cl. 31.2: Programme requirements (detailed requirements like float, time risk allowances, information from others etc.) Cl. 31.3: Project Manager has 2 weeks to accept the programme. If not accept, state reasons Cl. 32 Onerous requirement for the Contractor to revise the programme (prospective approach, no longer retrospective); failing in updating the programme, Project Manager s assessment of compensation event (cl. 64.2) Cl. 36 Acceleration Project Manager may instruct Contractor to submit quotation for acceleration to achieve Completion before the completion date

12 Time Cases for Discussion 1. Whether the Contractor s Programme should include time risk allowance for inclement weather? 2. Can the planned Completion shown in the Contractor s programme go beyond the completion date? 3. If the Contractor s programme shows a duration for design acceptance different from the period for reply as stated in the Contract Data, which duration prevails?

13 PN Highlights on Time Programme Acceptance: Better have an Accepted Programme in place, otherwise will become a compensation event (Cl (9) or Cl (6)), or the Project Manager to make his own assessment of compensation event(s) under Cl Programme meeting / workshop to ensure mutual understanding Detailed sub-programme for next 3 months or so Identify key changes in subsequent revised programmes Programme Register to trace changes of planned Completion and Completion Date

14 NEC provisions, PN Highlights and Common Issues SUBCONTRACTING

15 Subcontracting NEC Provisions Cl. 26.1: If a Contractor subcontracts works, he is responsible for Providing the Works as if he had not subcontracted Cl. 26.2: Contractor submits the name of each proposed Subcontractor Cl. 26.3: Contractor submits the proposed conditions of contract for each subcontract The Contractor does not appoint a Subcontractor until the Project Manager has accepted them.

16 PN Highlights on Subcontracting Clause 26 (with amendments) should be followed Clause C9 of the standard additional conditions of contract sets out the tender requirements for subcontracting for Options C & D and for compensation events under Options A & B Should not prevent the appointment of any proposed Subcontractor on unreasonable grounds Project Manager should attend pre-tender meetings 2-stage selection process with alternative designs can be accepted Ensure competitive tender Declaration of no linkage Qualification of tender is not accepted; clarification is needed if there is different interpretation

17 PN Highlights on Subcontracting If insufficient number of return tenders, Project Manager should make decision within three weeks If not the lowest tender is proposed, Project Manager should make decision within three weeks Practices to ensure a smooth subcontracting process Benefits from early Project Manager s involvement in the subcontracting process Involve Subcontractors in regular meetings during construction Finalize subcontracts as soon as possible Discuss whether new Subcontractors will be invited for compensation events with reasons; if yes, clauses C9 and C11 of the standard additional conditions of contract should be followed

18 Subcontracting Cases for Discussion 4. Will a design consultant be treated as a subcontractor in target cost? How the design fee be recovered Defined Cost or Fee? 5. Whether the Contractor should follow the subcontracting or procurement procedures for works / services required at early construction stage such as hoarding erection, security? 6. Can the Project Manager accept Subcontractor whose tender return price is not the lowest? 7. If the accepted Subcontractor quits, does a retender process require or the 2 nd lowest tender can be proposed?

19 NEC provisions, PN Highlights and Common Issues PAYMENT

20 Payment NEC Provisions Clause 1 definition of terms (PWDD, Fee, Defined Cost, etc.) Clause 5 payment process (payment applications [as amended], payment assessment, payment date, etc.) X1 Price adjustment for inflation X6 Bonus for Early Completion X7 Delay Damages X14 Advanced payment to the Contractor X16 Retention X17 Low performance damages X20 Key performance indicators

21 PN Highlights on Payment Project Manager decides the first assessment date (clause 50.1) PAH 25-day rule payment to the Contractor within 25 days from the assessment date for contracts using NEC Clause 51.2 each certified payment is made within three weeks of the assessment date or, if a different period stated in the Contract Data, within the period stated Interest not for corrected amounts in later certificates due to compensation event or other reasons (clause 51.3 [as amended]) X1 Price Adjustment for Inflation X1.4 for Options A & B and X1.5 for Options C & D A total of 34 pages (out of 120) on checking of payments covering: Start-up procedures Checklists

22 Payment Cases for Discussion 8. There were confusion in payment related to People since the definition has been amended to exclude management and supervisory staff : Is a land surveying team entitled for payment under People of the Schedule of Cost Components [as amended]? Is a procurement team classified as management and supervisory staff? Is the MPF for management and supervisory staff part of the amount due? 9. Are performance tied payments in X20 subject to retention (X16)? 10. Item 23 of the Schedule of Cost Components is deleted. Will the Contractor be entitled for full payment of the purchased Equipment?

23 NEC provisions, PN Highlights and Common Issues COMPENSATION EVENT

24 Compensation Event NEC Provisions Cl lists 19 situations which are compensation events if happen Cl lists Employer s risks Clauses 61 to 65 set out procedures in handling compensation events

25 Compensation Event NEC Provisions

26 Compensation Events Cl (13): Weather measurement worse than that once in ten years (but has been amended to:) One or more of the following weather conditions: (i) the hoisting of tropical cyclone warning signal No. 8 or above, or (ii) Black Rainstorm Warning, or (iii) Red Rainstorm Warning, or (iv) Amber Rainstorm Warning, or (v) inclement weather and/or its consequences adversely affecting the progress of the works.

27 Compensation Events Cl (20): A Change in Law as defined in Clause [A1] of the additional conditions of contract. (21): A shortage of labour which would have been unreasonable for an experienced Contractor to have allowed for at the tender closing date.

28 PN s Highlights on Compensation Event Amendment to cl time only Weather (cl. 60.1(13)) time only for A & B Unforeseen physical conditions (cl. 60.1(12)) difference from the Site Information (cl. 60.2) Shortage of labour (cl. 60.1(21)) time only Utility interface (cl. 60.1(5)) time only Change in law (cl. 60.1(20)) as stated in additional conditions of contract A1; X2 not used Prevention (cl. 60.1(19)) time only Change to the Works Information (cl. 60.1(1)) similar to variations ; not applicable to Contractor s design Correction to an assumption of a compensation event (cl. 60.1(17)) assumption made by PM only Delay by the Employer or Others (cl. 60.1(2) or (5)) time only Failure to respond (cl. 60.1(6)) Contractor s design, subcontractors procurement Change in quantities (cl to 60.6) re-measurement record Assessment of prolongation costs time-related resources; to be established early

29 Compensation Event Delegate s authority up to HK$300,000 Talk before submission in view of PM s authority Cl effect of compensation event Defined Cost plus Fee; cl Contractor s risk For Options A & B rates or lump sums can be used if agreed but not subject to fee percentage Assessment should be properly documented in the Project Office for audit Programme update Changes to the Activity Schedule (cl. 54.2) payment follows the adjusted Activity Schedule

30 Compensation Event Cases for Discussion 11. EPD s notification of increasing the waste disposal charges in August 2016: Is this a compensation event? Such increase does not cause additional resources in the physical works. Does the Employer need to pay Contractor the Fee? 12. What if Subcontractors quotations for compensation events do not follow the NEC s approach, i.e. not use the Schedule (or Shorter Schedule) of Cost Components?

31 GROUP SHARING

32 Thank you

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald Housekeeping Safety Facilities 2

More information

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4 Engineering and Construction Contract review of changes from NEC3 Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main

More information

Form of Agreement Between the Client And the Quantity Surveyor

Form of Agreement Between the Client And the Quantity Surveyor Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

NEC 3: How to claim as the main

NEC 3: How to claim as the main SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced

More information

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/ MOMBASA Beach Hotel NGULIA Safari Lodge VOI Safari Lodge KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/2017-2018 KENYA

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

Professional Services Contract

Professional Services Contract Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing

More information

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

Webinar - The Project Manager in the NEC4 ECC: What s new and different? Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed

More information

Public Private Partnerships (PPPs) Projects

Public Private Partnerships (PPPs) Projects Development Process of Public Private Partnerships (PPPs) Projects By Dr Paul H K Ho 1 Disclaimer Funded by Commerce, Industry and Technology Bureau, The Government of the Hong Kong Special Administrative

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising)

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Making and defending claims Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Public Works Contracts Dealing with Change Introduction Minimising Change Schedule

More information

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. TENDER NO. TCG/F&P/5/2017-2018 SEPTEMBER 2017 TABLE OF CONTENTS

More information

TRADING PROCEDURES FOR METAL FUTURES TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents

TRADING PROCEDURES FOR METAL FUTURES TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents TRADING PROCEDURES FOR METAL FUTURES TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents CHAPTER 1 TRADING Page 1.1 Method of Trading... 1-1 CHAPTER 2 ELIGIBILITY TO TRADE

More information

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1 CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General

More information

COUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES

COUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES COUNTY GOVERNMENT OF NYERI DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT PROPOSED CONSTRUCTION OF GUMBA GICHAGI FOOTBRIDGE IN RUGI WARD CGN/INF/62/16-17 BILLS OF QUANTITIES ISSUED BY: COUNTY WORKS OFFICER COUNTY

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

Subcontract Agreement

Subcontract Agreement Subcontract Agreement SA - 2009 Project: Trade: Subcontractor: SA - 2009 Number: FOREWORD A good working relationship between the Contractor and Subcontractor is critical to ensuring construction projects

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

NEC4 Key Commercial Changes

NEC4 Key Commercial Changes NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

Construction Law Update The NEC4 suite of contracts are here!

Construction Law Update The NEC4 suite of contracts are here! Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411

More information

Subcontract agreement

Subcontract agreement Subcontract agreement SA - 2017 Project: Trade: Subcontractor: Reference: FOREWORD to SA-2017 SA-2009 was a historic collaboration between parties representing builders and subcontractors to produce a

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Unpacking framework agreements for the delivery and maintenance of infrastructure

Unpacking framework agreements for the delivery and maintenance of infrastructure Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or

More information

APPLICATION FORM FOR ASHK EXAMINATION (MAY 2019)

APPLICATION FORM FOR ASHK EXAMINATION (MAY 2019) THE ACTUARIAL SOCIETY OF HONG KONG 1803 Tower One, Lippo Centre, 89 Queensway, Hong Kong Tel: (852) 2147 9278 Fax: (852) 2147 2497 Website: www.actuaries.org.hk Email: info@actuaries.org.hk APPLICATION

More information

REPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY

REPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY REPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY TENDER DOCUMENTS (Main Works) W.P ITEM NO. D111/RV/BOT/1501 JOB NO.10053A

More information

The NEC 3 Engineering and Construction Contract

The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston

More information

Procedure for Electronic Bid Submission

Procedure for Electronic Bid Submission Procedure for Electronic Bid Submission Tendering Procedures, Requirements and Materials The following tendering procedures shall apply to the purchase of Goods and/or Services in an amount estimated to

More information

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated

More information

HKIS Resolving Disputes between Contractors

HKIS Resolving Disputes between Contractors HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com

More information

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT 1. Definition and Duration These conditions form part of a quotation submitted by the Contractor to the Client named in the quotation. The Contractor

More information

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable

More information

SURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS

SURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALSS BK SURCO Limited Suite 1901-2, 19 th Floor, Hopewell Centre 183 Queen s Road

More information

Commercial (QS) Core Competencies (Feb 17)

Commercial (QS) Core Competencies (Feb 17) 01 Financial and commercial processes in civil engineering Optimum Activity Detail of A K E Management of budgets for civil engineering works. Cost forecasting, management and control processes including

More information

TRADING PROCEDURES FOR STOCK INDEX FUTURES AND STOCK INDEX OPTIONS TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS )

TRADING PROCEDURES FOR STOCK INDEX FUTURES AND STOCK INDEX OPTIONS TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) TRADING PROCEDURES FOR STOCK INDEX FUTURES AND STOCK INDEX OPTIONS TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents Page CHAPTER 1 METHOD OF TRADING... 1-1 CHAPTER 2 ELIGIBILITY

More information

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) Ref: W/RFQ-GCC GENERAL CONDITIONS OF CONTRACT REQUEST FOR QUOTATION [Issued in terms of section

More information

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU COUNTY GOVERNMENT OF KIAMBU DIRECTORATE OF PUBLIC WORKS PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU AT TENDER NO. KCG/YASC/STADIUM/001/2015/2016 TENDER DOCUMENTS ISSUED BY: PREPARED/CHECKED

More information

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU COUNTY GOVERNMENT OF KIAMBU DIRECTORATE OF PUBLIC WORKS PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU AT TENDER NO. KCG/YASC/STADIUM/005/2015/2016 TENDER DOCUMENTS ISSUED BY: PREPARED/CHECKED

More information

BK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS

BK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALS Extensions of Time Valuation of Variations Bonds, Guarantees, Collateral Warranties

More information

SCHEDULE 1 CHANGE ORDERS

SCHEDULE 1 CHANGE ORDERS SCHEDULE 1 CHANGE ORDERS SCHEDULE 1 DBFM AGREEMENT 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and

More information

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT) Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the

More information

2 The Contractor s main responsibilities

2 The Contractor s main responsibilities Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor

More information

ANNEX VIII a STANDARD FORMATS AND TEMPLATES

ANNEX VIII a STANDARD FORMATS AND TEMPLATES ANNEX VIII a STANDARD FORMATS AND TEMPLATES STANDARD BID EVALUATION FORMAT FOR THE PROCUREMENT OF GOODS 1 Preface 1. This standard tender evaluation format for the procurement of Goods has been prepared

More information

REPUBLIC OF KENYA MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN DEVELOPMENT

REPUBLIC OF KENYA MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN DEVELOPMENT REPUBLIC OF KENYA MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN DEVELOPMENT STATE DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT PROPOSED CIVIL SERVANTS HOUSING SCHEME AT EMBU TOWN, EMBU COUNTY

More information

CHAPTER 1 25 INTRODUCTION

CHAPTER 1 25 INTRODUCTION CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time

More information

STANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS)

STANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS) STANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS) National Competitive Tendering (NCT) VOLUME I Tender Reference:. Issue Date: Day/Month/Year Public Procurement Authority Accra, Ghana

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

Sheila Belayutham CHAPTER 6 CONTROL

Sheila Belayutham CHAPTER 6 CONTROL CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s

More information

Purchasing Procedures Manual

Purchasing Procedures Manual Purchasing Procedures Manual March 2014 Table of Contents Purchases of Goods, Equipment and Services... 1 Appendix A - Purchasing Methods Introduction... A - 1 General Purchasing Requirements... A - 3

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

AIRPORT AUTHORITY HONG KONG

AIRPORT AUTHORITY HONG KONG AIRPORT AUTHORITY HONG KONG GENERAL CONDITIONS OF CONTRACT BUILDING AND CIVIL WORKS ISSUE NO. 10 August 2011 [this page not used] GENERAL CONDITIONS OF CONTRACT FOR BUILDING AND CIVIL WORKS TABLE OF CONTENTS

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),

More information

Contract [Number] [Contract Name] Contract Documents. Minor Works / Direct Appoint

Contract [Number] [Contract Name] Contract Documents. Minor Works / Direct Appoint Contract [Number] [Contract Name] Contract Documents Minor Works / Direct Appoint This proforma document provides the basis for the development of physical works contract documents for the Transport Agency

More information

Workshop 4 FIDIC Contracts (Update on New Documents)

Workshop 4 FIDIC Contracts (Update on New Documents) Workshop 4 FIDIC Contracts (Update on New Documents) Employer s New Obstacle: Commencement Date and Related Clauses Dr.Sarwono Hardjomuljadi Tuesday, 04 October 2011, 14.00 15.30 Employer s New Obstacle:

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with

More information

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017 BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable

More information

Terms and Conditions

Terms and Conditions Terms and Conditions SERVICES Taking such steps as are reasonable to enable MFA to be satisfied within the limits of the professional skill and care set out in clause 2-1 that the plans and works comply

More information

Any additional services not detailed in the Quotation, and the price is subject to variation to take account of changes in any exclusions.

Any additional services not detailed in the Quotation, and the price is subject to variation to take account of changes in any exclusions. STANDARD TERMS & CONDITIONS for QUOTATIONS. Bitu-mill (Road Maintenance) Pty Ltd, Bitu-mill (Civil) Pty Ltd, Bitu-mill Services Pty Ltd and Bitu-mill Equipment Pty Ltd ( Bitu-mill ) These terms and conditions

More information

[Project Name] NZTA Contract No. [Contract Number] Conditions of Contract

[Project Name] NZTA Contract No. [Contract Number] Conditions of Contract [Project Name] NZTA Contract No. [Contract Number] DOCUMENT CHANGE FORMAT CODES This proforma document provides the basis for the development of physical works contract

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Please note that this comparison is for guidance only and does not purport to be complete and exhaustive. All corrections and improvements

More information

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012 2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management

More information

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch / Framework agreements The Standard for Infrastructure Procurement and Delivery Management includes provisions for framework agreements. Framework agreements have similarities with term service and transversal

More information

Cl Offence Individual Corporation

Cl Offence Individual Corporation Attachment 1: Contracting Party's Offences & Penalties Cl Offence Individual Corporation 21(4) Failure to inform the principal and commissioner (in the approved form) within 5 business days of entering

More information

LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK. Michele Cyna

LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK. Michele Cyna October I992 Transport No. RD-12 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK Michele Cyna Delays in the completion

More information

FIDIC WORKSHOP 2016 GROUP 6

FIDIC WORKSHOP 2016 GROUP 6 FIDIC WORKSHOP 2016 GROUP 6 QUESTION 1 WHAT ARE THE ESSENTIAL REQUIREMENTS FOR FORMATION OF CONTRACT? DISCUSS WHETHER A BINDING AND ENFORCEABLE CONTRACT HAS BEEN CONCLUDED BETWEEN JOLLY AND CAN-DO. 1.

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 INTRODUCTION TO THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki

More information

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice

More information

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:

More information

Risk Management. Financial Risk. Asset and liability management

Risk Management. Financial Risk. Asset and liability management Risk Management CITIC Limited has established a risk management and internal control system covering all business segments to identify, assess and manage various risks in the Group s business activities.

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES INVITATION FOR QUOTATIONS FOR CONSTRUCTION OF CIVIL WORKS UNDER SHOPPING PROCEDURES To Dear Sirs, Sub : INVITATION FOR QUOTATIONS FOR CONSTRUCTION

More information

September 2017 CONSULTATION PAPER DELISTING AND OTHER RULE AMENDMENTS

September 2017 CONSULTATION PAPER DELISTING AND OTHER RULE AMENDMENTS September 2017 CONSULTATION PAPER DELISTING AND OTHER RULE AMENDMENTS CONTENTS Page No. EXECUTIVE SUMMARY 1 CHAPTER 1: INTRODUCTION 2 CHAPTER 2: LONG SUSPENSION, DELISTING FRAMEWORK AND PROPOSED RULE AMENDMENTS

More information

THE HONG KONG INSTITUTE OF SURVEYORS

THE HONG KONG INSTITUTE OF SURVEYORS PART II ASSESSMENT 2013 DAY 2 Wednesday, 18 th September, 2013 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main

More information

ANNEX VIII b STANDARD FORMATS AND TEMPLATES

ANNEX VIII b STANDARD FORMATS AND TEMPLATES ANNEX VIII b STANDARD FORMATS AND TEMPLATES STANDARD BID EVALUATION FORMAT FOR THE PROCUREMENT OF CIVIL WORKS 1 Preface 1. This standard tender evaluation format for the procurement of Civil Works has

More information

AMENDMENTS APRIL 2013

AMENDMENTS APRIL 2013 AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The

More information

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals GENERAL CONDITIONS 1 GENERAL PROVISIONS.................................... 1 1.1 Definitions The Contract Persons Dates, Times and Periods Money and Payments Other Definitions 1.2 Interpretation 1.3 Priority

More information

GOVERNMENT OF KARNATAKA

GOVERNMENT OF KARNATAKA Annexure I K/W-1 GOVERNMENT OF KARNATAKA -------------------------------------------------- (Name of Organization) ------------------------------------------------ ----------------------------------------------

More information

Off-Site Manufacturing

Off-Site Manufacturing Off-Site Manufacturing The Legal Implications YORhub Conference 15 th November 2018 Dr Julie Morrissy A word of warning MODERNISE OR DIE 1 Modernise or die 2016 - The Farmer Review of the UK Construction

More information

Case study: Delivering the first phase of two new universities for the South African government. Dr Ron Watermeyer Spencer Hodgson

Case study: Delivering the first phase of two new universities for the South African government. Dr Ron Watermeyer Spencer Hodgson Case study: Delivering the first phase of two new universities for the South African government Dr Ron Watermeyer Spencer Hodgson Wits capital projects programme Started 2007 Refurbishment of old buildings

More information

Hang Seng MPF. Annual Member Newsletter. Hang Seng MPF Service Hotline Hang Seng MPF website hangseng.com/empf August 2014

Hang Seng MPF. Annual Member Newsletter. Hang Seng MPF Service Hotline Hang Seng MPF website hangseng.com/empf August 2014 Hang Seng MPF Annual Member Newsletter 2014 8 August 2014 Hang Seng MPF website hangseng.com/empf Hang Seng MPF Service Hotline 2213 2213 Important notes The Hang Seng Mandatory Provident Fund SuperTrust,

More information

Proposal Adequacy Checklist

Proposal Adequacy Checklist The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror s checklist,

More information

SUPPLY of LED POWER LIGHTS WITH STAND FOR THE GOVERNMENT FILM UNIT

SUPPLY of LED POWER LIGHTS WITH STAND FOR THE GOVERNMENT FILM UNIT SUPPLY of LED POWER LIGHTS WITH STAND FOR THE GOVERNMENT FILM UNIT BIDDING DOCUMENT DEPARTMENT OF GOVERNMENT INFORMATION BID No: DI/PRO/04/19/2016/TEC 05 Bids will be closed at 1100 hours on.01.08.2018

More information

RESULTS OF THE 2011 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MARCH Prepared by: Prof. HJ Marx

RESULTS OF THE 2011 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MARCH Prepared by: Prof. HJ Marx RESULTS OF THE 2011 SURVEY OF THE cidb CONSTRUCTION INDUSTRY INDICATORS MARCH 2012 Prepared by: Prof. HJ Marx of Quantity Surveying and Construction Management University of the Free State marxhj@ufs.ac.za

More information