B. Progress Schedule
|
|
- Elmer Page
- 5 years ago
- Views:
Transcription
1 B. Progress Schedule Schedule Costs 2002 C&MS the cost of preparing and updating the schedule is incidental to all contract items C&MS Unless otherwise included as a pay item in the Contract Documents, the cost of preparing and updating the schedule is incidental to all contract items.
2 B. Progress Schedule Early Completion Schedule 2002 C&MS Escrow Documents when accepted progress schedule shows an early completion of Work more than 10 Calendar Days before the Completion Date C&MS Added B.2. Early Completion Schedule An Early Completion Schedule is defined as a baseline schedule which anticipates completion of all work prior to the Completion Date established by the contract documents and the Contractor submits as an Early Completion Schedule.
3 B. Progress Schedule 2005 C&MS The Engineer will initiate a change order amending the Completion Date to the finish date shown on the accepted Early Completion Schedule. All contract provisions concerning the Completion Date such as incentives, disincentives, excusable delays, compensable delays, and liquidated damages will be measured against the amended Completion Date. In the event that the Contractor elects not to execute the change order amending the Completion Date; the Contractor waives its rights to delay damages in meeting the projected early Completion Date.
4 C. Escrow Documents 2002 C&MS Escrow Documents are required under the following circumstances: 1. early completion schedule shows completion of Work more than 10 Calendar Days before the Completion Date 2. when required by the Contract Documents 2005 C&MS No longer linked to Early Completion Schedules Eliminated Escrow Documents provision from C&MS New Escrow Bid Documents Proposal Note 110 Will only be considered for use on projects >$30 million or of a highly technical nature
5 Time Extension and Payment for Excusable Delays 2002 C&MS A. General 2 nd paragraph states that the Department will consider paying the Contractor for excusable, compensable delays from a projected finish date earlier than the Completion Date 2005 C&MS A. General Deleted 2 nd paragraph due to new Early Completion Schedule provision
6 Time Extension and Payment for Excusable Delays 2002 C&MS A. General No mention of shared duty to mitigate damages 2005 C&MS A. General Added explanation of Duty to Mitigate Mitigation of any delay, whether caused by the Department, Contractor, third party or an intervening event, is a shared contract and legal requirement. Mitigation efforts include, but are not limited to, re-sequencing work activities, acceleration, and continuation of work through an otherwise planned shutdown period. The Contractor and Engineer must explore and discuss potential mitigation efforts in a timely manner and must agree upon costs or cost sharing responsibilities prior to their implementation.
7 Extra and Force Account Work 2002 C&MS D.3.a. Field Overhead Distinguished as D.3 Additional Allowable Delay Costs Due to Engineer-Ordered Suspensions from D.2 Allowable Delay Costs C&MS D.2.e. Field Overhead Limits payment for field overhead to utility/railroad delays, engineer-ordered suspensions, and Department neglect.not delays due to revised work. Added to the list of delay costs set forth in D.2 Allowable Delay Costs.
8 Extra and Force Account Work 2002 C&MS D.3.a. Field Overhead The Department will pay the Contractor for field overhead costs during a delay period if the Contractor has incurred an excusable, compensable delay that delays the Work at least 10 calendar days beyond the original Completion Date; these days are cumulative throughout the project C&MS D.2.e. Field Overhead provided all of the following criteria are met: (1) The Contractor or subcontractor has incurred an excusable, compensable delay that delays the Work at least 10 Calendar Days beyond the original Completion Date. These days are cumulative throughout the project. (2) The delay for which payment of field overhead is sought is only due to delays defined in D.2, D.3, and D.5.
9 Extra and Force Account Work 2002 C&MS D.3.a. Field Overhead No reference to subcontractor entitlement C&MS D.2.e. Field Overhead The Department will pay any Contractor or subcontractor for field overhead costs
10 Extra and Force Account Work 2002 C&MS D.3.b. Home Office Overhead Limits payment for home office overhead to engineerordered suspensions.not delays due to utility/railroad delays, Department neglect, or revised work C&MS D.2.f. Home Office Overhead Sets forth same two criteria for payment as Field Office Overhead Added to the list of delay costs set forth in D.2 Allowable Delay Costs.
11 Extra and Force Account Work 2002 C&MS D.3.b. Home Office Overhead A significant subcontractor may submit a claim for reimbursement 2005 C&MS D.2.f. Home Office Overhead Clearly designates which subcontractors may submit a claim for home office overhead Any subcontractor that has approved C-92 s for subcontracted work totaling $4,000, or more is eligible for reimbursement provided
12 Extra and Force Account Work 2002 C&MS D.3.b. Home Office Overhead Addresses normal winter shutdown periods No provisions addressing UNANTICIPATED winter shutdown periods or construction periods HOOP = (exc./comp. delay x orig. contract $ x 5.5%) contract duration * Normal winter shutdown periods are subtracted out of duration terms
13 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Sets forth new calculation which clearly addresses UNANTICIPATED winter shutdown periods and construction periods
14 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Payment will be made for every eligible day beyond the original contract completion date at the Home Office Overhead Daily Rate. Step 1: Determine HOOH Daily Rate Daily HOOP = (orig. contract $ x.08) contract duration * Normal winter shutdown periods are NOT subtracted out of duration term
15 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Payment for unanticipated construction period is distinguished from payment for unanticipated winter period Unanticipated construction period refers to the period between May 1 and November 30 Unanticipated winter period refers to the period between December 1 and April 30
16 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Step 2: Determine HOOH Payment for Unanticipated Construction Period CP HOOP = Daily HOOP x D D = all excusable, compensable delays minus all delays due to D.1 revised work and D.4 government acts other than Department (Calendar Days)
17 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Step 3: Determine HOOH Payment for Unanticipated Winter Period WP HOOP = Daily HOOP x F x (D/E) D = all excusable, compensable delays minus all delays due to D.1 revised work and D.4 government acts other than Department (Calendar Days) E = all excusable, compensable delays plus all excusable, noncompensable delays (Calendar Days) F = 151
18 Extra and Force Account Work 2005 C&MS D.2.f. Home Office Overhead Step 4: Determine Total HOOH Payment Total HOOP = CP HOOP + WP HOOP
19 HOOP Hypo Facts: Execution of Contract: 6/13/04 Original Completion Date: 9/30/05 Original Contract Amount: $12,000,000
20 HOOP Hypo Delays to Critical Path (Calendar Days): Weather 50 (excusable, non-compensable) Utility 91 (excusable, compensable) * BUT, 16 of the weather days were concurrent with the utility delay. So, only 75 of the utility delay days are compensable Extra Work 39 days (excusable, compensable) Total Time Extensions: = 164 Cal. Days The delays extend the project over the winter, so Cal. Days (time ext.) (winter shutdown) = 315 Cal. Days 9/30/05 (Orig. Compl. Date) Cal. Days = 8/11/06 Revised Completion Date: 8/11/06
21 HOOP Hypo Delays to Critical Path (calendar days): Weather 50 (excusable, non-compensable) Utility 91 (excusable, compensable) * BUT, 16 of the weather days were concurrent with the utility delay. So, only 75 of the utility delay days are compensable Extra Work 39 days (excusable, compensable) Excusable, compensable = = 114 Cal. Days Excusable, non-compensable = 50 Cal. Days
22 HOOP Hypo Step 1: Determine HOOH Daily Rate Daily HOOP = (orig. contract $ x.08) contract duration * Normal winter shutdown periods are NOT subtracted out of duration term Daily HOOP = ($12,000, x.08) = $ Cal. Days
23 HOOP Hypo Step 2: Determine HOOH Payment for Unanticipated Construction Period CP HOOP = Daily HOOP x D Daily HOOP = $ (from previous page) D = all excusable, compensable delays minus all delays due to D.1 revised work and D.4 government acts other than Department (Calendar Days) D =114 39(EW) = 75 CP HOOP = $ x 75 Cal. Days = $151,899
24 HOOP Hypo Step 3: Determine HOOH Payment for Unanticipated Winter Period WP HOOP = Daily HOOP x F x (D/E) Daily HOOP = $ (from previous page) D = 75 Cal. Days (from previous page) E = all excusable, compensable delays plus all excusable, non-compensable delays (Calendar Days) F = 151 or 152 in leap year E = (weather) = 164 WP HOOP = $ x 151 x (75 Cal. Days/164 Cal. Days) = $139,858.23
25 HOOP Hypo Step 4: Determine Total HOOH Payment Total HOOP = CP HOOP + WP HOOP Total HOOP = $151,899 + $139, = $291,757.23
26 Thank You
S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows:
S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1.1 The last sentence of 1804 is deleted and replaced with the following: If the Contractor
More informationSection 108. PROSECUTION AND PROGRESS
108.01 Section 108. PROSECUTION AND PROGRESS 108.01. Subcontracting of Contract Work. No portion of the contract may be subcontracted, other than the providing of necessary materials, except as provided
More informationOREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor
More information108 PROSECUTION AND PROGRESS SECTION 108 PROSECUTION AND PROGRESS
SECTION 108 PROSECUTION AND PROGRESS 108.1 NOTICE TO PROCEED a. General. For each project, the Engineer will issue to the Contractor a Notice to Proceed, a written notice to the Contractor to begin the
More informationKiller Contract Clauses. Presented by Ben Westcott Shareholder Andrews Myers, PC
Killer Contract Clauses Presented by Ben Westcott Shareholder Andrews Myers, PC bwestcott@andrewsmyers.com Liability Considerations Design Defects Concealed Conditions Schedule Insurance Payment Terms
More information108 PROSECUTION AND PROGRESS SECTION 108 PROSECUTION AND PROGRESS
SECTION 108 PROSECUTION AND PROGRESS 108.1 NOTICE TO PROCEED a. General. For each Project, the Engineer will issue to the Contractor a Notice to Proceed, a written notice to the Contractor to begin the
More informationProving and Tracking Damages of your Claim
Proving and Tracking Damages of your Claim Jeffrey E. Fuchs, PE, CPA 1 1. Compensability 2. Excusability of a Delay 3. How is Compensable Delay Priced? 4. Costs and Rates 5. What Should a Schedule Expert
More informationReviewing Construction Claims INDOT Contracts
Reviewing Construction Claims INDOT Contracts Why do we have claims? Changed Conditions Causes the work to substantially differ in kind or nature from the work as required in the original contract. (104.02)
More informationDOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS
DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:
More informationSri Lanka Accounting Standard-LKAS 11. Construction Contracts
Sri Lanka Accounting Standard-LKAS 11 Construction Contracts CONTENTS paragraphs SRI LANKA ACCOUNTING STANDARD-LKAS 11 CONSTRUCTION CONTRACTS OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING
More informationProving and Tracking Damages of your Claim
Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving
More informationL 320/46 EN Official Journal of the European Union
L 320/46 EN Official Journal of the European Union 29.11.2008 INTERNATIONAL ACCOUNTING STANDARD 11 Construction contracts OBJECTIVE The objective of this standard is to prescribe the accounting treatment
More informationEASTERN OREGON UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
EASTERN OREGON UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THIS CONTRACT IS BETWEEN: OWNER: Eastern Oregon University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as
More information104 SCOPE OF WORK SECTION 104 SCOPE OF WORK
SECTION 104 SCOPE OF WORK 104.1 INTENT OF CONTRACT AND SCOPE OF CONTRACT a. Perform all work necessary to construct or reconstruct the Project. Use the best general engineering and construction practices.
More informationSECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS
SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8.1 8-1.01 Unit Price Contracts... 8.1 8-1.02 Lump Sum or Job Contracts... 8.1 8-1.03
More informationSTANDARD PROCEDURE FOR VALUE ENGINEERING IN CONSTRUCTION
Standard Procedure No.: 510-008(SP) Effective Date: September 14, 2011 Responsible Division: Construction Management Approved: Megan Blackford, P.E. Deputy Director, Division of Construction Management
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION. October 19, 2012
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION October 19, 2012 1113.01 Description 1113.02 References 1113.03 Definitions 1113.04 Value Engineering Change
More informationPN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS
PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS 101.01 On page 1, Add the following: NOTE: The fact that the bid items for this Design-Build project are general rather than
More informationSAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS
SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS The following changes are made to the Section II. Instruction
More informationAPPENDIX B TO COMPREHENSIVE AGREEMENT UOSA CONTRACT VSS UOSA VEHICLE SERVICE STATION FORM OF STAGE 2: FINAL DESIGN AMENDMENT
APPENDIX B TO COMPREHENSIVE AGREEMENT UOSA CONTRACT VSS UOSA VEHICLE SERVICE STATION FORM OF STAGE 2: This Stage 2: Final Design Amendment (Final Design Amendment) is an Amendment to the Comprehensive
More informationUniversity of Maryland College Park Change Order Guidelines. I. Introduction
University of Maryland College Park Change Order Guidelines I. Introduction This document is intended as a guideline for those currently doing business and those interested in pursuing business with the
More informationEvaluating Schedule Impacts. By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06
Evaluating Schedule Impacts By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06 Overview Definitions Methods of Evaluating Delays Best Practices 2 Classification of Project Delays (Risk Point of View) Non-excusable
More informationSSAP 23 STATEMENT OF STANDARD ACCOUNTING PRACTICE 23 CONSTRUCTION CONTRACTS
SSAP 23 STATEMENT OF STANDARD ACCOUNTING PRACTICE 23 CONSTRUCTION CONTRACTS (Issued May 1998; Revised January 2001) The standards, which have been set in bold italic type, should be read in the context
More informationClaim Avoidance on Highway Projects
Claim Avoidance on Highway Projects Joseph R. Hellenbrand, P. E., PSP Capital Project Management, Inc. ASHE National Conference Bismarck, North Dakota June 13, 014 1 Joe Hellenbrand P.E.; PSP 0 years of
More informationTHE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-2 (2013 Edition)
THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-2 (2013 Edition) Standard Form of Contract Between Construction Manager and Contractor (Construction Manager At-Risk) This document
More informationSection 80 Execution and Progress
AC 150/5370-10G 7/21/2014 Section 80 Execution and Progress 80-01 Subletting of contract. The Owner will not recognize any subcontractor on the work. The Contractor shall at all times when work is in progress
More informationConstruction Contracts
International Accounting Standard 11 Construction Contracts This version includes amendments resulting from IFRSs issued up to 31 December 2009. IAS 11 Construction Contracts was issued by the International
More informationSTANDARD PROCEDURE FOR PROCESSING CHANGE ORDERS
Approved: Standard Procedure No. 510-010(SP) Effective: 06/18/2010 Responsible Division: Construction Management Supersedes Standard Procedure: 510-010(SIP) Dated: 05/29/2008 William H. Lindenbaum, P.E.,
More informationVIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT
SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent
More informationSECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES
SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule
More informationThe BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have
More informationSECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY)
SECTION 01 32 16.16 NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) PART 1- GENERAL 1.1 DESCRIPTION: SPEC WRITER NOTES: 1. Coordinate this Design-Build Specification with FAR 52.232, VAAR 852.236 and Section
More informationPROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr.
PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr. (a) General. The Contractor is encouraged to develop, prepare, and submit
More informationAIA Document A133 TM 2009
AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price
More informationSECTION PROGRESS SCHEDULE
NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01310. SECTION 01311 PART 1 GENERAL 1.1
More informationARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES
ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract
More informationMitigating Delay Claims and Scheduling Best Practices
Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las
More informationSECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)
SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment
More informationLiquidated Damages and Scope Changes in Korean Government Contracts
Liquidated Damages and Scope Changes in Korean Government Contracts 2014.07.01 INTRODUCTION Liquidated Damages Treatment of LDs under Korean Act on Contracts to which the Government is a Party ( ACGP )
More informationSECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS
SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8-1 8-1.01 Unit Price Contracts... 8-1 8-1.02 Lump Sum or Job Contracts... 8-1 8-1.03
More informationDocument A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)
Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT
More informationVIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS
S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted
More informationitaia..." Document A
itaia..." Document A 133-2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price
More informationIn September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents:
In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: A101-2017: Standard Form of Agreement Between Owner and Contractor where
More informationCONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND. Insert CM Firm. Insert Name of Project. Insert Project Number
CONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND Insert CM Firm Insert Name of Project Insert Project Number University of Rochester Planning and Project Management 271 East River
More informationRichard J. Long, P.E. and Rod C. Carter, CCP, PSP
Richard J. Long, P.E. and Rod C. Carter, CCP, PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationFinal: Total 200 points (3-hour exam)
Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000
More informationCONSTRUCTION CONTRACT ANALYSIS. Robert Zellmer, CCA Manager Baker Tilly
CONSTRUCTION CONTRACT ANALYSIS Robert Zellmer, CCA Manager Baker Tilly OVERVIEW Today s topics: Contract Key Terms Documentation Requirements Red Flags LEARNING OBJECTIVE Deepen management s understanding
More informationComparison of 2007 and 2017 AIA contract documents
Construction & Design Risk Briefing Winter 2017 Comparison of 2007 and 2017 AIA contract documents Architects should consider switching over to the 2017 edition sooner rather than later. As with all form
More informationBID FORM (Lump Sum or Unit Price)
BID FORM (Lump Sum or Unit Price) BIDDER S Name and Address: Telephone: Fax: Federal Tax ID #: New Mexico Tax ID #: CID License # ITB NO.: 15-109 NAME: Cameo ES Roof Abatement and non ACM Roofing Removal
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 2600 MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK PART 1 GENERAL 1.01 SUMMARY A. Section includes requirements that supplement the paragraphs of Document
More informationSEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS
SEVENTEENTH ANNUAL SOUTHERN SURETY AND FIDELITY CLAIMS CONFERENCE St. Pete Beach, Florida th th MAY 4-5, 2006 A PRIMER ON EXTENDED PERFORMANCE COSTS IN A CLAIMS ENVIRONMENT (EMPHASIS ON THE EICHLEAY FORMULA)
More informationStandard Form of Agreement Between Contractor and Subcontractor
Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,
More informationIntroduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk
Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction
More informationDFARS Procedures, Guidance, and Information
PGI 216.2 FIXED-PRICE CONTRACTS (Revised December 31, 2012) PGI 216.203 Fixed-price contracts with economic price adjustment. PGI 216.203-4 Contract clauses. Contracting officers should use caution when
More informationSession 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES
Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation
More informationProject Delays and Extensions of Time. Dr Tony Farrow
Project Delays and Extensions of Time Dr Tony Farrow Topics 1. Why Extensions of Time? 2. Methods of Analysis and examples 3. Schedule Float 4. Concurrent Delay 5. Exercise 6. Questions Construction Contracts
More informationSTANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN
STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND THE CONSTRUCTION MANAGER Construction
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationCOUNTY TRANSPORTATION INFRASTRUCTURE FUND GRANT AGREEMENT
STATE OF TEXAS COUNTY OF TRAVIS COUNTY TRANSPORTATION INFRASTRUCTURE FUND GRANT AGREEMENT THIS AGREEMENT is made by and between the State of Texas, acting by and through the Texas Department of Transportation,
More informationStandard Form of Agreement Between Contractor and Subcontractor
Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal
More informationBUILDING CONSTRUCTION AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
Agenda Item: Action Consent BUILDING CONSTRUCTION AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER OWNER: Palm Beach State College 4200 Congress Avenue Lake Worth, FL 33461 CONSTRUCTION MANAGER: Date Table
More informationWelcome to the Model Residential Owner/Design Consultant Professional Service Agreement
Welcome to the Model Residential Owner/Design Consultant Professional Service Agreement The Council for the Construction Law Section of the Washington State Bar Association prepared this Model Residential
More informationM52: Delays, Stop Work Orders, and Termination in Grants and Contracts
M52: Delays, Stop Work Orders, and Termination in Grants and Contracts Presented by: J. Michael Slocum, Esquire SLOCUM & BODDIE, P.C. 5400 Shawnee Road, Suite 300 Alexandria, Virginia 22312 (703) 451-9001
More informationMemo No. 2. Meeting Date(s) PCC June 26, 2018
Memo No. 2 MEMO Issue Date June 15, 2018 Meeting Date(s) PCC June 26, 2018 Contact(s) Mary Mazzella Lead Author Ext. 434 Jason Bond Practice Fellow Ext. 279 John Schomburger PTA Ext. 443 Project Project
More informationPROCUREMENT CODE. Part A Authority to Bind County to a Contract
PROCUREMENT CODE ARTICLE 4 CONTRACT FORMATION Part A Authority to Bind County to a Contract 4-101 Authorization By Dollar Amount. Regardless of the acquisition or disposal method to be used, the level
More informationAIA Document A101 TM 2007
AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,
More informationBID PROPOSAL. To RM Builders on behalf of the Cherokee Nation Entertainment (hereinafter called Owner).
BID PROPOSAL PLACE: RM Builders 3441 W. 46 th Street Muskogee, OK 74401 BID PACKAGE #: DATE: Proposal of (hereinafter called Bidder) a corporation, organized and existing under the laws of the State of
More informationGuidance on adjustments to the Baseline Profit Rate. Introduction 3. Baseline profit rate (Step 1) 5. Cost risk adjustment (Step 2) 6
Contract Profit Rate Guidance on adjustments to the Baseline Profit Rate - March 2016 ii Guidance on adjustments to the Baseline Profit Rate Contents Introduction 3 Baseline profit rate (Step 1) 5 Cost
More informationCompany Name: Address: Date: OFFICAL SIGNATURE PRINT
Section 3 Clause A. The work to be performed under this contract is subject to the requirements of section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C. 1701u (section 3). The
More informationDESIGN AND CONSTRUCTION RESPONSIBILITY AND REIMBURSEMENT AGREEMENT BETWEEN THE CITY OF PLACERVILLE AND THE El DORADO IRRIGATION DISTRICT
DESIGN AND CONSTRUCTION RESPONSIBILITY AND REIMBURSEMENT AGREEMENT BETWEEN THE CITY OF PLACERVILLE AND THE El DORADO IRRIGATION DISTRICT FOR THE WESTERN PLACERVILLE INTERCHANGES PROJECT, PHASE 2 CITY CIP:
More informationPART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder
PART 3 Lump Sum Design-Build Agreement Between Department and Design-Builder This AGREEMENT is made as of the day of in the year of, by and between the following parties, for services in connection with
More informationAPPENDIX A TO COMPREHENSIVE AGREEMENT UOSA CONTRACT S/1 BUILDING S/1 RENOVATIONS FORM OF STAGE 2: DESIGN-BUILD WORK AMENDMENT
APPENDIX A TO COMPREHENSIVE AGREEMENT UOSA CONTRACT S/1 BUILDING S/1 RENOVATIONS FORM OF STAGE 2: DESIGN-BUILD WORK AMENDMENT This Stage 2: Design-Build Work Amendment ( DB Work Amendment) is an Amendment
More informationPART 3. Comprehensive Agreement Between Department and Design-Builder
PART 3 Between Department and Design-Builder This COMPREHENSIVE AGREEMENT for the I-64 Hampton Roads Bridge-Tunnel Project (the Agreement ) is made as of [ ], 2019 (the Agreement Date ), by and between
More informationCOUNTY OF SANTA BARBARA,
NOTICE TO BIDDERS Notice is hereby given that the General Services Department, County of Santa Barbara will receive bids for: COUNTY OF SANTA BARBARA, General Building Construction Job Order Contract Project
More informationSTANDARD CONTRACT EXECUTION FORMS
THE BIDDING AND CONTRACT PROVISIONS Document Section 00 50 00 - Standard Contract Execution Forms (Standard Contract Set) STANDARD CONTRACT EXECUTION FORMS 1. EXECUTION OF THE AGREEMENT 1.1 Extraneous
More informationAGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND J.T. VAUGHN CONSTRUCTION, LLC DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5928 04/16 Project No. 01-3228 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND J.T. VAUGHN CONSTRUCTION, LLC DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
More informationClarification Lot C Commercial List No.03. Ref Clause / Page Description Bidders Query Client response 1 Compliance with Laws 1.11.
Clarification Lot C Commercial List 03 1 Compliance with Laws 1.11.2(b) The Contractor shall indemnify and hold harmless the Employer from and against any and all liabilities, damages, claims, fines, penalties
More informationSECTION SCHEDULING OF WORK. A. Section covers scheduling of work activities including: 5. Suspension of WORK and delays.
SECTION 01 32 13 SCHEDULING OF WORK PART 1 GENERAL 1.01 SECTION INCLUDES A. Section covers scheduling of work activities including: 1. Other work at site. 2. Working hours. 3. Change of CONTRACT TIMES.
More informationCIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION
CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR SCHEDULES 8 + 9 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR
More informationMARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT
MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT THE CONTRACT IS BETWEEN: OWNER: MARION COUNTY A political subdivision of the state of Oregon And TBD Contractor (referred
More informationConstruction Contracts
Indian Accounting Standard (Ind AS) 11 Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT COSTS 16 21 RECOGNITION OF CONTRACT
More informationDocument A401 TM. Standard Form of Agreement Between Contractor and Subcontractor
Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,
More informationSTANDARD FORM AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER FOR PROFESSIONAL SERVICES. THIS AGREEMENT is made this day of, 20,
STANDARD FORM AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER FOR PROFESSIONAL SERVICES THIS AGREEMENT is made this day of, 20, (AGREEMENT) between, (OWNER) and, a Virginia Corporation, whose office location
More informationAGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK
AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK 1 ARTICLE 1 SCOPE OF WORK 2 DEFINITIONS TABLE OF CONTENTS 3 CONTRACTOR
More informationProject Time-Cost Trade-Off
Project Time-Cost Trade-Off 7.1 Introduction In the previous chapters, duration of activities discussed as either fixed or random numbers with known characteristics. However, activity durations can often
More informationOFFSHORE OUTSOURCING POLICY: CP 6032
SUBJECT: OFFSHORE OUTSOURCING POLICY: Department of Origin: Compliance and Audit Department Responsible Position: Vice President of Compliance and Audit Date(s) of Review and Revision: 11/11, 06/12, 02/14;
More informationSECTION SUPPLEMENTARY CONDITIONS
SECTION 00800 SUPPLEMENTARY CONDITIONS PART 1 GENERAL 1.01 GENERAL CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management
More informationConstruction Management-at-Risk Agreement
This ( Agreement ), by and between the Lone Star College ( LSC or Owner ) and ( Construction Manager ), referred to as Party individually or Parties collectively, shall become effective upon the date this
More informationDocument A Standard Form of Agreement Between Contractor and Subcontractor
Document A401 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name, legal
More informationTHE BIDDING AND CONTRACT PROVISIONS Document Section General Conditions (Standard Multiple and Single Contract Sets)
THE BIDDING AND CONTRACT PROVISIONS Document Section 00 70 00 General Conditions (Standard Multiple and Single Contract Sets) GENERAL CONDITIONS ARTICLE 1 DEFINITIONS 1.1 "Applicable Laws" means all laws,
More informationDocument A401 TM. Standard Form of Agreement Between Contractor and Subcontractor
Document A401 TM 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,
More informationStandard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:
Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,
More informationDocument A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:
Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT
More informationIPTC-CONTRACTOR GENERAL CONSTRUCTION CONTRACT
IPTC-CONTRACTOR GENERAL CONSTRUCTION CONTRACT This IPTC-CONTRACTOR GENERAL CONSTRUCTION CONTRACT ( Contract ) is made and entered into as of the day of March 2015, by and between the Indianapolis Public
More informationInsurance Requirements
SECTION A. CONTRACTOR shall procure, pay for and maintain the following insurance written by companies approved by the State of Texas and acceptable to CITY. The insurance shall be evidenced by delivery
More informationState Government Procurement
The following excerpts from the Arizona Revised Statutes are laws ACEC of Arizona initiated and secured for our industry. For further details regarding laws in the State of Arizona, go to http://www.azleg.gov
More informationSECTION SUPPLEMENTARY CONDITIONS A. APPLICATION
SECTION 00 73 13 SUPPLEMENTARY CONDITIONS A. APPLICATION 1. The Standard Form of Agreement of the American Institute of Architects, Document A101-2007, General Conditions of the Contract of the American
More informationAudit certificates. Training Seminar Brussels 28 November 2006
Audit certificates Training Seminar Brussels 28 November 2006 Overview Introduction Audit certificate requirements What When By whom Audit certificate template Audit certificate guidance notes for contractors
More informationBID INSTRUCTIONS / BID FORMS. For DSA REQUIRED ADA IMPROVEMENTS LEONARDO DA VINCI K-8 SCHOOL
Business Services Contracts Office 5735 47th Avenue Sacramento, CA 95824 (916) 643-2464 Gerardo Castillo, Chief Business Officer Kimberly Teague, Contract Specialist BID INSTRUCTIONS / BID FORMS For DSA
More information