Carlos Consulting Group

Size: px
Start display at page:

Download "Carlos Consulting Group"

Transcription

1 Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group Roseville, CA

2 Introduction There are lucky project managers whose projects were completed on time and within budget. However, chances are these PMs represent a small minority. Everyone else has probably faced a situation where one of the following statements is true: The project is within budget and schedule but we do not see the expected results The project is taking longer than expected The project is costing more than anticipated

3 The novice project manager probably uses analysis tools that are considered two-dimensional. Budget and Actual are the two dimensions. But in looking at a broader picture, there is a much needed third dimension- one that reflects performance and efficiency. Performance and efficiency indicate whether or not we are actually completing the intended tasks and producing the expected project deliverables within the designated budget and schedule.

4 Earned Value Management The process of considering scope, schedule, and resources, measured against a project s actual performance. It compares the planned amount of work to the completed tasks, to the projects cost, to determine if the cost, schedule, and work completed (thus far) are all in synch and in accordance with the plan. This analysis will show past performance and will estimate future efforts to complete the project (with the desired results).

5 The Project and Assumptions To help us understand the Earned Value Management, let s apply the process and formulas to a case study. Building A Playhouse Ann would like to build an outdoor playhouse for her children. She will hire five different contractors who will each perform a specific task. There are five separate tasks, at varying hours and cost per hour.

6 Ann has agreed to pay the contractors on a time and material basis The project estimates include a total of 30 hours of construction time at a total cost of $2,395. Typically, the tasks are scheduled to be performed sequentially. Based on the work plan, it is determined that the project can be completed within five weeks (where each task will take one week).

7 The Project Budget Task # Description Budget Hrs Hrly Cost Total Est Cost T1 Floor 6.00 $ 100 $ T2 Frame 6.00 $ 75 $ T3 Roof 4.00 $ 65 $ T4 Interior 7.00 $ 80 $ T5 Exterior 7.00 $ 75 $ $ 2,395.00

8 The Basic EVM Formulas Symbol Description Formula Explanation PV Planned Value None The estimated value of the work planned to be done thus far. AC Actual Costs None The total costs incurred to date, based on timesheets, invoices, other expenses, etc. EV Earned Value -Sum of all tasks (Task Budget * % Completed) The estimated value of (intended) work completed thus far, as it relates to the expected deliverables.

9 Project Analysis At The End of Week 1 By the end of week 1, the floor should be completed. However, the contractor did not finish. He put in 5 hours and completed 60% of the floor. Symbol PV Value $600 Formula Our budget figure for Task 1 AC $500 5 $100 per hour EV $360 Budget for this task times the percent completed $600 * 60%

10 Ann is worried because the floor contractor did not complete the task on time. The contractor assures her that he will finished the floor on Monday. However, he argues that an unforeseen problem came up with the installation of the floor. So Ann agrees to pay him two extra hours of work ($200). Ann is also wondering how she can measure the performance (and efficiency) of the floor contractor. So she decides to use two additional attributes of EVM.

11 The Performance Index Calculations Symbol Description Formula Explanation CPI Cost Performance Index EV/AC CPI compares the relationship between the Earned Value and Actual Cost. I am (only) getting (blank) cents performance out of every $1 spent. SPI Schedule Performance Index EV/PV SPI compares the relationship between the Earned Value and Planned Value. I am only progressing at (blank) % of the original plan.

12 The Performance Index Calculations Symbol CPI SPI Value 72% 60% Formula $360 / $500 $360 / $600 The CPI index tells Ann that she is receiving $.72 cents performance out of every $1 spent. The SPI index tells Ann that she is only progressing at 60% of the original plan.

13 Ann is also wondering how the extra time and cost will affect the final cost to the project. So she reviews the next three formulas. Symbol Description Formula Explanation BAC Budget At Completion N/A The original budget for the total job EAC Estimate At Completion BAC / CPI The amount "currently expected" for the total project cost ETC Estimate To Complete EAC-AC From this point on, how much MORE do you expect the cost will be to finish the job

14 Budget Completion Estimates (in dollars) Symbol BAC EAC ETC Value $2, $3, $2, Formula The original Budget $2,395 /.72 $3, $500 *Calculating a value for EAC can be tricky. There are four different methods for calculating EAC. Each method can yield a different result. Since Ann employs the principle of conservatism and wants the worst case scenario she uses the formula the yields the highest figure. (Refer to the weekly worksheets for all EAC formulas).

15 At this point, Ann is not worried about the projected $200 budget overrun. But she should be; this is only the first task and who knows what can happen with the remaining contractors. Now that Ann has a handle on the formulas used thus far, she decides to forge ahead and calculate the remaining EVM attributes.

16 The Variance Calculations Symbol Description Formula Explanation VAC Variance At Completion BAC-EAC How much over or under budget will the project come in at. (This assumes that each task will have the same inefficiency as task 1) CV Cost Variance (in dollars) EV-AC Negative is over budget, Positive is under budget SV Schedule Variance (in dollars) EV-PV Negative is behind schedule, Positive is ahead of schedule

17 The Variance Calculations Symbol VAC CV SV Value - $ $ $ Explanation $ $ $ $ $ VAC assumes that each task will have the same inefficiency as seen thus far with Task 1. This is why VAC (at this point) does not equal the $200 cost overrun of Task 1. The Cost (CV) and Schedule (SV) variances indicate that the project is over budget and behind schedule.

18 Overall Efficiency Ratings Symbol Description Formula Explanation PE Planned Earned EV/BAC Project % Complete (as it relates to time and deliverables) PS Percent Spent AC/BAC Project % Spent (as it relates to cost) CSI Cost Schedule Index CPI * SPI The overall efficiency rating. The further CSI is from 1.0, the project will have difficulties in recovering.

19 Overall Efficiency Ratings Symbol PE PS CSI Value 15.0% 20.9% Explanation $ / $ $ / $ % * 60% The values for PE and PS do not surprise Ann. She knows this is week one and the figures look right. But CSI is surprising. This value is far from 1 so it indicates a problem with the project s overall efficiency.

20 EVM - Building A Playhouse Financial Summary - Week 1 Project Information Project duration (weeks) 5 Project start date 7/1/07 This report date 7/6/07 Work Period Number 1 Estimated end date 8/3/07 (Enter values were you see a blue font) (The sample case assumes that tasks can be completed concurrently) Task # Description Budget Hrs Hrly Cost Total Est Cost Actual Hrs To Date Cost To Date Percentage of Tasks Completed *1 T1 Floor 6.00 $ 100 $ $ % T2 Frame 6.00 $ 75 $ $ - 0% T3 Roof 4.00 $ 65 $ $ - 0% T4 Interior 7.00 $ 80 $ $ - 0% T5 Exterior 7.00 $ 75 $ $ - 0% $ 2, $ *1 - Information as reported by contractors Term Description Value Term Description Value PV Planned Value *2 $ BAC Budget At Completion $ 2, AC Actual Cost $ EAC *3 Estimate At Completion $ 3, EV Earned Value $ ETC Estimate To Complete $ 2, CPI Cost Performance Index 72.00% VAC Variance At Completion $ (931.39) SPI Schedule Performance Index 60.00% CV Cost Variance (in dollars) $ (140.00) *2 Remember that PV is based on what should have been completed thus far. SV Schedule Variance $ (240.00) For multi-period projects, it will not equal the same value as BAC. *3 Using Max Value of EAC #1, EAC #3, or EAC #4 (Using EAC #2 will create a circular error) Term Description Value Your project Status: PE Planned Earned 15.0% Schedule Variance PS Percent Spent 20.9% If SV = 0 CSI Cost Schedule Index If SV > 0 If SV < 0 Project Behind Schedule Alternate methods to Calculate EAC Cost Variance Term Description Value If CV = 0 EAC #1 BAC/CPI $ 3, If CV > 0 EAC #2 AC + ETC $ 3, If CV < 0 Over Budget EAC #3 AC + BAC - EV $ 2, EAC #4 AC +[(BAC-EV)/CPI] $ 3,326.39

21 Project Analysis At The End of Week 2 The floor contractor finished his task. As agreed (by Ann), it took two extra hours and cost an additional $200. The framing contractor was able to complete the work within the estimated time and budget. By the end of week two, the project was back on schedule, but over budget.

22 Financial Summary - Week 2 EVM - Building A Playhouse Project Information Project duration (weeks) 5 Project start date 7/1/07 This report date 7/6/07 Work Period Number 2 Estimated end date 8/3/07 (Enter values were you see a blue font) (The sample case assumes that tasks can be completed concurrently) Task # Description Budget Hrs Hrly Cost Total Est Cost Actual Hrs To Date Cost To Date Percentage of Tasks Completed *1 T1 Floor 6.00 $ 100 $ $ % T2 Frame 6.00 $ 75 $ $ % T3 Roof 4.00 $ 65 $ $ - 0% T4 Interior 7.00 $ 80 $ $ - 0% T5 Exterior 7.00 $ 75 $ $ - 0% (Enter values were you see a blue font) $ 2, $ 1, *1 - Information as reported by contractors Term Description Value Term Description Value PV Planned Value *2 $ 1, BAC Budget At Completion $ 2, AC Actual Cost $ 1, EAC *3 Estimate At Completion $ 2, EV Earned Value $ 1, ETC Estimate To Complete $ 1, CPI Cost Performance Index 84.00% VAC Variance At Completion $ (456.19) SPI Schedule Performance Index % CV Cost Variance (in dollars) $ (200.00) *2 Remember that PV is based on what should have been completed thus far. SV Schedule Variance $ - For multi-period projects, it will not equal the same value as BAC. *3 Using Max Value of EAC #1, EAC #3, or EAC #4 (Using EAC #2 will create a circular error) Term Description Value Your project Status: PE Planned Earned 43.8% Schedule Variance PS Percent Spent 52.2% If SV = 0 Project On Schedule CSI Cost Schedule Index If SV > 0 If SV < 0 Alternate methods to Calculate EAC Cost Variance Term Description Value If CV = 0 EAC #1 BAC/CPI $ 2, If CV > 0 EAC #2 AC + ETC $ 2, If CV < 0 Over Budget EAC #3 AC + BAC - EV $ 2, EAC #4 AC +[(BAC-EV)/CPI] $ 2,851.19

23 Financial Summary - Week 2 EVM Analysis $1, $1, $1, Value in $$ $ $ $ PV AC EV $ $0.00 Period 1 Period 2 Time EVM Item Period 1 Period 2 PV $ $1, AC $ $1, EV $ $1,050.00

24 Project Analysis At The End of Week 3 The framing contractor finished his task. The roofing contractor arrived late Friday and was only able to put in 2.5 hours. He estimated that 40% of the roof was completed.

25 EVM - Building A Playhouse Financial Summary - Week 3 Task # Description Budget Hrs Hrly Cost Total Est Cost Actual Hrs To Date Cost To Date Percentage of Tasks Completed *1 T1 Floor 6.00 $ 100 $ $ % T2 Frame 6.00 $ 75 $ $ % T3 Roof 4.00 $ 65 $ $ % T4 Interior 7.00 $ 80 $ $ - 0% T5 Exterior 7.00 $ 75 $ $ - 0% (Enter values were you see a blue font) $ 2, $ 1, *1 - Information as reported by contractors Term Description Value Term Description Value PV Planned Value *2 $ 1, BAC Budget At Completion $ 2, AC Actual Cost $ 1, EAC *3 Estimate At Completion $ 2, EV Earned Value $ 1, ETC Estimate To Complete $ 1, CPI Cost Performance Index 87.92% VAC Variance At Completion $ (328.95) SPI Schedule Performance Index 88.09% CV Cost Variance (in dollars) $ (158.50) *2 Remember that PV is based on what should have been completed thus far. SV Schedule Variance $ (156.00) For multi-period projects, it will not equal the same value as BAC. *3 Using Max Value of EAC #1, EAC #3, or EAC #4 (Using EAC #2 will create a circular error) Term Description Value Your project Status: PE Planned Earned 48.2% Schedule Variance PS Percent Spent 54.8% If SV = 0 CSI Cost Schedule Index If SV > 0 If SV < 0 Project Behind Schedule Alternate methods to Calculate EAC Cost Variance Term Description Value If CV = 0 EAC #1 BAC/CPI $ 2, If CV > 0 EAC #2 AC + ETC $ 2, If CV < 0 Over Budget EAC #3 AC + BAC - EV $ 2, EAC #4 AC +[(BAC-EV)/CPI] $ 2,723.95

26 Financial Summary - Week 3 $1, $1, EVM Analysis Value in $$ $1, $ $ $ $ PV AC EV $0.00 Period 1 Period 2 Period 3 Time EVM Item Period 1 Period 2 Period 3 PV $ $1, $1, AC $ $1, $1, EV $ $1, $1,154.00

27 Project Analysis At The End of Week 4 The roofing contractor finished his task but he needed an extra hour. The interior contractor made good progress but was not able to finish. He put in 6 hours and estimated that 80% of the interior was completed.

28 EVM - Building A Playhouse Project Information Project duration (weeks) 5 Project start date 7/1/07 This report date 7/6/07 Work Period Number 4 Estimated end date 8/3/07 (Enter values were you see a blue font) Financial Summary - Week 4 (The sample case assumes that tasks can be completed concurrently) Task # Description Budget Hrs Hrly Cost Total Est Cost Actual Hrs To Date Cost To Date Percentage of Tasks Completed *1 T1 Floor 6.00 $ 100 $ $ % T2 Frame 6.00 $ 75 $ $ % T3 Roof 4.00 $ 65 $ $ % T4 Interior 7.00 $ 80 $ $ % T5 Exterior 7.00 $ 75 $ $ - 0% (Enter values were you see a blue font) $ 2, $ 1, *1 - Information as reported by contractors Term Description Value Term Description Value PV Planned Value *2 $ 1, BAC Budget At Completion $ 2, AC Actual Cost $ 1, EAC *3 Estimate At Completion $ 2, EV Earned Value $ 1, ETC Estimate To Complete $ CPI Cost Performance Index 89.92% VAC Variance At Completion $ (268.38) SPI Schedule Performance Index 94.01% CV Cost Variance (in dollars) $ (197.00) *2 Remember that PV is based on what should have been completed thus far. SV Schedule Variance $ (112.00) For multi-period projects, it will not equal the same value as BAC. *3 Using Max Value of EAC #1, EAC #3, or EAC #4 (Using EAC #2 will create a circular error) Term Description Value Your project Status: PE Planned Earned 73.4% Schedule Variance PS Percent Spent 81.6% If SV = 0 CSI Cost Schedule Index If SV > 0 If SV < 0 Project Behind Schedule Alternate methods to Calculate EAC Cost Variance Term Description Value If CV = 0 EAC #1 BAC/CPI $ 2, If CV > 0 EAC #2 AC + ETC $ 2, If CV < 0 Over Budget EAC #3 AC + BAC - EV $ 2, EAC #4 AC +[(BAC-EV)/CPI] $ 2,663.38

29 Financial Summary - Week 4 EVM Analysis Value in $$ $2, $2, $1, $1, $ $0.00 Period 1 Period 2 Period 3 Period 4 Time PV AC EV EVM Item Period 1 Period 2 Period 3 Period 4 PV $ $1, $1, $1, AC $ $1, $1, $1, EV $ $1, $1, $1,758.00

30 Project Analysis At The End of Week 5 The interior was completed but the contractor needed an extra half hour. The exterior contractor completed the work as expected. The project was completed by the end of Week 5.

31 EVM - Building A Playhouse Project Information Project duration (weeks) 5 Project start date 7/1/07 This report date 7/6/07 Work Period Number 4 Estimated end date 8/3/07 (Enter values were you see a blue font) Financial Summary - Week 5 (The sample case assumes that tasks can be completed concurrently) Task # Description Budget Hrs Hrly Cost Total Est Cost Actual Hrs To Date Cost To Date Percentage of Tasks Completed *1 T1 Floor 6.00 $ 100 $ $ % T2 Frame 6.00 $ 75 $ $ % T3 Roof 4.00 $ 65 $ $ % T4 Interior 7.00 $ 80 $ $ % T5 Exterior 7.00 $ 75 $ $ % (Enter values were you see a blue font) $ 2, $ 2, *1 - Information as reported by contractors Term Description Value Term Description Value PV Planned Value *2 $ 2, BAC Budget At Completion $ 2, AC Actual Cost $ 2, EAC *3 Estimate At Completion $ 2, EV Earned Value $ 2, ETC Estimate To Complete $ - CPI Cost Performance Index 94.48% VAC Variance At Completion $ (140.00) SPI Schedule Performance Index % CV Cost Variance (in dollars) $ (140.00) *2 Remember that PV is based on what should have been completed thus far. SV Schedule Variance $ - For multi-period projects, it will not equal the same value as BAC. *3 Using Max Value of EAC #1, EAC #3, or EAC #4 (Using EAC #2 will create a circular error) Term Description Value Your project Status: PE Planned Earned 100.0% Schedule Variance PS Percent Spent 105.8% If SV = 0 Project On Schedule CSI Cost Schedule Index If SV > 0 If SV < 0 Alternate methods to Calculate EAC Cost Variance Term Description Value If CV = 0 EAC #1 BAC/CPI $ 2, If CV > 0 EAC #2 AC + ETC $ 2, If CV < 0 Over Budget EAC #3 AC + BAC - EV $ 2, EAC #4 AC +[(BAC-EV)/CPI] $ 2,535.00

32 Financial Summary - Week 5 EVM Analysis Value in $$ $3, $2, $2, $1, $1, $ $0.00 Period 1 Period 2 Period 3 Period 4 Period 5 Time PV AC EV EVM Item Period 1 Period 2 Period 3 Period 4 Period 5 PV $ $1, $1, $1, $2, AC $ $1, $1, $1, $2, EV $ $1, $1, $1, $2,395.00

33 Final Project Analysis The project was completed on time but over budget. The final cost totaled $2, (5.8% over budget). The final performance indicators include: Term Description Value PE Planned Earned 100.0% PS Percent Spent 105.8% CSI Cost Schedule Index 0.945

34 Closing There is much more to EVM than discussed in this presentation. But you are now aware of the third dimension of a project s financial analysis. All three dimensions are key elements that must be considered when analyzing project performance. The EVM formulas provide a mathematical analysis of past and potential future performance. Unfortunately, they cannot explain why the inefficiencies occur. For this, a project manager will need to examine the work of each resource in order to understand why they perform the way they do.

35 Carlos Consulting Group About the Author Tom Carlos has over 25 years of cumulative experience in business, technical, and training environments. He is a Certified Project Management Professional (PMP) and member of the Sacramento Valley PMI Chapter. Carlos Consulting Group Roseville, CA Ph: (916) Tom@CarlosConsulting.com

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

A Layman s Guide to Earned Value

A Layman s Guide to Earned Value A Layman s Guide to Earned Value A TenStep White Paper Contact us at info@tenstep.com TenStep, Inc. 2363 St. Davids Square Kennesaw, GA. 30152 877.536.8434 770.795.9097 If you are a project manager, you

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

A Practical Way To Learn About EVM. ***The Deck Project***

A Practical Way To Learn About EVM. ***The Deck Project*** A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

QUALITY CONTROL PROCESS

QUALITY CONTROL PROCESS 1.0 SCOPE The Enterprise Project Management Office (EPMO) established overarching Quality Policy, Quality Objectives in the 0100-0100-005-QMS EPMO QUALITY MANUAL. This procedure defines specific EPMO Information

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor

More information

Detailed Project Scheduling and Cost Management

Detailed Project Scheduling and Cost Management Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute

More information

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

Techniques to Assist Delivery of Projects

Techniques to Assist Delivery of Projects Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

Monitoring System For Project Cost Control In Construction Industry

Monitoring System For Project Cost Control In Construction Industry Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Objectives of Project Cost Control System

Objectives of Project Cost Control System Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

ENGINEERING MANAGEMENT (GE

ENGINEERING MANAGEMENT (GE بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Chapter 11 Project Execution and Control

Chapter 11 Project Execution and Control Chapter 11 Project Execution and Control Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Phase C: Project Execution Most projects

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

CAPM Exam Prep.

CAPM Exam Prep. CAPM Exam Prep (What it really takes to prepare and pass) An ebook by Project Road Training, LLC www.project-road.com Bill Baxter Version 6-1 Project Road Training, LLC has been reviewed and approved as

More information

Optimization on Earned Value Method Combined with Critical Path

Optimization on Earned Value Method Combined with Critical Path Optimization on Earned Value Method Combined with Critical Path Qi-bin Zheng and Xing Bi Abstract When calculating the schedule performance using the traditional earned value method, the earned value in

More information

Project Performance Status Report

Project Performance Status Report Bahrain Polytechnic Project Performance Status Report Mechanical Project 6 (project management) Husain Alfarhan 201102238/Yahya Saif 201001047/Raed Algharaifi 201101654/Ali Yusuf 201102285/Sayed Mujtaba

More information

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Performance Analyzer Formulas. Assumptions. Current Month Adjustments User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived

More information

Homework 6 Questions and Answers

Homework 6 Questions and Answers I.E. 406 PROJECT SCHEDULING AND CONTROL Fall 2012 Murat Sandikcioglu (original by Dr.Onur ÇOKGÖR) Homework 6 Questions and Answers CRITICAL CHAIN PROJECT MANAGEMENT (CCPM) & EARNED VALUE ANALYSIS (EVA)

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

Project Management Webinar

Project Management Webinar Project Management Webinar Earned Value Basics Initiate Project Intelligence Things to Know All participants will be on mute Questions are welcome Use the question box to ask questions PM training is valid

More information

Basic Project Management

Basic Project Management PDHonline Course P103H (8 PDH) Basic Project Management Instructor: William J. Scott, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

CONSTRUCTION PROJECT RISK CONTROL BASED ON EXPERTISE USING FUZZY SET THEORY

CONSTRUCTION PROJECT RISK CONTROL BASED ON EXPERTISE USING FUZZY SET THEORY CONSTRUCTION PROJECT RISK CONTROL BASED ON EXPERTISE USING FUZZY SET THEORY Andrzej Minasowicz*, Bartosz Kostrzewa, and Jacek Zawistowski Department of Civil Engineering, Warsaw University of Technology,

More information

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

The Mystery of Earned Value - An Oil & Gas Owner s Perspective The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Quick Reference Card PPM Pro Project Data Field Dictionary

Quick Reference Card PPM Pro Project Data Field Dictionary Actual Completion Date This is the date the project actual completed. When this date is entered the project Status should be moved to Completed. This field is used in the standard Project metric reports.

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects where there is difficult to have an overall visibility of risks a lack of understanding of

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information