1 MINISTRY OF ENERGY AND MINERAL RESOURCES OF THE REPUBLIC OF INDONESIA DIRECTORAT GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION By Director of Various New and Renewable Energy T Jakarta, 10 May 2013

2 I. Background 3 II. Legal Basis 4 III. Power Purchase Principle 5 IV. Purchase Price and criterion 6 V. Quota Bidding Mechanism 7 VI. Public Bidding Procedure 8 VII. Quota Determination Procedure 9 VIII. Requirement for Public Bidding on Quota Capacity 10 IX. Right of Business Entities (enterprise) of the Quota Bidding Participant 13 X. Liability of Business Entities of Quota Bidding Winner 14 XI. Sanction of Business Entities of Quota Bidding Winner 15

3 I. BACKGROUND 1. For interconnection system, prioritized for substitution of electricity generation using fuel, which in turn can reduce the fuel subsidy; 2. For isolated systems, its development is directed to systems that still use diesel power plants; 3. Government budget is limited so it is necessary to increase the role of private sector in renewable energy, including solar; 4. To attract the necessary investment benchmark price for providing price certainty without negotiation; 5. Accomplishments of energy mix target should be driven

4 II. LEGAL BASIS 1. Law Number 30 year 2007 on Energy Article 20 Paragraph 5 Energy supply of new energy sources and renewable energy sources by business entities, permanent and individual establishment may obtain facilities and / or incentives from the Government and/ or the local government in accordance with the authority for a specified period to achieve its economic value. 2. President Regulation No. 5 Year 2006 concerning National Energy Policy is targeting contribution of new renewable energy amounted to 17% in the energy mix primer (until today share of NRE 6.9%). 3. Commitment of The Government for lower gas emissions CO2 by 26% by 2020 or 41% with international support.

5 III. PRINCIPLES OF POWER PURCHASE 1. PT PLN (Persero) is obliged to purchase all electricity generated from solar photovoltaic Enterprises (IPP). 2. Purchase price of electricity used in the power purchase agreement of solar Photovoltaics are final. 3. Purchase of electricity from solar photovoltaic capacity based on supply quotas set by DGNREEC which proposed by PT. PLN (Persero).

6 IV. PURCHASE PRICE AND CRITERION 1. Purchase price of electricity from solar photovoltaic for all capacity assigned with the highest standard price of 25 cents USD / kwh 2. If the use of photovoltaic solar modules with DCL at least 40%, given the incentives so that the purchase price of electricity is set to the highest standard price of 30 cents USD / kwh. 3. The purchase price includes the full cost of the interconnection of generation to the point of interconnection of electric power networks PT. PLN (Ltd.). 4. Criteria in determining quotas and the location is the burden and the ability of PLN system to absorb on-grid solar power production with a capacity of between 1-10 MW and location of isolated subsystem, which is still partly or wholly supplied from diesel-oil subsystems and BPP on the above price Highest Purchase Price in MEMR design.

7 V. QUOTA BIDDINGMECHANISM 1. Director general of DGNREEC offer Quota capacity to Entity in accordance with the determination of quotas Capacity 2. Quota offer capacity conducted through a public tender. 3. When offering Quota capacity, there is 1 (one) Enterprises that register, then the period of the auction is extended for 7 working days. 4. When the extension of the auction has ended and still followed by 1 Enterprises, the tender process continued

8 VI. PUBLIC BIDDING PROCEDURE 1. Capacity auction quota can be followed by a Business Entity. 2. In 1 package auction, 1 Enterprises can only participate in one consortium. 3. Bid Documents must be uploaded (up load) through the auction website application electronically quota capacity. 4. Bid Documents uploaded (up load) in phase 1 consisting of two covers, which cover 1 contains the requirements for administrative, technical, and financial, and the cover 2 contains price quotation. 5. Bid evaluation using the threshold scoring system and the lowest price. 6. Lowest price is the selling price of electricity is the lowest offered by the participants, expressed in U.S. $ cents / kwh.

9 VII. QUOTA DETERMINATION PROCEDURE 1. DGNREEC deliver massive capacity quota plan to PT PLN (Persero). 2. PT. PLN propose details quota capacity to DG of DGNREEC, no later than 60 days after the amount capacity quota delivered. 3. DGNREEC sets quota by considering the capacity of the proposed details of quota capacity at the beginning of the year.

10 VIII. REQUIREMENT FOR PUBLIC BIDDING ON QUOTA CAPACITY... (1) 1. Enterprises can follow the auction process must meet the requirements Quota Capacity administrative, technical, and financial. 2. Administrative requirements include at least: a. integrity fact; b. identity of the applicant / certificate of incorporation Enterprises; c. profile of the enterprise; Taxpayer Identification Number; d. Partnership Agreement / Joint Operation, when it is in a form of consortium 3. Minimum financial requirements include: a. financial statements audited by a public accountant unless the new company by attaching the financial statements; b. Bid Security in the form of a bank guarantee of 2% (two percent) of the total investment value of state-owned banks or the major banks (prime bank) based in Jakarta; c. affidavit with the ability to open an account (escrow account) between the Enterprises and DGNREEC at 20% of total development Photovoltaics PLTS investment later than 15 working days after adoption as the preferred bidder by DG of

11 VIII. REQUIREMENT FOR PUBLIC BIDDING ON QUOTA CAPACITY...(2) 4. Minimum technical requirements include: a. construction site plan that took into account the technical requirements of connection that comes with the map and the coordinates of its location; b. implementation schedule for the construction of solar photovoltaic and scheduled Commercial Operation Date (COD) of PLTS Photovoltaics; c. projected production and sale of electricity for 20 years; d. work plan and budget; e. Detailed Design Build (Detailed Engineering Design) solar photovoltaic; f. list of experts in the field of solar photovoltaic, especially those who have the technical capability of operational solar photovoltaic with demonstrated experience in the field of solar photovoltaic development; g. organizational structure of the implementation of development; h. Technical specifications of solar Photovoltaics (solar module capacity and type); i. letters of support for the manufacturer of photovoltaic modules and inverters;

12 VIII. REQUIREMENT FOR PUBLIC BIDDING ON QUOTA CAPACITY...(3) j. When using an imported product must attach a statement that the photovoltaic module and inverter imported used meets international standards as evidenced by a certificate of product certification agency independent k. when using domestic products must attach: Recapitulation Form for the whole solar photovoltaic; a statement that the photovoltaic modules and inverters domestic products used in compliance with the applicable technical standards in Indonesia, as evidenced by a certificate of product test results from testing agencies, and statement using domestic products to components other than the main component that meets national standards.

13 IX. RIGHTS OF BUSINESS ENTITIES OF THE QUOTA BIDDERS 1. In 1 package of auction, 1 Enterprises can only participate in one consortium. 2. Auction participants registering from the date of announcement of the auction up to at least 1 day before the deadline for uploading the Bid Document. 3. Auction participants after registration Tender documents can be downloaded from the date of registration up to 1 day before the deadline for uploading the Bid Document. 4. Participants who entered the Bidding Documents may submit a written rebuttal over the announcement of the winning bidder to DGNREEC within 5 working days after the announcement of the winner of the auction accompanied by evidence of irregularities. 5. An objection may be brought by the participants either individually or jointly with other participants in case of deviation procedures.

14 X. LIABILITY OF BUSINESS ENTITIES OF QUOTA BIDDING WINNER 1. auction winners Entity must deposit funds for Photovoltaic solar development implementation on behalf of the Enterprise and DGNREEC on state-owned banks or the major banks (prime bank) located in Jakarta by 20% of the total investment of solar photovoltaic development, no later than 15 working days after named the winner of the auction by DGNREEC. 2. The entity (Enterprises) can use the deposited funds for the construction of solar photovoltaic investments needs after reaching financial close. 3. PT. PLN (Persero) within a maximum period of 60 days after the assignment of the purchase of electricity required to sign a PPA and report on its implementation to the DGNREEC. 4. Enterprises tender winner shall achieve financial close within a maximum period of 3 months after the signing of the PPA. 5. Enterprises shall open the auction winner of Solar Photovoltaics development later than 3 months after financial close.

15 XI. SANCTION FOR BUSINESS ENTITIES OF QUOTA BIDDING WINNER 1. The entities or enterprises as the auction winner that can not fulfill its obligations, subject to administrative sanctions include written warnings. 2. Given a written warning by DGNREEC most 3 times the warning period 1 (one) month respectively. 3. Given a written warning by the proposed PT. PLN (Persero) or based on an evaluation by DGNREEC. 4. Enterprises as an auction winners received a written warning penalty after expiry of the three written warnings not perform its obligations, then the assignment to the PT. PLN canceled by the Minister on the recommendation of DGNREEC. 5. When the assignment to the PT. PLN canceled by the Minister then the PPA is terminated, and Director General (DG) of DGNREEC propose to the Director General of Electricity (DGE) to establish purchase assignment of power to a new state electricity company (Ltd.)

16 DESIGN IMPLEMENTATION MECHANISM OF MINISTER REGULATION OF PHOTOVOLTAIC SOLAR POWER PLANT PROVISION DGNREEC PLN PPA + Financial Close PLN DEVELOPER CONSTRUCTION DEVELOPER

17 Solar PP Quota Bidding: 1. DGNREEC submit Quota to PLN 2. President Director of PLN propose detail quota to DGNREEC 3. DGNREEC Sets the proposal of detail quota Start CYCLE OF IMPLEMENTATIO N OF MINISTER REGULATION ON SOLAR POWER Public Bidding: 1.Announcement, Registration, Explanation Socialization, Submission of Bidding Document 2.Evaluation of Bidding document 3.Proffing 4.Winner determination 5.Objection Period Assignment for Purchasing: 1.DGNREEC submits the winner to DGE 2.Minister issues letter of assignment to PLN 3.Business Entity/enterprise deposit fund for Solar PP development 4.Signing on Sale Agreement 5.Financial Close 6.Period of the Working start 64 days 46 days asap asap asap Max 60 day Max 90 days Max 90 days Remark Extension period of the construction implementation max 12 months Construction implementation Period Commercial Operation Date (COD) 540 days / 18 month 890 days / ± 30 months

18 Terima Kasih Go Green Indonesia! energi hijau, energi masa depan KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN, DAN KONSERVASI ENERGI Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950; Telp/Faks :

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

One Stop Integrated Services Geothermal Licensing

One Stop Integrated Services Geothermal Licensing invest in BKPM 2016 One Stop Integrated Services Geothermal Licensing INDONESIA INVESTMENT COORDINATING BOARD Hanung Harimba Rachman Director of Investment Planning for Agribusiness and Natural Resources,

More information

BANK INDONESIA REGULATION NUMBER: 5/4/PBI/2003 CONCERNING ISSUANCE, SALE AND PURCHASE, AND ADMINISTRATION OF SOVEREIGN DEBT INSTRUMENTS

BANK INDONESIA REGULATION NUMBER: 5/4/PBI/2003 CONCERNING ISSUANCE, SALE AND PURCHASE, AND ADMINISTRATION OF SOVEREIGN DEBT INSTRUMENTS BANK INDONESIA REGULATION NUMBER: 5/4/PBI/2003 CONCERNING ISSUANCE, SALE AND PURCHASE, AND ADMINISTRATION OF SOVEREIGN DEBT INSTRUMENTS THE GOVERNOR OF BANK INDONESIA, Considering : a. whereas Bank Indonesia

More information

PPP IDENTIFICATION AND PPP PLANNING

PPP IDENTIFICATION AND PPP PLANNING PPP IDENTIFICATION AND PPP PLANNING Mohammad Taufiq Rinaldi Planner Directorate of PPP and Financial Engineering Ministry of National Planning Agency/BAPPENAS Republic of Indonesia Asia PPP Practioners

More information

Table 1: Comparison of Installed Cost Forecasts

Table 1: Comparison of Installed Cost Forecasts 1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision for Canada s solar energy

More information

PRESIDENT OF THE REPUBLIC OF INDONESIA LAW OF THE REPUBLIC OF INDONESIA NUMBER 24 YEAR 2011 THE IMPLEMENTING AGENCY OF SOCIAL SECURITY

PRESIDENT OF THE REPUBLIC OF INDONESIA LAW OF THE REPUBLIC OF INDONESIA NUMBER 24 YEAR 2011 THE IMPLEMENTING AGENCY OF SOCIAL SECURITY LAW NUMBER 24 YEAR 2011 ON THE IMPLEMENTING AGENCY OF SOCIAL SECURITY BY THE GRACE OF THE GOD ALMIGHTY PRESIDENT, Consider : a. that the social security system shall be program of the state of which aimed

More information

Solar Renewable Energy Credit Aggregation Customer Information

Solar Renewable Energy Credit Aggregation Customer Information Solar Renewable Energy Credit Aggregation Customer Information Thank you for choosing Hampshire Council of Governments as your Solar Renewable Energy Credit (SREC) Aggregator! We are excited to be working

More information

BANK INDONESIA REGULATION NUMBER : 9/3/PBI/2007 CONCERNING GOVERNMENT SECURITIES AUCTION AND ADMINISTRATION THE GOVERNOR OF BANK INDONESIA,

BANK INDONESIA REGULATION NUMBER : 9/3/PBI/2007 CONCERNING GOVERNMENT SECURITIES AUCTION AND ADMINISTRATION THE GOVERNOR OF BANK INDONESIA, Unofficial Translation BANK INDONESIA REGULATION NUMBER : 9/3/PBI/2007 CONCERNING GOVERNMENT SECURITIES AUCTION AND ADMINISTRATION THE GOVERNOR OF BANK INDONESIA, Considering : a. whereas Bank Indonesia

More information

PROCEDURES FOR THE MANAGEMENT OF COUNTRY-TO- COUNTRY REPORTS DIRECTOR GENERAL OF TAX,

PROCEDURES FOR THE MANAGEMENT OF COUNTRY-TO- COUNTRY REPORTS DIRECTOR GENERAL OF TAX, Type: By: Number: Date: Title: REGULATION (PER) DIRECTOR GENERAL OF TAX (DIRGENTAX) 29/PJ/2017 DECEMBER 29, 2017 (JAKARTA) PROCEDURES FOR THE MANAGEMENT OF COUNTRY-TO- COUNTRY REPORTS DIRECTOR GENERAL

More information

Conditions for tender of aid for electricity generated by onshore wind turbines, open door offshore wind turbines, and solar PV installations

Conditions for tender of aid for electricity generated by onshore wind turbines, open door offshore wind turbines, and solar PV installations Conditions for tender of aid for electricity generated by onshore wind turbines, open door offshore wind turbines, and solar PV installations December 2017 1 1. THE CONTRACTING AUTHORITY... 4 2. REGULATION

More information

MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA COPY

MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA COPY COPY REGULATION OF THE MINISTER OF FINANCE NO. 170/PMK.02/2013 CONCERNING PROCEDURES FOR PROVISION OF THE BUDGET, CALCULATION, PAYMENT, AND THE ACCOUNTABILITY OF ELECTRICITY SUBSIDY BY THE GRACE OF THE

More information

EUROPEAN COMMISSION Background and objectives of the notified project

EUROPEAN COMMISSION Background and objectives of the notified project EUROPEAN COMMISSION Brussels, 27.9.2016 C(2016) 6326 final PUBLIC VERSION This document is made available for information purposes only. Subject: State Aid SA.44626 (2016/N) Denmark Pilot tender for aid

More information

REGULATION OF INVESTMENT COORDINATING e-licensing BOARD NO. 13 of 2017

REGULATION OF INVESTMENT COORDINATING e-licensing BOARD NO. 13 of 2017 Shifting to digital age : Toward paperless licensing REGULATION OF INVESTMENT COORDINATING e-licensing BOARD NO. 13 of 2017 Deputy Chairman for Investment Services ONE STOP SERVICE CENTER - BKPM Jakarta,

More information

STUDY ON PUBLIC PROCUREMENT SYSTEM FOR JCM PROJECT

STUDY ON PUBLIC PROCUREMENT SYSTEM FOR JCM PROJECT STUDY ON PUBLIC PROCUREMENT SYSTEM FOR JCM PROJECT To achieve sustainability and replication of JCM Project Model To achieve JCM sustainability, it is necessary to promote widely JCM project model in cooperation

More information

DECREE OF THE MINISTER OF COMMUNICATION AND INFORMATION TECHNOLOLGY NUMBER : 04/PER/M.KOMINFO/01/2006

DECREE OF THE MINISTER OF COMMUNICATION AND INFORMATION TECHNOLOLGY NUMBER : 04/PER/M.KOMINFO/01/2006 1 DECREE OF THE MINISTER OF COMMUNICATION AND INFORMATION TECHNOLOLGY NUMBER : 04/PER/M.KOMINFO/01/2006 0N AUCTION PROCEDURE OF RADIO FREQUENCY SPECTRUM BAND OF 2.1 GHz FOR THE PROVISION OF IMT-2000 CELLULAR

More information

THE PRESIDENT OF THE REPUBLIC OF INDONESIA REGULATION OF THE GOVERNMENT OF THE REPUBLIC OF INDONESIA

THE PRESIDENT OF THE REPUBLIC OF INDONESIA REGULATION OF THE GOVERNMENT OF THE REPUBLIC OF INDONESIA REGULATION OF THE GOVERNMENT OF THE REPUBLIC OF INDONESIA NUMBER 10 OF 2011 ON PROCEDURES OF FOREIGN LOANS PROCUREMENT AND GRANTS RECEIPT BY THE GRACE OF GOD ALMIGHTY Considering : a. that in order to

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA DIRECTOR GENERAL OF TAXES REGULATION NUMBER PER-10/PJ/2017 CONCERNING

MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA DIRECTOR GENERAL OF TAXES REGULATION NUMBER PER-10/PJ/2017 CONCERNING MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA DIRECTOR GENERAL OF TAXES REGULATION NUMBER PER-10/PJ/2017 CONCERNING THE APPLICATION PROCEDURE OF DOUBLE TAXATION CONVENTION DIRECTOR GENERAL OF TAXES,

More information

- 2 - COPY OF FINANCIAL SERVICES AUTHORITY REGULATION NUMBER 60 /POJK.04/2017 ON THE ISSUANCE AND THE TERMS OF GREEN BOND

- 2 - COPY OF FINANCIAL SERVICES AUTHORITY REGULATION NUMBER 60 /POJK.04/2017 ON THE ISSUANCE AND THE TERMS OF GREEN BOND - 2 - FINANCIAL SERVICES AUTHORITY OF THE REPUBLIC OF INDONESIA COPY OF FINANCIAL SERVICES AUTHORITY REGULATION NUMBER 60 /POJK.04/2017 ON THE ISSUANCE AND THE TERMS OF GREEN BOND BY THE GRACE OF GOD THE

More information

SEPTEMBER 2017 LEGAL ALERT. general. agrarian affairs and spatial planning

SEPTEMBER 2017 LEGAL ALERT. general. agrarian affairs and spatial planning LEGAL ALERT SEPTEMBER 2017 SSEK Legal Alert is a monthly publication of SSEK, Indonesian Legal Consultants. SSEK s lawyers, advisors and associates provide a wide range of legal services to Indonesian

More information

Section I DETAILED NOTICE INVITING TENDER

Section I DETAILED NOTICE INVITING TENDER Section I West Bengal Renewable Energy Development Agency (An organization of Department of Power and NES Government of West Bengal) BIKALPA SHAKTI BHAVAN, Plot J1/10, Block EP & GP, Sector V, Salt Lake

More information

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory

More information

5% - if the local component is from. NSS introduction date From 01 January 2025 From 01 January 2020 Entities obliged to participate in the auctions

5% - if the local component is from. NSS introduction date From 01 January 2025 From 01 January 2020 Entities obliged to participate in the auctions Main differences of the draft laws alternative to the draft law On Amendments to Certain s of Ukraine on the Development of Competitive Electricity Production from Alternative Energy Sources (reg. No.

More information

Agenda. Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks

Agenda. Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks Agenda Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks 1 Enel today 1 Global and diversified operator 40 bn Regulated Asset Base 62 mn distribution end users

More information

Support regimes for offshore wind in Europe Florian Bauernfeind

Support regimes for offshore wind in Europe Florian Bauernfeind Winter Academy 2018 Trading, Sales and Financing in the European Energy Market and Industry Support regimes for offshore wind in Europe Florian Bauernfeind Vattenfall Agenda 1. Wind Power in Vattenfall

More information

Development Credit Agreement

Development Credit Agreement Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 3909 YF Public Disclosure Authorized Development Credit Agreement (Transport Rehabilitation Project) Public Disclosure Authorized between SERBIA

More information

Dominion Energy Virginia

Dominion Energy Virginia Request for Proposal 2017 Solicitation for New Photovoltaic Solar and Onshore Wind Power Supply Generation October 16, 2017 Dominion Energy Virginia TABLE OF CONTENTS Table of Contents PART I RFP Overview...

More information

Solar/ Renewable Energy - Alternative Power Source. Richmond, NH. Cheshire County Sheriff s Office. Request for Proposals

Solar/ Renewable Energy - Alternative Power Source. Richmond, NH. Cheshire County Sheriff s Office. Request for Proposals Solar/ Renewable Energy - Alternative Power Source Richmond, NH Cheshire County Sheriff s Office Request for Proposals The County of Cheshire (Sheriff s Office) is requesting a Letter of Intent, followed

More information

Central Bank of Seychelles Operational Guidelines from Policy Tools: Foreign Exchange Auctions (FEA)

Central Bank of Seychelles Operational Guidelines from Policy Tools: Foreign Exchange Auctions (FEA) Central Bank of Seychelles Operational Guidelines from Policy Tools: (FEA) June 2017 1.0 Introduction The Central Bank of Seychelles (thereafter referred to as the Bank) can intervene in the domestic market

More information

PT Paiton Energy A Case Study in Renegotiation

PT Paiton Energy A Case Study in Renegotiation PT Paiton Energy A Case Study in Renegotiation Session on Yong Hee Kong PPP Resource & Research Centre, Kuala Lumpur PT Paiton During Construction 1 PT Paiton Energy (almost complete) Pt Paiton Energy

More information

GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY. GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014)

GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY. GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014) GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014) TABLE OF CONTENTS CHAPTER ONE GENERAL... 1 I. Title and Introduction...

More information

Ministry of Physical Infrastructure and Transport BIDDING DOCUMENT. For. Construction of Railway Track Bed

Ministry of Physical Infrastructure and Transport BIDDING DOCUMENT. For. Construction of Railway Track Bed Government of Nepal Ministry of Physical Infrastructure and Transport Department of Railways Rail and Metro Development Project Battisputali, Kathmandu BIDDING DOCUMENT For Construction of Railway Track

More information

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS Issuance Date: July 1, 2013 The Narragansett Electric Company d/b/a National Grid i Table of Contents I. Introduction and Overview...1

More information

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis:

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis: Java Bali 500-Kilovolt Power Transmission Crossing Project (RRP INO 42362) FINANCIAL ANALYSIS 1. General Methodology. Financial analysis of the project has been undertaken in accordance with Asian Development

More information

REGULATION OF BANK INDONESIA NUMBER 19/8/PBI/2017ON NATIONAL PAYMENT GATEWAY BY THE BLESSINGS OF THE ALMIGHTY GOD GOVERNOR OF BANK INDONESIA,

REGULATION OF BANK INDONESIA NUMBER 19/8/PBI/2017ON NATIONAL PAYMENT GATEWAY BY THE BLESSINGS OF THE ALMIGHTY GOD GOVERNOR OF BANK INDONESIA, UNOFFICIAL TRANSLATION REGULATION OF BANK INDONESIA NUMBER 19/8/PBI/2017ON NATIONAL PAYMENT GATEWAY BY THE BLESSINGS OF THE ALMIGHTY GOD GOVERNOR OF BANK INDONESIA, Considering : a. that to realize smooth,

More information

The development of offshore wind - The case of Denmark

The development of offshore wind - The case of Denmark 9 February 2017 The development of offshore wind - The case of Denmark Camilla Holbech, Deputy Manager Danish Wind Industry Association Zooming in on the Danish wind industry More than 30,000 employees

More information

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS BRIEFING GREEK RENEWABLES SUPPORT SCHEME PROPOSALS MARCH 2016 BRIEF OUTLINE OF THE SCHEME PHOTOVOLTAIC PROJECTS TRANSITIONAL PROVISIONS NON-INTERCONNECTED ISLANDS COMPETITIVE BIDDING PROCESS FROM 2017

More information

Attachment B: Examples. Auction Notice California Cap-and-Trade Program and Québec Cap-and-Trade System Joint Auction of Greenhouse Gas Allowances

Attachment B: Examples. Auction Notice California Cap-and-Trade Program and Québec Cap-and-Trade System Joint Auction of Greenhouse Gas Allowances Attachment B: Examples Auction Notice California Cap-and-Trade Program and Québec Cap-and-Trade System Joint Auction of Greenhouse Gas Allowances This attachment provides information and examples of how

More information

The following words and terms shall have the following meanings when used in this Tariff:

The following words and terms shall have the following meanings when used in this Tariff: Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

Armstrong South East Asia Clean Energy Fund LP

Armstrong South East Asia Clean Energy Fund LP Armstrong South East Asia Clean Energy Fund LP Solar Energy South East Asia Financing Small Power Projects 26 th November 2014 Fund Executive Summary Sector focus Fund premise & rationale Growing energy

More information

Key lessons from South Africa s Renewable Energy IPP Programme

Key lessons from South Africa s Renewable Energy IPP Programme Key lessons from South Africa s Renewable Energy IPP Programme Management Program in Infrastructure Reform and Regulation University of Cape Town Competitive tenders for RE IPPs 2011 DoE issued RfP for

More information

Ceiling Price: The procurement ceiling price of $ per kilowatt-hour ( kwh ), as established in 225 C.M.R (3)(a)4.

Ceiling Price: The procurement ceiling price of $ per kilowatt-hour ( kwh ), as established in 225 C.M.R (3)(a)4. REQUEST FOR PROPOSALS FOR THE 100 MEGAWATT COMPETITIVE PROCUREMENT UNDER THE SOLAR MASSACHUSETTS RENEWABLE TARGET ( SMART ) PROGRAM Issued November 13, 2017 1. INTRODUCTION Pursuant to regulations promulgated

More information

BANK INDONESIA REGULATION NUMBER: 6/2/PBI/2004 CONCERNING THE BANK INDONESIA - SCRIPLESS SECURITIES SETTLEMENT SYSTEM (BI-SSSS)

BANK INDONESIA REGULATION NUMBER: 6/2/PBI/2004 CONCERNING THE BANK INDONESIA - SCRIPLESS SECURITIES SETTLEMENT SYSTEM (BI-SSSS) BANK INDONESIA REGULATION NUMBER: 6/2/PBI/2004 CONCERNING THE BANK INDONESIA - SCRIPLESS SECURITIES SETTLEMENT SYSTEM (BI-SSSS) THE GOVERNOR OF BANK INDONESIA, Considering: a. whereas to assist the Government

More information

Government of Nepal Ministry of Physical Infrastructure and Transport. Department of Railways. Battisputali, Kathmandu BIDDING DOCUMENT.

Government of Nepal Ministry of Physical Infrastructure and Transport. Department of Railways. Battisputali, Kathmandu BIDDING DOCUMENT. Government of Nepal Ministry of Physical Infrastructure and Transport Department of Railways Battisputali, Kathmandu BIDDING DOCUMENT For Construction of Office Building for Department of Railways Medium

More information

Renewable Energy Guidance

Renewable Energy Guidance NewClimate Institute, Verra Renewable Energy Guidance Guidance for assessing the greenhouse gas impacts of renewable energy policies May 2018 How to describe the policy or action being assessed 5. DESCRIBING

More information

Pilot tender for solar PV.

Pilot tender for solar PV. Pilot tender for solar PV www.ens.dk/en/solarpv Page 1 Agenda 14.00 14.15 Welcome and short introduction Morten Bæk, Director General of the Danish Energy Agency 14.15 15.00 Presentation of the Danish

More information

THE PRESIDENT OF THE REPUBLIC OF INDONESIA,

THE PRESIDENT OF THE REPUBLIC OF INDONESIA, THE PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 76/2007 REGARDING THE CRITERIA AND ESTABLISHMENT OF CLOSED BUSINESS LINE AND OPEN BUSINESS WITH CONDITIONS IN RESPECT OF CAPITAL INVESTMENT

More information

Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company

Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company Bidding Rules for the Auctions Under the Competitive Bidding Process of Ohio Power Company CBP Rules Contents Contents Contents... i ARTICLE I. Introduction...1 I.1. Background...1 I.2. Overview...1 ARTICLE

More information

MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA

MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA COPY REGULATION OF THE MINISTER OF FINANCE NUMBER 5/PMK.02/2013 CONCERNING PROCEDURES FOR THE DEPOSIT OF NON TAX GOVERNMENT REVENUE FROM DIVIDENS BY THE GRACE OF GOD ALMIGHTY THE MINISTER OF FINANCE, Considering

More information

microfit RULES Version 1.6 December 8, 2010

microfit RULES Version 1.6 December 8, 2010 microfit RULES Version 1.6 December 8, 2010 Ontario Power Authority, 2010 RULE CHANGE (May 19, 2010) IN-SERIES METERING IS NO LONGER PERMITTED UNDER THE microfit RULES. In-series metering is no longer

More information

Tamil Nadu Energy Development Agency

Tamil Nadu Energy Development Agency Tamil Nadu Energy Development Agency Rate contract tender for empanelment of vendors for supply, installation and commissioning of cumulative capacity of 100MW Grid Connected Rooftop Solar PV power plants

More information

Terms of Participation in Auctions for Government Securities Distributors

Terms of Participation in Auctions for Government Securities Distributors Terms of Participation in Auctions for Government Securities Distributors The classification of government securities distributors applies to those bidders eligible to participate directly in the tender

More information

OJK: Foreign capital in insurance industry complies with the law

OJK: Foreign capital in insurance industry complies with the law OJK: Foreign capital in insurance industry complies with the law Discussion with the Supervising Deputy Commissioner of the Non-Bank Financial Industry (NBFI) of the Financial Service Authority, Edy Setiadi.

More information

LOCAL CONTENT. Brazil Petroleum

LOCAL CONTENT. Brazil Petroleum LOCAL CONTENT Brazil Petroleum The project 1 - background Resource-rich countries are increasingly inserting requirements for local content ( local content provisions ) into their legal framework, through

More information

REPUBLIC OF KENYA LAKE VICTORIA SOUTH WATER SERVICES BOARD LAKE VICTORIA WATER SUPPLY AND SANITATION PROGRAM PHASE TWO (LVWATSAN II)

REPUBLIC OF KENYA LAKE VICTORIA SOUTH WATER SERVICES BOARD LAKE VICTORIA WATER SUPPLY AND SANITATION PROGRAM PHASE TWO (LVWATSAN II) REPUBLIC OF KENYA LAKE VICTORIA SOUTH WATER SERVICES BOARD LAKE VICTORIA WATER SUPPLY AND SANITATION PROGRAM PHASE TWO (LVWATSAN II) Tender for Supply and Delivery of 7 No. Tractors Through National Competitive

More information

COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 76/PMK.03/2013 CONCERNING

COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 76/PMK.03/2013 CONCERNING COPY REGULATION OF THE MINISTER OF FINANCE NUMBER 76/PMK.03/2013 CONCERNING LAND AND BUILDING TAX ADMINISTRATION OF MINING SECTOR FOR OIL, NATURAL GAS, AND GEOTHERMAL MINING BY THE GRACE OF GOD ALMIGHTY

More information

Contents. Section 2: Tax credits for environment industry activities

Contents. Section 2: Tax credits for environment industry activities Contents Section 1: Definitions Article 1: Definitions Section 2: Tax credits for environment industry activities Article 2: Tax credit rate Article 3: Procedures to take advantage of this tax credit Section

More information

RE Growth Enrollment and Tariff Overview

RE Growth Enrollment and Tariff Overview RE Growth Enrollment and Tariff Overview Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Presentation

More information

MINUTES OF THE 2ND PRE-BID MEETING

MINUTES OF THE 2ND PRE-BID MEETING MINUTES OF THE 2ND PRE-BID MEETING NIT. : 08/SE(Elec)/TTD/TPT/2015-16 Name of work : Design, Engineering, Supply, Installation, Testing & Commissioning of 10 MWp grid based solar PV power plant with single

More information

NIT FOR TENDER NO. CGI 0949 P19

NIT FOR TENDER NO. CGI 0949 P19 NIT FOR TENDER NO. CGI 0949 P19 OIL INDIA LIMITED (A Government of India Enterprise) Pipeline Headquarters P. O. Udayan Vihar, Guwahati-781171, Assam, India E mail: ellora@oilindia.in E-Tender OIL INDIA

More information

TERMS OF PARTICIPATION IN AUCTIONS FOR GOVERNMENT SECURITIES DISTRIBUTORS

TERMS OF PARTICIPATION IN AUCTIONS FOR GOVERNMENT SECURITIES DISTRIBUTORS Bank of Canada EFFECTIVE 13 DECEMBER 2005 TERMS OF PARTICIPATION IN AUCTIONS FOR GOVERNMENT SECURITIES DISTRIBUTORS The classification government securities distributor, applies to those bidders eligible

More information

RECONSTRUCTION AND DEVELOPMENT

RECONSTRUCTION AND DEVELOPMENT Public Disclosure Authorized CONFRORMED COPY LOAN NUMBER 7905-ID Public Disclosure Authorized Project Agreement (Additional Financing for the Extended Deployment of the Enterprise Resource Planning System

More information

REGULATIONS FOR INVESTMENTS IN ELECTRICITY NETWORKS IN NIGERIA 2015

REGULATIONS FOR INVESTMENTS IN ELECTRICITY NETWORKS IN NIGERIA 2015 REGULATIONS FOR INVESTMENTS IN ELECTRICITY NETWORKS IN NIGERIA 2015 REGULATION NO: NIGERIAN ELECTRICITY REGULATORY COMMISSION In exercise of its powers to make Regulations conferred by Section 96 (1) &

More information

DETERMINING AN ENTITY S BID GUARANTEE...

DETERMINING AN ENTITY S BID GUARANTEE... Auction Examples California Cap-and-Trade Program and Québec Cap-and-Trade System Joint Auction of Greenhouse Gas Allowances Updated on September 14, 2018 TABLE OF CONTENTS I. BACKGROUND... 1 II. DETERMINING

More information

Agenda item 18: Policies on the formal replenishment process

Agenda item 18: Policies on the formal replenishment process Page 10 Also requests the Secretariat to take into account in developing the terms of reference of the procedure: (i) (ii) The need for the assets of the GCF to be covered by the appropriate privileges

More information

Subject to Legal Review for Accuracy, Clarity and Consistency. I have the honor to acknowledge your letter [of this date], which reads as follows:

Subject to Legal Review for Accuracy, Clarity and Consistency. I have the honor to acknowledge your letter [of this date], which reads as follows: Dear Minister : I have the honor to acknowledge your letter [of this date], which reads as follows: In connection with the signing [on this date] of the Trans-Pacific Partnership Agreement (TPP Agreement),

More information

II. On the Definition - Supplement definitions as follows:

II. On the Definition - Supplement definitions as follows: II. On the Definition - Supplement definitions as follows: Fair Price of CTRA Share Purchase : means fair price per share of CTRA, to be purchased by CTRA from the shareholders disapproving the decision

More information

Second Quarter 2018 Ended September 30, 2017 Earnings Presentation

Second Quarter 2018 Ended September 30, 2017 Earnings Presentation India s first private grid connected MW solar plant India s first distributed rooftop solar project over one megawatt Pan India portfolio of solar assets in 22 States Issued India s first solar Green Bond

More information

GOVERNMENT OF THE NORTHWEST TERRITORIES (GNWT) SHORT-FORM REQUEST FOR PROPOSALS

GOVERNMENT OF THE NORTHWEST TERRITORIES (GNWT) SHORT-FORM REQUEST FOR PROPOSALS GOVERNMENT OF THE NORTHWEST TERRITORIES (GNWT) SHORT-FORM REQUEST FOR PROPOSALS Short-Form Request for Proposals This document contains general instructions and terms and conditions that apply to the Short-Form

More information

Economic and financial feasibility of PV projects

Economic and financial feasibility of PV projects Economic and financial feasibility of PV projects Monika BIERI Research Associate Solar Energy Research Institute of Singapore (SERIS) National University of Singapore (NUS) SERIS INDUSTRY DAY on PV Quality

More information

Legal Regulations on National Promotion for the Use of Sources of Renewable Energy to Generate Electric Power. Issue of the Regulations of Act

Legal Regulations on National Promotion for the Use of Sources of Renewable Energy to Generate Electric Power. Issue of the Regulations of Act ELECTRIC POWER Decree 531/2016 Legal Regulations on National Promotion for the Use of Sources of Renewable Energy to Generate Electric Power. Issue of the Regulations of Act 27191. In Buenos Aires, on

More information

WITH THE BLESSING OF GOD ALMIGHTY THE BOARD OF COMMISSIONERS OF FINANCIAL SERVICES AUTHORITY,

WITH THE BLESSING OF GOD ALMIGHTY THE BOARD OF COMMISSIONERS OF FINANCIAL SERVICES AUTHORITY, UNOFFICIAL TRANSLATION Disclaimer: this document is an unofficial English translation of the original Indonesian text of Financial Services Authority Regulation Number 13/POJK.03/2017 concerning The Use

More information

Morocco s experience in financing solar projects

Morocco s experience in financing solar projects Morocco s experience in financing solar projects February 5, 2019 1 Morocco s Energy Strategy 2 RENEWABLE ENERGIES, AT THE HEART OF MOROCCO S ENERGY STRATEGY Strong will of increasing renewable energy

More information

Legal developments in offshore wind energy in the Netherlands; part 5

Legal developments in offshore wind energy in the Netherlands; part 5 Energy Legal developments in offshore wind energy in the Netherlands; part 5 Introduction Just before the summer recess of Parliament important progress has been made with respect to the preparation for

More information

TRANSFER PRICING DOCUMENTATION IN POLAND

TRANSFER PRICING DOCUMENTATION IN POLAND T A X TRANSFER PRICING DOCUMENTATION IN POLAND 2018 Advicero Tax Sp. z o.o. All rights reserved. TABLE OF CONTENTS INTRODUCTION... 3 KEY AMENDMENTS IN TRANSFER PRICING REGULATIONS... 3 WHEN COMPANIES /

More information

NO. DOCUMENT IN PLACE OF PLEASE READ AS

NO. DOCUMENT IN PLACE OF PLEASE READ AS Contract KE/SPV-01: Design, Engineering, Manufacture, Supply, Storage Civil work, Erection, Testing & Commissioning of the Rooftop Solar PV project including Operation and Comprehensive Maintenance (O&M)

More information

SOLAR ENERGY CORPORATION OF INDIA LIMITED DRAFT 1000 MW GRID CONNECTED ROOF TOP SOLAR PV SCHEME FOR GOVERNMENT BUILDINGS UNDER CAPEX AND RESCO MODELS

SOLAR ENERGY CORPORATION OF INDIA LIMITED DRAFT 1000 MW GRID CONNECTED ROOF TOP SOLAR PV SCHEME FOR GOVERNMENT BUILDINGS UNDER CAPEX AND RESCO MODELS SOLAR ENERGY CORPORATION OF INDIA LIMITED DRAFT 1000 MW GRID CONNECTED ROOF TOP SOLAR PV SCHEME FOR GOVERNMENT BUILDINGS UNDER CAPEX AND RESCO MODELS 1000 MW GRID CONNECTED ROOF TOP SOLAR PV SYSTEM SCHEME

More information

FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS

FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS INDONESIA INFRASTRUCTURE GUARANTEE FUND (IIGF) FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS United Nations Economic And Social Commission For Asia And

More information

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT CONFORMED COPY LOAN NUMBER 7971-BY Loan Agreement (Road Upgrading and Modernization Project) between REPUBLIC OF BELARUS and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Dated November 19, 2010

More information

Loan Agreement LOAN NUMBER 8714-ID. (Regional Infrastructure Development Fund Project) between REPUBLIC OF INDONESIA. and

Loan Agreement LOAN NUMBER 8714-ID. (Regional Infrastructure Development Fund Project) between REPUBLIC OF INDONESIA. and Public Disclosure Authorized OFFICIAL DOCUMENTS LOAN NUMBER 8714-ID Public Disclosure Authorized Loan Agreement Public Disclosure Authorized (Regional Infrastructure Development Fund Project) between REPUBLIC

More information

Questions Answers. Numerous answers have been provided to questions (a), (b), (c) and (d) please, consult the previous replies.

Questions Answers. Numerous answers have been provided to questions (a), (b), (c) and (d) please, consult the previous replies. Questions Answers 1. Please confirm whether the certificate, confirming the content of Form F, Part 1, Schedule 3 from the Tender Documentation, shall be in a pre-approved template form. No, there is no

More information

Instructions to Bidders DATA SHEET

Instructions to Bidders DATA SHEET Instructions to Bidders DATA SHEET The following data for the supply of goods and related services shall complement / supplement the provisions in the Instruction to Bidders. In the case of a conflict

More information

MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA INDONESIA CAPITAL MARKET AND FINANCIAL INSTITUTIONS SUPERVISORY AGENCY COPY OF

MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA INDONESIA CAPITAL MARKET AND FINANCIAL INSTITUTIONS SUPERVISORY AGENCY COPY OF MINISTRY OF FINANCE OF THE REPUBLIC OF INDONESIA Unofficial Translation INDONESIA CAPITAL MARKET AND FINANCIAL INSTITUTIONS SUPERVISORY AGENCY COPY OF REGULATION OF THE CHAIRPERSON OF INDONESIA CAPITAL

More information

STATE ENERGY PROGRAM GOVERNMENT OF PUERTO RICO

STATE ENERGY PROGRAM GOVERNMENT OF PUERTO RICO COMMONWEALTH OF PUERTO RICO STATE OFFICE OF ENERGY POLICY GREEN ENERGY FUND Tier 1 Reference Guide (Revised on August 17, 2017) STATE ENERGY PROGRAM GOVERNMENT OF PUERTO RICO TABLE OF CONTENTS CHAPTER

More information

New Development Bank s 2016 Green Financial Bond Duration Assurance

New Development Bank s 2016 Green Financial Bond Duration Assurance Appendix I New Development Bank s 2016 Green Financial Bond Duration Assurance Description of the use of proceeds (Reporting Period: 1 January 2017 18 July 2018) In accordance with The Announcement on

More information

Polish model of Capacity Market

Polish model of Capacity Market Polish model of Capacity Market As of 18 January 2018, the Act of 8 December 2017 on capacity market ( Act ) has entered into force. The aims of the Act are: (c) (d) to introduce incentives for construction

More information

13. What banking business in foreign currency is permitted to use foreign currency?

13. What banking business in foreign currency is permitted to use foreign currency? FREQUENTLY ASKED QUESTIONS BANK INDONESIA CIRCULAR NO. 17/11/DKSP /DKSP DATED 1 JUNE 2015 CONCERNING MANDATORY USE OF RUPIAH WITHIN THE TERRITORY OF THE REPUBLIC OF INDONESIA A. GENERAL REVIEW 1. What

More information

International Conference on Information Systems for Business Competitiveness (ICISBC 2013) 211

International Conference on Information Systems for Business Competitiveness (ICISBC 2013) 211 International Conference on Information Systems for Business Competitiveness (ICISBC 2013) 211 Decision Support System for Evaluation Procurement of Goods with Simple Additive Weighting Method (SAW) Fajar

More information

Official Journal of the European Union

Official Journal of the European Union 13.5.2014 L 138/5 COMMISSION DELEGATED REGULATION (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions

More information

Gujarat State Project Management Unit (SPMU) ICZM Project Gujarat Ecology Commission, Gandhinagar

Gujarat State Project Management Unit (SPMU) ICZM Project Gujarat Ecology Commission, Gandhinagar Gujarat State Project Management Unit (SPMU) ICZM Project Gujarat Ecology Commission, Gandhinagar National Competitive Bidding for Supply & Installation of Solar Renewable Energy Applications and Related

More information

West Bengal Renewable Energy Development Agency

West Bengal Renewable Energy Development Agency West Bengal Renewable Energy Development Agency (An organization of Department of Power and NES Government of West Bengal) BIKALPA SHAKTI BHAVAN, Plot J1/10, Block EP & GP, Sector V, Salt Lake Electronics

More information

Boosting Infrastructure Financing through Risk Mitigation Instruments

Boosting Infrastructure Financing through Risk Mitigation Instruments Boosting Infrastructure Financing through Risk Mitigation Instruments Financing Sources for Public-Private Partnerships Forum Kuala Lumpur, 25 November 2015 Dr Armand Hermawan CFO Indonesia Infrastructure

More information

4.2 Definitions In this Clause 4 and Schedule E the following terms shall have the meanings ascribed to them below:-

4.2 Definitions In this Clause 4 and Schedule E the following terms shall have the meanings ascribed to them below:- 4. BLACK START CAPABILITY [Note: this clause will need substantial amendment to reflect the circumstances of any individual case, for example the type of Black Start Plant, use of distillate fuel, whether

More information

Tamil Nadu Energy Development Agency

Tamil Nadu Energy Development Agency Tamil Nadu Energy Development Agency Rate contract tender for empanelment of vendors for supply, installation and commissioning of cumulative capacity of 100MW Grid Connected Rooftop Solar PV power plants

More information

Terms of Reference (ToR)

Terms of Reference (ToR) Terms of Reference (ToR) for the procedure of tender awarding under the tender procedure named: Delivery of glycols (No. 4P/POIR.0142/2018) as part of the Intelligent Development Operational Program, 2014-2020

More information

EU FUNDS AFTER THE ACCESSION TO THE EUROPEAN UNION - TOWARDS A NEW FINANCIAL PERSPEKTIVE

EU FUNDS AFTER THE ACCESSION TO THE EUROPEAN UNION - TOWARDS A NEW FINANCIAL PERSPEKTIVE EU FUNDS AFTER THE ACCESSION TO THE EUROPEAN UNION - TOWARDS A NEW FINANCIAL PERSPEKTIVE PPT Title: Good practice examples and experiences from Lithuania Viktoras Sirvydis, Resident Twinning Adviser EU

More information

Minister of Trade of the Republic of Indonesia REGULATION OF THE MINISTER OF TRADE OF THE REPUBLIC OF INDONESIA NUMBER : 45/M-DAG/PER/9/2009

Minister of Trade of the Republic of Indonesia REGULATION OF THE MINISTER OF TRADE OF THE REPUBLIC OF INDONESIA NUMBER : 45/M-DAG/PER/9/2009 Minister of Trade of the Republic of Indonesia REGULATION OF THE MINISTER OF TRADE OF THE REPUBLIC OF INDONESIA NUMBER : 45/M-DAG/PER/9/2009 CONCERNING IMPORTER IDENTITY NUMBER (API) BY THE GRACE OF GOD

More information

Law on Privatization I. BASIC PROVISIONS. 1. Subject of the Law and General Principles. 2. Scope of privatization and entities to be privatized

Law on Privatization I. BASIC PROVISIONS. 1. Subject of the Law and General Principles. 2. Scope of privatization and entities to be privatized Law on Privatization (Official Gazette of the RS", No. 38/2001, 18/2003 and 45/2005 ) I. BASIC PROVISIONS 1. Subject of the Law and General Principles Article 1. This law governs the conditions and the

More information

Authorized Translation CHAIRMAN OF INVESTMENT COORDINATING BOARD REPUBLIC OF INDONESIA

Authorized Translation CHAIRMAN OF INVESTMENT COORDINATING BOARD REPUBLIC OF INDONESIA CHAIRMAN OF INVESTMENT COORDINATING BOARD REPUBLIC OF INDONESIA COPY REGULATION OF THE CHAIRMAN OF INVESTMENT COORDINATING BOARD REPUBLIC OF INDONESIA NUMBER 19 OF 2015 ON AMENDMENT ON REGULATION OF THE

More information

Corrigendum No. 2 to Standard Tender Document (Schedule III Coal Mines) (For iron and steel, cement and captive power plant sector)

Corrigendum No. 2 to Standard Tender Document (Schedule III Coal Mines) (For iron and steel, cement and captive power plant sector) Corrigendum 2 to Standard Tender (Schedule III Coal Mines) (For iron and steel, cement and captive power plant sector) Date: February 10, 2015 1. The amendments/ additions mentioned in a. Corrigendum to

More information