ITEM 5 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing a Purchase of Four (4) New Tier IV AC
|
|
- Charity Welch
- 5 years ago
- Views:
Transcription
1 ITEM 5 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing a Purchase of Four (4) New Tier IV AC Traction Passenger Locomotives with Siemens Industry, Inc. for an Amount Not- To-Exceed $30,896,568 with Options to Purchase up to Four (4) Additional Units During the Five-Year Contract Term, and Authorizing and Directing the Executive Director to Execute the Agreement
2 REQUEST FOR PROPOSAL On February 14, 2018, SJRRC released a Request for Proposals (RFP) for the solicitation of New Tier IV AC Traction Passenger Locomotives with proposals due on March 21, As part of the solicitation process, proposers shall meet the delivery date no later than December 15, As a result of the solicitation, the Rail Commission received proposals from the following three manufacturers: Motive Power, Inc. Boise, Idaho Progress Rail Locomotive, Inc. Muncie, Indiana Siemens Industry, Inc. Sacramento, California
3 REQUEST FOR PROPOSAL All three manufacturers are FTA approved Transit Vehicle Manufacturers. The proposals were evaluated by a panel consisting of SJRRC s Director of Operations, SJRRC s Director of Capital Projects and Herzog s General Manager. As a result of the evaluations, Siemens Industry, Inc. was deemed the most responsive and responsible proposal. The contract is to be awarded for an amount not-to-exceed $30,896,568 for the initial 4 units with the base unit price of $7,269,445 per locomotive plus delivery, training, operations & maintenance manuals costs and $1,500,00 for special tooling & capital spares. No. Quantity Item Unit Price Extended Price 1 4 New Tier IV AC Traction Passenger Locomotives $7,269,445 $29,077, Delivery Price to Stockton $22,900 $91,600 3 Lump Sum Training N/A $116,189 4 Lump Sum Operations & Maintenance Manuals N/A $110,999 5 Lump Sum Special Tooling & Capital Spares N/A $1,500,000 Total Base Contract $30,896,568
4 PROTEST UPDATE The contract will have the option to purchase for up to four (4) additional units during the five-year contract term. On March 30, 2018, the Rail Commission received a protest from Motive Power, Inc. with the Staff s Recommendation of awarding the contract to Siemens Industry, Inc. The protest was received within forty-eight (48) hours of the SJRRC staff s recommendation as stated in the RFP. SJRRC acknowledged the bid protest and assembled a bid protest review panel and anticipates resolution prior to the Board Meeting. If the protest results in a change of recommendation, a revised staff report can be provided to the Commissioners.
5 FISCAL IMPACT & RECOMMENDATION Fiscal Impact: The funding sources of the initial orders are from the Bay Area Air Quality Management District through the Carl Moyer Program Grant of which was cofunded by the San Joaquin Valley Air Pollution Control District, Transit and Intercity Rail Capital Program (TIRCP), and Low Carbon Transit Operations Program (LCTOP) allocations. Recommendation: Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing a Purchase of Four (4) New Tier IV AC Traction Passenger Locomotives with Siemens Industry, Inc. for an Amount Not-To-Exceed $30,896,568 with Options to Purchase up to Four (4) Additional Units During the Five-Year Contract Term, and Authorizing and Directing the Executive Director to Execute the Agreement.
6 ITEM 6 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing Contract Amendment #3 to Extend the Contract by Exercising the Second Option Year for Information Technology Services to Interwest Consulting Group for an Amount Not-To-Exceed $185,000 and Authorizing and Directing the Executive Director to Execute Contract Amendment #3
7 BACKGROUND Background: On April 4, 2014, the Board of Commissioners Approved a Resolution for a Three-Year contract with Two (2) One-Year Options to Interwest Consulting Group for Information Technology Services. The Approved Resolution for the initial Three-Year term is in the amount not-toexceed $750,000. On April 7, 2017, the Board of Commissioners Approved a Resolution for Contract Amendment #2 to exercise the first option year to renew the contract through April 30, 2018.
8 CONTRACT AMENDMENT This item is to exercise the second option year of the Information Technology Services contract with Interwest Consulting Group. The option to renew is at the sole discretion of SJRRC. Interwest Consulting Group agreed to continue the service at the same hourly rates as in the original proposal dated February 25, The cost of the option year is Not-To-Exceed $185,000 of which $75,000 is for the day-to-day operations, support, and maintenance, $60,000 is for ACE operations support including Security Camera, Train Wi-Fi, and Airwatch Mobile Device Management support and maintenance, and $50,000 for Capital Projects.
9 FISCAL IMPACT & RECOMMENDATION Fiscal Impact: Costs associated with this Amendment are identified in the San Joaquin Regional Rail Commission/ACE/SJJPA Fiscal Year 2017/2018 Operating Budget in the Project Management, Services, and Supplies Category in the Professional Services General line; Contracted Services Category in Professional Services Operations line; and Capital Budget in E-Ticketing line. Recommendation: Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing Contract Amendment #3 to Extend the Contract by Exercising the Second Option year for Information Technology Services to Interwest Consulting Group for an Amount Not-To-Exceed $185,000 and Authorizing and Directing the Executive Director to Execute Contract Amendment #3.
10 ITEM 7 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Adopting Fiscal Year 2017/2018 Budget Amendment #3, Reclassifying Three Capital Projects and Increasing the Capital Budget for Two Capital Projects in the Amount of $2,480,000, from $54,518,773 to $56,998,773
11 BACKGROUND On June 2, 2017, the Board of Commissioners approved the FY 2017/2018 SJRRC/ACE/SJJPA Operating and Capital Budgets. On September 1, 2017, the Board of Commissioners approved a resolution for Fiscal Year 2017/2018 Budget Amendment #1 to add two capital projects to the Capital Budget and increase the Capital Budget in the amount of $275,830 from $54,242,943 to $54,518,773. On November 3, 2017, the Board of Commissioners approved a resolution for Fiscal Year 2017/2018 Budget Amendment #2 and increased the San Joaquin Joint Powers Authority (SJJPA) Operating Budget in the Amount of $763, from $52,093,669 to $52,857,297.
12 BUDGET AMENDMENT This amendment will reclassify three (3) capital projects and increase the Capital Budget in the amount of $2,480,000 for two (2) capital projects. Details of the changes are described below: Capital Budget: 1. Reclassification: $600,000 from SJJPA Minor Cap to Safety/Security Projects. The funding source is Prop 1B CalOES and is identified in the SJRRC Capital Budget. 2. Reclassification: $393,710 from E-Ticketing to Positive Train Control (PTC). The funding source is Prop 1B PTMISEA and is identified in the SJRRC Capital Budget.
13 BUDGET AMENDMENT 3) Reclassification: $200,000 from E-Ticketing to Safety/Security Projects. The funding source is Prop 1B TSSDRA and is identified in the SJRRC Capital Budget. 4) Increase Capital Budget by $2,480,000 for two capital projects: $100,000 for RMF Wayside Power $2,380,000 for Cabral Station Track Extension Funding for these projects are identified in the Amendment of the Measure K Cooperative Agreement (C ) with SJCOG and approved by the SJCOG Board on October 26, 2017
14 BUDGET AMENDMENT Amendment #3 Capital Projects 2017/2018 Original Project Total for FY 17/18 Updated Project Total for FY 17/18 Cabral Station Track Extension 5,000,000 7,380,000 E-Ticketing 844, ,913 Safety/Security Projects 0 800,000 Positive Train Control 3,726,880 4,120,590 RMF Wayside Power 200, ,000 SJJPA Minor Capital Projects 1,600,000 1,000,000 Total 54,518,773 56,998,773 32% 70% 100% 10% 33% 38% 5%
15 FISCAL IMPACT & RECOMMENDATION Fiscal Impact: This amendment increases the SJRRC Capital Budget by $2,480,000 for FY 2017/2018, from $54,518,773 to $56,998,773. Recommendation: Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Adopting Fiscal Year 2017/2018 Budget Amendment #3, Reclassifying Three Capital Projects and Increasing the Capital Budget for Two Capital Projects in the Amount of $2,480,000, from $54,518,773 to $56,998,773.
16 ITEM 8 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Appointing the Stanislaus County Council of Governments as an Ex-Officio Member of the Commission
17 EX-OFFICIO REQUEST BY STANISLAUS COUNTY Due to the discussions taking place regarding the planning and funding of the ACE extension and operations into the Stanislaus region as a result of SB 132, The StanCOG Board, at their March 29 th meeting, approved a request to the Rail Commission to start the process toward StanCOG s participation on the SJRRC Board. The request seeks an Ex-Officio seat as an initial form of representation, with a desire to secure a voting member seat as the expansion into Stanislaus County progresses.
18 EX-OFFICIO REQUEST BY STANISLAUS COUNTY At the March 2 nd Rail Commission meeting, staff and Counsel presented options for involving elected officials from future ACE expansion counties on the Rail Commission Board. Section 4.2 of the First Amended Joint Powers Agreement for the San Joaquin Regional Rail Commission and Section 8.2 of the Commission s By-laws state, upon a majority vote of the regular voting members present, the Commission may appoint Ex-Officio nonvoting members to the Commission. If approved by the process noted above, StanCOG would be invited to appoint a representative to participate in the Rail Commission meetings on its behalf.
19 EX-OFFICIO REQUEST BY STANISLAUS COUNTY Recommendation: Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Appointing the Stanislaus County Council of Governments as an Ex-Officio Member of the Commission.
20 ITEM 9 SJRRC 2018/2019 Conceptual Work Program
21 BACKGROUND The Conceptual Work Program lays out the priorities and focus for the upcoming fiscal year. It includes the oversight of the San Joaquins Intercity Rail service since the Rail Commission serves as the Managing Agency on behalf of the SJJPA Board.
22 WORK PROGRAM AND BUDGET SCHEDULE April 6 th, 2018 Conceptual Work Program May 4 th, 2018 Draft Work Program and Budget June 6 th, 2018 Final Work Program and Budget
23 CONCEPTUAL WORK PPROGRAM ACE Based upon the five years of work through the ACEforward planning effort and the funding programs of SB1 and SB132, this next year s efforts will focus on addressing existing ACE service capacity issues related to platforms, parking, shuttles and rolling stock. The expansion effort will focus on the capital projects related to the Ceres extension and, subject to the results of the Transit and Intercity Capital Rail Program (TIRCP), may include capital projects related to expanded service to Sacramento for both ACE and the San Joaquins. A 4-train service scenario is assumed to continue, along with the implementation of a pilot Saturday service program once PTC certification is complete. Coordination will also continue with the High Speed Rail Authority (HSR) and the Tri-Valley San Joaquin Valley Rail Authority for connections to the HSR network and BART.
24 CONCEPTUAL WORK PPROGRAM SAN JOAQUINS Morning Express Service will start on May 7 th. This service can be provided without additional cost by adjusting current train schedules. The Morning Express will start in Fresno and arrive in Sacramento just before 8:00am. The new overall schedule allows for a full day in Sacramento and a half day, both in the morning and afternoon. Based upon the success of the Sacramento Morning Express concept, a Bay Area Morning Express train is planned for start-up in April of The capital program for the San Joaquins is focused on double platforms in the Valley and station upgrades for parking, lighting, security cameras and waiting room improvements.
25 ITEM 10 Presentation by Train Riders Association of California (TRAC)
26 CHARTING A NEW COURSE FOR CENTRAL VALLEY CONNECTIVITY THE NEXT BIG STEP FOR ACE 26
27 ACEforward 27
28 ACEforward 28
29 WHAT S LEFT? 29
30 TRUE INTERCITY SERVICE TRAC s intercity paper 30
31 OUR RAIL NETWORK 31
32 OUR CURRENT NETWORK 32
33 ALTAMONT CORRIDOR (Project Newsletter from 2011) 33
34 ACRP ALTERNATIVES 34
35 35
36 36
37 PUBLIC-PRIVATE PARTNERSHIP 37
38 ACE HAS A CHOICE. THIS: 38
39 OR THIS: 39
40 SHIFTING THE ROUTE 40
41 THERE S JOBS THERE! Stockton Modesto Merced Fresno 41
42 NEW DESTINATIONS 42
43 ACE EXTENSION TO CERES/MERCED 43
44 TRAC S ALTERNATIVE 44
45 SERVING SACRAMENTO 45
46 QUESTIONS AND DISCUSSION Train Riders Association of California Please send comments to: 46
47 ITEM 11 Authorize SJRRC Chair to Submit a SJRRC Comment Letter on the California High-Speed Rail Authority s Draft 2018 Business Plan
48 COMMENT LETTER ON CHSRA DRAFT 2018 BUSINESS PLAN The California High-Speed Rail Authority (CHSRA) Draft 2018 Business Plan was released on March 9, The full CHSRA Draft 2018 Business Plan is available on the CHSRA website. Comments on this draft Business Plan are due to CHSRA no later than May 7, 2018.
49 HIGHLIGHTS OF CHSRA DRAFT 2018 BUSINESS PLAN CHSRA will complete the 119-mile segment in the Central Valley (Madera Shafter) Extends the Valley to Valley initial operating segment to San Francisco and Bakersfield. Acknowledges cost increases affecting each segment of the project, ranging from 20-35% and revised schedules that will push out delivery dates for the Silicon Valley to Central Valley Line and Phase 1 High- Speed Rail System.
50 HIGHLIGHTS OF CHSRA DRAFT 2018 BUSINESS PLAN Proposes to deliver 224 Miles of High-Speed Rail Ready Infrastructure for Use by 2027: Madera to Bakersfield & San Francisco to Gilroy. Isolate the Tunneling in the Pacheco Pass as the Final Piece to Complete Silicon Valley to Central Valley service: Engage Public and Private Sector. Continue Bookend Investments in Southern and Northern California.
51 HIGHLIGHTS OF CHSRA DRAFT 2018 BUSINESS PLAN
52 HIGHLIGHTS OF CHSRA DRAFT 2018 BUSINESS PLAN Highlights the coordinated efforts with the Connected Corridor North Study. Done in partnership with the Central Valley Rail Working Group, SJRRC, SJJPA, CalSTA and Caltrans. Identifies a path forward for better, faster, more frequent and more coordinated passenger rail service between the San Joaquin Valley and Sacramento.
53 HIGHLIGHTS OF CHSRA DRAFT 2018 BUSINESS PLAN Additional areas of importance in the Draft Plan to the SJRRC include: A commitment to continue to work with SJRRC and other Northern California rail partners to identify and prioritize near-term regional rail improvements as part of the Northern California Unified Rail Service. Highlights that connecting Merced as part of the Initial Operating Segment remains a high priority to CHSRA. Continues to identify Madera as a HSR station to provide connectivity with the San Joaquins.
54 COMMENT LETTER ON CHSRA 2018 DRAFT BUSINESS PLAN A draft SJRRC comment letter which is recommended for Board approval was included in briefing materials. Fiscal Impact There is no fiscal impact. Recommendation Authorize SJRRC Chair to Submit a SJRRC Comment Letter on the California High-Speed Rail Authority s Draft 2018 Business Plan.
55 ITEM 12 SJRRC and SJCOG Partnership on a Pilot Program to Incentivize Rideshare and Carpools at the Lathrop/Manteca and Tracy Stations
56 BACKGROUND SJRRC staff have been working to reduce parking impacts at the Lathrop/Manteca and Tracy stations due to increased ridership. Repainting lots and removing park and ride users have helped. SJRRC staff have been working with SJCOG staff on ways to further reduce parking congestion at the Lathrop/Manteca and Tracy stations.
57 PROGRAM Using Dibs, a program through SJCOG to connect transit users with other riders for carpools or transit options, SJRRC and SJCOG plan to offer a $75 gas gift card for those that create a carpool to the stations. Eligibility: Form new carpools at Lathrop/Manteca and Tracy stations. Drivers must log trip through Dibs Web site. Have to utilize program for two months. Must be ACE 20 trip or monthly pass holder. Must rideshare at least three times per week. Cost of the program is $3000, with SJRRC and SJCOG splitting the cost, and would include up to 40 carpoolers.
SAN JOAQUIN REGIONAL RAIL COMMISSION ANNUAL FINANCIAL REPORT
ANNUAL FINANCIAL REPORT FOR THE FISCAL YEAR ENDED June 30, 2016 Prepared by: Fiscal Department TABLE OF CONTENTS JUNE 30, 2016 INTRODUCTORY SECTION Letter of Transmittal... 3 Organizational Chart... 9
More informationCalifornia High-Speed Rail Project
California High-Speed Rail Project Summary of Major Changes Between: Draft 2012 Business Plan (November 1, 2011) Revised 2012 Business Plan (April 2, 2012) 1 April 2, 2011 1 Subject to consideration of
More informationACEForward 9,900,000. Positive Train Control 2,800, ,695. UPRR Capital Access Fee 3,242, ,503 2,130,776
Commissioner, Bob Johnson, Chair, City of Lodi Commissioner, Michael Maciel, ViceChair, City of Tracy Commissioner, Moses Zapien, San Joaquin County Commissioner, Scott Haggerty, Alameda County Executive
More informationWORK PROGRAM & BUDGET
2014 2015 WORK PROGRAM & BUDGET Fiscal Year 2014/2015 Work Program and Budget Bob Johnson, Chair City of Lodi Steve Bestolarides San Joaquin County Brent H. Ives City of Tracy Kathy Miller City of Stockton
More informationAPPENDIX I REVENUE PROJECTION AND ASSUMPTIONS
APPENDIX I REVENUE PROJECTION AND ASSUMPTIONS The 2018 StanCOG Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) financial forecasts provide revenue projections for StanCOG member
More informationSAN JOAQUIN REGIONAL RAIL COMMISSION Meeting of July 8, 2011
Item 5.1: Minutes of June 3, 2011 The regular meeting of the San Joaquin Regional Rail Commission was held at 8:00 a.m., June 3 rd, 2011 at the Robert J. Cabral Station, 949 East Channel Street Stockton,
More informationThe Potential for Shared Use Mobility in Affordable Housing Complexes in Rural California
The Potential for Shared Use Mobility in Affordable Housing Complexes in Rural California A Research Report from the University of California Institute of Transportation Studies Susan Pike, Ph.D., Post-Doctoral
More informationThe Future Scenarios
The Future Scenarios Developing the Scenarios Once the policy approach for each scenario was defined, the financial, service, and capital assumptions were developed further and are detailed in three supporting
More informationAGENDA September 26, :30 PM Hanford City Council Chambers/Civic Auditorium 400 North Douty Street Hanford, CA
AGENDA September 26, 2014 12:30 PM Hanford City Council Chambers/Civic Auditorium 400 North Douty Street Hanford, CA This Agenda shall be made available upon request in alternative formats to persons with
More informationAppendix. G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY
Appendix G RTP Revenue Assumptions REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Exhibit G-1 2014 RTP REVENUE FORECAST ASSUMPTIONS LOCAL REVENUES Measure K Sales Tax Renewal Program: Description:
More informationITEM 5 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing a Two-Year and Eleven-Month Contract
ITEM 5 Approve Resolution of the Board of Commissioners of the San Joaquin Regional Rail Commission Authorizing a Two-Year and Eleven-Month Contract with Two One-year Options for Financial Auditing Services
More informationCOOPERATIVE AGREEMENT FY 2004/05 VENTURA INTERCITY SERVICE TRANSIT AUTHORITY (VISTA) CONEJO CONNECTION
COOPERATIVE AGREEMENT FY 2004/05 VENTURA INTERCITY SERVICE TRANSIT AUTHORITY (VISTA) CONEJO CONNECTION This Agreement is made and entered into by the City of Calabasas (Calabasas) and the Ventura County
More informationSubject: Creation of an Eco Pass
To: Board of Directors Date: April, 2014 From: Anne Muzzini, Director of Planning & Marketing Reviewed by: Subject: Creation of an Eco Pass Summary: The concept of creating an Eco Pass has been reviewed
More informationCaltrain Service Preparing for FY2012 Caltrain Benefits Environment, Economy, Quality of Life
Caltrain Service Preparing for FY2012 Caltrain Benefits Environment, Economy, Quality of Life If traveling via automobile, Caltrain riders would increase regional CO2 emissions by 89,850 metric tons or
More informationQuarterly Status Report
Capital Projects Quarterly Status Report 2nd Quarter FY2018: October 01 December 31, 2017 Prepared for the March 07, 2018 SamTrans Board Meeting San Mateo County Transit District San Mateo County Transit
More informationBOARD OF DIRECTORS MEETING
Revised 12/10/14 See Item No. 11 SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY BOARD OF DIRECTORS MEETING FRIDAY, DECEMBER 12, 2014 10:00a.m. LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (METRO)
More informationMEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008
MEMORANDUM TO: FROM: Santa Clara Valley Transportation Authority Board of Directors Michael T. Burns General Manager DATE: August 4, 2008 SUBJECT: BART Operating Subsidy This memorandum summarizes and
More informationEXECUTIVE COMMITTEE MEETING STANCOG BOARD ROOM 1111 I STREET, SUITE 308 MODESTO, CA MONDAY, JANUARY 8, :00 PM
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus EXECUTIVE COMMITTEE MEETING STANCOG
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO.: 13 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Authorizing the Director of Transportation to submit
More informationIntroduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit
Joint Board Ownership Workshop November 16, 2018 1 Introduction Project Overview How Express Lanes Work 101 Managed Lane Financial Forecast Performance Comparison Ownership Considerations Transit Equity
More informationINFORMATIONAL REPORT
HUMBOLDT COUNTY ASSOCIATION OF GOVERNMENTS Regional Transportation Planning Agency Humboldt County Local Transportation Authority Service Authority for Freeway Emergencies 611 I Street, Suite B Eureka,
More informationCHAPTER 9 FINANCIAL CONSIDERATIONS
CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the Berryessa Extension Project (BEP) Alternative and the Silicon Valley Rapid Transit
More informationSTAFF REPORT Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) Scenario Performance Update for Board Direction
November 2017 Board of Directors STAFF REPORT SUBJECT: RECOMMENDED ACTION: 2018 Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) Scenario Performance Update for Board Direction Support
More informationPaul Keener, Alameda County Public Works
ALAMEDA COUNTY TRANSPORTATION COMMISSION Alameda County Safe Routes to Schools Laurel Poeton, Alameda County Transportation Commission James Martin Perez Work, Alameda County Safe Routes to Schools A l
More informationContracts Administration Management Action Plan Status June 20, 2013
Related to Agenda Item W1 Contracts Administration Management Action Plan Status June 20, 2013 Background In January 2012, the Board authorized an on-call management and consulting services contract with
More informationCHAPTER 9 FINANCIAL CONSIDERATIONS
CHAPTER 9 FINANCIAL CONSIDERATIONS 9.1 INTRODUCTION This chapter presents anticipated costs, revenues, and funding for the BEP and the SVRTP. A summary evaluation of VTA s financial plan for the proposed
More informationUniversity Link LRT Extension
(November 2007) The Central Puget Sound Regional Transit Authority, commonly known as Sound Transit, is proposing to implement an extension of the Central Link light rail transit (LRT) Initial Segment
More informationThis Page Intentionally Left Blank.
This Page Intentionally Left Blank. End- of-the Year Program Compliance Report FY 13-14 Page 2 MASS TRANSIT PROGRAM Compliance Report Summary Fiscal Year 2013-14 1. Did your agency receive Measure B Mass
More informationProposed FY2012 Operating Budget
Proposed FY2012 Operating Budget June 2, 2011 Overview Began budget discussions in January 2011 Reviewed FY2012 Preliminary Operating Budget at the May 5, 2011 JPB meeting Followed up Board member questions
More informationPage 2 of 9 project costs are included in the budget consistent with the adopted Measure C and Measure J Strategic Plans. Below is a summary of the FY
Meeting Date: Subject Summary of Issues Recommendations Financial Implications Options Attachments (See APC Packet dated 3/1/18) Changes from Committee Approval of FY 2017-18 Midyear Budget for the Contra
More informationJULY 17, 2018 FINAL AGENDA SENIOR CITIZEN AND DISABLED RESIDENT TRANSPORTATION ADVISORY COMMITTEE REPORT (NEXT SCHEDULED REPORT DECEMBER 2018)
NEW JERSEY TRANSIT CORPORATION NJ TRANSIT BUS OPERATIONS, INC. NJ TRANSIT RAIL OPERATIONS, INC. NJ TRANSIT MERCER, INC. NJ TRANSIT MORRIS, INC. REGULARLY SCHEDULED BOARD OF DIRECTORS MEETINGS JULY 17,
More informationCalifornia High-Speed Rail Peer Review Group
Lou Thompson Chairman Walter Bell Diane Eidam Stacey Mortensen The Honorable Darrell Steinberg Senate President Pro Tem State Capitol Building Room 205 Sacramento, CA 95814 April 6, 2014 The Honorable
More informationApplication to fund Executive level position for the Altamont Regional Rail Working Group
SUBJECT: FROM: Application to fund Executive level position for the Altamont Regional Rail Working Group Michael Tree, Executive Director DATE: August 1, 2016 Action Requested The staff recommendation
More informationSAN JOAQUIN COUNTY NTD VANPOOL REPORTING SUBSIDY PARTICIPATION AGREEMENT
SAN JOAQUIN COUNTY NTD VANPOOL REPORTING SUBSIDY PARTICIPATION AGREEMENT dibs, a program of the San Joaquin Council of Governments (SJCOG) is offering a lease fare subsidy to qualifying vanpools in San
More informationVTA Board of Directors: We are forwarding you the following: Letter of support regarding sales tax measure
From: Board.Secretary Sent: Thursday, July 28, 2016 5:05 PM To: VTA Board of Directors Subject: VTA Correspondence: Letter of Support Regarding Sales Tax Measure VTA Board of Directors: We are forwarding
More informationANNUAL PROCUREMENT PLAN ANNUAL Q Q 2015
ANNUAL PROCUREMENT PLAN 2Q ANNUAL 2018-1Q 2019 3Q 2015 THIS PAGE INTENTIONALLY LEFT BLANK 2 TABLE OF CONTENTS INTRODUCTION 4 PROFESSIONAL SERVICES 7 CONSTRUCTION 9 MATERIAL 11 OTHER 15 3 ANNUAL PROCUREMENT
More informationAdopted Biennial Budget
Santa Clara Valley Transportation Authority Adopted Biennial Budget Fiscal Years 21 and 211 July 1, 29 June 3, 21 and July 1, 21 June 3, 211 Search Instructions Items in this PDF version of the FY 21 and
More informationAdministration and Projects Committee STAFF REPORT March 1, 2018 Page 2 of 9 Below is a summary of the FY adopted budget and the proposed midy
Administration and Projects Committee STAFF REPORT Meeting Date: March 1, 2018 Subject Summary of Issues Recommendations Financial Implications Options Approval of FY 2017 18 Midyear Budget for the Contra
More informationTransit Subsidy. Mission Statement. Mandates
Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,
More informationSOCIAL SERVICES TRANSPORTATION ADVISORY COUNCIL MEETING STANCOG BOARD ROOM 1111 I STREET, SUITE 308 MODESTO, CA WEDNESDAY, JANUARY 3, :00 AM
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus SOCIAL SERVICES TRANSPORTATION ADVISORY
More informationBOARD OF DIRECTORS WORKSHOP MEETING MINUTES
BOARD OF DIRECTORS WORKSHOP MEETING April 25, 2008 MINUTES 1. CALLED TO ORDER The Workshop Meeting of the Santa Clara Valley Transportation Authority s (VTA) Board of Directors was called to order by Chairperson
More informationMTC OVERVIEW OF SB 1 (BEALL AND FRAZIER)
MTC OVERVIEW OF SB 1 (BEALL AND FRAZIER) NEW & AUGMENTED FUNDING PROGRAMS Below is a summary of the funding provided by program and the new revenue sources authorized in Senate Bill 1 (Beall and Frazier).
More informationNEW YORK STATE OFFICE OF THE STATE COMPTROLLER
NEW YORK STATE OFFICE OF THE STATE COMPTROLLER H. Carl McCall STATE COMPTROLLER COMMUTER CHOICE PROGRAMS AT FOUR UPSTATE PUBLIC TRANSPORTATION AUTHORITIES 2000-S-30 DIVISION OF MANAGEMENT AUDIT AND STATE
More informationFY18 Final Results Budget Outlook, FY20-22
FY18 Final Results Budget Outlook, FY20-22 Objectives Provide background necessary for consideration of fiscal pressures that exist prior to electrification Service levels Ridership Member agency funding
More informationChapter 6. Transportation Planning and Programming. Chapter 6
Chapter 6 Planning and ming Chapter 6 73 Chapter 6 Planning and ming VTA prepares a variety of transportation planning and programming documents that impact Santa Clara County s future mobility. Planning
More information2016 STATE LEGISLATIVE PROGRAM
2016 STATE LEGISLATIVE PROGRAM The California Transit Association s 2016 State Legislative Program is an integral part of making our vision a reality, and is part and parcel of our mission to further the
More informationMeasure B Expenditures Across All Programs FY Report Card
Measure B Across All Programs Report Card Altamont Commuter Express Projects Program Actual Mass Transit 2,820,948 2,824,169 (3,221) Totals: 2,820,948 2,824,169 (3,221) Capital Fund Reserve (FY 1316 Capital
More informationFY17 FY16 Valley Metro RPTA Sources of Funds FY17 vs FY16
FY17 ADOPTED ANNUAL OPERATING AND CAPITAL BUDGET Valley Metro Regional Public Transportation Authority (RPTA) provides public transportation services for Maricopa County located in the metro Phoenix, Arizona.
More informationAMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS
FOR IMMEDIATE RELEASE May 19, 2011 ATK-11-076a Contact: Media Relations 202 906.3860 AMTRAK PURSUING PRIVATE INVESTMENT TO SUPPORT NORTHEAST CORRIDOR HIGH-SPEED RAIL PLANS WASHINGTON Amtrak is developing
More informationTRANSIT SYSTEM MAINTENANCE AND RENOVATION. VEHICLES - Caltrain
Item 6 Enclosure Board November 13, 2018 2019 PROPOSITION K 5-YEAR PRIORITIZATION PROGRAM TRANSIT SYSTEM MAINTENANCE AND RENOVATION VEHICLES - Caltrain Pending Board Approval: November 27, 2018 Prepared
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 12 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Finance and Information Technology BRIEF DESCRIPTION: Adopting the SFMTA s Fiscal Year (FY) 2019 2023 Capital
More informationRe: Proposed Low Carbon Transit Operations Program (LCTOP) Guidelines, FY
BY EMAIL: jila.priebe@dot.ca.gov Jila Priebe, Office Chief of Transit Programs California Department of Transportation Division of Rail and Mass Transportation, MS #39 P.O. Box 942874 Sacramento, CA 94274-0001
More informationTransit Subsidy. Mission Statement. Mandates
Mission Statement The Potomac and Rappahannock Transportation Commission (PRTC) is a multi-jurisdictional agency representing Prince William, Stafford, and Spotsylvania Counties and the Cities of Manassas,
More informationMadera County Transportation Commission. Policy Board Meeting
Madera County Transportation Commission Policy Board Meeting LOCATION Madera County Transportation Commission Board Room 2001 Howard Road, Suite 201 Madera, California 93637 DATE January 23, 2019 TIME
More informationFY METROLINK BUDGET AND LACMTA'S COMMUTER RAIL PROGRAM
9 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net FINANCE, BUDGET AND AUDIT COMMITTEE JUNE 19, 2013 SUBJECT: ACTION: FY 2013-14 METROLINK BUDGET AND LACMTA'S COMMUTER RAIL PROGRAM
More information2018 Regional Transportation Improvement Program: Amendment No. 1
2018 Regional Transportation Improvement Program: Amendment No. 1 Transportation Committee Item 4 January 18, 2019 Summary of Changes 2 Transportation Committee Item 4 January 18, 2019 1 RTIP Project Tables
More informationChapter 9 Financial Considerations. 9.1 Introduction
9.1 Introduction Chapter 9 This chapter presents anticipated costs, revenues, and funding for the NEPA BART Extension Alternative. A summary of VTA s financial plan for the BART Extension Alternative is
More informationCaltrain Funding 101
Caltrain Funding 101 Prepared for: SFMTA Board Meeting Prepared by: Caltrain Staff Date: February 7, 2012 Caltrain Funding 101 Overview Funding contribution is guided by Joint Powers Agreement Funding
More informationExecutive Summary - Fiscal Year 2016 Valley Metro Rail Preliminary Annual Operating and Capital Budget
Executive Summary - Fiscal Year 2016 Valley Metro Rail Preliminary Annual Operating and Capital Budget Valley Metro Rail, Inc. (VMR) is a public non-profit corporation whose members are the cities of Chandler,
More informationCMAQ COST-EFFECTIVENESS THRESHOLD DOCUMENTATION FOR THE STANISLAUS COUNCIL OF GOVERNMENTS 2011 FTIP
CMAQ COST-EFFECTIVENESS THRESHOLD DOCUMENTATION FOR THE STANISLAUS COUNCIL OF GOVERNMENTS 2011 FTIP The Congestion Mitigation and Air Quality (CMAQ) program provides funding for transportation projects
More informationMemorandum. Date: June 14, 2018 To: From:
Agenda Item 4 Memorandum Date: June 14, 2018 To: From: Subject: Treasure Island Mobility Management Agency Committee Cynthia Fong Deputy Director for Finance & Administration Eric Cordoba Deputy Director
More informationSPECIAL MEETING OF EXECUTIVE COMMITTEE STANCOG BOARD ROOM 1111 I STREET, SUITE 308 MODESTO, CA MONDAY, JANUARY 7, :00 AM
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus SPECIAL MEETING OF EXECUTIVE COMMITTEE
More informationCalifornia Mental Health Services Authority FINANCE COMMITTEE TELECONFERENCE AGENDA
California Mental Health Services Authority FINANCE COMMITTEE TELECONFERENCE AGENDA May 7, 2018 3:00 p.m. 4:00 p.m. Dial-in Number: 916-233-1968 Access Code: 3043 Colusa County Department of Behavioral
More informationMemorandum. Request for Proposals (RFP): Integrated Ticketing Feasibility Study
Memorandum To: From: Consulting Firms Michelle Prince, Assistant Regional Planner Date: October 24, 2018 Re: Request for Proposals (RFP): Integrated Ticketing Feasibility Study The San Joaquin Council
More informationTRAVEL, CONFERENCE, TRAINING AND BUSINESS EXPENSE REIMBURSEMENT POLICY
TRAVEL, CONFERENCE, TRAINING AND BUSINESS EXPENSE REIMBURSEMENT POLICY This document establishes a set of policies relating to travel, conference, training and business expenses, and establishes procedures
More informationProposition 1B and the Strategic Growth Plan
Proposition 1B and the Strategic Growth Plan Presentation before the Senate Transportation and Housing Committee California Department of Transportation Proposition 1B Just one component of the Strategic
More informationSeptember Board of Directors Briefing Materials. September 24, 2018 FISCAL YEAR. NNEPRA Office Wells Town Hall Sanford Road Wells, ME 12:30pm
FISCAL YEAR September 2018 2019 Board of Directors Briefing Materials September 24, 2018 NNEPRA Office Wells Town Hall Sanford Road Wells, ME 12:30pm Concert Night at the Garden NNEPRA FY2019 Action Plan
More informationTable of Contents. TransPar Audit. Follow-up Review
Table of Contents TransPar Audit Follow-up Review September, 2012 Page Number BACKGROUND 2 OBJECTIVE, SCOPE AND METHODOLOGY 2-3 FINDINGS 3-11 1 BACKGROUND At the School Board s request, the district engaged
More information% Share of the overall budget increase Fixed Route 1,407, % 64% Paratransit 106, % 4.8% WHEELS on. prior year
SUBJECT: LAVTA s Operating & Capital Budget for FY 2019 FROM: Tamara Edwards, Director of Finance DATE: June 4, 2018 Discussion Attached for your approval is the draft LAVTA Operating Budget for FY 2019
More informationAudit and Finance Subcommittee
MEETING OF THE Audit and Finance Subcommittee MEETING DATE January 12, 2017 TIME LOCATION 12:00 p.m. Valley Metro 101 N. 1st Ave., 10th Floor Lake Mead Conference Room (10B) Phoenix, AZ 85003 VALLEY METRO
More informationSan Joaquin Valley Unified Air Pollution Control District
San Joaquin Valley Unified Air Pollution Control District 2008-09 Adopted Budget TABLE OF CONTENTS Budget Financial Sumniary Budget Summary Schedule of Estimated Revenues Total District - Line Item Detail
More informationWake County. People love to be connected. In our cyberspace. transit plan CONNECTING PEOPLE, CONNECTING THE COUNTY
Wake County transit plan CONNECTING PEOPLE, CONNECTING THE COUNTY EXECUTIVE SUMMARY People love to be connected. In our cyberspace driven world, people can stay connected pretty much all of the time. Connecting
More informationProposition 53 Public Vote on State Revenue Bonds (Official Title: Revenue Bonds. Infrastructure Projects. State Legislature and Voter Approval.
Proposition 53 Public Vote on State Revenue Bonds (Official Title: Revenue Bonds. Infrastructure Projects. State Legislature and Voter Approval.) CALTAX POSITION: NEUTRAL The California Taxpayers Association
More informationFunding Local Public Transportation
Funding Local Public Transportation I. Metro A. SORTA, early history In 1969 the Southwest Ohio Regional Transit Authority was established by Hamilton County with Hamilton County as its jurisdiction. In
More informationSAN JOSE, CALIFORNIA. Comprehensive Annual Financial Report. For Fiscal Year Ended June 30, 2004
SANTA CLARA VALLEY TRANSPORTATION AUTHORITY SAN JOSE, CALIFORNIA Comprehensive Annual Financial Report For Fiscal Year Ended June 30, 2004 Prepared by: Fiscal Resources Division SANTA CLARA VALLEY TRANSPORTATION
More informationSOLTRANS BOARD MEETING SUPPLEMENTAL REPORTS / HANDOUTS December 19, 2013 MEETING HANDOUTS
SOLTRANS BOARD MEETING SUPPLEMENTAL REPORTS / HANDOUTS December 19, 2013 MEETING HANDOUTS Agenda Item 8 SolTrans Curtola Park and Ride Hub Project Update PowerPoint Presentation Agenda Item 9 SolTrans
More informationSanta Clara Valley Transportation Authority
Santa Clara Valley Transportation Authority Comprehensive Annual Financial Report For Fiscal Year Ended June 30, 2005 1996 Measure B U.S. 101 Widening Highway Project Paratransit services offer alternatives
More informationSan Francisco Paratransit
San Francisco Paratransit Addendum #1 SF Paratransit Van Services: SFMTA/DAAS Group Van, & DAAS Shopping Shuttle No. 16-493-001 October 28, 2016 Proposal Submission Deadline: Wednesday, November 9, 2016
More informationALAMEDA County Transportation Commission. Alameda County Transportation Commission GUARANTEED RIDE HOME PROGRAM GUIDELINES
ALAMEDA County Transportation Commission Alameda County Transportation Commission GUARANTEED RIDE HOME PROGRAM GUIDELINES Updated April 2017 Contents Introduction 2 Program Basics 3 Program Registration
More informationItem #4 JANUARY 30, 2015 MEETING MINUTES PG. 2 Approve the January 30, 2015 meeting minutes.
AGENDA COASTAL EXPRESS POLICY ADVISORY COMMITTEE Wednesday, March 25, 2015, 11:00 a.m. Ventura City Hall, Second Floor Community Room 501 Poli Street, Ventura, CA 93002 Item #1 Item #2 Item #3 CALL TO
More informationPerformance-Based Operating Assistance Allocation Methodology
Performance-Based Operating Assistance Allocation Methodology Amy Inman Acting Planning &Mobility Programs Administrator Department of Rail and Public Transportation SB1140 Public Meeting October 2, 2013
More informationVictor Valley Transit Authority
ANNUAL OPERATING AND CAPITAL BUDGET FISCAL YEAR 2016 2017 (As approved by the Board of Directors) June 20, 2016 VICTOR VALLEY TRANSIT AUTHORITY FY 2017 BUDGET OPERATING EXPENSE SUMMARY System FY 2016/17
More informationContra Costa Transportation Authority STAFF REPORT Meeting Date: July 20, 2016 Subject Summary of Issues Recommendations Approval of FY Transp
Contra Costa Transportation Authority STAFF REPORT Meeting Date: Subject Summary of Issues Recommendations Approval of FY 2016-17 Transportation Demand Management Program Funding - Measure J Commute Alternatives
More informationMinutes NASHVILLE METROPOLITAN TRANSIT AUTHORITY BOARD OF DIRECTORS MEETING. January 26, 2017
Minutes NASHVILLE METROPOLITAN TRANSIT AUTHORITY BOARD OF DIRECTORS MEETING January 26, 2017 I. CALL TO ORDER: The regular meeting of the Nashville Metropolitan Transit Authority (MTA) Board of Directors
More informationEXECUTIVE COMMITTEE MEETING STANCOG BOARD ROOM 1111 I STREET, SUITE 308 MODESTO, CA MONDAY, FEBRUARY 4, :00 PM
City of Ceres City of Hughson City of Modesto City of Newman City of Oakdale City of Patterson City of Riverbank City of Turlock City of Waterford County of Stanislaus EXECUTIVE COMMITTEE MEETING STANCOG
More informationPublic Transportation Department Anchorage: Performance. Value. Results.
Anchorage: Performance. Value. Results. Mission Serve Anchorage residents and visitors by providing public transportation that emphasizes quality, safety, cost effectiveness, and economic vitality. Core
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Operating Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation March 6, 2018 1 Guiding Principles: FY 2013-2018 Vision:
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE
CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE DATE: TO: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Nury Martinez, Chair, Energy and the Environment Committee
More informationAn Economic and Policy Analysis of the Introduction of High-Speed Rail in California: -
An Economic and Policy Analysis of the Introduction of High-Speed Rail in California: - Phase I from the San Francisco Bay Area to Los Angeles and Anaheim A Masters Project by David R. Tucker Dr. Lincoln
More information2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006
State Legislative Items: Additional Transportation Funding 2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006 Position: The Northern Virginia Transportation
More informationWashington Metropolitan Area Transit Authority Metro Budget Overview
Washington Metropolitan Area Transit Authority Metro Budget Overview February 2011 Metro 10,877 Employees (10,974 budgeted) 1,491 Buses 588 Escalators and 237 Elevators 106 Miles of Track 92 Traction Power
More informationSAN JOAQUIN REGIONAL RAIL COMMISSION MEASURE B PROGRAM FUND
MEASURE B PROGRAM FUND Independent Auditors Report, Financial Statements, Supplementary Information and Other Reports For the Year Ended June 30, 2015 MEASURE B PROGRAM FUND JUNE 30, 2015 TABLE OF CONTENTS
More informationMEMORANDUM. To: Fred Butler and Shelley Winters From: Stephen Falbel Re: NHDOT Public Transportation Policy Date: May 11, 2018
MEMORANDUM To: Fred Butler and Shelley Winters From: Stephen Falbel Re: NHDOT Public Transportation Policy Date: May 11, 2018 This memorandum presents the results of an analysis of a potential policy statement
More informationBallot Measure Description
2016 BALLOT MEASURE SCORERD AZ Flagstaff The Flagstaff City Council has approved placing a 10-year 0.295% renewal on the November ballot for the Northern Arizona Intergovernmental Public Transportation
More informationFY 2018 Adopted Wake Transit Work Plan
FY 2018 Adopted Wake Transit Work Plan Fiscal Year (FY 2018) Wake Transit Work Plan Table of Contents FY 2018 Wake Transit Work Plan Introduction 3 FY 2018 Operating Budget & Multi-Year Operating Program
More informationIntercity Transit Community Update
Intercity Transit Community Update Mission and Vision Mission: Our mission is to provide and promote transportation choices that support an accessible, sustainable, livable, healthy, prosperous community.
More informationEconomic Impact of Public Transportation Investment 2014 UPDATE
Economic Impact of Public Transportation Investment 2014 UPDATE May 2014 Acknowledgements This study was conducted for the American Public Transportation Association (APTA) by Economic Development Research
More informationFinancial Feasibility of Contra Costa County Ferry Service,
Draft Final Report Financial Feasibility of Contra Costa County Ferry Service, 2015-2024 Prepared for: Contra Costa Transportation Authority Prepared by: Economic & Planning Systems, Inc. May 29, 2014
More informationRECIPROCITY INFORMATION BOOKLET
RECIPROCITY INFORMATION BOOKLET SAN JOAQUIN COUNTY EMPLOYEES RETIREMENT ASSOCIATION 6 SO. EL DORADO STREET SUITE 400 STOCKTON, CA 95202 PHONE (209) 468-2163 FAX (209) 468-0480 January 2005 This is intended
More informationPIERCE TRANSIT BOARD MEETING Training Center, St. Helens Room September 13, :00 P.M. AGENDA
PIERCE TRANSIT BOARD MEETING Training Center, St. Helens Room September 13, 2010 4:00 P.M. AGENDA CALL TO ORDER ROLL CALL APPROVAL OF VOUCHERS PUBLIC COMMENT PRESENTATION Operator of the Quarter Dan Twaites
More information