An Investigative Study of Risk Management Practices of Major U.S. Contractors
|
|
- Sharon McGee
- 5 years ago
- Views:
Transcription
1 An Investigative Study of Risk Management Practices of Major U.S. Contractors Musibau SHOFOLUWE & Tesfa BOGALE Department of Construction Management & Occupational Safety & Health North Carolina Agricultural & Technical State University Greensboro, North Carolina, 27411, United States ABSTRACT The construction industry, as in any other business, has its own risks and challenges arising from change which is inherent in construction. Because all risks associated with a construction project cannot be eliminated, there is a need for a risk management process to manage and/or control all types of risks. Risk management has been traditionally applied instinctively, with risks remaining implicit and managed by judgment and informed by experience. Despite the importance of risk management in construction business, little is known regarding the industry s response to risk and the techniques employed for risk management. Most of the research studies undertaken in the construction industry have focused on risk allocation, global project risks and other aspects of risk management. No recent study has specifically focused on evaluating and assessing risk management practices and techniques of general contractors in the United States. The objective of this study was to investigate and assess the current status of risk management practices of major general contractors in United States. Keywords: Risks, Risk Management, Construction, Research, Risk Identification, Analysis. 1. INTRODUCTION The construction industry is a significant component of most countries economies. In the United States, the industry accounts for 7.2 million employees more than 5% of the total non-farm workforce and around 8% of GDP, making it one of the largest sectors of the economy [1]. The industry, as in any other business, has its own risks and challenges arising from change, which is inherent in construction. The construction industry is widely associated with high degree of risk due to the nature of construction, business activities, process, environment and organization [2]. Construction work involves risks and uncertainties regardless of its size, but as the size and complexity of a project increase, the risk involved will also increase. Risk has been defined in many ways and assessed in terms of fatalities and injuries, in terms of probability of reliability or in terms of the likely effects on a project depending on particular industry [3]. Since this study dealt with risks in the construction industry, risk was defined within the project context. Project risk is defined as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective such as time, cost, scope or quality [4]. Similarly, in construction projects each of the objectives will likely be influenced by risk and uncertainty [3]. Risk exists when a decision is expressed in terms of a range of possible outcomes and when known probabilities can be attached to the outcome. On the other hand, uncertainty exists when there is more than one possible outcome of a course of action but the probability of each outcome is not known [3]. The industry is inherently affected by changes in nature and human imperfection. Therefore, the application of risk management allows for effective management of these factors. In addition, since all risks involved in a construction project cannot be eliminated, there is a need for a risk management process to manage all types of risks and to obtain the maximum degree of elimination or control of
2 risks. The increase in size and the complexity of projects have made the ability to manage risks throughout the construction process a central element in preventing unwanted consequences [5]. The objective of project risk management is to increase the probability and impact of positive events and decrease the probability and impact of events that are adverse to project objective [4]. The ultimate purpose of risk management is risk mitigation, which can be accomplished by revising a project plan so that uncertainty can be reduced without any significant effect on the project s objectives [6]. 2. PURPOSE OF STUDY There is no doubt to the fact that risk is inherent in all types of businesses. However, construction industry accounts for a lion share of risks vis-à-vis other large industries such as manufacturing and service industries. Study conducted by Smith, Merna, and Jobling in 2006 shows that construction industry places relatively little importance on technical risks compared to other industries [3]. Similar studies also show that most construction contractors have developed risk management techniques that rely on historical information and previous experience, which help to assess risk but do not help to evaluate the consequences of risk. In addition, most contractors make decisions based on their intuition, judgment or experiences rather than through a formal and systematic risk management process due to lack of familiarity with the concept and methods of risk management [6]. Thus, the purpose of this study was to investigate and assess current risk management practices of major general contractors in the United States. 3. OBJECTIVES OF THE STUDY The study focused on the overall aspects of risk management practices of general contractors. Specifically, the study attempted to gather information on the following factors: Major risks involved in construction projects in the United States Risk management practices and frequency of usage of risk management techniques, including risk identification, risk assessment, risk analysis, risk response and risk monitoring Important barriers to implementing risk management processes. 4. METHODOLOGY This study was conducted to investigate and assess the current status of risk management practices of major general contractors in the United States. The population for the study consisted of top 400 contractors listed in the ENR 2008 publication. Of this population, a sample of 200 participants was randomly selected to participate in the study. A structured survey questionnaire was used to gather information relative to respondents demographics and their risk management practices, including risk identification, risk assessment, risk analysis, risk response and risk monitoring. Also, respondents were asked to indicate what they perceived to be major barriers to implementing risk management system in their organizations. A total of 40 completed questionnaires were returned, yielding a response rate of 20 percent. The data collected was analyzed using SPSS 17 software. Descriptive statistics was used to calculate the mean rating for ranking the important project risks, frequently used risk management practices, and major barriers to implementation of risk management. One-way ANOVA was used to test for significant differences in the perception of project risk importance and perception of barriers to implementation of risk management among contractors with differing work specialty. It was also used to test for significant differences in the practice of risk management techniques among contractors with differing work specialty. To test for any possible relationship between barriers to implementation of risk management and the practice of risk management techniques, a Pearson correlation analysis was performed, using a significance level of 0.05.
3 5. FINDINGS Respondents were asked to identify their top two work specialty areas. Fig. 1 presents the classification of general contractors according to their work specialties. As can be seen, 50% of the respondents engage in commercial and residential work, with 30% in industrial and Highway and Heavy construction. The rest are engaged in commercial and industrial work. Where: W = weight assigned or scale value of respondent s response for the specified project risk: W=1, 2, 3, 4 and 5; F i = frequency of the i th response; n = total number of respondents to the specified project risk; i = response scale value = 1,2,3,4 and 5 for negligible risk, low risk, moderate risk, high risk, and extreme risk, respectively. Analysis of the findings shows that 5 of the 14 construction project risks were ranked by the general contractors to be very important or severe. These risks include: safety, defective design, quality of work, financial risk and incompetence of subcontractors (in descending order). See Table 1. Project Risk Description Mean Rank Figure 1. Classification of contractors based on work specialties. When asked if they implement any form of risk management practices, an overwhelming majority (95%) indicated that they do. They also indicated that their companies have a formal written procedure for risk management. Respondents were also asked to rank 14 identified project risks based on their importance or severity on a scale of 1 to 5; where 5 represents extreme risk, 4 represents high risk, 3 represents moderate risk, and 2 and 1 represent low risk and negligible risk, respectively. The mean rating values were determined using the following formula: Mean rating = i 5 1 W * F n i Eq. (1) Safety Defective design Quality of work Financial risk Incompetence of Subcontractors Claims and disputes Inflation & sudden changes in price Delayed payment Defective material Differing site condition Labor and equipment productivity Labor, equipment & material availability Force majeure/act of God Site access/right of way Table 1. Ranking of construction project risk based on mean rating value An assessment of the risk management practices shows that site visit, check list, and brainstorming were the most frequently used risk identification techniques. Insurance coverage, financial capability and allocation of risks were factors that were widely considered in assessing the severity of a project risk. Qualitative risk analysis methods were found to be the most frequently used among general contractors. Consequently intuition/judgment/experience and
4 decision analysis were the most widely used risk analysis techniques. In terms of risk, response techniques, insurance, reducing likelihood of occurrence and risk transfer were found to be techniques most often used by contractors. Data analysis also shows that contractors frequently used periodic document review as a risk monitoring technique. Lack of joint risk management mechanism, lack of time, and shortage of knowledge on risk management were found to be the top three barriers to implementation of risk management. The one-way ANOVA result did not indicate any significant difference in the perceptions of general contractors of differing work specialty regarding the top ranked five construction project risks. However, significant differences exist in the perceptions of contractors regarding delayed payment (F = 3.384, P = 0.045) and labor, equipment, and material availability (F = 3.842, P = 0.030). Also, there was no statistically significant difference in the practice of risk management techniques among the different contractor groups. However, significant differences exist in their perception of site visit for risk identification, economic condition of the country for risk assessment and use of Monte-Carlo simulation for risk analysis technique. There was no significant difference between the contractor groups in their perception of major barriers to risk management implementation. In order to assess any correlation between barriers to risk management implementation and various risk management practices and techniques, a Pearson correlation analysis was performed. Several correlations were found, including the following: Use of brainstorming correlates with lack of formal risk management, ineffective risk control and monitoring, lack of expertise in risk management, and lack of time. Using site visit, risk data base and case-based approach were correlated with lack of time, lack of joint risk management and lack of expertise in risk management, respectively. Among risk assessment factors, duration of the work, quality of work, and project location correlated with lack of risk consciousness. For risk analysis methods; using qualitative methods correlated with lack of joint risk management. Use of consulting experts correlated with lack of formal risk management, ineffective risk control and monitoring strategies, and lack of risk consciousness. For risk analysis techniques; using decision analysis, algorithm and Mont-Carlo simulation correlated with lack of joint risk management. Decision analysis was further correlated with ineffective risk control and monitoring. Furthermore, using probability analysis and risk premium correlated with unavailability of sound data. Using algorithm also correlated with lack of time. Among the risk response techniques, only risk transfer correlated with unavailability of sound data. However, the analysis found no correlation between risk monitoring techniques and the barriers to risk management implementation. CONCLUSION This study was conducted to assess the risk management practices of major contracting firms in the United States. The study found that most contractors had formal written procedures for risk management, indicating an awareness of the importance of risk management in construction business. Also, contractors of all various work specialties had similar perception towards the importance of project risks. General contractors did not differ in their practices of risk management techniques, except for the use of site visit in risk identification, consideration of economic condition of the country in assessing risk importance, and use of Monte Carlo simulation for risk analysis. During the process of risk management, contractors use a wide variety of techniques in their practice. However, in risk analysis, traditional method of analysis using intuition/judgment/ experience is still the most commonly used technique. Qualitative risk analysis methods are also widely used. The findings of this study parallel other research findings that suggest that only few techniques were currently being used for risk monitoring. Although there was no single dominant barrier to risk management implementation, the lack of joint risk management, risk consciousness, expertise in risk management, and lack of time need to be addressed in order to improve risk management practices.
5 REFERENCES [1] Simonson, K. (2008). Quick facts about the construction industry. Building Material. Retrieved from agcbuild/downloads/quickfacts.pdf [2] Kartam, N. A., & Kartam, S. A. (2001). Risk and its management in the Kuwaiti construction industry: A contractors' perspective. International Journal of project Management, 19, [3] Smith, N. J., Merna, T., & Jobling, P. (2006). Managing risk in construction projects (2 nd ed.). Oxford, UK: Blackwell Publishing [4] PMI (Project Management Institute) (2004). A guide to the project management body of knowledge (PMBOK Guide). Newton Square, PA: Project Management Institute. [5] Maytorena, E., Winch, G. M., Freeman, J., & Kiely, T. (2007). The influence of experience and information search styles on project risk identification performance, IEEE Transactions on Engineering Management, 54(2), [6] Kim, S., & Bejaj, D. (2000). Risk management in construction: An approach for contractors in South Korea. Cost Engineering, 42(1),
RISK IDENTIFICATION ANALYSIS IN CONSTRUCTION PROJECT
RISK IDENTIFICATION ANALYSIS IN CONSTRUCTION PROJECT Dr. Neeraj D. Sharma 1, Hiren A. Rathod 2 Professor, Civil Engineering Department, S.N.P.I.T&R.C., Umrakh, Gujarat, India 1 Asst. Professor, Civil Engg.
More informationManaging Project Risk DHY
Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or
More informationThe Impact of Project Type on Risk Timing and Frequency
1831 The Impact of Project Type on Risk Timing and Frequency Anthony J. PERRENOUD 1, Kenneth T. SULLIVAN 2, and Kristen C. HURTADO 3 1 School of Sustainable Engineering and the Built Environment, Arizona
More informationInternational Journal of Advance Engineering and Research Development A MODEL FOR RISK MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS
Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 06, June -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 A MODEL
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationRISK MANAGEMENT IN CONSTRUCTION PROJECTS 1
RISK MANAGEMENT IN CONSTRUCTION PROJECTS 1 Mubin M. Shaikh 1 Department of Civil Engineering, Maharashtra Institute of Technology, Pune Email: 1 mubin_shaikh@rediffmail.com Abstract Construction industry
More informationRISK MANAGEMENT IN THE DIFFERENT PHASES OF A CONSTRUCTION PROJECT A STUDY OF ACTORS INVOLVEMENT
RISK MANAGEMENT IN THE DIFFERENT PHASES OF A CONSTRUCTION PROJECT A STUDY OF ACTORS INVOLVEMENT Ekaterina Osipova 1 Department of Civil, Mining and Environmental Engineering Luleå University of Technology,
More informationSECTION II.7 MANAGING PROJECT RISKS
SECTION II.7 MANAGING PROJECT RISKS 1. WHAT ARE RISK ANALYSIS AND RISK MANAGEMENT? Any uncertainty in the scope of the Project, the cost of delivery and time scale for delivery, will present either a risk
More informationINTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS. Prof. Reda Abdulaal Vice Presidency for Projects
INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS Prof. Reda Abdulaal Vice Presidency for Projects December 2009 Objectives & Outcomes of this Presentation December 2009 Introduction to Risk Managment
More informationProject Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich
Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements
More informationTHE IMPACT OF EUROPEAN PROJECTS ON THE DEVELOPMENT OF THE NORTHWEST REGION OF ROMANIA. Ioana MUREŞAN 1 Răzvan NISTOR 2 Liviu ILIEŞ 3
THE IMPACT OF EUROPEAN PROJECTS ON THE DEVELOPMENT OF THE NORTHWEST REGION OF ROMANIA Ioana MUREŞAN 1 Răzvan NISTOR 2 Liviu ILIEŞ 3 ABSTRACT Project management is a relatively new field and still developing.
More informationCONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL
CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL Dr Suwarna Torgal Assistatnt Professor, IET, DAVV, Indore ( M P ) ABSTRACT There are many risks events that adversely affect the
More informationInnovative Approach to Risk Analysis and Management of Oil and Gas Sector EPC Contracts from a Contractor s Perspective
Journal of Business & Economics Vol.5 No.2 (July-December 2013) pp. 149-170 Innovative Approach to Risk Analysis and Management of Oil and Gas Sector EPC Contracts from a Contractor s Perspective Sajjad
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationRISK MANAGEMENT IN CONSTRUCTION PROJECTS AND ANALYSIS
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AND ANALYSIS Meti Retesh Shivasangappa 1, Sneha. K. Sawant 2 and Smita Pataskar 3 1 Pursuing ME Construction Management, D.Y. Patil College of Engineering, Akurdi,
More informationMaster Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards
Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards A framework for the integration of risk management into the project and construction industry, following
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationFeasibility Analysis Simulation Model for Managing Construction Risk Factors
Feasibility Analysis Simulation Model for Managing Construction Risk Factors Sang-Chul Kim* 1, Jun-Seon Yoon 2, O-Cheol Kwon 3 and Joon-Hoon Paek 4 1 Researcher, LG Engineering and Construction Co., Korea
More informationAnalysis of Risk Factors for Highway Construction Projects in Egypt
Journal of Civil Engineering and Architecture 9 (2015) 526-533 doi: 10.17265/1934-7359/2015.05.004 D DAVID PUBLISHING Analysis of Risk Factors for Highway Construction Projects in Egypt Mahmoud Mohamed
More informationThe Contractor Perception Towers Industrialised Building System Risk in Construction Projects in Malaysia
American Journal of Applied Sciences 6 (5): 937-942, 2009 ISSN 1546-9239 2009 Science Publications The Contractor Perception Towers Industrialised Building System Risk in Construction Projects in Malaysia
More informationInternational Journal of Advance Engineering and Research Development
Scientific Journal of Impact Factor(SJIF): 3.134 International Journal of Advance Engineering and Research Development Volume 2,Issue 5, May -2015 e-issn(o): 2348-4470 p-issn(p): 2348-6406 Ranking of Risk
More informationclient user GUIDE 2011
client user GUIDE 2011 STEP ACTION Accessing Risk Register 1. Type https://www.scm rms.ca/riskregister/login.aspx 2. Click in the Username field on the Risk Register home page. 3. Type your Username and
More informationRisk assessments of contemporary accidents in construction industry
Risk assessments of contemporary accidents in construction industry Michal Kraus 1,* 1 Institute of Technology and Business in České Budějovice, Department of Civil Engineering, 70 01 České Budějovice,
More informationCost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS
Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs
More informationA Study on Risk Analysis in Construction Project
A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------
More informationRISK MANAGEMENT IN CONSTRUCTION PROJECTS
International Journal of Advances in Applied Science and Engineering (IJAEAS) ISSN (P): 2348-1811; ISSN (E): 2348-182X Vol-1, Iss.-3, JUNE 2014, 162-166 IIST RISK MANAGEMENT IN CONSTRUCTION PROJECTS SUDARSHAN
More informationCEM-520-Construction Contracting. Assessment of Risks Management Perception and Practices of Construction Contractors in Saudi Arabia. Dr. S.
CEM-520-Construction Contracting Assessment of Risks Management Perception and Practices of Construction Contractors in Saudi Arabia Dr. S. Assaf CONSTRUCTION ENGINEERING AND MANAGEMENT By Ali A. Al-Salman
More informationEvery project is risky, meaning there is a chance things won t turn out exactly as planned.
PMBOK 5 Ed. DEI- Every project is risky, meaning there is a chance things won t turn out exactly as planned. percent of runaway projects Did no risk management at all 38 percent did some, and 7 percent
More informationProject Risk Management
Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management
More informationEFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011
EFFECTIVE TECHNIQUES IN RISK MANAGEMENT Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011 Effective Techniques in Risk Management Risk Management Overview Exercise #1 Break Risk IT Exercise #2 Break Risk
More informationAssessment of Risk and Its Application for Residential Construction Projects: A Case Study
Assessment of Risk and Its Application for Residential Construction Projects: A Case Study Prof. Mohan M. Dusane 1, Prof. Pankaj P. Bhangale 2 1 Department of Civil Engineering, MET s IOT-Polytechnic,
More informationProject Management Certificate Program
Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949
More informationKidsafe NSW Risk Management Plan. August 2014
Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name
More informationAMA Implementation: Where We Are and Outstanding Questions
Federal Reserve Bank of Boston Implementing AMA for Operational Risk May 20, 2005 AMA Implementation: Where We Are and Outstanding Questions David Wildermuth, Managing Director Goldman, Sachs & Co Agenda
More informationRisk Assessment in Construction of Highway Project
Risk Assessment in Construction of Highway Project Ankit Vishwakarma, Ashish Thakur, Sushant Singh Department of Civil Engineering, Dr.D.Y.Patil Institute of Engineering and Technology, Pimpri, Pune-411018,
More informationIntroduction to Risk for Project Controls
Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project
More informationEffect of Change Management Practices on the Performance of Road Construction Projects in Rwanda A Case Study of Horizon Construction Company Limited
International Journal of Scientific and Research Publications, Volume 6, Issue 0, October 206 54 ISSN 2250-353 Effect of Change Management Practices on the Performance of Road Construction Projects in
More informationRISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA
RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED
More informationAvailable online at ScienceDirect. Procedia Engineering 161 (2016 )
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 161 (2016 ) 163 167 World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium 2016, WMCAUS 2016 Cost Risk
More informationRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction Sharayu P. Pawar 1, Dr. M.N.Bajad 2, Prof. Mr. R.D. Shinde 3 1PG Student (Construction Management), RMD Sinhgad College of
More informationLCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP
PMP Review Chapter 6 Risk Planning Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study Guide book.
More informationCOST MANAGEMENT TECHNIQUES PRACTICES BY BUILDING CONTRACTORS NETWORK IN TAMILNADU
Volume 117 No. 9 2017, 145-149 ISSN: 1311-8080 (printed version); ISSN: 1314-3395 (on-line version) url: http://www.ijpam.eu doi: 10.12732/ijpam.v117i9.26 ijpam.eu COST MANAGEMENT TECHNIQUES PRACTICES
More informationEvaluation of Construction Risks Impact on Construction Project Manager s
International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 10, Issue 5 (May 2014), PP.01-05 Evaluation of Construction Risks Impact on Construction
More informationPresented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.
Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An
More informationChapter-8 Risk Management
Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not
More informationWe will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field.
Welcome We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. To login to the audio portion of the web conference, dial
More informationCOST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING
ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,
More informationIntegrated Management System For Construction Projects
Integrated Management System For Construction Projects Abbas M. Abd 1, Amiruddin Ismail 2 and Zamri Bin Chik 3 1 Correspondence Authr: PhD Student, Dept. of Civil and structural Engineering Universiti
More informationProgrammatic Risk Management in Space Projects
r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands
More informationMapping Table of Comparison Proposed Section 600, Provisions of Non-Assurance Services to an Audit Client
Agenda Item 2-H Mapping Table of Comparison Proposed Section 600, Provisions of Non-Assurance Services to an Audit Client 290.154 Firms have traditionally provided to their audit clients a range of non-assurance
More informationPoor Man s Approach to Monte Carlo
Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).
More informationHamdouraby SY ESKEMA PhD PROGRAM
Hamdouraby SY ESKEMA PhD PROGRAM RISK IMPACT EVALUATION IN INTERNATIONAL CONSTRUCTION PROJECTS: THE CASE OF WEST AFRICA PRESENTATION OUTLINE RESEARCH BACKGROUND PROBLEM STATEMENT RESEARCH PHILOSOPHY RESEARCH
More informationA Risk Management Approach to Address Construction Delays from Client Aspect
1497 A Risk Management Approach to Address Construction Delays from Client Aspect Abdullah Albogamy 1, Nashwan Dawood 2 and Darren Scott 3 School of Science & Engineering, Teesside University, UK 1 PhD
More informationCOMPARATIVE ANALYSIS OF METHODOLOGIES FOR RISK MANAGEMENT OF STRATEGIC INVESTMENT PROJECTS
COMPARATIVE ANALYSIS OF METHODOLOGIES FOR RISK MANAGEMENT OF STRATEGIC INVESTMENT PROJECTS Dragana Vukovic 1 ; Jelena Joksic 2 ; Ph.D. Djordje Mihailovic 3 1 The College of Applied Technical Science Arandjelovac,
More informationProject Risk Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within
More informationProject Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP
Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive
More informationRisk Management Policy and Framework
Risk Management Policy and Framework Risk Management Policy Statement ALS recognises that the effective management of risks is a fundamental component of good corporate governance and is vital for the
More informationTable of Contents Advantages Disadvantages/Limitations Sources of additional information. Standards, textbooks & web-sites.
Table of Contents Table of Contents 1. Consequence Analysis & Risk Reduction Option Selection 1.1. A description of the techniques, including its purpose 1.1.0.. Introduction 1.1.0.3. Consequence Analysis
More informationDownload slides on SEO Südwest
Risk management in SEO projects Introduction and process model Download slides on SEO Südwest Risk-boosting factors in all projects Lack of time, deadlinesdli Bad acquisition and controlling of key performance
More informationRISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS
N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...
More informationUPDATED IAA EDUCATION SYLLABUS
II. UPDATED IAA EDUCATION SYLLABUS A. Supporting Learning Areas 1. STATISTICS Aim: To enable students to apply core statistical techniques to actuarial applications in insurance, pensions and emerging
More informationCHAPTER 6 DATA ANALYSIS AND INTERPRETATION
208 CHAPTER 6 DATA ANALYSIS AND INTERPRETATION Sr. No. Content Page No. 6.1 Introduction 212 6.2 Reliability and Normality of Data 212 6.3 Descriptive Analysis 213 6.4 Cross Tabulation 218 6.5 Chi Square
More informationAssessing The Financial Literacy Level Among Women in India: An Empirical Study
Assessing The Financial Literacy Level Among Women in India: An Empirical Study Bernadette D Silva *, Stephen D Silva ** and Roshni Subodhkumar Bhuptani *** Abstract Financial Inclusion cannot be achieved
More informationCost Overrun Assessment Model in Fuzzy Environment
American Journal of Engineering Research (AJER) e-issn : 2320-0847 p-issn : 2320-0936 Volume-03, Issue-07, pp-44-53 www.ajer.org Research Paper Open Access Cost Overrun Assessment Model in Fuzzy Environment
More informationImpressions from Applying ISO to an Avalanche Mitigation Project
Impressions from Applying ISO 31000 to an Avalanche Mitigation Project Bruce Jamieson 1 and Alan Jones 2 1 Dept. of Civil Engineering, University of Calgary, Calgary, Canada 2 Dynamic Avalanche Consulting
More informationFinal draft RTS on the assessment methodology to authorize the use of AMA
Management Solutions 2015. All rights reserved. Final draft RTS on the assessment methodology to authorize the use of AMA European Banking Authority www.managementsolutions.com Research and Development
More informationScienceDirect. A Study of Construction Claim Management Problems in Malaysia
Available online at www.sciencedirect.com ScienceDirect Procedia Economics and Finance 23 ( 2015 ) 63 70 2nd GLOBAL CONFERENCE on BUSINESS, ECONOMICS, MANAGEMENT and TOURISM, 30-31 October 2014, Prague,
More informationRISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited
RISK MANAGEMENT PROFESSIONAL 1 www.pmtutor.org Powered by POeT Solvers Limited This presentation is copyright 2009 by POeT Solvers Limited. All rights reserved. This presentation is protected by the Nigerian
More informationANALYSIS OF RISK MANAGEMENT IN RESIDENTIAL BUILDING USING PRIMAVERA WEB SOFTWARE
ANALYSIS OF RISK MANAGEMENT IN RESIDENTIAL BUILDING USING PRIMAVERA WEB SOFTWARE Mr. DARSHAN E 1,Mr. ARUN KUMAR C J 2,Mr. RAJEEVA S J 3,Dr. G.NARAYANA 4 1 PG STUDENT, Department of Civil Engineering, SJCIT
More informationManaging Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways
Managing Project Risks Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways Abstract Nearly all projects have risks, both known and unknown. Appropriately managing
More informationCost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE
Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK
ANNEXURE A ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK CONTENTS 1. Enterprise Risk Management Policy Commitment 3 2. Introduction 4 3. Reporting requirements 5 3.1 Internal reporting processes for risk
More informationBetter decision making under uncertain conditions using Monte Carlo Simulation
IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics
More informationRisk Assessment and Handling in Ethiopian Commercial Banks: A Comparative Study of Public and Private Sectors
Risk Assessment and Handling in Ethiopian Commercial Banks: A Comparative Study of Public and Private Sectors 1. Introduction ISSN 2278 0211 (Online) Abdella Kossa Lecturer, Department of Management, College
More informationCHPATER - 4 RESEARCH MEHTODOLOGY
CHPATER - 4 RESEARCH MEHTODOLOGY 4.1 Introduction: Considering the complexity of investment decision making as well as the structure of mutual fund industry in India, the aim of this thesis is to survey
More informationEvaluating the impact of risk factors on construction projects cost in Nigeria
The International Journal Of Engineering And Science (IJES) Volume 3 Issue 6 Pages 10-15 2014 ISSN (e): 2319 1813 ISSN (p): 2319 1805 Evaluating the impact of risk factors on construction projects cost
More informationRESEARCH ON THE SOURCES OF RISK FOR AGRICULTURAL COOPERATIVES IN NORTHEASTERN BULGARIA
Trakia Journal of Sciences, Vol. 15, Suppl. 1, pp 206-215, 2017 Copyright 2017 Trakia University Available online at: http://www.uni-sz.bg ISSN 1313-7069 (print) ISSN 1313-3551 (online) doi:10.15547/tjs.2017.s.01.038
More informationAn Approach to risk quantification in construction projects using EMV analysis
An Approach to risk quantification in construction projects using EMV analysis R. C. WALKE * Research student for Ph. D. course, V. J. T. I., Mumbai University PROF. V.M. TOPKAR Head, Civil and Environmental
More informationUnit 9: Risk Management (PMBOK Guide, Chapter 11)
(PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should
More informationPLANNING AND BUILDING QUALIFIABLE EMBEDDED SYSTEMS: SAFETY AND RISK PROPERTIES ASSESSMENT FOR A LARGE AND COMPLEX SYSTEM WITH EMBEDDED SUBSYSTEMS
PLANNING AND BUILDING QUALIFIABLE EMBEDDED SYSTEMS: SAFETY AND RISK PROPERTIES ASSESSMENT FOR A LARGE AND COMPLEX SYSTEM WITH EMBEDDED SUBSYSTEMS Nuno Silva (1), Rui Lopes (1), Ricardo Barbosa (1) (1)
More informationWC-5 Just How Credible Is That Employer? Exploring GLMs and Multilevel Modeling for NCCI s Excess Loss Factor Methodology
Antitrust Notice The Casualty Actuarial Society is committed to adhering strictly to the letter and spirit of the antitrust laws. Seminars conducted under the auspices of the CAS are designed solely to
More informationAN INTEGRATED APPROACH BASED STRUCTURAL MODELLING FOR DEVELOPING RISK ASSESSMENT FRAMEWORK FOR REAL ESTATE PROJECTS IN INDIA
International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 13, December 2018, pp. 1721-1736, Article ID: IJCIET_09_13_171 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=13
More informationRisk Management. CITS5501 Software Testing and Quality Assurance
Risk Management CITS5501 Software Testing and Quality Assurance (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, 2005) 2017, Semester 1 Definition of Risk A risk is a
More informationRISKS AND RISK TREATMENTS IN PUBLIC PRIVATE PARTNERSHIP PROJECTS
RISKS AND RISK TREATMENTS IN PUBLIC PRIVATE PARTNERSHIP PROJECTS Bing Li, A. Akintoye and C.Hardcastle School of Built and Natural Environment, Glasgow Caledonian University, Glasgow G4 0BA, UK Public
More informationStudy of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun
Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun A.G.D.Premalal 1, R.K.P.C.B. Mudalige 1 and S.N.Malkanthi 1 1 Department of Civil and Environmental
More informationRISK MANAGEMENT LECTURE 5. Ahmed Elyamany
RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.
More informationA Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach
A Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach By Ahmed Magdi Ibrahim Aboshady A Thesis Submitted to the Faculty of Engineering at Cairo University In Partial Fulfillment
More informationRisk Management Made Easy. I. S. Parente 1
Risk Management Made Easy I. S. Parente 1 1 Susan Parente, MS Engineering Management, PMP, CISSP, PMI-RMP, PMI-ACP, CSM, CSPO, PSM I, ITIL, RESILIA, CRISC, MS Eng. Mgmt.; S3 Technologies, LLC, Principal
More informationThe Certified Islamic Specialist in Risk Management
1 The Certified Islamic Specialist in Risk Management Introduction: Due to the sheer nature of their varied and complex activities, banks are often exposed to an array of risks such as credit risks, market
More informationISO/DIS 9001:2015 Risk-Based Thinking
ISO/DIS 9001:2015 Risk-Based Thinking Whittington & Associates, LLC 6175 Hickory Flat Highway, Suite 110-303, Canton, GA 30115 www.whittingtonassociates.com 770-517-7944 Version 1.0: 01/10/15 2015 Whittington
More informationScouting Ireland Risk Management Framework
No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015
More informationAN INTRODUCTION TO RISK CONSIDERATION
AN INTRODUCTION TO RISK CONSIDERATION Introduction This cookbook aims at recalling basic concepts and providing simple tools and possibilities of applying the "considering of risks and opportunities" in
More informationMohammad Chizari and Ahmad Yaghoubi Tarbiat Modarres University. James R. Lindner Texas A&M University
DOI: 10.5191/jiaee.2003.10105 Perceptions of Rural Livestock Insurance among Livestock Producers and Insurance Specialists in Isfahan Province, Iran Mohammad Chizari and Ahmad Yaghoubi Tarbiat Modarres
More informationThe Risky Business of. Risk Management
The Risky Business of Risk Management 1 About Me: Jan Holt, PMP Project Management Professional (PMP) since 2005 Project Management Institute (PMI) Michiana Chapter President PMP Prep Class Instructor
More informationPost-Class Quiz: Information Security and Risk Management Domain
1. Which choice below is the role of an Information System Security Officer (ISSO)? A. The ISSO establishes the overall goals of the organization s computer security program. B. The ISSO is responsible
More informationDeveloping a Bankruptcy Prediction Model for Sustainable Operation of General Contractor in Korea
Developing a Bankruptcy Prediction Model for Sustainable Operation of General Contractor in Korea SeungKyu Yoo 1, a, JungRo Park 1, b,sungkon Moon 1, c, JaeJun Kim 2, d 1 Dept. of Sustainable Architectural
More informationChapter 9: Reducing Project Duration 4KF3
Lecture Notes Options for Accelerating Project Completion Unconstrained Resources o Adding resources o Outsourcing o Overtime o Core project team o Do it twice Constrained Resources o Fast-tracking o Critical-chain
More informationZurich Hazard Analysis (ZHA) Introducing ZHA
Introducing ZHA March 8, 2019 21st Annual Master Property Program Annual Loss Control Workshop Michael Fairfield, CSP Zurich North America - Risk Engineering Introducing ZHA Objectives After this introduction,
More informationDeveloping Risk Source and Risk Event Breakdown Structures: A New Approach to Risk Identification in Complex Environments
Abdirad, H., Nazari, A., Gholizadeh, P., & Ansari, A. (2012). Developing" Risk Source" and" Risk Event" Breakdown Structures: A New Approach to Risk Identification in Complex Environments. International
More information