Environmental Planning Statement

Size: px
Start display at page:

Download "Environmental Planning Statement"

Transcription

1 Operational Programmes for Malta Cohesion Policy Investing in Our Future This Project is being considered for European Union part-financing Operational Programme I Cohesion Policy Investing in Competitiveness for a Better Quality of Life Cohesion Fund Demolition of Existing Buildings and Construction of a Grade Separated Junction Triq M A Vassalli j/w Triq tas-sliema Gżira San Ġwann Msida MALTA PA/04917/09 Environmental Planning Statement Appendix Two C 30 July 2012 prepared by ERSLI Consultants Ltd on behalf of Transport Malta

2 Issue 3 30 May 2012 Ove Arup & Partners Ltd The Arup Campus Blythe Gate Blythe Valley Park Solihull West Midlands B90 8AE United Kingdom This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility is undertaken to any third party. Job number

3 Contents 1 Introduction 1 2 Design Options 2 Page 2.1 Option A Option B 2 3 Existing Data Traffic Data Accident Data 6 4 Traffic Modelling Introduction VISSIM Microsimulation VISSIM Modelling Modelling Period and Runs Calibration Outputs 11 5 Cost Estimations Construction Costs Maintenance Costs 14 6 Benefits Estimation Time Savings Accident Data Vehicle Operating Costs Carbon Emissions 20 7 Economic Appraisal 21 8 Financial Appraisal 23 9 Sensitivity and Risk Analysis Sensitivity tests Critical variables Switching Values Risk Analysis Appraisal Summary 30 J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCXJ:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX

4 Appendices Appendix A Scheme drawings Appendix B VISSIM Modelling Appendix C Calculations and CBA results J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCXJ:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX

5 1 Introduction Arup has been commissioned by the Joint Assistance to Support Projects in European Regions () to undertake an assessment of the Kappara Junction Project in Malta. is an existing at-grade roundabout linking Triq Mikiel Anton Vassalli with Triq Tas-Sliema. The junction has 4 arms and suffers from congestion during peak periods. As a part of the TEN-T project, it is proposed to upgrade this roundabout to ease congestion. This report sets out the undertaken for 2 options for the Kappara Junction upgrade. These 2 options are described in Section 2 of this report. Section 3 provides information regarding the traffic, turning movements and accident data for the Kappara Roundabout. Section 4 describes the traffic modelling, while section 5 summarises the estimated cost for each option. Section 6 provides the benefits resulting from the proposed schemes. Section 7 summarises the findings of the economic analysis. Section 8 provides the financial analysis of the scheme. Section 9 describes the sensitivity and risk analysis undertaken for the project. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 1

6 2 Design Options Two options are presented for the upgrade of the Kappara Roundabout. The drawings associated with each option are provided in Appendix A. 2.1 Option A Option A consists of a grade separated roundabout with an overpass joining the main flow. The overpass joins the traffic in both direction of the Triq Mikiel Anton Vassalli. Slip roads are provided to allow traffic interchange between Triq Tas-Sliema and Triq Mikiel Anton Vassalli. Drawing KAPP/PL/002 of Appendix A summarises Option A. 2.2 Option B Option B consists of removing the existing roundabout and replaces it by a free flow route along Triq Mikiel Anton Vassalli. The traffic interchange between Triq Tas-Sliema and Triq Mikiel Anton Vassalli is achieved by a proposed roundabout, signalised junction, bridge, and a number of slip roads. The proposed design is provided in Appendix A. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 2

7 3 Existing Data 3.1 Traffic Data A traffic survey for Kappara Roundabout was undertaken for the AM and PM peak hours. The AM peak hour survey was conducted in July 2010, while the only available survey for the PM peak hour was from July Table 3.1 describes the four arms on the roundabout. Table 3.1: Description of arms of Kappara Roundabout Arm Arm A Arm B Arm C Arm D Description Triq Mikiel Anton Vassalli - Northbound Triq Tas-Sliema - Eastbound Triq Mikiel Anton Vassalli - Southbound Triq Tas-Sliema - Westbound The traffic survey showed that for the AM peak hour, Triq Mikiel Anton Vassalli represents the major opposing links of the roundabout as illustrated in Table 3.2. Table 3.2: Distribution of AM traffic by arm Arm Arm A Arm B Arm C Arm D Percentage of Flow 40.5% 11.9% 38.3% 9.2% Table 3.3 shows the turning movements at the roundabout for the AM peak hour. This shows that the largest movements are between Arm A and Arm C, through traffic on Triq Mikiel Anton Vassalli, with 987 vehicles going from Arm C to Arm A and 1,579 vehicles in the opposite direction during the peak hour. Table 3.3: AM peak hour turning movements Arm Arm A Arm B Arm C Arm D Arm A Arm B Arm C 1, Arm D Table 3.4 presents the turning movements at the roundabout of all the incoming flow during the AM peak hour. Table 3.4: AM peak hour turning movement percentages Arm Arm A Arm B Arm C Arm D Arm A 2.2% 19.5% 53.0% 25.3% Arm B 62.6% 2.6% 2.9% 31.9% Arm C 89.7% 1.8% 0.7% 7.8% Arm D 63.1% 14.9% 21.3% 0.7% J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 3

8 Traffic survey data for the AM peak hour was provided by Transport Malta as well as the average annual daily traffic (AADT). This data was used to derive factors used to convert the AADT on each arm into an AM peak hour. These are provided in Table 3.5. Table 3.5: AM peak hour flow to AADT factors by turning movement Arm Arm A Arm B Arm C Arm D Arm A Arm B Arm C Arm D For the study in this report, it is assumed that the distribution of traffic and AM peak to AADT conversion factors shown in Tables 3.2 to 3.5 remain constant throughout the analysis. It has been assumed that traffic will increase at a rate of 1% per year. This assumption was based on advice from Transport Malta on standard growth rates currently used. Up until around 10 years ago, the standard annual traffic growth rate used by the Local Planning Authority (MEPA) when requesting Traffic Impact Statements (TIS) was 4% per annum, taken from the UK IHT s TIS guidelines. After collecting data over a period of several years from permanent traffic counters, the growth rate for Malta was established in 2002/3 as 2% per annum until 2010, dropping to 1.5% until However, in recent years it has become apparent, particularly on strategic roads, that these rates may be too high. In recent TISs, Transport Malta has accepted a 1% per annum growth rate when estimating traffic growth beyond the 5 th year of operation. Whilst traffic volume surveys are not yet available to confirm these figures, Transport Malta believe that this growth rate of 1% per annum is appropriate from their experience. Table 3.6 shows the AM peak hour traffic by arm throughout the appraisal period based on this growth assumption. Table 3.6: AM peak hour traffic by arm and year Arm Arm A 1,860 1,946 2,044 2,150 2,260 2,375 2,420 Arm B Arm C 1,760 1,831 1,926 2,024 2,126 2,235 2,278 Arm D Table 3.7 shows the PM peak hour turning movements based on the 2004 traffic count. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 4

9 Table 3.7: PM peak hour turning movements 2004 Arm Arm A Arm B Arm C Arm D Arm A , Arm B Arm C 1, Arm D A 1% traffic growth per year was applied to the traffic count in Table 3.7 to get from traffic flows in 2004 to traffic flows in 2010 (Table 3.8). The largest movements are between Arm A and Arm C, through traffic on Triq Mikiel Anton Vassalli, with 1,653 vehicles going from Arm C to Arm A and 1,314 vehicles in the opposite direction during the peak hour Table 3.8: PM peak hour turning movements 2010 Arm Arm A Arm B Arm C Arm D Arm A , Arm B Arm C 1, Arm D The traffic survey showed that for the PM peak hour, Triq Mikiel Anton Vassalli represents the major opposing links of the roundabout as illustrated in Table 3.9. Table 3.9: Distribution of PM traffic by arm Arm Arm A Arm B Arm C Arm D Percentage of Flow 51.25% 7.35% 27.58% 13.82% Table 3.10 presents the turning movements at the roundabout of all the incoming flow during the PM peak hour. Table 3.10: PM peak hour turning movement percentages Arm Arm A Arm B Arm C Arm D Arm A 1.1% 14.4% 59.0% 25.5% Arm B 59.1% 2.1% 5.5% 33.2% Arm C 87.1% 1.8% 1.0% 10.1% Arm D 46.2% 23.2% 27.7% 2.9% The AADT data was used to derive factors used to convert the AADT on each arm into an PM peak hour. These are provided in Table J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 5

10 Table 3.11: PM peak hour flow to AADT factors by turning movement Arm Arm A Arm B Arm C Arm D Arm A Arm B Arm C Arm D Table 3.12 shows the PM peak hour traffic by arm throughout the appraisal period based on this growth assumption. Table 3.12: PM peak hour traffic by arm and year Arm Arm A 2,804 2,947 3,097 3,255 3,421 3,595 3,668 Arm B Arm C 1,508 1,584 1,665 1,750 1,840 1,933 1,972 Arm D Accident Data Accident data for Kappara Roundabout were provided by Transport Malta for years between 2002 and Only the 5 most recent years were used in the cost benefit analysis. The data corresponding to the accidents in years 2004 to 2008 are presented in Table Table 3.13: Numbers of accidents over the period Year Accidents Fatal Serious Slight J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 6

11 4 Traffic Modelling 4.1 Introduction Time savings are one of the major benefits that need to be quantified in the cost benefit analysis. In order to compute the benefits resulting from time savings, one needs to determine the time of travel from an origin to a destination for the different appraised options. A number of options, ranging from simple calculations to software modelling, are available to determine the travel time. VISSIM microsimulation was adopted for traffic modelling of. 4.2 VISSIM Microsimulation VISSIM was selected as the modelling tool for the Kaparra Junction for its ability to capture the delays in travel time resulting from the interaction of the incoming flows on the arms with the circulation flow in the roundabout the additional distances for travel under Option B together with the effects of the proposed roundabout and signalised junction on traffic speed restrictions on the different links 4.3 VISSIM Modelling Three different models were generated for the, one corresponding to the existing roundabout, one for Option A, and one for Option B. Dynamic analysis was adopted in the modelling where the turning movements were taken to be the Origin Destination (OD) matrix. The same OD matrix was used for the 3 models. 4.4 Modelling Period and Runs The models were run for two time periods corresponding to the AM and PM peak hours. For each period, the model was run for a duration of 1.5 hours to allow 15min shoulder on both sides of the peak hour for the traffic to build up before the evaluation. The models were run with traffic flows for the years 2010, 2015, 2020, 2025, 2030, 2035, and Calibration Calibration is required to ensure that the modelling results are robust and can be used in the cost benefit analysis. The only available data for the are traffic counts conducted for the AM and PM peak hours. No other data such as queue length, or travel time are available. Therefore, the validation of the models will be based on the traffic flow. Tables 4.1 to 4.6 provide a comparison between actual and modelled flows for year They show that the modelled traffic is within 10% of the observed. This calibrates the models and therefore they will be used in the analysis. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 7

12 Table 4.1: AM peak hour flow for existing junction (actual/modelled) Arm Arm A Arm B Arm C Arm D Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A Arm B Arm C 1,579 1, Arm D Table 4.2: AM peak hour flow for Option A (actual/modelled) Arm Arm A Arm B Arm C Arm D Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A Arm B Arm C 1,579 1, Arm D J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 8

13 Table 4.3: AM peak hour flow for Option B (actual/modelled) Arm A Arm B Arm C Arm D Arm Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A Arm B Arm C 1,579 1, Arm D Table 4.4: PM peak hour flow for existing junction (actual/modelled) Arm Arm A Arm B Arm C Arm D Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A ,653 1, Arm B Arm C 1,314 1, Arm D J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 9

14 Table 4.5: PM peak hour flow for Option A (actual/modelled) Arm A Arm B Arm C Arm D Arm Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A ,653 1, Arm B Arm C 1,314 1, Arm D Table 4.6: PM peak hour flow for Option B (actual/modelled) Arm A Arm B Arm C Arm D Arm Observed Modelled Observed Modelled Observed Modelled Observed Modelled Arm A ,653 1, Arm B Arm C 1,314 1, Arm D J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 10

15 4.6 Outputs Travel Times calculated by VISSIM are used to quantify the time saving benefits or disbenefits. Travel Times are defined as the average travel time it takes a vehicle to move from one defined point to another. In additional to the time of travel, Travel Times include the waiting time resulting from queuing or stopping at the entry of roundabout to give way. Appendix B provides the VISSIM networks. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 11

16 5 Cost Estimations 5.1 Construction Costs A cost estimate for each of the options was made by Transport Malta in March Based on DG Regio Guidance and our experience in the preparation of application forms to the Cohesion Fund and European Regional Development Fund on behalf of other beneficiaries, the treatment of the capital costs used in economic and financial appraisal should be as follows: i. The total capital costs should be reflected in the economic appraisal, that is ineligible and well as eligible costs should be included ii. iii. iv. Contingencies should be excluded from the capital cost used to estimate the Economic Internal rate of Return and Economic Net Present Value1 VAT on eligible cost should be excluded (as this element of VAT is recoverable by Transport Malta)2. VAT on ineligible cost is included (as this element of VAT is not recoverable by Transport Malta). Table 5.1 and Table 5.2 summarise the cost breakdown. Table 5.1: Estimated construction costs for Option A and Option B in Item Option A Option B Preliminaries 351, , Site Clearance 101, , Road Restraint systems 330, , Drainage and Service Ducts 434, ,158, Earth Works 2,128, ,501, Pavement Works 1,021,148,32 1,583, Kerbs-Footpath-Paved Area 187, , Traffic Signs and Road Markings 21, , Road Lightings - CCTV 262, , Electric Works 105, , Structural Concrete 5,402, ,867, Bridge Expansion 486, , Special Structures 2,270, ,331, Blockwork and Stonework 2,873, , Shifting Cables 660, , Total (excluding VAT) 16,636, ,815, See Application Form footnote to section E Treatment of VAT in the major project applications. DG Regio Note 11 June J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 12

17 18% VAT 2,994, ,566, Total Including VAT (18%) 19,631, ,382, Table 5.2: Costs summary for Option A and Option B in Description Option A Option B 1 Eligible fees excluding VAT a Design fees 150, ,000 b Construction cost 17,096, ,466, c Supervision 800, , d Land acquisition 4,564, ,661, e Publicity 25, , f Geotechnical investigation 29, , g Contingency 2,266, ,313, h VAT 4,487, ,580, Ineligible excluding VAT 507, , a VAT 91, , Total cost including VAT 30,019, ,625, Total including nonrecoverable VAT excluding contingencies 23,265, ,731, J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 13

18 5.2 Maintenance Costs Maintenance costs for each option are derived based on the BCEOM study Final Report for Transport Infrastructure Projects in Malta. BCEOM distinguished between the maintenance costs for the existing roads and for newly constructed roads. In this CBA report, the total road surface area for the existing and for the proposed schemes is used to calculate the maintenance costs. The existing roundabout area is 1,800m². In Option A, the overpass will add additional road surface area of 6,000m². In Option B, the total road surface area including the scheme is 21,750m². As both options increase the surface area of road which needs to be maintained, total maintenance costs are higher with the scheme than they are currently. The maintenance strategy adopted in this study and based on the BCEOM report is as follows: For existing road o Periodic maintenance: In year 3 a wearing course overlay, followed by an overlay with scarifying in year 13, year 23, and every 10 years after o Routine maintenance: road cleaning, road marking, and culvert cleaning every year o Routine maintenance: crack sealing, and patching every year for 6% of the total road surface. In the years where overlay is undertaken, there is assumed to be no routine maintenance cost for crack sealing and patching. For new road/overpass o Periodic maintenance: 11 years then 21 years after an overlay using imported aggregate occurs. It is assumed that the first overlay takes place in year 10. o Routine maintenance: road cleaning, road marking, and culvert cleaning every year o Routine cleaning: crack sealing and patching for 1% of the total surface area of the road. In the years where overlay is undertaken, there is assumed to be no routine maintenance cost for crack sealing and patching. The cost for each item associated with road maintenance is provided in Table 5.3. Table 5.2 is adopted from the BCEOM study with costs converted to year 2010 prices 3. These costs exclude VAT. 3 Costs were converted to 2010 prices using the consumer price index for Malta taken from the IMF s World Economic Outlook database J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 14

19 Table 5.3: Maintenance cost breakdown, 2010 prices (excluding VAT) Description Cost ( /m 2 ) Cleaning, road markings and signs 1.24 Crack Sealing Patching Overlay Overlay with scarifying Overlay on new road 9.64 It has been assumed that as the road becomes older, the routine maintenance costs will increase. For crack sealing and patching, the cost increases by 2% each year until an overlay is undertaken, after which the cost returns to its original level. This applies to both the Do Nothing and the Do Something scenarios. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 15

20 6 Benefits Estimation The costs of both options for Kappara Roundabout are appraised against the resulting benefits. The main benefits quantified for the purpose of this report are the benefits of time savings, benefits of accident reduction, benefits of vehicle operation costs, and benefits of carbon emission. 6.1 Time Savings Under the proposed design in Option A, traffic on Triq Mikiel Anton Vassalli going in the north and south directions will use the overpass and therefore will not go through the roundabout. This will reduce the congestion on the roundabout and therefore results in time saving for all vehicles. With this arrangement, fewer cars will be using the roundabout resulting in time saving to these vehicles, and the overpass is designed to be free flowing (according to Transport Malta) therefore the vehicles using it will not encounter any delays. Under the proposed design in Option B traffic on Triq Mikiel Anton Vassalli going in the north and south directions will not go through the roundabout. This will eliminate the congestion currently encountered on the existing roundabout. Vehicles on Triq Tas-Sliema will use the proposed roundabout, signalised intersection, bridge, and slip roads. VISSIM micro-simulation software was used to quantify the travel time per vehicle using the roundabout and the overpass. The travel time per vehicle from its origin to its destination was obtained for the different modelled years. These were linearly interpolated to find out the delays corresponding to the other years. Note that the time saving per vehicle is quantified as the difference in the travel time between the existing situation and the proposed scenario. Speed limits were imposed on the different components of the model. For Option A, a 30kph limit was imposed on the gyratory, 50kph on the approach road, and 60kph on the overpass. For Option B, a 30kph limit was imposed on the approach to the roundabout and signalised intersection, 50km on the bridge, and 60km on the main road. The values of time used in this CBA were based on the Developing Harmonised European Approaches for Transport Costing and Project Assessment (HEATCO). Table 6.1 provides the values of time and journey purpose split between work and non-work. Table 6.1: Value of time and journey purpose split, per hour, 2002 values Description Work Non-work Average Value of Time ( /hr) Journey Split 15% 85% 100% The time savings calculation is presented in Appendix C. The following assumptions should be noted: A constant traffic growth of 1% per year is applied to the 2010 AADT The split of traffic at the different arms remains the same, throughout the appraisal period, as provided in Tables 3.4 and 3.10 J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 16

21 The traffic on the overpass is free flowing The journey split remains identical to the values in Table 6.1 throughout the appraisal period. It is assumed that no queuing on the overpass (Option A), and proposed Triq Mikiel Anton Vassalli road (Option B) takes place as a result of congestion elsewhere on the network The benefits have been calculated for one AM and one PM peak hour and each of these hours was then factored by 2 to reflect two AM and two PM peak hours as the most heavily trafficked periods. As traffic count data was only available for one hour in each peak period, a more accurate factor based on traffic volumes could not be calculated, but based on the consultants experience this is considered to be a reasonable assumption. Calculating benefits only for the peak hours is likely to be a conservative assumption as Transport Malta have indicated that day time traffic volumes in this area outside of the peak hours, particularly on working days, generally remain at least 50% of those in the peaks and at times this can result in pressures on the capacity of this junction. However delays would not be as great at lower traffic volumes as they are in the peaks and it has therefore been assumed that their contribution to the overall results would not be substantial and hence they have not been included in the analysis. 6.2 Accident Data The number of accidents is expected to decrease as a result of the proposed scheme. This is the direct result of the reduction of traffic flow due to the split of traffic between the different elements of the road network (roundabouts, overpass, bridge, etc ). Actual accident data, presented in Table 3.13, were used to generate a relationship between the number of accidents per year and the overall AADT of the Kappara Roundabout. The UK s Design Manual for Roads and Bridges (DMRB) suggests a relationship of the form Where A is the annual number of accidents f is a function of traffic flow and a and b are constant that varies with the type of roundabout. a should be calculated from actual accident data if they are available. For the Kappara Roundabout, the value of b is set at , while the value of a was computed from the actual accident data. The number of accidents per year for the Kappara Roundabout is estimated using the following equation: (1) 4 Based on DMRB J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 17

22 For the existing Kaparra Junction, the roundabout is assumed to be in a non-built up area with speed above 40mph (UK COBA Manual). Under Option A, a different accident rate is assumed for, where the roundabout is considered in a built up area with speed up to 40 mph (UK COBA Manual). This assumption is made to reflect the reduction in the traffic volume going through the roundabout as a result of Option A proposal. In Option B, where a new roundabout and signalised junction are constructed, values for a and b have been taken from DMRB, using the values for standard roundabouts with speeds of up to 40mph, 4 arms and a dual lane approach. This gives a value for a of and for the roundabout and signalised junction respectively, and for b of and for the roundabout and signalised junction respectively Accidents on the overpass, bridge and links were also quantified using the DMRB for Option A and Option B. The number of accidents on the link is related to the million vehicle km (mvk) multiplied by a personal injury accident rate (pia). The pia/mvk for the overpass is set at Therefore, the number of accidents on the links is obtained by The cost per accident was estimated based on values per casualty avoided in the Guide to Cost-Benefit Analysis on Investment Projects (European Commission 2008). The estimated value per casualty in 2002 prices are summarised in Table 6.2. Table 6.2: Estimated values for casualties avoided (2002 prices, ) Description Fatality Serious Injury Slight Injury Estimated Value ( ) 1,445, ,500 13,700 Equation (1) and (2) were used to estimate the number of accidents per year for the existing roundabout and the proposed Do Something options over the appraisal period. Different accident severity splits were adopted per accident based on COBA Manual. The benefits representing the savings due to the accident avoided are based on the difference in the numbers of accidents per year between the existing and the Do Something scenarios. The accident savings calculation is presented in Appendix C with the following assumptions: The existing Kappara Roundabout is assumed to be a roundabout with 4 arms and dual highest link standard. The approach velocity is assumed to be above 50kph The overpass Option A), and proposed Triq Mikiel Anton Vassalli road (Option B) are considered to be a modern road with a speed limit of 60kph The accident rates are assumed to be constant throughout the appraisal period (2) J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 18

23 6.3 Vehicle Operating Costs The vehicle operating costs (VOC) are based on a change in average travel speed. The VOC are split into two types, fuel and non-fuel. The fuel VOC is quantified based on the average fuel consumption. The relationship between speed (V) and fuel consumption (L) is given in the equation below Where a, b, c, and d are constant obtained from the UK s Transport Analysis Guidance (TAG) Unit Values of Time and Operation Costs 5. Table 6.3 provides the information used for the VOC benefits. Table 6.3: Fuel cost per litre (2010 prices) Description Petrol Diesel Pump Price (, 2010) VAT 18% 18% Fuel Tax 52% 42% Economic cost (, 2010) source The economic appraisal uses the resource cost of fuel, excluding the cost of fuel duty and VAT. The BCEOM study provides a split of vehicle between cars, light good vehicles (LGV), heavy good vehicle (OGV), and buses (PSV). Table 6.4 summarises this split Table 6.4: Vehicles split Vehicle Percentage Cars 90.0 LGVs 2.1 OGV1 4.6 OGV2 2.3 PSV 1.0 The non-fuel VOC is calculated using the formula C = a 1 + b 1 /V Where a 1 and b 1 are constants obtained from the UK s Transport Analysis Guidance (TAG) Unit Values of Time and Operation Costs (converted from pence to Euro cent), C is the cost per kilometre travelled and V is the average speed. Non fuel VOCs are made up of oil, tyres, maintenance depreciation and vehicle capital saving (for vehicles travelling in working time only). 5 Source: J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 19

24 The benefits from the VOC are calculated based on the following assumptions The split between petrol and diesel is adopted as set out in the UK s Transport Analysis Guidance (TAG) Unit The growth in the resource cost of petrol and diesel is as set out in the UK s Transport Analysis Guidance Unit The constants used in the non-fuel VOC formula do not change over time The traffic split presented in Table 6.4 is applicable for each year of the appraisal period The VOC calculations were performed for 4 hours corresponding to 2 AM peak hours and 2 PM peak hours 6.4 Carbon Emissions The change in carbon emissions has been calculated based on the amount of fuel consumed in the existing and with project scenarios over 4 hours corresponding to 2 AM peak hours and 2 PM peak hours. Fuel consumption has been calculated as described in section 6.3 above. The amount of carbon emitted for each litre of fuel consumed has been calculated using the values given in the UK s WebTAG guidance unit Values per tonne of carbon emitted have been taken from HEATCO deliverable 5, Chapter 6. As the values for carbon in HEATCO are given in 2002 prices, these have been converted to 2010 prices using the consumer price index for Malta. Other non-greenhouse gases and noise impacts have not been assessed quantitatively as part of this appraisal. Given the small magnitude of the carbon benefits the non-greenhouse gas and noise impacts are likely to be small. Qualitatively, Option B will bring traffic closer to some houses than it is currently due to the new roundabouts whereas in Option A the traffic will affect the same houses it does currently. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 20

25 7 Economic Appraisal A cost benefit analysis was performed for the proposed schemes. The benefits are represented by the savings resulting in time, accident, vehicle operating costs and carbon emission reductions. The costs are mainly the construction costs, land costs, and the maintenance costs. The CBA analysis results are provided in Appendix C. The following points should be noted when interpreting the CBA outputs. The appraisal period is 25 years from the opening year of 2014 (final appraisal year 2038) Constant 2010 prices are used Prices are discounted to 2012 values The appraisal has been carried out incrementally using the difference between the scenarios with and without the project The value of time and estimated cost per accident was assumed to increase throughout the appraisal period in relation to the forecasted gross domestic product per capita in Malta with an elasticity of 0.7 (as recommended in HEATCO Deliverable 5). The values for GDP per capita were obtained from the International Monetary Fund (IMF). The GDP per capita growth year on year and values of time are shown in Table 7.1. No forecasts were available beyond 2015 therefore growth has been assumed to continue at the same rate beyond this year. Table 7.1: GDP per capita growth and values of time (2010 values) GDP per capita growth 0.8% 0.9% 1.2% 1.6% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% Value of time ( /hr) GDP per capita growth 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% Value of time ( /hr) A discount rate of 5.5% was used in the appraisal The number of trips is assumed to be the same both with and without the project there is no generated traffic with the scheme VAT has been excluded from the economic analysis Residual values have been included for the road construction elements, which are assumed to have a 30 year life (5 years remaining at the end of the appraisal period) and for the drainage and retaining wall elements, which are assumed to have a 50 year life (25 years remaining at the end of the appraisal period) 6. All other elements are assumed to have no residual 6 Assumptions on the life are taken from HEATCO Deliverable 5. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 21

26 value, that it they have reached the end of their useful life by the end of the appraisal period. Table 7.2 summarises the CBA outputs Table 7.2: CBA summary results (values discounted to 2012) Description NPV Costs ( ) NPV Benefits ( ) NPV ( ) BCR EIRR (%) Option A 21,108,148 37,914,234 16,806, Option B 21,588,851 60,339,972 38,751, Table 7.3 presents the contribution of time savings, accident savings, and VOC to the overall benefits of each appraised option. Table 7.3: Benefits breakdown (% of total value of benefits when values discounted to 2010) Option Time Savings Accident Savings VOC Savings Carbon savings Option A 57.08% 34.12% 0.87% 0.07% Option B 81.84% 16.95% 1.10% 0.11% Both options result in additional road surface and therefore increased maintenance costs with the scheme. Table 7.3 shows that for Option A, over half of the benefits (57%) are generated from time savings, whilst accident savings make up approximately a third of the benefits. Vehicle operating costs and reductions in carbon emissions make up only a very small proportion of the benefits. For Option B, the majority of the benefits, (82%) comes from time savings. Accident savings account for further 17% of the benefits, whilst the contributions from vehicle operating costs and change in carbon emissions are limited. Both of the proposed options have good rates of return. However, Option B has the highest return on the investment at 16.5%, whilst for Option A the rate is 11.1%. Table 7.3 shows that most of the benefits, for both options, come from the time savings. These time benefits are the direct results of the time savings for the vehicles travelling along Triq Mikiel Anton Vassalli. The benefits from the vehicle operation costs and carbon emissions are limited due to the increase in the travel distances under the proposed schemes J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 22

27 8 Financial Appraisal A financial appraisal was carried out for the two proposed options. As there will be no revenues generated by the project, this appraisal includes the capital costs and maintenance costs only. The appraisal contains the following assumptions: The appraisal period is 25 from the opening year of 2013 Constant 2010 prices are used Costs include VAT at 18% Residual values have been included as described in section 7 above A discount rate of 5% was used in the financial appraisal The financial appraisal results are shown in Table 8.1. Table 8.1: Results of financial appraisal (values discounted to 2010) Description FNPV ) FIRR (%) Option A -24,460, Option B -26,307, As would be expected for a non revenue generating project of this nature, the FNPV and FIRR for both options are negative. The full financial appraisal for both options is shown in Appendix C. The funding gap calculations are shown below in Table 8.2 for Option A and Table 8.3 for Option B. However, as the project is not revenue generating, in accordance with the guidelines items 9 and 10 have been ignored and the funding gap set to 100%. Table 8.2: Funding gap calculation for Option A Main Elements and Parameters Value Not discounted Value Discounted (NPV) 1 Reference period (years) 25 2 Financial discount rate (%), real 5.0% 3 Total investment cost (in current euro, not discounted) 13,726,382 4 Total investment cost (in euro, discounted) 12,450,233 5 Residual value (in euro, not discounted) 2,943,105 6 Residual value (in euro, discounted) 788,306 7 Revenues (in euro, discounted) 0 8 Operating costs (in euro, discounted) 257,410 9 Net revenue (in euro, discounted) = (7) - (8) + (6) 10 Eligible expenditure [Art 55 (2)] (in euro, discounted) = (4) - (9) 11 Funding gap rate (%) = (10) / (4) % J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 23

28 Table 8.3: Funding gap calculation for Option B Main Elements and Parameters Value Not discounted Value Discounted (NPV) 1 Reference period (years) 25 2 Financial discount rate (%), real 5.0% 3 Total investment cost (in current euro, not discounted) 28,003,356 4 Total investment cost (in euro, discounted) 26,034,866 5 Residual value (in euro, not discounted) 3,514,000 6 Residual value (in euro, discounted) 941,219 7 Revenues (in euro, discounted) 0 8 Operating costs (in euro, discounted) 453,162 9 Net revenue (in euro, discounted) = (7) - (8) + (6) 10 Eligible expenditure [Art 55 (2)] (in euro, discounted) = (4) - (9) 11 Funding gap rate (%) = (10) / (4) % J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 24

29 9 Sensitivity and Risk Analysis 9.1 Sensitivity tests Sensitivity tests were carried out to check the impact of changes to different aspects of the economic and financial appraisals. These tests assessed the sensitivity of the NPV and IRR to changes in: 1. Scheme costs (plus 25% or minus 5%) 2. Maintenance costs (plus or minus 10%) 3. Traffic growth assumptions (plus 5% or minus 25% on the growth rate assumed in the Base scenario) 4. Accident reduction with scheme (plus 5% or minus 25% on the accidents number) The sensitivity tests have been carried out only on the preferred option, taken to be Option B as this has the higher rate of return. The tests demonstrated that the NPV and IRR are robust as shown in Table 9.1. Table 9.1: Results of the sensitivity tests (FNPV and ENPV discounted to 2010) Variable tested FIRR 9.2 Critical variables To test whether the variables tested in the sensitivity tests were critical variables, the change in NPV in response to a 1% change in the values of the input variables was calculated. To be considered a critical variable, the NPV should change by more than 1% (based on the threshold in EC guidance). The results are shown in Table 9.2. FIRR change FNPV FNPV change Table 9.2: Critical value analysis (ENPV and FNPV discounted to 2010) Critical value test ENPV ENPV change FNPV FNPV change Capital cost +1% 38,537, % -26,568, % Maintenance costs +1% 38,743, % -26,313, % Traffic growth +1% 38,849, % -26,307, % Accident reduction with scheme +1% 38,588, % -26,307, % EIRR EIRR change ENPV Base -8.36% -26,307, % 38,751,121 ENPV change Capital cost +25% -8.46% 1% -32,816,707 25% 13.58% -18% 33,403,106-14% Capital cost -5% -8.33% 0% -25,006,247-5% 17.28% 4% 39,820, % Maintenance costs +10% -8.48% 1% -26,365, % 16.52% 0% 38,670, % Maintenance costs -10% -8.25% -1% -26,256, % 16.55% 0% 38,823, % Traffic growth +5% -8.36% 0% -26,307, % 16.62% 0% 39,241, % Traffic growth -25% -8.36% 0% -26,307, % 16.34% -1% 37,936, % Accident reduction with scheme +5% -8.36% 0% -26,307, % 16.34% -1% 37,936, % Accident reduction with scheme -25% -8.36% 0% -26,307, % 16.13% -2% 36,371, % J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 25

30 On this basis, none of the variable are critical variables for the ENPV. The ENPV was most sensitive to a change in the capital costs, with a 1% change giving a 0.55% change in the ENPV. There are also no critical variables for the FNPV, which was most sensitive to a change in capital cost, with a 1% change in the capital cost resulting in a 0.99% change to the FNPV. 9.3 Switching Values No variables have been identified as being critical for the ENPV or FNPV. However, a switching value was calculated for the capital cost. The switching value is defined as the value that would have to occur for the NPV of the project to become zero. The FNPV of the scheme is million Euro (discounted to 2010) and for each 1% change in the capital cost the FNPV changes by 0.26 million Euro. Therefore for the FNPV to be equal to zero (and the project therefore to be able to cover its own costs), the capital cost would need to reduce by 100%. This is an impossible scenario. The ENPV of the scheme is 38.7 million Euro (discounted to 2010) and for each 1% change in the capital cost the FNPV changes by 0.39 million Euro. Therefore for the ENPV to be equal to zero, the capital cost would need to increase by 181.1%. This is an unlikely scenario 9.4 Risk Analysis A Monte Carlo risk analysis has been carried out for the ENPV and EIRR. The following variables shown in Table 9.3 have been identified as key change variables and used in the risk analysis. Table 9.3: Key change variables used in risk analysis Variable Minimum Maximum Capital cost -25% +5% Maintenance cost -10% +10% Traffic growth -25% +5% Accident reduction with scheme -25% +5% No correlation has been assumed between any of the variables tested. A triangular distribution has been assumed for each of the variables using the minimum and maximum values shown above. The probability distributions are based on our experience about a reasonable range of variables as there are no statistical data available. It is usual practice to use triangular probability distributions where risk is estimated by an expert or panel of experts. The simulation was run for 1,000 iterations. Probability density and cumulative probability distributions are shown for the ENPV in Figures 9.1 and 9.2 below. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 26

31 Cumulative probability Probability distribution Figure 9.1: Probability density distribution for ENPV Probability distribution for NPV NPV (million Euro) Figure 9.2: Cumulative probability distribution for ENPV 100% Cumulative probability distribution for NPV 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% NPV (Million Euro) The ENPV in the Base scenario is 38.7 million Euro (discounted to 2010). These results show that on the above assumptions, the probability that the ENPV will be negative is zero. Probability density and cumulative probability distributions are shown for the EIRR in Figures 9.3 and 9.4 below. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 27

32 Cumulative probability 14.00% 14.50% 15.00% 15.50% 16.00% 16.50% 17.00% 17.50% 18.00% Probability distribution Figure 9.3: Probability density distribution for EIRR 0.25 Probability distribution for EIRR EIRR Figure 9.4: Cumulative probability distribution for EIRR 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% Cumulative probability distribution for EIRR 0% 13.5% 14.5% 15.5% 16.5% 17.5% EIRR The EIRR in the Base scenario is 16.54%. These results show that on the above assumptions, the probability that the EIRR will be lower than the discount rate of 5.5% is zero. Summary statistics are shown in Tables 9.4 and 9.5 below. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 28

33 Table 9.4: Summary statistics for the risk analysis ENPV (mil Euro, discounted to 2010) Minimum Mean Maximum Mode Standard deviation EIRR (%) The risk analysis shows that even with pessimistic assumptions the project remains economically viable. Table 9.5: ENPV and EIRR risk analysis summary ENPV (mil Euro, discounted to 2010) 50 th percentile 5%/95% 10%/90% 25%/75% / / /39.64 EIRR (%) / / /16.66 J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 29

34 10 Appraisal Summary This report presents the feasibility of the two options being considered to update the Kappara Roundabout. In Option A the roundabout would be grade separated with an overpass carrying through traffic for Triq Mikiel Anton Vassalli. In Option B the traffic interchange between Triq Tas-Sliema and Triq Mikiel Anton Vassalli is achieved by a proposed roundabout, signalised junction, bridge, and a number of slip roads. The costs of the schemes are estimated at 23.3 million Euro for Option A and 23.7 million Euro for Option B, in 2010 prices including non recoverable VAT excluding contingencies. The economic appraisal has considered the benefits of the schemes in terms of time savings, accident savings, vehicle operating cost savings and changes in carbon emissions. Both options showed a good rate of return, 11.1% for Option A and 16.5% for Option B. Option B has the higher rate of return and is considered to be the better of the two options. As the scheme is not revenue generating, the financial appraisal showed negative rates of return for the two options, and the funding gap was set at 100%. The sensitivity and risk analysis has shown that the NPV and IRR are robust and even pessimistic assumptions are highly unlikely to undermine the economic viability of the scheme. J:\210000\ \4 INTERNAL PROJECT DATA\4-05 REPORTS\KAPPARA JUNCTION\APRIL 2012\KAPPARA JUNCTION - FS - ISSUE 3 MAY 2012.DOCX Page 30

35 Appendix A Scheme drawings

36

37 30.47 A Legend Existing building Existing kerb Contract Limit New boundary wall New kerb Ramp New road paint marking Zebra crossing Proposed Crash barriers Niche Bus stop shelter Survey sheets No. 5273, 5274,5473 and H G F E D C B A Issued for MEPA Issued for Information Issued for Information E.C.F J.M.R.Z.Oct.11 E.C.F S.P.D R.Z.Sept.11 E.C.F W.P.R.Z.Jun.11 Revision Alterations Drawn Checked Approved Date Proposed Niche PROJECT No : PROJECT No. 2 PROJECT TITLE : DEMOLITION OF EXISTING BUILDINGS AND CONSTRUCTION OF OVERPASS, INCLUDING THE RE-ALIGNMENT OF EXISTING ROAD (KAPPARA JUNCTION -EA15) DRAWING TITLE : PROPOSED LAYOUT DATE : FILE No : DRAWING No : 26th October 2011 RD/448/07/6 KAPP/BO/PL/001 SHEET SIZE SCALE : REVISION : A 1 1 : 500 C CHIEF OFFICER Ing. SIMON GRIMA ARCHITECT ROBERT ZERAFA CHECKED BY J. MERCIECA DRAWN BY SHEET No: E. C. FARRUGIA 5

THE COBA 2017 USER MANUAL PART 2 THE VALUATION OF COSTS AND BENEFITS. Contents. Chapter. 1. The Valuation of Time Savings

THE COBA 2017 USER MANUAL PART 2 THE VALUATION OF COSTS AND BENEFITS. Contents. Chapter. 1. The Valuation of Time Savings _ THE COBA 2017 UER MANUAL _ PART 2 THE VALUATION OF COT AND BENEFIT Contents Chapter 1. The Valuation of Time avings 2. The Valuation of Vehicle Operating Costs 3. The Valuation of Accidents 4. The Valuation

More information

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million) Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) ECONOMIC ANALYSIS A. Project Costs 1. This chapter outlines the methodology and results of the economic analysis for the project, comprising

More information

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA Contents Chapter 1. The COBA Method 2. The Do-Minimum and Do-Something Options 3. The Fixed Trip Matrix 4. Discounting and the Price Basis 5.

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction Bridge Replacement for Improved Rural Access Sector Project (RRP PNG 43200) ECONOMIC ANALYSIS A. Introduction 1. The economic analysis of the proposed project has been carried out in accordance with ADB

More information

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

Draft Environmental Impact Statement. Appendix G Economic Analysis Report Draft Environmental Impact Statement Appendix G Economic Analysis Report Appendix G Economic Analysis Report Economic Analyses in Support of Environmental Impact Statement Carolina Crossroads I-20/26/126

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

Project Appraisal Guidelines for National Roads Unit Guidance on using COBALT

Project Appraisal Guidelines for National Roads Unit Guidance on using COBALT Project Appraisal Guidelines for National Roads Unit 6.4 - Guidance on using COBALT October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is

More information

11,879 NPV=PVB-PVC Benefit to Cost Ratio (BCR) BCR=PVB/PVC

11,879 NPV=PVB-PVC Benefit to Cost Ratio (BCR) BCR=PVB/PVC Analysis of Monetised Costs and Benefits (,000) Present Value of Benefits (PVB - 000's) 13,358 Present Value of Costs (PVC - 000's) 1,479 Net Present Value (NPV - 000's) 11,879 NPV=PVB-PVC Benefit to Cost

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Additional Financing of National Motorway M-4 Gojra Shorkot Khanewal Section Project (RRP PAK 48402) ECONOMIC AND FINANCIAL ANALYSIS A. General 1. Roads are the main mode of transport in Pakistan, accounting

More information

Lancashire County Council. A682 Centenary Way Viaduct Refurbishment Scheme. Benefit Cost Analysis and Gross Value Added Assessment Technical Note

Lancashire County Council. A682 Centenary Way Viaduct Refurbishment Scheme. Benefit Cost Analysis and Gross Value Added Assessment Technical Note Lancashire County Council A682 Centenary Way Viaduct Refurbishment Scheme Benefit Cost Analysis and Gross Value Added Assessment Technical Note March 2015 Document Control Sheet BPP 04 F8 Version 15; March

More information

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD 1 Introduction The objective of the cost benefit economic analysis is to identify and quantify the benefits and costs associated with the project. This

More information

Project Appraisal Guidelines for National Roads Unit Minor Projects ( 0.5m to 5m)

Project Appraisal Guidelines for National Roads Unit Minor Projects ( 0.5m to 5m) Project Appraisal Guidelines for National Roads Unit 14.0 - Minor Projects ( 0.5m to 5m) February 2017 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII)

More information

The evaluation of traffic microsimulation modelling

The evaluation of traffic microsimulation modelling Urban Transport 769 The evaluation of traffic microsimulation modelling D. O Cinnéide & B. O Mahony Traffic Research Unit, University College Cork, Ireland Abstract In recent years, traffic simulation

More information

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

Economic Analysis Concepts

Economic Analysis Concepts Economic Analysis Concepts Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds

More information

The accuracy of traffic microsimulation modelling

The accuracy of traffic microsimulation modelling Urban Transport XII: Urban Transport and the Environment in the 21st Century 277 The accuracy of traffic microsimulation modelling D. O Cinneide & D. Connell Traffic Research Unit, University College Cork,

More information

Greenlane East Interchange/Great South Road Improvements. Approved Organisation: NZTA (HNO) and Auckland Transport (Auckland City Council)

Greenlane East Interchange/Great South Road Improvements. Approved Organisation: NZTA (HNO) and Auckland Transport (Auckland City Council) Post implementation reviews completed in 2011/12 Reviews represent the views of independent consultants and are used by the NZTA to identify potential opportunities for improvements. Greenlane East Interchange/Great

More information

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number:

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number: Project Summary This project summary page details the benefit cost analysis (BCA) for the Route 37 Corridor Safety Sweep Project. A BCA provides estimates of the anticipated benefits that are expected

More information

I-75 at Overpass Road Interchange

I-75 at Overpass Road Interchange Benefit-Cost Analysis Supplementary Documentation TIGER Grant Program I-75 at Overpass Road Interchange Pasco County, FL October 16, 2017 0 Benefit-Cost Analysis Supplementary Documentation 1. Introduction

More information

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive Western Regional Road Corridor Investment Program (RRP MON 41193) A. Project Costs and Benefits ECONOMIC ANALYSIS 1. Project Costs. The project s capital costs include the costs of the road works, design,

More information

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 Appendix 6 ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 1. Background. The Second Rural Connectivity Investment Program will support the Government of India in improving rural connectivity through the

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360) A. Background ECONOMIC AND FINANCIAL ANALYSIS 1. The province of Khyber Pakhtunkhwa in northwest Pakistan covers almost six degrees

More information

32 nd Street Corridor Improvements

32 nd Street Corridor Improvements Benefit-Cost Analysis Supplementary Documentation TIGER Discretionary Grant Program 32 nd Corridor Improvements USDOT TIGER BCA Results City of Joplin, MO April 29, 2016 32nd Corridor Improvements Contents...

More information

Department for Transport. Transport Analysis Guidance (TAG) Unit Guidance on Rail Appraisal

Department for Transport. Transport Analysis Guidance (TAG) Unit Guidance on Rail Appraisal Department for Transport Transport Analysis Guidance (TAG) Unit 3.13.1 Guidance on Rail Appraisal August 2007 1 Contents 1 Introduction 3 1.1 Background 3 1.2 Scope and Structure 3 2 SRA Appraisal Criteria

More information

PUBLIC INQUIRY QUESTION

PUBLIC INQUIRY QUESTION M4 Corridor around Newport PUBLIC INQUIRY QUESTION REFERENCE NO. : PIQ/164 RAISED BY: The Inspector DATE: 26/02/2018 RESPONDED BY: Matthew Jones DATE: 20/03/2018 SUBJECT: List of questions from the Inspectors

More information

Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities. Municipal Funding Agreement Guide.

Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities. Municipal Funding Agreement Guide. Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities Municipal Funding Agreement Guide January 2010 Administered by: Association of Municipalities of Ontario 200 University

More information

This update fully addresses the issues raised by DfT in its response to the February 2008 submission.

This update fully addresses the issues raised by DfT in its response to the February 2008 submission. Executive Summary Introduction 1. This document forms the Major Scheme Business Case (MSBC) submission to the Department for Transport (DfT), seeking Programme Entry for Croxley Rail Link. It is the culmination

More information

APP/P2.1/ECO. Economic Case Main Proof of Evidence Neil Chadwick

APP/P2.1/ECO. Economic Case Main Proof of Evidence Neil Chadwick Economic Case Main Proof of Evidence Neil Chadwick PROOF OF EVIDENCE NEIL CHADWICK ECONOMIC CASE/VALUE FOR MONEY TRANSPORT AND WORKS ACT 1992 MIDLAND METRO (WOLVERHAMPTON CITY CENTRE EXTENSION) ORDER

More information

Proiect cofinanțat de Uniunea Europeană prin Fondul European de Dezvoltare Regională

Proiect cofinanțat de Uniunea Europeană prin Fondul European de Dezvoltare Regională www.ampost.ro Proiect cofinanțat de Uniunea Europeană prin Fondul European de Dezvoltare Regională Transportation Government of Romania Ministry of Transport September 2013 Romania General Transport Master

More information

TECHNICAL NOTE. 1 Purpose of This Document. 2 Basic Assessment Specification

TECHNICAL NOTE. 1 Purpose of This Document. 2 Basic Assessment Specification TECHNICAL NOTE Project MetroWest Phase 1 Modelling & Appraisal Date 23 rd July 2014 Subject MetroWest Phase 1 Wider Impacts Assessment Ref 467470.AU.02.00 Prepared by CH2MHILL 1 Purpose of This Document

More information

Annex A TUBA Time Savings Summary

Annex A TUBA Time Savings Summary Annex A TUBA Time Savings Summary Annex A: TUBA Time Savings Summary Profile of Time Benefits The scale of discounted benefits over time is shown in the two figures below for both the full and no decay

More information

CBA of transport infrastructure projects in Germany

CBA of transport infrastructure projects in Germany CBA of transport infrastructure projects in Germany Dr. Catharina Horn Federal Transport Infrastructure Planning, Investment Policy Paris, 27th of February 2014 www.bmvi.de 1. The Federal Transport Infrastructure

More information

HDM-4 Applications. Project Appraisal. Project Formulation. Maintenance Policy Optimization. Road Works Programming. Network Strategic Analysis

HDM-4 Applications. Project Appraisal. Project Formulation. Maintenance Policy Optimization. Road Works Programming. Network Strategic Analysis HDM-4 Applications HDM-4 Applications Project Appraisal Project Formulation Maintenance Policy Optimization Road Works Programming Network Strategic Analysis Standards & Policies 2 Project Appraisal Concerned

More information

Tampa Bay Express Planning Level Traffic and Revenue (T&R) Study

Tampa Bay Express Planning Level Traffic and Revenue (T&R) Study Tampa Bay Express Planning Level Traffic and Revenue (T&R) Study Project Report FPN: 437289-1-22-01 Prepared for: FDOT District 7 February 2017 Table of Contents Executive Summary... E-1 E.1 Project Description...

More information

Roads Economic Decision Model (RED)

Roads Economic Decision Model (RED) Roads Economic Decision Model (RED) March 2006 Rodrigo Archondo-Callao The World Bank RED Objectives Simplify the economic evaluation of unpaved roads Better capture the economic benefits of a project

More information

A Summary of Changes to the HS2 Economic Case

A Summary of Changes to the HS2 Economic Case A Summary of Changes to the HS2 Economic Case April 2011 Contents 1 Introduction 4 2 Cost Changes 6 3 Appraisal Changes 7 4 Summary of Changes 9 Annex 1: Capital Costs 10 Annex 2: Operating Costs 13 Annex

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Chittagong-Cox s Bazar Railway Project, Phase 1 (RRP BAN 46452-002) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS 1. The proposed project will construct 102

More information

Highway Engineering-II

Highway Engineering-II Highway Engineering-II Chapter 7 Pavement Management System (PMS) Contents What is Pavement Management System (PMS)? Use of PMS Components of a PMS Economic Analysis of Pavement Project Alternative 2 Learning

More information

APP/P2.1 Neil Chadwick Economic Case/Value for Money Main Proof of Evidence

APP/P2.1 Neil Chadwick Economic Case/Value for Money Main Proof of Evidence APP/P2.1 APP/P2.1 Neil Chadwick Economic Case/Value for Money Main Proof of Evidence PROOF OF EVIDENCE FOR WEST MIDLANDS COMBINED AUTHORITY NEIL CHADWICK, DIRECTOR STEER DAVIES GLEAVE ECONOMIC CASE/VALUE

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Railway Rolling Stock Project (RRP BAN 49094) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves procurement of 214 meter gauge (MG) passenger carriages, 50 broad gauge (BG) passenger

More information

Long-Term Monitoring of Low-Volume Road Performance in Ontario

Long-Term Monitoring of Low-Volume Road Performance in Ontario Long-Term Monitoring of Low-Volume Road Performance in Ontario Li Ningyuan, P. Eng. Tom Kazmierowski, P.Eng. Becca Lane, P. Eng. Ministry of Transportation of Ontario 121 Wilson Avenue Downsview, Ontario

More information

Implementing the MTO s Priority Economic Analysis Tool

Implementing the MTO s Priority Economic Analysis Tool Implementing the MTO s Priority Economic Analysis Tool presented at 6th National Conference on Transportation Asset Management presented by Alison Bradbury Ontario Ministry of Transportation November 2,

More information

Alleviating Traffic Congestion in Manila, Appraisal of the Pasig Expressway. Baher El-Hifnawi Cambridge Resources International Inc.

Alleviating Traffic Congestion in Manila, Appraisal of the Pasig Expressway. Baher El-Hifnawi Cambridge Resources International Inc. Alleviating Traffic Congestion in Manila, Appraisal of the Pasig Expressway Baher El-Hifnawi Cambridge Resources International Inc. Glenn P. Jenkins Queen s University, Kingston, Canada. Eastern Mediterranean

More information

I-44/US-75 Interchange and Related Improvements on I-44 in Tulsa County

I-44/US-75 Interchange and Related Improvements on I-44 in Tulsa County I-44/US-75 Interchange and Related Improvements on I-44 in Tulsa County Cost-Effectiveness Analysis Supplementary Documentation FASTLANE Discretionary Grant Program I-44/US-75 Interchange and Related Improvements

More information

CEN/P2.1/ECO. Economic Case / Value for Money Main Proof of Evidence Neil Chadwick

CEN/P2.1/ECO. Economic Case / Value for Money Main Proof of Evidence Neil Chadwick Economic Case / Value for Money Main Proof of Evidence Neil Chadwick PROOF OF EVIDENCE NEIL CHADWICK ECONOMIC CASE / VALUE FOR MONEY CASE TRANSPORT AND WORKS ACT 1992 MIDLAND METRO (BIRMINGHAM CITY CENTRE

More information

Assessment of Wider Economic Impacts for the Wellington Northern Corridor RoNS. FINAL REPORT Version 1.0. Submitted by Richard Paling Consulting

Assessment of Wider Economic Impacts for the Wellington Northern Corridor RoNS. FINAL REPORT Version 1.0. Submitted by Richard Paling Consulting Assessment of Wider Economic Impacts for the Wellington Northern Corridor RoNS FINAL REPORT Version 1.0 Submitted by Richard Paling Consulting August 2013 Assessment of Wider Economic Impacts for the Wellington

More information

Options for Breich Station. Appraisal Report

Options for Breich Station. Appraisal Report Options for Breich Station Appraisal Report Updated document dated August 2017 Contents Executive Summary 3 Introduction and Objectives 5 Scheme Options and Base Case 8 Costs and Benefits 11 Appraisal

More information

CE 561 Lecture Notes. Transportation System Performance. Set 4. -interaction between demand and supply Demand

CE 561 Lecture Notes. Transportation System Performance. Set 4. -interaction between demand and supply Demand CE 561 Lecture Notes Set 4 Transportation System Performance -interaction between demand and supply Demand p, Price p 0 D 3 = α βp p 1 D 2 D 1 0 1, Vol. Short-run change in demand due to change in price

More information

Hot Springs Bypass Extension TIGER 2017 Application. Benefit-Cost Analysis Methodology Summary

Hot Springs Bypass Extension TIGER 2017 Application. Benefit-Cost Analysis Methodology Summary TIGER 2017 Application Overview This project proposes to extend the Hot Springs Bypass (US 70/US 270) from US 70 to State Highway 7 in Garland County, Arkansas. The 5.5 mile facility will initially consist

More information

ECONOMIC ANALYSIS. Table 1: Economic costs by project component

ECONOMIC ANALYSIS. Table 1: Economic costs by project component Jiangxi Fuzhou Urban Integrated Infrastructure Improvement Project (RRP PRC 44007) A. Project Costs and Benefits ECONOMIC ANALYSIS 1. The project s capital costs include the civil works, land acquisition

More information

Phase 2 Preliminary Business Case. Appendix E Wider Impacts Report

Phase 2 Preliminary Business Case. Appendix E Wider Impacts Report Phase 2 Preliminary Business Case Appendix E Wider Impacts Report July 2015 MetroWest Phase 2 MetroWest Phase 2 Preliminary (Strategic Outline) Business Case Wider Economic Impacts Prepared for West of

More information

Project Appraisal Guidelines

Project Appraisal Guidelines Project Appraisal Guidelines Unit 9.0 Post Project Review August 2011 Project Appraisal Guidelines Unit 9.0 Post Project Review Version Date Comments 1.0 August 2011 New Guidance This document is available

More information

Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support

Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support Massimo Marra JASPERS Networking and Competence Centre IPA Conference Impact Assessment What can we

More information

DEVELOPMENT OF THE LINSIG MICROSIMULATION TOOLKIT ABSTRACT

DEVELOPMENT OF THE LINSIG MICROSIMULATION TOOLKIT ABSTRACT DEVELOPMENT OF THE LINSIG MICROSIMULATION TOOLKIT ABSTRACT This paper will introduce the conceptualisation, development and delivery of a new software interface between widely used microsimulation modelling

More information

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources Weston Package Phase 1 Major Scheme Business Case 6 The Financial Case Scheme cost, financial risk and funding sources 6.1 Introduction This Section sets out how the council proposes to finance the Weston

More information

Appendix J Western Corridor Regeneration Scheme. Benefits Realisation Plan & Monitoring and Evaluation Plan

Appendix J Western Corridor Regeneration Scheme. Benefits Realisation Plan & Monitoring and Evaluation Plan Appendix J Western Corridor Regeneration Scheme Benefits Realisation Plan & Monitoring and Evaluation Plan April 2014 [Final Report] Strategic Transportation Planning Torbay Council 2nd Floor Electric

More information

Economic impact of the National Cycle Network

Economic impact of the National Cycle Network Economic impact of the National Cycle Network This report identifies some of the benefits of the National Cycle Network (NCN), from the wider economic benefits of the whole network to the impact on the

More information

Project Economic and Financial Appraisal & Risk Analysis: A focus on GCF Funding Proposal

Project Economic and Financial Appraisal & Risk Analysis: A focus on GCF Funding Proposal Project Economic and Financial Appraisal & Risk Analysis: A focus on GCF Funding Proposal Obadiah K. Mungai Chief Environmental Economist & Chair NIE/AE Steering Committee NEMA Outline GCF s Investment

More information

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Reviewing and Approving TYNDP A Regulatory Perspective Evangelos Penglis Partner, VIS Economic & Energy Consultants 08/12/2017

More information

Cowal Gold Project Addendum to the Transport of Hazardous Materials Study

Cowal Gold Project Addendum to the Transport of Hazardous Materials Study Cowal Gold Project Addendum to the Transport of Hazardous Materials Study On 7 February 2017 the Cowal Gold Project s (the Project) Development Consent (DA 14/98) was modified to reflect approval of the

More information

Welsh Government Great Western Main Line Electrification - Cardiff to Swansea Demand Forecasting and Economic Appraisal Technical Note

Welsh Government Great Western Main Line Electrification - Cardiff to Swansea Demand Forecasting and Economic Appraisal Technical Note Great Western Main Line - Cardiff to Swansea Demand Forecasting and Economic Appraisal Technical Note 117300-82 Issue May 2012 Ove Arup & Partners Ltd 4 Pierhead Street Capital Waterside Cardiff CF10 4QP

More information

Manual Cost Benefit Analysis

Manual Cost Benefit Analysis Republic of Serbia MINISTRY OF INFRASTRUCTURE Manual Cost Benefit Analysis Republic of Serbia Reference R20100299/31275000/ABU/EGR Version 6.0 Zoetermeer, December 2010 R20100299.doc Preface Serbia is

More information

Presentation at Asian Highways Investment Forum. Performance based Maintenance Contracts for Highways

Presentation at Asian Highways Investment Forum. Performance based Maintenance Contracts for Highways Presentation at Asian Highways Investment Forum Bangkok, 8-9, October 2013 United Nations Economic & Social Commission For Asia & The Pacific Performance based Maintenance Contracts for Highways By Atul

More information

Purpose. 2 Third Crossing Business Plan

Purpose. 2 Third Crossing Business Plan Business Plan April 18, 2017 Purpose This is the third of three information sheets on critical pieces of work related to the preliminary design and business plan development for the Third Crossing. This

More information

Appendix 1 In-Depth Checks

Appendix 1 In-Depth Checks Appendix 1 In-Depth Checks The following appendix sets out the In-Depth Checks undertaken by the Department for the 2016 Quality Assurance Report. The three projects/programmes selected for review are:

More information

TSHWANE BRT: Development of a Traffic Model for the BRT Corridor Phase 1A Lines 1 and 2

TSHWANE BRT: Development of a Traffic Model for the BRT Corridor Phase 1A Lines 1 and 2 TSHWANE BRT: Development of a Traffic Model for the BRT Corridor Phase 1A Lines 1 and 2 L RETIEF, B LORIO, C CAO* and H VAN DER MERWE** TECHSO, P O Box 35, Innovation Hub, 0087 *Mouchel Group, 307-317,

More information

Economic Assessment of a Fixed Link across the Fehmarn Belt

Economic Assessment of a Fixed Link across the Fehmarn Belt Danish Ministry of Transport Economic Assessment of a Fixed Link across the Fehmarn Belt Summary Report March 2004 in cooperation with Danish Ministry of Transport Economic Assessment of a Fixed Link across

More information

Benefit Cost Analysis for the San Juan Multi-Modal Transportation System: Infrastructure and Safety Improvements

Benefit Cost Analysis for the San Juan Multi-Modal Transportation System: Infrastructure and Safety Improvements Benefit Cost Analysis for the San Juan Multi-Modal Transportation System: Infrastructure and Safety Improvements Final Submitted to: April 24, 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...3 INTRODUCTION...5

More information

This report was produced by Atkins Ltd for the Highways Agency for the specific purpose of a Meta-analysis of POPE findings.

This report was produced by Atkins Ltd for the Highways Agency for the specific purpose of a Meta-analysis of POPE findings. December 2008 Notice This report was produced by Atkins Ltd for the Highways Agency for the specific purpose of a Meta-analysis of POPE findings. This report may not be used by any person other than the

More information

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Corridors of Commerce DRAFT Scoring and Prioritization Process Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Project Purpose To develop and implement a scoring and project

More information

Traffic Impact Analysis Guidelines Methodology

Traffic Impact Analysis Guidelines Methodology York County Government Traffic Impact Analysis Guidelines Methodology Implementation Guide for Section 154.037 Traffic Impact Analysis of the York County Code of Ordinances 11/1/2017 TABLE OF CONTENTS

More information

ENVIRONMENT AND TRANSPORT

ENVIRONMENT AND TRANSPORT EUROPEAN COMMISSION REF Nº:... ANNEX D PROJECT TITLE:.. THE COHESION FUND - 000-006 APPLICATION FOR ASSISTANCE COUNCIL REGULATION (EC) N 64/94 of 6 May 994 COUNCIL REGULATION (EC) N º 64/99 of June 999

More information

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM Frequently Asked Questions SMEC COMPANY DETAILS SMEC Australia Pty Ltd Sun Microsystems Building Suite 2, Level 1, 243 Northbourne Avenue, Lyneham ACT

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

Methodology for CBA preparation SOP Environment

Methodology for CBA preparation SOP Environment Methodology for CBA preparation SOP Environment Programming Meeting for water and wastewater projects in the period 2008-2009 Mamaia, 10-13 th July 2008 Massimo Marra JASPERS Regional Office for Romania

More information

Energy Conservation Resource Strategy

Energy Conservation Resource Strategy Energy Conservation Resource Strategy 2008-2012 April 15, 2008 In December 2004, EWEB adopted the most recent update to the Integrated Electric Resource Plan (IERP). Consistent with EWEB s three prior

More information

Review of Operating Expenses

Review of Operating Expenses Review of Operating Expenses Workstream Report 31 March 2011 Page 1 of 14 Table of contents 1 Executive Summary... 1 2 Summary of Business Case... 2 2.1 Summary of Business Case content relating to workstream...

More information

Economic Implications of Selection of Long-Life versus Conventional Caltrans Rehabilitation Strategies for High-Volume Highways

Economic Implications of Selection of Long-Life versus Conventional Caltrans Rehabilitation Strategies for High-Volume Highways Economic Implications of Selection of Long-Life versus Conventional Caltrans Rehabilitation Strategies for High-Volume Highways Draft report prepared for the CALIFORNIA DEPARTMENT OF TRANSPORTATION Division

More information

The Implementation of Engineering Economy in the Transport Development - A Case Study of Road Transport

The Implementation of Engineering Economy in the Transport Development - A Case Study of Road Transport Abstract The Implementation of Engineering Economy in the Transport Development - By Winner Yousman The engineering economy is a part of skill and knowledge of cost engineering could be applied in many

More information

PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT

PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT Pruethipong Singhatiraj 1, Chatchai Chuangching 1 and Boonkua Janbanjong 1 1 Department of Highways,

More information

Title of Document Greater Dublin Area Draft Transport Strategy Task Order 61 Outline Transport User Benefits Assessment

Title of Document Greater Dublin Area Draft Transport Strategy Task Order 61 Outline Transport User Benefits Assessment DOCUMENT IDENTIFICATION TABLE Client/Project owner National Transport Authority Title of Document Greater Dublin Area Draft Transport Strategy 2015-2035 Task Order 61 Task Outline Transport User Benefits

More information

Keswick to Penrith Railway

Keswick to Penrith Railway Keswick to Penrith Railway Stage 2 Report: H6-08 Keswick to Penrith Railway Stage 2 Report: JMP CONSULTING MINERVA HOUSE, EAST PARADE, LEEDS, LS1 5PS. T 0113 244 4347 F 0113 242 3753 E leeds@jmp.co.uk

More information

Important Note. Airport Authority Hong Kong

Important Note. Airport Authority Hong Kong Important Note Airport Authority Hong Kong (AAHK) is responsible for preparing the Hong Kong International Airport (HKIA) Master Plan 2030 and commissioning the associated consultancies. At different stages

More information

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E.

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. Texas Research and Development Inc. 2602 Dellana Lane,

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction North Pacific Regional Connectivity Investment Project (RRP PAL 46382) ECONOMIC ANALYSIS A. Introduction 1. Project summary. The Asian Development Bank (ADB) will support Palau to develop a fiber optic

More information

REPORT TO RAC WA JANUARY 2018 MOTORIST TAXATION REVENUE AND ROAD SPENDING IN WESTERN AUSTRALIA

REPORT TO RAC WA JANUARY 2018 MOTORIST TAXATION REVENUE AND ROAD SPENDING IN WESTERN AUSTRALIA REPORT TO RAC WA JANUARY 2018 MOTORIST TAXATION REVENUE AND ROAD SPENDING IN WESTERN AUSTRALIA ACIL ALLEN CONSULTING PTY LTD ABN 68 102 652 148 LEVEL NINE 60 COLLINS STREET MELBOURNE VIC 3000 AUSTRALIA

More information

Preparing a Cost Benefit Analysis and Cost-Effectiveness Analysis

Preparing a Cost Benefit Analysis and Cost-Effectiveness Analysis Preparing a Cost Benefit Analysis and Cost-Effectiveness Analysis 2017 CEF Transport SESAR call Information Day - 19 October 2017 Julien Bollati Financial Engineering Manager INEA - Innovation and Networks

More information

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 6 Implementation Plan

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 6 Implementation Plan SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP Module 6 Implementation Plan Sustainable Urban Mobility Plans: Delivery & Implementation Plans Identifying phased approach to delivery and programming

More information

EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS

EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS EXECUTIVE SUMMARY EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS by Stephen A. Cross, P.E. Associate Professor University of Kansas Lawrence, Kansas and Robert L. Parsons, P.E. Assistant

More information

DMP (Decision Making Process)

DMP (Decision Making Process) DMP (Decision Making Process) Office of Systems Analysis Planning Road School March 7, 2007 Driving Indiana s Economic Growth *** Please note: This is derived from the United States Military Decision Making

More information

Vocational Qualifications (QCF, NVQ, NQF) CPC (Certificate of Professional Competence)

Vocational Qualifications (QCF, NVQ, NQF) CPC (Certificate of Professional Competence) Vocational Qualifications (QCF, NVQ, NQF) CPC (Certificate of Professional Competence) Level 3 CPC (Certificate of Professional Competence) for Transport Managers (International Passenger Transport) -

More information

Deliverable 5 Proposal for Harmonised Guidelines

Deliverable 5 Proposal for Harmonised Guidelines Contract No. FP6-2002-SSP-1/502481 HEATCO Developing Harmonised European Approaches for Transport Costing and Project Assessment Specific Support Action PRIORITY SSP 3.2: The development of tools, indicators

More information

Alchemy Economics the UK government s conjuring trick to justify airport expansion"

Alchemy Economics the UK government s conjuring trick to justify airport expansion Alchemy Economics the UK government s conjuring trick to justify airport expansion" Prepared by: Keith Buchan of Transport Climate Commissioned by WWF-UK June 2008 Page 1 of 6 Alchemy Economics the UK

More information

analysis The,.inclusion of benefits from reduced accident rates in highwa cos5bne'fit liti-e

analysis The,.inclusion of benefits from reduced accident rates in highwa cos5bne'fit liti-e : '. r, ', ' :',. ' ' '. '. ;..... p. -(. ' i ' - -:(,:, '. ; "'- -.-;" ;.......:" ' ".. :-',-.; ',, ' ' -.. TRANSPORT RESEARCH LABORATORY I A I N 3 R ' -.; - liti-e The,.inclusion of benefits from reduced

More information

DRAFT TREASURE ISLAND FINANCIAL MODELING & ANALYSIS DOCUMENTATION MEMORANDUM

DRAFT TREASURE ISLAND FINANCIAL MODELING & ANALYSIS DOCUMENTATION MEMORANDUM DRAFT TREASURE ISLAND FINANCIAL MODELING & ANALYSIS DOCUMENTATION MEMORANDUM PREPARED FOR: PREPARED B Y: JULY 21, 2016 55 TABLE OF CONTENTS Table of Contents... 2 Table of Figures... 4 Table of Tables...

More information

Wichelstowe Southern Access

Wichelstowe Southern Access On behalf of Swindon Borough Council Project Ref: 24177/5511 Rev: AA Date: January 2018 Office Address: Caversham Bridge House, Waterman Place, Reading, Berkshire RG1 8DN T: +44 (0)118 950 0761 E: reading@peterbrett.com

More information

DRAFT MEMORANDUM -- For Discussion Purposes Only. James R. Musbach and Garrett K. Gray. Subject: Nevada State College Financing Program; EPS #18067

DRAFT MEMORANDUM -- For Discussion Purposes Only. James R. Musbach and Garrett K. Gray. Subject: Nevada State College Financing Program; EPS #18067 DRAFT MEMORANDUM -- D RAFT M EMORANDUM To: From: NSC Committee James R. Musbach and Garrett K. Gray Subject: Nevada State College Financing Program; EPS #18067 Date: April 8, 2009 Introduction Economic

More information

Risk Approach to Prioritising Maintenance Risk Factors for Value Management

Risk Approach to Prioritising Maintenance Risk Factors for Value Management Transport Research Laboratory Risk Approach to Prioritising Maintenance Risk Factors for Value Management by R Abell CPR966 2/462_155 CLIENT PROJECT REPORT Transport Research Laboratory CLIENT PROJECT

More information

Attached we are sending you the JASPERS Independent Quality Review Report for the above mentioned project.

Attached we are sending you the JASPERS Independent Quality Review Report for the above mentioned project. To the attention of Mr Jerzv Solecki Director of the ERDF Department Marshall Office of the Silesian Voivodeship ul. Ligonia 46 40-037 Katowice Poland Luxembourg, 13 December 2016 SG/AS/JASPERS/2016-1574/AA/HG/mla

More information

Capital Project Business Case Gilden Way Upgrading, Harlow

Capital Project Business Case Gilden Way Upgrading, Harlow Capital Project Business Case Gilden Way Upgrading, Harlow The template This document provides the business case template for projects seeking funding which is made available through the South East Local

More information