PT Paiton Energy A Case Study in Renegotiation

Size: px
Start display at page:

Download "PT Paiton Energy A Case Study in Renegotiation"

Transcription

1 PT Paiton Energy A Case Study in Renegotiation Session on Yong Hee Kong PPP Resource & Research Centre, Kuala Lumpur PT Paiton During Construction 1

2 PT Paiton Energy (almost complete) Pt Paiton Energy - PE or the Project is a US$ 2.7 billion fully complete and commissioned 1,230 MW (2 x 650 MW) coal-fired base load power plant, located on the Northeast coast of Java, Indonesia. Background to IPP 1990, GOI introduced IPP policy (World Bank, etc.) May (plus 2, later in Sept 1991) companies bid for Units 7 & 8 Units 1 & 2 - PLN, Units 3, 4, 5 and 6 - future IPPs June Award to BMMG Consortium (BHP, Edison Mission Energy, Mitsui, GE Capital) 1994 (after 21 months of negotiation) PT Paiton Energy and PLN executed PPA PLN advised by international advisers - Lazard, Warburg, Lehman, Lahmeyer, USAID 2

3 Background to IPP (continued) Tariffs were in USD COD (Commercial Operations Dates) - May and July 1999 Rp devalued during turmoil caused by fall of Suharto Also, demand fell due to economic crisis PLN declined to dispatch plant for several months PE and PLN sued each other. President Habibie ordered parties back to negotiating table in November 1999 New PPA agreed by PLN and PE in December 2001 Original Tariff Structure Four components A - capacity charge B - fixed op/maintenance charge C - coal fuel charge ( pass-through ) D - variable operation/ maintenance charge Components C & D vary depending on electricity generated Component A was scheduled to step-down over time as senior long-term debt was amortized. It had common facilities for sharing with future IPP on same site. 3

4 Tariffs (continued) Costs included building common infrastructure facilities that would be shared with the other units eventually Component A (of the Tariffs) is projected as follows: Years 1-6 Rupiah eqv of 6.12 cents/kwh Years 7-12 Rupiah eqv of 5.97 cents/kwh Years Rupiah eqv of 3.10 cents/kwh GOI wanted a front-loaded tariff to lower the cost of power in later years Projected ave total tariff Rupiah eqv 6.3 cents/kwh FSA - Coal Supply Agreement Lenders insisted on assurances on ample coal supply 1995 Coal-Supply Agreement signed with PT Adaro Indonesia, a subsidiary of BHP - advised by international experts. Main terms: Single source coal supplier Dedicated reserves for 15 years, at all times Dedicated stockpile of 200,000 tonne at Kelanis bargeloading facility Dedicated fleet of tugs and barges from Kelanis to Indonesia Bulk Terminal (IBT) facility 2 dedicated Handymax vessels to transport from IBT to Paiton site Plant stockpile of 670,000 tonnes capacity 4

5 Original Coal Supply Chain Why Renegotiation Was Necessary Rp tumbled. (exchange rate dropped from 2450 to 7400 USD) PLN s revenue was in Rp. (USD equivalent tariff dropped from 7 cents to 2 cents per KWh) PLNs demand collapse temporarily due to 1997 financial crisis GOI was called to help but PLN s position because untenable. 5

6 Why Renegotiation Was Necessary (continued) PLN refused to used Paiton for dispatching Under the terms of Paiton s financing documents, PE was forced to go to court. PLN also sought to declare Paiton PPA null and void. When Habibie came into power in November 1999, he sought an amicable solution to this problem. Group Discussion (10 minutes) How would you advise on: What PLN and IPP should do? (Should IPP dispatch/ supply power during negotiation? Should GOI not honour their Letter of Comfort? Should IPP continue to sue PLN and GOI? Should PLN sue for unfair PPA?) The tariff structure and rates? The fuel supply chain (and its rates)? The way to negotiate? 6

7 Restructuring the PPA November PLN and PE began negotiation. February First interim agreement. (PLN agrees to pay for actual cost of energy dispatched plus a small amount for capacity charge) (insufficient) January Second Interim Agreement (increased amount for capacity charge) (sufficient to cover opex and interest) December Commercial Agreement on pricing, arrearages and related provisions of PPA. Binding Term Sheet (BTS) prepared. BTS - Four Parts to It (Both parties agree to abide) 1. Standstill of all legal proceedings 2. Confidentiality of ongoing discussions 3. Agreed-upon commercial issues (including changes to PPA) 4. BTS implementation plan (deadline - 31 March 2002) 7

8 Broad Re-Structured Terms Terms extended from 30 to 40 years Component A (capacity charge) - no longer step-down, now constant. Resultant tariff 30% lower Component C (coal fuel charge) - CIF cost at jetty Coal Supply Chain restructured Restructuring the Coal Supply Chain By 1999, Adaro s coal was USD 10 per tonne higher due mainly to its supply chain Main coal-supply chain restructuring actions: Remove need for dedicated reserves Remove stockpile requirement Remove restrictions of dedicated tugs/barges Remove need for intermediate storage at IBT Eliminate Handymax vessels Multi-source supplies (Adaro now provides 60%-70%) 8

9 Restructured Coal Supply Chain 9

10 Lessons Learnt - Appropriate Risk Allocation for IPP Projects in Today's Environment Host government s risks : Changes in currency risks (devaluing Rp) Demand and supply (crisis reduced demand) Changes in law (political decisions and contractsanctity - honour all agreements) Force majeure (those in control of government) Inconvertibility (of currency USD/Rp) Transmission network Allocation of Risks - IPP s Risks Construction (turnkey) Financing (answerable to financiers) Fuel supply (cost pass-through - any incentives to reduce costs?) O & M Capex Investment 10

11 The Paiton Paradigm Historical: The original financing was a groundbreaking transaction, evidenced by over 15 awards. Complexity: The restructuring involves an extremely complex network of parties consisting of 3 key sponsors, PLN/Gov t of Indonesia, 2 major export credit agencies, 2 bilateral agencies, 36 international commercial banks, bondholders and other project parties. Size: The US$ 2.7 billion project remains a benchmark for non-recourse transactions globally. Coming in the wake of the Indonesian macroeconomic crisis, so too is the project's restructuring; The Paiton Paradigm (continued) Management and Process: The project was exemplary in the management of the complex co-ordination process required to find consensus among an extremely diverse group of project stakeholders making full use of transparency, engagement and communication (i.e. the restructuring website); Approach: This restructuring represents a ground-breaking example of consensus-based restructuring of non-recourse project debt through equitable burden sharing among key project parties with the clear intention to achieve stakeholders' restructuring goals; and 11

12 The Paiton Paradigm (continued) Results: The project achieved a sustainable long term restructuring solution for all parties: (1) no principle haircuts to debt or equity; and (2) a sustainable tariff for long-term contractual stability. Transaction Overview Background: The project is a 1,230 MW coal-fired base load power plant fully completed and commissioned on the Northeast coast of Java, Indonesia. The project is 40% owned by a subsidiary of Edison Mission Energy; 32.5% by a subsidiary of Mitsui & Co., Ltd.; 12.5% by a limited partnership affiliated with and managed by General Electric Capital Corporation, and 15% through a loan to PT Batu Hitam Perkasa (collectively the sponsors"). 12

13 Transaction Overview (continued) History: The financing of the project was closed in 1995 with a total debt package of US$ 1.8 billion. A bond tranche was subsequently added in Lenders and guarantors/insurers include USEXIM, JBIC, OPIC and NEXI (the agencies"), a syndicate of 36 international commercial banks and a syndicate of bondholders. Transaction Overview (continued) Restructuring: Principal was originally scheduled to commence amortizing in November However, due to the Indonesian macroeconomic crisis and its effects on power demand in Indonesia, cashflow was below the original projections. Hence, the project and its stakeholders entered into restructuring negotiations. During this period, interest was kept current through a combination of interim payments from PLN and in large part to the sponsors' contribution of US $ 240 million of contingent equity in

14 Restructuring Overview No haircut of debt or equity Principles: The debt restructuring process for the USD 1.8 billion of non-recourse project debt formally began in October 2001 and was based on the key principle that there would be no haircut to debt or equity. The project's proposal to the lenders, agreed to in principle by the agencies on 24 September 2002 was for a 2-year extension of the original maturity date of the agencies' tranches and a re-setting by the agencies of their interest rates to current benchmark levels. Restructuring Overview (continued) No haircut of debt or equity (2) Outcome: All the agencies agreed to the commercial terms of the debt restructuring and the deal was then presented to the commercial banks on 8 October The approval of all commercial banks was received. The restructuring documentation was signed in December 2002, CP's were then met and the restructuring closed on 14 February 2003 with the entry of USEXIM. 14

15 Restructuring Overview (continued) USEXIM dept participation USEXIM commitment: A key element and major achievement, of the debt restructuring was USEXIM's ability to apply a "risk-sharing" concept to the commercial banks. The result was a USEXIM "take-out" of 75% or US$ 381 million (USEXIM A tranche) of the US$ 508 million USEXIM construction facility, leaving the commercial banks with a residual exposure of US$ 127 million (USEXIM B tranche). This was a one hundred cents on the dollar takeout for 75% of the exposure. Restructuring Overview (continued) No back-ending of amortization for commercial banks Commercial bank amortization: The commercial bank residual exposure was divided on a pro-rata basis among the 36 banks in the syndicate and has a straight line amortization (therefore no principal back-ending) with a maturity matching the JBIC B tranche. Agency amortization: Agencies agreed to a back-ended amortization profile enabling the commercial banks to retain their original amortization profile. 15

16 What Caused the Paiton Restructuring? The original debt profile: OECD consensus agreement requirements delivered a tariff that was not politically defensible; The lenders requirement for certainty in the fuel chain: created an expensive fuel cost; Public tariff of PLN was heavily subsidized creating a politically sensitive gap with private power tariffs; Debt profile was based on projections of demand, not actuals; The US$ debt/ Rp. Cashflow mismatch with a mitigation structure based on legal mitigation rather than project logic. Original Coal Supply Chain 16

17 Restructured Coal Supply Chain Paiton was needed to be operational by the government - 17

18 Debt Structure Pre-Restructuring Debt Structure Post-Restructuring 18

19 Burden-Sharing and Win-Win Are Important Principles Burden sharing was allocated equitably among the stakeholders, creating a win-win scenario: Sponsors injected US $ 240 million of contingent equity to keep interest current and cover project costs; Sponsors agreed to accept a lower return; PLN agreed to pay for arrears payments with no change to risk allocations under the PPA; Coal supply chain counter-parties agreed to terminate/renegotiate their contracts; Burden-Sharing & Win-Win Are Important (continued) Burden sharing was allocated equitably among the stakeholders, creating a win-win scenario: (continued) EPC contractor agreed to release care, custody and control of the plant to allow the project to dispatch electricity, to reduce its claims and paid over time; Agencies agreed to reduce interest rates and to backend their debt USEXIM agreed to participate in the debt; Commercial banks agreed to an interim principal deferral and then accept risk sharing with USEXIM; and The project accepted the expense, in time and effort, to execute a sustainable restructuring platform to a professional "best practices" standard. 19

20 Debt Restructuring Process The restructuring process entailed satisfying the interests of all Project parties, often times in parallel with each other. 20

21 Advisors to the Project Significant advisors Financial Advisor: ABN AMRO Lenders' Engineer: Mott MacDonald Lenders' Fuel Advisor: JTBoyd Lawyers: Skadden Arps (counsel to the project), Latham & Watkins (counsel to the lenders) 21

Boosting Infrastructure Financing through Risk Mitigation Instruments

Boosting Infrastructure Financing through Risk Mitigation Instruments Boosting Infrastructure Financing through Risk Mitigation Instruments Financing Sources for Public-Private Partnerships Forum Kuala Lumpur, 25 November 2015 Dr Armand Hermawan CFO Indonesia Infrastructure

More information

Nigeria Infrastructure Building Conference 2014

Nigeria Infrastructure Building Conference 2014 Nigeria Infrastructure Building Conference 2014 May 2011 Project Finance as a viable option for financing Infrastructure Projects P R E P A R E D B Y: Helen Brume Divisional Head, Power, Infrastructure

More information

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager Developing the Power Sector through Private Investment in Mongolia Edgar Saravia Program Manager October 2008 Setting the Context Government of Mongolia ( GoM ) wishes to introduce PSP in power generation

More information

Electricity Sector Regulatory Developments, Opportunities and Challenges

Electricity Sector Regulatory Developments, Opportunities and Challenges Indonesian Energy and Infrastructure Seminar Electricity Sector Regulatory Developments, Luke Devine Hadiputranto, Hadinoto & Partners is a member of Baker & McKenzie International, a Swiss Verein with

More information

What will be covered today? o o o

What will be covered today? o o o What will be covered today? o o o 2 Project finance is the financing of long-term infrastructure based upon a non-recourse structure. 3 Project finance is about identifying each risk associated with the

More information

FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS

FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS INDONESIA INFRASTRUCTURE GUARANTEE FUND (IIGF) FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS United Nations Economic And Social Commission For Asia And

More information

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis:

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis: Java Bali 500-Kilovolt Power Transmission Crossing Project (RRP INO 42362) FINANCIAL ANALYSIS 1. General Methodology. Financial analysis of the project has been undertaken in accordance with Asian Development

More information

NEWS RELEASE FROM ADARO ENERGY

NEWS RELEASE FROM ADARO ENERGY NEWS RELEASE FROM ADARO ENERGY General Media: For further information please contact: Mr. Andre J. Mamuaya Director and Corporate Secretary Tel: (6221) 521 1265 Fax: (6221) 5794 4687 Email: corpsec@ptadaro.com

More information

1. Introduction. 2. Background. Agenda Item 10.3-Micro Eco Reform-Att A-Ann 3 INDONESIA - ANNEX 3

1. Introduction. 2. Background. Agenda Item 10.3-Micro Eco Reform-Att A-Ann 3 INDONESIA - ANNEX 3 1. Introduction Agenda Item 10.3-Micro Eco Reform-Att A-Ann 3 INDONESIA - ANNEX 3 This Annex sets out our findings in relation to the current status of implementation of the IPP Principles in Indonesia.

More information

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT Sustainable Energy Access in Eastern Indonesia Electricity Grid Development Program (RRP INO 50016) PROGRAM EXPENDITURE AND FINANCING ASSESSMENT 1. The program expenditure and financing assessment reviews

More information

470 Megawatt Power Plant Karachi, Pakistan

470 Megawatt Power Plant Karachi, Pakistan 470 Megawatt Power Plant Karachi, Pakistan Information Memorandum Cavalier Energy Corporation has been awarded a 25 year contract by the Government of Pakistan to Build, Own and Operate a 470 Megawatt

More information

Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria

Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria dentons.com Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria Briefing Note: December 2016 Contacts Dominic Spacie Partner Dentons UKMEA LLP One Fleet

More information

Bringing Clean Energy Projects To Reality: Presentation to the Global Workshop on Clean Energy Development

Bringing Clean Energy Projects To Reality: Presentation to the Global Workshop on Clean Energy Development Bringing Clean Energy Projects To Reality: Presentation to the Global Workshop on Clean Energy Development Bret J. Logue Managing Director, Wellford Energy Group Introduction to the Wellford Energy Group

More information

Project Finance An Overview

Project Finance An Overview Project Finance An Overview KAMAL TAK ICAI, Navi Mumbai Chapter December 16, 2012 1 Project Finance An Overview What is Project Financing? How is it different? How are Projects developed? Various Project

More information

Mong Duong Power Project, the Largest Project Finance Deal in Vietnam - Lessons Learnt and Key Takeaways

Mong Duong Power Project, the Largest Project Finance Deal in Vietnam - Lessons Learnt and Key Takeaways Mong Duong Power Project, the Largest Project Finance Deal in Vietnam - Lessons Learnt and Key Takeaways 1. Introduction Mong Duong Power Project is the Vietnam s biggest IPP now under construction. The

More information

NEWS RELEASE Jakarta, 31 October 2013

NEWS RELEASE Jakarta, 31 October 2013 NEWS RELEASE Jakarta, 31 October 2013 General Media Contact: Devindra Ratzarwin, Corporate Secretary corsec@ptadaro.com Financial Media Contact: Cameron Tough, Head of Investor Relations cameron.tough@ptadaro.com

More information

RABAI POWER. February 24, 2010

RABAI POWER. February 24, 2010 RABAI POWER Aldwych Power developer in Africa Founded in 2004 by management and FMO Current shareholders: PAIDF, FMO, EAIF and management Shareholder in CEC, shareholder/manager Kelvin Largest shareholder

More information

PPP Fiscal Risk Management - The Implementation

PPP Fiscal Risk Management - The Implementation 2011/FMP/CON/017 Session 6 PPP Fiscal Risk Management - The Implementation Submitted by: Indonesia Conference on the Framework and Options for Public and Private Financing of Infrastructure Washington,

More information

PPAs and Tariff Design

PPAs and Tariff Design RENEWABLE ENERGY TRAINING PROGRAM FINANCING RENEWABLE ENRGY PROJECTS PPAs and Tariff Design Bassem Abou Nehme Energy Finance Consultant TWI - Financial Solutions 1 Outline What is a PPA? Structure of PPA

More information

PacifiCorp Utah All Source Request for Proposal 2016 Resource. Issued January 6, 2012 Responses May 9, 2012

PacifiCorp Utah All Source Request for Proposal 2016 Resource. Issued January 6, 2012 Responses May 9, 2012 PacifiCorp Utah All Source Request for Proposal 2016 Resource Issued January 6, 2012 Responses May 9, 2012 TABLE OF CONTENTS Page SECTION 1. INTRODUCTION... 7 SECTION 2. RESOURCE ALTERNATIVES AND PROPOSAL

More information

Petronet LNG Limited A Case Study. Mohit Saraf Senior Partner Luthra & Luthra Law Offices 1

Petronet LNG Limited A Case Study. Mohit Saraf Senior Partner Luthra & Luthra Law Offices 1 Petronet LNG Limited A Case Study Mohit Saraf Senior Partner Luthra & Luthra Law Offices 1 Implementation Methodology Contractual Structure EPC Contractors/ Technology Licenser Sponsors & Other Shareholders

More information

INDEPENDENT POWER PRODUCERS

INDEPENDENT POWER PRODUCERS RATING METHODOLOGY INDEPENDENT POWER PRODUCERS An independent rating opinion on relative ability of an Independent Power Producer to honor financial obligations Content Scope Risk Analysis Completion Risk

More information

RENEWABLE ENERGY PROJECT FINANCING

RENEWABLE ENERGY PROJECT FINANCING RENEWABLE ENERGY PROJECT FINANCING Yiannis Saratsis Head of Project Finance MAY 2018 I. Eurobank & RES financing Eurobank & RES Eurobank remains committed in the financing of Renewable Energy Projects

More information

IPP s Project Risk Classification

IPP s Project Risk Classification IPP has to ensure that under all Project Agreements and Contracts he only bears, as far as possible, those risks within its control. The table below is a summary of relevant risks and mitigating factors

More information

By Director of Various New and Renewable Energy T

By Director of Various New and Renewable Energy T MINISTRY OF ENERGY AND MINERAL RESOURCES OF THE REPUBLIC OF INDONESIA DIRECTORAT GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION By Director of Various New and Renewable Energy T Jakarta, 10 May

More information

Compensatory Tariff Orders and Fine Balancing Act by CERC

Compensatory Tariff Orders and Fine Balancing Act by CERC CARE RESEARCH Compensatory Tariff Orders and Fine Balancing Act by CERC CERC has finally notified the long awaited Compensatory Tariff orders on imported coal based Tata and Adani Mundra projects. With

More information

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects Seminar on African Electrical Interconnection Module 6 - Financing Interconnection Projects Module 6 - Financing Interconnection Projects Contents 1) Major Financing Features 2) Basic Financing Approaches

More information

Compensatory Tariff Orders...A Fine Balancing Act by CERC

Compensatory Tariff Orders...A Fine Balancing Act by CERC Impact Analysis: Compensatory Tariff Orders...A Fine Balancing Act by CERC March 11, 2014 CERC has finally notified the long awaited Compensatory Tariff orders on imported coal based Tata and Adani Mundra

More information

NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT. Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division

NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT. Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division Context Results are based on study of the OECD Nuclear

More information

NEWS RELEASE FROM ADARO ENERGY

NEWS RELEASE FROM ADARO ENERGY NEWS RELEASE FROM ADARO ENERGY General Media: For further information please contact: Mr. Devindra Ratzarwin Corporate Secretary Tel: (6221) 521 1265 Fax: (6221) 5794 4687 Email: corsec@ptadaro.com Financial

More information

renewables Made in Germany Initiative

renewables Made in Germany Initiative renewables Made in Germany Initiative Renewable Energy Sector Indonesia Financing Opportunities and Risk Mitigation Jakarta, November 3rd, 2015 Project Finance International: Dr. Joachim Richter PFI Corporate

More information

Overview of financing energy projects in Thailand

Overview of financing energy projects in Thailand Overview of financing energy projects in Thailand 2004 Cogeneration Week in Thailand 23-25 March 2004 Miracle Grand Convention Hotel, Bangkok Alan Dale Gonzales COGEN 3 Chief Business Adviser 1 OVERVIEW

More information

Power Sector Reform India The Long Road Ahead

Power Sector Reform India The Long Road Ahead Power Sector Reform India The Long Road Ahead Rahul Tongia Department of Engineering & Public Policy/ School of Computer Science University February 19, 2003 2 Outline Overview of the Indian power sector

More information

Perspective on Financing Wind Energy Projects. June 16, 2016

Perspective on Financing Wind Energy Projects. June 16, 2016 Perspective on Financing Wind Energy Projects June 16, 2016 Agenda 2 1 Risk Matrix 3 Context Setting Way Forward KEY SEGMENTS IN THIS PRESENTATION 3 Indian Energy Sector Landscape Bank Lending Sector wise

More information

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to Power Purchase Agreement (PPA) Guidelines Zambia Lusaka August 7 to 11 2017 I. Objective of the PPA Guideline II. Length of the Agreement III. Commissioning Process IV. Sale and Purchase V. PPA Pricing

More information

Cost of Equity (USD)

Cost of Equity (USD) 1 2 3 4 Cost of Equity Best-in-Class Country Power Market Permits Social Acceptance Developer Grid /Transmission Counterparty Financial Sector Political Currency/Macro. Cost of Equity Kazakhstan BAU 1.3%

More information

Due Diligence checklist for [insert project name]

Due Diligence checklist for [insert project name] Due Diligence checklist for [insert project name] Draft February 2016 PricewaterhouseCoopers, ABN 52 780 433 757 Darling Park Tower 2, 201 Sussex Street, GPO BOX 2650, SYDNEY NSW 1171 T: +61 2 8266 0000,

More information

RENEWABLE ENERGY/ENERGY EFFICIENCY AND THE CDM

RENEWABLE ENERGY/ENERGY EFFICIENCY AND THE CDM RENEWABLE ENERGY/ENERGY EFFICIENCY AND THE CDM Break-out Groups Session - Geothermal Dr. Hardiv H Situmeang International Workshop World Bank September 13 14, 2006 The Ballroom, Four Seasons Hotel, Jakarta

More information

ENERGY FOR CHANGE February

ENERGY FOR CHANGE February ENERGY FOR CHANGE February 2018 1 Key questions: What is Adaro Energy guidance for 2018? What is the outlook for coal industry? What is the progress of Adaro Energy s projects? What is Adaro Energy s strategy

More information

The 27th Training Program of Asian Exim Banks Forum (AEBF) on Project Finance

The 27th Training Program of Asian Exim Banks Forum (AEBF) on Project Finance The 27th Training Program of Asian Exim Banks Forum (AEBF) on Project Finance How do ECA/MLA covered structures in PF transactions affect syndication? June 6, 2014 Investment Banking Jun Palanca Regional

More information

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner The policy and regulatory aspects of a bankable solar power project Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner Contents 1. The restriction of subsidies and policy priorities. 2.

More information

DELIVERING ENERGY TO BUILD THE NATION. May

DELIVERING ENERGY TO BUILD THE NATION. May DELIVERING ENERGY TO BUILD THE NATION May 2017 www.adaro.com Disclaimer These materials have been prepared by PT Adaro Energy (the Company ) and have not been independently verified. No representation

More information

IOSCO GEM COMMITTEE CONFERENCE LONG-TERM FINANCING THROUGH CAPITAL MARKETS

IOSCO GEM COMMITTEE CONFERENCE LONG-TERM FINANCING THROUGH CAPITAL MARKETS IOSCO GEM COMMITTEE CONFERENCE LONG-TERM FINANCING THROUGH CAPITAL MARKETS Panel Discussion #2 : Role of Intermediaries in Facilitating Long- Term Financing through Capital Markets Lee K. Kwan Chief Executive

More information

CONFERENCE REPORT BACKGROUND

CONFERENCE REPORT BACKGROUND BACKGROUND Asia Pacific Infrastructure Partnership (APIP) Dialogue with the Government of Indonesia 22 October 2012 * 2:30 pm 5:30 pm Ballroom 3, The Ritz Carlton Jakarta Mega Kuningan, Jakarta, Indonesia

More information

MYPD3 Application January 2013

MYPD3 Application January 2013 MYPD3 Application 2014-2018 January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of any offer

More information

DELIVERING ENERGY TO BUILD THE NATION September

DELIVERING ENERGY TO BUILD THE NATION September DELIVERING ENERGY TO BUILD THE NATION September 2016 www.adaro.com Disclaimer These materials have been prepared by PT Adaro Energy (the Company ) and have not been independently verified. No representation

More information

SAMRA Wastewater Treatment Plant A Major Asset for Jordan

SAMRA Wastewater Treatment Plant A Major Asset for Jordan SAMRA Wastewater Treatment Plant A Major Asset for Jordan 1-Project Overview The water cycle 21/10/2014 Page 2 1-Project Overview - map 1-Project Overview Flows and Loads As Samra WWTP phase I BOT contract

More information

Matthew F. Hilzinger Chief Financial Officer

Matthew F. Hilzinger Chief Financial Officer Matthew F. Hilzinger Chief Financial Officer Morgan Stanley Global Electricity & Energy Conference April 3, 2008 Forward-Looking Statements This presentation includes forward-looking statements within

More information

A HIGH LEVEL RED FLAG REVIEW OF THE NIGERIAN ELECTRIC SUPPLY INDUSTRY

A HIGH LEVEL RED FLAG REVIEW OF THE NIGERIAN ELECTRIC SUPPLY INDUSTRY A HIGH LEVEL RED FLAG REVIEW OF THE NIGERIAN ELECTRIC SUPPLY INDUSTRY Gbite Adeniji March 21, 2014 INTRODUCTION 25-Mar-14 2 GAS PRODUCER NBET POWER PURCHASE AGREEMENT GENCO/IPP TRANSMISSION [TCN = MO &

More information

Doheny Desalination Project Value-for-Money Analysis. March

Doheny Desalination Project Value-for-Money Analysis. March Doheny Desalination Project Value-for-Money Analysis March 22 2017 Presentation Overview Team Introductions Goals of the VfM Analysis Financial Model Estimated Monthly Impacts to Typical Households In

More information

LEGAL ASPECTS OF PROJECT FINANCE. Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL

LEGAL ASPECTS OF PROJECT FINANCE. Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL ` LEGAL ASPECTS OF PROJECT FINANCE Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL About the speaker Anjan Neupane, Partner/Advocate, Neupane Law Associates LLB (Hons.) First Class, University

More information

AT Capital The Global Financial Crisis: Lessons Learnt in the Electricity Sector in Bangladesh

AT Capital The Global Financial Crisis: Lessons Learnt in the Electricity Sector in Bangladesh AT Capital The Global Financial Crisis: Lessons Learnt in the Electricity Sector in Bangladesh Ifty Islam, Managing Partner ifty.islam@at-capital.com Asian Tiger Capital Partners, Feb 9,2011 www.at-capital.com

More information

Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and. Robert Opini, Advisor, Regulatory Reporting. NERSA South Africa

Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and. Robert Opini, Advisor, Regulatory Reporting. NERSA South Africa Ethel Teljeur, Fulltime Regulator Member Primarily Responsible for Piped-gas; and Robert Opini, Advisor, Regulatory Reporting NERSA South Africa Boosting Investor Confidence: The Role of Regulators The

More information

We Energies. Request for Proposal Renewable Energy Supply 2014

We Energies. Request for Proposal Renewable Energy Supply 2014 We Energies Request for Proposal Renewable Energy Supply 2014 Page 2 of 12 I. Introduction A. Summary of Request for Proposals Wisconsin Electric Power Company (We Energies) requests proposals (Proposals)

More information

Overview of Financing Agreements for Project Finance

Overview of Financing Agreements for Project Finance Overview of Financing s for Project Finance A Lender s Perspective 5 June 2014 Asian Development Bank 27th Training Program of Asian EXIM Banks Forum on Project Finance About Efic Australia s export credit

More information

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016 The Economics and Financing of Distributed Generation Investment Budapest, Hungary November 17, 2016 Topics to Cover How to Finance Distributed Generation Investments 1 Importance of financial aspects

More information

Delivering Positive Energy

Delivering Positive Energy Delivering Positive Energy September 2015 Disclaimer 2 These materials have been prepared by PT Adaro Energy (the Company ) and have not been independently verified. No representation or warranty, expressed

More information

JBIC Financial Facilities for Coal Fired Power Plant Project

JBIC Financial Facilities for Coal Fired Power Plant Project JBIC Financial Facilities for Coal Fired Power Plant Project 12 March 2012, Belgrade Japan Bank for International Cooperation(JBIC) JBIC is the international wing of Japan Finance Corporation (JFC) Overview

More information

Financing Offshore wind farms. Financing offshore wind farms: How banks view risks and what they can do

Financing Offshore wind farms. Financing offshore wind farms: How banks view risks and what they can do Financing Offshore wind farms Financing offshore wind farms: How banks view risks and what they can do How do you get there? Risk overview in phases Development phase Construction phase Operational phase

More information

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) LOAN/GEF GRANT

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) LOAN/GEF GRANT Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 30244 Public Disclosure Authorized PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) ON A LOAN/GEF GRANT Public Disclosure

More information

PROJECT FINANCE GLOSSARY

PROJECT FINANCE GLOSSARY API Gravity Availability Barrel Barrel of oil equivalent Barter Base load plant Berne Union Bid Bond BOT BPCD BTU Bullion Buyer Credit Capacity charge A measure of density of Crude Oil or other liquid

More information

Power Sector Reform and Investment Comparing Uganda with Kenya and Tanzania

Power Sector Reform and Investment Comparing Uganda with Kenya and Tanzania Power Sector Reform and Investment Comparing Uganda with Kenya and Tanzania Prof Anton Eberhard Management Program in Infrastructure Reform and Regulation University of Cape Town Drivers for utility reform

More information

Project Capital Solutions. Supporting the American Trade & Finance Company (ATRAFIN)

Project Capital Solutions. Supporting the American Trade & Finance Company (ATRAFIN) Project Capital Solutions Supporting the American Trade & Finance Company (ATRAFIN) Objective of the Program BRIEF FRAMEWORK OF THE MICRO-GRID LEASING PROGRAM The American Trade & Finance Company (ATRAFIN)

More information

Philippines Natural Gas Master Plan Transaction Structure Phase Two Public Consultation 20 th March Prepared for: Supported by: Prepared by:

Philippines Natural Gas Master Plan Transaction Structure Phase Two Public Consultation 20 th March Prepared for: Supported by: Prepared by: Philippines Natural Gas Master Plan Transaction Structure Phase Two Public Consultation 20 th March 2014 Prepared for: Supported by: Prepared by: Disclaimer The World Bank commissioned the study, supported

More information

2016 Strategic Financial Plan Debt Management Policy

2016 Strategic Financial Plan Debt Management Policy Attachment G Page 1 of 15 Debt Management Policy Introduction The County of Orange Debt Management Policy provides guidance for the issuance of bonds and other forms of indebtedness to finance capital

More information

Associated Industries of Massachusetts (AIM) is pleased to provide the following comments to the above mentioned issue.

Associated Industries of Massachusetts (AIM) is pleased to provide the following comments to the above mentioned issue. March 13, 2017 By Email to marfp83c@gmail.com The Massachusetts Department of Energy Resources ( DOER ) The Massachusetts Office of the Attorney General ( AGO ) Fitchburg Gas & Electric Light Company d/b/a

More information

Manual for the IPP Checklist

Manual for the IPP Checklist Manual for the IPP Checklist Introduction This manual is intended both for the ATI underwriters, for IPPs and sponsors who consider applying for political risk and liquidity risk cover, and for government

More information

ELECTRICITY REFORM STATUS IN ROMANIA AND THE ASSESMENT OF THE DISTRIBUTION PRIVATIZATION REQUIERMENTS

ELECTRICITY REFORM STATUS IN ROMANIA AND THE ASSESMENT OF THE DISTRIBUTION PRIVATIZATION REQUIERMENTS ELECTRICITY REFORM STATUS IN ROMANIA AND THE ASSESMENT OF THE DISTRIBUTION PRIVATIZATION REQUIERMENTS Gh. Indre M. Indre I. Conecini Romania Electricity industry is facing in the whole world radical changes

More information

PT HARUM ENERGY Tbk 9M 2016 Summary and Highlights

PT HARUM ENERGY Tbk 9M 2016 Summary and Highlights 31 October 2016 PT HARUM ENERGY Tbk 9M 2016 Summary and Highlights Important Note: The results provided below reflect the unaudited consolidated results of PT Harum Energy Tbk. ( the Company ) for the

More information

INDIKA ENERGY RESULTS FOR THE PERIOD ENDED DECEMBER 31, 2017

INDIKA ENERGY RESULTS FOR THE PERIOD ENDED DECEMBER 31, 2017 FOR IMMEDIATE DISTRIBUTION 19 March 2018 INDIKA ENERGY RESULTS FOR THE PERIOD ENDED DECEMBER 31, 2017 Jakarta - PT Indika Energy Tbk. (IDX: INDY) Indonesia s leading integrated energy company, reported

More information

Yanino Waste Processing Plant City of St. Petersburg

Yanino Waste Processing Plant City of St. Petersburg Yanino Waste Processing Plant City of St. Petersburg Project Briefing 26 October 2009 Page 1 Table of Contents Sections 1. Executive Summary. 3 2. Waste Processing Industry in St. Petersburg.....4 3. Project

More information

Slide 1 Cover. Thank you for joining us today. This is Jeff Armfield, Senior Vice President and Chief Financial Officer for Santee Cooper.

Slide 1 Cover. Thank you for joining us today. This is Jeff Armfield, Senior Vice President and Chief Financial Officer for Santee Cooper. Slide 1 Cover Thank you for joining us today. This is Jeff Armfield, Senior Vice President and Chief Financial Officer for Santee Cooper. Slide 2 Disclaimer Before we begin, I will pause to allow you to

More information

PPPs Risk Sharing: Public and Private Roles

PPPs Risk Sharing: Public and Private Roles PPPs Risk Sharing: Public and Private Roles Sara Sigrist Legal Consultant PPPs (LEGPS) Legal Program Coordinator PPP in Infrastructure Resource Center www.worldbank.org/ppp Why PPPs? PPPs combine the different

More information

AEC And the Challenges in Mining Business. Worapone Pongsuwan Banpu Public Company Limited October 17, 2013

AEC And the Challenges in Mining Business. Worapone Pongsuwan Banpu Public Company Limited October 17, 2013 AEC And the Challenges in Mining Business Worapone Pongsuwan Banpu Public Company Limited October 17, 2013 Contents 1 Banpu Business Overview 2 3 3 Banpu 3 Decades of Growth Banpu Overseas Investment 4

More information

2016 Strategic Financial Plan Debt Management Policy

2016 Strategic Financial Plan Debt Management Policy Attachment A Page 1 of 16 Debt Management Policy Introduction The County of Orange Debt Management Policy provides guidance for the issuance of bonds and other forms of indebtedness to finance capital

More information

The World Bank. East Asia. Assessing the Potential Impact of the Credit Crisis on the Power Sector. Background Presentation Material

The World Bank. East Asia. Assessing the Potential Impact of the Credit Crisis on the Power Sector. Background Presentation Material The World Bank East Asia Assessing the Potential Impact of the Credit Crisis on the Power Sector Background Presentation Material Towards an Integrated Energy Agenda Beyond 2020 International Energy Conference,

More information

MBF1223 Financial Management Prepared by Dr Khairul Anuar

MBF1223 Financial Management Prepared by Dr Khairul Anuar MBF1223 Financial Management Prepared by Dr Khairul Anuar L3 Project Financing www.mba638.wordpress.com Objectives To understand what project financing is and what steps are involved in securing and managing

More information

Overview of cogeneration project development

Overview of cogeneration project development Overview of cogeneration project development 2004 Cogeneration Week in Thailand 23-25 March 2004 Miracle Grand Convention Hotel, Bangkok Romel M. Carlos Financial Advisor Project Development Process Commissioning

More information

POWER SECTOR REFORM AND SUBSIDIES. Budak Dilli ESMAP KNOWLEDGE EXCHANGE FORUM GENEVA October 2018

POWER SECTOR REFORM AND SUBSIDIES. Budak Dilli ESMAP KNOWLEDGE EXCHANGE FORUM GENEVA October 2018 POWER SECTOR REFORM AND SUBSIDIES Budak Dilli ESMAP KNOWLEDGE EXCHANGE FORUM GENEVA October 2018 OVERVIEW OF TURKISH POWER SECTOR Population :80 Million, Geographic Area :780,500 km 2 Rapid demand growth:

More information

COMMON MARKET FOR EASTERN AND SOUTHERN AFRICA POWER PURCHASE AGREEMENT GUIDELINES

COMMON MARKET FOR EASTERN AND SOUTHERN AFRICA POWER PURCHASE AGREEMENT GUIDELINES COMMON MARKET FOR EASTERN AND SOUTHERN AFRICA POWER PURCHASE AGREEMENT GUIDELINES DECEMBERR 2014 LUSAKA 1 POWER PURCHASE AGREEMENT GUIDELINES 1 Objective of the PPA Guideline The main objective of the

More information

BUSINESS COMMITTEE MEETING PAPER AGENDA ITEM 2A

BUSINESS COMMITTEE MEETING PAPER AGENDA ITEM 2A BUSINESS COMMITTEE MEETING PAPER AGENDA ITEM 2A Topic Report on the operational performance of cash market clearing and settlement services Date of the Meeting 2 March 2017 Purpose of this paper Action

More information

Takeout Finance Scheme for Financing Viable Infrastructure Projects

Takeout Finance Scheme for Financing Viable Infrastructure Projects Takeout Finance Scheme for Financing Viable Infrastructure Preamble In the Union Budget speech for the year 2009-10, the Hon ble Union Finance Minister stated To stimulate public investment in infrastructure,

More information

World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects. Workshop Program

World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects. Workshop Program World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects Workshop Program 3 June, 2015 Richard MacGeorge Successful preparation of bankable projects Getting Projects From Fairway

More information

Delivering Positive Energy

Delivering Positive Energy Delivering Positive Energy February 2016 Disclaimer 2 These materials have been prepared by PT Adaro Energy (the Company ) and have not been independently verified. No representation or warranty, expressed

More information

Creating Value, Driving Growth, Building Indonesia. Delivering Positive Energy

Creating Value, Driving Growth, Building Indonesia. Delivering Positive Energy Creating Value, Driving Growth, Building Indonesia Delivering Positive Energy June 2016 Disclaimer 2 These materials have been prepared by PT Adaro Energy (the Company ) and have not been independently

More information

ENERGY FOR CHANGE June 2017

ENERGY FOR CHANGE June 2017 ENERGY FOR CHANGE June 2017 Key questions: What is the outlook for coal supply and demand? How has Adaro performed? What is Adaro s strategy and future plan? Supply response is apparent 2,500 2,000 1,500

More information

July 10, FIT prices are indexed, but this is not too relevant for PHRED.

July 10, FIT prices are indexed, but this is not too relevant for PHRED. July 10, 2013 Response Matrix to Comments from Ray Tomkins/ECA (Consultant, External Peer Reviewer) on draft PAD for Philippines Renewable Energy Development (PHRED) Project In general, the reviewer is

More information

Levelizing Expectations

Levelizing Expectations Levelizing Expectations Sungwoo Kim Regional Head of Climate Change & Sustainability in Asia Pacific, KPMG Table of Contents Global shift of investors [ 03 ] Major risks concerned [ 11 ] How to meet investors

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

INDIKA ENERGY RESULTS FOR THE PERIOD ENDED SEPTEMBER 30, 2017

INDIKA ENERGY RESULTS FOR THE PERIOD ENDED SEPTEMBER 30, 2017 Mainly FOR IMMEDIATE DISTRIBUTION 27th November 2017 INDIKA ENERGY RESULTS FOR THE PERIOD ENDED SEPTEMBER 30, 2017 Jakarta - PT Indika Energy Tbk. (IDX: INDY) Indonesia s leading integrated energy company,

More information

Resolution adopted by the General Assembly. [on the report of the Second Committee (A/66/438/Add.3)]

Resolution adopted by the General Assembly. [on the report of the Second Committee (A/66/438/Add.3)] United Nations A/RES/66/189 General Assembly Distr.: General 14 February 2012 Sixty-sixth session Agenda item 17 (c) Resolution adopted by the General Assembly [on the report of the Second Committee (A/66/438/Add.3)]

More information

Opportunities & Challenges by. Nadeem Babar Orient Power Company Ltd. November 2015

Opportunities & Challenges by. Nadeem Babar Orient Power Company Ltd. November 2015 Opportunities & Challenges by Nadeem Babar Orient Power Company Ltd November 2015 1 The Opportunity Market offers long term opportunities of growth for those who understand the risks Half of Power produced

More information

Appendix B-2. Term Sheet for Tolling Agreements. for For

Appendix B-2. Term Sheet for Tolling Agreements. for For Appendix B-2 Term Sheet for Tolling Agreements for For 2015 Request For Proposals For Long-Term Developmental Combined-Cycle Gas Turbineand Existing Capacity and Energy Resources in WOTAB DRAFT Entergy

More information

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER ENMAX Corporation 2017 Q2 INTERIM REPORT ENMAX Corporation CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries

More information

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process

NYISO Posting for FERC Order 890 Describing the NYISO Planning Process NYISO Posting for FERC Order 890 Describing the NYISO Planning Process September 14, 2007 ` NYISO Posting for FERC Order 890 Filing DRAFT Table of Contents Section: Page No: I. Cover Memo - Draft OATT

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

6 August 2018 Bangkok, Thailand. Noritaka Akamatsu Senior Advisor (Financial Cooperation & Integration) Asian Development Bank

6 August 2018 Bangkok, Thailand. Noritaka Akamatsu Senior Advisor (Financial Cooperation & Integration) Asian Development Bank 6 August 2018 Bangkok, Thailand Noritaka Akamatsu Senior Advisor (Financial Cooperation & Integration) Asian Development Bank Instruments Indirect financing of public infrastructure In 2015, 25 DMCs (96%

More information

Actual neighborhood of Sunrun customer homes

Actual neighborhood of Sunrun customer homes This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements

More information

DAC METHODOLOGIES TO MEASURE THE AMOUNTS MOBILISED FROM THE PRIVATE SECTOR

DAC METHODOLOGIES TO MEASURE THE AMOUNTS MOBILISED FROM THE PRIVATE SECTOR DAC METHODOLOGIES TO MEASURE THE AMOUNTS MOBILISED FROM THE PRIVATE SECTOR Guarantees, syndicated loans, shares in collective investment vehicles, direct investment in companies, credit lines 2018 update

More information

Workshop on Regional Electricity Trade and Market Development

Workshop on Regional Electricity Trade and Market Development Workshop on Regional Electricity Trade and Market Development Cross-border Electricity Trade and Tariffs April 23, 2014 Cross-border Electricity Trade (CBT) Flows within which part of the transmission

More information