San Pedro Elementary School Community Town Hall Meeting #1 March 22, 2017 MINUTES

Size: px
Start display at page:

Download "San Pedro Elementary School Community Town Hall Meeting #1 March 22, 2017 MINUTES"

Transcription

1 H Y HIBSER YAMAUCHI Architects, Inc. San Pedro Elementary School Community Town Hall Meeting #1 March 22, 2017 MINUTES Date: March 22, 2017 Chair(s): tbd Time: 6:00 7:00 PM Scribe: Tim Steele School Site: San Pedro Elementary School Address: 498 Pt. San Pedro Rd., San Rafael, CA Attendees: Andrea Alonzo (AA) Architects, Inc. Architect David Flores (DF) San Pedro Elementary School, Parent Shane Franco (SF) San Pedro Elementary School, Teacher Felicita Hernandez (FH) Design Committee, Parent Mimi Melodia (MM) San Pedro Elementary School, Principal Mark Van Pelt (MVP) Van Pelt Construction Services, President Pete Norgaard (PN) Van Pelt Construction Services, V.P. of Operations Terese Sladowska (TS) Van Pelt Construction Services, Design Manager Tim Steele (TTS) Architects, Inc., Architect Patricia Talke (PT) San Pedro Elementary School, Teacher Dan Zaich, Ed.D. (DZ) SRCS, Senior Director Capital Facilities Schedule: Town hall meeting: 1. March 29 th at 6:00 7:00 pm (parents) New Business: Town hall meeting: Community members were not present during the presentation. HY team presented to Mimi Melodia, Dan Zaich, and Terese Sladowska. Action Required: No action is required Proposed Option 3 Layout for Two-Story Modular HY presented option 3 with newly added conference room for Mimi. Action Required: HY to modify option 3 layout to move conference room closer to her office.

2 San Pedro Elementary School Page 2 of 2 Site Design Committee - Minutes 03/22/ Fire Lane Dan Zaich would like to see if a fire lane can go around entire campus. Action Required: HY to provide a study for Dan to see if a fire lane can fit around entire campus Future Meetings Design committee meetings are complete. Last town hall meeting on March 29 th with the parents. HY will present interim housing layout, option 3 layout, architectural elevations, and 3D perspectives. Action Required: HY to send PowerPoint in advance of the next town hall meeting for translator to review. End of Minutes

3 SAN RAFAEL CITY SCHOOLS SIGN-IN SHEET SRCS Bond Measure A & B Site Name: San Pedro Elementary School Meeting Community Town Hall Meeting #1 Name: Date March 22, 2017 Time: 6:00 7:00 pm Print Name Signature Company Name Phone Address Marie (Mimi) Melodia San Pedro Elementary School, Principal (415) mmelodia@srcs.org David Flores Design Committee, Parent (415) Floresranch31@gmail.com Shane Franco San Pedro Elementary School, Teacher (415) sfranco@srcs.org Felicita Hernandez Design Committee, Parent (415) hernandezsara.211@yahoo.com Patricia Talke Design Committee, SPES Teacher (415) ptalke@srcs.org Pete Norgaard Van Pelt Construction Services (707) pete@vpcsonline.com Terese Sladowska Van Pelt Construction Services (707) terese.sladowska@vpcsonline.com Dan Zaich, Ed.D. San Rafael City Schools, Senior (415) dzaich@srcs.org Director Capital Facilities Tim Steele Architects, Inc. (510) tsteele@hy-arch.com Architect Andrea Alonzo Architects, Inc. 510) aalonzo@hy-arch.com Page 1 of 2

4 SAN RAFAEL CITY SCHOOLS SIGN-IN SHEET Print Name Signature Company Name Phone Address Page 2 of 2

5 S A N P E D R O E L E M E N TA R Y S C H O O L P R O G R A M F O R N E W M A I N B U I L D I N G A N D I N T E R I M H O U S I N G HIBSER YAMAUCHI Architects, Inc.

6 WELCOME! We are pleased to present the planned improvements at our school. Let us introduce ourselves

7 WELCOME! Our team includes: San Pedro Elementary School Design Committee Marie Melodia, Principal David Flores, Parent Shane Franco, Teacher Felicita Hernandez, Parent Patricia Talke, Teacher The District Team & Van Pelt Construction Services Dan Zaich, Ed.D., Senior Director Capital Facilities, SRCS Mark van Pelt President, VPSC Pete Norgaard V.P. of Operations, VPCS Terese Sladowska Design Manager, VPCS Architects, Inc. & Consultants Tim Steele, Architect Andrea Alonzo, Job Captain Mark Sorensen, Civil Engineer Underwood & Rosenblum Tiffany Kane, Electrical Engineer WHM Consulting Linda Gates, Landscape Architect Gates Associates

8 T h e n e e d f o r i m p r o v e m e n t s : San Pedro Elementary School has been a neighbor in the community since Over 60 years! It is a wonderful school site, nestled into the hill. Unfortunately, it has many needs. The main building is obsolete and many classrooms in portables need a permanent home.

9 T h e n e e d f o r i m p r o v e m e n t s : All of the Kindergarten classrooms are 30% smaller than the minimums set by the California Department of Education. Also, none have individual restrooms for these youngest children, also required by the Education Code.

10 T h e n e e d f o r i m p r o v e m e n t s : The Main administration office is tiny and cramped. This is the main waiting area for visitors, students, and parents. It is also for anyone waiting to see the Principal. It is too small to serve the needs of the school.

11 T h e n e e d f o r i m p r o v e m e n t s : There are too few staff restrooms. One is so small it is hard to fit inside to take a picture!

12 T h e n e e d f o r i m p r o v e m e n t s : The infrastructure needed to serve 21 st Century learning is far beyond its useful life.

13 T h e n e e d f o r i m p r o v e m e n t s : Ten portables are used to house classrooms and school programs. These decade-old temporary buildings have reached the end of their serviceable lives. They reduce the space needed for the playground. And they re an eyesore!

14 T h e D i s t r i c t B o n d P r o g r a m : To address the needs of San Pedro and other schools, several steps have been taken: Facility assessments and master planning were completed at the end of 2014 San Rafael voters generously approved Bond Measures A & B in November, 2015 Design for San Pedro Elementary School started at the beginning of 2017

15 T h e p r o j e c t a h e a d : Bond funds at San Pedro will do the following: Replace the main classroom / administration building and portables with one new building Provide a temporary home for offices and classrooms while the new building is built Restore the fields and playgrounds.

16 T h e p r o j e c t a h e a d : So here are the specifics

17 C A M P U S E L E M E N T S T O B E R E L O C AT E D O R D E M O L I S H E D EXISTING (2) PORTABLES TO BE RELOCATED FOR INTERIM HOUSING EXISTING ADMIN AND CLASSROOM BUILDING TO BE DEMOLISHED EXISTING (8) PORTABLES TO BE REMOVED ONCE NEW BUILDING IS CONSTRUCTED AND INTERIM HOUSING IS REMOVED

18 E X I S T I N G S T R E E T F R O N TA G E C O N D I T I O N S Main classroom / administration building to be replaced

19 E X I S T I N G C A M P U S C O N D I T I O N S KINDER PLAYGROUND PORTABLES BY ADMIN AMPITHEATER COVERED WALKWAY GREENHOUSE MAIN PLAYGROUND BACK PORTABLES FIELDS

20 P R O P O S E D I N T E R I M H O U S I N G L AY O U T

21 E X I S T I N G S T R E E T F R O N TA G E C O N D I T I O N S Temporary home for interim housing

22 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G S I T E P L A N When temporary housing is complete, work begins on a new main building. NEW BUILDING LIBRARY CLASSROOMS EAST WING MPR EXISTING PORTABLES INTERIM HOUSING PLAY FIELDS HEAD START The new building replaces existing facilities in kind it is not changing the number of classrooms

23 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G F I R S T L E V E L F L O O R P L A N Proposed New Building: ± 22,000 SF 35 feet tall Steel frame Stucco exterior Standing seam Metal roofs Size and finishes appropriate for the site Modular construction to save costs PEACE GARDEN OUTDOOR SEATING PLAYGROUND FIRE LANE GAS ENCLOSURE ELECTRICAL ENCLOSURE EXISTING BUILDING EXISTING BUILDING PARKING LOT TRASH ENCLOSURE

24 SPEECH THERAPY P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G F I R S T L E V E L F L O O R P L A N CLASSROOMS ADMINISTRATION CIRCULATION/ UTILITIES TRANSITIONAL KINDERGARTEN TRANSITIONAL KINDERGARTEN STAIRS STORAGE UTILITY STAIRS KINDERGARTEN KINDERGARTEN KINDERGARTEN STAIRS KINDERGARTEN NURSE PRINCIPAL CONFERENCE ROOM & FAMILY SERVICE CUSTODIAN FIRE RISER PEACE GARDEN LOUNGE WORKROOM PSYCH COUN COUN ELEVATOR ADMIN GAS ENCLOSURE EXISTING TRASH ENCLOSURE TO BE RELOCATED

25 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G S E C O N D L E V E L F L O O R P L A N CLASSROOMS ADMINISTRATION CIRCULATION/ UTILITIES ROOF BELOW STAIRS CLASSROOM 4 CUSTODIAN CLASSROOM 3 STAFF RESTROOM BOOK STORAGE ROOF BELOW CLASSROOM 1 CLASSROOM 2 STAIRS NEWCOMERS GIRLS RESTROOM STAIRS ENCLOSED HALLWAY COVERED WALKWAY ELEVATOR RSP BOYS RESTROOM CLASSROOM 5 CLASSROOM 6 CLASSROOM 7

26 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G S E C T I O N S HVAC CLASSROOM 4 HALLWAY NEWCOMERS TRANSITIONAL KINDERGARTEN CONFERENCE ROOM & FAMILY SERVICE HVAC NORTH BUILDING SECTION CLASSROOM 1 HALLWAY CLASSROOM 6 KINDERGARTEN 2 WORKROOM SOUTH BUILDING SECTION

27 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G S E C T I O N S HALLWAY HALLWAY KINDERGARTEN KINDERGARTEN KINDERGARTEN KINDERGARTEN TRANSITIONAL KINDERGARTEN TRANSITIONAL KINDERGARTEN

28 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G E L E V A T I O N S FRONT ELEVATION SOUTH BUILDING SIDE ELEVATION

29 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G E L E V A T I O N S KINDERGARTEN SIDE ELEVATION NORTH BUILDING SIDE ELEVATION

30 V I E W F R O M PA R K I N G L O T

31 V I E W N E A R A D M I N I S T R AT I O N E N T R A N C E

32 P E R S P E C T I V E 1

33 P E R S P E C T I V E 2

34 P E R S P E C T I V E 2 I N T E R I M H O U S I N G R E M O V E D

35 P R O P O S E D L AY O U T O F T W O - S T O R Y B U I L D I N G C O M P L E T E NEW BUILDING CLASSROOMS EAST WING LIBRARY MPR HEAD START PLAY FIELDS Play fields playground will be restored when the new main building is complete and the interim housing is removed.

36 T E N TAT I V E S C H E D U L E : April 2017: School Board review of Schematic Design September 2017: Start of regulatory review Spring 2018: Construction of interim housing with portables June 2018: Demolition of old building and start of construction

37 Q U E S T I O N S & C O M M E N T S THANK YOU!

38 Q U E S T I O N S & C O M M E N T S Questions or comments? Please contact: Dan Zaich, Ed.D. dzaich@srcs.org and cc: Terese Sladowska terese.sladowska@vpcsonline.com

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR

More information

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure

More information

Wed, May 6,2009 FILE #:

Wed, May 6,2009 FILE #: ARCHITECTURE URBAN DESIGN INTERIOR DESIGN MEETING MINUTES PROJECT NAME: BVSD Birch Elementary School DATE: 22 April 2009 NOTES BY: Wells Squier PROJECT #: 509023.00 Wed, May 6,2009 MEETING #: 002 NEXT

More information

Construction Total. Subtotal: $ 863,540 $ 172,708 $ 124,350 $ 1,160,598 $ 232,120 $ 1,392,717

Construction Total. Subtotal: $ 863,540 $ 172,708 $ 124,350 $ 1,160,598 $ 232,120 $ 1,392,717 Page 1 of 14 Hamilton School K-8 Phase District Basic Upgrades to Schools / Code Requirements Quantity Unit /Unit Soft s at 1 ADA path of travel walkways 1 LS $ 100,000 $ 100,000 $ 20,000 $ 14,400 $ 134,400

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)

More information

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)

More information

PROJECT BUDGET PRESENTATION

PROJECT BUDGET PRESENTATION PROJECT BUDGET PRESENTATION Monomoy Regional High School Building Committee Meeting June 19, 2012 Project Features Serves 700 Students Grades 8-12 8 th Grade Wing located near main entrance 168,000 GSF

More information

Progress Update Identified Needs & Capital Plan

Progress Update Identified Needs & Capital Plan Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary

More information

POJOAQUE VALLEY SCHOOL DISTRICT October 12, 2016

POJOAQUE VALLEY SCHOOL DISTRICT October 12, 2016 POJOAQUE VALLEY SCHOOL DISTRICT October 2, 206 Results from data gathered from community meeting held September 20, 206 regarding use of current bond funds and goals setting for possible 207 bond On Tuesday,

More information

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved

More information

Why did we undertake a comprehensive Educational Facility Master Plan?

Why did we undertake a comprehensive Educational Facility Master Plan? NUSD EDUCATIONAL FACILITY MASTER PLAN Why did we undertake a comprehensive Educational Facility Master Plan? Novato Unified School District (NUSD) has thirteen school sites that provide the educational

More information

Performance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012

Performance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012 Thomas County School System Performance Audit on 2008 and 2013 SPLOST Revenues 300 Mulberry Street, Suite 300 P.O. Box 1877 Macon, Georgia 31202-1877 Phone: (800) 277-0050 Facsimile: (478) 464-8051 Web:

More information

Lake Mills Area School District Community Survey Results. Spring 2018

Lake Mills Area School District Community Survey Results. Spring 2018 Lake Mills Area School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in late May through mid-june of 2018. Residents within the District were mailed a paper survey.

More information

Local ballot measure: B. Redding School District Bond Measure

Local ballot measure: B. Redding School District Bond Measure B Redding School District Bond Measure Ballot question To improve the quality of education; repair/replace leaky roofs; modernize and construct classrooms, restrooms and school facilities; and make health,

More information

HUENEME ELEMENTARY SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE T

HUENEME ELEMENTARY SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE T HUENEME ELEMENTARY SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE T Under this measure, the Hueneme Elementary School District ( District ) is submitting a bond measure, described below,

More information

38 th A n n u a l C o n f e r e n c e o n S c h o o l F a c i l i t i e s

38 th A n n u a l C o n f e r e n c e o n S c h o o l F a c i l i t i e s MANAGING RISK v. REWARD HOW TO BALANCE CREATIVE DESIGN WITH THE REALITIES OF PROJECT BUDGETS, SCHEDULES & SCOPE 38 th A n n u a l C o n f e r e n c e o n S c h o o l F a c i l i t i e s Panel Moderator:

More information

Action Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List

Action Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities

More information

SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S

SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters

More information

Time Item Notes: Presenter. Approval of Meeting Minutes (see attachment) -October 26, 2016 Please fill out: Public Input Request form

Time Item Notes: Presenter. Approval of Meeting Minutes (see attachment) -October 26, 2016 Please fill out: Public Input Request form WOODBURN SCHOOL DISTRICT 103 Bond Advisory & Accountability Committee Agenda Woodburn School District Office 1390 Meridian Drive January 18, 2017 6:30-8:30 pm Time Item Notes: Presenter 6:30-6:35 Welcome

More information

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019

Welcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019 Welcome School Public Meeting January 17, 2019 January 21, 2019 How Did We Get Here? August 2017 started talking to Architects and Construction Managers We retained an architectural firm to design a Conceptual

More information

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects

More information

APPENDIX A FULL TEXT OF BOND MEASURE

APPENDIX A FULL TEXT OF BOND MEASURE APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

DAT MEETING NOTES # 1

DAT MEETING NOTES # 1 DAT MEETING NOTES # 1 MOA ARCHITECTURE Design Advisory Team 821 17 th Street, Suite 400 Denver, Colorado 80202 303.308.1190 Phone 303.308.1197 Fax Project: Superior Elementary School Date: 11 November

More information

BOARD OF EDUCATION Attachment: Discussion 12. PALO ALTO UNIFIED SCHOOL DISTRICT Date: Bob Golton, Bond Program Manager

BOARD OF EDUCATION Attachment: Discussion 12. PALO ALTO UNIFIED SCHOOL DISTRICT Date: Bob Golton, Bond Program Manager BOARD OF EDUCATION Attachment: Discussion 12 PALO ALTO UNIFIED SCHOOL DISTRICT Date: 02.23.16 TO: FROM: SUBJECT: Glenn Max McGee, Superintendent Bob Golton, Bond Program Manager Addison Elementary School

More information

Ballot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools

Ballot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,

More information

PERRIS ELEMENTARY SCHOOL DISTRICT

PERRIS ELEMENTARY SCHOOL DISTRICT PERRIS ELEMENTARY SCHOOL DISTRICT 2006 & 2014 General Obligation Bond Authorizations Measures S & C Citizens' Oversight Committee Report March 1, 2018 2006 GENERAL OBLIGATION BOND ELECTION 2006 Measure

More information

BERKELEY UNIFIED SCHOOL DISTRICT

BERKELEY UNIFIED SCHOOL DISTRICT BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan

More information

Muskego Norway Schools Community Survey Results. Fall 2015

Muskego Norway Schools Community Survey Results. Fall 2015 Muskego Norway Schools Community Survey Results Fall 2015 Survey Summary The community survey was conducted in October of 2015 Residents within the District were mailed a paper survey. Each survey included

More information

M E M O R A N D U M O F C O N F E R E N C E

M E M O R A N D U M O F C O N F E R E N C E May 3, 2013 M E M O R A N D U M O F C O N F E R E N C E PROJECT Montgomery County Public Schools Potomac Elementary School Feasibility Study ARCHITECT S PROJECT NO. 522030 DATE AND LOCATION April 30, 2013,

More information

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee AGENDA November 17, 2011 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center & Demolition Science Center

More information

Freedom Area School District Community Survey Results. Fall 2018

Freedom Area School District Community Survey Results. Fall 2018 Freedom Area School District Community Survey Results Fall 2018 Survey Summary The survey was conducted in late October/early November of 2018. Residents within the District were mailed a paper survey.

More information

REQUEST FOR PROPOSALS CONSTRUCTION MANAGER AS CONSTRUCTOR

REQUEST FOR PROPOSALS CONSTRUCTION MANAGER AS CONSTRUCTOR REQUEST FOR PROPOSALS CONSTRUCTION MANAGER AS CONSTRUCTOR Addendum No. 1 1. A preliminary Project Budget which includes all anticipated work items is included for reference in preparing a response to this

More information

Harleton ISD May 7, 2016 Bond Proposal FAQs

Harleton ISD May 7, 2016 Bond Proposal FAQs Harleton May 7, 2016 Bond Proposal FAQs How was the total projected cost of the project developed? The cost of the project was based upon data concerning average costs of school construction found on the

More information

SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE A BOND AUDIT REPORT. For the Year Ended June 30, 2015 * * *

SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE A BOND AUDIT REPORT. For the Year Ended June 30, 2015 * * * AUDIT REPORT * * * CHAVAN & ASSOCIATES, LLP CERTIFIED PUBLIC ACCOUNTANTS 1475 SARATOGA AVE., SUITE 180 SAN JOSE, CA 95129 Table of Contents Page No. FINANCIAL SECTION: Independent Auditor s Report... 1-2

More information

19 South Tejon Street, Suite Colorado Springs, CO Tel: Fax:

19 South Tejon Street, Suite Colorado Springs, CO Tel: Fax: PROJECT: Arapahoe Ridge High School PROJECT NO: 08010 DATE: June 24, 2008 MEETING REPORT ATTENDANCE: Rex Hartman (BVSD), Joan Bludorn (ARHS), Dave Krassowski (ARHS), Peggy Slater (Print shop), Pat Z. (RTA),

More information

Measure G Quarterly Progress Update

Measure G Quarterly Progress Update Measure G Quarterly Progress Update May 4, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure G is

More information

CMP Strategy Project Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects)

CMP Strategy Project Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects) 2006-20 CMP Strategy Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects) Architectural Research Consultants, Incorporated October, 2004 Cluster: Albuquerque 244 DOLORES

More information

Measure G Quarterly Progress Update

Measure G Quarterly Progress Update Measure G Quarterly Progress Update February 3, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure

More information

Information. June 06, 2017 The Board awarded a contract to gkkworks/belli Architects.

Information. June 06, 2017 The Board awarded a contract to gkkworks/belli Architects. Measure T Update Prepared by: Joseph Reyes, Executive Director Facilities Planning & Construction Management Presented to the Board: October 02, 2018 1. Measure T Implementation Plan Information June 06,

More information

Bond Oversight Committee Bond program. January 7, 2016

Bond Oversight Committee Bond program. January 7, 2016 Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver

More information

Architect: WESKetch Architecture, Inc, Millington, NJ. William Kaufman/Tom Vierschilling

Architect: WESKetch Architecture, Inc, Millington, NJ. William Kaufman/Tom Vierschilling April 20, 2017 INVITATION FOR CONTRACTORS TO BID Project Address: 40 Maple Street Summit, NJ 07901 Project Summary Overview: Approximately 3,220 sf 3 rd story addition over existing 2 story building in

More information

MUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA

MUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA KERN COUNTY NORTH EDWARDS, CALIFORNIA FINANCIAL AND PERFORMANCE AUDIT JUNE 30, 2018 TABLE OF CONTENTS JUNE 30, 2018 PAGE INTRODUCTORY SECTION TABLE OF CONTENTS i FINANCIAL SECTION INDEPENDENT AUDITOR'S

More information

LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES

LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES 1 LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES Lake Central Priority for Use of Facilities: Group I: Direct School-related Activities (100% Lake Central employees) e.g. classes, school clubs,

More information

Ballot Measures-LL Section

Ballot Measures-LL Section LL To repair and modernize aging classrooms/school facilities at local elementary/intermediate schools, repair termite damage, dry rot, deteriorating roofs, plumbing, and electrical, improve student safety/security,

More information

FREQUENTLY ASKED QUESTIONS (FAQs)

FREQUENTLY ASKED QUESTIONS (FAQs) FREQUENTLY ASKED QUESTIONS (FAQs) Q. What is a school bond? A. A bond election requires the voter to express support for or against the district selling school bonds. If the bond election is approved,

More information

Program and Project Status Update

Program and Project Status Update Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1 Capital Improvement Program General Updates Close out of completed projects

More information

P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y

P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y Measure Q Update P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y 1 5 2 0 1 5 Agenda 1. P R E L I M I N A R Y R E S P O N S E T O

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid

More information

BERKELEY UNIFIED SCHOOL DISTRICT Construction Bond Oversight Committee

BERKELEY UNIFIED SCHOOL DISTRICT Construction Bond Oversight Committee BERKELEY UNIFIED SCHOOL DISTRICT Construction Bond Oversight Committee AGENDA May 10, 2012 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting Minutes

More information

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

Beaver Dam Unified School District Community Survey Results. Spring 2016

Beaver Dam Unified School District Community Survey Results. Spring 2016 Beaver Dam Unified School District Community Survey Results Spring 2016 Survey Summary The community survey was conducted in May of 2016. Residents within the District were mailed a paper survey. Each

More information

Minutes Capital Planning and Budget Committee Thursday, August 23, 2012

Minutes Capital Planning and Budget Committee Thursday, August 23, 2012 Minutes Capital Planning and Budget Committee Thursday, August 23, 2012 The meeting of the Capital Planning and Budget Committee was called to order at 1:00 pm by Committee Chair Regent Jeffrey Bartell

More information

Facilities Development and Operations

Facilities Development and Operations Facilities Development and Operations Dashboard/Metrics Report California State University, East Bay July 1, 2016 to June 30, 2017 1 Who We Are: Vice President Administration & Finance Division Associate

More information

c a p í t a l A R E T R O S P E C T I V E A R C H I T E C T U R E

c a p í t a l A R E T R O S P E C T I V E A R C H I T E C T U R E c a p í t a l A R E T R O S P E C T I V E A R C H I T E C T U R E 2 0 0 9-2 0 1 9 Capital A is ten years old. From working at my kitchen table during the Great Recession, to becoming an established Architecture

More information

West Bend School District Community Survey Results. Spring 2018

West Bend School District Community Survey Results. Spring 2018 West Bend School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in June of 2018. Residents within the District were mailed a paper survey. Each survey included a

More information

Program: Facilities and Construction Management. Program Based Budget Page 117

Program: Facilities and Construction Management. Program Based Budget Page 117 Program: Facilities and Construction Management Program Based Budget 2014-2016 Page 117 Program: Facilities and Construction Management Vision: To develop and maintain town buildings that is safe, comfortable

More information

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015 Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015 Measure V Bond Construction Fund Year Ended June 30, 2015 Table of Contents Page Independent Auditors'

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development Georgia Institute of Technology Advanced Computing Technology Building Draft Program Initial Program Development Issued April 2, 2001 Introduction Scope This document is a summary of the Session for the

More information

SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room

SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room Enclosure #01 SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room Members Present: James Ruigomez, Chair; Gino Gasparini, Shelley Kessler,

More information

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of

More information

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of

More information

LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES

LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES 1 LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES Lake Central Priority for Use of Facilities: Group I: Direct School-related Activities (100% Lake Central employees) e.g. classes, school clubs,

More information

Hollis Historic District Commission

Hollis Historic District Commission Hollis Historic District Commission Minutes of the May 4, 2006 meeting Draft Copy Call to Order Chairman Liz Barbour called the meeting of the Hollis Historic District Commission to order at 7:30P.M. The

More information

Status: Structural steel installation underway at primary building. Observatory construction underway.

Status: Structural steel installation underway at primary building. Observatory construction underway. Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Barnesville Public Schools Proposed Building Program

Barnesville Public Schools Proposed Building Program August 1, 2018 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent

More information

Orange Unified School District (C) Copyright March 2018 All Rights Reserved

Orange Unified School District (C) Copyright March 2018 All Rights Reserved ORANGEUNIFIED UNIFIEDSCHOOL SCHOOLDISTRICT DISTRICT ORANGE Orange Unified School District (C) Copyright March 2018 All Rights Reserved 1 The Office of the Assistant Superintendent of Business Services

More information

MEASURE E - CITIZENS BOND OVERSIGHT COMMITTEE June 7, :00 p.m.

MEASURE E - CITIZENS BOND OVERSIGHT COMMITTEE June 7, :00 p.m. Yosemite Community College District MEASURE E CITIZENS BOND OVERSIGHT COMMITTEE June 7, 2017 2:00 p.m. Columbia College Manzanita Conference Room 11600 Columbia College Drive Sonora, CA MEETING AGENDA

More information

SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE J BOND AUDIT REPORT. August 31, 2016 * * *

SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE J BOND AUDIT REPORT. August 31, 2016 * * * SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE J BOND AUDIT REPORT August 31, 2016 * * * CHAVAN & ASSOCIATES, LLP CERTIFIED PUBLIC ACCOUNTANTS 1475 SARATOGA AVE., SUITE 180 SAN JOSE, CA 95129

More information

OFFICE OF HISTORIC RESOURCES City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012

OFFICE OF HISTORIC RESOURCES City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012 City Hall 200 N. Spring Street, Room 559 Los Angeles, CA 90012 February 2, 2015 TO: Jose Huizar, Chair Planning and Land Use Management Committee FROM: Ken Bernstein, AICP Manager, Office of Historic Resources

More information

THIS IS AN APPLICATION FOR A BUILDING PERMIT

THIS IS AN APPLICATION FOR A BUILDING PERMIT THIS IS AN APPLICATION FOR A BUILDING PERMIT 1. Read these instructions and carefully complete the application. 2. No building or structure shall be erected, added to or structurally altered or the use

More information

Facilities Management and Planning Organizational Review Phase II Update

Facilities Management and Planning Organizational Review Phase II Update MEMORANDUM Office of College Services DATE: September 3, 2013 TO: CC: FROM: SUBJECT: President Mary Spilde, Vice President Brian Kelly Facilities Management & Planning Organizational Review Team Jennifer

More information

Capital Projects Completed since 1988

Capital Projects Completed since 1988 Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990

More information

DISTRICT HISTORY Referendum ($585,000) Purchase of 10 Acres / Football Field Original junior high building (present old section of MS)

DISTRICT HISTORY Referendum ($585,000) Purchase of 10 Acres / Football Field Original junior high building (present old section of MS) 1917 Auburn Township HS ($50,000) 1948 Referendum ($240,000) Two-story section of present elementary Gym / Cafeteria / Kitchen Became K-12 district 1954 Referendum ($130,000) AG/IT shop area Band / Vocal

More information

Bond Amount: $18,470,000. Proposed I&S Tax Rate Increase: $.3180

Bond Amount: $18,470,000. Proposed I&S Tax Rate Increase: $.3180 Bond Amount: $18,470,000 Proposed I&S Tax Rate : $.3180 How was the EBISD 2017 Bond developed? The bond package was developed from K-12 academic needs identified by our fifty-member community facilities

More information

Monthly Report. April 2017

Monthly Report. April 2017 Monthly Report April 2017 El Paso ISD Bond Program Program Manager: Jacobs Table of Contents Report Date: 04/30/2017 Understanding the Monthly Report... 3 Executive Summary. 7 Program Report by Phase...

More information

Annual Report on Parish Facilities. Patrick Jendraszak

Annual Report on Parish Facilities. Patrick Jendraszak Annual Report on Parish Facilities Patrick Jendraszak May 15, 2018 Buildings & Grounds Committee Andy Bauer (School Liaison) Sue MacGill (School Liaison) Progress on Last Year s Plans Renovate Grades 3/4

More information

Public Presentation Capital Bond November 27, 2017

Public Presentation Capital Bond November 27, 2017 Public Presentation Capital Bond November 27, 2017 Capital Bond The Board of Education facilities committee working in concert with building administration, central administration, and the district architect

More information

2017 Bond Program Summary

2017 Bond Program Summary 2017 Bond Program Summary Middle School #3 (off Vail Divide) $ 76,225,750 Middle School #3 Off-site Utility and Road Construction $ 2,100,000 Elementary School #7 (in Rough Hollow) $ 33,130,150 Bee Cave

More information

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES Weston Public Schools PROPOSED BUDGET OF EXPENDITURES 2012-2013 School Facilities 2012-2013 Budget Presentation Please refer to pages 111-117 in the Budget Binder Budget Preface The Past: Unreliable boilers

More information

REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING

REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING Request for Qualifications (RFQ) due: 3:00pm local time, August 17, 2018 Page 1 of 8 Section One Introduction

More information

The Vineyard Town Planning Commission held a regular meeting on Wednesday, April 19, 2017, starting at 6:30 PM in the Vineyard Town hall.

The Vineyard Town Planning Commission held a regular meeting on Wednesday, April 19, 2017, starting at 6:30 PM in the Vineyard Town hall. MINUTES OF THE VINEYARD TOWN PLANNING COMMISSION MEETING Vineyard City Offices, 240 East Gammon Road, Vineyard, Utah Wednesday, April 19, 2017 at 6:30 p.m. PRESENT Commissioner Chair Chris Judd Commissioner

More information

MINUTES PLANNING COMMISSION MEETING. May 1, 2017

MINUTES PLANNING COMMISSION MEETING. May 1, 2017 MINUTES PLANNING COMMISSION MEETING A regular meeting of the Planning Commission of the City of Rolling Hills Estates was called to order at 7:00 p.m. in the City Hall Council Chambers, 4045 Palos Verdes

More information

USF Health Science Center Facilities Planning & Construction Project Status Update May 4, 2010 Submitted by Stan Douglas HSC Facilities Director

USF Health Science Center Facilities Planning & Construction Project Status Update May 4, 2010 Submitted by Stan Douglas HSC Facilities Director USF Health Science Center Facilities Planning & Construction Project Status Update May 4, 2010 Submitted by Stan Douglas HSC Facilities Director 5/7/2010 1 Construction or Bid Phase Projects 5/7/2010 2

More information

EVENT MANAGEMENT RESERVATION POLICIES RESERVATION POLICIES OFF CAMPUS ENTITIES

EVENT MANAGEMENT RESERVATION POLICIES RESERVATION POLICIES OFF CAMPUS ENTITIES RESERVATION POLICIES RESERVATION POLICIES LSU Auxiliary Services Event Management Office is responsible for the reservation of event spaces in and around the LSU Student Union. Additional policies for

More information

Pleasantdale Elementary

Pleasantdale Elementary DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School

More information

Workers Compensation Update

Workers Compensation Update Employee Benefits and Risk Management, HREQ Workers Compensation Update ~ At the end of the day, the goals are simple: safety and security ~ Jodi Rell Inside this Edition: Workers Compensation Designee

More information

Ronald E. McNair Discovery Learning Academy

Ronald E. McNair Discovery Learning Academy DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive

More information

Robert Shaw Theme Elementary

Robert Shaw Theme Elementary DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

Event Planning Guide

Event Planning Guide Event Planning Guide Sunset Coffee Building 1019 Commerce Street Houston, Texas 77002 EVENT PLANNING GUIDE Sunset Coffee Building Plaza, Café & Rooftop Terrace Introduction History The Sunset Coffee Building

More information

Conducting a Facilities Condition Assessment as Part of Your Capital Planning. FEFPA July 5, 2011

Conducting a Facilities Condition Assessment as Part of Your Capital Planning. FEFPA July 5, 2011 Conducting a Facilities Condition Assessment as Part of Your Capital Planning FEFPA July 5, 2011 Agenda Introduction History and Goals Process Physical Condition Analysis and Ranking Educational Adequacy

More information

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 Space Utilization Study Analysis Ongoing questions regarding enrollment and the use of our facilities 2010 an internal analysis was performed with no decisions

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Borough of Phoenixville Master Schedule of Fees Effective January 1, 2015

Borough of Phoenixville Master Schedule of Fees Effective January 1, 2015 Borough of Phoenixville Master Schedule of Fees Effective January 1, 2015 Applicants are responsible to review all Borough Subdivision and Land Development Ordinances and Zoning Ordinances for determining

More information

Western s critical need to stay on track with our overall expansion of access and orderly phased development throughout campus;

Western s critical need to stay on track with our overall expansion of access and orderly phased development throughout campus; Karen W. Morse President An equal opportunity university 56 High Street Bellingham, Washington 985-90 60.650.80 Fax: 60.650.650 October 6, 007 The Honorable Christine Gregoire Governor of the State of

More information

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013 Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013 Measure V Bond Construction Fund Year Ended June 30, 2013 Table of Contents Page Independent Auditors'

More information

CH-UH Board of Education Meeting. June 27, 2017

CH-UH Board of Education Meeting. June 27, 2017 CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle

More information

OXNARD SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE R OXNARD SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE R

OXNARD SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE R OXNARD SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE R OXNARD SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE R Under this measure, the Oxnard School District ( District ) is submitting a bond measure, described below, to the voters for

More information