IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-47610) ON A CREDIT

Size: px
Start display at page:

Download "IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-47610) ON A CREDIT"

Transcription

1 Public Disclosure Authorized Document of The World Bank Report No: ICR2482 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-0 IDA-1 IDA-47610) ON A CREDIT Public Disclosure Authorized IN THE AMOUNT OF SDR MILLION (US$ MILLION EQUIVALENT) TO THE PEOPLES REPUBLIC OF BANGLADESH FOR THE MUNICIPAL SERVICES PROJECT Public Disclosure Authorized Urban Sector Unit Bangladesh Country Unit South Asia Region December 27, 2012

2 CURRENCY EQUIVALENTS (Exchange Rate Effective November 30, 2012) Currency Unit = Bangladeshi Taka 1.00 = US$ 0.01 US$ 1.00 = Tk FISCAL YEAR July 1 June 30 ABBREVIATIONS AND ACRONYMS ADB BMDF CAS ERR FOAP GOB IDA LGED MDF MPRC MSU NPV PMU PPA Asian Development Bank Bangladesh Municipal Development Fund Country Assistance Strategy Economic Rate of Return Financial and Operational Action Plan Government of Bangladesh International Development Association Local Government Engineering Department Municipal Development Fund Municipal Performance Review Committee Municipal Support Unit Net Present Value Project Monitoring Unit Participatory and Partnership Approach Vice President: Isabel M. Guerrero Country Director: Ellen A. Goldstein Sector Manager: Ming Zhang Project Team Leader: Zahed H. Khan ICR Team Leader: Janis D. Bernstein

3

4 PEOPLES REPUBLIC OF BANGLADESH Municipal Services Project CONTENTS Data Sheet Page A. Basic Information B. Key Dates C. Ratings Summary D. Sector and Theme Codes E. Bank Staff F. Results Framework Analysis G. Ratings of Project Performance in ISRs H. Restructuring I. Disbursement Graph Main Document 1. Project Context, Development Objectives and Design Key Factors Affecting Implementation and Outcomes Assessment of Outcomes Assessment of Risk to Development Outcome Assessment of Bank and Borrower Performance Lessons Learned Comments on Issues Raised by Borrower/Implementing Agencies/Partners Annex 1. Project Costs and Financing Annex 2. Outputs by Component Annex 3. Economic and Financial Analysis Annex 4. Bank Lending and Implementation Support/Supervision Processes Annex 5. Beneficiary Survey Results Annex 6. Summary of Borrower's ICR and/or Comments on Draft ICR Annex 7. List of Supporting Documents Map IBRD 33368

5

6 A. Basic Information Country: Bangladesh Project Name: Municipal Services Project ID: P L/C/TF Number(s): IDA-0,IDA- 1,IDA ICR Date: 07/19/2012 ICR Type: Core ICR Lending Instrument: SIL Borrower: GOB Original Total Commitment: XDR M Disbursed Amount: XDR M Revised Amount: XDR M Environmental Category: B Implementing Agencies: Local Government Engineering Department, Bangladesh Municipal Development Fund Cofinanciers and Other External Partners: B. Key Dates Process Date Process Original Date Revised / Actual Date(s) Concept Review: 08/31/1997 Effectiveness: 10/25/ /25/1999 Appraisal: 06/13/1998 Restructuring(s): 2/10/ /21/ /23/2010 Approval: 03/16/1999 Mid-term Review: 03/02/2002 Closing: 06/30/ /30/2012 C. Ratings Summary C.1 Performance Rating by ICR Outcomes: Risk to Development Outcome: Bank Performance: Borrower Performance: Satisfactory Moderate Moderately Satisfactory Satisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Bank Ratings Borrower Ratings Quality at Entry: Satisfactory Government: Moderately Satisfactory Quality of Supervision: Moderately Satisfactory Implementing Agency/Agencies: Satisfactory Overall Bank Performance: Moderately Satisfactory Overall Borrower Performance: Satisfactory i

7 C.3 Quality at Entry and Implementation Performance Indicators Implementation QAG Assessments (if Indicators Performance any) Potential Problem Project at any time (Yes/No): Problem Project at any time (Yes/No): DO rating before Closing/Inactive status: Yes Yes Moderately Satisfactory Rating Quality at Entry (QEA): Highly Satisfactory Quality of Supervision (QSA): Moderately Unsatisfactory D. Sector and Theme Codes Original Actual Sector Code (as % of total Bank financing) General water, sanitation and flood protection sector Other social services Sub-national government administration Urban Transport 5 5 Theme Code (as % of total Bank financing) Municipal finance Municipal governance and institution building Participation and civic engagement Pollution management and environmental health Urban services and housing for the poor E. Bank Staff Positions At ICR At Approval Vice President: Isabel M. Guerrero Mieko Nishimizu Country Director: Ellen A. Goldstein Frederick Thomas Temple Sector Manager: Ming Zhang Frannie F. Humplick Project Team Leader: Zahed H. Khan Jonathan S. Kamkwalala ICR Team Leader: Janis D. Bernstein ICR Primary Author: Janis D. Bernstein F. Results Framework Analysis Project Development Objectives (from Project Appraisal Document) The Project Development Objective (PDO) is to improve environmental and infrastructure service delivery in urban areas. See section 1.2 for the entire PDO. ii

8 Revised Project Development Objectives (as approved by original approving authority) The Project Development Objective did not change during the implementation of the original project or the Additional Financing. (a) PDO Indicator(s) Indicator Baseline Value Original Target Values (from approval documents) Formally Revised Target Values Actual Value Achieved at Completion or Target Years Indicator 1.1 Municipalities able to plan, prioritize, and implement service improvement by end of project. Value Phase 1: 16 AF 2010 (Quantitative or Qualitative) Phase 2: Date achieved 03/16/ /30/ /30/ /30/2012 By 2010, 92 cities had received MSU capacity building and support for community Comments mobilization. During the AF 2010, the MSU extended the capacity building to another 91 cities. Indicator 1.2 Management reform in municipalities completed. Value (Quantitative or Qualitative) 0 Phase 1: 16 Phase 2: 40 AF Date achieved 03/16/ /30/ /30/ /30/2012 Comments By 2010, 133 cities achieved management reform. By June 30, 2012, another 50 completed reforms in project planning, tax and water tariff collection, and managing municipal accounts. Indicator 1.3 Demand driven and cost recovery measures introduced for revenue generating sub-projects. Value (Quantitative or Qualitative) 0 Phase 1: 16 Phase 2: 40 AF Date achieved 03/16/ /30/ /30/ /30/2012 By 2010, 112 cities had introduced these measures; under the AF2010, another 56 cities were Comments required to involve participation in project selection and to initiate measures to improve cost recovery. Indicator 2.1 MDF created and operational for on-lending to municipalities. BMDF operations BMDF operations streamlined and Value streamlined and its BMDF created and coordination (Quantitative or MDF not established coordination with operational with LGED and Qualitative) LGED and other other relevant agencies strengthened agencies strengthened Date achieved 03/16/ /1/ /30/ /30/2012 iii

9 Comments Indicator 2.2 Value (Quantitative or Qualitative) Under the AF2010, a new indicator was introduced - to streamline its operations and to strengthen coordination with LGED (for details on all of the measures taken, see Sec. 3.2 (b) of the ICR main text. Municipal Performance Review Committee (MPRC) established and operational by end of Phase 1 MPRC does not exist MPRC established and operational Established on July 5, 1999 Operational on March 16, 2002 Date achieved 03/16/ /16/2002 Comments Indicator 3.1 Value (Quantitative or Qualitative) The MPRB was established on July 5, 1999 and fully operational by March 16, 2002, when the first meeting was held. Physical investments targeting poverty and environmental improvements through community participation. No target established in PAD because of 595 works 0 the demand driven 595 works packages packages nature; by the AF of completed with BMDF completed with 2010, 454 works funding in 154 towns BMDF funding packages had been financed. Date achieved 03/16/ /30/ /30/ /30/2012 Phase II investments involved participation in planning and implementing sub-projects aimed Comments at poverty and environmental improvement. Specific targets for Phase 1 are described below. (b) Intermediate Outcome Indicator(s) Indicator Baseline Value Original Target Values (from approval documents) Indicator 1.1 Municipal Development Fund established by July 1, BMDF established by BMDF established July 1, 2000 Date achieved 03/16/ /9/ /9/2002 The delay was due mainly to the severe floods of 2000 which diverted project staff attention to Comments finance urgent repairs, and the transitional government putting final steps on hold until new government took over. Indicator 1.2 Municipal Performance Review Committee (MPRC) established by June 30, Established by June MPRC established 30, 1999 Date achieved 03/16/ /5/ /5/1999 Comments Indicator 1.3 Municipal Support Unit (MSU) fully staffed and working, as agreed with the Bank, by July 1, MSU fully staffed and working by July 1, 1999 MSU fully staffed and working iv Formally Revised Target Values Actual Value Achieved at Completion or Target Years

10 Date achieved 03/16/ /25/ /25/1999 Comments Indicator 1.4 Partnership and Participatory Approach (PPA) designed, in agreement with the Bank, by September 30, PPA designed in PPA designed in 0 agreement with the agreement with Bank Bank by September 30, 1999 Date achieved 03/16/ /30/ /30/1999 Comments Indicator 1.5 All Phase I participating city corporations and municipalities implement Financial and Operational Action Plan by June 30, All Phase I CCs and municipalities implement FOAP by June 30, 2000 All Phase I CCs and municipalities implemented FOAPs Date achieved 03/16/ /30/ /30/2000 Comments Indicator 1.6 At least 40 other municipalities implement FOAP by June 30, Phase I CCs and municipalities implemented FOAPs Date achieved 07/30/ /30/ /30/2004 Comments Indicator 2.1 Roads constructed/rehabilitated. 0 50% Phase I road works completed by June 30, % Phase I road works completed by June 30, 2001 Works completed Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. Indicator 2.2 Drainage facilities improved. 67% (25 km) completed by June 30, Works completed 100% (37 km) completed by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. Indicator 2.3 Construction of public toilets completed. v

11 0 68% (32 toilets) completed by June 30, 2000 Works completed 100% (47 toilets) completed by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. Indicator 2.4 Rehabilitation of water supply facilities completed. 75% (9 km) of water lines completed in Khulna by June 30, Works completed 100% (12 km) of water lines completed in Khulna by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. Indicator 2.5 Municipal markets upgraded. 50% (8) completed by June 30, Works completed 100% completed by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. Indicator 2.6 Bus/truck terminals constructed or rehabilitated in each city corporation and municipality. Two new bus terminals constructed by June 30, Seven new bus terminals constructed by June 30, 2001 Three bus terminals rehabilitated by June 30, 2001 Works completed Two new truck terminals constructed by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 Comments By 2005, 95% of the works were completed. Due to the need to redirect LGED s efforts to urgent repair works related to the 2000 floods, the project did not meet original target dates. vi

12 Indicator 2. 7 Facilities for solid waste management put in place Disposal sites identified/improved in all 16 phase 1 participating cities and municipalities by June 30, All community bins constructed and operated by June 30, 2001 Works completed All waste transport equipment procured and operational by June 30, 2001 Date achieved 03/16/ /31/ /31/2006 By 2005, 95% of the works were completed, and the original targets were not met due to the Comments 2000 floods. Disposal sites were not improved for all 16 Phase I cities due to land acquisition issues. New Indicator MDF-funded sub-projects in 56 more municipalities providing grant and loan funding for for AF 2010 schemes selected locally and implemented and loan repayments underway BMDF working with 112 municipalities BMDF working with 168 municipalities BMDF worked with 154 municipalities 826 km roads 1,156 km roads 1,128 km roads Value (Quantitative or Qualitative) 8500 street lights 175 km drains 75 public toilets 11,500 street lights 265 km drains 87 public toilets 24,960 street lights 260 km drains 87 public toilets 75 kitchen markets 90 kitchen markets 211 kitchen markets Value (Quantitative or Qualitative) 137 km water supply pipelines 167 km water supply pipelines 173 km water supply pipelines Date achieved 06/1/ /30/ /30/2012 Comments By 2010, BMDF had funded 454 packages that were completed. By 6/30/2012, 595 projects had been completed in 154 ULBs. The loan recovery rate is 75%. New Indicator Capacity building inputs by MSU extended to 50 more municipalities with expected increase for AF 2010 in holding tax collection in the 48-70% range in 20 additional municipalities. Ongoing capacity building in Capacity building in Capacity building in 92 municipalities 142 municipalities 142 municipalities 75 municipalities with tax billing computerized 125 municipalities (total) tax billing computerized 142 municipalities tax billing computerized vii

13 7,405 municipal staff provided training 8,400 municipal staff (total) provided training 8,400 municipal staff provided training 20% increase in tax collection in 20 municipalities 25% increase in tax collection by municipalities (average/range) viii 17.5% increase in tax collection by municipalities (average/range) Date achieved 06/1/ /30/ /28/2012 The 17.5% increase in tax collection is based on a sample of 39 cities; 23 had tax collection Comments rates in the 48-95% range; another 7 had collection rates in the 40-47% range. G. Ratings of Project Performance in ISRs No. Date ISR Actual Disbursements DO IP Archived (USD millions) 1 04/22/1999 Satisfactory Satisfactory /02/1999 Satisfactory Satisfactory /06/2000 Satisfactory Satisfactory /22/2000 Satisfactory Satisfactory /28/2000 Satisfactory Satisfactory /01/2001 Satisfactory Satisfactory /24/2001 Satisfactory Satisfactory /29/2001 Satisfactory Satisfactory /12/2001 Satisfactory Satisfactory /06/2002 Satisfactory Satisfactory /24/2002 Satisfactory Satisfactory /24/2003 Satisfactory Satisfactory /22/2003 Satisfactory Satisfactory /08/2004 Unsatisfactory Unsatisfactory /23/2004 Unsatisfactory Unsatisfactory /25/2005 Satisfactory Satisfactory /07/2005 Satisfactory Satisfactory /29/2006 Satisfactory Moderately Satisfactory /01/2006 Moderately Satisfactory Satisfactory /08/2007 Satisfactory Satisfactory /30/2007 Satisfactory Satisfactory /27/2008 Satisfactory Satisfactory /30/2008 Satisfactory Satisfactory /26/2009 Satisfactory Satisfactory /29/2009 Satisfactory Satisfactory /25/2010 Satisfactory Satisfactory /12/2010 Satisfactory Satisfactory /10/2011 Satisfactory Moderately Satisfactory /25/2012 Moderately Satisfactory Moderately Satisfactory /10/2012 Moderately Satisfactory Moderately Satisfactory

14 H. Restructuring (if any) Restructuring Date(s) Board Approved PDO Change ISR Ratings at Restructuring DO 2/10/2005 S S IP Amount Disbursed at Restructuring in USD millions 12/21/2007 S S /06/2010 S S Reason for Restructuring & Key Changes Made Additional funding of US$11 million reallocated from another IDA project, and reallocation of $15 million from the BMDF component for infrastructure rehabilitation in response to a major flood in September 2004 Addition of US$25 million and extension of closing date in response to a major flood for urgent repairs to flood damaged infrastructure, and to further operationalize BMDF. Additional financing of US$42 million to scale up BMDF operations. I. Disbursement Profile ix

15 1. Project Context, Development Objectives and Design 1.1 Context at Appraisal Country and Sector Background. At the time of project appraisal, the path of economic growth in Bangladesh was uncertain. As discussed in the Bangladesh Country Assistance Strategy (CAS) for the period , it could either remain a desperately poor country or become a nascent tiger economy, but it never managed to be either. Though better than in other developing countries at that time, the country s growth was too slow to have a significant impact on poverty. Nearly 36 percent of the population remained below the poverty line for the very poor; 53 percent below the poverty line for the poor. The Government of Bangladesh (GOB) also was confronting severe challenges in overcoming the institutional constraints to pursuing sound development activities. Despite a slowdown of population growth since independence (1971), the population (70 million) was expected to rise over the next 30 years by 60 million. The urban population had been growing at a rate of about 4.2 percent per annum. Until the early 1990s, this rapid growth was occurring mainly in the country s four metropolitan areas (Dhaka, Chittagong, Khulna, and Rajshahi). By the latter 1990s, smaller municipalities were experiencing rapid growth rates as well. Regardless of their size, all of the municipalities in Bangladesh at the time of project appraisal were facing: (a) inadequate urban infrastructure services; (b) weak management and financial capacity; (c) fragmentation of urban sector responsibilities among numerous central government agencies; and (c) an increasing level of urban poverty and accompanying environmental degradation. To respond to these issues, as highlighted in the CAS, the Bank aimed to assist the country in improving the coverage and efficiency of basic urban services; support private sector growth and urban poverty reduction through the formulation and implementation of appropriate strategies for institutional and financial reforms in municipalities; and support fiscal decentralization. In this context, the GOB with World Bank assistance designed the Bangladesh Municipal Services Project (MSP) to address the weak institutional and financial capacities that were undermining sustainable service delivery, and to promote sound urban management. Rationale for Bank Assistance. The World Bank s involvement in the project was valuable for several reasons. First, the Bank had supported the development of an urban strategy which mapped the policy, institutional, and financial reforms necessary to underpin and sustain the investments to be made in this sector, and thus improve municipal service delivery. Guided by this strategy, the Bank also had experience supporting Bangladesh s urban sector through one urban development project, five water supply projects, and its continuing dialogue on key urban development issues. Involvement in the MSP would offer the Bank the opportunity to lead and shape the urban development agenda, particularly on policy reforms, and use its leverage to help the GOB prepare and implement institutional and financial reforms likely to have maximum impact. Lastly, the World Bank s participation in the project would afford the Bank the opportunity to apply its broad experience in the urban sector to help the GOB and donors coordinate appropriate responses to the urban challenges in Bangladesh. 1

16 1.2 Original Project Development Objectives (PDO) and Key Indicators The original PDO was to improve environmental and infrastructure service delivery in urban areas. Specifically, the project would: (a) strengthen the institutional capacity of selected municipal corporations and secondary towns to plan, finance, implement, and operate urban infrastructure services in an efficient and sustainable manner, (b) improve resource mobilization and allocation, and fiscal discipline through the creation of an improved financing mechanism for urban infrastructure investment; and (c) support the GOB and municipalities to reduce urban poverty and improve environmental conditions of urban communities through the financing of critical urban infrastructure and services. The original indicators that would be used to measure progress in meeting these outcomes included: (a) Number of municipalities able to plan, prioritize, and implement service improvements by the end of the project (Phase 1:16; Phase 2:40); (b) Number of municipalities that completed management reform (Phase 1: 16; Phase 2: 40); (c) Demand driven and cost recovery measures introduced for revenue generating sub-projects; (d) Municipal Development Fund (MDF) created and operational for on-lending to municipalities; (e) Municipal Performance Review Board established and operational by the end of Phase 1; (f) Physical investments targeting poverty and environmental improvements implemented through community participation. 1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and reasons/justification The project was restructured three times to respond to two major floods in 2004 and 2007, and to scale up the demand-driven MDF operations. In 2005, US$11 million was added to the project, together with relocation of US$15 million from the BMDF component to the Flood Damage Rehabilitation (FDR) component, in response to a major flood in September After another severe flood in 2007, the Project was allocated an additional credit of SDR15.8 million (US$24.5 million) as part of the Bank s Post Flood Recovery Assistance Program. In 2010, an Additional Financing of US$42 million was approved to continue and scale up the project s successful program of infrastructure and capacity building support. Thus, overall, the project received reallocations and additional funding three times for a total of US$77.5 million. The PDO was not revised. The indicators were revised to reflect the additional financing. The revised indicators are: (a) Municipalities (183) able to plan, prioritize, and implement service improvements by end of project. (b) Management reform in municipalities completed in 183 municipalities. (c) Introduce demand driven and cost recovery measures; the target increased to 168 municipalities. (d) Streamline BMDF operations and strengthen coordination with LGED and other relevant agencies. This indicator was introduced under the AF of 2010 to replace the one requiring MDF operational for on-lending to municipalities and Municipal Performance Review 2

17 Board established and operational because these latter two targets had been achieved during the original investment. (e) Add 150 more works packages targeting poverty and environmental improvements through community participation funded by BMDF. This indicator was introduced in the AF or At that time, 454 works packages had been completed with BMDF funding; the new target became 595 works packages. 1.4 Main Beneficiaries As described in the PAD, the main direct beneficiaries of the project would be: (a) the residents of participating municipalities who would receive improved infrastructure services; and (b) staff at both national and local levels, who would benefit from capacity building. The PAD also notes that long-term project sustainability through community participation in the operation and maintenance (O&M) of urban infrastructure would be achieved through the adoption of the Participatory and Partnership Approach (PPA). This approach would encourage greater involvement of women in planning and managing activities that would directly contribute to improving their living conditions. The entire municipal population, including the poor and women, would benefit from the improved coverage of services as well as upgrades of the existing municipal infrastructure. The PAD also notes that any improvements in service coverage and quality would have a disproportionately positive impact on lower income groups because they were least likely to have these services at the time of project preparation. 1.5 Original Components (as approved) The original project had seven components divided into two phases. The first phase included civil works, equipment, and technical assistance (TA) to be implemented through the Local Government Engineering Department (LGED). Physical investments would be financed according to the traditional method of selecting investments for specific municipalities meeting IDA requirements. The second phase would support a MDF that would finance civil works, equipment, goods, and TA. First Phase Component 1 Civil Works (US$35.8 million). This would include the following: (a) Water Supply - rehabilitation of existing systems and equipment for O&M in 2 municipalities as well as urgent works (e.g., rehabilitation of hydrants, valve chambers, and overhead tanks). Khulna, which had the most severe water supply problems, would receive rehabilitation of 12 km of the distribution system (the largest amount). (b) Sanitation - construction of 47 public toilets (latrines and washing facilities for men and women) in 15 municipalities, and a pilot small-bore sewerage program in Khulna. Communities and/or the private sector would be involved in O&M of public toilets as well as the pilot sewerage in Khulna through the PPA. 3

18 (c) Roads and Drainage - upgrading and rehabilitation of existing road and drainage networks and systems. The road improvements would include renovation of deteriorated roads; conversion of earthen, gravel, or brick roads to bitumen roads; road widening; bridge renewal; and construction of footpaths and culverts. Drainage improvements would include drain reconstruction and conversion of earthen drains to brick-walled drains. This first phase would include about 220 km road improvements and about 37 km of drainage improvements. A PPA would be used in drain cleaning, and in carrying out a public awareness campaign about the need to keep drains clear from solid waste. (d) Bus and Truck Terminals- construction and rehabilitation of bus and truck terminals in all participating city corporations and municipalities. (e) Slum Improvement - pilots in Khulna and about five other municipalities. Physical investments would include improved water supply, on-site sanitation, footpaths, and street lighting. Slum communities would be organized with NGOs' assistance so they could identify their own needs and priority investments programs. Communities would be actively involved in planning, implementation, and O&M. (f) Solid Waste Management - equipment for primary collection. A PPA would be used in selecting sites for communal bins. Existing disposal sites would be improved in Khulna and Rajshahi from open to controlled dumping. Municipalities without formal disposal sites would receive technical assistance for identifying a suitable disposal site. (g) Markets - upgrading and/or rehabilitation of 16 existing municipal markets in the municipalities participating in this phase. (h) Land Acquisition to implement the bus/truck terminal and sanitation components. Component 2 Equipment (US$3.9 million). This component includes (a) solid waste equipment to improve primary collection, including waste transport vehicles (tipping trucks and trailers) in Khulnaand Rajshahi; and (b) motor vehicles and computers for personnel located in the field, and computer equipment and consumables for support personnel at each pourashava. Component 3 Technical Assistance (US$ 7.9 million). This would include: Institutional Development most of the TA would aim at (i) strengthening and institutionalizing the Pourashava Support Unit of LGED into a Municipal Support Unit (MSU) to support city corporations and pourashavas; and (ii) creating a municipality performance monitoring unit within the MSU to develop a municipality information data base and related applications systems. The MSU would consist of: (a) a Central Support Unit located at LGED; (b) a City Corporation Unit, located at the City Corporations; and (c) field advisors assigned to groups of 3 pourashavas. In addition, a central Monitoring Unit would be set up, and consultants would be recruited for the Central and City Corporation Support Units as well as for the Monitoring Unit to design and set up systems and procedures and train MSU personnel. 4

19 Municipal Data Base - TA would be provided to create and implement a municipal information data base and related applications systems. The project also would finance the development of the database/systems and related training and implementation. Community Development and Participation - TA would be provided for (i) hiring NGOs to develop a community participation program; (ii) conducting a workshop; and (iii) conducting a micro-credit study. The project also would finance consultants in community participation consultants to work with the MSU at various levels. Municipal Development Fund - TA for establishing the Municipal Development Fund (MDF) involving (i) preparation of the structure and incorporating the MDF as a legal entity; (ii) establishing the management structure of the MDF, including defining the initial organization structure, writing job descriptions, and assisting in recruiting suitable individuals to man key positions; and (iii) drafting policies and procedures both for operational areas and for financial management and accounting. Completion of all TA activities would be considered triggers for the implementation of Phase II. Studies Phase I studies included: (i) Environmental Management Action Plans in Khulna and Rajshahi for sanitation and solid waste management, and (ii) a hydrogeological investigation for Khulna. Project Implementation - TA for project management unit for design and construction supervision for two years initially, to be extended as needed during the second phase. Training - provided to MSU, LGED, and municipalities. Most training would be on-the-job in accounting, planning, and management. Project Staffing and Incremental O&M - additional staff for MSU and MDF as well as incremental O&M costs for project assets and MSU operating costs. Component 4 - Special Consideration (US$7.6 million). Also referred to as the Chittagong Hill Tracts, Component 4 would finance physical investments in three municipalities (Rangamati, Bandarban, and Khagrachari) which had lagged behind other municipalities in service provision and urban development. Component 5 - Flood Damage Rehabilitation (US$16.2 million). This component would finance rehabilitation of municipalities affected by the 1998 floods. The rehabilitation work would be determined upon completion of a needs assessment. Second Phase Component 6 - Municipal Development Fund (US$78.0 million). A Municipal Development Fund (MDF) would be established at the beginning of Phase II to start operating at the beginning of the third year of project execution. The Fund would finance municipal subprojects consisting of civil works, equipment, goods, and technical assistance. It would be established as an 5

20 autonomous agency, with resources provided through a US$70 million line of credit from IDA and GOB contributions. Component 7 Technical Assistance (US$4.6 million). This includes (a) support to the MDF specialists in sub-project appraisal, including technical review of proposals for compliance with environmental, social, economic, and financial feasibility; (b) technical support to municipalities to help them prepare sub-project proposals and FOAPs to make them eligible for MDF financing; and (c) incremental O&M costs for the MDF and MSU during the first three years. 1.6 Revised Components The components were not revised. 1.7 Other Significant Changes Although the components did not change, there were changes in funding and the project schedule (see table below). As a result of severe flooding in 2004, and in view of LGED s demonstrated success in implementing the first phase of investment, US$15 million of the original credit was reallocated from the BMDF component, along with US$11 million from another project, to the Flood Damage Rehabilitation component to be used to restore critical communication and transportation networks in the affected municipalities. At that time, the original closing date of June 30, 2005 was extended to June 30, After another severe flood in 2007 and in recognition of the good implementation performance under the original project, an AF of SDR 15.8 million (US$25 million equivalent) was approved in 2008 to help rehabilitate damaged urban infrastructure as part of the Emergency 2007 Flood Restoration and Recovery Assistance Program. The funds were allocated to the MSP to be used to rehabilitate urban roads, bridges, culverts, and drainage channels in flood-affected municipalities. Also at that time, the credit closing date was extended from June 30, 2008 to June 30, 2011 because activities were to be scaled up and targets enhanced. In 2010, there was another AF of SDR 27.8 million (US$42 million equivalent) to scale up BMDF-financed improvements in urban infrastructure as well as to continue the municipal financial and management capacity building under LGED. This new credit extended financing for urban infrastructure improvements to an additional 170 towns and extended the municipal capacity strengthening program to about 142 out of the 315 urban ULBs in the country. The AF also tightened fiduciary controls and supported the development of a program of improvement in urban infrastructure and institutional development over the medium term that would become the basis of projects to be funded by the Bank or other agencies. In addition, the BMDF would provide follow-up financing to 16 municipalities that made particularly good use of the first financing and could carry out further investments, and MSU would continue its trouble shooting for the 133 municipalities that had received support for capacity building. The AF also resulted in another extension of the closing date to June 30,

21 Component Appraisal Estimate Changes in World Bank Financing for MSP Reallocation of $15 m from BMDF to FR and US$11 m added from other project Additional Financing (US$25 m) for FR (Cr - 1) Additional Financing (US$42m) (Cr BD) Total ( ) Year Phase I- Physical Investments Phase II- MDF 70 (15 m of orig. credit reallocated to FDR) Chittagong Hills Tracts TA and Project Staffing Flood Damage Rehabilitation (US$15m +$11m ) (FDR) Incremental O&M Costs Total Note: The US$11million allocated to the MSP from another project does not appear in overall project financing in the World Bank project data sheets. The total reported by the Bank system is US$205.6 million. Also note that the overall total takes into account the reallocation of US$15 million from the Phase II-MDF in 2004 to the FDR component. 2. Key Factors Affecting Implementation and Outcomes 2.1 Project Preparation, Design and Quality at Entry QAG rating Highly Satisfactory QAG provided the highly satisfactory rating on QAE on the basis of the following main points. First, the team made a serious effort to analyze the difficult institutional issues and came up with the means for addressing them. QAG also noted that the project had benefited from an earlier decision to delay project preparation in order to undertake urban sector work that provided the core of the analysis and the proposed solutions as well as the time to build up support within the country. QAG further acknowledged the serious effort made by the team to incorporate social development issues in a sensitive, focused way that would help navigate the institutional and 7

22 bureaucratic difficulties, clear team commitment and support in LGED, and an understanding of the risks taken and the appropriateness of the measures contained in the project to address them. The ICR agrees with the points raised by QAG, but not the rating. The following are additional factors that would support a satisfactory rating. The design was appropriate to meet the project s objectives. The project s development objectives were clear and the components were well designed to address them. The project would address the (i) urgent need for basic urban services, particularly in small ULBs with lowincome areas, (ii) weak local government institutions through the provision of technical assistance to improve the institutional and financial capacity of participating municipalities; (iii) poor local resource mobilization and cost recovery through the establishment of a municipal development fund and capacity building; (iv) prior neglect of the O&M aspects of infrastructure by focusing on rehabilitation, and provision of technical assistance towards maintenance activities; and (v) need to improve sustainability of services through a participatory and partnership approach (PPA) in the planning, implementation, and O&M of these services. The design took into account the Bank's experience with earlier urban projects worldwide and in Bangladesh. The team responsible for project design was aware that many of the earlier multisectoral urban projects that focused on poverty alleviation through investments in basic infrastructure and housing included poorly integrated and ill-prepared components were too complex to be properly implemented. The design took into account the need to simplify the design, be realistic in determining small municipalities financial capacities, and emphasize strengthening of their financial and institutional frameworks to help ensure sustainability. Prior to the MSP, the Bank s involvement with the urban sector in Bangladesh included the Urban Development Project (approved in FY88), which focused on slum upgrading in Dhaka and drainage improvements in Dhaka and Chittagong, and five IDA-financed urban water supply projects. Although physical progress on the completed projects was satisfactory, the institutional and financial performance was not adequate and the projects confronted problems related to land acquisition, counterpart financing, and procurement. Based on the lessons from these earlier projects, the design emphasized the need for: (a) generating broad stakeholder commitment and interest; (b) establishing the willingness of the municipal authorities to borrow for the improvements before funding would be committed, and (c) directing attention to such issues as land acquisition, sub-project design, and procurement arrangements during project preparation. Based on the lessons from the completed projects, the design also responded to the need to: (a) achieve sustainable institutional and policy improvements by emphasizing underlying institutional problems rather than on achieving specific institutional and financial targets; and (b) establish a clear link between underlying problems, project objectives, and the project components. These issues were addressed in the project mainly through the demand-driven approach inherent in the BMDF. Because the introduction of the BMDF represented the first time that such a fund would be established in Bangladesh, an important lesson learned from experience in other countries was that the sustainability of such a funding mechanism would depend on the creditworthiness of its borrowers, and the need for a strong commercial orientation of the fund, which would operate without political interference. Taking into account the weak capacity of the ULBs in Bangladesh, 8

23 however, the design incorporated a realistic approach to assessing eligibility by requiring a participating ULB to prepare a Financial and Operational Action Plan (FOAP), which included an assessment of capacity and a plan for improving the ULB s financial standing so it could sustain an investment in urban infrastructure. The design also took into account the need to establish the BMDF as a commercially oriented, autonomous agency that would introduce transparency and equity into resource allocation for urban infrastructure nationwide. Project design took into account alternative approaches, the trade-offs between them, and the rationale for the final decisions. The three alternative approaches included: traditional urban lending versus the MDF approach, traditional grant financing versus loan grant financing mix, and single project versus phased approach. Unlike the traditional approach with pre-selected municipalities and components, introducing the MDF was considered optimal because the ULBs applied for demand driven financing (and differed from the supply driven approach) for providing long term and sustainable infrastructure financing and capacity building. The loangrant financing mix was considered preferable to traditional grant financing because it had the potential for leveraging funds for greater cost recovery. Project design benefitted from public participation and consideration of social issues. The project took into account the results of a social assessment, and the possibility of causing resentment on the part of the municipalities that are lagging in reforms to receive funding that had traditionally come from the central government. To mitigate this risk, the BMDF would be set up as an autonomous agency under the Ministry of Finance, with financing decisions made by a Steering Committee/Board of Directors from different spectra of society. The design also incorporated a PPA to help ensure ownership and the social sustainability of the project. The design could have been improved if it included funds for carrying out beneficiary assessments during project implementation to determine the extent to which the ultimate beneficiaries were satisfied with the project-related processes and improvements. Notwithstanding the above, the ICR team noted QAE issues that were not adequately addressed during the design of the investment. The main project outcome indicators were not clearly defined. Although the main PDO objectives were well articulated, there could have been clearer definitions of the PDO indicators such as municipality is able to plan, prioritize, and implement service improvements by end of project and management reform was completed. With regard to the outcome relating to support for reducing poverty and improving environmental conditions in urban communities through community participation, it would be difficult to establish targets for these in the PAD when a large part of the project s physical investments would be demand driven and determined only after the project was under implementation. The design underestimated the time needed to establish and operationalize the BMDF. Based on the original design, the BMDF was expected to be established as a legal entity with a clear ownership and management structure, registered with all concerned agencies, and ready to administer $78.0 million of project funds after two years of project implementation. The team greatly underestimated the amount of time it would take to obtain all the necessary approvals and financial flow arrangements for the MDF to be registered and operational. 9

24 The design could have included mechanisms to better coordinate local capacity building with BMDF investments throughout the entire project period. Better planned and programmed technical assistance could have been available throughout the project to help ensure that the ULBs that received funding would have the necessary capacity to adequately maintain them. 2.2 Implementation The MSP had a 12-year implementation period. The project became effective on October 25, 1999 and closed on June 30, 2012, seven years after the original closing date. The total project financing increased by $77.5 million during the 12-year period with three reallocations and additional funding. Several factors influenced project performance and justified the need for multiple project extensions. The three most important factors were: (a) the implementation competence of LGED and successful implementation of Phase I investments; (b) the delay in establishing and operationalizing the BMDF, and its subsequent success leading to an AF in 2010; and (c) massive floods in Bangladesh during the years 2000, 2004, and 2007 which led to additional allocations of funds in 2004 and 2008 in order to respond to the urgent need to repair damaged infrastructure. These and other factors are discussed below. Phase I Performance. Despite initial start up delays, the implementation of Phase 1 investments was carried out successfully. More than 95% of the original MSP components (LGED portion) were completed by June 30, 2005, the original closing date. Capacity building through the Municipal Support Unit (MSU) was set up within LGED and continued throughout the life of the project to build institutional and financial capacities in the ULBs, and to assist municipalities in meeting the eligibility criteria for project support. The good performance under Phase 1 reflected LGED s strong leadership which continued throughout project implementation. The strong performance under Phase 1 and the need to address urgent repairs caused by the floods of 2000, 2004, and 2007 also led to additional project funding, which greatly increased the number of activities to be led by LGED. Thus some of the original target dates could not be met. BMDF Delay and Subsequent Performance. Although the Borrower was fully supportive of the concept of BMDF during project preparation and appraisal, the Fund was not formally registered until 2002, and not fully operational until 2004, three years behind the original schedule. The main reasons for the delay related primarily to: (a) the fact that the government was in transition in 2001 when the BMDF was expected to become operational, and the transitional government put the decision to formally register the BMDF on hold until the new government took over; and (b) the severe floods of 2000, which diverted the attention of the project staff to finance urgent works to repair critical transportation and communications networks. Despite the start up delays and its difficulties in securing good quality technical staff and consistent leadership, the BMDF ultimately became an effective instrument for allocating funds to ULBs for critically needed infrastructure improvements. This assistance would not have been available to many ULBs, especially the small municipalities, if they continued to depend solely on the block grants administered from the national governments. As a result of BMDF s successful operation, in 2010, US$42 million was added to the project to help finance the scaling up of improvements in urban infrastructure as well as municipal 10

25 financial and management capacity. At that time, the project was performing well. There were significant benefits achieved in the participating municipalities as well as a strong demand for additional support. The AF would help to extend the financing of urban infrastructure improvements to some 170 towns, and extend the municipal capacity strengthening program to about 183 municipalities (out of 315 urban local bodies in Bangladesh). The AF of 2010 also would support development of the next generation of urban improvement programs and require tightening of fiduciary controls. By May 2010, practices adopted under the project for municipal institutional and infrastructure development represented significant improvements, including: (a) greater authority and responsibility of the municipalities in selecting and implementing the investments with matching operational and financial plans, (b) substantial self and loan financing requirements, (c) improved project evaluation and management, (d) improved municipal management and revenue systems, and (e) improved procurement practices. Demand for BMDF Financing. Throughout project implementation and after closing, there has been a continuous demand for BMDF support for infrastructure projects, and sense of ownership on the part of the participating ULBs and project communities. By the time of project closing, there was a backlog of over 200 project proposals seeking funding. Floods and Related Changes in Project Financing, Activities, and Schedule. Following the serious flood and heavy rainfall during the 2004 monsoon, a joint decision was made by the GOB and World Bank that urgent rehabilitation works in 67 flood-affected municipalities would be undertaken with IDA support through a credit reallocation of US$15 million from BMDF to LGED. The project also received a reallocation of US$11 million from the Private Sector Infrastructure Development Project (Cr. 2995). Accordingly, the DCA was amended and the credit closing date was extended to June 30, In response to another flood crisis in 2007, through the Emergency 2007 Flood Restoration and Recovery Assistance Program, the MSP received additional financing of US$25 million to support rehabilitation of urban roads, bridges, culverts, and drainage channels in municipalities damaged by the floods. This AF was allocated to MSP on the basis of LGED s strong performance under Phase I. Through this, LGED again demonstrated its effectiveness in expediting the urgent works needed to address critical flood damage in numerous municipalities. The change also meant an extension of the closing date to June 30, Finally, the AF of 2010 (US$42 million) was allocated to the MSP to allow the BMDF and LGED to further strengthen their investment and capacity building programs. The AF also supported the preparation of a follow up investment. Mid-Term Review. The MTR (2002) provided a comprehensive assessment of progress toward development objectives and implementation performance. While the review recognized that the overall implementation of the project s first phase was satisfactory, it raised serious concerns that the project encountered what was then a two year delay in establishing the BMDF. The Bank also noted in its review that it may have been overly optimistic given the country context, the weak institutional capacity of municipalities, and inherent governance problems to expect completion of all first phase investments, involving over 1,000 contracts within two years. Thus, the main recommendations of the MTR were to revise some of the project outcomes and target 11

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sustainable Development Unit South Asia Region Document of The World Bank FOR OFFICIAL

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35380 IDA-35381)

More information

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project f Validation Report Reference Number: PVR-370 Project Number: 29041 Loan Number: 1947 December 2014 Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project Independent Evaluation Department

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Water and Urban I1 Africa Region Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-92459) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$30.00 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-92459) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$30.00 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-42570 TF-92459)

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

US$M): Sector Board : Social Development Cofinancing (US$M (US$M US$M): US$M):

US$M): Sector Board : Social Development Cofinancing (US$M (US$M US$M): US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR14437 1. Project Data: Date Posted : 09/22/2014 Public Disclosure Authorized Public Disclosure Authorized Country:

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT),

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT), Public Disclosure Authorized Document of The World Bank Report No: ICR00003583 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) ON A GRANT IN

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002249 IMPLEMENTATION COMPLETION AND RESULTS

More information

The World Bank Kenya Infrastructure Finance/PPP project (P121019)

The World Bank Kenya Infrastructure Finance/PPP project (P121019) Public Disclosure Authorized AFRICA Kenya Financial Systems Practice Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 4 ARCHIVED on 22-Dec-2014 ISR17114 Implementing Agencies: Public Private

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-3967/ ARTF / ARTF ) IN THE AMOUNT OF SDR 17 MILLION US$25 MILLION EQUIVALENT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-3967/ ARTF / ARTF ) IN THE AMOUNT OF SDR 17 MILLION US$25 MILLION EQUIVALENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-3967/ ARTF

More information

Bangladesh: Chittagong Hill Tracts Rural Development Project

Bangladesh: Chittagong Hill Tracts Rural Development Project Validation Report Reference Number: PVR-222 Project Number: 32467 Loan Number: 1771(SF) December 2012 Bangladesh: Chittagong Hill Tracts Rural Development Project Independent Evaluation Department ABBREVIATIONS

More information

The World Bank LK GPOBA - Access to Sanitation Project (P111161)

The World Bank LK GPOBA - Access to Sanitation Project (P111161) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF LK GPOBA - ACCESS TO SANITATION PROJECT APPROVED ON JUNE 8, 2011 TO DEMOCRATIC

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Project Name Region Sector Project ID Borrower(s) Report No. PID5794 Lebanon-Municipal Infrastructure Project (@+) Middle East and North Africa Region Other Urban Development LBPE50544 Lebanese Republic

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON A CREDIT IN THE AMOUNT OF SDR 14.4 MILLION (US$23.7 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON A CREDIT IN THE AMOUNT OF SDR 14.4 MILLION (US$23.7 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON

More information

The World Bank CG Rep. Skills Development for Employability Project (P128628)

The World Bank CG Rep. Skills Development for Employability Project (P128628) Public Disclosure Authorized AFRICA Congo, Republic of Education Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 17-Jun-2017 ISR27973 Implementing Agencies: Ministry

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (DRAFT) (IDA-36810) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (DRAFT) (IDA-36810) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0000777 IMPLEMENTATION COMPLETION AND RESULTS

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Report No. PID6809 Project Pakistan-Punjab Municipal Development (+) Fund Project Region Sector Project ID Borrower Implementing Agencies South Asia Urban PKPE55293 Government of Pakistan (GOP) Date PID

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002035 IMPLEMENTATION COMPLETION AND RESULTS

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF URBAN III - PHASE II PROJECT GRANT IDA-H3300 APPROVED ON JULY 9, 2007

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF URBAN III - PHASE II PROJECT GRANT IDA-H3300 APPROVED ON JULY 9, 2007 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45590) ON A LOAN IN THE AMOUNT OF US$516.

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45590) ON A LOAN IN THE AMOUNT OF US$516. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR0000807 IMPLEMENTATION

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-37900) ON A CREDIT IN THE AMOUNT OF SDR 6.70 MILLION (US$ 9.12 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-37900) ON A CREDIT IN THE AMOUNT OF SDR 6.70 MILLION (US$ 9.12 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001435 IMPLEMENTATION COMPLETION AND RESULTS

More information

The World Bank Municipal Services Improvement (P096481)

The World Bank Municipal Services Improvement (P096481) Public Disclosure Authorized EUROPE AND CENTRAL ASIA Macedonia, former Yugoslav Republic of Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 15 ARCHIVED on 15-Jun-2015

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3524A IDA TF-26222) ON A CREDIT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3524A IDA TF-26222) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35240 IDA-3524A

More information

to ensure that the urban poor in participating Kelurahans benefit from improved socio -economic and local governance conditions.

to ensure that the urban poor in participating Kelurahans benefit from improved socio -economic and local governance conditions. Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number: ICRR14905 1. Project Data: Date Posted: 06/02/2016 Public Disclosure Authorized Public Disclosure Authorized Public

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0020321 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project ID P107840 Country Macedonia, former

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003680 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF-92396 TF-96083)

More information

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Responsible

More information

Project Name Philippines-Local Government Finance & Development Project (LOGOFIND)

Project Name Philippines-Local Government Finance & Development Project (LOGOFIND) Public Disclosure Authorized Report No. PID4841 Project Name Philippines-Local Government Finance (@+)... & Development Project (LOGOFIND) Region East Asia and Pacific Region Sector UY - Other Urban Development

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Unit Europe and Central Asia Region Document of The World Bank RESTRUCTURING

More information

Liberia Reconstruction Trust Fund Implementation Manual

Liberia Reconstruction Trust Fund Implementation Manual Liberia Reconstruction Trust Fund Implementation Manual Updated November 2009 2011-02-28 LRTF Implementation Manual 1 I. Background... 3 II. Coverage... 3 III. General Principles... 4 IV. Project Development

More information

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT Public Disclosure Authorized The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES24760 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785)

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Operation Name:

More information

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864)

The World Bank Kabul Urban Transport Efficiency Improvement Project (P131864) Public Disclosure Authorized SOUTH ASIA Afghanistan Transport & Digital Development Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 09-Feb-2018

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469)

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Operation Name: Second National

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650)

More information

Implementation Status & Results Report Niger Disaster Risk Management and Urban Development Project (P145268)

Implementation Status & Results Report Niger Disaster Risk Management and Urban Development Project (P145268) Public Disclosure Authorized AFRICA Niger Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 8 ARCHIVED on 04-Apr-2018 ISR30085 Implementing

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0680, CIDA-54421) ON A INTERNATIONAL DEVELOPMENT ASSOCIATION GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H0680, CIDA-54421) ON A INTERNATIONAL DEVELOPMENT ASSOCIATION GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0000656 IMPLEMENTATION COMPLETION AND RESULTS

More information

Actual Project Name : Mn - Sustainable Livelihoods Country: Mongolia US$M): Project Costs (US$M

Actual Project Name : Mn - Sustainable Livelihoods Country: Mongolia US$M): Project Costs (US$M IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 10/29/2008 Report Number : ICRR12989 PROJ ID : P067770 Appraisal Actual Project Name : Mn - Sustainable Project Costs (US$M US$M):

More information

The World Bank DTF: MA-Local Government Support Program (P144438)

The World Bank DTF: MA-Local Government Support Program (P144438) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Morocco Social, Urban, Rural and Resilience Global Practice Global Practice Recipient Executed Activities Investment Project Financing FY 2014

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON

More information

US$M): Sector Board : Public Sector (US$M US$M): Cofinancing (US$M. ICR Review

US$M): Sector Board : Public Sector (US$M US$M): Cofinancing (US$M. ICR Review Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR14400 1. Project Data: Date Posted : 07/24/2014 Public Disclosure Authorized Public Disclosure Authorized Public

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47980) ON A LOAN IN THE AMOUNT OF USD 300 MILLION THE REPUBLIC OF INDIA FOR THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47980) ON A LOAN IN THE AMOUNT OF USD 300 MILLION THE REPUBLIC OF INDIA FOR THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00003125 IMPLEMENTATION COMPLETION AND RESULTS

More information

Country Practice Area(Lead) Additional Financing Indonesia Water P161514

Country Practice Area(Lead) Additional Financing Indonesia Water P161514 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020651 Public Disclosure Authorized Public Disclosure Authorized Project ID P096532 Project Name ID:

More information

Actual Project Name : Social Insurance. US$9.7 US$9.4 Technical Assistance Project (SITAP) Country: Bosnia and US$M): Project Costs (US$M

Actual Project Name : Social Insurance. US$9.7 US$9.4 Technical Assistance Project (SITAP) Country: Bosnia and US$M): Project Costs (US$M IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 10/22/2008 Report Number : ICRR12969 PROJ ID : P071004 Appraisal Actual Project Name : Social Insurance Project Costs (US$M US$M):

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT. A CREDIT (IDA-46110) and A GRANT (IDA-H6940)

IMPLEMENTATION COMPLETION AND RESULTS REPORT. A CREDIT (IDA-46110) and A GRANT (IDA-H6940) Public Disclosure Authorized Document of The World Bank Report No: ICR00003458 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT ON A CREDIT (IDA-46110)

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 7 ARCHIVED on 28-Jun-2017 ISR27403 Implementing Agencies:

More information

The World Bank NP: Strengthening the Office of the Auditor General (P127040)

The World Bank NP: Strengthening the Office of the Auditor General (P127040) Public Disclosure Authorized SOUTH ASIA Nepal Financial Management Global Practice Recipient Executed Activities Specific Investment Loan FY 2012 Seq No: 3 ARCHIVED on 20-Feb-2015 ISR18017 Implementing

More information

RESTRUCTURING PAPER ON A

RESTRUCTURING PAPER ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A Report No: 63424-AR PROPOSED PROJECT

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021272 Public Disclosure Authorized Public Disclosure Authorized Operation ID P159774 Country Fiji Operation Name Fiji Post-Cyclone Winston

More information

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Department of Fisheries Ministry of Natural Resources Teone, Funafuti TUVALU Email: proptuv@gmail.com / proptuv@tuvalufisheries.tv

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON A CREDIT IN THE AMOUNT OF SDR16.4 MILLION (US$25 MILLION EQUIVALENT)

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON A CREDIT IN THE AMOUNT OF SDR16.4 MILLION (US$25 MILLION EQUIVALENT) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-43710) ON

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-39590) ON A CREDIT IN THE AMOUNT OF SDR15 MILLION (US$22 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-39590) ON A CREDIT IN THE AMOUNT OF SDR15 MILLION (US$22 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-39590) ON

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270) Public Disclosure Authorized SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR EUROPE AND CENTRAL ASIA Kazakhstan Transport & ICT Global Practice IBRD/IDA Specific Investment

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974) ON A LOAN IN THE AMOUNT OF USD 200.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974) ON A LOAN IN THE AMOUNT OF USD 200. Public Disclosure Authorized Document of The World Bank Report No: ICR00003656 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974)

More information

SERBIA AND MONTENEGRO-Montenegro Environmentally Sensitive Tourist Areas Project Region

SERBIA AND MONTENEGRO-Montenegro Environmentally Sensitive Tourist Areas Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Updated Project Information Document () Report No: AB131 Project Name SERBIA AND MONTENEGRO-Montenegro

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48040) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$57.4 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48040) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$57.4 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00003643 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48040) ON A CREDIT IN THE AMOUNT OF SDR 37.80

More information

STATUS OF PROJECTS IN EXECUTION FY09 SOPE

STATUS OF PROJECTS IN EXECUTION FY09 SOPE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY09 SOPE COUNTRY: RWANDA Operations Policy and Country

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011 Public Disclosure Authorized Document of The World Bank Report No: 65071-CM Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND

More information

Implementation Status & Results Sri Lanka Public Sector Capacity Building (P097329)

Implementation Status & Results Sri Lanka Public Sector Capacity Building (P097329) Public Disclosure Authorized Public Disclosure Authorized @ The World Bank Implementation Status & Results Sri Lanka Public Sector Capacity Building (P97329) Report No: ISR553 o o Operation Name: Public

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-73220) ON A LOAN IN THE AMOUNT OF US$50 MILLION TO THE REPUBLIC OF PERU FOR A

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-73220) ON A LOAN IN THE AMOUNT OF US$50 MILLION TO THE REPUBLIC OF PERU FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-73220)

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE Public Disclosure Authorized Document of The World Bank Public Disclosure Authorized RESTRUCTURING PAPER ON A Report No: RES19152 Public Disclosure Authorized Public Disclosure Authorized PROPOSED PROJECT

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001476 IMPLEMENTATION COMPLETION AND RESULTS

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-10288) ON A CREDIT IN THE AMOUNT OF SDR 96.4 MILLION (US$150 MILLION EQUIVALENT)

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-10288) ON A CREDIT IN THE AMOUNT OF SDR 96.4 MILLION (US$150 MILLION EQUIVALENT) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00003276 IMPLEMENTATION COMPLETION AND RESULTS

More information

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN Terms of Reference for Consultants 1. BACKGROUND INFORMATION Government of Vanuatu has requested TA support in the formulation and preparation of a national infrastructure

More information

Actual Project Name : Urban Infrastructure & Project Costs (US$M US$M): Sector Board : Water Cofinancing (US$M US$M): US$M):

Actual Project Name : Urban Infrastructure & Project Costs (US$M US$M): Sector Board : Water Cofinancing (US$M US$M): US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR13817 1. Project Data: Date Posted : 06/27/2013 Public Disclosure Authorized Public Disclosure Authorized Public

More information

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021115 Public Disclosure Authorized Public Disclosure Authorized Project ID P118737 Project Name ENERGY

More information

US$M): Sector Board : FPD Cofinancing (US$M US$M): (US$M US$M):

US$M): Sector Board : FPD Cofinancing (US$M US$M): (US$M US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR13644 1. Project Data: Date Posted : 07/14/2011 Public Disclosure Authorized Public Disclosure Authorized Public

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910)

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92489) ON A GRANT IN THE AMOUNT OF US$ 21.0 MILLION PEOPLE S REPUBLIC OF CHINA FOR A

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92489) ON A GRANT IN THE AMOUNT OF US$ 21.0 MILLION PEOPLE S REPUBLIC OF CHINA FOR A Public Disclosure Authorized Document of The World Bank Report No: ICR00002509 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92489) ON A GRANT IN THE AMOUNT OF US$ 21.0

More information

Implementation Status & Results India Assam State Roads Project (P096018)

Implementation Status & Results India Assam State Roads Project (P096018) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results India Assam State Roads Project (P096018) Operation Name: Assam State Roads Project (P096018) Project Stage: Implementation

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-36721) ON A CREDIT IN THE AMOUNT OF SDR 14.3 MILLION (US$ 18.0 MILLION EQUIVALENT) AND AN

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-36721) ON A CREDIT IN THE AMOUNT OF SDR 14.3 MILLION (US$ 18.0 MILLION EQUIVALENT) AND AN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001647 IMPLEMENTATION COMPLETION AND RESULTS

More information

Myanmar Southeast Asia Disaster Risk Management Project (P160931)

Myanmar Southeast Asia Disaster Risk Management Project (P160931) Public Disclosure Authorized EAST ASIA AND PACIFIC Myanmar Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 3 ARCHIVED on 26-Aug-2018

More information

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325) AFRICA Mozambique Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2007 Seq No: 22 APPROVED ISR29261 Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:23-May-2007

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT IN THE AMOUNT OF SDR 3.4 MILLION (US$5.0 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT IN THE AMOUNT OF SDR 3.4 MILLION (US$5.0 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00004097 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME) ON A LOAN IN THE AMOUNT OF US$108 MILLION TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME) ON A LOAN IN THE AMOUNT OF US$108 MILLION TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME)

More information

Implementation Status & Results Central African Republic Support to Vulnerable Groups Community Development Project (P111679)

Implementation Status & Results Central African Republic Support to Vulnerable Groups Community Development Project (P111679) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Central African Republic Support to Vulnerable Groups Community Development Project (P111679) Operation

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Madagascar Urban Development Global Practice IBRD/IDA Specific Investment Loan FY 2006 Seq No: 21 ARCHIVED on 30-Dec-2014 ISR17647 Implementing Agencies: Public Disclosure

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020665 Public Disclosure Authorized Public Disclosure Authorized Project ID P117440 Country El Salvador

More information

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Mozambique -Roads and Bridges Management and Maintenance Program - Phase II (P083325) AFRICA Mozambique Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2007 Seq No: 24 ARCHIVED on 29-Aug-2018 ISR33744 Implementing Agencies: ROAD FUND (Fundo de Estradas),

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-57202) ON A LOAN IN THE AMOUNT OF 20.0 MILLION US$ EQUIVALENT)

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-57202) ON A LOAN IN THE AMOUNT OF 20.0 MILLION US$ EQUIVALENT) Public Disclosure Authorized Document of The World Bank Report No: ICR00002536 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48200 TF-57202) ON A LOAN IN THE AMOUNT OF

More information

India: Karnataka Urban Development and Coastal Environmental Management Project

India: Karnataka Urban Development and Coastal Environmental Management Project Validation Report Reference Number: PVR-334 Project Number: 30303 Loan Number: 1704 November 2014 India: Karnataka Urban Development and Coastal Environmental Management Project Independent Evaluation

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3773A IDA-H0410) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3773A IDA-H0410) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR0000762 IMPLEMENTATION COMPLETION AND RESULTS

More information

The World Bank Third Secondary and Local Roads Project (P148048)

The World Bank Third Secondary and Local Roads Project (P148048) Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THIRD SECONDARY AND LOCAL ROADS PROJECT APPROVED ON JULY 3, 2014 TO GEORGIA REPORT NO.:

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 44212 June 2014 Proposed Loan and Administration of Loan and Grants People s Republic of Bangladesh: Coastal Towns Environmental

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001475 IMPLEMENTATION COMPLETION AND RESULTS

More information

Project Name. Region Sector

Project Name. Region Sector Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report

More information

Implementation Status & Results Haiti Strengthening the Management of Agriculture Public Services (GFRP) (P113623)

Implementation Status & Results Haiti Strengthening the Management of Agriculture Public Services (GFRP) (P113623) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Haiti Strengthening the Management of Agriculture Public Services (GFRP) (P113623) Operation Name:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Uzbekistan Water Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 12-Jan-2018 ISR30620 Implementing Agencies: Republic

More information