Evaluating Schedule Impacts. By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06

Size: px
Start display at page:

Download "Evaluating Schedule Impacts. By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06"

Transcription

1 Evaluating Schedule Impacts By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06

2 Overview Definitions Methods of Evaluating Delays Best Practices 2

3 Classification of Project Delays (Risk Point of View) Non-excusable Excusable Compensable Non-compensable 3

4 Non-excusable Delays Contractor problems result in schedule impacts Contractor not entitled to either time extension or compensation Examples: Late Submittals Late Material Delivery Insufficient Manpower.. 4

5 Excusable Non-compensable Delays Uncontrollable events such as weather, strikes, etc. sometimes referred to as Force Majeure Contractor is eligible for time extension Contractor not eligible for extended General Conditions costs Contractor has to meet burden of proof 5

6 Excusable Compensable Delays Owner or owner s agent problems result in schedule impacts Contractor eligible for time extension Contractor eligible for extended General Conditions cost Contractor has to meet burden of proof 6

7 Concurrent Delays Definition: Concurrent Delay is experienced on a construction project when two or more separate delay events occur during the same time period. Multiple causes to a critical path delay with both contract parties involved. In the absence of one party s cause, the other party s cause will govern. The schedule has more than one critical path with a separate delay affecting each at the same time (very rare) 7

8 Concurrent Delays Significance Determines compensability Apportionment: Where both parties contribute to the delay neither can recover damages unless there is clear evidence by which we can apportion the delay and the expense attributable to each party 8

9 Concurrent Delays Elements: Two or more delays occur during the same time period Both delays impact the critical path Delays may be caused by either or both parties, or unforeseen events In the absence of one delay event, the other delay event will govern. Governing Rules: The float belongs to the project Both parties have the right to use any additional float The Critical Path with respect to a specific milestone is the path with the least total float 9

10 Concurrent Delays: Concurrent delay by owner and contractor is excusable but not compensable Contractor Delay: 5 days lost in fabrication Delay events occur during the same time period They impacted the critical path Critical Path Activity Owner Delay: 5 days lost in reviewing the installation procedure Concurrent cause of Critical Path Delay of 5 Days In the absence of one delay event, the other delay event will govern. Result: 5 excusable (non-compensable) days to contractor 10

11 Concurrent Delays: Concurrent delay by contractor and an uncontrollable event is excusable but not compensable Contractor Delay: 5 days lost due to productivity issues Critical Path Activity 5 Days of CP Slippage Critical Path Activity 3 days of Rain Delay events occur during the same time period They impacted the critical path In the absence of one delay event, the other delay event will govern. Concurrent cause of Critical Path Delay of 3 Days Result: 3 excusable (non-compensable) days 2 non-excusable days 11

12 Concurrent Delays: Concurrent delay by owner and an uncontrollable event is excusable but not compensable Critical Path Activity Owner Delay: 15 days lost resolving a design issue 15 Days of CP Slippage 10 days of Rain Critical Path Activity Delay events occur during the same time period They impacted the critical path In the absence of one delay event, the other delay event will govern. Concurrent cause of Critical Path Delay of 10 Days Result: 10 excusable non-compensable days 5 excusable compensable days 12

13 Example: Delays Concurrent Owner Delay Impacting Framing Activity (12 days) 12 WF L1 WF L2 TF=5 days 5 Submittal/Fabrication L2 7 Contractor Delay Impacting Fabrication (7 days) Delay events occur during the same time period They impacted the critical path WF L1 5 7 WF L2 In the absence of one delay event, the other delay event will govern. Submittal/Fabrication L2 Result: 7 days of Concurrent Delay (Excusable, Non-compensable) WF L1 5 7 WF L2 7 CP Delay Non-critical Delay 5 7 Submittal/Fabrication L2 7 13

14 Example: Delays not Concurrent Owner Delay Impacting Foundation Activity 15 TF=5 Foundation Steel Erection Delay events occur during the same time period Steel Fabrication Delay not during same time frame: 10 7 Contractor Delay Impacting Steel Fabrication 5 Foundation Steel Erection 1 st CP Slippage 5 They impacted the critical path In the absence of one delay event, the other delay event will govern. Steel Fabrication 7 5 Added Float Contractor has the right to use the added float Delay during same time frame: 10 Steel Fabrication 5 7 Foundation 3 5 Steel Erection Added Float 2 nd CP Slippage 14 Result: Total Critical Path Slippage of 10 days is Compensable.

15 Delay Mitigation Contractor has an implied obligation to accelerate to mitigate delays, when possible. Further or additional acceleration might be possible, but might also have a price tag. The cost of further or additional mitigation needs to be evaluated against the cost of time extension. 15

16 Recovery Schedules & Proposals Requesting a Recovery Proposal to recover from an Owner-caused delay limits the Contractor s right to the added Float in non critical paths created by the owner-caused delay. Unrealistic Recovery Schedules can be used to hide Contractor delays and delay concurrency. 16

17 Methodology for Delay Quantification Total-Time Schedule Approach Adjusted As-Planned Schedule Approach Adjusted As-Built Schedule Approach Contemporaneous Time Frame Analysis 17

18 Total-Time Approach As-planned Duration Ownercaused Project Delay As-built Duration To use this approach, the Contractor needs to show: (1) As-planned schedule reasonable and constructible (2) It manned the job as planned and deployed the resources prudently (3) It did not cause any delays (4) There is no other reasonable way to quantify the delay 18

19 Adjusted As-Planned Approach As-planned Ownercaused Project Delay Adjusted As-planned Ownercaused Delay Ownercaused Delay As-planned duration and logic unchanged (Too hypothetical) Baseline Critical Path is the basis for the analysis Ignores Concurrency of delays 19

20 Collapsed As-Built But For Approach As-planned As-Built Owner Delay Contractor Delay Collapsed As-built Contractor Delay Owner-caused Project Delay As-Built schedule is used as the base for the analysis Ignores the timing of the delay (what was the critical path at the time of delay?) Does not evaluate concurrent delays 20

21 Contemporaneous Approach 2 Delays As-planned 1 st Delay Update Date Contractorcaused Delay Contractor-caused Project Delay 2 nd Delay Contractorcaused Delay Ownercaused Delay Owner-caused Project Delay Update Date 21

22 Contemporaneous Approach Same but Owner Delay Happened First As-planned 1 st Delay Update Date Ownercaused Delay Owner-caused Project Delay 2 nd Delay Ownercaused Delay No Project Delay Update Date Contractorcaused Delay 22

23 Contemporaneous Approach TIA Event Update Analysis Fragnet Analysis The importance of timing: When the delay-causing events occurred What was the Critical Path when the delay-causing events occurred Using current schedule updates as the basis for analysis Takes into account the dynamic nature of the schedule Concurrency and therefore compensability of delays can be evaluated. The most preferred method 23

24 LAUSD Scheduling Specification Calls for contemporaneous Fragnet approach Requests supporting elements: Baseline schedule, weekly and monthly schedule updates Baseline and monthly schedule submittals reviewed/accepted for quality 24

25 LAUSD Scheduling Specification; Steps Contractor recognizes an impact Contractor notifies District of actual or potential impact in a timely manner Pre-delay schedule prepared by Contractor Pre-delay schedule approved by District Delay Fragnet prepared by Contractor Delay Fragnet approved by District Net impact calculated/negotiated 25

26 Projected Delays Projected delays are delays or portions of a delay that extend into the future They are time estimates They affect the Critical Path LAUSD Specifications calls for the approval of projected delays (Fragnets) before they can be incorporated into the schedule 26

27 Projected Delays 27

28 Risk!!!! What if Contractor and District could not reach an agreement regarding the amount of time extension and/or the compensability of the delay? 28

29 Risk!!!! What if the District wrongfully rejects the Contractor s request for time extension and/or compensation? 29

30 Risk!!!! What if the Contractor does not provide the specified backup to support the time extension/compensation request? 30

31 Elements of Constructive Acceleration Based on the owner s unjustified refusal to grant a time extension or failure to act Requires that: A cause exists that would justify a time extension A proper request for a time extension Denial of that request Demand (express or implied) that performance be completed on time An actual acceleration 31

32 Best Practice Enforce the contract requirement for a good baseline schedule and schedule updates with a narrative for each as required Enforce the contract requirement for a formal notice announcing a potential delay Enforce the contract requirement for a Fragnet showing Critical Path impact Enforce the contract requirement for timely submittal of all the above 32

33 Best Practice Do not waive the contract requirements by your act or failure to act Do not give up on sending a letter requesting the schedule submittal Do not give up on sending a letter requesting a Fragnet as backup for a COP requesting time extension In your requests, always explain the reasons why you need the schedule or the Fragnet. 33

34 Best Practice Use the Notice of Event tool to establish a track record of communication on potential delays. This will reduce surprises at the end of the project District has contractual right to know so it can make decisions to mitigate and/or evaluate options Investigate the criticality of the issue and act on it Respond to the notice until closed 34

35 Best Practice When scope is added to the Critical Path, shift the risk to the contractor as soon as possible District has no control over the execution of the added scope and therefore should not be assuming the risk 35

36 Best Practice When scope is added to the Critical Path, shift the risk to the contractor as soon as possible Request the time estimate and schedule analysis Negotiate time Contractor has right to reasonable contingency, not sandbagging Consider recovery schedules, if applicable Make them commit 36

37 Best Practice Analyze and negotiate delays on a monthly basis. Calculate the net monthly Critical Path slippage, if any Request Fragnets, if not submitted yet Allocate/proportion delaying factors (owner, contractor, concurrent) Schedule a meeting to understand/negotiate Always take the initiative to document/issue the results of the meeting even if only partial or no agreement is reached 37

38 Best Practice Analyze and negotiate delays on a monthly basis. Negotiation meetings must address all claimed delays that affected the project within a specific time frame The objective is to resolve delays up to the end point of the time frame Assumptions on projected portions of a delay must be documented as part of the agreement 38

39 Best Practice Demonstrate good faith even if the Contractor is not cooperating In case the Contractor does not provide the appropriate backup/analysis for a delay that you recognize, run your own analysis, put it on the table for discussion and present the Contractor with an offer for resolution. Issue a letter documenting your effort 39

40 Best Practice Demonstrate good faith even if the Contractor is not cooperating If you re able to reach only partial resolution with the Contractor, isolate the disputed portion and issue a separate unilateral CO for this portion If you re unable to reach any resolution with the Contractor, issue a unilateral CO for time extension Avoid constructive acceleration by discussing recovery options 40

41 Key Points to Remember Communicate Document Enforce the requirements of your contract Do not waive the requirements by your act or lack of action Shift the risk to the Contractor, for work that you have no control over, as soon as possible 41

42 Key Points to Remember Negotiate time impacts on a monthly basis Demonstrate good faith even if the Contractor is not cooperating 42

43 QUESTIONS? 43

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

by Robert B. McCullough, PE, CCE, CFCC, CDT McCullough & Associates

by Robert B. McCullough, PE, CCE, CFCC, CDT McCullough & Associates by Robert B. McCullough, PE, CCE, CFCC, CDT McCullough & Associates www.mccullough-group.com Complete Project on time On budget With specified quality Avoid Claims Document your work Schedule Document

More information

Mitigating Delay Claims and Scheduling Best Practices

Mitigating Delay Claims and Scheduling Best Practices Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las

More information

Claim Avoidance on Highway Projects

Claim Avoidance on Highway Projects Claim Avoidance on Highway Projects Joseph R. Hellenbrand, P. E., PSP Capital Project Management, Inc. ASHE National Conference Bismarck, North Dakota June 13, 014 1 Joe Hellenbrand P.E.; PSP 0 years of

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Richard J. Long, P.E. and Rod C. Carter, CCP, PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim. Michael E. Stone

How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim. Michael E. Stone How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim Michael E. Stone Construction Delays & CPM Schedules Recognize different types of delays Understand how to use P3 to measure

More information

Simply put, when a contractor-caused delay

Simply put, when a contractor-caused delay CDR.07 Concurrent Delays What Are They and How to Deal With Them? George E. Baram, PE CCE Simply put, when a contractor-caused delay occurred at the same time as an owner-caused delay, we have a concurrent

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS. MASIN PROJECTS PRIVATE LIMITED (

PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS. MASIN PROJECTS PRIVATE LIMITED ( PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS BY:- ROHIT SINGHAL, SHISHIR KANT, ADARSH KUMAR MASIN PROJECTS PRIVATE LIMITED (www.masinproject.com) Page 1 of 10 ABSTRACT Infrastructure, construction and

More information

Reviewing Construction Claims INDOT Contracts

Reviewing Construction Claims INDOT Contracts Reviewing Construction Claims INDOT Contracts Why do we have claims? Changed Conditions Causes the work to substantially differ in kind or nature from the work as required in the original contract. (104.02)

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

Section 108. PROSECUTION AND PROGRESS

Section 108. PROSECUTION AND PROGRESS 108.01 Section 108. PROSECUTION AND PROGRESS 108.01. Subcontracting of Contract Work. No portion of the contract may be subcontracted, other than the providing of necessary materials, except as provided

More information

PACING DELAY. Project Controls Expo 18 th Nov Emirates Stadium, London. The Practical Effect on Construction Projects & Delay Claims

PACING DELAY. Project Controls Expo 18 th Nov Emirates Stadium, London. The Practical Effect on Construction Projects & Delay Claims Project Controls Expo 18 th Nov 2014 Emirates Stadium, London PACING DELAY The Practical Effect on Construction Projects & Delay Claims About the Speaker Philip M. Spinelli Director, Navigant Consulting,

More information

SHATTERING THE WINDOWS SCHEDULE ANALYSIS METHOD

SHATTERING THE WINDOWS SCHEDULE ANALYSIS METHOD SHATTERING THE S SCHEDULE ANALYSIS METHOD Daniel Quackenbush, PA Sean M. Dillon, Esq. Quackenbush & Associates, Inc. Moye, O Brien, Pickert, and Dillon, LLP There are nine principal, commonly utilized

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI E 54R07 SA M PL RECOVERYSCHEDULI NGASAPPLI EDI NENGI NEERI NG, PROCUREMENT,AND CONSTRUCTI ON AACE International Recommended Practice No. 54R-07 RECOVERY SCHEDULING AS APPLIED IN ENGINEERING, PROCUREMENT,

More information

Project Delays and Extensions of Time. Dr Tony Farrow

Project Delays and Extensions of Time. Dr Tony Farrow Project Delays and Extensions of Time Dr Tony Farrow Topics 1. Why Extensions of Time? 2. Methods of Analysis and examples 3. Schedule Float 4. Concurrent Delay 5. Exercise 6. Questions Construction Contracts

More information

SECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES

SECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

Final: Total 200 points (3-hour exam)

Final: Total 200 points (3-hour exam) Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment Acknowledgments: (June 23, 2009 Revision) Kenji P. Hoshino, PSP CFCC (Author)

More information

B. Progress Schedule

B. Progress Schedule 108.02.B. Progress Schedule Schedule Costs 2002 C&MS the cost of preparing and updating the schedule is incidental to all contract items. 2005 C&MS Unless otherwise included as a pay item in the Contract

More information

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows:

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1.1 The last sentence of 1804 is deleted and replaced with the following: If the Contractor

More information

MANAGEMENT OF VARIATIONS & CONSTRUCTION CLAIMS

MANAGEMENT OF VARIATIONS & CONSTRUCTION CLAIMS MANAGEMENT OF VARIATIONS & CONSTRUCTION CLAIMS PROJECT CONTROLS CONFERENCE SYDNEY, 2017 1 8/29/2017 MANAGEMENT OF VARIATIONS & CONSTRUCTION CLAIMS 1 / 2016 NAVIGANT CONSULTING, INC. ALL RIGHTS RESERVED

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE [---Section 01315A should be used for contracts for which a fully-developed computergenerated critical path method is appropriate for managing

More information

CDR.02. Staking Your Claim: Effective Claim Resolution

CDR.02. Staking Your Claim: Effective Claim Resolution CDR.02 Staking Your Claim: Effective Claim Resolution Mr. Philip D. Barnard, PE W ithout question, construction disputes consume precious time, money and resources for all parties involved. Regardless

More information

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT JESÚS DE LA GARZA 1 AND APIRATH PRATEAPUSANOND 2 1-2 Charles E. Via, Jr. Department of

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

Project Procedures. That Will Ensure Payment In Difficult Economic Times. By Neil Sinclair and Daniel Louw DMS International, Inc.

Project Procedures. That Will Ensure Payment In Difficult Economic Times. By Neil Sinclair and Daniel Louw DMS International, Inc. Project Procedures That Will Ensure Payment In Difficult Economic Times By Neil Sinclair and Daniel Louw DMS International, Inc. Introduction In today s market, subcontractors are pursuing work by cutting

More information

Job Acceleration: What Does It Really Cost You?

Job Acceleration: What Does It Really Cost You? Job Acceleration: What Does It Really Cost You? Suing for damages caused by acceleration is not as common as suing for damages caused by delays. But that tide is turning, and you need to know how to document

More information

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD http://pmsymposium.umd.edu 1 APPLICATIONS Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE 2018 Project Management Symposium Friday, May 11, 2018 9:45am

More information

Change Order Training. March 2, 2004

Change Order Training. March 2, 2004 Change Order Training March 2, 2004 Change Order The purpose of a Change Order is to communicate and record changes in the Contract Amount, Milestones and/or Contract Time. 45 days from Change Order Proposal

More information

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES March 1, 2007 SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES General This supplemental specification addresses the Critical Path Method (CPM) construction schedule requirements

More information

TIME IMPACT ANALYSIS IN ENGINEERING & CONTRACTING PROJECTS: AN INDUSTRIAL CASE ABSTRACT

TIME IMPACT ANALYSIS IN ENGINEERING & CONTRACTING PROJECTS: AN INDUSTRIAL CASE ABSTRACT TIME IMPACT ANALYSIS IN ENGINEERING & CONTRACTING PROJECTS: AN INDUSTRIAL CASE Paolo Sanvito (P) Franco Caron (1) Simone Valentini (2) PMP; IPMA B Certificate IPMA C Certificate Degree in Ing. Gest. Subcontract

More information

SECTION PROGRESS SCHEDULE

SECTION PROGRESS SCHEDULE NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01310. SECTION 01311 PART 1 GENERAL 1.1

More information

LONG INTERNATIONAL. James M. Bolin

LONG INTERNATIONAL. James M. Bolin James M. Bolin LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com James M. Bolin Table of

More information

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES PROLONGATION COST CLAIMS THE BASIC PRINCIPLES HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim Jeffrey E. Fuchs, PE, CPA 1 1. Compensability 2. Excusability of a Delay 3. How is Compensable Delay Priced? 4. Costs and Rates 5. What Should a Schedule Expert

More information

This paper proposes contractual language intended to

This paper proposes contractual language intended to CDR.14 Proposed Specification Language Regarding Pacing Mr. Kenji P. Hoshino PSP This paper proposes contractual language intended to specify and predetermine rules for applying the pacing concept to delays

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress

More information

Construction Project Management from the Owner s Perspective

Construction Project Management from the Owner s Perspective Construction Project Management from the Owner s Perspective Presented at: IMUA 2013 Annual Meeting May 21, 2013 Page 1 Agenda Introduction to Risk Management Risk through the Project Life Cycle Project

More information

Somewhere in Time - Securing and Protecting your Contractual Rights

Somewhere in Time - Securing and Protecting your Contractual Rights Howard KLEIN, United Kingdom Keywords: Ascertaining Delays, Delay Costs, Notice, Provisions, Extension of Time, Records, Construction Economics. SUMMARY Time is money and this is no less the case on construction

More information

Building Liability Procurement and Project Delays: Covering All the Bases

Building Liability Procurement and Project Delays: Covering All the Bases Building Liability Procurement and Project Delays: Covering All the Bases The Canadian Institute s 22 nd Annual Conference on Provincial/ Municipal Government Liability. January 28, 2016 Damon Stoddard,

More information

CPM MANAGEMENT ANALYSIS REPORT SOUTH STREET ELEMENTARY SCHOOL NEWARK, NJ

CPM MANAGEMENT ANALYSIS REPORT SOUTH STREET ELEMENTARY SCHOOL NEWARK, NJ 1300 ROUTE 73 SUITE 301 MOUNT LAUREL, NEW JERSEY 08054 TEL: (609) 261-0100 FAX: (609) 261-8584 email:whi-corp@whi-inc.com internet: www.whi-inc.com CPM MANAGEMENT ANALYSIS REPORT SOUTH STREET ELEMENTARY

More information

FLORA: New Forensic Schedule Analysis Technique

FLORA: New Forensic Schedule Analysis Technique FLORA: New Forensic Schedule Analysis Technique Long D. Nguyen, Ph.D. 1 and William Ibbs 2 Abstract: While various factors such as float ownership, logic change, and resource allocation FLORA affect results

More information

Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical?

Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical? Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical? Presented by Mark Nagata, PSP, Director/Shareholder, Trauner Consulting Services, Inc. 8/14/17 Meet Your Presenter, Mark Nagata,

More information

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY)

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) SECTION 01 32 16.16 NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) PART 1- GENERAL 1.1 DESCRIPTION: SPEC WRITER NOTES: 1. Coordinate this Design-Build Specification with FAR 52.232, VAAR 852.236 and Section

More information

Final Estimates Level 2

Final Estimates Level 2 Final Estimates Level 2 Module 9: Submittal of the Final Estimate & Offer of Final Payment 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 1 9-1 Module Content Final Estimates Package Final

More information

Risk Management for Tunnel Planning, Design and Construction

Risk Management for Tunnel Planning, Design and Construction ALDEA SERVICES Risk Management for Tunnel Planning, Design and Construction Robert J F Goodfellow, P.E. Senior Vice President August 14, 2017 UNIVERSAL LAWS OF TUNNELING Major Tunnel Project? DON T TAKE

More information

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder PART 3 Lump Sum Design-Build Agreement Between Department and Design-Builder This AGREEMENT is made as of the day of in the year of, by and between the following parties, for services in connection with

More information

APPENDIX VIII EXAMINATIONS OF EBT SERVICE ORGANIZATIONS

APPENDIX VIII EXAMINATIONS OF EBT SERVICE ORGANIZATIONS APPENDIX VIII EXAMINATIONS OF EBT SERVICE ORGANIZATIONS Background States must obtain an examination report by an independent auditor of the State electronic benefits transfer (EBT) service providers (service

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving

More information

Train Management Guidelines

Train Management Guidelines Train Management Guidelines Draft Document approval Author Name Position Title Signature Date Reviewers Approver Revision Register Version Date Position Title Amendment / Reason for revision Contents Introduction...3

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

EXECUTION VERSION JULY 31, 2012 COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF JULY 31, 2012 BY AND BETWEEN

EXECUTION VERSION JULY 31, 2012 COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF JULY 31, 2012 BY AND BETWEEN COMPREHENSIVE AGREEMENT RELATING TO THE I-95 HOV/HOT LANES PROJECT DATED AS OF BY AND BETWEEN VIRGINIA DEPARTMENT OF TRANSPORTATION, an Agency of the Commonwealth of Virginia AND 95 EXPRESS LANES LLC,

More information

Extension of Time (EOT) principles

Extension of Time (EOT) principles Anand ANTHONY 安杰褔 [M: 9693 0407] CHARTERED BUILDING ENGINEER (UK), Adjudicator (Malaysia), Mediator (UK) EXPERT in FORENSIC PLANNING (Delay/Disruption/Production/Acceleration)

More information

CONSTRUCTION SCHEDULE DELAYS

CONSTRUCTION SCHEDULE DELAYS Federal Publications - Construction Schedule Delays Washington, DC November, 2014 CONSTRUCTION SCHEDULE DELAYS Jessica Haire Fox Rothschild LLP Phone: 202-461-3109 E-mail: jhaire@foxrothschild.com What

More information

Tri-Cities Academic Building Washington State University Richland, WA Project Manual

Tri-Cities Academic Building Washington State University Richland, WA Project Manual Tri-Cities Academic Building Washington State University Richland, WA Project Manual Project No. 8589-2016 Issued 9/25/2018 Washington State University Facility Services, Capital Tri-Cities Academic Building

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Concurrent Delay The Owner s Newest Defense

Concurrent Delay The Owner s Newest Defense Concurrent Delay The Owner s Newest Defense Emily R. Federico Associate Director, Navigant Consulting, Inc. Fairfield, CT BS, Industrial Engineering Certified Planning & Scheduling Professional (PSP) Experienced

More information

POSTPONEMENT OF CONTRACT COMPLETION DATES AND WAIVER OF LIQUIDATED DAMAGES. The Construction and Material Specifications, Sections and 108.

POSTPONEMENT OF CONTRACT COMPLETION DATES AND WAIVER OF LIQUIDATED DAMAGES. The Construction and Material Specifications, Sections and 108. Effective: March 19, 1997 Responsible Office: Highway Management Policy Number: 512-001(P) Jerry Wray Director POSTPONEMENT OF CONTRACT COMPLETION DATES AND WAIVER OF LIQUIDATED DAMAGES PURPOSE: This policy

More information

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL 2nd edition February 2017 www.scl.org.uk Published by the Society of Construction Law (UK), 234 Ashby Road, Hinckley, Leicestershire, LE10 1SW.

More information

STAYING IN CONTROL OF DELAY CLAIMS WHILE MITIGATING DELAYS

STAYING IN CONTROL OF DELAY CLAIMS WHILE MITIGATING DELAYS GLOBAL CONSTRUCTION STAYING IN CONTROL OF DELAY CLAIMS WHILE MITIGATING DELAYS John Kimon Yiasemides, Associate Director, Navigant Construction contractors have the obligation under U.S. Common Law to

More information

These Special Conditions of the Contract for Construction amend and supplement the General Conditions for Construction Contracts Public Housing Programs (Form HUD-5370). The paragraph numbers and headings

More information

AGREEMENT FOR CONSTRUCTION MANAGER SERVICES between JEA and

AGREEMENT FOR CONSTRUCTION MANAGER SERVICES between JEA and AGREEMENT FOR CONSTRUCTION MANAGER SERVICES between JEA and This AGREEMENT is made as of the day of, (the Effective Date ), by and between the following parties, for services in connection with the Project

More information

Tip and Trick Bulletins 2/1/04

Tip and Trick Bulletins 2/1/04 IN THIS ISSUE Primavera Project Planner (P3) Version 3.1 Survival Guide for Using Constraints by Eric Chou, PE A constraint is a restriction imposed on the schedule to control the results (such as Start

More information

technical factsheet 134

technical factsheet 134 technical factsheet 134 Guidance on the application of UITF 40 Revenue recognition and service contracts BACKGROUND NOTE TO PUBLICATION OF THIS GUIDANCE NOTE On 10 March 2005, the Urgent Issues Task Force

More information

OECD Transfer Pricing Guidelines for Multinational Enterprises and Tax Administrations

OECD Transfer Pricing Guidelines for Multinational Enterprises and Tax Administrations OECD Transfer Pricing Guidelines for Multinational Enterprises and Tax Administrations 2009 Edition B 366258 TABLE OF CONTENTS - 5 Table of Contents Preface 11 Glossary 17 Chapter I The Arm's Length Principle

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising)

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Making and defending claims Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Public Works Contracts Dealing with Change Introduction Minimising Change Schedule

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

4. Outline of EIA for Development Assistance

4. Outline of EIA for Development Assistance 4. Outline of EIA for Development Assistance 4.1 EIA and Development EIA has an important role to play resolving these environmental problems through its ability to contribute to environmentally sound

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

10 Tips For Pursuing Claims After Construction Accidents

10 Tips For Pursuing Claims After Construction Accidents Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com 10 Tips For Pursuing Claims After Construction Accidents

More information

Steve Zickefoose, Manager Construction Claims Unit (CCU) LOS ANGELES UNIFIED SCHOOL DISTRICT Facilities Services Division CONSTRUCTION CLAIMS

Steve Zickefoose, Manager Construction Claims Unit (CCU) LOS ANGELES UNIFIED SCHOOL DISTRICT Facilities Services Division CONSTRUCTION CLAIMS Steve Zickefoose, Manager Construction Claims Unit (CCU) LOS ANGELES UNIFIED SCHOOL DISTRICT Facilities Services Division CONSTRUCTION CLAIMS COURSE GOALS Claim Process Avoid or Manage Claims Define Claims

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND THE CONSTRUCTION MANAGER Construction

More information

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.) Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

Webinar: Making the Right Choices in Government Contracting Part 3

Webinar: Making the Right Choices in Government Contracting Part 3 Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.

More information

SPECIFICATION NO.1197S Addendum No.5 Attachment B. New and Revised Specification Sections. Page 1 of 2 Specification No. 1197S Addendum No.

SPECIFICATION NO.1197S Addendum No.5 Attachment B. New and Revised Specification Sections. Page 1 of 2 Specification No. 1197S Addendum No. SPECIFICATION NO.1197S Addendum No.5 Attachment B New and Revised Specification Sections Page 1 of 2 Specification No. 1197S Addendum No. 5 ATTACHMENT B TABLE OF CONTENTS New Specification Sections or

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

ARTICLE 8: BASIC SERVICES

ARTICLE 8: BASIC SERVICES THE SCOPE OF SERVICES ADDED BY THIS AMENDMENT IS FOR A CM AT RISK PROJECT ONLY. THE SCOPE OF SERVICES SPECIFIED BELOW INCLUDES ARTICLES 8.1, 8.3, 8.4, 8.5, 8.6, 8.7 AND 8.8. THE SERVICES SPECIFIED IN ARTICLE

More information

OECD TRANSFER PRICING GUIDELINES FOR MULTINATIONAL ENTERPRISES AND TAX ADMINISTRATIONS

OECD TRANSFER PRICING GUIDELINES FOR MULTINATIONAL ENTERPRISES AND TAX ADMINISTRATIONS OECD TRANSFER PRICING GUIDELINES FOR MULTINATIONAL ENTERPRISES AND TAX ADMINISTRATIONS STEVEN A. MUSHER DEPUTY ASSOCIATE CHIEF COUNSEL (INTERNATIONAL-TECHNICAL) August 14, 2001 OECD WHERE TRANSFER PRICING

More information

By electronic delivery. September 17, 2004

By electronic delivery. September 17, 2004 1120 Connecticut Avenue, NW Washington, DC 20036 1-800-BANKERS www.aba.com World-Class Solutions, Leadership & Advocacy Since 1875 By electronic delivery September 17, 2004 Nessa Feddis Senior Federal

More information

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Project No. 9574-2018 Issued 7/19/2017 Washington State University Facility Services, Capital Terre View Research

More information

Construction & Time. Dr. Julian Critchlow

Construction & Time. Dr. Julian Critchlow 1 Construction & Time It has been said that the only major construction project to finish on time and to budget was a church where, presumably, divine intervention played a role Dr. Julian Critchlow 2

More information

TERMS AND CONDITIONS (FO ADVANTAGE CARD)

TERMS AND CONDITIONS (FO ADVANTAGE CARD) TERMS AND CONDITIONS (FO ADVANTAGE CARD) These terms and conditions apply to your FO Advantage Card. You must read them carefully. In these terms and conditions "you" means the named FO Advantage Cardholder

More information

Project Risk Management Remove, Mitigate, Manage

Project Risk Management Remove, Mitigate, Manage Project Risk Management Remove, Mitigate, Manage Jeri Krug Torsak Project Controls Manager Regional Transportation District Jeri.Torsak@rtd-Denver.com Overall Comments Hire the best and the brightest,

More information

A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL

A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL A paper given to a meeting of the Society of Construction Law in London on 8th May 2006 Richard H Lowe, Evans

More information

Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc.

Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc. Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc. August 10, 2015 Scott Lowe, P.E. Principal, Trauner Consulting Services 30 years experience Professional Engineer

More information

New disclosures for corporates Are you prepared to tell all?

New disclosures for corporates Are you prepared to tell all? New disclosures for corporates Are you prepared to tell all? 1 March 2018 Disclosure requirements more detailed than ever before Your first annual disclosures under the new standards may feel a long way

More information

FUTURE CONCRETE 2014 QATAR

FUTURE CONCRETE 2014 QATAR FUTURE CONCRETE 2014 QATAR Delay and Disruption in the Construction of Mega Projects Dr. Khaled Ahmed Al-Naas 2 nd December 2014 Background Generally projects face delay and disruption especially the mega/complex

More information

HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 4 TO THE REQUEST FOR PROPOSALS FOR THE

HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 4 TO THE REQUEST FOR PROPOSALS FOR THE HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 4 TO THE REQUEST FOR PROPOSALS FOR THE HONOLULU RAIL TRANSIT PROJECT CITY CENTER UTILITIES RELOCATION CONSTRUCTION CONTRACT

More information