Cost Avoidance 1: M&V Fundamentals Steve Heinz, PE, CEM, CMVP

Size: px
Start display at page:

Download "Cost Avoidance 1: M&V Fundamentals Steve Heinz, PE, CEM, CMVP"

Transcription

1 Cost Avoidance 1: M&V Fundamentals Steve Heinz, PE, CEM, CMVP Founder & CEO EnergyCAP, Inc. AEE International Energy Engineer of the Year (2013)

2 Webinar #1 in a series of four: Session #1: M&V Fundamentals Session #2: Calendarization & Normalization Session #3: Basics of EnergyCAP Cost Avoidance Session #4: Cost Avoidance Reports

3 What is M&V and why is it important? M&V is Measurement & Verification of energy and cost savings resulting from an energy savings initiative.

4 It s important! M&V is one of the six foundational pillars of energy management: Manufacturer Contractor (Installer) Designer (Engineer/specifier) Building owner (Savings beneficiary) Financer (Owner or third party) M&V

5 Manufacturer Financer (Owner or third party) M&V ties it all together! Contractor (Installer) Building Owner (Savings beneficiary) Designer (Engineer/specifier)

6 Quiz In 2014 we spent $3M on electric bills. We hired an Energy Manager on 1/1/2015 who implemented a comprehensive energy management program. In 2015 we spent $4M. We should: A. Fire our Energy Manager B. Praise our Energy Manager C. We need more information before making a decision

7 In 2014 we spent $3M on electric bills. We hired an Energy Manager on 1/1/2015 who implemented a comprehensive energy management program. In 2015 we spent $4M. But we also added 75,000 sq ft, increased occupant count by 7%, increased weekly operating schedule by 9% and absorbed a 5% electric price increase. Oh, and we had a record-setting hot summer. We should: A. Fire our Energy Manager B. Praise our Energy Manager C. We need more information before making a decision

8 In 2014 we spent $3M on electric bills. We hired an Energy Manager on 1/1/2015 who implemented a comprehensive energy management program. In 2015 we spent $4M. But we also added 75,000 sq ft, increased number of occupants by 7%, increased operating hours by 9% and absorbed a 5% electric price increase. Oh, and we had a record-setting hot summer. Based on the 2014 baseline, our M&V software calculated that without our energy management program we would have spent $4.8M in It looks like we avoided a cost of $800,000 in We should: B. Praise our Energy Manager

9 This illustrates a key concept: Measurement and verification of energy savings is necessary because you can t simply compare year-toyear out of pocket expenditures. You have to compare what you did spend with how much you would have spent in the absence of energy efficiency, in other words how much you avoided spending.

10 IPMVP The U.S. Department of Energy and other impartial agencies funded the development of the IPMVP (The International Performance Measurement and Verification Protocol) beginning in the mid-1990 s.

11 IPMVP (cont d) Today it is managed by an international nonprofit agency called The Efficiency Valuation Organization. The Federal Government uses a version of it to value the savings for all Federal energy projects.

12 IPMVP Options for M&V A. Retrofit isolation. Measure and estimate parameters. ( Key Parameter Measurement ) Example: Lighting retrofit B. Retrofit isolation. Submeter actual energy use. ( All Parameter Measurement ) Example: Chiller replacement

13 IPMVP Options for M&V (con t) C. Compare before/after utility bills. ( Whole Facility ) Example: Behavior-based program D. Comprehensive computer modeling. ( Calibrated Simulation ) Example: HVAC controls retrofit

14 EnergyCAP uses only Option C IPMVP Option C Baseline cost: $1,000 Current cost: $1,200 KWH: 10,000 ($0.10/kWh) KWH: 8,000 ($0.15/kWh) BATCC cost: $1,500 (10,000 kwh x $0.15/kWh) (Baseline Adjusted to Current Conditions) Cost Avoidance=BATCC Cost Current Cost Cost avoidance: $1,500 - $1,200 = $300

15 Adjust the baseline to current conditions Degree days imported from AccuWeather (see Energy unit price Floor area Changes in length of billing period Occupants, hours, production New equipment

16 WARNING! Cost avoidance calculations are seldom as simple as plug and play. Adjusting the baseline to current conditions for significant changes in occupancy and equipment requires high skill level engineering analysis plus accurate details about what changed and when.

17 Savings: Adjusted baseline minus today s actual bill

18 Savings: Adjusted baseline minus today s actual bill

19 Savings: Adjusted baseline minus today s actual bill

20 Limitations of Option C M&V When you have implemented several projects, it s difficult to discern the results of each individually. The further back the base year, the less reliable the calculations due to many changes in occupancy, equipment, etc. When peak demand charges are a major cost driver, there are valuation complexities. Non-standard baseline adjustments require engineering analysis, high skill level and substantial time commitment.

21 Savings Reports can be: 1. Ongoing. Calculate and report savings periodically throughout the life of the contract or program. EnergyCAP approach. 2. One-Time Stipulated. All parties agree to a one-time calculation; no further reporting is needed. This approach is favored by most ESCOs for most retrofit projects.

22 All calculation formulas are documented and flow charted

23 EnergyCAP s Cost Avoidance M&V module: Adheres to the calculation requirements of IPMVP Has been used with essentially the same format & calculations since 1985 Cost avoidance has been calculated for tens of thousands of buildings (over 20,000 buildings currently in EnergyCAP Online have active cost avoidance reporting)

24 ISO (Measurement and Verification of Energy Performance) says: The purpose of M&V is to provide confidence to interested parties that reported results are credible... [including] appropriate accuracy and management of uncertainty

25 But I don t want appropriate accuracy or any uncertainty. I want a 100% accurate, 100% certain cost avoidance report.

26 Reports will always have an element of uncertainty and less than 100% accuracy because you can t measure the absence of energy usage. We must estimate it using a consistently-applied recognized methodology.

27 We must accept a certain level of accuracy and uncertainty.

28 Resources: Become a member of EVO ( Download IPMVP from EVO CMVP Certified Measurement & Verification Professional ( M&V Software: EnergyCAP w/cost avoidance

29 Q&A

MEASUREMENT AND VERIFICATION AND THE IPMVP

MEASUREMENT AND VERIFICATION AND THE IPMVP MEASUREMENT AND VERIFICATION AND THE IPMVP EPC TOOLKIT FOR HIGHER EDUCATION APRIL 2009 INDEX IPMVP: THE PRINCIPLES IPMVP: THE DIFFERENT OPTIONS THE COSTS OF M&V 3 4 7 With permission from the author, this

More information

NEW DIRECTIONS IN MEASUREMENT AND VERIFICATION FOR PERFORMANCE CONTRACTS

NEW DIRECTIONS IN MEASUREMENT AND VERIFICATION FOR PERFORMANCE CONTRACTS NEW DIRECTIONS IN MEASUREMENT AND VERIFICATION FOR PERFORMANCE CONTRACTS John M. Avina, CEM (President, Abraxas Energy Consulting) John A. Shonder (Senior Mechanical Engineer, Oak Ridge National Laboratory)

More information

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document.

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document. ESA / IGA Schedules Project Documents include the following Schedules which are incorporated herein and made a part of the IGA and ESA when approved by the ISSUER and ESCO: Schedule A Schedule B Schedule

More information

Nordonia Hills City Schools REGULAR MEETING AGENDA

Nordonia Hills City Schools REGULAR MEETING AGENDA Nordonia Hills City Schools REGULAR MEETING AGENDA July 20, 2015 BOARD OF EDUCATION MEMBERS Nick Berchtold Chad Lahrmer (330)468 1286 Doug Masteller (330)468 1036 Tammy Strong (330)908 1202 Jim Szabo (330)467

More information

Brian J. McCarter. Profiting from the Connecticut Commercial PACE Financing Opportunity. Moderated by:

Brian J. McCarter. Profiting from the Connecticut Commercial PACE Financing Opportunity. Moderated by: Profiting from the Connecticut Commercial PACE Financing Opportunity February 21, 2013 Moderated by: Brian J. McCarter Chairman & CEO Sustainable Real Estate Solutions, Inc. (SRS) Sponsored by: Speaker

More information

GUARANTEED LONG-TERM SAVINGS PERSISTENCE AN OWNER S PERSPECTIVE

GUARANTEED LONG-TERM SAVINGS PERSISTENCE AN OWNER S PERSPECTIVE GUARANTEED LONG-TERM SAVINGS PERSISTENCE AN OWNER S PERSPECTIVE Tarek Bou-Saada, CEM Energy Manager Texas Health and Human Services Commission Charles Culp, Ph.D., P.E. Assoc. Professor, Dept of Architecture

More information

Toronto Hydro Electric System Limited

Toronto Hydro Electric System Limited Toronto Hydro Electric System Limited Draft Evaluation, Measurement and Verification Plan: Commercial, Institutional and Small Industrial Monitoring & Targeting ( M&T ) Submitted to: Ontario Energy Board

More information

Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016

Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016 Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016 Delaware Sustainable Energy Utility 500 West Loockerman Street, Suite 400 Dover, DE 19904 302-883-3048 1 Public

More information

UNIDO EnMS Expert Training Module 1 Day 3. Trainers Location

UNIDO EnMS Expert Training Module 1 Day 3. Trainers Location UNIDO EnMS Expert Training Module 1 Day 3 Trainers Location 1 Topic Duration (hours) Exercise (mins) Break duration Start Time End Time DAY 3 Calculating energy savings 15 30 08:30 09:15 Financial Analysis

More information

Engineer/ESCO Application Guide (Last updated )

Engineer/ESCO Application Guide (Last updated ) Engineer/ESCO Application Guide (Last updated 11-14-2011) Prepared By: Abundant Power Solutions, LLC 704-271-9886 Toll Free: 888-271-9378 www.abundantpower.com www.alabamasaves.com info@alabamasaves.com

More information

Recipe for Developing a Winning M&V Formula in Indian ESCO Projects: Balancing Rigor and Accuracy with Cost-Effectiveness and Practicality

Recipe for Developing a Winning M&V Formula in Indian ESCO Projects: Balancing Rigor and Accuracy with Cost-Effectiveness and Practicality Recipe for Developing a Winning M&V Formula in Indian ESCO Projects: Balancing Rigor and Accuracy with Cost-Effectiveness and Practicality Dr. Satish Kumar, USAID ECO-III Project Asia ESCO Conference 2010

More information

Briefing to the Dallas City Council s Budget, Finance and Audit Committee June 18, 2012

Briefing to the Dallas City Council s Budget, Finance and Audit Committee June 18, 2012 Briefing to the Dallas City Council s Budget, Finance and Audit Committee June 18, 2012 Energy Conservation is largely based on behavioral practices to use [energy] in a more efficient manner it is essential

More information

ESPC and UESC: Energy Projects without Appropriations

ESPC and UESC: Energy Projects without Appropriations ESPC and UESC: Energy Projects without Appropriations Phil Coleman Lawrence Berkeley National Lab August 4, 2008 Outline What are these things, anyway? Why can t I just do the projects from appropriations?

More information

EFFECTIVE IMPLEMENTATION OF IPMVP OPTION C- WHOLE BUILDING MEASUREMENT MEASUREMENT AND VERIFICATION PLANS

EFFECTIVE IMPLEMENTATION OF IPMVP OPTION C- WHOLE BUILDING MEASUREMENT MEASUREMENT AND VERIFICATION PLANS EFFECTIVE IMPLEMENTATION OF IPMVP OPTION C- WHOLE BUILDING MEASUREMENT MEASUREMENT AND VERIFICATION PLANS PREPARED BY TAC-TOUR ANDOVER CONTROLS TODD PORTER, KLIP WEAVER, KEVIN VAUGHN AUGUST 12, 2005 1

More information

2018 New Construction Rebate Application

2018 New Construction Rebate Application BUSINESS 2018 New Construction Rebate Application Save money on qualified construction projects Read about rebates for your home and business at mid.org/rebates REV01.2018 PURPOSE The MPower Business:

More information

DTE Energy Multifamily Program

DTE Energy Multifamily Program DTE Energy Multifamily Program 2016 Policies and Procedures Manual The DTE Energy Multifamily Program provides incentives for Multifamily property owners who upgrade their facilities with energy efficient

More information

SCHEDULE E M&V PROCEDURES FOR THE ENERGY PERFORMANCE PROGRAM FOR MULTI- SITE CUSTOMERS

SCHEDULE E M&V PROCEDURES FOR THE ENERGY PERFORMANCE PROGRAM FOR MULTI- SITE CUSTOMERS SCHEDULE E M&V PROCEDURES FOR THE ENERGY PERFORMANCE PROGRAM FOR MULTI- SITE CUSTOMERS Table of Contents 1.0 EXECUTIVE SUMMARY... 4 1.1.1 Eligibility... 4 1.1.2 Project Boundary... 4 1.1.3 Raw Data Requirements...

More information

BUSINESS INCENTIVE PROGRAM APPLICATION

BUSINESS INCENTIVE PROGRAM APPLICATION BUSINESS INCENTIVE PROGRAM APPLICATION PART A APPLICANT INFORMATION (Financial incentive payment will be made to Applicant ONLY.) 1. Applicant: Legal Name of Business (the "Applicant"): Address: City:

More information

Evaluation, Measurement & Verification Framework for Washington

Evaluation, Measurement & Verification Framework for Washington Evaluation, Measurement & Verification Framework for Washington Issued September 8, 2011 SOURCE DOCUMENTS Information used in the development of this document came from PacifiCorp practices and experience,

More information

Energy Services Coalition (ESC) Nevada Chapter. Local Public Sector ESPC Training. August 10, 2017

Energy Services Coalition (ESC) Nevada Chapter. Local Public Sector ESPC Training. August 10, 2017 Energy Services Coalition (ESC) Nevada Chapter Local Public Sector ESPC Training August 10, 2017 1 Why do ESPC Projects Generate Happy Customers? Repurposes existing expenditures and invests in your own

More information

Appendix B. The EnergyRM EE PPA

Appendix B. The EnergyRM EE PPA Appendix B The EnergyRM EE PPA Description One specific variant of an EE PPA that is being discussed in Oregon and the Northwest is a model proposed by EnergyRM and Equilibrium Capital, which will be referred

More information

REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSAL. For. Energy Performance Engineering/Consulting Services. For The. CREC Magnet Schools

REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSAL. For. Energy Performance Engineering/Consulting Services. For The. CREC Magnet Schools REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSAL For Energy Performance Engineering/Consulting Services For The CREC Magnet Schools CREC RFP #2017-0815 Issue Date: SEP 22, 2017 Written Responses Due: OCT

More information

IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO

IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO12100940 On January 17, 2012, L. 2007, c. 340 (codified at N.J.S.A. 48:3-60.3) ( Act ), was

More information

Province-Wide Pay-For-Performance (P4P) Draft Program Documents Webinar: IESO response to input received

Province-Wide Pay-For-Performance (P4P) Draft Program Documents Webinar: IESO response to input received Province-Wide Pay-For-Performance (P4P) Draft Program Documents Webinar: IESO response to input received The IESO is designing a new province-wide pay-for-performance program for Multi Distributor Customers

More information

DTE Energy s Energy Efficiency Program for Business Policies and Procedures Manual

DTE Energy s Energy Efficiency Program for Business Policies and Procedures Manual DTE Energy s Energy Efficiency Program for Business 2015 Policies and Procedures Manual DTE Energy s Energy Efficiency Program for Business provides incentives for business customers who upgrade their

More information

IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO

IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO IN THE MATTER OF THE IMPLEMENTATION OF A2528/S2344 (N.J.S.A. 48:3-60.3) AND THE SBC CREDIT PROGRAM DOCKET NO. EO12100940 On January 17, 2012, L. 2007, c. 340 (codified at N.J.S.A. 48:3-60.3) ( Act ), was

More information

Flexibility Options for Energy Performance Contracts (EPC)

Flexibility Options for Energy Performance Contracts (EPC) Flexibility Options for Energy Performance Contracts (EPC) Horizon 2020 Grant Agreement No. 696040 Deliverable D2.6 This project has received funding from the European Union s Horizon 2020 research and

More information

Custom Commercial Standard Offer Program (CCSOP) 2018 Program Manual

Custom Commercial Standard Offer Program (CCSOP) 2018 Program Manual Custom Commercial Standard Offer Program (CCSOP) 2018 Program Manual Date: 12/15/2017 CONTENTS 1 Introduction... 3 2 Program Overview... 3 3 Custom Commercial Standard Offer... 3 3.1 Customer Eligibility...

More information

Third-Year Program Results for a Utility Recommissioning Program

Third-Year Program Results for a Utility Recommissioning Program Third-Year Program Results for a Utility Recommissioning Program Ellen Franconi, PhD, Martin Selch, Jim Bradford PhD, PE Nexant, Inc. Bill Gruen Xcel Energy Synopsis Xcel Energy offers the Recommissioning

More information

Verification of Savings Project Update to CCC

Verification of Savings Project Update to CCC Verification of Savings Project Update to CCC April 21, 2007 Project Team David Jump, QuEST, project lead Ken Gillespie, PG&E Hannah Friedman, PECI, CCC Technical Manager Kirstin Pinit, PECI, CCC Project

More information

Double Ratio Estimation: Friend or Foe?

Double Ratio Estimation: Friend or Foe? Double Ratio Estimation: Friend or Foe? Jenna Bagnall-Reilly, West Hill Energy and Computing, Brattleboro, VT Kathryn Parlin, West Hill Energy and Computing, Brattleboro, VT ABSTRACT Double ratio estimation

More information

Energy Efficiency Case Study: Performance Contracting

Energy Efficiency Case Study: Performance Contracting Energy Efficiency Case Study: Performance Contracting 3N 111(d) Meeting December 4, 2014 Ashley Patterson Director, Government Relations & Public Policy Ameresco Chris Hessler Partner AJW, Inc. ESCO Working

More information

Delivering Efficiency as a Service: The Metrus ESA

Delivering Efficiency as a Service: The Metrus ESA Delivering Efficiency as a Service: The Metrus ESA May 22, 2018 Overview Metrus develops, finances, owns, and operates large-scale efficiency projects for Fortune 500 companies and major industrial customers.

More information

Commercial and Industrial Energy Efficiency Program Manual

Commercial and Industrial Energy Efficiency Program Manual Commercial and Industrial Energy Efficiency Program Manual - 2018 Table of Contents Commercial & Industrial Energy Efficiency Program Manual Section 1: Introduction... 3 1.1 Program Overview... 3 Section

More information

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M U N I V E R S I T Y O F N O R T H A L A B A M A R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M R F P 2 0 1 7-23

More information

Greenhouse Gas Reporting and Accruals. Steve Heinz, PE, CEM, CMVP Founder & CEO EnergyCAP, Inc.

Greenhouse Gas Reporting and Accruals. Steve Heinz, PE, CEM, CMVP Founder & CEO EnergyCAP, Inc. Greenhouse Gas Reporting and Accruals Steve Heinz, PE, CEM, CMVP Founder & CEO EnergyCAP, Inc. Greenhouse Gas Fundamentals Global Energy Flows W m -2 The Greenhouse Effect Infrared energy flows marked

More information

STANDARD AND CUSTOM INCENTIVES PRE-APPROVAL AND FINAL APPLICATION FORM

STANDARD AND CUSTOM INCENTIVES PRE-APPROVAL AND FINAL APPLICATION FORM PRE-APPROVAL AND FINAL APPLICATION FORM The ComEd Energy Efficiency Program offers incentives to help facilities save money by improving the efficiency of their equipment. Receive standard cash incentives

More information

Draft Small Customer Aggregation Program Rules

Draft Small Customer Aggregation Program Rules Draft Small Customer Aggregation Program Rules 1. Aggregations must be at least 2.0 MW for DADRP, 1.0 MW for RTDRP, 100 kw for SCR and 100 kw for EDRP. In each case the requirement is zone-specific. The

More information

Dollars to $ense Energy Efficiency Financing Mini-Workshop

Dollars to $ense Energy Efficiency Financing Mini-Workshop Dollars to $ense Energy Efficiency Financing Mini-Workshop February 11, 2014 The International Centre Workshop Learning Objectives To increase awareness and skill in obtaining financing for energy efficiency

More information

Dollars to $ense. Energy Efficiency Financing Mini-Workshop. February 11, 2014 The International Centre

Dollars to $ense. Energy Efficiency Financing Mini-Workshop. February 11, 2014 The International Centre Dollars to $ense Energy Efficiency Financing Mini-Workshop February 11, 2014 The International Centre Workshop Learning Objectives To increase awareness and skill in obtaining financing for energy efficiency

More information

The Transformation of Commercial &Industrial Energy Efficiency Programs: A Whole-Building Approach to Energy Savings

The Transformation of Commercial &Industrial Energy Efficiency Programs: A Whole-Building Approach to Energy Savings The Transformation of Commercial &Industrial Energy Efficiency Programs: A Whole-Building Approach to Energy Savings Valentina Rozanova and Tom Rooney, TRC Companies, Inc. Jack Ruderman, New Hampshire

More information

Existing Building Policy Proposal. Cost Evaluation

Existing Building Policy Proposal. Cost Evaluation Existing Building Policy Proposal Cost Evaluation Apartment Roof Replacement 55, square feet, 5 floors, roof is 11, sq ft. Green Roof Coverage requirement: 3% or 3,3 sq ft. Cool Roof + small amount of

More information

NYISO s Compliance Filing to Order 745: Demand Response. Wholesale Energy Markets

NYISO s Compliance Filing to Order 745: Demand Response. Wholesale Energy Markets NYISO s Compliance Filing to Order 745: Demand Response Compensation in Organized Wholesale Energy Markets (Docket RM10-17-000) Donna Pratt NYISO Manager, Demand Response Products Market Issues Working

More information

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ #

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ # Name: Lackawanna County Address: 200 Adams Ave Address: Scranton PA 18503 Introduction REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ # 345-12-1 Lackawanna County is requesting Qualifications

More information

Scaling-up energy efficiency investment in buildings. Part of the Investor Confidence Project Europe Presentation for UK stakeholders 17 June, 2015

Scaling-up energy efficiency investment in buildings. Part of the Investor Confidence Project Europe Presentation for UK stakeholders 17 June, 2015 Scaling-up energy efficiency investment in buildings Part of the Investor Confidence Project Europe Presentation for UK stakeholders 17 June, 2015 Agenda Introduction UK market need and current status

More information

PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY

PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY VERSION 2.0 6 October 2016 TABLE OF CONTENTS OVERVIEW... 3 STATUTORY AND PROGRAMMATIC REQUIREMENTS... 4 PACE PROJECT PROCESS... 6 HOW PACE PROJECTS ARE ASSESSED...

More information

Accounting For Decision Making

Accounting For Decision Making Accounting For Decision Making Topic 7 Costing products and services Goals for this session Explain why managers need estimates of the costs of both responsibility centres and products; Describe the basic

More information

Historical Performance of the U.S. ESCO Industry: Results from the NAESCO Project Database

Historical Performance of the U.S. ESCO Industry: Results from the NAESCO Project Database LBNL-46070 Historical Performance of the U.S. ESCO Industry: Results from the NAESCO Project Database C.A. Goldman, P. Juergens, M. Fowlie, J. Osborn & K. Kawamoto,LBNL, Terry Singer, NAESCO Environmental

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Industry Drivers of Commissioning: Programs & Legislation

Industry Drivers of Commissioning: Programs & Legislation Industry Drivers of Commissioning: Programs & Legislation Michael C. English, PE, CCP, LEED AP Senior Partner, Horizon Engineering Associates, LLP Randy Gunn Managing Director, Navigant George Malek, PE,

More information

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE FEBRUARY 8, 2019 INVESTMENT GRADE AUDIT SUMMARY REPORT SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE in support of Act 77/39 Guaranteed Energy Savings Agreement (GESA) Reynolds Energy Services, Inc. 3300 North

More information

Phase 1: Written Qualifications. Phase 2: Client Reference Checks. Phase 3: Evaluation: Oral Interviews

Phase 1: Written Qualifications. Phase 2: Client Reference Checks. Phase 3: Evaluation: Oral Interviews APPENDIX C-1: SAMPLE EVALUATION FORMS Phase 1: Written Qualifications Phase 2: Client Reference Checks Phase 3: Evaluation: Oral Interviews Appendix C-1: Page 1 Insert Name of Institution Energy Performance

More information

Long Term Financial Planning Process Update. 24 Nov 2014

Long Term Financial Planning Process Update. 24 Nov 2014 Long Term Financial Planning Process Update 24 Nov 2014 1 Direction Requested Confirm scope of model and understanding of scenarios being utilized in Long Term Financial Planning (LTFP). 2 Intent & Scope

More information

Application Terms & Conditions and Final Payment Agreement

Application Terms & Conditions and Final Payment Agreement Prescriptive, Self-Direct Custom Program & Self-Direct Application Terms & Conditions and Final Payment Agreement Version: January 1, 2015 January 2017 TERMS AND CONDITIONS AEP Ohio offers Efficient Products

More information

The Cost of Medicare During Retirement

The Cost of Medicare During Retirement Private Wealth Management Products & Services The Cost of Medicare During Retirement There are two primary influences on the cost of Medicare for an individual. The first of these is when the retiree applies

More information

SCOPE OF WORK PROJECT NO. A STATE OF NEW JERSEY Honorable Philip D. Murphy, Governor Honorable Sheila Y. Oliver, Lt.

SCOPE OF WORK PROJECT NO. A STATE OF NEW JERSEY Honorable Philip D. Murphy, Governor Honorable Sheila Y. Oliver, Lt. SCOPE OF WORK 3 rd Party Measurement and Verification Services New Jersey Department of Military and Veterans Affairs Vineland Veterans Memorial Home Vineland, Cumberland County, N.J. PROJECT NO. A1257-02

More information

InvestSmart Business Energy Upgrades

InvestSmart Business Energy Upgrades Application Instructions This application is required for participation in for Custom projects with qualifying measures not found in the Lighting or Standard Programs. Complete participation information

More information

PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA

PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor Advice Letter: 3460-E-A (U 338-E) February 17, 2017 Russell G. Worden Managing

More information

2019 Demand Management Program Application

2019 Demand Management Program Application Checklist To ensure your application is filled out correctly so that Con Edison can quickly process your request, please use the following checklist as you complete your submission. Customer and facilities

More information

New Jersey Clean Energy Collaborative. Regulatory Reporting

New Jersey Clean Energy Collaborative. Regulatory Reporting New Jersey Clean Energy Collaborative New Jersey Clean Energy Collaborative Table of Contents Overview...1 Contents and Timetables...1 Quarterly Reports...1 Annual Reports...2 Performance Reports...2 Evaluation

More information

Evaluation, Measurement, & Verification Principles and Vermont Examples

Evaluation, Measurement, & Verification Principles and Vermont Examples Evaluation, Measurement, & Verification Principles and Vermont Examples Walter Poor, Vermont Public Service Department December 4, 2014 Topics EM&V Resources Evaluation Fundamentals Definitions Why Evaluate

More information

Energy Saving Improvement Programs

Energy Saving Improvement Programs Introducing Energy Saving Improvement Programs aka: ESIP; ESCO; P.L. 2009, c. 4; A-1185A Marc Pfeiffer, Deputy Director Division of Local Government Services What ESIP is All About Retrofitting public

More information

FIVE YEAR PLAN FOR ENERGY EFFICIENCY

FIVE YEAR PLAN FOR ENERGY EFFICIENCY FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011

More information

Solvency II. Insurance and Pensions Unit, European Commission

Solvency II. Insurance and Pensions Unit, European Commission Solvency II Insurance and Pensions Unit, European Commission Introduction Solvency II Deepened integration of the EU insurance market 14 existing Directives on insurance and reinsurance supervision, insurance

More information

PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY

PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY VERSION 3.0 13 January 2018 TABLE OF CONTENTS OVERVIEW... 3 STATUTORY AND PROGRAMMATIC REQUIREMENTS... 4 PACE PROJECT PROCESS... 6 HOW PACE PROJECTS ARE ASSESSED...

More information

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS 1. INTRODUCTION Van Dyke Public Schools is requesting proposals from Energy Services Companies (ESCOs)

More information

REQUEST FOR PROPOSALS. for ENERGY-EFFICIENCY RELATED FACILITIES IMPROVEMENTS PER THE TERMS OF ACT 39 OF 2010

REQUEST FOR PROPOSALS. for ENERGY-EFFICIENCY RELATED FACILITIES IMPROVEMENTS PER THE TERMS OF ACT 39 OF 2010 REQUEST FOR PROPOSALS for ENERGY-EFFICIENCY RELATED FACILITIES IMPROVEMENTS PER THE TERMS OF ACT 39 OF 2010 THE PENNSYLVANIA GUARANTEED ENERGY SAVINGS ACT for the DELAWARE COUNTY INTERMEDIATE UNIT MORTON,

More information

Program Overview. Presented by: Tracy Phillips, CEM, CDSM, CMVP Director, CO C-PACE Program

Program Overview. Presented by: Tracy Phillips, CEM, CDSM, CMVP Director, CO C-PACE Program Program Overview Presented by: Tracy Phillips, CEM, CDSM, CMVP Director, CO C-PACE Program 1 C-PACE Session Summary C-PACE Background & Structure How C-PACE Works Benefits of C-PACE for EE/RE Industry

More information

Focus on Energy Economic Impacts

Focus on Energy Economic Impacts Focus on Energy Economic Impacts 2015-2016 January 2018 Public Service Commission of Wisconsin 610 North Whitney Way P.O. Box 7854 Madison, WI 53707-7854 This page left blank. Prepared by: Torsten Kieper,

More information

U. S. Department of Housing and Urban Development Office of Public and Indian Housing

U. S. Department of Housing and Urban Development Office of Public and Indian Housing U. S. Department of Housing and Urban Development Office of Public and Indian Housing Special Attention of: NOTICE: PIH-2011-36 (HA) Public Housing Agencies; Issued: July 8, 2011 HUD Directors of Public

More information

COVINA-VALLEY UNIFIED SCHOOL DISTRICT

COVINA-VALLEY UNIFIED SCHOOL DISTRICT COVINA-VALLEY UNIFIED SCHOOL DISTRICT REQUEST FOR PROPOSAL ENERGY PERFORMANCE CONTRACTING SERVICES RFP NO. 15-16-105 REQUEST FOR PROPOSAL SUBMITTAL DEADLINE NOVEMBER 6, 2015 AT 11:00AM SUBMIT TO: COVINA-VALLEY

More information

CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM

CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM Presentation 10/30/15 1 PROGRAM OVERVIEW 1. Background General Allocation Amounts Annual Funding Release 2. Project Types

More information

Building Optimization Analysis (BOA) Tool Training

Building Optimization Analysis (BOA) Tool Training Building Optimization Analysis (BOA) Tool Training Dave Moser, Senior Engineer, PECI Michelle Lichtenfels, Program Manager, PECI September 8 and 13, 2010 Training Objectives Use the BOA Tool to calculate

More information

Guaranteed Energy Savings Contracts: Step-By-Step Contracting Process

Guaranteed Energy Savings Contracts: Step-By-Step Contracting Process Guaranteed Energy Savings Contracts: Step-By-Step Contracting Process I. Key Terms 1 Norma R. Houston Guaranteed Energy Savings Contract (GESC) A contract for the evaluation, recommendation, or implementation

More information

Energy Savings Performance Contracting Program Process Description

Energy Savings Performance Contracting Program Process Description Energy Savings Performance Contracting Program Process Description I. Program History The Energy Savings Performance Contracting (ESPC) program was developed to provide a means to install energy conservation

More information

Underwriting Energy Efficiency Financing in the Innovative Connecticut PACE Program

Underwriting Energy Efficiency Financing in the Innovative Connecticut PACE Program Critical Issues Series Energy efficiency in the Commercial Real Estate Industry Underwriting Energy Efficiency Financing in the Innovative Connecticut PACE Program A n t h o n y J. Buonicore, P.E., BCEE,

More information

Energy Efficiency Financing for the Commercial and Institutional Building Sector

Energy Efficiency Financing for the Commercial and Institutional Building Sector Energy Efficiency Financing for the Commercial and Institutional Building Sector Dec. 5, 2013 Alex J Hill Philippe Dunsky Marina Malkova DUNSKY ENERGY CONSULTING (514) 504-9030 info@dunsky.ca OUTLINE /

More information

US Experience with Energy Savings Performance Contracts

US Experience with Energy Savings Performance Contracts US Experience with Energy Savings Performance Contracts John A. Shonder Oak Ridge National Laboratory Building Systems 2006 Conference Helsinki, Finland March 22, 2006 Background U.S. is the world s largest

More information

BPA Energy Efficiency Option 1 Custom Project Calculator Instructions

BPA Energy Efficiency Option 1 Custom Project Calculator Instructions B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Energy Efficiency Option 1 Custom Project Calculator Instructions Revised 12/3/2012 Table of Contents Purpose of Option 1 Custom Project Calculator

More information

Welcome! 4/20/2018. Industrial Hygiene Statistics- The Next Generation WELCOME

Welcome! 4/20/2018. Industrial Hygiene Statistics- The Next Generation WELCOME WELCOME + The meeting room is currently muted. Audio: Use your computer speakers, or dial 1-800- 768-2983; Access code 8460751 Mute: Your line has been muted as a courtesy to others. Q/A: There will be

More information

Basic Commercial Standard Offer Program (BCSOP) 2018 Program Manual

Basic Commercial Standard Offer Program (BCSOP) 2018 Program Manual Basic Commercial Standard Offer Program (BCSOP) 2018 Program Manual Date: 12/15/2017 CONTENTS 1 Introduction... 3 2 Program Overview... 3 3 Basic Commercial Standard Offer... 3 3.1 Customer Eligibility...

More information

CUMULATIVE IMPACT ASSESSMENT OF THE BASEL REFORM PACKAGE DATA AS OF DECEMBER 2015

CUMULATIVE IMPACT ASSESSMENT OF THE BASEL REFORM PACKAGE DATA AS OF DECEMBER 2015 CUMULATIVE IMPACT ASSESSMENT OF THE BASEL REFORM PACKAGE DATA AS OF DECEMBER 2015 Contents Introduction 3 Overview of the results 4 Annex: Methodological considerations 7 2 Introduction In 2014, the Basel

More information

ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY

ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY LBNL-55002 ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY Public and Institutional Markets for ESCO Services: Comparing Programs, Practices and Performance Nicole Hopper, Charles Goldman and Jennifer

More information

State HIE Cooperative Agreement Program Webinar

State HIE Cooperative Agreement Program Webinar State HIE Cooperative Agreement Program Webinar 10/07/09 Office of the National Coordinator Call Agenda CALL AGENDA I. Submitting the application Steve Daniels, Alexis Lynady II. Review of new FAQs developed

More information

Pay For Performance (P4P) Program Guide for Commercial & Industrial (C&I) New & Existing Buildings

Pay For Performance (P4P) Program Guide for Commercial & Industrial (C&I) New & Existing Buildings Pay For Performance (P4P) Program Guide for Commercial & Industrial (C&I) New & Existing Buildings Fiscal Year 20182019 (7/1/20172018 through 6/30/20182019) Table of Contents 1. Purpose... 5 2. General

More information

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 17-M-0178 - Petition of Orange and Rockland Utilities, Inc. for

More information

Energy Efficiency Insurance. Global & Indian scenario

Energy Efficiency Insurance. Global & Indian scenario Energy Efficiency Insurance Global & Indian scenario International Energy Efficiency Insurance Product Scenario Some international products studied were: 1. Energy Savings Insurance Implementing Agency:

More information

Load and Billing Impact Findings from California Residential Opt-in TOU Pilots

Load and Billing Impact Findings from California Residential Opt-in TOU Pilots Load and Billing Impact Findings from California Residential Opt-in TOU Pilots Stephen George, Eric Bell, Aimee Savage, Nexant, San Francisco, CA ABSTRACT Three large investor owned utilities (IOUs) launched

More information

Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities. Municipal Funding Agreement Guide.

Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities. Municipal Funding Agreement Guide. Transfer of Federal Gas Tax Revenues Under the New Deal for Cities and Communities Municipal Funding Agreement Guide January 2010 Administered by: Association of Municipalities of Ontario 200 University

More information

Classroom and Class Lab Utilization

Classroom and Class Lab Utilization Classroom and Class Lab Utilization Tom Keaton Director, Finance and Resource Planning Texas Higher Education Coordination Board Space Performance Scoring (SPS) Current Guideline Classroom Use, 38 Hours

More information

INNOVATIVE, HIGH-IMPACT ENERGY EFFICIENCY RETROFIT FINANCING OPPORTUNITIES IN THE CANADIAN COMMERCIAL BUILDING SECTOR

INNOVATIVE, HIGH-IMPACT ENERGY EFFICIENCY RETROFIT FINANCING OPPORTUNITIES IN THE CANADIAN COMMERCIAL BUILDING SECTOR INNOVATIVE, HIGH-IMPACT ENERGY EFFICIENCY RETROFIT FINANCING OPPORTUNITIES IN THE CANADIAN COMMERCIAL BUILDING SECTOR Prepared for TORONTO ATMOSPHERIC FUND (TAF) May 2014 50 Ste-Catherine St. West, suite

More information

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT Oxford Development Company, As Agent for the Southwestern Pennsylvania Corporation, a 501 (c) 3 Corporation Regional Enterprise Tower 425 Sixth

More information

Retro-Commissioning Draft Impact Evaluation Plan

Retro-Commissioning Draft Impact Evaluation Plan Prepared by SBW Consulting, Inc. PWP, Inc. For the California Public Utilities Commission December 19, 2007 TABLE OF CONTENTS EXECUTIVE SUMMARY... 5 1. PROGRAMS EVALUATED... 8 2. EVALUATOR CONTACT INFORMATION...

More information

5 YEARS. CASE STUDY with Utility Bills

5 YEARS. CASE STUDY with Utility Bills CASE STUDY with Utility Bills 5 YEARS Performance Review: The First Independent Retailer in the US to Retrofit with LED Tubes. In 2009, a third generation family business took the initiative to invest

More information

The CPI (Consumer Price Index) is used to implement rent changes based on an index such as the Consumer Price Index.

The CPI (Consumer Price Index) is used to implement rent changes based on an index such as the Consumer Price Index. Commercial Module Introduction The commercial lease contains information on five functional areas - CPI Rent Increases, CAM (Common Area Maintenance), Escalation, Overage, and Estimated charges. It is

More information

SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. ENERGY EFFICIENCY AND CUSTOMER-OWNED RESOURCES.

SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. ENERGY EFFICIENCY AND CUSTOMER-OWNED RESOURCES. 25.181. Energy Efficiency Goal. (a) (b) (c) Purpose. The purposes of this section are to ensure that: (1) electric utilities administer energy savings incentive programs in a market-neutral, nondiscriminatory

More information

HVAC-4 Deemed Measures Uncertainty Study, Year 2

HVAC-4 Deemed Measures Uncertainty Study, Year 2 ENERGY HVAC-4 Deemed Measures Uncertainty Study, Year 2 Public Webinar for California Public Utilities Commission Rachel Murray 1 2016-09-01 CPUC Webinar for HVAC-4, Yr 2 SAFER, SMARTER, GREENER Presentation

More information

ENERGY SAVING PERFORMANCE CONTRACTING MANUAL FOR MISSISSIPPI S PUBLIC AGENCIES JULY 2014

ENERGY SAVING PERFORMANCE CONTRACTING MANUAL FOR MISSISSIPPI S PUBLIC AGENCIES JULY 2014 ENERGY SAVING PERFORMANCE CONTRACTING MANUAL FOR MISSISSIPPI S PUBLIC AGENCIES JULY 2014 DISCLAIMER This manual has been prepared for the Mississippi Development Authority Energy and Natural Resources

More information

Exhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan

Exhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan Exhibit DAS-1 Tucson Electric Power Company Demand-Side Management Program Portfolio Plan 2008-2012 TABLE OF CONTENTS 1. Introduction...3 2. DSM Portfolio Performance Costs, Savings and Net Benefits...3

More information

Comprehensive Energy Management Services

Comprehensive Energy Management Services Request for Qualifications (RFQ) for: Comprehensive Energy Management Services Under the Massachusetts General Laws, Chapter 25A, Section 11I A Guaranteed Energy Savings Contract Requested by: The Merrimack

More information