1 PPP IDENTIFICATION AND PPP PLANNING Mohammad Taufiq Rinaldi Planner Directorate of PPP and Financial Engineering Ministry of National Planning Agency/BAPPENAS Republic of Indonesia Asia PPP Practioners Network Conference Seoul, November 2017
2 2 Strategy On Infrastructure Development Fulfillment of Basic Needs 100% Drinking Water access 100% sanitation access Connectivity Maritime Highway + Regional Development/ Growth Center Infrastructure to support Leading Sectors Marine Highway Intermodal Regional Development/ Growth Center Leading Sector Agricultural Urban Transport Development of Road,Rail Based Mass Transport System & Intermodal Improve the capacity and quality of the urban road network Urban Transport Development Concept 96.6% electrification ratio Avoid Shift Improve Livable housing access Border & underdeveloped regions accessibility Transportation Safety & Security Developed Area Intermodal Port Area Intermodal Broadband Development: e-government, e-health, e-education, e-logistic, e-commerce, Energy Development: 35 GW Target 1,200 kwh/capita in 2019 ( current facts: Vietnam 1,300 kwh/capita, Malaysia 4,400 kwh/capita) Under- Developed Area Manufacturing Service and Tourism Network to Support Efficiency Journey Increased share of Public Transport Develop sustainable urban transport Increased utilization Technology Transportation Institutional integration Transportation Institutional integration
3 Investment Needs and Strategy Investment Value (The Sources) Public Investment: Provision of Public Facilities Total Value of Investment Required in Infrastructure * : Government Budget: USD 148.2Bn (41.3%) SOE : USD 79.8Bn Category Definition low Social Investment Investment that does not possess direct investment feedback to the object. IRR Weighted Average Cost of Capital (WACC) Special Commercial PPP Investment Investment with yields under eligibility standards so it needs partly investment reduction from the Government s social investment. Investment with yields meeting investment eligibility standards but seen as less attractive or risky as government intervention is needed. high General Commercial Investment Investment with attractive yields as role of government is reduced for regulating and promoting. USD 359.2Bn (IDR 4,796.2Tn) (22.2%) Private Participation: USD 131.1Bn (36.5%) Example Source of Funding Social Security Education Security Health Security Government funding (APBN & APBD) Drinking water material Mass public transportation Government funding + commercial funding Toll road Ports Commercial funding promoted by the government Electricity Airports Gas pipe Commercial funding Source: BAPPENAS Internal Analysis *) 1 : Calculation based on infrastructure investment (required) to be a middle income country by Source: Bappenas- JICA, 2014: Background Study for RPJMN , Analyst team of Ministry of National Development Planning (BAPPENAS) RPJMN: National Medium-term Development Planning Non-Government Budget Investment Financing (PINA) For s with IRR > 13 % 3
4 4 Annual Planning And Budgeting Process Evaluation Development Theme, Goals, Policy Direction & Priorities Review on Basic Number KEM PPKF & Budget Availabilty Draft Annual Plan (RKP) & Indicative allocation First Discussion with Parliament President Regulation on Annual Plan and Budget allocation Draft State Budget Discussion with Parliament for State Budget Law State Budget Law and Budget Allocation December/ January January February February March May June July/August August/ September November PPP Identification and Priorities Programs and activities proposal for supporting implementation and sustainability of PPP Approval Programs and activities budget for supporting implementation and sustainability of PPP
5 5 Decision Making for Infrastructure Financing Line Ministry Budget (State Budget) Proposals Proposals Proposals Evaluation and Decision for Suitable Financing for Priority (e.g Value for Money -VfM) Transfer to Local Budget (State Budget) Local Budget Priority PPP Non-Government Budget Investment Financing (PINA)
6 THIS Planning Thematic Holistic Integrative Spatial Proposals Proposals Proposals Priority Thematic Focus on long/mid-term plan to national priority Holistic interconnection process from beginning to end Integrative Integration of various institution programs and financing Spatial focus on space and location PPP on National Development Planning and Budgeting under Bappenas Coordination: Preparation Transaction Government Contribution (In kind provision, Special Allocation Fund, VGF) Availability Payment Integrative infrastructure and programs in supporting PPP Local Government Contribution Example: Umbulan Water Supply VGF (MoF) In Kind Provision (MoPW) Special Allocation Fund (Bappenas and MoF) Land acquisition and access road (Local government 6
7 There Are 19 Sectors Covered For PPP In Indonesia Transportation Energy Conservation Electricity Seaports Roads Airports Railways Road Transportation Toll Roads Power Plants Fiber Optic Toll Bridges Transmission e-gov Street Lighting Oil, Gas, and Renewable Energy Road Telecommunications and Informatics CONNECTIVITY Water Supply SOCIAL FACILITIES URBAN FACILITIES Centralized Waste Water Management Localized Waste Water Management Tourism Sports, Art, and Culture Facilities Urban Facility Penitentiary Education Facilities Health Public Housing Waste Management System Water Resources and Irrigation Traditional Market Zone 7
8 Private as the project innitiator (UNSOLICITED) Government as the project innitiator (SOLICITED) PPP Stages in Indonesia Solicited and Unsolicited Schemes PLANNING PREPARATION TRANSACTION Preliminary Identification Study Outline Business Case (OBC) Final Business Case (FBC) Pre Qualification Request for Proposal Bid Award PPP Agreement Signing Financial Close Construction USD 8.8 billion proponent submits a proposal and pre-fs document to GCA Business Entity submits FS Pre-FS document evaluation to get pre-fs approval GCA gives the rights to project proponent to prepare FS FS evaluation Issuing approval letter Tender Preparation. PPP Agreement Signing Financial Close 12 projects include 2 unsolicited toll road projects: Krian Legundi Bunder Manyar (USD 0.9 billion) Jakarta Cikampek Elevated II (USD 0.1 billion) Jatiluhur Water Supply (USD million) GCA: Government Contracting Agency 8
9 9 Successful PPP Schemes in Indonesia There are 6 implemented schemes as benchmarks for future PPP projects PPP projects based on structure development PPP projects based on project preparation Government Guarantee Coal-Fired Power Plant Central Java 2x1000 MW (USD 4,200.0 million) Success Fee Scheme Coal-Fired Power Plant Central Java 2x1000 MW (USD 4,200.0 million) Tariff & Viability Gap Fund (VGF) Umbulan Drinking-Water Facility (USD million) Bangun Cipta Kontraktor Unsolicited PPP Jakarta Cikampek II Elevated Toll Road (USD million) PT Ranggi Sugiron Perkasa Availability Payment (AP) for Investment Return Palapa Ring Optic-Fiber Network (USD million) Government In-Kind (Construction Support) Solo Kertosono Toll Road (USD million) Cisumdawu Toll Road (USD million) Balikpapan Samarinda Toll Road (USD million) Manado Bitung Toll Road (USD million) Total: USD 2,318.8 million
10 PPP PIPELINE PPP TARGET Public Private Partnerships (PPP/KPBU) Progress A. PROJECT VALUE Construction USD 8.8 billion USD 0.6 billion Financial Close USD 0.6 billion USD 3.5 billion Transaction until PPP Agreement Signing Preparation B. PROJECT SUMMARY Construction 12 1 Transaction until PPP Agreement Signing 10 Quick Win s 2018 (total project value: USD 3.6 billion) 1. Serang Panimbang Toll Road 2. Jakarta Cikampek South Toll Road 3. Probowangi Toll Road 4. Nambo Regional Waste Management 5. Bandar Lampung Water Supply 6. Jatiluhur Water Supply USD 3.5 billion USD 6.8 billion + 5 Under Calculation s USD 0.1 billion USD 6.7 billion + 12 Under Calculation s Financial Close Preparation Suramadu Toll Bridge 8. West Semarang Water Supply 9. Pekanbaru Regional Water Supply 10. Sidoarjo General Hospital Source: BAPPENAS Internal Analysis 10
11 PPP Institutional Breakthrough CAPITAL PLACE, 8 TH FLOOR JALAN JENDERAL GATOT SUBROTO KAV. 18 JAKARTA SELATAN PHONE: PPP Office Coordination and Facilitation based on each institution : Bappenas is responsible in identification and planning (coordination for preparing project and integrating with national development planning) MoF provides fiscal support facility (PDF and VGF Facility) MoHA gives consideration on regional fiscal related with Regional AP LKPP acts as transaction probity BKPM makes sure investors credibility and market sounding process CMEA acts as debottlenecking facilitator PT. Penjaminan Infrastruktur Indonesia (Persero)/IIGF does government guarantee process Capacity Building 11 11
12 PPP Office Workflow In Indonesia Government Contracting Agency (GCA) as Implementing Unit GCA Bappenas (Planning) BKPM makes sure investors credibility and market sounding process Ministry of Home Affair gives consideration on regional fiscal related with Regional AP IIGF informally gives an input on OBC and FBC development process Bappenas plans OBC budget LKPP acts as transaction probity IIGF does government guarantee process PPP Unit under MoF provides PDF and VGF facility Parcitipating Institutions Coordinating Ministry of Economic Affairs Ministry of National Development Planning/BAPPENAS Ministry of Finance Ministry of Home Affairs National Procurement Agency (LKPP) National Investment Coordinating Board (BKPM) Indonesia Infrastructure Guarantee Fund PQ RfP PPP Agreement Signing Construction and Operation Stage Identification and Proposal Feasibility Study OBC Development FBC Development Bid Award Financial Close Screening and Selection Stage Preparation Stage Transaction Stage The Coordinating Ministry of Economics Affairs as Debottlenecking Facilitator BKPM : Investment Coordinating Board IIGF : Indonesia Infrastructure Guarantee Fund Bappenas: Ministry of National Development Planning MoF LKPP PQ : Ministry of Finance : National Procurement Agency : Pre-Qualification RfP : Request for Proposal OBC : Outline Business Case FBC : Final Business Case AP : Available Payment 12
13 13 Summary PPP is one of solutions for fulfilling financial gap in infrastructure investment. Once decided as PPP, many programs needs to be provided in order to make PPP sustain (using T H I S Approach). BAPPENAS, as a planning agency, coordinates, facilitates and plans all the programs that integrate with the development of PPP in order to fulfill or to serve people need and also to make PPP sustain. Moreover BAPPENAS ensures PPP and all supporting programs inline with National Development Planning.
14 감사합니다 Kamsahamnida Thank You Terima Kasih Find us at: Directorate of PPP and Financial Engineering Ministry of National Development Planning/BAPPENAS Gedung Baru, 4 th floor Jalan Taman Surapati No. 2 Jakarta Pusat Indonesia Phone: pkps@bappenas.go.id 14 14
and PINA Schemes Social Investment Investment that does not possess direct investment feedback to the object.
Total Value of Investmen t Required in Infrastruct ure * 015-019: US$ 59.Bn (IDR 4,796.Tn) Financing Infrastructure Development 015-019 Increasing the significant role of SOE & Private Sector through Public
More informationExposure of Indonesia Infrastructure Project
REPUBLIK INDONESIA Prof. Bambang Brodjonegoro, Ph.D. Minister of National Development Planning / Head of National Development Planning Agency Exposure of Indonesia Infrastructure Project London, 15 March
More informationExposure of Indonesia Infrastructure Project
REPUBLIK INDONESIA Prof. Bambang Brodjonegoro, Ph.D. Minister of National Development Planning / Head of National Development Planning Agency Exposure of Indonesia Infrastructure Project Asia Matters Roundtable
More informationA brief on current Indonesia s PPP Program. Directorate General of Budget Financing and Risk Management - Ministry of Finance Republic of Indonesia
A brief on current Indonesia s PPP Program Directorate General of Budget Financing and Risk Management - Ministry of Finance Republic of Indonesia 1 Indonesia has been striving to close infrastructure
More informationEXECUTING AND DEVELOPING PPP PROJECTS: AN INDONESIAN EXPERIENCE
Ungasan Bay View Hotel & Convention Bali 10 October 2018 KEMENTERIAN KEUANGAN DIREKTORAT JENDERAL PENGELOLAAN PEMBIAYAAN DAN RISIKO DIRECTORATE GENERAL OF BUDGET FINANCING AND RISK MANAGEMENT MINISTRY
More informationImproving Creditworthiness and Project Quality in Ensuring The Implementation of Government-Business Infrastructure Project
Improving Creditworthiness and Project Quality in Ensuring The Implementation of Government-Business Infrastructure Project Muhammad Wahid Sutopo Executive Business Director PlanoCosmo, ITB Bandung, 2
More informationThe way ahead for Indonesia : How to ensure the financing for its infrastructure projects Dr. Robert Pakpahan, Ak
The way ahead for Indonesia : How to ensure the financing for its infrastructure projects Dr. Robert Pakpahan, Ak Director General of Financing and Risk Management, Ministry of Finance Indonesia Infrastructure
More informationQuality Infrastructure Preparation and Transaction
Quality Infrastructure Preparation and Transaction Tulus Hutagalung Committee for Acceleration of Priority Infrastructure Delivery Tokyo, 13 th August 2018 Indonesia Current Project Development Facility
More informationFACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS
INDONESIA INFRASTRUCTURE GUARANTEE FUND (IIGF) FACILITATING ACCESS TO FINANCE FOR INFRASTRUCTURE PROJECTS: ESTABLISHING DEDICATED INSTITUTIONS United Nations Economic And Social Commission For Asia And
More informationIndonesia. PPP Country Profile Indonesia. 1. Overview
Last Revised: June 2015 Indonesia 1. Overview ASEAN s largest economy, Indonesia, has grown at a robust real GDP growth rate within a range of 5.0 6.5 percent from 2004 to 2014, with an exception of a
More informationIndonesia. 1. Noteworthy practices for project preparation. Case Study
Case Study Indonesia 1. Noteworthy practices for project preparation EXISTING ENABLING ENVIRONMENT Domestic infrastructure financing institutions created by the Ministry of Finance are introducing good
More informationThe Role of Non-Government Budget Investment (PINA) for Infrastructure Development in Indonesia
REPUBLIK INDONESIA The Role of Non-Government Budget Investment (PINA) for Infrastructure Development in Indonesia Ekoputro Adijayanto CEO PINA Center for Private Investment Special Staff to the Minister
More informationInnovative Financing Scheme to Accelerate the New Urban Agenda s Infrastructure Development Targets
A LEADING CATALYST IN FACILITATING INDONESIA S INFRASTRUCTURE DEVELOPMENT Innovative Financing Scheme to Accelerate the New Urban Agenda s Infrastructure Development Targets Darwin T. Djajawinata Director
More informationSMI AS A LOCAL PARTNER FOR FOREIGN INVESTORS IN INFRASTRUCTURE PROJECT INVESTMENT IN INDONESIA
SMI AS A LOCAL PARTNER FOR FOREIGN INVESTORS IN INFRASTRUCTURE PROJECT INVESTMENT IN INDONESIA Emma Sri Martini, President Director PT Sarana Multi Infrastruktur (Persero) a leading catalyst in the acceleration
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Public Private Partnership Global Practice Recipient Executed Activities Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 29-Jun-2017
More informationIndonesia Infrastructure Development: Sectoral Policy Update
Indonesia Infrastructure Development: Sectoral Policy Update Indonesia Infrastructure Investment Forum Dwianto Eko Winarno Project Director of Transportation Sector Seoul, 21 September 2017 Infrastructure
More informationIndonesia s Business Potentials
REPUBLIC OF INDONESIA Ambassador Mulya Wirana @ Proforum 2015 Indonesia s Business Potentials Lisbon, Portugal 18 November 2015 1 4 th World s Most Populous Country 248 million Population (in 2013) 17,508
More informationThe 5 th Asian Think Tank Development Forum Colombo, September 2017
POTENTIAL INSTRUMENTS TOWARD SUSTAINABLE URBAN INFRASTRUCTURAL DEVELOPMENT IN INDONESIA The 5 th Asian Think Tank Development Forum Colombo, 21-22 September 2017 CARUNIA MULYA FIRDAUSY Professor of Economics
More informationINFRASTRUCTURE INVESTMENT IN EMERGING MARKETS AND DEVELOPING ECONOMIES A BRIEF LOOK AT INDONESIA. Raj Kannan, Managing Director
INFRASTRUCTURE INVESTMENT IN EMERGING MARKETS AND DEVELOPING ECONOMIES A BRIEF LOOK AT INDONESIA Raj Kannan, Managing Director 2 July 2015 St. Catherine s College, Oxford CONTENTS 1. Overview of Indonesia
More informationBoosting Infrastructure Financing through Risk Mitigation Instruments
Boosting Infrastructure Financing through Risk Mitigation Instruments Financing Sources for Public-Private Partnerships Forum Kuala Lumpur, 25 November 2015 Dr Armand Hermawan CFO Indonesia Infrastructure
More informationFor any enquiries to :
Thursday & Friday, 5-6 March 208 09.30-4.00 Andaz Liverpool Street Hotel, 40 Liverpool St, London EC2M 7QN For any enquiries email to : iipc.london@investinindonesia.uk A. BACKGROUND A.. Infrastructure
More informationNinth UNCTAD Debt Management Conference
Ninth UNCTAD Debt Management Conference Geneva, 11-13 November 2013 Contingent Liabilities by Mr. Scenaider Siahaan Director of Debt Strategy and Portfolio Ministry of Finance Indonesia The views expressed
More information1 PPP in Indonesia: Risk Allocation Guideline
1 PPP in Indonesia: Guideline 2 PPP in Indonesia: Guideline FOREWORD The increasing demand for infrastructure development to support Indonesia s economic growth has led the Government of Indonesia to provide
More informationOne Stop Integrated Services Geothermal Licensing
invest in BKPM 2016 One Stop Integrated Services Geothermal Licensing INDONESIA INVESTMENT COORDINATING BOARD Hanung Harimba Rachman Director of Investment Planning for Agribusiness and Natural Resources,
More informationDraft PPP Policy Outline
Note 7 May 2012 Draft PPP Policy Outline This note is the seventh in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership (PPP) programs.
More informationPPIAF Assistance in Indonesia
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PPIAF Assistance in Indonesia July 2012 Since 2000 PPIAF has funded 19 activities in
More informationBy Director of Various New and Renewable Energy T
MINISTRY OF ENERGY AND MINERAL RESOURCES OF THE REPUBLIC OF INDONESIA DIRECTORAT GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION By Director of Various New and Renewable Energy T Jakarta, 10 May
More informationGLOBAL INFRASTRUCTURE FACILITY. A partnership platform for greater investment in the infrastructure of emerging markets and developing economies
GLOBAL INFRASTRUCTURE FACILITY A partnership platform for greater investment in the infrastructure of emerging markets and developing economies COLLABORATION FINANCE LEVERAGE IMPACT The Global Infrastructure
More informationIndonesia Infrastructure Investment Forum Seoul, September 2017 INFRASTRUCTURE PROJECTS PIPELINE
Indonesia Infrastructure Investment Forum Seoul, 20-21 September 2017 INFRASTRUCTURE PROJECTS PIPELINE 1 PPP PROJECTS 2 3 REPUBLIK INDONESIA Solicited PPP Project Scheme PLANNING PREPARATION TRANSACTION
More informationGuideline for Risk Allocation of Infrastructure Projects under PPP Scheme in Indonesia. Version Indonesia Infrastructure Guarantee Fund
Guideline for of Infrastructure Projects under PPP Scheme in Indonesia Version 1.0-0 - Indonesia Infrastructure Guarantee Fund 1 PPP in Indonesia: Guideline REMARKS BY THE MINISTER OF FINANCE OF THE REPUBLIC
More informationOpportunity of Infrastructure Financing. Darmawan Junaidi Director PT Bank Mandiri (Persero) Tbk
Opportunity of Infrastructure Financing Darmawan Junaidi Director PT Bank Mandiri (Persero) Tbk Indonesia s Development Plan THE GOVERNMENT HAS TARGETED SOME HIGH INDICATORS IN THE RPJMN 2015-2019 Development
More informationRecent experience of establishing a PPP framework to mitigate fiscal risks in Bangladesh
(Strengthened Fiscal Management in Asia) Recent experience of establishing a PPP framework to mitigate fiscal risks in Bangladesh 4 June 2018 Mita Conference Hall, Tokyo PPP Authority Prime Minister s
More informationThe Role of Bank Mandiri in Infrastructure Financing. Ferry M.Robbani Senior Vice President PT Bank Mandiri (Persero) Tbk
The Role of Bank Mandiri in Infrastructure Financing Ferry M.Robbani Senior Vice President PT Bank Mandiri (Persero) Tbk Indonesia s Development Plan THE GOVERNMENT HAS TARGETED SOME HIGH INDICATORS IN
More informationPPP in Korea. Highlights on its Institutions. Director General Hyoung-Kwon, Ko. Ministry of Strategy and Finance. November 11.
PPP in Korea Highlights on its Institutions November 11. 2012 Director General Hyoung-Kwon, Ko Ministry of Strategy and Finance 1 Table of Contents I Framework of PPPs in Korea II Performance Highlights
More informationMINISTRY OF PLANNING AND INVESMENT PUBLIC PROCUREMENT AGENCY OVERVIEW OF PPP IN VIET NAM
MINISTRY OF PLANNING AND INVESMENT PUBLIC PROCUREMENT AGENCY OVERVIEW OF PPP IN VIET NAM HCM city, 22 May 2018 1 Content 1. PPP decree and Investor selection decree 2. Overview of potential projects 2
More informationBasic Concept of Availability Payment (AP) and Budgeting Implication
JICA Technical Assistance Basic Concept of Availability Payment (AP) and Budgeting Implication July 26, 2017 KPPIP Support Facility Table of Content 1. Basic Concept of Availability Payment (AP) 2. AP
More informationSECTOR ASSESSMENT (SUMMARY): INDUSTRY AND TRADE
Stepping Up Investments for Growth Acceleration Program- Subprogram 2 (RRP INO 48134) SECTOR ASSESSMENT (SUMMARY): INDUSTRY AND TRADE 1. This sector assessment describes the binding constraints to achieving
More informationPPP Fiscal Risk Management - The Implementation
2011/FMP/CON/017 Session 6 PPP Fiscal Risk Management - The Implementation Submitted by: Indonesia Conference on the Framework and Options for Public and Private Financing of Infrastructure Washington,
More informationLocal Government Challenges to Implement Public Private Partnership Projects in Indonesia
, pp. 83-96 DOI:10.1515/hjbpa-2017-0026 Local Government Challenges to Implement Public Private Partnership Projects in Indonesia Erwin, SONDANG S. erwinsondangsiagian@yahoo.com Asep, SUMARYANA asep.sumaryana@unpad.ac.id
More informationForeign Direct Investment in Indonesia
Foreign Direct Investment in Indonesia Michael S. Carl michaelcarl@ssek.com SSEK Legal Consultants LawAsia Sydney 2017 9 October 2017 Indonesia - Challenges Administration of President Joko Widodo (Jokowi)
More information2017 INVESTMENT OPPORTUNITIES IN INDONESIA
HIGH LEVEL FORUM: 2017 INVESTMENT OPPORTUNITIES IN Prof. Bambang Brodjonegoro, Ph.D Minister of National Development Planning / Head of National Development Planning Agency June 2017 2 OUTLINE 1 Indonesia
More informationIndonesia Deep Dive GIF ADVISORY COUNCIL MEETING OCTOBER 16, 2018
Indonesia Deep Dive GIF ADVISORY COUNCIL MEETING OCTOBER 16, 2018 Yogyakarta Bawen Toll Road (Road Sector) BPJT / MOF Project Overview The Yogyakarta - Bawen toll-road will connect existing Semarang -
More informationPUBLIC PRIVATE PARTNERSHIP IN NEPAL. Sushil Bhatta Member, National Planning Commission Government of Nepal
PUBLIC PRIVATE PARTNERSHIP IN NEPAL Sushil Bhatta Member, National Planning Commission Government of Nepal 1 Outline Context Role of PPP in Infrastructure Evolution of Legal Framework for PPP PPP Practice
More informationInvesting in Indonesia:
invest in Prepared for Indonesia Investment Seminar, ASEAN-Japan Centre Fukuoka, 10 July 2014 Investing in Indonesia: Opportunities for Growth INDONESIA INVESTMENT COORDINATING BOARD Rudy Salahuddin Director
More informationINDONESIAINVESTMENT OUTLOOK AND POLICY DEVELOPMENT
invest in INDONESIAINVESTMENT OUTLOOK AND POLICY DEVELOPMENT Jakarta, 16 September 2014 INDONESIA INVESTMENT COORDINATING BOARD (BKPM) 2014 by Indonesian Investment Coordinating Board. All rights reserved
More informationThailand s Innovation Financing for Infrastructure
Thailand s Innovation Financing for Infrastructure Wachiraya Permbhusri Director of PPP Bureau The State Enterprise Policy Office Policy Dialogue on Infrastructure Financing Strategies for Sustainable
More informationValue for Money Test in Korea
Global Roundtable on Value for Money Value for Money Test in Korea Hyeon PARK Executive Director Public and Private Infrastructure Investment Management Center (PIMAC), KDI hpark@kdi.re.kr/ +82-19-445-2511
More informationJapanese ODA Loan. Ex-ante evaluation
Japanese ODA Loan Ex-ante evaluation 1. Name of the Program Country: The Republic of Indonesia Project name: Connectivity Development Policy Loan Loan Agreement December 2, 2013 Loan Amount: 19,848 million
More informationINDONESIA ECONOMIC QUARTERLY CLOSING THE GAP. Frederico Gil Sander Lead Economist October 3, 2017
INDONESIA ECONOMIC QUARTERLY CLOSING THE GAP Frederico Gil Sander Lead Economist October 3, 2017 How is the economy doing? What to expect in 2018? Closing the gap Growth steady amid mostly favorable conditions
More informationCompany Overview & Investment Opportunities
Company Overview & Investment Opportunities as of February 8 For Discussion Only Company Overview Company Overview Brief Snapshot Company Highlights Leading toll road operator in Indonesia with 40 years
More informationThe Role of PT. Sarana Multi Infrastruktur in Infrastructure Development
The Role of PT. Sarana Multi Infrastruktur in Infrastructure Development 1 OUTLINE Background Profile Framework Financing Policy Challenges Target 2 BACKGROUND Rationale 1. Global economic condition 2.
More informationContents. Executive Summary 3 Introduction to Indonesia Profile of Indonesia and South Jakarta
Contents CONTENTS PAGE Executive Summary 3 Introduction to Indonesia Profile of Indonesia and South Jakarta Project Partners Key Growth Drivers Lead Contractor PT Rayka Market Overview Telecommunication
More informationIndonesia: Infrastructure Reform Sector Development Program (Subprograms 1, 2, and 3, and an Infrastructure Project Development Facility)
ompletion Report Project Numbers: 40009-013, 40009-023, 40009-033, and 40009-043 Loan Numbers: 2263, 2264, 2475, and 2708 Grant Number: 0064 Technical Assistance Number: 4872 August 2017 Indonesia: Infrastructure
More informationB. Whereas the development of infrastructure requires debt of longer maturity to supplement the debt funds presently available; and
Scheme for Financing Viable Infrastructure Projects through a Special Purpose Vehicle called the India Infrastructure Finance Company Limited (IIFCL) (Revised) 1. Preamble A. Whereas the Government of
More informationINVESTING IN INDONESIA Investment Policy & Opportunity
invest in Taipei, 30 May 2014 INVESTING IN INDONESIA Investment Policy & Opportunity Mohamad Faizal Director of Investment Dept., IETO 2014 by Indonesian Investment Coordinating Board. All rights reserved
More information13. What banking business in foreign currency is permitted to use foreign currency?
FREQUENTLY ASKED QUESTIONS BANK INDONESIA CIRCULAR NO. 17/11/DKSP /DKSP DATED 1 JUNE 2015 CONCERNING MANDATORY USE OF RUPIAH WITHIN THE TERRITORY OF THE REPUBLIC OF INDONESIA A. GENERAL REVIEW 1. What
More informationJoint Press Release on the Third Steering Committee Meeting of the Metropolitan Priority Areas for Investment and Industry
Joint Press Release on the Third Steering Committee Meeting of the Metropolitan Priority Areas for Investment and Industry October 9, 2012 The Third Steering Committee Meeting of the Metropolitan Priority
More informationPPP Policies, Performances & Prospects of the Republic of Korea
PPP Policies, Performances & Prospects of the Republic of Korea 2007. 10.5 CHANG, Byoung-Wan Minister of Planning and Budget Contents Ⅰ Overview of Korean PPPs Ⅱ Performance Highlights Ⅲ Prospects on Korean
More informationORISSA PUBLIC PRIVATE PARTNERSHIP POLICY-2007
ORISSA PUBLIC PRIVATE PARTNERSHIP POLICY-2007 PLANNING & CO-ORDINATION DEPARTMENT RESOLUTION No.12711 / PPP 38/2006 Dated 07 th August 2007 Sub: - ORISSA PUBLIC PRIVATE PARTNERSHIP (PPP) POLICY- 2007 1
More informationInvesting in Indonesia: Perspectives from Regulators and Business Boston University Asian Alumni Festival
Investing in Indonesia: Perspectives from Regulators and Business Boston University Asian Alumni Festival Thomas Trikasih Lembong Chairman of Indonesia Investment Coordinating Board (BKPM) Jakarta, 3 November
More informationMinisterio de Finanzas. Argentina ś PPP Plan Public Private Partnership Under Secretariat
Ministerio de Finanzas Argentina ś PPP Plan Public Private Partnership Under Secretariat 1 Global infrastructure deficit 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 Required investment
More informationRepublic of Indonesia
Republic of Indonesia 2018 Investor Update Stability at the Forefront with Unwavering Reforms Commitment June 2018 Disclaimer This presentation has been prepared by the Republic of Indonesia (the Republic
More informationStrategy #1: Partnering with the Private Sector through PPP. EY Infrastructure Advisory. October 2017
Strategy #1: Partnering with the Private Sector through PPP EY Infrastructure Advisory October 2017 EY Infrastructure Advisory Page 2 EY s Infrastructure Advisory and Project Finance Advisory Capabilities
More informationFindings from The Survey on Promoting Planning and Implementation of SDGs in the Republic of Indonesia
Findings from The Survey on Promoting Planning and Implementation of SDGs in the Republic of Indonesia Prof. Dr. Yoko Ishida Center for the Study of International Cooperation in Education, Hiroshima University
More informationFinancing initiatives for reducing vulnerability and increasing resilience to impact of climate change. IMACC GIZ PAKLIM
Financing initiatives for reducing vulnerability and increasing resilience to impact of climate change. IMACC 29.07.2013 Adaptation Finance for : Central Government Local Government Private Sector Households
More informationValue for Money (VfM) Analysis Virginia s experiences and lessons learned
Value for Money (VfM) Analysis Virginia s experiences and lessons learned May 28, 2013 Morteza Farajian Program Manager Virginia s Enabling P3 Legislation Public-Private Transportation Act of 1995 Intent
More informationin Developing Countries in FY2010 Access Road in Republic of Indonesia SUMMARY March 2011
Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2010 Study on the PPP Project Formulation of Tanjung Priok Access Road in Republic of Indonesia SUMMARY March 2011 第 1 章
More informationPublic Private Partnership in Turkey
www.kalkinma.gov.tr T.R. MINISTRY OF DEVELOPMENT Public Private Partnership in Turkey SEDEF YAVUZ NOYAN Head of Public Private Partnership Department Outline What is PPP, Rationale for PPP in Turkey The
More informationKorea PPP System. - Ha Jung Yoon KRIHS 국토연구원
Korea PPP System - Ha Jung Yoon 2015. 10. 13 국토연구원 KRIHS Contens 1. Korea PPP System 2. Governmental Supports 3. PPI Performance Result during 10 years 4. Status and Prospects on PPI in Korea 5. Case Study
More informationSelecting the Right Projects / Sectors for PPP Implementation
the Right s / Sectors for PPP Implementation Policy Dialogue on PPP for Infrastructure Development in South Asia Organized by UN ESCAP 21-22 September 2015 PPP Macro Level Large number of commercial banks,
More informationThe Future of Indonesia s Cities
The Future of Indonesia s Cities Director for Urban Affairs, Housing and Settlement Ministry of National Development Planning/ National Development Planning Agency Indonesia 1 Rapid urbanization, absolute
More informationDeveloping Institutional Framework for Regulatory Reform: Indonesian Experience
Developing Institutional Framework for Regulatory Reform: Indonesian Experience B. Raksaka Mahi Special Advisor to the Coordinating Minister of Economic Affairs and Vice Secretary of National Team for
More informationEquity Research PT Waskita karya (Persero) Tbk
Equity Research karya (Persero) Tbk 3 August 2018 Construction, Equity Price IDR. 2070 Target Price IDR. 3140 JKSE Index 6011.72 3500 3000 2500 2000 1500 1000 500 0 Last Price (IDR) LS Stock Code Bloomberg
More informationIndonesia Medium-term Fiscal Policy Framework Striking The Right Balance Between Reform and Growth
Euromoney Indonesia Financing & Investment Forum 2018 04 April 2018 Indonesia Medium-term Fiscal Policy Framework Striking The Right Balance Between Reform and Growth Prof. Suahasil Nazara Head of Fiscal
More informationSTUDY ON PUBLIC PROCUREMENT SYSTEM FOR JCM PROJECT
STUDY ON PUBLIC PROCUREMENT SYSTEM FOR JCM PROJECT To achieve sustainability and replication of JCM Project Model To achieve JCM sustainability, it is necessary to promote widely JCM project model in cooperation
More informationDecree No.15/2015/ND-CP dated 14/02/2015 on Public Private Partnership Investment (PPP) (Effective from 10/4/2015)
Decree No.15/2015/ND-CP dated 14/02/2015 on Public Private Partnership Investment (PPP) (Effective from 10/4/2015) 1 Old legal framework on PPP Decision No. 71/2010/QD-TTg on pilot PPP Projects Decree
More informationInvestment Climate in Myanmar U San Myint Deputy Director General Directorate of Investment and Company Administration
Investment Climate in Myanmar U San Myint Deputy Director General Directorate of Investment and Company Administration Content 1. Investment Situation in Myanmar 2. Investment Policy 3. New Myanmar Investment
More informationM.Sc. in economics and political science (1970) at University of Copenhagen Member of the Danish Association of economist (DJOEF)
1 Born: 1945 Nationality: Danish Company: ApS Lange-Müllers Alle 2 2960 Rungsted Kyst, Denmark Tel: +45 45 86 94 88 E-mail: lrc@lrc.dk Web : www.lrc.dk Position : Partner, ApS, Denmark Years with firm:
More informationGOVERNMENT OF ARUNACHAL PRADESH DEPARTMENT OF PLANNING
GOVERNMENT OF ARUNACHAL PRADESH DEPARTMENT OF PLANNING No. PD (PPP) 3/2010-11 Dated Itanagar, the 12th April, 2011 To. The Principal Secretaryl Commissioner/Secretary, GOVT. OF ARUNACHAL PRADESH. Sub:
More informationWorld Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects. Workshop Program
World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects Workshop Program 3 June, 2015 Richard MacGeorge Successful preparation of bankable projects Getting Projects From Fairway
More informationInfrastructure financing challenges of Cambodia
Infrastructure financing challenges of Cambodia Gaps, Modalities and Recommendations Shuvojit Banerjee UNESCAP The Importance of Infrastructure Improving Infrastructure is vital for achieving multiple
More informationImproving public investment efficiency for infrastructure development
National Workshop on Infrastructure Financing Strategies for Sustainable Development in Viet Nam Hanoi, 3 October 2017 Improving public investment efficiency for infrastructure development Mr Mathieu Verougstraete
More informationINDONESIA I N V E S T I N. Indonesia Investment Climate and How to Approach the Indonesian Market. invest in
invest in Indonesia-Australia Business Conference Yogyakarta, 17 November 2015 I N V E S T I N INDONESIA Indonesia Investment Climate and How to Approach the Indonesian Market INDONESIA INVESTMENT COORDINATING
More informationVision Valley. The government provides tax incentives to attract RM6.5 billion ($1.5 billion) in investments and create 14,000 jobs.
Public Private Partnership Development in Southeast Asia 11 Vision Valley. The government provides tax incentives to attract RM6.5 billion ($1.5 billion) in investments and create 14,000 jobs. 4. Thailand
More informationPrivate Capital in Infrastructure in ASEAN: How the Global Infrastructure Facility can help. November, 2015
Private Capital in Infrastructure in ASEAN: How the Global Infrastructure Facility can help. November, 2015 Agenda Private Participation in Infrastructure (PPI) in ASEAN ASEAN PPP Pipeline Work Global
More informationSoutheast Asian Infrastructure
New Report Investment and Market Opportunities in n Infrastructure SouthEast Infrastructure magazine (www.southeastasiainfra.com) is a leading source of information and analysis on infrastructure development
More informationINDONESIA PHASE II OF THE INDONESIA GREEN GROWTH PROGRAM OVERVIEW HIGHLIGHTS OVERALL OBJECTIVES CONTEXT. RELEVANT SDGs
INDONESIA PHASE II OF THE INDONESIA GREEN GROWTH PROGRAM OVERVIEW Country / Global implementation Thematic area Indonesia Lower Middle Income Country (LMIC) Multi-sectoral Project start date Q1 2016 Funding
More informationRepublic of the Maldives: Preparing Business Strategy for Port Development
Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed
More informationREGULATION OF INVESTMENT COORDINATING e-licensing BOARD NO. 13 of 2017
Shifting to digital age : Toward paperless licensing REGULATION OF INVESTMENT COORDINATING e-licensing BOARD NO. 13 of 2017 Deputy Chairman for Investment Services ONE STOP SERVICE CENTER - BKPM Jakarta,
More informationSustainability and Efficiency of Public Investment Spending in the Philippines: Challenges and Opportunities
Sustainability and Efficiency of Public Investment Spending in the Philippines: Challenges and Opportunities Tokyo Fiscal Forum 10-11 June 2015 Rosario G. Manasan Philippine Institute for Development Studies
More informationFinancing Sustainable Infrastructure In Asia. Fei Yu Deputy Representative Asian Development Bank North American Representative Office
Financing Sustainable Infrastructure In Asia Fei Yu Deputy Representative Asian Development Bank North American Representative Office Agenda The Asia Scene The sustainable infrastructure gap The current
More informationINVESTMENT COORDINATING BOARD
invest in Indonesia Investment Promotion Tokyo, 4 March 2014 INDONESIA Investment and Economic Outlook INDONESIA INVESTMENT COORDINATING BOARD Mahendra Siregar Chairman 2014 by Indonesian Investment Coordinating
More informationPrivate Participation in Infrastructure in Korea
Private Participation in Infrastructure in Korea 9 Oct. 2008 Bong Hwan CHO Ministry of Strategy and Finance Republic of Korea Contents PPI Overview Performance Highlights Future of Korean PPI PPI Overview
More informationGovernment of Indonesia
Government of Indonesia GOVERNMENT OF THE REPUBLIC OF INDONESIA, MINISTRY OF VILLAGE, DISADVANTAGED REGIONS DEVELOPMENT AND TRANSMIGRATION (KEMENDESA) & UNITED NATIONS CHILDREN S FUND (UNICEF) (January
More informationNational Urban Policy: Cities as Engine of Growth
National Urban Policy: Cities as Engine of Growth Minister of National Development Planning/ Head of National Development Planning Agency The 4th Planocosmo International Conference Bandung, 4 April 2018
More informationPublic Private Partnership in Turkey
www.kalkinma.gov.tr T.R. MINISTRY OF DEVELOPMENT Public Private Partnership in Turkey SEDEF YAVUZ NOYAN Head of Public Private Partnership Department Outline Investment Prospects Turkey s PPP Experience
More informationRole of Private Equity in Urban
Role of Private Equity in Urban Infrastructure July 18, 2013 Agenda Private Equity in India An overview Indian Infrastructure opportunity Key framework facilitating Infrastructure investment Uba Urban
More informationINDONESIA UPDATE: NEW NEGATIVE INVESTMENT LIST
June 6, 2016 INDONESIA UPDATE: NEW NEGATIVE INVESTMENT LIST To Our Clients and Friends: What is the Negative Investment List? The "Negative Investment List" or "DNI[1]" is a regulation issued under Indonesian
More informationKENYA S PPP EXPERIENCE AND PIPELINE PROJECTS
KENYA S PPP EXPERIENCE AND PIPELINE PROJECTS AFRICAN CONFERENCE ON PUBLIC PRIVATE PARTNERSHIP 6-7 DEC 2012 SPEKE RESORT, KAMPALA, UGANDA Presentation By ENG STANLEY K, KAMAU HEAD OF PUBLIC PRIVATE PARTNESRSHIPS,
More informationSUSTAINABLE DEVELOPMENT FINANCING FOR FULFILLING CLIMATE CHANGE MITIGATION AND ADAPTATION COMMITMENT
BADAN KEBIJAKAN FISKAL KEMENTERIAN KEUANGAN RI SUSTAINABLE DEVELOPMENT FINANCING FOR FULFILLING CLIMATE CHANGE MITIGATION AND ADAPTATION COMMITMENT Presented by: Dr Parjiono Director of Centre for Climate