Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong
|
|
- Trevor Martin
- 5 years ago
- Views:
Transcription
1 Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager Mobile: January 2017
2 Note: This set of notes has been prepared according to the speaker s interpretation of the NEC and related documents and is intended for knowledge sharing purpose only. While every care has been taken in the assembly of this material, no responsibility for loss occasioned to any person acting or refraining from action occasioned by or as a result of any material included herein can be accepted by the speaker.
3
4
5 DEVB's website (for access by the construction industry stakeholders)
6 DevB Webpage:
7 Contents in the 120-pages PN Background Information (Chapters 1 3) Pre-Tender Stage (Chapter 4) Tender Stage (Chapter 5) Construction Stage (Chapter 6) Knowledge Sharing (Chapter 7) This 120-pages PN Part A (a living document) is for ECC only. There will be Part B and Part C for TSC and PSC.
8 Key Topics in Part A for ECC 1. Option selection A Partnering A Pain/Gain for target cost contracts A Pre-tender estimate, contingency and provisional sums A Tender documents set of standard documents such as amendments to the NEC clauses, ACC, etc. 6. Effective project management A6.1 to A Healthy financial management under target cost contracts A Cost control and corruption prevention for subcontracting A pages 9. Payment checking for target cost contracts A Equitable risk allocation and management of compensation events A CSD and alternative proposals A Performance benchmarking A Knowledge sharing 7
9 Coverage in this Seminar NEC provisions, highlights of the PN and common issues in the following aspects: Time (Programme) Subcontracting Payment Compensation event Specific issues encountered / anticipated by the participants
10 NEC provisions, PN Highlights and Common Issues TIME (PROGRAMME)
11 Time NEC Provisoins Cl. 31.1: Contractor submits a first programme; failing in submitting the first programme, 25% payment reduction (cl. 50.3) Cl. 31.2: Programme requirements (detailed requirements like float, time risk allowances, information from others etc.) Cl. 31.3: Project Manager has 2 weeks to accept the programme. If not accept, state reasons Cl. 32 Onerous requirement for the Contractor to revise the programme (prospective approach, no longer retrospective); failing in updating the programme, Project Manager s assessment of compensation event (cl. 64.2) Cl. 36 Acceleration Project Manager may instruct Contractor to submit quotation for acceleration to achieve Completion before the completion date
12 Time Cases for Discussion 1. Whether the Contractor s Programme should include time risk allowance for inclement weather? 2. Can the planned Completion shown in the Contractor s programme go beyond the completion date? 3. If the Contractor s programme shows a duration for design acceptance different from the period for reply as stated in the Contract Data, which duration prevails?
13 PN Highlights on Time Programme Acceptance: Better have an Accepted Programme in place, otherwise will become a compensation event (Cl (9) or Cl (6)), or the Project Manager to make his own assessment of compensation event(s) under Cl Programme meeting / workshop to ensure mutual understanding Detailed sub-programme for next 3 months or so Identify key changes in subsequent revised programmes Programme Register to trace changes of planned Completion and Completion Date
14 NEC provisions, PN Highlights and Common Issues SUBCONTRACTING
15 Subcontracting NEC Provisions Cl. 26.1: If a Contractor subcontracts works, he is responsible for Providing the Works as if he had not subcontracted Cl. 26.2: Contractor submits the name of each proposed Subcontractor Cl. 26.3: Contractor submits the proposed conditions of contract for each subcontract The Contractor does not appoint a Subcontractor until the Project Manager has accepted them.
16 PN Highlights on Subcontracting Clause 26 (with amendments) should be followed Clause C9 of the standard additional conditions of contract sets out the tender requirements for subcontracting for Options C & D and for compensation events under Options A & B Should not prevent the appointment of any proposed Subcontractor on unreasonable grounds Project Manager should attend pre-tender meetings 2-stage selection process with alternative designs can be accepted Ensure competitive tender Declaration of no linkage Qualification of tender is not accepted; clarification is needed if there is different interpretation
17 PN Highlights on Subcontracting If insufficient number of return tenders, Project Manager should make decision within three weeks If not the lowest tender is proposed, Project Manager should make decision within three weeks Practices to ensure a smooth subcontracting process Benefits from early Project Manager s involvement in the subcontracting process Involve Subcontractors in regular meetings during construction Finalize subcontracts as soon as possible Discuss whether new Subcontractors will be invited for compensation events with reasons; if yes, clauses C9 and C11 of the standard additional conditions of contract should be followed
18 Subcontracting Cases for Discussion 4. Will a design consultant be treated as a subcontractor in target cost? How the design fee be recovered Defined Cost or Fee? 5. Whether the Contractor should follow the subcontracting or procurement procedures for works / services required at early construction stage such as hoarding erection, security? 6. Can the Project Manager accept Subcontractor whose tender return price is not the lowest? 7. If the accepted Subcontractor quits, does a retender process require or the 2 nd lowest tender can be proposed?
19 NEC provisions, PN Highlights and Common Issues PAYMENT
20 Payment NEC Provisions Clause 1 definition of terms (PWDD, Fee, Defined Cost, etc.) Clause 5 payment process (payment applications [as amended], payment assessment, payment date, etc.) X1 Price adjustment for inflation X6 Bonus for Early Completion X7 Delay Damages X14 Advanced payment to the Contractor X16 Retention X17 Low performance damages X20 Key performance indicators
21 PN Highlights on Payment Project Manager decides the first assessment date (clause 50.1) PAH 25-day rule payment to the Contractor within 25 days from the assessment date for contracts using NEC Clause 51.2 each certified payment is made within three weeks of the assessment date or, if a different period stated in the Contract Data, within the period stated Interest not for corrected amounts in later certificates due to compensation event or other reasons (clause 51.3 [as amended]) X1 Price Adjustment for Inflation X1.4 for Options A & B and X1.5 for Options C & D A total of 34 pages (out of 120) on checking of payments covering: Start-up procedures Checklists
22 Payment Cases for Discussion 8. There were confusion in payment related to People since the definition has been amended to exclude management and supervisory staff : Is a land surveying team entitled for payment under People of the Schedule of Cost Components [as amended]? Is a procurement team classified as management and supervisory staff? Is the MPF for management and supervisory staff part of the amount due? 9. Are performance tied payments in X20 subject to retention (X16)? 10. Item 23 of the Schedule of Cost Components is deleted. Will the Contractor be entitled for full payment of the purchased Equipment?
23 NEC provisions, PN Highlights and Common Issues COMPENSATION EVENT
24 Compensation Event NEC Provisions Cl lists 19 situations which are compensation events if happen Cl lists Employer s risks Clauses 61 to 65 set out procedures in handling compensation events
25 Compensation Event NEC Provisions
26 Compensation Events Cl (13): Weather measurement worse than that once in ten years (but has been amended to:) One or more of the following weather conditions: (i) the hoisting of tropical cyclone warning signal No. 8 or above, or (ii) Black Rainstorm Warning, or (iii) Red Rainstorm Warning, or (iv) Amber Rainstorm Warning, or (v) inclement weather and/or its consequences adversely affecting the progress of the works.
27 Compensation Events Cl (20): A Change in Law as defined in Clause [A1] of the additional conditions of contract. (21): A shortage of labour which would have been unreasonable for an experienced Contractor to have allowed for at the tender closing date.
28 PN s Highlights on Compensation Event Amendment to cl time only Weather (cl. 60.1(13)) time only for A & B Unforeseen physical conditions (cl. 60.1(12)) difference from the Site Information (cl. 60.2) Shortage of labour (cl. 60.1(21)) time only Utility interface (cl. 60.1(5)) time only Change in law (cl. 60.1(20)) as stated in additional conditions of contract A1; X2 not used Prevention (cl. 60.1(19)) time only Change to the Works Information (cl. 60.1(1)) similar to variations ; not applicable to Contractor s design Correction to an assumption of a compensation event (cl. 60.1(17)) assumption made by PM only Delay by the Employer or Others (cl. 60.1(2) or (5)) time only Failure to respond (cl. 60.1(6)) Contractor s design, subcontractors procurement Change in quantities (cl to 60.6) re-measurement record Assessment of prolongation costs time-related resources; to be established early
29 Compensation Event Delegate s authority up to HK$300,000 Talk before submission in view of PM s authority Cl effect of compensation event Defined Cost plus Fee; cl Contractor s risk For Options A & B rates or lump sums can be used if agreed but not subject to fee percentage Assessment should be properly documented in the Project Office for audit Programme update Changes to the Activity Schedule (cl. 54.2) payment follows the adjusted Activity Schedule
30 Compensation Event Cases for Discussion 11. EPD s notification of increasing the waste disposal charges in August 2016: Is this a compensation event? Such increase does not cause additional resources in the physical works. Does the Employer need to pay Contractor the Fee? 12. What if Subcontractors quotations for compensation events do not follow the NEC s approach, i.e. not use the Schedule (or Shorter Schedule) of Cost Components?
31 GROUP SHARING
32 Thank you
Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)
NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session
More informationENGINEERING AND CONSTRUCTION CONTRACT
THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation
More informationExperience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement
Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting
More informationNEC3 ECC Introductory Training
NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:
More informationCHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016
CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,
More informationNEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012
NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald Housekeeping Safety Facilities 2
More informationNEC4 Engineering and Construction Contract review of changes from NEC3
Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main
More informationForm of Agreement Between the Client And the Quantity Surveyor
Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.
More informationStandard forms of partnering contracts The ultimate contractual commitment? Part 4
Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard
More informationNEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date
NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated
More informationCommon Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council
Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract
More informationConstruction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager
London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner
More informationNEC 3: How to claim as the main
SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced
More informationKENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/
MOMBASA Beach Hotel NGULIA Safari Lodge VOI Safari Lodge KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/2017-2018 KENYA
More informationNEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage
NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project
More informationProfessional Services Contract
Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing
More informationWebinar - The Project Manager in the NEC4 ECC: What s new and different?
Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed
More informationPublic Private Partnerships (PPPs) Projects
Development Process of Public Private Partnerships (PPPs) Projects By Dr Paul H K Ho 1 Disclaimer Funded by Commerce, Industry and Technology Bureau, The Government of the Hong Kong Special Administrative
More informationNEC3 ECC target contract option principles and innovative applications
INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract
More informationSpeaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising)
Making and defending claims Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Public Works Contracts Dealing with Change Introduction Minimising Change Schedule
More informationREPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.
REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. TENDER NO. TCG/F&P/5/2017-2018 SEPTEMBER 2017 TABLE OF CONTENTS
More informationTRADING PROCEDURES FOR METAL FUTURES TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents
TRADING PROCEDURES FOR METAL FUTURES TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents CHAPTER 1 TRADING Page 1.1 Method of Trading... 1-1 CHAPTER 2 ELIGIBILITY TO TRADE
More informationCONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1
CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General
More informationCOUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES
COUNTY GOVERNMENT OF NYERI DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT PROPOSED CONSTRUCTION OF GUMBA GICHAGI FOOTBRIDGE IN RUGI WARD CGN/INF/62/16-17 BILLS OF QUANTITIES ISSUED BY: COUNTY WORKS OFFICER COUNTY
More informationNEC4 ENGINEERING & CONSTRUCTION CONTRACT
1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box
More informationSubcontract Agreement
Subcontract Agreement SA - 2009 Project: Trade: Subcontractor: SA - 2009 Number: FOREWORD A good working relationship between the Contractor and Subcontractor is critical to ensuring construction projects
More informationSection 7. General Conditions of Contract for the Procurement of Works
Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5
More informationNEC4 Key Commercial Changes
NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County
More informationPeter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.
CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC
More informationConstruction Law Update The NEC4 suite of contracts are here!
Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411
More informationSubcontract agreement
Subcontract agreement SA - 2017 Project: Trade: Subcontractor: Reference: FOREWORD to SA-2017 SA-2009 was a historic collaboration between parties representing builders and subcontractors to produce a
More informationMDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
More informationUnpacking framework agreements for the delivery and maintenance of infrastructure
Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or
More informationAPPLICATION FORM FOR ASHK EXAMINATION (MAY 2019)
THE ACTUARIAL SOCIETY OF HONG KONG 1803 Tower One, Lippo Centre, 89 Queensway, Hong Kong Tel: (852) 2147 9278 Fax: (852) 2147 2497 Website: www.actuaries.org.hk Email: info@actuaries.org.hk APPLICATION
More informationREPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY
REPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY TENDER DOCUMENTS (Main Works) W.P ITEM NO. D111/RV/BOT/1501 JOB NO.10053A
More informationThe NEC 3 Engineering and Construction Contract
The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston
More informationProcedure for Electronic Bid Submission
Procedure for Electronic Bid Submission Tendering Procedures, Requirements and Materials The following tendering procedures shall apply to the purchase of Goods and/or Services in an amount estimated to
More informationNEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.
Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and
More informationThe following amendments have been made to the June 2005 edition deleted: and of notified early warning matters
AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated
More informationHKIS Resolving Disputes between Contractors
HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com
More informationGENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT
GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT 1. Definition and Duration These conditions form part of a quotation submitted by the Contractor to the Client named in the quotation. The Contractor
More informationThe NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister
The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable
More informationSURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS
BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALSS BK SURCO Limited Suite 1901-2, 19 th Floor, Hopewell Centre 183 Queen s Road
More informationCommercial (QS) Core Competencies (Feb 17)
01 Financial and commercial processes in civil engineering Optimum Activity Detail of A K E Management of budgets for civil engineering works. Cost forecasting, management and control processes including
More informationTRADING PROCEDURES FOR STOCK INDEX FUTURES AND STOCK INDEX OPTIONS TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS )
TRADING PROCEDURES FOR STOCK INDEX FUTURES AND STOCK INDEX OPTIONS TRADED ON THE AUTOMATED TRADING SYSTEM OF THE EXCHANGE ( HKATS ) Table of Contents Page CHAPTER 1 METHOD OF TRADING... 1-1 CHAPTER 2 ELIGIBILITY
More informationMINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)
MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) Ref: W/RFQ-GCC GENERAL CONDITIONS OF CONTRACT REQUEST FOR QUOTATION [Issued in terms of section
More informationPROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU
COUNTY GOVERNMENT OF KIAMBU DIRECTORATE OF PUBLIC WORKS PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU AT TENDER NO. KCG/YASC/STADIUM/001/2015/2016 TENDER DOCUMENTS ISSUED BY: PREPARED/CHECKED
More informationPROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU
COUNTY GOVERNMENT OF KIAMBU DIRECTORATE OF PUBLIC WORKS PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU AT TENDER NO. KCG/YASC/STADIUM/005/2015/2016 TENDER DOCUMENTS ISSUED BY: PREPARED/CHECKED
More informationBK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS
BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALS Extensions of Time Valuation of Variations Bonds, Guarantees, Collateral Warranties
More informationSCHEDULE 1 CHANGE ORDERS
SCHEDULE 1 CHANGE ORDERS SCHEDULE 1 DBFM AGREEMENT 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and
More informationreads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)
Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the
More information2 The Contractor s main responsibilities
Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor
More informationANNEX VIII a STANDARD FORMATS AND TEMPLATES
ANNEX VIII a STANDARD FORMATS AND TEMPLATES STANDARD BID EVALUATION FORMAT FOR THE PROCUREMENT OF GOODS 1 Preface 1. This standard tender evaluation format for the procurement of Goods has been prepared
More informationREPUBLIC OF KENYA MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN DEVELOPMENT
REPUBLIC OF KENYA MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN DEVELOPMENT STATE DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT PROPOSED CIVIL SERVANTS HOUSING SCHEME AT EMBU TOWN, EMBU COUNTY
More informationCHAPTER 1 25 INTRODUCTION
CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time
More informationSTANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS)
STANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS) National Competitive Tendering (NCT) VOLUME I Tender Reference:. Issue Date: Day/Month/Year Public Procurement Authority Accra, Ghana
More informationICES. Narrative. Applicant s name
ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed
More informationDelay Expert practical tips for making delay claims
Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of
More informationSheila Belayutham CHAPTER 6 CONTROL
CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s
More informationPurchasing Procedures Manual
Purchasing Procedures Manual March 2014 Table of Contents Purchases of Goods, Equipment and Services... 1 Appendix A - Purchasing Methods Introduction... A - 1 General Purchasing Requirements... A - 3
More informationThe New NZS 3910:2013
The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first
More informationNEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry
NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation
More informationSUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)
SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012
More informationAIRPORT AUTHORITY HONG KONG
AIRPORT AUTHORITY HONG KONG GENERAL CONDITIONS OF CONTRACT BUILDING AND CIVIL WORKS ISSUE NO. 10 August 2011 [this page not used] GENERAL CONDITIONS OF CONTRACT FOR BUILDING AND CIVIL WORKS TABLE OF CONTENTS
More informationAGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)
AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE
More informationOREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor
More informationShort Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of
Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),
More informationContract [Number] [Contract Name] Contract Documents. Minor Works / Direct Appoint
Contract [Number] [Contract Name] Contract Documents Minor Works / Direct Appoint This proforma document provides the basis for the development of physical works contract documents for the Transport Agency
More informationWorkshop 4 FIDIC Contracts (Update on New Documents)
Workshop 4 FIDIC Contracts (Update on New Documents) Employer s New Obstacle: Commencement Date and Related Clauses Dr.Sarwono Hardjomuljadi Tuesday, 04 October 2011, 14.00 15.30 Employer s New Obstacle:
More informationThe following amendments have been made to the June 2005 edition deleted: and of notified early warning matters
AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with
More informationBIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017
BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable
More informationTerms and Conditions
Terms and Conditions SERVICES Taking such steps as are reasonable to enable MFA to be satisfied within the limits of the professional skill and care set out in clause 2-1 that the plans and works comply
More informationAny additional services not detailed in the Quotation, and the price is subject to variation to take account of changes in any exclusions.
STANDARD TERMS & CONDITIONS for QUOTATIONS. Bitu-mill (Road Maintenance) Pty Ltd, Bitu-mill (Civil) Pty Ltd, Bitu-mill Services Pty Ltd and Bitu-mill Equipment Pty Ltd ( Bitu-mill ) These terms and conditions
More information[Project Name] NZTA Contract No. [Contract Number] Conditions of Contract
[Project Name] NZTA Contract No. [Contract Number] DOCUMENT CHANGE FORMAT CODES This proforma document provides the basis for the development of physical works contract
More informationFIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management
FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract
More informationComparison between the Red Book 1999 and the MDB Harmonised Edition 2010
Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Please note that this comparison is for guidance only and does not purport to be complete and exhaustive. All corrections and improvements
More informationKelvin N. F. Lau Associate Vice President. 2 Februray 2012
2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management
More informationFramework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /
Framework agreements The Standard for Infrastructure Procurement and Delivery Management includes provisions for framework agreements. Framework agreements have similarities with term service and transversal
More informationCl Offence Individual Corporation
Attachment 1: Contracting Party's Offences & Penalties Cl Offence Individual Corporation 21(4) Failure to inform the principal and commissioner (in the approved form) within 5 business days of entering
More informationLANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK. Michele Cyna
October I992 Transport No. RD-12 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK Michele Cyna Delays in the completion
More informationFIDIC WORKSHOP 2016 GROUP 6
FIDIC WORKSHOP 2016 GROUP 6 QUESTION 1 WHAT ARE THE ESSENTIAL REQUIREMENTS FOR FORMATION OF CONTRACT? DISCUSS WHETHER A BINDING AND ENFORCEABLE CONTRACT HAS BEEN CONCLUDED BETWEEN JOLLY AND CAN-DO. 1.
More information2 nd Edition September 2005 (Second Edition of CIDB document 1020)
Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF
More informationTHE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016
THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 INTRODUCTION TO THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki
More informationNew Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking
New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice
More informationA18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management
A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:
More informationRisk Management. Financial Risk. Asset and liability management
Risk Management CITIC Limited has established a risk management and internal control system covering all business segments to identify, assess and manage various risks in the Group s business activities.
More informationMAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS
MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3
More informationW-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES
W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES INVITATION FOR QUOTATIONS FOR CONSTRUCTION OF CIVIL WORKS UNDER SHOPPING PROCEDURES To Dear Sirs, Sub : INVITATION FOR QUOTATIONS FOR CONSTRUCTION
More informationSeptember 2017 CONSULTATION PAPER DELISTING AND OTHER RULE AMENDMENTS
September 2017 CONSULTATION PAPER DELISTING AND OTHER RULE AMENDMENTS CONTENTS Page No. EXECUTIVE SUMMARY 1 CHAPTER 1: INTRODUCTION 2 CHAPTER 2: LONG SUSPENSION, DELISTING FRAMEWORK AND PROPOSED RULE AMENDMENTS
More informationTHE HONG KONG INSTITUTE OF SURVEYORS
PART II ASSESSMENT 2013 DAY 2 Wednesday, 18 th September, 2013 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main
More informationANNEX VIII b STANDARD FORMATS AND TEMPLATES
ANNEX VIII b STANDARD FORMATS AND TEMPLATES STANDARD BID EVALUATION FORMAT FOR THE PROCUREMENT OF CIVIL WORKS 1 Preface 1. This standard tender evaluation format for the procurement of Civil Works has
More informationAMENDMENTS APRIL 2013
AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The
More information2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals
GENERAL CONDITIONS 1 GENERAL PROVISIONS.................................... 1 1.1 Definitions The Contract Persons Dates, Times and Periods Money and Payments Other Definitions 1.2 Interpretation 1.3 Priority
More informationGOVERNMENT OF KARNATAKA
Annexure I K/W-1 GOVERNMENT OF KARNATAKA -------------------------------------------------- (Name of Organization) ------------------------------------------------ ----------------------------------------------
More informationOff-Site Manufacturing
Off-Site Manufacturing The Legal Implications YORhub Conference 15 th November 2018 Dr Julie Morrissy A word of warning MODERNISE OR DIE 1 Modernise or die 2016 - The Farmer Review of the UK Construction
More informationCase study: Delivering the first phase of two new universities for the South African government. Dr Ron Watermeyer Spencer Hodgson
Case study: Delivering the first phase of two new universities for the South African government Dr Ron Watermeyer Spencer Hodgson Wits capital projects programme Started 2007 Refurbishment of old buildings
More informationHang Seng MPF. Annual Member Newsletter. Hang Seng MPF Service Hotline Hang Seng MPF website hangseng.com/empf August 2014
Hang Seng MPF Annual Member Newsletter 2014 8 August 2014 Hang Seng MPF website hangseng.com/empf Hang Seng MPF Service Hotline 2213 2213 Important notes The Hang Seng Mandatory Provident Fund SuperTrust,
More informationProposal Adequacy Checklist
The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror s checklist,
More informationSUPPLY of LED POWER LIGHTS WITH STAND FOR THE GOVERNMENT FILM UNIT
SUPPLY of LED POWER LIGHTS WITH STAND FOR THE GOVERNMENT FILM UNIT BIDDING DOCUMENT DEPARTMENT OF GOVERNMENT INFORMATION BID No: DI/PRO/04/19/2016/TEC 05 Bids will be closed at 1100 hours on.01.08.2018
More informationRESULTS OF THE 2011 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MARCH Prepared by: Prof. HJ Marx
RESULTS OF THE 2011 SURVEY OF THE cidb CONSTRUCTION INDUSTRY INDICATORS MARCH 2012 Prepared by: Prof. HJ Marx of Quantity Surveying and Construction Management University of the Free State marxhj@ufs.ac.za
More information