RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1
|
|
- Magnus O’Brien’
- 5 years ago
- Views:
Transcription
1 RETURN TO ROME Project Management Fundamentals 1
2 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed Time - Days Project Management Fundamentals Slide 2
3 Cost Plan: $4,000 Four Day Rome Project S-Curve Cost vs Time Actual vs. Plan $3,300 $3,000 = Plan $2,100 $2,000 $1,100 $1,000 $900 $1,000 $2,400 = Actual Cumulative Cost of completing Milestones $ Time -- Days) Slide 3
4 The Four Day ROME Project REVISITED with EVIE EARNED VALUE ANALYSIS Current Status (as of Day 3) 1. % Total Cost Incurred: 60% 2. % Total Project Work Completed: 50% 3. % Planned Work Completed to Date: 67% x 4. % Planned Cost Incurred to Date: 114% 114% for Work Done vs. 73% for Work Scheduled i.e. $2,400 / $2,100 not $2,400 / $3,300 AC / EV AC / PV Project Management Fundamentals Slide 4
5 Planned Cum Costs (BUDGET) S-CURVE TRANSFORM Cost vs. Work (Milestones) = EARNED VALUE Best Practice Integrated Review of Implementation Planned Cum Work (Milestones) Project Management Fundamentals 5
6 The Transform effectively shows the integrated relationship between successfully completed Work (i.e. Quality) and its Actual, as well as its Planned, Cost (Rather than in accordance with the original Planned Schedule & Budget) Project Management Fundamentals Slide 6
7 Cost Plan: $4,000 Four Day Rome Project with S-CURVE TRANSFORM of Actual Cost vs. Planned Work as of Day 3 $3,300 $3,000 $2,100 $2,000 $1,100 = Planned Value; $1,000 $1,000 & Cumulative $900 Earned Value for the Milestones $0 Completed 0 $2, Work (Milestones) Project Management Fundamentals = Actual Cost Cumulative Cost of completing Milestones Slide 7
8 Earned Value Analysis (EVA) Compared with Traditional Analysis Earned Value Analysis reveals that contrary to the Traditional Cost vs. Schedule S-Curve Instead of a cost savings, there is actually a COST Overrun for the Work Completed (i.e. the first two Milestones) Although all the budgeted funds for the period have not yet been spent the Project is currently both Behind Schedule & has a Cost Overrun Project Management Fundamentals Slide 8
9 VARIANCE & Graphics for Monitoring & Evaluating Project Performance OVERVIEW 9
10 % Variance from Target (Plan) EVA Control Chart Variance + 100% - 100% % Cost Variance = (EV AC) / EV % Schedule Variance = (EV PV) / PV Four Day Rome Project over budget 14% Cost - 9% Variance - 18% - 36% behind schedule Schedule Variance - 48% Projected Time Schedule Schedule Can track Both Schedule & Cost Variances over Project time Management on this Fundamentals chart Slide 10
11 EVA Control Chart Significant Points to Note: Cost TARGET (EV) &/or SCHEDULE plotted through the Center of the Chart Cost (AC) &/or Schedule (PV) VARIANCE (% Variance) on Y Axis Time-Series Tracking is on X Axis Trends can be visualized based on historic Data Project Management Fundamentals Slide 11
12 EVALUATING PERFORMANCE For Quality Control and Management Decisionmaking purposes during implementation monitoring, a more meaningful scale of gradations, or ratings -- rather than just simple percentages -- should be established on the control chart for various performance levels. 12
13 % Variance from Target EVALUATING PERFORMANCE A Control Chart Target Indicators: etc
14 % Variance from Standard Tolerances EVALUATING PERFORMANCE An Accept/Reject Quality Control Chart REJECT ACCEPT ACCEPT REJECT Target 14 Indicators: etc
15 % Variance from Target EVALUATING PERFORMANCE Management Decision-making Control Chart Indicators: etc Refer to Project Mgr Refer to Supervisor No action Necessary Target No action Necessary Refer to Supervisor Refer to Project Mgr
16 The key measure of performance is really the EARNED VALUE i.e. the Actual Cost of the Work successfully completed to date : compared to the Planned Cost for that same Work Regardless of when it was completed i.e. whether ahead of, behind, or in accordance with the planned schedule NOT the Burn Rate at which the budget for the Scheduled Work was Spent Project Management Fundamentals Slide 16
17 EVIE The EARNED VALUE concept provides a Different Perspective for analyzing project implementation performance Project Management Fundamentals Slide 17
18 Regardless of its Actual Cost Earned Value is merely The original estimated Cost to perform a Project Activity or Work Breakdown Structure Component When that work is completed Project Management Fundamentals Slide 18
19 Well... So What...? If The Earned Value is Greater Than the Actual Cost You got a Bargain i.e. a Cost Underrun, or Savings! If The Earned Value is the Same as the Actual Cost SoSo i.e. So Far, So Good, you are on Budget! If The Earned Value is Less Than the Actual Cost You re in Trouble i.e. you ve incurred a Cost Overrun! Project Management Fundamentals Slide 19
20 Earned Value is The original Cumulative Estimated Cost to perform Project Activity Work i.e. Work Breakdown Structure Packages, Components -- &/or to Reach Milestones When the work is completed Regardless of when originally scheduled, or the Actual Cost Project Management Fundamentals Slide 20
21 Earned Value Analysis (EVA) Compared with Traditional Analysis Earned Value Analysis reveals that contrary to the Traditional Cost vs. Schedule S-Curve There is actually a COST Overrun for the Work Completed (i.e. the first two Milestones) So the True Situation is that although all the budgeted funds for the period have not yet been spent, the Project is: Behind Schedule & has a Cost Overrun Project Management Fundamentals Slide 21
22 The Four Day ROME Project EARNED VALUE ANALYSIS Current Status (as of Day 3) End of Project Forecast: 1. Time: 1 Day Slippage 2. Cost: $571 Overrun * NOT $1,091 Savings or $300 Overrun, or SWAG *Consistently Derived by VAC (i.e. another Earned Value formula) VAC = BAC - BAC x AC EV Project Management Fundamentals Slide 22
23 Without an Analysis of Earned Value as shown by the S-Curve Transform the Traditional Perspective is inadequate, and even Misleading! Project Management Fundamentals Slide 23
24 Key EV Indicators Drivers Four Drivers : KEYS to Understanding Earned Value Analysis 1. PV = Planned Value [NOTE: Also known as the Budgeted Cost of Work Scheduled, BCWS or BS ] The Amount originally Planned to be Spent for the Work originally Scheduled to be Done to Date 2. AC = Actual Cost of Work Performed, ACWP or AP The Amount Actually Spent for the Work Actually Done to Date -- NOTE: Regardless Whether or Not it was Planned &/or Scheduled ACWP or AP 3. EV = Earned Value [NOTE: Also known as the Budgeted Cost of Work Performed, BCWP or BP ] The Original Amount Planned to be Spent for the Work Actually Done to Date [From PV: The Baseline Work Budget] 4. BAC = Budgeted Cost at Completion The Amount originally Planned to be Spent for the Total Project Project Management Fundamentals Slide 24
25 A Note & Caution RE Actual Cost Actual Cost (ACWP) for Earned Value is really only Estimated rather than Actual! Cost accruals by accounting departments occur at different times than activities - for which the cost was intended - were/are performed, or items procured. i.e. advances before, or payments following billings &/or invoicing for activities, and receipt of materials, equipment or services. Project Management Fundamentals 25
26 Consequently -- to preclude inadvertently exceeding their budget -- Project Managers should track their expenditures for subcontracts, consultants, purchased labor, goods and supplies, travel, per diems etc., as soon as they are allocated with intent to be incurred -- as well as the Project s estimated running Indirect Cost and the cumulative accrued total reported as their Actual Costs as of the reported time period. Project Management Fundamentals 26
27 Although the Project Manager s Estimated Actual Cost is also sometimes referred to as Approved or Accrued Actual Cost (AAC) I prefer to call it A Crude Actual Cost In any event, remember that Actual Cost reported by program & project managers in Earned Value Analysis is NOT the same as the financial manager s perspective of actual costs for any advances, invoices received &/or payments made (at a much later date) for goods acquired & services rendered. Project Management Fundamentals 27
28 EVM APPLICATION There is a systematic pattern in the relationship between These Four indicators: PV AC EV & BAC that provide a consistent, unified analysis of project performance, as well facilitating presentation of a Project s Implementation Status in familiar terms. Project Management Fundamentals Slide 28
29 EV vs Traditional Analysis An Example $3,300 Traditional Actual vs. Scheduled Cost Comparison $2,400 Traditional Analysis: Actual Costs to date were Less than Planned indicating a Cost UNDERRUN, but not whether the work was completed. Planned Value PV (i.e. the Budget for the Time period) Actual Cost AC to date Project Management Fundamentals Slide 29
30 EV vs Traditional Analysis An Example Traditional Analysis of 4 day ROME : Actual Costs to date were Less than Planned indicating a Cost Underrun. EVA s Analysis: 1. Spending Rate was slower than planned, but Traditional Actual vs. Scheduled Cost Comparison Actual Costs $3,300 for the work successfully completed were greater than planned Thus instead of an Underrun there is A Cost Overrun 2. Furthermore, since the Earned Value! is less than the Planned Value as of that time period, $2,400 this indicates that the Project is also Behind Schedule $2,100 EV Actual Cost for Work Completed vs. Planned Cost Comparison i.e. Budget regardless of the work plan schedule $3,300 $2,400 $2,100 Planned Value PV (i.e. the Budget for the Time period) Actual Cost AC to date Earned Value EV (Budget for the completed Work) Slide 30
31 EVA Analysis Another Example $410 $530 $440 EV Analysis: 1. Spending is greater than planned, and Actual Costs for the work successfully completed are also greater than planned i.e. A Cost Overrun. 2. However, since the Earned Value is also Greater than the Planned Value as of that date, this indicates that the Project is Ahead of Schedule Planned Value PV (Budget for the Time period) Actual Cost AC Earned Value EV (Budget for the completed Job) Project Management Fundamentals Slide 31
32 EVM INNOVATION II During implementation Thirteen (13) different Combinations* of PV AC & EV. are possible Reflecting 13 different Performance Status Conditions * Technical Note: Derived from 25 or 27 Permutations (i.e. 1 x 5 x 5 or 3 x 3 x 3) See Appendix Project Management Fundamentals Slide 32
33 Unfortunately, Traditional Time & Cost Monitoring systems DO NOT analyze and report project status systematically in terms of these 13 possible scenarios -- even though the information already exists. Consequently, erroneous management decisions can be -- and often are -- made. Project Management Fundamentals Slide 33
34 HOWEVER, You Can...! The characteristics of these Thirteen different combinations Can be rank-ordered and color-coded from 1 (High) to 13 (Low) To create an overall Integrated Project Performance Index (PPI) Project Management Fundamentals Slide 34
35 Project Performance Index (PPI)* & Traffic Light System (TLS)* for Quick & Easy Application of Earned Value Project Management Fundamentals Slide 35
36 Of these Thirteen Project Status Conditions: 6 are Good for each indicator 4 are Mixed (i.e. good & bad ), and 3 are Bad for all indicators Project Management Fundamentals Slide 36
37 Possible States of Project Implementation PV AC EV PV AC EV Target In terms of PV AC & EV PV AC EV The Constellation Combinations Project Management Fundamentals Slide 37
38 Project Performance [Index] Planned Value PV Actual Cost AC Earned Value EV [Index] PROJECT STATUS CONDITION 1 $100 $80 $120 Good. Work ahead of schedule & with cost savings on work done, as well as an apparent cost under-run on the budget. 2 $100 $100 $120 Good. Work is ahead of schedule, with cost savings even though the budget has been spent as planned. 3 $100 $80 $100 Good. Work is on schedule, with cost savings. 4 $100 $120 $140 Good. Work is ahead of schedule, with costs savings. [But may have a cash flow problem if funds are released incrementally.] 5 $100 $120 $120 Good. Work is ahead of schedule, with costs as planned for work done. [But may have a cash flow problem if funds are released incrementally.] 6 $100 $100 $100 Ideal. Everything going according to plan On Schedule & Spending. [Extremely Rare!] 7 $100 $60 $80 Mixed Good & Bad. Saving money on the work performed; but work is behind schedule. Project Management Fundamentals Slide 38
39 Project Perform - ance [Index] Planned Value PV Actual Cost AC Earned Value EV [Index] PROJECT STATUS CONDITION 7 $100 $60 $80 Mixed Good & Bad. Saving money on the work performed; but work is behind schedule. 8 $100 $120 $100 Mixed Good & Bad. Work on schedule, but cost overrun incurred. [May have a cash flow problem if funds are released incrementally.] 9 $100 $80 $80 Mixed Good & Bad. Spending as planned; but work is behind schedule. 10 $100 $140 $120 Mixed Good & Bad. Work ahead of schedule, but a cost overrun has been incurred. [May have a cash flow problem if funds released incrementally.] 11 $100 $80 $60 BAD. Spending is slower than planned, but the Value is low indicating a cost overrun; and the work is also behind schedule. 12 $100 $100 $80 BAD. Although the spending rate is as planned, since the Value is low, there is a cost overrun; and the work is also behind schedule. 13 $100 $120 $80 BAD. Work behind schedule, cost overrun [and possible cash flow problem.] Project Management Fundamentals Slide 39
40 1. PPI & TRAFFIC LIGHT SYSTEM QUICK & EASY TEMPLATE for monitoring INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 40
41 41
42 2. EVA SOFTWARE for monitoring INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 42
43 Monitoring the Triple Threat with EVA-2006 Calculating all the foregoing Earned Value Indicators manually for various status situations and preparing the related charts is laborious, time-consuming, as well as prone to error. However, I have developed a software program (in a Project Management Toolkit ) that calculates these EVA indicators and draws related charts and graphs. The Tool Kit is available from: Project Management Fundamentals Slide 43
44 2. Automated Early Warning Traffic Light System To facilitate both computation and analysis I had Software developed to: 1. Calculate all the other 16 EV indicators from the four basic Drivers 2. Display the Performance Index results in Color -- with Icons & a summary explanation 3. Together with several supporting graphics and an Executive Summary Project Management Fundamentals Slide 44
45 EVA-2006 Software* Accepts project plan & implementation driver data [activity/milestone work schedule & cost] Then calculates: Monetary data in two (2) different currencies Eighteen (18) key Earned Value Performance indicators Assesses the Project Status Condition on a 13- point scale, & a color-coded Traffic Light system as either Good Mixed or Bad Provides an Executive Summary for briefings with several supporting graphics [See EVA PPI & Traffic Light in my Project Management Tool Kit ] *Programmed by BLASTASIA Slide 45
46 Project Management Fundamentals Slide 46
47 Monitoring the Triple Threat Three (3) BAD States Planned Cost of Work Scheduled PPI - Project Performance Index Current Project Status: Condition Work Being Completed Behind Schedule 2. Positive Cash Flow Actual Cost of Work Performed 3. Cost Overrun Incurred on the Work Done Earned Value of Work Performed $3,300 $2,400 $2,100 Project Management Fundamentals Slide 47
48 EVA Quadra-Graph Project Implementation Summary COST VARIANCE 100% Under Budget 0% Over Budget Current Status 100% 0% Behind Ahead 100% SCHEDULE Project Management VARIANCE Fundamentals Slide 48
49 EXECUTIVE SUMMARY ANALYSIS Automatically computed: The Project s Present Status Condition is PPI 11: BAD The Project is 53% Complete (%CS), and is 36% Behind Schedule (%CV) At current trends, the project is now estimated to complete on 20-Aug-2016 (ECD) US$2,171 will be needed to complete the project (ETC) For a total of US$4,671 (EAC) This represents a Cost Overrun of US$571 (VAC) Project Management Fundamentals Project Management Fundamentals Slide 49
50 EVA SOFTWARE DEMONSTRATIONS Project Management Fundamentals Slide 50
51 3. PIMS QUICK & EASY TEMPLATE for Recording, Tracking, Monitoring & Analyzing INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 51
52 ROJECT ID: PROJECT INTEGRATED MONITORING SYSTEM (PIMS) -- WORK, BUDGET & COST PERFORMANCE For Projects up to One Hundred (100) Months duration with Milestone %s, Physical & Financial S-Curves, Control Chart Variance, Earned Value Histogram, S- Curve Transform & PPIndex Sample Demonstration Planned MON Indirect Overhead Project Duration: 7 THS OK Rate: 25% 2014, Dr. Kenneth F. Smith, PMP INSTRUCTIONS FOR USE. On initial use, first Delete all the data in the Three yellow cells above, and the cell & Four yellow Rows in the table below. Then enter YOUR PLAN, & ACTUAL Data in the yellow cells, and immediately view the Analyzed results in the table, graphs and chart below. YEAR 1 YEAR MONTHS Jan-15 Feb-15 Mar- 15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 ilestones nned (POW) umulative estones Plan ect Planned ost / Mo direct Cost allocated] ct + Indirect OH Cost umulative ct + Indirect OH ulative MS PLAN Sep- 15 V=BCWS ulative Cost $6 $10 $19 $26 $34 $39 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 PLAN ctual Cost AC+OH 2013 Dr. $7 Kenneth $8 F. $1 Smith, $4 PMP $10 $3 Project Management Fundamentals 52 umulative $7 $15 $16 $20 $30 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 Oct- 15 Nov- 15 Dec-15 Jan-16 Feb-16 Mar- 16 Apr-16 May- 16 Jun-16 Jul-16 Aug $5 $3 $8 $5 $7 $4 $1 $1 $1 $1 $1 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6 $4 $9 $6 $8 $5 $1 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6 $10 $19 $26 $34 $39 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $
53 ANALYSIS Percent Complete On, Ahead or Behind Schedule On, Over or Under Budget 14% 14% 43% 43% 57% 71% 71% Project Performance Index (PPI) PPI Key: 1 through 6 = GOOD EV = BCWP "Earned Value" $6 $6 $10 $10 $19 $26 $26 Running Budget Variance from Plan 14% 46% -18% -22% -11% -15% -18% Work Schedule Variance from Plan 0% -40% -47% -60% -42% -34% -36% True Cost Variance from Plan 14% 144% 56% 94% 54% 29% 29% Project Management Fundamentals 53
Earned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationEarned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING
More informationNOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:
NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM
More informationUse of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM
Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationProject Performance Evaluation By Earned Value Method
Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *
More informationEarned Schedule Analysis
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI
More informationThe First Steps in Implementing a Simplified Earned Value Management System
2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More informationGate Value Method Overview document
Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person
More informationThe Cost Monitoring of Construction Projects Through Earned Value Analysis
211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More informationProject Assessment Exercise
Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at
More information9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.
Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control
More informationEarned Value Management Guide
1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress
More informationEVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes
EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationJefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7
Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,
More informationPredicting The Future
Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties
More informationProject Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:
Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationProfessional Development Seminar Series
Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context
More informationJames A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)
Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com
More informationCS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III
LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date
More informationEarning Value From Risk
Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned
More informationProject Management -- Monitoring the progress
Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a
More informationLong Description. Figure 15-1: Contract Status. Page 1 of 7
Page 1 of 7 Figure 15-1: Contract Status A single performance report provides the status of the Program at a point in time. When combined with previous reports, a much more revealing picture of the Program
More informationFrom Suspicion to Invaluable Transition of Two Project Managers
From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition
More informationANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?
ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1
More informationProject Monitoring and Control Project Closure. Week 8
Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring
More informationCumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationPredicting Project Completion Date Using Earned Value Management
Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationEarned Value Management
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards
More informationENGINEERING MANAGEMENT (GE
بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control
More informationBudgeting & Financial Reporting
Budgeting & Financial Reporting CEPI BUDGET TEMPLATE INSTRUCTIONS For use by potential awardees and awardees Updated 5/30/2017 TABLE OF CONTENTS 1 General Guidance... 4 1.1 About this document... 4 1.2
More informationEarned Schedule in Action
Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationDEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers
1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program
More informationCE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System
CE303 Introduction to Construction g PROJECT COST MANAGEMENT & BUSINESS METHODS LEARNING OBJECTIVES The student should be able to: Define and understand the need for a cost control system. Describe the
More informationFactor Leave Accruals. Accruing Vacation and Sick Leave
Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization
More informationRoberta Tomasini Defense Acquisition University DSN
$ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program
More informationTRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA
TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor
More informationAnalysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh
Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS
More informationeurope GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors
eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationEarned Value Management (EVM) and the Acquisition Program
American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.
More informationfor 9 Sep 15 SoCal ICEAA Workshop
Two Complementary EVM Cost-Risk Models Part 2 1. Use of EVM Trend Tool (EVMTT) to Forecast Cost Risks with 4 Case Study Examples 2. Integrated Cost-Risk Model (ICRM) Utilizing ACEIT for 9 Sep 15 SoCal
More informationConnecting Earned Value to the Schedule
Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned
More informationProject Management: Cost
Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationEarned Value Management Handbook. arne. alu
Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change
More informationSchedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia
Schedule Analysis and Predictive Techniques Using Earned Schedule 16 th IPM Conference Tysons Corner, Virginia 17 th November 2004 Walt Lipke OC-ALC/MAS Tinker AFB OK walter.lipke@tinker.af.mil 405-736-3341
More informationTitle: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:
DATA ITEM DESCRIPTION Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT Number: Approval Date: 20091026 AMSC Number: N9105 Limitation: DTIC Applicable: N/A GIDEP Applicable: N/A Office
More informationKey Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado
Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept
More informationEarned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence
Earned Value and PRINCE2 Alex Davis Programme Manager Close Combat Programme Support Office Ministry of Defence PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom
More informationCalifornia ISO. Flexible Ramping Product Uncertainty Calculation and Implementation Issues. April 18, 2018
California Independent System Operator Corporation California ISO Flexible Ramping Product Uncertainty Calculation and Implementation Issues April 18, 2018 Prepared by: Kyle Westendorf, Department of Market
More informationObjectives of Project Cost Control System
Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final
More informationA Case for Project Revenue Management. Peter Varani PMP
A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach
More informationDetailed Project Scheduling and Cost Management
Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More informationPerformance measurement
MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda
More informationTHE VALUE OF EARNED VALUE MANAGEMENT
THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs
More informationAgile Methods with. Performance-Based Earned Value
Agile Methods with Performance-Based Earned Value CMMI Technology Conference Abstract 7110 November 20, 2008 Paul Solomon, PMP Performance-Based Earned Value www.pb-ev.com 1 Agenda Customer expects valid
More information(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett
(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford
More informationProfit Is Important But Cash Flow Is Critical!
Profit Is Important But Cash Flow Is Critical! Did you know cash flow puts more contractors out of business than any other single thing.except improper labor pricing! It s true. You can be priced absolutely
More informationChapter 11 Project Execution and Control
Chapter 11 Project Execution and Control Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Phase C: Project Execution Most projects
More informationSpheria Australian Smaller Companies Fund
29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771
More informationCritical Path and Earned Value Management
Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method
More informationOracle Project Portfolio Management Cloud Using Project Performance Reporting
Oracle Project Portfolio Management Cloud Using Project Performance Reporting Release 9 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E53157-01
More informationGLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Project Status Overview Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 1
More informationHumphreys &Associates, Inc.
Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion
More informationIntegrated Cost Schedule Risk Analysis Using the Risk Driver Approach
Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012
More informationPresenting Earned Value
Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationJohn Chapman. Earned Value and PRINCE2
Earned Value and PRINCE2 John Chapman PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries. Why are we here? Do PRINCE2 and Earned Value relate
More informationPerformance Analyzer Formulas. Assumptions. Current Month Adjustments
User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived
More informationPMP Exam Prep Coaching Program
PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to
More informationSoftware Process and Management
Software Process and Management Gu Qing Nanjing University 2006-2-28 1 Chapter 5. Project Tracking Project Tracking and Control Progress Management Project Termination 2 1. Project Tracking and Control
More informationXML Publisher Balance Sheet Vision Operations (USA) Feb-02
Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786
More informationProject Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition
Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition Chapter Fourteen Cost Control Do Project Managers Control Costs, Monitor Costs, or Both? Cost Management
More information5-D Integrated Earned Value Analysis
5-D Integrated Earned Value Analysis Erol Yurtseven, October 2013 Budgeting Scheduling Design Coordination Quantity Survey Technical Office 3 4 Technical Office Design Dept & Technical Office 2 5 Cost
More informationBusiness & Financial Services December 2017
Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationUsing projections to manage your programs
Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based
More informationProject Management Variance Analysis Example Xls
We have made it easy for you to find a PDF Ebooks without any digging. And by having access to our ebooks online or by storing it on your computer, you have convenient answers with project management variance
More information1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#12 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More informationCarlos Consulting Group
Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group
More information[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,
More information