Maintaining Contract and Project Management Alignment Throughout the Contract Lifecycle

Size: px
Start display at page:

Download "Maintaining Contract and Project Management Alignment Throughout the Contract Lifecycle"

Transcription

1 #78 US DOE Procurement Process Trends and Contractor Delivery Challenges Maintaining Contract and Project Management Alignment Throughout the Contract Lifecycle Ken Rueter President and Project Manager URS CH2M Oak Ridge, LLC 1

2 Contract at a Glance Contract Information Awarded under Federal Acquisition Regulation (FAR) Part 15.2 Size - $2.6 Billion Contract Duration and Specifics -Base CLINs 8/1/11 through 7/31/16 -Option CLINs 8/1/16 through 7/31/20 ETTP Contract Scope of Work and Primary Mission/Role at Site Decontamination & Demolition (D&D) of the major facilities at the East Tennessee Technology Park - K-25 and K-27 Uranium Enrichment Plants - Other facilities such as the Centrifuge, TSCA Incinerator, and K-1037 Barrier Plant Environmental remediation of contaminated soils Significant waste management activities disposal of radioactive waste both onsite and offsite Perform surveillance, maintenance and operations activities at DOE EM owned facilities at ETTP, Oak Ridge National Laboratory, and Y-12 National Security Complex 2

3 Maintaining Two Sides of the Coin Contract and Project Management Alignment UCOR and DOE worked together to establish alignment between Total Estimated Contract Cost with the Contract Budget Base at contract true up Identified Material Difference s (MDs) during Transition Periodic partnering meeting with customer to determine de minimis MDs and scheduled and established a chunking process Streamline Negotiations by using Federal Acquisition Regulation (FAR) Profit; (c)6 aka small dollar changes Managed challenges by appointing Ombudsmen {DOE & UCOR} Worked true-up, transition and alignment process as a project 3

4 Setting the Stage for Maintaining Alignment Through Contract and Project Execution Phase Exercising Option CLINs The same discipline is needed when Option CLINs are exercised UCOR and DOE OREM began planning for exercising of Option CLINs 22 months in advance By that time ~90Min clean-up scope needed exercised Operations CLINs (5 and 6) had not been exercised nor baselined Clean-up CLINs (7a and 7b) had a contract constrained Period of Performance (POP) end date Operations CLINs were a DOE provided plug cost and needed to be priced and known changes incorporated UCOR planned to utilize operational efficiencies from CLIN 5 to support establishment of Management Reserves in the option period Would allow approved baseline to be used for development of budget requests beyond FY16 4

5 Contract Options Execution and Completion Feb Mar Apr May Jun Jul Aug Sep Oct Nov 2/15 CLINs 7C and 8 DOE UCOR Contracting Officer issues letter of intent to exercise remaining CLINs 2/15 Option CLINs 7C and 8 exercised 2/15 UCOR provide Baseline Change Request (BCR) for Option CLINs 7 & 8 3/15 DOE approve CLINs 7 and 8 BCR 3/15 UCOR implements CLINs 7C and 8 BCR 180 Days 11/15 CLINs 5 and 6 DOE UCOR 4/15 UCOR submit Contract Change Proposals (CCPs) for Option CLINs 5 & 6 material differences Technical Evaluation PNM Development Negotiation etc. 10/15 CCPs Definitized 10/15 UCOR submit BCR for Option CLINs 5 & 6 DOE exercises Option CLINs 5 & 6 11/15 DOE approves BCR for Option CLINs 5 & 6 DAS Contract Options Execution and Completion R0 January

6 Planning the Work Partnering: UCOR and OREM set the stage at semi-annual partnering session Discussed performance and need Established teams to plan and accomplish work Committed to success Teams worked with DOE Headquarters Head Contracting Authority (HCA) to establish the alignment plan to exercise the options HCA provided expectations and requirements Contract first, baseline to follow Foresight avoided need for directed change in most instances Avoided gaps in the execution of cleanup scope 6

7 Work the Plan Contract Delivery and Long term management Staying committed to alignment Now ingrained into entire process including exercising of option Contract Line Item Numbers (CLINs) Importance of sequencing and timing Contractor provides CCPs for known change conditions (similar to MDs during transition) {FAR Changes Cost-Reimbursement} Changes are definitized first into Option CLINs CLINs with updated pricing are exercised via contract modification Baseline Change Request (BCR) follow contract actions {FAR Earned Value Management System} Performance based assignment IPT must demonstrate progress executing base period cleanup scope Option continues to fulfill an existing requirement Risks are adequately identified and potentially mitigated 7

8 Two Sides of the Coin Base Period Contract Authorized Scope Fee = $127.1M Fee = $127.1M AUW $14.2M MR = $10.6M Total Contract Price Total Contract Cost = $1,669.2M PMB - $1,672.8 Total Contractor Baseline Contract Budget Base Total Contract Cost = $1,683.4M Total Contract Price = $1,810.5M Total Contract Budget Base = $1,683.4M Total Contract = $1,810.5M 8

9 Two Sides of the Coin with Options Exercised Contract Authorized Scope Fee = $151.5M Fee = $151.5M AUW $14.7M MR = $46.6M Total Contract Price Total Contract Cost = $2,419.1M PMB - $2,387.2 Total Contractor Baseline Contract Budget Base Total Contract Cost = $2,433.8M Total Contract Price = $2,585.3M Total Contract Budget Base = $2,433.8M Total Contract = $2,585.3M 9

10 Ken Rueter 10

FOR - ARRA Financial and Operational Review Report Investigations

FOR - ARRA Financial and Operational Review Report Investigations Program Description 96-3133 Investigations This appropriation funds studies to determine the need, engineering feasibility, and economic and environmental return to the Nation of potential solutions to

More information

The EM Budget. Intergovernmental Meeting with the US Department of Energy December 12-14, Terry Tyborowski

The EM Budget. Intergovernmental Meeting with the US Department of Energy December 12-14, Terry Tyborowski The EM Budget Intergovernmental Meeting with the US Department of Energy December 12-14, 2012 Terry Tyborowski Office of Environmental Management Deputy Assistant Secretary for Program Planning and Budget

More information

URANIUM ENRICMWNT. Analysis of Decontamination and Decomnussionmg Scenarios

URANIUM ENRICMWNT. Analysis of Decontamination and Decomnussionmg Scenarios GAO November 1991 United States General Accounting Office Brieflingg Report to the Chairman, Subcommittee on Energy and Power, Committee on Energy and Commerce, House of Representatives URANIUM ENRICMWNT

More information

State and Tribal Government Working Group

State and Tribal Government Working Group State and Tribal Government Working Group Steve Trischman Director, Office of Budget and Planning May 2017 www.energy.gov/em 1 Agenda Primary Phases of Budget Planning and Budget Timeline How and When

More information

Work Program Integration Initiative (WPII)

Work Program Integration Initiative (WPII) Florida Department of TRANSPORTATION Work Program Integration Initiative (WPII) Florida PALM Executive Steering Committee Meeting February 27, 2019 Florida Department of Transportation Agenda Overview

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

Financial & Business Highlights For the Year Ended June 30, 2017

Financial & Business Highlights For the Year Ended June 30, 2017 Financial & Business Highlights For the Year Ended June, 17 17 16 15 14 13 12 Profit and Loss Account Operating Revenue 858 590 648 415 172 174 Investment gains net 5 162 909 825 322 516 Other 262 146

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2013 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR TO DATE FINANCIAL

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

11 May Report.xls Office of Budget & Fiscal Planning

11 May Report.xls Office of Budget & Fiscal Planning Education and General Fund Actual Revenues and s by Month MTD YTD Change Revenue Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Per 14 Total over FY06 Enrollment Fees $ 8,211 $ 219 $ 41,952 ($ 818) $

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Fiscal Year 2018 Columbia Generating Station Annual Operating Budget

Fiscal Year 2018 Columbia Generating Station Annual Operating Budget Fiscal Year 2018 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

Fiscal Year 2018 Project 1 Annual Budget

Fiscal Year 2018 Project 1 Annual Budget Fiscal Year 2018 Project 1 Annual Budget Table of Contents Table Page Summary 3 Summary of Costs Table 1 4 Treasury Related Expenses Table 2 5 Summary of Full Time Equivalent Table 3 6 Positions Cost-to-Cash

More information

FY20 BUDGET TIMETABLE

FY20 BUDGET TIMETABLE FY20 BUDGET TIMETABLE (Revised - 3/21/19- see last page for listing of revisions made to original timetable) Date Day Time Meeting Activity Jan 8 Tue 9:30 a.m. BCC Mtg BCC Regular Meeting Jan 15 Tue 9:30

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ENVIRONMENTAL MANAGEMENT URANIUM ENRICHMENT DECONTAMINATION AND DECOMMISSIONING FUND

UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ENVIRONMENTAL MANAGEMENT URANIUM ENRICHMENT DECONTAMINATION AND DECOMMISSIONING FUND KPMG The Global Leader UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ENVIRONMENTAL MANAGEMENT URANIUM ENRICHMENT DECONTAMINATION AND DECOMMISSIONING FUND Financial Statements September 30,1994 and 1993

More information

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner.

Status of the Unemployment Trust Fund and Related Issues. Commission on Unemployment Compensation. Ellen Marie Hess, Commissioner. Status of the Unemployment Trust Fund and Related Issues Commission on Unemployment Compensation August 8, 2018 Ellen Marie Hess, Commissioner 2 Trust Fund Data Standard Forecast (Millions of Dollars)

More information

Fiscal Year 2017 Columbia Generating Station Annual Operating Budget

Fiscal Year 2017 Columbia Generating Station Annual Operating Budget Fiscal Year 2017 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT WEIGHTAGES JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC ANNOUNCEMENT DATE 19.Dez.14 27.Jän.15 24.Feb.15 26.Mär.15 27.Apr.15 26.Mai.15 25.Jun.15 28.Jul.15 26.Aug.15 23.Sep.15 27.Okt.15 25.Nov.15 MUDARIB

More information

Executive Summary. July 17, 2015

Executive Summary. July 17, 2015 Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

Fiscal Year 2016 Columbia Generating Station Annual Operating Budget

Fiscal Year 2016 Columbia Generating Station Annual Operating Budget Fiscal Year 2016 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

Expected Economic Impact of Constructing and Operating a New Onsite Disposal Facility in Oak Ridge

Expected Economic Impact of Constructing and Operating a New Onsite Disposal Facility in Oak Ridge Baker Reports 2:16 Expected Economic Impact of Constructing and Operating a New Onsite Disposal Facility in Oak Ridge Matthew N. Murray, Director Howard H. Baker Jr. Center for Public Policy Becky Davis,

More information

Home and Community Based Services (HCBS) Waiver Monthly Surplus-Deficit Report for Waiver Program Expenditures. June 20, 2016

Home and Community Based Services (HCBS) Waiver Monthly Surplus-Deficit Report for Waiver Program Expenditures. June 20, 2016 Home and Community Based Services (HCBS) Waiver Monthly Surplus-Deficit Report for Waiver Program Expenditures June 20, 2016 Appropriations and Expenditure Information The Fiscal Year 2015-16 General Appropriations

More information

MEDICAID FEDERAL SHARE OF MATCHING FUNDS

MEDICAID FEDERAL SHARE OF MATCHING FUNDS MEDICAID FEDERAL SHARE OF MATCHING FUNDS revised by EDR based on FFIS Estimated for FFY 2019 August 3, 2017 Effective State Budget Year State adopted February 2017 State State FY real Difference in state

More information

GENERAL FUND AT A GLANCE Category Budget YTD Actual % % Year Passed Resources 50.00% Uses 50.00% $0 $1,928,600

GENERAL FUND AT A GLANCE Category Budget YTD Actual % % Year Passed Resources 50.00% Uses 50.00% $0 $1,928,600 City of Edmond Monthly Financial Report FY 2007/2008 Through the Month Ended Unaudited - Intended for Management Purposes Only The following is a summary of the City's financial results for operating funds.

More information

Calcom Vision Limited. FY18-19 Q2 (July-Sept 18) Investors Release 29 th October, 2018

Calcom Vision Limited. FY18-19 Q2 (July-Sept 18) Investors Release 29 th October, 2018 Vision Limited FY18-19 Q2 (July-Sept 18) Investors Release 29 th October, 2018 Index FY2018-19 Q2 Performance - Review FY2018-19 Sales Review Key Focus Area of the Past Quarter: Materials Requirement Planning

More information

GENERAL FUND AT A GLANCE Category Budget YTD Actual % % Year Passed Resources 8.33% Uses 8.33% $0 $1,330,750

GENERAL FUND AT A GLANCE Category Budget YTD Actual % % Year Passed Resources 8.33% Uses 8.33% $0 $1,330,750 City of Edmond Monthly Financial Report FY 2008/2009 Through the Month Ended Unaudited - Intended for Management Purposes Only The following is a summary of the City's financial results for operating funds.

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL

More information

FY19 BUDGET TIMETABLE

FY19 BUDGET TIMETABLE FY19 BUDGET TIMETABLE (Revised - 8/08/18 - see last page for listing of revisions made to original timetable) Date Day Time Meeting Activity 2018 Jan 9 Tue 9:30 a.m. BCC Mtg BCC Regular Meeting Jan 16

More information

City of Justin NOVEMBER

City of Justin NOVEMBER City of Justin MONTHLY FINANCIAL REPORT NOVEMBER - 2018 1 Revenues: Sales tax revenue is up 14.5% from this time prior year and November s sales tax collections increased 2.4% from November 2017. The City

More information

Building the Future D A.. DAVIDSON DA CONFERENCE SEPTEMBER 11, 2012

Building the Future D A.. DAVIDSON DA CONFERENCE SEPTEMBER 11, 2012 Building the Future D A DAVIDSON CONFERENCE D.A. DAVIDSON CONFERENCE SEPTEMBER 11, 2012 SAFE HARBOR STATEMENT The matters discussed in this presentation may make projections and other forward-looking statements

More information

Integrated Priority List (IPL) Discussion

Integrated Priority List (IPL) Discussion Integrated Priority List (IPL) Discussion John Lopez Office of Integration & Planning DOE-Savannah River Savannah River Site Citizens Advisory Board January 25, 2016 www.energy.gov/em 1 Purpose Provide

More information

August 31, 2016 Financial Report

August 31, 2016 Financial Report August 31, 2016 Financial Report Capital Metropolitan Transportation Authority 10/14/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE

TERMS OF REFERENCE FOR THE INVESTMENT COMMITTEE I. PURPOSE The purpose of the Investment Committee (the Committee ) is to recommend to the Board the investment policy, including the asset mix policy and the appropriate benchmark for both ICBC and any

More information

2013/2014 Biennial Budget 2 nd Quarter 2014 Financial Report and Mid-Year Budget Adjustment. Presented by City Council Study Session July 29, 2014

2013/2014 Biennial Budget 2 nd Quarter 2014 Financial Report and Mid-Year Budget Adjustment. Presented by City Council Study Session July 29, 2014 2013/2014 Biennial Budget 2 nd Quarter 2014 Financial Report and Mid-Year Budget Adjustment Presented by City Council Study Session July 29, 2014 1 2 nd Quarter 2014 Financial Presentation General Fund

More information

Algo Trading System RTM

Algo Trading System RTM Year Return 2016 15,17% 2015 29,57% 2014 18,57% 2013 15,64% 2012 13,97% 2011 55,41% 2010 50,98% 2009 48,29% Algo Trading System RTM 89000 79000 69000 59000 49000 39000 29000 19000 9000 2-Jan-09 2-Jan-10

More information

Project Connect. August 10, 2011

Project Connect. August 10, 2011 Project Connect August 10, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting

More information

Voya Indexed Universal Life-Protector

Voya Indexed Universal Life-Protector calculation examples Values as of 07/28/2018 Voya ed Universal Life-Protector Issued by Security Life of Denver Insurance Company Required training! VFA Registered Representatives must review the Required

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

Capturing equity gains whilst protecting portfolios

Capturing equity gains whilst protecting portfolios Capturing equity gains whilst protecting portfolios Edward Park Q2 2018 MSCI North America Total Return in USD (2017 Discrete Calendar Months) 4.00% 3.50% 3.00% 2.50% 2.00% 1.50% 1.00% 0% 0.00% Jan-17

More information

Financial Report for the Month of SEPTEMBER

Financial Report for the Month of SEPTEMBER WILLOUGHBY, OH Financial Report for the Month of SEPTEMBER Month Ended SEPTEMBER 30, 2013 BOARD OF EDUCATION Mrs. Margaret Warner, President SUPERINTENDENT Mr. Steve Thompson Mrs. Sharon Scott, Vice President

More information

Eversource. Removal of Mercury Boilers. at Schiller Station

Eversource. Removal of Mercury Boilers. at Schiller Station Eversource Removal of Mercury Boilers at Schiller Station Monthly Status Report September 2017 Date: October 31, 2017 Subject: Schiller Station Units 1 & 2 Mercury Boiler Removal Monthly Status Report

More information

Using projections to manage your programs

Using projections to manage your programs Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based

More information

Cost Estimation of a Manufacturing Company

Cost Estimation of a Manufacturing Company Cost Estimation of a Manufacturing Company Name: Business: Date: Economics of One Unit: Manufacturing Company (Only complete if you are making a product, such as a bracelet or beauty product) Economics

More information

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to:

1.2 The purpose of the Finance Committee is to assist the Board in fulfilling its oversight responsibilities related to: Category: BOARD PROCESS Title: Terms of Reference for the Finance Committee Reference Number: AB-331 Last Approved: February 22, 2018 Last Reviewed: February 22, 2018 1. PURPOSE 1.1 Primary responsibility

More information

Operating Reserves Educational Session Part B

Operating Reserves Educational Session Part B Operating Reserves Educational Session Part B Energy Market Uplift Senior Task Force September 17, 2013 Joseph Bowring Joel Romero Luna Operating Reserves Operating reserves can be grouped into five categories:

More information

2019 Recology San Mateo County Compensation Adjustment Application

2019 Recology San Mateo County Compensation Adjustment Application 2019 San Mateo County Adjustment TAC Meeting September 13, 2018 Adjustment Table 1 Total Contractor's Base Incentives / Disincentives Total Contractor's 2018 Cost 2019 Cost Change % $56,793,053 $57,890,585

More information

Project NEON Interim Finance Committee Rudy Malfabon Director

Project NEON Interim Finance Committee Rudy Malfabon Director Project NEON Interim Finance Committee Rudy Malfabon Director October 22, 2014 1 Project Benefits Safety & Congestion 1,000 crashes per year! Connectivity /Mobility for City Redevelopment Efforts Congestion:

More information

BANK OF GUYANA. BANKING SYSTEM STATISTICAL ABSTRACT Website:

BANK OF GUYANA. BANKING SYSTEM STATISTICAL ABSTRACT Website: BANK OF GUYANA BANKING SYSTEM STATISTICAL ABSTRACT Website: www.bankofguyana.org.gy RESEARCH DEPARTMENT November 2010 STATISTICAL ABSTRACT TABLES CONTENTS 1. MONETARY AUTHORITY 1.1 Bank of Guyana: Assets

More information

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018 Jan-01 $12.9112 $10.4754 $9.7870 $1.5032 $29.2595 $275.39 $43.78 $159.32 $25.33 Feb-01 $10.4670 $7.8378 $6.9397 $1.5218 $29.6447 $279.78 $44.48 $165.68 $26.34 Mar-01 $7.6303 $7.3271 $5.0903 $1.5585 $27.2714

More information

Factor Leave Accruals. Accruing Vacation and Sick Leave

Factor Leave Accruals. Accruing Vacation and Sick Leave Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization

More information

QUARTERLY FINANCIAL REPORT March 31, 2018

QUARTERLY FINANCIAL REPORT March 31, 2018 California Independent System Operator QUARTERLY FINANCIAL REPORT March 31, 2018 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

City of Joliet 2014 Revenue Review. October 2013

City of Joliet 2014 Revenue Review. October 2013 City of Joliet 2014 Revenue Review October 2013 General Fund 2014 Est. Revenues = $163.6 M Licenses, Permits, Fees Gaming Taxes 5% 12% Sales Taxes 27% Income Taxes 9% Charges for Services 14% Other Taxes

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

QUARTERLY FINANCIAL REPORT June 30, 2017

QUARTERLY FINANCIAL REPORT June 30, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT June 30, 2017 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

Illinois Job Index. Growth Rate %

Illinois Job Index. Growth Rate % Illinois Job Index Release Data Issue 03/14/2011 Jan 1990 / Jan 2011 2011.02 www.real.illinois.edu For January Illinois Job Index, the Nation, RMW and the state all had positive job growth. The monthly

More information

CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP

CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS Presented by : Hany Ismail, MSc, PMP CONSTRUCTION CLAIMS MANAGEMENT EOT DELAYS ANALYSIS LESSON 7 TIME IMPACT WINDOW DELAY ANALYSIS TECHNIQUE TIME IMPACT

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

LIFE CYCLE ASSET MANAGEMENT. Project Budget Process. Good Practice Guide GPG-FM-019. March 1996

LIFE CYCLE ASSET MANAGEMENT. Project Budget Process. Good Practice Guide GPG-FM-019. March 1996 LIFE YLE Good Practice Guide ASSET MANAGEMENT Project Budget Process March 1996 Department of Energy Office of Field Management Office of Project and Fixed Asset Management ontents TABLE OF ONTENTS 1.

More information

BANK OF GUYANA. BANKING SYSTEM STATISTICAL ABSTRACT Website:

BANK OF GUYANA. BANKING SYSTEM STATISTICAL ABSTRACT Website: BANK OF GUYANA BANKING SYSTEM STATISTICAL ABSTRACT Website: www.bankofguyana.org.gy RESEARCH DEPARTMENT March 2010 STATISTICAL ABSTRACT TABLES CONTENTS 1. MONETARY AUTHORITY 1.1 Bank of Guyana: Assets

More information

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Fiscal Year 2010 Columbia Generating Station Annual Operating Budget Table of Contents Table Page Summary 3 Key Assumptions/Qualifications 4 Memorandum of Agreement (MOA) Table 1 5 Columbia Station Costs

More information

Performance Report October 2018

Performance Report October 2018 Structured Investments Indicative Report October 2018 This report illustrates the indicative performance of all Structured Investment Strategies from inception to 31 October 2018 Matured Investment Strategies

More information

CURRENT CLOSURE STATUS OF ELIGIBLE DISCHARGES. Eligible Discharges Rehabilitated per Fiscal Year as of September 29, 2017

CURRENT CLOSURE STATUS OF ELIGIBLE DISCHARGES. Eligible Discharges Rehabilitated per Fiscal Year as of September 29, 2017 CURRENT CLOSURE STATUS OF ELIGIBLE DISCHARGES FY 2017-18 Discharges Closed as of September 29, 2017 Projection FY 2017-18 Current Discharges Closed Percent Closure Type 425 171 40.2% FY 2017-18 Closures

More information

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of July 31 Unaudited Balance Sheet As of July 31 Total Enrollment: 407 Assets: Cash $ 9,541,661 $ 1,237,950 Invested Cash 781,689 8,630,624 Premiums Receivable 16,445 299,134 Prepaid 32,930 34,403 Assessments Receivable

More information

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of January 31

HIPIOWA - IOWA COMPREHENSIVE HEALTH ASSOCIATION Unaudited Balance Sheet As of January 31 Unaudited Balance Sheet As of January 31 Total Enrollment: 371 Assets: Cash $ 1,408,868 $ 1,375,117 Invested Cash 4,664,286 4,136,167 Premiums Receivable 94,152 91,261 Prepaid 32,270 33,421 Assessments

More information

DEVELOPING PERFORMANCE MEASURES FOR THE ENVIRONMENTAL MANAGEMENT PROGRAM Dan M. Berkovitz Jessica S. Arcidiacono

DEVELOPING PERFORMANCE MEASURES FOR THE ENVIRONMENTAL MANAGEMENT PROGRAM Dan M. Berkovitz Jessica S. Arcidiacono DEVELOPING PERFORMANCE MEASURES FOR THE ENVIRONMENTAL MANAGEMENT PROGRAM Dan M. Berkovitz Jessica S. Arcidiacono ABSTRACT The Office of Environmental Management (EM) has developed a set of corporate performance

More information

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 $50 Historical Pricing PJM COMED, Around the Clock $48 $46 $44 $42 $40 $38 $36 $34 $32 $30 $28 $26 Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 The information presented above was gathered

More information

HART Financial Snapshot. HART Finance and Audit Committee January 23, 2017

HART Financial Snapshot. HART Finance and Audit Committee January 23, 2017 HART Financial Snapshot HART Finance and Audit Committee January 23, 2017 1 Requested January 3, 2017 Cash flow management overview Fund balance update including year end fund balance reported in the past

More information

Japan Securities Finance Co.,Ltd

Japan Securities Finance Co.,Ltd Japan Securities Finance Co.,Ltd \ mil ( )ratio of OR Mar-13 Mar-14 Securities Finance Bussiness 14,093 16,363 Margin Loan Business 6,625 9,240 (37.5%) (47.2%) Interest on Loans 1,760 4,012 Interest

More information

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDER UNDER

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDER UNDER LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDER UNDER JSF LRIP 6 CONTRACT NUMBER N00019-11-C-0083 Generated using

More information

FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS. FAR Number Title Latest Update MATERIAL REQUIREMENTS AUG 2000

FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS. FAR Number Title Latest Update MATERIAL REQUIREMENTS AUG 2000 FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS 1. The following FAR clauses apply to all non-commercial orders: 52.211-5 MATERIAL REQUIREMENTS AUG 2000 52.215-20 REQUIREMENTS FOR COST OR PRICING DATA

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2017 Date: May 10, 2017 I. Summary CTA s financial results are $0.6 million favorable to budget

More information

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015

More information

Looking at a Variety of Municipal Valuation Metrics

Looking at a Variety of Municipal Valuation Metrics Looking at a Variety of Municipal Valuation Metrics Muni vs. Treasuries, Corporates YEAR MUNI - TREASURY RATIO YEAR MUNI - CORPORATE RATIO 200% 80% 175% 150% 75% 70% 65% 125% Average Ratio 0% 75% 50% 60%

More information

Arkansas Works Overview. Work And Community Engagement Requirement

Arkansas Works Overview. Work And Community Engagement Requirement 1 Arkansas Works Overview Work And Community Engagement Requirement Arkansas Works Populations & Work and Community Engagement Requirement 2 Arkansas Works enrollees will fall into three categories for

More information

FPSBI/M-VI/03-01/10/WN-23 (1+0.09/4)^4-1 ( )/( )-1

FPSBI/M-VI/03-01/10/WN-23 (1+0.09/4)^4-1 ( )/( )-1 Solutions-Irawati Senna 1) B) 2) A) Nominal interest rate Effective rate Inflation Real rate of return 9.00% p.a. 9.31% p.a. 5.50% p.a. 3.61% p.a. (1+0.09/4)^4-1 (1+0.0931)/(1+0.055)-1 3) D) Amount of

More information

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600

More information

Accountant s Compilation Report

Accountant s Compilation Report Tel: 817-738-2400 Fax: 817-738-1995 www.bdo.com 6050 Southwest Blvd, Suite 300 Fort Worth, TX 76109 Accountant s Compilation Report Joseph Portugal Town Administrator Town of Westover Hills, Texas Management

More information

FOR OFFICIAL USE ONLY (FOUO)

FOR OFFICIAL USE ONLY (FOUO) SITE-SPECIFIC MEMORANDUM OF UNDERSTANDING BETWEEN THE U.S. ARMY CORPS OF ENGINEERS, THE U.S. NUCLEAR REGULATORY COMMISSION, THE U.S. DEPARTMENT OF ENERGY OFFICE OF ENVIRONMENTAL MANAGEMENT, AND THE NATIONAL

More information

Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary

Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary Revenue Estimating Conference Tobacco Tax and Surcharge Executive Summary February 12, 2014 The Revenue Estimating Conference reviewed Tobacco Tax and Surcharge revenues on February 12, 2014. The forecasts

More information

Historical Pricing PJM PSEG, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Historical Pricing PJM PSEG, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 $70 Historical Pricing PJM PSEG, Around the Clock $65 $60 $55 $50 $45 $40 $35 $30 $25 Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22 The information presented above was gathered and compiled

More information

Division of Bond Finance Interest Rate Calculations. Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates

Division of Bond Finance Interest Rate Calculations. Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates Division of Bond Finance Interest Rate Calculations Revenue Estimating Conference Interest Rates Used for Appropriations, including PECO Bond Rates November 16, 2018 Division of Bond Finance Calculation

More information

Foundations of Investing

Foundations of Investing www.edwardjones.com Member SIPC Foundations of Investing 1 5 HOW CAN I STAY ON TRACK? 4 HOW DO I GET THERE? 1 WHERE AM I TODAY? MY FINANCIAL NEEDS 3 CAN I GET THERE? 2 WHERE WOULD I LIKE TO BE? 2 Develop

More information

Investment DANA FIXED INCOME STRATEGIES.

Investment DANA FIXED INCOME STRATEGIES. Investment DANA Advisors THE WISE CHOICE HERITAGE A strong family culture Since our founding in 1980, Dana has remained independent and Employee-owned. Our investment firm is built on trust, integrity,

More information

Inland Waterways Users Board Meeting No. 71 Little Rock, Arkansas

Inland Waterways Users Board Meeting No. 71 Little Rock, Arkansas Inland Waterways Users Board Meeting No. 71 Little Rock, Arkansas Financial Report & Project Summaries Mr. Jon Soderberg USACE Headquarters May 1, 2014 US Army Corps of Engineers FY 13 Status of Trust

More information

Isle Of Wight half year business confidence report

Isle Of Wight half year business confidence report half year business confidence report half year report contents new company registrations closed companies (dissolved) net company growth uk company share director age director gender naming trends sic

More information

NEI [Revision 0] Use of the Nuclear Decommissioning Trust Fund

NEI [Revision 0] Use of the Nuclear Decommissioning Trust Fund NEI 15-06 [Revision 0] Use of the Nuclear Decommissioning Trust Fund [THIS PAGE IS LEFT BLANK INTENTIONALLY] NEI 15-06 [Revision 0] Nuclear Energy Institute Use of the Nuclear Decommissioning Trust Fund

More information

Strategic Plan Progress Report Goal 4 Focus. May 2015 San Francisco, California

Strategic Plan Progress Report Goal 4 Focus. May 2015 San Francisco, California Strategic Plan Progress Report Goal 4 Focus May 2015 San Francisco, California 1 Goal 4 focus Create a workplace that delivers outstanding service Objective 4.1 Improve internal communications Objective

More information

Board of Directors October 2018 and YTD Financial Report

Board of Directors October 2018 and YTD Financial Report Board of Directors October 2018 and YTD Financial Report Consolidated Financial Results Operating Margin October ($30,262) $129,301 ($159,563) Year-to-date $292,283 $931,358 ($639,076) Excess of Revenue

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

Simple Interest. S.Y.Tan. 1.1 Simple Interest

Simple Interest. S.Y.Tan. 1.1 Simple Interest Simple Interest Interest (I) a benefit in the form of a fee that lender received for letting borrower use of his money Origin date (O.D.) the date on which the borrowed money is received by the borrower

More information

TVA BOARD MEETING AUGUST 22, 2013

TVA BOARD MEETING AUGUST 22, 2013 TVA BOARD MEETING AUGUST 22, 2013 TVA BOARD MEETING 2 CONSENT AGENDA Health Savings Account Contract Pharmacy Benefits Managers Contract Assistant Corporate Secretary Designations 3 CHAIRMAN S REPORT AUGUST

More information

A Study on Risk Analysis in Construction Project

A Study on Risk Analysis in Construction Project A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------

More information

CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks

CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks CONTINUOUS SETTLEMENT AND THE ROLE OF KPEI SECURITIES LENDING Providing Intermediated Financing Methods To Set A New Business Risks By: Hoesen President Director KPEI (Indonesia Central Counter Party)

More information

DOWRW ME/RW--O U.S. Department of Energy Office of Civilian Radioactive Waste Management Washington, DC 20585

DOWRW ME/RW--O U.S. Department of Energy Office of Civilian Radioactive Waste Management Washington, DC 20585 DOWRW-0225-1 ME/RW--O 225-1 U.S. Department of Energy Office of Civilian Radioactive Waste Management Washington, DC 20585 DISCLAIMER This report was prepared as an account of work sponsored by an agency

More information

PRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. January 2019

PRESS RELEASE. Securities issued by Hungarian residents and breakdown by holding sectors. January 2019 7 March 2019 PRESS RELEASE Securities issued by Hungarian residents and breakdown by holding sectors January 2019 According to securities statistics, the amount outstanding of equity securities and debt

More information

Approve Financial Stability Plan (aka Project FIT) for UW Medicine

Approve Financial Stability Plan (aka Project FIT) for UW Medicine STANDING COMMITTEES F 5 Finance and Asset Management Committee Approve Financial Stability Plan (aka Project FIT) for UW Medicine RECOMMENDED ACTION It is the recommendation of the administration and the

More information