NEC3 ECC Introductory Training

Size: px
Start display at page:

Download "NEC3 ECC Introductory Training"

Transcription

1 NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1

2 Introductions John Rayner Name: NEC3 Knowledge: Content General Overview & principles Payment Early warnings and compensation events Roles and responsibilities, Defects and the programme 2

3 Perceptions. Contractual negative, aggressive, claim conscious transparent positive, collaborative, pro-active contractual = transparent = less disputes = more satisfactory result Objectives of the NEC Clarity Stimulus to good management Flexibility 3

4 Clarity Stimulus to good management Objectives of the NEC written in straight forward plain language - avoids legal phrases and as far as possible Clarity subjective terms no long sentences uses bullet points no cross referencing between the clauses process driven, with flow charts available to demonstrate the process and ensure that there are no open ends Flexibility series of defined terms identified within the contract contract specific items kept separate in Contract Data Flexibility Stimulus to good management Objectives of the NEC used across the whole of the construction industry Clarity flexible design allocation responsibility used across a range of contract strategies allows a series of bolt on optional clauses to allow the contract to be tailored to meet the requirements of a specific project Flexibility used internationally as well as domestically 4

5 Stimulus to good management Stimulus to good management Objectives of the NEC clauses/processes intended to help the management of the project, not hinder Clarity obligates actions, and within period stated or within period of reply identifies risk early when effects can be best managed assessments of compensation events based on predicted not retrospective effect. Flexibility programme revised and accepted forms integral part of the contract Overview of the NEC3 - Principles Clause 10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. 5

6 Overview of the NEC3 The Suite Engineering and Construction Contract Engineering and Construction Sub-contract Engineering and Construction Short Contract Engineering and Construction Short Sub-Contract Professional Services Contract Professional Services Short Contract Adjudicator s Contract Term Service Contract Term Service Short Contract Framework Contract Supply Contract Short Supply Contract ECC General Structure and Form The Core Clauses Main Option Clauses Secondary Option Clauses Contract Data Parts 1 & 2 Schedule of Cost Components Works Information Site Information 6

7 Contract Format Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Contract Data Part 1 Contract Data Part 2 Schedule of Cost Components Works Information Site Information Core Clauses Core Clauses Contract Data Part 1 Contract Data Part 2 Arranged in a structure that helps gain familiarity Clearly defined sections Limited cross referencing Written in ordinary language Flow chart basis led to simplified structure Are not altered by the Works Site Options, Information merely Information added to with unique numbering Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Schedule of Cost Components 7

8 Core Clauses Core Clauses 1 General 2 The Contractor s main responsibilities 3 Time 4 Testing and Defects 5 Payment 6 Compensation Events 7 Title 8 Risks and Insurance 9 Termination Main Option Clauses Contract Data Part 1 Main Option Clauses Contract Data Part 2 Option A: Priced contract with Activity Schedule Core Clauses Option B: Priced contract with Bill of Quantities Main Option Clauses Option C: Target contract with Activity Schedule Secondary Option Clauses Option D: Target contract with Bill of Quantities Y (UK) Option Clauses Option E: Cost reimbursable contract Schedule of Cost Components Works Information Site Information Option F: Management contract Option W1 or W2 Dispute Resolution 8

9 Employer increasing financial risk Main Option Risk Balance F Management contract Target Price with Activity Schedule E C Cost reimbursable D B Target Price with Bill of Quantities Bill of Quantities A Activity Schedule Contractor increasing financial risk Secondary Option Clauses Secondary Option Clauses Contract Data Part 1 Contract Data Part 2 X1 Price adjustment for inflation X2 Changes in Law X3 Multiple currencies X4 Parent Company Guarantee X5 Sectional Completion X6 Bonus Works for early Site completion Information Information X7 Delay damages Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Schedule of Cost Components 9

10 Secondary Option Clauses Secondary Option Clauses X12 Partnering X13 Performance bond X14 Advanced payment to the Contractor X15 Limitation of the contractor s liability for his design to reasonable skill and care Secondary Option Clauses Secondary Option Clauses X16 Retention X17 Low performance damages X18 Limitation of liability X20 Key Performance Indicators (not used with X12) Option Z additional conditions of contract 10

11 Y(UK) Option Clauses Contract Data Part 1 Option Y(UK) Clauses Contract Data Part 2 Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Schedule of Cost Components Y(UK)1 Project bank account Y(UK)2 Housing Grants, Construction and Regeneration Act 1996 / Local Democracy, Economic Development and Construction Act 2009 Works Information Site Information Y(UK)3 The Contracts (Rights of Third Parties) Act 1999 Contract Data Part 1 Contract Data Part 1 Contract Data Part 1 Contract Data Part 2 Employer s Information Core Clauses Key roles (E, PM, S) Boundaries of the site Period for reply Time scales, Defects, payment Compensation Events and risk Option clause requirements Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Key date Schedule Sectional of completion Works Site Cost Contractor s Information share Information Components Retention percentage Option Z 11

12 Contract Data Part 2 Contract Data Part 2 Contract Data Part 1 Contractor s Information Core Clauses Key people Matters to be included in the risk register Main Option Clauses WI for Contractor s design First programme Secondary Data Option for Clauses the Main Option Data for the schedule of cost components Y (UK) Option Equipment Clauses rates Working Area Overheads Defined Cost rates and percentages for design and manufacture and Schedule of Contract fabricationworks Site Cost Data Part 2 Information Information Components People percentage Published list of Equipment and percentage adjustment Schedule of Cost Components Schedule of Cost Components Contract Data Part 1 People Equipment Plant and materials Charges Contract Data Part 2 Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Manufacture and fabrication Design Insurance Schedule of Cost Components Works Information Site Information 12

13 Works Information Works Information Contract Data Part 1 Contract Data Part 2 Specifies Core Clausesand describes the works Main Option Clauses States any constraints on how Secondary Option Clauses the Contractor Provides the Works Y (UK) Option Clauses Documents are referenced in the Contract Data Schedule of Cost Components Works Information Given in an instruction Site Information Site Information Schedule of Cost Components Contract Data Part 1 Contract Data Part 2 Describes Core Clausesthe Site and its surroundings Main Option Clauses Referenced in the Contract Data Secondary Option Clauses SI reports and test results Physical condition reports Y (UK) Option Clauses References to available information Statutory undertakers Schedule of Cost Components H&S Files Works Information Site Information Contains only factual information 13

14 Exercise The NEC3 uses the Contract Data to define the full terms and conditions. The pro-foma entry is: The conditions of contract are the core clauses and the clauses for main Option...., dispute resolution Option... and secondary Options... of the NEC3 Engineering and Construction Contract April Write out the definition of the conditions of contract selecting the right options to ensure that the commercial requirements are met. Break 14

15 Employer increasing financial risk Payment Options (Main Options A F) Payment provisions are stated in main options A to F Each options varies the financial risk Payment depends on the definition of Price for Work Done to Date Option A A Activity Schedule Contractor increasing financial risk 15

16 Employer increasing financial risk Main Option A Priced Contract with Activity Schedule Activity Schedule does not have to describe all the work Paid only on Completing each activity Shorter Schedule of Cost Components or agreed rates and prices No recovery for the costs of preparing compensation events Option B B Bill of Quantities A Activity Schedule Contractor increasing financial risk 16

17 Employer increasing financial risk Main Option B Priced contract with bill of quantities Use chosen method of measurement BoQ corrected and new rates used/agreed Payment on a remeasure basis Final BoQ a complete description of the works No recovery for the costs of preparing compensation events Options C & D Target Price with Activity Schedule C D B Target Price with Bill of Quantities Bill of Quantities A Activity Schedule Contractor increasing financial risk 17

18 Main Options C & D Target Contract with Activity Schedule (C) or Bill of Quantities (B) Activity Schedule or Bill of Quantities is not a payment document Contractor paid on a Defined Cost plus Fee basis Pain/Gain share on Completion and final account Risk in the target similar to Option A Contractor recovers the costs of preparing compensation events Option C&D Pain/Gain Contractor s share (% set at tender stage) PWDD Employer pays PWDD Prices (target) with CE s at Completion Prices (target) at award 18

19 Employer increasing financial risk Option E Target Price with Activity Schedule E C Cost reimbursable D B Target Price with Bill of Quantities Bill of Quantities A Activity Schedule Contractor increasing financial risk Main Option E Cost reimbursable contract Contractor paid Defined Cost plus the Fee Compensation events require the Contractor to re-forecast 19

20 Employer increasing financial risk Option F F Management contract Target Price with Activity Schedule E C Cost reimbursable D B Target Price with Bill of Quantities Bill of Quantities A Activity Schedule Contractor increasing financial risk Main Option F Management contract Contractor does no or little work Contractor lets work packages Contractor is paid a tendered fee for the work undertaken 20

21 Employer increasing financial risk Option A A Activity Schedule Contractor increasing financial risk Activity Schedule - Definitions 11.2 (20) The Activity Schedule is the activity schedule unless later changed in accordance with this contract (27) The Price for Work Done to Date is the total of the Prices for each group of completed activities and each completed activity which is not in a group. A completed activity is one which is without Defects which would either delay or be covered by immediately following work (30) The Prices are the lump sum prices for each of the activities on the Activity Schedule unless later changed in accordance with this contract. 21

22 The Activity Schedule - Programme 31.4 The Contractor provides information which shows how each activity on the Activity Schedule relates to the operations on each programme which he submits for acceptance. The Activity Schedule - Payment 54.1 Information in the Activity Schedule is not Works Information or Site Information If the Contractor changes a planned method of working at his discretion so that the activities on the Activity Schedule do not relate to the operations on the Accepted Programme, he submits a revision of the Activity Schedule to the Project Manager for acceptance A reason for not accepting a revision of the Activity Schedule is that it does not comply with the Accepted Programme, any changed Prices are not reasonably distributed between the activities or the total of the Prices is changed. 22

23 Activity Schedule - CE s Assessments for changed Prices for compensation events are in the form of changes to the Activity Schedule. The Activity Schedule Effectively they are a bar on a bar chart, which the Contractor has priced An activity can include fixed overheads, time related charges, temporary works, materials on site as well as the permanent works. The activity schedule is drawn from the programme, but is a separate document Under Option A, Priced Contract Contractor is paid price for activity if completed by next assessment date Determines cash flow & the Prices 23

24 Lunch Early warnings The NEC is based on the principle that foresight applied collaboratively mitigates problems and shrinks risk 24

25 Early warnings Clause 16 What is it s aim Note early warnings do not give entitlement to additional money or time only compensation events will do that. Both parties are obligated to give early warnings (10.1) Early warnings 16.1 The Contractor and the Project Manager give an early warning by notifying the other as soon as either becomes aware of any matter which could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use In the notification the Contractor and the Project Manager state whether the early warning must be dealt with immediately. 25

26 Two extremes of understanding: Project Manager stated that he does not want any early warnings on this project two extremes of understanding: Project Manager stated that he does not want any early warnings on this project Project Manager says Give me as many early warnings as you can 26

27 Absence of an early warning If the Project Manager decides that the Contractor did not give an early warning of the event which an experienced contractor could have given, he notifies this decision to the Contractor when he instructs him to submit a quotation for a compensation event (61.5) The Project Manager is able to review and incorporate in his assessment the consequences of a lost opportunity to mitigate the event (63.5) Disallowed Cost if the cost was incurred because the Contractor did not give an early warning the contract requires him to give Early warnings The early warning process is the contractual communication tool to identify potential problems consider proposals to avoid or mitigate their effect seek mutually acceptable solutions Early warnings should be encouraged as a positive process They should not be seen as a precursor to a compensation event claim 27

28 Early warnings exercise Sketch out the flow chart for the early warning process Consider the interaction of the Project Manager and the Contractor Early warnings exercise 28

29 Compensation events Compensation events are the NEC3 ECC s mechanism to reimburse the Contractor for: Risk events Additional works Additional attendances Breaches of contract by the Employer, Project Manager and the Supervisor The compensation event process Deemed acceptance 2 weeks after reminder Notification by PM or C PM s decision 8 week time bar for certain CE s (61.3.) < 2 weeks PM to state any assumptions May be instructed to submit proposed or alternative quotes Instruct a quote C submits quote Should an EW been given? < Deemed acceptance 2 weeks after reminder PM response (accept / not accept / self assess) < 2 weeks PM assessment (if required) < Only changes if PM s assumptions are incorrect Implementation 29

30 Compensation event exercise Identify those events for which the time bar in clause 61.3 does not apply. Determine which of the scenarios are, or are not, compensation events. Evaluating Compensation Events 63.1 The changes to the Prices are assessed as the effect of the compensation event upon the actual Defined Cost of the work already done, the forecast Defined Cost of the work not yet done and the resulting Fee. 30

31 Defined Cost 11.2 (22) Defined Cost is the cost of the components in the Shorter Schedule of Cost Components whether work is subcontracted or not excluding the cost of preparing quotations for compensation events. Fee 11.2 (8) The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the Defined Cost of subcontracted work and the direct fee percentage to the Defined Cost of other work. 31

32 Schedule of Cost Components Schedule of Cost Components Contract Data Part 1 People Equipment Plant and materials Charges Contract Data Part 2 Core Clauses Main Option Clauses Secondary Option Clauses Y (UK) Option Clauses Manufacture and fabrication Design Insurance Schedule of Cost Components Works Information Site Information SSCC Pigeon Holes People Equipment P&M CHarges M&F Design In WA Used in WA Purchasing PFPO Off Site Employees Site based In the List Delivery Cancelled Paid Rates in CD Visiting CT Data Packaging Authorities OHD s Agency Purchased Testing PM & S Expenses Credits Specials 32

33 What s in the Fee Everything that can t be pigeon holed! Insurance Bonds and warranties Costs incurred for overheads outside the Working Areas Costs incurred by people outside the Working Areas The cost of preparing quotations for compensation events Profit & risk (corporate rather than operational) Break 33

34 THE ROLE OF THE PROJECT MANAGER AND SUPERVISOR Role of the Project Manager Principal Obligations To act in accordance with the Contract To act as an agent of the Employer To act impartially on certain matters To act in spirit of mutual trust and co-operation 34

35 Role of the Project Manager Project Manager tribunal Subcontractor Contract Admin Adjudicator Subcontractor Comm Mgt Design Employer Contractor Subcontractor H&S Designer Doc Control Supplier Stakeholder Mgt Communications Planning Project Control Key responsibilities of the PM To communicate in a form which can be read, copied and recorded To reply to a communication within the period of reply To issue certificates to the Employer and the Contractor To notify the Contractor before delegating any actions May give an instruction which changes the Works Information To give early warning of matters (delay, cost or performance) To enter early warning matters in the Risk Register To record decisions made by revising the Risk Register To accept particulars of the Contractor s design To accept replacement persons proposed by the Contractor 35

36 Role of the Supervisor Project Manager tribunal Subcontractor Contract Admin Adjudicator Subcontractor Comm Mgt Design Employer Contractor Subcontractor H&S Designer Doc Control Stakeholder Mgt Communications Supervisor Quality Control Supplier Planning Project Control Role of Supervisor Ensure on behalf of the Employer, that the works are provided to the standard and performance required in the Works Information; Witness and/or carry out tests and inspections; Notification of Defects; Issuance of the Defects Certificate. 36

37 What is a Defect? Who s responsibility Correcting Defects Uncorrected Defects Defects Defects Clause 11.2 (5) A Defect is a part of the works which is not in accordance with the Works Information or, a part of the works designed by the Contractor which is not in accordance with this contract or Applicable Law or the Contractor s design which the Project Manager has accepted. 37

38 Defect terminology Defect see 11.2(5) defect correction period The period of time the Contractor has to correct a Defect defect date the period of time after Completion that the Contractor is entitled to return to correct any Defects in the works Defects Certificate A certificate issued after the defects date stating what Defects remain uncorrected or a statement that there are none. Notifying Defects Clause 42.1 Until the defects date, the Supervisor may instruct the Contractor to search for a Defect. Clause 60.1 (10) If no Defect is found the matter is a compensation event unless the search was needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Clause 42.2 Until the defects date, the Supervisor notifies the Contractor of each Defect as soon as he finds it and the Contractor notifies the Supervisor of each Defect as soon as he finds it. 38

39 Choices on defective work Correction by the Contractor Pre-Completion (43.1) Post-Completion (43.2) defects correction period / defects date / access availability Correction by Others When access is provided Cost to Employer (45.1) When access is not provided Cost to Contractor (45.2) Accepting non-correction of a Defect Submission of a Quotation (44.2) Other commercial implications Clause 11.2 (25) Disallowed Cost Correcting Defects after Completion; correcting Defects caused by the Contractor not complying with a constraint on how he is to Provide the Works stated in the Works Information 39

40 Exercise Sketch (not to scale) a contract time line showing; starting date Completion the defects date (assume 12 months) defects correction periods 1) before Completion, and 2) after Completion Issue of the Defect Certificate Defect Correction Defect notified Defect notified defect correction period for Defects notified before Completion defect correction period Defect notified defect correction period Defect notified defect correction period Defect notified Completion defects date Completion Certificate issued within 1 week of the Project Manager deciding Completion has been achieved Period between Completion and the defects date (typically 12 months) Defects Certificate issued at this point or at the defects date if the defect correction period for the last notified Defect ends before the defects date 40

41 Programme Objectives Understand the programming requirements of an NEC contract Understand the commercial and operational implications of the NEC programming mechanisms The Accepted Programme Reflection of the work done and to be done Not Site information or Works Information Belongs to the Contractor Each new programme when accepted supersedes the previous one Used to assess time in a compensation event Fundamental to the management of a project Requires considerable effort to maintain for good reason 41

42 The Accepted Programme Planned Completion, fluctuates with risk occurrences Terminal float, maintains Contractor s effectiveness Key Dates: Employer requirements clear and unambiguous Acceptances especially Contractor design Plant and Materials the Employer is to provide e.g. specialist materials or standard plant Order and timing of the work documents must be compatible Resource statements be careful when calling for information 84 42

43 Float Free float: the amount of time a task can be delayed before affecting any other task Total float: the amount of time a task can be delayed without affecting planned Completion Terminal float: the float between planned Completion and the Completion Date belongs to the Contractor Free float and total float are available to accommodate the time effects of compensation events and therefore in essence belong to the project Float Start Completion Date Activity 1 TRA Activity 2 TRA Planned Completion Activity 3 Activity 4 TRA Activity 5 TRA Free Float Terminal Float Total Float 43

44 Float Start Completion Date Activity 1 TRA Activity 2 TRA Planned Completion Activity 3 Activity 4 TRA Free Float Activity 5 TRA Terminal Float Time Risk Allowance Activity Activity TRA TRA Start Start Activity A Activity A 1w 1w 4 4 weeks Activity B Activity B 1d 1d 4 weeks4 weeks Activity C Activity C 1d 1d 4 weeks 4 weeks Activity D Activity D 0d 0d 3 Activity E Activity E 2d 2d Activity F Activity F 1d 1d Planned Completion Planned Completion 0d 0d Completion Date Completion Date 0d 0d 44

45 Time Risk Allowance Activity TRA Start Activity A 1w 4 weeks Time Risk Allowance of 1 week Activity B 1d 4 weeks Activity C 1d 4 weeks Activity D 0d Activity E 2d Activity F Planned Completion Completion Date 1d 0d 0d Time Risk Allowance CE 1 week delayed access to A Activity TRA Start Activity A 1w 4 weeks Activity B 1d 4 weeks Activity C 1d 4 weeks Activity D 0d Activity E 2d Activity F Planned Completion Completion Date 1d 0d 0d 45

46 Time Risk Allowance X Activity TRA Start Activity A 1w Activity B 1d 4 weeks Activity C 1d 4 weeks Activity D 0d Activity E 2d Activity F 1d Planned Completion 0d Completion Date 0d Time Risk Allowance Activity TRA Start Activity A 1w 4 weeks Activity B 1d 4 weeks Activity C 1d 4 weeks Activity D 0d Activity E 2d Activity F Planned Completion 1d 0d 1 Week Completion Date 0d 46

47 Impacts on completion Activity Float Start services Activity A 4 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w Activity G 5w 5 weeks float Activity H Planned Completion Completion Date 5w Impacts on completion Activity Float Start services Activity A 4 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w Activity G 5w 5 weeks float Activity H Planned Completion 5w Completion Date Acceleration CE's 47

48 Impacts on completion Activity Float Start services Activity A 4 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w Activity G 5w 5 weeks float Activity H 5w Planned Completion ANYTHING ANYTHING Completion Date Impacts on completion Activity Float Start services Activity A 4 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w Activity G 5w Activity H Planned Completion Completion Date 5w 48

49 Impacts on completion Activity Float Start services Activity A 5 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w 4 weeks Activity G 4w Activity H 4w Planned Completion Completion Date 1w Impacts on completion Activity Float Start services Activity A 4 weeks Activity B Activity C Activity D Activity E 4 weeks Activity F 5w Activity G 5w Activity H Planned Completion Completion Date 5w 49

50 Impacts on completion Activity Float Start services Activity A Activity B Activity C Activity D Activity E 4 weeks Activity F 5w 2 weeks Activity G 6w Activity H 6w Planned Completion Completion Date 1w 1w Dealing with Early Warnings The Contractor shows on each revised programme: The effects of implemented compensation events So what should be put onto a programme in terms of early warnings? 50

51 Dealing with Early Warnings Activity Duration DIG HOLE INSTALL PIPE BACKFILL Activity 4w Duration DIG Activity HOLE Activity 2w Duration 4w -1 Duration INSTALL DIG Activity HOLEPIPE DIG HOLE 2w Duration 2w 4w w INSTALL ACCESS BACKFILL INSTALL DIG ROAD HOLEPIPE INSTALL 4w PIPE 2w 4w 2w BACKFILL INSTALL ACCESS PIPE BACKFILL ROAD 4w 2w 2wOBSTRUCTION ENCOUNTERED INSTALL BACKFILLACCESS INSTALL ROADACCESS ROAD 4w 2w 4wEARLY WARNING OBSTRUCTION NOTIFIED (WORK ENCOUNTERED STOPPED) INSTALL ACCESS ROAD 4w RISK REDUCTION EARLY OBSTRUCTION WARNING MEETING ENCOUNTERED OBSTRUCTION NOTIFIED (WORK ENCOUN STOP EARLY OBSTRUCTION RISK WARNING REDUCTION ENCOUNTERED EARLY NOTIFIED WARNING MEETING (WORK NOTIFI STOP EARLY RISK WARNING REDUCTION NOTIFIED RISK MEETING REDUCTION (WORK STOP M RISK REDUCTION MEETING Dealing with Early Warnings Activity Duration DIG HOLE INSTALL PIPE BACKFILL INSTALL ACCESS ROAD 4w 2w 2w 4w OBSTRUCTION ENCOUNTERED EARLY WARNING NOTIFIED (WORK STOPPED) RISK REDUCTION MEETING Risk reduction meeting actions: Designer revisits design of access road to consider 3 options 1. Relocate pipe route 2 weeks 2. Breakout section of obstruction 1 week 3. Breakout all of the concrete obstruction 6 weeks What is done and what is shown on the revised programme? 51

52 Dealing with Early Warnings We are in Week 4 and due to submit a revised programme Given the above what would you show on the revised programme that you are about to submit? 1. Show event on programme but with no effect on planned Completion 2. Show event and when linked/rescheduled affects planned Completion by 1/2/3/4/6/7/8 weeks? Consider what time effect should be due this event Dealing with Early Warnings Activity Duration DIG HOLE EW001 Risk reduction meeting EW001 Design review Complete Excavtion EW001 Additional Works INSTALL PIPE BACKFILL INSTALL ACCESS ROAD 3w 1w 1w 1w 1w 2w 2w 4w Show 3 week delay to the excavation Programme narrative explains that EW is under review and further time may / may not result once more details are established Next submitted programme shows full effect of what is likely to be a compensation event 52

53 Dealing with Early Warnings INTENT To show realistic effect to contract on programme and get accepted as latest Accepted Programme FACT Show minimum effect that this event will have on programme: HAVE already lost one week between EW notified and RR meeting WILL take minimum one week for designers to review options WILL take minimum one week for quickest solution SOLUTION Show three week delay to activity - programme Programme narrative explains that the event is under review and further time effect may/may not result once more details established Next revised programme will show full affect of what is likely to be classed as a compensation event at that stage Assessing Time in CE s 63.3 A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme. A delay to a Key Date is assessed as the length of time that, due to the compensation event, the planned date when the Condition stated for a Key Date will be met is later than the date shown on the Accepted Programme 53

54 Programme Example Programme Example Activity Duration Start services Activity A Activity B Activity C Activity D Activity E Activity F Planned Completion Terminal float Completion Date 4w 2w 4w 2w 2w 4w 1w Activities A-E are critical Activity F is non-critical Delay damages at 10,000 per week 54

55 Programme Example Activity Duration Start services Activity A Activity B Activity C Activity D Activity E Activity F Planned Completion Terminal float Completion Date 4w 2w 4w 2w 2w 4w 1w Week 4 submission A is three weeks behind and able to recover Unable to accelerate any future activities 1 week terminal float used up therefore pc is 2 weeks late Programme Example Activity Duration Start services Activity A Activity B Activity C Activity D Activity E Activity F Planned Completion Completion Date 7w 2w 4w 2w 2w 4w Programme reviewed and accepted at week 5. Programme is Accepted and therefore is re-baselined 55

56 Programme Example Activity Duration Start services Activity A Activity B Activity C Activity D Activity E Activity F Planned Completion Completion Date 7w 2w 4w 2w 2w 8w At week 6 the Project Manager issues CE001 the doubles the scope of Activity F from 4 weeks to 8 weeks What happens to planned Completion and the Completion Date Is the Contractor liable for any delay damages ( 10k / week)? Programme Example Planned Completion is week 17, Completion Date still week 15 and Contractor liable for 20,000 delay damages? Planned Completion week 17. Completion Date moves to week 19 and Contractor liable for 0 damages? Planned Completion week 17, Completion Date moves to week 17, and Contractor liable for 0 damages? Something else.? 56

57 Programme Example 63.3 A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme. A delay to a Key Date is assessed as the length of time that, due to the compensation event, the planned date when the Condition stated for a Key Date will be met is later than the date shown on the Accepted Programme Programme Example Activity Duration Start services Activity A Activity B Activity C Activity D Activity E Activity F Planned Completion Completion Date 7w 2w 4w 2w 2w 8w Test under 63.3 is change to planned Completion Planned Completion is unaffected by the CE Answer is (1): Planned Completion is 17, Completion Date still week 15 and Contractor remains potentially liable for delay damages at 20,000 57

58 Programme Example Be careful when a revised programme shows a delay to planned Completion Date Check there is nothing you can practically do, i.e. Increase resources Overlap activities to be a concurrent as possible Remember the programme needs to be realistically and achievable Remember liability for damages hence back to RELATIONSHIPS Summary General Overview & principles Payment Early warnings and compensation events Roles and responsibilities, Defects and the programme 58

59 The Cycle of (NEC) Life EW s Pay CE s Prog Pay The works Pay T&D Pay Questions? 59

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4 Engineering and Construction Contract review of changes from NEC3 Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

The Key Role of the NEC Programme and who really owns the float?

The Key Role of the NEC Programme and who really owns the float? The Key Role of the NEC Programme and who really owns the float? Presentation: Objectives of the NEC form Programme requirements under NEC Ownership of float Acceptance of programmes Issues with other

More information

Professional Services Contract

Professional Services Contract Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable

More information

2 The Contractor s main responsibilities

2 The Contractor s main responsibilities Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor

More information

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

Webinar - The Project Manager in the NEC4 ECC: What s new and different? Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton

More information

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation

More information

Construction Law Update The NEC4 suite of contracts are here!

Construction Law Update The NEC4 suite of contracts are here! Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411

More information

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1 CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated

More information

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT) Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald Housekeeping Safety Facilities 2

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996 NEC4 ECC 5 Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996 This practice note has been prepared due to feedback from UK based users who

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with

More information

MacRoberts. A law firm as individual as you.

MacRoberts. A law firm as individual as you. MacRoberts. A law firm as individual as you. The New NEC4: Exploring the Key Changes Mike Barlow, Partner MacRoberts LLP www.macroberts.com Glasgow Edinburgh Dundee 1 THE NEC4 ENGINEERING AND CONSTRUCTION

More information

The Contractor s NEC3 ECC Handbook

The Contractor s NEC3 ECC Handbook The Contractor s NEC3 ECC Handbook The Contractor s NEC3 ECC Handbook Steven C. Evans This edition first published 2017 2017 John Wiley & Sons Ltd All rights reserved. No part of this publication may

More information

The NEC 3 Engineering and Construction Contract

The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston

More information

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success All in the Clause NEC to NEC4 Comparison of Core Clause 6 Compensation Events giving priority to your commercial success About us We provide: Quantity surveying and cost management Commercial management

More information

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

NEC 3: How to claim as the main

NEC 3: How to claim as the main SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced

More information

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS C1.2 Contract Data Part one - Data provided by the Employer Clause Statement Data 1 General The conditions of contract are the core clauses and the clauses for main Option B: Priced Contract with Bill

More information

AMENDMENTS APRIL 2013

AMENDMENTS APRIL 2013 AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The

More information

Unpacking framework agreements for the delivery and maintenance of infrastructure

Unpacking framework agreements for the delivery and maintenance of infrastructure Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date:... /... /.../ This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative)

More information

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb.

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb. NEC3 A Practical Guide to Compensation Events Chris Holden LLB FRICS FBEng MCIArb www.kerrigans.net Introduction The intention of this presentation is to provide a practical approach to dealing with compensation

More information

NEC4 Key Commercial Changes

NEC4 Key Commercial Changes NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County

More information

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT 1. Definition and Duration These conditions form part of a quotation submitted by the Contractor to the Client named in the quotation. The Contractor

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

General terms and conditions

General terms and conditions General terms and conditions 1. Scope Our offers, deliveries and other services are exclusively carried out based on the following terms of sale and delivery. We shall not acknowledge any opposing or deviating

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

2 CONTRACT 3 SPECIFIC ITEMS INCLUDED AND EXCLUDED FROM QUOTE. Balclutha. Cromwell

2 CONTRACT 3 SPECIFIC ITEMS INCLUDED AND EXCLUDED FROM QUOTE. Balclutha. Cromwell TERMS OF TRADE 1 DEFINITIONS (a) Quote means the quotation provided by Balcrom for the supply of Products. (b) Products means all goods and materials provided by Balcrom to the Customer under the Contract.

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) Ref: W/RFQ-GCC GENERAL CONDITIONS OF CONTRACT REQUEST FOR QUOTATION [Issued in terms of section

More information

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND PROFESSIONAL ARCHITECT (PrArch) PROFESSIONAL SENIOR ARCHITECTURAL TECHNOLOGIST (PrSArchT) mark applicable registration

More information

PURCHASE ORDER TERMS AND CONDITIONS

PURCHASE ORDER TERMS AND CONDITIONS PURCHASE ORDER TERMS AND CONDITIONS 1. SUPPLY OF GOODS AND/OR SERVICES 1.1 In consideration or payment of the Price by the Company, the Contractor must supply the Goods and/or provide the Services to the

More information

Construction traps and solutions for development projects

Construction traps and solutions for development projects Construction traps and solutions for development projects Joe Bellhouse BrookStreet des Roches LLP Nick Woodruff Arcadis APS Project Management 15 June 2011 About the speakers Joe Bellhouse Joe Bellhousee

More information

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8.1 8-1.01 Unit Price Contracts... 8.1 8-1.02 Lump Sum or Job Contracts... 8.1 8-1.03

More information

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012 2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

Page 1 CONTRACT DATA. used in conjunction with the. JBCC Minor Works Agreement. Edition published March 2014

Page 1 CONTRACT DATA. used in conjunction with the. JBCC Minor Works Agreement. Edition published March 2014 Page 1 Preface JBCC Constituents Association of South African Quantity Surveyors South African Black Technical and Allied Careers Organisation Application of JBCC Contract Documents Warning CONTRACT DATA

More information

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.

Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No. Page 1 BOARD NOTICE 30 OF 2007 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the Engineering Profession Act, 2000, (Act No.46 of

More information

NEC: AN EARLY WARNING OF NEC4 S CHANGES TO THE EARLY WARNING CLAUSE

NEC: AN EARLY WARNING OF NEC4 S CHANGES TO THE EARLY WARNING CLAUSE Eleventh Edition - November 2017 NEC: AN EARLY WARNING OF NEC4 S CHANGES TO THE EARLY WARNING CLAUSE Author: Kelly Stannard Change is inevitable in construction contracts and the uncertainty associated

More information

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below: DOMESTIC SUB-CONTRACT CONDITIONS These are the Domestic Sub-Contract Conditions referred to by the Articles of Agreement to which they are attached. In the event that these Domestic Sub-Contract Conditions

More information

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

EAST Cards Terms and Conditions. Provisions specific to consumers only are in red and those specific to businesses only are in blue.

EAST Cards Terms and Conditions. Provisions specific to consumers only are in red and those specific to businesses only are in blue. EAST Cards Terms and Conditions INTRODUCTION What these terms cover. These are the terms and conditions of sale which apply to any order for EAST card packs (the products ) that you place with us via email

More information

Breakdown of the Overall Price: A heading-by-heading list of the rates and costs making up the price for a lump-sum or global sum contract.

Breakdown of the Overall Price: A heading-by-heading list of the rates and costs making up the price for a lump-sum or global sum contract. GLOSSARY Administrative Order: Any instruction or order issued by the Project Manager/Leader/Engineer to the Contractor in writing regarding the execution of the contract. Beneficiary Country: The Maltese

More information

ScottishPower Gas and Electricity. General Terms and Conditions for Domestic Customers

ScottishPower Gas and Electricity. General Terms and Conditions for Domestic Customers ScottishPower Gas and Electricity General Terms and Conditions for Domestic Customers 2 Part 1 Glossary of important terms 1 The words listed below have the following meanings in these terms and conditions

More information

Subcontract conditions

Subcontract conditions AS 2545 1993 (Incorporating Amendment No. 1) Australian Standard Subcontract conditions This Australian Standard was prepared by Committee OB/3, General Conditions of Contract. It was approved on behalf

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date: This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative) [If

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006

More information

Current as of 1 May

Current as of 1 May General terms and conditions of purchase for transport, assembly, disassembly, waste disposal and other equipment-related services, including plant operation, VW AG / general purchasing division (current

More information

General Terms and Conditions for Purchasing

General Terms and Conditions for Purchasing General Terms and Conditions for Purchasing 1. Applicability and Conclusion of Contract These Terms and Conditions for Purchasing apply to all business transactions with the supplier or other contractors

More information

GENERAL TERMS AND CONDITIONS OF PURCHASE OF CADCON HOLDING GMBH

GENERAL TERMS AND CONDITIONS OF PURCHASE OF CADCON HOLDING GMBH 1. General 1.1. The general terms and conditions of purchase below of CADCON Holding GmbH (hereinafter referred to as "CADCON") apply to the ordering from the Contractor and the delivery of goods by the

More information

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. TENDER NO. TCG/F&P/5/2017-2018 SEPTEMBER 2017 TABLE OF CONTENTS

More information

SOUTHERN COMMUNICATIONS LIMITED TELEPHONE SYSTEMS - TERMS AND CONDITIONS OF SALE

SOUTHERN COMMUNICATIONS LIMITED TELEPHONE SYSTEMS - TERMS AND CONDITIONS OF SALE SOUTHERN COMMUNICATIONS LIMITED TELEPHONE SYSTEMS - TERMS AND CONDITIONS OF SALE Please read these Terms in conjunction with our Privacy Notice 1. INTERPRETATION 1.1 In these terms and conditions (Terms),

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email

More information

GUIDANCE FOR PROFESSIONAL CONSULTANTS

GUIDANCE FOR PROFESSIONAL CONSULTANTS Diocese of Westminster Education Service Page 1 MANDATORY DOCUMENTATION GUIDANCE FOR PROFESSIONAL CONSULTANTS RICS Standard Form of Consultant s Appointment RICS Standard Form of Consultant s Appointment

More information

General Terms and Conditions of Business of Renusol Europe GmbH (As at 12/04/2017)

General Terms and Conditions of Business of Renusol Europe GmbH (As at 12/04/2017) General Terms and Conditions of Business of Renusol Europe GmbH (As at 12/04/2017) Clause 1 General Provisions Scope of Application 1. These General Terms and Conditions of Business (hereinafter referred

More information

HKIS Resolving Disputes between Contractors

HKIS Resolving Disputes between Contractors HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com

More information

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK 1 ARTICLE 1 SCOPE OF WORK 2 DEFINITIONS TABLE OF CONTENTS 3 CONTRACTOR

More information

EIMSKIP GENERAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND/OR SERVICES

EIMSKIP GENERAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND/OR SERVICES EIMSKIP GENERAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND/OR SERVICES 1. Definitions Parties means the Company and the Supplier collectively, as parties to a contract on the purchase and procurement

More information

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:- Anti-Bribery & Corruption Policy of Intent STONBURY LIMITED TERMS AND CONDITIONS FOR SUBCONTRACTORS 1. INTERPRETATION (1) In these sub-contract conditions of agreement, the following words and phrases

More information

THE HONG KONG INSTITUTE OF SURVEYORS

THE HONG KONG INSTITUTE OF SURVEYORS PART II ASSESSMENT 2013 DAY 2 Wednesday, 18 th September, 2013 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main

More information

General Conditions of Purchase

General Conditions of Purchase Page 1 of 5 General Conditions of Purchase General conditions of purchase of (KL), Zurich (0610) 1. General - Scope of validity 1.1 These conditions of purchase apply exclusively for all orders on the

More information

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder PART 3 Lump Sum Design-Build Agreement Between Department and Design-Builder This AGREEMENT is made as of the day of in the year of, by and between the following parties, for services in connection with

More information

GENERAL TERMS AND CONDITIONS OF BUSINESS FOR HOTEL ACCOMMODATION CONTRACTS I. Area of validity

GENERAL TERMS AND CONDITIONS OF BUSINESS FOR HOTEL ACCOMMODATION CONTRACTS I. Area of validity GENERAL TERMS AND CONDITIONS OF BUSINESS FOR HOTEL ACCOMMODATION CONTRACTS I. Area of validity 1. These Terms and Conditions of Business apply to contracts for the letting of hotel rooms for accommodation

More information

Emtelle UK Limited Conditions Of Sale Of Goods

Emtelle UK Limited Conditions Of Sale Of Goods Emtelle UK Limited Conditions Of Sale Of Goods 1. INTERPRETATION 1.1 In these terms and conditions the following words have the following meanings: Buyer the person(s) or company whose order for the Goods

More information

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals GENERAL CONDITIONS 1 GENERAL PROVISIONS.................................... 1 1.1 Definitions The Contract Persons Dates, Times and Periods Money and Payments Other Definitions 1.2 Interpretation 1.3 Priority

More information

3 OUR INSTALLERS 4 OUR RESPONSIBILITY

3 OUR INSTALLERS 4 OUR RESPONSIBILITY NPOWER SALE TERMS & CONDITIONS FOR NEST THERMOSTAT 1 OUR CONTRACT These Terms & Conditions apply to the Contract between you and us. Please read them carefully. Words which appear in bold type throughout

More information

Standard Form Project Agreement (hub DBFM Projects)

Standard Form Project Agreement (hub DBFM Projects) Standard Form Project Agreement (hub DBFM Projects) Version 2: June 20122.1: October 2013 . THIS STANDARD FORM PROJECT AGREEMENT MUST BE USED IN CONJUNCTION WITH THE STANDARD PROJECT AGREEMENTS USER S

More information

AMANDA ENERGY PTY LTD STANDARD FORM ELECTRICITY CONTRACT

AMANDA ENERGY PTY LTD STANDARD FORM ELECTRICITY CONTRACT AMANDA ENERGY PTY LTD STANDARD FORM ELECTRICITY CONTRACT CONTENTS Clause Page 1. Supply of Electricity... 1 2. Term of Contract... 1 3. Prices and Fees... 3 4. Billing... 5 5. Payment of Your Bill... 6

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8-1 8-1.01 Unit Price Contracts... 8-1 8-1.02 Lump Sum or Job Contracts... 8-1 8-1.03

More information

Subcontract Agreement

Subcontract Agreement Subcontract Agreement SA - 2009 Project: Trade: Subcontractor: SA - 2009 Number: FOREWORD A good working relationship between the Contractor and Subcontractor is critical to ensuring construction projects

More information

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/ MOMBASA Beach Hotel NGULIA Safari Lodge VOI Safari Lodge KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/2017-2018 KENYA

More information