IMPLEMENTATION COMPLETION REPORT MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) Public Disclosure Authorized. Document of The World Bank

Size: px
Start display at page:

Download "IMPLEMENTATION COMPLETION REPORT MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) Public Disclosure Authorized. Document of The World Bank"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION REPORT MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) CouLntry Department 3 Africa Region JANUARY Report No This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.

2 Current Unit = Malawi Kwacha (MK) CURRENCY EQUIVALENT US$1.00 = MK 2.70 (May 1989) = SDR US$1.00 =MK (Dec. 1994)= SDR US$1.00 = MK (June 1996) = SDR WEIGHTS AND MEASURES Metric System FISCAL YEAR OF BORROWER April 1 - March 31 ABBREVIATIONS AND ACRONYMS DCA DEVPLAN ICR ID I ID II IDA IMF GOM HIID MDC MIM MOF MOWS OPRPG SACS SAL SAR SDR TA TACS TMP TOT UK/ODA UNDP UOM WB Development Credit Agreement Development Plan Implementation Completion Report Institutional Development Project I Institutional Development Project II International Development Association International Monetary Fund Government of Malawi Harvard International Institute for Development Management Development Consultant Malawi Institute of Management Ministry of Finance Ministry of Works and Supplies Operations Policy Department Surtax Administration Computer System Structural Adjustment Loan Staff Appraisal Report Special Drawing Rights Technical Assistance (Income) Tax Administration Computer System Tax Modernization Program Training of Trainers United Kingdom/Overseas Development Administration United Nations Development Program University of Malawi World Bank Vice-President Country Director Staff Member Callisto Madavo Barbara Kafka Ladipo Adamolekun, Principal Public Sector Management Specialist

3 PREFACE... Table of Contents FOR OFFICIAL USE ONLY ii EVALUATION SUMMARY... iii INTRODUCTION... PROJECT OBJECTIVES AND DESCRIPTION... IMPLEMENTATION EXPERIENCE AND RESULTS... SUMMARY OF FINDINGS... PART L PROJECT IMPLEMENTATION ASSESSMENT PROJECT IDENTITY... 1 BACKGROUND... 1 PROJECT OBJECTIVE AND DESCRIPTION... 1 ACHIEVEMENT OF PROJECT OBJECTIVES... 2 MAJOR FACTORS AFFECTING THE PROJECT... 3 IMPLEMENTATION RECORD... 3 PROJECT SUSTAINABILITY AND FUTURE OPERATION... 5 BANK'S PERFORMANCE... 5 BORROWER'S PERFORMANCE... 5 ASSESSMENT OF OUTCOME... 6 KEY LESSONS LEARNED... 6 TAX REFORM PROGRAM... 7 PART H. COMMENTS CONTRIBUTED BY THE BORROWER PART ImL STATISTICAL TABLES TABLE A: SUMMARY OF ASSESSMENTS (MM TABLE IB: SUMMARY OF ASSESSMENTS (TAX MODERNIZATION PROGRAM) TABLE 1C: SUMMARY OF ASSESSMENTS (COMPOSITE OF TABLES IA AND 1B)... I TABLE 2: RELATED BANK CREDITS TABLE 3: PROJECTIMETABLE TABLE 4: CUMULATIVE ESTIMATED AND ACTUAL DISBURSEMENTS (US$ MILLION) TABLE 5: PROJECT COSTS (US $ THOUSANDS) TABLE 6A: PROJECT FINANCING (US $ MILLION) TABLE 6B: ALLOCATION OF CREDIT PROCEEDS (OBTAINED FROMM I) TABLE 7A: PARTICIPANTS AT MIM's COURSES TABLE7B: CONSULTING PROJECTS BY CATEGORY TABLE 7C: CONSULTING PROJECTS BY SECTOR...,,,,,.,,,,.. 20 TABLE 8: COMPLIANC WITH E CREDIT COVENANTS TABLE9: BANKRESOURCES: STAFFINPUTS TABLE 10: BANKRESOURCES: MISSIONS Appendices APPENDIX A LIST OF PERSONS MET DURING THE MISSION... 1 APPENDIX B TWINNING ARRANGEMENT BETWEEN ARA CONSULTANTS AND THE MALAWI INSTITUTE OF MANAGEMENT... 3 APPENDIX C EVOLUTION OF THE ENDOWMENT OF THE MALAWI INSTITUTE OF MANAGEMENT APPENDIX D CONSTRUCTION OF MALAWI INSTITUTION OF MANAGEMENT REPORT BY MINISTRY OF WORKS AND SUPPLIES APPENDIX E MALAWI INSTITUTE OF MANAGEMENT - ORGANIZATIONAL CHART AT INCEPTION MALAWI INSTITUTE OF MANAGEMENT - PROPOSED NEW ORGANIZATIONAL CHART APPENDIX F REPORTS AND OFFICIAL DOCUMENTS ON FILE This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. iii iii iv v

4

5 IMPLEMENTATION COMPLETION REPORT MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) Preface This is the Implementation Completion Report (ICR) for the First Institutional Development Project (ID I) in Malawi, for which Credit 2036-MAI in the amount of SDR8,800,000 was approved on June 13, 1989 and which became effective on January 8, The original closing date for the credit was December 31, The closing date was extended thrice for a total of eighteen months, with a final closing date of June 30, The last twelve months of extension was necessary to allow for the delivery of approved purchases and the completion of the claims for expenditure. By November 4, 1996, the undisbursed balance of the credit was US$143, This amount was canceled effective from the same date. The amount approved in 1989 was US$11,300,000 and the amount disbursed by November 4, 1996 was US$12,051, The total amount disbursed is higher than the amount approved because of gains due to the appreciation of the SDR in terms of dollars. The ICR was jointly prepared by the Institutional and Social Policy and the Country Department 3 (Preface, Evaluation Summary, Parts I and III). The report was reviewed by Barbara Kafka, (Country Director for Malawi). The Borrower's comments on the ICR constitute Part Preparation of this ICR was undertaken during a Bank mission in January/February The draft ICR served as the Aide Memoire of the mission and was discussed at a wrap-up meeting. With the approval of the Southern Africa Department's Operations Adviser who had consulted with OPRPG, the report follows the "simplified form of ICR" as per footnote 3 (c) of OP It was considered inappropriate to undertake a comprehensive ICR, as spelled out in the April 1995 directive on ICR (OP 13.55), because the major beneficiary of the credit, the Malawi Institute of Management (MIM), will also be supported under the successor Second Institutional Development Project (ID II) with about 30 percent of the total Credit amount. It was agreed that the elaborate ICR required under OP would be more appropriate at the completion of ID II. The report is based, inter alia, on the Staff Appraisal Report; the Credit Agreement; Supervision reports; correspondence between the Bank and the Borrower; internal Bank Memoranda; and interviews with Bank and Malawi Government officials who were closely associated with the project. ' The UNDP that co-financed parts of the project and was expected to provide parallel financing for some other parts was invited to participate in the ICR mission but declined the invitation. However, the mission met with the relevant UNDP staff and a copy of the draft ICR was sent to them. The Borrower's conunents on the ICR were not shared with the UNDP. ii

6

7 MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) Evaluation Summary Introduction 1. The Government of Malawi decided to establish a management institute as part of a project for institutional development. The Malawi Institute of Management (MIM) was to provide in-service training for middle and senior managers in the public, parastatal and private sectors. The proposed project also included the strengthening of institutional capacity in the Ministry of Finance and the continuation of an on-going Tax Modernization Program. The institutional strengthening actions of MOF were to be derived from the Ministry's Development Plan (DEVPLAN) prepared with the assistance of the UNDP. Project preparation was completed in 1989 with negotiations in April and Board approval was granted in June. The project became effective in January Project Objectives and Description 2. Project Objectives. The project's objective was to strengthen national economic management. The Malawi Institute of Management was to offer a wide range of training programs and seminars aimed at improving the capacity of Malawian managers in the public and private sectors. The strengthening program in the Ministry of Finance was to improve the Ministry's capacity to manage public resources through upgrading processes for budgeting, accounting and auditing, debt management and claims, and to improve revenue flows through modernization of the tax system. 3. Project Description. The project was to establish and operate the Malawi Institute of Management (MIM) to train managers in the public and private sectors in management techniques. In addition to its own campus, MIM was to work closely with the University of Malawi, sharing facilities with two of the University's affiliates, Chancellor College and the Polytechnic. An Endowment Fund was to be established to receive all the fees MIM generated during the five-year project investment period. Income from its endowment, along with annual fees, were to help MIM cover its operating expenses in the post-project period. The project was to fund MIM's civil works, furniture, equipment and operating costs. A Canadian consortium was selected to provide initial technical services under a twinning agreement. 4. The project was also to assist the Ministry of Finance (MOF) with the implementation of its Development Plan and its ongoing tax modernization program. MOF was to be reorganized to strengthen its forward budgeting capability, to improve government accounting and auditing, and to strengthen claims processing and debt management. The project was also to continue support for the ongoing tax modernization begun under SAL III. The tax progran was to focus on reforms in trade taxes, more efficient collection of corporate taxes and an improved duty-drawback scheme to promote export growth. The project was expected to provide the technical assistance, equipment and training iii

8 required to help MOF carry out its Development Plan and tax modernization program. UNDP was expected to provide US$6.0 million equivalent in parallel financing. 5. It turned out that at project completion in 1994,2 implementation of the MOF component had not taken off, except the Tax Modernization Program which continued to be implemented. The story of the non-implementation of the major part of the MOF component is provided separately at the end of "Part I: Project Implementation Assessment". The next sections on "Implementation Experience and Results" and "Summary of Findings" are devoted to the project component on the Malawi Institute of Management (MIM) and to the sub-component on Tax Modernization, the only part of the MOF component that was implemented. Implementation Experience and Results 6. Based on the review of available documents both at Headquarters and in the field as well as on interviews conducted in the field, the mission found that: A. MIM. * Training: MIM exceeded planned targets for participants during the first three years but fell short of the targets in the last two years. The conduct of in-house management traimng proved particularly attractive for private sector enterprises. MIM revised and re-designed selected generic courses and introduced some new courses, notably in the areas of Business Management and Human Resources Management. But localization of training materials progressed at a lower pace than expected. * Consultancy: MIM recorded impressive achievements in consultancy with a cumulative total of over 150 tasks. The respective shares of clients among the civil service, statutory corporations and private sector enterprises were 20 percent, 31 percent and 25 percent. MIM's clients expressed satisfaction with the quality of work performed. The only complaints were occasional delays caused by work overload. * Research: MIM's record in the area of research was poor and the Management Development Consultants (MDCs) failed to exploit the mutually beneficial linkages between training, consultancy and research. * Civil Works: The construction of the campus of MIM was successfully completed, some nine months behind schedule. The construction work appears very satisfactory and the entire complex stands out as a beautiful and functional facility. 2 The original completion date for this project was June 30, 1994, six months before the initial closing date of December 31, However, some implementation activities continued until December 1994 and project credit was still used to cover some operational expenses until June 30, 1995 when the component on MIM under the successor Second Institutional Development Project (ID II) became effective. Although the closing date was extended to June 30, 1996, project credit was only used for the purchase of supplies and equipment that had been approved before December 31, Therefore, 1994 will be used as the project completion date in this report. iv

9 B. Tax Modernization Program The results achieved under the TMP were mixed. The tax base was broadened with the introduction of surtax and some tax officials attended in-country and overseas training courses, focused on tax auditing techniques, surtax administration, tax collection and tax policy analysis. But the income tax administration computer system that was designed and installed could not be upgraded when this became necessary. There was also delay in the design and installation of a computerized system for customs and excise administration. Summary of Findings The first part of this summary focuses on MIM and the second part is on the TMP. A. MIM 7. Overall, the project outcome in respect of MIM was satisfactory and the establishment of the institute can be called a partial success story. Although a definite opinion on the sustainability of MIM would have to await the completion of the successor Second Institutional Development Project (ID II), a cross-section of the Institute's clients expressed confidence in its future, provided it learns from the lessons of the first five years. The following were identified as the areas of improvement that could contribute significantly to MIM's prospects for self-financing and sustainability: costconsciousness, diversification and aggressive marketing of training and consultancy products, more systematic consultation with clients, creative use of visiting trainers (adjunct faculty), networking both in-country and abroad, and optimal utilization of campus facilities. 8. The main positive lessons learned are: * Country ownership and commitment built through intensive participation at project preparation and maintained through implementation (the beneficiary organization, MIM, was also the implementation agency) were key ingredients for ensuring satisfactory project outcome. * Establishing MIM as a parastatal with significant autonomy ensured a sense of responsibility and accountability. To enhance this autonomy the practice of seconding civil servants to MIM was abandoned in 1993 and the incumbent chairman of MIM's Governing Board (1995) was selected from the private sector. * Donor coordination was effective throughout the project cycle, from preparation through implementation. The Bank was informed about the mid-term Evaluation undertaken by GOM and UNDP and it received a copy of the report. In turn, every Bank supervision mission consulted in detail with UNDP. All this contributed to the achievement of project development objectives * Clarity in the objectives set for technical assistance (TA) as was the case for ARA consultants (provided under a twinning arrangement with MIM) helped to guarantee some tangible results even though some of the objectives were not achieved. The concrete results recorded were particularly notable in the areas of curriculum and teaching materials development, staff training and development of consultancy capability. v

10 * Supervision with appropriate skills mix, and with adequate frequency, had a positive impact on project implementation. 9. The following are the lessons from implementation problem areas: B. TMP * The weakness of the accounting function in an implementation agency is certain to have adverse consequences for disbursement, auditing and procurement. MIM's limited capacity in accounting was largely responsible for the problems experienced in these areas. MIM was obliged to appoint a professionally qualified accountant as a condition of credit disbursement under ID II. * The implications of the objective of self-financing for MIM should have been spelled out more clearly with strong emphasis on cost-consciousness, examples of investment opportunities and monitoring targets for measuring progress toward the achievement of the objective. The fact that successive MIM chief executives failed to devote adequate attention to the subject meant that little progress was made. * Although MIM was granted significant autonomy, the composition of its Governing Board, with about 80 percent senior civil servants, and the employment of several civil servants as MDCs resulted in the enthronement of civil service culture in the Institute. Progress toward a business and entrepreneurial culture was slow. The recent increase in the number of Board members from the private sector, with one of them as its chairman, could help to hasten the transition from a civil service culture to a business culture. * The weak points in the twinning arrangement between ARA consultants and MIM included, among others, poor management of the transition from the expatriate Principal to a Malawian Principal; inadequate attention to the skills mix of the consultants recruited for MIM; limited interaction between some ARA experts and their Malawian counterparts; and inadequate attention to research and the development of a business culture. * The high proportion of TA funds that is spent on the payment of salaries and other expenses of expatriates, compared to what is spent directly on building capacity (fellowships for training and purchase of training materials and equipment), is certain to remain a controversial subject. The ARA/MIM experience was not an exception. Overall, about 72 percent of a total of US$4.2 million (provided by UNDP) was spent on the ARA consultants compared with only 28 percent on building local capacity in MIM. 10. The importance attached to TMP by both the Government and the donors who supported its implementation (UNDP and the World Bank) ensured that it was actually implemented even though the other activities under the MOF component were not implemented. However, the results were mixed with some achievements recorded in the areas of tax policy reform (broadening the tax base) and training. Problems included building local capacity in tax policy analysis, increased staff training, and installation of computerized systems for income tax, customs and excise administration. vi

11 11. The main lessons from the TMP relate to the role of TA in capacity building for development: * Resident TA that is almost an enclave, as was the case with Harvard Institute for International Development (HIID) for most of the period, could perform satisfactorily in some areas (such as the reform of tax policy and the design of new computer systems) but inadequate oversight by the beneficiary government could result in avoidable errors such as the unupgradable TACS. With the advantage of hindsight, one can now say that the oversight the GOM tried to provide through request for periodic reports turned out to be ineffective as HIID produced thick reports (including new proposals for extension of contract) that were not critically reviewed. After the disbursement of the funds provided under the IDA credit was completed in July 1991, the World Bank only monitored developments regarding TMP. And the UNDP apparently did not supervise the utilization of the additional grants that it provided. The result of all this from 1992 onwards was one "bridging finance" after another (always at the request of GOM) with no real check on what had been achieved. Thus, for example, the inadequacy of the TACS was not discovered until late in * The poor coordination (involving GOM, UNDP and the World Bank) evident in the plans for the computerization of customs administration suggests that the new strategy GOM was putting in place for donor coordination in the field of TA for economic and fiscal management (January/February 1995) needed to be fine-tuned. (Subsequently, some finetuning of donor coordination mechanisms was carried out and the IMF, UNDP and UK/ODA are now supporting GOM's efforts to improve tax and customs administration). * The training of counterparts in specialized areas of tax policy analysis and the design and installation of computer systems produced the same mixed results as in TA efforts in many other developing countries: many counterparts were sent for training but only a few have returned to strengthen tax administration. Some were lost to other sectors of the economy while a few were lost to natural causes. Currently, GOM has only two experts in tax policy analysis and GOM has decided to utilize part of the new Second Institutional Development credit to build tax policy analysis capacity. vii

12

13 MALAWI INSTITUTIONAL DEVELOPMENT PROJECT (CREDIT 2036-MAI) Part 1. Project Implementation Assessment Project Identity Project Name Institutional Development Project (ID I) Credit No MAI RVP Unit AF1C3 Country Malawi Background 1. In 1985, the Government of Malawi decided to establish a management institute and it formally requested the Bank for assistance in GOM's decision was based on studies carried out between 1979 and 1985 on how it could provide in-service training for middle-level and senior officials in the civil service. Following a further preparatory study, it was decided that a Malawi Institute of Management would be established with a main campus in Lilongwe and satellite campuses in Zomba and Blantyre. The satellite campuses were intended to help ensure close collaboration between the proposed MIM and the University of Malawi (UOM) through its Chancellor College at Zomba and the Polytechnic in Blantyre. Furthermore, MIM was expected to use the satellite campuses for courses aimed at the numerous parastatal and private enterprises in the Blantyre area. 2. By 1988, GOM had decided to make the establishment of MIM part of a larger project for institutional development. The proposed project included the strengthening of institutional capacity in the Ministry of Finance (MOF) and the continuation of an on-going Tax Modernization Program (TMP). The institutional strengthening actions of MOF were to be derived from the Ministry's Development Plan (DEVPLAN) prepared with the assistance of the UNDP. Project preparation was completed in 1989 with negotiations in April and Board approval was granted in June. The project became effective in January Project Objective and Description 3. Project objective. The project's objective was to strengthen national economic management. The Malawi Institute of Management was to offer a wide range of training programs and seminars aimed at improving the capacity of Malawian managers in the public and private sectors. The strengthening program in the Ministry of Finance was to improve the Ministry's capacity to manage public resources through upgrading processes for budgeting, accounting and auditing, debt management and claims, and to improve revenue flows through modernization of the tax system.

14 4. Project Description. The project was to establish and operate the Malawi Institute of Management (MIM) to train managers in the public and private sectors in management techniques. In addition to its own campus, MIM was to work closely with the University of Malawi, sharing facilities with two of the University's affiliates, Chancellor College and the Polytechnic. An Endowment Fund was to be established to receive all the fees MIM generated during the five-year project investment period. Income from its endowment, along with annual fees, were to help MIM cover its operating expenses in the post-project period. The project was to fund MIM's civil works, furniture, equipment and operating costs. A Canadian consortium, ARA consultants, was selected to provide initial technical services under a twinning agreement (see Appendix B). 5. The project was also to assist the Ministry of Finance with the implementation of its Development Plan and its ongoing tax modernization program. MOF was to be reorganized to strengthen its forward budgeting capability, to improve government accounting and auditing, and to strengthen claims processing and debt management. The project was also to continue support for the ongoing tax modernization program (TMP)begun under SAL III. The tax program was to focus on reforms in trade taxes, more efficient collection of corporate taxes and an improved duty-drawback scheme to promote export growth. The project was expected to provide the technical assistance, equipment and training required to help MOF carry out its Development Plan and tax modernization program. UNDP was expected to provide US$6.0 million equivalent in support of the project. At the implementation stage, only the TMP sub-component continued to be implemented. Following the detailed "Implementation Assessment" of the MIM component, a brief assessment of the TMP is provided and this is followed by the story of the non-implementation of the MOF component. A. MIM Achievement of Project Objectives 6. The objective of establishing MIM as a center of excellence for training and consultancy in management was achieved to a great extent. The Mid-Term Evaluation Report prepared jointly by the UNDP and the Government of Malawi in July 1992 declared MIM a success story, pointing to the fact that it was providing high quality training and consultancy services for the civil service, the parastatals and the private sector. At that point in time, MIM steadily exceeded the targets set for it in respect of both training and consultancy and its Endowment Fund was much larger than had been anticipated. At the end of the project, a verdict of apartial success story would be more appropriate. MIM did not fully meet the targets set for participants at its courses in 1993 and However, consultancy activities remained at levels that were above what had been anticipated in the SAR. Although the Endowment Fund was almost thrice the amount projected in the SAR, the real value of the total amount was probably only slightly over the initial projection because of high inflation and rapid depreciation of the Malawi Kwacha in 1993/1994. The goal of self-financing for MIM at the end of the project, that is, the capacity to meet its operating costs from its Endowment Fund along with annual fees, was not achieved (see Appendix C). 2

15 Major Factors Affecting the Project 7. The poor performance of the Malawian economy from 1992 onwards, due partly to the suspension of overseas development assistance (excluding humanitarian aid) for governance reasons and partly to successive droughts, reduced the demand for MIM's services. Although the actual impact is difficult to measure, MIM's clients admitted that a period of staff reduction and reduced profits was also matched by reduced resources for training and consultancy services. 8. The political transition that dominated the last two years of project implementation (1993 and 1994) had some impact on the project. While the construction of MIM's campus was completely insulated from this factor, the leadership crisis at the Institute which persisted for most of 1993 could be traced, in part, to the new atmosphere of questioning of authority prevailing in the larger society. In the end, the first Malawian Principal who was appointed in April 1992 was removed in September (The interim Principal who took over from him was confirmed in the position a year later). This leadership crisis interlude adversely affected MIM's performance in 1993 and (In addition to the Principal, MIM lost three of its MDCs whose secondment from the Civil Service was terminated as part of the resolution of the leadership issue). Implementation Record 9. Key Performance Indicators. The SAR provided key performance indicators in two areas of MIM's activities: participants in its courses and the progress recorded in building up its Endowment Fund. A summary of the targets set for MIM regarding participants at its courses and the actual achievements is provided in Table 7A. The targets set regarding the Endowment Fund and the actual results are recorded in Appendix C. 10. Training, Consultancy and Research. As shown in Table 7A, MIM exceeded the planned targets for participants during the first three years but fell short of the targets in the last two years. The adverse effect of the leadership crisis of 1993 was the major explanatory factor of this decline in performance. The mix of training through the delivery of generic courses and the conduct of in-house (tailor made) training (in form of consultancy) was uneven - participation in in-house training was very high in both 1993 and 1994 when there was a significant decline in the participation in generic training courses. MIM's clients expressed great satisfaction with in-house management training courses throughout the project period. The courses are designed in close collaboration with relevant officials of the enterprises concerned and this ensured both relevance and ownership. They were also cost-effective because they were delivered in-house to varying numbers of clients' employees. Significantly, the private sector made greater demand on MIM's in-house courses than the parastatal and public sectors. Selected generic courses were revised and re-designed and some new courses introduced, notably in the areas of Business Management and Human Resources Management. But localization of training materials progressed at a lower pace than expected. With regard to the objective of having clients pay for the full costs of training at MIM, GOM's 1990 directive to ministries to make annual budgetary allocations for training was not faithfully implemented and MIM sent confusing signals to its clients by failing to systematically phase out the fellowships for its courses. 11 MIM's achievements in consultancy were very impressive. The SAR only mentioned that it would conduct some consultancy tasks, yielding only modest earning that would be paid to its Endowment Fund. Tables 7B and 7C show the number of consultancy tasks undertaken by MIM during the period. The respective shares of the civil service, statutory corporations and private sector 3

16 enterprises are 20 percent, 31 percent and 25 percent. The significant contributions of consultancy to MIM's Endowment Fund is reflected in Appendix C. MIM's clients expressed satisfaction with the quality of work performed by the MDCs. The only complaints were occasional delays caused by work overload. Within, MIM there was lack of adequate monitoring of the balance between training and consultancy. Specifically, there was a tendency to spend more time on consultancy (which yielded additional earning for the MDCs) than MIM's own rules formally allowed, leaving reduced time for training and research. In theory, each MDC was expected to share his/her time as follows: 60 percent for training; 30 percent for consultancy and 10 percent for research. In practice, MDCs spent, on average, more than 40 percent of their time on consultancy. 12. MIM's record in the area of research was poor. The occasional efforts made did not yield any significant results. The attempts to launch a publication, were quickly abandoned and no real effort was made to disseminate what MIM learned about management in the Malawian milieu. The MDCs failed to exploit the mutually beneficial linkages between training, consultancy and research. 13. Civil Works. The construction of the campus of MIM in Kanengo, Lilongwe, was successfully completed, some nine months behind schedule. The construction work appears very satisfactory and the entire complex stands out as a beautiful and functional facility. (See Appendix D, "Construction of Malawi Institute of Management. Report by Ministry of Works and Supplies"). 14. Disbursements, Counterpart Financing and Co-financing. Disbursement data show a steady utilization of project credit that was very close to the projections in the SAR for the mniddle years. Total credit disbursed by November 4, 1996 was US$12.1 million. 3 The undisbursed balance at project closing was canceled. 15. Counterpart financing was provided by GOM as required in the DCA. Of the US$1.6 million government contribution envvuag?.d, US$2.5 million was actually spent. Thuls, the Borrower's share of project financing was 21 percent (see Table 6A). 16. UNDP, the cofinancier, was expected to contribute about US$6 million to the financing of the project UNDP's actual contribution was US$4.1 million Procurement. The major procurement in the project was the contract for MIM's campus and this was done according to acceptable Bank procedures. Procuring vehicles and other equipment also followed acceptable Bank procedures. The final tendering for carpets and furnishing of the buildings on MIM's campus was delayed partly because it had to be prepared over several iterations to ensure compliance with established procedures. To allow adequate time for completing the procurement process, the original closing date of December 31, 1994 was extended thrice at the request of the Government for a total of eighteen months, with a final closing date of June 30, This figure includes the SDR 620,000 (US$0.8 million) spent on TA and training for the Tax Modernization Program. 4 While UNDP's actual financing of MIM is known, data on its actual financing of the Tax Modernization Program are not available. The non-financing of the other activities under the MOF component is discussed separately below. 4

17 Project Sustainability and Future Operation 18. MIM has been firmly established as a management Institute and continued IDA support under the Second Institutional Development project (ID II) is intended to help consolidate the achievements recorded under ID I. While a verdict on the institute's sustainability would have to await the completion of ID II, the single performance criterion set for it under the new operation is the progress it makes towardfinancial self-reliance. To this end, performance indicators have been established to monitor progress and project credit will be provided on a declining basis to ensure that the Institute's own resources are progressively used to meet operating costs. The SAR for ID II requires MIM to progressively cover its salaries and operating costs from its Endowment Fund as follows: 20 percent in 1995/96, 40 percent in 1996/97, 60 percent in 1997/98, and 80 percent in 1998/99. Bank's Performance 19. Identification of the project was largely completed by the Government before IDA assistance was formally requested. Preparation was a joint effort of the Government and IDA. UNDP as cofinancier provided some inputs. In appraisal, the innovative idea of an Endowment Fund for MIM was adopted but the expectation that the Fund would help to ensure MIM's financial self-reliance at the end of the project turned out to be unrealistic. Similarly, the scope of physical infrastructure envisaged for MIM - one main campus in Kanengo (Lilongwe), one satellite campus each in Zomba (Chancellor College) and Blantyre (at The Polytechnic) and some staff housing - was far beyond what the project credit could finance. These ambitious plans were agreed upon by IDA and the Government at negotiations. However, the physical infrastructure plan was quickly scaled down to the construction of the main canpus by the end of the first year of project implementation. 20. Supervision by IDA was adequate: an average of two supervision missions per year. Only two task managers were involved from project preparation through project completion. This continuity had a positive impact on project implementation. To ensure that MIM was provided with relevant advice and some comparative perspectives, one Institutional Development Specialist with first-hand familiarity with the work of similar Institutes in Sub-Saharan Africa participated in one of the two supervision missions in 1990, 1991, 1992 and The self-standing reports prepared by the Institutional Development Specialists contain thoughtful observations and suggestions that MIM could continue to mine for use in future. IDA failed to get MIM to submit audit reports on time. However, the delayed audit reports were unqualified and they were accompanied by useful "management reports" which consistently drew attention to MIM's lack of cost-consciousness. IDA monitored adherence to procurement and disbursement procedures fairly closely and a major case of misprocurement was averted because of the vigilance of the Resident Mission which was systematically involved in project supervision. Borrower's Performance 21. The fact that project identification had been completed by the Government before it requested IDA assistance was a strong evidence of country ownership and commitment. Subsequently, the involvement of several pioneering MIM staff in projectpreparation further deepened borrower ownership and commitment. Government decision to grant significant autonomy to MIM as a parastatal enhanced its smooth take off and steady progress. In implementation, MIM's 5

18 capacity was rather limited in its Accounting Section and this was largely responsible for the delayed audits and persistent errors in disbursements. MIM staff responsible for procurement did not fully master IDA's procurement procedures and this almost resulted in a serious mis-procurement in Covenant compliance was very satisfactory; all covenants relating to MIM in the Development Credit Agreement were met on schedule. In project operation, MIM's coordination with the Ministry of Finance was inadequate, with IDA serving as a link on occasions. Some improvement was noticeable during the last year of project implementation. Assessment of Outcome 22. Overall, the project outcome was satisfactory. Indeed, there is a real sense in which the establishment of MIM could be called apartial success story. The ICR mission found unanimity on MIM's relevance and satisfactory performance among its clients in the public, parastatal and private sectors. It was variously referred to as a "welcome management gap filler", a "very useful institution", a "superb initiative" and the "best in the market". Although a definite opinion on its sustainability would have to await the completion of ID II, it is significant that the cross-section of its clients expressed confidence in its future, provided it learns from the lessons of the first five years. MIM's staff as well as all six key members of the Governing Board met by the mission shared this opinion. (See Appendix A). There was broad agreement on the areas of improvement that could contribute significantly to MIM's prospects for self-financing by the end of ID II: cost-consciousness, diversification and aggressive marketing of training and consultancy products, more systematic consultation with clients, creative use of visiting trainers (adjunct faculty), networking both in-country and abroad, and optimal utilization of campus facilities. Key Lessons Learned 23. The main positive lessons learned are: * Country ownership and commitment built through intensive participation at project preparation and maintained through implementation (the beneficiary organization, MIM, was also the implementation agency) were key ingredients for ensuring satisfactory project outcome. * Establishing MIM as a parastatal with significant autonomy ensured a sense of responsibility and accountability. To enhance this autonomy the practice of seconding civil servants to MIM was abandoned in 1993 and the incumbent chairman of MIM's Governing Board was selected from the private sector. * Donor coordination was effective throughout the project cycle, from preparation through implementation. The Bank was informed about the Mid-Term Evaluation undertaken by GOM and UNDP and it received a copy of the report. In turn, every Bank supervision mission consulted in detail with UNDP. All this contributed to the achievement of project development objectives. * Clarity in the objectives set for TA as was the case for ARA consultants helped to guarantee some tangible results even though some of the objectives were not achieved. The concrete results recorded were particularly notable in the areas of curriculum and 6

19 teaching materials development, staff training and development of consultancy capability. * Supervision with appropriate skill mix, and with adequate frequency, had a positive impact on project implementation. 24. The following are the lessons from implementation problem areas: * The weakness of the accounting function in an implementation agency is certain to have adverse consequences for disbursement, auditing and procurement. MIM's limited capacity in accounting was largely responsible for the problems experienced in these areas. MIM was obliged to appoint a professionally qualified accountant as a condition of credit disbursement under ID II. * The implications of the objective of self-financing for MIM through the Endowment Fund should have been spelled out more clearly with strong emphasis on cost-consciousness, examples of investment opportunities and monitoring targets for measuring progress toward the achievement of the objective (see Appendix C). The fact that successive MIM chief executives failed to devote adequate attention to the subject meant that little progress was made. - Although MIM was granted significant autonomy, the composition of its Governing Board, with about 80 percent senior civil servants, and the employment of several civil servants as MDCs resulted in the enthronement of civil service culture in the Institute. Progress toward a business and entrepreneurial culture was slow. The recent increase in the number of Board members from the private sector, with one of them as its chairman, could help to hasten the transition from a civil service culture to a business culture. * The weak points in the twinning arrangement between ARA consultants and MIM included, among others, poor management of the transition from the expatriate Principal to a Malawian Principal; inadequate attention to the skill mix of the consultants recruited for MIM; limited interaction between some ARA experts and their Malawian counterparts; and inadequate attention to research and the development of a business culture. * The high proportion of TA funds that is spent on the payment of salaries and other expenses of expatriates, compared to what is spent directly on building capacity (fellowships for training and purchase of training materials and equipment), is certain to remain a controversial subject. The ARA/MIM twinning experience was not an exception (see Appendix B). Overall, about 72 percent of a total of US$4.2 million was spent on the ARA consultants compared with only 28 percent on building local capacity in MIM. B. TMP 5 5 This assessment is brief, compared to that of MIM, because the IDA funding was disbursed quickly within the first eighteen months of project life. Subsequent funding was through "bridging finance" that was most often provided retroactively (mostly by UNDP) and the full details were not available to the ICR mission. 7

20 25. According to the Development Credit Agreement, the Ministry of Finance (MOF) was expected to implement TMP "with the assistance of suitable consultants." As already mentioned, the TMP, was already on-going when the other components of the project were being prepared. The first implementation phase was through a two-year contract signed with the Harvard Institute for International Development (HIID) in IDA's contribution to the TMP was SDR 620,000 to be spent on TA and training. By July 1991, the IDA credit allocated to the TMP had been spent and over US $1.0 million of UNDP funds had also been spent on the program. In 1992, UNDP allocated an additional US $0.5 million to the TMP. 26. Before the HIID contract was renewed for another two-year period (March February 1994), the major achievements of the TMP were in respect of tax policy and legislative reform, especially the broadening of the tax base. Surtax, a value-added type of taxation, was introduced and later expanded to cover most services. An income tax administration computer system (TACS) and a surtax administration computer system (SACS) were designed, installed and made operational. Many tax officials attended in-country training courses and a few were sent on overseas training. The incountry training courses focused on tax auditing techniques, surtax administration, and tax collection administration (using training manuals prepared by HIID experts). The overseas training courses were focused on tax policy analysis and computer studies. The achievements recorded during the period consisted of the addition of new features to the computerized income tax system and the design of a computerized system for customs and excise administration. By February 1995, the system was partially ready to begin operation. In-country training of the staff of both the Income Tax Department and the Department of Customs and Excise also continued, especially in computer applications. 27. Notwithstanding the achievements recorded, the mission found that GOM was dissatisfied with the performance of its tax and customs administration. The computerized system designed for the Income Tax Department is not upgradable and the existing system has to be expanded and new equipment must be purchased. With regard to customs administration, new technical assistance to be provided by the IMF and UK/ODA could mean that only the aspect of HIID computerization work relating to customs administration in border posts would be used for about two years while a new system, the ASYCUDA (reputed to be performing satisfactorily in many developing countries), developed externally, would be installed. If this were to happen, the current system developed for Malawi will be discarded. It would also mean that the Customs Department would not be able to exchange data easily with the computer system already in place for income tax and surtax administration. All this would amount to a huge waste of resources: all the expenses on research, design, programming and computer-related training would be lost. Only some of the recently purchased equipment would be salvaged. Key Lessons Learned 28. The main lessons from the TMP relate to the role of TA in capacity building for development: Resident TA that is almost an enclave, as was the case with HIID for most of the period, could perform satisfactorily in some areas (such as the reform of tax policy and the design of new computer systems) but inadequate oversight by the beneficiary government could result in avoidable errors such as the unupgradable TACS. With the advantage of hindsight, one can now say that the oversight the GOM tried to provide through request for periodic reports turned out to be ineffective as HIID produced thick reports (including new proposals for extension of contract) that were not critically reviewed. After the 8

21 disbursement of the funds provided under the IDA credit was completed in July 1991, the World Bank only monitored developments regarding the TMP. And the UNDP apparently did not supervise the utilization of the additional grants that it provided. The result of all this from 1992 onwards was one "bridging finance" after another (always at the request of GOM), with no real check on what had been achieved. Thus, for example, the inadequacy of the TACS was not discovered until late in * The poor coordination evident in the plans for the computerization of customs administration suggests that the new strategy being put in place for donor coordination in the field of TA for economic and fiscal management (January/February 1995) needed to be fine-tuned. (Some fine-tuning of donor coordination mechanisms has since taken place and the IMF, UNDP and UK/ODA are now supporting GOM's efforts to improve tax and customs administration). * The training of counterparts in specialized areas of tax policy analysis and the design and installation of computer systems produced the same mixed results as in TA efforts in many other developing countries: many counterparts were sent for training but only a few have returned to strengthen tax administration. Some were lost to other sectors of the economy while a few were lost to natural causes. Currently, GOM has only two experts in tax policy analysis and GOM has decided to utilize part of the new Second Institutional Development credit to build tax policy analysis capacity. C. MOF's Devplan: Implementation Failure 29. The identification and preparation of the MOF component involved GOM, UNDP and the Bank. Although there were consultations among all three partners during the preparation phase, the studies undertaken with financial support from the UNDP and the Bank were not effectively coordinated. A Bank-supported study, "Building Capacity for the Future: A Program to Strengthen the Organisational Performance of the Malawi Ministry of Finance in a Period of Structural Adjustment" was completed in February, 1988 while the UNDP-supported study on the Development Plan (DEVPLAN) of MOF was not completed until February, According to the Development Credit Agreement, MOF was expected to implement its comprehensive development plan by taking all necessary measures to: "(a) restructure its organisation, in accordance with such plan, with the assistance of consultants, as necessary; (b) (i) prepare a plan for introducing a forward budget system; (ii) develop terms of reference for a user needs study of computerization requirements; and (iii) prepare a plan for improving its audit services; (c) prepare a human resources development plan including a timetable for filling vacancies for professional positions in MOF." 30. In September 1990, UNDP approved US$3.5 million to support the MOF DEVPLAN but the project document was not finalised until October 1991 when it was renamed "Government Financial Management Development" and the project fund was reduced to US$2.5 million. The institutional 9

22 strengthening activities spelled out in the project document were to focus on government financial management, government accounting, government auditing and taxation. (The specificity in the project description contained in the Bank's DCA had disappeared). 31. At the fonnal completion of ID I in June 1994, implementation of the MOF component had not taken off apart from implementation of the Tax Modernization Program (TMP) which continued with periodic interruptions. GOM, the Bank (which provided the framework ID project) and UNDP (which approved funds for the MOF component) failed to coordinate effectively to ensure implementation. (See GOM's views on this problem in Part II of the Report). A major problem on the part of GOM was the lack of continuity and quality in the staffing of MOF in some critical positions for most of the period. This delayed the finalisation of the project document and after UNDP had approved the project, MOF was unable to provide qualified staff to take charge of implementation. Because the MOF component was regarded as one single package (excluding the TMP), the activities aimed at strengthening the Accountant General's office could not be implemented even though the AG and his staff were ready for action. 32. UNDP was unable to persuade GOM to employ some technical assistants to lead the implementation effort. GOM did not want a large proportion of the project fund to be spent on the salaries of TA. It was at this juncture that UNDP proposed a further reduction of its allocation from $2.5 million to US$ 1.1 million in (This new reduction coincided with a general reduction of UNDP's total support for the Fifth Country program, ). Finally, UNDP abandoned pressing for the implementation of the Government Financial Management Development Project in July 1994 when it diverted the project fund to a new initiative, called Capacity Building Program for Economic Management (CBPEM). 33. The continuous promise of impending agreement between GOM and UNDP between 1990 and 1992 prevented the Bank from considering any amendment to the project's Development Credit Agreement to take into account the non-implementation of the MOF component. Eventually, by the time the preparation of the successor Second Institutional Development Project (ID II) began in 1992, both GOM and the Bank agreed to take into account the lessons of implementation failure of the MOF component under ID I, especially in respect of the use of technical assistance. Furthermore, strengthening the capacity of the office of the Accountant General was constituted into a distinct subcomponent of ID II. Key Lessons Learned 34. The following are the key lessons learned from this unsuccessful effort to strengthen the institutional capacity of the MOF. * The studies sponsored by IDA and UNDP did not involve MOF staff who were only required to react to the reports of the studies. This was responsible for the delay in finalising the project document. More importantly, MOF staff did not seem committed to the project. * UNDP's excellent idea of using Govermments as executing agencies for its development programmes runs the risk of failure in cases where there is limited local management capacity as in the MOF experience. 10

Document of The World Bank

Document of The World Bank Document of The World Bank PROJECT COMPLETION NOTE OF A LEARNING AND INNOVATION LOAN IN THE AMOUNT OF SDR 2.7 MILLION (US$4 MILLION EQUIVALENT) TO THE REPUBLIC OF MALAWI FOR A DEVELOPMENT LEARNING CENTER

More information

GOOD PRACTICE CASE STUDY BANGLADESH: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT 1 BACKGROUND

GOOD PRACTICE CASE STUDY BANGLADESH: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT 1 BACKGROUND GOOD PRACTICE CASE STUDY BANGLADESH: CAPACITY DEVELOPMENT IN PUBLIC FINANCIAL MANAGEMENT 1 BACKGROUND 1. This case study reviews the efforts of Government of Bangladesh (GoB) to develop capacity in and

More information

Mid Term Review of Project Support for enhancing capacity in advising, examining and overseeing macroeconomic policies

Mid Term Review of Project Support for enhancing capacity in advising, examining and overseeing macroeconomic policies Mid Term Review of Project 00059714 Support for enhancing capacity in advising, examining and overseeing macroeconomic policies Final Evaluation Report Date of Report: 8 August 2013 Authors of Report:

More information

INTEGRATED SAFEGUARDS DATA SHEET

INTEGRATED SAFEGUARDS DATA SHEET Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET IDENTIFICATION / CONCEPT STAGE Date ISDS Prepared/Updated:

More information

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Department of Fisheries Ministry of Natural Resources Teone, Funafuti TUVALU Email: proptuv@gmail.com / proptuv@tuvalufisheries.tv

More information

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Water and Urban I1 Africa Region Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

Project development objective/outcomes

Project development objective/outcomes Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized THE SAINT VINCENT & THE GRENADINES HIV/AIDS PREVENTION AND CONTROL PROJECT PE-PO76799

More information

L 347/174 Official Journal of the European Union

L 347/174 Official Journal of the European Union L 347/174 Official Journal of the European Union 20.12.2013 REGULATION (EU) No 1292/2013 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 11 December 2013 amending Regulation (EC) No 294/2008 establishing

More information

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931)

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF LAND HUSBANDRY, WATER HARVESTING AND HILLSIDE IRRIGATION PROJECT APPROVED

More information

Table 1 the Road Network of Mozambique (in kilometers)

Table 1 the Road Network of Mozambique (in kilometers) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB2867 Roads

More information

Country Practice Area(Lead) Additional Financing Afghanistan Governance P150632,P150632

Country Practice Area(Lead) Additional Financing Afghanistan Governance P150632,P150632 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021292 Public Disclosure Authorized Public Disclosure Authorized Project ID P120427 Project Name AF: ARTF-Public Fin. Mgmt. Reform II Country

More information

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue Technical Assistance Report Project Number: 46429-001 Capacity Development Technical Assistance (CDTA) April 2013 Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal

More information

Bilateral Guideline. EEA and Norwegian Financial Mechanisms

Bilateral Guideline. EEA and Norwegian Financial Mechanisms Bilateral Guideline EEA and Norwegian Financial Mechanisms 2014 2021 Adopted by the Financial Mechanism Committee on 9 February 2017 09 February 2017 Contents 1 Introduction... 4 1.1 Definition of strengthened

More information

The World Bank MW: Mining Governance and Growth Support Project (P120825)

The World Bank MW: Mining Governance and Growth Support Project (P120825) Public Disclosure Authorized AFRICA Malawi Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 10 ARCHIVED on 05-Jan-2018 ISR28752 Implementing Agencies: Government

More information

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4199 UG Public Disclosure Authorized Financing Agreement (Uganda Public Service Performance Enhancement Project) between Public Disclosure Authorized

More information

ASIAN DEVELOPMENT BANK TAR:PRC

ASIAN DEVELOPMENT BANK TAR:PRC ASIAN DEVELOPMENT BANK TAR:PRC 34096-03 TECHNICAL ASSISTANCE TO THE PEOPLE'S REPUBLIC OF CHINA FOR ADVISORY SUPPORT FOR THE NATIONAL COUNCIL FOR THE SOCIAL SECURITY FUND October 2003 CURRENCY EQUIVALENTS

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK TAR:UZB 36498

ASIAN DEVELOPMENT BANK TAR:UZB 36498 ASIAN DEVELOPMENT BANK TAR:UZB 36498 TECHNICAL ASSISTANCE TO THE REPUBLIC OF UZBEKISTAN FOR DEVELOPMENT OF THE CAPITAL MARKET July 2003 CURRENCY EQUIVALENTS (as of 30 June 2003) Currency Unit sum SUM1.00

More information

BRUSSELS, BELGIUM 22 SEPTEMBER 2004

BRUSSELS, BELGIUM 22 SEPTEMBER 2004 WRITTEN STATEMENT OF SIR DAVID TWEEDIE CHAIRMAN, INTERNATIONAL ACCOUNTING STANDARDS BOARD, TO THE COMMITTEE ON ECONOMIC AND MONETARY AFFAIRS OF THE EUROPEAN PARLIAMENT BRUSSELS, BELGIUM 22 SEPTEMBER 2004

More information

September Preparing a Government Debt Management Reform Plan

September Preparing a Government Debt Management Reform Plan September 2012 Preparing a Government Debt Management Reform Plan Introduction Preparing a Government Debt Management Reform Plan The World Bank supports the strengthening of government debt management

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) 2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) TECHNICAL SPECIFICATIONS 15 July 2016 1 1) Title of the contract The title of the contract is 2nd External

More information

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18 Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18 1. Basic information 1.1. CRIS Number: 2010/022-154 1.2. Title: Technical Assistance and Project Preparation Facility (TA&PPF)

More information

Guidelines for Financial Assurance Planning

Guidelines for Financial Assurance Planning For Global Fund Grants Guidelines for Financial Assurance Planning June 2016 Geneva, Switzerland The financial assurance plan provides improvements to the way the Global Fund obtains financial assurance

More information

Gift Aid and reliefs on donations

Gift Aid and reliefs on donations Report by the Comptroller and Auditor General HM Revenue & Customs Gift Aid and reliefs on donations HC 733 SESSION 2013-14 21 NOVEMBER 2013 4 Key facts Gift Aid and reliefs on donations Key facts 2bn

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS)

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) OPERATIONS POLICY AND COUNTRY SERVICES APRIL 2, 2002 FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) CONTENTS Page I. Introduction..1 II.

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Project Name Region Sector Project ID Borrower(s) Report No. PID5794 Lebanon-Municipal Infrastructure Project (@+) Middle East and North Africa Region Other Urban Development LBPE50544 Lebanese Republic

More information

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments Annex 1. Identification Title/Number Trinidad and Tobago Annual Action Programme 2010 on Accompanying Measures on Sugar; CRIS reference: DCI- SUCRE/2009/21900 Total cost EU contribution : EUR 16 551 000

More information

REPORT 2015/174 INTERNAL AUDIT DIVISION

REPORT 2015/174 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/174 Audit of management of selected subprogrammes and related capacity development projects in the United Nations Economic and Social Commission for Asia and the Pacific

More information

Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program Grant Agreement

Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program Grant Agreement Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MDTF GRANT NUMBER TF013825 Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION REPORT FEDERAL REPUBLIC OF NIGERIA

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION REPORT FEDERAL REPUBLIC OF NIGERIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Human Development 3 Africa Region Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION

More information

DSA Report of Project Activities: July 1 st to September 31 st, 1997

DSA Report of Project Activities: July 1 st to September 31 st, 1997 DSA Report of Project Activities: July 1 st to September 31 st, 1997 Project Report: Q-2 Decentralization Support Activity Project Ministry of Finance & Ministry of Economy Development and Cooperation

More information

Guideline for strengthened bilateral relations. EEA and Norway Grants

Guideline for strengthened bilateral relations. EEA and Norway Grants Guideline for strengthened bilateral relations EEA and Norway Grants 2009 2014 Adopted by the Financial Mechanism Committee 29.03.2012, amended on 28 January 2016 Contents 1 Purpose of the guideline...

More information

III. modus operandi of Tier 2

III. modus operandi of Tier 2 III. modus operandi of Tier 2 Objective, country and project eligibility 70 Budget and timing 71 Project preparation: formulation of proposals 71 Project appraisal 72 Project approval 73 Agreements and

More information

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON)

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) Board of Directors IN.365-10 21 December 2010 Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) The attached Report is circulated at the request of the Director General, Independent Evaluation

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Lebanon Social Protection & Labor Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 09-Jan-2017

More information

Armenia: Infrastructure Sustainability Support Program

Armenia: Infrastructure Sustainability Support Program Technical Assistance Report Project Number: 46220 Policy and Advisory Technical Assistance (PATA) December 2012 Armenia: Infrastructure Sustainability Support Program The views expressed herein are those

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

Country Practice Area(Lead) Additional Financing Finance, Competitiveness and

Country Practice Area(Lead) Additional Financing Finance, Competitiveness and Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020839 Public Disclosure Authorized Public Disclosure Authorized Project ID P108080 Project Name XK

More information

Indonesia: Capacity Building in Urban Infrastructure Management Project

Indonesia: Capacity Building in Urban Infrastructure Management Project Validation Report Reference Number: PCV: INO 2008-68 Project Number: 27289 Loan Number: 1572-INO May 2009 Indonesia: Capacity Building in Urban Infrastructure Management Project Independent Evaluation

More information

STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF

STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF Ministry of Finance STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF 2017-2020 www.mfin.gov.rs REPUBLIC OF SERBIA MINISTRY OF FINANCE TABLE OF CONTENTS

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

Financing (In USD Million) Financing Source

Financing (In USD Million) Financing Source Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 06-Dec-2012 I. BASIC INFORMATION 1. Basic Project Data INTEGRATED

More information

Global Environment Facility Grant Agreement

Global Environment Facility Grant Agreement Public Disclosure Authorized CONFORMED COPY GEF GRANT NUMBER TF092100 Public Disclosure Authorized Global Environment Facility Grant Agreement (Agricultural Development Program Support Project) Public

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Program-for-Results Financing 1

Program-for-Results Financing 1 Operational Manual BP 9.00 - Program-for-Results Financing These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. BP 9.00 February, 2012

More information

INTERNATIONAL MONETARY FUND AND THE INTERNATIONAL DEVELOPMENT ASSOCIATION MALAWI

INTERNATIONAL MONETARY FUND AND THE INTERNATIONAL DEVELOPMENT ASSOCIATION MALAWI INTERNATIONAL MONETARY FUND AND THE INTERNATIONAL DEVELOPMENT ASSOCIATION MALAWI Poverty Reduction Strategy 2003/04 Annual Progress Report Joint Staff Advisory Note Prepared by the Staffs of the IMF and

More information

ECOTEC FROM PRE-ACCESSION TO ACCESSION. Thematic Evaluation. of European Union Phare Programme

ECOTEC FROM PRE-ACCESSION TO ACCESSION. Thematic Evaluation. of European Union Phare Programme FROM PRE-ACCESSION TO ACCESSION Thematic Evaluation of European Union Phare Programme Phare Support to Economic and Social Cohesion in Bulgaria and Romania ECOTEC European Commission Directorate-General

More information

REPORT 2015/041 INTERNAL AUDIT DIVISION. Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations

REPORT 2015/041 INTERNAL AUDIT DIVISION. Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations INTERNAL AUDIT DIVISION REPORT 2015/041 Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations Overall results relating to the effective management of mine action

More information

Internal Audit of the Republic of Albania Country Office January Office of Internal Audit and Investigations (OIAI) Report 2017/24

Internal Audit of the Republic of Albania Country Office January Office of Internal Audit and Investigations (OIAI) Report 2017/24 Internal Audit of the Republic of Albania Country Office January 2018 Office of Internal Audit and Investigations (OIAI) Report 2017/24 Internal Audit of the Albania Country Office (2017/24) 2 Summary

More information

REPORT 2016/038 INTERNAL AUDIT DIVISION. Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan

REPORT 2016/038 INTERNAL AUDIT DIVISION. Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan INTERNAL AUDIT DIVISION REPORT 2016/038 Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan Overall results relating to the effective management of operations in

More information

Action Fiche for Libya

Action Fiche for Libya Action Fiche for Libya 1. IDENTIFICATION Title/Number Total cost Aid method / Method of implementation Public administration capacity-building facility (ENPI/2011/276-708) EU contribution: EUR 4.5 million

More information

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION 1.1 OVERVIEW Preamble 1.1.1 The African Development Bank is the premier financial development institution in Africa dedicated to combating poverty and

More information

THE REPUBLIC OF UGANDA

THE REPUBLIC OF UGANDA THE REPUBLIC OF UGANDA REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF EAST AFRICAN PUBLIC HEALTH LABORATORIES NETWORKING PROJECT (EAPHLNP)IDA CREDIT NO.4531-UG FOR THE YEAR ENDED 30 TH JUNE

More information

IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL

IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL CHAPTER 6 IMPLEMENTING THE PARIS DECLARATION AT THE COUNTRY LEVEL 6.1 INTRODUCTION The six countries that the evaluation team visited vary significantly. Table 1 captures the most important indicators

More information

Maldives: Enhancing Tax Administration Capacity

Maldives: Enhancing Tax Administration Capacity Completion Report Project Number: 47150-001 Technical Assistance Number: 8525 August 2018 Maldives: Enhancing Tax Administration Capacity This document is being disclosed to the public in accordance with

More information

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. Public Disclosure Authorized CONFORMED COPY GRANT NUMBER H732 -AF Public Disclosure Authorized Financing Agreement Public Disclosure Authorized (Financial Sector Rapid Response Project) between ISLAMIC

More information

Ebola Recovery and Reconstruction Trust Fund Grant Agreement

Ebola Recovery and Reconstruction Trust Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS GRANT NUMBER: TFOA1023 Public Disclosure Authorized Ebola Recovery and Reconstruction Trust Fund Grant Agreement (LABOR-INTENSIVE PUBLIC WORKS TO MITIGATE

More information

Job Description and Requirements Programme Manager State-building and Governance Job no in the EU Delegation to the Republic of Yemen

Job Description and Requirements Programme Manager State-building and Governance Job no in the EU Delegation to the Republic of Yemen JOB PROFILE 17/08/2013 Job Description and Requirements Programme Manager State-building and Governance Job no. 127004 in the EU Delegation to the Republic of Yemen Job Type: Contract Agent Function Group

More information

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) LOAN/GEF GRANT

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) LOAN/GEF GRANT Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 30244 Public Disclosure Authorized PROJECT COMPLETION NOTE (SCL-4198; WBTF28362) ON A LOAN/GEF GRANT Public Disclosure

More information

Assignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information

Assignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information P R O C U R E M E N T N O T I C E Assignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information 1.1 Background information on the Regional School of

More information

Introduction. The Assessment consists of: Evaluation questions that assess best practices. A rating system to rank your board s current practices.

Introduction. The Assessment consists of: Evaluation questions that assess best practices. A rating system to rank your board s current practices. ESG / Sustainability Governance Assessment: A Roadmap to Build a Sustainable Board By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com November 2017 Introduction This is a tool for

More information

Capacity Development Strategies and Priorities Supporting Research, Developing Minds

Capacity Development Strategies and Priorities Supporting Research, Developing Minds Capacity Development Strategies and Priorities 2013 2018 Supporting Research, Developing Minds Introduction A key part of the Sheikh Saud Bin Saqr Al Qasimi Foundation s mission is to develop and deliver

More information

I Introduction 1. II Core Guiding Principles 2-3. III The APR Processes 3-9. Responsibilities of the Participating Countries 9-14

I Introduction 1. II Core Guiding Principles 2-3. III The APR Processes 3-9. Responsibilities of the Participating Countries 9-14 AFRICAN UNION GUIDELINES FOR COUNTRIES TO PREPARE FOR AND TO PARTICIPATE IN THE AFRICAN PEER REVIEW MECHANISM (APRM) Table of Contents I Introduction 1 II Core Guiding Principles 2-3 III The APR Processes

More information

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection Technical Assistance Report Project Number: 47042-001 Policy and Advisory Technical Assistance (PATA) October 2013 People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

More information

Information note. Revitalization of the Palestinian Fund for Employment and Social Protection

Information note. Revitalization of the Palestinian Fund for Employment and Social Protection INTERNATIONAL LABOUR ORGANIZATION REGIONAL OFFICE FOR ARAB STATES Information note Revitalization of the Palestinian Fund for Employment and Social Protection Implementing Partners: Ministry of Labour,

More information

Document of The World Bank USE ONLY

Document of The World Bank USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION REPORT REPUBLIC

More information

Evaluation Study. Midterm Review Process. Operations Evaluation Department

Evaluation Study. Midterm Review Process. Operations Evaluation Department Evaluation Study Reference Number: SES:REG 2008-78 Special Evaluation Study Update December 2008 Midterm Review Process Operations Evaluation Department ABBREVIATIONS ADB Asian Development Bank BTOR back-to-office

More information

3.08. OntarioBuys Program. Chapter 3 Section. Background. Ministry of Finance

3.08. OntarioBuys Program. Chapter 3 Section. Background. Ministry of Finance Chapter 3 Section 3.08 Ministry of Finance OntarioBuys Program Chapter 3 VFM Section 3.08 Background OntarioBuys is a government initiative launched in 2004 to achieve savings in the procurement of goods

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The PPTA will review and assess the performance of the secondary education subsector in Viet Nam and identify the challenges, which

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GOVERNMENT S CENTRAL PUBLIC ADMINISTRATION REFORM (CPAR) PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GOVERNMENT S CENTRAL PUBLIC ADMINISTRATION REFORM (CPAR) PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A Project No: 105602 PROPOSED PROJECT

More information

Liberia Reconstruction Trust Fund Implementation Manual

Liberia Reconstruction Trust Fund Implementation Manual Liberia Reconstruction Trust Fund Implementation Manual Updated November 2009 2011-02-28 LRTF Implementation Manual 1 I. Background... 3 II. Coverage... 3 III. General Principles... 4 IV. Project Development

More information

EUROPEAN UNION. Brussels, 22 November 2013 (OR. en) 2011/0384 (COD) PE-CONS 68/13

EUROPEAN UNION. Brussels, 22 November 2013 (OR. en) 2011/0384 (COD) PE-CONS 68/13 EUROPEAN UNION THE EUROPEAN PARLIAMT THE COUNCIL Brussels, 22 November 2013 (OR. en) 2011/0384 (COD) PE-CONS 68/13 RECH 370 COMPET 589 ATO 88 IND 219 MI 667 EDUC 309 TELECOM 210 ER 370 V 739 REGIO 163

More information

US$M): Sector Board : FPD Cofinancing (US$M US$M): (US$M US$M):

US$M): Sector Board : FPD Cofinancing (US$M US$M): (US$M US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR13644 1. Project Data: Date Posted : 07/14/2011 Public Disclosure Authorized Public Disclosure Authorized Public

More information

Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme Project Fiche for Programme Support

Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme Project Fiche for Programme Support Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme 2003 2006 2005 Project Fiche for Programme Support 1. Basic Information 1.1 CRIS Number: BG 2005/017-455.01;04 1.2 1.2 Title:

More information

Philippines: Mindanao Basic Urban Services Sector Project

Philippines: Mindanao Basic Urban Services Sector Project Validation Report Reference Number: PCV: PHI 2011-25 Project Number: 30551 Loan Number: 1843 September 2011 Philippines: Mindanao Basic Urban Services Sector Project Independent Evaluation Department ABBREVIATIONS

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,300, Original Commitment 30,400,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Jun ,300, Original Commitment 30,400, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020110 Public Disclosure Authorized Project ID P107311 Country Mozambique Project Name MZ-Nat'l Dec

More information

FINANCIAL MANAGEMENT ASSESSMENT

FINANCIAL MANAGEMENT ASSESSMENT Greater Malé Environmental Improvement and Waste Management Project (RRP MLD 51077) EXECUTIVE SUMMARY FINANCIAL MANAGEMENT ASSESSMENT 1. The financial management assessment (FMA) was conducted for the

More information

1. Introduction. Food Security and Environment Protection, Economic Cooperation and Social Development Peace and Security and Humanitarian Affairs

1. Introduction. Food Security and Environment Protection, Economic Cooperation and Social Development Peace and Security and Humanitarian Affairs TERMS OF REFERENCE FOR CONSULTANCY TO UNDERTAKE REGIONAL TRAINING NEEDS ASESSMENT ON REGIONAL TRADE AND INTEGRATION ISSUES AS SUPPORT TO CAPACITY BUILDING IN TRADE NEGOTIATION SKILLS. 1. Introduction The

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No. PID7125 Project Name Argentina-Special Structural Adjustment... Loan (SSAL)

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

The World Bank Mauritania Public Sector Governance Project (P146804)

The World Bank Mauritania Public Sector Governance Project (P146804) Public Disclosure Authorized AFRICA Mauritania Governance Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 27-Feb-2018 ISR31581 Implementing Agencies: Ministry of Economy

More information

IEG. ICR Review Independent Evaluation Group. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

IEG. ICR Review Independent Evaluation Group. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number: ICRR14822 1. Project Data: Date Posted: 09/29/2015 Public Disclosure Authorized Public Disclosure Authorized Public

More information

The World Bank Social Assistance System Strengthening Project (P123960)

The World Bank Social Assistance System Strengthening Project (P123960) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF SOCIAL ASSISTANCE SYSTEM STRENGTHENING PROJECT APPROVED ON JANUARY 22,

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF GEOTHERMAL POWER GENERATION DEVELOPMENT PROJECT GEF TF IND APPROVED ON MAY 29, 2008 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Project Name Comoros-Health Project... (Previously Second Human Resources Project)

Project Name Comoros-Health Project... (Previously Second Human Resources Project) Report No. PID5951 Project Name Comoros-Health Project... (Previously Second Human Resources Project) Region Sector Project ID Borrower Implementing Agency Africa Basic Health KMPE52887 Government of Comoros

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

STANDARD PROJECT FICHE

STANDARD PROJECT FICHE STANDARD PROJECT FICHE 1. Basic Information 1.1 CRIS Number : 2004-016-919.04 1.2 Title: Preparation for Extended Decentralized Implementation System (EDIS) in the management of pre-accession funds in

More information

Maldives: Developing the Revenue Administration Management Information System

Maldives: Developing the Revenue Administration Management Information System Completion Report Project Number: 44414-012 Technical Assistance Number: 7946 July 2015 Maldives: Developing the Revenue Administration Management Information System This document is being disclosed to

More information

THE INTERNATIONAL MONETARY FUND AND INTERNATIONAL DEVELOPMENT ASSOCIATION NIGER

THE INTERNATIONAL MONETARY FUND AND INTERNATIONAL DEVELOPMENT ASSOCIATION NIGER THE INTERNATIONAL MONETARY FUND AND INTERNATIONAL DEVELOPMENT ASSOCIATION NIGER Poverty Reduction Strategy Paper Progress Report Joint Staff Advisory Note Prepared by the Staffs of the International Monetary

More information

Implementation Status & Results Yemen, Republic of Yemen Accountability Enhancement Project (P148288)

Implementation Status & Results Yemen, Republic of Yemen Accountability Enhancement Project (P148288) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Yemen, Republic of Yemen Accountability Enhancement Project (P148288) Operation Name: Yemen Accountability Enhancement

More information

AUDIT UNDP COUNTRY OFFICE BANGLADESH. Report No Issue Date: 28 May 2015

AUDIT UNDP COUNTRY OFFICE BANGLADESH. Report No Issue Date: 28 May 2015 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP COUNTRY OFFICE IN BANGLADESH Report No. 1429 Issue Date: 28 May 2015 Table of Contents Executive Summary i I. About the Office 1 II. Good practice 1 III.

More information

ANNEX: IPA 2010 NATIONAL PROGRAMME PART II - BOSNIA AND HERZEGOVINA. at the latest by 31 December years from the final date for contracting.

ANNEX: IPA 2010 NATIONAL PROGRAMME PART II - BOSNIA AND HERZEGOVINA. at the latest by 31 December years from the final date for contracting. EN EN EN ANNEX: IPA 2010 NATIONAL PROGRAMME PART II - BOSNIA AND HERZEGOVINA 1. IDENTIFICATION Beneficiary Bosnia and Herzegovina CRIS number 2010 / 022-674 Year 2010 Cost EUR 6 000 000 Implementing Authority

More information

International Monetary Fund Washington, D.C.

International Monetary Fund Washington, D.C. 2010 International Monetary Fund May 2010 IMF Country Report No. 10/138 November 2009 January 29, 2001 January 29, 2001 January 29, 2001 January 29, 2001 Maldives: Action Plan for PFM Reforms Based on

More information

Country Practice Area(Lead) Additional Financing

Country Practice Area(Lead) Additional Financing Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021281 Public Disclosure Authorized Public Disclosure Authorized Project ID P149884 Project Name CF-

More information

THE DEVELOPMENT OF CHINA S ESCO INDUSTRY,

THE DEVELOPMENT OF CHINA S ESCO INDUSTRY, THE DEVELOPMENT OF CHINA S ESCO INDUSTRY, 2004-2007 July 28, 2008 THE DEVELOPMENT OF CHINA S ESCO INDUSTRY, 2004-2007 July 28, 2008 China s ESCO 1 industry has grown at an astonishingly fast pace during

More information

NINETY-FOURTH MEETING WASHINGTON, D.C. OCTOBER

NINETY-FOURTH MEETING WASHINGTON, D.C. OCTOBER DEVELOPMENT COMMITTEE (Joint Ministerial Committee of the Boards of Governors of the Bank and the Fund on the Transfer of Real Resources to Developing Countries) NINETY-FOURTH MEETING WASHINGTON, D.C.

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 18-Nov-2016 ISR25624 Implementing Agencies: National Bank

More information