RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

Size: px
Start display at page:

Download "RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1"

Transcription

1 RETURN TO ROME Project Management Fundamentals 1

2 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed Time - Days Project Management Fundamentals Slide 2

3 Cost Plan: $4,000 Four Day Rome Project S-Curve Cost vs Time Actual vs. Plan $3,300 $3,000 = Plan $2,100 $2,000 $1,100 $1,000 $900 $1,000 $2,400 = Actual Cumulative Cost of completing Milestones $ Time -- Days) Slide 3

4 The Four Day ROME Project REVISITED with EVIE EARNED VALUE ANALYSIS Current Status (as of Day 3) 1. % Total Cost Incurred: 60% 2. % Total Project Work Completed: 50% 3. % Planned Work Completed to Date: 67% x 4. % Planned Cost Incurred to Date: 114% 114% for Work Done vs. 73% for Work Scheduled i.e. $2,400 / $2,100 not $2,400 / $3,300 AC / EV AC / PV Project Management Fundamentals Slide 4

5 Planned Cum Costs (BUDGET) S-CURVE TRANSFORM Cost vs. Work (Milestones) = EARNED VALUE Best Practice Integrated Review of Implementation Planned Cum Work (Milestones) Project Management Fundamentals 5

6 The Transform effectively shows the integrated relationship between successfully completed Work (i.e. Quality) and its Actual, as well as its Planned, Cost (Rather than in accordance with the original Planned Schedule & Budget) Project Management Fundamentals Slide 6

7 Cost Plan: $4,000 Four Day Rome Project with S-CURVE TRANSFORM of Actual Cost vs. Planned Work as of Day 3 $3,300 $3,000 $2,100 $2,000 $1,100 = Planned Value; $1,000 $1,000 & Cumulative $900 Earned Value for the Milestones $0 Completed 0 $2, Work (Milestones) Project Management Fundamentals = Actual Cost Cumulative Cost of completing Milestones Slide 7

8 Earned Value Analysis (EVA) Compared with Traditional Analysis Earned Value Analysis reveals that contrary to the Traditional Cost vs. Schedule S-Curve Instead of a cost savings, there is actually a COST Overrun for the Work Completed (i.e. the first two Milestones) Although all the budgeted funds for the period have not yet been spent the Project is currently both Behind Schedule & has a Cost Overrun Project Management Fundamentals Slide 8

9 VARIANCE & Graphics for Monitoring & Evaluating Project Performance OVERVIEW 9

10 % Variance from Target (Plan) EVA Control Chart Variance + 100% - 100% % Cost Variance = (EV AC) / EV % Schedule Variance = (EV PV) / PV Four Day Rome Project over budget 14% Cost - 9% Variance - 18% - 36% behind schedule Schedule Variance - 48% Projected Time Schedule Schedule Can track Both Schedule & Cost Variances over Project time Management on this Fundamentals chart Slide 10

11 EVA Control Chart Significant Points to Note: Cost TARGET (EV) &/or SCHEDULE plotted through the Center of the Chart Cost (AC) &/or Schedule (PV) VARIANCE (% Variance) on Y Axis Time-Series Tracking is on X Axis Trends can be visualized based on historic Data Project Management Fundamentals Slide 11

12 EVALUATING PERFORMANCE For Quality Control and Management Decisionmaking purposes during implementation monitoring, a more meaningful scale of gradations, or ratings -- rather than just simple percentages -- should be established on the control chart for various performance levels. 12

13 % Variance from Target EVALUATING PERFORMANCE A Control Chart Target Indicators: etc

14 % Variance from Standard Tolerances EVALUATING PERFORMANCE An Accept/Reject Quality Control Chart REJECT ACCEPT ACCEPT REJECT Target 14 Indicators: etc

15 % Variance from Target EVALUATING PERFORMANCE Management Decision-making Control Chart Indicators: etc Refer to Project Mgr Refer to Supervisor No action Necessary Target No action Necessary Refer to Supervisor Refer to Project Mgr

16 The key measure of performance is really the EARNED VALUE i.e. the Actual Cost of the Work successfully completed to date : compared to the Planned Cost for that same Work Regardless of when it was completed i.e. whether ahead of, behind, or in accordance with the planned schedule NOT the Burn Rate at which the budget for the Scheduled Work was Spent Project Management Fundamentals Slide 16

17 EVIE The EARNED VALUE concept provides a Different Perspective for analyzing project implementation performance Project Management Fundamentals Slide 17

18 Regardless of its Actual Cost Earned Value is merely The original estimated Cost to perform a Project Activity or Work Breakdown Structure Component When that work is completed Project Management Fundamentals Slide 18

19 Well... So What...? If The Earned Value is Greater Than the Actual Cost You got a Bargain i.e. a Cost Underrun, or Savings! If The Earned Value is the Same as the Actual Cost SoSo i.e. So Far, So Good, you are on Budget! If The Earned Value is Less Than the Actual Cost You re in Trouble i.e. you ve incurred a Cost Overrun! Project Management Fundamentals Slide 19

20 Earned Value is The original Cumulative Estimated Cost to perform Project Activity Work i.e. Work Breakdown Structure Packages, Components -- &/or to Reach Milestones When the work is completed Regardless of when originally scheduled, or the Actual Cost Project Management Fundamentals Slide 20

21 Earned Value Analysis (EVA) Compared with Traditional Analysis Earned Value Analysis reveals that contrary to the Traditional Cost vs. Schedule S-Curve There is actually a COST Overrun for the Work Completed (i.e. the first two Milestones) So the True Situation is that although all the budgeted funds for the period have not yet been spent, the Project is: Behind Schedule & has a Cost Overrun Project Management Fundamentals Slide 21

22 The Four Day ROME Project EARNED VALUE ANALYSIS Current Status (as of Day 3) End of Project Forecast: 1. Time: 1 Day Slippage 2. Cost: $571 Overrun * NOT $1,091 Savings or $300 Overrun, or SWAG *Consistently Derived by VAC (i.e. another Earned Value formula) VAC = BAC - BAC x AC EV Project Management Fundamentals Slide 22

23 Without an Analysis of Earned Value as shown by the S-Curve Transform the Traditional Perspective is inadequate, and even Misleading! Project Management Fundamentals Slide 23

24 Key EV Indicators Drivers Four Drivers : KEYS to Understanding Earned Value Analysis 1. PV = Planned Value [NOTE: Also known as the Budgeted Cost of Work Scheduled, BCWS or BS ] The Amount originally Planned to be Spent for the Work originally Scheduled to be Done to Date 2. AC = Actual Cost of Work Performed, ACWP or AP The Amount Actually Spent for the Work Actually Done to Date -- NOTE: Regardless Whether or Not it was Planned &/or Scheduled ACWP or AP 3. EV = Earned Value [NOTE: Also known as the Budgeted Cost of Work Performed, BCWP or BP ] The Original Amount Planned to be Spent for the Work Actually Done to Date [From PV: The Baseline Work Budget] 4. BAC = Budgeted Cost at Completion The Amount originally Planned to be Spent for the Total Project Project Management Fundamentals Slide 24

25 A Note & Caution RE Actual Cost Actual Cost (ACWP) for Earned Value is really only Estimated rather than Actual! Cost accruals by accounting departments occur at different times than activities - for which the cost was intended - were/are performed, or items procured. i.e. advances before, or payments following billings &/or invoicing for activities, and receipt of materials, equipment or services. Project Management Fundamentals 25

26 Consequently -- to preclude inadvertently exceeding their budget -- Project Managers should track their expenditures for subcontracts, consultants, purchased labor, goods and supplies, travel, per diems etc., as soon as they are allocated with intent to be incurred -- as well as the Project s estimated running Indirect Cost and the cumulative accrued total reported as their Actual Costs as of the reported time period. Project Management Fundamentals 26

27 Although the Project Manager s Estimated Actual Cost is also sometimes referred to as Approved or Accrued Actual Cost (AAC) I prefer to call it A Crude Actual Cost In any event, remember that Actual Cost reported by program & project managers in Earned Value Analysis is NOT the same as the financial manager s perspective of actual costs for any advances, invoices received &/or payments made (at a much later date) for goods acquired & services rendered. Project Management Fundamentals 27

28 EVM APPLICATION There is a systematic pattern in the relationship between These Four indicators: PV AC EV & BAC that provide a consistent, unified analysis of project performance, as well facilitating presentation of a Project s Implementation Status in familiar terms. Project Management Fundamentals Slide 28

29 EV vs Traditional Analysis An Example $3,300 Traditional Actual vs. Scheduled Cost Comparison $2,400 Traditional Analysis: Actual Costs to date were Less than Planned indicating a Cost UNDERRUN, but not whether the work was completed. Planned Value PV (i.e. the Budget for the Time period) Actual Cost AC to date Project Management Fundamentals Slide 29

30 EV vs Traditional Analysis An Example Traditional Analysis of 4 day ROME : Actual Costs to date were Less than Planned indicating a Cost Underrun. EVA s Analysis: 1. Spending Rate was slower than planned, but Traditional Actual vs. Scheduled Cost Comparison Actual Costs $3,300 for the work successfully completed were greater than planned Thus instead of an Underrun there is A Cost Overrun 2. Furthermore, since the Earned Value! is less than the Planned Value as of that time period, $2,400 this indicates that the Project is also Behind Schedule $2,100 EV Actual Cost for Work Completed vs. Planned Cost Comparison i.e. Budget regardless of the work plan schedule $3,300 $2,400 $2,100 Planned Value PV (i.e. the Budget for the Time period) Actual Cost AC to date Earned Value EV (Budget for the completed Work) Slide 30

31 EVA Analysis Another Example $410 $530 $440 EV Analysis: 1. Spending is greater than planned, and Actual Costs for the work successfully completed are also greater than planned i.e. A Cost Overrun. 2. However, since the Earned Value is also Greater than the Planned Value as of that date, this indicates that the Project is Ahead of Schedule Planned Value PV (Budget for the Time period) Actual Cost AC Earned Value EV (Budget for the completed Job) Project Management Fundamentals Slide 31

32 EVM INNOVATION II During implementation Thirteen (13) different Combinations* of PV AC & EV. are possible Reflecting 13 different Performance Status Conditions * Technical Note: Derived from 25 or 27 Permutations (i.e. 1 x 5 x 5 or 3 x 3 x 3) See Appendix Project Management Fundamentals Slide 32

33 Unfortunately, Traditional Time & Cost Monitoring systems DO NOT analyze and report project status systematically in terms of these 13 possible scenarios -- even though the information already exists. Consequently, erroneous management decisions can be -- and often are -- made. Project Management Fundamentals Slide 33

34 HOWEVER, You Can...! The characteristics of these Thirteen different combinations Can be rank-ordered and color-coded from 1 (High) to 13 (Low) To create an overall Integrated Project Performance Index (PPI) Project Management Fundamentals Slide 34

35 Project Performance Index (PPI)* & Traffic Light System (TLS)* for Quick & Easy Application of Earned Value Project Management Fundamentals Slide 35

36 Of these Thirteen Project Status Conditions: 6 are Good for each indicator 4 are Mixed (i.e. good & bad ), and 3 are Bad for all indicators Project Management Fundamentals Slide 36

37 Possible States of Project Implementation PV AC EV PV AC EV Target In terms of PV AC & EV PV AC EV The Constellation Combinations Project Management Fundamentals Slide 37

38 Project Performance [Index] Planned Value PV Actual Cost AC Earned Value EV [Index] PROJECT STATUS CONDITION 1 $100 $80 $120 Good. Work ahead of schedule & with cost savings on work done, as well as an apparent cost under-run on the budget. 2 $100 $100 $120 Good. Work is ahead of schedule, with cost savings even though the budget has been spent as planned. 3 $100 $80 $100 Good. Work is on schedule, with cost savings. 4 $100 $120 $140 Good. Work is ahead of schedule, with costs savings. [But may have a cash flow problem if funds are released incrementally.] 5 $100 $120 $120 Good. Work is ahead of schedule, with costs as planned for work done. [But may have a cash flow problem if funds are released incrementally.] 6 $100 $100 $100 Ideal. Everything going according to plan On Schedule & Spending. [Extremely Rare!] 7 $100 $60 $80 Mixed Good & Bad. Saving money on the work performed; but work is behind schedule. Project Management Fundamentals Slide 38

39 Project Perform - ance [Index] Planned Value PV Actual Cost AC Earned Value EV [Index] PROJECT STATUS CONDITION 7 $100 $60 $80 Mixed Good & Bad. Saving money on the work performed; but work is behind schedule. 8 $100 $120 $100 Mixed Good & Bad. Work on schedule, but cost overrun incurred. [May have a cash flow problem if funds are released incrementally.] 9 $100 $80 $80 Mixed Good & Bad. Spending as planned; but work is behind schedule. 10 $100 $140 $120 Mixed Good & Bad. Work ahead of schedule, but a cost overrun has been incurred. [May have a cash flow problem if funds released incrementally.] 11 $100 $80 $60 BAD. Spending is slower than planned, but the Value is low indicating a cost overrun; and the work is also behind schedule. 12 $100 $100 $80 BAD. Although the spending rate is as planned, since the Value is low, there is a cost overrun; and the work is also behind schedule. 13 $100 $120 $80 BAD. Work behind schedule, cost overrun [and possible cash flow problem.] Project Management Fundamentals Slide 39

40 1. PPI & TRAFFIC LIGHT SYSTEM QUICK & EASY TEMPLATE for monitoring INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 40

41 41

42 2. EVA SOFTWARE for monitoring INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 42

43 Monitoring the Triple Threat with EVA-2006 Calculating all the foregoing Earned Value Indicators manually for various status situations and preparing the related charts is laborious, time-consuming, as well as prone to error. However, I have developed a software program (in a Project Management Toolkit ) that calculates these EVA indicators and draws related charts and graphs. The Tool Kit is available from: Project Management Fundamentals Slide 43

44 2. Automated Early Warning Traffic Light System To facilitate both computation and analysis I had Software developed to: 1. Calculate all the other 16 EV indicators from the four basic Drivers 2. Display the Performance Index results in Color -- with Icons & a summary explanation 3. Together with several supporting graphics and an Executive Summary Project Management Fundamentals Slide 44

45 EVA-2006 Software* Accepts project plan & implementation driver data [activity/milestone work schedule & cost] Then calculates: Monetary data in two (2) different currencies Eighteen (18) key Earned Value Performance indicators Assesses the Project Status Condition on a 13- point scale, & a color-coded Traffic Light system as either Good Mixed or Bad Provides an Executive Summary for briefings with several supporting graphics [See EVA PPI & Traffic Light in my Project Management Tool Kit ] *Programmed by BLASTASIA Slide 45

46 Project Management Fundamentals Slide 46

47 Monitoring the Triple Threat Three (3) BAD States Planned Cost of Work Scheduled PPI - Project Performance Index Current Project Status: Condition Work Being Completed Behind Schedule 2. Positive Cash Flow Actual Cost of Work Performed 3. Cost Overrun Incurred on the Work Done Earned Value of Work Performed $3,300 $2,400 $2,100 Project Management Fundamentals Slide 47

48 EVA Quadra-Graph Project Implementation Summary COST VARIANCE 100% Under Budget 0% Over Budget Current Status 100% 0% Behind Ahead 100% SCHEDULE Project Management VARIANCE Fundamentals Slide 48

49 EXECUTIVE SUMMARY ANALYSIS Automatically computed: The Project s Present Status Condition is PPI 11: BAD The Project is 53% Complete (%CS), and is 36% Behind Schedule (%CV) At current trends, the project is now estimated to complete on 20-Aug-2016 (ECD) US$2,171 will be needed to complete the project (ETC) For a total of US$4,671 (EAC) This represents a Cost Overrun of US$571 (VAC) Project Management Fundamentals Project Management Fundamentals Slide 49

50 EVA SOFTWARE DEMONSTRATIONS Project Management Fundamentals Slide 50

51 3. PIMS QUICK & EASY TEMPLATE for Recording, Tracking, Monitoring & Analyzing INTEGRATED PROJECT PERFORMANCE STATUS Project Management Fundamentals Slide 51

52 ROJECT ID: PROJECT INTEGRATED MONITORING SYSTEM (PIMS) -- WORK, BUDGET & COST PERFORMANCE For Projects up to One Hundred (100) Months duration with Milestone %s, Physical & Financial S-Curves, Control Chart Variance, Earned Value Histogram, S- Curve Transform & PPIndex Sample Demonstration Planned MON Indirect Overhead Project Duration: 7 THS OK Rate: 25% 2014, Dr. Kenneth F. Smith, PMP INSTRUCTIONS FOR USE. On initial use, first Delete all the data in the Three yellow cells above, and the cell & Four yellow Rows in the table below. Then enter YOUR PLAN, & ACTUAL Data in the yellow cells, and immediately view the Analyzed results in the table, graphs and chart below. YEAR 1 YEAR MONTHS Jan-15 Feb-15 Mar- 15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 ilestones nned (POW) umulative estones Plan ect Planned ost / Mo direct Cost allocated] ct + Indirect OH Cost umulative ct + Indirect OH ulative MS PLAN Sep- 15 V=BCWS ulative Cost $6 $10 $19 $26 $34 $39 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 PLAN ctual Cost AC+OH 2013 Dr. $7 Kenneth $8 F. $1 Smith, $4 PMP $10 $3 Project Management Fundamentals 52 umulative $7 $15 $16 $20 $30 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 $33 Oct- 15 Nov- 15 Dec-15 Jan-16 Feb-16 Mar- 16 Apr-16 May- 16 Jun-16 Jul-16 Aug $5 $3 $8 $5 $7 $4 $1 $1 $1 $1 $1 $1 $1 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6 $4 $9 $6 $8 $5 $1 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6 $10 $19 $26 $34 $39 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $40 $

53 ANALYSIS Percent Complete On, Ahead or Behind Schedule On, Over or Under Budget 14% 14% 43% 43% 57% 71% 71% Project Performance Index (PPI) PPI Key: 1 through 6 = GOOD EV = BCWP "Earned Value" $6 $6 $10 $10 $19 $26 $26 Running Budget Variance from Plan 14% 46% -18% -22% -11% -15% -18% Work Schedule Variance from Plan 0% -40% -47% -60% -42% -34% -36% True Cost Variance from Plan 14% 144% 56% 94% 54% 29% 29% Project Management Fundamentals 53

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

Gate Value Method Overview document

Gate Value Method Overview document Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

Project Assessment Exercise

Project Assessment Exercise Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

Predicting The Future

Predicting The Future Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

Long Description. Figure 15-1: Contract Status. Page 1 of 7

Long Description. Figure 15-1: Contract Status. Page 1 of 7 Page 1 of 7 Figure 15-1: Contract Status A single performance report provides the status of the Program at a point in time. When combined with previous reports, a much more revealing picture of the Program

More information

From Suspicion to Invaluable Transition of Two Project Managers

From Suspicion to Invaluable Transition of Two Project Managers From Suspicion to Invaluable Transition of Two Project Managers June 2010 Shilpi Kumar & Sunita Raman Agenda Unisys and HOLMES 2 Nature of Projects and Roles Why EVA? How? EVA in Development Projects Transition

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

Project Monitoring and Control Project Closure. Week 8

Project Monitoring and Control Project Closure. Week 8 Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

ENGINEERING MANAGEMENT (GE

ENGINEERING MANAGEMENT (GE بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control

More information

Budgeting & Financial Reporting

Budgeting & Financial Reporting Budgeting & Financial Reporting CEPI BUDGET TEMPLATE INSTRUCTIONS For use by potential awardees and awardees Updated 5/30/2017 TABLE OF CONTENTS 1 General Guidance... 4 1.1 About this document... 4 1.2

More information

Earned Schedule in Action

Earned Schedule in Action Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

CE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System

CE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System CE303 Introduction to Construction g PROJECT COST MANAGEMENT & BUSINESS METHODS LEARNING OBJECTIVES The student should be able to: Define and understand the need for a cost control system. Describe the

More information

Factor Leave Accruals. Accruing Vacation and Sick Leave

Factor Leave Accruals. Accruing Vacation and Sick Leave Factor Leave Accruals Accruing Vacation and Sick Leave Factor Leave Accruals As part of the transition of non-exempt employees to biweekly pay, the UC Office of the President also requires standardization

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

for 9 Sep 15 SoCal ICEAA Workshop

for 9 Sep 15 SoCal ICEAA Workshop Two Complementary EVM Cost-Risk Models Part 2 1. Use of EVM Trend Tool (EVMTT) to Forecast Cost Risks with 4 Case Study Examples 2. Integrated Cost-Risk Model (ICRM) Utilizing ACEIT for 9 Sep 15 SoCal

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia Schedule Analysis and Predictive Techniques Using Earned Schedule 16 th IPM Conference Tysons Corner, Virginia 17 th November 2004 Walt Lipke OC-ALC/MAS Tinker AFB OK walter.lipke@tinker.af.mil 405-736-3341

More information

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date: DATA ITEM DESCRIPTION Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT Number: Approval Date: 20091026 AMSC Number: N9105 Limitation: DTIC Applicable: N/A GIDEP Applicable: N/A Office

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence Earned Value and PRINCE2 Alex Davis Programme Manager Close Combat Programme Support Office Ministry of Defence PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom

More information

California ISO. Flexible Ramping Product Uncertainty Calculation and Implementation Issues. April 18, 2018

California ISO. Flexible Ramping Product Uncertainty Calculation and Implementation Issues. April 18, 2018 California Independent System Operator Corporation California ISO Flexible Ramping Product Uncertainty Calculation and Implementation Issues April 18, 2018 Prepared by: Kyle Westendorf, Department of Market

More information

Objectives of Project Cost Control System

Objectives of Project Cost Control System Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

Detailed Project Scheduling and Cost Management

Detailed Project Scheduling and Cost Management Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

Agile Methods with. Performance-Based Earned Value

Agile Methods with. Performance-Based Earned Value Agile Methods with Performance-Based Earned Value CMMI Technology Conference Abstract 7110 November 20, 2008 Paul Solomon, PMP Performance-Based Earned Value www.pb-ev.com 1 Agenda Customer expects valid

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

Profit Is Important But Cash Flow Is Critical!

Profit Is Important But Cash Flow Is Critical! Profit Is Important But Cash Flow Is Critical! Did you know cash flow puts more contractors out of business than any other single thing.except improper labor pricing! It s true. You can be priced absolutely

More information

Chapter 11 Project Execution and Control

Chapter 11 Project Execution and Control Chapter 11 Project Execution and Control Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Phase C: Project Execution Most projects

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Critical Path and Earned Value Management

Critical Path and Earned Value Management Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method

More information

Oracle Project Portfolio Management Cloud Using Project Performance Reporting

Oracle Project Portfolio Management Cloud Using Project Performance Reporting Oracle Project Portfolio Management Cloud Using Project Performance Reporting Release 9 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E53157-01

More information

GLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope

GLAST Large Area Telescope: Project Status Overview. Gamma-ray Large Area Space Telescope Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Project Status Overview Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu 650-926-2726 1

More information

Humphreys &Associates, Inc.

Humphreys &Associates, Inc. Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion

More information

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach David T. Hulett, Ph.D. Hulett & Associates 24rd Annual International IPM Conference Bethesda, Maryland 29 31 October 2012 (C) 2012

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

John Chapman. Earned Value and PRINCE2

John Chapman. Earned Value and PRINCE2 Earned Value and PRINCE2 John Chapman PRINCE2 is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries. Why are we here? Do PRINCE2 and Earned Value relate

More information

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Performance Analyzer Formulas. Assumptions. Current Month Adjustments User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Software Process and Management

Software Process and Management Software Process and Management Gu Qing Nanjing University 2006-2-28 1 Chapter 5. Project Tracking Project Tracking and Control Progress Management Project Termination 2 1. Project Tracking and Control

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition

Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition Chapter Fourteen Cost Control Do Project Managers Control Costs, Monitor Costs, or Both? Cost Management

More information

5-D Integrated Earned Value Analysis

5-D Integrated Earned Value Analysis 5-D Integrated Earned Value Analysis Erol Yurtseven, October 2013 Budgeting Scheduling Design Coordination Quantity Survey Technical Office 3 4 Technical Office Design Dept & Technical Office 2 5 Cost

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Using projections to manage your programs

Using projections to manage your programs Using projections to manage your programs To project total provider reimbursements To do what ifs based on caseloads or other metrics To project amounts of admin & support available for spending Based

More information

Project Management Variance Analysis Example Xls

Project Management Variance Analysis Example Xls We have made it easy for you to find a PDF Ebooks without any digging. And by having access to our ebooks online or by storing it on your computer, you have convenient answers with project management variance

More information

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#12 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information