NEPAL ELECTRICITY AUTHORITY

Size: px
Start display at page:

Download "NEPAL ELECTRICITY AUTHORITY"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NEPAL ELECTRICITY AUTHORITY ENGINEERING SERVICES RESETILEMENT ACTION PLAN Khimti Dhalkebar 220 kv TransmissionLine Project Updated Report (Volume 1: Main Text) Submitted to TransmissionLine/Substation Construction Department DurbarMarg,Kathmandu PreparedandSubmittedby Environmental&SocialStudies Department AdwaitMarg,Kathmandu Phoneno , Fax: March2014

2 Table of Contents EXECUTIVE SUMMARY... II 1.0 INTRODUCTION STUDY METHODOLOGY DESKSTUDY FIELD VISIT PROJECT DESCRIPTION OF THE PROJECT BACKGROUND PROJECT LOCATION PROJECT FEATURES IMPACT ASSESSMENT AND MITIGATION MEASURES PROJECT IMPACTS Impact Categories Physical Displacement of Households Severely Project Affected Families IMPACTS MITIGATION MEASURES Cash Assistance Equal to Minimum Wage Rate Resettlement and Rehabilitation (R&R) Assistances Livelihood Restoration Package COMPENSATION PAYMENT CONSULTATIONS AND COUNSELING VULNERABLE GROUPS DISCLOSURE INSTITUTIONAL ARRANGEMENT, IMPLEMENTATION SCHEDULE AND GRIEVANCE REDRESSING INSTTITUTIONAL ARRANGEMENT IMPLEMENTATION SCHEDULE GRIEVANCE REDRESS MECHANISM ESTIMATED BUDGET List of Tables: Table 3.1: Salient Features... 6 Table 4.1: No. of Owners Affected by Loss of Land and Structures... 8 Table 4.2: No. of Owners Losing more than 25% Land by Tower Pads... 9 Table 4.5: Livelihood Restoration Measures to SPAFs Losing > 25% Land Table 4.6: R&R Assistances for Displaced SPAFs Table 4.7: Livelihood Restoration Package for Project Affected Families (PAFs) Table 4.8: Compensation Payment Status in the Project, March Table 4.9: Compensation Paid and Pending Amount Table 5.1 Proposed Implementation Schedule of RAP Table 6.1: Estimated Budget for Implementing the RAP i

3 Executive Summary The 220 kv double circuit 73 km long KhimitDhalkebar Transmission Line Project is under construction aiming to evacuate the power generated from the various ongoing and proposed hydropower projects to be developed in the north east and central hills of Nepal. The transmission line starts from Khimti of Dolakha District and ends atdhalkabar of Dhanusa District. The proposed transmission line alignment traverses through the Dolakha, Ramechhap, Sindhuli, Mahotari and Dhanusa districts of Central Development Region. This updated Resettlement Action Plan (RAP) has been prepared replacing the previous Abbreviated Resettlement Action Plan (ARAP) prepared in 2006 by NEA. This plan adopts the policyprovisions outlinedin theoperational Manual of Environmental Social Impact Assessment developed by NEA in The changes in population, migration and new settlements in the Project area as well as the increased impacts in land, houses and properties by the Project made it necessary to update the RAP. In addition, the Project s approach in land acquisition on full purchase for a section of ROW for road construction close to the market area of Sindhuli impacting sizable amount of land and quite a high figure of compensation made it mandatory to update the previous ARAP which recorded very limited impacts in The RAP, based on the latest information available from the Project, has assessed the project s impacts more precisely also suggesting realistic mitigation measures to address the impacts. In total, 1080 families of 3 districts have been identified as affected families by the Project which include 440 families of Sindhuli district, 584 families of Ramechap and 56 families of Dhanusha district. Among the PAFs affected by the Project, the highest numbers of land owners accounting 773 will be affected by Right of Way (RoW) of the transmission line followed by 131 owners who will be affected by tower pads and 53 families who will be losing 65 structures in all 3 districts. The ROW acquisition by the Project will also displace 8 families in Sindhuli raising the number to a total of 61 displaced families. The RAP indicates that 94 families will be affected more adversely by the Project who are included in the category of Severely Project Affected Families (SPAFs). Of them, 33 families lose 25% or more land to the Project whereas 61 families will be physically displaced from their original place of residence as they need to be resettled due to the impact of transmission line. Across the districts, 47 SPAFs are in Sindhuli, 36 in Ramechap and 11 in Dhanusha. Various mitigation measures have been proposed to minimize or neutralize the adverse impacts faced by the project affected families. In case of SPAFs, specific mitigation measures have been proposed in addition to normal livelihood improvement supports provided for all affected families. Keeping in view the social safeguard measures specified in the Operational Manual, 2009, different impacts mitigation measures have been proposed. ii

4 These include mainly the compensation of affected land and other properties at replacement value, and Resettlement and Rehabilitation (R&R) assistances comprising of the followings; Cash assistance equal to minimum wage rate Transportation allowances Rental allowances Hardship allowances, and House construction allowance The SPAFs and PAFs will be provided various entitlements as per the policy outline provided in the Operational Manual of Environmental Social Impact Assessment. The SPAFs will be provided total amount of Rs each against R&R assistances. Besides, a common livelihood restoration package comprising of skill training and agricultural inputs use training has been proposed for all PAFs. The Project is advised to commence the implementation of activities proposed in the updated RAP from mid April 2014 and complete all tasks within June A major task of the Project is to complete the compensation payment to the affected families as well as R&R assistances and livelihood restoration measures. The Environmental and Social Studies Division (ESSD) of NEA which has prior work experience in the Project needs to be engaged fully by the Project to implement the RAP beginning April By deploying the competent field staff, the Project requires to work in war footing in order to accomplish the pending RAP implementation which is strongly linked with the Project s physical construction. iii

5 1.0 Introduction Nepal, one of the poorest countries in the world, continues to face severe power shortage, mainly due to inadequate power generation to meet the increasing demand of hydro power for all purposes ranging from household use to industrial operations and infrastructures development. The annual peak electricity demand is increasing with an average rate of about 10% annually leading to unprecedented load shedding since last one decade and this situation is expected to continue for next few years until sufficient power is generated from the projects that are currently under construction or in pipelines. The severe power shortage with a load shedding of up to 18 hours a day, in some years, has adversely impacted the development potential of the nation causing too much of inconveniences beyond tolerable level to the general public. The annual peak power demand of Nepal was estimated at 946 Mega Watt (MW) in 2010/11 whereas the peak time available electricity was only 706 MW (during wet season) resulting in a net deficit of more than 200 MW electricity during wet season (including the electricity imported from India). However, the dry season availability was only about 300 MW resulting in about 650 MW deficit, which was more than double of the supply capacity. To cater present increasing demand of hydro power in Nepal, the new hydropower projects needs to be constructed and the existing capacity of the transmission system needs to be upgraded or new transmission line should be constructed. In view of future system development plan, Nepal Electricity Authority (NEA) proposed Khimti Dhalkebar 220 kv D/C Transmission Line Project to evacuate the power generated from Tamakoshi River and other potential hydropower projects of this region. This transmission line will also be connected to the two existing Independent Power Producer (IPP) namely Khimti and Bhotekoshi with a view to export power to India as well as to cater the power to the load centers of eastern region of the country. The Project is financed by the World Bank to meet the objectives of GON power evacuation system in extending access to electricity supply to a larger percentage of the population. Since the KhimtiDhalkebar (KD) Transmission Line Project is being funded by the World Bank, it has tobe implemented in line of the "the Operational Manual of Environmental and Social Impact Assessment, 2009 prepared by the NEA for Additional Financing of the Power Development Project. In compliance with the Policy Requirements, a separate Social Impact Assessment (SIA) report was prepared focusing on social baseline, impacts, mitigation measures and social monitoring of Khimti- Dalkebar 220 kv transmission line project which was updated later. The World Bank review mission in the past recommended for the preparation of Abbreviated Resettlement Action Plan (ARAP) to address limited impacts of the Project identified in the earlier stage. However, it was noted during implementation that the Project s impacts both in terms of affected families and properties were significantly higher than what were reported by the ARAP in In addition, there has been some change in Project s strategy to acquire the lands and properties in a short stretch of RoW in Sindhuli with a different approach to address the loss of land and structures. In view of these changes, t the preparation of this updated Resettlement Action Plan(RAP) was considered essential which assesses all the Project issues and impacts suggesting mitigation measures that should be implemented to address the adverse impacts of project affected peoples (PAPs).. 1

6 The Environmental and Social Studies Department (ESSD) of NEA collected the latest available information and updated this document as per the contract signed between Transmission Line/Substation Construction Department and the ESSD. Public hearing programs were organized at Manthali of Ramechap district and Dhalkebar of Dhanusha district in order to provide opportunity for the maximum participation of local people and to discuss the findings of the EIA & SIA study and to collect the issues/ concerns of local people on resettlement. The relevant issues raised by local people and representatives of the VDCs and line agencies are incorporated in final EIA & SIA and ARAP report. Nine focus group meetings, indepth interviews and public consultation were organized specially for relocates to explore the issues and concerns related to house relocation. However, for this updated RAP, all the information about project s impacts i.e affected people, lands, and structures as well as the compensation value and amount paid were collected from the Project. The updated RAP mainly focuses on the impacts of the Project on Project Affected Families including those severely affected (those losing more than 25% of land) and households displaced due to loss of structures. The RAP also provides information on compensation status as well as Resettlement and Rehabilitation (R&R) Assistances and livelihood restoration measures to all PAFs, The Project s adverse impacts and mitigation measures are presented in Chapter V of this plan. 2

7 2.0 Study Methodology 2.1 DESK STUDY The desk study includes the review of technical reports of the project, topo maps of 1:25,000 scales, district profiles of affected Districts and VDC profiles. During the desk study, all the necessary information were collected from the available secondary sources. All relevant information associated with socio-economic and cultural environments were reviewed and analyzed. On the basis of the reviewed information, data gaps were identified and the techniques described below were used to generate the remaining data. 2.2 FIELD VISIT The field investigation was carried out by a multi-disciplinary team of experts, which comprised of Sociologist, Economist, ACRP expert and Surveyor. The fieldwork was conducted in February-March, April-May and October- November and lasted for about 60 days in Team traversed in project area to collect information on existing socioeconomic &cultural environment of theprojectaffectedareaand affected households.the required baseline information was collected during the field survey by using the following techniques. Collected data were tabulated and analyzed in computer and output tables are presented in the report. Questionnaire interviews, Checklists, Focus group discussions Questionnaire Interview Pre-tested questionnaires were designed and applied by a trained team of enumerators to solicit the information from the affected families. Census survey was conducted for 17 households only which were affected by Angle Towers as per the design while preparing the ARAP in Two types of questionnaire were designed and used for the survey. The first set of questionnaire was designed to collect information ondemographic characteristics,basichealth conditions, income and expenditure,availabilityof infrastructure facilities, water and energy related issues, information about project, attitude towards settlement and expectations from the project. The second set of questionnaire was used to collect information on t gender issues which was used in the field survey to analyzethe status of woman, their attitude towards the project, the possible impacts on woman due to the implementation of the project and other gender issues. Checklist Key informant survey was also a major survey instrument, which was employed during the field visit to gather socio-economic and cultural information of the people, Two sets of checklists were designed. The VDC level checklist was designed to collect information on basic demographic and migration patterns, food sufficiency and cropping 3

8 patterns, existence of user's groups/committees, public facilities and infrastructure, labour force availability, existence of archaeological and religious places and existence of disadvantaged groups and ethnic minorities. The agricultural checklist was designed to collect the price rates of various agricultural products cultivated in the project affected VDCs and Municipality. This volume of the RAP contains only the main text. The Chapter Plan of the Report is as follows. Executive Summary Chapter 1: Introduction Chapter 2: Methodology Chapter 3: Brief Description of the Project Chapter 4: Impact Assessment and Mitigation Measures Chapter 5: Institutional Arrangement, Implementation Schedule & Grievance Redress Mechanism Chapter 6: Estimated Budget Focus Group Discussion Group discussions were organized to give special attention to issues concerning specific target groups such as women, children and farmers. The local elite and other knowledgeable persons were also included in the discussion. Other occupational caste groups, ethnic minorities, women and disadvantaged groups were included in the discussion, which gave opportunity for the people in the project area to voice their concerns and ask questions regarding the project. This provided in-depth information associated with their religion, culture, festivals, etc. All the Annexes referred in this text are provided in separate volume. The Annex volume 2 contains 5 Annexes. These include: Annex 1: Entitlement Matrix, Annex 2: Land Acquired for Tower Pads and Losses, Annex-3: Land Acquired for ROW in Ramechap District, Annex 4: List of Owners and compensation status for ROW land acquired under full purchase and Annex 5: Compensation Payment for Land Acquired for Tower Pads. 4

9 3.0 Project Description of the Project 3.1 BACKGROUND To evacuate the power generated from the various planed and proposed hydropower projects in the Tamakoshi basin and to feed the load centres in the substation at Dhalkebar of Dhanusha district, a 73 km long, double circuit, 220 kv Transmission Line Project has been proposed. The proposed transmission line will starts from Khimti of Dolakha District and ends to Dhalkabar of Dhanusa District. The proposed transmission line alignment traverses through the Dolakha, Ramechhap, Sindhuli, Mahotari and Dhanusa districts of Eastern Development Region. For the purpose of the SIA study, the study area is defined as the project area consisting of the right of way, substation area as well as the area that will be impacted due to the construction and operation of the project. The same area is considered as the project area for the preparing the RAP study. The proposed project covers 16 VDCs and one Municipality of the five districts. At present, the project area is accessible up to Manthali of Ramechhap district and Khurkotof Sindhuli district via PuspaLal Highway and B.P Koirala highway respectively. This road has been used for the construction of the T/L Project. A small stretch of the transmission line from Manthali to Khurkot is not connected with road where other means of transportation such as helicopter and porter will be used. For the transportation of the construction material in this stretch local labour will be used from the nearest road head to the construction site. Thus, no access road is required to construct for this project. The right of way of the proposed project will be 15 meter each side from the centrelineand approximately 12.5m x 12.5m area will be required for tower foundation. In most of the areas span of the tower will be 350 meter and in total 230 towers will be constructed in 73 km alignment. The number of angle points is 53 and tower is steel lattice structure, self supportedtype. The project component also includes extension of two 132 kv line bays, one each at Khimtiand Dhalkebar substations. The estimated cost for the proposed project was US$ 22 million, to be funded jointly by the World Bank, GON and NEA. In order to carry out the project works the entire stretch of the power line route will be segmented into two work sections and will be controlled from two ends. The working group of each section will be more or less mobile; hence small size temporary camp will be constructed for the construction of the project. 3.2 PROJECT LOCATION The project is located in Central Development Region and covers five districts of Janakpur Zone namely Dolakha, Ramechhap, Sindhuli, Mahottari and Dhanusha (figure). The 5

10 northern portion of the route alignment is accessible by Kirne- Manthaliand Khurkot district road and up to Bardibas the line is parallel to Banepa- Bardibas Road. The section from Bardibas to Dhalkebar is accessible through East West Highway. The nearest airport is Janakpur and regular flights are available from Kathmandu. 3.3 PROJECT FEATURES The total length of the alignment is approximately 73 kilometres. The right of way of the proposed project is 15 meter from the centre line on each side and approximately 12.5m x 12.5-m area has been acquired for tower foundation. The tower height is meters. Table 3.1: Salient Features Project: Zone: District: VDC/ Municipality: TL Line Length: Span: Khimti Dhalkebar 220 kv Transmission Line Project Janakpur Dolakha, Ramechhap, Sindhuli, Mahottari and Dhanusha Sahare, Khimti, Gelu, Tilpung, Kathjor, Manthali, Bhaluwajor, Bhimeshore, Ratanchura, Ranichauri, Jalkanya, Bhadrakali, Gairibas, TulasiBahunmara, Bengadabar and DhalkebarVDCs and KamalamaiMunicipality, 73 km 350 meters No. of Angle Point: 53 6

11 No. of Tower 188 Voltage Level: RoW: Tower Type: Circuit: Conductor: 220 kv 30 meters Steel Lattice Structure, self supported Double ACSR BISON, Duplex Earth Wire: EHS 7/3.35 Foundation Type: Foundation Area: Bay Extension: Funded by: Pad and Chimney isolated x meters (approx. average per foundation) One at Khimti substation and another at Dhalkebar substation World Bank, GON and NEA 7

12 4.0 Impact Assessment and Mitigation Measures 4.1 PROJECT IMPACTS The 73 km long KhimtiDhalkebar 220 kv Transmission Line crosses over different types of land use sections viz government and community forests, rivers and streams, private agricultural land and some settlements including residential area close to district head quarter in Sindhuli district. Based on the available information from the Project, this Chapter updates the various adverse issues and impacts affecting the local peoples and communities and suggests mitigation measures to address them. Based on the identified impacts and mitigation plans, the institutional arrangements, implementation schedule and the required budget have also been estimated to manage the adverse impacts in consistent with the Operational Manual of Environmental Social Impact Assessment, Impact Categories The TL Project apparently causes four types of adverse impacts to the Project Affected Families (PAFs) in three districts vizsindhuli, Ramechap and Dhanusha. Permanent land loss by tower pads, loss of structures (residential and others) by tower pads and TL within ROW and restriction in land use in ROW are three major adverse impacts of the Project. In Sindhuli, the purchase of ROW land for road along 1.5 km TL alignment has also resulted in land loss to the people. Table.depicts that 131 land plots were affected by tower pads, 565 plots by ROW and 159 plots by road in Kamalamai Municipality of Sindhuli district. In addition, 65 structures owned by 53 owners were also affected by the Project in 3 districts (Table 4.1). Table 4.1: No. of Owners Affected by Loss of Land and Structures S. N. Districts Tower Pads ROW Road Structures Owners (No.) Plots (No.) Owners (No.) Plots (No.) Owners (No.) Plots (No.) No. of Owners No. of Structures 1 Sindhuli Ramechap Dhanusha Total Source: Project Office, 2014 Among the land losing households, 33 land owners lose more than 25% of their land for tower pads with the highest number in Ramechhap district and the lowest in Dhanusha district. The owners losing 25% or more land for tower pads would naturally encounter increased loss of foodgrain production directly affecting their food security and livelihoods than those losing less amount of land and these are defined as Severely Project Affected 1 Estimated figure as land survey is yet to be completed 2 Estimated figure as land survey is yet to be completed 8

13 Families (SPAFs). The land losers of this category will, therefore, be entitled for assistances that would help them increase their foodgrain production and livelihood restoration so that the livelihoodsafter the project would either improve or at least remain equal to the preproject level. The list of SPAFs losing more than 25% land permanently for tower pads is provided in Annex 2 for all three districts. Table 4.2: No. of Owners Losing more than 25% Land by Tower Pads S.N. Districts Owners (No) Plots (No.) 1 Sindhuli Ramechap Dhanusha 3 3 Total Source: Project Office, Physical Displacement of Households Available information reveals that 53 households will be displaced in total that are built within 30 metre from the centre of ROW and most of these are residential structures. These include highest number in Sindhuli and lowest in Dhanusha district. In addition, 8 households will be displaced by feeder road that will be built within 30 metre of ROW in a section in Kamalamai Municipality in Sindhuli. Table 4.3: No. of Households Displaced by Loss of Structures S. N. Districts Tower Pads and Row Road Total 1 Sindhuli Ramechap Dhanusha 8 8 Total Source: Project Office, Severely Project Affected Families The displaced households are also defined as Severely Project Affected Families (SPAFs) irrespective of their land loss by other components of the Project. These households would generally suffer more due to loss of their shelter and other amenities viz toilets, drinking water, biogas etch until they get fully settled in a new place with similar type of facilities. The provisions of Resettlement and Rehabilitation (R&R) Assistances proposed for these households are meant to support them to restore their livelihoods within a reasonable period of time after their physical displacement from the place of their origin. 9

14 Table 4.4: Severely Project Affected Families (SPAFs) S.N. Districts Losing > 25% Land Losing Res. Structures Total 1 Sindhuli Ramechap Dhanusha Total Source: Project Office, 2014 Note: SPAFs are defined to be of two categories: i) those losing 25% or more land, and ii) Families losing residential structures. Many households in the Project area are affected by ROW of the Transmission Line which results in land use restriction. The land use restriction in 30 metre width of ROW restricts the owners to construct any permanent structures or grow taller timber or fruit trees above certain height. The ROW land however can be used for agricultural purposes. In lieu of the land use restriction, the project has paid 10% of the land compensation value for the affected portion of land in ROW. More information on land use restriction and compensation payment is provided in Annex IMPACTS MITIGATION MEASURES Various mitigation measures have been proposed to minimize or neutralize the adverse impacts faced by the project affected families. In case of SPAFs, specific mitigation measures have been proposed in addition to normal livelihood improvement supports to be provided for all affected families. Keeping in view the social safeguard measures specified in the Operational Manual, 2009, the following impacts mitigation measures have been proposed. The eligibility of PAFs and SPAFs for different types of entitlements is provided in Annex 1, separate volume. i) Compensation of affected land and other properties at replacement value, and ii) Resettlement and Rehabilitation Assistances comprising of the followings; Cash assistance equal to minimum wage rate Transportation allowances Rental allowances Hardship allowances, and House construction allowance The details of the assistances designed for different types of affected groups are presented in the sections below Cash Assistance Equal to Minimum Wage Rate 10

15 In case of SPAFs losing more than 25% land, cash assistance equivalent to 6 months of minimum wage rate (Rs 200 for 75 working days in 6 months based on work opportunity available locally) amounting to Rs in total has been proposed. In total, 33 SPAFs of 3 districts will be entitled for this assistance which amounts to Rs with the lowest amount in Dhanusha and the highest in Ramechap district. This amount will be used by SPAFs to increase agricultural productivity and income to make up the deficit caused by reduced land holding size after the land acquisition by the Project. Table 4.5: Livelihood Restoration Measures to SPAFs Losing > 25% Land S.N. Districts SPAFs (No.) Minimum Agri. Wage (Rs) * Total 1 Sindhuli 10 15, ,000 2 Ramechap 20 15, ,000 3 Dhanusha 3 15,000 45,000 Total/Average 33 15, ,000 Source: Estimated based on minimum wage rate of GON. *In Nepal, the working opportunity in agriculture is low which is estimated to be 150 days a year. Based on this the SPAFs would have been provided employment for 75 days in 6 month time with a minimum wage rate of Rs 200/ day or Rs 15,000 within a period of 6 months which is slightly more than GON minimum wage rate of Rs 150/ day for unskilled labour as published in Nepal Gazette, 2008, notice of GON Resettlement and Rehabilitation (R&R) Assistances The latest figures reveal that a total of 53 families will be displaced from the place of their original residence. The R&R assistances include transportation cost, house rent, hardship allowance and house construction allowance which amounts to Rs per displaced family. The rationale behind paying these assistances to the displaced families or SPAFs is to extend them support during the period of their placement from one place to another place until their new residential structure is built and becomes usable for the family members. The amount of total R&R assistance to 53 SPAFs is estimated at Rs out of which only less than one third SPAFs have received part of this amount. In order to expedite the Project work, it is extremely important for the Project to pay the R&R assistances to the SPAFs that has been pending for several years. Table 4.6: R&R Assistances for Displaced SPAFs S.N. Districts SPAF s (No.) Transpo rtation Cost House Rent Assistances (Rs) Hardship Allowanc e House Constructio n Allowance Total All Total 1 Sindhuli Ramechap Dhanusha Total/ Average

16 Source: Estimated based on RAP and Operational Manual for Environmental and Social Assessment Framework Livelihood Restoration Package The Project requires to pay due attention to deliver package services aiming to improve the overall livelihoods of the affected families. This will be possible through enhanced level of skill training in agriculture and livestock sub-sector covering all affected families. Skill training in using agricultural inputs is normally useful for many rural households to optimize their crop productivity. It may include transfer of technical knowhow with updated information among farming households including males and females by imparting training and demonstration. Similarly, the technical knowhow in using agricultural inputs is also critical for many farming households which would help them to use appropriate amount of quality inputs viz improved seeds, pesticides, organic manure, irrigation etc. which would enhance their crop productivity and income. Training in crop diseases and their treatment is also of equal importance for farming households. Some households would prefer to receive skill training in livestock raising and veterinary services as a means of improving their income and livelihoods. Table 4.7: Livelihood Restoration Package for Project Affected Families (PAFs) S.N. Districts PAFs (No.) Skill Training * Agri. Inputs ** Total 1 Sindhuli Ramechap Dhanusha Total * Skill training cost is estimated at the rate of Rs 3000 per household. ** Agri inputs related training cost is estimated at the rate of Rs 1500 per household The livelihood restoration package is provisioned to all PAFs affected by the Project which figures out to 1080 in total although this figure may change slightly during the course of implementation. The executing agencies of these package services will require to work out detailed operational plans in coordination with the PAFs so that the services could be delivered as per the felt needs and interest of the peoples. 4.3 COMPENSATION PAYMENT A major mitigation measure to address the issue of adverse impacts (loss of land, houses, income sources etc.) caused by the project is through compensation of all losses at replacement value. The Compensation Determination Committee (CDC), which is a statutory body to determine the compensation rates, has already fixed the compensation amount for most of the losses in all districts except in ROW in Sindhuli district. The CDC which is formed in every district under the Chairmanship of Chief District Officer (CDO) takes into account the following references to determine the rates. Market rates of land prevailed in land transaction in the district Land rates fixed by the Land Revenue Office in the district Valuation of building (structures and other facilities) based on prevailing norms, and 12

17 Consultations with PAFs representatives. In KhimtiDhalkebar TL Project, compensation payment is still in progress and it was much delayed due to disputes between affected people and the Project. Compensation has been paid partially for all the affected assets i.e land and structures but some owners are still resisting accepting the compensation as some of them do not want the Project to be aligned through their areas. Most of the APs showed their concerns with potential health hazards on the belief that the high voltage TL Project would be the source of major diseases adversely affecting their reproductive system which would put them at great risk permanently. This is largely due to inadequate information dissemination consultations by the Project with the APs from the beginning. The Project s compensation payment status for different headings is shown in Table 4.8. The total compensation amount of the Project is a whopping Rs million and a much large percentage accounting nearly 95% is allocated for purchasing land for road in ROW. For rest others like land for tower pads, ROW land and structures, the amount of compensation is relatively low. Of the total compensation amount for road, there is still a major share which is yet to be settled. The details of compensation paid for land acquired for Tower Pads are provided in Annex 5. Table 4.8: Compensation Payment Status in the Project, March 2014 S.No. Districts PAFs (No.) Estimated Compensation Amount (Rs) Compensation Paid (Rs) Total Compensation Pending (Rs) All Total Tower Pads Row * Road Structures Total Tower Pad ROW Road Structures Total Paid (Rs) Tower Pads ROW Road Structures 1 Sindhuli Ramechap Dhanusha Total * In Sindhuli, the ROW compensation is calculated based on estimated number of Plots in ROW (220) and average amount of compensation of Rs per plot as the ROW land is not yet measured. On the whole only 60.8% compensation has been paid to PAFs in the Project and the payment figures differ significantly across the districts. In the Dhansha, the percentage of compensation paid is highest whereas the corresponding figure is lowest in Sindhuli where a significant amount is yet to be paid, mainly for the land acquired for road in the ROW. Table 4.9: Compensation Paid and Pending Amount S.No. Districts PAFs (No.) Total Total Compensati Compensati on Amount onpaid Total Pending Total Paid over Total Compensat ion Total due All Total (Rs) (Rs) (Rs) % % % 1 Sindhuli Ramechap Dhanusha Total

18 Given the high figure of compensation yet to be paid, the Project needs to expedite the process of payment as early as possible. The Project should hold intensive dialogues with the PAFs, inform them fully about Project s impacts on health and their livelihoods so that they would come ahead for collecting compensation. 4.4 CONSULTATIONS AND COUNSELING Continued consultation with the Project affected peoples (PAPs) is part of social planning and implementation. The Project should engage its field staff for regular consultations with the PAFs during the implementation of RAP so that the PAFs who are in problem to produce legal documents for claiming compensation and those having other problems can be supported closely by the Project s field based staff. The consultations will also provide opportunities to disseminate and share information about RAP and Project activities in advance which will be useful to create an enabling environment for both Project and people to work together. Equally important is the counselling services to the PAFs and SPAFs for utilizing the compensation amount received by them. In absence of timely counselling services, many PAFs receiving money against compensation often take wrong decisions to make proper use of the same with adverse impacts in their livelihoods. The victims of such PAFs would include children, women and elderly people who would face hardship to sustain their livelihoods. 4.5 VULNERABLE GROUPS In the changed context of the Project including its impacts to a larger group of households, an updated Vulnerable Community Development Plan (VCDP) has been prepared in parallel with this RAP. The updated VCDP suggests site and community specific potential activities and programmes based on the felt needs of the people living close to the transmission line alignment. The purpose of the VCDP is also to address the issues of broader communities rather than individuals who will be affected adversely by the Project. The settlements dominated by Indigenous Peoples (IPs) and Dalits are accorded priority in the VCDP including women of all caste/ ethnic groups. The implementation of VCDP, which is prepared in close consultations with the project affected peoples, will help improve the livelihoods of the people by improving their access to various essential physical facilities and services viz drinking water, minor irrigation, skill training, conservation of forest resources and so forth. In addition, the VCDP also consist of specific programs aimed to conserve the rich historical and religious sites of the project area. 4.6 DISCLOSURE The Project will require disclosing the updated RAP by 15 April The summary translated version (in Nepali language) of RAP along with the entitlement should be disclosed in soft and hard copy. The soft copy should be disclosed by posting in website of NEA and the Project. The hard copies should be made available in Project Offices in the site, the head office as well as in public places like VDCs, DDCs and Municipality where the general public will have easy access of the documents. 14

19 5.0 Institutional Arrangement, Implementation Schedule and Grievance Redressing 5.1 INSTTITUTIONAL ARRANGEMENT The overall responsibility of implementing this updated RAP lies with Nepal Electricity Authority and the Khimti-Dalkebar 220 kv Transmission Line Project. The CDC/ Project has major role in the valuation of affected properties, follow up of the grievances put forth by the PAPs and pay compensation and R&R assistances as well as providing livelihood restoration measures on time. The Environmental and Social Studies Department (ESSD) of NEA which was engaged since the beginning of Project implementation has to be reengaged fully and responsibly to implement the activities proposed in the updated RAP. ESSD will work in close coordination with the Project Manager and chief of the KDTL. The Communication Officer along with two Liaison Officers and project field staff will be responsible for facilitating RAP implementation including relocation of SPAFs who will be physically displaced. In addition, Project will be assisted by ESSD. ESSD will have to report the progress of RAP implementation on monthly basis for the remaining period of project implementation. 5.2 IMPLEMENTATION SCHEDULE The Project will implement all the activities proposed in the updated RAP by June 30, Any further delay in the implementation of RAP will not only prolong the issues but also cause delay for remaining construction works of the Project. The following timeframe is suggested to implement the RAP. Table 5.1 Proposed Implementation Schedule of RAP S.N. RAP Activities April May June Remarks Disclose the updated RAP == Summary in Nepali language 2 Complete compensation payment for land, structures, R&R assistances ======== ======= ====== Payment of pending amount 3 Hire competent NGOs to provide skill training and implementing livelihood options === ======= For livelihood restoration of PAFs 4 Continue consultations ======== ======= ====== 5 Provide counselling services ==== ======= ====== For utilizing the compensation for assets creation and income generation 15

20 5.3 GRIEVANCE REDRESS MECHANISM At Project level, an effective grievance redress mechanism will be established to allow project affected persons (PAPs) to file or appeal any disagreeable decisions, practices and activities with which they are not satisfied. As part of the grievance redress mechanism (GRM), the PAPs will be made fully aware of their rights and the procedures to follow and also file their grievances in writing accordingly. The PAPs will have unhindered access to the grievance redress officials to forward and file complains without being intimidated or being deterred by excessive bureaucratic hurdles. Furthermore, APs will be exempted from all administrative fees incurred, pursuant to the grievance redressed procedures except for cases filed in court. Proposed mechanism for grievance resolution has four stages as given below in the Box. Box-1: Stages of Grievance Redress Mechanism Stage 1: Stage 2: Stage 3: Stage 4: Communication Officer: Complaints of PAPs on any aspects affecting their properties, income and livelihoods adversely will be reported to the Communication Officer based in the field. The Official will review the grievance, visit the site if necessary to assess the issues and arrange meeting with the APs and other people in the community to settle the disputes informally or formally. Such meeting or consultation with the involvement of Communication Officer and village level leaders will be helpful to come up with a proper solution. It will be the responsibility of the Officer to resolve the issue within 15 days from the date of the complaint received. Communication officer will be assisted by two Liaison officers hired by project in this regard. Project Manager: If no understanding or amicable solution is reached or no response made from the Communication Officer as mentioned in Stage 1, the APs can appeal to the Project Manager with his complaint. The Project Manager will hold a joint meeting with the APs, the Project field staff and other concerned members of the community. The Project Manager, after hearing all the grievances and visiting the sites if necessary, will settle the grievance within 15 days after lodging the complaint to him. CDO: If the complaints or grievances of PAPs are not resolved at first and second stage mentioned above, the APs will directly approach to the Chief District Officer (CDO) who is also the Chairperson of the CDC. While lodging the complaints, the APs must produce adequate documents / proofs to support his/her grievances. The CDO or his staff will take the decisions within 15 days of registering the appeal and resolve the issues. District Court: If the APs are not satisfied with the decision of CDO or in absence of any response of its representatives within 15 days of the complaints filed, the APs, as his/her last resort, may appeal about the complaints and file the case to the court with the required evidences and documents as asked by the court. The court will be the final authority to take decision on the grievances within 35 days from the date of grievance field to him. 16

21 6.0 Estimated Budget The estimated budget for implementing complete RAP including the activities performed in the past is Rs million. Of this amount, significant amount of compensation has already been paid whereas the remaining amount is also quite significant. In addition, the cost for R&R assistances and livelihood restoration measures for SPAFs and PAFs is also quite notable. Table 6.1: Estimated Budget for Implementing the RAP S.N. Budget Headings Rs. Remarks 1 Compensation Payment 1.1 Tower Pads Based on Project s estimates 1.2 RoW Land do 1.3 Road (Full purchase)* do 1.4 Structures and R&R assistances do Sub total R&R Assistances to displaced SPAFs 2.1 R&R assistance (61 Rs per SPAF) Livelihood Restoration Support to 33 SPAFs losing more than 25% Rs per SPAF Sub total Livelihood Restoration of 1080 PAFs 3.1 Skill training in agriculture/ livestock Training for using agri. Inputs Sub total Compensation for Other Damages 4.1 Crop losses during construction Lumpsum 4.2 Loss of trees and fruits do Sub total Implementation Cost 51 NGO hiring for 6 months Lumpsum (for livelihood restoration and other training) 5.2 Communication and Information Dissemination Sub total All Total Contingency (5% of the total cost) Grand Total *The figure is based on the reported amount in a BTOR, December Preparation and distribution of IEC materials and campaigning 17

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Resettlement Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP June 2012 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Ghupa-Sanghu

More information

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= COMPENSATION,

More information

SECOND PROGRESS REPORT INDIA VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT (LOAN NO IN)

SECOND PROGRESS REPORT INDIA VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT (LOAN NO IN) INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION SECOND PROGRESS REPORT ON THE IMPLEMENTATION OF MANAGEMENT S ACTION PLAN IN RESPONSE TO THE INSPECTION PANEL

More information

CHAPTER-1: INTRODUCTION

CHAPTER-1: INTRODUCTION CHAPTER-1: INTRODUCTION 1.1 Background Nepal Electricity Authority (NEA) is constructing a 220 kv transmission line from Bharatpur to Bardaghat in Nepal to strengthen the power transmission network of

More information

Earthquake 2005 Recovery and Reconstruction

Earthquake 2005 Recovery and Reconstruction Earthquake 2005 Recovery and Reconstruction 2 Earthquake 8 Oct 2005 Nine Districts 1. MANSHERA 2. BATAGRAM 3. SHANGLA 4. ABBOTTABAD 5. KOHISTAN Epicentre 6. MUZAFFARABAD 7. NELUM 8. BAGH 9. RAWALAKOT Depth:

More information

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project Final Resettlement Monitoring Report Document stage: Final Project number: Loan 2517 May, 2017 VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote s Sector Project Sub-project:

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE . Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic

More information

Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community)

Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community) Community Managed Revolving Fund (Sustainable mechanism of microfinance practices to disadvantaged community) A paper presented in Micro Finance Summit 2008 New departure in expanding the outreach of Micro-finance

More information

CAO Investigation of IFC/MIGA Social and Environmental Performance in relation to:

CAO Investigation of IFC/MIGA Social and Environmental Performance in relation to: CAO COMPLIANCE CAO Investigation of IFC December 15, 2017 CAO Investigation of IFC/MIGA Social and Environmental Performance in relation to: Bujagali Energy Limited and World Power Holdings, Uganda (Bujagali-07)

More information

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Phase 3 Consultation in Indonesia January 26-28, 2016 Objective Illustrate

More information

GOVERNMENT OF KARNATAKA

GOVERNMENT OF KARNATAKA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF KARNATAKA Karnataka Urban Water Supply Modernization Project (KUWSMP) RESETTLEMENT

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Nepal Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2015 Seq No: 5 ARCHIVED on 28-Jun-2017 ISR28273 Implementing Agencies: Ministry of

More information

Planning, Budgeting and Financing

Planning, Budgeting and Financing English Version Planning, Budgeting and Financing Post-Disaster Recovery and Reconstruction Activities in Khammouane Province, Lao PDR Developed under the Khammouane Development Project (KDP), Implemented

More information

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening SFG1532 Public Disclosure Authorized AZERBAIJAN REPUBLIC Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY AZERBAIJAN MOTORWAY IMPROVEMENT

More information

Safeguards Monitoring Report

Safeguards Monitoring Report Safeguards Monitoring Report Semiannual Report Covering July-Dec 2016 period February 2017 (ESDIP) Tranche-2 Chimtala- Arghandi 220 kv DC Transmission Line Subproject (DABS - 006/ICB) Prepared by Da Afghanistan

More information

Overview of PADR process

Overview of PADR process SECTION 3 Overview of PADR process PADR is a methodology for use at community level. It involves active engagement, with the community, in a process to explore the risks they face and the factors contributing

More information

STEP 7. Before starting Step 7, you will have

STEP 7. Before starting Step 7, you will have STEP 7 Gap analysis Handing out mosquito nets in Bubulo village, Uganda Photo credit: Geoff Sayer/Oxfam Step 7 completes the gap-analysis strand. It should produce a final estimate of the total shortfall

More information

Notice of Entering into a Compact with the Federal Democratic Republic of Nepal

Notice of Entering into a Compact with the Federal Democratic Republic of Nepal This document is scheduled to be published in the Federal Register on 09/28/2017 and available online at https://federalregister.gov/d/2017-20847, and on FDsys.gov BILLING CODE 921103 MILLENNIUM CHALLENGE

More information

COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH

COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH Note: The following is based on the provisions of The Acquisition and Requisition of Immovable Property Ordinance

More information

Republic of Uzbekistan Project «Construction of new electrified railway Angren-Pap» World Bank SJSRWC «UzbekistonTemirYullari»

Republic of Uzbekistan Project «Construction of new electrified railway Angren-Pap» World Bank SJSRWC «UzbekistonTemirYullari» Republic of Uzbekistan SFG1338 v2 Project «Construction of new electrified railway Angren-Pap» World Bank SJSRWC «UzbekistonTemirYullari» Livelihood Restoration Plan for Persons Affected by Project Public

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: SAM 35132 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE INDEPENDENT STATE OF SAMOA FOR PREPARING THE SAVAI I RENEWABLE ENERGY PROJECT November 2002 CURRENCY

More information

Terms of Reference (ToR) Business Potential survey in Doti District

Terms of Reference (ToR) Business Potential survey in Doti District Terms of Reference (ToR) Business Potential survey in Doti District 1. Background Good Neighbors International (GNI) is an international humanitarian and development NGO in general consultative status

More information

Detailed Project Report. Devitar-Phulasi-Pokhari Road Subproject Ramechhap

Detailed Project Report. Devitar-Phulasi-Pokhari Road Subproject Ramechhap Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project Lalitpur, Nepal Earthquake Emergency Assistance Project

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/27/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

Education and Employment Status of Dalit women

Education and Employment Status of Dalit women Volume: ; No: ; November-0. pp -. ISSN: -39 Education and Employment Status of Dalit women S.Thaiyalnayaki PhD Research Scholar, Department of Economics, Annamalai University, Annamalai Nagar, India. Abstract

More information

UNITED REPUBLIC OF TANZANIA NATIONAL AGEING POLICY

UNITED REPUBLIC OF TANZANIA NATIONAL AGEING POLICY UNITED REPUBLIC OF TANZANIA NATIONAL AGEING POLICY MINISTRY OF LABOUR, YOUTH DEVELOPMENT AND SPORTS September, 2003 TABLE OF CONTENTS CHAPTER ONE PAGE 1. INTRODUCTION. 1 1.1 Concept and meaning of old

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

More information

Community Survey NEPAL - ROUND

Community Survey NEPAL - ROUND Community Survey NEPAL - ROUND 2 12. 09. 2015 The views expressed in this publication are those of the author(s) and do not necessarily reflect the views of the United Nations or DFID. This publication

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Birgunj Sub metropolitan City, Nepal

Birgunj Sub metropolitan City, Nepal Birgunj Sub metropolitan City, Nepal Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: - - Organization: - Title/Position: -

More information

BASELINE SURVEY ON REVENUE COLLECTION & STRATEGIES FOR IMPROVING LOCAL REVENUE IN PUNTLAND May- June 2013

BASELINE SURVEY ON REVENUE COLLECTION & STRATEGIES FOR IMPROVING LOCAL REVENUE IN PUNTLAND May- June 2013 BASELINE SURVEY ON REVENUE COLLECTION & STRATEGIES FOR IMPROVING LOCAL REVENUE IN PUNTLAND May- June 2013 Jointly Conducted by: Puntland Ministries of Interior and Finance Garowe 1 Acknowledgement The

More information

Bone Bolango, Indonesia

Bone Bolango, Indonesia Bone Bolango, Indonesia Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: Yusniar Nurdin Organization: BNPB Title/Position: Technical

More information

Mournag, Tunisia. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( )

Mournag, Tunisia. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( ) Mournag, Tunisia Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: Kamal Alelwy Organization: La ville de Mournag Title/Position:

More information

Palu, Indonesia. Local progress report on the implementation of the Hyogo Framework for Action ( )

Palu, Indonesia. Local progress report on the implementation of the Hyogo Framework for Action ( ) Palu, Indonesia Local progress report on the implementation of the Hyogo Framework for Action (2013-2014) Name of focal point: Yusniar Nurdin Organization: BNPB Title/Position: Technical Support Consultant

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 14-Jul-2014

More information

PRODUCTIVE SECTOR COMMERCE PDNA GUIDELINES VOLUME B

PRODUCTIVE SECTOR COMMERCE PDNA GUIDELINES VOLUME B PRODUCTIVE SECTOR COMMERCE PDNA GUIDELINES VOLUME B 2 COMMERCE CONTENTS n INTRODUCTION 2 n ASSESSMENT PROCESS 3 n PRE-DISASTER SITUATION 4 n FIELD VISITS FOR POST-DISASTER DATA COLLECTION 5 n ESTIMATION

More information

Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project

Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project Terms of Reference (TOR) For Final Evaluation & Outcome Assessment of Promotion of Sustainable Agriculture for Nutrition and Food Security (POSAN FS) Project Re-circulation date: 11/01/ Closing date: 18/01/

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-49320,IDA-H Jun ,274,997.95

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-49320,IDA-H Jun ,274,997.95 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021427 Public Disclosure Authorized Public Disclosure Authorized Project ID P112893 Country Nepal Project

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Bhutan Second Rural Access

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Prepared by Central Vietnam Power Projects

More information

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED THE REPUBLIC OF UGANDA REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA ELECTRICITY TRANSMISSION COMPANY LIMITED KARUMA INTERCONNECTION PROJECT FEASIBILITY STUDY FOR PERIOD 5 TH

More information

Palu, Indonesia. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( )

Palu, Indonesia. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( ) Palu, Indonesia Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: Yusniar Nurdin Organization: BNPB Title/Position: Technical

More information

VIE: Power Transmission Investment Program Tranche 3

VIE: Power Transmission Investment Program Tranche 3 Social Monitoring Report 2 nd Quarterly Report June 2017 VIE: Power Transmission Investment Program Tranche 3 Installation of a second transformer bank for 220 kv Duc Hoa substation Installation of a second

More information

Progress on the Strengthening of the European Integration Structures

Progress on the Strengthening of the European Integration Structures TENTH MEETING OF THE STABILISATION AND ASSOCIATION PROCESS TRACKING MECHANISM CONCLUSIONS PRISTINA, 14 JULY 2006 The tenth meeting of the Stabilisation and Association Process Tracking Mechanism was held

More information

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS July 13, 2015 Office of the Compliance Advisor Ombudsman (CAO) COMPLIANCE APPRAISAL: SUMMARY OF RESULTS IFC Investment in Bilt Paper B.V., Malaysia Project #34602 Complaint 01 Ballarpur International Graphic

More information

RESETTLEMENT ACTION PLAN

RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RESETTLEMENT ACTION PLAN for the Corridor Highway project Component 1 - Corridor Xd,

More information

Pidie Jaya, Indonesia

Pidie Jaya, Indonesia Pidie Jaya, Indonesia Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: Yusniar Nurdin Organization: BNPB Title/Position: Technical

More information

CASA-1000 Project List of FAQs

CASA-1000 Project List of FAQs 1. What is the objective of the project? CASA-1000 Project List of FAQs The objective of the CASA-1000 project is to provide for the export of the available summer electricity surpluses from Tajikistan

More information

Beirut, Lebanon. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( )

Beirut, Lebanon. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( ) Beirut, Lebanon Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Name of focal point: Bilal Hamad Organization: - Title/Position: - E-mail address:

More information

Impact of Deprived Sector Credit Policy on Micro Financing Presented by Nepal Rastra Bank

Impact of Deprived Sector Credit Policy on Micro Financing Presented by Nepal Rastra Bank Impact of Deprived Sector Credit Policy on Micro Financing Presented by Nepal Rastra Bank Introduction: The deprived sector credit policy is directed credit policy of Nepal Rastra Bank, which is designed

More information

USAID-Funded Nepal Hydropower Development Project (NHDP)

USAID-Funded Nepal Hydropower Development Project (NHDP) USAID-Funded Nepal Hydropower Development Project (NHDP) Facilitating investment in HPP: Balancing stakeholder interests in securing social license Kiran Vergis 23-Jan-2017 Kathmandu This document was

More information

Skardu, Pakistan. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (First Cycle)

Skardu, Pakistan. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (First Cycle) Skardu, Pakistan Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (First Cycle) Name of focal point: Habib Mughal Organization: UN-HABITAT - Pakistan Title/Position:

More information

FISCAL STRATEGY PAPER

FISCAL STRATEGY PAPER REPUBLIC OF KENYA MACHAKOS COUNTY GOVERNMENT THE COUNTY TREASURY MEDIUM TERM FISCAL STRATEGY PAPER ACHIEVING EQUITABLE SOCIAL AND ECONOMIC DEVELOPMENT IN MACHAKOS COUNTY FEBRUARY2014 Foreword This Fiscal

More information

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution.

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution. ANNEX ICELAND NATIONAL PROGRAMME 2012 1 IDENTIFICATION Beneficiary Iceland CRIS decision number 2012/023-648 Year 2012 EU contribution 11,997,400 EUR Implementing Authority European Commission Final date

More information

TERMS OF REFERENCE Final evaluation consultant AUP Project, Kayin State, Myanmar

TERMS OF REFERENCE Final evaluation consultant AUP Project, Kayin State, Myanmar TERMS OF REFERENCE Final evaluation consultant AUP Project, Kayin State, Myanmar 1. Background The European Union approved a project (February 2013 to April 2017) implemented by a consortium of HelpAge

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

with UNDP for the Union of the Comoros 25 June 2015 NDA Strengthening & Country Programming

with UNDP for the Union of the Comoros 25 June 2015 NDA Strengthening & Country Programming with UNDP for the Union of the Comoros 25 June 2015 NDA Strengthening & Country Programming PAGE 1 OF 12 Country (or region) Executive Summary (in one page) Union of the Comoros Submission Date 29/05/2015

More information

Program-for-Results Financing 1

Program-for-Results Financing 1 Operational Manual BP 9.00 - Program-for-Results Financing These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. BP 9.00 February, 2012

More information

Community-Based SME For Road Maintenance

Community-Based SME For Road Maintenance Community-Based SME For Road Maintenance Insights from the W.B and IADB-Peruvian Rural Roads maintenance contracts Project & Poverty Reduction Presented by Jacob Greenstein (EGAT) Scope of Presentation

More information

PUBLIC PRIVATE PARTNERSHIP IN NEPAL. Sushil Bhatta Member, National Planning Commission Government of Nepal

PUBLIC PRIVATE PARTNERSHIP IN NEPAL. Sushil Bhatta Member, National Planning Commission Government of Nepal PUBLIC PRIVATE PARTNERSHIP IN NEPAL Sushil Bhatta Member, National Planning Commission Government of Nepal 1 Outline Context Role of PPP in Infrastructure Evolution of Legal Framework for PPP PPP Practice

More information

Skardu, Pakistan. Local progress report on the implementation of the Hyogo Framework for Action (First Cycle)

Skardu, Pakistan. Local progress report on the implementation of the Hyogo Framework for Action (First Cycle) Skardu, Pakistan Local progress report on the implementation of the Hyogo Framework for Action (First Cycle) Name of focal point: Habib Mughal Organization: UN-HABITAT - Pakistan Title/Position: Manager

More information

BASELINE SURVEY OF MINORITY CONCENTRATION DISTRICT. Executive Summary of Leh District (Jammu and Kashmir)

BASELINE SURVEY OF MINORITY CONCENTRATION DISTRICT. Executive Summary of Leh District (Jammu and Kashmir) BASELINE SURVEY OF MINORITY CONCENTRATION DISTRICT Background: Executive Summary of Leh District (Jammu and Kashmir) The Ministry of Minority Affairs (GOI) has identified 90 minority concentrated backward

More information

India s model of inclusive growth: Measures taken, experience gained and lessons learnt

India s model of inclusive growth: Measures taken, experience gained and lessons learnt India s model of inclusive growth: Measures taken, experience gained and lessons learnt Dr. Pronab Sen Principal Adviser Planning Commission Government of India Macro Economic Context High Growth trajectory-

More information

SESSION SIX SUBSIDY AND INSTITUTIONAL FINANCING

SESSION SIX SUBSIDY AND INSTITUTIONAL FINANCING SESSION SIX SUBSIDY AND INSTITUTIONAL FINANCING SESSION SIX Subsidy And Institutional Financing 6.1 Introduction It was seen in the previous session that some benefits of a biogas plant accrue not only

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 02-Sep-2014

More information

Executive summary Siddharth Nagar

Executive summary Siddharth Nagar Executive summary Siddharth Nagar 1.1. Introduction: A Survey conducted by Centre Government highlighted the fact that as many as 90 districts, having minority concentration, are backward and of these

More information

Evaluation Approach Project Performance Evaluation Report for Loan 2167 and Grant 0006-SRI: Tsunami-Affected Areas Rebuilding Project September 2015

Evaluation Approach Project Performance Evaluation Report for Loan 2167 and Grant 0006-SRI: Tsunami-Affected Areas Rebuilding Project September 2015 Asian Development Bank 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org www.adb.org/evaluation Evaluation Approach Project Performance

More information

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road

Resettlement Plan. India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Resettlement Plan Document Stage: Draft Project Number: 41598 September 2013 India: National Capital Region Urban Infrastructure Financing Facility Project 1 - Bahadurgarh-Badli Road Prepared by the Haryana

More information

MIMAP-Nepal Poverty and Development Monitoring System & Decentralized Planning in Nepal

MIMAP-Nepal Poverty and Development Monitoring System & Decentralized Planning in Nepal MIMAP-Nepal Poverty Monitoring System & Decentralized Planning in Nepal Shiva Sharma (MIMAP-Nepal Team Leader) National Labour Academy-Nepal Anamnagar, Kathmu Phone: 977-1-268076, Fax: 977-1-248073 Email:

More information

SECURING THE SOCIETY IN SALUSIA

SECURING THE SOCIETY IN SALUSIA SECURING THE SOCIETY IN SALUSIA 1 PROBLEM STATEMENT As the advisor to the Finance Minister of Salusia, you have been tasked to recommend measures to address the challenges related to social security and

More information

Kansas Policy Survey: Spring 2001 Survey Results Short Version

Kansas Policy Survey: Spring 2001 Survey Results Short Version Survey Results Short Version Prepared by Chad J. Kniss with Donald P. Haider-Markel and Steven Maynard-Moody December 2001 Report 266B Policy Research Institute University of Kansas Steven Maynard-Moody,

More information

THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA NATIONAL POLICY AND STRATEGY ON DISASTER RISK MANAGEMENT. July 2013 Addis Ababa

THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA NATIONAL POLICY AND STRATEGY ON DISASTER RISK MANAGEMENT. July 2013 Addis Ababa THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA NATIONAL POLICY AND STRATEGY ON DISASTER RISK MANAGEMENT July 2013 Addis Ababa 1 Content 1. Introduction... 3 2. Policy Vision,Mission and Objectives... 4 3.Policy

More information

Expenditure Forecast Methodology

Expenditure Forecast Methodology Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box

More information

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project FINAL EVALUATION VIE/033 Climate Adapted Local Development and Innovation Project PROJECT SUMMARY DATA Country Long project title Short project title LuxDev Code Vietnam Climate Adapted Local Development

More information

RESTRUCTURING PAPER ON A SECOND PROPOSED PROJECT RESTRUCTURING DAKAR DIAMNIADIO TOLL HIGHWAY PROJECT CREDIT 4579-SN BOARD APPROVAL DATE JUNE 2, 2009

RESTRUCTURING PAPER ON A SECOND PROPOSED PROJECT RESTRUCTURING DAKAR DIAMNIADIO TOLL HIGHWAY PROJECT CREDIT 4579-SN BOARD APPROVAL DATE JUNE 2, 2009 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Country Department AFCF1 Africa Region Document of The World Bank RESTRUCTURING

More information

GEF SGP PROJECT PROPOSAL TEMPLATE AND GUIDELINES. Rwanda. [Date proposal]

GEF SGP PROJECT PROPOSAL TEMPLATE AND GUIDELINES. Rwanda. [Date proposal] GEF SGP PROJECT PROPOSAL TEMPLATE AND GUIDELINES Rwanda [Date proposal] i GENERAL REQUIREMENTS The Project Proposal should include the standard cover sheet, a one-page table of contents and not more than

More information

Science for DRM 2020: acting today, protecting tomorrow. Table of Contents. Forward Prepared by invited Author/s

Science for DRM 2020: acting today, protecting tomorrow. Table of Contents. Forward Prepared by invited Author/s : acting today, protecting tomorrow Table of Contents Forward Prepared by invited Author/s Preface Prepared by DRMKC Editorial Board Executive Summary Prepared by Coordinating Lead Authors 1. Introduction

More information

Dr. P.Velusamy Assistant Professor, Department of co operation, Sri Ramakrishna mission Vidyalaya College of arts and science, Coimbatore.

Dr. P.Velusamy Assistant Professor, Department of co operation, Sri Ramakrishna mission Vidyalaya College of arts and science, Coimbatore. ATTAINING THE MARKET THROUGH INNOVATIVE STRATEGIES A CASE STUDY ON KARIAMPALAYAM PRIMARY AGRICULTURAL COOPERATIVE SOCIETY-COIMBATORE DISTRICT-TAMILNADU Dr. P.Velusamy Assistant Professor, Department of

More information

(Unofficial Translation) NEPAL GAZETTE PART 2

(Unofficial Translation) NEPAL GAZETTE PART 2 (Unofficial Translation) NEPAL GAZETTE Published by Government of Nepal (Vol. 61) Kathmandu; 2068, Bhadra 23 (September 9, 2011) (Supplement 23) PART 2 Government of Nepal Ministry of Law and Justice The

More information

Results from a social protection technical assistance program. July 2011

Results from a social protection technical assistance program. July 2011 Results from a social protection technical assistance program July 2011 Political and Development Context Simultaneous transitions Conflict to peace Unitary system to a federal polity Monarchical, hierarchical

More information

Vietnam Central Highland Poverty Reduction Project Findings and Arrangements to Enhance Ethnic Minority Participation September 24, 2013

Vietnam Central Highland Poverty Reduction Project Findings and Arrangements to Enhance Ethnic Minority Participation September 24, 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized A. Overview Vietnam Central Highland Poverty Reduction Project Findings and Arrangements

More information

ITP Evaluation Process Plan

ITP Evaluation Process Plan ITP Evaluation Process Plan HVDC Conversion Project The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical data

More information

Continuum of Care (CoC) and Emergency Solutions Grant Program (ESG) 2015 Policy Manual

Continuum of Care (CoC) and Emergency Solutions Grant Program (ESG) 2015 Policy Manual Continuum of Care (CoC) and Emergency Solutions Grant Program (ESG) 2015 Policy Manual Table of Contents Overview 2 General Standards.. 3 CoC Standards 6 ESG Standards 7 Street Outreach 9 Shelter Services

More information

Tracking Government Investments for Nutrition at Country Level Patrizia Fracassi, Clara Picanyol, 03 rd July 2014

Tracking Government Investments for Nutrition at Country Level Patrizia Fracassi, Clara Picanyol, 03 rd July 2014 Tracking Government Investments for Nutrition at Country Level Patrizia Fracassi, Clara Picanyol, 03 rd July 2014 1. Introduction Having reliable data is essential to policy makers to prioritise, to plan,

More information

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT Himachal Pradesh Clean Energy Transmission Investment Program (RRP IND 43464) TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT A. INTRODUCTION 1. The

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Social Monitoring Report Final Report December 2016 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Prepared by the Southern

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents EXECUTIVE

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June 2017 IND: Green Energy Corridor and Grid Strengthening Project (320 kv VSC-HVDC power transmission lines between Pugalur, Tamil Nadu and North Trichur, Kerala) Annexures

More information

Karlstad, Sweden. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( )

Karlstad, Sweden. Local progress report on the implementation of the 10 Essentials for Making Cities Resilient ( ) Karlstad, Sweden Local progress report on the implementation of the 10 Essentials for Making Cities Resilient (2013-2014) Mayor: Ulf Nyqvist Name of focal point: -Anna -Sjödin Organization: -Karlstad Municipality

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4152 Second Madhya Pradesh District Poverty Initiatives Project Project Name

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4152 Second Madhya Pradesh District Poverty Initiatives Project Project Name Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4152 Second Madhya Pradesh

More information

Kind of Service: Electric Class of Service: As Applicable Docket No.: U Order No.: 19 Part IV. Rate Schedule No. 60 Effective: 3/31/16

Kind of Service: Electric Class of Service: As Applicable Docket No.: U Order No.: 19 Part IV. Rate Schedule No. 60 Effective: 3/31/16 4 th Revised Sheet No. 60.0.1 Schedule Sheet 1 of 14 Replacing: 3 rd Revised Sheet No. 60.0.1 60.0.0. EXTENSION OF FACILITIES 60.0.1. TABLE OF CONTENTS SECTION TITLE SCHEDULE SHEET 60.1. REGULATORY AUTHORITY

More information

Terms of Reference. Impact Assessment Study of

Terms of Reference. Impact Assessment Study of Terms of Reference For Impact Assessment Study of Partnership in Climate Services for Resilient Agriculture in India (PCSRA) ToR No: ABC122019XYZ Dated: 31-1-2019 Partnership in Climate Services for Resilient

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 29-Jan-2013

More information

A Case Study on Socio - Economic Conditions of Agricultural Labourers in Idaikal Village in Tirunelveli District. Dr. T.

A Case Study on Socio - Economic Conditions of Agricultural Labourers in Idaikal Village in Tirunelveli District. Dr. T. Volume: 3; No: 2; June-2017. pp 256-264. ISSN: 2455-3921 A Case Study on Socio - Economic Conditions of Agricultural Labourers in Idaikal Village in Tirunelveli District Dr. T. Vijayanthi Assistant Professor

More information

2018 Report. July 2018

2018 Report. July 2018 2018 Report July 2018 Foreword This year the FCA and FCA Practitioner Panel have, for the second time, carried out a joint survey of regulated firms to monitor the industry s perception of the FCA and

More information

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli)

ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN. Subproject: SH-70 (Gaya to Rajauli) ASIAN DEVELOPMENT BANK RESETTLEMENT PLAN Subproject: SH-70 (Gaya to Rajauli) BIHAR STATE HIGHWAYS PROJECT ROAD CONSTRUCTION DEPARTMENT (RCD) GOVERNMENT OF BIHAR FEBRUARY 2008 TABLE OF CONTENTS ITEM Page

More information

48081 v1. India: Andhra Pradesh Road Sector Project. Environmental and. Social Management Framework. For. Maintenance Road. (approx.

48081 v1. India: Andhra Pradesh Road Sector Project. Environmental and. Social Management Framework. For. Maintenance Road. (approx. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 48081 v1 India: Andhra Pradesh Road Sector Project Environmental and Social Management

More information

It was observed from the final SIA and SIMP reports, Capital City Master Plan, Infrastructure:

It was observed from the final SIA and SIMP reports, Capital City Master Plan, Infrastructure: AN APPRAISAL REPORT OF THE EXPERT GROUP CONSTITUTED FOR STUDY OF THE SOCIAL IMPACT ASSESSMENT REPORT OF KURAGALLU 1&2(v) The District Collector, Guntur, has constituted an Expert Group through the orders

More information

Amaravati Sustainable Capital City Development Project (ASCCDP) Revised Draft. Resettlement Action Plan for Flood Mitigation Works

Amaravati Sustainable Capital City Development Project (ASCCDP) Revised Draft. Resettlement Action Plan for Flood Mitigation Works Public Disclosure Authorized Amaravati Sustainable Capital City Development Project (ASCCDP) Public Disclosure Authorized Revised Draft Resettlement Action Plan for Flood Mitigation Works Public Disclosure

More information

DOCUMENT OF THE EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT STRATEGY FOR ALBANIA

DOCUMENT OF THE EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT STRATEGY FOR ALBANIA DOCUMENT OF THE EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT STRATEGY FOR ALBANIA REPORT ON THE INVITATION TO THE PUBLIC TO COMMENT 1. Overview of the public consultation process The objective of this

More information