SCENARIO-BASED CONTRACTS: USING SCENARIO PLANNING AND VALUATION METHODS TO MANAGE RISK IN ALTERNATIVE DELIVERY METHODS. Adjo A. Amekudzi, Ph.D.

Size: px
Start display at page:

Download "SCENARIO-BASED CONTRACTS: USING SCENARIO PLANNING AND VALUATION METHODS TO MANAGE RISK IN ALTERNATIVE DELIVERY METHODS. Adjo A. Amekudzi, Ph.D."

Transcription

1 SCENARIO-BASED CONTRACTS: USING SCENARIO PLANNING AND VALUATION METHODS TO MANAGE RISK IN ALTERNATIVE DELIVERY METHODS Adjo A. Amekudzi, Ph.D. Associate Professor, School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta, GA 30332, Tel: , Fax: , Christy Mihyeon Jeon Graduate Research Assistant, School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta, GA 30332, Tel: , Fax: , Total Word Count: 4,744 Submission Date: July 8, 2005

2 Amekudzi and Jeon 2 ABSTRACT In both developing and developed economies, several governments are considering alternative delivery methods such as design-build (DB), build-operate-transfer (BOT), and build-ownoperate-transfer (BOOT) schemes for multibillion-dollar mega infrastructure projects. These schemes come with various political, financial, and legal risks in both socioeconomic settings. This paper discusses sources of risk in the Channel Tunnel project, one of the most notable megaprojects in the world, and introduces applications of scenario planning and valuation methodologies to manage selected risks in BOT and BOOT schemes by creating scenario-based or dynamic contracts. Such contracts can insulate better the contractor and create enable host governments to provide more favorable conditions for infrastructure systems delivery. KEY WORDS Alternative Delivery Methods, Risk Management, Asset Management, Scenario Planning, Channel Tunnel

3 Amekudzi and Jeon 3 INTRODUCTION In both developing and developed economies, several governments are considering alternative delivery methods such as design-build (DB), build-operate-transfer (BOT), and build-ownoperate-transfer (BOOT) schemes for multibillion-dollar mega infrastructure projects. In the United States, the design-build (DB) method of contracting has been increasing steadily: the volume of domestic DB contracts has grown from $6 billion to $56 billion since 1982 and now represents 23 percent of the non-residential U.S. market (1). Also, highways, tunnels, and light rail systems are increasingly being built through build-operate-transfer (BOT) concession agreements in which private companies construct and collect tolls on new infrastructure for a mutually agreed-upon period of time (2). These schemes, DB, BOT, and BOOT, come with various political, financial, and legal risks in both socioeconomic settings. This paper discusses sources of risk in the Channel Tunnel project, one of the most notable megaprojects in the world, and introduces applications of scenario planning and valuation methodologies to manage selected risks in BOT and BOOT schemes by creating scenario-based or dynamic contracts. Such contracts can insulate better the contractor and enable host governments to provide more favorable conditions for infrastructure systems delivery. METHODOLOGY The intent of this paper is to demonstrate how scenario planning methodology coupled with valuation techniques can be used to manage risks associated with large-scale civil infrastructure projects that are procured through alternative delivery methods. In recent decades, several megaprojects have been completed all over the world. Megaprojects are projects worth several billions of dollars that typically have significant cost overruns and lower-than-predicted revenues, e.g. the Channel Tunnel that connects the United Kingdom to the European mainland, the Boston Central Artery Tunnel (CA/T) Project, Mexico City metro, and Malaysia s North-South Expressway (3). Table 1 shows examples of megaprojects and their associated construction cost overruns and lower-than-expected revenues. Some of these projects have been procured using alternative delivery methods. For example, as shown in Table 1, the Channel Tunnel was a BOOT project and the Malaysia s North-South Highway used a BOT scheme to finance them through private-sector involvement (3, 4). In a BOT structure, entrepreneurs form consortia to make substantial equity investments in a special-purpose project company, which then builds the facility, operates it long enough to pay back the debt finance, and eventually transfers rights and responsibilities of further operations of the facility to the government. On the other hand, a BOOT scheme refers to situations where the project company also owns the facility throughout the period (3). Also, the DB method, in which the agency or owner holds a single contract with a single entity for both the design and construction of a project, has been applied to mass transit rail projects, e.g., the Alameda Corridor rail project in Los Angeles and the Hudson Bergen light rail in New Jersey (5, 6). Megaprojects have various risks including political, financial, cultural, and legal risks. The United Nations Industrial Development Organization (UNIDO) identified two major categories of primary risks for large-scale BOT projects: (1) general risks related to the macroenvironmental factors of the host country and (2) project-specific risks controlled by the project participants (7). General risks can be categorized as (1) political risks, e.g., sovereign risks and instability risks; (2) financial risks, e.g., currency devaluation, foreign exchange fluctuation,

4 Amekudzi and Jeon 4 fluctuation of interest rates, and inflation; and (3) legal risks, e.g., the host country s changes in the legal system such as taxation and regulations. Project-specific risks can be classified by specific risks pertaining to the different project stages: development, construction, and operation. Delays in project completion and cost overruns, caused by technical difficulties, poor management, or a combination of both, are general types of the construction stage risks. On the other hand, increased cost of operation and insufficient revenue from the completed project can be identified as common types of operation stage risks (7). Malaysia s North-South Highway project, for example, has faced six major sources of risks, including foreign exchange and interest risk, lack of equity, cost overruns, completion delays, force majeure, and revenue risk (4). Such risks contribute to the significant cost overruns that have been experienced by several megaprojects in the past several decades. For megaprojects that are procured using alternative delivery methods, opportunities exist for managing these risks using scenario-based methodologies combined with valuation techniques to explore the impacts of existing uncertainties or risk factors (for example, project delivery time, projected demand for the project, inflation etc.) on the project outcome. In essence, for each risk factor, plausible scenarios can be developed to capture the boundary conditions that might occur (e.g., on-time project delivery versus delayed delivery, high project demand versus low demand, and high inflation versus low inflation), and valuation methods can be applied to assess the impacts of these conditions on the project value. In particular, for BOT or BOOT projects, such scenarios can be used to evaluate feasible times for recouping project investments (i.e., the operation period) before the facility is transferred to the owner. The operate period would be longer in less favorable conditions i.e. conditions with project delays, low system demand and high inflation, for example. With a better handle on the impacts of these risk factors on the project value, contracts can be written to address different plausible scenarios that might reasonably occur -- and the scenarios that most closely match the actual outcome of the project can then be called into effect to protect both the contractor and government owner of the project. In the sections below, the proposed scenario/valuation methodology is applied to the Channel Tunnel project. Using the Channel Tunnel project as a case study, major system risks are identified, and plausible boundary conditions for these risk factors (e.g., time for project delivery, system demand, and inflation) are determined. These boundary conditions are then used to craft plausible scenarios for the system that capture plausibly favorable and nonfavorable conditions for the contractor and owner. The value of the system over its life cycle is then estimated based on these plausible scenarios to determine several likely values that the project might assume during its life cycle based on the prevailing risks. A discussion follows explaining how these values can be used to determine realistic operation times in the BOT or BOOT contract for the various plausible scenarios -- both to protect the contractor and create more favorable conditions for the government owner to attract contractors for such projects in the future. CASE STUDY As more multibillion-dollar mega infrastructure projects are being proposed and constructed around the world, it has become clearer that such projects tend to show noticeably poor performance records with respect to economy, environment, and public support (2). These projects are easily exposed to various risks such as project delays, inflation, cost overruns, and lower demand or revenues than predicted. For instance, the Channel Tunnel, opened in 1994 at a

5 Amekudzi and Jeon 5 construction cost of $12.6 billion (1997 prices converted to US$ at $1.59 to 1 British Pound -- March 20, 1997), has faced several near-bankruptcies resulting from construction cost overruns of 80 percent due to financing costs, 140 percent higher than what was predicted; and revenues less than half of those forecast (3, 8). This section discusses those risk factors and applies valuation methodology to estimate the difference in facility value based on the projected and actual conditions and characteristics of the Channel Tunnel project. Project Background The Channel Tunnel, also known as the Chunnel and Eurotunnel, opened in 1994, and is the longest underwater rail tunnel in Europe connecting France and the UK (3). This project is the flagship of private financing in the transport sector and was a build-own-operate-transfer (BOOT) project with a concession, originally lasting fifty-five years, later extended to sixty-five years as part of a settlement regarding responsibility for cost overruns, and later again extended to ninety-nine years in an attempt to secure project viability (3). As the concessionaire, Eurotunnel manages the infrastructure of the Channel Tunnel, operates accompanied truck shuttle and passenger shuttle services between UK and France, and earns toll revenue from other train operators, such as Eurostar, which use the Tunnel (9). The total investment costs for the project were predicted at $7.1 billion (1997 prices) in 1987, but actual costs turned out to be $12.6 billion (1997 prices) resulting in a cost overrun of 80 percent (3). Moreover, the actual financing cost turned out to be $ 18.6 billion (1997 prices), 140 percent higher than the forecast $7.8 billion (1997 prices) (3, 8). Traffic forecasting for the Channel Tunnel done at the time of the decision to construct the tunnel estimated 15.9 million passengers on the Eurostar trains in the opening year while actual traffic in 1995, the first full year of operations, was 2.9 million passengers, only 18 percent of the number of passengers predicted. In 2001, after more than six years of operations, the number of passengers had grown to 6.9 million, which was still 43 percent of the original estimate for the opening year. Rail freight traffic was projected at 7.2 million gross tonnes for the opening year while actual traffic was 1.3 million gross tonnes in 1995, 18 percent of the freight projected, and had grown to 2.4 million tonnes, 33 percent of the freight projected in 2001 (3). Table 2 shows the conspicuous differences between predicted and actual project delivery timeline, travel demand, investment/financing costs, and operating profit. Valuation Based on the project records presented in Table 2, this section analyzes the economic value of the project focusing on the differences between the envisaged and actual worth of the project. The net present value (NPV) of the project, the traditional method for quantifying the financial attractiveness of investment, was selected as the value criterion and calculated from the sum of the present values (today's dollars) of the annual cash flows minus the initial investment. These annual cash flows, discounted or adjusted by integrating uncertainty and time value of money, are the net benefits estimated from revenues minus costs (10). The predicted and actual NPVs for the Channel Tunnel project were generated by following three steps (10). First, the size and timing of the expected future cash flows were identified since we already know the projected and actual investment cost of the project ($7.1 billion versus $12.6 billion). The life span of this project is considered to be 120 years because

6 Amekudzi and Jeon 6 the Tunnel lining was designed for a 120-year life, according to the Channel Tunnel construction facts, which means that no significant deterioration in performance is expected to occur over this period (11). After opening a year late in May 1994, its first and second year of operation produced a loss of $2.1 billion (12). Operating profit of the project, calculated by subtracting operating expenditure from total turnover, has been annually reported as approximately $300 million per year since Cash flow without actual records, including operating profit for the years and , is assumed to have a regular cycle and repeat the same ups and downs of the operating profit for the 7-year period of operations from 1998 through Based on the available actual cash flow, the operating profit that might have been predicted before the project was started was also estimated based on the ratio of the actual demand to predicted demand for Eurostar, the passenger rail system that uses the Tunnel. Second, the discount rate or the estimated rate of return for the project was determined to convert a future amount of money to its equivalent present value. In 2004, Eurotunnel reported an implicit discount rate of 7.2% determined in accordance with the existing standard on the basis of the Eurotunnel constituting a single income generating unit and using the adjusted present value (APV) methodology (13). The real discount rate of 7.2% per year was adjusted with an average inflation rate of 2.75%, for the period from (14), and thus 10.15% was considered an appropriate inflation-adjusted interest rate for calculating NPVs of this project (15). Third and lastly, the NPVs based on predicted and actual project records were calculated using the generic NPV equation: n n Bt Ct Operating Pr ofit NPV = ( ) = C + t 0 t t= 0 (1 + r) t= 1 (1 + r) where B = benefit, C = cost, r = discount rate, t = 0,1,, n, n = life span of the project (n=120), C 0 = investment cost. Predicted and Actual NPVs of the Channel Tunnel Table 3 reveals the differences between predicted and actual NPVs of the Channel Tunnel project based on predicted and actual cash flows. Cash flows are assumed to repeat the same upand-down cycles of the operating profit for the 7-year period from 1998 through The table shows cash flows for the first seventeen years of facility operation through While the predicted NPV of the project is negative $200.2 million, the actual NPV turns out to reach the value of negative $11.8 billion, about sixty times lower than the projected value, due to significant construction cost overruns (80%) and lower-than-expected revenues. Therefore, we can conclude that the investment for the project can never be recouped during the 120-year project life cycle and the project will not possibly attain the status of economic sustainability with the expected cash flows. It should be noted that we could only quantify benefits that accrue from the operation of the Tunnel excluding any other social or environmental benefits such as higher quality of life, better air quality from decreased usage of other modes of transportation,

7 Amekudzi and Jeon 7 etc. Figure 1 graphically captures all the project costs and revenues, e.g., initial construction cost and annual operating costs, annual revenues, and operating profit of the project. Sensitivity Analysis When conducting cost-benefit analysis, sensitivity analysis is generally performed to identify those parameters that are both uncertain and for which the project decision is sensitive (16). This section applies sensitivity analysis to capture the impacts of various risk factors of the Channel Tunnel project on the value of the project. Using plausible bounds for the projected risk parameters, several plausible scenarios are developed. The project value (life cycle) for each plausible scenario is then estimated. As presented earlier, the Channel Tunnel experienced a one-year delay for project delivery, severe construction cost overruns, and lower-than-predicted revenues. In addition, the inflation rate is a classic type of the financial risk, in particular, for longer and large-scale projects such as the Channel Tunnel. Sensitivity and risk analysis are conducted following three steps using the base case of the actual NPV of the project. First, plausible boundary conditions based on those risk factors, (i.e., time for project delivery, travel demand, and inflation), are identified and the resulting scenarios are used to depict favorable and non-favorable conditions that the project may face. Second, the value (NPV) of the system over its life cycle is calculated based on these likely scenarios, to determine several plausible values that the project might assume based on the prevailing risks. Finally, a discussion is presented to explain how these values might be used to determine realistic operation times in the BOT or BOOT contract for the various plausible scenarios that might occur, both to protect the contractor and create more favorable conditions for the owner to attract contractors for such projects in the future. Table 4 presents the impacts of several plausible conditions on the value of the project. These boundary conditions are determined based on selected risk factors as follows: (1) delayed project delivery (two years) versus earlier delivery (one year); (2) low demand (only 20 percent of what was originally predicted) versus high demand (reaching the predicted demand in the first year of operation), and (3) high inflation (5% per year) versus low inflation (1% per year). Meanwhile, the base scenario for the comparative analysis is determined based on the actual conditions of the Channel Tunnel. Generally speaking, sensitivity analysis is performed when the project is in the planning stage to help effective project decisions by incorporating possible uncertainty factors in the project analysis. This paper, however, focuses on an analysis based on actual project records, e.g., project delivery, demand, inflation rate, etc., and presents plausible scenarios around the actual project conditions to assess how prevailing risks might have caused the project outcomes to vary. Thus, we set the actual situation of the Channel Tunnel: one year of delayed project delivery, 43 percent of the demand originally predicted, and an inflation rate of 2.75%, as the base scenario. In the case of the project timeline, the value of the project substantially decreases, i.e., -$15,088M down from -$11,836M (base case): corresponding to a 27.5% decrease. This is because if the project were completed two years later, additional construction costs for financing extra two years, land acquisition fees, and engineering fees for two extra years would be added. In addition, two years of revenue and positive social benefit would be lost. On the other hand, the NPV of the project would significantly increase, i.e., - $9,765M up from -$11,836M (base case) corresponding to a 17.5% increase, in the case where the project was completed one year early, i.e., if the project was finished just in time in If system demand turned out to be only 20 percent of the predicted demand, the value of the project

8 Amekudzi and Jeon 8 would decrease notably, i.e., -$13,260M down from -$11,836M (base case) corresponding to a 12% decrease, because of much lower revenues. When system demand reaches the predicted demand, the NPV of the project considerably improves: -$7,653M corresponding to a 35.3% increase relative to the base case. While the NVP of the project decreases by 14% in the case where the annual inflation rate is as high as 5 percent, the value of the project increases notably by 19.4% when the inflation rate is as low as 1 percent. As shown in Table 5, the NPV of the project ranges significantly from 38% less than the actual value to 60% above the actual value if the lower and upper limits respectively of project delivery time, project demand, and inflation are used to craft plausible boundary scenarios. Part of the intent of BOT and BOOT contracts is to determine feasible time frames for the concession holder or contractor to operate the project, in order to recoup the amounts invested into the project, before turning over the project to the government (owner). It is notable that subsequent to the opening of the Channel Tunnel project, the operation period in the BOOT contract has been revised twice to enable the project to achieve economic sustainability, as described in the Project Background section above. Such revisions have caused negative publicity for the project in general, indicating that project finances have not been managed effectively, and calling into question the economic sustainability of the project. The scenario/valuation analysis conducted in this paper is the type of analysis that could be used during the planning stages of a megaproject, such as the Channel Tunnel, to determine alternative plausible values that the project might assume, given prevailing risks. Such alternative values could then be used to calculate feasible operating times that would allow the contractor to recoup their investments made in the project, in a range of favorable to non-favorable conditions. The BOOT contract would thus contain several plausible operation times that correspond to plausible prevailing conditions that could occur after the project was opened for operation. The contractor would then be allowed to select the operation time most closely corresponding with actual project operating conditions -- so that the contractor might recoup the original investment without the need for revising the operating period after the fact (which causes negative publicity and detracts from a positive image for megaprojects). In essence, what is being proposed here is a scenariobased contract of sorts that proactively considers the most dominant risk factors influencing project value, and builds language into the contract to manage such risks. Such contracts would enable contractors to feel more secure in undertaking BOT and BOOT type projects that are laden with uncertainty. Such contracts would also help foster a more positive image for governments in that they would be willing to consider the existing uncertainties in megaprojects up front and proactively accommodate their resulting risks in the BOT or BOOT contract. LIMITATION OF STUDY This study introduces the application scenario planning combined with valuation methodologies to manage major risks of large-scale civil infrastructure projects that are procured using BOT or BOOT schemes. Several assumptions are made to assess the value of the Channel Tunnel. First, the future cash flow for the project is expected to have a regular cycle and repeat the same ups and downs with respect to operations for the 7-year period of operations from 1998 through Second, the operating revenues that would have been projected before the project was started are estimated based on the ratio of the actual demand to the predicted demand for Eurostar. Third and lastly, it should be noted that we could only quantify benefits that come from the operation

9 Amekudzi and Jeon 9 of the Tunnel excluding any other social or environmental benefits such as a higher quality of life, and better air quality from decreased usage of other modes of transportation, etc. SUMMARY In both developing and developed economies, several governments are considering alternative delivery methods such as design-build (DB), build-operate-transfer (BOT), and build-ownoperate-transfer (BOOT) schemes for multibillion-dollar mega infrastructure projects. These schemes come with various political, financial, and legal risks in both socioeconomic settings. The intent of this paper is to demonstrate how scenario planning methodology can be combined with valuation techniques to manage risks associated with a large-scale civil infrastructure projects procured through alternative delivery methods. The Channel Tunnel is used as a case study. Plausible scenarios are developed to capture the boundary conditions that might occur based on various risk factors, (e.g., on-time project delivery versus delayed delivery, high demand versus low demand, and high inflation versus low inflation), and valuation methods are applied to assess the impacts of these risks on the project value, the net present value (NPV) of the project. In particular, for BOT or BOOT projects, such scenarios can be used to evaluate feasible times for recouping project investments (i.e., the operation period) before the facility is transferred to the owner. The case study analysis shows that the operate period would be longer in less favorable conditions i.e. conditions with project delays, low system demand, and high inflation, for example. With a better handle on the impacts of these risk factors on the project value, contracts can be written to address different plausible scenarios that might reasonably occur -- and the scenarios that most closely match the actual outcome of the project can be called into effect to protect both the contractor and government owner of the project. Such scenario-based or dynamic contracts can insulate the contractor better and allow host governments to provide more favorable conditions for infrastructure systems delivery. ACKNOWLEDGEMENT This work was supported by the National Science Foundation (NSF) under Grant No : Application of Portfolio Theory and Sustainability Metrics to Civil Infrastructure Management. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of the NSF.

10 Amekudzi and Jeon 10 REFERENCES [1] ASCE Design-Build Contracting, Continuing Education Series Pamphlet, Accessed in July [2] Institute for Transportation and Development Policy, Privatization: Will It Lead to Sustainable Transport? A Paper Prepared for the Conference on Transport and Environment, Manila, the Philippines, December 10-12, [3] Flyvbjerg, B., Bruzelius, N., Rothengatter, W., Megaprojects and Risks: An Anatomy of Ambition, Cambridge Univ. Press, Cambridge, UK, [4] Schaufelberger, John E. Risk Management on Build-Operate-Transfer Projects, Construction Research Congress 2005, ASCE. [5] Web Definition for Design-Build, Accessed in July [6] Schaufelberger, John E. Use of Design-Build on Mass Transit Rail Projects, Construction Research Congress 2005, ASCE. [7] United Nations Industrial Development Organization (UNIDO). Guideline for the Development through Build-Operate-Transfer (BOT) Projects, Vienna, [8] "Eurotunnel: Au Revoir Alastair," The Sunday Times (London), October 6, [9] Website of Eurotunnel, Accessed in June [10] Definition of NPV (Net Present Value), n.htm, Accessed in June [11] Accessed in June [12] Winch, Graham M. The Channel Fixed Link: Le Projet du Siecle, Case Study, MEng 450, The University of Manchester, United Kingdom, November [13] Eurotunnel, Eurotunnel 2004 Results, April 2005, Accessible at E C69/0/Annualresults2004UK.pdf. [14] Accessed in June [15] Blank, L. and Tarquin, A. Engineering Economy, Fifth Edition, McGraw-Hill, [16] Accessed in June 2005.

11 Amekudzi and Jeon 11 LIST OT TABLES AND FIGURES TABLES TABLE 1 Cost Overruns, Less-than-predicted Revenues, and Contract Type of Selected Megaprojects TABLE 2 Predicted and Actual Records of the Channel Tunnel TABLE 3 Predicted and Actual NPVs of the Channel Tunnel TABLE 4 Impacts of Risk Factors on the NPVs of the Channel Tunnel TABLE 5 NPVs for Lower and Upper Boundary Scenario TABLE 1 Cost Overruns, Less-than-predicted Revenues, and Contract Type of Selected Megaprojects TABLE 2 Predicted and Actual Records of the Channel Tunnel TABLE 3 Predicted and Actual NPVs of the Channel Tunnel TABLE 4 Impacts of Risk Factors on the NPVs of the Channel Tunnel TABLE 5 NPVs for Lower and Upper Boundary Scenario FIGURE 1 Costs, Revenues, and Operating Profit of Channel Tunnel

12 Amekudzi and Jeon 12 TABLE 1 Cost Overruns, Less-than-predicted Revenues, and Contract Type of Selected Megaprojects Project Cost overrun (%) Actual demand (%) of the forecast, opening year Type of private financing Channel Tunnel, UK, France BOOT Boston CA/T, USA 196 N/A N/A Denver International Airport N/A 55 N/A Boson-Washington-N.Y. rail 130 N/A N/A Mexico City metro, Mexico N/A Shinkansen Joetsu rail, Japan 100 N/A N/A Malaysia s North-South Highway 146 N/A BOT [Adapted from Megaprojects and Risks (2003) and Schaufelberger (2005)]

13 Amekudzi and Jeon 13 TABLE 2 Predicted and Actual Records of the Channel Tunnel Risk Factor Projected Actual or % of the predicted Project Delivery April, 1993 May, month Demand Rail Passenger 2.9 (1995) 18.0% (million) 15.9 (1994) 6.9 (2001) 43.0% (million gross tonnes) Rail Freight 1.3 (1995) 18.0% 7.2 (1994) 2.4 (2001) 33.0% Investment Cost (1997 prices, Billion and $) (conversion to US$ at in 1997) $7.04 $ % Financing Cost (1997 prices, Billion and $) $7.8 $ % Operating Profit by the year 2004 (Billion and $) 4.31 (EST) 0.35 $6.87 (EST) $ % Sources: Megaprojects and Risks (2003), Eurotunnel: Au Revoir Alastair (1997), and Winch (1998).

14 Amekudzi and Jeon 14 TABLE 3 Predicted and Actual NPVs of the Channel Tunnel Year Inflation-adjusted interest rate = 10.15% Predicted Cash Flow (Million $) Actual Cash Flow (Million $) NPV ($ Million) ,836.01

15 Amekudzi and Jeon 15 Billion$ ('97prices 2, ,000-4,000-6,000-8,000-10,000-12,000-14,000 '94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 ' Year Costs Revenues Operating Profit FIGURE 1 Costs, Revenues, and Operating Profit of Channel Tunnel Source: Eurotunnel Annual Accounts

16 Amekudzi and Jeon 16 TABLE 4 Impacts of Risk Factors on the NPVs of the Channel Tunnel Base Case NPV -11,836.0 (Million $) Inflation-adjusted Interest Rate Project Timeline Travel Demand Inflation Rate Completed 2 yrs later Completed 1 yr early Only 20% of predicted demand Reach at the predicted demand 5% (high) 1% (low) 10.15% 10.15% 10.15% 10.15% 12.56% 8.27% NPV (Million $) -15,088.0 (-27.5%) -9,764.8 (+17.5%) -13,260.1 (-12.0%) -7,653.2 (+35.3%) -13,480.7 (-13.9%) -9,537.5 (+19.4%)

17 Amekudzi and Jeon 17 TABLE 5 NPVs for Lower and Upper Boundary Scenario Lower Boundary Scenario Base Case Upper Boundary Scenario Inflation-adjusted Interest Rate NPV (Million $) Scenario with demand at 20% of the predicted, project completed 2 years later than predicted, inflation at 5% Scenario with demand reaching at the predicted, project completed 1 year earlier than predicted, inflation at 1% 12.56% 10.15% 8.27% -16,369.5 (-38.3%) -11, ,713.1 (+60.2%)

Eurotunnel Revised: August 31, 2001

Eurotunnel Revised: August 31, 2001 Firms and Markets Mini-Case Eurotunnel Revised: August 31, 2001 The idea of building a fixed link to connect England and France is a very old one; the first proposal was presented to Napoleon in 1802.

More information

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1 SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL Petter Gokstad 1 Graduate Assistant, Department of Finance, University of North Dakota Box 7096 Grand Forks, ND 58202-7096, USA Nancy Beneda

More information

Residual Value and its Importance in Concession Agreements for Infrastructure Problems

Residual Value and its Importance in Concession Agreements for Infrastructure Problems European Research Studies, Vol. XVII, Issue (2), 2014 pp. 32-40 Residual Value and its Importance in Concession Agreements for Infrastructure Problems Evgenios Tassopoulos 1, Sotirios Theodoropoulos 2

More information

Getlink: 2017 Increase in annual result

Getlink: 2017 Increase in annual result PRESS RELEASE 21 February 2018 6:15 a.m. Getlink: 2017 Increase in annual result Revenue increased by 4% 1 to 1.033 billion EBITDA increased to 526 million (+6%) Consolidated net profit of 113 million

More information

Long-Term Debt Financing

Long-Term Debt Financing 18 Long-Term Debt Financing CHAPTER OBJECTIVES The specific objectives of this chapter are to: explain how an MNC uses debt financing in a manner that minimizes its exposure to exchange rate risk, explain

More information

The Hero/Heroines Quest

The Hero/Heroines Quest Mega Projects Mega Claims The Hero/Heroines Quest Up and Running or Up and Stumbling? The Biggest, The Costliest The Most Technologically Advanced, The most Architecturally Adventourous, The most Iconically

More information

I-66 RFI Response Vinci Concessions USA 25 November 2013

I-66 RFI Response Vinci Concessions USA 25 November 2013 General: 1. Please describe your firm, its experience in relation to public-private partnership projects, and its potential interest in relation to the Project (e.g., design/engineering firm, construction

More information

International Conference on Promoting PPP in the UNECE Region. 5-8 June 2007 Tel Aviv

International Conference on Promoting PPP in the UNECE Region. 5-8 June 2007 Tel Aviv International Conference on Promoting PPP in the UNECE Region 5-8 June 2007 Tel Aviv 1 Contents 1. Bank Leumi - Facts and Information 2. Bank Leumi and Project Finance in Israel 3. Significant Funding

More information

Support Loan Concept for the Viability of a BOT Road Project

Support Loan Concept for the Viability of a BOT Road Project Support Loan Concept for the Viability of a BOT Road Project Swapan Kumar Bagui 1) and Ambarish Ghosh 2) 1) PhD Student, Dept. of Civil Engrg., Bengal Engrg. and Science University, Shibpur, Howrah 711

More information

DEVELOPMENT AND IMPLEMENTATION OF A NETWORK-LEVEL PAVEMENT OPTIMIZATION MODEL FOR OHIO DEPARTMENT OF TRANSPORTATION

DEVELOPMENT AND IMPLEMENTATION OF A NETWORK-LEVEL PAVEMENT OPTIMIZATION MODEL FOR OHIO DEPARTMENT OF TRANSPORTATION DEVELOPMENT AND IMPLEMENTATION OF A NETWOR-LEVEL PAVEMENT OPTIMIZATION MODEL FOR OHIO DEPARTMENT OF TRANSPORTATION Shuo Wang, Eddie. Chou, Andrew Williams () Department of Civil Engineering, University

More information

Flyvbjerg, Bent. Accountable Megaproject Decision-making

Flyvbjerg, Bent. Accountable Megaproject Decision-making Name: Title: Organization: Country: Flyvbjerg, Bent Professor Aalborg University Denmark Accountable Megaproject Decision-making Accountable Megaproject Decision Making Principles of Governance of Major

More information

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents Review of the Federal Transit Administration s Transit Economic Requirements Model Contents Summary Introduction 1 TERM History: Legislative Requirement; Conditions and Performance Reports Committee Activities

More information

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E.

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. Texas Research and Development Inc. 2602 Dellana Lane,

More information

Equitable Financial Evaluation Method for Public-Private Partnership Projects *

Equitable Financial Evaluation Method for Public-Private Partnership Projects * TSINGHUA SCIENCE AND TECHNOLOGY ISSN 1007-0214 20/25 pp702-707 Volume 13, Number 5, October 2008 Equitable Financial Evaluation Method for Public-Private Partnership Projects * KE Yongjian ( ), LIU Xinping

More information

The economic impact of the UK Maritime Services Sector

The economic impact of the UK Maritime Services Sector The economic impact of the UK Maritime Services Sector A Report for Maritime UK (including regional breakdown) February 2013 Contents 1 Executive summary...2 2 Introduction...5 2.1 The channels of economic

More information

Project Evaluation and Programming I Project Evaluation

Project Evaluation and Programming I Project Evaluation Project Evaluation and Programming I Project Evaluation presented to MIT 1.201 Class presented by Lance Neumann Cambridge Systematics, Inc. November 20, 2008 Transportation leadership you can trust. Outline

More information

Buenos Aires - Colonia Bridge Project, Financial and Economic Appraisal. Chun-Yan Kuo International Tax Program, Harvard University

Buenos Aires - Colonia Bridge Project, Financial and Economic Appraisal. Chun-Yan Kuo International Tax Program, Harvard University Buenos Aires - Colonia Bridge Project, Financial and Economic Appraisal Chun-Yan Kuo International Tax Program, Harvard University Glenn P. Jenkins HIID Harvard University Development Discussion Paper

More information

Using real options in evaluating PPP/PFI projects

Using real options in evaluating PPP/PFI projects Using real options in evaluating PPP/PFI projects N. Vandoros 1 and J.-P. Pantouvakis 2 1 Researcher, M.Sc., 2 Assistant Professor, Ph.D. Department of Construction Engineering & Management, Faculty of

More information

Public vs. Private Projects

Public vs. Private Projects 1.011 Project Evaluation Public vs. Private Projects Carl D. Martland Project Evaluation in the Private Sector Analysis focuses on financial issues NPV based upon incremental costs and benefits and the

More information

DEVELOPING BEST PRACTICES FOR PROMOTING PRIVATE SECTOR INVESTMENT IN INFRASTRUCTURE

DEVELOPING BEST PRACTICES FOR PROMOTING PRIVATE SECTOR INVESTMENT IN INFRASTRUCTURE ADB DEVELOPING BEST PRACTICES FOR PROMOTING PRIVATE SECTOR INVESTMENT IN INFRASTRUCTURE ROADS Asian Development Bank The views, conclusions, and recommendations presented here are those of the study consultants,

More information

NCHRP Consequences of Delayed Maintenance

NCHRP Consequences of Delayed Maintenance NCHRP 14-20 Consequences of Delayed Maintenance Recommended Process for Bridges and Pavements prepared for NCHRP prepared by Cambridge Systematics, Inc. with Applied Research Associates, Inc. Spy Pond

More information

FY Statewide Capital Investment Strategy... asset management, performance-based strategic direction

FY Statewide Capital Investment Strategy... asset management, performance-based strategic direction FY 2009-2018 Statewide Capital Investment Strategy.. asset management, performance-based strategic direction March 31, 2008 Governor Jon S. Corzine Commissioner Kris Kolluri Table of Contents I. EXECUTIVE

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 574 580 Creative Construction Conference 2015 (CCC2015) A method for estimating contingency based on project complexity

More information

Chapter 8 Cost Estimating and Budgeting

Chapter 8 Cost Estimating and Budgeting Chapter 8 Cost Estimating and Budgeting Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Cost overrun % Cost Overruns on Projects

More information

Eurotunnel Group 2016 annual profits up

Eurotunnel Group 2016 annual profits up PRESS RELEASE 1 st March 2017 6:30 a.m. Eurotunnel Group 2016 annual profits up Revenues increased by 4% to 1.023 billion 1 EBITDA increased to 514 million Net consolidated profit increased strongly to

More information

Creating Value Through Private- Public Partnerships for Infrastructure Development

Creating Value Through Private- Public Partnerships for Infrastructure Development Creating Value Through Private- Public Partnerships for Infrastructure Development Dominic Barton McKinsey & Company September 6, 2005 This report is solely for the use of client personnel. No part of

More information

FEASIBILITY STUDY AND ECONOMIC ASSESSMENT FOR AL-QADISIYAH UNIVERSITY HOSPITAL OF SPECIALIZED SURGERIES

FEASIBILITY STUDY AND ECONOMIC ASSESSMENT FOR AL-QADISIYAH UNIVERSITY HOSPITAL OF SPECIALIZED SURGERIES International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 9, September 2018, pp. 63 72, Article ID: IJCIET_09_09_009 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=9

More information

ECONOMIC SENSITIVITY ANALYSIS OF WALAYAR - VADAKKANCHERRY B.O.T. CONTRACT ROAD PROJECT A CASE STUDY

ECONOMIC SENSITIVITY ANALYSIS OF WALAYAR - VADAKKANCHERRY B.O.T. CONTRACT ROAD PROJECT A CASE STUDY ECONOMIC SENSITIVITY ANALYSIS OF WALAYAR - VADAKKANCHERRY B.O.T. CONTRACT ROAD PROJECT A CASE STUDY R. R. Kshatriya 1, Monika B. Murkute 2,Sonia G. Upadhyay 3 1 Assistant Professor, Department of Civil

More information

Constructing a Capital Budget

Constructing a Capital Budget A capital budget can be used to analyze the economic viability of a business project lasting multiple years and involving capital assets. It is divided into three parts. The first part is the initial phase

More information

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1 A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

2007 PRO FORMA RESULTS* Groupe Eurotunnel: a profitable Group. Revenues increased for the third year in succession: +6%, to 775 million

2007 PRO FORMA RESULTS* Groupe Eurotunnel: a profitable Group. Revenues increased for the third year in succession: +6%, to 775 million PRESS RELEASE 8 April 2008 2007 PRO FORMA RESULTS* Groupe Eurotunnel: a profitable Group Revenues increased for the third year in succession: +6%, to 775 million Shuttle revenues, Eurotunnel s core activity,

More information

Infrastructure Decision Making and Cost Containment. Matti Siemiatycki Geography and Planning University of Toronto

Infrastructure Decision Making and Cost Containment. Matti Siemiatycki Geography and Planning University of Toronto Infrastructure Decision Making and Cost Containment Matti Siemiatycki Geography and Planning University of Toronto Cost Overruns and Delays: A Problem that Unites the Nation Cost Overruns and delays are

More information

FINANCIAL APPRAISAL OF PROJECTS

FINANCIAL APPRAISAL OF PROJECTS FINANCIAL APPRAISAL OF PROJECTS (Special Emphasis to Railways) S. N. BANERJEA Joint Economic Adviser Railway Board New Delhi BASIC THEORY OF PROJECT APPRAISAL PROJECT IDENTIFICATION PROJECT APPRAISAL PROJECT

More information

Getlink: All-time record annual results in 2018

Getlink: All-time record annual results in 2018 PRESS RELEASE 21 February 2019 06:30 a.m. Getlink: Alltime record annual results in 2018 Revenue increased by 5% 1 to 1.079 billion EBITDA increased to 569 million (+9%) 2 Consolidated net profit of 130

More information

Transportation Improvement Program and Incentives for Local Planning

Transportation Improvement Program and Incentives for Local Planning Capital District November 9, 2004 Transportation Committee Transportation Improvement Program and Incentives for Local Planning CDTC has been successful in funding 36 Linkage Program planning studies since

More information

2016 Third Quarter Traffic and Revenue 19 October 2016 Jacques Gounon Chairman & Chief Executive Officer

2016 Third Quarter Traffic and Revenue 19 October 2016 Jacques Gounon Chairman & Chief Executive Officer 2016 Third Quarter Traffic and Revenue 19 October 2016 Jacques Gounon Chairman & Chief Executive Officer 1. EUROTUNNEL GROUP Key fact & figures in Q3 2016 2. RAIL FREIGHT ACTIVITY Europorte 3. FIXED LINK

More information

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2. House Bill 20 Implementation Tuesday,, 1:00 P.M. Capitol Extension E2.020 INTRODUCTION In response to House Bill 20 (HB 20), 84 th Legislature, Regular Session, 2015, and as part of the implementation

More information

Indian Sovereign Yield Curve using Nelson-Siegel-Svensson Model

Indian Sovereign Yield Curve using Nelson-Siegel-Svensson Model Indian Sovereign Yield Curve using Nelson-Siegel-Svensson Model Of the three methods of valuing a Fixed Income Security Current Yield, YTM and the Coupon, the most common method followed is the Yield To

More information

GEORGE MASSEY TUNNEL REPLACEMENT PROJECT

GEORGE MASSEY TUNNEL REPLACEMENT PROJECT COMBINED MONTHLY AND QUARTERLY PROGRESS REPORT FOR QUARTER ENDING JUNE 30, 2014 GEORGE MASSEY TUNNEL MONTHLY STATUS REPORT SEPTEMBER 2017 FOREWORD TO MONTHLY STATUS REPORT On September 6, 2017, the Minister

More information

Delegation Bugsas Ankara 31. October 2008

Delegation Bugsas Ankara 31. October 2008 Delegation Bugsas Ankara 31. October 2008 Light Rail Projects Financing Financing Public Transport Infrastructure and Systems: Fundamental Approaches and International Examples of Private Financed Projects

More information

AAPA Finance Seminar Seaport Project Financing

AAPA Finance Seminar Seaport Project Financing AAPA Finance Seminar Seaport Project Financing April 9, 2014 Presented by: David C. Miller, Managing Director Public Financial Management, Inc. 300 South Orange Avenue, Suite 1170 Orlando, Florida 32801

More information

Comparison between new financial analysis and ECI-result (2002)

Comparison between new financial analysis and ECI-result (2002) REPORT FEHMARNBELT FIXED LINK Financial Analysis - February 23 Comparison between new financial analysis and ECI-result (22) Prepared by Sund & Bælt / Femer Bælt March 23 A division of Sund & Bælt Holding

More information

Half-Year Results 25 JULY 2018

Half-Year Results 25 JULY 2018 Half-Year Results 25 JULY 2018 GETLINK SUMMARY KEY MESSAGES 1 H1 2018 KEY FIGURES 2 H1 2018 FINANCIAL RESULTS 3 1 KEY MESSAGES KEY MESSAGES H1 2018: NEW RECORDS Eurotunnel Traffic Cars +2% to 1.2 M Trucks

More information

Headline Verdana Bold. Uganda PPP Act - Implications for Public Sector Accounting Kenneth LEGESI Deloitte (Uganda) Limited

Headline Verdana Bold. Uganda PPP Act - Implications for Public Sector Accounting Kenneth LEGESI Deloitte (Uganda) Limited Headline Verdana Bold Uganda PPP Act - Implications for Public Sector Accounting Kenneth LEGESI Deloitte (Uganda) Limited About us Kenneth Legesi Infrastructure and Capital Projects / PPP Advisory Deloitte

More information

Comprehensive Project

Comprehensive Project APPENDIX A Comprehensive Project One of the best ways to gain a clear understanding of the key concepts explained in this text is to apply them directly to actual situations. This comprehensive project

More information

The Volatility-Based Envelopes (VBE): a Dynamic Adaptation to Fixed Width Moving Average Envelopes by Mohamed Elsaiid, MFTA

The Volatility-Based Envelopes (VBE): a Dynamic Adaptation to Fixed Width Moving Average Envelopes by Mohamed Elsaiid, MFTA The Volatility-Based Envelopes (VBE): a Dynamic Adaptation to Fixed Width Moving Average Envelopes by Mohamed Elsaiid, MFTA Abstract This paper discusses the limitations of fixed-width envelopes and introduces

More information

Important Note. Airport Authority Hong Kong

Important Note. Airport Authority Hong Kong Important Note Airport Authority Hong Kong (AAHK) is responsible for preparing the Hong Kong International Airport (HKIA) Master Plan 2030 and commissioning the associated consultancies. At different stages

More information

Over Budget and Behind Schedule: The Causes and Cures of Infrastructure Cost Overruns

Over Budget and Behind Schedule: The Causes and Cures of Infrastructure Cost Overruns Over Budget and Behind Schedule: The Causes and Cures of Infrastructure Cost Overruns Thursday, January 21, 2016 Matti Siemiatycki (University of Toronto) Andy Manahan (RCCAO) Ehren Cory (Infrastructure

More information

RISK MANAGEMENT IN PUBLIC-PRIVATE PARTNERSHIP ROAD PROJECTS USING THE REAL OPTIONS THEORY

RISK MANAGEMENT IN PUBLIC-PRIVATE PARTNERSHIP ROAD PROJECTS USING THE REAL OPTIONS THEORY I International Symposium Engineering Management And Competitiveness 20 (EMC20) June 24-25, 20, Zrenjanin, Serbia RISK MANAGEMENT IN PUBLIC-PRIVATE PARTNERSHIP ROAD PROJECTS USING THE REAL OPTIONS THEORY

More information

DIRECTIVE SUR LA GESTION DES PROJETS MAJEURS D INFRASTRUCTURE PUBLIQUE

DIRECTIVE SUR LA GESTION DES PROJETS MAJEURS D INFRASTRUCTURE PUBLIQUE Notice to reader on accessibility: This document complies with the SGQRI 008-02 standard of the Gouvernement du Québec in order to be accessible to every individual whether or not they have a disability.

More information

The role of Build Operate Transfer in promoting RES projects

The role of Build Operate Transfer in promoting RES projects The role of Build Operate Transfer in promoting RES projects December 2003 European Commission (Directorate-General for Energy and Transport) Contract no. NNE5/2002/52: OPET CHP/DH Cluster TITLE: THE ROLE

More information

Financing Infrastructure. Rory Maxwell

Financing Infrastructure. Rory Maxwell Financing Infrastructure Rory Maxwell Introduction Models of Finance PPP and Risk The Current and Potential Market The Model and The Opportunity Conclusions Introduction The Railway Consultancy provides

More information

Long-Term Projection of Traffic and Revenues for Equity Analysis

Long-Term Projection of Traffic and Revenues for Equity Analysis Long-Term Projection of Traffic and Revenues for Equity Analysis By Ray Tillman, P.E.; John Smolley; Kathy Massarelli, AICP; Art Goldberg, P.E.; Art Pratt, P.E.; and Phil Eshelman For more than 50 years,

More information

In addition to embarking on a new dialogue on Ohio s transportation priorities,

In addition to embarking on a new dialogue on Ohio s transportation priorities, Strategic Initiatives for 2008-2009 ODOT Action to Answer the Challenges of Today In addition to embarking on a new dialogue on Ohio s transportation priorities, the Strategic Initiatives set forth by

More information

FINAL REPORT RESIDENTIAL TRIP GENERATION: GROUND COUNTS VERSUS SURVEYS. Jared M. Ulmer Graduate Research Assistant

FINAL REPORT RESIDENTIAL TRIP GENERATION: GROUND COUNTS VERSUS SURVEYS. Jared M. Ulmer Graduate Research Assistant FINAL REPORT RESIDENTIAL TRIP GENERATION: GROUND COUNTS VERSUS SURVEYS Jared M. Ulmer Graduate Research Assistant Arkopal K. Goswami Graduate Research Assistant John S. Miller, Ph.D., P.E. Senior Research

More information

Irvine Corona Expressway Project Financing Review

Irvine Corona Expressway Project Financing Review Irvine Corona Expressway Project Financing Review Sperry June 4, 2010 1 The Proposed Irvine Corona Expressway (ICE) Project Project screening is key aspect of pre-development discussions Environmental

More information

Annex A TUBA Time Savings Summary

Annex A TUBA Time Savings Summary Annex A TUBA Time Savings Summary Annex A: TUBA Time Savings Summary Profile of Time Benefits The scale of discounted benefits over time is shown in the two figures below for both the full and no decay

More information

Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads

Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads TRANSACTION ADVISORY SERVICES PPP ADVISORY Partnerships in Transportation Workshop Transportation PPPs beyond Toll Roads Alistair SAWERS, Head of Transport, PPP Advisory, Ernst & Young 1 Introduction Brownfield

More information

An Introduction to PPP s

An Introduction to PPP s An Introduction to PPP s AAPA Facilities Engineering Seminar San Diego November 8 th, 2007 Presented by Manju Chandrasekhar Vice President Halcrow, Inc. Outline A Definition of PPP s Principles of PPP

More information

5.- RISK ANALYSIS. Business Plan

5.- RISK ANALYSIS. Business Plan 5.- RISK ANALYSIS The Risk Analysis module is an educational tool for management that allows the user to identify, analyze and quantify the risks involved in a business project on a specific industry basis

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

Risks in Build Operate Transfer (BOT) Infrastructure Project: A Case Study on Shirwal-Lonand-Phaltan-Baramati Road Project

Risks in Build Operate Transfer (BOT) Infrastructure Project: A Case Study on Shirwal-Lonand-Phaltan-Baramati Road Project Risks in Build Operate Transfer (BOT) Infrastructure Project: A Case Study on Shirwal-Lonand-Phaltan-Baramati Road Project Amol Prabhakar Garole 1 PG Scholar TSSM s Padmabhooshan Vasantdada Patil Institute

More information

Transportation Infrastructure Project Cost Overrun Risk Analysis Risk Factor Analysis Models

Transportation Infrastructure Project Cost Overrun Risk Analysis Risk Factor Analysis Models Transportation Infrastructure Project Cost Overrun Risk Analysis Risk Factor Analysis Models b y Qing W u B.Sc, Shanghai University of Finance & Economics, 1999 A THESIS SUBMITTED IN PARTIAL FULFILLMENT

More information

Capital Projects Succeed through Planning and Predictability

Capital Projects Succeed through Planning and Predictability Capital Projects Succeed through Planning and Predictability Why do enterprises undertake capital projects? Because engineering, designing, and building a new industrial facility (like an oil, gas, or

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

EVALUATING MULTIPLE DIMENSIONS OF VISITORS' TRADEOFFS BETWEEN ACCESS AND CROWDING AT ARCHES NATIONAL PARK USING INDIFFERENCE CURVE ANALYSIS*

EVALUATING MULTIPLE DIMENSIONS OF VISITORS' TRADEOFFS BETWEEN ACCESS AND CROWDING AT ARCHES NATIONAL PARK USING INDIFFERENCE CURVE ANALYSIS* EVALUATING MULTIPLE DIMENSIONS OF VISITORS' TRADEOFFS BETWEEN ACCESS AND CROWDING AT ARCHES NATIONAL PARK USING INDIFFERENCE CURVE ANALYSIS* Steven R. Lawson Ph.D. Candidate in Natural Resources, University

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

20 Years of Commuter Benefits: Where We've Been and Where We're Going

20 Years of Commuter Benefits: Where We've Been and Where We're Going December 19, 2006 20 Years of Commuter Benefits: Where We've Been and Where We're Going By Larry Filler President and CEO, TransitCenter Inc This summer, as gas prices reached a national average of nearly

More information

Presentation to the Ethiopia Government Delegation to Canada on PPP. Peter Kieran May 15, 2014 Ottawa, Ontario

Presentation to the Ethiopia Government Delegation to Canada on PPP. Peter Kieran May 15, 2014 Ottawa, Ontario Presentation to the Ethiopia Government Delegation to Canada on PPP Peter Kieran May 15, 2014 Ottawa, Ontario Overview Who is CPCS? Public-Private Partnerships / Transaction Advisory Services Example:

More information

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project

Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project Using Online Simulation Technique for Revenue-Based Value for Money Assessment Model in PPP Project http://dx.doi.org/10.3991/ijoe.v9i3.2804 Wei Peng 1,2, Honglei Liu 1, * 1 Tongji University, Shanghai

More information

METHODOLOGY FOR MEASURING THE OCCUPATIONAL HEALTH AND SAFETY RISKS IN TOURISM COMPANIES

METHODOLOGY FOR MEASURING THE OCCUPATIONAL HEALTH AND SAFETY RISKS IN TOURISM COMPANIES METHODOLOGY FOR MEASURING THE OCCUPATIONAL HEALTH AND SAFETY RISKS IN TOURISM COMPANIES Biljana Gjorgjeska, Ph.D., Associate Professor University "Gone Delco", Faculty of Medical Sciences, Štip, Republic

More information

DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT. [Docket No. FR-6046-N-01] Family Self-Sufficiency Performance Measurement System ( Composite Score )

DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT. [Docket No. FR-6046-N-01] Family Self-Sufficiency Performance Measurement System ( Composite Score ) This document is scheduled to be published in the Federal Register on 12/12/2017 and available online at https://federalregister.gov/d/2017-26696, and on FDsys.gov Billing Code: 4210-67 DEPARTMENT OF HOUSING

More information

THE UNDERGROUND ECONOMY AND AUSTRALIA S GDP

THE UNDERGROUND ECONOMY AND AUSTRALIA S GDP FEATURE ARTICLE: INTRODUCTION THE UNDERGROUND ECONOMY AND AUSTRALIA S GDP A publication titled Measuring the Non-Observed Economy: A Handbook, was released in 2002. It was jointly authored by the Organisation

More information

A New Method of Cost Contingency Management

A New Method of Cost Contingency Management A New Method of Cost Contingency Management Mohammed Wajdi Hammad, Alireza Abbasi, Michael J. Ryan School of Engineering and Information Technology, University of New South Wales (UNSW Australia), Canberra

More information

Economic Analysis Concepts

Economic Analysis Concepts Economic Analysis Concepts Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds

More information

INSIGHTS INTO THE FINANCIAL OPERATION OF BOOT SCHEME TOLL ROADS IN AUSTRALIA

INSIGHTS INTO THE FINANCIAL OPERATION OF BOOT SCHEME TOLL ROADS IN AUSTRALIA 1 INSIGHTS INTO THE FINANCIAL OPERATION OF BOOT SCHEME TOLL ROADS IN AUSTRALIA Dr John L. Goldberg Honorary Associate School of Architecture, Design Science and Planning The University of Sydney 2006 E-mail:

More information

A Note on Capital Budgeting: Treating a Replacement Project as Two Mutually Exclusive Projects

A Note on Capital Budgeting: Treating a Replacement Project as Two Mutually Exclusive Projects A Note on Capital Budgeting: Treating a Replacement Project as Two Mutually Exclusive Projects Su-Jane Chen, Metropolitan State College of Denver Timothy R. Mayes, Metropolitan State College of Denver

More information

FREQUENTLY ASKED QUESTIONS: HIGHWAY P3S

FREQUENTLY ASKED QUESTIONS: HIGHWAY P3S FREQUENTLY ASKED QUESTIONS: HIGHWAY P3S by Austill Stuart and Baruch Feigenbaum May 2018 Reason Foundation s mission is to advance a free society by developing, applying and promoting libertarian principles,

More information

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment

1 EXECUTIVE SUMMARY. Figure 1-1: SR 156 Study Area & Monterey Expressway Alignment 1 EXECUTIVE SUMMARY The Transportation Agency for Monterey County (TAMC) Board commissioned a Level 2 Traffic and Revenue study on the feasibility of collecting tolls to fund the proposed new SR156 connector

More information

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT JESÚS DE LA GARZA 1 AND APIRATH PRATEAPUSANOND 2 1-2 Charles E. Via, Jr. Department of

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. 1.040/1.401 Project Management

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Additional Financing to the Third Primary Education Development Project (RRP BAN 42122) ECONOMIC AND FINANCIAL ANALYSIS 1. This document provides an analysis of the economic rationale for additional financing

More information

Strategic Planning Prof. Richard de Neufville

Strategic Planning Prof. Richard de Neufville Strategic Planning Prof. Richard de Neufville Istanbul Technical University Air Transportation Management M.Sc. Program Airport Planning and Management / RdN Airport Planning and Management Module 23 January

More information

Best Practice in National Support for Urban Transportation

Best Practice in National Support for Urban Transportation São Paulo, Brazil. Image: Ana Paula Hirama Best Practice in National Support for Urban Transportation Part 2: Growing Rapid Transit Infrastructure Funding, Financing, and Capacity November 2015 Lead Authors:

More information

Risk Premia of Aluminum Forwards: a Guide for the Trader in the Primary Aluminum Metals Market

Risk Premia of Aluminum Forwards: a Guide for the Trader in the Primary Aluminum Metals Market Risk Premia of Aluminum Forwards: a Guide for the Trader in the Primary Aluminum Metals Market Abstract Clint Brown Industrial Engineering Manager, Sanden International Shekar Shetty Associate Professor

More information

II Simpósio Internacional PwC Inovação em Gestão Pública Abril 2011

II Simpósio Internacional PwC Inovação em Gestão Pública Abril 2011 www.pwc.com/br II Simpósio Internacional PwC Inovação em Gestão Pública Abril 2011 Agenda 1. PwC 2. Global PPP context 3. What is PPP 4. Payment Mechanisms and Demand Risk 5. Alternative Financing Models

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 5.01 Page 1 of 2 EXECUTING AGENCY S PROJECT PROGRESS REPORT A. Introduction 1. Loan regulations and loan and project agreements require the borrower and executing

More information

PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT

PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT PUBLIC PRIVATE PARTNERSHIP IN THAILAND HIGHWAYS A CASE STUDY ON AN EXTENSION OF DONMUANG TOLLWAY PROJECT Pruethipong Singhatiraj 1, Chatchai Chuangching 1 and Boonkua Janbanjong 1 1 Department of Highways,

More information

International University of Japan Graduate School of International Business

International University of Japan Graduate School of International Business International University of Japan Graduate School of International Business Project Financing (FIN 4370) (An Essential Tool for International Development) Fall 2015 Instructor: Instructor's Contact: Mr.

More information

2016 Annual results of Groupe Eurotunnel SE 1 st March 2017 Jacques Gounon Chairman and Chief Executive Officer

2016 Annual results of Groupe Eurotunnel SE 1 st March 2017 Jacques Gounon Chairman and Chief Executive Officer 2016 Annual results of Groupe Eurotunnel SE 1 st March 2017 Jacques Gounon Chairman and Chief Executive Officer #VitalLink 1. 2016 KEY FIGURES 2. CONCESSION AND INFRASTRUCTURE 3. 2016 FINANCIAL RESULTS

More information

Profitability Evaluation Of Capital Investment With Net Present Value (Npv) And Internal Rate Of Return (Irr) Method In Pt GGG Karawang, West Java

Profitability Evaluation Of Capital Investment With Net Present Value (Npv) And Internal Rate Of Return (Irr) Method In Pt GGG Karawang, West Java IOSR Journal of Business and Management (IOSR-JBM) e-issn: 2278-487X, p-issn: 2319-7668. Volume 20, Issue 7. Ver. VI (July. 2018), PP 64-75 www.iosrjournals.org Profitability Evaluation Of Capital Investment

More information

New Financing Trends Impact on Tunnelling Contracts

New Financing Trends Impact on Tunnelling Contracts Martin Holfelder, Dipl.-Ing., Member of Management, Bilfinger Berger AG, Civil Tunnelling Arne Speer, Dipl.-Ing., Regional Director East, Bilfinger Berger BOT Europe GmbH Contents of PPP Projects Return

More information

Why surety gets the job done on P3 projects

Why surety gets the job done on P3 projects Why surety gets the job done on P3 projects 1 Why surety gets the job done on P3 projects Public-Private Partnership projects (P3s) involve a complex mix of new relationships and risk transfers for the

More information

GOVERNMENT OF MONTENEGRO SECRETARIAT FOR DEVELOPMENT PROJECTS

GOVERNMENT OF MONTENEGRO SECRETARIAT FOR DEVELOPMENT PROJECTS Pursuant to Article 21 of the Decree on Fostering Direct Investments (Official Gazette of Montenegro 8/15) GOVERNMENT OF MONTENEGRO SECRETARIAT FOR DEVELOPMENT PROJECTS publishes the PUBLIC ANNOUNCEMENT

More information

Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar

Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar Professor of International Finance Capital Budgeting Agenda Define the capital budgeting process, explain the administrative

More information

Non-Energy Benefits (NEBs) from ENERGY STAR : Comprehensive Analysis of Appliance, Outreach, and Homes Programs 1

Non-Energy Benefits (NEBs) from ENERGY STAR : Comprehensive Analysis of Appliance, Outreach, and Homes Programs 1 Non-Energy Benefits (NEBs) from ENERGY STAR : Comprehensive Analysis of Appliance, Outreach, and Homes Programs 1 Leah Fuchs, Skumatz Economic Research Associates, Inc. Lisa A. Skumatz, Skumatz Economic

More information

(Translation) Bor.Jor. (Wor) 21 /2015. May 11, 2015

(Translation) Bor.Jor. (Wor) 21 /2015. May 11, 2015 Bor.Jor. (Wor) 21 /2015 (Translation) May 11, 2015 To: Re: Managing directors of listed companies, member companies, non-member companies, financial advisors and legal advisors Amendments to the SET regulations

More information

A STUDY ON GROWTH AND DEVELOPMENT OF STEEL INDUSTRY IN INDIA

A STUDY ON GROWTH AND DEVELOPMENT OF STEEL INDUSTRY IN INDIA A STUDY ON GROWTH AND DEVELOPMENT OF STEEL INDUSTRY IN INDIA Asif Pervez Research Scholar, Dept. of Commerce, Aligarh Muslim University, Aligarh. Email: Asifpervez10@gmail.com. Abstract The Role of Iron

More information

HSR in California: Uncertainty, Risk and Risk Transfer.

HSR in California: Uncertainty, Risk and Risk Transfer. HSR in California: Uncertainty, Risk and Risk Transfer. What does this mean and why does it matter? Lou Thompson HSR Management Course Mineta Transportation Institute February 14, 2013 Thompson Galenson

More information