Risk Assessment in Projects of Shipbuilding, Ship Repairing and Ship Conversion

Size: px
Start display at page:

Download "Risk Assessment in Projects of Shipbuilding, Ship Repairing and Ship Conversion"

Transcription

1 Risk Assessment in Projects of Shipbuilding, Ship Repairing and Ship Conversion Hugo Miguel Martins Pais Centre for Marine Technology and Engineering (CENTEC), Instituto Superior Técnico, Technical University of Lisbon, Portugal ABSTRACT: It s intended to create a risk management model concerning an evaluation that may be applied to construction projects, repairs and naval conversion. For it s not ordinary in the industrial area and especially in the naval area, the risk assessment is done through risk factors, having so little scientific literature that may support this approach. The model presented here is an iterative process that should be done through the entire project s life cycle and that abridges the sustainability factors of the project. That are, time, cost and quality. As many other risk evaluation processes concerning other non-naval areas, this model identifies, evaluates and treats the project s risks, but furthermore considers the risk factors of the project during its evaluation. The risk approach through risk factors allows a more delicate risk pre-selection, improving the evaluation method and making the risk management process more efficient. The developed model was applied to a ship building project of a fluvial ferry for transportation of people and vehicles. The number of identified risks doesn t not allow to present them all in this article, so it was intended to give some examples of the processed risks. Keywords: Risk, Risk Management Process, Risk Factor, Risk Identification, Qualitative Assessment, Quantitative Assessment, Risk Treatment, Naval Engineering, Sustainability, Time, Cost, Quality. 1. INTRODUCTION It s intended to develop a methodology to assess a project in the point of view of their risks in the way of decrease the probability of the occurrence of these events or, in the case of occurrence, to define treatment strategies that make these risks affect the project as little as possible. The developed model must have applicability in naval engineering projects, namely projects of shipbuilding, ship repairing and ship conversion, so it will be applied to a ship building project. There are very different ways to define risks, but we can define it as the combination of the probability of an event and its consequence [1]. There are no projects without risks, but they can affect the project s objectives in different ways, namely in his sustainability. There are risks that affect the project positively, called Opportunities, but there are others that affect the project negatively, called Threats. These last are the ones we pretend to assess, because they are the most common risks in projects. The model developed is iterative and is composed by four sub-processes: risk identification, risk 1 assessment, risk treatment and risk monitoring. In this work it will be done an explanation of these subprocesses, as well as its surroundings. The risk management process presented here is centered in risk factors assessment. This procedure is not very common, and is little the literature that addresses this matter. However, it s possible that this procedure bring some benefits, namely in the selection of the most critical risks. The model was applied to a shipbuilding case. The vessel used is a fluvial ferry for transportation of people and vehicles. Starting with the construction contract and the descriptive memory act, it will be made the first iteration of the model, but just considering the conception period of the project s life cycle. Risks that may appear in other phases were not assessed. The sub-process of risk monitoring was not applied, because the construction was not made. The International Standard Organization (ISO) defines some standards of risk management to be applied in projects, they are ISO31000 [2]. These standards provide guidelines to the identification,

2 assessment and treatment of risks, the standard use in this study was the 2009 s edition. Out of the sphere of the naval engineering, there are some risk management models, defined by entities that applies this own methods to assess risks. The National Aeronautics and Space Administration (NASA) has defined, in 2007, its own guidelines [3], as made by the Department of Energy of the United States of America in 2008 [4]. More than methods for the risk management, they provide templates to be used by their teams. In the literature there are some works that analyze the risks with a suitable detail, in this study, the work of Chapman and Ward [5] and the PMBOK Guide [6], by Project Management Institute were consulted. 2. THE RISK MANAGEMENT MODEL AND ITS APPLICATIONS TO A SHIPBUILDING PROJECT 2.1. THE SHIP The risk management model was applied to a shipbuilding project of a hypothetical ship. This ship is a fluvial ferry and the objective is to transport people and vehicles between the margins of a river. The construction contract and the descriptive memory act of the ship were used as bases for the application of the method. All the risks processed were presented in those documents. The ship must be built using the good practices of the shipbuilding and be followed by the rules and regulamentation with respect of stability, safety, navigability and maneuverability. The main characteristics of the ship are: Maximum length over all 50m Maximum Draft 1.90m Seated Passengers 350 Vehicles 35 Crew 4 Service Velocity 11 knots Fuel Autonomy 360 hours 2.2. RISK MANAGEMENT PROCESS In general the risk management is made using the experiences of the past combined with a reasonable judgment of the situation, rarely is used a methodology exclusively created to deal with risks. But depending on the importance and complexity of the project, the use of the experience or a reasonable judgment may not be sufficient. Here appears the necessity of a risk management process. The Project Management Institute [6] defines a risk as an uncertain event, which if occurs has positive or negative effect on project objectives. So, risks can be of two different types, they can be positive risks, that bring benefits to the project called Opportunities, or they can be negative, called Threats, that can cause damages to the sustainability of the project. These last are those that will be studied in this work. The Risks called threats are characterized by two main dimensions: the impact and the probability of occurrence. The impact is the damage that the occurrence of the risk makes in the project, the probability of occurrence is the possibility of the risk materializes. This two dimensions act directly in the sustainability of the project, so they will be one of the bases of the risk assessment PROJECT AND PROJECT MANAGEMENT The Project Management Institute [6] defines project as a temporary endeavor undertaken to create a unique product, service, or result. So there are three types of different projects: the creation of a product (the one that we are interested in this study), the execution of a service, and obtaining a result. PMI says that a project is temporary because it has a well defined period of life, with a beginning and an end, described by project s life cycle. Chapman and Ward [5] proposed a typical project s life cycle, composed only by four main stages: Conception, Planning, Execution and Conclusion. In the case of a ship, these stages are integrated in the ship s life cycle (Conception, Planning, Execution, Operation, Repair and Scrapping). In the risk management process, the stages of Conception and Planning of the project s life cycle are the most important, because the majority of the risks must be identified, assessed and treated during these stages. During this two stages should be undertaken the first and more important iteration of the process. The intensity of the risk management process tends to decrease in the others stages of the project life cycle. 2

3 Fig 1 - Intensity of the Risk Management Process vs Project Life Cycle The project management is defined by PMI as the application of knowledge, skills, tools and techniques to project activities to meet project requirements. Project management is accomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring and controlling, and closing THE SUSTAINABILITY OF THE PROJECT AND THE RISK MANAGEMENT There are three factors in the sustainability of projects: Time, Cost and Quality. They can have the same importance to the sustainability or not, it depends on the industry but here we will consider that they are equal in importance. Depending on the risk, it can affect just one of these factors; however, all the factors will be affected by the occurrence of the risk. It means that Time, Cost and Quality haves a relationship. This relationship can be exposed as a sustainability triangle. Fig 2 - Sustainability Triangle The risk treatment is applied into these factors, because is in Time, Cost and Quality that we want to avoid problems. The impact of the occurrence of a risk is studied during the risk evaluation sub-processes; an easy approach is to use risk factors RISK MANAGEMENT TEAMS The risk management depends on the team that applies the process. Experienced, cohesive and proactive teams make the process easier and turn better the efficiency of the process. The team need to be defined when the risk management plan is defined and the project s team must be part of it, because they are the elements that have a better knowledge about it. The constitution of a specialized team in the process has some advantages, namely when there are no culture of risk management. The incorporation of external experts in the risk management team, mostly in projects with high complexity occurs several times. All the stakeholders may take part of the team too, or, at least, should be taken into account. This incorporation minimizes the external risks of the project RISK IDENTIFICATION The risk identification sub-process is one of the most important tasks in risk management. The methods involved in the identification must be applied exhaustively, with responsibility to ensure that all the possible risks are identified. A risk identification performed poorly can make all the process fail, because the identification is the base for the risk evaluation and risk treatment. There are a few methods that can be used in the risk identification sub-processes, the most important are [7]: - Analysis of Documents; - Techniques for Collecting Information; - Analysis of Historical Data; - Analysis of assumptions; - Diagram Techniques; - SWOT Analysis; - Specialized Analysis. In the application of the model to the ship, they were used four methodologies. As the start point of the study was the construction contract and the descriptive memory act, the analysis of documents was a very useful tool in the process, allowing the identification of the risks present in those documents. The techniques for collecting information were used too, due to clarify some risks not so obvious in the documents. Specialized analysis was performed to go deeper in the existing information. Last but not least, the diagram 3

4 techniques, namely the use of the fault trees diagrams provided some precious information in the identification of risk factors. Fault trees are an inductive methodology to determine the potential causes of accidents, fail of systems in general and to determine the failure probability [8]. In this case they were used to determine the risk factors of each risk USE OF A RISK BREAKDOWN STRUCTURE (RBS) The identified risks need to be organized in a way that turns possible to understand the relationship between them, the common sources and the stages of the project s life cycle in which they appear. It is not sufficient to create a list of identified risks, it's necessary to develop an organizational methodology that makes it easier to access the risks and that allows a quick and complete transmission of information. Hillson [9], suggests that the creation of a RBS must take in to account the project development and the specific risk sources of the sector or industry. For that, there is in the literature a few generic RBS that can be used as a start point to create a specific RBS for the project. The higher levels of a RBS are normally called as Risk Categories. These categories are used to group families of risks that are separated by lower levels, but still having the same risk category. In the application of the model to a shipbuilding project, the RBS created and used in all the risk management process is: 1. Project 1.1. Schedule 1.2. Tactics 1.3. Tasks 1.4. Costs 2. Ship owner 2.1. Funds 2.2. Scope 2.3. Objectives 3. Extern 3.1. Politics 3.2. Legislation 3.3. Environment 3.4. Market 3.5. Culture 3.6. Stakeholders 4. Internal 4.1. Infrastructure 4.2. Human Resources 4.3. Management 4.4. Organic structure 4.5. Safety The RBS is composed by four risk categories: Project, Ship owner, Internal and External Risks. However, as all the information available was the construction contract and the descriptive memory act, it wasn t possible to fill all the risk categories RISK REGISTER After the identification of risks and the allocation of the RBS the risks should be registered in a document that works like a data base. This document is called Risk Register and it is the final documentation in the risk identification sub-process. This document collects all the risks, in a common format, with all the information found. In general in a risk register, it should be present information about, at least, the RBS, a description of the risk, the risk factors, the risk category and the factor of the sustainability that suffers the major impact of the occurrence of the risk. The addition of more information about the risks is favorable to the risk identification sub-process. The process of risk management is iterative, so the risk register is updated throughout the project. They were found 28 different risks in the risk identification sub-process undertaken to the case of the shipbuilding project. However, it was decided to show only 5 risks, due to the space occupied in this article. 4

5 RBS Risk Risk Factor The ship must have capacity for 350 persons. 2% Less : Ship Rejected. The ship must have capacity for 35 Vehicles. Less than 31: Ship Rejected. The ship must produce a low wash in all velocities Maximum draft of 1.9m in load condition Fuel Autonomy for 360 hours The previous table shows the risk register of 5 risks founded during the risk identification sub-process for the shipbuilding contract. As said previously, the risk factors were founded using fault trees RISK EVALUATION The scope of the risk evaluation is to apply techniques that allow a better understanding of the impact and the probability of occurrence of a risk. With these methods, it s intended that the assessment is not performed only by the experience but also by promoting studies that turns the projects more efficient. When changes in the goals of the projects occur, the risk evaluation must be redone, to verify if it s necessary to promote changes in the assessments already done. The risk register must be checked to ensure that there are no unidentified risks The risk assessment was done in two parts, a qualitative evaluation and a quantitative evaluation. In the first one, the impact and the probability of occurrence are assessed in a quantitative way. In the second part the consequences of the occurrence of a risk, and the respective probability are computed. The objective of this separation on the risk evaluation is to find the most critical risks and just assess these ones in a quantitative way QUALITATIVE EVALUATION The qualitative evaluation is the first step in the risk evaluation sub-process. It s not intended in this part to find precise values of the impact and the probability of occurrence, but, using qualitative - Architecture of the space for passengers poorly designed. - Architecture of the space for vehicles poorly designed. - Aft hull forms poorly designed; - Inappropriate Propeller. - Weight evaluation fail; - Hull forms poorly designed. - Poor analysis of the fuel consumption curves; - Fuel tank capacity insufficient. Tab 1 - Risk Register 5 Risk Category Project Project Ship Owner Ship Owner Ship Owner Sustainability Impact Time Time Cost/Time Quality Time methods, to measure the risks and find the more important ones to be evaluated quantitatively. The qualitative evaluation is composed by three different steps: the evaluation of risk factors, the P-I Score and the plot of the risk in a risk matrix. Within the qualitative evaluation the risks considered not critical will not proceed to the next steps, but they will be documented to be treated in the next subprocess RISK FACTORS EVALUATION The risk factors, found in the risk identification subprocess using fault trees, act directly in the project, being a threat to the sustainability. So it makes sense to evaluate them according to their severity to the sustainability of the project. It s important to note that a risk factor can be present in more than one risk within the same project. This fact makes that risk factors present in more than one risk need to be evaluated according with that condition. The evaluation starts with the construction of a table containing the risk factors and the number of times that each one appears in the risk register. Then, each risk factor must be evaluated in the sustainability: Time, Cost and Quality. For that we can use levels of risk [10], a qualitative scale shown on Tab 2. Level of Risk Insignificant 0 Low 1 Medium 2 High 3 Tab 2 - Level of Risk for risk factors evaluation

6 To compute the final impact of a given risk factor, it can be used the following formula: = Where: I is the Impact caused by the risk factor; NR is the number of repetition of that risk factor in the risk register; T is the Time; C is the Cost; Q is the Quality. After the computation of all impacts it must be done a ranking of risk factors. It should be decided a criteria to define the risks that should pass to the P-I Score calculations and the ones that should be documented. In the application made in this study, it was decided that only the risks corresponding to the 50% risk factors that cause more impact should pass to P-I Score computation. The evaluation of the risk factor of the five risks used here is show in Tab 3. Risk Level Risk Factor NR T C Q Impact Architecture of the space for passengers poorly designed. Architecture of the space for vehicles poorly designed Inappropriate propeller Hull forms poorly designed Poor analysis of the fuel consumption curves Fuel tank capacity insufficient Aft hull forms poorly designed Weight evaluation fail Tab 3 - Evaluation of risk factors The risk factors shaded in grey stayed in the 50% more important risk factors, so the risks that proceed in evaluation are: 2.1.5, and The risks and must be documented to a future treatment P-I SCORE The next step in the qualitative evaluation is the P-I Score [7]. This computation will allow proceeding to the plot of the risks in a risk matrix, so it s a very important computation that must be done with accuracy. The evaluation must be done using qualitative values and when the complexity of the project justifies it, external experts can be called to evaluate the risks. The formula to compute the P-I Score is: = 2 Where: GR is the P-I Score; I is the impact. Po is the probability of occurrence. As exposed in Equation 2, the P-I Score use qualitative values of probability of occurrence and the impact. The value for these two dimensions must be assigned using a grading scale, which must be the same for all the risks. The proposed scales [7], for the impact and probability of occurrence are: Impact Insignificant 1 Low 2 Moderate 3 High 4 Catastrophic 5 Tab 4 - Qualitative values for Impact Probability of Occurrence Very Low 1 Low 2 Moderate 3 High 4 Very High 5 Tab 5 - Qualitative values for probability of occurrence For the shipbuilding project used as example, some experts were contacted to evaluate risks. They are members of the project team of the major shipyards in Portugal, Estaleiros Navais de Viana do Castelo and Arsenal do Alfeite, and Francisco Gomes Lopes, professor in the Naval Architecture and Marine Engineering Department at IST. The average results of the risks still under evaluation are shown in Tab 6. RBS Average Average Prob. P-I Impact of Occurrence Score Tab 6 - P-I Score 6

7 RISK MATRIX The creation of the risk matrix is the last step in the qualitative evaluation and complements the P-I Score computations. This matrix has as inputs the probability of occurrence and the impact of the risks and it has as output the P-I Score [3]. The advantage of the creation of this matrix is that it allows to plot the risks in a colored grid to quickly verify their severity and allowing an anticipation of the type of treatment that the risk may have. The dimension of the matrix has to be the same of the qualitative values used in P-I score. In some cases, the creation of the risk matrix concludes the risk evaluation process. It occurs because the simplicity of the project allows it, or because there are no sufficient data to undertake quantitative analyses. The risk matrix developed to the qualitative values used in the P-I Score is: PROBABILITY OF OCCURRENCE IMPACT Tab 7 - Risk Matrix The risks that pass to the quantitative evaluation are those risk marked in color red and orange; the others must be documented to a future treatment. The risks still in evaluation in the example have the following mapping in the risk matrix: consequences of the occurrence of a risk and compute the probability of those consequences. It is a different type of assessment that just must be undertaken when it exist sufficient data about the risks. It is better not to do a quantitative evaluation when there are no sufficient data about the risks because it can introduce some errors in the process that can damage the entire project. The classical approach to find the consequences of a risk is creating event trees and the use of simulations or historical data to find the probability of those consequences. The creation of event trees is a quantitative methodology that allows doing an inductive analysis. Starting with an initial event, the method develops all the sequences of events that result of the assumption of the fail or success of the previous event [8]. In this way, it is possible to find the consequences of the initial event that is the occurrence of a risk. The probability of those consequences can be found by simulation, typically using Monte Carlo simulations or using historical data [4]. The problem of using simulations is that you need to know some initial data that not always are available. In the other hand, you just can use historical data if you have experience with similar projects. To brand new projects it isn t possible use this type of data. In the example given here, for the last risk in evaluation (risk ) it was used historical data to find the probability of the consequences, obtained from the experts. The event tree created for that risk is presented in Fig Tab 8 - Mapping in the risk matrix The risks and are out of the critical zone of the risk matrix, so they will not proceed to the quantitative evaluation QUANTITATIVE EVALUATION The scope of the quantitative evaluation is different from the scope of the qualitative evaluation. The quantitative evaluation aims to find the different 7 Fig 3 - Event tree of the risk From the event tree it s possible to conclude that the necessity of small changes in the displacement of the ship due to the excess of draft has a probability of 3/85, and the probability of drastic changes in displacement is 1/85.

8 RISK TREATMENT The sub-process of risk treatment handles the risks in the way of minimize the threats that they can cause to the project. This sub-process develops some procedures that act in the probability and consequences of the occurrence of a risk. The treatments suggested to the risk must follow some requirements to be applied. They must be as adequate as possible to the risk, be in agreement with the cost and the time of the project and they must be decided with the agreement of all the risk management team. There are four types of different treatments for the risk, the decision criteria has as start point the risk register and the documentation produced in the risk evaluation sub-process [4]. Those treatments are: Avoidance, Transfer, Mitigation and Acceptance. - Avoidance: it is to not allow the occurrence of the risk. Normally this type of treatment is applied to the consequences of the risks presented in the most critical zone of the risk matrix, where the probability and the impact are higher; - Transfer: It is to charge other entities for the consequences of a risk. A risk can be transferred with a sub-contracting or the creation of insurance. This type of treatment is applied to risks with lower probability of occurrence but with high impact; - Mitigation: This treatment tries to decrease the probability of occurrence or the impact of some risks. The mitigation implies to undertake premature actions that may be more advantageous than eliminate the consequences of the occurrence of the risk. The costs related with this type of treatment must be in agreement with the probability and impact of the risk. It is normally applied to risks with medium impact and probability; - Acceptance: This treatment is characterized by don t act about the risk. Is a treatment applied to risks with low impact. There are two types of acceptance, the passive acceptance and the active acceptance. The passive acceptance doesn t define any strategy to the consequences of the risk and it just acts in case of occurrence. The active acceptance is characterized by the definition of contingency plans in case of occurrence of the risk. 8 Each treatment acts in different types of risks, so it s possible to plot the different types of treatment in the risk matrix Fig 4. Fig 4 - Plot of the risk treatments in the matrix Depending on the risks, the plot of the treatment in the risk matrix needs to be carefully done and must be undertaken with some critical sense, in some cases it may not be advantageous to define the treatment by the matrix. RBS Risk Treatment Avoidance: Higher control in the spaces architecture Avoidance: Higher control in the spaces architecture Mitigation: Detailed study about the hull flow. Expert analysis. Avoidance: Control in the displacement computation and in the distribution of weights Active Acceptance: Contingency plan providing for the budgeting of an additional fuel tank on board Tab 9 - Risk Treatment As shown in the previous table, the risks and don t have the treatment proposed by the plot. In fact the consequences of the occurrence of these risks are too high to be accepted, as the plot proposed RISK MONITORING This is the last sub-process of the risk management process and it is intended to verify if the risk treatments are appropriate to the project during the application. The treatments defined for the risks can be applied in future stages of the project and this sub-process is necessary to verify if the treatment still valid when applied. If the project has not changed and the conditions that determine the treatment were the same, it can be applied, but otherwise it needs to be reformulated.

9 The identification and control of the residual and secondary risks must be done during this subprocess. The risk monitoring is responsible by producing documentation that provides information about the project s progress in the risk point of view. This sub-process was not applied to the shipbuilding project. 3. CONCLUSIONS The application of the process to the shipbuilding project was successful but there are some reflections that must be made. The risk management model presented here is centered in the risk factors. This type of procedure is not usual in the risk management processes developed before, but it was verified that the identification of the risk factors in the risk identification sub-process promotes it because with them is possible to identify common sources and, eventually, identify new risks. In the sub-process of risk evaluation, the use of the risk factors has advantages too. The use of these factors to compute their impact in the sustainability of the project allows identifying the most critical risks, turning the risk evaluation easier in P-I Score computations. In fact, computing the P-I Score to all the risks it was verified that the risks selected as critical by the risk factors method had in average a score 23.5% higher than the ones selected as not critical. This last observation leads us to another; The use of a bigger grading scale in the P-I Score computation, and consequently the use of a bigger risk matrix, promotes a better differentiation of the risks. The differences between the scores obtained by the critical and the non-critical risks, in the risk factor evaluation point of view, should increase with this application. The quantitative risk evaluation was done recurring to historical data provided by a shipyard. The use of this data is simple and profitable, but it must be applied just in cases where there are solid data bases, otherwise the results cannot be considered credible. 9 In the risk treatment sub-process was verified that the use of the risk matrix plot to decide what treatment a risk must have, need to be done carefully, because sometimes the result is not the more convenient. In a future study it must be useful developing a method that predicts, in the risk treatment subprocess, the budget and the estimated time needed to the implementation of the treatment. 4. REFERENCES [1] ISO GUIDE 73, Risk Management Vocabulary - Guidelines for use in standards, [2] ISO 31000, Risk Management - Principles and guidelines, [3] NASA, Exploration Systems - Risk Management Plan, NASA, Ed. Washington, [4] Department of Energy - United States of America, Risk Management guide, DOE-USA, Ed. Washington, [5] Chapman, C. and Ward, S., Project Risk Management, 2nd ed. John Wiley and Sons Ltd, [6] Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 4th ed., Project Management Institute, [7] F J Gomes Lopes, Gestão do Risco - Lições do Eng. Gomes Lopes, APQ, [8] E. E. Lewis, Introduction to Reliability Engineering, 2nd ed., New York, Wiley, [9] Hillson, D.,, Use a Risk Breakdown Structure (RBS) to Undestand Your Risks, October [10] Guedes Soares, C., Gomes Lopes, F., Pedro Mendes, J., "Método para Identificação e Gestão de Riscos em Projectos de Engenharia," in Riscos industriais e Emergentes, Volume I, C. Guedes Soares et al., Eds. Lisboa: Edições Salamandra Lda, 2009, pp [11] Gomes Lopes, F., Gestão e Organização de Estaleiros Navais - Lições do Eng. Gomes

10 Lopes, IST, [12] Guedes Soares, C., "Metodologia para a Análise e Gestão de Riscos," in Análise e Gestão de Riscos, Segurança e Fiabilidade - Vol. I, C. Guedes Soares, A. P. Teixeira, and P. Antão, Eds. Lisboa: Edições Salamndra, 2005, pp [13] NUREG, Reactor safety study - an assessment of accident risks is U. S. commercial nuclear power plants", WASH NUREG 75/014 U. S. Nuclear Regulatory Commision, Ed. Washington, USA,

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 6 Risk Planning Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study Guide book.

More information

Project Selection Risk

Project Selection Risk Project Selection Risk As explained above, the types of risk addressed by project planning and project execution are primarily cost risks, schedule risks, and risks related to achieving the deliverables

More information

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration. Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL

CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL Dr Suwarna Torgal Assistatnt Professor, IET, DAVV, Indore ( M P ) ABSTRACT There are many risks events that adversely affect the

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED

More information

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive

More information

Evolution of the Portuguese Construction Sector

Evolution of the Portuguese Construction Sector Evolution of the Portuguese Construction Sector Application of the Structure-Conduct-Performance Paradigm Tiago Gomes Romão Extended Abstract Supervisor: Professor Carlos Paulo Oliveira da Silva Cruz March

More information

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Unit 9: Risk Management (PMBOK Guide, Chapter 11) (PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should

More information

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.

More information

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Every project is risky, meaning there is a chance things won t turn out exactly as planned. PMBOK 5 Ed. DEI- Every project is risky, meaning there is a chance things won t turn out exactly as planned. percent of runaway projects Did no risk management at all 38 percent did some, and 7 percent

More information

Information Technology Project Management, Sixth Edition

Information Technology Project Management, Sixth Edition Management, Sixth Edition Prepared By: Izzeddin Matar. Note: See the text itself for full citations. Understand what risk is and the importance of good project risk management Discuss the elements involved

More information

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Managing Project Risks Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Abstract Nearly all projects have risks, both known and unknown. Appropriately managing

More information

Project Management Certificate Program

Project Management Certificate Program Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949

More information

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards A framework for the integration of risk management into the project and construction industry, following

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME Journal of KONES Powertrain and Transport, Vol. 21, No. 4 2014 ISSN: 1231-4005 e-issn: 2354-0133 ICID: 1130510 DOI: 10.5604/12314005.1130510 APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY

More information

Risk Management Made Easy 1, 2

Risk Management Made Easy 1, 2 1, 2 By Susan Parente ABSTRACT Many people know and understand risk management but are struggling to integrate it into their project management processes. How can you seamlessly incorporate project risk

More information

AN INTRODUCTION TO RISK CONSIDERATION

AN INTRODUCTION TO RISK CONSIDERATION AN INTRODUCTION TO RISK CONSIDERATION Introduction This cookbook aims at recalling basic concepts and providing simple tools and possibilities of applying the "considering of risks and opportunities" in

More information

Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port Domain

Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port Domain Journal of Traffic and Transportation Engineering 5 (2017) 271-278 doi: 10.17265/2328-2142/2017.05.004 D DAVID PUBLISHING Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port

More information

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra Risk Management Process-02 Lecture 06 By: Kanchan Damithendra Risk Analysis Risk Register The main output of the risk identification process is a list of identified risks and other information needed to

More information

client user GUIDE 2011

client user GUIDE 2011 client user GUIDE 2011 STEP ACTION Accessing Risk Register 1. Type https://www.scm rms.ca/riskregister/login.aspx 2. Click in the Username field on the Risk Register home page. 3. Type your Username and

More information

Risk Management Made Easy. I. S. Parente 1

Risk Management Made Easy. I. S. Parente 1 Risk Management Made Easy I. S. Parente 1 1 Susan Parente, MS Engineering Management, PMP, CISSP, PMI-RMP, PMI-ACP, CSM, CSPO, PSM I, ITIL, RESILIA, CRISC, MS Eng. Mgmt.; S3 Technologies, LLC, Principal

More information

Best Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc.

Best Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc. Best Practices in Project Risk Management Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc. What is Project Risk Management? PMBOK Definition of Project

More information

Homeowners Ratemaking Revisited

Homeowners Ratemaking Revisited Why Modeling? For lines of business with catastrophe potential, we don t know how much past insurance experience is needed to represent possible future outcomes and how much weight should be assigned to

More information

Integrated Earned Value Management and Risk Management Approach in Construction Projects

Integrated Earned Value Management and Risk Management Approach in Construction Projects Volume-7, Issue-4, July-August 2017 International Journal of Engineering and Management Research Page Number: 286-291 Integrated Earned Value Management and Risk Management Approach in Construction Projects

More information

Project Risk Management

Project Risk Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within

More information

The Basics of Risk Management

The Basics of Risk Management The Basics of Risk Management Greg Sepeda, PE Sigma Consulting Group, Inc. Louisiana Transportation Conference March 1, 2016 The Basics of Risk Management What Why When Who and How? What is Risk? Risk

More information

An Approach to risk quantification in construction projects using EMV analysis

An Approach to risk quantification in construction projects using EMV analysis An Approach to risk quantification in construction projects using EMV analysis R. C. WALKE * Research student for Ph. D. course, V. J. T. I., Mumbai University PROF. V.M. TOPKAR Head, Civil and Environmental

More information

The Risky Business of. Risk Management

The Risky Business of. Risk Management The Risky Business of Risk Management 1 About Me: Jan Holt, PMP Project Management Professional (PMP) since 2005 Project Management Institute (PMI) Michiana Chapter President PMP Prep Class Instructor

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

Risk management as an element of processes continuity assurance

Risk management as an element of processes continuity assurance Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 63 ( 2013 ) 873 877 The Manufacturing Engineering Society International Conference, MESIC 2013 Risk management as an element

More information

RISK EVALUATION OF PRODUCTION AND IMPLEMENTATION OF THE PROJECT

RISK EVALUATION OF PRODUCTION AND IMPLEMENTATION OF THE PROJECT Category: original scientific paper Rados Bozica 1 Rados Ante 2 RISK EVALUATION OF PRODUCTION AND IMPLEMENTATION OF THE PROJECT Abstract: One of the key parts during the project cycle of the technical

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium. http://pmsymposium.umd.edu/pm2018/ RISK MANAGEMENT Susan Parente MADE EASY PMP, PMI-RMP, PMI-ACP, CSM, CSPO, PSM I, CISSP, CRISC, RESILIA, ITIL, MS Eng. Mgmt. Associate Professor, Post University, CT,

More information

M_o_R (2011) Foundation EN exam prep questions

M_o_R (2011) Foundation EN exam prep questions M_o_R (2011) Foundation EN exam prep questions 1. It is a responsibility of Senior Team: a) Ensures that appropriate governance and internal controls are in place b) Monitors and acts on escalated risks

More information

DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK?

DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK? DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK? Dr. István Fekete Corvinus University of Budapest H-1093 Budapest Fővám tér 8. Tel: +3630-456-3424 e-mail: istvan.fekete@uni-corvinus.hu Keywords: risk

More information

Optimizing the Incremental Delivery of Software Features under Uncertainty

Optimizing the Incremental Delivery of Software Features under Uncertainty Optimizing the Incremental Delivery of Software Features under Uncertainty Olawole Oni, Emmanuel Letier Department of Computer Science, University College London, United Kingdom. {olawole.oni.14, e.letier}@ucl.ac.uk

More information

DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage

DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage DECEMBER 2017 Copyright SLBS Saint Lucia Bureau of Standards,

More information

ASPECTS REGARDING THE QUALITATIVE ANALYSIS OF RISKS DUE TO THE OCCURRENCE OF LOW PROBABILITY AND VERY HIGH IMPACT EVENTS

ASPECTS REGARDING THE QUALITATIVE ANALYSIS OF RISKS DUE TO THE OCCURRENCE OF LOW PROBABILITY AND VERY HIGH IMPACT EVENTS Review of the Air Force Academy No 1 (31) 2016 ASPECTS REGARDING THE QUALITATIVE ANALYSIS OF RISKS DUE TO THE OCCURRENCE OF LOW PROBABILITY AND VERY HIGH IMPACT EVENTS Florin-Catalin OLTEANU*, Catalin

More information

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and

More information

Business Auditing - Enterprise Risk Management. October, 2018

Business Auditing - Enterprise Risk Management. October, 2018 Business Auditing - Enterprise Risk Management October, 2018 Contents The present document is aimed to: 1 Give an overview of the Risk Management framework 2 Illustrate an ERM model Page 2 What is a risk?

More information

Feasibility Analysis Simulation Model for Managing Construction Risk Factors

Feasibility Analysis Simulation Model for Managing Construction Risk Factors Feasibility Analysis Simulation Model for Managing Construction Risk Factors Sang-Chul Kim* 1, Jun-Seon Yoon 2, O-Cheol Kwon 3 and Joon-Hoon Paek 4 1 Researcher, LG Engineering and Construction Co., Korea

More information

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management INTERNATIONAL STANDARD ISO/IEC 27005 Second edition 2011-06-01 Information technology Security techniques Information security risk management Technologies de l'information Techniques de sécurité Gestion

More information

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1 SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL Petter Gokstad 1 Graduate Assistant, Department of Finance, University of North Dakota Box 7096 Grand Forks, ND 58202-7096, USA Nancy Beneda

More information

The Impact of Project Type on Risk Timing and Frequency

The Impact of Project Type on Risk Timing and Frequency 1831 The Impact of Project Type on Risk Timing and Frequency Anthony J. PERRENOUD 1, Kenneth T. SULLIVAN 2, and Kristen C. HURTADO 3 1 School of Sustainable Engineering and the Built Environment, Arizona

More information

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management Project Management Professional (PMP) Exam Prep Course 11 - Project Slide 1 Project Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Bounding the Composite Value at Risk for Energy Service Company Operation with DEnv, an Interval-Based Algorithm

Bounding the Composite Value at Risk for Energy Service Company Operation with DEnv, an Interval-Based Algorithm Bounding the Composite Value at Risk for Energy Service Company Operation with DEnv, an Interval-Based Algorithm Gerald B. Sheblé and Daniel Berleant Department of Electrical and Computer Engineering Iowa

More information

D6.2 Risk Assessment Plan

D6.2 Risk Assessment Plan D6.2 Risk Assessment Plan Project number: 730830 Project acronym: Project title: Safe4RAIL Start date of the project: 1 st of October, 2016 Duration: Programme: Safe4RAIL: SAFE architecture for Robust

More information

International Comparisons of Corporate Social Responsibility

International Comparisons of Corporate Social Responsibility International Comparisons of Corporate Social Responsibility Luís Vaz Pimentel Department of Engineering and Management Instituto Superior Técnico, Universidade de Lisboa June, 2014 Abstract Companies

More information

Programmatic Risk Management in Space Projects

Programmatic Risk Management in Space Projects r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework Risk Management Policy Statement ALS recognises that the effective management of risks is a fundamental component of good corporate governance and is vital for the

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project - Traditional, Agile, Extreme 7TH Edition Authors: Robert K. Wysocki

More information

STCW 78: Manila Amendments and Some Risk Assessment Aspects

STCW 78: Manila Amendments and Some Risk Assessment Aspects STCW : Manila Amendments and Some Risk Assessment Aspects Vladimir Loginovsky DSc, Professor, Admiral Makarov State Maritime Academy vl.loginovsky@rambler.ru Abstract: in accordance with Manila Amendments

More information

Means of Improving the Management of Projects Financed by the European Union

Means of Improving the Management of Projects Financed by the European Union Means of Improving the Management of Projects Financed by the European Union Răzvan NISTOR 1 Ioana Natalia MUREŞAN Abstract Projects financed by the European Union generate effects on organizations that

More information

Applied Risk Assessment into EPC Projects By Pulung Susilo Rahardjo

Applied Risk Assessment into EPC Projects By Pulung Susilo Rahardjo Applied Risk Assessment into EPC Projects By Pulung Susilo Rahardjo Theory & Practise Overview: A risk is any factor that has the possibility of causing harm and/or loss the project. A risk is also any

More information

Conceptualisation Stage Continued

Conceptualisation Stage Continued Conceptualisation Stage Continued Conceptualisation Inputs to conceptualisation stage Influencing factors Stakeholder analysis Feasibility Risk Outputs from conceptualisation stage Risk Structured Approach

More information

THE IMPACT OF EUROPEAN PROJECTS ON THE DEVELOPMENT OF THE NORTHWEST REGION OF ROMANIA. Ioana MUREŞAN 1 Răzvan NISTOR 2 Liviu ILIEŞ 3

THE IMPACT OF EUROPEAN PROJECTS ON THE DEVELOPMENT OF THE NORTHWEST REGION OF ROMANIA. Ioana MUREŞAN 1 Răzvan NISTOR 2 Liviu ILIEŞ 3 THE IMPACT OF EUROPEAN PROJECTS ON THE DEVELOPMENT OF THE NORTHWEST REGION OF ROMANIA Ioana MUREŞAN 1 Răzvan NISTOR 2 Liviu ILIEŞ 3 ABSTRACT Project management is a relatively new field and still developing.

More information

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,

More information

Procedures for Management of Risk

Procedures for Management of Risk Procedures for Management of Policy Sponsor: Name of Parent Policy: Policy Contact: Procedure Contact: Vice President Finance and Administration Enterprise Management Policy Vice President Finance and

More information

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty? Objectives RISK MANAGEMENT What is risk? Why should risk be managed? How do we identify risk? How do we manage risk? What is Risk? Definition: An uncertain event or condition that, if it occurs, has a

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

MULTI-PARTY RISK MANAGEMENT PROCESS (MRMP) FOR A CONSTRUCTION PROJECT FINANCED BY AN INTERNATIONAL LENDER

MULTI-PARTY RISK MANAGEMENT PROCESS (MRMP) FOR A CONSTRUCTION PROJECT FINANCED BY AN INTERNATIONAL LENDER MULTI-PRTY RISK MNGEMENT PROCESS (MRMP) FOR CONSTRUCTION PROJECT FINNCED BY N INTERNTIONL LENDER Jirapong Pipattanapiwong and Tsunemi Watanabe School of Civil Engineering, sian Institute of Technology,

More information

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field.

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. Welcome We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. To login to the audio portion of the web conference, dial

More information

Contingency Reserve and Uncertainty

Contingency Reserve and Uncertainty Contingency Reserve and Uncertainty By Carol Elzink 25 June 2012 Overview This whitepaper discusses the importance of, and clarifies Uncertainty and the Funding Reserves required to provide a complete

More information

APPENDIX 1. Transport for the North. Risk Management Strategy

APPENDIX 1. Transport for the North. Risk Management Strategy APPENDIX 1 Transport for the North Risk Management Strategy Document Details Document Reference: Version: 1.4 Issue Date: 21 st March 2017 Review Date: 27 TH March 2017 Document Author: Haddy Njie TfN

More information

Risk Management: Assessing and Controlling Risk

Risk Management: Assessing and Controlling Risk Risk Management: Assessing and Controlling Risk Introduction Competitive Disadvantage To keep up with the competition, organizations must design and create a safe environment in which business processes

More information

Impressions from Applying ISO to an Avalanche Mitigation Project

Impressions from Applying ISO to an Avalanche Mitigation Project Impressions from Applying ISO 31000 to an Avalanche Mitigation Project Bruce Jamieson 1 and Alan Jones 2 1 Dept. of Civil Engineering, University of Calgary, Calgary, Canada 2 Dynamic Avalanche Consulting

More information

PMP (2018) PMBOK 6th Edition PMI. Project Management Professional (PMBOK 6th Edition)

PMP (2018) PMBOK 6th Edition PMI. Project Management Professional (PMBOK 6th Edition) PMI PMP (2018) PMBOK 6th Edition Project Management Professional (PMBOK 6th Edition) Download Full Version : https://killexams.com/pass4sure/exam-detail/pmi-001 QUESTION 903 Which process documents the

More information

Regulation DD-12.0: Risk Assessment Study

Regulation DD-12.0: Risk Assessment Study Regulation DD-12.0: Risk Assessment Study 12.0 Risk Assessment Study 12.1 Guidelines for Conducting Risk Assessment (RA) Study 12.2 Outline for Risk Assessment Study Report 12.3 Specific Fire Protection

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

1. Define risk. Which are the various types of risk?

1. Define risk. Which are the various types of risk? 1. Define risk. Which are the various types of risk? Risk, is an integral part of the economic scenario, and can be termed as a potential event that can have opportunities that benefit or a hazard to an

More information

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

RISK MANAGEMENT PROFESSIONAL. 1   Powered by POeT Solvers Limited RISK MANAGEMENT PROFESSIONAL 1 www.pmtutor.org Powered by POeT Solvers Limited This presentation is copyright 2009 by POeT Solvers Limited. All rights reserved. This presentation is protected by the Nigerian

More information

Key Aspects for Managing a Project

Key Aspects for Managing a Project Key Aspects for Managing a Project What is a Project? Definition: A project is a temporary endeavor undertaken to create a unique product, service or result. The temporary nature of projects indicates

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

Mining. LCC methodology application for equipment replacement strategy definition. Mineração. Abstract. 1. Introduction. 2. Material and method

Mining. LCC methodology application for equipment replacement strategy definition. Mineração. Abstract. 1. Introduction. 2. Material and method http://dx.doi.org/10.1590/0370-44672018720141 Eduardo Cruvinel Kayashima 1,2 https://orcid.org/0000-0002-6377-5079 Ubirajara Marques Junior 1,3 https://orcid.org/0000-0002-5302-9451 1 CSN Mineração - Maintenance

More information

Minimizing Basis Risk for Cat-In- Catastrophe Bonds Editor s note: AIR Worldwide has long dominanted the market for. By Dr.

Minimizing Basis Risk for Cat-In- Catastrophe Bonds Editor s note: AIR Worldwide has long dominanted the market for. By Dr. Minimizing Basis Risk for Cat-In- A-Box Parametric Earthquake Catastrophe Bonds Editor s note: AIR Worldwide has long dominanted the market for 06.2010 AIRCurrents catastrophe risk modeling and analytical

More information

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: PRINCE2 Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 1.0 Exam M QUESTION 1 Identify the missing word(s) from the following sentence. A project is a temporary organization that is

More information

Download slides on SEO Südwest

Download slides on SEO Südwest Risk management in SEO projects Introduction and process model Download slides on SEO Südwest Risk-boosting factors in all projects Lack of time, deadlinesdli Bad acquisition and controlling of key performance

More information

ก ก Tools and Techniques for Enterprise Risk Management (ERM)

ก ก Tools and Techniques for Enterprise Risk Management (ERM) ก ก Tools and Techniques for Enterprise Risk Management (ERM) COSO ERM ISO ERM 31 2554 10:45 12:15.. 301, 302, 307 ก ก COSO Internal Control ERM Integrated Framework Application Technique ISO 31000 Guide

More information

Introduction to Risk for Project Controls

Introduction to Risk for Project Controls Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project

More information

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management Jeff Hollingdale DQS South Africa jeffh@dqs.co.za PAS 55 Risk Management The guideline states: (4.4.7);

More information

Technical Debt (TD) ( Technical Debt (TD) 1 / 23

Technical Debt (TD)   (  Technical Debt (TD) 1 / 23 Technical Debt (TD) https://softwarch.wordpress.com (https://softwarch.wordpress.com) Technical Debt (TD) 1 / 23 Introducing the metaphor Technical Debt The term technical debt was coined by Ward Cunningham.

More information

An Investigative Study of Risk Management Practices of Major U.S. Contractors

An Investigative Study of Risk Management Practices of Major U.S. Contractors An Investigative Study of Risk Management Practices of Major U.S. Contractors Musibau SHOFOLUWE & Tesfa BOGALE Department of Construction Management & Occupational Safety & Health North Carolina Agricultural

More information

machine design, Vol.7(2015) No.4, ISSN pp

machine design, Vol.7(2015) No.4, ISSN pp machine design, Vol.7(205) No.4, ISSN 82-259 pp. 9-24 Research paper ANALYSIS AND RISK ASSESSMENT OF IMPLEMENTATION OF THE AUTOMATED CAR PARKING SYSTEM PROJECT Radoslav TOMOVIĆ, * - Rade GRUJIČIĆ University

More information

GOV : Enterprise Risk Management Policy

GOV : Enterprise Risk Management Policy Name: Responsibility: Complements: Enterprise Risk Management Framework Coordinator, Enterprise Risk Management GOV-080-005: Enterprise Risk Management Policy Draft Date: November 2006; January 2012 Revised

More information

A Utility Perspective: Subsidized Projects How Much Should You Pay?

A Utility Perspective: Subsidized Projects How Much Should You Pay? A Utility Perspective: Subsidized Projects How Much Should You Pay? Joseph P. Kimlinger 1 and Dennis D. Dobbs 2 1 Dynegy Midwest Generation, Inc., 2828 N. Monroe St., Decatur, IL 62526, 2 Consumers Energy,

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

Probabilistic Benefit Cost Ratio A Case Study

Probabilistic Benefit Cost Ratio A Case Study Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case

More information

Offshore & Marine Projects and Risks Management

Offshore & Marine Projects and Risks Management An Intensive 5 Day Training Course Offshore & Marine Projects and Risks Management 02-06 Sep 2018, Dubai 02-OCT-17 R.E.P. ID: 4349 The Registered Education Provider (R.E.P. ID:4349) status with the Project

More information

AN INTEGRATED APPROACH BASED STRUCTURAL MODELLING FOR DEVELOPING RISK ASSESSMENT FRAMEWORK FOR REAL ESTATE PROJECTS IN INDIA

AN INTEGRATED APPROACH BASED STRUCTURAL MODELLING FOR DEVELOPING RISK ASSESSMENT FRAMEWORK FOR REAL ESTATE PROJECTS IN INDIA International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 13, December 2018, pp. 1721-1736, Article ID: IJCIET_09_13_171 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=13

More information