STATUS OF PROJECTS IN EXECUTION FY09 SOPE

Size: px
Start display at page:

Download "STATUS OF PROJECTS IN EXECUTION FY09 SOPE"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY09 SOPE Operations Policy and Country Services OCTOBER 02, 2009

2 Introduction The Status of Projects in Execution (SOPE) Report for FY09 provides information on all IBRD/IDA projects that were active as of June 30, The World Bank has issued a SOPE Report every year as an internal communication to the Board of Executive Directors. In accordance with the Bank s revised disclosure policy, since FY02, the SOPE Report is available to the public. The report is intended to bridge the gap in information available to the public between the Project Appraisal Document or Program Document, disclosed after the Bank approves a project, and the Implementation Completion Report, disclosed after the project closes. In addition to the project progress description, the FY09 SOPE report 1 contains project level comparisons of disbursement estimates and actual disbursements, and a table showing the loan/credit/grant amount and disbursements to date. Table of Contents Introduction... 1 East Asia and Pacific Regional Projects... 3 Cambodia... 9 China Indonesia Kiribati Lao People's Democratic Republic Malaysia Mongolia Pacific Islands Papua New Guinea Notes: Amounts and Graphs for loans/credits/grants in currencies other than U.S. dollars may not match exactly due to exchange rate fluctuations over the life of the project. Disbursement graphs are not included for Development Policy Operations, which provide quick-disbursing financing to support policy and institutional reforms. For these operations, funds are disbursed in one or more stages (tranches), released when the borrower complies with agreed prior actions. Projects which are not yet effective may not have a planned disbursement schedule and thus will not include a graph. Status of Projects in Execution - FY09 1

3 Philippines Samoa Solomon Islands Thailand Timor-Leste Tonga Vietnam Status of Projects in Execution - FY09

4 East Asia and Pacific Regional Projects Project Name(ID): Sector: received Additional Financing during Project 4e-GEF MARINE ELECTRONIC HWY (P068133) East Asia and Pacific 13-Jun Jun-2011 Ports, waterways and shipping (80%); Central government administration (20%) no A demonstration project to reduce the user costs and environmental damage of marine navigation through the Straits of Malacca and Singapore. The project is significantly behind schedule and has not made good progress toward achieving its objectives. The hydrographic survey critical to carrying out other parts of the project has not been done. Although improved navigation and communications equipment has been installed on about 160 large ships, the electronic navigation charts and other information that these systems would use cannot be prepared without data from the pending hydrographic survey. TF Closed USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 3

5 Lending Information/Disbursement Summary (in millions USD) 4 Status of Projects in Execution - FY09

6 Sector: received Additional Financing during Project Targeted Research for Coral Reefs (P078034) East Asia and Pacific 23-Sep Aug May-2010 Tertiary education (95%); General agriculture, fishing and forestry sector (5%) no The objectives are to (a) align the expertise and resources of the global coral reef community around key research questions related to the resilience and vulnerability of coral reef ecosystems, and integrate the results and disseminate them in formats readily accessible to managers and decision makers; and (b) build the capacity for science-based management of coral reefs in developing countries. The project has made excellent progress toward achieving its objectives. It has coordinated world-class scientific research on key aspects of coral reef ecosystem sustainability in four regions of the world, reported the results in top journals such as Science and Nature, and enhanced global knowledge and awareness about the likely impacts of local and global threats and how best to address them. At the 11th International Coral Reef Symposium, researchers supported by the project led discussions ranging from the future of reefs under climate change and increasing population pressure, to local interventions to strengthen governance, improve management, and enhance the resilience of reefs to these impacts. Manuals, atlases, guidance notes, policy briefs and decision support tools related to these themes are available on the web ( in a variety of languages. In the lead-up to the December 2009 negotiations on a new climate change treaty, the project has also influenced discussions on target thresholds for CO2 and possible tipping points for coral reef ecosystems. It has also built capacity locally at Centers of Excellence in Mexico, the Philippines and Tanzania, and has supported 50 of the best and brightest young coral reef scientists from the developing world through graduate and postdoctoral scholarships at leading universities, with mentoring by senior scientists. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 5

7 Lending Information/Disbursement Summary (in millions USD) 6 Status of Projects in Execution - FY09

8 Sector: received Additional Financing during Project 4E - Livestock Waste Management (P079610) East Asia and Pacific 21-Mar Jan Dec-2010 Animal production (69%); Central government administration (20%); Sub-national government administration (10%); Agricultural extension and research (1%) no The project development objective is to reduce the major negative environmental and health impacts of rapidly increasing concentrated livestock production on the open waters and thus on the people of East Asia. Its Global Environmental Objective is to reduce livestock-induced, landbased pollution and the environmental degradation of the South China Sea. The project is expected to yield only limited direct impact on water quality of the South China Sea because the selected demonstration areas represent negligible fractions of the total pollution load. A noticeable pollution reduction in the South China Sea catchment areas can be achieved through the replication of the demonstrated livestock waste management practices throughout the participating countries (China, Thailand, and Vietnam). A replication strategy has been tested in all three participating countries. A list of farms for replication has been selected in China. A nation-wide program to replicate livestock waste management practices through a Carbon Finance project was developed in Thailand to involve about 36 medium and large sized farms. A total of 20 farms have been selected in Vietnam as potential participants for this purpose. TF Closed USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 7

9 Lending Information/Disbursement Summary (in millions USD) 8 Status of Projects in Execution - FY09

10 Cambodia Project Name(ID): Sector: received Additional Financing during Project KH - Road Asset Mgmt (ADB/AusAID) (P106603) Cambodia 20-May Sep-2013 Roads and highways (97%); Central government administration (3%) no To ensure continued effective use of the rehabilitated national and provincial road network in support of the economic development of Cambodia. The Credit became effective only in December, but initial progress is good. A series of fiduciary, technical and managerial training programs took place between January and March Key consultancies have started including the first year design consultant who came on board in April. Procurement of civil works should start early in FY10. The business case for the Merit Based Performance Incentive program has been approved in principle by the government. Although very early in implementation, these start-up activities will contribute to allowing the project to meet its PDO. IDA Effective XDR Status of Projects in Execution - FY09 9

11 Lending Information/Disbursement Summary (in millions USD) 10 Status of Projects in Execution - FY09

12 Sector: received Additional Financing during Project KH-Rural Electrif. & Transmn (P064844) Cambodia 16-Dec May Sep-2009 Power (78%); Central government administration (14%); Renewable energy (8%) no The main development objectives of the project are to: (a) improve power sector efficiency and reliability and reduce electricity supply costs; (b) improve standards of living and foster economic growth in rural areas by expanding rural electricity supplies; and (c) strengthen electricity institutions, the regulatory framework and the enabling environment for sector commercialization and privatization. The project's global environmental objective is to overcome barriers to renewable energy development in Cambodia, including those related to lack of policy framework, financing, information and institutional capacity. Remarkable progress has been made over the last year. Construction of a double-circuit 115 kv transmission line of 14 kms is now complete, as well as the stringing of the second circuit of existing 115kV transmission lines of 23km. The newly constructed and upgraded 115 kv transmission lines will be energized in July 2009, and will soon allow an additional 100 megawatts of power to flow from Vietnam. Extension of the medium-voltage transmission lines is well underway. About 120km of medium-voltage transmission lines have been constructed to extend power to areas west of Phnom Penh and in Kampot, Takeo and Sihanoukville provinces. Extension of the rural electricity grid (off-grid), continues to progress as well. The Rural Electrification Fund is providing sub-grants to enable about 49,000 households to connect to the rural grid. Some 16,730 new households were connected as of June These achievements will improve living standards and foster economic growth in rural areas by expanding electricity supplies. Generally speaking, these achievements will help improve power supply efficiency and improve the reliability of Electricite du Cambodge (EDC). The Electricity Authority of Cambodia (EAC) continued to make good progress in project implementation as well as in gradually strengthening the regulatory framework. EAC had expanded the list of registered licensees to 225 as of June 2009, exceeding the project target of 180. Nine new licenses were issued during These steps will strengthen the institutional and regulatory environment to enable sustainability. Status of Projects in Execution - FY09 11

13 IDA Effective XDR IDA-Q2990 Closed USD TF Closed USD Lending Information/Disbursement Summary (in millions USD) 12 Status of Projects in Execution - FY09

14 Sector: received Additional Financing during Project KH-PROVL & RURAL INFRA (P071207) Cambodia 11-Sep Jul Dec-2010 Roads and highways (83%); Central government administration (9%); Sub-national government administration (8%) no To assist the Kingdom of Cambodia to enhance the livelihood of the peoples residing in the provinces of Kampong Thom, Oddar Meanchey, Preah Vihear and Siem Reap with sustainable access to markets and essential services through (i) a program of road rehabilitation and maintenance; (ii) a program of capacity building and training; and (iii) development of improved public policies and strategies. Progress toward meeting the PDO is progressing if modestly. The Ministry of Public Works and Transportation (MPWT) has established and is utilizing the Road Management System, and is increasing attention to regular periodic and routine maintenance planning and budgeting. Road safety and HIV/AIDS programs are underway. These activities should enable sustainable access to markets and essential services. The Ministry of Rural Development has been less successful in achieving its target outputs of developing improved public policy and strategies. The recent extension of the closing date will provide additional time to further build institutional capacity and build key infrastructure necessary to fully meeting the PDO. IDA Effective XDR IDA-Q2790 Closed USD IDA-Q2791 Closed USD TF Closed USD TF Effective USD Status of Projects in Execution - FY09 13

15 Lending Information/Disbursement Summary (in millions USD) 14 Status of Projects in Execution - FY09

16 Sector: received Additional Financing during Project KH-Demand for Good Governance (P101156) Cambodia 02-Dec Mar-2013 Law and justice (30%); Other social services (23%); General public administration sector (17%); Sub-national government administration (15%); Media (15%) no To enhance the demand for good governance in priority reform areas by strengthening institutions, supporting partnerships, and sharing lessons Project just became effective June 24, 2009 so no significant progress towards meeting the PDO can be reported for FY09. IDA-H4410 Effective XDR IDA-Q5540 Closed USD IDA-Q6070 Closed USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 15

17 KH - GMS Power Trade Project (P105329) Cambodia 05-Jun Dec-2011 Sector: Power (100%) received Additional Financing during no The objective is to enhance power trade within Greater Project Mekong Sub/Region with a view to also bringing affordable gird-based electricity to selected provinces in Cambodia. the development objectives is considerably delayed due to delays in procurement; no contracts for any major project component have been signed. However, an Independent Procurement Agency has been hired to carry out all procurement work, and with the updated procurement schedule, the project is still expected to be completed within the original timeframe. IDA-H3010 Effective XDR Lending Information/Disbursement Summary (in millions USD) 16 Status of Projects in Execution - FY09

18 Sector: received Additional Financing during Project KH- Trade Facilitation & Competitiveness (P089196) Cambodia 02-Jun May Dec-2009 Other domestic and international trade (80%); General public administration sector (20%) A minor restructuring was undertaken to enable further analysis of the proposed Trade Information Website Promote economic growth by reducing transaction costs associated with trade and investment, introducing transparency in investment processes, and facilitating access of enterprises to export markets. Progress toward meeting the development objectives has been encouraging. The computerized customs system (ASYCUDA) has been deployed at the Port of Sihanoukville and the first few matching grants under the Export Market Access Fund have been granted. In addition, to facilitate foreign investment, the Law on Concessions - which governs private participation in infrastructure - has been adopted and an Investor Aftercare Unit is being created. There are, however, challenges to the sustainability of the ASYCUDA system and its roll out, which are being addressed by the Government. IDA-H1650 Effective XDR IDA-Q4560 Closed USD Status of Projects in Execution - FY09 17

19 Lending Information/Disbursement Summary (in millions USD) 18 Status of Projects in Execution - FY09

20 Sector: received Additional Financing during Project KH-Land Allocation for Soc.and Eco. Dev. (P084787) Cambodia 20-May Jun-2013 General agriculture, fishing and forestry sector (65%); Subnational government administration (35%) no The objective is to improve the process for identification and use of state land transferred to eligible poor and formerly landless or land-poor recipients selected through a transparent and well-targeted process. The project has been effective for about nine months. In that time, over 5,000 hectares have been registered as state private land and selection has been completed for over 1000 eligible land recipients. These early achievements indicate progress toward improving the process for identifying and using state land for eligible persons. First food for work has been provided and contracts for access tracks and potable water are advanced. These livelihood development support activities will help land recipients settle into their communities more easily and use their state lands. IDA Effective XDR IDA-H3860 Effective XDR TF Closed USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 19

21 Lending Information/Disbursement Summary (in millions USD) 20 Status of Projects in Execution - FY09

22 KH - Trade Development Support Program (P109648) Cambodia 07-Jan Mar-2012 Sector: Public administration- Industry and trade (100%) received Additional Financing during no The objectives of the program are to (a) increase Cambodia's capacity in formulating and implementing appropriate trade policies that lead to transparency and efficiency in traderelated transactions and export competitiveness; and (b) Project support the implementation of Cambodia's Diagnostic for Trade Integration Strategy in the context of the #Integrated Framework for Trade Related Technical Assistance to Least Developed Countries#. The program, which is effective since March 2009, is at its start-up stage. Good progress has been made to set up the program structure, which enables the Government to manage its "Trade Sector-Wide Approach". TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 21

23 Cambodia - Public Fin. Mgmt. & Accnt. (P087945) Cambodia 27-Jun Jan-2012 Sector: Central government administration (100%) received Additional Financing during no The development objective of the project is to improve public financial management by strengthening: (a) the mobilization of Project public resources; (b) the management of public resources; (c) the management of human resources; and (d) external audit capacity. The PFM Reform Program continued to make progress during FY2009, although the impact of the global financial crises has begun to impact on Government Budgetary Operations in the last two quarters. Key project development performance indicators show:(a) Domestic revenue in RGC fiscal year 2008 was 24% above budget and reached the target of 12.5% GDP. Midyear performance for FY09(Jan-Jun 2009)shows an 8% drop against budget; (b) A new Financial Systems Law, was enacted in May 2008, a more comprehensive 2009/2011 MTEF was developed, Budget Strategic Plans were developed for all ministries and further improvements were made to the presentation of the 2009 budget with more detailed information disclosed on the Domestic Capital Budget. In addition, more regular and comprehensive monthly fiscal reporting took place although the data was subject to frequent revision. A Fiscal Transparency plan for Extractive Industries was also developed; (c)the MEF pilot MBPI scheme was mainstreamed and extended to eight additional government entities including the Ministry of Health, based in part on the pilot work in MEF, the Council for Administrative Reform is also currently developing a new PAR program including set of HRM and HRD policies; (d)an integrated support program for the National Audit Authority has been agreed between government and Development Partners, full implementation however awaits further progress on commitments to publication of an Annual Audit Report (2006). IDA-H2410 Effective XDR TF Effective USD TF Closed USD Status of Projects in Execution - FY09

24 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 23

25 Sector: received Additional Financing during Project KH-EFA-FTI Catalytic Trust Fund (P109925) Cambodia 10-Apr Jun-2010 Primary education (71%); Pre-primary education (22%); Central government administration (5%); Sub-national government administration (2%) no To improve grade 1 right-age entry, net enrollment, retention, progression rates and grade 6 completion rates in primary education As a result of a slow start-up, the Project was still in too early a stage for meaningful progress. TF Effective USD Lending Information/Disbursement Summary (in millions USD) 24 Status of Projects in Execution - FY09

26 Sector: received Additional Financing during Project KH-Avian Influenza Emergency Project (P100084) Cambodia 24-Mar Dec-2011 Central government administration (49%); Agricultural extension and research (26%); Sub-national government administration (13%); Health (8%); Animal production (4%) no The objective is to reduce the threat of Avian Influenza infection in poultry and humans. The project became effective in August The Government has appointed core teams for implementing agencies at the national and provincial levels. These agencies are highly committed and very active in quality implementation of all of the project activities. There are no significant issues at present and although it is very early in implementation, it appears likely that the development objectives can be achieved. IDA-H3610 Effective XDR TF Effective USD TF Effective USD Status of Projects in Execution - FY09 25

27 Lending Information/Disbursement Summary (in millions USD) 26 Status of Projects in Execution - FY09

28 Sector: received Additional Financing during Project KH- RURAL INVESTMENT & LOCAL GOVERNANCE (P071146) Cambodia 22-Apr Feb Dec-2010 Sub-national government administration (30%); Central government administration (20%); General agriculture, fishing and forestry sector (20%); General water, sanitation and flood protection sector (15%); Roads and highways (15%) no The objectives are: (a) provide priority public goods and services at the commune level; and (b)strengthen decentralized and deconcentrated participatory local governance systems at the commune and provincial levels. There has been good progress. In 2008, project support to the Commune/Sangkat (C/S) Fund financed commune-level development priorities identified through the participatory commune planning process in over 1,100 communes in 23 provinces, principally for small-scale rural infrastructure. About the most popular choice was rural roads and road structures; the next most popular choices were small-scale irrigation, rural water supply and school buildings. All of these will provide priority public good and services at commune level. To strengthen local governance systems, project arrangements have been built into regular government structures, mechanisms and procedures. The principles, systems and procedures which the project has helped to establish for the C/S Fund apply to all communes in Cambodia. IDA Effective XDR IDA-H3260 Effective XDR TF Closed USD Status of Projects in Execution - FY09 27

29 Lending Information/Disbursement Summary (in millions USD) 28 Status of Projects in Execution - FY09

30 Sector: received Additional Financing during Project KH-Health Sector Support Project (P070542) Cambodia 19-Dec Oct Dec-2010 Health (80%); Non-compulsory health finance (10%); Central government administration (5%); Sub-national government administration (5%) no The objective of this project is to contribute to the improvement of the health status of the population by: (a) increasing the accessibility and the quality of health services; and (b) assisting the Kingdom of Cambodia to implement its Health Sector Strategic Plan and strengthen the sector's capacity to manage resources efficiently. The project is on track to meet most of its key indicator targets (including for communicable disease control and maternal health), as confirmed in the 2009 Joint Annual Performance Review. A few key indicators are lagging (notably malnutrition). Updated data are not yet available for child and maternal mortality, but should be forthcoming once the 2008 census data is analyzed. The project has supported the successful piloting and implementation of performance-based contracting in operational districts, as well as expansion of Health Equity Funds, which have increased access by the poor to tertiary care. IDA Effective XDR IDA-H0150 Effective XDR IDA-H0160 Effective XDR TF Closed USD TF Closed GBP Status of Projects in Execution - FY09 29

31 Lending Information/Disbursement Summary (in millions USD) 30 Status of Projects in Execution - FY09

32 Sector: received Additional Financing during Project KH-Cambodia Education Sector Support (P070668) Cambodia 12-May Nov Dec-2010 Secondary education (45%); Other social services (25%); Primary education (14%); General public administration sector (9%); Tertiary education (7%) no The project development objectives will support the National Poverty Reduction Strategy goals to expand access to educational services by addressing supply, demand, quality and efficiency constraints, especially focusing on the poorest and groups at risk. Outcomes have been positive on all project development objectives. To expand access, 224 lower secondary schools were constructed and the construction of 195 was completed in poor and underserved areas. In 2009, scholarships were provided to 18,999 students, of which 64% were girls. Transition rates in target schools are higher than expected and majority of those who stay until Grade 6 continue to Grade 7. Activities relating to leadership development decentralized school improvement and national assessment are well on target. The higher education components are moving forward toward meeting the project development objective, with slight delay in the expansion of the new library. IDA Effective XDR IDA-H1610 Effective XDR TF Closed USD TF Closed USD TF Effective USD Status of Projects in Execution - FY09 31

33 Lending Information/Disbursement Summary (in millions USD) 32 Status of Projects in Execution - FY09

34 Sector: received Additional Financing during Project KH-Second Health Sector Support Program (P102284) Cambodia 19-Jun Jun-2014 Health (44%); Central government administration (24%); Subnational government administration (24%); Other social services (4%); Compulsory health finance (4%) no To support the implementation of the Government's Health Strategic Plan to improve health outcomes through strengthening institutional capacity and mechanisms by which the Government and development partners can achieve more effective and efficient sector performance. The project was only effective from January 2009, so implementation is in the early stages. The Project provided financing for the 2009 Annual Operational Plans (AOP) to support priority activities in central Health directorates as well as all Provinces, and has also supported the transition of nine Operational Districts toward Internal Performance-Based Contracts, with capacity-building support from NGOs. A comparison of health management information system data from the first half of 2009 with the first half of 2008 shows that nearly all the maternal health service indicators have improved. The Project is financing the scaling up of Health Equity Fund (HEF) in coordination with other partners, which has significantly improved use of hospital services by the poor. The project's innovative coordination arrangements (involving seven donor partners) are also progressing well. IDA Effective XDR TF Effective USD Status of Projects in Execution - FY09 33

35 Lending Information/Disbursement Summary (in millions USD) 34 Status of Projects in Execution - FY09

36 Sector: received Additional Financing during Project KH-Land Management and Administration (P070875) Cambodia 26-Feb Oct Dec-2009 Central government administration (90%); Law and justice (5%); Tertiary education (3%); Other industry (2%) no The objectives are to improve land tenure security and promote the development of efficient land markets. The project has surveyed and adjudicated 1.4 million land parcels and continues to make progress toward its target of 1.55 million (approximately 90% complete with four months remaining before Credit closing). In addition 1.1 million titles have been issued to beneficiaries representing approximately 118% of the target value. The project has also made good progress in delivering expected legal and regulatory framework improvements and in strengthening capacity within the Ministry of Land Management to implement land titling activities. Canada now supports implementation of the same land titling and registration system in 3 provinces in addition to the 11 provinces under IDA support. The land titling program is making contributions to improve tenure security for title recipients and in developing efficient land markets; however recent rapid increases in land values have led to increased land conflicts and brought pressure on informal settlers occupying deemed state land in both urban and rural areas. Concerns have been raised with Government recently regarding issuance of a 99 year lease in Phnom Penh and ensuring proper implementation of the project environment and social guidelines. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09 35

37 Lending Information/Disbursement Summary (in millions USD) 36 Status of Projects in Execution - FY09

38 Sector: received Additional Financing during Project KH-PROV & PERI-URB WATER (P073311) Cambodia 22-Apr Jun-2010 Water supply (80%); Central government administration (15%); Sanitation (5%) no To assist the Kingdom of Cambodia to move forward in fulfilling the Millennium Development Goals in water supply and sanitation by At the original closing date of June 2008, the Government of Cambodia decided not to proceed with the provincial towns water component, being implemented by the Ministry of Industry, Mines and Energy. A restructuring plan was drawn up to move unallocated funds from that component to the periurban water supply component being implemented by the Phnom Penh Water Supply Authority (PPWSA). This restructuring was discussed in detail in FY09, but it remains to be finalized and formally approved. Progress in FY09 was limited to the PPWSA component, where activities continued to provide water connections to poor households on the outskirts of the city. The water program for the poor has reached over 16,000 families and the sanitation program has reached almost 1100 families. A feasibility study for construction of a water treatment plant and extension of network was completed, but it will be financed through other means. Overall, these project activities, although advancing rather slowly, will assist the government to meet its Millenium Development Goals in the water sector. IDA Effective XDR IDA-H0340 Effective XDR TF Closed USD TF Closed USD Status of Projects in Execution - FY09 37

39 Lending Information/Disbursement Summary (in millions USD) 38 Status of Projects in Execution - FY09

40 China Project Name(ID): Sector: received Additional Financing during Project CN-Liaoning Med. Cities (LMC) III (P099224) China 27-May Dec-2013 District heating and energy efficiency services (97%); Oil and gas (3%) no The project development objective is to assist Liaoning Province in improving the energy efficiency and environmental performance of heating and gas services in Project areas of the Project Cities. The project just became effective in November 2008, so implementation is still in the early stages. However, procurement of the three first subprojects is moving ahead and in some cases construction has started, with completion targeted for the 2009 heating season. Selection of the project management consultant is nearly complete as well. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 39

41 Sector: received Additional Financing during Project CN-Shanghai APL III (P096923) China 25-Jun Jun-2015 Water supply (74%); Sewerage (20%); Solid waste management (5%); Public administration- Water, sanitation and flood protection (1%) no To improve Shanghai's resource and environmental sustainability in the core and suburban areas The project was just approved on June 25, IBRD Not Effective USD Status of Projects in Execution - FY09

42 Sector: received Additional Financing during Project CN Xining Flood and Watershed Mgmt (P101829) China 02-Jun Dec-2014 Flood protection (60%); Other social services (20%); Public administration- Water, sanitation and flood protection (12%); Sewerage (8%) no The development objective of the project is to improve the protection of property and safety of people from flood events and bring about sustainable utilization of land and water resources within Xining Municipality. The PDO is to be achieved through the provision of (a) a greater level of flood protection and enhanced flood management; (b) improved wastewater collection; (c) improved soil and water conservation of catchments; and (d) institutional strengthening and capacity building in Xining Municipality. It is still at early implementation stage. Signing of legal documents took place in August, Effectiveness approval is undergoing. IBRD Not Effective USD Status of Projects in Execution - FY09 41

43 Sector: received Additional Financing during Project CN-W. Region Rural Water & Sanitation (P095315) China 26-Jun Sep-2012 Water supply (63%); Sanitation (27%); Sub-national government administration (5%); Other social services (5%) no To increase access of poor participating communities to sustainable and equitable water supply, sanitation and hygiene promotion services by adopting an integrated and participatory approach. Implementation of this project was partially interrupted in May 2008 by the Wenchuan Earthquake. The Project management office (PMO) was involved in the emergency rescue and reconstruction work in the months directly following the catastrophe. The PMO is now recovering and the management of this project is improving as seen by the fact that the pace of implementation is accelerating. Construction of the necessary water and sanitation facilities is underway to enable the project to meet the PDO of increasing access of water and sanitation services by the poor. The institutional components are also making progress and these will help ensure participation and ultimately sustainability. IBRD Effective USD TF Effective GBP Status of Projects in Execution - FY09

44 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 43

45 Sector: received Additional Financing during Project CN-Jiangxi Shihutang Navi & Hydropower (P101988) China 25-Sep Jun-2014 Ports, waterways and shipping (60%); Renewable energy (40%) no The development objective (PDO) of the proposed project is to improve utilization of the Gan River for more reliable freight transport and for cleaner energy production through: (a) improving inland waterway transport capacity and service levels for primary and secondary industries in the Nanchang- Ganzhou corridor of the Gan River; and (b) generating renewable electricity to help meet rapidly growing demand for energy in the region. The project was launched in April The implementation of the project has been progressing smoothly towards achieving its development objectives. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) 44 Status of Projects in Execution - FY09

46 Sector: received Additional Financing during Project CN-4th Inland Waterways (P077137) China 25-Mar Jun-2011 Ports, waterways and shipping (65%); Renewable energy (15%); Power (10%); Sub-national government administration (10%) A loan reallocation was done on the Guangdong Component (Part B) in late June A loan extension was given to Guangdong Component in late July 2009 as the Guangxi Component will be closed on schedule (Jan.31,2010). To assist the Borrower in (1) improving market access for its southern region by upgrading navigation conditions on the region 's major east-west river and other waterways feeding traffic into the Zhujiang River Delta region; and (2)meeting the growing energy demand in Guangdong and Guangxi by harnessing water flow in two rivers in such region to generate environmentally clean electricity. The project has continued to make progress towards achieving its development objectives. For the Guangxi Component, the traffic between Baise-Nanning was lower than the planned because the vessels could not navigate throughout the corridor due to the on-going channelization works. For the Guangdong Component, some of the intermediate indicators in terms of implementation progress lagged behind the original schedule due to various causes such as extraordinary floods and low capacity of some contractors. The implementing agency has been taking solid steps to strengthen contract management and to accelerate the implementing progress. In general, project implementation is making progress. IBRD Effective USD Status of Projects in Execution - FY09 45

47 Lending Information/Disbursement Summary (in millions USD) 46 Status of Projects in Execution - FY09

48 Sector: received Additional Financing during Project CN-Han River Urban Environment (P087224) China 29-Apr Jun-2014 Sewerage (59%); Solid waste management (37%); Subnational government administration (4%) no To reduce urban pollution generated from wastewater and solid waste through proper collection, treatment and disposal in selected second-tier cities, mainly located in the Han River area of Hubei This project just became effective in September Implementation of the works necessary to reduce urban pollution is somewhat behind schedule due a number of factors: instances of preliminary designs and drawings being inconsistent with feasibility studies approved by the Bank; delays in preparation of good quality bidding documents; site changes for a few civil works; and resettlement needing to be carried out before works can begin. International technical assistance mobilized in February 2009, so management of the project should proceed more smoothly and the PDO should be achievable. IBRD Effective USD Status of Projects in Execution - FY09 47

49 Lending Information/Disbursement Summary (in millions USD) 48 Status of Projects in Execution - FY09

50 Sector: received Additional Financing during Project CN-Jiangsu Water and Wastewater Project (P096926) China 02-Jun Dec-2014 Sewerage (50%); Water supply (49%); Public administration- Water, sanitation and flood protection (1%) no To improve the efficiency and effectiveness of water and wastewater services and reduce pollution discharges to local rivers in Jiangsu Province The project is not yet effective. IBRD Not Effective USD Status of Projects in Execution - FY09 49

51 Sector: received Additional Financing during Project CN- Bengbu Integrated Environment Improv (P096925) China 11-Mar Jun-2014 Flood protection (50%); Sewerage (25%); General water, sanitation and flood protection sector (11%); Roads and highways (10%); Sub-national government administration (4%) no To improve the effectiveness and sustainability of selected urban environmental services delivered in Bengbu Municipality. Good progress is being made in the preparation of detailed designs and bidding documents. A few contracts have been awarded and a significant number of contracts should be awarded in the first six months of FY10. These activities will allow the project to improve service delivery. The capacity building work is also well underway. The Project Management Office is staffed with general management officers and clerical staff, but needs additional technical specialists to perform its tasks more efficiently. It is still early in implementation, but the project is moving well toward meeting its PDO. IBRD Effective USD Status of Projects in Execution - FY09

52 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 51

53 Sector: received Additional Financing during Project CN-Xi'an Sustainable Urban Transport (P092631) China 24-Jun Jun-2015 Roads and highways (50%); General transportation sector (26%); Other social services (15%); Sub-national government administration (9%) no The objective is to improve transport accessibility and mobility in Xi'an Municipality while protecting its cultural heritage and reducing the environmental impact of the urban transport system. The project has overcome a few early implementation issues and is now progressively satisfactorily will be the first year of reporting results indicator but, nonetheless, it is expected the project will achieve its development objectives. IBRD Not Effective USD Status of Projects in Execution - FY09

54 Sector: received Additional Financing during Project CN-Fuzhou Nantai Island Peri-Urban Dev (P070519) China 15-Dec Jun-2011 Roads and highways (87%); General transportation sector (10%); Sub-national government administration (3%) no The objective of the project is to support sustainable peri-urban development in Fuzhou (as it expands to include Nantai Island) by providing strategic transport infrastructure and by strengthening the city's decision support system on land development and management. Good progress was made towards reaching the PDO in FY09 with the signing of contracts worth some $250 million. Construction under the strategic road component is advancing well with Phase I of the Nan Jiang Bin Lu road complete and Phase II underway. Construction is also underway on the Third Ring Road and the Kuiqui Bridge. Under the public transport component, preliminary designs for the Jinshan Depot (and the associated terminal and dispatch center) are complete but implementation is slow due to resettlement difficulties. Activities under both these components will support peri-urban development in Fuzhou by providing strategic transport infrastructure. Under the technical assistance (TA) component, the port development report is nearly complete, while contracts for several other key TAs (bus priority assessment, long-range public transport development) are being negotiated. Mobilization of consultants should take place in FY10. Once these TAs are completed, they will help strengthen the city's decision support system on land development and management. IBRD Effective USD Status of Projects in Execution - FY09 53

55 Lending Information/Disbursement Summary (in millions USD) 54 Status of Projects in Execution - FY09

56 Sector: received Additional Financing during Project CN-Liaoning Medium Cities Infrastructure (P099992) China 27-Jun Dec-2011 Roads and highways (70%); General transportation sector (16%); Sanitation (14%) no To assist the Borrower's Project Cities in enhancing: (i) the performance and quality of their existing urban transport infrastructure in terms of mobility, access, and safety; (ii) the efficiency and effectiveness of their urban public transport and road maintenance services; and (iii) the responsiveness of their urban transport systems to the needs of population without access to private motorized vehicles. Good progress was made towards reaching the PDO in FY09. Work has been completed on 15 works contracts and is ongoing on 19 other works contracts. In total, contracts for physical works, mostly road works of about US$220 million, have been completed. Over the course of the year, the project cities have significantly strengthened their attention to the needs of vulnerable road users including pedestrians and cyclists. Procurement is currently underway for 13 works contracts worth about US$80 million. These include key elements of the public transport investments in all the project cities. Additionally, procurement is underway for the equipment related to the traffic safety and road maintenance components. Contracts have also been signed and work has started for technical assistance activities related to public transport and road safety. Together these activities are helping the project cities to improve the performance and quality of their existing urban transport infrastructure in terms of mobility, access, and safety; and the responsiveness of their urban transport systems to the needs of the population without private motorized vehicles. Additionally, the cities are being encouraged to move from city-owned companies for executing road maintenance works to relying on competitive processes for road maintenance. This is supporting the cities to improve the efficiency and effectiveness of their road maintenance services. IBRD Effective USD Status of Projects in Execution - FY09 55

57 Lending Information/Disbursement Summary (in millions USD) 56 Status of Projects in Execution - FY09

58 Sector: received Additional Financing during Project CN-GEF-Termite Control Demonstration (P082992) China 29-Jun Dec-2010 Housing construction (64%); Central government administration (16%); Sub-national government administration (16%); Petrochemicals and fertilizers (4%) no The objective is to mitigate environmental and health risks associated with the use of chlordane and mirex in termite control by: (a) demonstrating the elimination of their use through the introduction of integrated pest management (IPM) in selected areas; and (b) preparing a national replication program for the complete phase-out of the use of chlordane and mirex in China by Progress toward meeting the PDO is on track. The project has produced a 60% drop in the use of chlordane and mirex (C&M) for termite control in the demonstration areas. Consultants have been selected to begin work on the comprehensive policy, regulatory and institutional reforms to be drawn up under the project. The closure and clean-up of the Liyang Guanghua Chemical Company will not take place as the company withdrew from the project; however environmental assessments of eight other C&M producers have been completed and one will be selected to take its place. The first batch of termite bait systems has been installed and has proved an effective alternative to chemical C&M systems, demonstrating the viable use of integrated pest management (IPM). Nearly 2000 technicians from termite control stations in the three project provinces (Jiangsu, Anhui, and Hunan) have been trained in IPM to ensure sustainability. A proposal for the development of a national replication program has been developed and will be considered in FY10. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 57

59 Lending Information/Disbursement Summary (in millions USD) 58 Status of Projects in Execution - FY09

60 Sector: received Additional Financing during Project CN-GEF-PCB Mgnt & Disposal (P082993) China 15-Dec Jun-2010 Other industry (57%); Solid waste management (33%); Subnational government administration (6%); Central government administration (4%) no The objective of the project is to identify and demonstrate environmentally-sound and cost-effective policies, procedures and techniques for safely managing and disposing of China's temporarily-stored polychlorinated biphenyl (PCBs) and associated PCB-contaminated wastes. Progress toward meeting the PDO is proceeding reasonably well. Provincial PCB guidelines have been completed and national guidelines will be drawn up next which together will result in environmentally sound and cost-effective policies. PCB burial sites in Zhejiang have been identified and equipment for their excavation is under procurement. Procurement of a thermal desorption unit to safely treat soils contaminated with PCBs in Zhejiang is complete, but installation is not yet underway, pending the resolution of social issues near the work site. The upgrading of a PCB incinerator in Shenyang is complete, and a trial burn is scheduled for September Once the trials are successfully completed, excavation of PCB burial sites in Zhejiang may begin. These activities, upon completion, will demonstrate effective procedures and techniques for safely managing and disposing of China's PCB waste. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 59

61 Lending Information/Disbursement Summary (in millions USD) 60 Status of Projects in Execution - FY09

62 Sector: received Additional Financing during Project CN-SICHUAN URBAN DEV (P083322) China 07-Sep Dec-2013 Roads and highways (67%); Flood protection (14%); Sewerage (13%); General agriculture, fishing and forestry sector (4%); Other social services (2%) no The project is to improve core urban functions in an equitable and resource efficient manner by removing identified infrastructure bottlenecks hampering land development, transport, and environmental conditions in four second-tier cities in Sichuan Province. Progress was slow in fiscal year 2009 due to the catastrophic earthquake that struck Sichuan Province in May The project 's implementing agencies all had to shift their priorities away from the project toward the recovery and rehabilitation efforts. The Province suffered a fiscal imbalance caused by the expenses related to the emergency work which resulted in counterpart funding issues for this project. The cost of construction materials and goods increased due to the huge demand imposed by the quake. Capacity shortages among local construction companies occurred. The land development component has suffered reductions in demand for land and depressed prices. All these conditions adversely affected implementation progress, The implementing agencies are now starting to recover from the demands imposed by the earthquake. Some restructuring of the project may be necessary, but the Province is still committed to the PDO, and the project is still expected to reach its PDO without major delays. IBRD Effective USD Status of Projects in Execution - FY09 61

63 Lending Information/Disbursement Summary (in millions USD) 62 Status of Projects in Execution - FY09

64 CN-ShiZheng Railway (P099062) China 24-Jun Dec-2013 Sector: Railways (100%) received Additional Financing during no The objective is to meet growing freight and passenger market demand in the railway corridor between Shijiazhuang and Project Zhengzhou, while substantially improving the level of service offered to customers. The early implementation progress of the project is very good, spurred on by the economic stimulus program of China. Contracts for civil works for all five contract sections of the corridor have been awarded and construction started in October 2008 and is progressing well. Although it is still early, indications are that the development objective will be met. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 63

65 Sector: received Additional Financing during Project CN-Anhui Highway Rehab & Improvement (P099112) China 22-Apr Jun-2012 Roads and highways (99%); Sub-national government administration (1%) no The project aims to increase the effective use of the road infrastructure in the Anhui Province to support its social and economic development, as evidenced by the increase in the flows of passenger and freight traffic along key corridors across the province at lower costs and with improved safety. The project was signed on Aug. 8, 2008 and became effective on Nov. 6, Overall values for performance indicators are moving along the expected trends. However, it is too early to make a full assessment of the effective progress towards achievement of the PDO as no works have been completed. For those indicators related to institutional development actions, terms of reference have been agreed upon and consultants are being selected, and the task team is closely monitoring and supporting the implementation. IBRD Effective USD Status of Projects in Execution - FY09

66 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 65

67 Sector: received Additional Financing during Project CN-Gansu Cultural & Natural Heritage (P091949) China 20-Mar Dec-2013 Other social services (55%); General transportation sector (29%); General water, sanitation and flood protection sector (10%); Solid waste management (3%); General public administration sector (3%) no The project development objective is to generate benefits for local communities from the development of sustainable cultural tourism in Gansu Province. As of end June, this project had been effective for nine months, but implementation was delayed by the Wenchuan Earthquake which struck Gansu Province as well as Sichuan Province. Consequently, the project launch workshop was postponed until late March So far the project is making progress, but is being somewhat hampered by a lack of high quality bidding documents. The capacity of the provincial management office requires strengthening in order to draft solid design proposals and good quality bid documents. These are necessary to start the construction work required to develop tourism in the province in a sustainable manner. IBRD Effective USD Status of Projects in Execution - FY09

68 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 67

69 CN-MSE Finance (P096285) China 19-Jun Jun-2011 Sector: Micro- and SME finance (95%); Banking (5%) received Additional Financing during no Project The project development objective is to expand credit flows to MSEs on a mass-market and commercially sustainable basis. development objective is substantial. The total outreach expanded to 60,000 micro borrowers, disbursed 95% of the IBRD loan funds under the project, with the actual non performing loan of less than 1%. A number of participating financial intermediaries (PFIs) have internalized the MSE lending technologies. The project has contributed to the sustainable institutional development of the PFIs. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) 68 Status of Projects in Execution - FY09

70 CN-GEF-NINGBO WATER & ENVMT (P090336) China 29-Jun Feb Dec-2010 Sector: General water, sanitation and flood protection sector (100%) received Additional Financing during no To reduce land-based pollution along the Cixi coast and the Project East China Sea, promote the replication of innovative low cost wastewater treatment techniques, and encourage coastal zone conservation. Good progress on implementation is being maintained with almost all contracts having been awarded. Works under the Cixi Wetlands Restoration Project are scheduled for completion by grant closing. Restoration works have commenced at the natural wetlands. These works will help reduce land-based pollution. The construction of the Wetlands Visitor/Education Center is scheduled to commence shortly and this center should educate the public about coastal zone conservation. The only issue of concern is a proposal for land reclamation at Cixi Wetlands. The city government is considering a proposal to reclaim the newly developed mudflats for flood protection purposes. The Cixi Wetland Management Company has agreed to carry out an environmental impact assessment and a hydraulic study to investigate potential adverse impacts. Ningbo Municipal Government should consult with the Bank before making a decision to proceed with the proposal. Otherwise, the project is well positioned to achieve its DO by grant closing. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 69

71 Lending Information/Disbursement Summary (in millions USD) 70 Status of Projects in Execution - FY09

72 Sector: received Additional Financing during Project CN-Fujian Highway Sector Investment (P091020) China 12-Oct Jun-2012 Roads and highways (99%); Sub-national government administration (1%) no The project aims to increase the effective use of the road infrastructure in Fujian Province to support its social and economic development. This objective seeks to contribute to: (i) improving living conditions in rural areas-particularly those in the areas of the Province where poverty rates are higher-by enhancing the transport accessibility of the rural communities to economic opportunities and social services; (ii) stimulating higher economic growth in Fujian Province by reducing transport costs; and (iii) facilitating the interconnection across the coastal provinces. The PDO is, based on current achievements, likely to be achieved, as the interim outcomes are mostly consistent with the intended outcomes. This is supported by project implementation, which is progressing satisfactorily with the works under the Rural Roads component completed and the major earthworks, bridge and tunnel contracts on the Yong'an- Wuping Expressway more than 85% complete. An evaluation of the outcomes of the Rural Roads Program is currently underway and detailed results would become available during the next reporting period. IBRD Effective USD Status of Projects in Execution - FY09 71

73 Lending Information/Disbursement Summary (in millions USD) 72 Status of Projects in Execution - FY09

74 Sector: received Additional Financing during Project CN - GEF-Hai Basin Integr. Wat. Env.Man. (P075035) China 15-Apr Dec Dec-2010 Sewerage (35%); Central government administration (35%); Sub-national government administration (15%); Irrigation and drainage (15%) no The objective is to catalyze an integrated approach to water resource management and pollution control in the Hai Basin in order to improve the Bohai Sea environment. The project continues to make progress toward achieving its development objective. With the capacity building of the national experts and officials, the Ministry of Water Resources (MWR) and Ministry of Environment Protection (MEP) as well as other local implementing agencies are now able to use the integrated water and environment management approach for water resources management and pollution control in the Hai Basin. Improvements are being seen in many areas, particularly: (a) improved cooperation between MWR, MEP, river basin authority, municipal/ provincial and county governments; (b) enhanced data and information sharing among the related implementing agencies; and (c) reduced waste-water discharges from cities and counties to the Bohai Sea. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 73

75 Lending Information/Disbursement Summary (in millions USD) 74 Status of Projects in Execution - FY09

76 Sector: received Additional Financing during Project CN-3rd Xinjiang Hwy Project (P058847) China 05-Sep Dec-2009 Roads and highways (94%); Sub-national government administration (6%) no To improve transport infrastructure and sector governance in support of social and economic development in Xinjiang Uygur Autonomous Region. All PDOs are already reached and surpassed. Overall, the progress toward achievement of the PDO is considered satisfactory. The Bank has added value in many areas such as stimulating the economy along the highway, raising awareness and building capacity on road safety, and enhancing the road agency's asset management skills. The overseas training program under the IDRP of this Project has lagged behind for many reasons. These training were carefully selected at the Appraisal time to build the capacity and invite international best practices to Xinjiang. The project has been extended for two years in order to complete these remaining training activities and small amount of civil works remained from the Local Road Program. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 75

77 Lending Information/Disbursement Summary (in millions USD) 76 Status of Projects in Execution - FY09

78 Sector: received Additional Financing during Project CN-Tec Coop Credit IV (P042299) China 18-May Dec-2009 Central government administration (50%); Sub-national government administration (50%) no The objective of the project is to provide continued support to the Government of China in its economic and structural reform effort, help capacity building and improve the project preparation. The project is close to completion. Out of the 44 approved subprojects, 38 have been closed. The remaining 6 have achieved satisfactory results in FY09. It is expected that the PDOs will be fully achieved when the 6 subprojects conclude their implementation in a few months. IBRD Effective USD IDA Effective XDR TF Closed GBP Status of Projects in Execution - FY09 77

79 Lending Information/Disbursement Summary (in millions USD) 78 Status of Projects in Execution - FY09

80 CN-NanGuang Railway (P112359) China 24-Jun Dec-2014 Sector: Railways (100%) The objective is to provide additional transport capacity and Project reduce transport time between the less developed western region in southwest China and the relatively more developed Pearl River delta region. The project is not yet effective. The early implementation progress of the project has exceeded expectations with resettlement and land acquisition moving forward rapidly. Some construction activities have begun. Transport demand between the two regions remains strong. Early indications are that the project will achieve its development objectives. IBRD Not Effective USD Status of Projects in Execution - FY09 79

81 CN-Shanxi Coal Bed Methane Development (P100968) China 19-May Dec-2014 Sector: Power (99%); Public administration- Energy and mining (1%) received Additional Financing during no The development objective of the project is to increase the production and utilization of CBM/CMM to replace coal as fuel Project for thermal use and to reduce GHGs and local air pollutants associated with coal combustion. The project was approved on May 19, The legal documents were signed on July 2, The effectiveness is expected in September IBRD Not Effective USD Status of Projects in Execution - FY09

82 Sector: received Additional Financing during Project CN-Rural Health (P084437) China 24-Jun Dec-2013 Compulsory health finance (36%); Central government administration (32%); Health (27%); Sub-national government administration (5%) no To provide increased and more equitable access to quality health services, improved financial protection, and better management of public health threats in pilot provinces and counties, with lessons to support reforms in non-project areas. The project has made encouraging progress towards its objectives in the first six months of its implementation. All forty county proposals have been prepared and subsequently reviewed; and the first batch of project counties have started the implementation and the overwhelming majority are ready to implement the first year activities in the key reform areas (health financing, service delivery and core public health services). The Central Government of China issued on 17 March 2009 its Opinion on Deepening the Health Care System Reform, which defined the overall goals, principles and contents of health care system reform from 2009 to The government recognized that the design of the project is highly in line with the national policies. Officials from the Ministry of Finance and Ministry of Health stressed the significance of the project in providing experience of health reform and raised specific questions to be answered by the project through innovations and pilot programs. County and provincial participants will need to provide flexibility to reflect ongoing reform priorities and local needs. IBRD Effective USD TF Closed USD TF Effective GBP Status of Projects in Execution - FY09 81

83 Lending Information/Disbursement Summary (in millions USD) 82 Status of Projects in Execution - FY09

84 Sector: received Additional Financing during Project CN-TIANJIN URB DEV II (P040599) China 20-May Sep Jun-2011 Sewerage (45%); Sub-national government administration (25%); General transportation sector (20%); Flood protection (10%) no To enhance the efficiency and equity of urban wastewater management and transportation systems, and thus facilitate the sustainable development of Tianjin and serve as a model for other cities in China. Progress toward meeting the Project Development Objectives improved during FY09. The outputs completed include rehabilitation of sections of the Dagu Canal within the city limits, thus improving the environment around those sections. Completion of the hazardous waste landfill will allow safe disposal of hazardous sludge from the city canals. For wastewater treatment, one of the plants is 50% complete while the other is at feasibility stage after its location was changed. These plants, upon completion, will enhance wastewater management. In the roads sector, road rehabilitation works are ongoing and bidding for a bus depot is underway. These works will enhance the city's transportation systems. Also, recommendations from the transport and drainage sector studies have already prompted major initiatives to restructure these two sectors to improve their effectiveness and efficiency. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 83

85 Lending Information/Disbursement Summary (in millions USD) 84 Status of Projects in Execution - FY09

86 Sector: Project CN-Eco-Farming (P096556) China 02-Dec Jun-2014 Renewable energy (70%); Crops (20%); Agricultural extension and research (10%) The objective is to deliver direct environmental and economic benefits from the integration of biogas in farming and cooking in rural households. In addition, the project aims to reduce greenhouse gas emissions through methane combustion and reduced burning of coal and firewood in the project areas. The project had just become effective before the close of the reporting period. IBRD Not Effective USD IBRD Not Effective USD Status of Projects in Execution - FY09 85

87 Sector: received Additional Financing during Project CN-SHANDONG ENVMT 2 (P077752) China 27-Feb Mar Dec-2013 Sanitation (77%); Water supply (13%); Solid waste management (9%); Sub-national government administration (1%) no The project development objective is to improve the environmental conditions in participating municipalities and counties. The Global Environment Objective of the GEF activity is to reduce land-based pollution along the Yantai coast and the Bohai Sea through development of a pilot septic-tank management system in Yantai and dissemination of the Yantai model in Shandong Province and in other parts of China. At the midterm review conducted in March 2009, progress toward meeting the PDO was smooth. Water supply access is rising as expected as are volumes of treated wastewater. Solid waste collected and transferred to sanitary landfills is 95% of the end of project target already. These activities will help improve environmental conditions in the participating municipalities and counties. Water and wastewater tariffs were adequate to meet operating expenditures in 2008, to ensure sustainability. With regards to the GEF DO, the GEFfinanced component in Yantai has begun and implementation is going well. Upon completion, the volume of sewage collected and treated is expected to meet targets for success. IBRD Effective USD Status of Projects in Execution - FY09

88 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 87

89 Sector: received Additional Financing during Project CN-HENAN TOWNS WATER (P081348) China 27-Jun Jun-2013 Water supply (77%); Sanitation (9%); Sewerage (9%); Subnational government administration (5%) no Create or expand water supply and wastewater management services and improve the planning, regulatory, and operational capacity of sector institutions. Works to create or expand water supply and wastewater services are underway although implementation is significantly slower than planned at appraisal, mostly due to slow preparation of detailed designs and bidding documents. Originally 38 counties were to participate in the project; however six dropped out leaving available US$35 million from the IBRD loan. Discussions on how to use these funds to enhance project impact are ongoing. Delays in mobilizing technical assistance (TA) for project management and for improving utility operations are slowing progress on the project objective to better the planning, regulatory and operational capacity of the sector. Once these key TAs are in place, management should improve and overall progress toward meeting the PDO should accelerate. IBRD Effective USD Status of Projects in Execution - FY09

90 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 89

91 Sector: received Additional Financing during Project CN-LIUZHOU ENVIRONMENT MGMT (P081346) China 24-May Jan Jun-2011 Sewerage (88%); Sanitation (5%); Solid waste management (5%); Sub-national government administration (2%) no To sustainably improve the environmental conditions in Liuzhou through improved wastewater treatment, sanitation control, and solid waste management. Implementation is progressing well. The wastewater component, accounting for 90% of the Bank loan, is about one year ahead of schedule and the assets constructed are of good quality. The industrial pollution control component has achieved its targets. These will contribute greatly to improving the environmental conditions in Liuzhou. The public toilet and solid waste management components are about one year behind schedule due to difficulties with land acquisition, resettlement and objections of neighborhoods in affected areas. Some key adjustments have been made recently and it is expected that the solid waste component will be able to make up time. The municipal government has approved a wastewater tariff adjustment which will improve the financial situation of the Liuzhou Municipal Wastewater Company, but further increases will be necessary to ensure the sustainability of the Company. The water quality of the Liujiang River in recent months has been between Class II and III of the stipulated surface water standards which is better than the original target of Class III standards at the four monthly river water quality monitoring points. IBRD Effective USD Status of Projects in Execution - FY09

92 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 91

93 Sector: received Additional Financing during Project CN-Changjiang/Pearl River Watershed Reha (P081255) China 27-Jun Jun-2012 Forestry (23%); Crops (22%); Irrigation and drainage (20%); Animal production (20%); Flood protection (15%) no The objective of the project is to improve the livelihoods of farmers and to protect the environment in poor and highlydegraded watersheds of the Changjiang and Pearl River Basins. The prospect of achieving the project development objective depends on revising the project scope as soon as possible. Significant input price increases and the depreciation of the US dollar against the Chinese Yuan since project appraisal have seriously impacted the project, requiring a reduction of scope (as unit prices would have to be increased). The scope of the project will have to be reduced by about 30% in terms of the number of watersheds and number of beneficiaries. It is anticipated that the intended demonstration effects of integrated watershed management and its potential scaling-up would remain even after a reduction in scope. Meantime, activities in most of the first batch watersheds have been completed and activities have started in the second batch of watersheds. IBRD Effective USD TF Closed USD TF Effective EUR Status of Projects in Execution - FY09

94 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 93

95 Sector: received Additional Financing during Project CN-CHONGQING SMALL CITIES (P081161) China 21-Jun Jun-2012 Water supply (35%); Roads and highways (33%); Flood protection (21%); Sanitation (8%); Sub-national government administration (3%) The restructuring created a new component to carry out the preparation of a proposed Chongqing Urban Rural Integration Project using unallocated Loan proceeds of US$1.2 million. The project development objective is to support emerging small cities to improve the efficiency and effectiveness of infrastructure service delivery, to accommodate the rapid urban growth. Project implementation is progressing modestly. The project is supporting improvements to infrastructure service delivery through (a) water supply investments (58% complete); (b) flood protection works (57% complete); road construction (39% complete); and public sanitation (59% complete). Efficiency and effectiveness of the investments are being reinforced through the institutional component. IBRD Effective USD Status of Projects in Execution - FY09

96 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 95

97 Sector: received Additional Financing during Project CN-ZHEJIANG URBAN ENVMT (P066955) China 29-Jan Jun Jun-2010 Sewerage (35%); Roads and highways (25%); Other social services (25%); Solid waste management (10%); Water supply (5%) The goal of the restructuring was to utilize project loan savings to support additional investments in line with the original project development objectives. The specific additional investments include the rehabilitation of the Yue Kingdom cultural heritage site in Shaoxing Municipality. To enhance the efficiency and equity of waste management in Ningbo (wastewater)and Hangzhou (solid waste) municipalities and redevelop the historic city centers of Shaoxing and Cicheng. Good progress continues to be made toward meeting the project's development objective. Physical implementation in all three project cities is progressing well and significant technical assistance activities have been implemented. The redevelopment of the historic inner city of Shaoxing is advanced (including the additional investments financed through restructuring) while corresponding developments under a smaller component in Cicheng are behind schedule. In Ningbo, two large wastewater treatment plants and associated sewage networks are complete, thereby enhancing wastewater management. The expansion of Hangzhou landfill is also well advanced which will enhance efficiency in the solid waste sector. A further restructuring is expected in FY10 to utilize loan savings in the Ningbo component. An extension of the closing date may be necessary to complete any additional works. IBRD Effective USD TF Closed USD TF Closed USD Status of Projects in Execution - FY09

98 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 97

99 Sector: received Additional Financing during Project CN-2nd GEF Energy Conservation (P067337) China 24-Oct May Jun-2010 District heating and energy efficiency services (91%); Noncompulsory pensions, insurance and contractual savings (7%); Central government administration (2%) no To expand domestic investment in energy efficiency projects through the aggressive development of China's nascent Energy Management Company (EMC) industry, thereby achieving large-scale energy efficiency improvements and associated reductions in the growth of carbon dioxide emissions and other pollutants. The key indicators of success in achieving the Project Development Objectives (PDOs) are the total annual energy efficiency investments generated by Energy Management Companies (EMC), and the associated annual energy savings and reductions in carbon dioxide emissions. The progress toward meeting the PDOs continues to be satisfactory; the Project is meeting or exceeding the key performance indicators. In 2008, the total investments on Energy Performance Contract (EPC) projects in China reached at least USD1.5 billion, yielding about 67 million tce of energy savings over the lifetime of the projects and about 48 million tons of CO2 emission reductions. The Project has also built the capacity of the China Energy Conservation Service Industry Association (EMCA) as a training institution and focal point for the growing EMC industry in China. TF Effective USD Status of Projects in Execution - FY09

100 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 99

101 Sector: received Additional Financing during Project CN-SHANGHAI URB ENVMT APL1 (P070191) China 17-Jun Apr Mar-2010 Sewerage (73%); Solid waste management (20%); Subnational government administration (7%) no The project is to put in place some of the underpinnings and enabling conditions to pursue an integrated, metropolitan-wide approach for managing the urban environment, and to install, in both the city center and districts, facilities already known to be high priority to achieve metropolitan-wide environmental objectives. The civil works necessary to achieve metropolitan-wide environmental objectives are nearing completion and all should be done by the end of Tariff increases to ensure sustainability of the sector have been made for industrial and commercial customers, but tariff increases are pending for residential customers. On institutional reforms, the Shanghai Municipal Sewerage Company is in the process of merging with all its operating subsidiary companies at district level into a single company (except for wastewater treatment operations) to increase efficiency. Shanghai Municipal Government has adopted service contracting and bidding arrangements for solid waste operations in the city. The project is expected to meet its PDO overall. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

102 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 101

103 Sector: received Additional Financing during Project CN - Agricultural Technology Transfer (P069862) China 28-Apr May Dec-2010 Agricultural extension and research (45%); Agricultural marketing and trade (25%); Agro-industry (20%); Information technology (5%); Other social services (5%) no The objective of the project is to develop and test innovative models for agricultural technology transfer and application aimed to generate additional farm income in high-value markets with a potential for scaling- up. The project aims to give poor farmers the opportunity to participate in high-value agricultural markets, both domestically and internationally. The Project is on track toward meeting its development objectives. It has about 120 sub-projects under implementation covering many different aspects of technology and institutional innovation. There have been interesting technological innovations introduced under the project. Some examples include shared production facilities for dairy and poultry for small scale farmers; cooperatives for farm machinery, input supply and marketing; food safety at fresh produce markets; promotion of long term investments in tree crops; field production methods for herbal medicine production to preserve wild species; breeding program and brand name improvement for indigenous livestock species; and use of alternative energy sources for greenhouse production. Some of the key lessons learned from the project on the process of managing and monitoring a competitive grant facility have been incorporated into the government s own investment programs. The implementing agency for this project in collaboration with WBI is expected to hold an international workshop next year to disseminate the lesson learned from the project to other countries. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

104 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 103

105 CN-Guizhou-Guangzhou Railway (P107559) China 16-Apr Dec-2015 Sector: Railways (100%) received Additional Financing during no The objective is to provide additional transport capacity and reduce transport time between the less developed western Project region in southwest China and the relatively more developed Pearl River delta region. The project implementation is progressing rapidly with most of the resettlement and land acquisition completed and a majority of the construction underway. Though early, the project is expected to achieve its development objective. IBRD Not Effective USD Status of Projects in Execution - FY09

106 CN-Yixing Pumped Storage Project (P068058) China 20-Mar Dec-2010 Sector: Power (97%); Sub-national government administration (3%) received Additional Financing during no The proposed project is to increase the overall efficiency of the power sector in Jiangsu Province in two ways: (a) through the design and implementation of a far-reaching restructuring of the sector to further competition at the generation level and to provide large consumers access to generators; (b) through Project the construction of a pumped storage plant and associated transmission in Yixing to ease acute peaking problems and improve generation mix that would create the conditions for more flexible dispatch and improved supply reliability, an essential requirement for well-functioning competitive markets. The implementation of the pumped storage component has progressed satisfactorily. Despite a major delay in delivery of equipment and a number of technical defects in the equipment, the project implementing agency (JPSPC) managed to commission four units of the Yixing pumped storage power plant in June 2009, only slightly behind the schedule. However, as more time is needed to test the equipment and eliminate all technical defects, more time is required to disburse the remaining loan proceeds. Therefore, the Bank has extended the closing date of the loan by one year at the request of the Ministry of Finance. Progress in design and implementation of competitive power market is less satisfactory due to several reasons. Since the project appraisal in 2003, China suffered acute power shortages which made it impossible to introduce a real competition. Also China piloted a sort of power market at the regional level which delayed the introduction of an integrated competitive power market. The reform actions already implemented in China (full separation of generation from the network business, more efficient pricing, strengthened institutional capacity, spinning of non-core businesses) have created some competitive pressure among generators to improve efficiency. In addition, JPSPC has adopted many policies and measures to improve the efficiency of the power supply system. Therefore, almost all outcome indicators are achieved through these actions. As it is unlikely that China will have a full-flagged power market any time soon, some subcomponents of the project will need to be cancelled. This would not affect project objectives, as many actions to improve efficiency of power supply have been successfully Status of Projects in Execution - FY09 105

107 implemented and the project development objective is likely to be met. IBRD Effective USD TF Closed USD Lending Information/Disbursement Summary (in millions USD) 106 Status of Projects in Execution - FY09

108 CN-Renewable Energy II (CRESP II) (P096158) China 07-Feb Sep-2010 Sector: Renewable energy (100%) received Additional Financing during no The objective is to demonstrate early success in large-scale, renewable energy development with participating local Project developers in one pilot autonomous region and one pilot province. The project is progressing well toward achieving its development objectives. Under the Zhejiang small hydropower component, 13 out of 16 small hydropower subprojects have been completed, including rehabilitation of 8 existing small hydropower plants and construction of 5 small hydropower plants. The remaining three sub-projects will be completed by the end of The 100 MW Huitengxile wind farm component overcame the initial institutional and procurement difficulties, which delayed contracting. Finally, all contracts were signed about two years after the project became effective. The turbine supply contract was signed on February 27, Construction is expected to start in August 2009 and the project should be completed by mid Therefore, an extension of the closing date, which is currently September 30, 2010, will be required to complete the Huitengxile Wind Farm project. IBRD Effective USD Status of Projects in Execution - FY09 107

109 Lending Information/Disbursement Summary (in millions USD) 108 Status of Projects in Execution - FY09

110 CN-Guangxi Integrated Forestry Dev (P088964) China 14-Dec Dec-2012 Sector: Forestry (94%); Sub-national government administration (6%) received Additional Financing during no The objective is to improve the effectiveness of forest management and institutional arrangements in timber Project production, watershed protection and nature reserve management in selected areas of the Guangxi Zhuang Autonomous Region. The project has continued to make progress towards achieving its development objectives. Up to December 31, 2008, a total of about 120,600 ha of timber plantations has been established, around 60% of the project target, which is ahead of the project schedule. Plantations were established in accordance with the improved technical models and quality standards set by the project. The watershed management component, including establishing around 3,140 ha of carbon finance plantations, and the nature reserve improvement component are also implemented well and have contributed to the ecological environment improvement and biodiversity conservation. IBRD Effective USD Status of Projects in Execution - FY09 109

111 Lending Information/Disbursement Summary (in millions USD) 110 Status of Projects in Execution - FY09

112 Sector: Project GD Technical&Vocational ED and Training (P096707) China 02-Jun Dec-2014 Vocational training (95%); Public administration- Education (5%) The project development objective is to improve the quality and relevance of technical education in three schools and produce lessons from this experience as a guide for future school reforms and policy development. The Project was not yet effective before the close of the reporting period. IBRD Not Effective USD Status of Projects in Execution - FY09 111

113 Sector: Project CN-Yunnan Urban Env (P096812) China 05-May Jun-2015 Public administration- Water, sanitation and flood protection (28%); General water, sanitation and flood protection sector (18%); Solid waste management (18%); Sewerage (18%); Other social services (18%) To assist Yunnan Province in improving the effectiveness and coverage of critical urban infrastructure services in selected counties and the effectiveness of lake basin management in Dianchi The project is not yet effective. IBRD Not Effective USD Status of Projects in Execution - FY09

114 Sector: received Additional Financing during Project CN-Guizhou Cultural and Natural Heritage (P091950) China 05-May Jun-2016 Other industry (43%); Other social services (24%); General water, sanitation and flood protection sector (13%); General transportation sector (13%); General industry and trade sector (7%) no To assist Guizhou Province in increasing economic benefits to local communities (including minority groups) through increased tourism and better protection of cultural and natural heritages The project is not yet effective. IBRD Not Effective USD Status of Projects in Execution - FY09 113

115 Sector: received Additional Financing during Project CN- GEF-Thermal Power Efficiency (P098654) China 05-May-2009 Public administration- Energy and mining (61%); District heating and energy efficiency services (26%); Power (13%) no The project development objective is to reduce coal consumption and GHG emission per unit of electricity production in Shanxi Province, Shandong Province and Guangdong Province in China. The project was not effective before the close of the reporting period. TF Closed USD Status of Projects in Execution - FY09

116 Sector: received Additional Financing during Project CN-5th Inland Waterways (P085333) China 11-Oct Jun-2011 Ports, waterways and shipping (50%); Renewable energy (35%); Sub-national government administration (15%) no The project's development objective is to enhance the standard of living in the Han River region by developing its potential water resources, including: a) increasing the waterway transport capacity along the Han River and its costeffectiveness; and (b) ensuring the availability of sustainable hydropower and water resources for use in the Xiangfan area and the Tangdong farmland region. The PDO indicators are measurable only upon completion of the Project and will be examined at the appropriate time. The intermediate indicators in terms of the physical construction progress show that the project has continued progressing well to achieve its development objectives. The implementation of the Technical Assistance component needs to be accelerated. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 115

117 Sector: received Additional Financing during Project CN-Wenchuan Earthquake Recovery Project (P114107) China 12-Feb Jun-2014 General water, sanitation and flood protection sector (55%); General transportation sector (25%); Health (13%); General education sector (5%); District heating and energy efficiency services (2%) no To restore essential infrastructure, health, and education services to at least levels existing prior to the Wenchuan Earthquake, and where appropriate, to provide for expansion of services, while reducing the vulnerability to seismic and flood hazards and building capacity of local governments to manage the recovery program The project was just declared effective on June 17, IBRD Not Effective USD Status of Projects in Execution - FY09

118 Sector: received Additional Financing during Project `CN-Economic Reform Implementation (P085124) China 11-Apr Oct Dec-2011 Central government administration (65%); Sub-national government administration (30%); Banking (5%) no The project development objective is to assist the GOC in implementing its reform and development agenda by significantly increasing the adoption and use of sound reform and development strategies, policies and implementation plans through a series of technical assistance subprojects tailored to address specific challenges through institutional capacity building at the national and sub-national levels. The project continues to achieve its PDOs in FY09. Overall, result-orientation has been further strengthened in management of subprojects. Satisfactory results have been achieved in most subprojects that have completed or will complete soon. Quality management is satisfactory in most subprojects. And a number of SIAs have been outstanding in effective and efficient project implementation. IBRD Effective USD TF Effective GBP Status of Projects in Execution - FY09 117

119 Lending Information/Disbursement Summary (in millions USD) 118 Status of Projects in Execution - FY09

120 Sector: received Additional Financing during Project CN-GEF-WB Urban Transport Partnership (P090335) China 24-Jun Jun-2013 General transportation sector (48%); Sub-national government administration (32%); Central government administration (20%) no The project is to help achieve a paradigm shift in China's urban transport policies and investments toward the promotion of public and non-motorized transport, modes that are less energy intensive and polluting than those fostered by current urban land-use planning and transport systems in China. The project just became effective in January 2009 and progress has been slow in large part due to the client's wish to change implementing agencies. However, work has begun in one of the project cities (Weihai) and a number of contracts are now under procurement in other project cities. It is expected that more substantial progress will be made in FY10 once issues related to implementation arrangements are fully resolved. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 119

121 Lending Information/Disbursement Summary (in millions USD) 120 Status of Projects in Execution - FY09

122 Sector: received Additional Financing during Project CN-GEF-Heat Reform & Bldg Egy Eff. (P072721) China 17-Mar Sep Dec-2011 Housing construction (40%); District heating and energy efficiency services (32%); Sub-national government administration (17%); Central government administration (11%) no To achieve substantial, sustained and growing increases in energy efficiency in urban residential buildings and the heating systems in China's cold climate regions. Project implementation is progressing if somewhat slowly. Several key indicators of increasing energy efficiency in urban residential buildings have been exceeded. For example 99% of current year new housing completion complies with applicable building energy efficiency standards compared to a project target of 80%. These building improvements have allowed for a cumulative coal savings capacity of over 526,000 tons carbon equivalent or 80% of the project target. However the current financial crisis has reduced occupancy rates of residential buildings, putting at risk the completion of consumption-based billing. New residential stock billed according to heat consumption is very low (2-3%) compared to the project target of 50%. Heating companies have been reluctant to implement consumption based billing due to its perceived risks and rapid increases in fuel costs as well as local pressure to keep heat prices low. An extension of the closing date to achieve the PDO may be necessary but it is too early to determine at this time. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 121

123 Lending Information/Disbursement Summary (in millions USD) 122 Status of Projects in Execution - FY09

124 CN- Energy Efficiency Financing (P084874) China 27-May Dec-2013 Sector: District heating and energy efficiency services (100%) received Additional Financing during no The project is to improve the energy efficiency of medium and Project large-sized industrial enterprises in China, and thereby reduce their adverse environmental impacts on climate. Both the Chinese counterparts and the Bank agreed that the project implementation has had a successful start since the effectiveness of the loan and GEF grant in October For the GEF financed components, the PMO has been formally established, fully staffed, and equipped by NDRC and the Project Steering Committee (PSC) will be established soon. Since its establishment, the PMO has organized several trainings for the two financial intermediaries, the EXIM Bank of China and Huaxia Bank, on how to identify eligible energy efficiency sub-projects for the IBRD loan financing. It has been also providing technical assistance to the two banks in preliminarily screening of sub-projects and approving eligible sub-projects submitted by the two banks on behalf of NDRC. For the IBRD lending component, the two financial intermediaries have (1) established a good system in energy efficiency financing; (2) built strong capacity of its staff both in the headquarter and related branches; (3) processed significant amount of energy efficiency loans; and (4) built up a strong subproject pipeline for future lending. By early March, 2009, the EXIM Bank had approved 15 energy efficiency subprojects with a total actual disbursement of the IBRD loan of US$ million and US$ 117 million equivalent local currency loans out of its own resources. IBRD Effective USD IBRD Effective USD Status of Projects in Execution - FY09 123

125 Lending Information/Disbursement Summary (in millions USD) 124 Status of Projects in Execution - FY09

126 Sector: received Additional Financing during Project CN-Inner Mongolia Highway & Trade Corrid (P068752) China 15-Feb Jun-2010 Roads and highways (99%); Sub-national government administration (1%) no The main objective of the project is to sustain and promote the development of cross-border trade between China on one hand and Russia and Mongolia on the other by improving transport infrastructure and logistics. The project has made good progress in achieving its development objectives. Most of the project components have been completed and are meeting their required purpose. However, some indicators are not currently meeting their target values, particularly the case for the trade indicators and traffic volumes. The trade facilitation component and its sustainability require continued attention. Efforts are being made to carefully monitor the trade data trend. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 125

127 Sector: received Additional Financing during Project CN-Guiyang Transport (P093963) China 08-Jan Dec-2012 Roads and highways (85%); General transportation sector (14%); Sub-national government administration (1%) no The objective is to increase the access and mobility of Guiyang Municipality's transport users through priority infrastructure investments while establishing more sustainable mechanisms for rural road maintenance, as well as enhancing capacity for keeping municipal debt under control. The project continues to make good progress towards achieving its development objectives. The Youxiao Road component, in particular, is proceeding very well. The rural transport component is proceeding steadily though slower than expected. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) 126 Status of Projects in Execution - FY09

128 Sector: received Additional Financing during Project CN-3rd Jiangxi Hwy (P093906) China 27-Jun Dec-2010 Roads and highways (97%); Sub-national government administration (3%) no The project development objective is to improve east-west passenger and freight flows in Jiangxi province by investing in the construction of an expressway, enhancing local roads, and strengthening highway management. The construction of the RGE expressway has been going very well and of a highly satisfactory quality, and is expected to open traffic later this year. Some of the TA components have already showed impact on sectoral policy. Overall, the project is on the right track to achieve the PDO. The greatest risk remains being the delays in completing the 31 Km section between the RGE expressway and Fujian province. This situation is currently going through changes in ownership and investment entity and is expected to be settled soon. The project is going through restructuring in reflection of the reduction of scope and increase in disbursement percentage for the Local Road Improvement Program component. This change does not have negative impact on achieving the PDO. IBRD Effective USD Status of Projects in Execution - FY09 127

129 Lending Information/Disbursement Summary (in millions USD) 128 Status of Projects in Execution - FY09

130 Sector: received Additional Financing during Project CN-Shandong Flue Gas Desulfurization (P093882) China 27-May Jun-2012 Power (49%); District heating and energy efficiency services (49%); Sub-national government administration (2%) no The development objective of the proposed project is to reduce SO2 emission in the heat and power sector and enhance the capacity of regulatory authorities to monitor and enforce compliance with their SO2 emission reduction program. The project is performing below expectations. One of four subprojects is nearly completed but the three others are dropped due to identification of alternative financing. Suitable substitute subprojects are expected to be identified this fiscal year. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 129

131 CN-TAI BASIN URBAN ENVMT (P057933) China 03-Aug Sep Jun-2010 Sector: Sewerage (90%); Flood protection (10%) received Additional Financing during no To improve the quality of life of the rapidly increasing urban population and enhance economic competitiveness in Wuxi and Suzhou, key municipalities in the Tai Basin and the Project Yangtze River Delta economic region, by alleviating degradation of water resources and improving the quality of the urban environment. Progress toward meeting the PDO is progressing modestly. Good progress is being made in implementing the physical works necessary to alleviate the degradation of water resources and improve the quality of the urban environment. All wastewater treatment plants will be commissioned by June 2010 and their overall capacity utilization should exceed 70%. The agreed institutional and financial reforms have not, however, been adopted. The recent extension of the loan closing date will allow more time for the borrower to implement an action plan to address these issues substantively by closing. A restructuring has been agreed in principle to utilize loan savings to construct a 25,000 m3/day wastewater treatment plant that would further enhance achievement of the PDO. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

132 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 131

133 Sector: received Additional Financing during Project CN-Accounting Reform & Development (P051856) China 23-Feb Oct Dec-2009 Tertiary education (83%); Central government administration (17%) no The overarching objective is to assist the modernization of accounting in China. The project continues to make progress toward achieving its development objective. Supported by the project China has successfully converged 38 accounting standards with International Financial Reporting Standards (IFRS). Currently, China continues to improve the accounting standards, promotes international convergence of accounting and accelerates the development of accounting regulations, internal control, accounting information standardization and theoretical research. These measures have helped the accounting community provide better services for economic and social development, thereby contributing to the development of the global accounting industry. The establishment of three national accounting institutes (NAIs) has made great contributions to enhance China s training capacity on accounting and financial management. The NAIs provided effective and efficient market demand based courses, good training environment to China s accounting and financial management personnel, to expand their knowledge on business and enhance their capacity of implementing the accounting standards as well as improve their business skills. IBRD Effective USD IDA Effective XDR Status of Projects in Execution - FY09

134 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 133

135 Sector: received Additional Financing during Project CN-Gansu & Xinjiang Pastoral Development (P065035) China 09-Sep Jun-2010 Animal production (50%); Agricultural marketing and trade (25%); Agricultural extension and research (25%) no The objective of the project is to promote sustainable natural resource management and to increase the incomes of herders and farmers in the project areas. The global environment objective of the project is to maintain and nurture natural grassland ecosystems. The project is getting close to completion and is demonstrating good results. the development objective has been good. Observed income differences in project households compared with non-project households can be directly attributed to increased lamb survival (due to warm sheds), increased lamb growth rate (due to a combination of warm sheds, better nutrition and cross-breeding), improved quality (cross-breeding and nutrition) and a change in lambing time (warm sheds) so that sales coincide better with peak market demands # all achieved through project activities in fodder production, livestock breeding, livestock fattening, and livestock shed improvements. Culling of unproductive animals and introduction of higher quality and more productive animals combined with improved nutrition is enabling an increasing number of farmers and herders to decrease their flock sizes and thus reduce the pressure on grasslands. Positive impacts of GEF financed activities are also been demonstrated. Rotation grazing is reducing pressure on grasslands. An example is a herder who solely rely on grassland for forage - has been able to reduce his total number of sheep by 50% through improved nutrition gained from rotational grazing (introduced by the GEF program) and through reduction of trespass grazing due to secure boundary fences (financed by GEF). Carbon sequestration research work is rendering results showing that enclosure from grazing is increasing carbon sequestration capacity of the grassland from 20% to 50%. A river conservation program that includes fencing of a wetland river head to exclude livestock is demonstrating significant increase in ground cover, plant density, standing biomass, and increase in biodiversity. Grazing protection programs are resulting in rapid improvement with density and cover doubling, and biomass increase of 20% inside exclosure. Natural rodent control programs (establishing eagle and hawk stands) have reduced active rodent burrows with 134 Status of Projects in Execution - FY09

136 85% over the past 4 years resulting in increased ground cover (30-50%) and biomass, etc. IBRD Effective USD TF Closed USD TF Closed USD TF Closed USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 135

137 Sector: received Additional Financing during Project CN-GUANGDONG/PRD2 (P081776) China 21-Mar Dec-2012 Sewerage (39%); Flood protection (31%); Sub-national government administration (20%); Sanitation (10%) no To reduce water pollution in the Pearl River system originating from Foshan and Jiangmen municipalities. In general, the project is making positive progress toward achieving its development objective despite some delay. The Jiangmen component is being implemented well with most civil works construction expected to be completed by end of this year. The Foshan component is lagging due to delay in design and land acquisition but is catching up. Progress against the key outcome indicators can only be measured after the construction is completed. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) 136 Status of Projects in Execution - FY09

138 Sector: received Additional Financing during Project CN-Heilongjiang Dairy (P086629) China 24-Jan Dec-2010 Animal production (69%); Agricultural extension and research (27%); Crops (3%); Sub-national government administration (1%) no The objectives are: (a) to improve the financial viability of existing and new dairy operations in selected areas of Heilongjiang province; and (b) to demonstrate innovative technologies to reduce green-house gas emissions and increase carbon sequestration. Progress towards the development objective has been slow during FY09. The biggest hurdle has been the procurement of cattle, which is fundamental to achieving the objectives of the project. Importation of cattle has proven to be problematic, and ultimately the procurement method has been changed to facilitate procurement. This has improved the project's performance. On the positive side, nearly all investments to be financed by counterpart funding have been completed. The last supervision mission encouraged the PPMO to refocus on the original objectives and pay closer attention to achieving the institutional change that is required to meet the objective. IBRD Effective USD TF Effective USD Status of Projects in Execution - FY09 137

139 Lending Information/Disbursement Summary (in millions USD) 138 Status of Projects in Execution - FY09

140 Sector: received Additional Financing during Project CN-Hubei Shiman Highway (P081749) China 24-Jun Dec-2009 Roads and highways (97%); Sub-national government administration (3%) no The main objective of the project is to support socioeconomic development of Hubei province by enhancing its access to other provinces, particularly the western region of China, improving local mobility within poor, remote western parts of the province, and strengthening governance of the provincial road sector. The PDO indicators depict a satisfactory trend towards achieving intended project outcomes, especially improving local mobility within poor, remote western parts of province and strengthening governance of the provincial road sector. However, due to the Shaanxi section of the expressway that remains closed, the average traffic volumes of the main investment is lower than estimated at Appraisal. Since the traffic volume on the Shiyan - Manchuanguan Corridor appears to be in line with expectations during Appraisal, the main shortcoming is that the level of traffic diverted to the expressway is still quite low. It is estimated that the traffic volume on Shiman expressway after the opening of the Shaanxi section will be significantly increased, the gap with the estimate at appraisal will not exceed 30%. IBRD Effective USD Status of Projects in Execution - FY09 139

141 Lending Information/Disbursement Summary (in millions USD) 140 Status of Projects in Execution - FY09

142 Sector: received Additional Financing during Project CN ODS IV PHASE OUT PRJ (P039838) China 21-Nov Dec Jun-2011 Other industry (94%); Central government administration (6%) no The objective of the project is to phase out the production and consumption of Ozone Depleting Substances (ODS) to enable China to fulfill its obligations under the Montreal Protocol. The project is meeting its development objectives with China meeting its overall Ozone Depleting Substance (ODS) phaseout targets and the specific requirements under the project. Preparation activities for the follow-on HCFC Phase-Out project, being funded under this project, are also on schedule. To be specific, all CFC production has been completely phased out except for (a) 100 tons of halon 1301; (b) 7,342 tons of CTC; and (c) 79 tons of TCA -- all fully compliant with agreements. CFC consumption is phased out in the foam, refrigeration, and mobile AC sectors, and is within agreed levels in the pharmaceutical aerosol sector. TF Closed USD TF Effective USD TF Closed USD TF Closed USD TF Closed USD Status of Projects in Execution - FY09 141

143 Lending Information/Disbursement Summary (in millions USD) 142 Status of Projects in Execution - FY09

144 CN-Sustainable Forestry Development (P064729) China 16-Apr Oct Aug-2009 Sector: Forestry (100%) received Additional Financing during no The project development objective is to ensure that viable, participatory and locally managed systems for conservation, management and sustainable use of forest resources and associated biodiversity are developed and adopted to promote Project the sustainable development of forest resources and protect natural environment. The global environmental objective is to foster improved conservation and sustainable management of biodiversity in remaining natural forest areas. Overall implementation during the final year of the project before closing has proceeded well and the project is likely to achieve the development objectives. The plantation development component has been highly successful with nearly 200,000 hectares of new timber plantations and 42,000 hectares of economic tree plantations established with high survival rates and economic returns. In addition, improved silvicultural practices are in place. Under the protected areas component, all 13 nature reserves supported by the project have developed and are implementing up-to-date management plans leading to improved in-situ conservation of biodiversity in these areas. The project has also been successful in implementing community-based livelihoods, awareness raising, and training activities for biodiversity conservation. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 143

145 Lending Information/Disbursement Summary (in millions USD) 144 Status of Projects in Execution - FY09

146 Sector: received Additional Financing during Project CN-IAIL III (P084742) China 11-Oct Sep Dec-2010 Irrigation and drainage (68%); Agricultural extension and research (12%); General public administration sector (11%); Forestry (5%); General agriculture, fishing and forestry sector (4%) no The objectives are: (a) to increase water and agricultural productivity in low- and medium-yield farm land areas; (b) to raise farmers' incomes and strengthen their competitive capacity under post-access conditions of the World Trade Organization; and (c) to demonstrate and promote sustainable participatory rural water resources management and agroecological environmental management in the Huang-Huai-Hai River Basin area. Implementation progress is ahead of schedule and the Project is likely to achieve its development objectives. Based on the monitoring data provided by the Project Management Office, 482,044 ha of low-and medium-yield farm land have been improved under the project. This has reportedly resulted in an improvement of both production conditions and water saving in the project area. Canal water delivery efficiency in the improved areas has risen from 55% to 80%. Irrigation quota has reduced from 6,185 m3/ha to 3,745 m3/ha while water productivity has increased from baseline value of 1.05 kg/m3 to 1.69 kg/m3. 98% of the canals in Water User Association areas are in good operational condition. Linked to the loan Project, the new GEF Climate Change (CC) Project (US$5 million, approved in early 2008) demonstrates an innovative method for integrating CC adaptation support into this ongoing Project and national comprehensive agricultural development program. These two operations are jointly contributing to improving irrigation and drainage infrastructure, promoting CC adaptation activities, modernizing agricultural production, increasing farmer access to markets, and strengthen the agricultural value chain for farmers, which all help increase farmers' incomes. IBRD Effective USD Status of Projects in Execution - FY09 145

147 Lending Information/Disbursement Summary (in millions USD) 146 Status of Projects in Execution - FY09

148 Sector: received Additional Financing during Project CN-Basic Education in Western Areas (P073002) China 09-Sep Jun Dec-2009 Primary education (95%); Sub-national government administration (3%); Central government administration (2%) no The Project aims to improve access to and the completion of affordable and quality basic education for poor boys and girls in over a hundred counties in Sichuan, Gansu, Yunnan Provinces, and Ningxia Hui and Guangxi Zhuang Autonomous Regions. Progress towards achieving objectives is steady. The indicators show continuous improvement in enrollment rates, dropout rates, minority and gender equity, student pass rates in mathematics and Chinese language, and percentage of qualified teachers in project counties. The project counties in all five provinces have over 90 percent of students enrolled and over 90 percent of teachers having achieved the required qualification. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 147

149 Lending Information/Disbursement Summary (in millions USD) 148 Status of Projects in Execution - FY09

150 CN-3rd National Railway (P086515) China 23-Jan Jun-2012 Sector: Railways (99%); Central government administration (1%) received Additional Financing during no The objective is to expand the capacity of China's railway Project system to meet the growing demand for transport of people and goods between Guizhou and Yunnan Provinces. Progress towards achieving the development objective is satisfactory though provincial counterpart funding has lagged substantially behind expectations. Nonetheless, transport demand between the target regions remains strong and current funding shortfalls are expected to be addressed. IBRD Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 149

151 CN-NINGBO WATER & ENVMT (P086505) China 17-Mar Feb Dec-2010 Sector: Water supply (55%); Sewerage (45%) received Additional Financing during no To facilitate the expansion and quality of water and Project wastewater services in Ningbo City and Cixi City in an economically efficient and environmentally sustainable manner. Good progress is being maintained. All physical works necessary to expand water and wastewater services should be completed by the December 2010 loan closing except possibly for the Maojiaping water treatment plant, which is seeing some delays related to land acquisition and changes to pipe alignments. Progress toward increasing efficiency and ensuring sustainability is being made through the smooth implementation of the technical assistance component. Compliance with financial covenants is partial, and the borrower should raise tariffs as necessary to ensure compliance and thus sustainability. IBRD Effective USD Status of Projects in Execution - FY09

152 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 151

153 Sector: received Additional Financing during Project CN-LIAONING MED CITIES INFRAS 2 (P092618) China 26-Jun Dec-2013 Water supply (42%); Sewerage (34%); Solid waste management (17%); Flood protection (6%); Sub-national government administration (1%) no The objective is to improve the performance and sustainability of water supply, wastewater, and solid waste services in the project cities and thus contribute to improving the Bohai Sea water quality. Implementation was slow to start with nearly 12 months delay after loan effectiveness. However during fiscal year 2009, procurement activities and physical implementation accelerated satisfactorily. These activities are designed to improve water, wastewater and solid waste services in the project cities to help the project meet its development objective. Two issues, however, may negatively impact the likelihood of achieving the development objective and may require the project to be restructured during These two issues are: (a) continued delays starting the Public Utility Improvement Program; and (b) the potential cancellation of the Fushun water supply component due to a shortage of counterpart funds. IBRD Effective USD Status of Projects in Execution - FY09

154 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 153

155 Sector: received Additional Financing during Project CN-SHANGHAI URBAN APL2 (P075732) China 05-Jul Mar-2011 Sewerage (50%); Water supply (20%); Sub-national government administration (20%); Solid waste management (10%) no The project objective is to expand the environmental management agenda in the metropolitan area. The civil works necessary to expand the environmental management agenda are underway. A technical review of the sludge treatment systems at Bailonggang and Zhuyuan caused some delay, which resulted in the current disbursement lag. Feasibility studies and environmental assessment reports of these systems were revised and were cleared by the Bank from the engineering and environmental points of view. The implementing agencies are experiencing some financial difficulties, and are relying on subsidies to help meet financial covenants. On the institutional front, the Shanghai Municipal Sewerage Company is merging with its subsidiaries into one company (except for wastewater treatment operations) to increase efficiency. Also the city is contracting out solid waste managing operations in line with a recent government order. Overall, the project is making good progress toward its PDO. IBRD Effective USD Status of Projects in Execution - FY09

156 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 155

157 Sector: received Additional Financing during Project CN-HUNAN URBAN DEV (P075730) China 16-Sep Jan Dec-2010 Flood protection (45%); Sewerage (27%); General transportation sector (20%); Mining and other extractive (5%); Other social services (3%) no To foster greater integration in the Changsha-Zhuzhou- Xiangtan (CZT) Region of Hunan Province through priority investments addressing specific regional needs in a sustainable manner. Little real progress on the ground has been made toward meeting the PDO. Under the Corridor component, the Changsha section is moving forward albeit it with delays stemming from slow resettlement. Construction under the Changsha wastewater component is proceeding smoothly. The Zhuzhou Clean Coal component may not proceed due to market changes and the deteriorating financial situation of Hunan Zhuxi Clean Coal Company. It is likely that the Zhaoshan component will be canceled. These various adjustments to the project scope will likely be made in a major restructuring in FY10. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

158 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 157

159 Sector: received Additional Financing during Project CN-GUANGDONG/PRD UR ENVMT (P075728) China 08-Jun Sep Dec-2009 Sewerage (88%); Solid waste management (7%); Subnational government administration (5%) no The project development objective is to improve the quality of the environment in key cities in the Pearl River Delta using an integrated regional planning approach to facilitate continued economic and social development. The Global Environment Objective is to reduce pollution loading to the Pearl River Delta and South China Sea through increased inter- and intramunicipal environmental services delivery. Implementation of the wastewater component over the last year has been very slow, especially concerning installation of the sewerage network whose completion rate stands at only 42% of the project target. Inadequate network progress means that the two wastewater treatment plants built under the project are currently operating at 70% capacity, compared to the target of 90%. The hazardous waste component is also significantly behind schedule due to a shortage of counterpart funds and land acquisition issues. Neither component can be completed by the current closing date. While progress toward improving the quality of the environment has been made, full achievement of the DO will depend on an extension of the loan closing date. With regard to financial sustainability the government has approved a wastewater tariff increase, but it is inadequate to meet covenants in the legal agreements. The GEF components have also encountered significant delays due to land acquisition issues. Most activities will only start bidding in FY10 and cannot be completed by the closing date, so the GEF DO is not likely to be met without an extension. IBRD Effective USD Status of Projects in Execution - FY09

160 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 159

161 Sector: received Additional Financing during Project CN-Shaanxi Ankang Road Development (P075613) China 13-Mar Jun-2012 Roads and highways (99%); Sub-national government administration (1%) no The objective of the Project is to assist the Borrower in improving passenger and freight traffic flows in an efficient and safe manner along the corridor from Ankang to Maoba in Shaanxi Province by: (i) enhancing road infrastructure capacity and network integration along the corridor Ankang- Maoba; (ii) increasing accessibility to markets and social services for the lower-income families in rural areas of Ankang; and (iii) strengthening Shaanxi Provincial Communications Department's capacity in managing the increasing number of kilometers of roads under its responsibility in the Shaanxi province and, in particular, within the Ankang region. The PDO is, based on current achievements, likely to be achieved, as site assessments show progress consistent with the intended outcomes. Supervision assessments of the development indicators showed good progress under the rural road component, as the impact of completed roads already provide anecdotal information. A formal assessment is currently being undertaken to quantify the outcomes. Additionally, project implementation is progressing well with works under the Rural Roads component progressing to schedule and the major earthworks, bridge and tunnel contracts on the Ankang-Maoba-Expressway is more than 65% complete. IBRD Effective USD Status of Projects in Execution - FY09

162 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 161

163 Sector: received Additional Financing during Project CN - Poor Rural Communities Development (P071094) China 21-Jun Jun Dec-2010 General agriculture, fishing and forestry sector (65%); Roads and highways (13%); Sub-national government administration (10%); General water, sanitation and flood protection sector (6%); General education sector (6%) no The objective is to improve the security of livelihoods and to achieve the sustained participation of the poorest rural people in project design, implementation, monitoring and evaluation in eighteen counties of the three project provinces. The overall progress is on track toward achieving its development objectives (DO). The problem of imbalance between the implementation of the project's components has been largely overcome, which has directly improved the likelihood of achieving t he DOs. Available evidence from the Project Management Office's monitoring system indicates that the project is contributing to improvements in well-being and livelihoods in the project area. More specifically, project data shows that the incidence of poverty in the project villages has declined (32% to 12% in Sichuan, 62% to 49% in Yunnan, 80% to 66% in Guangxi); households' supply of grain has increased (percentage of villagers with less than 150kg grain/year decreased from 14% to 8% in Sichuan, 13% to 8% in Yunnan), access to drinking water and road transport has improved (54% to 72% in Sichuan and 68% to 89% in Yunnan), and elementary school enrollment rates have gone up (81% to 95% in Sichuan and 94% to 99% in Yunnan). IBRD Effective USD TF Closed USD TF Closed USD TF Effective GBP Status of Projects in Execution - FY09

164 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 163

165 CN-Tuberculosis Control Project (P071147) China 21-Mar Aug Mar-2010 Sector: Health (93%); Sub-national government administration (7%) received Additional Financing during no The project's main development objectives are to achieve Project 70% case detection rate for smear positive TB cases and 85% cure rate. The Project continues doing well and has already achieved and sustained the three major targets of (i) DOTS coverage: since June 2005, all 1501 project sites fully implement DOTS, accounting for a coverage of 100%; (ii) case detection - in 2008, 261,950 new smear positive patients were diagnosed or 111% fulfillment of the target set for 2008, and (iii) treatment success: cure and treatment success rates for new smear positive patients put on treatment in 2007 were 92.9% and 94.6% respectively, which exceeds the target for cure of 85%. The Project also contributes to the overall success of China National TB Control Program. Central and provincial levels have been developing plan for sustainability. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

166 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 165

167 CN-Hubei Yiba Highway (P101258) China 31-Mar Dec-2015 Sector: Roads and highways (100%) received Additional Financing during no The PDO is to improve passenger and freight flows in the Project Yichang-Badong corridor by construction of an expressway with enhanced environmental management practices. The project is not declared effective yet, and the works has not started. It is too early to assess the progress towards achieving PDO. IBRD Not Effective USD Status of Projects in Execution - FY09

168 Sector: received Additional Financing during Project CN-Migrant Skills Dev. and Employment (P085376) China 24-Jun Aug-2012 Vocational training (48%); Adult literacy/non-formal education (24%); Central government administration (21%); Other social services (7%) no To support the transition of rural workers to urban areas to access better employment opportunities with the aim of improving their incomes and working conditions. During the global economic downturn, commitment to the project at both the central and local levels remains strong, and the project activities designed are still very relevant. There has been progress towards its objectives since the project launch. The development of modular training curricula for migrant workers has been started in order to target the training needs of migrant workers. Employment services in the provinces were functioning well to facilitate the labor mobility and promote the urban-rural integration. IBRD Effective USD Status of Projects in Execution - FY09 167

169 Lending Information/Disbursement Summary (in millions USD) 168 Status of Projects in Execution - FY09

170 Sector: received Additional Financing during Project CN-Jiangxi Integrated Agric. Modern. (P065463) China 20-Nov Aug Jun-2010 Irrigation and drainage (50%); Agricultural extension and research (15%); Agricultural marketing and trade (15%); Animal production (10%); Crops (10%) no The objective of the project is to improve the livelihoods of rural households in project counties in Jiangxi Province. Project implementation has been making steady progress towards achievement of the Project Development Objective. Implementation of Irrigation and Drainage component, Farm Production Improvement component and Market System Development component in most participating counties is expected to complete by the end of Project completion is expected as originally planned. Monitoring report indicated evidence of improvement of livelihood of participating rural households. The original designed coverage of the number of participating household will not be reached because of the reduced project budget (in local currency) due mainly to devaluation of the Loan value (USD against local currency) and the price increase of major project inputs. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 169

171 Lending Information/Disbursement Summary (in millions USD) 170 Status of Projects in Execution - FY09

172 Indonesia Project Name(ID): Sector: received Additional Financing during Project ID-Initiatives for Local Govern. Reform (P076174) Indonesia 09-Jun Sep-2009 General transportation sector (40%); Sub-national government administration (30%); Irrigation and drainage (15%); Water supply (10%); Power (5%) no The objective is to pilot support to district (kabupaten) governments in improving transparency, accountability and public participatory practices and in undertaking reforms in financial management and procurement. Implementation of the governance reform program has been slower than expected and the pilot has not reached as many districts as originally planned. However, recent progress has been promising and the project is in the process of being restructured and extended, with the goal of consolidating and enhancing the improvements achieved in the 14 current participating districts, rather than expanding the pilot to additional districts. All of the participating districts have completed the first phase of reforms, and 11 of them have fully implemented phase 2 and are more than halfway through phase 3 (final phase). As a result of the reforms implemented, most kabupaten have achieved significant progress in participatory planning, financial management, and procurement capacity. In general, kabupaten have opted for smaller subprojects than expected, and have thus been able to complete substantially more investment subprojects than originally planned (128 against a target of 74). Subprojects implemented include road and bridge rehabilitation, irrigation canals, water supply distribution systems, and school rehabilitation for post-earthquake reconstruction. Status of Projects in Execution - FY09 171

173 IBRD Effective USD IDA Effective XDR TF Closed USD TF Closed USD TF Closed USD TF Closed USD TF Effective GBP Lending Information/Disbursement Summary (in millions USD) 172 Status of Projects in Execution - FY09

174 Sector: received Additional Financing during Project ID-Water Resources & Irr.Sector Mgt Prog (P059931) Indonesia 26-Jun Mar Dec-2010 Irrigation and drainage (50%); General water, sanitation and flood protection sector (50%) no The program's objectives are to (a) improve management and infrastructure related to water resources and irrigation (b) increase farm incomes and productivity, improve food security, and reduce vulnerability to economic shocks and natural disasters, and (c) strengthen governance and capacity in key agencies. Although early implementation was slower than expected and the targets have not yet been achieved, progress toward the objectives has improved substantially, and the closing date has been extended by one year. The project has helped to mainstream improved management practices and procedures at both the national and regional level, and to establish a new national water council, three provincial water councils, more than 50 provincial river basin management agencies, and more than 900 local water user/ irrigator associations as well as about 30 District Irrigation Committees. Progress has been made toward improving river basin management and coordination, but role-sharing agreements and other key steps are still pending. Investments in irrigation infrastructure have lagged, but the participatory design and planning for these works is largely completed now and the initiation of works subprojects is expected to increase sharply. The results of outcome monitoring, though preliminary, show improvements in agricultural productivity, efficiency of water use, and institutional governance, as well as fewer conflicts over the use of water resources. IBRD Effective USD IBRD Effective USD IDA Effective XDR TF Effective USD TF Closed USD Status of Projects in Execution - FY09 173

175 Lending Information/Disbursement Summary (in millions USD) 174 Status of Projects in Execution - FY09

176 Sector: received Additional Financing during Project ID-Aceh Infra. Reconst. Facility (IRFF) (P101785) Indonesia 11-Dec Jun-2010 General water, sanitation and flood protection sector (34%); Roads and highways (33%); Ports, waterways and shipping (33%) no The objective of the Infrastructure Reconstruction Financing Facility is to assist the province of Aceh and 12 local governments in Aceh and Nias to reconstruct, rehabilitate strategic infrastructure and extend key infrastructure services of adequate quality standards that meet the needs of communities where infrastructure was damaged by the tsunami of 2004 and the subsequent earthquake. The project is proceeding well and is expected to achieve its development objective. Investments already carried out under the project have resulted in rehabilitation of 361 km of roads and completion of 2 ports subprojects and 10 water and flood protection subprojects. The quality of the works has been satisfactory and they have provided significant benefits for local communities. Another 418 km of roads, 2 ports subprojects, and 1 water and flood protection scheme under still under implementation and are on schedule to be completed before the closing date. TF Effective USD Status of Projects in Execution - FY09 175

177 Lending Information/Disbursement Summary (in millions USD) 176 Status of Projects in Execution - FY09

178 Sector: received Additional Financing during Project National Program for Community Empower (P105002) Indonesia 20-May Dec-2011 Sub-national government administration (25%); Water supply (20%); Irrigation and drainage (20%); Roads and highways (20%); Primary education (15%) US$300 million in additional financing was approved to allow for the continuation and full scale-up of the program. PNPM's overall objective is to reduce poverty and improve local-level governance in rural areas of Indonesia through the provision of investment resources to support productive proposals developed by communities, using a participatory planning process. The project made very good progress toward its development objective during the first year of implementation. In 2008 the block grant program provided financing for productive activities in about 2,600 kecamatans. Almost all of the works in the 2008 funding cycle have been completed or are nearing completion. A sample survey of 700 subprojects found that, in the overwhelming majority, the quality of the outputs was moderately or highly satisfactory. Although implementation of the 2009 program has been delayed by late budget disbursements, community planning for the 2009 funding cycle is completed in most districts, and the program's scope will be expanded to cover about 4,370 kecamatans. A study carried out in December 2008, before most of the first round of subprojects had been completed, found only modest improvements in selected community health and education indicators, but as the program advances more clear-cut results are expected. IBRD Effective USD IBRD Not Effective USD IDA Effective XDR TF Effective USD TF Effective USD Status of Projects in Execution - FY09 177

179 Lending Information/Disbursement Summary (in millions USD) 178 Status of Projects in Execution - FY09

180 Sector: received Additional Financing during Project ID ODS I- UMBRELLA (P003701) Indonesia 24-Oct Sep Dec-2010 Other industry (98%); Banking (1%); Central government administration (1%) no The objective is to carry out Indonesia's Montreal Protocol Country Program for phasing out the use of ozone-depleting substances (ODS) The project is ahead of the schedule agreed under the Montreal Protocol for phasing out consumption of ODS in developing countries by The government banned the import of CFCs in 2008 and had previously halted the import of halons as well. Indonesian industries have successfully adopted and applied non-ods technologies, and the capacity of government to implement and monitor the phase-out program has improved significantly under the project. During the coming year the project will focus on providing technical assistance to complete the phase-out of ODS use in aerosols, foams, mobile air conditioning and metered-dose inhalers. TF Effective USD Status of Projects in Execution - FY09 179

181 Lending Information/Disbursement Summary (in millions USD) 180 Status of Projects in Execution - FY09

182 Dutch Education Support Program-BOS (P115725) Indonesia 15-Jan Jun-2010 Sector: Public administration- Education (100%) received Additional Financing during no Project Improved management of BOS funds by schools and school committees. This Trust funded activity provided for a nationwide training program on school based management and the use of school operational funds, supporting the BOS-KITA project. A cascade approach was used, starting with national training of trainers, through provinces and districts and down to schools, involving principals and school committee representatives, reaching nearly 600,000 people. Nearly all schools have been reached: training impacts will be measured next year. TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 181

183 ID-Avian and Human Influ Control (P103654) Indonesia 15-Dec Dec-2009 Sector: Animal production (80%); Health (20%) received Additional Financing during no The objective is to assist in controlling Highly Pathogenic Avian Influenza (HPAI) infection at source in domestic poultry, to reduce the amount of HPAI virus circulating in the Project environment, and thereby reduce the risks of human infection and the possible mutation of the HPAI virus to a form more easily transmitted from human to human. Despite improvements in recent months, there have been serious delays in implementation progress. The closing date was extended by five months so that ongoing activities could be completed and disbursements accelerated. This would allow achievement of many but not all key project development objectives. Some progress has been made on participatory disease surveillance and response, and on procurement of vaccines, vaccination equipment, and rapid testing. However, it is likely that less than half of the $3.8 million allocated for vaccines will be used. Completion of a poultry sector restructuring study and community awareness and training activities is uncertain, and it is likely that activities aimed at improving the poultry culling compensation system will be cancelled. TF Effective USD TF Effective USD Status of Projects in Execution - FY09

184 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 183

185 Basic Education Capacity-Recipient Exec (P115724) Indonesia 06-Jun-2007 Sector: General education sector (100%) received Additional Financing during no Improved education governance and efficient resource use, Project and strengthened capacity of existing education management information systems at local level. This Trust Funded project is progressing well. A solid base has been prepared for capacity development support in education governance in 25 districts. These districts are currently preparing proposals for capacity development support grants which will reach them in late 2009 through a reformed, decentralized funding mechanism. 184 Status of Projects in Execution - FY09

186 ID-Domestic Gas Market Development Proj. (P077175) Indonesia 13-Dec Mar-2011 Sector: Oil and gas (100%) received Additional Financing during no The objective is to improve economic efficiency and reduce Project pollution by substituting gas for more expensive and more polluting fuels, such as diesel, fuel oil and coal. The project is making good progress toward achieving its development objective. Some of the works to expand the distribution network of the gas company (PGN) have already been completed and almost all of the remaining work is under way. PGN has increased both it gas sales and supply contracts, allowing it to convert more than twice as many customers to gas as originally projected. Reductions in major air pollutants and greenhouse gases under the project already substantially exceed the project's targets. O n the capacity and regulatory side, progress has been made on giving third parties access to PGN's transmission and distribution system. Although technical assistance activities have provided a road map for improving service, management, planning, security, and safety, follow-up will be required to ensure that these recommendations are implemented and their full benefits realized. IBRD Effective USD IBRD Effective USD Status of Projects in Execution - FY09 185

187 Lending Information/Disbursement Summary (in millions USD) 186 Status of Projects in Execution - FY09

188 Sector: received Additional Financing during Project ID-Support for Poor and Disadvant Areas (P078070) Indonesia 09-Jun Dec-2011 Other social services (30%); Health (20%); General education sector (20%); Sub-national government administration (15%); Law and justice (15%) no The objectives of the project are to strengthen governance, promote growth, and improve service delivery in 40 of the poorest districts of Indonesia. Implementation in the early stages of the project was slower than expected, but progress toward achieving the development objectives improved during the past year. Block grant disbursements to districts and subdistricts are well underway, and are mainly financing investments in local health and education infrastructure and services. The project has also helped increase the use of alternative dispute resolution mechanisms in communities, established community health committees, and trained and supported local community legal advisors, teachers, and health services providers. Local stakeholders, including government officials and communities, continue to express satisfaction with the project s field activities. Surveys are currently under way to better evaluate the performance and outcomes of the project so far. Status of Projects in Execution - FY09 187

189 IBRD Effective USD IBRD Effective USD IDA Effective XDR TF Closed USD TF Closed USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD Lending Information/Disbursement Summary (in millions USD) 188 Status of Projects in Execution - FY09

190 ID-Comm. Based Settlement Rehab. (Yogya) (P103457) Indonesia 05-Jan Mar Jun-2010 Sector: Housing construction (80%); Other social services (20%) received Additional Financing during no To meet the needs of targeted households for (a) seismic Project resistant housing and (b) community infrastructure in selected disaster affected villages in Central and West Java, and Yogyakarta. The project continues to perform well and is meeting its development objective. Housing reconstruction (about 15,000 units) has been completed and virtually all the houses are now occupied. Most of the 50 or so houses that are still unoccupied are undergoing additional construction or expansion at the option and expense of the owners. More than 94% of the beneficiaries, both men and women, say they are satisfied with the reconstructed houses, and more than 98% of the houses have met seismic standards. Infrastructure reconstruction has also progressed well, despite some slight delays. So far 80 of the 101 targeted communities have prepared community settlement plans, and more than 60 communities have already completed some of the proposed works using small block grants provided under the project. TF Effective USD Status of Projects in Execution - FY09 189

191 Lending Information/Disbursement Summary (in millions USD) 190 Status of Projects in Execution - FY09

192 Sector: received Additional Financing during Project ID-KECAMATAN DEV. 3 (P079156) Indonesia 26-Jun Dec Dec-2009 Sub-national government administration (25%); Water supply (20%); Irrigation and drainage (20%); Roads and highways (20%); Primary education (15%) no The objective is to reduce poverty and improve local governance in rural villages, including (a) institutionalizing participatory processes in local government, (b) cost effective provision of basic social and economic infrastructure, and (c) strengthening the capacity of microfinance institutions to manage and monitor funds in a sustainable manner. The project (KDP3) has performed very well, and with activities nearly completed it has met or exceeded most of it outcome indicators. Participatory processes have been improved through the establishment of participatory village community organizations in more than 1,500 kecamatans and the widespread adoption of the project's participatory framework into local planning and programs. Block grants under the project helped finance thousands of small-scale investment subprojects to improve roads, water supply, sanitation, irrigation, schools, and other social and economic infrastructure identified by the communities and implemented with cofinancing from the national and district governments, as well as the direct beneficiaries themselves. Local microfinance institutions have been successfully strengthened, with about 1,200 community groups and kecamatan financial management units (UPKs) assisted under KDP3 and its follow-on project KDP3B. These institutions now manage on average more than 100 million rupiah each. IBRD Effective USD IBRD Effective USD IDA Effective XDR TF Closed USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 191

193 Lending Information/Disbursement Summary (in millions USD) 192 Status of Projects in Execution - FY09

194 Sector: received Additional Financing during Project ID-WSSLIC II (P059477) Indonesia 15-Jun May Dec-2010 General water, sanitation and flood protection sector (49%); Health (31%); Sub-national government administration (12%); Primary education (7%); Central government administration (1%) no The objectives of the project are to improve the health status, productivity, and quality of life of poor communities in underserved rural villages in the project provinces. The project is making excellent progress towards achieving the objectives. As of March 2009, all of the originally targeted villages have started implementation of activities; over 90% have functioning water supply systems and had completed capacity building activities for sanitation infrastructure. The village based Sustainability Monitoring System shows significant improved access to water and sanitation; 60% increased access to water among poor households and 18% improved sanitation among poor households. A rigorous impact evaluation is ongoing and results will be available in 6 to 9 months. The project has been extended with 18 months to allow sanitation interventions to be further developed as well as impact evaluation work to be finalized. IDA Effective XDR TF Closed AUD Status of Projects in Execution - FY09 193

195 Lending Information/Disbursement Summary (in millions USD) 194 Status of Projects in Execution - FY09

196 Sector: received Additional Financing during Project ID-Eastern Indonesia Region Transp. 2 (P074290) Indonesia 22-Jun Apr Mar-2011 Roads and highways (92%); Sub-national government administration (4%); Aviation (2%); Ports, waterways and shipping (2%) no The objectives are to (a) improve the condition of the strategic road network in order to reduce transport costs and enhance regional accessibility, (b) support decentralization of planning and management responsibilities for civil works on provincial and kabupaten roads to their respective governments, and (c) increase the efficiency, quality and transparency of works procurement and implementation the development objectives continued to improve during the past year, and the closing date has been extended to allow for completion of investments that fell behind schedule during the early years of implementation. About 600 kilometers of national, provincial, and kabupaten roads have already been improved or rehabilitated, and a large share of the remaining planned investments are now underway. There also have been improvements in the management capacity and transparency of the national, provincial, and local government agencies participating in the project. This includes increased transparency in the procurement process, with community observers included at key steps, introduction of e- procurement on national road contracts, and extensive publication of data on the ministry's official website. IBRD Effective USD IBRD Effective USD Status of Projects in Execution - FY09 195

197 Lending Information/Disbursement Summary (in millions USD) 196 Status of Projects in Execution - FY09

198 Sector: received Additional Financing during Project Public Expend. Supp. Facility (DPL-DDO) (P115199) Indonesia 03-Mar Dec-2010 Central government administration (31%); General finance sector (23%); General industry and trade sector (23%); Banking (15%); Mining and other extractive (8%) no To reassure financial markets and secure back-up financing for the budget in the event market access is restricted, support measures to mitigate any adverse effects of the global economic crisis and maintain critical public expenditures. Financial market indicators suggest the PESF has thus far helped to boost confidence in Indonesia's credit-worthiness and macroeconomic policy framework, helping the government to meet most of its gross financing needs from market sources and maintain critical public expenditures. IBRD Not Effective USD Status of Projects in Execution - FY09 197

199 Sector: received Additional Financing during Project ID-WSSLIC III (PAMSIMAS) (P085375) Indonesia 27-Jun Jun-2013 Water supply (34%); Sanitation (33%); Other social services (17%); Sub-national government administration (9%); Central government administration (7%) no To increase the number of low-income rural and peri-urban populations accessing improved water and sanitation facilities and practicing improved hygiene behaviors as part of Government's efforts to achieve water supply and sanitation millennium development goals. Although the project did not become effective until almost two years after approval, it is now making relatively good progress. So far the project has been working in over 2,000 villages and has a goal of eventually reaching 5,000 villages. More than 150,000 households have already benefited from the project's water supply schemes. The project is gaining momentum and is likely to achieve its development objective, though some issues that could cause further delay must still be resolved. IDA Effective XDR Status of Projects in Execution - FY09

200 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 199

201 Sector: received Additional Financing during Project ID-HIGHER EDUCATION (P085374) Indonesia 09-Jun Oct Jun-2011 Tertiary education (99%); Central government administration (1%) no The objectives are to create an enabling environment for the evolution of autonomous public higher education institutions (HEIs), and to develop effective support mechanisms for the improvement of the quality, relevance, efficiency, and equity of higher education. The prospects of attaining the project's development objectives remain good. The first three years of project implementation confirmed that grants are facilitating positive outcomes in the quality, relevance, efficiency, and equity of supported programs. In January 2009 a Law on Higher Education came into effect. Solid progress has been made in designing a management information system (MIS) for higher education. The proposed restructuring will support refocusing the project to improve the project performance. IBRD Effective USD IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

202 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 201

203 Sector: received Additional Financing during Project Govt Finl Mgt & Revenue Admin Project (P085133) Indonesia 21-Dec Dec-2013 Central government administration (93%); Law and justice (7%) The project was restructured and extended in The new closing date for the project is December The restructured project will provide support to i) a new treasury system, ii) a new tax court case management system, iii) minor packages of technical assistance to the Indonesian Parliament and iv) capacity building in the fiscal policy office in the Ministry of Finance. To strengthen efficiency, governance and transparency in public financial management and revenue administration. There has been substantial progress toward development objectives with the signing of the contract for an integrated financial management information system (IFMIS). The contract for this system, designed to deliver improved budget and treasury execution, was signed in July In related areas the Government's cash management has been improved through the implementation of daily sweep of revenue accounts into the Treasury Single Account (TSA) for all commercial banks, while a Medium Term Expenditure Framework (MTEF) and Performance Based Budgeting (PBB) have also been introduced as part of a revised program structure with measurable results and targets for budget year of IBRD Effective USD IBRD-P4040 Closed USD IBRD-P4041 Closed USD IDA Effective XDR TF Closed USD TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

204 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 203

205 Sector: received Additional Financing during Project ID-Early Childhood Education and Dev (P089479) Indonesia 27-Jun Dec-2013 Pre-primary education (90%); Central government administration (5%); Sub-national government administration (5%) no The development objective of the project is to improve poor children's overall development and readiness for further education within a sustainable quality early childhood education development system. As a result of this project, targeted poor communities are now better able to engage in participatory planning to improve early childhood education and development services, and are receiving information, and expressing interest in participation. Block grants have enabled 2800 ECED facilities to be established and enroll more than 155,000 students. Policy on ECED standards is completed and awaiting Ministry approval. 38 of 50 districts have established ECED positions in district government. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09

206 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 205

207 Sector: received Additional Financing during Project ID-UPP3 (P084583) Indonesia 17-May Mar-2011 Other social services (32%); General transportation sector (29%); General water, sanitation and flood protection sector (13%); General education sector (13%); Health (13%) no To provide improved services for the urban poor and strengthen community and government institutions for responsive service delivery. The project has made very good progress toward achieving its objectives. Implementation has been completed in more than 1,700 urban wards (kelurahans), with activities and investments ongoing in another 500 kelurahans. Community Boards of Trustees (BKMs) established under the project in the kelurahans have improved community awareness, broadened participation, and strengthened capacity for community development planning and investment. The project includes 800 facilitators and city coordinators to provide implementation support and assistance at the district and kalurahan level. Through community grants and subloans it has helped finance construction or improvement of 1,500 km of small roads, 750 km of tertiary drainage, and 427 community health facilities, rehabilitated 8,170 of the poorest houses, and upgraded 10,400 community or household solid waste and sanitation facilities. Micro-credit has also been provided for more than 32,800 income-generating activities through community-administered revolving funds established and financed by the project. Overall the project has already benefited about 3.2 million households. IBRD Effective USD IBRD Effective USD IDA Effective XDR Status of Projects in Execution - FY09

208 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 207

209 Sector: received Additional Financing during Project Aceh Economic Dev Financing Facility (P109024) Indonesia 16-Dec Jun-2012 General agriculture, fishing and forestry sector (45%); Animal production (25%); General industry and trade sector (20%); Public administration- Agriculture, fishing and forestry (5%); Public administration- Industry and trade (5%) no The project will promote post-tsunami economic recovery and foster sustainable equitable long-term economic development in Aceh. To achieve this, the project will finance sub-projects that contribute toward the following development objectives, identified by the GoA as key for sustainable economic development in Aceh: (a) Development of job-creating, market-driven enterprises engaged in value-added processing and manufacturing, especially in agriculture and fisheries; (b) Sustainable improvement of production quality and value in agriculture, fisheries and estate crops that contributes to alleviation of poverty; (c) Increase in international trade, especially direct exports; and (d) Increase in domestic and foreign investment in Aceh. The Government of Indonesia and the World Bank negotiated the EDFF grant in December A sticky point in the negotiations, but one that was agreed upon, was the need for the DIPA to provide funds to the province as a block grant ('social aid'). The grant agreement was signed at the end of December 2008 and the project became effective on 30 March During project preparation but more intensively since the grant was signed, the World Bank team and the implementing agencies have had meetings with MoF to explain the project and ensure a smooth issuance of the DIPA. There has been relatively good progress on implementation otherwise, with a consulting firm selected to provide project management services to GoA and 86 subproject proposals having been received, signaling the high expectations that this project has created in Aceh. TF Effective USD Status of Projects in Execution - FY09

210 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 209

211 PINTAR (P100740) Indonesia 15-Jan Dec-2015 Sector: Central government administration (100%) received Additional Financing during no The objective is to improve operations core tax administration systems by re-engineering tax practices, upgrading Project information systems (using web-services), improving taxpayer compliance and reducing taxpayer and tax administration burdens. PINTAR became effective on 7th August IBRD Not Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

212 ID KDP Nias (P100766) Indonesia 26-Oct Nov Dec-2009 Sector: Other social services (100%) received Additional Financing during no The project objective is to support BRR's strategy for district Project and provincial reconstruction and rehabilitation by providing housing, schools, local government offices and infrastructure for resettlement. Implementation is significantly behind schedule, largely due to the challenges of recruiting and retaining qualified consultants and facilitators in the remote areas targeted by the project. However, notable improvements in implementation have been made since the beginning of At the close of the reporting period, 1,685 houses had been completed and 1,713 were under construction; 71 schools were under construction; 4 local government offices had been completed and 22 were under construction; and 5 public infrastructure projects had been completed and 43 were under construction. This is well short of the original output targets, and in light the importance of the project investments and recent improvement in its performance, extension of the project is under consideration so that it objectives can be fully achieved. TF Effective USD Status of Projects in Execution - FY09 211

213 Lending Information/Disbursement Summary (in millions USD) 212 Status of Projects in Execution - FY09

214 Sector: received Additional Financing during Project ID-UPP2 (P072852) Indonesia 11-Jun Mar Dec-2009 General education sector (27%); Roads and highways (27%); Health (27%); Other social services (13%); Sub-national government administration (6%) no To (a) establish or support representative and accountable community organizations able to provide services to the urban poor and increase the voice of the poor in public decisionmaking; (b) make local government more responsive to the needs of the poor through increased cooperation with community organizations; and (c) improve services for the urban poor (financial services, social services and infrastructure). Most of the project's objectives and outputs have been achieved or exceeded. So far, more than 7,000 elected community boards o f trustees (BKMs) have been formed, and the project has financed over 16,900 km of small roads, 4,200 km of tertiary drainage, rehabilitation of more than 59,000 of the poorest houses, more than 40,000 units of solid waste and sanitation facilities, and about 1,700 community health facilities. It has also provided micro-financing for more than 100,000 income-generating activities through communityadministered revolving funds. Overall the project has benefited 10.7 million households. IBRD Effective USD IBRD Effective USD IDA Effective XDR IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 213

215 Lending Information/Disbursement Summary (in millions USD) 214 Status of Projects in Execution - FY09

216 Sector: received Additional Financing during Project ID-SF-Aceh UPP3 Extension (P096647) Indonesia 24-Aug Feb Dec-2009 General water, sanitation and flood protection sector (50%); Sub-national government administration (50%) no The objective of this project is to provide support for reconstruction and rehabilitation to urban communities impacted by the earthquake and tsunami. The project is meeting its development objective. Most of the works in the 402 targeted villages have now been completed, and almost all results indicators have been met. About 226 km of roads, 1,282 meters of small bridges, 165 km of drainage, 787 units of water supply, 281 public latrines; and 684 waste disposal facilities have been constructed or rehabilitated. The overall quality of the works is moderate, but it has been progressively improving during the course of the project as the capacity of the communities has been enhanced. TF Effective USD Status of Projects in Execution - FY09 215

217 Lending Information/Disbursement Summary (in millions USD) 216 Status of Projects in Execution - FY09

218 Sector: received Additional Financing during Project ID-Farmer Empower. Agric.Tech.&Info (P083742) Indonesia 13-Feb Jun-2012 Agricultural extension and research (60%); General agriculture, fishing and forestry sector (15%); Central government administration (14%); Sub-national government administration (11%) no The objective of the project is to develop a demand-driven, market-oriented agricultural services system based on partnerships between farmer groups, public agencies and private sector enterprises. The project is making progress toward the development objective, but implementation has been substantially slower than expected due to regulatory changes, procurement delays, and weak interagency coordination. However, the pace of implementation has improved in recent months, and government commitment to the program is strong. Grants for Farmer-Managed Extension Activities (FMAs) have already been disbursed in most project districts. Evaluation of the program and particularly the FMAs is currently under way, both to assess its early performance and outcomes as well as to help fine-tune its focus and put in place appropriate quality control and enhancement mechanisms as the project moves forward. IBRD Effective USD IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 217

219 Lending Information/Disbursement Summary (in millions USD) 218 Status of Projects in Execution - FY09

220 ID-Java-Bali Pwr Sector & Strength (P063913) Indonesia 26-Jun Dec-2009 Sector: Power (80%); Central government administration (20%) received Additional Financing during no The objective is to improve the reliability and efficiency of the power system in Java-Bali and strengthen the management Project capabilities of Indonesia's state power company (PLN) and state oil and gas company (PGN). The project made good progress in the past year and is on track to achieve its development objective. When completed, investments in the transmission network will reduce loadings at key 500kV and 150kV substations in Java-Bali and improve voltages at 150kV substations in southeastern Java. The capacity of the PLN has been strengthened, including the implementation of an integrated Enterprise Resource Planning system that has substantially improved the management of finances, materials, and human resources in all PLN business units in Java and Bali. Additional financing is under consideration to enable deployment of this system to Sumatra and Sulawesi as well. Technical studies have provided valuable inputs for improving energy markets and institutions, including a feasibility study funded by the project for the proposed $550 million Upper Cisokan Pump Storage hydropower plant that would increase peak generating capacity in Java IBRD Effective USD IBRD Effective USD Status of Projects in Execution - FY09 219

221 Lending Information/Disbursement Summary (in millions USD) 220 Status of Projects in Execution - FY09

222 Sector: received Additional Financing during Project ID-LAND MANAGEMENT &POLICY DEVT (P064728) Indonesia 29-Apr May Dec-2009 Central government administration (58%); Sub-national government administration (24%); Other social services (12%); Law and justice (4%); General agriculture, fishing and forestry sector (2%) no The objectives are to (a) improve land tenure security and enhance the efficiency, transparency and service delivery of land titling and registration and (b) enhance local government capacity to undertake land management functions with greater efficiency and transparency. Overall progress has been more modest than expected, and the project is not likely to fully achieve its objectives before the closing date. On the first objective, sound progress has been made in title distribution to improve land security, with about 2 million title certificates distributed to landowners. There have also been reasonable advances in developing a strategic land policy. However, there has been little progress in enhancing service delivery, governance, land records management, or land information systems. On the second objective, the project has helped strengthen the land administration and management capacity of nearly 400 local governments, and it is expected that this objective will be fully achieved. IBRD Effective USD IBRD Effective USD IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 221

223 Lending Information/Disbursement Summary (in millions USD) 222 Status of Projects in Execution - FY09

224 Sector: received Additional Financing during Project ID-Geothermal Power Generation Dev (P099757) Indonesia 29-May Jun-2011 Renewable energy (50%); Power (25%); Central government administration (25%) no The objective is to promote the expansion of economic and environmentally friendly geothermal power generation in Indonesia and reduce CO2 emissions from the power system. The project became effective in October 2008 and it is still too early in implementation to show tangible results. The Ministry of Energy and Mineral Resources (MEMR) has made good progress toward initiating activities aimed at (a) developing and implementing a pricing and incentive policy to address the incremental costs of geothermal power development and (b) designing a set of transaction procedures for competitively tendering greenfield geothermal development sites and for incentivizing expansion of power generation capacity in existing geothermal fields. A stakeholders group has been established as an advisory sounding board for the sector's reform program. TF Effective USD Status of Projects in Execution - FY09 223

225 Lending Information/Disbursement Summary (in millions USD) 224 Status of Projects in Execution - FY09

226 Sector: received Additional Financing during Project ID-Aceh-Infra. Reconstr Enabling Program (P100218) Indonesia 30-Jun Jun-2010 Water supply (25%); General water, sanitation and flood protection sector (25%); Roads and highways (25%); Ports, waterways and shipping (25%) no The objective of the Infrastructure Reconstruction Enabling Program (IREP) is to support the BRR's strategy for infrastructure reconstruction by providing high quality technical assistance services in infrastructure program management, planning, design, construction management, quality management and program monitoring. The Project will support BRR in overall coordination of the infrastructure reconstruction program. The project, which consists of five technical assistance packages, continues to make good progress toward achieving its objective. The performance of the five consultants providing technical assistance to the implementing agency continues to improve. The planning and design phases of the project have been successfully completed. The construction management, quality management, program monitoring, and training phases are ongoing. Some of the outputs of the project included significant on-the-job training for local contractors and local government engineers with respect to quality assurance and control procedures. The assistance and oversight provided under IREP has been critical to planning, implementing, and ensuring the quality of works financed by the Aceh Infrastructure Reconstruction Facility (IRFF), which includes road rehabilitation as well as ports, water, and flood protection subprojects. TF Effective USD Status of Projects in Execution - FY09 225

227 Lending Information/Disbursement Summary (in millions USD) 226 Status of Projects in Execution - FY09

228 ID Water and Sanitation Program (P095685) Indonesia 10-Feb-2005 Sector: Sanitation (50%); Water supply (50%) received Additional Financing during no The project development objective is to provide capacity building and technical assistance to bring about reformed and Project capable institutions for water and sanitation services and to support the development of related sector investment programs in Indonesia. the development objective improved significantly during the past year. The government's commitment to improve water supply and sanitation services is reflected in the development of new policies and regulations that include pro-poor approaches, as well as increased budget for the sector at both the national and local level. In the past year 12 cities have been assisted in the development of Citywide Sanitation Strategic Plans (CSSs) and 6 have already started implementation of the plans. The water for the poor program has proved successful and will be scaled up. Significant steps have been taken to increase investments and improve financial regulations in the sector to improve the performance, coverage, and sustainability of water utilities and sanitation development. Status of Projects in Execution - FY09 227

229 Sector: received Additional Financing during Project ID-SF-Aceh Community Settlement Reconstr (P096248) Indonesia 14-Sep Feb Feb-2010 Housing construction (80%); General water, sanitation and flood protection sector (20%) no The objective is to restore the living conditions (housing and basic infrastructure) of the communities affected by the devastating effects of the earthquake and tsunami that struck Nanggroe Aceh Darussalam and Nias on December 26, The project is well advanced in achieving its objective, has already completed most of its investments, and has nearly met all of its targets. Almost all of the housing rehabilitation (about 7,000 units) and reconstruction (about 8,000 units) has been completed. The project is in the final stages of restoring community infrastructure in about 180 villages, which significantly exceeds the original number targeted. The infrastructure completed so far includes 68 km of roads, 185 m of bridges, 83 km of drainage with more than 260 culverts and distribution boxes, 22 km of retaining walls, 194 water supply sources, and numerous other facilities such as community toilets and wash units, meeting halls, and street lighting. In general the quality is good, although in some areas significant improvements are required. It is expected that all works will be completed by the project closing date. TF Effective USD Status of Projects in Execution - FY09

230 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 229

231 Sector: received Additional Financing during Project ID-Strategic Roads Infrastructure (P079906) Indonesia 06-Jul Dec-2011 Roads and highways (92%); Central government administration (8%) no The objective is to improve economic competitiveness by improving the capacity and quality of strategic national roads on the islands of Java and Sumatra, improving road safety, and increasing the efficiency, quality, and transparency of civil works procurement and implementation in the Ministry of Public Works. The project got off to a slow start and during the past year it continued to experience delays, but is now beginning to make progress. Construction on the six large road contracts currently under way is going well, and work on a new group of roads is expected to begin toward the end of Although the project is substantially behind schedule, the issues that were causing the delays are largely resolved. As the efficiency, quality, and transparency of procurement continue to improve, the pace of implementation on civil works investments is expected pick up sharply. IBRD Effective USD IBRD-P4080 Closed USD IBRD-P4081 Closed USD TF Closed USD Status of Projects in Execution - FY09

232 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 231

233 Sector: received Additional Financing during Project ID: Dam Operational Improvement (DOISP) (P096532) Indonesia 19-Mar Dec-2013 General water, sanitation and flood protection sector (88%); Public administration- Water, sanitation and flood protection (12%) no The objectives are to (a) increase safety and functionality with respect to the bulk water supply of large reservoirs owned by the Ministry of Public Works, and (b) strengthen the safety and operational management policies, regulations, and administrative capacity of the Ministry of Public Works. The project had just become effective before the close of the reporting period. IBRD Not Effective USD Status of Projects in Execution - FY09

234 ID-BOS KITA Project (P107661) Indonesia 07-Oct Dec-2010 Sector: Primary education (70%); Secondary education (30%) received Additional Financing during no The objective of the Project is to improve access to quality education in Indonesia for all children of ages 7 to 15 by strengthening school-based management and community Project participation, improving existing fiduciary arrangements for greater transparency and accountability of the BOS program and, consequently, bringing about better utilization of BOS funds. The project is progressing well. There has been an increase in new student enrolment and in dropouts returning to school since the Government applied a higher unit cost for school operational assistance funds for The Government s manual for implementing the program has been revised to increase transparency and improve monitoring throughout the system, and representatives from schools, communities and local governments across the country have received training on it and on school based management more generally, under a supplementary Dutch Trust Fund. This Fund is also supporting a national social information campaign. The impacts of the training and the campaign will be seen next year. IBRD Effective USD Status of Projects in Execution - FY09 233

235 Lending Information/Disbursement Summary (in millions USD) 234 Status of Projects in Execution - FY09

236 Sector: received Additional Financing during Project ID - National UPP (PNPM UPP) (P096921) Indonesia 20-May Dec-2011 Roads and highways (27%); Health (27%); General education sector (27%); Other social services (13%); Sub-national government administration (6%) Additional financing of $115 million was approved in April 2009 to help finance the costs associated with scaled-up activities designed to enhance the impact of this wellperforming project. The closing date was also extended by nine months. The additional financing had not become effective before the close of the reporting period. The project development objective is to ensure that the urban poor in PNPM-Urban locations benefit from improved socioeconomic and local governance conditions. The project is making good progress toward its objectives. Small-scale community works are progressing in all the targeted kelurahans, and about 7,000 facilitators and coordinators are in place. The key project performance indicators have generally been met. More than 8,000 elected community boards of trustees (BKMs) have been formed and more than US$70 million in grant financing has been disbursed to kelurahans. The largest amount of grant financing is for infrastructure investments (65%), followed by productive activities (20%) and social activities (15%). The project has financed over 22,000 km of small roads, 6,000 km of drainage, rehabilitation of 80,000 of the poorest houses, 105,000 units of solid waste and sanitation facilities, and 12,700 community health facilities. It has also financed 136,000 income-generating activities through the revolving funds. IBRD Effective USD IBRD Not Effective USD IDA Effective XDR Status of Projects in Execution - FY09 235

237 Lending Information/Disbursement Summary (in millions USD) 236 Status of Projects in Execution - FY09

238 Sector: received Additional Financing during Project ID-BERMUTU (P097104) Indonesia 05-Jul Dec-2013 Tertiary education (78%); Central government administration (19%); Sub-national government administration (3%) no The objective is to contribute to the improvement of the overall quality and performance of teachers through enhancing teachers ' knowledge of subject matter and pedagogical skills in the classroom. Amount of funds that the Government has made available in their current budget document (DIPA) is very limited and the process to revise it (to include the required additional amount) has been long delayed; and accordingly the disbursement has been very slow. However, despite of these problems, the Government has managed to strategically allocate the existing funds within three key directorates so they are able to implement some key tasks which are foundations for other activities. Hence, the project demonstrates some considerable progress on some key activities which will lead to the achievement of PDO: (i) First batch of Accreditation Incentive Grants have been awarded to seven selected teacher training universities (LPTKs) and selection for the second batch is being finalized; (ii) First batch of the competitive Distance Learning Development Grants (DIP BPJJ) program which is aimed to increase the quantity and improve the quality of learning materials of PGSD S1 Distance Learning Program has been awarded for development of 14 subjects (iii) Various manuals for the working group of teacher, principal and supervisors are well in place and learning packages for teachers are being refined; (iv) selection of the proposals of the teachers working group grants is being processed and grants will be awarded (first batch) by end of September 2009; (v) Regulation/guidelines for Recognition of Prior Learning for teachers who are doing upgrading to S1 (bachelor degree) is well in place and has been socialized to relevant universities and policy makers; (vi) preparation of the induction program modules for beginning teachers and an instrument for classroom performance reporting on probationary teachers by the principal; (vii) development of a new structure for teachers performance evaluation, promotion and progression are in progress; and (viii) With strong facilitation from the Bank Task Team, the design and implementation arrangement of the impact evaluation are being refined; test items to measure teachers and students academic/substantive knowledge have been field tested. Note: It is expected that disbursement rate Status of Projects in Execution - FY09 237

239 will significantly increase in October 2009 upon the disbursement of the grant program (see point iv above) IBRD Effective USD IDA Effective XDR TF Effective USD Lending Information/Disbursement Summary (in millions USD) 238 Status of Projects in Execution - FY09

240 Sector: received Additional Financing during Project ID SPADA in Aceh and Nias (P097605) Indonesia 22-Dec Dec-2010 Other social services (40%); Health (30%); General education sector (30%) no The objectives are to strengthen governance, promote growth, and improve service delivery in participating provinces and districts. Although implementation has been slowed by procurement issues and recurring delays in budget allocation, the project has made reasonably good progress toward achieving its objectives. Planning and implementation of subproject investments in health and education facilities and services is going well. Local stakeholders, including government officials and communities, express satisfaction with the project activities and results, except when budgetary delays slow implementation. Despite some setbacks, the project is still likely to meet most of its goals. TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 239

241 Lending Information/Disbursement Summary (in millions USD) 240 Status of Projects in Execution - FY09

242 ID - Aceh Forest and Environment Project (P098052) Indonesia 10-Feb Aug Jun-2010 Sector: Forestry (100%) received Additional Financing during no The objective of the project is to protect critical environmental resources and services from the Leuser and Ulu Masen forest ecosystems during the post-tsunami reconstruction process. The project will also contribute toward mitigating negative Project impacts of reconstruction on the forests of Aceh, mainstreaming of environmental concerns into planning processes, and building sustainable capacity and institutions for forest protection. The project is making good progress toward achieving its objective. Through the project, a sustainable funding mechanism is being developed that is one of the most advanced initiatives in the world for Reducing Emissions from Deforestation and Degradation (REDD). In addition, the multistakeholder management framework for the Leuser and Ulu Masen forests and the construction of a provincial-level spatial plan are expected to be completed by the end of One of the project executing agencies, Fauna & Flora International, is working with local communities to map their customary forests and develop a REDD benefit-sharing mechanism to provide real and significant incentives to protect the forest of Ulu Masen. TF Effective USD TF Effective USD Status of Projects in Execution - FY09 241

243 Lending Information/Disbursement Summary (in millions USD) 242 Status of Projects in Execution - FY09

244 Sector: received Additional Financing during Project ID- Indo Infrastructure Finance Facility (P092218) Indonesia 24-Jun Dec-2013 Power (48%); Roads and highways (34%); Railways (11%); Ports, waterways and shipping (4%); Oil and gas (3%) no To strengthen and further develop the institutional framework of the financial sector to facilitate financing of commercially viable infrastructure projects, and thereby increase provision of private infrastructure in Indonesia. The project is not yet effective. IBRD Not Effective USD Status of Projects in Execution - FY09 243

245 Sector: received Additional Financing during Project ID Kecamatan Development Project 3B (P092019) Indonesia 24-Mar Jun Dec-2009 Sub-national government administration (25%); Water supply (20%); Irrigation and drainage (20%); Roads and highways (20%); Primary education (15%) no KDP3B has the overall development objectives of reducing poverty and improving local level governance in rural Indonesia. The project has performed well and is ahead of schedule on most of its output and outcome targets. The program's proven and flexible platform successfully allowed for a relatively smooth transition to a full national scale-up of activities in 2009, particularly for such a large project. Efforts to strengthen the management of revolving funds for sustainable local microfinance have been more successful than in previous projects. Development of an inter-village community oversight organization, a key step toward ensuring sustainable microfinance, is well advanced. IBRD Effective USD IBRD Effective USD IDA Effective XDR IDA Effective XDR TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

246 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 245

247 Sector: received Additional Financing during Project ID-USDRP (P071296) Indonesia 07-Jun Jun-2011 General industry and trade sector (69%); General transportation sector (22%); Central government administration (4%); Other social services (3%); Sub-national government administration (2%) no The project development objective is to improve urban services in participating municipalities. There has been good progress in improving the specific urban services selected by the local governments currently participating in the project, but there have been substantial delays in overall implementation. So far the urban investments have focused on rehabilitating and improving public markets and a transport terminal. However, because a number of the original participating governments dropped out of the program, implementation of investments in urban services will continue to lag until new participants finalize the process of joining the project and having their investment proposals approved. Initiation of the project's governance, reform, and capacity building activities was significantly delayed, but in recent months most of these activities have gotten under way as well. IBRD Effective USD IBRD Effective USD TF Closed USD TF Effective USD Status of Projects in Execution - FY09

248 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 247

249 Sector: received Additional Financing during Project ID - Coral Reef Rehab and Mgmt Prog II (P071316) Indonesia 25-May Apr Dec-2009 Other social services (35%); Sub-national government administration (30%); General agriculture, fishing and forestry sector (15%); Micro- and SME finance (12%); General education sector (8%) no The objective is to establish viable reef management systems in at least six priority Participating Districts through a financially sustainable program that is coordinated nationally but decentralized in implementation. This will empower and support coastal communities to sustainably co-manage the use of coral reefs and associated ecosystem resources, which will revive damaged or preserve intact coral reef ecosystems and, in turn, enhance the welfare of these communities. It is unlikely that the program will achieve its objectives by the current closing date. Despite initial delays and intermittent budget problems, the program has made important steps in organizing communities, developing sustainable coral reef management plans, and raising public awareness. However, the program has made limited progress in terms of actually creating enforceable conservation areas, implementing effective and sustainable community-based management, or achieving measureable gains in the restoration of reefs. The program operates in 257 villages, has established 15 local program implementation units, and has disbursed seed funds and village grants. On paper, collaboratively managed marine conservation areas cover more than 10 percent of reefs in the project target area, but it is too early to assess their effectiveness. The incomes of fishing households have increased in some communities, but this may be due to higher fish prices and larger catches (which may be putting more strain on fisheries) rather than the project's alternative income program. IBRD Effective USD IDA Effective XDR TF Closed USD TF Closed USD Status of Projects in Execution - FY09

250 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 249

251 Livelihood Rec. DI Yogyakarta & Cen Java (P109710) Indonesia 17-Feb May-2010 Sector: Micro- and SME finance (100%) received Additional Financing during no To assist micro, small and medium enterprises (MSMEs) affected by the earthquake to revitalize their businesses and to Project re-integrate affected low income communities back into economic life. Implementation has been slower than expected due to delay in finalizing the negotiations. Nevertheless, after signing the Grant Agreement, progress has been made in finalizing the complex mechanism for providing financial assistance via PNM, the wholesale bank, and the selected Financial Intermediaries in the region. Consensus with PNM as the main partner for channeling part of the Grant funds for financial assistance was reached, the MoU has been signed, and the project has become effective. TF Effective USD Status of Projects in Execution - FY09

252 Kiribati Project Name(ID): Sector: received Additional Financing during Project KI Adaptation Program PhaseII -Pilot Imp (P089326) Kiribati 01-Jun Nov Dec-2010 General public administration sector (45%); General agriculture, fishing and forestry sector (26%); Central government administration (24%); Sub-national government administration (5%) no The objective of the Adaptation Program Phase II is to integrate climate risk awareness and response into economic planning and pilot cost-effective climate change adaptation measures in priority sectors. the development objective has been much slower than planned, mainly due to human resources constraints that have since been resolved. Despite these initial delays, the project has made important strides in terms of (a) increasing awareness and participation at both the national and local level, (b) developing an updated water resource policy and implementation plan, (c) providing training in coastal hazard assessment and response, and (d) strengthening climate risk management capacity. In light of the ambitious scope and timeline of the original project design, the closing date has been extended by 18 months and a proposal is under consideration that would refocus the project s scope and simplify its implementation structure. TF Closed USD TF Effective AUD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 251

253 Lending Information/Disbursement Summary (in millions USD) 252 Status of Projects in Execution - FY09

254 Lao People's Democratic Republic Project Name(ID): LA - GMS Power Trade Project (P105331) Lao People's Democratic Republic 05-Jun Dec-2013 Sector: Power (86%); Renewable energy (14%) received Additional Financing during no The objective of the Project is to enhance power trade within Greater Mekong Sub-Region with a view to bringing reliable Project electricity to the Saravan province in Lao PDR, and creating the conditions for eventual interconnections of Lao PDR with other countries of the region. the development objective is well on track. The transmission line from Ban Hat province in Lao PDR to Cambodia has been delayed for six months due to procurement delays on the Cambodia side, but still could be achieved by project closing. Implementation of other components is on track: (i) the transmission line from Xeset 1 to Saravan substation is being installed and should be completed by December 2010; (ii) feasibility study for Houay Lamphan Gnai Hydro site will be completed by December 2009; (iii) bids for the design and supervision of the Load Dispatching Center are under evaluation; and (iv) the feasibility study for the 500 kv Collector Substation System in southern Lao PDR has been completed, with financing from the Asian Development Bank. All these activities will contribute to enhancing power trade within the Greater Mekong Sub-Region by bringing reliable electricity to the project areas. IDA-H3000 Effective XDR Status of Projects in Execution - FY09 253

255 Lending Information/Disbursement Summary (in millions USD) 254 Status of Projects in Execution - FY09

256 Sector: received Additional Financing during Project Lao Environment and Social Project (P090693) Lao People's Democratic Republic 30-Jun Jun Dec-2010 Central government administration (48%); Forestry (25%); Other social services (11%); Sub-national government administration (9%); General education sector (7%) no The objective of the project is to strengthen the management of environmental and social issues associated with the sustainable use of natural resources to enhance the quality of growth and reduce poverty. The project's performance in terms of number and quality of sub-grants has improved. The sub-grants focusing on developing capacity of agencies have helped to: (a) develop and improve regulatory and institutional implementation frameworks fundamental for ensuring sustainable use of natural resources (i.e., the Environmental and Social Impact Assessment); (b) forge oversight actions on existing hydropower projects; (c) facilitate safeguard actions at provincial level; and (d) initiate an institutional process to establish a river basin organization in one river basin. Technical assistance and operational support to these subgrants will ensure that the key agencies have adequate technical and management capacity to respond to the pressing needs due to the exponential growth in the hydropower and mining sectors. Similarly, sub-grants focusing on the community and conservation are helping raise awareness related to protected area management, promoting natural resource protection, and improving livelihoods of people. With these types of sub-grants, achieving the PDO is likely especially since the technical and operational capacity of implementing agency has strengthened. IDA-H1770 Effective XDR Status of Projects in Execution - FY09 255

257 Lending Information/Disbursement Summary (in millions USD) 256 Status of Projects in Execution - FY09

258 Lao PDR Customs & Trade Facilitation (P101750) Lao People's Democratic Republic 17-Jun Dec-2013 Sector: Central government administration (100%) received Additional Financing during no The objective of the project is to facilitate trade by improving the efficiency and effectiveness of customs administration. The Project Project will simplify customs procedures, eliminate duplication and redundancy, reduce transactions costs and time to clear goods, and increase transparency and accountability The project had a slow start and progress towards achieving PDO in FY09 is lagging. The finalization of the ASYCUDA contract which was planned to be executed shortly after project effectiveness, was delayed for several months, mainly due to unclear and complex procedural aspects. However, this delay has provided an opportunity to improve the contract clauses by integrating some valuable lessons learnt from other similar projects at evaluation phase. The project is now back on track and implementation will be accelerated over the next fiscal year to make up for lost time. IDA-H4030 Effective XDR Status of Projects in Execution - FY09 257

259 Lending Information/Disbursement Summary (in millions USD) 258 Status of Projects in Execution - FY09

260 Sector: received Additional Financing during Project LA-Poverty Reduction Fund Project (P077326) Lao People's Democratic Republic 25-Jun Dec Sep-2011 General transportation sector (28%); General education sector (28%); Other social services (25%); Central government administration (11%); Sub-national government administration (8%) The proposed additional financing supports the Project scale up and restructuring in the form of a 3 year extension of activities of the PRFP in the 14 poorest districts it already covered (out of 21 currently covered), initiating activities in 5 new poor districts, and adding a new sub-component, #Capacity Building of Local Institutions#, intended to promote participatory planning by enhancing the dialogue between communities and local governments. The village targeting mechanism and key performance indicators have also been modified to strengthen the pro-poor focus of the PRFP. The project aims to: (i) improve the access to public infrastructure and services at the village level; (ii) build capacity and empower villages in poor districts to manage their own public investment planning; and (iii) strengthen local institutions to support participatory decision making and conflict resolution processes at the village, inter-koumban, and district levels. The Project is progressing towards achieving the development objectives. From the beginning of implementation, the Project has financed 1924 non-training subprojects, complemented by 498 training subprojects, with coverage of 1471 villages. IDA Effective XDR IDA-H4180 Effective XDR IDA-Q3350 Closed USD Status of Projects in Execution - FY09 259

261 Lending Information/Disbursement Summary (in millions USD) 260 Status of Projects in Execution - FY09

262 Sector: received Additional Financing during Project LA-Avian and Human Influenza Control (P100081) Lao People's Democratic Republic 29-Jun Jun-2011 General public administration sector (35%); Health (29%); Agricultural extension and research (20%); Animal production (12%); Other social services (4%) no Contribute to Government's National Plan which aims to minimize the threat posed to humans and poultry sectors by highly pathogenic avian influenza infection and other zoonoses in Lao PDR, and to prepare for, control, and respond to influenza pandemics and other infectious disease emergencies in humans. During this fiscal year, 100% of diagnostic tests of suspected poultry cases were done within 48 hours (against 70% in 2008), and 100% of human cases were investigated within 24 hours (against 94% in 2008); Provinces providing timely weekly surveillance reports stands at 95%. Pandemic Plans have been prepared by 11 Provinces and 10 await approval by the Provincial CDC Committee chair; the remaining (6) Pandemic Plans are under preparation. Training has been, and will continue to be, the focus for animal health over the coming year, as will activities associated with pandemic preparedness. IDA-H2430 Effective XDR TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09 261

263 Lending Information/Disbursement Summary (in millions USD) 262 Status of Projects in Execution - FY09

264 Sector: received Additional Financing during Project LA-Health Services Improvement Project (P074027) Lao People's Democratic Republic 13-Sep Oct Jun-2011 Health (90%); Central government administration (5%); Compulsory health finance (5%) no To assist the Lao PDR to improve the health status of its population, particularly the poor and rural population, in eight Central and Southern Provinces. Available data indicate mixed progress towards the development objectives, with significant improvements in some indicators and slower progress in others. Weaknesses in monitoring data remain, however, making reliable assessment difficult. Progress in implementing key project activities and addressing concerns raised in the MTR indicate good prospects for sustained progress towards development objectives. Important achievements in this regard include: (1) strengthening of mechanism to support integrated maternal and child health activities at the village level; (2) development of plans to pilot free facility-based delivery; (3) implementation of health equity fund approach to improve access to services for the poor; and (4) training of students from ethnic minorities to strengthen provision of services in remote areas. IDA-H1830 Effective XDR IDA-Q4760 Closed USD TF Closed USD Status of Projects in Execution - FY09 263

265 Lending Information/Disbursement Summary (in millions USD) 264 Status of Projects in Execution - FY09

266 Sector: received Additional Financing during Project LA-Fin. Management Capacity Building Cr. (P077620) Lao People's Democratic Republic 25-Jun Dec Apr-2011 Central government administration (58%); Banking (35%); General industry and trade sector (7%) no The objective is to improve GOL budget preparation, execution, reporting and auditing systems; strengthen monitoring of state owned commercial bank operations, and to improve financial management of selected state owned enterprises. Progress towards meeting the development objectives has been good. For the first time, in-year budget execution reports were published for FY2008/9 in February The state audit organization submitted the annual audit report to Parliament in the June 2009 session. The standard bidding documents and procurement manual was adopted in June The revised chart of accounts was implemented for the FY2008/9 budget year (October 2009). The Treasury Single Account framework was adopted and budget revenue accounts consolidated under the National Treasury. Restructuring plans for 4 SOE's under restructuring were completed, and the SOE's sector strategy work commenced. IDA Effective XDR IDA-H3160 Effective XDR TF Closed USD Status of Projects in Execution - FY09 265

267 Lending Information/Disbursement Summary (in millions USD) 266 Status of Projects in Execution - FY09

268 Sector: received Additional Financing during Project LA-Second Education Development (P078113) Lao People's Democratic Republic 29-Apr Mar Feb-2010 Primary education (54%); Central government administration (35%); Tertiary education (11%) AusAID provides AUD 990,000 to cover the shortfall of devaluation of Australian dollar against UD dollar and Lao kip in order to complete all Component A activities in the additional 127 communities. The development objective is to increase primary school enrollment and completion (reduce repetition and drop-out rates) in the 19 poorest provinces. The project is making good progress towards achieving its objective as evidenced by 110,626 enrolled in the Project's target districts against a 2009/10 goal of 95,000. IDA Effective XDR IDA-H0840 Effective XDR IDA-Q3930 Closed USD TF Closed USD TF Effective AUD Status of Projects in Execution - FY09 267

269 Lending Information/Disbursement Summary (in millions USD) 268 Status of Projects in Execution - FY09

270 LA-Rural Electrification Phase I (P075531) Lao People's Democratic Republic 27-Apr Mar-2010 Sector: Power (85%); Renewable energy (15%) received Additional Financing during no The objectives are to increase access to electricity of rural Project households in villages of targeted provinces and improve financial performance of the power sector. The project continues to make good progress toward achieving its development objectives. For the grid extension to rural areas, connections for about 42% of the project targeted rural households had been made by the end of FY09, and 70% will be achieved by September 2009 at the current rate of progress. However, only 70% of project targets can be achieved with the original Credit funds due to price escalations for materials. Therefore, the remaining 30% of targets will be achieved through additional financing from Australian bilateral assistance (AusAID). For AusAid-funded activities, procurement is under way and completion is expected by December In off-grid electrification, 90% of the targeted connections should be made by October The additional financing and the necessary closing date extension will be processed in FY10. With the good results achieved to date and the additional financing, the project should increase access to electricity of rural households as foreseen. Implementation of the Action Plan for financial sustainability of the power sector is proceeding very well. The national electricity utility has closed its fiscal year with profits since 2007, due to the outstanding results on loss reduction (achieving 13% in 2009, well beyond the project target of 17%), good progress on settlement of Government arrears, and highly satisfactory tariff adjustments. Thus the project has achieved its objective of improving the financial performance of the power sector. IDA-H2180 Effective XDR TF Closed USD Status of Projects in Execution - FY09 269

271 Lending Information/Disbursement Summary (in millions USD) 270 Status of Projects in Execution - FY09

272 Sector: received Additional Financing during Project LA-Trade Development Facility Project (P106165) Lao People's Democratic Republic 16-Nov Feb-2012 General industry and trade sector (70%); Other domestic and international trade (30%) no The Trade Development Facility Project's development objective is to support the establishment of the National Integrated Frame work Governance Structure (NIFGS) and implement NIFGS's initial activities facilitating trade and crossborder movement of goods and increasing the capacity of the Government to undertake specific tasks related to regional and global economic integration. These activities in turn support the GOL's larger aims of poverty reduction and economic development, as reflected in the National Socio Economic Development Plan (NSEDP). The project became effective during the year under review and has had a successful first six months of implementation. The institutional structure for coordination has been put in place and investments have been made to expand the capacity of the core agencies responsible for implementing the program. A number of core diagnostic activities have been carried out, including in the garments and silk sectors. A draft Trade Facilitation Action Plan has been prepared. Support was provided to the GoL team during ongoing WTO accession negotiations. TF Effective USD Status of Projects in Execution - FY09 271

273 Lending Information/Disbursement Summary (in millions USD) 272 Status of Projects in Execution - FY09

274 Sector: received Additional Financing during Project LA-Public Fin. Mgnt. Streng MDTF (P108787) Lao People's Democratic Republic 15-Nov Oct-2011 General public administration sector (40%); Central government administration (30%); Sub-national government administration (30%) no Assist the Government of Lao PDR in: (i) improving budget planning; (ii) enhancing the quality of budget execution systems; (iii) foster increased reporting and transparency of public finances; and (iv) improving timeliness and quality of external audit The Multi-donor Trust Fund became effective in January 2009, following some delay in government approval of the grant. The MDTF was formally launched by the MOF, development partners and the World Bank in February The first annual work plan and half-year budget have been prepared and implementation has actually started. Major areas of support from the MDTF for this year are: introduction of Value Added Tax, technical design of the Treasury Information Management Information System, completion of centralization of treasury, tax and custom administrations. The main obstacle that affects the pace of implementation of MDTF activities is the weak procurement capacity of the PFMSU, the unit of Ministry of Finance which is responsible for providing trust fund implementation services. TF Effective USD Status of Projects in Execution - FY09 273

275 Lending Information/Disbursement Summary (in millions USD) 274 Status of Projects in Execution - FY09

276 LA-SUSTAINABLE FORESTRY FOR RURAL DEV. (P064886) Lao People's Democratic Republic 24-Jun Sep Dec-2011 Sector: Forestry (100%) received Additional Financing during Project With approval of $10 million in additional financing in December 2008, the project has been expanded to implement participatory sustainable forest management in production forest areas (adding five provinces and 19 districts, and effectively doubling the size of the project area from 650,000 hectares (ha) to 1.28 million ha) and further develop opportunities for community involvement. Additional progress on benefit-sharing with local communities from sales of timber is expected in the coming year. The objective is to achieve the sustainable management of production forests to alleviate rural poverty in the Project Provinces. Project achievements to date include the establishment of a nationwide Production Forest Area (PFA) system consisting of 51 PFAs covering about 3.6 million ha; the development of a national code of practice for production forests and guidelines on revenue-sharing and competitive timber sales; and successful implementation of Participatory Sustainable Forest Management (PSFM) in eight priority PFAs of four provinces covering about 650,000 ha. Of these 50,000 ha (in five subforest management areas in two provinces) have been certified in compliance with international standards of the Forest Stewardship Council (FSC). Independent audits have reconfirmed the sustainability of demonstrated forest management practices. In addition, village institutions for PSFM implementation and village development (VD) have been established and are functioning in all 18 project districts and 412 villages, with communities participating in all forest management and village development activities, which are funded by timber revenues and supplemental village grants provided by the project. This level of community participation will enhance sustainability. Forest monitoring and control systems have been developed and piloted at a significant scale and are expected to contribute to monitoring Reduced Emissions from Deforestation and Degradation (REDD) implementation as this program becomes operational in Lao PDR. Status of Projects in Execution - FY09 275

277 IDA Effective XDR IDA-H4460 Effective XDR TF Closed USD Lending Information/Disbursement Summary (in millions USD) 276 Status of Projects in Execution - FY09

278 Sector: received Additional Financing during Project LA-ROAD MAINT APL2 (P083543) Lao People's Democratic Republic 30-Jun Apr Dec-2009 Roads and highways (97%); Central government administration (3%) no The second phase Road Maintenance Program will expand the operation of financing and management systems for the sustainable roads maintenance with two primary objectives: (a) national and local road assets are preserved to provide sustainable improved travel and access; and (b) sustainable financing and management of roads are operational countrywide with improved institutional capacity. The project development objectives have substantially been achieved. Eighty-three percent of paved National roads are in excellent or good condition and 46% of the provincial road network is in good to fair condition. Domestic revenue has been mobilized to cover 82% and 9.4% of routine maintenance costs for National and provincial roads respectively. Since the start of the project 1,548km and 2,313km of National and provincial roads respectively have received periodic maintenance. Three-year performance contracts have been used for 3,864km of National roads. Significant achievements have been made in particular on increasing revenue collection for the Road Maintenance Fund, which is a domestic financing mechanism for road maintenance, with revenue collected from the road users, from approximately US$2 million in 2002 to US$20 million in The Fund is now adequate to cover 60% of the total needs for maintenance of the National road network. Progress on institutional capacity strengthening has also been reasonably good. Although there are still huge needs for further support, organizational aspects have been improved. Much road management has been tasked to provincial authorities, including planning, budgeting and contract management, leaving monitoring and supportive functions at central level. A large number of Ministry staff members at central, provincial and district levels have received training on technical, financial, contract management, and management. Progress on private sector development has also been made. A framework for national contractors and consultants capacity strengthening, including introduction of best commercial practice, financing mechanism design, improvement of public and private partnership, and contractor training, is being developed. Status of Projects in Execution - FY09 277

279 IDA Effective XDR TF Closed USD TF Effective USD TF Effective AUD Lending Information/Disbursement Summary (in millions USD) 278 Status of Projects in Execution - FY09

280 Sector: received Additional Financing during Project LAO PDR: Rice Productivity Improvement (P114617) Lao People's Democratic Republic 13-Jan Dec-2011 Crops (62%); Public administration- Agriculture, fishing and forestry (20%); Agricultural extension and research (18%) no The project objective is to improve smallholder incomes and food security by improving productivity of rice, the main crop, with better seed multiplication systems and good agricultural practices. The project became effective in the latter part of the reporting period and was still in too early a stage for meaningful progress. TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 279

281 Sector: received Additional Financing during Project LA-Khammouane Development Project (P087716) Lao People's Democratic Republic 17-Jun Mar-2014 Sub-national government administration (36%); Irrigation and drainage (24%); General agriculture, fishing and forestry sector (18%); Roads and highways (11%); Water supply (11%) no The project development objective is to strengthen the planning process and public financial management associated with the decentralized delivery of services and infrastructure, including irrigation development, in Khammouane Province. Implementation of the project just started in early The project office was set up with adequate staff and equipment. The key teams are fully functional and actual physical implementation of the project should begin in FY10. IDA-H4040 Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09

282 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 281

283 Malaysia Project Name(ID): MY OZONE DEPLETING SUBS (P004212) Malaysia 15-Aug Jun Dec-2010 Sector: Other industry (100%) received Additional Financing during no The objective is to carry out the Country Program to phase out Project the use of Ozone Depleting Substances (ODS) through the implementation of investment sub-projects to reduce the consumption of ODS. Malaysia is on target to meet its annual obligations for reducing Ozone Depleting Substances (ODS) under the Montreal Protocol, implementation progress is good, and the program continues to be well run. Total ODS consumption to be phased out in 2009 is 350 tons. The government has carried out public awareness activities on the phase-out of ODS in various sectors. With activities in all other ODS-consuming sectors already completed, during the past year the project focused on finalizing the phase-out in the mobile air conditioning (MAC) and refrigeration servicing (RS) sectors. The project helped train and register 3,891 technicians from 3,480 certified workshops to service mobile air conditioning units, which exceeds the original target of 3,000 workshops. Previous difficulties distributing vouchers for refrigeration servicing equipment in some areas have now been resolved, and 1,476 refrigeration technicians from 1,013 workshops have been trained and certified, exceeding the original target of 600 workshops. TF Effective USD Status of Projects in Execution - FY09

284 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 283

285 Mongolia Project Name(ID): Sector: received Additional Financing during Project MN Economic Capacity Tech. Assistance (P077778) Mongolia 24-Jun Jan Sep-2011 Central government administration (90%); Sub-national government administration (10%) no The objectives of the project are to improve: (i) public finance management and(ii) the effectiveness of public administration. The project has made some notable progress in FY09. The closing date for the project was extended to September 30, 2011 to allow for the satisfactory completion of many on-going tasks, and to enable technical assistance in new areas to respond to the economic crisis. The contract for developing a new Budgeting Information System was awarded and the system is currently under development. New TA with the National Innovation and Development Committee (the newly formed planning agency) was agreed to in order to strengthen strategic planning. It was also agreed that the HRMIS, the procurement of which was repeatedly delayed over the past three years, would be simplified and reduced in scope to make it more manageable and to allow for the reallocation of funds to respond to the new needs (for for example, strengthening planning) posed by the crisis IDA Effective XDR IDA-Q3500 Closed USD Status of Projects in Execution - FY09

286 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 285

287 Sector: received Additional Financing during Project MN-Index-Based Livestock Insurance (P088816) Mongolia 26-May Nov Jun-2011 General agriculture, fishing and forestry sector (66%); Noncompulsory pensions, insurance and contractual savings (20%); Central government administration (14%) no The objective is to ascertain the viability of index-based livestock insurance in Mongolia to reduce the impact of livestock mortality on herders through the piloting of indexbased livestock insurance in three provinces. Excellent progress has been made in achieving the project objective in FY09. High rates of livestock mortality triggered high payouts to herders in August 2008, which successfully demonstrated that mechanisms for paying claims worked well. Sales in 2009 had beaten all previous levels, up by 30 percent from 2008 and that despite the severe economic downturn in rural areas resulting from a collapse in cashmere prices. Due to this continued robust performance, IDA is now in discussion with government to scale up the project using Additional Financing, which is scheduled for Board presentation in October This will require a modification of the PDO to reflect the shift from piloting to scaling up. IDA Effective XDR TF Closed USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

288 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 287

289 MN-Energy Sector (P040907) Mongolia 03-May Apr Dec-2009 Sector: Power (97%); Central government administration (3%) received Additional Financing during no Project To reduce system losses and improve revenue collection in electricity distribution companies in Mongolia. The PDOs are likely to be achieved. The system losses for electricity distribution companies continue to decline and receivables are performing very well. Procurement-related issues have been largely resolved particularly with the finalization of contracts for construction of the Dornod I and 4Zam substations. The rehabilitation work for Ulaanbaatar Electricity Distribution Network (UBEDN) and Westrn Aimags is also proceeding satisfactorily and can be completed by the closing date. Consultancy inputs to improve Aimag performance and to strengthen UBEDN's distribution function are progressing satisfactorily and will help improve the performance of project utilities. The Government has requested Additional Financing of about US$16.5 million, to be considered by the Board in FY10. IDA Effective XDR Status of Projects in Execution - FY09

290 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 289

291 Sector: received Additional Financing during Project MN-Private Sector Development Credit II (P088992) Mongolia 28-Jun Nov Apr-2010 Micro- and SME finance (50%); General finance sector (30%); Banking (18%); Central government administration (2%) no Project Development Objective is to support commercial banks' efforts to develop the intermediate-term lending market for Mongolia's private sector. Though progress has been made over the 2nd half of 2008 towards supporting the medium term lending, project implementation was affected due to developments in the global and Mongolian financial markets. At the Government's request a component for consultancy services was added to support Bank of Mongolia capacity to address the emerging banking sector issues and prepare for any financial crisis management need in the future. The technical assistance program to strengthen capacity at the 3 PFIs is proceeding gradually albeit slowly as the banks are busy dealing with immediate issues. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

292 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 291

293 Sector: received Additional Financing during Project MN-Info & Com Infra Dev (P092965) Mongolia 08-Jun Jun Mar-2012 Telecommunications (61%); Central government administration (34%); General information and communications sector (5%) no The project's development objectives are to: (a) significantly increase the coverage and use of relevant ICT services among the rural population through an incentive program designed to encourage the participation of private operators in the rural segment of the ICT market; and (b) increase private sector participation in the delivery of e-government services, thereby improving public sector utilization of ICT. Project implementation is progressing well and the PDOs are on their way to being met. Access to and use of information and communication technology service among the rural population have significantly increased with the availability of modern mobile telephony services in all soum centers in Mongolia; access to public telephony services at the bagh level by 120 rural herder communities; and the installation of a modern Spectrum Monitoring System. Private sector participation in the delivery e-government services is also expected to increase once the internet services and e- government applications are in place. Preparation for the installation of these services and activities are underway after the initial delay. IDA-H2320 Effective XDR IDA-Q5180 Closed USD TF Effective USD Status of Projects in Execution - FY09

294 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 293

295 Sector: received Additional Financing during Project MN- Mining Sector Inst Strengthening TA (P108768) Mongolia 26-Jun Dec-2012 Central government administration (80%); Mining and other extractive (20%) no The objective is to further develop the policy, fiscal, legal, regulatory and institutional framework for the mining sector and to improve macroeconomic and mining sector management. The Project just became effective in May 2009 following a long delay in legal agreement signing by Government due to general elections immediately following Board approval. Project activities have recently commenced so it is too early to have achieved any specific outcomes. IDA Effective XDR IDA-H4110 Effective XDR Lending Information/Disbursement Summary (in millions USD) 294 Status of Projects in Execution - FY09

296 Sector: received Additional Financing during Project MN-Renewable Energy for Rural Access (P099321) Mongolia 19-Dec Dec-2011 Renewable energy (90%); Central government administration (8%); Health (1%); General education sector (1%) no To increase access to electricity and improve reliability of electricity service among the herder population and in off-grid soum centers. The global environment objective is to remove barriers to the development and use of renewable energy technologies in grid and off-grid connected systems and reduce emissions of carbon dioxide. The rehabilitation of the soum mini grid will further reduce diesel fuel consumption of the hybrid systems with additional CO2 emissions reduction benefits. The project is on its way to meeting its development objectives. The Government of Mongolia (GoM) has thus far sold and distributed 40,400 (81%) out of the total 50,000 solar home systems and wind turbine systems to herder families. These accomplishments should lead the project to meet its indicator of increasing the percent of the herder population with access to reliable electricity services. Furthermore, the GoM has also accelerated its Soum electricity access program and has rehabilitated 15 of the 30 mini grids, and has installed 11 of the 20 renewable diesel hybrid systems, with an additional five soums having been connected to the main power grid. This achievement will increase the number of people in off-grid soum centers with access to improved and reliable electricity services supported by renewable or renewable-diesel hybrid systems. In addition, 30 sales and service centers (SSCs) have been established towards the target of 50 SSCs upon completion. These additional SSCs will help to ensure sustainable delivery and after sales service to the herder population. IDA-H2630 Effective XDR TF Effective USD Status of Projects in Execution - FY09 295

297 Lending Information/Disbursement Summary (in millions USD) 296 Status of Projects in Execution - FY09

298 Sector: received Additional Financing during Project MN-Governance Assistance (P098426) Mongolia 23-May Jan-2012 Central government administration (81%); General public administration sector (19%) no Project Development Objectives are to i) improve the efficiency and effectiveness of governance processes in the management of public finances, (ii) promote transparency and accountability in the performance of public sector functions, and (iii) foster the investment climate in Mongolia. Overall progress has been satisfactory. Two project components -- on connecting the soums to the GFMIS and on TA for the National Statistical Office -- have been completed. Specifically, 210 soums have been connected to the GFMIS with the Government aiming to increase the number to the 253 soums with electricity connections this year. For the NSO the project supported the development and analysis of the last round of the household socio-economic survey, and upgrading the NSO's IT infrastructure. Other notable achievements for the year in the other project components are as follows: Anticorruption: The project is supporting the development of an online portal for income and asset declaration to standardize reporting formats and ease analysis. A second anti-corruption public awarnesess campaign in partnership with the Asia Foundation was also completed this year Mining cadastre: A consulting firm has been engaged to prepare the computer software to support licensing management. IDA-H2220 Effective XDR Status of Projects in Execution - FY09 297

299 Lending Information/Disbursement Summary (in millions USD) 298 Status of Projects in Execution - FY09

300 MN-MONSTAT (P113160) Mongolia 12-Jun Dec-2014 Sector: Central government administration (100%) received Additional Financing during no The main objective o f the project is to improve efficiency and effectiveness of the national statistical system of Mongolia to Project enable it to provide relevant, timely and reliable data for evidence-based policy making in support of Government s MDG-based National Development Strategy (NDS). The project is not effective yet. IDA Not Effective XDR Status of Projects in Execution - FY09 299

301 Sector: received Additional Financing during Project MN-Development Policy Credit (P115737) Mongolia 25-Jun Oct-2009 Banking (36%); Mining and other extractive (24%); Central government administration (24%); Other social services (16%) no The objectives are to: (a) improve capital budget planning and execution, and protect the maintenance of basic infrastructure; (b) protect the poor during the downturn; (c) strengthen confidence in the financial sector; and (d) clarify the mining policy framework. The DPC has been approved under the IDA Financial Crisis Response Fast-Track Facility. At the close of the reporting period all prior actions and conditions for program effectiveness were completed. The following key actions: (a) projects without feasibility studies have been excluded from the budget, and expenditure for the maintenance of basic infrastructure has been increased to a level of 3.4 percent of domestic investment, in a budget amendment in March 2009; (b) the government has prepared an action plan to reduce the leakage of social transfers to the non-poor and improve its targeting on the poor; (c) the central bank has prepared an action plan for the restructuring of the major bank that was put under the conservatorship at the end of 2008; and (d) the government has developed and adopted model investment agreements for the mining sector, clarifying its mining policy, including taxation and the state s capital participation in new ventures. In June, Parliament approved a second budget amendment, which increased the allocation to social transfers and domestic investment. This increase in social transfers ensures that the poor are protected while a new targeting system is being designed and implemented. IDA Effective XDR Status of Projects in Execution - FY09

302 MN-Enhanced Justice Sec Services (P101446) Mongolia 26-Jun Dec-2012 Sector: Law and justice (100%) received Additional Financing during no The project's development objective is to enhance the Project efficiency, transparency and accountability of justice sector institution s. The Project only became effective in June 2009 following a long delay in legal agreement signing by the Government due to general elections immediately following Board approval. Project activities have recently commenced, and it is too early to have achieved any specific outcomes. IDA Not Effective XDR IDA-H4130 Not Effective XDR Status of Projects in Execution - FY09 301

303 MN-UB SERVICES IMPROVMT 2 (P074591) Mongolia 29-Apr Mar Jun-2010 Sector: Water supply (100%) received Additional Financing during no Project To provide improved water supply to the urban poor in a sustainable manner. Progress toward meeting the PDO improved over FY09. Almost 65% of physical works are complete and all major civil works are scheduled for completion in calendar year These works will improve water supply to the urban poor. Progress on pricing policies to improve sustainability has also been made. Tariffs were increased for both water and wastewater for commercial and industrial customers. Tariff increases for residential customers remain to be approved. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09

304 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 303

305 Sector: received Additional Financing during Project MN-Sustainable Livelihoods Project II (P096439) Mongolia 19-Jun Jun-2012 Other social services (40%); Animal production (20%); Microand SME finance (18%); General public administration sector (17%); General education sector (5%) no The objective is to enhance livelihood security and sustainability by scaling-up institutional mechanisms that reduce the vulnerability of communities throughout Mongolia. Progress towards achieving the project development objective is proceeding well, albeit slightly behind schedule. Under the Pastoral Risk Management component, this component will improve pasture management and mitigate risks of herding, thereby reducing vulnerability of rural populations. The component is now operating in eight of the 21 provinces. The remaining provinces are experiencing delays due to the slow procurement of technical assistance, which is now at the bid evaluation stage. There have also been delays in procuring consultants to operate the Livestock Early Warning System. The Community Initiatives component, which aims to empower communities to participate in resource allocation for social infrastructure, is now fully functional in all districts throughout the country. The Microfinance Development component aims to increase the outreach of rural financial services providing opportunities for increased investment in income-generating activities. The component has been severely hit by the economic and financial crisis and disbursement has stopped due to the lack of credit demand and as financial institutions fail to meet the eligibility criteria. This will pick up once economic conditions improve. IDA Effective XDR IDA-H3130 Effective XDR TF Closed USD TF Effective USD TF Effective EUR Status of Projects in Execution - FY09

306 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 305

307 Sector: received Additional Financing during Project MN-Rural Education and Development -READ (P096328) Mongolia 23-May Sep Feb-2013 Primary education (75%); Central government administration (25%) no The objective of the project is to assist the Recipient in enhancing the quality of education in rural primary schools, grades 1-5, by improving students' access to, and use of, quality learning materials and improving teachers' skills through promoting professional networks. The project is still relevant and the development objectives remain valid. Progress under the project towards the objectives is steady in terms of getting books to children and training to teachers in difficult to reach rural schools. The books are well designed, and the cascade training and teachers' network are effective. The encouragement of borrowing and reading books in the classroom, the approach to ask students to make small and big books with their parents and teachers, and the acting out of the content of books have generated enthusiasm for reading beyond the classroom, spilling into the community. The Project is well on its way toward meeting its core development objectives. IDA-H2210 Effective XDR IDA-H3730 Effective XDR IDA-Q4990 Closed USD Status of Projects in Execution - FY09

308 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 307

309 Pacific Islands Project Name(ID): Sector: received Additional Financing during Project 4P-GEF Sustainable Energy Finance (P098423) Pacific Islands 12-Jun Dec-2017 Renewable energy (86%); Central government administration (9%); Micro- and SME finance (5%) no The project aims to significantly increase the adoption and use of renewable energy technologies in participating Pacific Island states through a package of incentives to encourage local financial institutions to participate in sustainable energy finance in support of equipment purchase. The global environment objective is to contribute to mitigating climate change through the reduction of greenhouse gas emissions in line with the United Nations Framework Convention on Climate Change. During the past year the project overcame a number of hurdles that were causing delays, and between July and October 2008 project activities were formally launched in Solomon Islands, Papua New Guinea, and Fiji. Each of these countries now has an overall fund manager, a dedicated project manager at each executing agency, participating financing institutions, and qualified retailers. Formalizing the participation of key parties and setting up these administrative processes is both complex and an integral part of the project's outputs, which makes getting these arrangements in place a noteworthy achievement in and of itself. In Solomon Islands there have been 12 approved individual loans and one approved energy business loan; and in Fiji two business loans have been approved. In all three countries additional applications are under review. The focus will now be on further training (in particular of the picohydro power and coconut oil conversion options), as well as on further outreach and marketing and involvement of additional Participating Financing Institutions. IFC is responsible for activities in the Marshalls and Vanuatu. 308 Status of Projects in Execution - FY09

310 TF Effective USD TF Effective USD TF Effective USD TF Effective USD TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 309

311 Papua New Guinea Project Name(ID): Sector: received Additional Financing during Project PNG-Smallholder Agriculture Development (P079140) Papua New Guinea 18-Dec Dec-2012 Roads and highways (66%); Crops (21%); Agricultural extension and research (8%); Other social services (3%); Subnational government administration (2%) no To increase, in a sustainable manner, the level of involvement of targeted communities in their local development through measures aimed at increasing oil palm revenue and local participation. Although the project was approved in late 2007 it did not become effective until the latter part of the reporting period and it is still at too early a stage to show meaningful progress. While the project is now under way, it is likely that the main activities will not begin implementation until the end of IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

312 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 311

313 Sector: received Additional Financing during Project PG Mining Sector Inst Strengthening TA 2 (P102396) Papua New Guinea 26-Jun Dec-2013 Central government administration (88%); Sub-national government administration (12%) no The objective is to improve the capacity of Government agencies to manage mining sector activities and to enhance the benefits from Extractive Industries (EI) to the national budget. The project has been very slow to achieve effectiveness due to a very long delay in project signing by the Government. The project became effective on August 3, Initial contracting activities have commenced supporting the Mineral Resources Authority and the Department of Mineral Policy and Geohazard Management. IDA Not Effective XDR Status of Projects in Execution - FY09

314 Sector: received Additional Financing during Project PG-ROAD MAINT. & REHAB (P004397) Papua New Guinea 06-Jun Dec-2009 Roads and highways (80%); Central government administration (11%); Sub-national government administration (9%) no The objectives are to (a) restore satisfactory physical condition and safety to parts of national and provincial roads and bridges in six project provinces; (b) strengthen strategic planning and management of road sector assets; (c) strengthen institutional arrangements for road maintenance; and (d) increase private sector contracting of maintenance works. The project has made significant progress toward achieving its objectives. However, during the past year it began to fall behind schedule in implementing the scaled-up program of investments agreed in About 750 km of national roads and 50 km of provincial roads are being restored or improved through routine maintenance, and the percentage of roads in good or fair condition has nearly tripled the pre-project figures. The planning, implementation, financial and procurement capacity in the road sector has also been strengthened considerably. The majority of national and provincial road investments are now based on specified annual works programs carried out through competitively bid contracts, whereas at the outset of the project it was common for these activities to be carried out on an ad hoc basis without competitive procurement. Although a full assessment is still pending, several indicators suggest that improved road conditions are yielding benefits for road users and the broader community. An extension of the project closing date is under consideration to allow time for the scaled-up investment program to be completed. IBRD Effective USD IDA Effective XDR Status of Projects in Execution - FY09 313

315 Lending Information/Disbursement Summary (in millions USD) 314 Status of Projects in Execution - FY09

316 Philippines Project Name(ID): Sector: received Additional Financing during Project PH-2ND WOMEN'S HEALTH & SAFE MOTHERHOOD (P079628) Philippines 21-Apr Oct Jun-2012 Health (75%); Central government administration (15%); Subnational government administration (5%); Compulsory health finance (3%); Other social services (2%) no The project will contribute to the national goal of improving women's health by: 1) Demonstrating in selected sites a sustainable, cost-effective model of delivering health services that increases access of disadvantaged women to acceptable and high quality reproductive health services and enables them to safely attain their desired spacing and number of children. 2) Establishing the core knowledge base and support systems that can facilitate countrywide replication of the project experience as part of mainstream approaches to reproductive health care within the framework of the Health Sector Reform Agenda. Although delayed, most interventions which were being (or are being) modeled have been mainstreamed in the new national strategy to reduce maternal mortality. Improved access by women to health services, particularly facility delivery services, has been documented. The project is also financing efforts to upgrade national capacities in training health staff on emergency obstetric services; designing and implementing behavioral change interventions, and ensuring safe blood supply. It has also contributed in generating government and other donor investments in the upgrade of hospitals and other health facilities that address women's health needs IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 315

317 Lending Information/Disbursement Summary (in millions USD) 316 Status of Projects in Execution - FY09

318 Sector: received Additional Financing during Project PH-Nat'l Prog Supt for ENV & NRMP (P096174) Philippines 26-Jun Dec-2012 General agriculture, fishing and forestry sector (30%); General water, sanitation and flood protection sector (30%); General public administration sector (22%); Forestry (10%); Mining and other extractive (8%) no The project's objective is to assist the Department of Environment and Natural Resources to improve the efficiency and effectiveness of its service delivery. The project has increased the pace of implementation during the past six months and is making progress toward meeting the development objectives, though implementation is still behind schedule. Most of the factors responsible for the delay have been addressed and there are positive signs the pace of implementation will increase further. A forward planning and budgeting strategy is now in place and services such as the issuance of tenure instruments have been improved. Major contracts are about to be awarded which include establishment of an MIS and carrying out a major baseline client satisfaction survey. The ecosystem management activities are picking up as watershed management plans are in advanced stages of preparation in the targeted areas and Local Government Units are beginning to identify livelihood projects that support integrated ecosystem management. Progress has been particularly good in the environmental management component where targets for monitoring environmental compliance and enforcement are being met. IBRD Effective USD Status of Projects in Execution - FY09 317

319 Lending Information/Disbursement Summary (in millions USD) 318 Status of Projects in Execution - FY09

320 Sector: received Additional Financing during Project PH-EC TF for Hlth Sector Reform (P102513) Philippines 04-Jun Dec-2010 Health (70%); Sub-national government administration (20%); Central government administration (10%) no The objective of the Trust Fund is to increase utilization of affordable and financially sustainable, good quality essential health services by the poor in participating localities through the progressive implementation of the Philippine Government's Health Sector Reform Agenda. The trust fund has financed, in six Provinces, the implementation of the provincial investment plans for health, which are expected to expand the scope and improve the quality of the health services provided to the poor by these provinces and their respective component towns and cities. Although evidence of improved access to health or improved health outcomes has yet to be shown, the funding support has triggered increased local government enrolment of the poor to the National Health Insurance Program; upgrading of the capacities and capabilities of their health staff and facilities; improved monitoring and reporting of local level health data and indicators; commitment to improving local government health-related procurement and financial management activities; and increased local government focus and even budgetary allocation for health. TF Effective EUR Status of Projects in Execution - FY09 319

321 Lending Information/Disbursement Summary (in millions USD) 320 Status of Projects in Execution - FY09

322 PH-NP Support for Basic Ed (P094063) Philippines 20-Jun Dec-2011 Sector: Primary education (60%); Secondary education (40%) received Additional Financing during no Project To improve quality and equity in learning outcomes for all Filipinos in basic education. Progress toward meeting the development objectives has been good. Significant improvements have been recorded in terms of net enrolment rate, completion rate, drop-out rate, and achievement rates at both the elementary and secondary level, compared to the previous year's performance and vis-avis targets. The regulatory and policy framework for ensuring greater access and better quality education outcomes has taken further shape, and ownership and buy-in for the various reform thrusts under the Basic Education Sector Reform Agenda that the project is supporting has considerably increased. Key elements of School-based Management, which is the linchpin of the reform agenda, are in place in many schools, and has had an impact on learning outcomes in the divisions where it was initially implemented. The project has influenced the policy of decentralizing more resources to the schools, thus enhancing equity and allowing a flexible and creative response to the school's and student's needs. A quality assurance framework was developed which will provide the key elements for standards-led improvement in all areas. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 321

323 Lending Information/Disbursement Summary (in millions USD) 322 Status of Projects in Execution - FY09

324 Sector: received Additional Financing during Project PH-Participatory Irrigation Development (P088926) Philippines 24-Jun Mar-2015 Irrigation and drainage (71%); Public administration- Agriculture, fishing and forestry (29%) no The Project aims to enhance the financial viability and institutional capacity of the National Irrigation Authority in improving irrigation service delivery; transfer increased O&M responsibilities in 58 national irrigation systems (NISs) to capable irrigators' associations (IAs); and increase irrigation efficiency and promote reliable access to water among farmers in the 58 NISs. The project was just approved before the close of the reporting period. The Loan Agreement has been signed on August 7, 2009 and is not yet effective. IBRD Not Effective USD TF Closed USD Status of Projects in Execution - FY09 323

325 Sector: received Additional Financing during Project PH-MMURTRIP (P057731) Philippines 21-Jun Mar Mar-2010 Roads and highways (81%); General transportation sector (16%); Sub-national government administration (3%) no To improve the operational efficiency and safety of the transport system of Metro Manila, and increase opportunities to use public transport and non-motorized transport (NMT). The Global Environment Facility (GEF) objective is to reduce greenhouse gas emissions, increase usage of zero-emission bicycle and pedestrian transport as a viable and beneficial alternate transport mode, and encourage the replication of this pilot program to other parts of Metro Manila, elsewhere in the Philippines, and in other countries. The project is on track towards achieving its development objective. The project has improved the operational efficiency of the transport system in Metro Manila: Travel time of transport users along the metropolis main corridor (Epifanio de los Santos Avenue or EDSA) has decreased from an average of 60 to 38 minutes. In addition, travel speed of motor vehicles improved in the secondary roads covered by the project. Safety especially of pedestrians is enhanced by the footbridges constructed along EDSA and Bicutan corridors. The Marikina Bridge and Access Road has been completed and is operational, providing improved access to Marikina Valley. The secondary roads are mostly completed, contributing to the increased capacity at intersections between secondary roads and project corridors. Efforts are now dedicated to complete the remaining activities, including a final evaluation of project outcomes, which is expected to confirm that the development objective is being achieved. The GEF objective is being met as the necessary infrastructure has been completed in December 2007 and workshops to promote bicycle use have been carried out. Survey data based on 14 hour traffic counts on selected streets with bikeways indicates that there has been a steady increase in bike use in Marikina. IBRD Effective USD Status of Projects in Execution - FY09

326 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 325

327 Sector: received Additional Financing during Project PH LAND ADMINISTRATION AND MANAGEMENT II (P073206) Philippines 31-May Apr Mar-2011 Central government administration (65%); Sub-national government administration (30%); Tertiary education (5%) no The objectives of the project are to increase land tenure security and improve land administration services through the implementation of institutional and legal reform, the realization of an accelerated land titling program, and the establishment of a fair and uniform property valuation system. Overall implementation progress has been modest. The first objective is unlikely to be achieved during the project's life. The key land administration institutional and legal reforms are most unlikely to be passed by the current Congress. Also, after 4 years of implementation, only around 20,000 titles have been issued to land owners. On the other hand, good progress has been made towards achieving the second objective concerning property valuation reform. The Real Estate Services Act was enacted in July 2009, and it is likely that the Valuation Reform Act bill will also be passed during the remaining period of the project. The development, testing and implementation of standards and procedures for property valuation are also progressing well. The project is now being restructured, which includes the revision of the project development objectives to enable more modest, yet still strategically relevant and important objectives, in terms of land administration, to be realized during the remaining life of the project. In addition, restructuring will encompass revisions to project outputs and indicators and a commensurate reduction in loan fund requirements. Re-structuring is expected to be completed by November IBRD Effective USD Status of Projects in Execution - FY09

328 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 327

329 Sector: received Additional Financing during Project PH KALAHI-CIDSS PROJECT (P077012) Philippines 17-Sep Jan May-2010 General water, sanitation and flood protection sector (20%); Roads and highways (20%); Health (20%); General education sector (20%); Other social services (20%) no The objective of the Project is to assist the government in strengthening participation of local communities in barangay governance, and developing their capacity to design, implement and manage development activities that reduce poverty. This objective establishes strong links between improved local governance and poverty reduction through community empowerment. The project is in its final phase of implementation. The number of community sub-projects supported by the project has increased to 5,289 (as of March 2009). To permit orderly completion of remaining project activities the project's closing date has been extended by 11 months to May 31, Most key performance indicators are on track to or have exceeded their targets. The results from a pilot program in 33 municipalities supported by the project are helping to identify the key factors and actions on the part of local governments, communities and other government agencies that contribute to the institutionalization of the project's benefits beyond the project's completion date. IBRD Effective USD TF Closed USD TF Closed USD TF Effective USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

330 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 329

331 Sector: received Additional Financing during Project PH- Natl Rds Improv. & Mgt Ph.2 (P079935) Philippines 13-May Dec-2012 Roads and highways (91%); Central government administration (9%) no The Program goal is the establishment of road management arrangements which ensure the upgrading and preservation of the National Road System (NRS) in an environmentally, socially and financially sustainable manner. The development objective for Phase 2 is: Improved operation, organizational effectiveness and fiduciary control in the management and financing of the national road system, to enhance road user satisfaction in the project areas and efficiency and integrity in the use of financial resources. The Project became effective in April The DPWH achieved good implementation progress to date, focusing mostly on both the establishment of the Project Management Office and procurement activities in support of the development objective. At this initial stage of project implementation it is not yet possible to assess to what extent the development objective would be achieved. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09

332 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 331

333 Sector: received Additional Financing during Project PH ODS INVESTMENT PROJE (P004406) Philippines 27-Sep Nov Jun-2010 Other industry (67%); Agro-industry (31%); Central government administration (1%); Banking (1%) no The objective of the project is to phase out Ozone Depleting Substances (ODS) by: (a) establishing an efficient mechanism for executing ODS phase-out projects through local institutions; and (b) implementing an initial group of costeffective priority sub-projects providing grant funding to subprojects through the Land Bank of the Philippines (LBP). The project continues to make significant progress in achieving its project objectives. The project has instituted alternative non-cfc technologies and cost-effective investments with the beneficiary enterprises and service shops, achieved great strides in strengthening the capacity of the DENR and other partner agencies such as the Bureau of Customs, Department of Trade and Industry, Land Transportation Office, etc. The project has also made good progress in the implementation of the National CFC phase-out plan and the sectors plans for the target industry sectors such as the manufacturing and servicing sectors. TF Effective USD TF Effective USD Status of Projects in Execution - FY09

334 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 333

335 Sector: received Additional Financing during Project PH-SUPPORT FOR STRATEGIC LOCAL DEV & INV (P064925) Philippines 29-Jun May Jun-2012 General water, sanitation and flood protection sector (50%); Roads and highways (20%); Renewable energy (13%); Subnational government administration (9%); Housing construction (8%) no To improve local public service provision and management by facilitating Local Government Unit (LGU) access to viable financing for strategic infrastructure investments. The mid-term review (MTR) mission (May 2009) assessed that the project remains on track in meeting its development objective. At MTR, the project has financed a total of 27 LGU subprojects, benefiting 17,329 households. The number of LGUs assisted so far represents more than half of the project target, and also indicate improvement in basic service provision in these LGUs as the project supported water supply systems, roads, drainage systems, public transport terminals, flood control systems, and public markets. Work is intensified to ensure that capacity of LGUs is improved in the process of providing them access to financing. Implementation issues noted so far are being addressed to mitigate the risks these pose to achieving the development objective. IBRD Effective JPY TF Closed USD TF Closed USD TF Effective USD Status of Projects in Execution - FY09

336 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 335

337 JUDICIAL REFORM SUPPORT PROJECT (P066076) Philippines 19-Aug Apr Dec-2009 Sector: Law and justice (100%) received Additional Financing during no The objective is to develop a more effective and successful judicial system that would foster public trust and confidence, by ensuring speedy and fair disposition of justice to all by Project improving the efficiency of case adjudication and access to justice; upgrading the integrity of the judiciary; strengthening institutional capabilities; and promoting stakeholder support for judicial reform. Progress is being made though it has been slow due to unanticipated implementation challenges. The Bank and Philippine judicial and executive authorities are in discussion about a possible extension of the loan closing date to enable achievement of the project development objective. IBRD Effective USD TF Closed USD TF Closed USD Status of Projects in Execution - FY09

338 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 337

339 PH-GEF-Electric Cooprtv System Loss Redu (P066532) Philippines 29-Apr May Dec-2011 Sector: Power (100%) received Additional Financing during no The project objective is to achieve significant and sustained energy efficiency improvements in electric cooperatives (ECs) in order to provide current and prospective viable EC customers with reliable and least-cost power supply over the Project long term. The global objective of the Global Environment Facility (GEF) is to reduce green house gas (GHG) emissions by removing barriers to energy efficiency investments in the rural power distribution sub-sector. The progress toward achieving its development objectives is lagging behind schedule. The project has not achieved the closing of its first transaction. Barriers identified at appraisal stage have prevailed during implementation and been compounded by lack of institutional coordination and cooperation. The Government has committed to a turnaround plan. It is expected that such a plan will lead to the closing of the first set of transactions in the near future. The project team will update the results framework once the final Mid- Term Review is submitted and agreed, TF Closed USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

340 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 339

341 PH-Rural Power Project (P066397) Philippines 04-Dec Mar Dec-2012 Sector: Power (50%); Renewable energy (50%) received Additional Financing during Project Additional Financing Bank loan was signed in May, 2009 and it is about to start implementation. USD 40 million was provided to scale up the growing demand of the renewable and energy efficiency projects. APL1: To (a) test and demonstrate viable business models that maximize leveraging of public resources with private investment for decentralized electrification; (b) support transformation of electric cooperatives (ECs); and (c) avoid carbon dioxide emissions through wider use of renewable energy. GEF: to mitigate global climate change caused by greenhouse gas (GHG) emissions through wider user of clean energy technologies Overall the project is on track toward meetings its development objectives. Implementation is lagging behind but progress has steadily improved over the last 12 months. Department of Energy proposes a more focused and streamlined strategy that will build on what has worked well and attempt other business models that show good prospects for sustainability. Development Bank of the Philippines is also proactively developing a strong pipeline of rural and renewable subprojects that are proposed to be financed under a follow up APL2. The Loan Guarantee Fund (LGF) will be dropped because it has met only limited MFI interest. There are already 9 new RET companies accredited and operating which has exceeded the original target of four. Further, CO2 emissions avoided is behind the target schedule but still on track to achieve the project end target. IBRD Effective USD IBRD Not Effective USD TF Closed USD TF Closed USD Status of Projects in Execution - FY09

342 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 341

343 PH-Support for Basic Ed. Sector Reform (P106443) Philippines 02-Jun Jun-2011 Sector: Primary education (100%) received Additional Financing during no Support the implementation of the Philippines' Basic Education Sector Reform Agenda which in turn aims to Project contribute to the achievement of the Philippines' basic education goal of improving quality and equity in learning outcomes After a slow start, the project is on track to meet its development objective. The mobilization and engagement of the much needed technical assistance and support to the various technical working groups for each key reform area through project financing has contributed to the development and issuance of critical policy instruments in the areas of quality assurance and accountability, application of teacher standards, adoption of school-based management practices in schools and resource mobilization at the school, division and regional levels. Support to the policy of decentralization of resources to the lower levels, especially to the schools, was provided through school grants for school and student improvement which are expected to create flexible space for a localized and appropriate response to student and school needs and improve quality. More classrooms were constructed under the project particularly in disadvantaged areas, which are contributing to a more conducive learning environment for the poor students. TF Effective AUD Status of Projects in Execution - FY09

344 PH-MANILA SEWERAGE 3 (P079661) Philippines 21-Jun Mar Jun-2010 Sector: Sewerage (50%); Sanitation (50%) received Additional Financing during no The development objectives are to: (a) increase the coverage Project and effectiveness of sewerage service delivery in participating areas of Metro Manila. The project is meeting its development objectives and progress has been made on several key outcome indicators which include: increase in consumer satisfaction on sewerage and sanitation services; 6% decline in diarrhea incidents per person, removal of biological oxygen demand (Target was 11,830 tons/year for Year 4, Actual was 75,928 tons/year); and the number of tanks de-sludged increased by 14.5% from 256,146 to 293,344. The sewage treatment plants are behind schedule but are still on track to meet the final target. Based on the positive progress of the project and the large demand to provide additional sewerage services, Manila Water (the implementing entity) has requested additional financing from the Bank. This request is currently being considered by the Bank. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 343

345 Lending Information/Disbursement Summary (in millions USD) 344 Status of Projects in Execution - FY09

346 Sector: received Additional Financing during Project PH-GEF-MANILA SEWERAGE 3 (P089082) Philippines 26-Jun Nov-2012 Sewerage (56%); Central government administration (37%); Sub-national government administration (7%) no The project development objectives are to assist the GOP in the Project Areas in: (a)identifying essential adjustments to administrative, institutional, and regulatory practices and existing legislations in order to attract private investments in the wastewater sector;(b)increasing the effectiveness of the agencies responsible for water pollution control through improved coordination; and (c)promoting innovative, simple and effective wastewater treatment techniques. The project is on track to meeting its development objectives. Several key outcomes are showing good progress: sanitation service coverage resulting from expanded investments has increased from 24% to 32% and reduction of pollution reaching bay has reached 10 thousand tons of BOD5/year. There is also evidence showing improved effectiveness of sector agencies resulting from functioning coordination. Increase in sewage service coverage is lagging behind but still on track. Measures are being taken to speed up procurement so that implementation is completed by project closing date. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 345

347 Lending Information/Disbursement Summary (in millions USD) 346 Status of Projects in Execution - FY09

348 PH Mindanao Trust Fund-Reconstr & Dev (P095173) Philippines 20-Jul Jun Dec-2010 Sector: Other social services (100%) received Additional Financing during no The development objective is that the communities of conflictaffected areas, internally displaced people, and rebel Project returnees benefit from visible restoration of some basic services of their choice and sustained by more accountable LGUs. The project is making substantial progress on most outcomes: Communities of conflict-affected areas have well implemented sub-projects of their choice (45 communities); reconstruction and rehabilitation interventions have been initiated with the implementing partner; Local Government Units' capacity improved in 44 barangays and 40 municipalities. The implementation is on track except for Central Mindanao which is in a difficult arm conflict environment. (Note: disbursement forecast is difficult to show because contribution to the Trust Fund is not fixed but on-going over time.) TF Effective USD TF Effective USD TF Closed EUR TF Effective USD TF Effective USD Status of Projects in Execution - FY09 347

349 Lending Information/Disbursement Summary (in millions USD) 348 Status of Projects in Execution - FY09

350 PH - ARMM Social Fund (P073488) Philippines 05-Dec Jan May-2010 Sector: Other social services (100%) received Additional Financing during no The objectives are: (a) to provide and/or improve sustained access to social and economic infrastructure and services by the poor and conflict-affected poor communities; (b) to provide capacity-building for women, youth and other community Project groups for improving food security, employment opportunities and household incomes; (c) to strengthen social cohesion and partnerships between and within communities; and (d) to improve local governance and institutional capacities for implementation. Outcomes have been positive on all project objectives despite some slowdown which was partly due to the regional elections, floods and law and order problems in Central Mindanao. Access to social and economic services by the poor and conflict-affected communities has been increased; beneficiaries have received literacy training; social cohesion and partnerships between and within communities has been strengthened (250 villages perceive better safety); local governance and institutional capacities improved (needbased local planning undertaken in 619 barangays); community-based educational system improved (22 educational system accredited. The ARMM Regional Govt has requested for and received an extension of closing date to May 2010 in order to allow for the preparation of additional financing for the project. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 349

351 Lending Information/Disbursement Summary (in millions USD) 350 Status of Projects in Execution - FY09

352 Sector: received Additional Financing during Project PH-NP Support for HNP (P075464) Philippines 29-Jun Jun-2011 Health (40%); Compulsory health finance (40%); Noncompulsory health finance (10%); Central government administration (10%) no To improve priority public health outcomes and increase utilization of health services by the poor in participating localities for conditions or diseases subject to intervention under the Project; and to increase financial protection of indigent households from the costs of health care. The project financed the national supply of vaccines which has helped increased reported percentage of fully immunized children to 91% in It has contributed in expanding of the poor to vaccines particularly Hepatitis B vaccines. It supported 16 provincial investment plans for health which are all prioritizing improved access by the poor to their health services. Although evidence of improved access to health or improved health outcomes has yet to be shown, the funding support has triggered increased local government enrolment of the poor to the National Health Insurance Program; upgrading of the capacities and capabilities of their health staff; improved monitoring and reporting of local level health data and indicators; commitment to improving local government health-related procurement and financial management activities; and increased local government focus and even budgetary allocation for health. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 351

353 Lending Information/Disbursement Summary (in millions USD) 352 Status of Projects in Execution - FY09

354 Sector: received Additional Financing during Project PHSecond Agrarian Reform Communities Dev (P071007) Philippines 26-Nov Sep Jun-2010 General public administration sector (25%); Roads and highways (25%); Water supply (25%); Agricultural marketing and trade (25%) A US$10 million Additional Financing (AF) was approved on March 19, 2009 to help finance the shortfall in resources due to foreign exchange rate fluctuations. The AF will primarily fund the completion of remaining critical infrastructure investments such as the construction and rehabilitation of small-scale irrigation facilities in selected agrarian reform communities (ARCs). The objective of the project is to significantly raise household incomes and the quality of life of the people in the targeted Agrarian Reform Communities (ARCs) by improving their productive assets, rural infrastructure and access to key support services. There is a high likelihood that the project development objective would be met given that five of the eight key performance indicators (KPIs) have been fully achieved or exceeded: (a) 222% increase in cropping intensity (target is 140%); (b) 16% increase in average crop yields (target is 15%); (c) 30%increase in average household business assets (target is 10%); (d) 68% reduction in travel time (target is 50%); and (e) good quality of infrastructure maintenance. The three other KPIs are also expected to be fully met at the end of the project given the current achievement rate: (a) 17% increase in the average real net household income (target is 20%); (b) 70% improvement in organizational maturity levels of Peoples Organizations (target is 75%); and (c) completion of 1,500 infrastructure units (currently at 1,098). IBRD Effective USD IBRD Not Effective USD TF Closed USD TF Closed USD TF Closed USD Status of Projects in Execution - FY09 353

355 Lending Information/Disbursement Summary (in millions USD) 354 Status of Projects in Execution - FY09

356 PH LAGUNA DE BAY INSTITUTIONAL STRENGTHE Project Name(ID): (P070899) Philippines 04-Dec Jan Jan-2010 Sector: General water, sanitation and flood protection sector (100%) received Additional Financing during no The objective of the project is to improve the environmental quality of the Laguna de Bay watershed through: (a) behavioral changes and activities undertaken by watershed Project users; and (b) improved planning, regulatory instruments and incentives, and participation in the environmental management of the watershed. The project is on track to meet its development objective. It is directly contributing to enabling the Laguna Lake Development Authority (LLDA), Local Government Units (LGUs), communities and other stakeholders achieve improved environmental quality in the Laguna de Bay and its watershed. In particular, environmental improvements have been noted in the lake as evidenced by the reduction in the industrial biochemical oxygen demand (BOD) loading. 20 out of 41 LGU-operated open dumps have been upgraded. This redounds to a significant reduction of the total volume of solid waste. On one hand, changes in the behavior of the watershed and lake users are manifested by the increased awareness and responsiveness of the LGUs, industries and other stakeholders on the issues besetting the lake. Finally, despite a slow start, LISCOP to date has attained, even surpassed, the targets for 16 of its 31 KPIs, a further 13 are at various stages of completion are likely to reach target by the extended closure date and only two have yet to be met and the implementing agency is working on these two indicators to be able to deliver them by end of the project. IBRD Effective USD TF Closed USD TF Effective USD TF Closed USD Status of Projects in Execution - FY09 355

357 Lending Information/Disbursement Summary (in millions USD) 356 Status of Projects in Execution - FY09

358 Sector: received Additional Financing during Project PH Mindanao Rural Dev. Project - Phase 2 (P084967) Philippines 22-Mar Dec-2012 Roads and highways (55%); Other social services (19%); Irrigation and drainage (15%); Sub-national government administration (8%); Water supply (3%) no The objectives are: (a) to improve livelihood opportunities of targeted communities; and (b) to institutionalize a decentralized system for agriculture and fisheries service delivery that promotes participation, transparency and accountability. The Project's implementation is lagging behind but was finally able to take off in January 2009 after the resolution of the issue on the financial cost sharing of subprojects. As a result, local governments are now undertaking active implementation and in collaboration with the Department of Agriculture are revising their implementation plans to consequently update earlier agreed milestones and targets. IBRD Effective USD TF Closed USD Status of Projects in Execution - FY09 357

359 Lending Information/Disbursement Summary (in millions USD) 358 Status of Projects in Execution - FY09

360 Support for Tax administration Reform (P101964) Philippines 13-Mar Dec-2011 Sector: Central government administration (100%) received Additional Financing during no To increase taxpayer compliance by increasing the efficiency and effectiveness of the Bureau of Internal Revenue (BIR) in Project the short-term, and to prepare the BIR for a sustainable and long-term reform. Program implementation continues to be slow. The main reason is insufficient management attention to reforms, as management attention has been diverted to short-term revenue collection. Other reasons for weak performance include inadequate staffing and lack of empowerment of the tax reform office and frequent changes in BIR management. Nevertheless, there has been some progress in the following areas: clean-up of the taxpayer registration and information system; data-matching process between the databases of the BIR and 22 local government units; increased understanding of the need for tax reform and of the reform itself among task force members. IBRD Effective USD TF Effective USD Status of Projects in Execution - FY09 359

361 Lending Information/Disbursement Summary (in millions USD) 360 Status of Projects in Execution - FY09

362 Samoa WS-2ND HEALTH SECTOR MGMT PROG SPT PRJ Project Name(ID): (P086313) Samoa 19-Jun Dec-2013 Sector: Health (75%); Central government administration (25%) received Additional Financing during no The development objective of the Project is to improve the effectiveness of the Government of Samoa in managing and Project implementing the Program based on the results from sector performance monitoring. A Demographic and Health Survey is underway, and the findings of the last STEPwise approach to surveillance (STEPS) survey will also be released shortly. These will provide the baseline data to monitor progress against the project objectives. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 361

363 Lending Information/Disbursement Summary (in millions USD) 362 Status of Projects in Execution - FY09

364 Sector: received Additional Financing during Project Samoa - Telecommunications & Post Reform (P075739) Samoa 17-Dec Oct Oct-2009 Telecommunications (50%); Postal services (40%); Law and justice (10%) no The Project Development Objective is to assist the Government of Samoa (GOES) in implementing a comprehensive reform of the telecommunications and postal sectors. This reform focuses on: (a) introducing competition and private participation in telecommunications and postal sectors; (b) advancing regulatory reform, and developing sector institutional capacity; and (c) extending access to basic communications, postal services, and information technologies. While the overall pace of project implementation reflects the limited institutional capacity in Samoa, the borrower and the implementing agencies have performed in a relatively satisfactory manner and remain strongly committed to the project objective to increase access to affordable telecommunications. The project has achieved a number of significant results: (i) competition in the telecommunication sector was introduced first in the mobile segment, and then to the entire sector since July 2009 (international gateway, undersea cable); in the postal sector, competition will be increased with the new postal bill tabled in Parliament early next year; (ii) the project supported the creation and the capacity building of the Office of the Regulator, in charge of the telecommunication sector, and soon of the broadcast and the postal sectors; (iii) access to basic communications services has increased by a factor of 8 mostly as the result of the introduction of competition. In addition, improvements in service quality and diversification have helped the business community, and the introduction of broadband and the development of high speed internet now allows the Government to prepare the next phase of ICT reform around its e-government strategy. This has paved the way for similar reforms in the Pacific. IDA Effective XDR Status of Projects in Execution - FY09 363

365 Lending Information/Disbursement Summary (in millions USD) 364 Status of Projects in Execution - FY09

366 Sector: received Additional Financing during Project WS-INFRA ASSET MGMT APL2 (P075523) Samoa 29-Dec Nov Jun-2010 Roads and highways (74%); Central government administration (18%); Flood protection (8%) no Key infrastructure assets are sustainable and managed effectively by a partnership of stakeholders. the development objectives has been good overall, but uneven. Most activities related to strengthening and reform of infrastructure management agencies, policies, and regulations are either completed or well advanced, and are expected to substantially improve the maintenance and long-term sustainability of Samoa's infrastructure assets. Implementation of many of the original physical works to improve roads, bridges, and pedestrian facilities have been completed successfully, though some key civil works have been delayed. While the likelihood of progress on some activities remains uncertain, the most important of the lagging investments are expected to get underway by the end of the year. IDA Effective XDR IDA Effective XDR IDA-H3110 Effective XDR TF Closed USD Status of Projects in Execution - FY09 365

367 Lending Information/Disbursement Summary (in millions USD) 366 Status of Projects in Execution - FY09

368 Solomon Islands Project Name(ID): SB-Solomon Islands Sustainable Energy (P100311) Solomon Islands 08-Jul Dec-2012 Sector: Power (100%) received Additional Financing during no The objective is to improve the operational Project efficiency, system reliability, and financial sustainability of the Solomon Islands Electricity Authority (SIEA). development objective(s): The project had just become effective before the close of the reporting period. IDA-H4150 Effective XDR Status of Projects in Execution - FY09 367

369 Sector: received Additional Financing during Project SB-Health Sector Support Project (TA) (P097671) Solomon Islands 20-Mar Mar-2011 Central government administration (63%); Sub-national government administration (27%); Health (10%) no The Project's development objective is to improve the institutional capacity of the Ministry of Health and Medical Services in the areas of public expenditure management and sector performance monitoring. Such capacity development would be critical to the overall success of the Health Sector Support Program in improving health services delivery and outcomes. b) Progress has been significantly delayed, and outcomes have yet to be achieved. Tangible progress to achieve project development objectives will not take place until after the fiscal year (estimated October 2009). Priority near-term actions for improved public financial management supporting the provincial level management of service delivery were agreed in May 2009 and are being implemented, which are likely to contribute to better outcomes in public expenditure management. IDA-H3600 Effective XDR Status of Projects in Execution - FY09

370 Sector: received Additional Financing during Project SB-Rural Development Program (P089297) Solomon Islands 11-Sep Nov-2012 General public administration sector (34%); Agro-industry (22%); Agricultural extension and research (19%); Other social services (16%); General transportation sector (9%) no The project development objective is to raise the living standards of rural households by establishing improved mechanisms for the delivery of priority economic and social infrastructure and services by the public and the private sector. After a slow start, the project is now on track to meet its development objective. The main issues causing the delays have been resolved, and project implementation and management arrangements have been strengthened as a result. Activities to improve local infrastructure, agricultural services, and rural business development have begun implementation. The system to monitor and evaluate the progress and outcomes of these activities is being finalized, and a baseline survey is expected to be completed shortly. IDA-H3320 Effective XDR TF Closed USD TF Effective EUR TF Effective USD Status of Projects in Execution - FY09 369

371 Lending Information/Disbursement Summary (in millions USD) 370 Status of Projects in Execution - FY09

372 Thailand Project Name(ID): TH OZONE DEPLETING SUBS (P004649) Thailand 02-Aug Apr Dec-2013 Sector: Other industry (100%) received Additional Financing during no The objective is to phase out the use of Ozone Depleting Substances (ODS) through: (a) the introduction of appropriate technology measures; (b) the institutional strengthening of Project responsible governmental entities; and (c) the implementation of specific cost-effective priority investments to reduce consumption of ODS. The National Ozone Depleting Substance (ODS) project will meet its phase-out targets by January 1, Progress is slower than anticipated but the development objective will be realized. Training and equipment delivery have improved. The procurement of machines for training centers has been delayed and will need discussion and cooperation with the Department of Land Transport. There will be a savings of about US$928,900 that need plans for utilization which will then need approval. The implementation of the National Methyl Bromide Phase-out Plan has advanced as the Department of Agriculture has continued to put in place a combination of policy measures, institutional strengthening, technical assistance and training programs that have set up a context in which the phase-out of methyl bromide can be carried out. Advances have been made in the preparation of investment components, while outreach programs and staffing will need to be expedited so that development objectives are achieved. TF Effective USD Status of Projects in Execution - FY09 371

373 Lending Information/Disbursement Summary (in millions USD) 372 Status of Projects in Execution - FY09

374 Sector: received Additional Financing during Project TH-HIGHWAYS MGMT (P075173) Thailand 09-Dec Jan Jun-2010 Roads and highways (95%); Sub-national government administration (5%) no The project is to assist the Borrower in enhancing the efficiency, productive use, and management of the Borrower's road network. The PDO remains unchanged under the restructuring and additional financing. The project is making modest progress toward achieving its PDO, especially with the successful implementation of the consultancy on highway public-private partnership financing and with the continuing work on designing and improving a pavement management system. These activities will help improve the management of the road network. Periodic maintenance works totaling 610 km, or 87% of the project target have been completed, as well as works to improve a substantial number of intersections. These works have reduced road roughness and improved efficiency and productive use of the road network. However, failed procurement processes for two major technical assistance contracts (performance-based maintenance and development of a centralized road database and asset maintenance and management system) slowed progress on improving road network management. The Bank carried out a procurement capacity assessment and agreed on remedial measures with the borrower to strengthen the procurement system. This work was key to laying a foundation for more successful procurement, particularly important because the borrower has requested a restructuring and additional financing, being processed in FY10. IBRD Effective USD TF Effective USD Status of Projects in Execution - FY09 373

375 Lending Information/Disbursement Summary (in millions USD) 374 Status of Projects in Execution - FY09

376 Timor-Leste Project Name(ID): Sector: received Additional Financing during Project Planning & Fin Mgt Capacity Building (P092484) Timor-Leste 21-Mar Jul-2011 Central government administration (95%); Sub-national government administration (5%) no The program development objective is sustainably strengthened planning, budgeting, public expenditure management and revenue administration for growth and poverty reduction, with emphasis on efficiency, effectiveness, accountability, integrity, service culture, and transparency. Implementation has accelerated rapidly. There has been reasonable progress toward meeting the development objective. Systems and processes for budget management are being simplified and strengthened. There has been a major increase in budget execution. Computerization of records and regular publication of public finance reports have contributed to strengthening transparency and accountability. Legislation for revenue and customs has been updated, and total revenue intake has increased. The Ministry of Finance has adopted a new Organic Law and implemented a major organizational reform strategy, including merit-based appointments. Focus is turning to bedding down all these reforms and strengthening capacity to implement them. IDA-H2100 Effective XDR TF Effective USD Status of Projects in Execution - FY09 375

377 Lending Information/Disbursement Summary (in millions USD) 376 Status of Projects in Execution - FY09

378 Sector: received Additional Financing during Project TP-SF-Gas Seep Harvesting Project (P092055) Timor-Leste 28-Mar Dec-2009 Power (65%); Oil and gas (30%); Central government administration (5%) no The objective is to demonstrate the technical and economic viability of harvesting seep gas from natural gas seeps to produce reliable and affordable power for isolated rural communities in the south eastern part of Timor-Leste. There have been lengthy delays in initiating project activities, but the issues causing these delays have been resolved and all planned investments are expected to be contracted and under way in the second half of This will include the design, supply, and installation of distribution lines, a power plant, and pre-paid meters. As a result of these delays little progress has been made so far toward the development objectives, but the prospects for achieving the objectives are good and an extension of the project closing date is under consideration to ensure that its benefits are fully realized. TF Effective USD Status of Projects in Execution - FY09 377

379 Lending Information/Disbursement Summary (in millions USD) 378 Status of Projects in Execution - FY09

380 Sector: received Additional Financing during Project TP - Youth Development Project (P106220) Timor-Leste 01-Jul Dec-2011 Other social services (62%); Public administration- Other social services (38%) no The objective is to promote youth empowerment and inclusion in development by expanding the capacities of and opportunities for youth groups to initiate and participate in community and local development initiatives. The project became effective in the latter part of the reporting period and was still in too early a stage for meaningful progress. IDA-H4140 Effective XDR Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 379

381 TP Energy Services Delivery Project (P095593) Timor-Leste 28-Jun Dec-2011 Sector: Power (65%); Central government administration (35%) received Additional Financing during no The project objectives are to stabilize the power services in Dili, by restoring or improving operational efficiency, reliability, safety and availability of the power supply, and to promote Project long-term sustainability of the power sector. These would, in turn, contribute to the social stability and economic development of the country. the development objectives has been mixed. The state electricity company (EdTL) has installed about 4,400 new meters that reportedly have already reduced unpaid electricity usage and increased revenue collection, thereby helping to put the power utility on a more financially sustainable footing. About 8,800 compact fluorescent light bulbs from prior stocks have also been distributed under the project to residential customers to increase the efficiency of energy use. However, investments to repair, rehabilitate, and improve Timor-Leste's power generation and distribution facilities are behind schedule, and institutional capacity building activities have not progressed as quickly as planned. IDA-H3170 Effective XDR TF Closed USD Status of Projects in Execution - FY09

382 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 381

383 Sector: received Additional Financing during Project TP-Health Sector Strategic Plan Support (P104794) Timor-Leste 13-Dec Jun-2013 Health (83%); Central government administration (12%); Subnational government administration (5%) no The overall objective of the project is to improve the quality and coverage of preventive and curative health services, particularly for women and children, in order to accelerate progress toward the health MDGs. The Project will have two parts (a) direct financial support based on the Health Sector Strategic Plan and Medium Term Expenditure Framework, and (b) addressing remaining challenges and innovations needed for the health sector to be prepared for the next generation of issues. Specific objectives for the first part include: (i) improve accessibility, demand and quality of health services; (ii) strengthen support services, human resource development, and management; and (iii) strengthen coordination, planning and monitoring. The second objective is to promote innovation and program development by providing resources to pilot and evaluate priority health sector innovations, such as demandside and service-provider incentives, public-private partnerships. Although just completing the first year of project implementation, the project is making progress toward meeting its development objectives. At the sectoral level, nearly all key indicators improved in 2008, including for childhood vaccination, assisted deliveries, and contraceptive use. The project has supported purchase of motorcycles and vehicles to improve outreach services, recruitment of technical assistance to improve the quality of service delivery, and assistance to strengthen the Ministry of Health's (MOH) capacity to manage and coordinate the health system. The MOH has also made progress in establishing contacts with nongovernmental organizations to strengthen district and community-level health and nutrition services; these contracts should commence later in The Ministry has also increasingly taken the lead in health sector coordination, including through convening annual sector performance reviews and quarterly coordination meetings with partners. 382 Status of Projects in Execution - FY09

384 IDA-H3430 Effective XDR TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 383

385 Sector: received Additional Financing during Project TP-Education Sector Support (P095873) Timor-Leste 19-Jun Jan-2013 Central government administration (70%); Secondary education (16%); Primary education (7%); Pre-primary education (7%) no To strengthen the capacity of the Ministry of Education and Culture for effective policy development, resource management, and innovation. Following a slow start up, the Project is on track to achieve its development objectives within the project timeframe. For the first time in Timor-Leste, the Ministry of Education has detailed baseline data on access and retention rates in education down to the district level. Timor-Leste is making progress toward achieving its MDG goals in education in terms of enrollments. IDA-H3100 Effective XDR TF Effective AUD Lending Information/Disbursement Summary (in millions USD) 384 Status of Projects in Execution - FY09

386 Tonga Project Name(ID): Sector: received Additional Financing during Project TO-HEALTH SECTOR SUPPORT PROJECT (P075230) Tonga 24-Jul Jun Jul-2009 Health (90%); Compulsory health finance (7%); Central government administration (3%) no The project development objective is to assist the Kingdom of Tonga in improving the performance of its health sector by supporting selected reforms to said health sector, including: (i) the development and implementation of appropriate health financing policies, and health information systems; and (ii) the improvement of the administrative, functional and technical quality of health facilities. The Project has made good progress towards meeting its objectives as evidenced by Government's sustained support to the health sector, the installation of the information system, and an estate management plan is now operational. IDA Closed XDR TF Closed USD Status of Projects in Execution - FY09 385

387 Lending Information/Disbursement Summary (in millions USD) 386 Status of Projects in Execution - FY09

388 Sector: Project TO-Transport Sector Consolidation (P096931) Tonga 08-Jul Dec-2011 Aviation (45%); Public administration- Transportation (43%); Ports, waterways and shipping (12%) The objectives are to consolidate the policy, planning, and regulatory capacity and operations of the newly created Ministry of Transport, and improve compliance with international safety and security standards in the civil aviation and maritime subsectors. After only six months of implementation, the project is making good progress toward achieving its development objectives. The civil aviation activities are under way and are meeting the performance expectations of both the government and airline customers. The maritime subsector activities are now commencing, with navigation aids and other facilities expected to quickly yield improvements in passenger security. Although implementation of physical works in the land transport sector are slightly delayed, positive steps are being made on the objectives related to institutional planning and capacity as the new ministry consolidates its operations. IDA-H4160 Effective XDR Status of Projects in Execution - FY09 387

389 Lending Information/Disbursement Summary (in millions USD) 388 Status of Projects in Execution - FY09

390 Sector: received Additional Financing during Project TO-Tonga Education Support Project (P079657) Tonga 16-Jun Oct Jun-2010 Central government administration (50%); Primary education (25%); Secondary education (25%) no The development objectives of the project are to: (i) create an environment that supports the development of effective mechanisms for the consistent and equitable improvement in basic schooling for all children; and (ii) improve the quality of education through school and community empowerment. Good progress is being made to achieve the development objectives. The Project successfully transfers funding directly to schools to cover the costs of maintenance, repairs, books, teacher materials, student materials, furniture and minor operating costs. Progress is being made in promoting development and innovation through school level planning and the establishment of minimum service standards. Consistent progress is being made in curriculum development and institution building elements; the new curricula being developed under the Project is expected to be rolled out soon. The development of an information system will allow for improved performance monitoring of the sector. IDA Effective XDR TF Effective USD Status of Projects in Execution - FY09 389

391 Lending Information/Disbursement Summary (in millions USD) 390 Status of Projects in Execution - FY09

392 Vietnam Project Name(ID): Sector: received Additional Financing during Project VN-Mekong Regional Health Support Proj (P079663) Vietnam 07-Mar Jun-2012 Health (88%); Non-compulsory health finance (8%); Compulsory health finance (3%); Central government administration (1%) no To improve health services in the Mekong region and to enhance access to and coverage of these services, especially for the poor. The project has made progress towards its development objectives on a number of fronts, in particular with respect to human resource development. The upcoming midterm review will provide an opportunity for in-depth evaluation of the progress to date and to make adjustments, if necessary in order to achieve the development objectives. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09 391

393 Lending Information/Disbursement Summary (in millions USD) 392 Status of Projects in Execution - FY09

394 Tax Administration Modernization Project (P099376) Vietnam 25-Sep Jun-2013 Sector: Central government administration (100%) received Additional Financing during no The project development objectives (PDOs) of the Tax Administration Modernization Project (TAMP) are to assist the General Department of Taxation (GDT) to strengthen governance in tax administration and to increase the level of voluntary compliance with the tax system by improving the effectiveness, efficiency, transparency and accountability of the tax administration. The project will have a positive impact on Project the business climate by building predictable and enforceable tax administration processes and procedures. The sustainability of revenue collection, and greater equity will also be supported through implementation of this project. The PDOs therefore are complementary to two higher level objectives of the country's four reform pillars, namely business led development, and strengthened governance systems. The progress towards achieving the PDO during the fiscal year of the reporting period has been slow due to implementation delays encountered for some critical planned activities. To foster a better understanding of the market for the Integrated Tax Administration Information System (ITAIS), the General Department of Taxation (GDT) and the Project Management Unit organized a discovery and learning workshop in April of This venue was a great opportunity for senior management, stakeholders and beneficiaries to get a comprehensive menu and assessment of potential off-theshelf-solutions for ITAIS. The outcome of this workshop has been positive as the lessons learnt have helped to better articulate the details of the technical solution and criteria for the bidding process which will be launched shortly. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09 393

395 Lending Information/Disbursement Summary (in millions USD) 394 Status of Projects in Execution - FY09

396 Higher Education DPProgram 1st Operation (P104694) Vietnam 23-Jun Dec-2009 Sector: Tertiary education (100%) received Additional Financing during no The Program aims to strengthen governance, rationalize financing, improve the quality of teaching and research, Project improve accountability for performance, and enhance transparency in financial management within the higher education sector. The project was not effective before the close of the reporting period. IDA Not Effective XDR Status of Projects in Execution - FY09 395

397 Sector: received Additional Financing during Project VN-HIFU DEVELOPMENT (P104848) Vietnam 20-Jun Dec-2012 General transportation sector (79%); Solid waste management (14%); Other social services (3%); Health (3%); Sanitation (1%) no To develop the Ho Chi Minh City Investment Fund for Urban Development (HIFU) as a model local development investment fund and increase private sector participation in financing municipal infrastructure in Ho Chi Minh City. The Project is making good progress toward the development objectives. Outcomes against most indicators are on track or exceeded the annual or end of project targets: It has invested in 5 well developed sub-projects with a total investment of US$16.2 million. Private capital leveraged in municipal infrastructure projects per year has been improved ($1 of project investment brought in $1.17 of private capital). All subprojects processed are in accordance with the Project Preparation and Appraisal Manual guidelines. The challenge for the project going forward will be to prepare a pilot equity transaction, which is underway. IDA Effective XDR Status of Projects in Execution - FY09

398 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 397

399 Fin Sector Modern and Info Mgnt System (P088759) Vietnam 30-Oct Dec-2014 Sector: Banking (60%); General finance sector (40%) received Additional Financing during no The objective of the Project is to assist the State Bank of Vietnam, the Credit Information Center and the Deposit Insurance of Vietnam to improve the delivery of their main functions in accordance with relevant international standards Project for the banking sector, through (a) developing a centralized and integrated system of advanced business processes and a modern information technology architecture; and (b) strengthening their institutional capacity in carrying out their operation. The project was approved by the Bank board in October 2008 and the Financing Agreement signed in April The IDA credit is expected to become effective within 90 days after the execution of the Financing Agreement. IDA Not Effective XDR TF Closed USD Status of Projects in Execution - FY09

400 Sector: received Additional Financing during Project VN-Renewable Energy Development Project (P103238) Vietnam 05-May Jun-2014 Renewable energy (99%); Public administration- Energy and mining (1%) no The objective of the proposed project is to increase the supply of electricity to the national grid from renewable energy sources on a commercially, environmentally and socially sustainable basis. The project was not effective before the close of the reporting period. IDA Not Effective XDR Status of Projects in Execution - FY09 399

401 Sector: received Additional Financing during Project VN -ICT Development (P079344) Vietnam 15-Sep Mar Jun-2011 Central government administration (43%); Sub-national government administration (35%); General industry and trade sector (22%) no The objectives are (a) to accelerate the use of information and communication technology and support institutional development in order to increase the efficiency and effectiveness of public administration, and improve public services delivery; and (b) foster private sector development, in particular by facilitating increased adoption of information and communication technology by small and medium enterprises. Some progress in achieving the project objectives has been made, particularly on the institutional development front with the e-government Enterprise Architecture (EA) for Danang already in draft since March 2009 to guide the city's e- government development. This would have a demonstration effect on other cities and provinces in Vietnam. The project is also being restructured to improve the implementation and likelihood of achieving the project objectives for the IDA-funded activities. The targeted date to complete the restructuring process is December IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

402 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 401

403 Sector: received Additional Financing during Project VN-RRD RWSS (P077287) Vietnam 15-Sep Jun-2011 Water supply (60%); Sewerage (18%); Sanitation (14%); Subnational government administration (5%); Central government administration (3%) no To improve water and household level sanitation services and their effective use in selected provinces in ways that are financially, technically, and environmentally sustainable. The Project is on track toward meeting the development objectives. About 8000 households used effectively piped schemes constructed. The Rural Water Supply & Sanitation Enterprises established and created a good foundation to manage and operate the systems in more sustainable way. Hygiene Sanitation coverage is increased (detailed data on the outcomes are being collected) IDA Effective XDR Status of Projects in Execution - FY09

404 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 403

405 VN - Forest Sector Development Project (P066051) Vietnam 08-Jul Jan Mar-2011 Sector: Forestry (100%) received Additional Financing during no The Project Development Objective is to achieve sustainable Project management of plantation forests and the conservation of biodiversity in special use forest. Implementation is advancing well and good progress is being made towards achieving the project development objectives. Under the Smallholder Plantation Forest Component, about 11,000 households have received Land Use Rights Certificates through the project and about 23,000 hectares of smallholder plantations have been established. Good progress is being made in nursery upgrading and in improving planting and seedling materials which are critical for long-term environmental sustainability and quality. Under the Special Use Forest (SUF) Component, the Vietnam Conservation Fund (VCF) has been established and is fully operational. The VCF is proving to be an effective financing mechanism for SUFs. A total of 46 SUFs small grant proposals are now under implementation throughout the country with financial support from the VCF. Monitoring of conservation impact is also in place and initial results show positive trends in conservation impacts. Finally, a number of policy reviews have been initiated, good progress has been made in the formation of forest farmer groups, and capacity building on independent forest management certification issues is underway. IDA Effective XDR TF Closed USD TF Closed EUR TF Effective EUR TF Effective EUR TF Effective EUR Status of Projects in Execution - FY09

406 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 405

407 Sector: received Additional Financing during Project VN-2ND HIGHER EDUCATION (P079665) Vietnam 20-Jun Jun-2012 Tertiary education (91%); Central government administration (9%) no Increase the quality of teaching and research in universities, in ways that improve the employability of graduates and the relevance of research. Significant progress has been made by the project during its first year of implementation. In particular in Component 2, the Training and Research Innovation Grants, major activities and large procurement contracts have been launched in all participating universities. Regarding the component 1 on capacity building for policy development, though the technical teams from concerned departments of MOET have been strengthened and staffed and the local consultants have been mobilized, the project needs to speed up the selection process for international consultants to push ahead with the policy development agenda. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09

408 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 407

409 Sector: received Additional Financing during Project VN-Avian & Human Influenza Control &Prep (P101608) Vietnam 13-Mar Nov Dec-2010 General public administration sector (50%); Health (21%); General agriculture, fishing and forestry sector (21%); Other social services (7%); Solid waste management (1%) no The objective is to increase the effectiveness of government services in reducing the health risk to poultry and humans from avian influenza in eleven high priority provinces and thus contribute to addressing highly pathogenic avian influenza (HPAI) at the national level by controlling the disease at source in domestic poultry, by early detection and response to poultry and human cases and by preparing for the medical consequences of a human pandemic. The project continues to make progress toward achieving the project development objectives. The project has improved the effectiveness of Government services in reducing the health risk to poultry and humans from avian influenza in eleven high priority provinces by controlling the disease at source in domestic poultry and by early detection and response to poultry and human cases. Some evidence included the upgraded capacity of the regional laboratories to support effective disease surveillance and early detection; the continued disease surveillance in farms, markets and slaughterhouses with better quality management, the improved capacity of Department of Livestock Production through overseas training; the use of telephone hotlines in all project provinces and the investigation of calls from farmers; the procurement of stockpiles of emergency supplies including emergency vaccine; the training of doctors and nurses in infection control and the overseas training for district doctors in medical management of pulmonary illness in intensive care units; the renovation of provincial isolation wards; the training health workers in behavior change communication, and the upgrading of district preventive medicine centers. Currently, about 5-10 cases per province that had outbreaks are investigated (mainly focused on lab testing). Number of fatal cases in the population decreased from 20 cases in 2004 to 4 cases in 2009, however the fatality rate of H5 N1 remained high (4 out of 4 in 2009 equivalent to 100%). 408 Status of Projects in Execution - FY09

410 IDA Effective XDR TF Effective USD TF Effective USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 409

411 Sector: received Additional Financing during Project VN-Priority Infra Investment (P086508) Vietnam 22-May Jun-2013 Roads and highways (48%); Sewerage (28%); Flood protection (14%); General water, sanitation and flood protection sector (7%); Sub-national government administration (3%) no The objective is to improve the efficiency, effectiveness and sustainability of urban services in Da Nang City. The project is on track toward meeting the development objectives although there have been some delays regarding the institutional development of the Danang Transportation Works Management and Drainage Company (TMDC), and increase in waste water tariffs. These issues are being discussed and expected to be resolved in the near future. It's still at a relatively early stage to make a comprehensive assessment of the progress on major outcomes. IDA Effective XDR IDA-Q5870 Closed USD TF Closed USD Status of Projects in Execution - FY09

412 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 411

413 Sector: received Additional Financing during Project VN-Rural Transport 3 (P075407) Vietnam 21-Feb Dec-2011 Roads and highways (92%); Central government administration (6%); Sub-national government administration (2%) no The development objective is to reduce travel costs and improve access to markets, off-farm economic opportunities, and social services for poor rural communities in the 33 participating provinces in Northern and Central Vietnam. The project continues to make progress toward achieving its development objectives albeit with slower than expected implementation mainly due to long review and approval process. The rehabilitation component has been progressing well as the biggest component and has been advancing in all 33 provinces. As for the maintenance component, 32 out of 33 participating provinces have submitted maintenance plans in support of better maintenance management of their respective road networks. Although the target for length of road rehabilitated will not be met within the existing budget due to the adverse impact of inflation and price escalations, discussions are being held in providing additional finance to make up for this short fall. IDA Effective XDR TF Effective GBP TF Effective GBP Status of Projects in Execution - FY09

414 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 413

415 Sector: received Additional Financing during Project Vietnam PCB Management Project (P099460) Vietnam 23-Jun-2009 Power (50%); Solid waste management (30%); Public administration- Energy and mining (10%); Public administration- Industry and trade (10%) no To develop capacity in Vietnam to actively manage the vast bulk of PCBs in the country, consistent with the provisions of the Stockholm Convention, and for Vietnam to become ready for the follow-on phase of destruction of all PCB-contaminated soils and equipments. The project was approved at the end of the fiscal year 2009 but was not signed nor became effective. TF Closed USD Status of Projects in Execution - FY09

416 VN-TRANS & DISTRIB 2 (P084871) Vietnam 28-Jul May Dec-2010 Sector: Power (100%) received Additional Financing during no Project The objective of the project is the efficient development of Vietnam's transmission and distribution system. The project is on track to achieve its development objectives. Implementation of 110KV, 220KV and 500kV substations and transmission lines are in good progress. The transmission company has formed and started operations and market operator now assigned to NLDC. Although somewhat behind the schedule set out at appraisal, most targets are expected to be met by the current closing date. IDA Effective XDR TF Closed USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 415

417 VN-RURAL ENERGY 2 (P074688) Vietnam 18-Nov Mar Jun-2014 Sector: Power (100%) received Additional Financing during Project The additional financing of $200 million was approved on 21 May 2009 and the Financing Agreement was signed on 9 July The objective is to improve access to good quality, affordable electricity services to rural communities, in an efficient and sustainable manner, to support Vietnam's efforts towards socio-economic development The project is making progress toward achieving its Development Objective. To date all the goods and works required for rehabilitation and expansion of communes under the original project have been procured. About 300 project communes out of 968 have been energized. Work in the remaining communes is expected to be completed by the end of The sub-projects under the additional financing are under implementation and procurement is under way. IDA Effective XDR IDA Not Effective XDR TF Closed USD Status of Projects in Execution - FY09

418 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 417

419 VN-Third Rural Finance Project (P100916) Vietnam 22-May Dec-2013 Sector: Micro- and SME finance (100%) received Additional Financing during no The objective is to increase economic benefits to rural private Project enterprises and households by increasing their access to finance. The project became effective in the latter part of the reporting period and was still in too early a stage for meaningful progress. IDA Effective XDR Lending Information/Disbursement Summary (in millions USD) 418 Status of Projects in Execution - FY09

420 Sector: received Additional Financing during Project VN-ROAD NETWORK IMPROVEMT (P059663) Vietnam 18-Dec Jul Dec-2009 Roads and highways (93%); Central government administration (7%) no To improve the national road network through increased preventive maintenance and selective upgrading, and an increase in the level of resources available for road maintenance and capacity for planning, budgeting, and monitoring road assets. The overall implementation progress continues to improve and the project is expected to achieve its development objective. Road roughness, measured by the International Roughness Index, continues to decline (IRI 4.2), indicating better road conditions on project roads. More than half of the training initiatives under the capacity development program are now complete. The National Road Database developed under the project is expected to be fully operational by project completion. Earlier delays, arising from the unexpected sharp rises in the cost of construction inputs, land acquisition and resettlement, among others necessitates a further extension of the credit closing date to allow completion of the works that can be accommodated within the available credit amount. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 419

421 Lending Information/Disbursement Summary (in millions USD) 420 Status of Projects in Execution - FY09

422 VN - National CFC & Halon Phaseout Pr (P083593) Vietnam 01-May Dec-2014 Sector: Other industry (100%) received Additional Financing during no The objective is to phase out Ozone Depleting Substances (ODS) in Vietnam as per the agreement between Vietnam and Project Montreal Protocol without undue economic cost and to ensure a smooth transition to an ODS-free economy. The project is likely to meet the project development objectives as the progress so far has exceeded all GEO targets. The Grant Agreement of the project was amended on 24 September 2008 to include a new Methyl Bromide phase out component which is making contribution to the same objectives. Consumption of Chlorofluorocarbons (CFC), Halon and CTC (Carbon Tetrachloride) is well within the Montreal Protocol limit. Consumption of methyl bromide for non-qps applications in 2008 confirmed in June The consumption reduction has exceeded the agreed targets (139 tones). TF Effective USD Status of Projects in Execution - FY09 421

423 Lending Information/Disbursement Summary (in millions USD) 422 Status of Projects in Execution - FY09

424 Sector: received Additional Financing during Project VN-MKG DELTA TRANSPORT INFRA DEV (P083588) Vietnam 22-May Dec-2013 Roads and highways (55%); Ports, waterways and shipping (40%); Central government administration (2%); Sub-national government administration (2%); Tertiary education (1%) no To improve access to markets by businesses, farmers and the poor with lower logistics costs resulting from the alleviation of key physical and institutional bottlenecks of the main transport corridors in the Mekong Delta region. Progress towards meeting the development objectives has been slower than anticipated, due to delays in the finalization of detailed design work. However, some contracts for works with estimated value of $50 million will be signed in next six month time and it would help to improve the project implementation status. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 423

425 Lending Information/Disbursement Summary (in millions USD) 424 Status of Projects in Execution - FY09

426 Sector: received Additional Financing during Project VN-HANOI URBAN TRANSPORT (P083581) Vietnam 03-Jul Dec-2013 Roads and highways (51%); General transportation sector (33%); Other social services (12%); Sub-national government administration (4%) no The development objective of the IDA Credit is to increase urban mobility in targeted areas in Hanoi The project is the early stages of implementation, and meaningful progress towards meeting the development objectives cannot be measured at this time. IDA Effective XDR IDA-Q5750 Closed USD TF Closed USD Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 425

427 VN-WATER SUPPLY DEV. (P073763) Vietnam 21-Dec Oct Jun-2012 Sector: Water supply (95%); Sanitation (5%) received Additional Financing during no To improve water and household sanitation services in district Project towns and large urban centers in ways that are financially and environmentally sustainable, thus enhancing the health and economic potential of the resident households. The project implementation is behind schedule but implementation has picked up recently. Feasibility studies that will lead to investments were approved by June 30, Now bidding documents are being prepared and most of the contracts related to the project (about 95% of the total value of the credit) are expected to be signed by June 30, Close monitoring of the project would be required to ensure that the contracts are signed in a timely manner so that the project objectives are met as planned. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

428 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 427

429 Sector: received Additional Financing during Project VN -Natural Disaster Risk Mngt Project (P073361) Vietnam 15-Sep Jan Jun-2010 Flood protection (70%); General public administration sector (9%); General education sector (7%); Roads and highways (7%); Health (7%) no The objective is to establish and implement a comprehensive risk-management framework for national disaster prevention, preparedness, mitigation and recovery. The project continues to make significant progress toward achieving the PDO. Construction of critical natural disaster prevention and mitigation works are either in good progress or completed with good quality. Safer commune plans were successfully implemented in the first 10 pilot communes in Ha Tinh, Thua Thien Hue and Ben Tre provinces. Provinces, who were suffering from Xangsane typhoon and Lekima storm, received timely financial support from Component 3 budget for reconstruction works. Progress of Component 4 on capacity building has also been accelerated with significant achievement to date. IDA Effective XDR TF Closed USD TF Closed USD TF Effective USD TF Effective USD Status of Projects in Execution - FY09

430 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 429

431 VN-Regional Blood Transfusion Centers (P073305) Vietnam 16-Apr Sep Sep-2009 Sector: Health (100%) received Additional Financing during no The objective is to secure the health benefits of safe blood Project transfusions for the population covered by hospitals served by Regional Blood Transfusion Centers. The project has made progress towards meeting its objectives as evidenced by the increased share of blood center collections drawn from voluntary and repeat voluntary donors. IDA Effective XDR TF Closed USD Lending Information/Disbursement Summary (in millions USD) 430 Status of Projects in Execution - FY09

432 Sector: received Additional Financing during Project VN - PRSC 8 (P111164) Vietnam 25-Jun Dec-2009 General education sector (20%); Other social services (20%); General industry and trade sector (20%); General public administration sector (20%); Banking (20%) no The Country Partnership Strategy (CPS), submitted to the Board in January 2007, concluded that the Socio-economic Development Program of the government incorporated the necessary poverty reduction principles, was broadly sound and was a plan that could both deliver growth and reduce poverty. The CPS defines the PRSC as one of the modalities to support the implementation of SEDP. The Program Document for PRSC 6 charts the second cycle of PRSC operations (PRSCs 6-10). PRSC8 was approved by the Board on a fast track basis on June 25, It is expected to become effective in November 2009 when the formalities are completed. There are no effectiveness conditions attached to the credit. IDA Not Effective XDR Status of Projects in Execution - FY09 431

433 Sector: received Additional Financing during Project VN-Mkg Transp & Flood Protection (P042927) Vietnam 20-Dec Jul Dec-2010 Roads and highways (80%); Flood protection (14%); Central government administration (6%) no The development objective is to: (a) complete the rehabilitation of Highway No. 1, including increased protection for certain flood-prone segments; and (b) improve the efficiency of the regional transport network in the Mekong Delta. The project is well advanced towards the achievement of the development objectives. Rehabilitation of Highway 1, including increased protection of flood prone sections, has been completed. Approximately 70km of regional network improvement has been completed, and further rehabilitation of 58 km is expected to improve access to rural areas by connecting them to the main trade and movement corridors. Construction of the Ganh Hao 2 Bridge and six bridges in the project s Dam Cung e Nam Can road section constitute fundamental linkages critical to the viability of the rehabilitated NH1 corridor and will improve network capacity by removing a significant bottleneck in Can Tho once completed. IDA Effective XDR IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09

434 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 433

435 Sector: received Additional Financing during Project VN-HIV/AIDS Prevention Project (P082604) Vietnam 29-Mar Dec Dec-2011 Health (70%); Central government administration (15%); Subnational government administration (10%); Other social services (5%) no The specific object of this project is to support programs designed to halt transmission of HIV/AIDS among vulnerable populations (People Living With HIV/AIDS, Injecting Drug Users, Commercial Sex Workers, and their clients and sexual partners) and between these vulnerable populations and the general population. The project has successfully set up and maintained a network of 2,000 peer educators and 1,300 collaborators who are participating in implementation of harm reduction activities at 20 project provinces and cities. A national M&E framework and indicator set were finalized, and put in use under project support. Starting from 0% in 2005, by December 2008, 100% of project provinces have established the adequate M&E system. At the end of 2006, more than 2500 health workers were trained on both professional skill and program management skill. In this regards, it's highlighted that the behavior change communication campaign on HIV/AIDS prevent ion and reducing stigma and discrimination have been executed by all project provinces, where 39 million of population are reached, through mass media. Percentage of vulnerable groups in project provinces reporting safer injection practices, and condom use in sexual intercourse have already exceeded the target which was set at 80% at the end of project. In December 2008, these targets were reached at % and 93.3%, respectively. IDA-H1520 Effective XDR TF Closed USD Status of Projects in Execution - FY09

436 Lending Information/Disbursement Summary (in millions USD) Status of Projects in Execution - FY09 435

437 VN-Rural Distribution Project (P099211) Vietnam 22-May Jun-2013 Sector: Power (100%) received Additional Financing during no The project development objective is to improve the reliability Project and quality of medium voltage service to targeted retail electricity distribution systems. The project is on track toward achieving its Development Objective, though at this moment it is too early to measure the outcome. To date about $10 million was disbursed, procurement for works and goods required for the project is progressing, about $40 million has been committed through signed contracts, and the constructions are started in the project sites. IDA Effective XDR Lending Information/Disbursement Summary (in millions USD) 436 Status of Projects in Execution - FY09

438 Sector: received Additional Financing during Project VIETNAM WATER RESOURCES ASSISTANCE (P065898) Vietnam 30-Mar May Dec-2011 Irrigation and drainage (80%); Flood protection (10%); Water supply (5%); Central government administration (3%); Other social services (2%) no The project development objectives are: (a) to foster agricultural diversification and productivity through irrigation system modernization, thereby raising farm household incomes and reducing rural poverty; (b) to establish effective systems of dam safety management and lower the risks associated with dams; and (c) to promote the environmentally sustainable development and management of water resources in the Thu Bon River Basin. The project is lagging behind schedule but has made progress recently and is likely to achieve its development objectives. The completion of technical detailed designs has paved the way for canal works to start in late Construction has started on the ground. Implementation of dam safety component continues to make progress with construction partially completed in some subprojects. Most of detailed engineering design of canal works has been completed. With the great efforts from the Ministry of Agriculture and Rural Development and the Project Management Units, the systems of dam safety management have been effectively set up. The water resources and environmental conditions in the Thu Bon River Basin have been also increasingly enhanced. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09 437

439 Lending Information/Disbursement Summary (in millions USD) 438 Status of Projects in Execution - FY09

440 VN - Rural Finance II Project (P072601) Vietnam 30-May Nov Sep-2009 Sector: Banking (85%); Micro- and SME finance (15%) received Additional Financing during no The objectives are to develop the rural economy and improve living conditions in the rural areas through: (a) encouraging private sector investments, particularly of farm households Project and private rural entrepreneurs; (b) strengthening the banking system's capacity to serve the rural economy; and (c) increasing access of the rural poor to financial services. Progress toward meeting the development objectives has been good. This Project has met most of the key performance indicators even with the current challenging economic and financial status. Subprojects financed by the Project bring positive impacts on agricultural diversification and off-farm employment, and have generated a total investment of US$740 million. The end-borrowers very much appreciated the financial services they received under the Project in developing their business and increasing their income as well as creating job for hired labors. There are also indications that the project is contributing positively to strengthening of the participating banks through the required implementation of institutional development plans, technical assistance, and training programs. This project has been used as an important vehicle for dialogue with the government on financial sector issues, and an important complement to the technical assistance provided by the financial sector unit. IDA Effective XDR Status of Projects in Execution - FY09 439

441 Lending Information/Disbursement Summary (in millions USD) 440 Status of Projects in Execution - FY09

442 VN-EC HEALTHCARE SUPPORT TO THE POOR (P110251) Vietnam 20-Jun-2008 Sector: Health (90%); Other social services (10%) received Additional Financing during no To improve the health status of the poor and ethnic minorities in the Northern Uplands and Central Highlands regions Project through (i) increased coverage of essential health services especially at the commune level; and (ii) improved health service planning at the district level. The Project was still in too early a stage for meaningful progress. Status of Projects in Execution - FY09 441

443 Sector: received Additional Financing during Project VN-Northern Upland Health Support Proje (P082672) Vietnam 13-Mar Aug-2014 Health (71%); Compulsory health finance (15%); Central government administration (8%); Sub-national government administration (6%) no To increase utilization of district health services especially among Decision 139 beneficiaries in the Northern Upland Provinces through (i) strengthening of district hospitals and (ii) reducing financial constraints to accessing health services. The Project was in too early a stage for meaningful progress. IDA Effective XDR TF Closed USD Lending Information/Disbursement Summary (in millions USD) 442 Status of Projects in Execution - FY09

444 Sector: received Additional Financing during Project Payment System and Bank Modernization 2 (P082627) Vietnam 10-Mar Feb Jun-2010 Banking (76%); Payment systems, securities clearance and settlement (24%) no The Project Development Objectives are to assist Vietnam's banking sector to (i) meet the demand of the economy for fast, reliable and safe payment services, (ii) broaden access to finance to facilitate the achievement of the government's poverty reduction targets, and (iii) improve the operations of the participating banks through expansions of the Inter Bank Payment System and the Core Banking Solutions. Significant progress has been achieved. Because of the completion of system expansions, high-value interbank transactions are now processed on a Real-Time, Gross Settlement basis; and the rest on an end-of-day net basis. This has greatly improved the pace and reliability of payment services provided by the Vietnam s banking system. Completed upgrading of network security and backup/disaster recovery capacity has enhanced system security and safety. New additional functionalities are being procured or installed to the core banking systems of the participating banks which will broaden and deepen the banks# outreach via internet and mobile phone banking. At the banks where project implementation has been completed or well in progress, management has access to daily balance sheet and other financial and operational information. However, not all the project entities have achieved the same outcomes. In particular, project implementation at one participating bank has suffered serious delays. In May-June 2009, the bank s management finally overcome the obstacles and mobilized adequate human and financial resources for project implementation. IDA Effective XDR TF Closed USD TF Effective USD Status of Projects in Execution - FY09 443

445 Lending Information/Disbursement Summary (in millions USD) 444 Status of Projects in Execution - FY09

446 Sector: received Additional Financing during Project VN-PRIMARY EDUC FOR DISADVANTAGED CHILRE (P044803) Vietnam 06-May Dec Dec-2009 Primary education (97%); Pre-primary education (2%); Central government administration (1%) no The objective is to improve access to primary school and the quality of education for disadvantaged children. Progress has been made in achieving the PDO with clear benefits to students in terms of student learning, decreased drop-out rates, increased attendance and retention, etc. PEDC interventions such as Teaching Assistant and School Readiness showed students performing better. Project schools meeting Fundamental School Quality Level continue to increase significantly, with PEDC targeting the poorest and most disadvantaged communities. IDA Effective XDR TF Closed USD TF Effective USD TF Closed USD TF Effective USD Status of Projects in Execution - FY09 445

447 Lending Information/Disbursement Summary (in millions USD) 446 Status of Projects in Execution - FY09

448 Sector: received Additional Financing during Project VN-GEF DEMAND SIDE MGMT & ENERGY (P071019) Vietnam 24-Jun May Jun-2010 District heating and energy efficiency services (70%); Power (30%) no The objective is to (a) develop and expand Demand Side Management (DSM) business programs and test new market transformation efforts within the national electric utility, Electricity of Vietnam (EVN); and (b) develop sustainable business models and mechanisms to support energy efficiency retrofit investments in commercial and industrial facilities. The GEF objective is the reduction of greenhouse gas emissions in the energy sector through systematic removal of barriers to DSM and EE investment. The project is on track toward achieving its development objectives. The Commercial Energy Efficiency Program has supported the development of sustainable business models and mechanisms to support energy efficiency retrofit investment. The training program and market promotion campaign were completed. The grant facility has been catalyzing investment transactions contributing to energy efficiency in Vietnam. By June 30, 2009, a total investment in 107 approved subprojects supported by the program is about $4.5 million. Green house gas emission reduction attributed to the approved subprojects is estimated to be 50,000 tons of CO2 annually. The two pilot programs on Solar Water Heater and Standard and Labeling have been completed effectively contributing to capacity building, formulation of policy and regulations and design of energy efficiency activities. The Law on Energy Efficiency has been submitted to the Government for its review before submission to the National Assembly for approval. TF Closed USD TF Effective USD Status of Projects in Execution - FY09 447

449 Lending Information/Disbursement Summary (in millions USD) 448 Status of Projects in Execution - FY09

450 Sector: Project VN - Agriculture Competitiveness Project (P108885) Vietnam 23-Sep Dec-2013 General agriculture, fishing and forestry sector (32%); Roads and highways (25%); Public administration- Agriculture, fishing and forestry (20%); Irrigation and drainage (12%); Agro-industry (11%) The project development objective is to strengthen the competitiveness of smallholder farmers, with a focus on eight provinces in central Vietnam, in collaboration with the agribusiness sector. The project is on track to achieving its development objectives. It has conducted business roundtable consultations and workshops with farmers, research institutes, local authorities and concerned agencies to assess demands of applied research and technological packages that directly respond to the need to improve productivity and quality and to meet market requirements. A short list of proposals for applied research and technologies needed in each province were drawn from these consultations. Initial progress was made towards establishing productive partnerships through information campaigns and meetings with agribusinesses and farmers to provide them information about opportunities under the project. The project has identified critical rural infrastructure needed to support product competitiveness and design for the first batch of rural schemes already started in some provinces and construction is expected to begin in It's still at too early a stage to measure the progress on major outcomes. IDA Effective XDR TF Closed USD Status of Projects in Execution - FY09 449

451 Lending Information/Disbursement Summary (in millions USD) 450 Status of Projects in Execution - FY09

452 Sector: received Additional Financing during Project Public Financial Management Reform Proj. (P075399) Vietnam 22-May Dec Feb-2011 Central government administration (75%); Sub-national government administration (25%) no The project development objective is to strengthen budget planning, execution, reporting and accountability. The Project continues to progress toward achieving the development objectives in FY09, with accelerated pace toward the end of the FY. The implementation of the Treasury and Budget Management Information System (TABMIS) has reached a critical milestone with system pilot go live launched in April It is expected the TABMIS will roll-out to the first 10 provinces by end In other areas, good progress has been recorded with the completion of the Medium Term Expenditure Frameworks (MTEFs) reports of in education, health, transport, and agriculture and rural development sectors and three provinces, and with the finalization of relevant training materials for learners at managerial level. The first-ever Public Debt Management Law was passed, consolidating the management of domestic and external debt. Eight guiding decrees for the law are under preparation with expected completion by year end. The creation of the Debt Management and External Finance Department (DMEFD) under the Ministry of Finance (MOF) has helped target the training and technical assistance inputs to those taking on the roles and responsibilities of public debt managers and executors. IDA Effective XDR TF Effective GBP TF Closed USD Status of Projects in Execution - FY09 451

453 Lending Information/Disbursement Summary (in millions USD) 452 Status of Projects in Execution - FY09

STATUS OF PROJECTS IN EXECUTION FY09 SOPE

STATUS OF PROJECTS IN EXECUTION FY09 SOPE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY09 SOPE COUNTRY: GUINEA Operations Policy and Country

More information

STATUS OF PROJECTS IN EXECUTION FY09 SOPE

STATUS OF PROJECTS IN EXECUTION FY09 SOPE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY09 SOPE COUNTRY: RWANDA Operations Policy and Country

More information

STATUS OF PROJECTS IN EXECUTION FY09 SOPE

STATUS OF PROJECTS IN EXECUTION FY09 SOPE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY09 SOPE COUNTRY: GUATEMALA Public Disclosure Authorized Operations Policy and Country

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Africa Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 13 ARCHIVED on 29-Dec-2016 ISR26629 Implementing Agencies: Ministry

More information

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Montenegro Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 26-May-2017 ISR27925 Implementing Agencies:

More information

STATUS OF PROJECTS IN EXECUTION FY10 SOPE SOUTH ASIA REGION. Nepal. Public Disclosure Authorized. Public Disclosure Authorized

STATUS OF PROJECTS IN EXECUTION FY10 SOPE SOUTH ASIA REGION. Nepal. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY10 SOPE Nepal Operations Policy and Country Services

More information

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325) AFRICA Mozambique Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2007 Seq No: 22 APPROVED ISR29261 Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:23-May-2007

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING PROVINCIAL AND RURAL INFRASTRUCTURE PROJECT (CREDIT 3822-KH)

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING PROVINCIAL AND RURAL INFRASTRUCTURE PROJECT (CREDIT 3822-KH) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sustainable Development Department Southeast Asia Country Management Unit East Asia and

More information

The World Bank. losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized. Public Disclosure Copy

The World Bank. losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized. Public Disclosure Copy losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Lao People's Democratic Republic Lao PDR - Mainstreaming

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325) AFRICA Mozambique Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2007 Seq No: 24 ARCHIVED on 29-Aug-2018 ISR33744 Implementing Agencies: ROAD FUND (Fundo de Estradas),

More information

Second Disaster Risk Management Development Policy Loan with a CAT-DDO (P155656)

Second Disaster Risk Management Development Policy Loan with a CAT-DDO (P155656) Public Disclosure Authorized EAST ASIA AND PACIFIC Philippines Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Development Policy Lending FY 2016 Seq No: 4 ARCHIVED on 21-Sep-2017

More information

6 Report No.: JSDSC1361 1

6 Report No.: JSDSC1361 1 Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE 6 Report No.: JSDSC1361 1,2 Date ISDS Prepared/Updated: 05-Nov-2015 Date ISDS Approved/Disclosed: 06-Nov-2015 Public Disclosure

More information

Cambodia Sustainable Development Resource Mobilization: Assessing Financing Gaps and Needs

Cambodia Sustainable Development Resource Mobilization: Assessing Financing Gaps and Needs Cambodia Sustainable Development Resource Mobilization: Assessing Financing Gaps and Needs KIM VEARA, LECTURER, DEPARTMENT OF ECONOMIC DEVELOPMENT, FACULTY OF DEVELOPMENT STUDIES, ROYAL UNIVERSITY OF PHNOM

More information

2015 Development Policy Financing Retrospective: Preliminary Findings

2015 Development Policy Financing Retrospective: Preliminary Findings 2015 Development Policy Financing Retrospective: Preliminary Findings Purpose of this Consultation Meeting on the DPF Retrospective The 2015 Retrospective will focus on the Bank s experience with Development

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 12 ARCHIVED on 08-Dec-2017

More information

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473)

Montenegro Institutional Development and Agriculture Strengthening (MIDAS) (P107473) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Montenegro Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 13 ARCHIVED on 12-Apr-2016 ISR23062 Implementing Agencies:

More information

Results-Based Rural Water Supply and Sanitation Under the National Target Program (P127435)

Results-Based Rural Water Supply and Sanitation Under the National Target Program (P127435) Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Water Global Practice Requesting Unit: EACVF Responsible Unit: GWA02 IBRD/IDA Program-for-Results Financing FY 2013 Team Leader(s): Lilian Pena

More information

Cambodia. Impacts of Global Financial Crisis

Cambodia. Impacts of Global Financial Crisis Cambodia Impacts of Global Financial Crisis Cambodia s economy has significant vulnerabilities to the global economic crisis. Cambodia is a small open economy with a dynamism based on a non-diversified

More information

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785)

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Operation Name:

More information

China s Current Economic Situation and Policy Implications

China s Current Economic Situation and Policy Implications China s Current Economic Situation and Policy Implications Xuesong Li Professor of Economics, xsli@cass.org.cn Deputy Director of Institute of Quantitative & Technical Economics Chinese Academy of Social

More information

EAST ASIA AND PACIFIC. Investment Project Financing P People's Republic of China

EAST ASIA AND PACIFIC. Investment Project Financing P People's Republic of China Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA31584 Project Name

More information

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857 Project

More information

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA1417

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA1417 PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No: PIDA1417 Project Name Parent Project Name Region Country Sector(s) Theme(s) Lending Instrument Project ID Parent Project ID Borrower(s)

More information

Implementation Status & Results Report Niger Disaster Risk Management and Urban Development Project (P145268)

Implementation Status & Results Report Niger Disaster Risk Management and Urban Development Project (P145268) Public Disclosure Authorized AFRICA Niger Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 04-Apr-2018 ISR30085 Implementing

More information

Implementation Status & Results India Assam State Roads Project (P096018)

Implementation Status & Results India Assam State Roads Project (P096018) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results India Assam State Roads Project (P096018) Operation Name: Assam State Roads Project (P096018) Project Stage: Implementation

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Uzbekistan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 12-Jan-2018 ISR30620 Implementing Agencies: Republic

More information

REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT

REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT THE GEF TRUST FUND Submission Date: 15 February 2008 Re-submission Date: 25 March 2008 GEFSEC PROJECT ID 1 : GEF AGENCY PROJECT

More information

Implementation Status & Results Indonesia Initiatives for Local Governance Reform Project (P076174)

Implementation Status & Results Indonesia Initiatives for Local Governance Reform Project (P076174) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Initiatives for Local Governance Reform Project (P076174) Operation Name: Initiatives

More information

Implementation Status & Results Philippines Rural Power Project (P066397)

Implementation Status & Results Philippines Rural Power Project (P066397) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Philippines Rural Power Project (P066397) Operation Name: Rural Power Project (P066397) Project

More information

MATRIX OF STRATEGIC VISION AND ACTIONS TO SUPPORT SUSTAINABLE CITIES

MATRIX OF STRATEGIC VISION AND ACTIONS TO SUPPORT SUSTAINABLE CITIES Urban mission and overall strategy objectives: To promote sustainable cities and towns that fulfill the promise of development for their inhabitants in particular, by improving the lives of the poor and

More information

Implementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207)

Implementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207) Operation Name: Transport Rehabilitation

More information

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469)

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Operation Name: Second National

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Nepal Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2015 Seq No: 5 ARCHIVED on 28-Jun-2017 ISR28273 Implementing Agencies: Ministry of

More information

STATUS OF PROJECTS IN EXECUTION FY08 SOUTH ASIA REGION COUNTRY: BANGLADESH. Public Disclosure Authorized. Public Disclosure Authorized

STATUS OF PROJECTS IN EXECUTION FY08 SOUTH ASIA REGION COUNTRY: BANGLADESH. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY08 COUNTRY: BANGLADESH Operations Policy and Country

More information

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy AFRICA Ethiopia Social Protection & Labor Global Practice IBRD/IDA Sector Investment and Maintenance Loan FY 2013 Seq No: 12 ARCHIVED on 09-Oct-2015

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 24-Feb-2015

More information

The World Bank Municipal Services Improvement (P096481)

The World Bank Municipal Services Improvement (P096481) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Macedonia, former Yugoslav Republic of Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 15-Jun-2015

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Country Sector(s) PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

More information

- 1 - Table 1. Cambodia: Policy Framework Paper Matrix,

- 1 - Table 1. Cambodia: Policy Framework Paper Matrix, - 1 - Table 1. Cambodia: Framework Paper Matrix, 1. Fiscal Reform Generate additional revenue of 4 percent of GDP over four years to 2002. a. Broaden revenue base. Review mechanism for timber royalties,

More information

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Public Disclosure Authorized SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice IBRD/IDA Specific Investment

More information

COMBINED PROJECT INFORMATION DOCUMENTS / INTEGRATED SAFEGUARDS DATA SHEET (PID/ISDS) APPRAISAL STAGE

COMBINED PROJECT INFORMATION DOCUMENTS / INTEGRATED SAFEGUARDS DATA SHEET (PID/ISDS) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized COMBINED PROJECT INFORMATION DOCUMENTS / INTEGRATED SAFEGUARDS DATA SHEET (PID/ISDS)

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

SECTOR ASSESSMENT (SUMMARY): TRANSPORT SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Myanmar is the largest country in the Greater Mekong Subregion (GMS) with a total land area

More information

Implementation Status & Results Samoa SAMOA HEALTH SECTOR MANAGEMENT PROGRAM SUPPORT PROJECT (P086313)

Implementation Status & Results Samoa SAMOA HEALTH SECTOR MANAGEMENT PROGRAM SUPPORT PROJECT (P086313) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Samoa SAMOA HEALTH SECTOR MANAGEMENT PROGRAM SUPPORT PROJECT (P086313) Operation Name: SAMOA HEALTH

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/15/2010 1. Basic Project Data Original

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT

More information

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Responsible

More information

TA for Capacity Development in Hydropower and Mining Sector (P109736)

TA for Capacity Development in Hydropower and Mining Sector (P109736) Public Disclosure Authorized EAST ASIA AND PACIFIC Lao People's Democratic Republic Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2010 Seq No: 15 ARCHIVED on 12-Nov-2018

More information

Implementation Status & Results Cambodia Cambodia Trade Facilitation and Competitiveness (Julian Clark co-ttl) (P089196)

Implementation Status & Results Cambodia Cambodia Trade Facilitation and Competitiveness (Julian Clark co-ttl) (P089196) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Cambodia Cambodia Trade Facilitation and Competitiveness (Julian Clark co-ttl) (P089196) Operation

More information

The World Bank Nam Theun 2 Social and Environment Project (P049290)

The World Bank Nam Theun 2 Social and Environment Project (P049290) Public Disclosure Authorized EAST ASIA AND PACIFIC Lao People's Democratic Republic Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2005 Seq No: 10 ARCHIVED on

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:CAM 36593 TECHNICAL ASSISTANCE TO THE KINGDOM OF CAMBODIA FOR IMPROVING INSURANCE SUPERVISION December 2002 CURRENCY EQUIVALENTS (as of 3 December 2002) Currency Unit riel (KR)

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 17 ARCHIVED on 29-Jun-2017 ISR27259 Implementing

More information

SUMMARY OF INSPECTION PANEL CASES October 15, 2012

SUMMARY OF INSPECTION PANEL CASES October 15, 2012 SUMMARY OF INSPECTION PANEL CASES October 15, 2012 REQUEST REQUEST RECEIVED REQUEST REGISTERED INSPECTION PANEL RECOMMENDATION AND ITS APPROVAL BY THE BOARD PANEL S ACTIVITY POLICIES AND PROCEDURES RAISED

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

The World Bank Building a Modern Fiscal System Technical Assistance (P154694)

The World Bank Building a Modern Fiscal System Technical Assistance (P154694) Public Disclosure Authorized EAST ASIA AND PACIFIC China Macro Economics & Fiscal Management Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 15-Jun-2017 ISR26699 Implementing

More information

STATUS OF PROJECTS IN EXECUTION FY07 SOPE TUNISIA

STATUS OF PROJECTS IN EXECUTION FY07 SOPE TUNISIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY07 SOPE TUNISIA Operations Policy and Country Services

More information

Implementation Status & Results Lao People's De Lao PDR Trade Development Facility Project (P106165)

Implementation Status & Results Lao People's De Lao PDR Trade Development Facility Project (P106165) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Lao People's De Lao PDR Trade Development Facility Project (P106165) Operation Name: Lao PDR Trade

More information

GLOBAL INFRASTRUCTURE FACILITY. A partnership platform for greater investment in the infrastructure of emerging markets and developing economies

GLOBAL INFRASTRUCTURE FACILITY. A partnership platform for greater investment in the infrastructure of emerging markets and developing economies GLOBAL INFRASTRUCTURE FACILITY A partnership platform for greater investment in the infrastructure of emerging markets and developing economies COLLABORATION FINANCE LEVERAGE IMPACT The Global Infrastructure

More information

RCI as Driver of Inclusive Growth

RCI as Driver of Inclusive Growth RCI as Driver of Inclusive Growth 19 July 2013 Alfredo Perdiguero Principal Economist Thailand Resident Mission Southeast Asia Department Asian Development Bank Disclaimer: In preparing any country program

More information

Implementation Status & Results Chad Public Financial Management Capacity Building (P090265)

Implementation Status & Results Chad Public Financial Management Capacity Building (P090265) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Chad Public Financial Management Capacity Building (P090265) Operation Name: Public Financial Management

More information

Implementation Status & Results Indonesia Project for Indonesian Tax Administration Reform (PINTAR) (P100740)

Implementation Status & Results Indonesia Project for Indonesian Tax Administration Reform (PINTAR) (P100740) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Project for Indonesian Tax Administration Reform (PINTAR) (P100740) Operation Name: Project

More information

The World Bank MN-Mining Infrastructure Investment Supp (P118109) (P118109)

The World Bank MN-Mining Infrastructure Investment Supp (P118109) (P118109) Public Disclosure Authorized EAST ASIA AND PACIFIC Mongolia Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 12 ARCHIVED on 01-Jun-2017 ISR28196 Implementing Agencies:

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Second Additional Financing to Road Rehabilitation & Maintenance Project Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Second Additional Financing to Road Rehabilitation & Maintenance Project Region Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Second Additional Financing to Road Rehabilitation & Maintenance Project Region AFRICA Sector Roads and highways (100%) Project ID P120723

More information

The World Bank Climate Change and Green Growth in Vietnam (P155824)

The World Bank Climate Change and Green Growth in Vietnam (P155824) Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Environment & Natural Resources Global Practice IBRD/IDA Development Policy Lending FY 2016 Seq No: 1 ARCHIVED on 20-Jun-2017 ISR27319 Implementing

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

Implementation Status & Results China China Wuhan Second Urban Transport (P112838)

Implementation Status & Results China China Wuhan Second Urban Transport (P112838) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results China China Wuhan Second Urban Transport (P112838) Operation Name: China Wuhan Second Urban Transport (P112838)

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021272 Public Disclosure Authorized Public Disclosure Authorized Operation ID P159774 Country Fiji Operation Name Fiji Post-Cyclone Winston

More information

Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353)

Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353) Public Disclosure Authorized Public Disclosure Authorized Project Name: Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353) Nigeria Edo State First Development

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) the Borrower has applied to ADB for a loan

More information

Implementation Status & Results Mozambique Health Commodity Security Project (P121060)

Implementation Status & Results Mozambique Health Commodity Security Project (P121060) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Mozambique Health Commodity Security Project (P121060) Operation Name: Health Commodity Security

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE WESTERN PROVINCES RURAL WATER SUPPLY, SANITATION AND HYGIENE PROMOTION PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE WESTERN PROVINCES RURAL WATER SUPPLY, SANITATION AND HYGIENE PROMOTION PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Madagascar Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2006 Seq No: 21 ARCHIVED on 30-Dec-2014 ISR17647 Implementing Agencies: Public Disclosure

More information

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized o INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE te: This ISDS will be considered

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 14-Jul-2014

More information

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 17 ARCHIVED on 29-Jun-2017 ISR28824 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Copy AFRICA Ghana Environment & Natural Resources Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 7 ARCHIVED on 10-Aug-2015 ISR18623 Implementing

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Nigeria Governance Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq

More information

Implementation Status & Results Kazakhstan SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

Implementation Status & Results Kazakhstan SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Kazakhstan SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC

More information

Implementation Status & Results Indonesia National Community Empowerment Program In Urban Areas For (P125405)

Implementation Status & Results Indonesia National Community Empowerment Program In Urban Areas For (P125405) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia National Community Empowerment Program In Urban Areas For 2012-2015 (P125405) Operation

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Dec ,872,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Dec ,872,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020840 Public Disclosure Authorized Public Disclosure Authorized Project ID P103470 Country OECS Countries

More information

Public Disclosure Copy. Implementation Status & Results Report Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

Public Disclosure Copy. Implementation Status & Results Report Gansu Cultural and Natural Heritage Protection and Development Project (P091949) Public Disclosure Authorized EAST ASIA AND PACIFIC China Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 8 ARCHIVED on 26-Nov-2014 ISR16372 Implementing Agencies: GANSU

More information

Flood Damage and Post-Flood Rehabilitation. Economic Performance in Q1/2012 and Outlook for 2012

Flood Damage and Post-Flood Rehabilitation. Economic Performance in Q1/2012 and Outlook for 2012 Presentation Outline 1 Flood Damage and Post-Flood Rehabilitation 2 Investment Plans of Strategic Committee for Reconstruction and Future Development 3 Economic Performance in Q1/2012 and Outlook for 2012

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE . Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic

More information

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272)

The World Bank Emergency 2007 Cyclone Recovery and Restoration Project (P111272) Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Emergency Recovery Loan FY 2009 Seq No: 14 ARCHIVED on 31-Dec-2015 ISR21491

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name Wenchuan

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931)

The World Bank Land Husbandry, Water Harvesting and Hillside Irrigation (P114931) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF LAND HUSBANDRY, WATER HARVESTING AND HILLSIDE IRRIGATION PROJECT APPROVED

More information

LRTF Quarterly Report March 1, As of February 22, 2012, the LRTF status was as follows: USD million

LRTF Quarterly Report March 1, As of February 22, 2012, the LRTF status was as follows: USD million LRTF Quarterly Report March 1, 2012 I. LRTF Administration As of February 22, 2012, the LRTF status was as follows: USD million Contributions Received Cash Contributions $146,902,156.80 Investment Income

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3247. Date ISDS Prepared/Updated: 11/28/2007 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3247. Date ISDS Prepared/Updated: 11/28/2007 I. BASIC INFORMATION. A. Basic Project Data Date ISDS Prepared/Updated: 11/28/2007 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3247 Country: Madagascar Project ID: P104049 Project Name:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 8 ARCHIVED on 14-Dec-2015

More information

ONE WASH NATIONAL PROGRAMME (OWNP)

ONE WASH NATIONAL PROGRAMME (OWNP) ONE WASH NATIONAL PROGRAMME (OWNP) ONE Plan ONE Budget ONE Report planning with linked strategic and annual WASH plans at each level budgeting re ecting all WASH-related investments and expenditures financial

More information

Report No.: ISDSA13978

Report No.: ISDSA13978 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 0 o Date ISDS Prepared/Updated: 29-Jul-2015 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL

More information

CC is a development issue - not just an environmental concern CC impacts on human development, economic growth, poverty alleviation and the

CC is a development issue - not just an environmental concern CC impacts on human development, economic growth, poverty alleviation and the CC is a development issue - not just an environmental concern CC impacts on human development, economic growth, poverty alleviation and the achievement of MDGs Long term: human lives and livelihoods are

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Transport Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 12 ARCHIVED on 24-Feb-2015 ISR18063 Implementing Agencies: Hanoi Urban

More information

Doing Business 2015 Fact Sheet: East Asia and the Pacific

Doing Business 2015 Fact Sheet: East Asia and the Pacific Doing Business 2015 Fact Sheet: East Asia and the Pacific Fifteen of 25 economies in East Asia and the Pacific implemented at least one regulatory reform making it easier to do business in the year from

More information

Mozambique has emerged from decades of war to become one

Mozambique has emerged from decades of war to become one IDA at Work Mozambique: From Post-Conflict Recovery to High Growth Mozambique has emerged from decades of war to become one of Africa s best-performing economies. One of the poorest countries in the world

More information