Water, Sewer and Storm Sewer Rate Analysis

Size: px
Start display at page:

Download "Water, Sewer and Storm Sewer Rate Analysis"

Transcription

1 Water, Sewer and Storm Sewer Rate Analysis August 8, North Main Street Bowling Green, Ohio

2 Table of Contents Introduction Summary Table Water Summary Water Table 2 Water Fund Projections Fund Balances Table 3 Water Rate Alternative : 3-Year Water Rate Adjustment Table 4 Proposed Water Readiness to Serve Charge (RSC) Table 5 Water Rate Alternative 2: RSC only Table 6 Proposed Water RSC Alternative Table 7 Water Rate Alternative 3: Proposed RSC & Water Rate Adjustment Sewer Table 8 Sewer Fund Projections Fund Balances Table 9 Sewer Rate Alternative : 3-Yr Sewer Rate Adjustment Table 0 Proposed Sewer Readiness to Serve Charge (RSC) Table Sewer Rate Alternative 2: RSC only Table 2 Proposed RSF Alternative Table 3 Sewer Rate Alternative 3: Proposed RSC & Sewer Rate Adjustment Storm Sewer Table 4 Storm Sewer Fund Projections Fund Balances Table 5 Storm Sewer Fund Rate Adjustment Conclusion APPENDIX Rate Adjustment Caparison Tables Current Rates Historic Rates Capital Improvement Plan - New Debt Charts Proposed Readiness to Serve Charge Water History and Projections - No Rate Increase Water Projections - Alternative Rate (Three-Year Rate Increase) Water Projections - Alternative Rate 2 (Readiness to Serve Charge) Water Projections - Alternative Rate 3 (Rate Increase & Readiness to Serve Charge) Sewer History and Projections - No Rate Increase Sewer Projections - Alternative Rate 2 (Readiness to Serve Charge) Sewer Projections - Alternative Rate 3 (Rate Increase & Readiness to Serve Charge) Storm Sewer History and Projections - No Rate Increase Storm Sewer Projections - Three-Year Rate Increase Customer Usage History by meter sizes Customer Billing History by meter sizes Summary History of Usage

3 Village o f Wellin gt o n INTRODUCTION The objective of this study was to examine the revenues from rates charged by the Village to recover the cost of providing water and wastewater service and storm sewer management to customers served by the Village. The major factors considered in establishing the proposed rate structures were:. Revenues must be sufficient to cover the cost of operation and maintenance, debt service requirements, plant equipment replacements, and normal year-to-year improvements to the system. 2. The total revenue produced should be distributed among the various users as equitably as possible by establishing rates and charges proportional to the benefit of services received. 3. The rates and charges recommended should produce the required revenues to operate the present facilities given future anticipated demands on the system. The rate structure itself should be in the simplest of form which will be consistent with the overall objectives of equity and sufficiency. 4. The prudent operation of a self-sufficient municipal utility system requires that it pay for its own operation and expansion, but be nonprofit making to the extent that it does not provide income in excess of realistic needs and a reasonable reserve. 5. Reasonable reserves have been determined to be 25% to 40% of Water Revenues, Sewer Revenues and Storm Sewer Revenues (typically). Alternative rate increases have been addressed which satisfy these concerns. Poggemeyer Design Group ( ) Rev. 8/8/207

4 Village o f Wellin gt o n SUMMARY The basic premise of this study effort was to review the current situation with the goal of adjusting water, wastewater and storm sewer rates to stabilize the operating funds and provide sufficient revenues and to construct required capital improvements. The historical data for revenue and expenses for the water and sewer operating funds was somewhat unique in that grant dollars are allocated to Revenue and Capital Improvement Projects and construction costs are paid from the operating fund. Debt is then amortized as a separate line item. This somewhat skews true revenue and expense balances. We have shown the balances on separate lines in the charts included in this report. Some transfers between funds were not clearly noted making beginning balances for the water and sewer funds not match ending balances of the prior year. In 205, there is a difference in the ending balance and the beginning balance in. The water fund decreases by $74, and the sewer fund decreases by $5, This was verified by Village staff and is noted on the worksheets. The transfer was a reallocation of previous expenses from construction projects to the appropriate funds. We did not verify these balances or that expenses are being properly allocated between the water and wastewater operating funds. This study also does not analyze the miscellaneous fees to ensure they accurately reflect costs of time attributed to tap fees, turn-on fees, repair fees, etc. This analysis is beyond the scope of our work. It should also be noted that the 207 Village Budget did not include an allocation of expenses for employee wages and benefits in the Storm Sewer Fund. Our projections include expenses to these line items as we believe storm sewer regulations will continue to become more stringent and it is anticipated that more time will be needed by Village personnel to meet these regulations. In summary, and based on projected revenue and expenses and existing with anticipated debt, the water fund expenses are exceeding revenues and the fund is depleting. Reserves are approximately a 20% through ; however, reserves drop to 5% in and the fund balance is projected to be negative by. The anticipated new debt projections are shown on the Capital Improvement Plan chart included in the Appendix. Poggemeyer Design Group ( ) Rev. 8/8/207 2

5 Village o f Wellin gt o n The sewer fund expenses are also exceeding the revenue. A 0,000 loan from the Village General Fund in 207 allowed the sewer fund to maintain a minimal positive balance. When the grant dollars allocated to revenue and expenses for construction projects are removed from the fund to show true revenue and expense balances there are approximately only 9% reserves available by the end of 207 and the Sewer Fund will have a negative balance in even with the repayment of the 0,000 General Fund contribution being repaid over a four-year period at $ per year. Even without repaying the 0,000 to the General Fund, the reserves for the Sewer Fund are projected to have a negative balance in. New debt is allocated starting in and includes the amortized costs for the current construction project on Adams Street. Additionally, $7,500 is added to the wastewater Contractual Services in and in for a pending required Wastewater Treatment Plant Improvement Study. The storm sewer fund is only adequate to pay the existing debt. The projected Storm Sewer Fund expenses are exceeding the projected revenue. With the new debt from the Adams Street Improvement project and the reallocation of expenses to pay employee wages and benefits to administer this fund, the fund is projected to have a negative balance in. Reserves for all funds should be maintained at 25% to 40% of revenue. Reserves serve to benefit the Village in a number of potential uses. They are a buffer for years of unpredictable income due to seasonal impacts and economic variables like shift reductions, temporary plant closures, industrial recycling, etc. Reserves are also used for emergency repairs and allow the Village to address Ohio EPA regulatory mandates which cannot be controlled. Additionally, they benefit the future CIP projects and credit rating for financing improvements and securing grant and loan funds. The charts included in this report show various alternative rate adjustments that meet the desired objective for each fund. There are many other alternatives that could be considered to accomplish the same balances including the potential for a fixed rate Readiness to Serve Charge based on meter size in addition to the Village s volume charge for the water and sewer funds. Poggemeyer Design Group ( ) Rev. 8/8/207 3

6 Village o f Wellin gt o n Once the Wastewater Treatment Plant Improvement Study is completed, a review of the Sewer Fund projections may be needed. The debt for any potential improvements is not included in amortized costs in the projections since we do not know the full extent of what may be needed. The Largest Users in the system make up approximately 9.5% of the water usage billed. Historically the 5/8" to " metered customers usage is slightly declining over the four (4) years of historic data decreasing from 8% of the water volume billed in 203 to 73.6% of the water volume billed in. Sewer flows billed for the 5/8" to " metered customers decline from 85.2% in 203 to 83.5% in. The percentage of larger than " meter customers increased water usage billed from 4.7% in 203 to 20% in and increased sewer flow billed from 2.4% in 203 to 4.7% in. The water produced at the water treatment plant supplying the distribution system remains fairly consistent from 204 to. Unaccounted for water is slightly increasing each year based on Village estimates of known non-billed water. The following table shows the calculation for water during the three (3) year period and the calculations for unaccounted for water: Table Water Summary SUMMARY Water Produced (gal.) 72,73 73,2 73,28 Water Billed (gal.) 2,77 8,65 8,60 Non-Billed Water (gal.) 3,07,800 4,805,400 3,930,400 Unaccounted Water (gal.) 37,942,200 39,762,600 40,753,600 % Of Unaccounted Water % Maintenance Water Calculations Hydrant Flushing (gal.),7 3,38 3,43 RLCWA/Avon Lake (gal.) WWTP Water Use (gal.) 5, 5, Village Buildings (gal.) 3,3 3,37 3,45 Fairgrounds (gal.) 200, , ,000 Waterline Breaks () (gal.) 2,22,800,946,400 2,08,400 Total 3,07,800 4,805,400 3,930,400 The waterline break estimate of water volume is based on calculating the water main size over a duration of two (2) hours. The time period for each waterline break was not individually calculated as this information is unknown; therefore, the water losses due to waterline breaks could be significantly higher. The Village, like most communities, has a significant amount of aged infrastructure. There are Poggemeyer Design Group ( ) Rev. 8/8/207 4

7 Village o f Wellin gt o n waterlines that are unsized and in poor condition. Because of this, the Village is operating its water system with the elevated storage tank at a lower elevation in order to reduce pressure within the water system with the intent of avoiding breaking older waterlines. It is highly recommended that a water system analysis and capital improvement plan be developed to begin a systematic replacement of these waterlines. Planned capital improvements are typically far less costly than emergency repairs. Poggemeyer Design Group ( ) Rev. 8/8/207 5

8 Village o f Wellin gt o n Water The normal operating expenses are increasing annually due to inflation and expenses are exceeding the projected revenue. The Village has several capital improvements planned for the distribution system as well as a water treatment plant expansion that will increase debt in the Water Fund. We extended the Water Fund projections to 202 because the OWDA loan on the water treatment plant debt ends in 202 with a final payment of approximately $3; however, new anticipated improvement debt will begin in and increase through the study period. Based on current projections, the Water Fund balance will be depleted in. Detailed charts of revenue and expenses are included in the Appendix. Grant or other funding dollars are also included in the revenue for the Water Fund along with the associated expenses for construction costs. An alternate method for monitoring the revenue and associated expenses for funded construction projects should be considered. Using a construction fund or other separate capital improvement fund is recommended. Table 2 is a summary of the projections and fund balances (207 is shown without grant dollars added to the revenue): TABLE 2 - Water Fund Summary With Projections Water Fund Projections Beginning Balance $284,37 $27,37 $76,450 $46,43 ($99,527) Projected Revenues $85 $869,600 $882,389 $895,370 $908,545 Projected Expenses $870,000 $964,52 $,02,425 $,04,30 $,025,756 Projected Balance $27,37 $76,450 $46,43 ($99,527) ($26,737) % Revenue Reserves 3.7% 20.3% 5.3% -.% -23.9% New Anticipated Debt $23,520 $47,040 $50,480 $53,99 Balance Without New Debt $27,37 $99,970 $93,453 ($49,047) ($62,88) The following tables show the fund balances with alternative rates for the four-year period and the resulting operating fund balance and percentage of reserves for each of the study years. Alternative one includes a 0% rate increase in, 7.5% in, and 5% in and 202: Poggemeyer Design Group ( ) Rev. 8/8/207 6

9 Village o f Wellin gt o n TABLE 3 - Water Rate Alternative Water Rate Adjustment year Rate Increase 0% 7.5% 5% 5% Projected Balance Operating Fund $27,37 $243,923 $234,762 $244,365 Projected Revenue $9 $,00,300 $,059,965 $,2,3 Projected Expenses $968,448 $,09,460 $,050,363 $,036,952 Projected Reserves $243,923 $234,762 $244,365 $39,526 % Revenue Reserves 25.9% 23.2% 23.% 28.7% The second rate alternative incorporates a Readiness to Serve Charge. The Readiness to Serve Charge concept is based on meter size potential maximum volume and the ability to supply water to various establishments within the community. This is specifically based on several published AWWA manuals for rate setting. AWWA Manual M6 Water Meters (2 nd Edition) rates the maximum capacity of meters by size. This allocates costs in a fair and reasonable basis of service capacity and is used to allocate debt from water and sewer projects benefitting the community. Alternative 2 is shown with a $4.00 per month Readiness to Serve Charge that increases with meter size based on AWWA standards. By incorporating the fixed fee, the Village would not have to increase water rates based on the study projections. The Readiness to Serve Charge is projected to generate $37,96 per year. The proposed Readiness to Serve Charge table shows a breakdown of the fee by meter size for both inside and outside users: Table 4 - Water Readiness to Serve Charge Beginning Meter Size Monthly (Inside) Monthly (Outside) 5/8" $4.00 $6.00 3/4" $6.00 $9.00 ".00 $5.00 ½" $20.00 $ " $32.00 $ " $60.00 $ " $20.00 $ " $ $ Poggemeyer Design Group ( ) Rev. 8/8/207 7

10 Village o f Wellin gt o n Table 5 shows the fund balances based on incorporating a Readiness to Serve Charge as shown in Table 4: TABLE 5 - Water Rate Alternative 2 Readiness to Serve Charge 202 Projected Balance Operating Fund $27,37 $34,366 $322,245 $34,22 Projected Revenue $869,600 $882,389 $895,370 $908,545 Projected Revenue Readiness to Serve Charge $37,96 $37,96 $37,96 $37,96 Total Projected Revenue $,007,56 $,020,305 $,033,286 $,046,46 Projected Expenses $964,52 $,02,425 $,04,30 $,025,756 Projected Reserves $34,366 $322,245 $34,22 $334,927 % Revenue Reserves 3.2% 3.6% 30.4% 3 Rate Alternative 3 incorporates a Readiness to Serve Charge with a $2.00 per month rate that increases with meter size and a 5% volume rate increase from through and a 3% increase in 202. The Readiness to Serve Charge is projected to generate $69,696 per year. The proposed Readiness to Serve Charge table shows a breakdown of the fee by meter size for both inside and outside users: Table 6 - Water Readiness to Serve Charge Beginning Meter Size Monthly Fee (Inside) Monthly Fee (Outside) 5/8" $2.00 $3.00 3/4" $3.00 $4.50 " $5.00 $7.50 ½".00 $5.00 2" $6.00 $ " $30.00 $ " $60.00 $ " 0.00 $50.00 Table 7 shows the fund balances based on incorporating a Readiness to Serve Charge as shown in Table 6 and increasing water rates in through 202: Poggemeyer Design Group ( ) Rev. 8/8/207 8

11 Village o f Wellin gt o n TABLE 7 - Water Rate Alternative 3 Water Rate Increase 4-Years with a Readiness to Serve $2.00/Month (5%) (5%) (5%) 202 (3%) Projected Balance Operating Fund $27,37 $273,929 $270,960 $283,580 Projected Revenue $89 $943,00 $989,405 $,08,577 Projected Revenue Readiness to Serve Charge $69,696 $69,696 $69,696 $69,696 Total Projected Revenue $968,696 $,02,796 $,059,0 $,088,273 Projected Expenses $966,38 $,05,764 $,046,482 $,03,808 Projected Reserves $273,929 $270,960 $283,580 $340,045 % Revenue Reserves 28.3% 26.8% 26.8% 3.2% We highly recommend that the Village pass a single ordinance of the chosen rates for the entire study period. The rate analysis should be reviewed annually based on the Village s implementation of planned capital improvements or if additional capital improvements are needed. Poggemeyer Design Group ( ) Rev. 8/8/207 9

12 Village o f Wellin gt o n Sewer The normal operating expenses are increasing annually due to inflation and expenses are exceeding the projected revenue. The Village has some capital improvements planned for the collection system, but other than the current-funded construction project, no other collection system debt is included within the projections for the 5-year study period. The Village has significant anticipated debt for the wastewater treatment plant beyond the study period and a study is recommended to analyze the best, most cost effective alternatives for the Village to maintain compliance with current and known pending EPA requirements. The cost for the wastewater treatment plant study is included in the projections for Contractual Services at $7,500 per year for two (2) years beginning in. Currently, the Village includes grant and funding dollars as well as project specific expenses in the operating fund. It is recommended that an alternate method for monitoring grant and other funding dollars and the associated expenses for construction projects should be considered. The Village borrowed 0,000 from the General Fund in 207 to maintain a positive balance in the Sewer Fund. Our projections include repaying the General Fund $ per year for four (4) years starting in. Even without making the repayment to the General Fund, expenses are exceeding revenues and based on projected expenses, the Sewer Fund balance will be negative in without a rate adjustment. Table 8 is a summary of the projected fund balances: TABLE 8 - Sewer Fund Summary with Projections Sewer Fund Projections 207 Beginning Balance $72,836 $57,836 ($44,432) ($26,55) Projected Revenues $,206,700 $826,500 $834,580 $842,74 Projected Expenses $,2,700 $,028,768 $,05,664 $,050,727 Projected Balance $57,836 ($44,432) ($26,55) ($469,50) % Revenue Reserves 3.% -5.4% -3.3% -55.7% New Anticipated Debt $6,994 $3,987 $3,986 Balance Without New Debt $57,836 ($37,438) ($247,528) ($455,55) Poggemeyer Design Group ( ) Rev. 8/8/207 0

13 Village o f Wellin gt o n Based on the expense projections, adjustments to the Sewer Rate are necessary to recover the funds needed to pay existing debt service and to maintain a self-sufficient nonprofit fund reflecting the desired reserves. In all rate alternatives our projections include repaying the General Fund $ per year for four (4) years starting in and the costs for the wastewater treatment plant study is included in the projections for Contractual Services at $7,500 per year for two (2) years beginning in. Detailed charts of revenue and expenses are included in the Appendix. Alternative includes increasing rates 30% in, 7.5% in and 2.5% in. These scheduled rate increases would allow reserves to 29% of the Revenue by the end of. Table 9 shows the suggested rate increases for the three-year period and the resulting operating fund balance and percentage of reserves for each of the study years: TABLE 9 - Sewer Rate Alternative Sewer Rate Adjustment 3-year Rate Increase 30% 7.5% 2.5% Projected Balance Operating Fund $57,836 $74,846 $243,5 Projected Revenues $,058,500 $,36,500 $,64,450 Projected Expenses $,04,49 $,068,23 $,068,38 Projected Reserves $74,846 $243,5 $339,84 % Revenue Reserves 6.5% 2.4% 29.% The second rate alternative incorporates a Readiness to Serve Charge with an $8.00 minimum base rate that increases with meter size. By incorporating the fixed fee, the Village would not have to increase sewer rates based on the study projections. The Readiness to Serve Charge is projected to generate $254,688 per year. The proposed Readiness to Serve Charge table shows a breakdown of the fee by meter size for both inside and outside users: Poggemeyer Design Group ( ) Rev. 8/8/207

14 Village o f Wellin gt o n Table 0 - Sewer Readiness to Serve Charge Beginning Meter Size Monthly Fee (inside) Monthly Fee (Outside) 5/8" $8.00 $2.00 3/4" $2.00 $8.00 " $20.00 $30.00 ½" $40.00 $ " $64.00 $ " $20.00 $ " $ $ " $ $ Table shows the fund balances based on incorporating a Readiness to Serve Charge as shown in Table 0: TABLE - Sewer Rate Alternative 2 Readiness to Serve Charge Projected Balance Operating Fund $57,836 $20,23 $247,809 Projected Revenue $826,500 $834,580 $842,74 Projected Revenue Readiness to Serve Charge $254,688 $254,688 $254,688 Total Projected Revenue $,08,88 $,089,268 $,097,429 Projected Expenses $,028,793 $,05,690 $,050,754 Projected Reserves $20,23 $247,809 $294,484 % Revenue Reserves 9.4% 22.8% 26.8% Rate Alternative 3 incorporates a Readiness to Serve Charge at $5.00 per month base rate that increases with meter size and a sewer rate increase in of 5% and an increase in of 5%. The Readiness to Serve Charge is projected to generate $59,80 per year. The proposed Readiness to Serve Charge table shows a breakdown of the fee by meter size for both inside and outside users: Poggemeyer Design Group ( ) Rev. 8/8/207 2

15 Village o f Wellin gt o n Table 2 - Sewer Readiness to Serve Charge Beginning Meter Size Monthly Fee (inside) Monthly Fee (outside) 5/8" $5.00 $7.50 3/4" $7.50 $.25 " $2.50 $8.75 ½" $25.00 $ " $40.00 $ " $75.00 $2.50 4" $50.00 $ " $ $ Table 3 shows the fund balances based on incorporating a Readiness to Serve Charge as shown in Table 2 and increasing sewer rates 5% in and 5% : TABLE 3 - Sewer Rate Alternative 3 Sewer Rate Adjustment Projected Balance Operating Fund $57,836 $220,626 $304,435 Projected Revenue $938,500 $984,500 $994,60 Projected Revenue Readiness to Serve Charge $59,80 $59,80 $59,80 Total Projected Revenue $,097,680 $,43,680 $,53,340 Projected Expenses $,034,89 $,059,87 $,059,05 Projected Reserves $220,626 $304,435 $398,760 % Revenue Reserves 20.% 26.6% 34.6% We highly recommend that the Village pass a single ordinance of the chosen rates for the entire study period. The rate analysis should be reviewed annually based on the Village s implementation of planned capital improvements or if additional capital improvements are needed. Poggemeyer Design Group ( ) Rev. 8/8/207 3

16 Village o f Wellin gt o n Storm Sewer The normal operating expenses are increasing annually due to inflation and expenses are exceeding the projected revenue. The Village s 207 Budget removed all charges for an employee s wages and benefits for administration of the storm sewer system and projects. The Village could fund these expenses through other Village funds, but we have allocated projected expenses to these line items with the intent to maintain a self-sufficient Storm Sewer Fund. The Village current capital improvement plan for the storm sewer system only includes the debt for the current construction project on Adams Street. Based on current projections, the Storm Sewer Fund balance will have a negative balance in. Detailed charts of revenue and expenses are included in the Appendix. Grant or other funding dollars are also included in the revenue for the Storm Sewer Fund along with the associated expenses for construction costs. An alternate method for monitoring the revenue and associated expenses for funded construction projects should be considered. Using a construction fund or other separate capital improvement fund is recommended. Table 4 shows the balances without the Grant/Funding dollars added to revenue and without the associated construction expenses (these items offset): TABLE 4 - Storm Sewer Fund Summary with Projections Storm Sewer Fund Projections 207 Beginning Balance $73,446 $78,946 ($5,360) ($94,655) Projected Revenues $ $ $ $ Projected Expenses 6,500 $96,306 $20,295 $204,502 Projected Balance $78,946 ($5,360) ($94,655) ($87,57) New Anticipated Debt $,933 $3,865 $3,865 Balance Less New Debt $78,946 ($3,427) ($90,790) ($76,269) Poggemeyer Design Group ( ) Rev. 8/8/207 4

17 Village o f Wellin gt o n Based on the expense projections, adjustments to the Storm Utility Rate are necessary to recover the funds needed to pay existing debt service and to maintain a self-sufficient nonprofit fund reflecting the desired reserves. Table 5 shows increasing the rate in to $6.00 per 2,900 S.F. These scheduled rate increases would allow reserves to be maintained at approximately 30% of the Revenue through the study period. TABLE 5 - Storm Sewer Utility Rate Adjustment per 2,900 S.F. Storm Sewer Rate Adjustment Projected Balance Operating Fund $78,946 $74,6 $65,286 Projected Revenues $9 $9 $9 Projected Expenses $96,335 $20,325 $204,532 Projected Reserves $74,6 $65,286 $52,754 % Revenue Reserves 38.9% 34.0% 27.5% Poggemeyer Design Group ( ) Rev. 8/8/207 5

18 Village o f Wellin gt o n CONCLUSION The required fund increases/adjustments to maintain proper operating expenses and basic recommended reserves have been neglected to the point where significant adjustments are now required. These volume rate increases are significant, but can be partially or totally offset by implementation of a Readiness to Serve Charge to pay for new and existing debt. The benefit to the Readiness to Serve Charge is that it is a fixed monthly charge. This seems to be more palatable to the users and it is also a more reliable revenue stream if there are reductions in volume usage that are often experienced with volume rate increases. Another more reliable alternative revenue source can be adjusting the minimum rates and/or volumes. This has the same net impact as a fixed rate Readiness to Serve Charge if properly implemented. The sooner the rates are adjusted, the less financial recovery will be required to stabilize the funds and create recommended reserves. This condition can be prevented in the future by annual reviews and annual inflationary adjustment that reflect expense impacts and volume usage fluctuations due to many economic variables that can occur. These volume usages are impacted by seasonal weather, new water saving fixtures and appliances, new industrial equipment, industrial recycling, shift reductions or reduced hours, etc. Poggemeyer Design Group ( ) Rev. 8/8/207 6

19 APPENDIX Village o f Wellin gt o n

20 Village o f Wellin gt o n Proposed Water and Sewer Rate Comparisons Existing Rate Alternative Alternative 2 Alternative 3 Water Inside Outside Inside Outside Inside Outside Inside Outside Minimum $7.75 $.6 $8.52 $2.77 $.75 $7.6.3 $ (5/8" $23.05 $34.79 $25.35 $38.26 $27.05 $40.79 $26.20 $ (5/8") $37.92 $57.33 $4.72 $63.06 $4.92 $63.33 $4.82 $ (5/8") $52.57 $79.28 $57.83 $87.20 $56.57 $85.28 $57.20 $86.25 Proposed Water and Sewer Rate Comparisons Existing Rate Alternative Alternative 2 Alternative 3 Sewer Inside Outside Inside Outside Inside Outside Inside Outside Minimum $7.75 $.6.07 $5.09 $5.75 $23.6 $3.90 $ (5/8" $23.05 $34.79 $29.96 $45.22 $3.05 $46.79 $3.50 $ (5/8") $37.92 $57.33 $49.36 $74.53 $45.92 $69.33 $48.6 $ (5/8") $52.57 $79.28 $ $60.57 $9.28 $65.45 $98.67 Storm Sewer: Rate Existing = $3.50 Proposed = $6.00 Page 7

21 Village o f Wellin gt o n Proposed Alternative Rate 202 Water 0% 7.5% 5% 5% Minimum $8.52 $9.6 $ (5/8" $25.35 $27.25 $28.6 $ (5/8") $4.72 $44.85 $47.09 $ (5/8") $57.83 $62.7 $65.28 $68.54 Proposed Alternative Rate 202 Sewer 30% 7.5% 2.5% 0% Minimum $.0 $ (5/8" $29.96 $32.2 $33.02 $ (5/8") $49.36 $53.06 $54.39 $ (5/8") $68.34 $73.47 $75.3 $75.3 Page 8

22 Village o f Wellin gt o n Proposed Alternative Rate 2 Water 202 Minimum $.75 $.75 $.75 $ (5/8" $27.05 $27.05 $27.05 $ (5/8") $4.92 $4.92 $4.92 $ (5/8") $56.57 $56.57 $56.57 $56.57 Proposed Alternative Rate 2 Sewer 202 Minimum $5.75 $5.75 $5.75 $ (5/8" $3.05 $3.05 $3.05 $ (5/8") $45.92 $45.92 $45.92 $ (5/8") $60.57 $60.57 $60.57 $60.57 Page 9

23 Village o f Wellin gt o n Proposed Alternative Rate 3 Water 202 Minimum $ (5/8" $26.20 $27.4 $28.68 $ (5/8") $4.82 $43.8 $45.90 $ (5/8") $57.20 $59.96 $62.85 $64.68 Proposed Alternative Rate 3 Sewer 202 Minimum $3.90 $4.36 $4.36 $ (5/8" $3.50 $32.83 $32.83 $ (5/8") $48.6 $50.79 $50.79 $ (5/8") $65.45 $68.47 $68.47 $68.47 Page 20

24 WATER INSIDE USER Alternative : 000 = $8.52 SEWER INSIDE USER Alternative : 000 =.07 Alternative 2 (5/8" Meter): Alternative 2 (5/8" Meter): 000 = $ $4.00 = $ = $ $8.00 = $5.75 Alternative 3 (5/8" Meter) 000 = $8.3 + $2.00 =.3 Alternative 3 (5/8" Meter) 000 = $8.9 + $5.00 = $3.9 Alternative : 0% Increase Alternative : 30% Increase Base Volume Rate Only, Add Readiness to Serve Charge Based on Meter Size Alternative 3: Volume Increase 5% Base Volume Rate Only, Add Readiness to Serve Charge Based on Meter Size Alternative 3: Volume Increase 5% INSIDE WATER RATES OUTSIDE WATER RATES INSIDE SEWER RATES OUTSIDE SEWER RATES INSIDE WATER RATES OUTSIDE WATER RATES INSIDE SEWER RATES OUTSIDE SEWER RATES Cost Per 000 gal Cost in Water Cost Per 000 gal Cost in Water Cost Per 000 gal Cost in Wastew ater Cost Per 000 gal Cost in Wastew ater Cost Per 000 gal Cost in Water Cost Per 000 gal Cost in Water Cost Per 000 gal Cost in Wastew ater Cost Per 000 gal Cost in Wastew ater $8.52,000 $8.52 $2.77,000 $ , $5.09,000 $5.09 $8.3,000 $8.3 $2.9,000 $2.9 $8.9,000 $8.9 $3.35,000 $3.35 $8.52 $8.45 $8.42 $8.34 $8.30 $8.26 $8.23 $8.2 $8.20 $8.9 $8.5 $8.3 $8. $8.09 $8.07 $8.05 $8.04 $8.03 $8.02 $8.0 $8.00 $7.99 $7.98 $7.98 $7.97 $7.96 $7.96 $7.93 $7.89 $7.85 $7.83 $7.8 $7.58 $7.5 0,000, ,000 $7.04 $25.35 $33.66 $4.72 $49.77 $57.83 $65.88 $73.93 $8.99 $90.04 $ $3.47 $2.28 $29.09 $36.90 $44.7 $52.52 $60.33 $68.4 $75.95 $83.76 $9.57 $99.38 $207.9 $25.00 $222.8 $ $276.0 $34.7 $ $390.3 $758.5 $,25.98 $2.77 $2.75 $2.75 $2.6 $2.52 $2.46 $2.4 $2.37 $2.34 $2.32 $2.27 $2.23 $2.9 $2.6 $2.3 $2. $2.09 $2.07 $2.05 $2.04 $2.02 $2.0 $2.00 $.99 $.98 $.97 $.96 $.92 $.85 $.79 $.75 $.7 $.38 $.27 0,000, ,000 $25.53 $38.26 $5.00 $63.06 $75.3 $87.20 $99.27 $.34 $23.4 $35.48 $47.2 $58.93 $70.66 $82.39 $94. $ $27.57 $ $24.02 $ $ $ $ $ $3.38 $323. $ $ $44.6 $47.59 $ $ $,38.22 $, $9.99 $9.95 $9.80 $9.76 $9.73 $9.7 $9.69 $9.67 $9.64 $9.6 $9.56 $9.54 $9.52 $9.50 $9.49 $9.47 $9.46 $9.45 $9.44 $9.43 $9.43 $9.42 $9.4 $9.40 $9.38 $9.32 $9.28 $9.25 $9.23 $8.96 $8.87 0,000, ,000 $20.4 $29.96 $39.78 $49.30 $58.82 $68.34 $77.86 $87.38 $ $5.64 $24.87 $34.0 $43.33 $52.56 $6.79 $7.02 $80.25 $89.48 $98.7 $ $27.7 $ $ $ $ $ $28.3 $ $37.29 $46.29 $46.28 $ $,330.7 $5.09 $5.07 $5.07 $4.9 $4.80 $4.72 $4.67 $4.62 $4.59 $4.56 $4.50 $4.45 $4.4 $4.37 $4.34 $4.3 $4.28 $4.26 $4.24 $4.22 $4.2 $4.9 $4.8 $4.7 $4.5 $4.4 $4.3 $4.09 $4.00 $3.93 $3.88 $3.84 $3.45 $3.32 0,000, ,000 $30.8 $45.22 $60.27 $74.53 $ $7.32 $3.59 $45.85 $60. $73.97 $87.83 $20.69 $25.55 $229.4 $ $257.3 $ $ $ $32.56 $ $ $354.4 $ $38.86 $395.7 $ $ $ $ $692.0 $,345.7 $, $8.3 $8.07 $8.03 $7.96 $7.92 $7.89 $7.86 $7.84 $7.83 $7.8 $7.78 $7.76 $7.74 $7.72 $7.70 $7.69 $7.67 $7.66 $7.65 $7.64 $7.63 $7.63 $7.62 $7.6 $7.6 $7.60 $7.60 $7.57 $7.53 $7.50 $7.47 $7.45 $7.24 $7.7 0,000, ,000 $6.26 $24.20 $32.3 $39.82 $47.5 $55.20 $62.89 $70.57 $78.26 $85.95 $ $5.77 $23.22 $30.68 $38.3 $45.59 $53.04 $60.50 $67.95 $75.4 $82.86 $90.32 $97.77 $ $22.68 $227.2 $ $ $ $ $ $, $2.9 $2.8 $2.7 $2.04 $.95 $.89 $.85 $.8 $.78 $.76 $.7 $.67 $.64 $.6 $.58 $.56 $.54 $.52 $.50 $.49 $.48 $.46 $.45 $.44 $.43 $.42 $.4 $.38 $.3 $.25 $.2 $ ,000, ,000 $24.37 $36.53 $48.68 $60.20 $7.72 $83.24 $ $7.80 $29.32 $40.52 $5.7 $62.90 $74.0 $85.29 $96.48 $ $28.87 $ $24.26 $ $ $ $ $ $ $39.62 $34.37 $ $450.5 $ $ $, $,64.04 $8.9 $8.83 $8.80 $8.72 $8.67 $8.64 $8.6 $8.59 $8.57 $8.56 $8.53 $8.50 $8.47 $8.45 $8.43 $8.42 $8.40 $8.39 $8.38 $8.37 $8.36 $8.35 $8.34 $8.34 $8.33 $8.32 $8.32 $8.30 $8.25 $8.2 $8.8 $8.6 $7.93 $7.85 0,000, ,000 $7.8 $26.50 $35.9 $43.6 $52.03 $60.45 $68.87 $77.30 $85.72 $ $8.63 $26.79 $34.96 $43.2 $5.29 $59.45 $67.62 $75.78 $83.95 $92. $ $ $26.6 $ $ $ $ $ $ $ $792.6 $,77.6 $3.35 $3.33 $3.33 $3.9 $3.09 $3.02 $2.97 $2.93 $2.90 $2.88 $2.82 $2.78 $2.74 $2.7 $2.68 $2.66 $2.64 $2.62 $2.60 $2.58 $2.57 $2.55 $2.54 $2.53 $2.52 $2.5 $2.50 $2.46 $2.38 $2.33 $2.28 $2.24 $.90 $.79 0,000, ,000 $26.69 $40.00 $53.3 $65.93 $78.55 $ $6.40 $29.02 $4.64 $53.90 $66.6 $78.42 $90.68 $ $25.20 $ $ $25.98 $ $ $ $30.02 $33.28 $ $ $ $ $ $ $ $62.7 $,89.96 $, P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 2 08/7/7

25 Change - 7.2% 2 7.0% Cost in Wastewater $7.78 $ $ RATE HISTORY SUMMARY FOR INITIAL 000 GALLONS INSIDE WATER RATES OUTSIDE WATER RATES INSIDE SEWER RATES Cost st Cost in Cost st Cost in Cost st Cost in 000 gal Change Water 000 gal Change Water 000 gal Change Wastewater $ % $ %.43 $5.9 - $5.9 $ % $ %.43 $ % $5.57 $ % $ %.43 $ $6.96 * $ % $7.45 $.6 7.0% $.6 $ % $7.45 ** OUTSIDE SEWER RATES Cost st 000 gal $7.78 $ $.6 $ % $7.75 $.6 4.0% $.6 $ % $7.75 $.6 4.0% $.6 *80% of Water Rate **00% of Water Rate Page 22 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw 08/7/7

26 May Rate Increase: 4% CURRENT SEWER RATES CURRENT WATER RATES OUTSIDE SEWER RATES INSIDE SEWER RATES OUTSIDE WATER RATES INSIDE WATER RATES Wastewater Cost in 000 gal Cost Per Wastewater Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per $.6,000 $.6 $7.75,000 $7.75 $.6,000 $.6 $7.75,000 $7.75 $23.2 $.6 $5.49 $7.75 $23.2 $.6 $5.49 $7.75 $34.79 $.57 $23.05 $7.56 $34.79 $.57 $23.05 $7.56 $46.36 $.57 $30.60 $7.56 $46.36 $.57 $30.60 $7.56 $ $37.92 $7.32 $ $37.92 $7.32 $ $45.25 $7.32 $ $45.25 $7.32 $ $52.57 $7.32 $ $52.57 $7.32 $ $59.89 $7.32 $ $59.89 $ $67.2 $ $67.2 $7.32 $2.9 0, $ ,000 $7.32 $2.9 0, $ ,000 $7.32 $23.6, $8.86,000 $7.32 $23.6, $8.86,000 $7.32 $ $88.96 $7.0 $ $88.96 $7.0 $ $96.06 $7.0 $ $96.06 $7.0 $ $7.0 $ $7.0 $ $7.0 $ $7.0 $ $7.36 $7.0 $ $7.36 $7.0 $ $24.46 $7.0 $ $24.46 $7.0 $ $3.56 $7.0 $ $3.56 $7.0 $ $38.65 $7.0 $ $38.65 $7.0 $ $45.75 $7.0 $ $45.75 $7.0 $ $52.85 $7.0 $ $52.85 $7.0 $ $59.95 $7.0 $ $59.95 $7.0 $ $67.05 $7.0 $ $67.05 $7.0 $ $74.5 $7.0 $ $74.5 $7.0 $ $8.25 $7.0 $ $8.25 $7.0 $ $ $7.0 $ $ $7.0 $ $ $7.0 $ $ $7.0 $ $ $7.0 $ $ $7.0 $ $26.40 $6.92 $ $26.40 $6.92 $ $ $6.92 $ $ $6.92 $ $285.6 $6.92 $ $285.6 $6.92 $ $ $6.92 $ $ $6.92 $ $ $6.92 $ $ $6.92 $, , $ ,000 $6.69 $, , $ ,000 $6.69 $, $, $6.69 $, $, $ /7/7 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 23

27 November 204 Rate Increase: 7% OUTSIDE SEWER RATES INSIDE SEWER RATES OUTSIDE WATER RATES INSIDE WATER RATES Wastewater Cost in 000 gal Cost Per Wastewater Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per $.6,000 $.6 $7.45,000 $7.45 $.6,000 $.6 $7.45,000 $7.45 $22.32 $.6 $4.89 $7.45 $22.32 $.6 $4.89 $7.45 $33.45 $.3 $22.6 $7.27 $33.45 $.3 $22.6 $7.27 $44.57 $.3 $29.4 $7.27 $44.57 $.3 $29.4 $7.27 $ $36.47 $7.04 $ $36.47 $7.04 $ $43.5 $7.04 $ $43.5 $7.04 $ $50.56 $7.04 $ $50.56 $7.04 $ $57.60 $7.04 $ $57.60 $7.04 $ $64.65 $7.04 $ $64.65 $ , $7.69 0,000 $ , $7.69 0,000 $7.04 $8.46, $78.73,000 $7.04 $8.46, $78.73,000 $7.04 $ $85.57 $ $85.57 $ $92.39 $ $92.39 $ $99.23 $ $99.23 $ $ $ $2.89 $ $2.89 $ $9.72 $ $9.72 $ $26.55 $ $26.55 $ $33.39 $ $33.39 $ $40.2 $ $40.2 $ $47.04 $ $47.04 $ $53.88 $ $53.88 $ $60.70 $ $60.70 $ $67.53 $ $67.53 $ $74.37 $ $74.37 $ $8.9 2 $ $8.9 2 $ $ $ $ $ $ $ $ $32.68 $9.96 $208.7 $6.66 $32.68 $9.96 $208.7 $6.66 $ $9.96 $ $6.66 $ $9.96 $ $6.66 $42.29 $9.96 $ $6.66 $42.29 $9.96 $ $6.66 $ $9.96 $ $6.66 $ $9.96 $ $6.66 $5.9 $9.96 $34.24 $6.66 $5.9 $9.96 $34.24 $6.66 $ ,000 $9.66 $ ,000 $6.43 $ ,000 $9.66 $ ,000 $6.43 $, $9.66 $983.9 $6.43 $, $9.66 $983.9 $ /7/7 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 24

28 202 Rate Increase: Increase only Sewer to 00% of Water Rate OUTSIDE SEWER RATES INSIDE SEWER RATES OUTSIDE WATER RATES INSIDE WATER RATES Wastewater Cost in 000 gal Cost Per Wastewater Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per.43, $6.96,000 $ , $6.96,000 $6.96 $ $3.92 $6.96 $ $3.92 $6.96 $ $20.7 $6.79 $ $20.7 $6.79 $ $27.49 $6.79 $ $27.49 $6.79 $5.52 $34.08 $5.52 $34.08 $6.38 $40.66 $6.38 $40.66 $7.25 $47.25 $7.25 $47.25 $8. $53.83 $8. $53.83 $90.98 $60.42 $90.98 $ ,000 $ , ,000 $ ,000.7,000 $73.58,000.7,000 $73.58,000 $20.29 $79.97 $20.29 $79.97 $29.87 $86.35 $29.87 $86.35 $39.45 $92.74 $39.45 $92.74 $49.03 $99.2 $49.03 $99.2 $ $ $68.20 $.89 $68.20 $.89 $77.78 $8.27 $77.78 $8.27 $87.36 $24.66 $87.36 $24.66 $96.94 $3.04 $96.94 $3.04 $ $37.42 $ $37.42 $26. $43.8 $26. $43.8 $ $50.9 $ $50.9 $ $56.57 $ $56.57 $ $62.96 $ $62.96 $ $ $ $ $ $ $ $ $ $82. 2 $ $82. 2 $ $9.3 $94.55 $6.22 $ $9.3 $94.55 $6.22 $ $9.3 $ $6.22 $ $9.3 $ $6.22 $ $9.3 $ $6.22 $ $9.3 $ $6.22 $ $9.3 $ $6.22 $ $9.3 $ $6.22 $ $9.3 $38.92 $6.22 $ $9.3 $38.92 $6.22 $ ,000 $9.03 $ ,000 $6.0 $ ,000 $9.03 $ ,000 $6.0 $,38.2 $9.03 $99.54 $6.0 $,38.2 $9.03 $99.54 $6.0 08/7/7 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 25

29 2008 Rate Increase: Increase only Sewer to 80% of Water Rate OUTSIDE SEWER RATES INSIDE SEWER RATES OUTSIDE WATER RATES INSIDE WATER RATES Wastewater 000 gal Wastewater 000 gal Water 000 gal Water 000 gal $8.34,000 $8.34 $5.57,000 $ , $6.96,000 $6.96 $6.69 $8.34 $.4 $5.57 $ $3.92 $6.96 $25.0 $8.32 $6.57 $5.43 $ $20.7 $6.79 $33.32 $8.32 $2.99 $5.43 $ $27.49 $6.79 $4.22 $7.89 $27.26 $5.26 $5.52 $34.08 $49.0 $7.89 $32.53 $5.26 $6.38 $40.66 $57.00 $7.89 $37.80 $5.26 $7.25 $47.25 $64.89 $7.89 $43.06 $5.26 $8. $53.83 $72.78 $7.89 $48.34 $5.26 $90.98 $60.42 $ ,000 $7.89 $ ,000 $ ,000 $ ,000 $88.57,000 $7.89 $58.86,000 $5.26.7,000 $73.58,000 $96.23 $7.66 $63.98 $5.0 $20.29 $ $7.66 $69.08 $5.0 $29.87 $86.35 $.56 $7.66 $74.9 $5.0 $39.45 $92.74 $9.22 $7.66 $79.30 $5.0 $49.03 $99.2 $26.90 $7.66 $84.40 $5.0 $ $34.56 $7.66 $89.5 $5.0 $68.20 $.89 $42.22 $7.66 $94.62 $5.0 $77.78 $8.27 $49.89 $7.66 $99.73 $5.0 $87.36 $24.66 $57.55 $ $5.0 $96.94 $3.04 $65.22 $ $5.0 $ $37.42 $72.89 $7.66 $5.05 $5.0 $26. $43.8 $80.55 $7.66 $20.5 $5.0 $ $50.9 $88.22 $7.66 $25.26 $5.0 $ $56.57 $95.88 $7.66 $30.37 $5.0 $ $62.96 $ $7.66 $ $5.0 $ $ $2.2 2 $7.66 $ $5.0 $ $ $ $7.66 $ $5.0 $ $82. 2 $ $7.45 $55.64 $4.98 $ $9.3 $94.55 $6.22 $ $7.45 $ $4.98 $ $9.3 $ $6.22 $ $7.45 $ $4.98 $ $9.3 $ $6.22 $ $7.45 $ $4.98 $ $9.3 $ $6.22 $ $7.45 $255.4 $4.98 $ $9.3 $38.92 $6.22 $ ,000 $7.22 $ ,000 $4.8 $ ,000 $9.03 $ ,000 $6.0 $,04.90 $7.22 $ $4.8 $,38.2 $9.03 $99.54 $6.0 08/7/7 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 26

30 December 4, 2006 Rate Increase: Water Increase 8%, Sewer Decrease 2% OUTSIDE SEWER RATES INSIDE SEWER RATES OUTSIDE WATER RATES INSIDE WATER RATES Wastewater Cost in 000 gal Cost Per Wastewater Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per Water Cost in 000 gal Cost Per $7.78,000 $7.78 $5.9,000 $5.9.43, $6.96,000 $6.96 $5.56 $ $5.9 $ $3.92 $6.96 $23.3 $7.75 $5.44 $5.06 $ $20.7 $6.79 $3.06 $7.75 $20.50 $5.06 $ $27.49 $6.79 $38.42 $7.36 $25.4 $4.9 $5.52 $34.08 $45.78 $7.36 $30.32 $4.9 $6.38 $40.66 $53.3 $7.36 $35.24 $4.9 $7.25 $47.25 $60.49 $7.36 $40.5 $4.9 $8. $53.83 $67.85 $7.36 $45.06 $4.9 $90.98 $60.42 $ ,000 $7.36 $ ,000 $ ,000 $ ,000 $82.56,000 $7.36 $54.88,000 $4.9.7,000 $73.58,000 $89.7 $7.5 $59.64 $4.76 $20.29 $79.97 $96.85 $7.5 $64.40 $4.76 $29.87 $ $7.5 $69.6 $4.76 $39.45 $92.74 $.4 $7.5 $73.92 $4.76 $49.03 $99.2 $8.29 $7.5 $78.68 $4.76 $ $25.44 $7.5 $83.44 $4.76 $68.20 $.89 $32.58 $7.5 $88.20 $4.76 $77.78 $8.27 $39.73 $7.5 $92.96 $4.76 $87.36 $24.66 $46.87 $7.5 $97.72 $4.76 $96.94 $3.04 $54.02 $ $4.76 $ $37.42 $6.6 $ $4.76 $26. $43.8 $68.3 $7.5 $2.0 $4.76 $ $50.9 $75.45 $7.5 $6.77 $4.76 $ $56.57 $82.60 $7.5 $2.53 $4.76 $ $62.96 $ $7.5 $ $4.76 $ $ $ $7.5 $ $4.76 $ $ $ $7.5 $ $4.76 $ $82. 2 $27.92 $6.94 $45.09 $4.64 $ $9.3 $94.55 $6.22 $ $6.94 $ $4.64 $ $9.3 $ $6.22 $ $6.94 $9.46 $4.64 $ $9.3 $ $6.22 $ $6.94 $ $4.64 $ $9.3 $ $6.22 $ $6.94 $ $4.64 $ $9.3 $38.92 $6.22 $ ,000 $6.73 $ ,000 $4.48 $ ,000 $9.03 $ ,000 $6.0 $, $6.73 $ $4.48 $,38.2 $9.03 $99.54 $6.0 08/7/7 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 27

31 Capital Improvement Plan - Water, Sewer & Storm Water Project Name/Description WATER Probable Cost Potential Funding Potential Grant Potential Finance Potential Rate Term (#yr) 207 Five Year Plan 202 Adams Street Waterline Improvement $96,799 L-O-EPA $24,926 $46,947 $24,926 WSRLA.63% OPWC 0% $4,335 $45 $8,669 $83 $8,669 $83 $8,669 $83 Ground Level Storage Tank & Reservoir Pumping Improvements $,30,200 L-O-EPA $7 $95,200 $7 WSLRA 0% HAB OPWC 0% $5,853 $2,97 $3,707 $5,833 $3,707 $5,833 $3,707 $5,833 Wenner Street Waterline Replacement $367,729 L-O-EPA $7 $7,729 $7 WSRLA.63% OPWC 0% $523 $2,97 $,046 $5,833 WTP Expansion Improvements $,39,520 L-O-EPA $7 $,04,520 $7 WSLRA 0% HAB OPWC 0% 30 Additional Potential Projects Past 5-Yr Study Period Vine Street Waterline Improvements Fairgrounds Road Waterline Replacement Dickson Street Waterline Improvements East St. Waterline Improvements Taylor Street Waterline Improvements Union Street Waterline Improvements McKinley Street Waterline Improvements $4,555 $248,820 $52,965 2,835 $95,880 $74,985 $84,80 L-O-EPA L-O-EPA L L L L L Western Water Dist. Main Repl. Erie/Industrial Elevated Tank Feed Line Meter Replacement $2,354,295 $2,202,430 $,04,290 L-O-EPA L-O L-O Total Water Improvements $9,89,483 $23,520 $47,040 $50,480 $53,99 SEWER Probable Cost Potential Funding Potential Grant Potential Finance Potential Rate Term (#yr) Adams Street Sanitary Sewer Improvement $289,753 L-O-EPA $36,700 $26,354 $36,700 WSRLA.63% OPWC 0% $6,382 $62 $2,764 $,223 $2,764 $,223 $2,764 $,223 Additional Potential Projects Past 5-Yr Study Period WWTP Improvements (Study Needed) $9,360,000 $ $9.36 M Magyar Street Sanitary Sewer Rehab. $7,500 North Main Street Sanitary Rehab $52,985 Forest Street Sanitary Sewer Repl. $397,755 L-O-EPA L-O L-O L-O Total Sewer Improvements $9,928,240 $6,994 $3,987 $3,987 $3,987 STORM WATER Probable Cost Potential Funding Potential Grant Potential Finance Potential Rate Term (#yr) Adams Street Drainage Improvement Total Storm Water Improvements $80,074 $80,074 L-O-EPA,42 $59,790,42 WSRLA.63% OPWC 0% $,764 $69 $,933 $3,527 $338 $3,865 $3,527 $338 $3,865 $3,527 $338 $3,865 L= Loan, O=Ohio Public Works Commission, EPA=DEFA, SU= Storm Utility Rates P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 28 08/7/7

32 Proposed Readiness to Serve Charge ALTERNATIVE 2 CUSTOMER COUNT Water NB - no bill NC - No charge Sub-Total Proposed Beginning ALTERNATIVE 2 CUSTOMER COUNT Sewer NB - No bill NC - No charge Proposed Beginning Water Beginning Readiness to Serve Charge Monthly Meter Size Fee 202 5/8" $4.00 $4.00 $4.00 $4.00 3/4" $6.00 $6.00 $6.00 $6.00 " WATER Outside 202 SEWER Outside ½" $20.00 $20.00 $20.00 $20.00 RW 2" $32.00 $32.00 $32.00 $32.00 OW - 5/8 Meter OW 2-3/4" Meter OW 4 - ½" Meter OW 5-2" Meter 29 3 $74.00 $9.00 $30.00 $44.00 $74.00 $9.00 $30.00 $44.00 $74.00 $9.00 $30.00 $44.00 $74.00 $9.00 $30.00 $44.00 OS - 5/8 Meter OS2-3/4" Meter OS4 - ½" Meter OS5-2" Meter 0 2 $32.00 $60.00 $92.00 $32.00 $60.00 $92.00 $32.00 $60.00 $ " 4" 6" $60.00 $20.00 $ $60.00 $20.00 $ $60.00 $20.00 $ $60.00 $20.00 $ Sub-Total WATER Inside W - 5/8" Meter W 2-3/4" Meter W 3 - " Meter W 4 - ½" Meter W 5-2" Meter W 6-3" Meter W 7-4" Meter W 8-6" Meter Sub-Total 35 2, ,59 $ $8,84.00 $92.00 $40.00 $ $, $80.00 $ $ $,36.00 $ $8,84.00 $92.00 $40.00 $ $, $80.00 $ $ $,36.00 $ $8,84.00 $92.00 $40.00 $ $, $80.00 $ $ $,36.00 $ $8,84.00 $92.00 $40.00 $ $, $80.00 $ $ $,36.00 Sub-Total SEWER Inside S - 5/8" Meter S2-3/4" Meter S3 - " Meter S4 - ½" Meter S5-2" Meter S6-3" Meter S7-4" Meter S8-6" Meter Sub-Total 4 2, ,38 $ $6, $ $ $ $, $ $ $ $20, $ $6, $ $ $ $, $ $ $ $20, $ $6, $ $ $ $, $ $ $ $20, Sewer Beginning Readiness to Serve Monthly Meter Size Fee 202 5/8" $8.00 $8.00 $8.00 $8.00 3/4" $2.00 $2.00 $2.00 $2.00 " $20.00 $20.00 $20.00 $20.00 ½" $40.00 $40.00 $40.00 $ " $64.00 $64.00 $64.00 $ " $20.00 $20.00 $20.00 $ " $ $ $ $ " $ $ $ $ TOTAL 2,96 $, $, $, $, TOTAL 2,82 $2, $2, $2, Anticipated Yearly Revenue $37,96.00 $37,96.00 $37,96.00 $37,96.00 Anticipated Yearly Revenue $254, $254, $254, ALTERNATIVE 3 ALTERNATIVE 3 CUSTOMER COUNT Water NB - no bill NC - No charge Sub-Total Proposed Beginning CUSTOMER COUNT Sewer NB - No bill NC - No charge Proposed Beginning Readiness to Serve Charge - With Rate Increases Each Year Monthly Meter Size Fee 5/8" 3/4" " $2.00 $3.00 $5.00 $2.00 $3.00 $5.00 $2.00 $3.00 $5.00 WATER Outside SEWER Outside ½" RW 2" $6.00 $6.00 $6.00 OW - 5/8 Meter OW 2-3/4" Meter OW 4 - ½" Meter OW 5-2" Meter 29 3 $87.00 $4.50 $5.00 $72.00 $87.00 $4.50 $5.00 $72.00 $87.00 $4.50 $5.00 $72.00 OS - 5/8 Meter OS2-3/4" Meter OS4 - ½" Meter OS5-2" Meter 0 2 $82.50 $37.50 $20.00 $82.50 $37.50 $20.00 $82.50 $37.50 $ " 4" 6" $30.00 $ $30.00 $ $30.00 $ Sub-Total 35 $78.50 $78.50 $78.50 Sub-Total 4 $ $ $ WATER Inside W - 5/8" Meter W 2-3/4" Meter W 3 - " Meter W 4 - ½" Meter W 5-2" Meter W 6-3" Meter W 7-4" Meter W 8-6" Meter Sub-Total 2, ,59 $4, $96.00 $70.00 $80.00 $ $90.00 $ $5, $4, $96.00 $70.00 $80.00 $ $90.00 $ $5, $4, $96.00 $70.00 $80.00 $ $90.00 $ $5, SEWER Inside S - 5/8" Meter S2-3/4" Meter S3 - " Meter S4 - ½" Meter S5-2" Meter S6-3" Meter S7-4" Meter S8-6" Meter Sub-Total 2, ,38,25.00 $ $37.50 $ $, $50.00 $ $ $3,025.00,25.00 $ $37.50 $ $, $50.00 $ $ $3,025.00,25.00 $ $37.50 $ $, $50.00 $ $ $3, Readiness to Serve Charge - With Rate Increases Each Year Monthly Meter Size Fee 5/8" 3/4" " ½" 2" 3" 4" 6" $5.00 $7.50 $2.50 $25.00 $40.00 $75.00 $50.00 $ $5.00 $7.50 $2.50 $25.00 $40.00 $75.00 $50.00 $ $5.00 $7.50 $2.50 $25.00 $40.00 $75.00 $50.00 $ TOTAL 2,96 $5, $5, $5, TOTAL 2,82 $3, $3, $3, Anticipated Yearly Revenue $69, $69, $69, Anticipated Yearly Revenue $59,80.00 $59,80.00 $59,80.00 P:\clients\97000\00322\RateStudy\Wellington W_S_ST Rate Study Rev.qpw Page 29 08/7/7

Village of Baltimore Water & Wastewater Analysis. July 2018

Village of Baltimore Water & Wastewater Analysis. July 2018 Village of Baltimore Water & Wastewater Analysis July 2018 Table of Contents Introductory Summary... 1 Data... 1 Water Treatment Plant (WTP)... 1 Production... 2 Costs & Debts... 2 Wastewater Treatment

More information

Ohio Environmental Protection Agency

Ohio Environmental Protection Agency Ohio Environmental Protection Agency Division of Environmental and Financial Assistance (DEFA) Office of Financial Assistance (OFA) Loan Nomination Instructions Ohio EPA Water and Wastewater Loan Programs

More information

Wastewater Rate Study. Villa Park, Illinois

Wastewater Rate Study. Villa Park, Illinois Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary

More information

SYCAMORE CITY COUNCIL AGENDA February 4, 2013

SYCAMORE CITY COUNCIL AGENDA February 4, 2013 1. CALL TO ORDER 2. INVOCATION 3. PLEDGE OF ALLEGIANCE 4. APPROVAL OF AGENDA 5. AUDIENCE TO VISITORS SYCAMORE CITY COUNCIL AGENDA February 4, 2013 CITY COMMITTEE MEETINGS No Meetings are Scheduled REGULAR

More information

Ohio s State Revolving Fund (SRF) Loan Programs Status and Direction

Ohio s State Revolving Fund (SRF) Loan Programs Status and Direction Ohio s State Revolving Fund (SRF) Loan Programs Status and Direction Ohio Water Environment Association Watershed Workshop October 30, 2014 Division of Environmental and Financial Assistance (DEFA) Division

More information

Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges

Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges UNC School of Government EFC 2017 Water & Wastewater Finance Workshop February 28 March 1, 2017 The William & Ida Friday

More information

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc.

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Squaw Valley PSD Water & Sewer Rate and Connection Fee Study February 15, 2017 Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Purpose of the District s Study Provide sufficient

More information

City of Riverbank. Water Rate Study FINAL 6/18/2015

City of Riverbank. Water Rate Study FINAL 6/18/2015 Water Rate Study FINAL 6/18/2015 Bartle Wells Associates Independent Public Finance Consultants 1889 Alcatraz Avenue Berkeley, California 94703 www.bartlewells.com Tel: 510-653-3399 June 18, 2015 6707

More information

TOWNSHIP OF WEST LINCOLN

TOWNSHIP OF WEST LINCOLN TOWNSHIP OF WEST LINCOLN April 18, 2016 dfa DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 664-B Vine Street St. Catharines Ontario Canada L2M 7L8 Telephone: (905) 938-0965

More information

Water Services Rate Study

Water Services Rate Study Report on the Water Services Rate Study Town of Telluride, Colorado Project No. 72447 August 2013 Water Services Rate Study prepared for Town of Telluride, Colorado August 2013 Project No. 72447 prepared

More information

Final Report Water and Sewer Rate Model Town of Denton, MD

Final Report Water and Sewer Rate Model Town of Denton, MD Final Report Water and Sewer Rate Model Town of Denton, MD January 30, 2014 MCET Water and Sewer Rate Model for Denton, MD Page 1 Table of Contents Water and Sewer Rate Model Study Town of Denton, MD January

More information

WATER AND WASTEWATER FUND REVENUES

WATER AND WASTEWATER FUND REVENUES WATER AND WASTEWATER FUND REVENUES Water revenues comprise $12.11 million, or 70.6% of total revenues of the fund, while wastewater (sewer) charges comprise $4.25 million, or 24.7% of total revenues. Water

More information

Ohio Environmental Protection Agency

Ohio Environmental Protection Agency Ohio Environmental Protection Agency Division of Environmental and Financial Assistance (DEFA) Office of Financial Assistance (OFA) Loan Application Instructions Ohio EPA Water and Wastewater Loan Programs

More information

First Reading - 11/07/2011 Effective Date - 11/21/2011 Second Reading 11/21/2011 Vote yeas nays

First Reading - 11/07/2011 Effective Date - 11/21/2011 Second Reading 11/21/2011 Vote yeas nays ORDINANCE NO. 2011-028 AN ORDINANCE APPROVING THE REVISED FINANCIAL RECOVERY PLAN FOR THE VILLAGE OF WAYNESVILLE, OHIO AND DECLARING AN EMERGENCY (RECOVERY PLAN #11) WHEREAS, the Auditor of State has declared

More information

The City of Sierra Madre

The City of Sierra Madre The City of Sierra Madre Comprehensive Water and Wastewater Cost of Service Study Report / December 24, 2018 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145 www.raftelis.com December

More information

YORK COUNTY, SOUTH CAROLINA

YORK COUNTY, SOUTH CAROLINA YORK COUNTY, SOUTH CAROLINA Water and Sewer Financial Planning and Rate Study Report October 25, 2017 1031 S. Caldwell Street Suite 100 Charlotte, NC 28203 Phone 704.373.1199 Fax 704.373.1113 www.raftelis.com

More information

Sewer Rates. General Information Sheet. July 18, 2017

Sewer Rates. General Information Sheet. July 18, 2017 Sewer Rates General Information Sheet July 18, 2017 Welcome to the City of O'Fallon's sewer rates public hearing. This meeting presents the preliminary findings to revise the sewer rates. In this public

More information

COMPREHENSIVE WATER AND SEWER RATE AND FEE STUDY VILLAGE OF ALGONQUIN

COMPREHENSIVE WATER AND SEWER RATE AND FEE STUDY VILLAGE OF ALGONQUIN COMPREHENSIVE WATER AND SEWER PREPARED FOR VILLAGE OF ALGONQUIN PREPARED BY RHMG ENGINEERS, INC. CONSULTING ENGINEERS 975 CAMPUS DRIVE, MUNDELEIN, IL 60060 JANUARY, 2016 Section I Executive Summary General

More information

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415)

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415) 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) 332-0244 Fax: (415) 332-0453 Budget FY 2017/18 Adopted by Board on June 5, 2017 BUDGET EXECUTIVE SUMMARY FISCAL YEAR 2017/18 DISTRICT OVERVIEW The Sausalito-Marin

More information

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by:

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by: CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY Prepared by: August 30, 2010 201 S. Lake Blvd, Suite 301 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com August 30, 2010 Mr. Chris

More information

PROGRAM GUIDELINES WSRLA Page 1 of 6 As of Jan 29, 2015

PROGRAM GUIDELINES WSRLA Page 1 of 6 As of Jan 29, 2015 PROGRAM GUIDELINES WSRLA Page 1 of 6 WHAT: Drinking Water Assistance Fund: Water Supply Revolving Loan Account Program For WHAT: LOANS for Planning/Design and/or Construction (Supplements also available)

More information

Temescal Valley Water District

Temescal Valley Water District Temescal Valley Water District Comprehensive Water, Recycled Water, and Wastewater Cost of Service Study Draft Report / December 7, 2016 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145

More information

WATER, WASTEWATER, AND RECLAIMED WATER RATE STUDY Public Meeting to Review Study Results. January 5, 2016

WATER, WASTEWATER, AND RECLAIMED WATER RATE STUDY Public Meeting to Review Study Results. January 5, 2016 WATER, WASTEWATER, AND RECLAIMED WATER RATE STUDY Public Meeting to Review Study Results January 5, 2016. Public Resources Management Group, Inc. Utility, Rate, Financial and Management Consultants Utility

More information

WATER AND SEWER RATE STUDY

WATER AND SEWER RATE STUDY FINAL WATER AND SEWER RATE STUDY B&V PROJECT NO. 179322.0100 PREPARED FOR City of Lynwood, CA JANUARY 11, 2017 Black & Veatch Holding Company 2011. All rights reserved. City of Lynwood, CA WATER AND SEWER

More information

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 EXECUTIVE SUMMARY The functions and duties of the Oro Valley Water Utility Commission include reviewing and developing

More information

M54. Developing Rates for Small Systems. Second Edition. Copyright 2016 American Water Works Association. All Rights Reserved.

M54. Developing Rates for Small Systems. Second Edition. Copyright 2016 American Water Works Association. All Rights Reserved. M54 Developing Rates for Small Systems Second Edition Contents List of Figures, v List of Tables, vii Preface, ix Acknowledgments, xiii Chapter 1 Basics of Water Ratemaking... 1 Basic Premise, 1 Water

More information

source pollution To provide low financing and interest To provide low contaminated site projects which provide water quality financing and benefits

source pollution To provide low financing and interest To provide low contaminated site projects which provide water quality financing and benefits WHAT: Pollution Control Loan Fund Municipal Facilities Program Standard LOANS for Planning/Design and/or LOANS for Planning/Desig n and/or For WHAT: (Supplements also available) Same Same Same for Wastewater

More information

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 The Financial Link Executive Summary - Water In May 2015, the City of Whitefish (City) retained AE2S to complete a Water and

More information

Crawford County, Ohio

Crawford County, Ohio Financial Forecast For the Years Ended December 31, 2006, 2007, and 2008 Actual; Years Ending December 31, 2009, 2010, and 2011 Forecasted 12/1/2009 1 Financial Forecast Table of Contents Page Schedule

More information

Village of Carol Stream

Village of Carol Stream Village of Carol Stream Special Meeting of the Village Board FY 19 Budget Workshop- Water and Sewer Carol Stream Fire Protection District Fire Station 28 365 Kuhn Road, Carol Stream, IL 60188 March 19,

More information

LAKE DON PEDRO COMMUNITY SERVICES DISTRICT Policy and Procedures Manual

LAKE DON PEDRO COMMUNITY SERVICES DISTRICT Policy and Procedures Manual EXHIBIT A LAKE DON PEDRO COMMUNITY SERVICES DISTRICT Policy and Procedures Manual POLICY TITLE: Reserve Policy POLICY NUMBER: (to be established) ADOPTED: July 18, 2016 AMENDED: This statement is intended

More information

SIGNIFICANT BUDGET CHANGES

SIGNIFICANT BUDGET CHANGES Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and

More information

VILLAGE OF NEVADA WYANDOT COUNTY TABLE OF CONTENTS. Independent Accountants Report... 1

VILLAGE OF NEVADA WYANDOT COUNTY TABLE OF CONTENTS. Independent Accountants Report... 1 TABLE OF CONTENTS TITLE PAGE Independent Accountants Report... 1 Combined Statement of Cash Receipts, Cash Disbursements, and Changes in Fund Cash Balances - All Governmental Fund Types - For the Year

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY REPORT January 2017 WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY PREPARED BY: ECONOMICS STRATEGY STAKEHOLDERS SUSTAINABILITY www.newgenstrategies.net 3420

More information

City of Sanibel. Sewer Expansion Feasibility Study Update GAI #A

City of Sanibel. Sewer Expansion Feasibility Study Update GAI #A City of Sanibel Sewer Expansion Feasibility Study 2011 Update GAI # July 2011 July 12, 2011 GAI Proj. # Mr. Gates Castle Utility Director City of Sanibel 800 Dunlop Road Sanibel, FL 33957 Subject: Sewer

More information

PUBLIC WORKS. AdrrWo Aal- P W. Tectl. (8) Const.lnsp.l Eng. Tech. Conv. Sile AtlendllnI (31) I. Y. SIte Supv,. Hvy. Eq Mech r-- HYy Eq Oper.

PUBLIC WORKS. AdrrWo Aal- P W. Tectl. (8) Const.lnsp.l Eng. Tech. Conv. Sile AtlendllnI (31) I. Y. SIte Supv,. Hvy. Eq Mech r-- HYy Eq Oper. PUBLIC WORKS ) UIiII\y Cps. s.. v.ww_. WW... C'"'_ Tectl. (8) AdrrWo Aal- P W....... "'""" ~... '" ".WWfP WW _. -(2) - WNTP Sf. WTP Operator (2) H I H WNTP WTP Operator labasst. (8) Const.lnsp.l Eng. Tech.

More information

FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018

FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018 FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Enhanced Clarification Facility Lucy Tunnel Boring Machine First Street Tunnel

More information

Water and Sewer Utility Rate Studies

Water and Sewer Utility Rate Studies Final Report Water and Sewer Utility Rate Studies July 2012 Prepared by: HDR Engineering, Inc. July 27, 2012 Mr. Mark Brannigan Director of Utilities 591 Martin Street Lakeport, CA 95453 Subject: Comprehensive

More information

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Phase 2 Cost of Service and Rate Design BLACK & VEATCH PROJECT NO. 192366 Black & Veatch Holding Company 2017. All rights

More information

SANITARY SEWER FUND PUBLIC WORKS

SANITARY SEWER FUND PUBLIC WORKS 285 2015 2016 2017 2017 2018 Actual Actual Budget Estimate Budget Beginning Net Position $ 1,556,256 $ 2,133,912 $ 3,537,945 $ 3,537,945 $ 3,333,823 Operating Revenue 5,758,183 6,475,486 6,751,246 6,681,766

More information

2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL

2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL 2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL Receive a presentation from Lewis Young Robertson & Burningham regarding the 2017 Utility Rate Study The purpose of the Council

More information

FORT COLLINS- LOVELAND WATER DISTRICT

FORT COLLINS- LOVELAND WATER DISTRICT FORT COLLINS- LOVELAND WATER DISTRICT Water Financial Planning and Rate Study Report March 16, 2018 District of Thousand Oaks Water and Wastewater Financial Plan Study Report March 16, 2018 Board of Directors

More information

SPRINGVILLE CITY CULINARY WATER IMPACT FEE ANALYSIS (IFA) MAY 2014

SPRINGVILLE CITY CULINARY WATER IMPACT FEE ANALYSIS (IFA) MAY 2014 SPRINGVILLE CITY CULINARY WATER IMPACT FEE ANALYSIS (IFA) MAY 2014 Adopted May 20, 2014 TABLE OF CONTENTS IMPACT FEE CERTIFICATION... 3 SECTION 1: EXECUTIVE SUMMARY... 4 PROPOSED CULINARY WATER IMPACT

More information

Cash Reserve Policy Guidelines. Copyright 2018 American Water Works Association

Cash Reserve Policy Guidelines. Copyright 2018 American Water Works Association Cash Reserve Policy Guidelines AWWA RATES & CHARGES COMMITTEE WHITEPAPER Cash Reserve Policy Guidelines INTRODUCTION Public and investor-owned water-resources related utilities (including water, wastewater,

More information

Utilities Rate Advisory Commission 04/21/2010 Item 2 - Midyear Budget Review APRIL 21,2010

Utilities Rate Advisory Commission 04/21/2010 Item 2 - Midyear Budget Review APRIL 21,2010 APRIL 21,2010 Presentation Overview FY09/10 Budget Development (History) FY09/10 Midyear Update FY10/11 Proposed Budget Budget-Driven Programmatic Impacts Department of Utilities Audits Topics of Interest

More information

Glacial Lakes Sanitary Sewer & Water District Utility Rate Study. Shelly Eldridge Ehlers Jeanne Vogt - Ehlers

Glacial Lakes Sanitary Sewer & Water District Utility Rate Study. Shelly Eldridge Ehlers Jeanne Vogt - Ehlers Glacial Lakes Sanitary Sewer & Water District Utility Rate Study Shelly Eldridge Ehlers Jeanne Vogt - Ehlers 05/30/2017 1 Background What are Utility Funds Utility funds are used to pay for operations,

More information

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT February 2, 218 This page was intentionally left blank. City of Calistoga Water Rate Study Report Page 2 February 2, 218 Dylan Feik City Manager City of

More information

CAPITAL RECOVERY POLICY TABLE OF CONTENTS

CAPITAL RECOVERY POLICY TABLE OF CONTENTS TABLE OF CONTENTS ARTICLE I GENERAL PROVISIONS Section 1.01 General Policy Statement... 1 Section 1.02 Authority... 1 Section 1.03 Definitions... 1 Section 1.04 Capital Recovery Fees as Conditions of Development

More information

INLAND EMPIRE UTILITIES AGENCY DEBT MANAGEMENT POLICY May 2016

INLAND EMPIRE UTILITIES AGENCY DEBT MANAGEMENT POLICY May 2016 Table of Contents Policy Statement... 3 Purpose of Policy... 3 Purpose and Use of Debt... 4 Debt Management... 5 Debt... 6 Coverage Target... 6 Debt Instrument Rating... 6 Debt Structuring... 6 Types of

More information

Introduction to Water and Sewer Fund Needs August 11, 2017

Introduction to Water and Sewer Fund Needs August 11, 2017 Introduction to Water and Sewer Fund Needs August 11, 2017 A lot of good things are happening in Buffalo and we hope to make some exciting announcements in the months to come, especially about possible

More information

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study Capital Region Water Water and Wastewater Rate Study Report November 22, 2017 Capital Region Water Water and Wastewater Rate Study TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 RATE STUDY SCOPE AND OBJECTIVES...1

More information

MAINTENANCE DEPARTMENT

MAINTENANCE DEPARTMENT MAINTENANCE DEPARTMENT E-78 City of Mercer Island 2007-2008 Budget Department: Maintenance The Maintenance Department consists of the following functions: 1) administration, 2) capital projects engineering,

More information

CRESTVIEW WATER AND SANITATION DISTRICT BUDGET

CRESTVIEW WATER AND SANITATION DISTRICT BUDGET CRESTVIEW WATER AND SANITATION DISTRICT BUDGET 2019 CONTENTS Independent Accountant s Report 1 Budget for the Year Ending December 31, 2019 2-3 Summary Budget Worksheet 2017 Actual, 2018 Projection and

More information

Village of Oak Park, IL Department of Finance. Quarterly Finance and Performance Report 2016, 1st Quarter

Village of Oak Park, IL Department of Finance. Quarterly Finance and Performance Report 2016, 1st Quarter Village of Oak Park, IL Department of Finance Quarterly Finance and Performance Report 2016, 1st Quarter May, 2016 Table of Contents Section 1: Introduction... 3 Section 2: 1 st Quarter Financial Report

More information

MICHIGAN STATE UNIVERSITY

MICHIGAN STATE UNIVERSITY 2010 Great Lakes Water Rate Survey Janice A. Beecher and Jason A. Kalmbach INSTITUTE OF PUBLIC UTILITIES MICHIGAN STATE UNIVERSITY beecher@msu.edu ipu.msu.edu Please do not distribute ib t by electronic

More information

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY DC Retail Water and Sewer Rates Committee - 1. Call to Order - Alan Roth, Chairman DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Board of Directors DC Retail Water and Sewer Rates Committee Tuesday November

More information

Biennial Budget Section II: Process/Policies

Biennial Budget Section II: Process/Policies BUDGET POLICIES This section of the budget sets forth the objectives of the budget as a policy document together with a description of the basis of the policy. Policy Context of the Budget The City budget

More information

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013 MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT September 2013 10540 TALBERT AVENUE, SUITE 200 EAST FOUNTAIN VALLEY, CALIFORNIA 92708 P. 714.593.5100 F. 714.593.5101 MARINA

More information

2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET

2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET THE GREENVILLE WATER AUTHORITY M E RCER COUNTY, PENNS YLV AN I A 2016 WATER SYSTEM ANNUAL REPORT & 2017 OPERATING BUDGET Prepared by: Robert J. Horvat www.entecheng.com Project No.: 4631.01 Dated: Entech

More information

TOWN OF PRESCOTT VALLEY

TOWN OF PRESCOTT VALLEY TOWN OF PRESCOTT VALLEY Management Services Department WATER & SEWER RATE STUDY July 27, 2017 TOWN OF PRESCOTT VALLEY REPORT OF PROPOSAL TO REVISE CERTAIN WATER AND WASTEWATER RATES, FEES AND SERVICE CHARGES

More information

Wastewater Utilities. FY Budget Presentation

Wastewater Utilities. FY Budget Presentation Utilities FY 2018-19 Budget Presentation 1 Volume Forecast Wastewater Customers by Class Fiscal Year Residential Commercial Wholesale Total Growth 2013 26,995 1.1% 3,091 0.8% 4 30,090 1.1% 2014 27,548

More information

City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE

City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE I. INTRODUCTION City of Arroyo Grande Department of Public Works REQUEST FOR PROPOSAL WATER AND WASTEWATER RATE STUDY UPDATE The City of Arroyo Grande, California (the City ) was incorporated as a general

More information

City of Newport News Virginia. Waterworks Ratings Presentation. April 27, 2017

City of Newport News Virginia. Waterworks Ratings Presentation. April 27, 2017 City of Newport News Virginia Waterworks Ratings Presentation April 27, 2017 I. Overview Newport News Waterworks Mission Statement: To provide high quality drinking water and support public health, safety,

More information

I. INTRODUCTORY SECTION

I. INTRODUCTORY SECTION Spartanburg Water System Spartanburg, South Carolina Comprehensive Annual Financial Report For the Year Ending June 30, 2017 I. INTRODUCTORY SECTION SPARTANBURG WATER SYSTEM SPARTANBURG, SOUTH CAROLINA

More information

SECTION G. RATES AND SERVICE FEES

SECTION G. RATES AND SERVICE FEES SECTION G. RATES AND SERVICE FEES UNLESS SPECIFICALLY DEFINED IN THIS SERVICE POLICY, ALL FEES, RATES, AND CHARGES AS STATED HEREIN SHALL BE NON-REFUNDABLE. 1. Classes of Users -- All users of the District

More information

UTILITY RATE STUDY. Public Hearing

UTILITY RATE STUDY. Public Hearing UTILITY RATE STUDY Public Hearing. Public January 23, 2018 Resources Management Group, Inc. Utility, Rate, Financial, and Management Consultants Rate Guiding Principles Recognized Revenues Should Be Sufficient

More information

An Integrated Water and Sewer Utility Planning and Rate Study for October 4 & 5, 2011

An Integrated Water and Sewer Utility Planning and Rate Study for October 4 & 5, 2011 An Integrated Water and Sewer Utility Planning and Rate Study for October 4 & 5, 2011 HID E 1 Integrated Study Scope of Study HID E 2 Scope of the Study Part 1: Capital Assets Inventory water & sewer system

More information

STORM WATER USER RATE STUDY

STORM WATER USER RATE STUDY LY STORM WATER USER RATE STUDY STORM WATER UTILITY OREM CITY, UTAH JANUARY 2016 PREPARED BY LEWIS YOUNG ROBERTSON & BURNINGHAM, INC. TABLE OF CONTENTS SECTION I: EXECUTIVE SUMMARY... 3 SECTION II: OVERVIEW

More information

I. INTRODUCTORY SECTION

I. INTRODUCTORY SECTION Spartanburg Water System Spartanburg, South Carolina Comprehensive Annual Financial Report For the Years Ended June 30, 2018 and 2017 I. INTRODUCTORY SECTION SPARTANBURG WATER SYSTEM SPARTANBURG, SOUTH

More information

BEFORE THE NORTH CAROLINA UTILITIES COMMISSION APPLICATION FOR TRANSFER OF PUBLIC UTILITY FRANCHISE AND FOR APPROVAL OF RATES INSTRUCTIONS

BEFORE THE NORTH CAROLINA UTILITIES COMMISSION APPLICATION FOR TRANSFER OF PUBLIC UTILITY FRANCHISE AND FOR APPROVAL OF RATES INSTRUCTIONS FORM REVISED 6/04 SELLER DOCKET NO. PURCHASER DOCKET NO. FILING FEE RECEIVED BEFORE THE NORTH CAROLINA UTILITIES COMMISSION APPLICATION FOR TRANSFER OF PUBLIC UTILITY FRANCHISE AND FOR APPROVAL OF RATES

More information

BASIC FINANCIAL STATEMENTS, MANAGEMENT DISCUSSION AND ANALYSIS, AND REQUIRED SUPPLEMENTAL INFORMATION

BASIC FINANCIAL STATEMENTS, MANAGEMENT DISCUSSION AND ANALYSIS, AND REQUIRED SUPPLEMENTAL INFORMATION BASIC FINANCIAL STATEMENTS, MANAGEMENT DISCUSSION AND ANALYSIS, AND REQUIRED SUPPLEMENTAL INFORMATION C O N T E N T S PAGE Independent Auditor's Report........................................... Management

More information

District of Clearwater Utility Rate Review

District of Clearwater Utility Rate Review District of Clearwater 2018 Utility Rate Review Janice Aver May 2018 Table of Contents BACKGROUND... 1 FULL COST OF SERVICE... 2 OPERATIONS... 3 CAPITAL... 5 RESERVES... 10 RATES... 12 RECOMMENDATIONS...

More information

SIGNIFICANT BUDGET CHANGES

SIGNIFICANT BUDGET CHANGES Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and

More information

BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida

BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida Financial Statements For the Years Ended BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND FINANCIAL STATEMENTS

More information

Budgeting for Municipal Enterprises

Budgeting for Municipal Enterprises Budgeting for Municipal Enterprises Glenn Barnes & Shadi Eskaf Senior Project Directors Environmental Finance Center at UNC School of Government SOG Course: Budgeting in Local Government Chapel Hill, NC

More information

CHAPTER XI. WATER & SEWER ARTICLE A. WATER CONNECTION FEES. New Water Connection Fees. Inside City Limits

CHAPTER XI. WATER & SEWER ARTICLE A. WATER CONNECTION FEES. New Water Connection Fees. Inside City Limits CHAPTER XI. WATER & SEWER ARTICLE A. WATER CONNECTION FEES Section 1. New Water Connection Fees Limits Service Complete Service Connection Installation (Potable or Irrigation) Meter Only Installation for

More information

ORANGE VILLAGE CUYAHOGA COUNTY REGULAR AUDIT

ORANGE VILLAGE CUYAHOGA COUNTY REGULAR AUDIT REGULAR AUDIT FOR THE YEAR ENDED DECEMBER 31, 2009 TABLE OF CONTENTS TITLE PAGE Cover Letter... 1 Independent Accountants Report... 3 Combined Statement of Cash Receipts, Cash Disbursements, and Changes

More information

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS Black & Veatch Holding Company 2011. All rights reserved. COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 26 MAY 2015 B&V PROJECT NO.

More information

CITY OF KAMLOOPS. Financial Statements for the Year-Ended 2013 December 31. Page 1 of 66

CITY OF KAMLOOPS. Financial Statements for the Year-Ended 2013 December 31. Page 1 of 66 CITY OF KAMLOOPS Financial Statements for the Year-Ended 2013 December 31 Page 1 of 66 CONSOLIDATED FINANCIAL STATEMENTS TABLE OF CONTENTS 2 Independent Auditor's Report 3-4 Management's Responsibility

More information

WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION

WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION March 2017 Adopted by Public Utility Board Resolution U-10910 on February 22, 2017 Adopted by City Council Ordinance No. 28413 on

More information

MORGANTOWN UTILITY BOARD (A Component Unit of the City of Morgantown) MONONGALIA COUNTY Single Audit For the Years Ended June 30, 2018 and 2017

MORGANTOWN UTILITY BOARD (A Component Unit of the City of Morgantown) MONONGALIA COUNTY Single Audit For the Years Ended June 30, 2018 and 2017 Single Audit For the Years Ended June 30, 2018 and 2017 313 Second St. 1907 Grand Central Ave. 150 W. Main St., #A 1310 Market St., #300 749 Wheeling Ave., #300 Marietta, OH 45750 Vienna, WV 26105 St.

More information

DENVER SOUTHEAST SUBURBAN WATER AND SANITATION DISTRICT MANAGEMENT S DISCUSSION AND ANALYSIS

DENVER SOUTHEAST SUBURBAN WATER AND SANITATION DISTRICT MANAGEMENT S DISCUSSION AND ANALYSIS The management of Denver Southeast Suburban Water and Sanitation District (the District) offers the readers of the District s financial statements this narrative overview and analysis of the financial

More information

HILLCREST UTILITY OPERATING COMPANY CUSTOMER RIGHTS AND RESPONSIBILITIES

HILLCREST UTILITY OPERATING COMPANY CUSTOMER RIGHTS AND RESPONSIBILITIES HILLCREST UTILITY OPERATING COMPANY CUSTOMER RIGHTS AND RESPONSIBILITIES Central States Water Resources Welcome Hillcrest Utility Customers Hillcrest Utility Operating Company Inc. (Hillcrest) has improved

More information

ORDINANCE NO AN ORDINANCE To Be Entitled:

ORDINANCE NO AN ORDINANCE To Be Entitled: AN ORDINANCE To Be Entitled: AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF FORT MYERS, FLORIDA, AMENDING THE CITY CODE, CHAPTER 90, UTILITIES, ARTICLE II WATER, SECTION 90-35 RATES AND CHARGES ESTABLISHED;

More information

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR Black & Veatch Holding Company 2011. All rights reserved. DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 21 MAY 2015 B&V PROJECT

More information

CITY OF RAPID CITY. Financial and Rate Setting Policies for the Water and Water Reclamation Utilities

CITY OF RAPID CITY. Financial and Rate Setting Policies for the Water and Water Reclamation Utilities CITY OF RAPID CITY Financial and Rate Setting Policies for the Water and Water Reclamation Utilities Financial and Rate Setting Policies i City of Rapid City Financial/Rate Setting Policies for the Water

More information

PARKVILLE WATER DISTRICT

PARKVILLE WATER DISTRICT PARKVILLE WATER DISTRICT WATER RATE STUDY DECEMBER 2017 RPI Consulting LLC Durango, Colorado TABLE OF CONTENTS Table of Contents 2 Summary of Findings 3 Water Rate Analysis 6 Usage patterns and existing

More information

DEPARTMENT OF PUBLIC WORKS UTILITIES

DEPARTMENT OF PUBLIC WORKS UTILITIES DEPARTMENT OF PUBLIC WORKS UTILITIES Mission Statement: Public Works - Utilities is dedicated to providing water, wastewater, and environmental services to the citizens of Rio Rancho and other City Departments.

More information

Module 8 Rate Design Overview for Small Water Systems

Module 8 Rate Design Overview for Small Water Systems Module 8 Rate Design Overview for Small Water Systems Workbook Financial/Managerial Series This course includes content developed by the Pennsylvania Department of Environmental Protection in cooperation

More information

Due to the numerous sections and comprehensiveness of this PP/OP, the following index is provided for quick reference and clarity:

Due to the numerous sections and comprehensiveness of this PP/OP, the following index is provided for quick reference and clarity: PHYSICAL PLANT OPERATING POLICY AND PROCEDURE : Utility Cost Projection DATE: September 7, 2007 PURPOSE The purpose of this Physical Plant Operating Policy and Procedure (PP/OP) is to establish a standard

More information

FORT BEND COUNTY MUNICIPAL UTILITY DISTRICT NO. 128 FORT BEND COUNTY, TEXAS FINANCIAL REPORT. July 31, 2018

FORT BEND COUNTY MUNICIPAL UTILITY DISTRICT NO. 128 FORT BEND COUNTY, TEXAS FINANCIAL REPORT. July 31, 2018 FORT BEND COUNTY MUNICIPAL UTILITY DISTRICT NO. 128 FORT BEND COUNTY, TEXAS FINANCIAL REPORT Table of Contents Schedule Page Independent Auditors Report 1 Management s Discussion and Analysis 5 BASIC

More information

COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY

COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY 1955 Workman Mill Road, Whittier, CA 90601-1400 Mailing Address: P.O. Box 4998, Whittier, CA 90607-4998 Telephone: (562) 699-7411, FAX: (562) 699-5422

More information

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 01 April, 2014 SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 Bill Zieburtz Richard Campbell Robert Chambers RATE SETTING PROCESS STUDY APPROACH RATE SETTING OBJECTIVES FINANCIAL PLAN

More information

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE UCS2018-0223 ATTACHMENT 1 FINANCIAL PLAN 2019-2022 WATER AND WASTEWATER LINES OF SERVICE 2018 MARCH 14 MAKING LIFE BETTER EVERY DAY UCS2018-0223 Financial Plan 2019-2022 - Water and Wastewater Lines of

More information

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program.

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program. Milwaukee Metropolitan Sewerage District s 2011-2020 Private Property Inflow and Infiltration Reduction Program Introduction Infiltration is the quantity of water entering a sewer system through such sources

More information

North Pecos Water & Sanitation District. Rates, Charges, Fees and Penalties Effective January 1, 2015

North Pecos Water & Sanitation District. Rates, Charges, Fees and Penalties Effective January 1, 2015 North Pecos Water & Sanitation District Rates, Charges, Fees and Penalties Effective January 1, 2015 Updated : 1-1-2015 RATES, CHARGES, FEES AND PENALTIES OF THE NORTH PECOS WATER AND SANITATION DISTRICT

More information

NOTIFICATION OF INTENTION TO BEGIN OPERATIONS IN AREA CONTIGUOUS TO PRESENT SERVICE AREA UTILITY

NOTIFICATION OF INTENTION TO BEGIN OPERATIONS IN AREA CONTIGUOUS TO PRESENT SERVICE AREA UTILITY FORM REVISED 8/00 DOCKET NO. Date submitted: Date proposed for service to begin: NOTIFICATION OF INTENTION TO BEGIN OPERATIONS IN AREA CONTIGUOUS TO PRESENT SERVICE AREA UTILITY 1. Trade name used for

More information

CONSOLIDATION PLAN PREPARED ON BEHALF OF THE MERGER ADVISORY COMMITTEE FOR THE CITY AND VILLAGE OF PEWAUKEE WAUKESHA COUNTY, WISCONSIN MARCH 25, 2010

CONSOLIDATION PLAN PREPARED ON BEHALF OF THE MERGER ADVISORY COMMITTEE FOR THE CITY AND VILLAGE OF PEWAUKEE WAUKESHA COUNTY, WISCONSIN MARCH 25, 2010 CONSOLIDATION PLAN PREPARED ON BEHALF OF THE MERGER ADVISORY COMMITTEE FOR THE CITY AND VILLAGE OF PEWAUKEE WAUKESHA COUNTY, WISCONSIN MARCH 25, 2010 MUNICIPAL ECONOMICS & PLANNING A Division of Ruekert/Mielke

More information

STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW

STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW STEGE SANITARY DISTRICT FINANCIAL PLAN AND RATE REVIEW June 2014 BARTLE WELLS ASSOCIATES Independent Public Finance Advisors 1889 Alcatraz Avenue Berkeley CA 94703 Tel. 510/653-3399 TABLE OF CONTENTS

More information