PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

Size: px
Start display at page:

Download "PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005"

Transcription

1 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1

2 AGENDA What is Cost Management? Cost Management Processes Some terms to be familiar with! How does the PMBoK Guide describe Cost Management? Discussion Slide 3 Project Cost Management Processes required to ensure the project is completed within the approved budget Resource Planning Cost Estimating Cost Budgeting Cost Control Slide 4 2

3 5.1 Overall Processes Initiation Activity Sequencing 6.4 Scope Planning Activity Definition 6.3 Schedule Development 5.3 Scope Definition 7.1 Resource Planning Activity Duration 7.2 Cost Estimating 7.3 Cost Budgeting 4.1 Project Plan Development Contract Closeout Slide Performance Reporting 10.4 Project Plan Execution 4.3 Overall Change Control Administrative Akram Closure Al-Najjar, PMP. Planned Value (PV) Slide 6 3

4 Planned Value (PV) Slide 7 Planned Value (PV) Previously (and still in many places) called Budgeted Costs for Work Scheduled (BCWS). A monetary representation of how much work was scheduled to be done at a point in time. Example: After 4 months, we are scheduled to complete Activity 1 and 75% of Activity 2 which are budgeted for a total of $32,000. The total project budget is $100,000. The Planned Value at 4 months is $32,000. Slide 8 4

5 Actual works Slide 9 Earned Value (EV) Slide 10 5

6 Actual Costs (AC) Slide 11 Actual works Slide 12 6

7 Earned Value (EV) Previously (and still in many places) called Budgeted Costs for Work Performed (BCWP). A monetary representation of how much work has been completed, using the baseline cost for that work, at a point in time. Example: After 4 months, we have completed Activity 1 and 50% of activity 2. The budgeted cost for this work completed was $24,000. The total project budget is $100,000. The Earned Value at 4 months is $24,000. Slide 13 Actual Costs (AC) Previously (and still in many places) called Actual Costs for Work Performed (ACWP). The monetary representation of the costs incurred at a point in time, regardless of how much work has been done. Example: After 4 months, we have completed Activity 1 and 50% of activity 2. The project costs at this point in time are $29,000. The total project budget is $100,000. The Actual Cost at 4 months is $29,000. Slide 14 7

8 Schedule Variance (SV) New: SV = EV PV = $24,000 - $32,000 = ($8,000) Old: SV = BCWP - BCWS The project has delivered $8,000 less work at this point in time than was planned. This project is behind schedule. This is a great way to depict ahead or behind on schedule, even though it is in monetary terms!!! Slide 15 Cost Variance (CV) New: CV = EV AC = $24,000 - $29,000 = ($5,000) Old: CV = BCWP - ACWP Slide 16 The project has cost $5,000 more to deliver the work done so far than was planned. This project is over budget. 8

9 Schedule Performance Index (SPI) New: SPI = EV / PV = $24,000 / $32,000 = 0.75 Old: SPI = BCWP / BCWS The project is delivering work slower than planned. The work is being done at 75% of the expected rate. Slide 17 Cost Performance Index (CPI) New: CPI = EV / AC = $24,000 / $29,000 = 0.83 Old: CPI = BCWP / ACWP The project is spending money faster than planned. Only 83% of work is being delivered for the amount of money being spent. Slide 18 9

10 Case 1 PV = $ 1,860 EV = $ 1,860 AC = $ 1,860 This is the ideal situation, where everything goes according to plan. Slide 19 Case 2 PV = $ 1,900 AC = $ 1,700 In this Case, without Earned Value measurements, it appears we re in good shape. Expenditures are less than planned. Spending Variance = - $ 200 Slide 20 10

11 Case 2 PV = $ 1,900 EV = $ 1,500 AC = $ 1,700 But with EV measurements, we see...$400 worth of work is behind schedule in being completed; i.e., we are 21 percent behind where we planned to be. SV = EV PV = - $ 400 SV % = SV / PV x 100 = - 21 % Slide 21 Case 2 PV = $ 1,900 EV = $ 1,500 AC = $ 1,700 In addition, we can see... Actuals exceed Value Earned (EV), i.e., $1,500 worth of work was accomplished but it cost $1,700 to do so. We have a $200 cost overrun (i.e., 13% over budget). CV = EV AC = - $ 200 CV % = CV / EV x 100 = - 13 % Slide 22 11

12 Case 2 PV = $ 1,900 EV = $ 1,500 AC = $ 1,700 This means only 79 cents worth of work was done for each $1.00 worth of work planned to be done. And, only 88 cents worth of work was actually done for each $1.00 spent SPI = EV / PV = $ 0.79 CPI = EV / AC = $ 0.88 Slide 23 Case 2 PV = $ 1,900 EV = $ 1,500 AC = $ 1,700 This is the worst kind of scenario, where all performance indicators are negative. SV = - $ 400; SPI = 0.79 CV = - $ 200; CPI = 0.88 Slide 24 12

13 Case 3 PV = $ 2,600 EV = $ 2,400 AC = $ 2,200 In this case there is bad news and good news. Slide 25 Case 3 PV = $ 2,600 EV = $ 2,400 AC = $ 2,200 The bad news is that our work efficiency is a bit low; we re getting only 92 cents of work done on the dollar. As a result, we are behind schedule. SPI = 0.92 SV = - $ 200; SV % = - 8 % Slide 26 13

14 Case 3 PV = $ 2,600 EV = $ 2,400 The good news is that we re under-running our budget. We re getting $1.09 worth of work done for each $1.00 we re spending. AC = $ 2,200 CV = + $ 200; CV % = + 8 % CPI = 1.09 Slide 27 Budget At Completion (BAC) This is the baseline cost of the total project. How much we planned to spend by the time we finished. Example: After 4 months, we have completed Activity 1 and 50% of Activity 2 The project costs at this point in time are $29,000. The total project budget is $100,000. The Budget At Completion is $100,000. Slide 28 14

15 Estimate At Completion (EAC) Based on where we are now, how much will it cost when the project is done? The answer depends on whether your past performance is a good indicator of expected future performance more Slide 29 Estimate At Completion (EAC) (1 st of 3 methods) If we know that we can finish the rest of the work as it was originally planned Use actual to-date plus budgeted amount for the rest of the work EAC = AC + BAC EV = $29,000 + $100,000 - $24,000 = $105,000 Slide 30 15

16 Estimate At Completion (EAC) If the original estimates were flawed, we should build new estimates for all the remaining work ETC is the Estimate to Complete the remaining work. EAC (2 nd of 3 methods) = AC + ETC = $29,000 + $120,000 = $1,49,000 Assume this was the total ETC from a completely rebuilt estimate Slide 31 Estimate At Completion (EAC) (3 rd of 3 methods) If we assume that past performance is a good indicator of future performance Use actual to-date plus budgeted amount for the rest of the work, modified by a performance factor, such as CPI EAC = AC + ((BAC EV)/CPI) = $29,000 + (($100,000 - $24,000)/0.83) = $126,506 (rounded off) Slide 32 16

17 EVM Performance Measures Slide 33 EVM and Basic PM Questions Slide 34 17

18 Present Value Budgeting technique that debates the future value of money based on inflation, etc. PV = FV (1 + r) t FV = amount of money t years from now r = interest rate (also called discount rate ) t = time period Slide 35 Present Value Year FV PV 0 $50,000 $50,000 1 $35,000 $31,819 2 $15,000 $12,397 Assume a 10% interest (or discount) rate PV (Year 1) = FV / (1 + r) t =$35,000/( ) 1 = $31,819 Slide 36 18

19 (NPV) Net Present value This Means the total benefits (income or revenue) less the cost. To calculate NPV you need to calculate the present value of each of the income and revenue figures then add up the present values. Time Period Income or revenue Present Value at 10% interest rate Costs Present Value at 10% interest rate Total NPV = =62 Slide 37 Payback Period The exact length of time needed to recover an initial investment as calculated from cash inflows. Month Costs Total Cost Benefits Total Benefits 1 $5000 $5000 $0 $0 2 $5000 $10000 $0 $0 3 $8000 $18000 $0 $0 4 $5000 $23000 $5000 $ $2000 $25000 $10000 $ $0 $25000 $10000 $ $0 $25000 $10000 $35000 PAYBACK PERIOD is 6 MONTHS Slide 38 19

20 Internal Rate Of Return (IRR) The interest (discount) rate where the present value of the benefits exactly equals the costs. The higher the rate, the better the project. An IRR of.15 means that you expect the project to return an average of 15% on your investment over a given time period (usually a number of years). Slide 39 Benefit Cost Ratio (BCR) Compares the cost to the benefits of different projects. A BCR of > 1 means the benefits are grater than the costs. A BCR of < 1 means the costs are grater than the benefits. A BCR =1 means the costs and benefits are the same. If the BCR of project A is 2.3 and BCR of project B is 1.7 which project would you select? The answer is A. the project with the higher BCR Slide 40 20

21 Exercise Accounting Standards Net present V Project A $95.00 Project B $75.00 Which you Pick? A IRR 13% 17% B Payback Period 16 Month 21 Month A Benefit Cost Ratio A Slide 41 Types Of Costs VARIBLE COST Any costs that change with the amount of production or the amount of work. Examples include the cost of material supplies, and wages. Fixed Costs Nonrecurring costs that do not change as production changes. Examples include set up, rental. Etc.. Direct Costs- Cost that are directly attributable to the work on project. Examples are team travel, team wages, recognition and cost of material used on the project Indirect costs Overhead items or costs incurred for the benefit of more than one project. Examples include taxes, fringe benefits, and janitorial services. Slide 42 21

22 SUNK COST : Expended Cost You have a project with an initial budget of US $1,000,000 You are halfway through the project and have spent US $ 2,000,000. Do you consider the US $ 1,000,000 over budget when determining whether to continue the project? The answer is no! Be aware that accounting standards say that sunk costs should not be considered when deciding whether to continue with a troubled project Slide 43 DEPRECIATION STRAIGHT LINE DEPRECIATION : the same amount of depreciation is taken each year, A US $ 1,000 item with a ten year useful life and no salvage value (how much item is worth at the end of its life) would be depreciated at US $100 per year. ACCELERATED DEPRECIATION you only need to know: There are two forms of accelerated depreciation Double Declining Balance and Sum of the Years Digits. They depreciate faster than straight line. You do not have to know what these two forms means or do any calculations. Slide 44 22

23 LIFE CYCLE COSTING LIFE CYCLE COSTING : Means that the cost of operation and maintenance phase to be consider and manage with the project cost PROJECT OPERATIONS AND MAINTENANCE PHASE costs costs Slide 45 PMBOK Chapter 7 There are 4 major processes: 1. Resource Planning 2. Cost Estimating 3. Cost Budgeting 4. Cost Control Slide 46 23

24 Cost Management Planning Controlling 7.1 Resource Planning 7.2 Cost Estimating 7.3 Cost Budgeting 7.4 Cost Control Slide 47 Resource Planning Determining physical resources needed (i.e., material, equipment, and people) and what quantities of each should be used and when they would be needed to perform project activities Slide 48 24

25 Resource Planning Tools & Techniques Expert judgment Alternatives identification PM software Inputs Scope statement WBS Resource pool description Organizational policies Historical information Activity durations estimates Slide 49 Outputs Resource requirements Inputs Work breakdown structure (WBS) Identifies the project elements that require resources Historical information Used to identify the types of resources that were required for similar work on previous projects Scope statement Contains project justification and the project objectives, which need to be considered Resource pool description Description of resources available, if necessary, to work on a project Organizational policies Of the performing organization, regarding staffing and the rental and purchase of supplies and equipment Activity duration estimates Slide 50 25

26 Tools & Techniques Expert judgment Expertise, provided by any group or individual, used to assess the inputs to this process Other units within organization Consultants Professional and technical associations Industry groups Alternatives identification PM software Used to organize resource pools, define resource availabilities and rates, and define resource calendars Slide 51 Outputs Resource requirements Description of the types (e.g., skill levels) and numbers of resources required by each element of the WBS Slide 52 26

27 Cost Estimating Process of developing an approximation (or estimate) for the cost of the resources necessary to complete the project activities Difference between cost estimating and pricing: Cost estimating: Assessing how much it will cost the organization to provide the product or service Pricing: Assessing how much the organization will charge for the product or service Cost estimating also includes identifying and considering cost alternatives Slide 53 Cost Estimating Inputs WBS Resource requirements Resource rates Activity duration estimates Estimating publications Historical information Chart of accounts Risks Tools & Techniques Analogous estimating Parametric modeling Bottom-up estimating Computerized tools Other cost estimating methods Slide 54 Outputs Cost estimates Supporting detail Cost management plan 27

28 Inputs WBS Used to organize the cost estimates and to ensure that the cost of all identified work has been estimated Resource requirements Resource rates Unit rates for each resource Activity duration estimates Affects cost estimates if project budget includes an allowance for the cost of financing (i.e., interest) Chart of accounts Coding structure used by the organization to report financial information. Cost estimates must be assigned to the correct accounting category. Slide 55 Inputs (cont.) Historical information Information on the cost of resources Project files Records of previous project results that are detailed enough to aid in developing cost estimates Commercial cost-estimating databases Historical information available commercially Project team knowledge Estimating publications Commercially available data on cost estimating Risks Since risks can have a significant impact on cost, the effect of risk on the cost estimates for each activity must be considered Slide 56 28

29 Tools & Techniques Analogous estimating (Expert judgment) Used to estimate total project costs if there is a limited amount of detailed information Parametric modeling Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot) Bottom-up estimating Estimating the cost of individual work items and then rolling up the costs to arrive at a project total Computerized tools PM software and spreadsheets Slide 57 Outputs Cost estimates Quantitative assessments of the cost of resources (e.g., units of currency or staff hours) Types of estimates Order of magnitude (-25% / +75%) Budget estimate (-10% / +25%) Definitive estimate (-5% / +10%) Supporting detail Description of estimated scope of work Documentation of the basis for the estimate Documentation of any assumptions made Range of possible results Slide 58 29

30 Cost Estimating Outputs (cont.) Cost management plan Describes how cost variances will be managed Part of the overall project plan Slide 59 Cost Budgeting Allocating the overall cost estimate to individual activities or work packages, in order to establish a cost baseline for measuring project performance Slide 60 30

31 Cost Budgeting Tools & Techniques Cost-budgeting tools and techniques Inputs Cost estimates WBS Project schedule Risk management plan Outputs Cost baseline Slide 61 Inputs Cost estimates WBS Identifies the project elements to which the costs will be allocated Project schedule Used to assign costs to project elements for the time period when costs will be incurred Risk management plan Often includes cost contingency, which can be determined on the basis of the expected accuracy of the estimate Slide 62 31

32 Tools & Techniques Cost budgeting tools and techniques Analogous estimating Parametric modeling Bottom-up estimating Computerized tools Slide 63 Outputs Cost baseline Time phased budget that will be used to measure and monitor the cost performance of the project BCWS ($K) Jan Feb Mar Apr May Jun Reporting Period Slide 64 32

33 Cost Control Influencing the factors that create changes to the cost baseline to ensure that changes are agreed upon Determining that the cost baseline has changed Managing the actual changes when and as they occur Includes: Monitoring cost performance to detect variances from the plan Ensuring that all appropriate changes are recorded Preventing incorrect, inappropriate, or unauthorized changes Informing the appropriate stakeholders of authorized changes Analyzing positive and negative variances and how they affect the other control processes Slide 65 Cost Control Tools & Techniques Cost change control system Performance measurement EVM Additional planning Computerized tools Inputs Cost baseline Performance reports Change requests Cost management plan Outputs Revised cost estimates Budget updates Corrective action Estimate at completion Project closeout Lessons learned Slide 66 33

34 Inputs Cost baseline Performance reports Information on cost performance Change requests Oral or written requests to change the budget Cost management plan Slide 67 Tools & Techniques Cost change control system Procedures used for making changes to the cost baseline Paperwork Tracking system Approval levels Performance measurement Assessment of the magnitude of any variation, the cause of the variance, and the corrective action needed Slide 68 34

35 Tools & Techniques (cont.) Additional planning Changes may require new or revised cost estimates or an analysis of alternative approaches Computerized tools Used for tracking the value of planned costs compared to actual costs and for predicting the effects of cost changes Earned Value Management Continuously measuring project performance by relating the planned value, the earned value for work accomplished, and the actual costs incurred Slide 69 Outputs Revised cost estimates Budget updates Corrective action Estimate at completion Forecast of most likely total project costs based on project performance and risk quantification Project closeout Processes and procedures for closing or ending a project Lessons learned Documented causes of variances Slide 70 35

36 Outputs Slide 71 Earned Value (EV) A method of measuring project performance by comparing the amount of work planned with that actually accomplished, in order to determine if cost and schedule performance are as planned Slide 72 36

37 Performance Measurement Baseline (PMB) The plan against which actual performance can be compared Based on budgets assigned to scheduled segments of work Build PMB by summing the PV for all control accounts, by reporting period Budget at completion (BAC) Equal to the cumulative PV for the total project Slide 73 Performance Measurement Baseline (PMB) Time-Phased Budget BCWS $K Jan Feb Mar Apr May Jun Reporting Period BAC Slide 74 37

38 Cost Control Planned Value (PV) Work schedule to be accomplished Performance Measurement Baseline 0 JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY PV CURRENT BAC PV JANUARY 0 FEBRUARY 2500 MARCH 8000 APRIL MAY JUNE JULY Slide 75 Earned Value Budgeted value of completed or in-process work Performance Measurement Baseline EV PV CURRENT PV EV JANUARY 0 0 FEBRUARY MARCH APRIL MAY JUNE JULY JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY Slide 76 38

39 Actual Costs (AC) Actual expenditures for completed or in- process work Performance Measurement Base CURRENT ACWP BCWS BC PV EV AC JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY Slide 77 Schedule Variance Comparing the EV, the amount originally budgeted for the work that has been completed or is inprocess, to the PV, the amount budgeted for the work that was planned to have been accomplished SV = EV PV A negative result means less work has been performed than was planned Slide 78 39

40 SV Example PV = $42,000 EV = $38,000 AC = $48,000 SV = EV PV = $38,000 $42,000 = - $4,000 SV% = SV / PV = - $4000 / $42,000 = = - 9.5% Slide 79 Cost Variance Comparing the amount originally budgeted for the work completed or in-process, the EV, to the actual costs of that work, the AC CV = EV AC A negative CV means more dollars were spent to accomplish the work than was planned Slide 80 40

41 Cost Variance Example PV = $42,000 EV = $38,000 AC = $48,000 CV = EV - AC = $38,000 $48,000 = - $10,000 CV% = CV / EV = - $10,000 / $38,000 = - 26% Slide 81 Performance Indices Dfn: Cost- and schedule-performance efficiency calculations; expressed in $ Cost Performance Index (CPI) CPI = EV/AC Schedule Performance Index (SPI) SPI = EV/PV Slide 82 41

42 CPI Example PV = $42,000 EV = $38,000 AC = $48,000 CPI = EV / AC = $38,000 / $48,000 = 0.79 $0.79 worth of work was actually done for each $1.00 spent Slide 83 SPI Example PV = $42,000 EV = $38,000 AC = $48,000 SPI = EV / PV = $38,000 / $42,000 = 0.90 $0.90 worth of work has been done for each $1.00 worth of work that was planned to be done Slide 84 42

43 Estimate at Completion (EAC) Dfn: The management s assessment of the cost of the project at completion After variance analysis, the estimated cost at completion is determined Slide 85 EAC Example One methodology: EAC = BAC / CPI BAC = $80,000 CPI = 0.79 EAC = $80,000 / 0.79 = $101,265 Slide 86 43

44 Variance at Completion BAC = $80,000 EAC = $101,265 VAC = BAC EAC = $80,000 $101,265 = -$21,265 Based on past performance, project will exceed planned budget by $21,265 Slide 87 To Complete Performance Index (TCPI) Work Remaining / Cost Remaining TCPI = (BAC EV) / (EAC AC) = ($ 80,000 $ 38,000) / ($ 101,265 $ 48,000) = $ 42,000 / $ 53,265 =.79 Slide 88 44

45 Earned Value Examples PV EV AC $1 $1 $1 On schedule On cost $2 $2 $1 On schedule Under cost $1 $1 $2 On schedule Over cost $1 $2 $2 Ahead of schedule On cost $1 $2 $3 Ahead of schedule Over cost $1 $2 $1 Ahead of schedule Under cost $3 $2 $1 Behind schedule Under cost $2 $1 $3 Behind schedule Over cost $2 $1 $1 Behind schedule On cost Slide 89 Example PV EV AC EAC BAC Slide 90 45

46 Sample Cost Problem BAC = $ 40k EV = $ 20k PV = $ 28k AC = $ 26k Calculate % of Work Scheduled % of Budget Spent % of Work Accomplished Cost Variance Schedule Variance Slide 91 Sample Solution Calculate % of Work Scheduled PV / BAC = $ 28K / $ 40K = 70 % % of Budget Spent AC / BAC = $ 26K / $ 40K = 65 % % of Work Accomplished EV / BAC = $ 20K / $ 40K = 50 % Cost Variance EV AC = $ 20K $ 26K = - $ 6K Schedule Variance EV PV = $ 20K $ 28K = - $ 8K Slide 92 46

47 Discussion Summary Any questions before we take a 10 minute break? Slide 93 47

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

PMP Exam Preparation Workshop Chapter 7 Project Cost Management PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

Project Monitoring and Control Project Closure. Week 8

Project Monitoring and Control Project Closure. Week 8 Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

PMI - Dallas Chapter. PMP Exam Sample Questions

PMI - Dallas Chapter. PMP Exam Sample Questions PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

Chapter 7: Project Cost Management. IT Project Management, Third Edition Chapter 7

Chapter 7: Project Cost Management. IT Project Management, Third Edition Chapter 7 Chapter 7: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

Project Management Certification. Multiple Choice Questions

Project Management Certification. Multiple Choice Questions Project Management Certification (PMP) Project Management Certification (PMP) Multiple Choice Questions QUESTION 1 In Project Cost Management, which input is exclusive to the Determine Budget process?

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that

More information

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data William Laing Technomics, Inc. wlaing@technomics.net 2011 ISPA/SCEA Joint Annual Conference & Training Workshop

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

PMI PMI-SP. PMI Scheduling Professional. Download Full Version : PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he

More information

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 5 Developing Project Budgets Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

PM tutor. Advanced Cost Theory. Presented by Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence. Powered by POeT Solvers Limited

PM tutor. Advanced Cost Theory. Presented by Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence. Powered by POeT Solvers Limited PM tutor Empowering Excellence Advanced Cost Theory Presented by Dipo Tepede, PMP, SSBB, MBA This presentation is copyright 2009 by POeT Solvers Limited. All rights reserved. This presentation is protected

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

Three Numbers to Measure Project Performance

Three Numbers to Measure Project Performance Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de

More information

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com 2010 ISPA/SCEA International Conference SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Ms

More information

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs) Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

ENGINEERING MANAGEMENT (GE

ENGINEERING MANAGEMENT (GE بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control

More information

EV in a War Zone: Understanding Earned Value & How to apply it.

EV in a War Zone: Understanding Earned Value & How to apply it. EV in a War Zone: Understanding Earned Value & How to apply it. 2017 CONSTRUCTION CPM CONFERENCE WED33, 2PM SPEAKER: ERIK TUMA, P.S.P Kandahar International Airport, Kandahar, Afghanistan Personal Introduction

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects where there is difficult to have an overall visibility of risks a lack of understanding of

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

A Practical Way To Learn About EVM. ***The Deck Project***

A Practical Way To Learn About EVM. ***The Deck Project*** A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information