B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a

Size: px
Start display at page:

Download "B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a"

Transcription

1 Administration and Projects Committee STAFF REPORT Meeting Date: October 1, 2015 Subject Summary of Issues State Route 4 (SR4) East Widening Project Loveridge Road to SR160 (Projects 1406/3001) Request to Deallocate/Reallocate Regional Measure 2 (RM2) Funds for Construction Services The Metropolitan Transportation Commission (MTC) authorized a total of $2,300,000 for the final design effort needed to incorporate the wider median and ebart compatible structures along SR4 from Loveridge Road to Hillcrest Avenue. The allocations were made in January 2008 ($800,000) and May 2008 ($1,500,000) for these specific tasks related to the freeway construction packages. The ebart related design was completed at a cost of $1,741,101, leaving a balance of $558,899 in RM2 funds. Experience with the Loveridge and Segment 1 construction projects suggests that maintaining additional reserve for ebart items and extra work would be prudent. This can be accomplished by requesting that the balance of the design funds be deallocated and reallocated to the Construction Phase of Segments 2 and 3A. Recommendations Staff seeks approval of Resolution P which will deallocate/reallocate $558,899 in RM2 funds to provide additional reserve for ebart requirements and extra work for the Construction Phase of Segments 2 and 3A. Staff also requests approval to submit to MTC a request to deallocate/reallocate these funds. Financial Implications Funds will not be available for the Authority s use until MTC has taken action on this request. Options Attachments The Authority could decline to approve the submittal. The additional RM2 funds would be deallocated and returned to the ebart project for BART s future use. A. Draft Regional Measure 2, Initial Project Report 5-1

2 B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a total of $96 million in RM2 Bridge Toll Funds to the ebart project for Environmental work, Design, Right-of-Way (ROW) and Construction. As co-sponsors, allocations have been made directly to either BART or the Authority with the other agency s concurrence. MTC authorized a total of $2,300,000 for the final design effort to incorporate the wider median and ebart structures into the SR4 Widening project construction packages, from Loveridge Road to SR160. The final cost for this work came in at $1,741,101, or $558,899 below the original estimate. Additionally MTC allocated $20.1 million for the Authority implemented construction phase, funding both ebart related construction capital and construction management costs. To date $17.7 million has been expended from the allocated amount for construction of all four segments. The two completed segments, Loveridge Road and Segment 1 have experienced cost overruns from the ebart items. While there are no known issues associated with Segments 2 and 3A, the savings from the design phase would help fund these overruns and provide additional cushion against unforeseen costs. Staff has worked with BART staff to develop the proposed deallocation and reallocation request and has their concurrence on this approach. 5-2

3 Regional Measure 2 (RM2) Initial Project Report (IPR) Project Title: RM2 Project No.: 13.1, 13.2, 13.3 ebart Project State Route 4 (SR4) Widening Project Loveridge to SR160 Rail Extension to East Contra Costa County Allocation History: MTC Approval Date Amount Phase #1: March ,750,000 ENV/ROW Sup #2 December ,500,000 PS&E #3 May PS&E (Transfer between subprojects) #4 June PS&E (Transfer between subprojects) #5 January ,000 PS&E #6 January ,000 PS&E #7 May ,500,000 PS&E #8 May ,500,000 PS&E #9 December ,000,000 ROW #10 May Deallocate ENV/Allocate PS&E #11 June ,000,000 CON #12 June ,000,000 ROW/CON #13 June ,000,000 PS&E #14 December ,150,000 PS&E/ROW/CON Total: $ 96,000,

4 Current Allocation Request: IPR Date Amount Being Requested Phase Requested 08/17/15 -$558,899 PS&E Rescission of the following: Allocation 6: $291,291 Allocation 8: $267,608 08/17/15 $558,899 CON I. OVERALL PROJECT INFORMATION A. Project Sponsor/Co-sponsor(s)/Implementing Agency The Contra Costa Transportation Authority (CCTA) and Bay Area Rapid Transit (BART) are cosponsoring agencies for AB 1171/RM1 funds. CCTA will be the implementing agency for the construction of ebart median structures to be integrated into Segments 1, 2, 3, 4, and 5 of The California State Department of Transportation (Caltrans)/CCTA SR4 contracts and for acquiring Right-of-Way (ROW) to accommodate ebart. B. Project Purpose The purpose of the ebart project and the SR4 widening project is to bring commute relief to the eastern portion of Contra Costa County in a reasonable period of time at a reasonable cost. Eastern Contra Costa County is the fastest growing part of the Bay Area, expecting population growth of 53% and job growth of 132% between 2000 and The area needs frequent, reliable, high quality transit service to connect the many and increasing number of homes in the area with the jobs in areas served by existing public transit, including BART. CCTA and BART have identified the SR4 median as the preferred route for future transit expansion. This application is for the allocation of funds for construction of improvements and construction management for the ebart portion of the widening project between Somersville Road and SR160. C. Project Description Project graphics to be sent electronically with this application The ebart Project (Project) will expand the existing BART system by ten miles, and extend transportation services to communities in east Contra Costa County that are currently not served by rail transit. Stations within the SR4 median would be designed to provide intermodal regional links to bus, shuttle, automobile, bicycle, and pedestrian networks. The Project will enhance the public's access to jobs, education, shopping, and social activities throughout the Bay Area. Diesel Multiple Unit (DMU) trains will operate on tracks to be constructed in the median of SR4 between the existing Pittsburg/Bay Point BART Station and the vicinity of the Hillcrest Avenue interchange in the City of Antioch. One transfer platform and two stations will be constructed along the 10-mile corridor. The DMU trains will operate on tracks to be constructed in the median of SR4. The portion of SR4 between the Pittsburg/Bay Point BART Station and Loveridge Road has already been widened to accommodate transit service. The portion of SR4 between Loveridge Road and Hillcrest Avenue is

5 proposed for widening by the Caltrans and CCTA, and has undergone environmental review. The schedule for construction and operation of ebart is contingent on the scheduled Caltrans widening of SR4 east of Somersville Road. A transfer platform and two stations will be constructed as part of the ebart Project. The transfer platform will be constructed east of the existing Pittsburg/Bay Point BART Station in the existing BART tailtrack area. A new passenger station paid for by the City of Pittsburg will be constructed at Railroad Avenue. A terminus station will be constructed in the vicinity of Hillcrest Avenue in Antioch. In addition, a maintenance platform will be constructed east of the Hillcrest Avenue Station. D. Impediments to Project Completion There are no currently known impediments to completion; however, contractor claims are always a potential risk. E. Operability N/A II. PROJECT PHASE DESCRIPTION and STATUS F. Environmental Does the National Environmental Policy Act (NEPA) Apply: Yes No California Environmental Quality Act (CEQA) - The BART Board of Directors certified the Final Environmental Report has been completed in compliance with CEQA on April 23, SR4 has obtained environmental clearance under a Negative Declaration/Environmental Assessment/Initial Study/NEPA/CEQA Re-Validation. G. Design 100% Design complete all segments. H. Right-of-Way (ROW) Activities/Acquisition 100% ROW complete all segments. I. Construction/Vehicle Acquisition This portion of the application is for construction and construction management activities between Somersville Road and SR160. III. PROJECT BUDGET J. ebart Project Budget *Amounts escalated to year of expenditure in thousands Phase Total Amount Environmental Studies & Preliminary Eng (ENV/PE/PA&ED) $26,000 Design - Plans, Specifications and Estimates (PS&E) $39,500 Right-of-Way Activities /Acquisition (ROW) $117,000 Construction/Rolling Stock Acquisition (CON) $342,491 Total Project Budget (in thousands) $524,

6 K. ebart Project Budget *Amounts de-escalated to current year in thousands Phase Total Amount Environmental Studies & Preliminary Eng (ENV/PE/PA&ED) $26,000 Design - Plans, Specifications and Estimates (PS&E) $39,500 Right-of-Way Activities /Acquisition (ROW) $117,000 Construction/Rolling Stock Acquisition (CON) $342,491 Total Project Budget (in thousands) $524,991 IV. OVERALL PROJECT SCHEDULE ebart Project Schedule Phase-Milestone Planned (Update as needed) Completion Start Date Date Environmental Document FY 2005 FY 2009 Environmental Studies, Preliminary Eng. (ENV/PE/PA&ED) FY 2005 FY 2009 Final Design - Plans, Specs. & Estimates (PS&E) FY 2008 FY 2016 Right-of-Way Activities /Acquisition (ROW) FY 2005 FY 2016 Construction (Begin Open for Use)/Acquisition/Operating Service (CON) FY 2011 FY 2018 SR4 Widening Project Schedule Phase-Milestone Planned (Update as needed) Completion Start Date Date Environmental Document FY 2001 FY 2005 Environmental Studies, Preliminary Eng. (ENV/PE/PA&ED) FY 2001 FY 2005 Final Design - Plans, Specs. & Estimates (PS&E) FY 2006 FY 2012 Right-of-Way Activities /Acquisition (ROW) FY 2007 FY 2013 Construction (Begin Open for Use)/Acquisition/Operating Service (CON) FY 2010 FY 2016 V. ALLOCATION REQUEST INFORMATION L. Detailed Description of Allocation Request

7 Describe the scope of the allocation request. Provide background and other details as necessary. This application rescinds unused funds from prior design allocations and reallocates those funds for construction to provide additional change order reserve for Segments 3 and 4, as follows: (1) Deallocate $291,291 from Allocation ; (2) Deallocate $267,608 from Allocation ; and (3) Allocate $558,899 for construction of ebart median structures to be integrated into Segments 3 and 4 of Caltrans/CCTA SR4 contracts Amount being requested (in escalated dollars) Deallocate Allocate Project Phase being requested $<558,899> $558,899 PS&E (deallocation) CON (allocation) Are there other fund sources involved in this phase? Yes No Date of anticipated Implementing Agency Board approval the RM2 IPR Resolution for the allocation being requested 09/16/15 Month/year being requested for MTC approval of allocation 10/15 M. Status of Previous Allocations (if any) Expenditures To-Date by Phase *Amounts in thousands Phase Date of last Expenditure Amount Expended to date Balance Remaining To be Expended ENV/PA&ED June 2015 $25,981 $569 PS&E June 2015 $38,399 $1,101 ROW June 2015 $104,550 $15,049 CON/Operating June 2015 $132,150 $201,614 Total to date (in thousands) $301,080 $218,333 Expenditures To-Date by Fund Source *Amounts in Thousands Fund Source Expended to Date Date of last Expenditure Amount Expended to date Balance Remaining To Be Expended BART funds June 2015 $50 $3,600 RM2 June 2015 $90,270 $5,730 TCRP June 2015 $5,250 $0 Prop 1B June 2015 $33,191 $16,631 SAP June 2015 $500 $0 Measure C June 2015 $400 $0 T-Plus June 2015 $100 $

8 AB 1171 June 2015 $88,106 $23,394 Measure J June 2015 $72,035 $65,865 RM1 June 2015 $0 $63,800 MTC STA June 2015 $300 $0 Tri Delta June 2015 $2,785 $0 CCTA Reimbursement June 2015 $6,007 $0 CCTA Hillcrest Interchange June 2015 $1,599 $0 City of Pittsburg June 2015 $487 $4,313 ECCRFFA June 2015 $0 $35,000 Total to date (in thousands) $301,080 $218,333 N. Workplan Workplan in Alternate Format Enclosed Task No. Description Deliverables 1 Construction Improved Median Somersville Road to SR160 O. Impediments to Allocation Implementation None VI. RM2 FUNDING INFORMATION P. RM2 Funding Expenditures for Funds being Allocated Completion Date June 2016 The companion Microsoft Excel Project Funding Spreadsheet to this IPR is included Q. Next Anticipated RM2 Allocation Request September 2015 for re-allocation VII. GOVERNING BOARD ACTION Check the box that applies: Governing Board Resolution attached Governing Board Resolution to be provided on or before: 10/23/2015 VIII. CONTACT/PREPARATION INFORMATION Contact for Applicant s Agency - BART Contact: Name: Ric Rattray Phone: Title: Group Manager mrattra@bart.gov Address: BART Planning Department 300 Lakeside Drive, 21 th Floor Oakland, CA

9 Contact for Applicant s Agency - CCTA Contact: Name: Susan Miller Phone: Title: Director of Projects smiller@ccta.net Address: 2999 Oak Road, Suite 100 Walnut Creek, CA Information on Person Preparing IPR: Name: Susan Miller Phone: Title: Director of Projects smiller@ccta.net Address: 2999 Oak Road, Suite 100 Walnut Creek, CA 9459 Name: Randall Carlton Phone: Title: Chief Financial Officer rcarlton@ccta.net Address: 2999 Oak Road, Suite 100 Walnut Creek, CA

10 RM2 Regional Traffic Relief Plan Request for Allocation Part 1: RM2 Implementing Agency Resolution of Project Compliance Resolution P Implementing Agency: Project Title: Contra Costa Transportation Authority State Route 4 (SR4) East Widening: Loveridge Road to SR160 Whereas, SB 916 (Chapter 715, Statutes 2004), commonly referred as Regional Measure 2 (RM2), identified projects eligible to receive funding under the Regional Traffic Relief Plan; and Whereas, the Metropolitan Transportation Commission (MTC) is responsible for funding projects eligible for RM2 funds, pursuant to California Streets and Highways Code Section 30914(c) and (d); and Whereas, MTC has established a process whereby eligible transportation project sponsors may submit allocation requests for RM2 funding; and Whereas, allocations to MTC must be submitted consistent with procedures and conditions as outlined in RM2 Policy and Procedures; and Whereas, Contra Costa Transportation Authority (Authority) is an eligible sponsor of transportation project(s) in RM2, Regional Traffic Relief Plan funds; and Whereas, the SR4 East Widening: Somersville Road to SR160 is eligible for consideration in the Regional Traffic Relief Plan of RM2, as identified in California Streets and Highways Code Section 30914(c) or (d); and Whereas, the RM2 allocation request, attached hereto in the Initial Project Report (IPR) and incorporated herein as though set forth at length, lists the project, purpose, schedule, budget, expenditure and cash flow plan for which the Authority is requesting that MTC allocate RM2 funds; and Resolved, that the Authority, and its agents shall comply with the provisions of the MTC s RM2 Policy Guidance (MTC Resolution No. 3636); and Resolved, that the Authority certifies that the project is consistent with the Regional Transportation Plan (RTP); and Resolved, that the year of funding for any design, Right-of-Way (ROW) and/or construction phases has taken into consideration the time necessary to obtain environmental clearance and permitting approval for the project; and 5-10

11 Resolved, that the SR4 East Widening: Somersville Road to SR160 is fully funded, and results in an operable and useable segment; and Resolved, that the Authority approves the updated IPR, attached to this resolution; and Resolved, that the Authority approves the cash flow plan, attached to this resolution; and Resolved, that the Authority in partnership with the Bay Area Rapid Transit District (BART) have reviewed the project needs and have adequate staffing resources to deliver and complete the project within the schedule set forth in the updated IPR, attached to this resolution; and Resolved, that the Authority is an eligible sponsor of projects in the RM2 Regional Traffic Relief Plan, Capital Program, in accordance with California Streets and Highways Code 30914(c); and Resolved, that the Authority is authorized to submit an application for RM2 funds for SR4 East Widening: Somersville Road to SR160 in accordance with California Streets and Highways Code 30914(c); and Resolved, that the Authority certifies that the projects and purposes for which RM2 funds are being requested is in compliance with the requirements of the California Environmental Quality Act (CEQA) (Public Resources Code Section 2l000 et seq.), and with the State Environmental Impact Report Guidelines (l4 California Code of Regulations Section l5000 et seq.) and if relevant the National Environmental Policy Act (NEPA), 42 USC Section 4-1 et. seq. and the applicable regulations thereunder; and Resolved, that there is no legal impediment to the Authority making allocation requests for RM2 funds; and Resolved, that there is no pending or threatened litigation which might in any way adversely affect the proposed project, or the ability of the Authority to deliver such project; and Resolved that the Authority indemnifies and holds harmless MTC, its Commissioners, representatives, agents, and employees from and against all claims, injury, suits, demands, liability, losses, damages, and expenses, whether direct or indirect (including any and all costs and expenses in connection therewith), incurred by reason of any act or failure to act of the Authority, its officers, employees or agents, or subcontractors or any of them in connection with its performance of services under this allocation of RM2 funds. In addition to any other remedy authorized by law, so much of the funding due under this allocation of RM2 funds as shall reasonably be considered necessary by MTC may be retained until disposition has been made of any claim for damages; and Resolved, that the Authority shall, if any revenues or profits from any non-governmental use of property (or project) are collected, that those revenues or profits shall be used exclusively for the public transportation services for which the project was initially approved, either for capital improvements or maintenance and operational costs, otherwise the MTC is entitled to a proportionate share equal to MTC s percentage participation in the projects(s); and 5-11

12 Resolved, that assets purchased with RM2 funds including facilities and equipment shall be used for the public transportation uses intended, and should said facilities and equipment cease to be operated or maintained for their intended public transportation purposes for its useful life, that MTC shall be entitled to a present day value refund or credit (at MTC s option) based on MTC s share of the Fair Market Value of the said facilities and equipment at the time the public transportation uses ceased, which shall be paid back to MTC in the same proportion that RM2 funds were originally used; and Resolved, that the Authority authorizes its Executive Director or his designee to execute and submit a request for the deallocation of funds from the final design phase and subsequent reallocation to the construction phase for the SR4 East Widening: Loveridge Road to SR160 to MTC for RM2 funds in the amount of $558,899, for the project, purposes and amounts included in the project application attached to this resolution; and Resolved, that the Executive Director or his designee is hereby delegated the authority to make non-substantive changes or minor amendments to the IPR as he/she deems appropriate; and Resolved, that a copy of this resolution shall be transmitted to MTC in conjunction with the filing of the Authority application referenced herein. Julie K. Pierce, Chair This RESOLUTION was entered into at a meeting of the Contra Costa Transportation Authority held October 21, 2015 in Walnut Creek, California Attest: Danice J. Rosenbohm, Executive Secretary 5-12

Application to fund Executive level position for the Altamont Regional Rail Working Group

Application to fund Executive level position for the Altamont Regional Rail Working Group SUBJECT: FROM: Application to fund Executive level position for the Altamont Regional Rail Working Group Michael Tree, Executive Director DATE: August 1, 2016 Action Requested The staff recommendation

More information

Agenda Item No. 6d January 27, Honorable Mayor and City Council Attention: Laura C. Kuhn, Interim City Manager

Agenda Item No. 6d January 27, Honorable Mayor and City Council Attention: Laura C. Kuhn, Interim City Manager Agenda Item No. 6d January 27, 2009 TO: FROM: SUBJECT: Honorable Mayor and City Council Attention: Laura C. Kuhn, Interim City Manager Rod Moresco, Director of Public Works/City Engineer RESOLUTION AUTHORIZING

More information

D ECCRFFA Strategic Plan Administration and Projects Committee STAFF REPORT March 3, 2016 Page 2 of 2 Changes from Committee Background In Augus

D ECCRFFA Strategic Plan Administration and Projects Committee STAFF REPORT March 3, 2016 Page 2 of 2 Changes from Committee Background In Augus Administration and Projects Committee STAFF REPORT Meeting Date: March 3, 2016 Subject State Route 4 (SR4) Balfour Road Interchange (Project 5005) Authorization to Execute Amendment No. 2 to Agreement

More information

Contra Costa Transportation Authority STAFF REPORT March 4, 2015 Page 2 of 2 reduce motor vehicle emissions. The funds are generated by a $4 vehicle r

Contra Costa Transportation Authority STAFF REPORT March 4, 2015 Page 2 of 2 reduce motor vehicle emissions. The funds are generated by a $4 vehicle r Contra Costa Transportation Authority STAFF REPORT Meeting Date: February 3, 2016 Subject Summary of Issues Recommendations Financial Implications Options Attachments Changes from Committee Approval of

More information

Administration and Projects Committee STAFF REPORT March 1, 2018 Page 2 of 9 Below is a summary of the FY adopted budget and the proposed midy

Administration and Projects Committee STAFF REPORT March 1, 2018 Page 2 of 9 Below is a summary of the FY adopted budget and the proposed midy Administration and Projects Committee STAFF REPORT Meeting Date: March 1, 2018 Subject Summary of Issues Recommendations Financial Implications Options Approval of FY 2017 18 Midyear Budget for the Contra

More information

Page 2 of 9 project costs are included in the budget consistent with the adopted Measure C and Measure J Strategic Plans. Below is a summary of the FY

Page 2 of 9 project costs are included in the budget consistent with the adopted Measure C and Measure J Strategic Plans. Below is a summary of the FY Meeting Date: Subject Summary of Issues Recommendations Financial Implications Options Attachments (See APC Packet dated 3/1/18) Changes from Committee Approval of FY 2017-18 Midyear Budget for the Contra

More information

4.A.14-2

4.A.14-2 4.A.14-1 4.A.14-2 Administration and Projects Committee STAFF REPORT Meeting Date: June 2, 2016 Subject Summary of Issues FY 2016-17 Proposed Budget for the Contra Costa Transportation Authority and Congestion

More information

Administration and Projects Committee STAFF REPORT June 4, 2015 Page 2 of 2 Attachments A. Letter from Caltrans dated May 15, 2015 Changes from Commit

Administration and Projects Committee STAFF REPORT June 4, 2015 Page 2 of 2 Attachments A. Letter from Caltrans dated May 15, 2015 Changes from Commit Administration and Projects Committee STAFF REPORT Meeting Date: June 4, 2015 Subject Summary of Issues Recommendations Financial Implications Options I-680/State Route 4 (SR4) Interchange Improvements

More information

B. Historical Summary Administration and Projects Committee STAFF REPORT April 6, 2017 Page 2 of 2 Changes from Committee Background PG&E owns and mai

B. Historical Summary Administration and Projects Committee STAFF REPORT April 6, 2017 Page 2 of 2 Changes from Committee Background PG&E owns and mai Administration and Projects Committee STAFF REPORT Meeting Date: April 6, 2017 Subject State Route 4 (SR4)/Balfour Road Interchange (Project 5005) Authorization to Execute No. 2 to Utility Agreement No.

More information

CHAPTER 9 FINANCIAL CONSIDERATIONS

CHAPTER 9 FINANCIAL CONSIDERATIONS CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the Berryessa Extension Project (BEP) Alternative and the Silicon Valley Rapid Transit

More information

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 2 Previous Central County Program 20a fund allocations helped advance transportation programs p

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 2 Previous Central County Program 20a fund allocations helped advance transportation programs p Planning Committee STAFF REPORT Meeting Date: June 3, 2015 Subject Summary of Issues Recommendations Approval of FY 2015-16 Allocation of Measure J Central County Additional Transportation Programs for

More information

Contra Costa Transportation Authority STAFF REPORT Meeting Date: July 20, 2016 Subject Summary of Issues Recommendations Approval of FY Transp

Contra Costa Transportation Authority STAFF REPORT Meeting Date: July 20, 2016 Subject Summary of Issues Recommendations Approval of FY Transp Contra Costa Transportation Authority STAFF REPORT Meeting Date: Subject Summary of Issues Recommendations Approval of FY 2016-17 Transportation Demand Management Program Funding - Measure J Commute Alternatives

More information

Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit

Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit Joint Board Ownership Workshop November 16, 2018 1 Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit Equity

More information

CHAPTER 9 FINANCIAL CONSIDERATIONS

CHAPTER 9 FINANCIAL CONSIDERATIONS CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the BEP and the SVRTP. A summary evaluation of VTA s financial plan for the proposed

More information

Alameda CTC Mass Transit Program Implementation Guidelines

Alameda CTC Mass Transit Program Implementation Guidelines Section 1. Purpose Alameda County Transportation Commission Implementation Guidelines for the Mass Transit Program Funded through Measure B, Measure BB, and Vehicle Registration Fees A. To delineate eligible

More information

Cancelled. Final Action

Cancelled. Final Action RESOLUTION NO. R2018-16 Baseline Budget and Schedule for the Lynnwood Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 05/10/2018 05/24/2018 Cancelled

More information

MINUTES OF SEPTEMBER 5, 2017

MINUTES OF SEPTEMBER 5, 2017 CITIZENS ADVISORY COMMITTEE (CAC) SAN MATEO COUNTY TRANSPORTATION AUTHORITY (TA) 1250 San Carlos Avenue, San Carlos CA 94070 Bacciocco Auditorium, 2 nd Floor MINUTES OF SEPTEMBER 5, 2017 MEMBERS PRESENT:

More information

Chapter 9 Financial Considerations. 9.1 Introduction

Chapter 9 Financial Considerations. 9.1 Introduction 9.1 Introduction Chapter 9 This chapter presents anticipated costs, revenues, and funding for the NEPA BART Extension Alternative. A summary of VTA s financial plan for the BART Extension Alternative is

More information

Proposition 1B and the Strategic Growth Plan

Proposition 1B and the Strategic Growth Plan Proposition 1B and the Strategic Growth Plan Presentation before the Senate Transportation and Housing Committee California Department of Transportation Proposition 1B Just one component of the Strategic

More information

Planning Committee STAFF REPORT May 3, 2017 Page 2 of 5 previous (2013) RTP. Furthermore, the region is expected to create 820,000 new housing units,

Planning Committee STAFF REPORT May 3, 2017 Page 2 of 5 previous (2013) RTP. Furthermore, the region is expected to create 820,000 new housing units, Planning Committee STAFF REPORT Meeting Date: May 3, 2017 Subject Summary of Issues Recommendations Financial Implications Options Attachments (Attachment A is new) Changes from Committee Comments on Draft

More information

San Francisco County Transportation Authority Prop K/Prop AA Allocation Request Form. Light Rail Vehicle Procurement

San Francisco County Transportation Authority Prop K/Prop AA Allocation Request Form. Light Rail Vehicle Procurement Item 5 Enclosure B Plans and Programs Committee October 7, 2014 FY of Allocation Action: 2014/15 San Francisco County Transportation Authority E5B-1 Project Name: Implementing Agency: Prop K Category:

More information

Memorandum. Date: June 14, 2018 To: From:

Memorandum. Date: June 14, 2018 To: From: Agenda Item 4 Memorandum Date: June 14, 2018 To: From: Subject: Treasure Island Mobility Management Agency Committee Cynthia Fong Deputy Director for Finance & Administration Eric Cordoba Deputy Director

More information

Regional Connector Transit Corridor Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT

Regional Connector Transit Corridor Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT State Clearinghouse Number: 2009031043 April 2010 Prepared for Los Angeles County Metropolitan

More information

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 6 Committee a comparison between the old and new guidelines for Authority reference. Background

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 6 Committee a comparison between the old and new guidelines for Authority reference. Background Planning Committee STAFF REPORT Meeting Date: June 3, 2015 Subject Summary of Issues Recommendations Financial Implications Options Attachments - New Changes from Approval of Revised 2014 CTP Work Plan

More information

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension RESOLUTION NO. R2015-04 Baseline and Schedule, and Approve Gates 5 and 6 for the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Board 04/23/15 Final Action Ahmad Fazel, DECM Executive

More information

Contract Review Sheet

Contract Review Sheet Contract Review Sheet Contract #: 30634 Person Sending: Tim Beaver Department: Public Works Contact Phone #: 503-365-3100 Date Sent: 17 Mar 2016 Contract Amendment # Lease IGA MOU Grant (attach approved

More information

Pima Association of Governments Transportation Improvement Program (TIP) Policies and Procedures

Pima Association of Governments Transportation Improvement Program (TIP) Policies and Procedures Pima Association of Governments Transportation Improvement Program (TIP) Policies and Procedures Introduction: These Policies and Procedures govern the programming of available regional funds through Pima

More information

Memorandum of Understanding, MOU No. M

Memorandum of Understanding, MOU No. M SCAG/VCTC MOU No. M-004-19 SCAG OWP No. 145-4844Q6.01 MEMORANDUM OF UNDERSTANDING BY AND BETWEEN THE SOUTHERN CALIFORNIA ASSOCIATION OF GOVERNMENTS (SCAG) AND THE VENTURA COUNTY TRANSPORTATION COMMISSION

More information

RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming

RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming RESOLUTION NO. R2017-31 Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 09/14/2017

More information

NORTH COUNTY CORRIDOR TRANSPORTATION EXPRESSWAY AUTHORITY. Funding Strategy to Further Implement State Route 132 Expressway and North County Corridor

NORTH COUNTY CORRIDOR TRANSPORTATION EXPRESSWAY AUTHORITY. Funding Strategy to Further Implement State Route 132 Expressway and North County Corridor NORTH COUNTY CORRIDOR TRANSPORTATION EXPRESSWAY AUTHORITY ITEM: 3a SUBJECT: Funding Strategy to Further Implement State Route 132 Expressway and North County Corridor STAFF RECOMMENDATIONS: Approve the

More information

HCAOG CONSULTANT SERVICES CONTRACT FOR PREPARATION OF THE

HCAOG CONSULTANT SERVICES CONTRACT FOR PREPARATION OF THE HCAOG CONSULTANT SERVICES CONTRACT FOR PREPARATION OF THE This is a contract, entered into on, in Eureka, California, between the HUMBOLDT COUNTY ASSOCIATION OF GOVERNMENTS, hereinafter called HCAOG, and,

More information

Approval of Bus Advertising Service Contract with the Bay Area Air Quality Management District. Christy Wegener, Director of Planning and Operations

Approval of Bus Advertising Service Contract with the Bay Area Air Quality Management District. Christy Wegener, Director of Planning and Operations SUBJECT: FROM: Approval of Bus Advertising Service Contract with the Bay Area Air Quality Management District Christy Wegener, Director of Planning and Operations DATE: November 28, 2017 Action Requested

More information

SUPERIOR COURT OF THE STATE OF CALIFORNIA COUNTY OF ALAMEDA, UNLIMITED JURISDICTION

SUPERIOR COURT OF THE STATE OF CALIFORNIA COUNTY OF ALAMEDA, UNLIMITED JURISDICTION 1 OFFICE OF THE GENERAL COUNSEL SAN FRANCISCO BAY AREA RAPID TRANSIT DISTRICT VICTORIA R. NUETZEL (SBN ) 00 Lakeside Drive, rd Floor West Oakland, CA - Tel: () -0 Fax: () -0 EMAIL: vnuetze@bart.gov Attorneys

More information

AGENDA Bacciocco Auditorium, 2 nd Floor 1250 San Carlos Avenue, San Carlos CA 94070

AGENDA Bacciocco Auditorium, 2 nd Floor 1250 San Carlos Avenue, San Carlos CA 94070 BOARD OF DIRECTORS 2011 SEAN ELSBERND, CHAIR OMAR AHMAD, VICE CHAIR JOSÉ CISNEROS NATHANIEL P. FORD, SR. ASH KALRA LIZ KNISS ARTHUR L. LLOYD ADRIENNE TISSIER KEN YEAGER MICHAEL J. SCANLON EXECUTIVE DIRECTOR

More information

TRANSMITTAL #2 FUNDING AGREEMENT BETWEEN SOUTH BAY CITIES COUNCIL OF GOVERNMENTS AND CITY OF LOS ANGELES HARBOR DEPARTMENT (PORT OF LOS ANGELES)

TRANSMITTAL #2 FUNDING AGREEMENT BETWEEN SOUTH BAY CITIES COUNCIL OF GOVERNMENTS AND CITY OF LOS ANGELES HARBOR DEPARTMENT (PORT OF LOS ANGELES) TRANSMITTAL #2 CITY OF LOS ANGELES HARBOR DEPARTMENT (PORT OF LOS ANGELES) CITY OF LOS ANGELES - HARBOR DEPARTMENT (PORT OF LOS ANGELES THIS FUNDING AGREEMENT is entered into this _ day of 2015 by and

More information

Dear Cities, Counties, Transit Agencies, and CMAs:

Dear Cities, Counties, Transit Agencies, and CMAs: June 18, 2007 Bay Area Public Agencies San Francisco Bay Area Subject: Call for Projects for MTC s 2007 Traffic Engineering Technical Assistance Program Dear Cities, Counties, Transit Agencies, and CMAs:

More information

SOUND TRANSIT RESOLUTION NO. R99-14

SOUND TRANSIT RESOLUTION NO. R99-14 SOUND TRANSIT RESOLUTION NO. R99-14 A RESOLUTION of the Board of the Central Puget Sound Regional Transit Authority to reallocate $10 million (1995 dollars) from the East Everett Park and Ride Lot to the

More information

Agreement for Reimbursement of Funds For Construction of Certain Tenant Improvements RECITALS

Agreement for Reimbursement of Funds For Construction of Certain Tenant Improvements RECITALS Agreement for Reimbursement of Funds For Construction of Certain Tenant Improvements This reimbursement agreement (this Agreement ) dated as of September 19, 2011, (the Effective Date ) by and between

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 12 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Adopting the SFMTA s Fiscal Year (FY) 2019 2023 Capital

More information

Analysis of the Alameda County Transportation Expenditure Plan Prepared by Alameda County Transportation Commission

Analysis of the Alameda County Transportation Expenditure Plan Prepared by Alameda County Transportation Commission Analysis of the Alameda County Transportation Expenditure Plan Prepared by Alameda County Transportation Commission Discussion: In 1986, voters approved Measure B, a 1/2 cent sales tax, to fund transportation

More information

COOPERATIVE AGREEMENT FY 2004/05 VENTURA INTERCITY SERVICE TRANSIT AUTHORITY (VISTA) CONEJO CONNECTION

COOPERATIVE AGREEMENT FY 2004/05 VENTURA INTERCITY SERVICE TRANSIT AUTHORITY (VISTA) CONEJO CONNECTION COOPERATIVE AGREEMENT FY 2004/05 VENTURA INTERCITY SERVICE TRANSIT AUTHORITY (VISTA) CONEJO CONNECTION This Agreement is made and entered into by the City of Calabasas (Calabasas) and the Ventura County

More information

Chapter 5: Cost and Revenues Assumptions

Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions Chapter 5: Cost and Revenues Assumptions INTRODUCTION This chapter documents the assumptions that were used to develop unit costs and revenue estimates for the

More information

SB 83 Additional Vehicle Registration Fee Expenditure Plan (July 15, 2010)

SB 83 Additional Vehicle Registration Fee Expenditure Plan (July 15, 2010) 1. INTRODUCTION A. SUMMARY In late October, the Governor signed into law SB 83 (Hancock), which authorizes congestion management agencies (CMAs) to impose an annual vehicle registration fee increase of

More information

TRANSBAY JOINT POWERS AUTHORITY

TRANSBAY JOINT POWERS AUTHORITY THIS STAFF REPORT COVERS CALENDAR ITEM NO.: 8 FOR THE MEETING OF: January 13, 2011 BRIEF DESCRIPTION: TRANSBAY JOINT POWERS AUTHORITY Presentation of the audited Financial Statements of the Transbay Joint

More information

Rule #1: Procedure for Distribution of Revenues for Transportation Services for Seniors and the Disabled

Rule #1: Procedure for Distribution of Revenues for Transportation Services for Seniors and the Disabled BOARD POLICY NO. 031 TransNet ORDINANCE AND EXPENDITURE PLAN RULES The following rules have been adopted and amended by the SANDAG Board of Directors in its role as the San Diego County Regional Transportation

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 4.a REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: September 1, 2015 SUBJECT: AUTHORIZE THE MAYOR TO EXECUTE THE COOPERATIVE AGREEMENT WITH THE CONTRA COSTA TRANSPORTATION

More information

COOPERATIVE AGREEMENT State Independent Quality Assurance (IQA)

COOPERATIVE AGREEMENT State Independent Quality Assurance (IQA) COOPERATIVE AGREEMENT State Independent Quality Assurance (IQA) 03-PLA-65-6.5/12.8 EA: 1F170 Agreement 03-0535 This Agreement, effective on, is between the State of California, acting through its Department

More information

Regional Transportation Plan Checklist (Revised February 2010)

Regional Transportation Plan Checklist (Revised February 2010) Regional Transportation Plan Checklist (Revised February 2010) (To be completed electronically in Microsoft Word format by the MPO/RTPA and submitted along with the draft RTP to Caltrans) Name of MPO/RTPA:

More information

CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2015

CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2015 CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2015 CENTRAL CONTRA COSTA TRANSIT AUTHORITY JUNE 30, 2015 TABLE OF CONTENTS

More information

P.L.2016, CHAPTER 56, approved October 14, 2016 Assembly, No. 10 (Fourth Reprint)

P.L.2016, CHAPTER 56, approved October 14, 2016 Assembly, No. 10 (Fourth Reprint) - C.:B-. Title. Chapter B. (Rename) Infrastructure Trust.,-0 - C.:B-0. to :B-0. - C.:B-. - - C.:B-. & :B-. - Repealer - Note P.L., CHAPTER, approved October, Assembly, No. 0 (Fourth Reprint) 0 0 AN ACT

More information

Pleasanton Bus Rapid Transit Corridor Enhancement Project On-Call Task Order for Project Design and Engineering

Pleasanton Bus Rapid Transit Corridor Enhancement Project On-Call Task Order for Project Design and Engineering SUBJECT: FROM: Pleasanton Bus Rapid Transit Corridor Enhancement Project On-Call Task Order for Project Design and Engineering Jennifer Yeamans, Senior Grants, Project Management & Contract Specialist

More information

CALIFORNIA TRANSPORTATION COMMISSION (CTC) GUIDELINES AND PROCEDURES FOR THE STATE HIGHWAY ACCOUNT LOAN PROGRAM (APPROVED BY CTC ON JUNE 15, 2000)

CALIFORNIA TRANSPORTATION COMMISSION (CTC) GUIDELINES AND PROCEDURES FOR THE STATE HIGHWAY ACCOUNT LOAN PROGRAM (APPROVED BY CTC ON JUNE 15, 2000) CALIFORNIA TRANSPORTATION COMMISSION (CTC) GUIDELINES AND PROCEDURES FOR THE STATE HIGHWAY ACCOUNT LOAN PROGRAM (APPROVED BY CTC ON JUNE 15, 2000) 1 AUTHORITY AND PURPOSE 2 SCOPE OF STATE HIGHWAY ACCOUNT

More information

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 2 Expenditure Plan and directed Air District staff to enter into a funding agreement with the A

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 2 Expenditure Plan and directed Air District staff to enter into a funding agreement with the A Planning Committee STAFF REPORT Meeting Date: June 3, 2015 Subject Summary of Issues Authorize CCTA s Executive Director to Sign TFCA Funding Agreement 16-CC Approval would authorize the Authority s Executive

More information

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD

2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD AGENDA ITEM NO. 2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD TO THE HONORABLE MAYOR AND COUNCIL: DATE: June 22, 2009 Subiect: ADOPTING RESOLUTION NO. 09-53, APPROVING THE CITY'S REVISED PROPOSITION

More information

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 3 Background Consistent with the Measure J Expenditure Plan, the proposed allocation is calcula

Planning Committee STAFF REPORT June 3, 2015 Page 2 of 3 Background Consistent with the Measure J Expenditure Plan, the proposed allocation is calcula Planning Committee STAFF REPORT Meeting Date: June 3, 2015 Subject Summary of Issues Recommendations Financial Implications Options Attachments Approval of FY 2015-16 Measure J Allocation for the Sub-Regional

More information

Transportation Development Act. Local Transportation Fund CLAIM MANUAL FY 2017/18

Transportation Development Act. Local Transportation Fund CLAIM MANUAL FY 2017/18 Transportation Development Act Local Transportation Fund CLAIM MANUAL FY 2017/18 Contents Chapter 1. Overview of the Transportation Development Act... 1-1 Local Transportation Fund (LTF)... 1-2 Where Does

More information

FUNDING AGREEMENT BETWEEN CALIFORNIA HIGHWAY PATROL AND SACRAMENTO TRANSPORTATION AUTHORITY

FUNDING AGREEMENT BETWEEN CALIFORNIA HIGHWAY PATROL AND SACRAMENTO TRANSPORTATION AUTHORITY Agreement No. 1 FUNDING AGREEMENT BETWEEN CALIFORNIA HIGHWAY PATROL AND SACRAMENTO TRANSPORTATION AUTHORITY THIS AGREEMENT, is made and entered into this 9th day of April, 2009, by and between the California

More information

ON-CALL CIVIL ENGINEERING CONSULTING SERVICES AGREEMENT BETWEEN THE CITY OF PITTSBURG AND [NAME OF CONSULTANT]

ON-CALL CIVIL ENGINEERING CONSULTING SERVICES AGREEMENT BETWEEN THE CITY OF PITTSBURG AND [NAME OF CONSULTANT] ON-CALL CIVIL ENGINEERING CONSULTING SERVICES AGREEMENT BETWEEN THE CITY OF PITTSBURG AND [NAME OF CONSULTANT] THIS Agreement ( Agreement ) for consulting services is made by and between the City of Pittsburg

More information

Imposing a Transactions and Use Tax to be Administered by the State Board of Equalization

Imposing a Transactions and Use Tax to be Administered by the State Board of Equalization ORDINANCE AND EXPENDITURE PLAN Regional Transportation Commission Ordinance No. RTC-CO-2017-01 Imposing a Transactions and Use Tax to be Administered by the State Board of Equalization The People of San

More information

Appendix. G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY

Appendix. G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Appendix G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Exhibit G-1 2014 RTP REVENUE FORECAST ASSUMPTIONS LOCAL REVENUES Measure K Sales Tax Renewal Program: Description:

More information

Financial Feasibility of Contra Costa County Ferry Service,

Financial Feasibility of Contra Costa County Ferry Service, Draft Final Report Financial Feasibility of Contra Costa County Ferry Service, 2015-2024 Prepared for: Contra Costa Transportation Authority Prepared by: Economic & Planning Systems, Inc. May 29, 2014

More information

CONSORTIUM FUNDING AGREEMENT NEIGHBORHOOD STABILIZATION PROGRAM 2 COUNTY OF CONTRA COSTA AND CITY OF PITTSBURG

CONSORTIUM FUNDING AGREEMENT NEIGHBORHOOD STABILIZATION PROGRAM 2 COUNTY OF CONTRA COSTA AND CITY OF PITTSBURG CONSORTIUM FUNDING AGREEMENT NEIGHBORHOOD STABILIZATION PROGRAM 2 COUNTY OF CONTRA COSTA AND CITY OF PITTSBURG THIS CONSORTIUM FUNDING AGREEMENT ( Agreement ) is dated as of, 2009, and is between the County

More information

REVISED Supplemental Agenda

REVISED Supplemental Agenda REVISED Supplemental Agenda One Gateway Plaza 3 rd Floor Boardroom PLANNING AND PROGRAMMING COMMITTEE Wednesday, May 20, 2009 1:00 P.M. 6.1 RECEIVE AND FILE status report on the Metro Gold Line Foothill

More information

RECAP OF PROCEEDINGS LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY

RECAP OF PROCEEDINGS LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY SUBJECT 1 APPROVE CONSENT CALENDAR S: 2, 6, 7, 8, 13, 18**, 19, 20, and 26 S 17, 32, 33, 35, 37**, 42 AND 44 WERE REMOVED FROM CONSENT CALENDAR. **REQUIRES 2/3 VOTE OF THE BOARD APPROVED A Y Y A Y Y Y

More information

AGREEMENT. WITNESS: This Agreement has been entered into by and between the

AGREEMENT. WITNESS: This Agreement has been entered into by and between the AGREEMENT WITNESS: This Agreement has been entered into by and between the GOLDEN GATE BRIDGE, HIGHWAY AND TRANSPORTATION DISTRICT (hereinafter GGBHTD ) and the MARIN COUNTY TRANSIT DISTRICT (hereinafter

More information

To: Board of Directors Date: June 15, From: Erick Cheung, Director of Finance

To: Board of Directors Date: June 15, From: Erick Cheung, Director of Finance To: Board of Directors Date: June 15, 2017 From: Erick Cheung, Director of Finance Reviewed by: SUBJECT: Revised Fiscal Year 2018 Draft and Ten Year Forecast SUMMARY: County Connection s Fiscal Year (FY)

More information

PERFORMANCE AUDIT OF COLUSA COUNTY LOCAL TRANSPORTATION COMMISSION FOR THE THREE YEARS ENDED JUNE 30, 2011

PERFORMANCE AUDIT OF COLUSA COUNTY LOCAL TRANSPORTATION COMMISSION FOR THE THREE YEARS ENDED JUNE 30, 2011 PERFORMANCE AUDIT OF COLUSA COUNTY LOCAL FOR THE THREE YEARS ENDED JUNE 30, 2011 SUBMITTED TO COLUSA COUNTY LOCAL THIS PAGE INTENTIONALLY LEFT BLANK PERFORMANCE AUDIT OF COLUSA COUNTY LOCAL Table of Contents

More information

Staff Report. Andrea Ouse, Director of Community and Economic Development Abhishek Parikh, Transportation Manager

Staff Report. Andrea Ouse, Director of Community and Economic Development Abhishek Parikh, Transportation Manager .d Staff Report Date: December, 1 To: From: Reviewed by: Prepared by: Subject: City Council Valerie J. Barone, City Manager Andrea Ouse, Director of Community and Economic Development Abhishek Parikh,

More information

FEDERAL LANDS ACCESS PROGRAM PROJECT MEMORANDUM OF AGREEMENT

FEDERAL LANDS ACCESS PROGRAM PROJECT MEMORANDUM OF AGREEMENT FEDERAL LANDS ACCESS PROGRAM PROJECT MEMORANDUM OF AGREEMENT Project / Facility Name: South Ocean Beach Trail Project Route: Bicycle Route 95 State: California City(ies): City and County of San Francisco

More information

Posted: Nevada Tahoe Conservation District Administrative Office, Douglas County Clerk, Washoe County Clerk, NV Division of Conservation Districts.

Posted: Nevada Tahoe Conservation District Administrative Office, Douglas County Clerk, Washoe County Clerk, NV Division of Conservation Districts. PO Box 915 Zephyr Cove, NV 89448 775-586-1610 x 21 Board Meeting Agenda November 15, 2018 4:00 PM (estimated 1 hour duration) Location: NTCD office or phone in Call in Information: (515) 739-1034, code

More information

Plans and Programs Committee January 12, 2016

Plans and Programs Committee January 12, 2016 Memorandum 01.07.16 Plans and Programs Committee January 12, 2016 Plans and Programs Committee: Commissioners Tang (Chair), Yee (Vice Chair), Breed, Farrell, Peskin and Wiener (Ex Officio) Anna LaForte

More information

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD

MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD October 1, 2015 MAJOR BUSINESS TERMS FOR THE TRANSFORM 66 P3 PROJECT IN THE COMMONWEALTH OF VIRGINIA DBFOM DELIVERY METHOD This Term Sheet ( Term Sheet ) provides a summary of major business terms to be

More information

The Transportation Partnership Opportunity Fund

The Transportation Partnership Opportunity Fund The Commonwealth of Virginia The Transportation Partnership Opportunity Fund Assistance Application September 2005 THE COMMONWEALTH OF VIRGINIA All applicants must complete Sections 1 and 2. Private entities

More information

ADMINISTRATION & FINANCE COMMITTEE MEETING AGENDA

ADMINISTRATION & FINANCE COMMITTEE MEETING AGENDA ADMINISTRATION & FINANCE COMMITTEE MEETING AGENDA Wednesday, December 4, 2013 9:00 a.m. Hanson Bridgett 1676 North California Blvd., Suite 620 Walnut Creek, California The committee may take action on

More information

PROJECT FUNDING AGREEMENT between ALAMEDA COUNTY TRANSPORTATION COMMISSION and the [INSERT PROJECT SPONSOR] for the [INSERT PROJECT TITLE]

PROJECT FUNDING AGREEMENT between ALAMEDA COUNTY TRANSPORTATION COMMISSION and the [INSERT PROJECT SPONSOR] for the [INSERT PROJECT TITLE] PROJECT FUNDING AGREEMENT between ALAMEDA COUNTY TRANSPORTATION COMMISSION and the [INSERT PROJECT SPONSOR] for the [INSERT PROJECT TITLE] This Project Funding Agreement ( AGREEMENT ), dated for reference

More information

Allocation of 18% Local Street Maintenance & Improvement Funds for Fiscal Years and

Allocation of 18% Local Street Maintenance & Improvement Funds for Fiscal Years and GROWTH MANAGEMENT PROGRAM CHECKLIST Allocation of 18% Local Street Maintenance & Improvement Funds for Fiscal Years 2015 16 and 2016 17 Introduction Note: This document may be downloaded from the Web at

More information

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Project No. 9574-2018 Issued 7/19/2017 Washington State University Facility Services, Capital Terre View Research

More information

DULLES CORRIDOR COMMITTEE

DULLES CORRIDOR COMMITTEE M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y DULLES CORRIDOR COMMITTEE Approval Of Phase 2 Cooperative Agreements With The Airports Authority And The Washington Metropolitan

More information

TRANSBAY JOINT POWERS AUTHORITY

TRANSBAY JOINT POWERS AUTHORITY TRANSBAY JOINT POWERS AUTHORITY Independent Auditor s Reports, Management s Discussion and Analysis, Basic Financial Statements and Other Supplementary Information Table of Contents Page(s) Independent

More information

Railroad DOT Mitigation Strategies (R16) Master Project Agreement

Railroad DOT Mitigation Strategies (R16) Master Project Agreement Railroad DOT Mitigation Strategies (R16) Master Project Agreement The master project agreement includes standard legal provisions that are common to nearly all projects and incorporates them into one overall

More information

Page 2 of 5 Options Attachments None 1. Do not transition the programs to CCTA and provide direction back to TRANSPAC. Changes from Committee Backgrou

Page 2 of 5 Options Attachments None 1. Do not transition the programs to CCTA and provide direction back to TRANSPAC. Changes from Committee Backgrou Meeting Date: Subject Summary of Issues Recommendations Financial Implications Approve Transition of Central and East County 511 Contra Costa and Safe Transportation for Children Program Oversight to the

More information

RIVERSIDE COUNTY TRANSPORTATION COMMISSION

RIVERSIDE COUNTY TRANSPORTATION COMMISSION RIVERSIDE COUNTY TRANSPORTATION COMMISSION DATE: May 9, 2012 TO: FROM: THROUGH: Riverside County Transportation Commission Budget and Implementation Committee Michele Cisneros, Accounting and Human Resources

More information

Between the Northern Virginia Transportation Commission and NVTC Project Number:

Between the Northern Virginia Transportation Commission and NVTC Project Number: Attachment #5C I66 Commuter Choice Program Standard Project Agreement for Transform 66: Inside the Beltway Project Toll Revenue Funding of Projects and Administration Between the Northern Virginia Transportation

More information

MTC OVERVIEW OF SB 1 (BEALL AND FRAZIER)

MTC OVERVIEW OF SB 1 (BEALL AND FRAZIER) MTC OVERVIEW OF SB 1 (BEALL AND FRAZIER) NEW & AUGMENTED FUNDING PROGRAMS Below is a summary of the funding provided by program and the new revenue sources authorized in Senate Bill 1 (Beall and Frazier).

More information

Review and Update of Year 2035 Regional Transportation Plan

Review and Update of Year 2035 Regional Transportation Plan Review and Update of Year 2035 Regional Transportation Plan #217752 1 Background Every four years, the Year 2035 Plan is reviewed Elements of review Validity of Plan Year 2035 forecasts Transportation

More information

City of Antioch Development Impact Fee Study

City of Antioch Development Impact Fee Study Report City of Antioch Development Impact Fee Study Prepared for: City of Antioch Prepared by: Economic & Planning Systems, Inc. February 2014 EPS #20001 Table of Contents 1. INTRODUCTION AND RESULTS...

More information

City of Sacramento City Council 915 I Street, Sacramento, CA,

City of Sacramento City Council 915 I Street, Sacramento, CA, City of Sacramento City Council 915 I Street, Sacramento, CA, 95814 www.cityofsacramento.org 9 Meeting Date: 6/7/2012 Report Type: Consent Title: Agreement: Fire Protection Service of Pacific-Fruitridge

More information

Appendix O. Transportation Financial Background

Appendix O. Transportation Financial Background Appendix O Transportation Financial Background Appendix Contents Background Consistency with Other Federal, State, and Local Documents Revenue Constrained Financial Assumptions Revenue Sources: Availability

More information

Administration and Projects Committee STAFF REPORT June 4, 2015 Page 2 of 2 Upon review of permitted investments available to the Authority, State law

Administration and Projects Committee STAFF REPORT June 4, 2015 Page 2 of 2 Upon review of permitted investments available to the Authority, State law Administration and Projects Committee STAFF REPORT Meeting Date: June 4, 2015 Subject Approval of the Authority s Investment Policy for FY 2015-16 Summary of Issues Recommendations Each year the Authority

More information

Working with Proportionate Fair-Share

Working with Proportionate Fair-Share Working with Proportionate Fair-Share December 2006 Presented by the Florida Department of Transportation Working with Proportionate Fair-Share Volume 1, December 2006 Presented by the Florida Department

More information

Appendix J: MTP Checklist. Introduction

Appendix J: MTP Checklist. Introduction J MTP Checklist Appendix J: MTP Checklist Introduction The 2016 Regional Transportation Plan (RTP) Guidelines includes a checklist that the Metropolitan Planning Organization is required to complete upon

More information

Quiet Zone Installation Agreement

Quiet Zone Installation Agreement Quiet Zone Installation Agreement THIS QUIET ZONE INSTALLATION AGREEMENT is made effective this 3rd day of August, 2009, by and between WatersEdge Land Company, L.L.C. ( WatersEdge ) and the City of Overland

More information

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008 MEMORANDUM TO: FROM: Santa Clara Valley Transportation Authority Board of Directors Michael T. Burns General Manager DATE: August 4, 2008 SUBJECT: BART Operating Subsidy This memorandum summarizes and

More information

Working with Proportionate Fair-Share

Working with Proportionate Fair-Share Working with Proportionate Fair-Share Final Volume 1, December 2006 Presented by the Florida Department of Transportation Table of Contents MPO RSI Metropolitan Planning Organization Roadway Segment Improvement

More information

EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT DRAFT REPORT AND NEXUS STUDY. Prepared For: Prepared By:

EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT DRAFT REPORT AND NEXUS STUDY. Prepared For: Prepared By: EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT AND NEXUS STUDY DRAFT REPORT Prepared For: East Contra Costa County Habitat Conservancy Prepared By: Robert D. Spencer, Urban Economics Sally E.

More information

CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2016

CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2016 CENTRAL CONTRA COSTA TRANSIT AUTHORITY CONCORD, CALIFORNIA BASIC FINANCIAL STATEMENTS WITH INDEPENDENT AUDITOR S REPORT JUNE 30, 2016 CENTRAL CONTRA COSTA TRANSIT AUTHORITY JUNE 30, 2016 TABLE OF CONTENTS

More information

Planning Committee STAFF REPORT April 5, 2017 Page 2 of 2 funds that are being applied toward implementation of the Authority s Priority Development A

Planning Committee STAFF REPORT April 5, 2017 Page 2 of 2 funds that are being applied toward implementation of the Authority s Priority Development A Planning Committee STAFF REPORT Meeting Date: April 5, 2017 Subject Summary of Issues Recommendations Financial Implications Circulation of Draft Fiscal Year (FY) 2017-18 Congestion Management Agency (CMA)

More information

ODOT Railroad Audit Circular No. 1

ODOT Railroad Audit Circular No. 1 Definitions, Audit Authority, and Guidance for Computing Overhead Rates for Railroads Release Date: January 1, 2010 Application: Unless and until revised by ODOT, this Circular is effective for actual

More information

Measure B Expenditures Across All Programs FY Report Card

Measure B Expenditures Across All Programs FY Report Card Measure B Across All Programs FY 1314 Report Card AC Transit FY 1314 Planned Projects Program Planned FY 1314 Actual FY 1314 Unspent Amount FY 1314 Unspent Percentage Mass Transit 19,715,268 18,188,651

More information

[MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER]

[MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] Resolution No 14-64, Exhibit A2 [MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] DATED AS OF MAY 1, 2015

More information