Final Estimates Level 2
|
|
- Maximillian Pierce
- 5 years ago
- Views:
Transcription
1 Final Estimates Level 2 Module 9: Submittal of the Final Estimate & Offer of Final Payment 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
2 Module Content Final Estimates Package Final Estimates Process Offer of Final Payment Submittal Package Notification Of Findings Letter Source Incentive Payments Required Letters 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
3 Final Estimate Package A Final Estimate Package is a compilation of all the documents required to substantiate the final amount paid to the contractor, as well as certification of materials and contract time used. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 3 The Final Estimates Package consists of: Offer of Final Payment Final As-Built Plans All quantity backup (Asphalt Lot Packages, Final Measurements, Pile Driving Logs, etc.) Contract Time File Material Certification Documents (PA Certification, etc.) Overruns and Underruns When applicable: Shop Drawings, As-Built Load Rating, etc. Required Forms ( , Z, Final , etc.) NOTE: This list may not be all inclusive for your project. Read your contract, Department guidance manuals and contact your DFEO for additional information. NOTE: This package should be submitted electronically (Collaboration Site, EDMS, CD, DVD, Thumb drive, FTP, etc.). Again, read your contract and contact your DFEO for their preference. 9-3
4 Final Estimate Package The Final Estimates Package will be submitted to the District Final Estimates Office (DFEO) within 30 days of Final Acceptance. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
5 Final Estimate Process 30 Days Project Final Acceptance RO Completes Final Estimate Package Preparation DFEO Review Resident Office (RO) Runs Last Progress Estimate RO Runs Final Estimate RO Sends to the Contractor: 1. Offer of Final Payment 2. Request for Refund 1. Regular Acceptance 2. Qualified Acceptance To DFEM RO Prepares Offer of Final Payment DFEO Reviews Offer of Final Payment and sends back to RO Contract Closeout 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
6 Final Estimate Process Resident Office Responsibility Run the last Progress Estimate Submit the Offer of Final Payment to the Contractor Submit the Final Estimates Package to the DFEO Resolve any issues that result from the Offer of Final Payment and the Final Estimates Package 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 6 It is the responsibility of Resident Office personnel to run the last progress estimate to bring all quantities up to date to match the certified amount. The offer of final payment will be made to the contractor within 30 days of Final Acceptance. The intent is to have the Final Estimate be a Zero Dollar Amount with the exception of an Overpayment. The Final Estimates Package will be turned in to the DFEO within 30 days after the Final Acceptance date. Any Certification of Quantities due the Contractor should be paid on the Progress Estimate. This will ensure that the Prime Contractor can fulfill their obligation to the Sub-Contractors and see that they are paid in a timely manner. Example: when the Contractor performs the MOT Striping at the end of the project, you will need to verify that the certified quantities are included in with the Progress Estimate. All pending items should be listed on the Offer of Final Payment Letter. 9-6
7 Final Estimate Process DFEO s Responsibility The District Final Estimates Office (DEFO) will receive a copy of the Offer of Final Payment Letter and Final Estimate Package from the Resident Offices. Any resolutions made subsequent to the Offer will be processed by the DFEO. Un encumber unused funds. Continue to provide training to Resident Office staff on an as needed basis. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 7 After the post audit review (PAR) has been completed, the DFEO needs to unencumber any unused contingency Supplemental Agreement(s) and any contingency pay item funds. When resident office staff is referenced it means both in-house and consultant staff that prepare final estimates. 9-7
8 Final Estimate Process Last Progress Estimate Immediately following Final Acceptance, the Resident Office will run the last Progress Estimate This progress estimate should match quantities to be certified on the Final Estimate 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 8 As soon as allowed after Final Acceptance, the Residency will need to run a Progress Estimate to reduce the monetary amount due the Contractor to zero. It is imperative to submit through EED for payment as soon as possible so that estimates can be processed in a expeditious manner and will not accumulate. EED stands for Electronic Estimates Disbursement through the Departments Comptroller Office. Verify with your DFEO to ensure EED applies to your project. There are some exceptions (example: Fast Response). The Progress should match quantities on the certified estimate which includes: All pay items up to date including any penalties, Fuel & Bituminous adjustments, Liquidated Damages, etc. Any Certification of Quantities due the Contractor should be paid on the Progress Estimate. This will ensure that the Prime Contractor can fulfill their obligation to the Sub-Contractors and see that they are paid in a timely manner. Example: when the Contractor performs the MOT Striping at the end of the project, you will need to verify that the certified quantities are included in with the Progress Estimate. The only remaining payment to be included in the Final Estimate would be released of retainage and any incentive payments allowed by the Contract. 9-8
9 Final Estimate Process Once the last Progress Estimate is paid through EED, contact the DFEM and DFEO staff by for establishment of proper approval levels to run the final estimate, you will be notified by once the approval level changes are made, at that time, you will generate and run the Final Estimate. Approval levels in SiteManager will need to be changed by the DFEO. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 9 Approval levels are described in the SiteManager Handbook
10 Final Estimate Process Setting SiteManager Approval Levels for Final Estimate Level 1 Project Administrator Level 2 Final Estimates Manager Level 3 Comptroller, EED Final Approval 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
11 Final Estimate Process The Final Estimate should be $0.00 with the exception of Retainage or any incentive payments. If overpayment occurs, then the last progress estimate will be changed to Final. Note: The last progress estimate and the offer will both be negative. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
12 Final Estimate Process The amount certified on the final estimate will be the amount shown on the Pay Item Summary and Certification Sheet. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 12 The Certified Final Estimate Package includes the Certification of Accuracy provided by the CEI and the Pay Item Summary and Certification sheet. All of these documents should match on amounts earned and payables for that contract. 9-12
13 Offer of Final Payment Submittal Package The Offer of Final Payment Submittal Package includes: Offer of Final Payment Letter Acceptance Letter (to be signed by the Contractor). Acceptance Letter gives 2 options: Regular Acceptance Option of Agreeing with Offer Qualified Acceptance Option of Disagreeing with Offer Contractor s Affidavit & Surety Release (Form 21 A) Other documents to be returned to the District Final Estimates office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
14 Offer of Final Payment Submittal Package Send electronically to the Contractor s Headquarters address The Headquarter s address is specified in the Contract It is recommended to have the DFEO review the offer of final payment package for correctness prior to sending to the Contractor. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 14 The Offer Letters need to be sent electronically to the Contractor s Headquarters address. This address is located in the Contract. If addresses are not provided in the contract, request the contact information from the Contractor. DO NOT SEND OFFER LETTERS TO THE FIELD OFFICE ADDRESS. If possible send to more than 1 person to ensure receipt by the Contractor. It is also recommended to send with a return receipt and/or request a written response acknowledging receipt. 9-14
15 Offer of Final Payment Submittal Package Will be submitted to the Contractor within 30 days of Final Acceptance. The offer amount should be zero except in the case of overpayment. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 15 See Section 9-8 of the Standard Specifications; Required Contract Document Language. All items listed in the Standard Specifications, Section 9-8, that are pertinent to the Contract and that have not been received, need to be shown on the Offer Letter to the Contractor. The intent is to have the Final Estimate be a Zero Dollar Amount with the exception of an Overpayment. When it is determined the contractor has been overpaid, the last progress estimate will be negative and a request for refund will be issued. 9-15
16 Final Estimates Level 2 Offer of Final Payment Submittal Package The Offer of Final Payment Submittal Package includes: Offer of Final Payment Letter Acceptance Letter (to be signed by the Contractor). Acceptance Letter gives 2 options: Regular Acceptance Option of Agreeing with Offer Qualified Acceptance Option of Disagreeing with Offer Contractor s Affidavit & Surety Release (Form 21 A) Other documents to be returned to the District Final Estimates office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
17 Offer of Final Payment Letter There are two types of offer letters: Offer of final payment Request for refund 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 17 Be sure, when making the offer, the correct letter is included in the package to the Contractor. The intent is to have the Final Estimate be a Zero Dollar Amount with the exception of an Overpayment. When it is determined the contractor has been overpaid, the last progress estimate will be negative and a request for refund will be issued. There will be ONLY ONE Offer of Final Payment or Request for Refund made to the Contractor, per Contract! All pending items should be listed on the Offer of Final Payment Letter. See Section 9-8 of the Standard Specifications; Required Contract Document Language. All items listed in Section 9-8, that are pertinent to the Contract and that have not been received, need to be shown on the Offer Letter to the Contractor. 9-17
18 This is an example of an Offer Letter on a single project. 9-18
19 This is an example of an Offer of Final Payment Letter for multiple FIN Projects 9-19
20 This is an example of a Request for Refund (Overpayment) Letter for a single project. This letter is to inform the Contractor the Department has overpaid him and we are requesting a refund of the monies owed to the Department. 9-20
21 This is an example of a Request for Refund (Overpayment) Letter for multiple projects. 9-21
22 Offer of Final Payment Submittal Package The Offer of Final Payment Submittal Package includes: Offer of Final Payment Letter Acceptance Letter (to be signed by the Contractor). Acceptance Letter gives 2 options: Regular Acceptance Option of Agreeing with Offer Qualified Acceptance Option of Disagreeing with Offer Contractor s Affidavit & Surety Release (Form 21 A) Other document to be returned to the District Final Estimates office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 22 Slide repeated for emphasis on Offer of Final Payment Process 9-22
23 Acceptance Letters There are two types of acceptance letters: Regular Acceptance Qualified Acceptance 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 23 Option a Regular or Full Acceptance: Contractor submitted what is actually accepted on the Initial Offer Letter. Option b Contractor does not agree with the actual offer amount. The Contractor will list the issues in question through this method Qualified Acceptance. 9-23
24 Acceptance Letters Regular Acceptance Letter This form, signed by the Contractor, signifies his agreement to either: Accept the amount offered Refund the amount requested by the Department (Overpayment) As full and final settlement of any and all claims to compensation. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 24 If the Contractor takes a full or regular acceptance, all that is left is to process the estimate for payment, and start the process of closing the project. NOTE: If the Contractor is overpaid, the request for Refund Letter will be sent to the Contractor via so that an electronic record is made of the Contractor s receipt. 9-24
25 Acceptance Letters Qualified Acceptance Letter This form, signed by the Contractor, signifies that they do not agree the offer amount is correct. The contractor will: Accept the amount offered or refund the amount requested Then detail the dollar amounts/pay items in dispute. The letter stipulates the contract shall remain open while the Contractor pursues resolution of disputes or pending claims. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 25 If the Contractor takes a qualified acceptance, it means they could accept the amount offered but have additional issues/disputes. The Contractor must provide, in writing, the dispute(s), or pending claim(s) with full particulars for all items and on all issues in the dispute(s). This includes itemized amounts claimed for all items and sufficient information about the location of the dispute to isolate the exact area of the dispute. This is submitted as part of the qualified acceptance letter. 9-25
26 This is an example of a Qualified Acceptance letter and where the Contractor disputes the final offer on the monies owed to him and describes any qualified issues in dispute. 9-26
27 Continued Qualified Acceptance Letter. 9-27
28 Offer of Final Payment Submittal Package The Offer of Final Payment Submittal Package includes: Offer of Final Payment Letter Acceptance Letter (to be signed by the Contractor). Acceptance Letter gives 2 options: Regular Acceptance Option of Agreeing with Offer Qualified Acceptance Option of Disagreeing with Offer Contractor s Affidavit & Surety Release (Form 21 A) Other documents to be returned to the District Final Estimates office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 28 Slide repeated for emphasis on Offer of Final Payment Process 9-28
29 Contractor s Affidavit & Surety Release (Form 21 A) This document is required to be submitted by the Contractor on all projects. It certifies the Contractor has complied with all terms of the contract. It provides release of the final payment by the Contractor s Surety. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
30 This is page 1 of 3 of the Contractor s Affidavit & Surety Consent (Form 21-A) 9-30
31 This is page 2 of 3 of the Contractor s Affidavit & Surety Consent (Form 21-A) 9-31
32 This is page 3 of 3 of the Contractor s Affidavit & Surety Consent (Form 21-A) 9-32
33 Offer of Final Payment Submittal Package The Offer of Final Payment Submittal Package includes: Offer of Final Payment Letter Acceptance Letter (to be signed by the Contractor). Acceptance Letter gives 2 options: Regular Acceptance Option of Agreeing with Offer Qualified Acceptance Option of Disagreeing with Offer Contractor s Affidavit & Surety Release (Form 21 A) Other documents to be returned to the District Final Estimates office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 33 Slide repeated for emphasis on Offer of Final Payment Process 9-33
34 Outstanding Documents After final acceptance, all documents from the Contractor will be sent directly to the District Final Estimates Office. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 34 Examples: 1. Final Construction Compliance with Specifications and Plans 2. Acceptance Letter 3. Contractor Survey 9-34
35 This is page 1 of 2 of the Construction Compliance with Specification & Plans, Form This is not only required at the final estimate, but also with each monthly partial estimate during the contract duration. This form must be received before payment can be made each month and prior to final payment. 9-35
36 This is page 2 of 2 of the Construction Compliance with Specification & Plans, Form
37 Notification of Findings Letter What happens when an Offer of Final Payment Letter has been sent to the Contractor and additional issues are found? A Notification of Findings Letter is sent to the Contractor detailing the additional issues found. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 37 Once an Offer of Final Payment Letter has been sent to the Contractor, there may be a need to send a Notification of Findings Letter on issues found after the offer letter has been sent. The DFEO performs PARs on Certified Estimate Packages. If errors are found during the PAR, the DFEO will notify the responsible party of their findings for concurrence, and a Notification Letter is sent to the Contractor. This letter will include all changes for the Contractor to either agree on or disagree with. 9-37
38 Notification of Findings Letter This letter will address specific issues that were added or corrected due to issues discovered on the final estimate. These changes are needed based on the findings of the Post Audit Reviews (PAR) or for additional information. This letter could be sent to the Contractor before or after an Acceptance Letter has been received. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 38 This letter may be in addition to the original offer or it may come after receiving the Acceptance Letter. 9-38
39 Notification of Findings Letter This letter will be issued to the Contractor by the DFEO Only those items listed are eligible to be qualified. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 39 This letter will be issued to the Contractor with the specific items listing those changes. The letter will state that, only those items listed are eligible to be qualified. If the Contractor takes exception to any of the items listed, they will be in addition to any and all items listed in the original qualified letter. ONLY DFEO WILL SEND OUT THE NOTIFICATION LETTER When sending the notification letter, the DFEO WILL NOT send the estimate with this letter. 9-39
40 Notification of Findings Letter What happens if, after receiving the Full Acceptance from the Contractor, there is an overpayment found based on the PAR review? The Contractor has a right to accept or reject any or all of these changes. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 40 If after receiving the Full Acceptance from the Contractor there is an overpayment found based on the PAR review, then the CCEI responsible for that particular contract will be held accountable to provide assistance in the recovery of those funds due the Department. The Contractor has a right to accept or reject any or all of these changes. This is a Certified Final Estimates Package from the resident office. The resident office is held accountable for the accuracy of the final estimate. 9-40
41 Notification of Findings Letter What happens after receiving the Overpayment Acceptance letter and Refund Check from the Contractor, there is an error found based on the PAR review? The Contractor has a right to accept or reject any of these changes. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 41 After receiving the Overpayment Letter and Refund Check from the Contractor, issue a notification letter to the Contractor of the specific issues addressing items that were added or corrected due to differences discovered on the final estimate. This may increase or decrease the overpayment. The Contractor has a right to accept or reject any of these changes. 9-41
42 Example of Notification of Findings letter. 9-42
43 Source Chapter 14 of the Review and Administration Manual describes the Final Estimate process Submittal of the Final Estimate 14.9 Contractor s Acceptance of the Final Estimate Notification Letter of Due to Additional Review 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 43 NOTE: The Review and Administration Manual (R&AM) is currently being updated. The information covered in Chapter 14 of the R&AM may be moved to the Construction Project Administration Manual (CPAM) in the near future. Look for updates and changes to these manuals. Admin.shtm Each manual has a past revisions link at the top of the page. Contact your DFEO with any questions. 9-43
44 Incentive Payments Examples: Liquidated Savings No excuse Bonus Lane Rentals Contact the DFEO by . Specify the dollar amount 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 44 If incentive payments such as liquidated savings, no-excuse bonus, lane rentals, incentive/disincentive, etc. are due, immediately following Final Acceptance, contact the DFEO by . In the correspondence to the DFEM, specify the dollar amount necessary for encumbrance for incentive payment. 9-44
45 Incentive Payments When can the incentive payment be made? After the Offer of Final Payment Who encumbers these funds? The District Office 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 45 No incentive payment can be made until the Offer of Final Payment is made to the Contractor, unless otherwise specified in the Contract. These monies must be encumbered by the District Office or designee, in cooperation with the DCE. 9-45
46 Required Letters Chapter 14 of the Review and Administration Manual shows examples of the required letters. Boilerplate letters are provided on the State Final Estimate s SharePoint Site. 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 9 46 Boilerplate letters are provided on the State Final Estimate s SharePoint Site. 9-46
47 ANY QUESTIONS? 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module
Florida Department of TRANSPORTATION
Florida Department of TRANSPORTATION 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 7 1 7-1 Module Content Importance of Contract Time Liquidated Damages Contract Time Documentation File Federal
More informationTOWN BRIDGE CONSTRUCTION ACCOUNTS 4.11 SPECIAL TOWN BRIDGE ALLOTMENT
TOWN BRIDGE CONSTRUCTION ACCOUNTS 4.11 SPECIAL TOWN BRIDGE ALLOTMENT NARRATIVE Periodically, the county may exceed their Town Bridge Allotment, if this occurs the county may receive a Special Town Bridge
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 4 1 4-1 Module Content Adjustments in SiteManager Line Item Adjustments Contract Adjustments
More informationERRORS, OMISSIONS, AND CONTRACTUAL BREACHES BY PROFESSIONAL ENGINEERS ON DEPARTMENT CONTRACTS
4/24/2012: Pen & Ink to clarify language in Appendix H for Statutes of Limitations and correct reference in Authority Section. Approved: Effective: February 18, 2010 Office: Production Support Topic No.:
More informationTOWN BRIDGE CONSTRUCTION ACCOUNTS 4.1 Chapter 4 TOWN BRIDGE CONSTRUCTION ACCOUNT
TOWN BRIDGE CONSTRUCTION ACCOUNTS 4.1 Chapter 4 TOWN BRIDGE CONSTRUCTION ACCOUNT TOWN BRIDGE ALLOTMENT NARRATIVE There are grant monies available from State Aid which is specific to Town Bridge Construction.
More informationSTANDARD PROCEDURE FOR PROCESSING CHANGE ORDERS
Approved: Standard Procedure No. 510-010(SP) Effective: 06/18/2010 Responsible Division: Construction Management Supersedes Standard Procedure: 510-010(SIP) Dated: 05/29/2008 William H. Lindenbaum, P.E.,
More informationPARTIAL UTILITY REFUND / TENTATIVE ACCEPTANCE AGREEMENT
Approved: Effective: May 17, 2017 Review: March 30, 2017 Office: Comptroller Topic No: 350-020-305-h Department of Transportation PARTIAL UTILITY REFUND / TENTATIVE ACCEPTANCE AGREEMENT PURPOSE: This procedure
More information3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.
the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2
More informationARTICLE 8: BASIC SERVICES
THE SCOPE OF SERVICES ADDED BY THIS AMENDMENT IS FOR A CM AT RISK PROJECT ONLY. THE SCOPE OF SERVICES SPECIFIED BELOW INCLUDES ARTICLES 8.1, 8.3, 8.4, 8.5, 8.6, 8.7 AND 8.8. THE SERVICES SPECIFIED IN ARTICLE
More informationApproved: Effective: January 20, 2016 Review: February 23, 2018 Office: Aviation Topic No d LOANS TO AIRPORTS
Approved: Effective: January 20, 2016 Review: February 23, 2018 Office: Aviation Topic No. Department of Transportation LOANS TO AIRPORTS PURPOSE: To provide policy guidance and a process for the administration
More informationDocument A Exhibit A
Design-Build Amendment Document A141 2014 Exhibit A This Amendment is incorporated into the accompanying AIA Document A141 2014, Standard Form of Agreement Between Owner and Design-Builder dated the day
More informationDIVISION 1 - GENERAL REQUIREMENTS SECTION APPLICATIONS FOR PAYMENT
DIVISION 1 - GENERAL REQUIREMENTS SECTION 01027 APPLICATIONS FOR PAYMENT I. GENERAL This section specifies administrative and procedural requirements governing Contractor Applications For Payment. II.
More informationContract Administration Final Exam
Contract Administration Final Exam 1. You want to solicit bids for a one year contract for concrete to support your roadway construction work. At this time, prices are fluctuating due to high demand and
More informationMARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT
MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT THE CONTRACT IS BETWEEN: OWNER: MARION COUNTY A political subdivision of the state of Oregon And TBD Contractor (referred
More informationOREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor
More informationAugust 24, Brunetta Gamble-Dillard, M.B.A. Associate Vice President for Business and Finance, RPS. Orlando F. McMeans, Ph.D. Executive Director
August 24, 2015 Brunetta Gamble-Dillard, M.B.A. Associate Vice President for Business and Finance, RPS Orlando F. McMeans, Ph.D. Executive Director ACCOUNTS PAYABLE MANUAL TABLE OF CONTENTS Introduction....
More informationCE303 Introduction to Construction Engineering 2/15/2011. CE303 Introduction to Construction Engineering. Construction Contracts Definition
CE303 Introduction to Construction Construction Contracts Learning Objectives ~ The Student should be able to : Explain the types and requirements of a Contract. Explain Notice to Proceed, Substantial
More informationAIA Document A103 TM 2007
AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the
More informationLikewise, consultant employee substitutions require resume and wage rate approvals prior to any work being completed by that person.
person qualified at a higher classification (i.e. TCIS in lieu of the requested TCI), PennDOT reserves the right to pay the firm for the classification originally requested. Under the terms and conditions
More informationSCHEME ADMINISTRATOR:
Version 2 All Companies applying for or taking out a Warranty on a New Development with LABC Warranty shall comply with these Rules. These Rules apply to all Companies applying for registration with LABC
More informationAPPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F
Subcontract No.: Enter Number Cost Code: Enter Code TOCCI BUILDING CORPORATION Vendor No.: Enter Number APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F To standardize the Application for Payment
More informationLast Name (Company) First Name SSN Disbursement % Mailing Address City State Zip
Account Servicing Agreement Allegro Escrow Services, a Division of Evergreen Note Servicing (hereinafter referred to as Servicer ), is hereby directed to establish a servicing account on behalf of the
More informationGENERAL EMPLOYEES' PENSION FUND ADMINISTRATION
GENERAL EMPLOYEES' PENSION FUND ADMINISTRATION July 22, 2002 REPORT # 548 OFFICE OF THE COUNCIL AUDITOR Suite 200, St. James Building July 22, 2002 Report No. 548 Honorable Members of the City Council
More informationPART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder
PART 3 Lump Sum Design-Build Agreement Between Department and Design-Builder This AGREEMENT is made as of the day of in the year of, by and between the following parties, for services in connection with
More informationTexas Department of Transportation
Consultant Errors & Omissions Correction and Collection - Policy and Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection - Policy and Procedures 1.0 Consultant Contract
More informationREQUEST FOR PROPOSALS
702 KAR 4:160 KENTUCKY DEPARTMENT OF EDUCATION REQUEST FOR PROPOSALS for CONSTRUCTION MANAGEMENT SERVICES School District: Project: Boyle County Boyle County Middle School RFP Date: June 20 30, 2016 CONTENTS
More informationDEATH AND SURVIVOR. Employer Responsibility p. 1 Survivor/Beneficiary p. 6 SURS Responsibility p.7. Rev Employer Responsibility
DEATH AND SURVIVOR Employer Responsibility p. 1 Survivor/Beneficiary p. 6 SURS Responsibility p.7 Rev. 11-15-04 Employer Responsibility A deceased active employee s retirement benefit must be calculated
More informationAiM User Guide Capital Planning and Project Management (CPPM) System
AiM User Guide Capital Planning and Project Management (CPPM) System 2011 AssetWorks Inc. 1777 NE Loop 410, Suite 1250 San Antonio, Texas 78217 (800) 268-0325 TABLE OF CONTENTS INTRODUCTION... 5 CHAPTER
More informationStandard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk
CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract
More informationMAINTENANCE CONTRACT ADMINISTRATION, INSPECTION, AND REPORTING
Approved: Effective: December 22, 2017 Review: October 10, 2017 Office: Maintenance Topic No.: 375-020-002-l Department of Transportation PURPOSE: MAINTENANCE CONTRACT ADMINISTRATION, INSPECTION, AND REPORTING
More informationApproved: Effective: May 17, 2017 Review: March 28, 2017 Office: Comptroller General Accounting Topic No.: h ACCOUNTS RECEIVABLE
Approved: Effective: May 17, 2017 Review: March 28, 2017 Office: Comptroller General Accounting Topic No.: 350-060-303-h Department of Transportation ACCOUNTS RECEIVABLE PURPOSE: To define requirements
More informationSECONDARY PARTICIPATION GUARANTY AGREEMENT
OMB NO.: 3245-0185 EXPIRATION DATE: 2/28/2017 SBA LOAN NUMBER SECONDARY PARTICIPATION GUARANTY AGREEMENT IMPORTANT INFORMATION THIS FORM IS TO BE USED FOR THE INITIAL TRANSFER ONLY. ALL SUBSEQUENT TRANSFERS
More informationDocument A Exhibit A Determination of the Cost of the Work
Document A121 2014 Exhibit A Determination of the Cost of the Work THE OWNER: (Name, legal status, address and other information) THE CONTRACTOR: (Name, legal status, address and other information) This
More informationRandolph County Schools. Renovations to Third Ward Elementary School
Randolph County Schools Pre-Bid Meeting Notes August 8, 2011; 11:00 a.m. Third Ward Elementary School, 111 Nathan St., Elkins, WV, 26241 This meeting was mandatory for General Contractors, optional for
More informationSECTION INSTRUCTION TO BIDDERS. Bidders may obtain sets of Bidding Documents from Engineer:
SECTION 00100 INSTRUCTION TO BIDDERS 1.01 SECURING DOCUMENTS Bidders may obtain sets of Bidding Documents from Engineer: Hethcoat & Davis, Inc. 278 Franklin Road, Suite 200 Brentwood, TN 37027 (615) 577-4300
More information0% introductory APR for the first 12 billing cycles following
PNC POINTS VISA / PNC POINTS VISA SIGNATURE IMPORTANT INFORMATION ABOUT RATES AND FEES Interest Rates and Interest Charges Annual Percentage Rate (APR) for Purchases APR for Balance Transfers 0% introductory
More informationOrlando-Orange County Expressway Authority
Orlando-Orange County Expressway Authority s Audit November 2012 2012 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA s management, audit committee, and board of directors.
More informationStandard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project
Document B108 2009 Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)
More informationStandard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price
November 3, 2014 Standard Form of Agreement Between Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price This document has important legal consequences. Consultation with
More informationTitle IV. Revenue & Finance
Title IV Revenue & Finance Chapters: Chapter 4.01 Chapter 4.02 Chapter 4.03 Chapter 4.04 Chapter 4.05 Budget generally Budget procedure Annual financial statement Contracts & purchasing Line of Credit
More informationAGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR
THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text
More informationEXHIBIT H FOR OFFICE OF FACILITIES PLANNING AND CONSTRUCTION (OFPC) MANAGED PROJECTS ONLY
THE UNIVERSITY OF TEXAS SYSTEM ADMINISTRATION JANUARY 1, 2016 EXHIBIT H FOR OFFICE OF FACILITIES PLANNING AND CONSTRUCTION (OFPC) MANAGED PROJECTS ONLY POLICY ON UTILIZATION HISTORICALLY UNDERUTILIZED
More information1 Exam Prep Business and Finance Practice Test 10
1 Exam Prep Business and Finance Practice Test 10 1. What is an advantage of a bad debt reserve? A. it reduces tax liability for earned profit B. it increases assets C. it increases profits D. it simplifies
More informationRefunds & Adjustments
Refunds & Adjustments Presented by Jonathan Golden, Justice Court Fund Wendy Bolton, Justice Court Fund 1 Refunds Court Orders Today s Presentation Local Court Order/Coram Nobis Superior Court Order Refunds
More informationFRESNO COUNTY EMPLOYEES RETIREMENT ASSOCIATION (FCERA) POLICIES AND PROCEDURES GOVERNING THE OVERPAYMENT OR UNDERPAYMENT OF MEMBER CONTRIBUTIONS
FRESNO COUNTY EMPLOYEES RETIREMENT ASSOCIATION (FCERA) POLICIES AND PROCEDURES GOVERNING THE OVERPAYMENT OR UNDERPAYMENT OF MEMBER CONTRIBUTIONS The Board of Retirement ( Board ) has a fiduciary obligation
More informationAlameda County Transportation Commission SAMPLE PROGRAM COMPLIANCE LANGUAGE: CONSTRUCTION
SAMPLE PROGRAM COMPLIANCE LANGUAGE: CONSTRUCTION For Alameda CTC-funded projects subject to the Local Business Contract Equity (LBCE) Program Note to Project Sponsor: Be sure that your legal staff reviews
More informationCOUNTY OF SONOMA. CAL-Card USER MANUAL
COUNTY OF SONOMA CAL-Card USER MANUAL DEPARTMENT OF GENERAL SERVICES PURCHASING DIVISION May 2012 TABLE OF CONTENTS SECTION PAGE NO. 1. General Information 1 2. Definitions 3 3. Authorized, Restricted
More informationAIA Document A133 TM 2009
AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price
More informationGeneral Terms and Conditions of Bricks & More B.V.
General Terms and Conditions of Bricks & More B.V. Table of contents: Article 1 - Definitions Article 2 - Trader's identity Article 3 - Applicability Article 4 - The offer Article 5 - The contract Article
More informationAGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status and address)
Document A134 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price AGREEMENT
More informationOHIO DEPARTMENT OF TRANSPORTATION OFFICE OF REAL ESTATE
DATE: July 1, 2015 OHIO DEPARTMENT OF TRANSPORTATION OFFICE OF REAL ESTATE TO: FROM: Users of the Real Estate Manual (Permits) Wendi Snyder, Utility & Railroad Program Manager RE: Changes and Updates to
More informationSTATE OF NEVADA DEPARTMENT OF HEALTH AND HUMAN SERVICES DIVISION OF WELFARE AND SUPPORTIVE SERVICES
STATE OF NEVADA DEPARTMENT OF HEALTH AND HUMAN SERVICES DIVISION OF WELFARE AND SUPPORTIVE SERVICES AUDIT REPORT Table of Contents Page Executive Summary... 1 Introduction... 6 Background... 6 Facilities
More informationAgency: Bus Area: Fiscal Year
Accounts Receivable 1 Are the agency's accounts receivable policies and procedures clearly stated through manuals, handbooks, or other media? 2 Are all receivable transactions properly and accurately recorded,
More informationGeneral Terms and Conditions for co-operation between the Swedish Pensions Agency and Fund Managers 01/10/2016
General Terms and Conditions for co-operation between the Swedish Pensions Agency and Fund Managers 01/10/2016 01/10/2016 Contents General Terms and Conditions for co-operation between the Swedish Pensions
More information14.24% to 24.24% when you open your account, based on your creditworthiness.
PNC CASH REWARDS VISA / PNC CASH REWARDS VISA SIGNATURE IMPORTANT INFORMATION ABOUT RATES AND FEES Interest Rates and Interest Charges Annual Percentage Rate (APR) for Purchases 14.24% to 24.24% when you
More informationREQUEST FOR PROPOSAL FOR EMS BILLING AND COLLECTION SERVICES. Emmet County Suite G Division Street Petoskey, Michigan 49770
REQUEST FOR PROPOSAL FOR EMS BILLING AND COLLECTION SERVICES Emmet County Suite G92 200 Division Street Petoskey, Michigan 49770 1 RFP-EC-04-18 The County of Emmet is seeking qualified vendors to submit
More informationReviewing Construction Claims INDOT Contracts
Reviewing Construction Claims INDOT Contracts Why do we have claims? Changed Conditions Causes the work to substantially differ in kind or nature from the work as required in the original contract. (104.02)
More informationRockdale ISD Accounts Payable Procedures
Accounts payable checks should be processed on a weekly basis for release by Thursday morning, or earlier dependent upon work schedules or holidays. Cut-off date for weekly processing is noon on Tuesday.
More informationFresno County Zoo Authority Procedures for Approving and Administering Measure Z Funds. Adopted November 11, 2005
Fresno County Zoo Authority Procedures for Approving and Administering Measure Z Funds Adopted November 11, 2005 Revised February 13, 2018 TABLE OF CONTENTS INTRODUCTION... 1 Exhibit 1 - Financial Management
More informationApproved: Effective: June 15, 2016 Review: May 15,2016 Office: Comptroller, General Accounting Office Topic No.: k REVOLVING FUNDS
Approved: Effective: June 15, 2016 Review: May 15,2016 Office: Comptroller, General Accounting Office Topic No.: 350-080-303-k Department of Transportation PURPOSE: REVOLVING FUNDS To provide direction
More informationStandard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent
CMAA Document A-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent 2013 EDITION This document is to be used in connection with the Standard Form of
More informationDCMA MANUAL Contract Debts
DCMA MANUAL 2501-10 Contract Debts Office of Primary Responsibility: Contract Maintenance Capability Effective: April 13, 2018 Releasability: Cleared for public release New Issuance Implements: DCMA-INST
More informationErroneous Payment of Living Quarters Allowance
Erroneous Payment of Living Quarters Allowance Notification of Debt and Debt Waiver Process (APF) 1 Debt Notification Process Once an employee is notified of erroneously receiving Living Quarters Allowance
More informationNew York State Public Service Commission
PSC NO. 220 ELECTRICITY ADDENDUM TYPES: SIR NIAGARA MOHAWK POWER CORPORATION ADDENDUM NO. 7 INITIAL EFFECTIVE DATE: AUGUST 16, 2017 STAMPS: ISSUED IN COMPLIANCE WITH ORDER IN CASE 16-E-0560 Issued August
More informationAGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER Pre-Construction and Construction Phase Services FP&M Project No, CP00Error! Bookmark not defined. AGREEMENT made by and between the Board of Regents, State
More informationVIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT
SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent
More informationREQUEST FOR BID (RFB) CLARIFICATIONS DOCUMENT. Section 1 Additional Administrative Information
REQUEST FOR BID (RFB) CLARIFICATIONS DOCUMENT Section 1 Additional Administrative Information 1.1 Purchasing Agent The Purchasing Agent identified in the RFB cover sheet is the sole point of contact regarding
More informationPART VII CONTRACT DELIVERABLES
PART VII CONTRACT DELIVERABLES SECTION TITLE Q R S T U Certificate of Insurance Surety Bonds Invoices Project Reports/Documents Closeout Submittals 58 SECTION Q CERTIFICATE OF INSURANCE Q.1 GENERAL REQUIREMENTS
More informationTitle Insurance and Settlement Company Best Practices
ALTA Best Practices Framework: Title Insurance and Settlement Company Best Practices Page 1 of 8 ALTA Best Practices Framework The ALTA Best Practices Framework has been developed to assist lenders in
More informationi) terms in heavy type are defined ii) values corresponding to the terms in italics are specified in the relevant Schedule.
general provisions General provisions Please note that in this contract: i) terms in heavy type are defined ii) values corresponding to the terms in italics are specified in the relevant Schedule. All
More information17.24% This APR will vary with the market based on the prime rate.
PNC PREMIER TRAVELER VISA SIGNATURE IMPORTANT INFORMATION ABOUT RATES AND FEES Interest Rates and Interest Charges Annual Percentage Rate (APR) for Purchases 17.24% This APR will vary with the market based
More informationAIA Document A102 TM 2007
AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the
More informationConstruction Phase Services: Pitfalls, Perils and Payment. RLI Design Professionals Design Professionals Learning Event DPLE 147 May 18, 2016
Construction Phase Services: Pitfalls, Perils and Payment RLI Design Professionals Design Professionals Learning Event DPLE 147 May 18, 2016 RLI Design Professionals is a Registered Provider with The American
More informationC. Appropriation a funding amount approved and designated by the City Commission as part of the capital budget process for project implementation.
City Commission Policy # 218 DEPARTMENT: Administration & Professional Services DATE ADOPTED: January 9, 1991 DATE OF LAST REVISION: April 27, 2016 218.01 AUTHORITY 218.02 PURPOSE City Commission adoption
More informationAIA Document A101 TM 2007
AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,
More informationAIA Document A102 TM 2007
AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the
More informationUniform General Conditions and Supplementary General Conditions for Construction Contracts
Rev. 7/15/14 Uniform General Conditions and Supplementary General Conditions for Construction Contracts Bold provisions are Supplementary General Conditions (SGC s) Rev. 7/15/14 Table of Contents Article
More informationImportant Information About Changes To Your Advisory Service
Important Information About Changes To Your Advisory Service March 29, 2018 Effective July 16, 2018, Fidelity will bring together multiple services. A new registered investment adviser called Fidelity
More informationTerms and conditions for large and corporate businesses for the supply of gas and electricity ( corporate terms )
Terms and conditions for large and corporate businesses for the supply of gas and electricity ( corporate terms ) October 2018 Version 10 (Ref: TC 10/18) britishgas.co.uk/business British Gas Trading Limited
More informationMDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
More informationChapter Survey. Required Contract Elements. Offer and Acceptance
Contract Management Chapter Survey Required Contract Elements Contract Provisions Breach of Contract Boilerplate Provisions Provisions to Limit Risk What Are Recitals? Types of Construction Contracts Contracting
More informationADVERTISING, SALE & AWARD
ADVERTISING, SALE & AWARD PRIMARY ROLES & RESPONSIBILITIES PRIMARY TASK ODOT LPA DEVELOP BID PROPOSAL PREPARE AND SUBMIT PS&E PACKAGE TO DISTRICT DISTRICT REVIEW OF PS&E PACKAGE (District LPA Manager with
More informationSand Purchase for Golf Course Bunker Renovation. Hoffman Estates Park District
Hoffman Estates Park District BID DATE: 12/5/16 BID TIME: 10am CST PREPARED BY: Brian Bechtold Director of Golf Operations 847-781-3679 HOFFMAN ESTATES PARK DISTRICT 1685 W. Higgins Road Hoffman Estates
More informationPublic Private Ventures Process Guide
Public Private Ventures Process Guide This guideline is applicable for proposed privatized transactions that utilize private bond proceeds or other private financing to fund a portion or all cost for development
More informationINVITATION TO BID. Pre-Bid Showing: Enter Date and Time Here. Please call by Enter Date and Time Here to reserve a bid packet and confirm attendance.
INVITATION TO BID Notice to Bidders: Bids will be received by the Port of Shelton, 21 W Sanderson Way, Shelton, WA 98584 for the following work order: Work Order: Enter # and Name Here Pre-Bid Showing:
More informationOregon Personal Income Tax
Oregon Personal Income Tax Electronic Filing Handbook For Software Developers and Tax Preparers Tax Year 2008 Published by Oregon Department of Revenue 10/08/2008 2:38 PM 1 Oregon Electronic Filing Business
More informationCITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION. CMD ATTACHMENT 1 Requirements for Construction Contracts
CITY & COUNTY OF SAN FRANCISCO Requirements for For Contracts $300,000 & over that are Advertised on or after August 1, 2016 PART I. GENERAL 1.01 SAN FRANCISCO ADMINISTRATIVE CODE CHAPTERS 12B AND 14B
More informationSECTION GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) AGREEMENT TABLE OF CONTENTS ARTICLE 1 DEFINITIONS... 2
SECTION 00 50 00 GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) AGREEMENT TABLE OF CONTENTS ARTICLE 1 DEFINITIONS... 2 ARTICLE 2 THE CONTRACT DOCUMENTS... 3 ARTICLE 3 WORK OF THIS CONTRACT... 4 ARTICLE
More informationThe Board and the Chancellor may amend or end this Program at any time and for any reason as allowed by Board Policy.
Section IV.E.3.20 Human Resources Faculty Leave Banking Program The Chancellor adopts these procedures in accordance with Section IV.E.20. of the Lone Star College System District Policy Manual ( Policy
More information13.74% to 22.74% when you open your account, based on your creditworthiness.
CASHBUILDER VISA / CASHBUILDER VISA SIGNATURE IMPTANT INFMATION ABOUT RATES AND FEES Interest Rates and Interest Charges Annual Percentage Rate (APR) for Purchases 13.74% to 22.74% when you open your account,
More informationWAGE WITHHOLDING FOR DEFAULTED STUDENT LOANS A HANDBOOK FOR EMPLOYERS. Revised June 30, 2008
WAGE WITHHOLDING FOR DEFAULTED STUDENT LOANS A HANDBOOK FOR EMPLOYERS Revised June 30, 2008 TABLE of CONTENTS A Letter to Employers..3 The Student Loan Program.4-5 The Basic Steps Employers Follow for
More informationCONSTRUCTION CONTRACT RIDER
CONSTRUCTION CONTRACT RIDER In connection with the work at, Massachusetts (the Development ) to be performed by (the Contractor ) pursuant to the Construction Contract dated, 20 between the Contractor
More informationAIA Document A102 TM 2007
AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the
More informationGENERAL TERMS OF PURCHASE BADER POLSKA SP.Z O.O. /limited liability company/
1. General Provisions GENERAL TERMS OF PURCHASE BADER POLSKA SP.Z O.O. /limited liability company/ The legal relationship between the Supplier of goods or services and Bader Polska Sp. z o.o., with its
More informationFrequently Asked Questions (FAQs) About the Penalties & Interest Project
Frequently Asked Questions (FAQs) About the Penalties & Interest Project General Project Information Question What does Go Live mean? When will the penalty and interest regulations be effective? Answer
More informationLoaded Everyday card terms and conditions
Loaded Everyday card terms and conditions Posted Online: 1 October 2013 Effective: 15 October 2013 The Loaded TM range of cards is issued by Kiwibank Limited and distributed by various organisations, including
More informationTimothy Winn Wedding Photography C o n f i r m a t i o n b o o k i n g f o r m (2013)
Timothy Winn Wedding Photography C o n f i r m a t i o n b o o k i n g f o r m (2013) Please fill in all sections as fully as possible, print off the completed form, and send to: Timothy Winn, 96 Way Lane,
More informationITA88 PROCESS GUIDE ITA88 PROCESS GUIDE AN EMPLOYERS GUIDE TO THE ITA88 AGENT APPOINTMENT PROCESS
AN EMPLOYERS GUIDE TO THE ITA88 AGENT APPOINTMENT PROCESS SEPTEMBER 2010 _v2.indd 1 1 9/21/10 4:10 PM AN EMPLOYERS GUIDE TO THE ITA88 AGENT APPOINTMENT PROCESS Introduction ITA88 AGENT APPOINTMENT Who
More informationTHIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-BS-EQC as follows:
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-BS-EQC ADDENDUM NUMBER ONE May 2, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL
More informationDocument C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser
Document C132 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Adviser AGREEMENT made as of the 14th day of July in the year 2014 (In words, indicate day, month and year.) BETWEEN
More information