1 Memorandum State of New York March 27, 2018 Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr. Bleiwas, This represents the MTA s Fourth Quarter, 2017, report concerning the status of its gap closing initiatives as required by the NY State Comptroller s Regulation 4, Section (c). According to the Regulation, the MTA must report each quarter, until implemented or rescinded, the status of each gap-closing initiative with a projected value equal to or greater than $1 million in any given fiscal year, including milestones, impact on staffing, current implementation status, actual savings or revenues to date and projected annual savings or revenues in comparison to Budget and Plan projections. Attached is a summary of the results of the 4th Quarter PEG Monitoring Program for 2017, as well as copies of the PEG Monitoring Milestone Reports. The summary shows that the MTA will track gap closing initiatives with an annual value of $575.8 million. Actual 4th Quarter savings of $569.8 million represents 99.0% of the planned annual savings. If you have any questions, please do not hesitate to call. Sincerely, Douglas Johnson Director, Division of Management & Budget cc: J. Lhota N. Griffith F. Ferrer K. DeDonno L. Schwartz K. Leopold B. Foran L. Liberto (OSDC)

2 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date PEG/AABB/BRP Monitoring Summary (Combined ) ($ in millions) MTA Agencies Monitored * (Full Year) "Planned" Savings "Realized" Savings 4th Quarter Results (ytd) Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of Implemented at end of Quarter Pos ($) ($) ($) ($) ($) ($) New York City Transit (6.023) 98.9% 98.9% Long Island Rail Road % 100.0% Metro-North Railroad N/A N/A MTA Bridges & Tunnels % 100.0% MTA Headquarters % 100.0% Staten Island Rail N/A N/A MTA Bus Company % 100.0% MTA CONSOLIDATED (6.023) 99.0% 99.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

3 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date BRP Monitoring Summary (2017 BRPs) ($ in millions) MTA Agencies 2017 BRPs Monitored * (Full Year) "Planned" Savings "Realized" Savings 4th Quarter Results (ytd) Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of 2017 Monitored at end of Quarter Pos ($) ($) ($) ($) ($) ($) New York City Transit * (6.023) 91.4% 91.4% Long Island Rail Road % 100.0% Metro-North Railroad N/A N/A MTA Bridges & Tunnels % 100.0% MTA Headquarters % 100.0% Staten Island Rail N/A N/A MTA Bus Company % 100.0% MTA CONSOLIDATED (6.023) 94.4% 94.4% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

4 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date BRP Monitoring Summary (2016 BRPs) ($ in millions) MTA Agencies 2016 BRPs Monitored * (Full Year) "Planned" Savings "Realized" Savings 4th Quarter Results (ytd) Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of 2016 Monitored at end of Quarter Pos ($) ($) ($) ($) ($) ($) New York City Transit * % 100.0% Long Island Rail Road N/A N/A Metro-North Railroad N/A N/A MTA Bridges & Tunnels N/A N/A MTA Headquarters N/A N/A Staten Island Rail N/A N/A MTA Bus Company N/A N/A MTA CONSOLIDATED % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

5 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date BRP Monitoring Summary (2015 BRPs) ($ in millions) MTA Agencies 2015 BRPs Monitored * (Full Year) "Planned" Savings "Realized" Savings 4th Quarter Results (ytd) Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of 2015 Monitored at end of Quarter Pos ($) ($) ($) ($) ($) ($) New York City Transit * N/A N/A Long Island Rail Road % 100.0% Metro-North Railroad N/A N/A MTA Bridges & Tunnels N/A N/A MTA Headquarters N/A N/A Staten Island Rail N/A N/A MTA Bus Company N/A N/A MTA CONSOLIDATED % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

6 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date BRP Monitoring Summary (2012 BRPs) ($ in millions) MTA Agencies 2012 BRPs Monitored * (Full Year) "Planned" Savings "Realized" Savings 4th Quarter Results (ytd) Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of 2012 Monitored at end of Quarter Pos ($) ($) ($) ($) ($) ($) New York City Transit * (22) % 100.0% Long Island Rail Road N/A N/A Metro-North Railroad N/A N/A MTA Bridges & Tunnels N/A N/A MTA Headquarters N/A N/A Staten Island Rail N/A N/A MTA Bus Company N/A N/A MTA CONSOLIDATED (22) % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

7 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date (2017 BRPs) ($ in millions) 4th Quarter results (ytd) "Realized" Savings 2017 BRPs "Planned" "Realized" Variance % of 2017 Monitored at as % of "Planned" Monitored * Savings Savings Fav/(Unfav) end of Quarter Savings BRP Tracking # PEG Name Pos ($) ($) ($) ($) ($) ($) NYCT NYCT BRP Terminal Cleaning Savings % 100.0% NYCT BRP Destaff Auxiliary Full-Time Station Booths (2.165) 0.0% 0.0% NYCT BRP Zero Fare Revenue Increase (2.100) 0.0% 0.0% NYCT BRP Health & Welfare - Medical Rebid % 100.0% NYCT BRP Administrative & OTPS Savings (1.758) 100.0% 0.0% NYCT BRP EAM Adjusments % 100.0% NYCT BRP Health & Welfare - Medical Rebid % 100.0% NYCT BRP Health & Welfare - NYSHIP DEVA % 100.0% NYCT BRP Mandated Training % 100.0% NYCT BRP Power Maintainer Vacancies % 100.0% NYCT BRP Maintenance Material and Contract Savings % 100.0% NYCT BRP Eagle Team Deployment % 100.0% NYCT BRP Bus Operator Hours of Service/OT Adjustment % 100.0% NYCT BRP Paratransit Shift Trips to Voucher/Taxi/E-Hail Providers % 100.0% NYCT BRP Tower Operator Economy % 100.0% Total NYCT BRPs (6.023) 91.4% 91.4% LIRR LIRR BRP Freight Contract Renewal Revenue % 100.0% LIRR BRP Tighter Controls and Prioritization of Non-payroll Funds to Core Mission Initiativ % 100.0% Total LIRR BRPs % 100.0% B&T B&T BRP Lower negotiated E-Z Pass tag price % 100.0% B&T BRP Major Maintenance and Bridge Painting % 100.0% Total B&T BRPs % 100.0% MTA HQ MTA HQ BRP MTA PD/HQ/BSC % 100.0% MTA HQ BRP Reduced Maintenance Expenses % 100.0% MTA HQ BRP Elimination of EAM contingency funding at MTA HQ % 100.0% MTA HQ BRP Security - MTA PD % 100.0% Total MTA HQ BRPs % 100.0% MTA Bus MTA Bus BRP OTPS % 100.0% Total MTBUS BRPs % 100.0% MNR NONE Total MNR BRPs N/A N/A Total MTA BRPs (6.023) 94.4% 94.4% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

8 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date (2016 BRPs) ($ in millions) 4th Quarter results (ytd) "Realized" Savings 2016 BRPs "Planned" "Realized" Variance % of 2016 Monitored at as % of "Planned" Monitored * Savings Savings Fav/(Unfav) end of Quarter Savings BRP Tracking # PEG Name Pos ($) ($) ($) ($) ($) ($) NYCT NYCT BRP Subways Timekeeping Consolidation % 100.0% NYCT BRP Prescription Drug Re-Bid % 100.0% NYCT BRP Administrative and OTPS Savings % 100.0% NYCT BRP Non-Represented Employees General Wage Adjustment % 100.0% Total NYCT BRPs % 100.0% LIRR MNR B&T MTA Bus MTA HQ NONE NONE NONE NONE NONE Total LIRR BRPs N/A #DIV/0! Total MNR BRPs N/A #DIV/0! Total B&T BRPs N/A #DIV/0! Total MTBUS BRPs N/A #DIV/0! Total MTAHQ BRPs N/A #DIV/0! Total MTA BRPs % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

9 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date (2015 BRPs) ($ in millions) 4th Quarter results (ytd) BRP Tracking # NYCT PEG Name 2015 BRPs Monitored * "Planned" Savings "Realized" Savings Variance Fav/(Unfav) "Realized" Savings as % of "Planned" Savings % of 2015 Monitored at end of Quarter Pos ($) ($) ($) ($) ($) ($) NONE N/A #DIV/0! Total NYCT BRPs N/A #DIV/0! LIRR LIRR BRP Amtrak Reimbursement for Property Insurance % 100.0% Total LIRR BRPs % 100.0% MNR B&T MTA Bus MTA HQ NONE NONE NONE NONE Total MNR BRPs N/A #DIV/0! Total B&T BRPs N/A #DIV/0! Total MTBUS BRPs N/A #DIV/0! Total MTAHQ BRPs N/A #DIV/0! Total MTA BRPs % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

10 Metropolitan Transportation Authority 4th Quarter 2017 Year-To-Date (2012 BRPs) ($ in millions) 4th Quarter results (ytd) "Realized" Savings 2012 BRPs "Planned" "Realized" Variance % of 2012 Monitored at as % of "Planned" Monitored * Savings Savings Fav/(Unfav) end of Quarter Savings BRP Tracking # PEG Name Pos ($) ($) ($) ($) ($) ($) NYCT NYCT BRP Paratransit Additonal Savings (22) % 100.0% Total NYCT BRPs (22) % 100.0% LIRR MNR B&T MTA Bus MTA HQ NONE NONE NONE NONE NONE Total LIRR BRPs N/A #DIV/0! Total MNR BRPs N/A #DIV/0! Total B&T BRPs N/A #DIV/0! Total MTBUS BRPs N/A #DIV/0! Total MTAHQ BRPs N/A #DIV/0! Total MTA BRPs (22) % 100.0% * The value of the monitored PEGs/AABBs/BRPs reflects re-estimates captured through the July 2017 Financial Plan and only includes those PEGs/AABBs/BRPs with an annual value of $1 million or more.

11 Metropolitan Transportation Authority 2017 NYCT PEG/BRP Monitoring Program 4th Quarter 2017 results In 2017, 20 BRP/PEG s were monitored with a full-year savings of 206 positions and $536.8 million. Results through the end of-the-year show that $530.8 million, or 98.9% of the planned BRP/PEG reductions of $538.8 million were realized and 206 position were reduced. The following 17 BRP/PEG s have been fully implemented and will no longer be monitored: 12-01, 16-01, 16-02, 16-03, 16-06, 17-01, 17-04, 17-06, 17-07, 17-08, 17-09, 17-10, 17-11, 17-12, 17-13, and The following 2 BRP/PEG s did not meet the plan savings and will no longer be monitored due to changes and/or updates to the BRP/PEG: This savings initiative has been withdrawn at the request of the MTA The MTA has decided not to advance public hearings, without which these savings cannot be achieved. This BRP has been rescinded.

12 MTA New York City Transit 2012 Monitoring Milestone Report Tracking No. 4th Quarter 2017 (Actual Results through December) NYCT Description: Status: Paratransit Additional Savings Savings reflect the annualized impact of 2011 decreased trip activity, continued diversion of trips from higher cost 'Primary' providers to lower cost taxis and vouchers and revised projections of annual trip growth (11% rather than 15% growth). These factors have also favorably affected insurance and fuel costs as the NYCT dedicated fleet is smaller and a larger number of trips are now routed towards taxi/voucher service. Savings are partially offset by reduced fare revenue and the addition of LIB personnel who have been assigned to various Paratransit functions. In addition reduced trip levels have also favorably affected scheduling and eligibility certification costs. This also includes the Paratransit Fare Incentives that replaces expensive paratransit trips with free rides on buses and subways. Savings projections were updated to reflect a 1.5% increase in 2017 trips from the 2016 weather adjusted level of completed trips and a 5.6% reduction from the previous plan (2016 July Forecast) projection of trips. Annual trip growth in 2018 and beyond has been lowered to 4.5%. The combined impact of reduced trip levels and the continued diversion of trips to lower cost taxi/voucher service favorably affects costs for transportation and fuel. Insurance costs are also lower as NYCT's dedicated fleet is smaller and a significant number of trips are routed towards taxi/voucher services. VALUE ($ in millions): Original Plan: (29) (29) (22) (24) (24) July Plan 2014 added additional savings to be captured in the 3rd quarter /1/2014 Nov Plan 2014 added additional savings to be captured in the 4th quarter /1/2014 July Plan 2015 added additional savings to be captured in the 3rd quarter /1/2015 July Plan 2016 added additional savings to be captured in the 3rd quarter /1/2016 July Plan 2017 added additional savings to be captured in the 3rd quarter /1/2016 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Fully Implemented (/No): No

13 MTA New York City Transit 2016 Monitoring Milestone Report Tracking No. 4th Quarter 2017 (Actual Results through December) NYCT Description: Subways Timekeeping Consolidation To achieve efficiencies, Subways will initiate a phased-in centralization of some of it's timekeeping functions, through Full savings of 50 positions and $5.1M will be achieved annually beginning in Status: This PEG has been reevaluated and revised in the November 2016 Plan Update to reflect savings of ten positions as opposed to the original 50 position savings. This is a result of a more detailed evaluation of the timekeeping functions in MOW since this proposal was originally submitted. Planned savings has been achieved; 10 positions were removed from the budget. VALUE ($ in millions): November 2016 Plan Update /1/2015 added in the 2015 July Plan Jul-15 10/1/2016 Revised in the 2016 November Plan Update Jan-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Fully Implemented (/No):

14 MTA New York City Transit 2016 Monitoring Milestone Report Tracking No. 4th Quarter 2017 (Actual Results through December) NYCT Description: Status: Prescription Drug Re-Bid Active and retired employees of NYCT (and eligible dependents) receive prescription medication benefits as part of their H&W benefits package. The previous pharmacy benefits management (PBM) contract with Optum RX expired March 31st, Express Scripts (ESI) was selected with its Commercial and Employee Group Waiver Plan (EGWP) offerings, which took effect April Savings have been achieved through fourth quarter VALUE ($ in millions): Original Plan: /1/2016 Implement new contract with (ESI) Jul-16 Jul-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Fully Implemented (/No):

15 MTA New York City Transit 2016 Monitoring Milestone Report Tracking No. 4th Quarter 2017 (Actual Results through December) NYCT Description: Status: Administrative and OTPS Savings Administrative savings include eliminating six positions in the Department of Subways and five traffic checking position from Operations due to operational efficiencies. OTPS reductions include savings from migrating telephone line service from Verizon to Broadview, and reducing frequency of employee facility extermination services, external printing services, special ticket stock, uniforms and inspection and testing services. The initiative has met expectations due to higher than planned OTPS reductions which offset Operations Planning position reductions which have not occurred. VALUE ($ in millions): Original Plan: /1/2016 Reductions begin in July Jul-16 Jul-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Fully Implemented (/No):

16 MTA New York City Transit 2016 Monitoring Milestone Report Tracking No. 4th Quarter 2017 (Actual Results through December) NYCT Description: Non-Represented Employees General Wage Adjustment The implementation dates for the general wage increase for non-represented employees in 2016 and all outyears, has been delayed from January 1st to July 1st. Status: The GWI was delayed from January 1st until July 1st, resulting in reduced labor costs for the first half of the year. VALUE ($ in millions): Original Plan: /1/2016 Nov-16 Jan-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Fully Implemented (/No):

17 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Terminal Cleaning Savings This initiative reduces terminal car cleaning on the overnight tours of the A, D, and F lines, where terminal car cleaning occurs at both ends of the line. Savings have been achieved. Positions were removed from the budget and the pick. PEG VALUE ($ in millions): Original Plan: /1/2016 Jul-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

18 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT De-staff Auxiliary Full-Time Station Booths In 2010, most auxiliary station booths were closed, creating a standard of one full-time staffed booth per station or station complex. Auxiliary full-time booths were retained at 18 station complexes for a variety of reasons and since 2010 a number of new in-system transfers have opened with no changes to booth staffing at these stations after the transfers opened. A re-evaluation of station booth staffing in spring 2015 identified seven booths, including two at stations with new in-system transfers, that could be destaffed with minimal impact on our customers. This savings initiative has been withdrawn at the request of the MTA. PEG VALUE ($ in millions): Original Plan: /1/2016 May-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Month Var (0.271) (0.271) (0.271) (0.271) (0.271) (0.271) (0.271) (0.271) (2.165) YTD Var (0.271) (0.541) (0.812) (1.083) (1.353) (1.624) (1.894) (2.165) (2.165) No

19 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Zero Fare Revenue Increase Additional fare revenue would be realized from changing Paratransit's Zero Fare Program participants to the Reduced Fare Program. Under this change, all Paratransit registrants would be made eligible for the Reduced Fare Program, under which registrants would pay half fare for regular transit service, rather than riding for free with a Zero Fare Card. The MTA has decided not to advance public hearings, without which these savings cannot be achieved. This BRP has been rescinded. PEG VALUE ($ in millions): Original Plan: /1/2016 Jul-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Month Var (0.350) (0.350) (0.350) (0.350) (0.350) (0.350) (2.100) YTD Var (0.350) (0.700) (1.050) (1.400) (1.750) (2.100) (2.100) No

20 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Health & Welfare - Medical Rebid Medical Rebid for hourly employees effective January 1, The medical plan contract for the TWU, ATU 726 and ATU 1056 expires at the end of The new contract reflects a significant savings in claim costs as a result of efficiencies and lower negotiated rates. The first year savings are partially offset by the cost of transition from the current carriers to the new, as such, the savings in 2017 are less than in the out-years. Savings have been achieved through fourth quarter PEG VALUE ($ in millions): Original Plan: /1/2016 Jul-16 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

21 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Administrative & OTPS Savings This initiative reflects full and part time position reductions in the Human Resources, System Safety and Operations Planning divisions. In addition, the initiative also reflects price discounts gained from rapid invoice payments as well as reduced contractual costs through more effective management in the Materiel, Human Resources and Corporate Communications departments. Despite meeting planned labor reductions, year end operating results fell below planned savings goals primarily due to higher than planned refuse collection and uniform costs. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Month Var. (0.293) (0.293) (0.293) (0.293) (0.293) (0.293) (1.758) YTD Var. (0.293) (0.586) (0.879) (1.172) (1.465) (1.758) (1.758) No

22 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT EAM Adjustments EAM will maximize the safety, service life, and efficiency of each and every physical asset at NYCT. Investments were made in prior Financial Plan and were allocated to the Central Project Management Office (PMO), Department of Subways (DOS), and Department of Buses (DOB). The initiative is proceeding as planned. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

23 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Health & Welfare - Medical Rebid In 2017, Aetna replaced Empire Blue Cross Blue Shield and United Healthcare for the hourly and supervisory medical coverage. The Medical Rebid savings initiative was created to factor in cost reductions from changing vendors. Savings have been achieved through fourth quarter PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

24 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Health & Welfare - NYSHIP DEVA In 2016, NYSHIP conducted a Dependent Eligibility Audit (DEVA), which produces savings by reducing coverage costs as members update their plans from Family to individual. Savings have been achieved. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

25 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Mandated Training The New York State Mandated Training program began in The program was extensive including 399,615 individual course enrollments for NYCT and was budgeted on overtime for Supervisory and Hourly employees accordingly. Based on changes in course requirements and enrollment population, savings can be achieved. Actual course requirements have been revised in line with savings projections. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Month Var YTD Var

26 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Power Maintainer Vacancies Due to difficulty in hiring Power Maintainers, savings can be achieved. It is expected that hiring will be at budgeted headcount by the end of This initiative reduces headcount to reflect vacancies and increases overtime in order to accommodate maintenance requirements during the hiring period. Power maintainer hiring status is still in progress. PEG VALUE ($ in millions): Original Plan: /1/2017 Continue to hire Power Mainters up to budget and improve recruiting and hiring processes Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

27 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Maintenance Material and Contract Savings After review of historical actuals and projected OTPS needs, the Dept of Subways and Buses reduced their materials and R&M budgets. Reductions include bus depot materials, DOB's Veeder Root Contract, and material savings in DCE. The 2017 component of this savings initiative focuses on OTPS reductions within the Department of Buses (DoB). DoB has achieved its projected OTPS savings goal. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

28 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Eagle Team Deployment Savings is based on the reduction and redeployment of RBS Eagle Teams. These teams were originally created to limit fare evasion on regular bus service. This program has been revised in subsequent financial plans because it is difficult to determine the effectiveness of the RBS Eagle Teams on local bus fare evasion. Savings will be achieved through redeployment to SBS and attrition. Savings have been achieved. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

29 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Bus Operator Hours of Service/OT Adjustment The FTA tasked the Transit Advisory Committee for Safety (TRACS) with establishing a Fatigue Management Program for the Bus and Rail Transit Industry. Senior managers of various public transportation agencies, including NYCT, are members of the National Safety Panel which provides inputs and support TRACS's efforts. The 2015 Financial Plan included an Hours of Service (HOS) provision while efforts continued to determine the appropriate policy regarding maximum tour length, minimum rest between tours, maximum number of consecutive working days and maximum number of on-duty hours over the consecutive working days. Savings reflect the net impact of position reductions and the use of overtime. Department of Buses has achieved labor savings through September and is expected to meet its full-year savings by year end. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

30 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Paratransit Shift Trips to Voucher/Taxi/E-Hail Providers Continued shift of trips from higher cost Primary service providers to lower cost providers including brokered car service, taxis and E-Hail services. Trips provided by the lower cost providers (brokered car service, taxis and E-Hail) have met forecast projections. PEG VALUE ($ in millions): Original Plan: /1/2017 Jul-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj Month Var YTD Var

31 MTA New York City Transit 4th Quarter 2017 (Actual Results through December) NYCT Tower Operator Economy Using the work program effective 12/18/2016, an analysis was completed to calculate how many tower operators were needed to operate the towers. The FTE calculation was then compared to the tower operators in the 2017 adopted budget. The budget included 24 positions more than the calculated tower operators required per the work program. Five of these tower operators are needed until the Fan Plant SCADA cut over is completed in 2019: the initial savings is 19 tower operators, and in 2019 the savings will increase to 24 tower operators. After further evaluation, savings estimates have been revised to reflect a reduction of 11 tower operators in 2017 as opposed to the initial 19 positions reflected in the July Plan. PEG VALUE ($ in millions): Original Plan: Revised Plan: /1/2017 Jul-17 9/18/2017 Sep-17 MONTHLY CASH SAVINGS ($ in millions) Plan Actual/Proj

32 Metropolitan Transportation Authority 2017 LIRR PEG/BRP Monitoring Program 4th Quarter 2017 results In 2017, 3 BRP/PEG s are being monitored with a full-year savings of 0 positions and $8.9 million. Results through the end of-the-year show that $8.9 million, or 100.0% of the planned BRP/PEG reductions of $8.9 million were realized and 0 positions were reduced. The following 3 BRP/PEG s have been fully implemented and will no longer be monitored: 15-02, and

33 MTA Long Island Rail Road 4th Quarter 2017 (Actuals through December) LIRR BRP Amtrak Reimbursement for Property Insurance Amtrak reimbursement for a portion of the property insurance for Penn Station New York and PSCC under the Level A Lease amendment. Amtrak has reimbursed the LIRR for all outstanding payments due through The 2017 budgeted amount included all retroactive payments through 2015 and the 2017 annual payment. Payments received through June include all retroactive payments through year end The outstanding unpaid balance is now current with only the 2017 (approx. $0.150 million) portion not yet paid. PEG VALUE: ($ in millions) Original Plan: Revised Nov Jul 15 Identify Savings Jun-15 Invoice AMTRAK Oct-15 KEY INDICATORS: Revenue Plan Actual/Proj. Month Var. YTD Var. MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj Month Var (1.372) YTD Var

34 MTA Long Island Rail Road 4th Quarter 2017 (Actuals through December) LIRR Freight Contract Renewal Revenue Pending 10 Year extension of freight contract would result in higher revenue Contract renewed and 2017 payment received. PEG VALUE: ($ in millions) Original Plan: Jul Nov Identify Savings Jul-15 Jul-15 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

35 MTA Long Island Rail Road 4th Quarter 2017 (Actuals through December) LIRR Tighter Controls and Prioritization of Non-payroll Funds to Core Mission Initiatives Funding reduction for miscellaneous contract services as a result of historical spending trends and programmatic initiatives. Examples of some of these reductions include vegetation management, parking garage maintenance, advertising, travel, membership dues, office supplies, RIght of Way materials and various other maintenance and professional services contracts. Expenses have been reduced. PEG VALUE: ($ in millions) Original Plan: Jul Jul Jul-16 Identify Savings Jul-16 Jul-16 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

36 Metropolitan Transportation Authority 2017 MTA B&T PEG/BRP Monitoring Program 4th Quarter 2017 results In 2017, 2 BRP/PEG s were monitored with a full-year savings of 0 positions and $6.6 million. Results through the end of-the-year show that $6.6 million, or 100.0% of the planned BRP/PEG reductions of $6.6 million were realized and 0 positions were reduced. The following 2 BRP/PEG s have been fully implemented and will no longer be monitored: and

37 MTA BRIDGES & TUNNELS 4rt Quarter 2017 (Actuals through December) MTA B&T Lower negotiated E-Z Pass tag price The projection for E-ZPass tag needs in the February Financial Plan was based on a unit price of $8.90 for the most widely distributed tag. B&T Procurement was able to negotiate that price down to $7.40, which yields plan-to-plan savings of approximately $6.3 million in total over the July Financial Plan period. PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

38 MTA BRIDGES & TUNNELS 4rt Quarter 2017 (Actuals through December) MTA B&T Major Maintenance and Bridge Painting Approximately 25% of B&T's non-labor financial plan is dedicated to a Major Maintenance and Bridge Painting Program that supplements and supports the large construction projects carried out through the Capital Programs. A comprehensive evaluation of these supplemental needs over the November Financial Plan period has yielded $5.4 million in 2017 savings and $5.9 million each year thereafter. PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

39 Metropolitan Transportation Authority 2017 MTAHQ PEG/BRP Monitoring Program 4th Quarter 2017 results In 2017, 4 BRP/PEG s were monitored with a full-year savings of 1 position and $20.0 million. Results through the end of-the-year show that $20.0 million, or 100.0% of the planned BRP/PEG reductions of $20.0 million were realized and 1 position was reduced. The following 4 BRP/PEG s have been fully implemented and will no longer be monitored: 17-01, 17-02, and 17-04

40 MTA HEADQUARTERS 4th Quarter 2017 (Actuals through December) MTA HQ MTA PD/HQ/BSC Additional vacancy savings identified for MTA Police, Headquarters and the Business Service Center. PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings Jul-17 Jul-17 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

41 MTA HEADQUARTERS 4th Quarter 2017 (Actuals through December) MTA HQ Reduced Maintenance Expenses Lower expected maintenance expenses PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings Jul-17 Jul-17 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

42 MTA HEADQUARTERS 4th Quarter 2017 (Actuals through December) MTA HQ Reduce Contingency Elimination of EAM contingency funding at MTA HQ PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings Jul-17 Jul-17 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

43 MTA HEADQUARTERS 4th Quarter 2017 (Actuals through December) MTA HQ Security - MTA PD The department identified areas where reductions could be made without disrupting the ability to maintain operations. These reductions are taken from Maintenance and Other Operating Contracts, Professional Service Contracts and Other Business expenses. There is also an elimination of 1 analyst position. PEG VALUE: ($ in millions) Original Plan: Jul Identify Savings Jul-17 Jul-17 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

44 Metropolitan Transportation Authority 2017 MTA Bus PEG/BRP Monitoring Program 4th Quarter 2017 results In 2017, 1 BRP/PEG was monitored with a full-year savings of 0 positions and $3.5 million. Results through the end of-the-year show that $3.5 million, or 100.0% of the planned BRP/PEG reductions of $3.5 million was realized and 0 positions were reduced. The following 1 BRP/PEG has been fully implemented and will no longer be monitored:

45 MTA Bus Company 4th Quarter 2017 (Actuals through December) MTA Bus OTPS These savings are based on a review of controllable non-labor OTPS categories resulting in recurring savings from This PEG has been fully implemented. PEG VALUE: ($ in millions) Original Plan: Jul Reduce OTPS expenses Jul-17 Jul-17 MONTHLY CASH SAVINGS: ($ in millions) Plan Actual/Proj

Memorandum. November 16, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr.

Memorandum. November 16, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr. Memorandum State of New York vember 16, 2017 Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York 10038 Dear Mr. Bleiwas, This represents the MTA s Third Quarter,

More information

Memorandum. May 28, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr.

Memorandum. May 28, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr. Memorandum State of New York May 28, 2014 Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York 10038 Dear Mr. Bleiwas, This represents the MTA s First Quarter,

More information

Memorandum. May 29, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr.

Memorandum. May 29, Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York Dear Mr. Memorandum State of New York May 29, 2015 Mr. Ken Bleiwas Office of the State Comptroller 59 Maiden Lane, 29 th Floor New York, New York 10038 Dear Mr. Bleiwas, This represents the MTA s First Quarter,

More information

($ in millions) Mid-Year

($ in millions) Mid-Year Table 1 Actual Variance Percent Actual Variance Percent Actual Variance Percent Revenue Farebox Revenue $379.0 $381.0 $2.0 0.5 $0.0 $0.0 $0.0 - $379.0 $381.0 $2.0 0.5 Vehicle Toll Revenue 122.6 125.2 2.5

More information

IV. Major Assumptions Projections

IV. Major Assumptions Projections IV. Major Assumptions 2005-2008 Projections Debt Service Debt Service in the Financial Plan The following table reflects debt service projections for 2004 through 2008 associated with existing approved

More information

BUDGETWATCH October 2018 Flash Report

BUDGETWATCH October 2018 Flash Report October 2018 Flash Report Overall Latest Condition (reporting on operations through September and subsidies through October): Passenger Revenues were slightly below the Forecast in September, marginally

More information

BUDGETWATCH April 2019 Flash Report

BUDGETWATCH April 2019 Flash Report April 2019 Flash Report Overall Latest Condition (reporting on operations through March and subsidies through April): Due to the early scheduling of the Finance Committee meeting, first-close preliminary

More information

MTA 2018 Adopted Budget

MTA 2018 Adopted Budget BUD17013_Budget2018_Cover_Budget cover 1/16/18 10:00 AM Page 1 MTA 2018 Adopted Budget February Financial Plan 2018 2021 February 2018 TABLE OF CONTENTS I. Overview... I-1 II. MTA Consolidated Financial

More information

BUDGETWATCH March 2019 Flash Report

BUDGETWATCH March 2019 Flash Report March 2019 Flash Report Overall Latest Condition (reporting on operations through February and subsidies through March): Overall, YTD preliminary net results were favorable mainly reflecting lower operating

More information

BUDGETWATCH September 2018 Flash Report

BUDGETWATCH September 2018 Flash Report September 2018 Flash Report (Forecast figures in this report refer to the 2018 Forecast) Overall Latest Condition (reporting on operations through August and subsidies through September): For reporting

More information

New York City Transit

New York City Transit New York City Transit MTA New York City Transit 2008 Preliminary Budget July Financial Plan 2008 2011 MISSION STATEMENT The mission of MTA New York City Transit is to provide customers with safe, reliable

More information

MTA ANNUAL DISCLOSURE STATEMENT UPDATE (2018 First Quarterly Update) August 2, 2018

MTA ANNUAL DISCLOSURE STATEMENT UPDATE (2018 First Quarterly Update) August 2, 2018 MTA ANNUAL DISCLOSURE STATEMENT UPDATE (2018 First Quarterly Update) August 2, 2018 This Metropolitan Transportation Authority ( MTA ) Annual Disclosure Statement Update (including Attachment A hereto,

More information

MTA 2007 Final Proposed Budget

MTA 2007 Final Proposed Budget MTA 2007 Final Proposed Budget November Financial Plan 2007 2010 DJC November 2006 Metropolitan Transportation Authority TABLE OF CONTENTS l. Introduction (i) Letter from the Executive Director (iii) ll.

More information

MTA 2018 Final Proposed Budget November Financial Plan Volume 1 November 2017

MTA 2018 Final Proposed Budget November Financial Plan Volume 1 November 2017 BUD0000_Budget2018_Cover.qxp_MTA_Prelim_Budget2011_Cover 10/2/17 10:42 AM Page 1 MTA 2018 Final Proposed Budget November Financial Plan 2018 2021 Volume 1 November 2017 OVERVIEW MTA 2018 Final Proposed

More information

BUDGETWATCH September 2014 Flash Report

BUDGETWATCH September 2014 Flash Report BUDGETWATCH September 2014 Flash Report (Forecast figures in this report, except the Summary of June Budgetwatch, refer to the 2014 Forecast) Summary of June Budgetwatch (reporting on operations through

More information

OVERVIEW. MTA 2019 Preliminary Budget July Financial Plan Volume 1

OVERVIEW. MTA 2019 Preliminary Budget July Financial Plan Volume 1 OVERVIEW MTA 2019 Preliminary Budget July Financial Plan 2019-2022 Volume 1 The MTA s July Plan is divided into two volumes: Volume 1 consists of financial schedules supporting the complete MTA- Consolidated

More information

MTA 2016 Final Proposed Budget November Financial Plan Volume 1 November 2015

MTA 2016 Final Proposed Budget November Financial Plan Volume 1 November 2015 BUD14074_Budget2016_Cover_MTA_Prelim_Budget2011_Cover 10/1/15 3:38 PM Page 1 MTA 2016 Final Proposed Budget November Financial Plan 2016 2019 Volume 1 November 2015 OVERVIEW MTA 2016 FINAL PROPOSED BUDGET

More information

VIIl. Agency Financial Plans and 12-Month Allocations

VIIl. Agency Financial Plans and 12-Month Allocations VIIl. Agency Financial Plans and 12-Month Allocations New York City Transit MTA NEW YORK CITY TRANSIT FEBRUARY FINANCIAL PLAN FOR 2006-2009 2005 FINAL ESTIMATE AND ADOPTED BUDGET FOR 2006 In accordance

More information

MTA Bridges and Tunnels 2005 Final Proposed Budget November Financial Plan

MTA Bridges and Tunnels 2005 Final Proposed Budget November Financial Plan MTA B&T MTA Bridges and Tunnels 2005 Final Proposed Budget November Financial Plan 2005 2008 MISSION STATEMENT MTA Bridges and Tunnels (B&T) operates seven bridges and two tunnels that form essential links

More information

BUDGETWATCH May 2018 Flash Report

BUDGETWATCH May 2018 Flash Report May 2018 Flash Report Overall Latest Condition (reporting on operations through April and subsidies through May): Passenger revenues were $15.1 million unfavorable in April, increasing the unfavorable

More information

Financial Report - FY 2017 Year to Date May 31, 2017

Financial Report - FY 2017 Year to Date May 31, 2017 Financial Report - FY 2017 Year to Date July 19, 2017 1 Major Highlights Revenue Sales tax remittances received through YTD April 2017 are 4.2% higher than YTD April 2016 Plaza Saltillo lease income budgeted

More information

METRO. Fiscal Year 2014 Monthly Board Report. May 2014

METRO. Fiscal Year 2014 Monthly Board Report. May 2014 METRO Fiscal Year 2014 Monthly Board Report Revenue Expense Ridership Performance 7/11/2014 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I Section

More information

BUDGETWATCH March 2018 Flash Report

BUDGETWATCH March 2018 Flash Report March 2018 Flash Report Overall Latest Condition (reporting on operations through February and subsidies through March): Passenger revenues were $6 million unfavorable in February, increasing the unfavorable

More information

BUDGETWATCH April 2015 Flash Report

BUDGETWATCH April 2015 Flash Report BUDGETWATCH April 2015 Flash Report Summary of March Budgetwatch (reporting on operations through February and subsidies through March): Overall, results through March were favorable mainly as a result

More information

MTA 2012 Adopted Budget February Financial Plan

MTA 2012 Adopted Budget February Financial Plan MTA 2012 Adopted Budget February Financial Plan 2012 2015 DJC February 2012 Metropolitan Transportation Authority TABLE OF CONTENTS I. Overview... I-1 II. MTA Consolidated 2012-2015 Financial Plan 2012:

More information

BUDGETWATCH May 2017 Flash Report

BUDGETWATCH May 2017 Flash Report May 2017 Flash Report Summary of April Budgetwatch (reporting on operations through March and subsidies through April): Overall, results were favorable for the month, and remained favorable YTD. Passenger

More information

MTA 2017 Final Proposed Budget November Financial Plan Volume 1 November 2016

MTA 2017 Final Proposed Budget November Financial Plan Volume 1 November 2016 BUD16055_Budget2017_Cover_MTA_Prelim_Budget2011_Cover 9/14/16 10:14 AM Page 1 MTA 2017 Final Proposed Budget November Financial Plan 2017 2020 Volume 1 November 2016 OVERVIEW MTA 2017 Final Proposed Budget

More information

METRO. Fiscal Year 2017 Monthly Performance Report. Revenue Expense Ridership Performance. October 2016

METRO. Fiscal Year 2017 Monthly Performance Report. Revenue Expense Ridership Performance. October 2016 METRO Fiscal Year 2017 Monthly Performance Report Revenue Expense Ridership Performance 11/18/2016 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section

More information

MTA 2006 Preliminary Budget

MTA 2006 Preliminary Budget MTA 2006 Preliminary Budget July Financial Plan 2006 2009 DJC July 2005 Metropolitan Transportation Authority TABLE OF CONTENTS l. Introduction Letter from Executive Director... l-1 ll. MTA Consolidated

More information

III. Major Assumptions Projections

III. Major Assumptions Projections III. Major Assumptions 2004-2008 Projections Utilization (Revenue, Ridership, Vehicle Traffic) UTILIZATION Baseline Before Gap-Closing Actions 2004 Ridership and Revenue In 2004, ridership on the various

More information

METRO. Fiscal Year 2015 Monthly Board Report. February 2015

METRO. Fiscal Year 2015 Monthly Board Report. February 2015 METRO Fiscal Year 2015 Monthly Board Report Revenue Expense Ridership Performance 4/2/2015 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I Section

More information

METRO. Fiscal Year 2013 Monthly Board Report. January 2013

METRO. Fiscal Year 2013 Monthly Board Report. January 2013 METRO Fiscal Year 2013 Monthly Board Report Revenue Expense Ridership Performance 2/14/2013 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I Section

More information

BUDGETWATCH March 2016 Flash Report

BUDGETWATCH March 2016 Flash Report March 2016 Flash Report Summary of February Budgetwatch (reporting on operations through January and subsidies through February): Overall results through February were slightly favorable. Net operating

More information

MTA 2019 BUDGET AND FINANCIAL PLAN ADOPTION MATERIALS

MTA 2019 BUDGET AND FINANCIAL PLAN ADOPTION MATERIALS MTA 2019 BUDGET AND 2019-2022 FINANCIAL PLAN ADOPTION MATERIALS MTA Finance Committee December 10, 2018 MTA Board December 12, 2018 MTA 2019 Budget and 2019-2022 Financial Plan Adoption Materials Table

More information

August 31, 2016 Financial Report

August 31, 2016 Financial Report August 31, 2016 Financial Report Capital Metropolitan Transportation Authority 10/14/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

MTA 2012 BUDGET ADOPTION MATERIALS

MTA 2012 BUDGET ADOPTION MATERIALS MTA 2012 BUDGET ADOPTION MATERIALS MTA Finance Committee December 19, 2011 MTA Board December 21, 2011 NOTICE CONCERNING THIS WEB-POSTED COPY In order for this web posted copy of the 2012 Budget Board

More information

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. February 2018 (First Quarter Fiscal Year-to Date)

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. February 2018 (First Quarter Fiscal Year-to Date) METRO Fiscal Year 2018 Monthly Performance Report Revenue Expense Ridership Performance (First Quarter Fiscal Year-to Date) 3/12/2018 Table of Contents Section A Section B Section C Section D Section E

More information

MTA 2013 Adopted Budget. February Financial Plan

MTA 2013 Adopted Budget. February Financial Plan MTA 2013 Adopted Budget February Financial Plan 2013 2016 February 2013 NOTICE CONCERNING THIS WEB POSTED COPY The MTA 2013 Budget and 2013 2016 Financial Plan staff summary and the Certification of the

More information

Operating Budget Stability

Operating Budget Stability Operating Budget Stability March Financial Update Report to Agenda Executive Summary March Performance Against FY16 Budget March Performance Against Same Period Last Year Appendix Financial Detail: March

More information

May 31, 2016 Financial Report

May 31, 2016 Financial Report 2016 May 31, 2016 Financial Report Capital Metropolitan Transportation Authority 7/13/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

METRO. Fiscal Year 2012 Monthly Board Report. September 2012 (Fourth Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2012 Monthly Board Report. September 2012 (Fourth Quarter Fiscal Year-to-Date) METRO Fiscal Year 2012 Monthly Board Report Revenue Expense Ridership Performance (Fourth Quarter Fiscal Year-to-Date) This report is based on a preliminary closing of the year-end financials for FY2012

More information

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for August 2018 Date: October 10, 2018 I. Summary CTA s financial results are favorable to budget for

More information

New York City Transit Authority Consolidated Financial Statements Management s Discussion and Analysis December 31, 2004 and 2003

New York City Transit Authority Consolidated Financial Statements Management s Discussion and Analysis December 31, 2004 and 2003 New York City Transit Authority Consolidated Financial Statements Management s Discussion and Analysis Index Page(s) Independent Auditors Report... 1 Management s Discussion and Analysis... 2 12 Consolidated

More information

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date)

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date) METRO Fiscal Year 2019 Monthly Performance Report Revenue Expense Ridership Performance (Third Quarter Fiscal Year-to Date) 12/12/2018 Table of Contents Section A Section B Section C Section D Section

More information

METRO MONTHLY BOARD REPORT

METRO MONTHLY BOARD REPORT METRO Revenue Expenses Service Performance Fiscal Year FY2011 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Summary Sales Tax Revenue Fare Revenue Operating

More information

Financial Outlook for the Metropolitan Transportation Authority

Financial Outlook for the Metropolitan Transportation Authority Financial Outlook for the Metropolitan Transportation Authority Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 6-214 September 213 Highlights Fares and tolls

More information

lii. Updated Forecast and Gap Closing Program

lii. Updated Forecast and Gap Closing Program lii. Updated Forecast and Gap Closing Program III. Updated Forecast and Gap Closing Program UPDATED FORECAST Real Estate Transaction Taxes: Baseline Real Estate Transaction Tax projections in the November

More information

MTA Long Island Rail Road

MTA Long Island Rail Road MTA Long Island Rail Road Budget July Financial Plan -2008 MISSION STATEMENT The mission of the MTA Long Island Rail Road is to provide a safe, accessible, clean, cost-effective, customer-focused rail

More information

IV. Major Assumptions Projections

IV. Major Assumptions Projections IV. Major Assumptions 2004-2008 Projections This page has been intentionally left blank. Utilization (Revenue, Ridership, Vehicle Traffic) This page has been intentionally left blank. UTILIZATION Baseline

More information

METRO. Fiscal Year 2012 Monthly Board Report. December 2011 (First Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2012 Monthly Board Report. December 2011 (First Quarter Fiscal Year-to-Date) METRO Fiscal Year 2012 Monthly Board Report Revenue Expense Ridership Performance (First Quarter Fiscal Year-to-Date) 1/27/2012 Table of Contents Section A Section B Section C Section D Section E Section

More information

BUDGETWATCH February 2016 Flash Report

BUDGETWATCH February 2016 Flash Report February 2016 Flash Report Overall Latest Condition (reporting on operations for January and subsidies through February): Overall, preliminary results were on target for the month and slightly favorable

More information

Capital Metropolitan Transportation Authority Monthly Performance & Financial Report For Period Ending October 31, 2012 Soft Close

Capital Metropolitan Transportation Authority Monthly Performance & Financial Report For Period Ending October 31, 2012 Soft Close Capital Metropolitan Transportation Authority Monthly Performance & Financial Report For Period Ending October 31, 2012 Soft Close Table of Contents SUMMARY REPORT Financial Performance -Sales Tax 3 -Other

More information

MTA 2011 Preliminary Budget

MTA 2011 Preliminary Budget MTA 2011 Preliminary Budget July Financial Plan 2011 2014 DJC Volume 1 July 2010 Metropolitan Transportation Authority MTA 2011 PRELIMINARY BUDGET JULY FINANCIAL PLAN 2011-2014 VOLUME 1 The MTA s July

More information

Metropolitan Transportation Authority (A Component Unit of the State of New York)

Metropolitan Transportation Authority (A Component Unit of the State of New York) (A Component Unit of the State of New York) Independent Auditors Review Report as of and for the Six-Month Period Ended June 30, 2018 Table of Contents INDEPENDENT AUDITORS REVIEW REPORT 3 MANAGEMENT S

More information

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017.

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for June 2018 Date: August 15, 2018 I. Summary CTA s financial results are unfavorable to budget for

More information

MTA 2015 Preliminary Budget. July Financial Plan

MTA 2015 Preliminary Budget. July Financial Plan MTA 2015 Preliminary Budget July Financial Plan 2015-2018 Volume 1 July 2014 OVERVIEW MTA 2015 PRELIMINARY BUDGET JULY FINANCIAL PLAN 2015-2018 VOLUME 1 The MTA s July Plan is divided into two volumes:

More information

Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Review Report

Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Review Report (A Component Unit of the State of New York) Independent Auditors Review Report as of and for the Nine-Month Period Ended September 30, 2018 Table of Contents INDEPENDENT AUDITORS REVIEW REPORT 3 MANAGEMENT

More information

AR7001-Financials11 7/10/07 8:34 PM Page 9 Financial Section

AR7001-Financials11 7/10/07 8:34 PM Page 9 Financial Section Financial Section This page is intentionally left blank. Independent Auditors Report INDEPENDENT AUDITORS REPORT To the Members of the Board of Metropolitan Transportation Authority We have audited the

More information

February 2016 Financial Report

February 2016 Financial Report 2016 February 2016 Financial Report Capital Metropolitan Transportation Authority 4/13/2016 Table of Contents SUMMARY REPORT Budgetary Performance - Revenue 2 - Sales Tax Revenue 5 - Operating Expenses

More information

Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Review Report

Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Review Report Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Review Report Consolidated Interim Financial Statements as of and for the Three-Month Period Ended

More information

MTA 2016 BUDGET AND FINANCIAL PLAN ADOPTION MATERIALS

MTA 2016 BUDGET AND FINANCIAL PLAN ADOPTION MATERIALS MTA 2016 BUDGET AND 2016-2019 FINANCIAL PLAN ADOPTION MATERIALS MTA Finance Committee December 14, 2015 MTA Board December 16, 2015 MTA 2016 Budget and 2016-2019 Financial Plan Adoption Materials Table

More information

BUDGETWATCH January 2019 Flash Report Special 2018 Year-End Flash Report

BUDGETWATCH January 2019 Flash Report Special 2018 Year-End Flash Report January 2019 Flash Report Special 2018 Year-End Flash Report Overall The January Budgetwatch is a flash look, focusing on some very preliminary 2018 actual revenue results, along with debt service, compared

More information

Metropolitan Transportation Authority

Metropolitan Transportation Authority Metropolitan Transportation Authority (A Component Unit of the State of New York) Independent Auditors Report Consolidated Financial Statements Years Ended December 31, 2007 and 2006 METROPOLITAN TRANSPORTATION

More information

FY2011 Budget Forum. District of Columbia. October 19, 2009

FY2011 Budget Forum. District of Columbia. October 19, 2009 FY2011 Budget Forum District of Columbia October 19, 2009 0 Meeting agenda What is Metro and what is the value of Metro service? What are the Fiscal Year 2011 budget challenges? What are the potential

More information

April 30, 2016 Financial Report

April 30, 2016 Financial Report 2016 April 30, 2016 Financial Report Capital Metropolitan Transportation Authority 6/15/2016 Table of Contents SUMMARY REPORT Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

MTA Final Proposed Budget. November Financial Plan

MTA Final Proposed Budget. November Financial Plan MTA 2014 Final Proposed Budget November Financial Plan 2014 2017 Volume 1 November 2013 OVERVIEW MTA 2014 FINAL PROPOSED BUDGET NOVEMBER FINANCIAL PLAN 2014-2017 VOLUME 1 The MTA s November Plan is divided

More information

METRO. Fiscal Year 2013 Monthly Board Report. December 2012 (First Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2013 Monthly Board Report. December 2012 (First Quarter Fiscal Year-to-Date) METRO Fiscal Year 2013 Monthly Board Report Revenue Expense Ridership Performance (First Quarter Fiscal Year-to-Date) 1/14/2013 Table of Contents Section A Section B Section C Section D Section E Section

More information

BUDGETWATCH January 2018 Special 2017 Year-End Flash Report

BUDGETWATCH January 2018 Special 2017 Year-End Flash Report January 2018 Special 2017 Year-End Flash Report Overall The January Budgetwatch is a flash look focusing on some very preliminary 2017 actual revenue results, along with debt service, compared with the

More information

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. May 2018 (Second Quarter Fiscal Year-to Date)

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. May 2018 (Second Quarter Fiscal Year-to Date) METRO Fiscal Year 2018 Monthly Performance Report Revenue Expense Ridership Performance (Second Quarter Fiscal Year-to Date) 6/12/2018 Table of Contents Section A Section B Section C Section D Section

More information

Operating Budget. Third Quarter Financial Report (July 2005 March 2006)

Operating Budget. Third Quarter Financial Report (July 2005 March 2006) Third Quarter Financial Report (July 2005 March 2006) INDEX A. Executive Summary...page 2 B. Revenue and Expense Analysis...page 3 C. Budget Variance Reports...page 14 D. Ridership and Performance Measures...page

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017.

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2018 Date: May 9, 2018 I. Summary CTA s financial results are $0.9 million favorable to budget

More information

Metropolitan Transportation Authority MTA Headquarters Reconciliation of 2004 Preliminary Budget with Revised 2003 Budget ($ in thousands)

Metropolitan Transportation Authority MTA Headquarters Reconciliation of 2004 Preliminary Budget with Revised 2003 Budget ($ in thousands) MTA HEADQUARTERS Metropolitan Transportation Authority MTA Headquarters Reconciliation of with Revised 2003 Budget ($ in thousands) Variance: favorable / (unfavorable) Two-Year 2003 2004 Total Net Operating

More information

Metropolitan Transportation Authority Proposed Capital Program

Metropolitan Transportation Authority Proposed Capital Program Metropolitan Transportation Authority Proposed 2008-2013 Capital Program Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 11-2008 March 2008 The proposed capital

More information

Financial Management Report... 3

Financial Management Report... 3 November 13, 2013 Table of Contents Financial Management Report... 3 OPERATING FUNDS STATEMENT OF REVENUES & EXPENSES... 3 METROPOLITAN COUNCIL INVESTMENT PERFORMANCE SHORT-TERM PORTFOLIO... 4 METROPOLITAN

More information

Capital Metropolitan Transportation Authority Monthly Financial Report For Period Ending November 30, 2013

Capital Metropolitan Transportation Authority Monthly Financial Report For Period Ending November 30, 2013 Capital Metropolitan Transportation Authority Monthly Financial Report For Period Ending November 30, 2013 Table of Contents SUMMARY REPORT Financial Performance -Sales Tax Revenue 3 -Other Revenue 4 -Operating

More information

With an MTA Career. are great, To learn more and apply for MTA s Employment Opportunities, go to:

With an MTA Career. are great, To learn more and apply for MTA s Employment Opportunities, go to: With an MTA Career the Benefits are great, the Rewards are greater! To learn more and apply for MTA s Employment Opportunities, go to: http://web.mta.info/mta/employment/ MTA Benefits and Rewards For non-represented

More information

METRO. Fiscal Year 2013 Monthly Board Report. November 2012

METRO. Fiscal Year 2013 Monthly Board Report. November 2012 METRO Fiscal Year 2013 Monthly Board Report Revenue Expense Ridership Performance 12/13/2012 Table of Contents Section A Section B Section C Section D Section E Section F Section G Section H Section I

More information

BUDGETWATCH January 2015 Special 2014 Year-End Flash

BUDGETWATCH January 2015 Special 2014 Year-End Flash BUDGETWATCH January 2015 Special 2014 Year-End Flash Overall: January Budgetwatch is a flash look focusing on some very preliminary 2014 actual revenue results compared with the Final Estimate that was

More information

Proposed Capital Plan Amendment. July 2013 MTA Board Briefing

Proposed Capital Plan Amendment. July 2013 MTA Board Briefing Proposed 2010-2014 Capital Plan Amendment July 2013 MTA Board Briefing Briefing Agenda Purpose of 2010-2014 Capital Plan Amendment Amendment overview Amendment highlights Efficiency initiatives Mitigation

More information

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017.

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for January 2018 Date: March 14, 2018 I. Summary CTA s financial results are $1.7 million unfavorable

More information

JP Morgan Public Finance Transportation Utility Conference

JP Morgan Public Finance Transportation Utility Conference JP Morgan Public Finance Transportation Utility Conference April 18-19, 2018 Presented by: Brenden Morgan Sr. Manager of Debt & Investments Table of Contents I. Overview of the Region and RTD II. Updates

More information

Financial Report Fiscal Year 2018

Financial Report Fiscal Year 2018 Financial Report Fiscal Year 2018 Year to Date December 31, 2017 Presented on February 14, 2018 1 Major Highlights Revenue FY2018 sales tax revenue budgeted at 2.5% growth over FY2017 Sales tax remittances

More information

Operating Budget. Second Quarter Financial Report

Operating Budget. Second Quarter Financial Report Second Quarter Financial Report INDEX A. Executive Summary... A-1 B. Revenue and Expense Analysis... B-1 C. Budget Variance Reports... C-1 D. Ridership and Performance Measures... D-1 Board Budget Committee

More information

Cash & Liquidity The chart below highlights CTA s cash position at February 2017 compared to February 2016.

Cash & Liquidity The chart below highlights CTA s cash position at February 2017 compared to February 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for February 2017 Date: April 5, 2017 I. Summary CTA s financial results are $0.3 million favorable

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Operating Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation March 20, 2018 1 Revises Baselines: FY 2019-2020 ($

More information

Report of Independent Accountants

Report of Independent Accountants Report of Independent Accountants Report of Independent Accountants PricewaterhouseCoopers LLP 1301 Avenue of the Americas New York NY 10019-6013 Telephone (646) 471-4000 Facsimile (646) 394-1301 To Members

More information

Contracts Administration Management Action Plan Status June 20, 2013

Contracts Administration Management Action Plan Status June 20, 2013 Related to Agenda Item W1 Contracts Administration Management Action Plan Status June 20, 2013 Background In January 2012, the Board authorized an on-call management and consulting services contract with

More information

FY06 Operating Budget. FY2006 Proposed Operating Budget. Final Summary for Board Referral

FY06 Operating Budget. FY2006 Proposed Operating Budget. Final Summary for Board Referral FY2006 Proposed Operating Budget Final Summary for Board Referral 1 Operating Statements Subsidy nearly $10M lower than December proposal Dec Base Other Subtot Mar Prop$ Adj Adj Changes Prop$ Revenues

More information

Fare evasion at NYCT

Fare evasion at NYCT Fare evasion at NYCT Fare evasion is up significantly in 2018 Evasion rates Percent 8% 2 7% 5% 3% 1% 13 210K daily 109K daily Buses 1 10. Subway 14.8% 2.1% 348K daily 1. 12. 208K daily 18.9% 16.3% 3.8%

More information

Metropolitan Transportation Authority

Metropolitan Transportation Authority O f f i c e o f t h e N e w Y o r k S t a t e C o m p t r o l l e r Division of State Government Accountability Metropolitan Transportation Authority Minority and Women s Business Enterprise Reporting

More information

II. Major Assumptions Projections- Baseline

II. Major Assumptions Projections- Baseline II. Major Assumptions 2009-2012 Projections- Baseline Overview MTA Initiatives OVERVIEW MTA INITIATIVES The MTA and all of its agencies continually strive to improve the transit services we provide our

More information

Metropolitan Transportation Authority: East Side Access Cost Overruns

Metropolitan Transportation Authority: East Side Access Cost Overruns Metropolitan Transportation Authority: East Side Access Cost Overruns Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 12-2013 March 2013 Highlights East Side

More information

Metropolitan Transportation Authority (A Component Unit of the State of New York)

Metropolitan Transportation Authority (A Component Unit of the State of New York) Metropolitan Transportation Authority (A Component Unit of the State of New York) Consolidated Financial Statements as of and for the Years Ended December 31, 2016 and 2015 Required Supplementary Information,

More information

APPENDIX A THE RELATED ENTITIES

APPENDIX A THE RELATED ENTITIES APPENDIX A THE RELATED ENTITIES This Appendix is dated April 27, 2001 and contains information only through that date. The MTA intends to update and supplement specific information contained herein in

More information

TSCC Budget Review TriMet

TSCC Budget Review TriMet TSCC Budget Review 2017-18 TriMet 1. Introduction to the District: The Tri-County Metropolitan Transportation District (TriMet) boundary covers about 575 square miles of the urban portions of Multnomah,

More information

Financial Report Fiscal Year 2018

Financial Report Fiscal Year 2018 Financial Report Fiscal Year 2018 Year to Date September 30, 2018 1 Major Highlights Revenue Sales tax remittances received in FY2018 are 6.5% higher than FY2017 Additional $20 million in operating grants

More information

Metropolitan Transportation Authority (A Component Unit of the State of New York)

Metropolitan Transportation Authority (A Component Unit of the State of New York) Metropolitan Transportation Authority (A Component Unit of the State of New York) Consolidated Financial Statements as of and for the Years Ended December 31, 2014, and 2013 Required Supplementary Information,

More information

METRO. Fiscal Year 2015 Monthly Board Report. September 2015 (Fourth Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2015 Monthly Board Report. September 2015 (Fourth Quarter Fiscal Year-to-Date) METRO Fiscal Year 2015 Monthly Board Report Revenue Expense Ridership Performance (Fourth Quarter Fiscal Year-to-Date) This report is based on a preliminary closing of the year-end financials for FY2015

More information

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively.

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for September 2016 Date: November 16, 2016 I. Summary CTA s financial results are $0.3 million unfavorable