NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012
|
|
- Kenneth Anderson
- 5 years ago
- Views:
Transcription
1 NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald
2 Housekeeping Safety Facilities 2
3 Introductions Richard Patterson Chartered Engineer Mott MacDonald Procurement Practice 21 years with Mott MacDonald Many forms of contract 15 years with the NEC A year with NEC as an NEC Consultant 3
4 There is a plan Some real basics on NEC Pre-award contract preparation The right contract structure Z clauses Works Information Early Contractor Involvement (ECI) Post-award contract management programme early warning (Risk Register and project risk register) compensation events target cost issues Preparing for NEC so what? Bedtime reading 4
5 NEC is well proven. And why we are here UK Institution of Civil Engineers (ICE) review existing contracts, case law development work for a new contract Consultative version - South Africa, Hong Kong, UK Engineering and Construction Contract (2nd Ed.) 10 years of successful use and expansion of NEC family Specifically endorsed by South African government NEC3 launched - users feedback; new contracts specifically endorsed by UK government 2009 trials by Hong Kong Government 5
6 By the way, please, just NEC N it s clearly not new E it s for far more than engineering C it s more than just a contract 6
7 NEC principles some really good ideas Flexibility Stimulus to good management Clarity and simplicity 7
8 Supply Supply Contract Supply Short Contract Flexibility the NEC Family High Complexity Low PSC Professional Services Contract ECC Engineering & Construction Contract ECS Engineering & Construction Subcontract ECSC Engineering & Construction Short Contract ECSS Engineering & Construction Short Subcontract TSC Term Services Contract TSSC Term Services Short Contract business case Framework Contract Adjudicator s Contract design construction operation
9 X3 X2 X1 Flexibility the Engineering and Construction Contract (ECC) Y(UK)2 X4 W1 X6 X5 Z X12 X7 X13 Y(UK)3 X16 X15 X14 W2 X20 X18 X17 A B C D E F additional conditions jurisdiction-specific options secondary options dispute resolution option payment option 1-9 core clauses 9
10 NEC is a stimulus to good management clear documents, roles and processes sort it out NOW approach focus on programme collaborative risk management effect of change based on forecast effect on time and cost not eg a historical bill of quantities flow charts for all processes A contract focused on the project radical! 10
11 Pre-award lessons 11
12 Start with right NEC contract! Engineering and Construction Contract (ECC) vs Engineering and Construction Short Contract (ECSC) Term Service Contract (TSC): Designed for a service, not really as a term contract. X19 Tasks need work vs NEC Framework Contract vs flexed Engineering and Construction Contract (ECC) Whatever you do: Requirements and constraints Risk Time Price 12
13 HK seems to have developed two sets of standard Z clauses. Works Information Don t mess with the structure - ECC form of agreement conditions of contract incorporates by ref. requires info.to be stated in Site Information Core Options Option Z Schedule (s) of Cost Components activity schedule or bill of quantities Contract Data part one part two Accepted Programme
14 Curb the Z clauses! Mott MacDonald at NEC Annual Seminar 2011: To what extent have Z clauses impacted on the NEC s success as a modern contract? Very happy to share 14
15 Guidance from NEC Additional conditions should be used only when absolutely necessary to accommodate special needs such as those peculiar to the country in which the work is to be done. (Guidance notes, 2005) Contra proferentum Of course, HK government has its reasons 15
16 The clauses support & interlink the whole beware 16
17 Types of Z clause identified in the research Onerous and unfair, 8% Valid, 6% Legal clarifications, 2% Works Information, 24% Risk profiling, 8% Turning back the clock, 16% Lack of NEC Knowledge, 16% 17 Shrinking Obligations, 20%
18 Z clauses create a more adversarial contract Overall 73% believed Zs create a more adversarial contract 18
19 Valid Z clauses? Mott MacDonald shared its issues on ECC2 with NEC. Very few remain in ECC3. Properly incorporating the Schedules of Cost Components Application for payment Intellectual Property Rights (IPR) Option A, B value engineering clause Options C and D - timing of payment of Contractors share Project specific risk allocation changes 19
20 Z clause lessons If extensive amendments required, use another form of contract! Drafters must be fluent in, and subscribe to, the principles of the NEC contract Z clauses should: be kept to a minimum not alter the general principles of NEC contracting be drafted in the style of the NEC use language from other clauses where possible be presented as an appendix to the Contract Data part one 20
21 Z clause lessons more! Drafters of Z clauses should: produce and use amended flow-charts provide rationale to support the inclusion of Z clauses at tender stage The team must produce effective and correct contract documents alongside the Z clauses Consider requesting prices for different options including and excluding certain Z clauses 21
22 But, forget the Z clauses, what do you actually want?! 22
23 Works Information what does it say on the tin? 20.1 The Contractor Provides the Works in accordance with the Works Information (option A and C) Information in the Activity Schedule is not Works Information or Site Information The following are compensation events. (1) The Project Manager gives an instruction changing the Works Information.. If it s not on the tin (in the WI) then the Contractor does not have to do it. Poor WI: busy Project Manager! 23
24 Works Information This is where the effort is required! No standard structure imposed by ECC But many references from the conditions All listed in the Guidance Notes Eg work to be done by the Completion Date parts of the works designed by Contractor (21.1) particulars of design for submission (21.2) Consider template/preface to ensure Works Information covers all these issues Repeat users should develop a template 24
25 Anyone preparing Works Information should read... 25
26 Managing uncertainty and risk using Early contractor involvement or Two stage tendering forecast outturn cost risk client s risk the Prices Contractor s risk base PSC contract for phase 1 award of contract ECC contract for phase 2 feasibility, outline design, detailed design, construction time OR single ECC contract with break point 26
27 Post-award lessons 27
28 Key issues for a successful implementation of an NEC project Communications As discussed. ie TALK to each other Clear system to formalise communications Programme (ECC) / plan (TSC) Meeting at least monthly Early warning and risk reduction Meeting at least weekly Compensation events Meeting ideally weekly Defined Cost (on target contracts) 28
29 The programme has to be taken seriously Programme is key to project management and so to ECC Detailed requirements for contents and updating of programme More than just a bar chart Even substantial contractors have been shocked! Get the first Accepted Programme in place at contract award Soft copy Monthly routine: discuss, understand, agree prior to formal submission 29
30 Early warning (Cl 16) vital part of ECC reciprocal obligations to both notify and solve Contractor and PM give an early warning aware of a matter which could increase the total of the Prices delay Completion, delay meeting a Key Date or impair the performance of the works in use 30
31 Early warning (Cl 16) Early warning has teeth! Sanction if not given Cl 63.5 compensation event assessed as if Contractor had given early warning Option C and D Disallowed Cost includes those costs incurred because no early warning given 31
32 Early warnings and the Risk Register PM enters early warning matters in Risk Register new in NEC3 risk reduction meeting; those attending co-operate in making and considering proposals to avoid or reduce risk, seeking solutions, deciding actions, updating Risk Register PM revises Risk Register to record decisions and issues 32
33 So what is the Risk Register. Risk Register includes a description of the risk and a description of the actions which are to be taken to avoid or reduce the risk The Risk Register in NEC3 has caused some confusion.. 33
34 Included, after award, as the ECC Risk Register Description of the risk Likelihood Impact (time) Impact (cost) Owner A project risk register, the contract, and the ECC s Risk Register Cost allowance Expiry date Actions to avoid or reduce the risk Description of risk Likelihood (%) Impact (time) Impact (cost) Owner Cost allowance Predicted expiry date Actual expiry date Actions to avoid or reduce the risk If relevant and to be talked about in post award risk reduction meetings then include in CD1 as the following matters will be included in the Risk Register the contract Contractor required to do? If so, then in Works Information. If C s design then in WI for C s design At clients risk? Also cut and stick as additional compensation event (option Z) or possibly Employer s risk from Contract Data part one Client s risk? overall amount included in Client s contingency outside Prices Contractor s risk? overall amount included in the Prices
35 Description of the risk project risk register and Risk Register Actions to avoid or reduce the risk Some project level risks may make it to Contract Data part 1 or 2 and so to ECC Risk Register All early warnings go to ECC Risk Register but are they worth going on project risk register? 35
36 project risk register and Risk Register The ECC PM updates the Risk Register (RR) and may also be the pm who manages the project risk register (prr)! RR has a subset of the columns of the prr RR may have risks (rows) that do not merit going on the prr and prr will have higher level project risks (rows) that do not belong on the RR for the contract Can we manage this as one database / spreadsheet? Need to keep the ECC Risk Register simple and used 36
37 Risk Register project risk register award of contract ECC Risk Register feasibility, outline design, detailed design, construction time 37
38 Early warnings and the Risk Register Encourages collaboration and proactive risk management Properly managed, it will also help management of risk management of change and processing of compensation events 38
39 NEC Risk Register consideration and tips For any early warning Information phase Agree aims Generate ideas Develop action plan actions to be clear and precise Update the Risk Register What about: Technical Queries (TQs) Requests for Information (RFIs) 39
40 NEC Risk Register consideration and tips (2) PM has to beware of changes to the Works Information Works best if integrated through the supply chain with NEC3 contracts and subcontracts run by Contractor? Beware clogging up process with too many risks with low likelihood and low impact Use a projector to put on to the wall: update there and then! 40
41 It s all about change change management = compensation events And who or what likes change? poor Works Info. = stressed Project Manager 41
42 You need to actively manage compensation events from day 1 Need to agree you want to manage them and monitor progress Clear processes and timescales in contract The team needs: Accepted Programme and programming skills QSs that understand cost and risk and the Contractor s cost system An agreed format for quotations A way of working with Contractor for acceptable quotations Negotiation skills and empowerment Use Project Manager s assumptions (61.6) Roll up the little ones? 42
43 For each compensation event Agree the sub-clause Be clear on the desired outcome eg clear changes to Works Information Discuss alternatives (62.1) for alternative ways Technical alternatives Time vs cost? Discuss risks and so any possible Project Manager assumptions (61.6) Changes to Contractor s working? Change to Completion Date? Change to Defined Cost? Review before formal submission 43
44 Prices, at tender PWDD Incremental certainty? No gap here if A or B changed Prices and Completion Date due to compensation events completion date time 44
45 Cost - on a well run NEC target contract Monitoring the Defined Cost against target understand the Contractor s cost accounting system in detail get items in the Fee separately coded at source monitor cost weekly formal audit plan Disallowed Costs accounts and records ensure and record any agreement around the edges of the definition disallow as far as possible at source in Contractor s management accounting system monitor weekly 45
46 NEC health checks how well are you doing? Date of and days since last Accepted programme Monthly and cumulative number of early warnings raised and outstanding Date of and days since last update to Risk Register Cumulative number and value of CEs notified Cumulative number and value of CEs implemented 46
47 NEC - So what for my organisation? People Process Technology 47
48 Process - review internal processes Pre-award determining procurement strategy Tender docs review standard specifications and drawings develop templates and/or guidance for eg Contract Data and Works Information A real challenge here in Hong Kong Contract management appointment of staff to ECC roles and delegation of actions change management decision making standard forms for communications audit 48
49 Technology use it Pre-award better ways of storing/sharing/maintaining documents Contract management planning software Consider how ECC processes to be communicated and recorded word and excel? database? proprietary software? 49
50 50
51 It s all about people, stupid People are they right for collaboration? willing to learn and change? empowered and competent to make decisions? Training training needs assessment ECC awareness for most; specific training for specific needs planning, costing, negotiation? roll-out of organisation s templates etc joint training with supply chain project start-up workshops 51
52 Bedtime reading 52
53 Some articles of mine, I hope, may be of interest Year Title NEC3: contracts for partnering Ground Conditions and Risk Allocation: Combining the NEC Engineering and Construction Contract (ECC) and the Geotechnical Baseline Report (GBR) 6 key links in the ECC NEC contracts as an enabler to Partnering Using NEC contracts to manage risk and avoid disputes Use of NEC in legal jurisdictions other than English law NEC A real opportunity for the Clerk of Works Where published NEC Newsletter No 56, October 2011 Tunnels and Tunnelling Magazine, Dec 2010 NEC Newsletter No 51, July 2010 May 2010 edition of 'The Partner', which is the annual publication of PSL, which is a CBI and BIS initiative to promote collaborative business relationships ' ICE s Management, Procurement and Law, 2009, No 4. NEC Newsletter, No,47, July 2009 Site Recorder, Magazine of the Institute of Clerks of Works NEC and Risk Management Using NEC for multiple site, undefined contracts NEC Newsletter No 40, Oct 2007 ICE s Civil Engineering, May
54 NEC manuals NEC Managing Reality Five volumes covering all aspects of NEC (ECC) Barry Trebes (Mott MacDonald) and Bronwyn Mitchell Thomas Telford publishing 54
55 NEC3 A User s Guide NEC3 A User s Guide Jon Broome ice publishing Published March
56 Remember: NEC is not a panacea or an easy answer NEC demands good documentation NEC demands active management 56
57 Further information (0) and / or Hayman Choi here in Hong Kong hayman.choi@mottmac.com.hk
58 Mott MacDonald 58
ENGINEERING AND CONSTRUCTION CONTRACT
THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation
More informationCourse agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)
NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session
More informationWebinar - The Project Manager in the NEC4 ECC: What s new and different?
Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed
More informationExperience Sharing on NEC Implementation and its Effectiveness in Hong Kong
Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has
More informationNEC3 ECC Introductory Training
NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:
More informationNEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry
NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation
More informationZ-CLAUSES: FRIEND OR FOE?
Z-CLAUSES: FRIEND OR FOE? INGA HALL K&L GATES LLP NEC3 CONTRACTS - OVERVIEW Deliberately and fundamentally different from other standard forms Collaborative not adversarial NEC website: where traditional
More informationCommon Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council
Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract
More informationExperience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement
Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting
More informationCONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1
CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General
More informationHelpful instructions for webinar attendees
Helpful instructions for webinar attendees 1. Ensure you have clicked Yes to the Integrated Voice pop up when you entered. If No, then log out and join again. This will ensure you have sound. It will not
More informationNEC4 ENGINEERING & CONSTRUCTION CONTRACT
1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box
More informationUnpacking framework agreements for the delivery and maintenance of infrastructure
Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or
More informationICES. Narrative. Applicant s name
ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed
More informationNEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage
NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project
More informationStandard forms of partnering contracts The ultimate contractual commitment? Part 4
Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard
More informationCHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016
CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,
More informationThe Contractor s NEC3 ECC Handbook
The Contractor s NEC3 ECC Handbook The Contractor s NEC3 ECC Handbook Steven C. Evans This edition first published 2017 2017 John Wiley & Sons Ltd All rights reserved. No part of this publication may
More informationPeter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.
CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC
More informationNEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date
NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated
More informationConstruction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager
London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner
More informationConstruction Law Update The NEC4 suite of contracts are here!
Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411
More informationConstruction Law Update: Spotlight on the NEC3 Engineering and Construction Contract
London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton
More informationFramework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /
Framework agreements The Standard for Infrastructure Procurement and Delivery Management includes provisions for framework agreements. Framework agreements have similarities with term service and transversal
More informationreads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)
Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the
More informationNEC4 Engineering and Construction Contract review of changes from NEC3
Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main
More informationCase study: Delivering the first phase of two new universities for the South African government. Dr Ron Watermeyer Spencer Hodgson
Case study: Delivering the first phase of two new universities for the South African government Dr Ron Watermeyer Spencer Hodgson Wits capital projects programme Started 2007 Refurbishment of old buildings
More informationNew Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking
New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice
More informationThe following amendments have been made to the June 2005 edition deleted: and of notified early warning matters
AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated
More informationNEC3 Term Service Contract By NEC (New Engineering Contract) READ ONLINE
NEC3 Term Service Contract By NEC (New Engineering Contract) READ ONLINE If searching for a book by NEC (New Engineering Contract) NEC3 Term Service Contract in pdf form, then you've come to the right
More informationNEC4 Key Commercial Changes
NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County
More informationResolution Legal Aid Committee s guide to Very High Cost cases and Prior Authority
Resolution Legal Aid Committee s guide to Very High Cost cases and Prior Authority Recently members of Resolution s Legal Aid Committee have visited the Legal Services Commission s offices in Birmingham
More informationSPECIAL TENDER CONDITIONS FOR THE
Page 1 SPECIAL TENDER CONDITIONS FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FEASIBILITY STUDIES Page 2 A. INTRODUCTION The following documents are available on http://emits.esa.int/
More informationLearning Le cy Document
PROGRAMME CONTROL Quantitative Risk Assessment Procedure Document Number: CR-XRL-Z9-GPD-CR001-50004 Document History: Revision Prepared Date: Author: Reviewed by: Approved by: Reason for Issue 1.0 15-06-2015
More informationHKIS Resolving Disputes between Contractors
HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com
More informationThe NEC 3 Engineering and Construction Contract
The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston
More informationNEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.
Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and
More informationNEC3 ECC target contract option principles and innovative applications
INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract
More informationThe New NZS 3910:2013
The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first
More informationTender Specifications attached to the Invitation to tender
Ref. Ares(2015)3457155-20/08/2015 Tender Specifications attached to the Invitation to tender Brussels, 20/08/2015 Invitation to tender N SRB/NEG/1/2015 for the provision of legal advice for bridge financing
More information2 nd Edition September 2005 (Second Edition of CIDB document 1020)
Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF
More informationAneurin Bevan Health Board
AUDIT COMMITTEE MEETING Minutes of the meeting held on Thursday 18 March 2010, at 9:30 a.m. in the Boardroom, Mamhilad House Present: Chris Koehli - Chair Peter Sampson - Vice Chair Wendy Bourton - Independent
More informationIn this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets.
Budgets and Planning Tools In this chapter: Configure a budget Report on budget versus actual figures Export budgets Project cash flow Chapter 23 479 Tuesday, September 18, 2007 4:38:14 PM 480 P A R T
More informationGUIDANCE FOR PROFESSIONAL CONSULTANTS
Diocese of Westminster Education Service Page 1 MANDATORY DOCUMENTATION GUIDANCE FOR PROFESSIONAL CONSULTANTS RICS Standard Form of Consultant s Appointment RICS Standard Form of Consultant s Appointment
More informationImplementing the Construction Supply Chain Payment Charter. January Guidance Note
Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and
More informationGuidelines for Improved Risk Management on Tunnels and Underground Structures in the United States of America
Guidelines for Improved Risk Management on Tunnels and Underground Structures in the United States of America Presented by: Joe O Carroll November 29, 2017 A code of practice is a set of written rules
More informationSubcontract conditions
AS 2545 1993 (Incorporating Amendment No. 1) Australian Standard Subcontract conditions This Australian Standard was prepared by Committee OB/3, General Conditions of Contract. It was approved on behalf
More informationOfficial. NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform.
NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform versions) Guidance NHS standard sub-contract for the provision of clinical services 2017/18
More informationHSCIC Financial Management and Reporting
HSCIC Financial Management and Reporting Author: Rebecca Giles/Carl Vincent Date 24 th February 2014 1 Copyright 2014, Health and Social Care Information Centre. Contents Contents 2 Introduction 3 Current
More informationSURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS
BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALSS BK SURCO Limited Suite 1901-2, 19 th Floor, Hopewell Centre 183 Queen s Road
More informationNIRS 2: Contract extension
NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 LONDON: The Stationery Office 0.00 Ordered by the House of Commons to be printed on 12
More informationFP6 Contract and Financial Reporting. The Basics for EC Consortia. Linda Polik Research Services
FP6 Contract and Financial Reporting The Basics for EC Consortia Linda Polik Research Services linda.polik@admin.ox.ac.uk Overview of Presentation 1) Contractual Issues 2) Financial Issues 3) Reporting
More informationThe NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister
The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable
More informationTRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS
C1.2 Contract Data Part one - Data provided by the Employer Clause Statement Data 1 General The conditions of contract are the core clauses and the clauses for main Option B: Priced Contract with Bill
More informationEquestrian Professional s Horse Business Challenge. Member s Support Program Workbook. Steps 1-3
Equestrian Professional s Horse Business Challenge Member s Support Program Workbook Steps 1-3 STEP 1 Get Your Books Ready for Year-end Step 1: Complete our bookkeeping checklist and get your books ready
More informationSPECIAL CONDITIONS OF TENDER
Page 1 SPECIAL CONDITIONS OF TENDER A. INTRODUCTION The following documents are available on http://emits.esa.int/ under "Reference Documentation" --> "Administrative Documents": ESA Procurement Regulations
More informationGCC: The GCC 2015 (3 rd Edition) Welcomed with Open Arms
FIFTH EDITION MAY 2016 GCC: The GCC 2015 (3 rd Edition) Welcomed with Open Arms Commentary on the Changes Introduced by the GCC 2015 (3 rd Edition) Author: Odette Potgieter During November 2015 the GCC
More informationfor Major Infrastructure Projects
for Major Infrastructure Projects Presented by: Pedram Daneshmand Senior Associate Director 4 th Annual Contract Selection and Risk for Major Projects, March 2011 Agenda Brief Introduction Project Delivery
More informationThe NEC Definitely, Maybe?
The NEC Definitely, Maybe? Rob Horne - Simmons & Simmons David Thomas QC - Keating Chambers Keith Strutt - DriverTrett General Introduction 1 / B_LIVE_EMEA1:1842195v2 The NEC Why is it relevant The 2015
More informationYellow cells denote information required to be entered. Grey cells denote no information should be entered.
A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular project or service, including an appropriate
More informationBasic Introduction to Project Cycle. Management Using the. Logical Framework Approach
Basic Introduction to Project Cycle Management Using the Logical Framework Approach Developed and Presented by: Umhlaba Development Services Umhlaba Development Services Noswal Hall, Braamfontein, Johannesburg,
More informationAudit & Compliance Guidance
Audit & Compliance Guidance Green Infrastructure Fund Guidance for Applicants September 2018 Disclaimer Applicants should be aware that as the Green Infrastructure Fund is a new programme, the guidance
More informationThe Key Role of the NEC Programme and who really owns the float?
The Key Role of the NEC Programme and who really owns the float? Presentation: Objectives of the NEC form Programme requirements under NEC Ownership of float Acceptance of programmes Issues with other
More informationMDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
More informationfor JD Edwards World and EnterpriseOne
www.insightsoftware.com for JD Edwards World and EnterpriseOne Version 1.0 Last Updated: August 31, 2011 Contents Best Practices for Usage of Insight Budgeting... 1 Version Summer 2011... 1 1. Introduction...
More informationshare ranges under the target cost options.
1 Intelligently setting the Contractor s share percentages and share ranges under the target cost options. By Jon Broome, leading edge projects consulting ltd Introduction. At the April 2012 NEC User s
More informationThe NEC3. The Unknowns
The NEC3 The Unknowns The Gaps Between the Express Terms; Is Clause 10.1 the Answer? First, a few unknowns in the NEC 1. What happens when the Accepted Programme is not accepted? 2. What happens when a
More informationMicrosoft Forecaster. FRx Software Corporation - a Microsoft subsidiary
Microsoft Forecaster FRx Software Corporation - a Microsoft subsidiary Make your budget meaningful The very words budgeting and planning remind accounting professionals of long, exhausting hours spent
More informationAll Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success
All in the Clause NEC to NEC4 Comparison of Core Clause 6 Compensation Events giving priority to your commercial success About us We provide: Quantity surveying and cost management Commercial management
More informationNorfolk County Council INTERNAL AUDIT REPORT County Farms Governance Arrangements Follow up January 2017
Norfolk County Council INTERNAL AUDIT REPORT County Farms Governance Arrangements Follow up January 2017 CONTENTS Executive Summary 3 Appendices: Detailed Findings and Recommendations 4 I Implementation
More informationSIGMA Public Procurement Training Manual. Update 2015
SIGMA Public Procurement Training Manual Update 2015 Module G 2 Rue André Pascal 75775 Paris Cedex 16 France mailto:sigmaweb@oecd.org Tel: +33 (0) 1 45 24 82 00 Fax: +33 (0) 1 45 24 13 05 www.sigmaweb.org
More informationCost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs
More informationBetter Contracts, Better Projects: The ConsensusDocs Solution
Better Contracts, Better Projects: The ConsensusDocs Solution Better Contracts, Better Projects: The ConsensusDocs Solution Richard H. Lowe Duane Morris LLP This session is eligible for 1 Contact Hour.
More information2 The Contractor s main responsibilities
Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor
More informationCLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND
CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND PROFESSIONAL ARCHITECT (PrArch) PROFESSIONAL SENIOR ARCHITECTURAL TECHNOLOGIST (PrSArchT) mark applicable registration
More informationCreating a Rolling Income Statement
Creating a Rolling Income Statement This is a demonstration on how to create an Income Statement that will always return the current month s data as well as the prior 12 months data. The report will be
More informationCORK COUNTY COUNCIL. Senior Resident Engineer Road Construction Supervision
CORK COUNTY COUNCIL Senior Resident Engineer Road Construction Supervision QUALIFICATIONS 1. Character Candidates shall be of good character. 2. Health Canidates shall be in a state of health such as would
More informationECMWF Copernicus Procurement
ECMWF Copernicus Procurement Invitation to Tender CLARIFICATIONS Clarifications issued 28 November 2017 ITT Ref: COP_031 ISSUED BY: ECMWF Administration Department Procurement Section We are pleased to
More informationComparison between the Red Book 1999 and the MDB Harmonised Edition 2010
Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Please note that this comparison is for guidance only and does not purport to be complete and exhaustive. All corrections and improvements
More informationCost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE
Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and
More informationCORK COUNTY COUNCIL. Resident Executive Engineer Road Construction Supervision QUALIFICATIONS
1. Character CORK COUNTY COUNCIL Resident Executive Engineer Road Construction Supervision Candidates must be of good character. 2. Health QUALIFICATIONS Candidates shall be in a state of health such as
More informationSurvival guide to challenging costs in major projects
challenging costs About this guide This publication outlines some of the challenges in estimating and managing costs that we have observed in our work on major projects. It offers Accounting Officers and
More informationBUILDING INFORMATION MODELLING (BIM) PROTOCOL SECOND EDITION. Standard Protocol for use in projects using Building Information Models
BUILDING INFORMATION MODELLING (BIM) PROTOCOL SECOND EDITION Standard Protocol for use in projects using Building Information Models Construction Industry Council I The BIM Protocol has been drafted by
More informationForm of Agreement Between the Client And the Quantity Surveyor
Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.
More informationMacRoberts. A law firm as individual as you.
MacRoberts. A law firm as individual as you. The New NEC4: Exploring the Key Changes Mike Barlow, Partner MacRoberts LLP www.macroberts.com Glasgow Edinburgh Dundee 1 THE NEC4 ENGINEERING AND CONSTRUCTION
More informationA18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management
A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:
More informationIllustration Software Quick Start Guide
Illustration Software Quick Start Guide The illustration software is primarily designed to create an illustration that highlights the benefits of downside risk management and illustrates the effects of
More informationRESULTS OF THE 2011 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MARCH Prepared by: Prof. HJ Marx
RESULTS OF THE 2011 SURVEY OF THE cidb CONSTRUCTION INDUSTRY INDICATORS MARCH 2012 Prepared by: Prof. HJ Marx of Quantity Surveying and Construction Management University of the Free State marxhj@ufs.ac.za
More informationFact Sheet Inventorship, Authorship and Ownership
European IPR Helpdesk Fact Sheet Inventorship, Authorship and Ownership March 2013 Introduction... 1 1 Ownership, Inventorship and Authorship... 2 2 The relevance of inventorship... 3 3 The relevance of
More informationRESULTS OF THE 2010 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MAY Prepared by: Dr HJ Marx
RESULTS OF THE 2010 SURVEY OF THE cidb CONSTRUCTION INDUSTRY INDICATORS MAY 2011 Prepared by: Dr HJ Marx of Quantity Surveying and Construction Management University of the Free State Marxhj@ufs.ac.za
More informationARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Financial Proposal. Part 6
ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Financial Proposal Part 6 Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space Ground
More informationRisk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36
Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...
More informationPlease feel free to ask questions or express view points.
Independence Respect Integrity Troy Kelley Change Order Pricing APWA Contract Administration Sub Committee s Change Order Workshop Series May 1, 8, 15, and 19, 2015 Chris Cortines, CPA and Principal Auditor
More informationAMENDMENTS APRIL 2013
AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The
More informationProfessional Services Contract
Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing
More informationThe following amendments have been made to the June 2005 edition deleted: and of notified early warning matters
AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with
More information1.12 Date of budget revision submission: Enter the month and year the budget revision was submitted for approval Prepared by: Enter the name of
Instructions for completion of budget template A guide and toolkit on project budgeting and cost allocation This guide contains a budget template to help organisations calculate the full cost of a particular
More informationE. Financial Feasibility Study
E. Financial Feasibility Study 1. Overview i. Scope and Methodology The Scope of Services under the Contract calls for the Financial Feasibility Study to: Assess whether the Program will be self-sustaining.
More informationDanny McFadden. Really understands how to work well with parties from different cultures
CEDR Accreditation: CEDR Panel Admission: 2000 2004 Languages: Location: English Mandarin China Really understands how to work well with parties from different cultures Mediation Feedback Danny McFadden
More informationMarina ZANCHI DG Research Directorate N International scientific cooperation
Marina ZANCHI DG Research Directorate N International scientific cooperation E-mail: marina.zanchi@cec.eu.int 1 Kick-off meeting Sofia 27 May 2005 Contract Reporting and Deliverables Financial Statements
More information